Whirlwind AA-Bank RAS Modifications
|
|
- Audrey Hodge
- 5 years ago
- Views:
Transcription
1 Whirlwind AA-Bank RAS Modifications Edison Team Members: Adrian Franco Electric System Planning Bill Zhang - Protection Engineering Obinna Obah - Power System Controls Hans Bakker - Communications Presentation to RASRS May 1,
2 OBJECTIVE Approval of Whirlwind AA-Bank RAS Modifications 2
3 Topics Adrian Franco Electric System Planning (ESP) Background Purpose/Operating Principles Planning Studies Bill Zhang Protection Design Modifications Design Requirements Relay Hardware Monitoring Abnormal Operation Conditions Hans Bakker Telecommunications Existing and new RAS Equipment Obinna Obah Power System Controls Objectives Reliability Automatic Arming Program Operation EMS Display 3
4 Electric System Planning Background Whirlwind Substation, designed for four 500/220 kv transformer banks ( AA Banks in SCE terminology), currently has three AA transformers banks in service (1AA, 3AA, & 4 AA) Previous RAS approvals: April 2014: Original approval by RASRS April 2015: 18 MW of generation was added to the RAS at Soleil Substation November 2015: 415 MW of generation was added to the RAS at Astoria, Garland, and Roy Substations July 2016: 108 MW of generation was added to the RAS at Teddy Substation November 2016: 3rd AA bank was added to Whirlwind Substation 4
5 Electric System Planning Purpose/Operating Principles The purpose of the Whirlwind AA Bank RAS is to prevent thermal overloads on the remaining Whirlwind AA Banks, upon loss of one (N-1) or two (N-2/N-1-1) of the three AA Banks, by tripping selected generation projects in the immediate area. Requesting approval to add the following projects to RAS Q643AJ-Willow Springs (Desert Flower Subs) 100 MW Q643R North Rosamond (Rattlesnake Subs) 150 MW Q1074 Gaskell West 20 MW Original Operating Date: July 21, 2015 Operating Date for requested changes: October 1,
6 Electric System Planning Whirlwind AA Bank RAS Area Map Location of SCE facilities and Generating Units TO VESTAL TO SPRINGVILLE SYCAMORE OMAR MIDWAY MAGUNDEN Mandible HIGHWIND CPC West CPC East WINDHUB Garland Suncreek MIDWAY PASTORIA PEF LEBEC EDMONSTON PUMPING PLANT (CDWR) BAILEY Manzana Desert Star Rose Meadow WHIRLWIND Kingbird Avenue Solar Ranch Roy Teddy WARNE ANTELOPE TO SANTA CLARA PARDEE VINCENT TO RIO HONDO TO MOORPARK TO SYLMAR TO GOODRICH TO MESA TO SAUGUS 6
7 Electric System Planning Planning Studies The purpose of the RAS Arming Study is to identify the appropriate RAS arming levels required under all plausible system operating conditions. The power flow cases were developed from the WECC base cases and SCE s transmission expansion base case series. The RAS Arming Study looks at a wide range of load levels, generation levels, and voltage conditions. Through this type of analysis, the RAS Arming Study identifies the appropriate contingencies that need to be protected by the RAS. 7
8 Electric System Planning Planning Studies Table 1-1 represents the queued generation up to Cluster 8 that have requested interconnection to Whirlwind Substation. In-service Now: 1858 MW Up to QC8: 3185 MW QC9: 1439 MW QC10: 580 MW 8
9 Electric System Planning Planning Studies Operating Voltages 500 kv System Voltages SOB0017 Whirlwind kv Whirlwind kv AA Bank Rating - SOB0033
10 Electric System Planning Contingency Analysis (N-1) The following table shows the outage overload results identified in the Whirlwind AA Bank RAS Arming Study. The table summarizes the maximum loading levels identified for the remaining AA banks under a single outage at different generation outputs. 10
11 Electric System Planning Contingency Analysis (N-1) The following table shows the resulting loading on the AA banks after the RAS has armed and tripped generation. MVAR Flow: PRE is after the loss of an AA bank but before the RAS trips generation 11
12 Electric System Planning Planning Studies N-1 Equation Y=1.0134x Orange line Needed to be at 99% of LTELL (MVA)
13 Electric System Planning Contingency Analysis (N-2/N-1-1) The following table shows the outage overload results identified in the Whirlwind AA Bank RAS Arming Study. The table summarizes the maximum loading levels identified for the remaining AA banks under an outage of two AA Banks at different generation outputs. 13
14 Electric System Planning Contingency Analysis (N-2/N-1-1) The following table shows the resulting loading on the AA banks after the RAS has armed and tripped generation. MVAR Flow: PRE is after the loss of an AA bank but before the RAS trips generation 14
15 Electric System Planning Planning Studies N-1-1 Equation Y=0.9977x Orange line Needed to be at 99% of LTELL (MVA)
16 Electric System Planning Planning Studies N-1 Equation Y=1.0134x N-1-1/N-2 Equation Y=0.9977x X= MW Flow on 1AA, 3AA & 4AA
17 Electric System Planning Bus Split Equation As part of this modification we will add the split bus operation equations
18 Electric System Planning Planning Studies Diagram shows theoretical power flow at Whirlwind AA Banks with all generation up to QC7 online 500kV BUS
19 Electric System Planning Planning Studies Section A: 1AA flow =909 MW Section B: 3AA+4AA flow = 1818 MW N-1 Equation Y=1.0134x X= 909 MW+1818 MW =2727 MW Generation armed = MW
20 Electric System Planning Planning Studies With the starting condition of one of the bus-sectionalizing breakers out for maintenance followed by Fault on transformer and stuck breaker 500kV BUS
21 Electric System Planning Planning Studies Current 3AA+4AA = 909 MW +909 MW = 1818 MW Using N-1-1/N-2 Equation Y=0.9977x Generation tripped = ~500 New Equation Using N-1-1/N-2 Equation Y=0.9977x X=3AA (909 MW)+4AA (909 MW)+CB1 (0 MW)+CB2 (219 MW) Actual generation needed to be tripped is ~718 MW
22 Electric System Planning Planning Studies N-1-1/N-2 Equation : Y=0.977x New Prosed equation is same as N-1-1/N-2 Y=0.9977x Changes under this condition X = Flow on (3AA+4AA+CB1+CB2) Generation tripped from Section B only
23 Electric System Planning Planning Studies Orange line Needed to be at 99% of LTELL (MVA) Section B has N-1
24 Electric System Planning Transient Stability Analysis Studies were performed with a scenario of normal fault clearing time of 6 cycles. Studies were performed with a scenario of a delayed fault clearing time of 13 cycles. Generation Tripping Times Worst case scenario : 25 cycles 24
25 Electric System Planning Conclusion The inclusion of the projects listed below did not have an adverse impact on the Whirlwind RAS. Q643AJ-Willow Springs MW Q643R North Rosamond 153 MW Q1074 Gaskell West 20 MW The Whirlwind RAS will initiate once an N-1 or N-2/N-1-1 outage of any of the three AA banks has been detected in order to prevent thermal overloads on the remaining AA banks New equation introduced in the event a bus split and an outage of one of the two AA banks in Section B occurs 25
26 Electric System Planning Conclusion The Whirlwind AA Bank RAS will trip a combination of the following generation to mitigate thermal overload: Once more generation connects to the Whirlwind 220 kv bus, the Whirlwind AA Bank RAS will need to be modified Transient stability studies concluded that the system will remain stable under various contingencies 26
27 WHIRLWIND RAS Protection Engineering Bill Zhang 27
28 Protection RAS Modifications Single Line Diagram of Whirlwind RAS 28
29 Rattlesnake Desert Flower Gaskell W1 Protection RAS Modifications Add two pairs of N60 relays at Whirlwind Subs for Monitoring the North and South 220kV Bus Section CB s Tripping interfaces to the three new Generations Add diversely-routed redundant communications paths to the new Generations Existing Generations 29
30 Protection RAS Modifications Add new arming points for The operation conditions of the 220 kv buses at Whirlwind being split (both South and North 220 kv Bus section CBs open) Tripping to the three new Generations Add watt transducers to the 220 kv bus section CBs at Whirlwind Subs and connect them to the EMS RTU. The EMS needs the bus section CB power flow (MW) in order to calculate the arming requirements for the new set of arming points 30
31 Protection Design Requirements The modifications comply with the existing RAS requirements Single failure cannot prevent trip output Redundant identical systems Diversely-routed redundant communications paths Contingency-triggered logic RAS action occurs only for an N-1 or N-2 outage condition for which the RAS is armed Arming logic prevents RAS operation if arming occurs after triggering contingency has occurred Pre-contingency arming by Automatic Arming Program 31
32 Protection Design Requirements Provide multiple means of arming Automatic Arming Program in EMS Remote Manual Arming via EMS Redundant RTU s One RTU for RAS-A One RTU for RAS-B RTU s provide the interface between EMS and RAS Controllers for Automatic Arming Program and Remote Manual Arming via EMS Local Manual Arming via N60 relay front-panel pushbuttons at Whirlwind Substation Used in case of RTU or EMS failure All RAS relays are dedicated to the RAS and do not share any function with any other protective scheme 32
33 Protection Relay Hardware GE N60 relays used throughout Except a C30 relay handing the Auto-Test Logic. Remote I/O (IEC GOOSE) Relay-to-Relay Communications Bank Monitors High and low-side CBs and currents are monitored independently Open CBs and lack of current on either side of the bank constitutes a bank-out condition Logic Processors N-1 and N-2 contingency detection Receiving Arming from EMS Local manual arming (pushbuttons) Transmission of trip signals to participating generators via Direct I/O communications over diversely-routed redundant C37.94 channels Tripping Relays (at Generation facilities) Monitored trip output contact for each circuit breaker to be tripped BFI output contact for each breaker to be tripped 33
34 Protection RAS Monitoring Relays/RTU/EMS Relay Failure alarms Relay Communications Failure and Trouble alarms CB Disagreement alarms CB Error alarms Arming status AA-Bank outage status RAS Trip alarm 4-second update 34
35 Abnormal Operating Conditions Relay Failure (Bank Monitor, Logic Processor, Tripping Relay) or Communications failure Disable the associated RAS (A or B) Complete loss of RAS What is considered as complete loss of RAS Loss of components in both RAS A and RAS B Loss of communications channels in both RAS A and RAS B Loss of RAS A comm channel and RAS B component, or vice versa Disable both RAS systems and request CAISO to implement congestion management to maintain AA-Bank flows to with acceptable limits 35
36 WHIRLWIND RAS Telecomm Engineering Hans Bakker 36
37 Telecommunications Existing and New Telecom Circuits ROY Rattlesnake Desert Flower SOLAR RANCH Gaskell West GARLAND AVENUE WHIRLWIND DESERT STAR TEDDY RING OF DIVERSE FIBER CABLE KING BIRD SOLEIL SOLAR Key Existing New 37
38 Telecommunications Whirlwind to Rattlesnake 38
39 Telecommunications Whirlwind to Desert Flower 39
40 Telecommunications Whirlwind to Gaskell West 40
41 Telecommunications EQUIPMENT REDUNDANCY EQUIPMENT DESCRIPTION MANUFACTURER MODEL REDUNDANCY CHANNEL BANK ZHONE IMACS 800 CPU, POWER SUPPLY, T1 MODULE OHSU IEEE C Channel Unit ZHONE I None, however spare channel port and channel reserved for future should the need arise. DACS Sycamore DNX-11 All critical electronics 1:1 SONET (LW) Alcatel - Lucent DMX Family of Access Multiplexer 1:1 41
42 Telecommunications SONET employs element management systems All sites have point alarms for equipment & environmental alarm Telecomm Control Center (TCC) monitors 24x7x365 using NetCool which replaced the previous tool NetExpert TCC responsible for coordination & dispatch of repair personal Comm Techs based through service territory; spare parts are stored at several key locations Priority 1 problems have 2 hour response time and 4 hour repair time. 42
43 WHIRLWIND RAS PROJECT Power System Controls Obinna Obah 43
44 Power System Controls Modifications to the Whirlwind RAS Project Objectives: The existing Whirlwind RAS (WHDRAS) automatic arming program will be modified to: Add Rattlesnake, Desert Flower and Gaskell West Generators Add arming points for N-1 AA transformer Banks with bus section CBs open Automatic arming program will calculate appropriate amount of generation to arm and trip to mitigate thermal overloads on the remaining bank(s) upon: N-1 or N-2 loss of any of the of AA transformer banks with bus sections paralleled N-1 loss of any of the AA transformer banks with both bus section CBs open 44
45 Power System Controls Modifications to the Whirlwind RAS Project Reliability: Automatic Arming program is a software application running in SCE s redundant Energy Management System (EMS) that monitors the status and loading of transformers and generators participating in the RAS. 45
46 Power System Controls Modifications to the Whirlwind RAS Project Automatic Arming Program Operation: The Whirlwind RAS automatic arming program runs every four seconds and retrieves transformer flow and status, bus section circuit breaker flow and status and generation output data used for arming determinations. Program calculates arming requirements every five minutes or whenever flows on monitored transformer banks change more than the value set by the operator. Utilizes best-fit algorithm to optimally arm the appropriate amount of generation to trip for N-1 and N-2 loss of any of the of AA bank transformers. 46
47 Power System Controls 47
48 SCE is requesting approval of Whirlwind AA-Bank RAS Modifications to add the following three projects: Willow Springs 100 MW N. Rosamond 150 MW Gaskell West 20 MW
49 Thank You!
Southern California Edison Company Tariff Title: Transmission Owner Tariff Tariff Record Title: Service Agreement No. 101 FERC FPA Electric Tariff ENGINEERING, DESIGN AND PROCUREMENT LETTER AGREEMENT BETWEEN
More informationStandard Development Timeline
PRC 012 2 Remedial Action Schemes Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective.
More informationPRC Remedial Action Schemes
PRC-012-2 Remedial Action Schemes A. Introduction 1. Title: Remedial Action Schemes 2. Number: PRC-012-2 3. Purpose: To ensure that Remedial Action Schemes (RAS) do not introduce unintentional or unacceptable
More informationSouthern California Edison Company Tariff Title: Transmission Owner Tariff Tariff Record Title: Service Agreement No. 92 FERC FPA Electric Tariff ENGINEERING, DESIGN AND PROCUREMENT LETTER AGREEMENT BETWEEN
More informationImplementation of BAL Dede Subakti
Implementation of BAL-002-2 Dede Subakti Agenda Background information Impact assessment Issue statement Implementation options Request for comments Page 2 Background Information NERC BAL-002-2 was approved
More informationContents Introduction Chapter 1 - Security Policy... 6
Policy statement Contents Introduction... 5 PURPOSE... 5 SYSTEM OPERATOR POLICIES TO ACHIEVE THE PPOS and dispatch objective... 5 Avoid Cascade Failure... 5 Frequency... 6 Other Standards... 6 Restoration...
More informationT-D Interconnections: Best Value Planning White Paper January 2016
T-D Interconnections: Best Value Planning White Paper Updated January 2016 1. Purpose This paper defines the process and criteria that together constitute joint best value planning (BVP) between ATC and
More informationTRIP OF MULTIPLE TRANSMISSION ELEMENTS IN THE SOUTHERN NSW AREA, 11 FEBRUARY 2017
TRIP OF MULTIPLE TRANSMISSION ELEMENTS IN THE SOUTHERN NSW AREA, 11 FEBRUARY 2017 REVIEWABLE OPERATING INCIDENT REPORT UNDER THE NATIONAL ELECTRICITY RULES Published: 15 September 2017 INCIDENT CLASSIFICATIONS
More informationTitle Page Southern California Edison Company Tariff Title: Transmission Owners Tariff Tariff Record Title: First Revised Service Agreement No. 39 FER
Title Page Southern California Edison Company Tariff Title: Transmission Owners Tariff Tariff Record Title: First Revised Service Agreement No. 39 FERC FPA Electric Tariff INTERCONNECTION FACILITIES AGREEMENT
More informationAppendix A. - Transmission Constraints. Physical and operational limitations on the transfer of electric power through transmission facilities, which
Appendix A - Transmission Constraints Physical and operational limitations on the transfer of electric power through transmission facilities, which include Contingencies and Nomograms. - Contingency A
More informationQ50 Facility Study. By Tucson Electric Power Company Transmission Planning March 7, Proposed Point of Interconnection: Vail Fort Huachuca 138kV
Q50 Facility Study Proposed Point of Interconnection: Vail Fort Huachuca 138kV By Tucson Electric Power Company Transmission Planning March 7, 2018 PREPARED BY: FACILITY STUDY PREPARED FOR: TUCSON ELECTRIC
More informationITP Evaluation Process Plan
ITP Evaluation Process Plan HVDC Conversion Project The goal of the coordinated Interregional Transmission Project (ITP) evaluation process is to achieve consistent planning assumptions and technical data
More informationTRIP OF VALES POINT 330 KV MAIN BUSBAR ON 27 JULY 2017 REVIEWABLE OPERATING INCIDENT REPORT UNDER THE NATIONAL ELECTRICITY RULES
TRIP OF VALES POINT 330 KV MAIN BUSBAR ON 27 JULY 2017 REVIEWABLE OPERATING INCIDENT REPORT UNDER THE NATIONAL ELECTRICITY RULES Published: 26 September 2017 INCIDENT CLASSIFICATIONS Classification Detail
More informationREISSUED JUNE 1, 1988
REVISED SHEET NO. 29 Effective: October 28, 1966 RULE NO. 14 REISSUED JUNE 1, 1988 Service Connections and Facilities on Customer's Premises A. METER INSTALLATIONS AND MISCELLANEOUS SERVICE EQUIPMENT ON
More informationBC HYDRO REAL TIME OPERATIONS OPERATING ORDER 7T 18. BC - US INTERCONNECTION Supersedes 7T-18 issued 15 December 2015
BC HYDRO REAL TIME OPERATIONS OPERATING ORDER 7T 18 BC - US INTERCONNECTION Supersedes 7T-18 issued 15 December 2015 Review Year: 2019 APPROVED BY: Original signed by: Paul Choudhury General Manager, Real
More informationCost Estimation for Regional Transmission Overlay Study (RTOS)
Cost Estimation for Regional Transmission Overlay Study (RTOS) Purpose & Key Takeaways Purpose: To provide detail for MISO s cost estimation approach Key Takeaways: Planning-Level and Scoping-Level MISO
More informationPOWER SYSTEM NOT IN A SECURE OPERATING STATE IN VICTORIA ON 15 JUNE 2016 REVIEWABLE OPERATING INCIDENT REPORT UNDER THE NATIONAL ELECTRICITY RULES
POWER SYSTEM NOT IN A SECURE OPERATING STATE IN VICTORIA ON 15 JUNE 2016 REVIEWABLE OPERATING INCIDENT REPORT UNDER THE NATIONAL ELECTRICITY RULES Published: November 2016 INCIDENT CLASSIFICATIONS Classification
More informationInformation Document FAC-008-AB-3 Facility Ratings ID # RS
Information Documents are not authoritative. Information Documents are for information purposes only and are intended to provide guidance. In the event of any discrepancy between an Information Document
More informationWECC Criterion PRC-003-WECC-CRT-1.3
WECC Criterion PRC-003-WECC-CRT-1.3 A. Introduction 1. Title: Analysis, Reporting, and Mitigation of Transmission and Generation Protection System and Remedial Action Scheme Misoperations Procedure 1 2.
More informationAlberta Utilities Commission
Alberta Utilities Commission In the Matter of the Need for the Grizzly Bear Creek Wind Power Plant Connection And in the matter of the Electric Utilities Act, S.A. 2003, c. E-5.1, the Alberta Utilities
More informationtransmission system. This project is referred to in the Transition Agreement as the Transmission Interconnection.
2 Application of Valley Electric Association, Inc. to the California Independent System Operator Corporation to Become a Participating Transmission Owner June 21, 2012 Valley Electric Association, Inc.
More informationMiCOM P443-6/P543-7/P841
MiCOM P443-6/P543-7/P841 Release Notes P443-6/P543-7/P841 Upgrade Platform Hardware Version: M, P Platform Software Version: 75, 65, 45 Publication Reference: P443-6/P543-7/P841-RNC1-TM-EN-1 ALSTOM 2013.
More informationAlberta Utilities Commission
Alberta Utilities Commission In the Matter of the Need for 138 kv and 240 kv Transmission System Development in the Red Deer Region And in the matter of the Electric Utilities Act, S.A. 2003, c. E-5.1,
More informationExpenditure Forecast Methodology
Forecast Methodology Regulatory Control Period 2018-19 to 2022-23 Version 1.0 Security Classification: Public ElectraNet Corporate Headquarters 52-55 East Terrace, Adelaide, South Australia 5000 PO Box
More informationEXCERPTS from the SAMS-SPCS SPS Technical Reference
Problem Statement The existing NERC Glossary of Terms definition for a Special Protection System (SPS or, as used in the Western Interconnection, a Remedial Action Scheme or RAS) lacks clarity and specificity
More informationComments of Pacific Gas & Electric Company Energy Imbalance Market Draft Tariff Language
Comments of Pacific Gas & Electric Company Energy Imbalance Market Draft Tariff Language Submitted by Company Date Submitted Will Dong Paul Gribik (415) 973-9267 (415) 973-6274 PG&E December 5, 2013 Pacific
More informationTRANSGRID PRICING METHODOLOGY 2015/ /18. Contents
Pricing Methodology TRANSGRID PRICING METHODOLOGY 2015/16 2017/18 Contents Pricing Methodology 1 Introduction 3 2 Duration 3 3 Which services are subject to this pricing methodology? 4 4 Overview of the
More informationConnection and Use of System Charge Methodology Statement ("Condition 25 Statement")
Connection and Use of System Charge Methodology Statement ("Condition 25 Statement") Revised Effective Date: 1 st January 2016 Approved by the Authority for Electricity Regulation, Oman Connection and
More informationAmendment to extend exceptional dispatch mitigated energy settlement rules and modify residual imbalance energy settlement rules
California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Nancy Saracino, Vice President, General Counsel & Chief Administrative Officer Date: September 7, 2012 Re:
More informationAppendix A. - Transmission Constraints. Physical and operational limitations on the transfer of electric power through transmission facilities, which
Appendix A - Transmission Constraints Physical and operational limitations on the transfer of electric power through transmission facilities, which include Contingencies and Nomograms. - Contingency A
More informationBusiness Practice Manual For. Queue Management. Version 12
Business Practice Manual For Queue Management Version 12 Revision Date: March 4June 27, 2014 Approval History Approval Date: February, 2014 Effective Date: March, 2014 BPM Owner: Deb Le Vine BPM Owner
More informationAlberta Utilities Commission
Alberta Utilities Commission In the Matter of the Need for the Irma Wind Power Project Connection And in the matter of the Electric Utilities Act, S.A. 2003, c. E-5.1, the Alberta Utilities Commission
More informationCOLUMBIAGRID GEOMAGNETIC DISTURBANCE DRAFT STUDY REPORT
COLUMBIAGRID GEOMAGNETIC DISTURBANCE DRAFT STUDY REPORT (NERC Standard TPL-007-1) Revision 1 February 1, 2018 ColumbiaGrid 8338 NE Alderwood Road, Suite 140 Portland, OR 97220 www.columbiagrid.org (503)
More informationOrange and Rockland Utilities, Inc. Issued in compliance with Order in Case 15-E-0036 dated 07/20/2015.
Orange and Rockland Utilities, Inc. Addendum - SIR-5 INITIAL EFFECTIVE DATE: July 27, 2015 To P.S.C. No. 3 - Electricity Issued in compliance with Order in Case 15-E-0036 dated 07/20/2015. New York State
More informationSIMULTANEOUS TRIP OF SOUTH EAST No.1 AND No kv SVCs ON 31 JULY 2017 REVIEWABLE OPERATING INCIDENT REPORT UNDER THE NATIONAL ELECTRICITY RULES
SIMULTANEOUS TRIP OF SOUTH EAST No.1 AND No.2 275 kv SVCs ON 31 JULY 2017 REVIEWABLE OPERATING INCIDENT REPORT UNDER THE NATIONAL ELECTRICITY RULES Published: 20 September 2017 INCIDENT CLASSIFICATIONS
More informationProject Coordination and Path Rating
Document name Category Project Coordination, Path Rating and Progress Report Processes ( ) Regional Reliability Standard ( ) Regional Criteria ( ) Policy (X) Guideline ( ) Report or other ( ) Charter Document
More informationNew York State Public Service Commission
PSC NO. 220 ELECTRICITY ADDENDUM TYPES: SIR NIAGARA MOHAWK POWER CORPORATION ADDENDUM NO. 7 INITIAL EFFECTIVE DATE: AUGUST 16, 2017 STAMPS: ISSUED IN COMPLIANCE WITH ORDER IN CASE 16-E-0560 Issued August
More information2018 General Rate Case. Transmission & Distribution (T&D) Volume 3 R System Planning
Application No.: Exhibit No.: Witnesses: A.1-0- A SCE-0, Vol. 0 R A E. Takayesu (U -E) 01 General Rate Case rd Errata ERRATA Transmission & Distribution (T&D) Volume R System Planning Before the Public
More informationJanuary 31, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC Dear Ms.
Regulation James A. Cuillier Director FERC Rates & Regulation January 31, 2014 Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426 Dear Ms.
More informationTABLE OF CONTENTS ARTICLE ONE: RECITALS... 5 ARTICLE TWO: ABBREVIATIONS, ACRONYMS, AND DEFINITIONS... 6 ARTICLE THREE: OPERATING COMMITTEE...
TABLE OF CONTENTS ARTICLE ONE: RECITALS... 5 ARTICLE TWO: ABBREVIATIONS, ACRONYMS, AND DEFINITIONS... 6 2.1 Abbreviations and Acronyms... 6 2.2 Definitions... 7 2.3 Rules of Construction... 10 ARTICLE
More informationConsumer Requirements for Distributed Generation Installation and Interconnection
Rio Grande Electric Cooperative, Inc. Consumer Requirements for Distributed Generation Installation and Interconnection (Click on links to be taken to the appropriate page) TABLE OF CONTENTS SECTION PAGE
More informationUK Power Networks. Overall Cost Benefit Analysis
UK Power Networks Overall Cost Benefit Analysis Contents 1 Executive Summary 3 1.1 Analysis Conclusions 3 1.2 Summary Table 4 2 Introduction 5 2.1 Scope 5 2.2 Input Parameters 6 2.3 Asset Replacement/Refurbishment
More informationNTTG REGIONAL TRANSMISSION PLAN. December 30, 2015
NTTG 2014-2015 REGIONAL TRANSMISSION PLAN December 30, 2015 1 Table of Contents Executive Summary... 3 Introduction... 3 The Northern Tier Transmission Group... 3 Participating Utilities... 4 Purpose of
More informationTown of Holly Springs
Meeting Date: March 20, 2018 Town of Holly Springs Town Council Meeting Agenda Form Town Clerk s Office Use: Agenda Item #: 8h Attachment #: 3h Agenda Placement: Consent Agenda (Special Recognitions (awards,
More informationElectricity Pricing Event Reports
Electricity Pricing Event Reports SEPTEMBER 2015 TABLE OF CONTENTS Friday 17 September 2015 High Energy price SA... 2 Tuesday 22 September 2015 High Energy price SA, VIC, TAS... 2 Wednesday 23 September
More informationSTATE OF NEW HAMPSHIRE BEFORE THE PUBLIC UTILITIES COMMISSION. Docket No. DE
STATE OF NEW HAMPSHIRE BEFORE THE PUBLIC UTILITIES COMMISSION Liberty Utilities (Granite State Electric) Corp. d/b/a Liberty Utilities Distribution Service Rate Case DIRECT TESTIMONY OF CHRISTIAN P. BROUILLARD
More informationNew Mexico Public Regulation Commission P. O. Box Paseo de Peralta Santa Fe, New Mexico 87504
THE NEW MEXICO INTERCONNECTION MANUAL (To be Used in Conjunction with New Mexico Public Regulation Commission Rule 17.9.568 NMAC, Interconnection of Generating Facilities with a Rated Capacity Up to and
More informationRegulation Director FERC Rates & Regulation. March 16, 2012
Regulation Director FERC Rates & Regulation March 16, 2012 Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426 Dear Ms. Bose: Pursuant to Section
More informationA. Introduction. Standard MOD Flowgate Methodology
A. Introduction 1. Title: Flowgate Methodology 2. Number: MOD-030-3 3. Purpose: To increase consistency and reliability in the development and documentation of transfer capability calculations for short-term
More informationCOMPARISION OF OFFSHORE REQUIREMENTS
Key to Table COMPARISION OF OFFSHORE REQUIREMENTS (Comparison based on GB Grid Code Issue 4 Revision 13 only and ENSTO - E RFG Internal Version dated 26 June 2012) (Note Does not include other Industry
More informationSupersedes: 9/01/11 (Rev.5) Preparer: Owner: Approver: Team Member, North America Process Safety Center of Expertise
Procedure No.: BC032.019 Page: 1 of 12 Preparer: Owner: Approver: Team Member, North America Process Safety Center of Expertise Manager, North America Process Safety Center of Expertise Sr. Vice President,
More informationSystem Impact Study Report Generation Interconnection Request # GI
System Impact Study Report Generation Interconnection Request # GI-2015-1 Executive Summary 250 MW Wind Generation Facility Comanche Daniels Park 345kV Line (L7015) Elbert County, Colorado Transmission
More informationInterconnection and Protection Engineering Breaking News: Policy Update
Interconnection and Protection Engineering Breaking News: Policy Update Unintentional Islanding Protection Practice for DER Chris Vance National Grid Engineering Policy Safety Message All field visits
More informationLoad and Resource Transmission Analysis 2011 through 2020
Load and Resource Transmission Analysis through June, Prepared by: Joe Costello, Igor Kormaz and Mark Stout Background Pursuant to the provisions of Tri-State s Network Operating Agreements with its network
More informationS atisfactory reliability and cost performance
Grid Reliability Spare Transformers and More Frequent Replacement Increase Reliability, Decrease Cost Charles D. Feinstein and Peter A. Morris S atisfactory reliability and cost performance of transmission
More informationAlberta Utilities Commission
Alberta Utilities Commission In the Matter of the Need for the Jenner Wind Energy Connection And in the matter of the Electric Utilities Act, S.A. 2003, c. E-5.1, the Alberta Utilities Commission Act,
More informationREBUTTAL TESTIMONY OF NEIL MILLAR ON BEHALF OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION
Application No.: --00 Exhibit No.: Witness: Neil Millar In the Matter of the Application of SOUTHERN CALIFORNIA EDISON COMPANY (UE) for a Certificate of Public Convenience and Necessity for the West of
More informationUNITED COOPERATIVE SERVICES. Distributed Generation Procedures & Guidelines Manual for Members
UNITED COOPERATIVE SERVICES Distributed Generation Procedures & Guidelines Manual for Members October 2015 TABLE OF CONTENTS GENERAL... 4 I. DETERMINE THE CATEGORY OF DG FACILITY... 5 1) Connection Level
More informationStandard for Interconnecting Small Generation 100 kw or Less with Electric Power Systems (EPS) (Interconnection Standard)
63 SOUTH CAROLINA Standard for Interconnecting Small Generation 100 kw or Less with Electric Power Systems (EPS) (Interconnection Standard) 1. Overview: This Standard contains the requirements, in addition
More informationBusiness Practice Manual For. Generator Management. Version 8
Business Practice Manual For Generator Management Version 8 Revision Date: June 30, 2015 Approval History Approval Date: February, 2014 Effective Date: March, 2014 BPM Owner: Deb Le Vine BPM Owner s Title:
More informationSPP REPORT ON TLR EVENTS FROM FEBRUARY 13 MARCH 4, 2002
SPP REPORT ON TLR EVENTS FROM FEBRUARY 13 MARCH 4, 2002 On seven occasions between February 13 and March 4, 2002, SPP initiated a TLR on the MorStiSooNor flow gate, #5067, that included firm service curtailments.
More informationInterconnection Application and Compliance Form For Photovoltaic Systems Up to 2 MW
Interconnection Application and Compliance Form For Photovoltaic Systems Up to 2 MW A. APPLICANT INFORMATION *Person/Company Name: *OUC Account No.: *Mailing Address: *City, State & Zip: Street Address
More informationCAPE HATTERAS ELECTRIC COOPERATIVE
CAPE HATTERAS ELECTRIC COOPERATIVE INTERCONNECTION STANDARD STANDARD FOR INTERCONNECTING SMALL GENERATION 100 kw OR LESS 1. Definitions: 1.1 Area EPS: Area Electric Power System: The electric facilities
More informationWECC Criterion TPL-001-WECC-CRT-3.1
WECC Criterion TPL-001-WECC-CRT-3.1 A. Introduction 1. Title: Transmission System Planning Performance 2. Number: TPL-001-WECC-CRT-3.1 3. Purpose: To facilitate coordinated near-term and long-term transmission
More informationBEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION IN THE MATTER OF THE APPLICATION OF ROCKY MOUNTAIN POWER FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY AND BINDING RATEMAKING TREATMENT FOR NEW WIND
More informationThe following Information Requests pertain to the spreadsheet file Attachment_H- 1_Formula_Rate_2015_-Run_1_posted_ _(effective_ ) :
TGST 1-1: Refer to PNM S 2014 FERC Form 1 page 207, line 50, Account 353 Station Equipment, please provide a description of significant projects ($5 million or more) contributing to the increase of approximately
More informationStandard MOD Flowgate Methodology
A. Introduction 1. Title: Flowgate Methodology 2. Number: MOD-030-1 3. Purpose: To increase consistency and reliability in the development and documentation of transfer capability calculations for short-term
More informationBANDERA ELECTRIC COOPERATIVE, INC. Tariff for Electric Service. Sheet No. Section III 1.0
1.0 340. Small Power Production Sections 340-345 of this tariff apply to the interconnection and parallel operation of all small power generating installations. All installations must meet all system performance
More informationAlberta Utilities Commission
Alberta Utilities Commission In the Matter of the Need for the Al Rothbauer 321S Substation And in the matter of the Electric Utilities Act, S.A. 2003, c. E-5.1, the Alberta Utilities Commission Act, S.A.
More informationSTATE OF NEW JERSEY OFFICE OF ADMINISTRATIVE LAW BEFORE HONORABLE IRENE JONES, ALJ ) ) ) ) ) ) ) ) )
STATE OF NEW JERSEY OFFICE OF ADMINISTRATIVE LAW BEFORE HONORABLE IRENE JONES, ALJ I/M/O the Verified Petition of Rockland Electric Company For Approval of Changes in Electric Rates, Its Tariff For Electric
More informationPortland General Electric Company P.U.C. Oregon No. E-18 Original Sheet No. C-1 RULE C CONDITIONS GOVERNING CUSTOMER ATTACHMENT TO FACILITIES
P.U.C. Oregon No. E-18 Original Sheet No. C-1 RULE C CONDITIONS GOVERNING CUSTOMER ATTACHMENT TO FACILITIES 1. Acceptance of Electricity Service By establishing or requesting a POD or by continuing an
More informationSouth Carolina Standard for Interconnecting Small Generation 100 kw or Less With Electric Power Systems (EPS) (Interconnection Standard)
South Carolina Standard for Interconnecting Small Generation 100 kw or Less With Electric Power Systems (EPS) (Interconnection Standard) 1. Overview: This Standard contains the requirements, in addition
More informationNERC TPL Standard Overview
NERC TPL-001-4 Standard Overview Attachment K Quarter 3 Stakeholder s Meeting September 29, 2016 1 Background New NERC TPL Standard 2016 TPL Plan and Status Update 2015 Planning Assessment Results Compliance
More information(U 338-E) SO4 PPA. Before the. Public Utilities Commission of the State of California
Application No.: Exhibit No.: Witnesses: A.18-03-XXX SCE-04 J. Martin (U 338-E) SO4 PPA Before the Public Utilities Commission of the State of California Rosemead, California March 19, 2018 LONG TERII
More informationFebruary 23, 2015 VIA ELECTRONIC FILING
February 23, 2015 VIA ELECTRONIC FILING The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: Southwest Power Pool, Inc., Docket
More information10-day Formal Comment Period with a 5-day Additional Ballot (if necessary), pursuant to a Standards Committee authorized waiver.
Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed
More informationSTCP19-5 Issue 002 Offshore Transmission System Compliance Process & Testing
STCP19-5 Issue 002 Offshore Transmission System Compliance Process & Testing STC Procedure Document Authorisation Company National Grid Electricity Transmission plc Name of Party Representative Signature
More informationSERVICE CLASSIFICATION NO. 14-RA STANDBY SERVICE
Fourth Revised Leaf No. 135 Consolidated Edison Company Superseding Second Revised Leaf No. 135 (Third Revised Leaf No. 135 Canceled) Applicable to Use of Service for SERVICE CLASSIFICATION NO. 14-RA The
More informationWECC Guideline: UNSCHEDULED FLOW REDUCTION GUIDELINE
The content of this document is an excerpt of the WECC Unscheduled Flow Mitigation Plan Document posted on www.wecc.biz. Introduction WECC : UNSCHEDULED FLOW REDUCTION GUIDELINE The combination of Scheduled
More informationBusiness Practice Manual For The Energy Imbalance Market. Version 78
Business Practice Manual For The Energy Imbalance Market Version 78 Revision Date: March 31May 31, 2017 Approval History Approval Date: October 2, 2014 Effective Date: October 2, 2014 BPM Owners: Mike
More information2018 General Rate Case
Application No.: A.16-09- Exhibit No.: SCE-0, Vol. 08 Witnesses: J. R. Goizueta M. Flores A (U 338-E) 018 General Rate Case Transmission & Distribution (T&D) Volume 8 - Infrastructure Replacement Before
More informationProject Assessment Conclusions Report
Powerlink Queensland Project Assessment Conclusions Report 27 August 2018 Addressing the secondary systems condition Disclaimer While care was taken in preparation of the information in this document,
More informationSouthern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.
Southern California Edison Revised Cal. PUC Sheet No. 64409-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 58722-E Schedule NEM Sheet 1 APPLICABILITY Applicable to Eligible Customer-Generators
More informationStandard for Interconnecting Small Generation 100 kw or Less with Electric Power Systems (EPS) (Interconnection Standard)
1. Overview: Standard for Interconnecting Small Generation 100 kw or Less with Electric Power Systems (EPS) (Interconnection Standard) This Standard contains the requirements, in addition to applicable
More informationBusiness Practice Manual For The Energy Imbalance Market. Version 89
Business Practice Manual For The Energy Imbalance Market Version 89 Revision Date: Jan 02, 2018May 31, 2017 Approval History Approval Date: October 2, 2014 Effective Date: October 2, 2014 BPM Owners: Mike
More informationAlberta Utilities Commission
Alberta Utilities Commission In the Matter of the Need for the ATCO Power Heartland Generating Station Connection And in the matter of the Electric Utilities Act, S.A. 2003, c. E-5.1, the Alberta Utilities
More informationIndependent Review of Aurora Network summary of findings. Michael Van Doornik, Manager Advisory (VIC) 31 October 2018
Independent Review of Aurora Network summary of findings Michael Van Doornik, Manager Advisory (VIC) 31 October 2018 Agenda 1. Terms of reference 2. Limitations of the review 3. Our approach to undertaking
More informationSOLAR PV INSTALLATION AT USC BASEBALL STADIUM
AMENDMENT NO. 7 TO SOLICITATION TO: ALL VENDORS FROM: Charles Johnson, Procurement Manager SUBJECT: SOLICITATION NUMBER: USC-RFP-1761-CJ SOLAR PV INSTALLATION AT USC BASEBALL STADIUM DATE: June 30, 2010
More informationSouthern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.
Southern California Edison Revised Cal. PUC Sheet No. 61411-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 53858-E Schedule TOU-BIP Sheet 1 APPLICABILITY This Schedule is optional
More information2012 Budget. Customer Presentation October 10, Helping to keep the lights on, businesses running and communities strong
2012 Budget Customer Presentation October 10, 2011 Helping to keep the lights on, businesses running and communities strong Welcome & Overview Welcome! Introductions Tom Finco Budget Overview Kevin Szalacinski
More informationTRANSMISSION CHARGING STATEMENT
TRANSMISSION CHARGING STATEMENT 1 September 2016 1 September 2016 TABLE OF CONTENTS Page 1 Introduction... 1 2 General System Charges... 4 3 Site Specific Charges... 5 4 Connection Assets... 8 5 Least
More informationBusiness Practice Manual For. Generator Management. Version 76
Business Practice Manual For Generator Management Version 76 Revision Date: April 30, 3015June 1, 2015 Approval History Approval Date: February, 2014 Effective Date: March, 2014 BPM Owner: Deb Le Vine
More informationA New Redundancy Strategy for High-Availability Power Systems
Kevin Covi IBM STG High-End Server Development A New Redundancy Strategy for High-Availability Power Systems Outline RAS Philosophy Review Power 6 Traditional approach Power 7 Hybrid approach Load lines
More informationSCE STANDARD CONTRACT LONG TERM POWER PURCHASE POWER PURCHASE CONTRACT BETWEEN SOUTHERN CALIFORNIA EDISON COMPANY AND SELLER
SCE STANDARD CONTRACT LONG TERM POWER PURCHASE POWER PURCHASE CONTRACT BETWEEN SOUTHERN CALIFORNIA EDISON COMPANY AND SELLER DOCUMENT NO. MASTERS/V10 EFFECTIVE DATE: SEPTEMBER 7, 1983 REVISED: MAY 4, 1984
More informationBusiness Practice Manual For. Generator Management. Version Revision Date: August 7September 8, Page i
Business Practice Manual For Generator Management Version 2021 Revision Date: August 7September 8, 2017 Page i Approval History Approval Date: February, 2014 Effective Date: March, 2014 BPM Owner: Deb
More informationIMPORTANT INFORMATION Invitation to Bid No. TS12-S-10 Kindly acknowledge important revisions to the terms and conditions under the bidding documents in details as follows: Volume I of IV 1. TC-SUB-01 Data
More informationJefferson Energy Cooperative Policy 124 DISTRIBUTED GENERATION POLICY
DISTRIBUTED GENERATION POLICY I. OBJECTIVE This document establishes the terms and conditions for the interconnection of distributed generation facilities and for providing net energy metering services
More informationImplementation Plan Project PRC-005 FERC Order No. 803 Directive PRC-005-6
Project 2007-17.4 PRC-005 FERC Order No. 803 Directive PRC-005-6 Standards Involved Approval: PRC 005 6 Protection System, Automatic Reclosing, and Sudden Pressure Relaying Maintenance Retirement: PRC
More informationWorkpapers. Transmission & Distribution Grid Operations SCE-03 Volume General Rate Case APPLICATION. An EDISON INTERNATIONAL Company
An EDISON INTERNATIONAL Company (U 338-E) 215 General Rate Case APPLICATION Workpapers Transmission & Distribution Grid Operations SCE-3 Volume 7 N ovem ber 213 1 Workpaper - Southern California Edison
More informationEnergy Storage Systems (ESS): Preparing to Deal with the Hazards
2017 NFPA Conference & Expo Energy Storage Systems (ESS): Preparing to Deal with the Hazards Presented by: Skip Donnell Engineering Manager Liberty Mutual Insurance Legal Disclaimer: Course Focus & Limitations
More information