CIV E 710 Sample Exam Questions. Activity a m b A B C D E F G H I B 80 Mhrs.

Size: px
Start display at page:

Download "CIV E 710 Sample Exam Questions. Activity a m b A B C D E F G H I B 80 Mhrs."

Transcription

1 1 IV 710 Sample xam Questions Question 1: a) The optimistic, most likely, and pessimistic durations for the activities in the small project shown are in the following table. What is the probability of the project being completed in 0 days or more? ctivity a m b H I 6 9 b) onsider the following payoff table: 1) Which stock would the optimistic investor choose? ) Which stock would the pessimistic investor choose? ) Which stock has the highest expected return given the probability of a poor economy is 10%, a good economy is 50%, and an excellent economy is 0%? raw you decision tree in this case. State of conomy Stock Poor ood xcellent IM T Q WT Question : Mhrs 16 Mhrs The following network represents the activities in a single unit. If you are to construct 6 units in 5 days, 8 Mhrs calculate the crews that need to be involved and draw the schedule of all activities. 96 Mhrs 7 Mhrs Men If budget cost is $1,000 per activity day, draw the WS chart. If by end of day 1, total actual expenditure is 50K, while the earned value is $5K. alculate the cost and schedule variances and comment on project status.

2 Question : - Two basic assumptions in riedman s model for bidding strategy are: - Monte arlo Simulation uses a distribution for activities durations, while PRT uses a distribution. - The general strategy to improve resource profiles in a project is to: - The general strategy to efficiently allocate limited resource in a project is to: - The general strategy to crash a project to meet a strict deadline is to: - In the small example below, determine the responsibility for the delay beyond deadline: a) Using ut-or analysis, owner s perspective; and b) Using ut-or analysis, contractor s perspective. s-planned ar hart s-uilt ar hart - If a typical competitor has a / ratio with mean value of 1.08 and standard deviation of 0.1, what is the markup associated with a 0% probability of winning typical competitors? What is the contractor s expected profit at this markup if the cost estimate for the job is $10,000,000?

3 Question : Your design team is establishing a multiple-criteria analysis for awarding bids to the most suitable contractors. The three criteria chosen are: bid price, years of experience, and financial strength (value of assets). To facilitate the analysis, the design team also established utility functions for the no. of experience years and the value of assets, as shown below. In addition, the team agreed that the bid price is 6 times as important as the experience, while the bid price is times as important as financial strength. ut, financial strength is times as important as experience Years 0 - ssets (mil.) > <1 In evaluating the bidders for a new job, three bids are received as follows: - ompany : bid= $1.5 mil.; 10 years experience; and value of assets = $5 mil. - ompany : bid= $1.9 mil.; years experience; and value of assets = $7 mil. - ompany : bid= $1.9 mil.; years experience; and value of assets = $1 mil. Which bidder should be selected and why? Other Questions iven the following project data, calculate and show: The logic network; the ritical path; and the overall % complete of the project, to-date. ctivity Predecessors uration ost x $1,000 ctual Percent omplete, to-date H I J,, H, I % 100% 70% 50% 15%

4 - What is your comment about the cost and schedule performances of a project having the following control curves at current date. - Two criticisms of PRT technique in dealing with uncertainty in project duration are: - One benefit of using Monte arlo Simulation over the PRT technique in dealing with uncertainty in project duration is: - alculate and show the critical path for the following project: uration ctivity (days) H 8 I 6 J 6 K 10 - The following O network shows durations in months: a. Perform PM calculation, determine the critical path, and draw a late bar chart. () (8) 9 H () 1 () 5 (6) 11 I (8) 15 K (5) 17 () 7 (6) (7) 1 J ()

5 5 - ctual daily percentage completes are shown below until the end of day 5. - alculate and draw the remaining schedule. - What is the expected project duration, as compared to plan? - alculate the ost Performance Index and the Schedule Performance Index at end of day 5. - omment on current progress. ctivity epends on Planned ur / $ --- / K ctual $ to date K % % % / K K / K 0 ctuals 5% 50% / 5K 5K 10% 10% 10% 10% 0% - typical subcontract involves the following small network. You are involved in constructing 6 of these units in 5 days. Manually calculate the number of crews that need to be involved in each activity. raw the schedule of all activities but consider the following conditions: Unit requires half the construction times in all activities. The crews for activity are limited to but the contractor will bring new machinery for this activity that will reduce its duration in units to 6 to only 6 days. o you meet the deadline? If not, write your comments. Mhrs 16 Mhrs 8 Mhrs 96 Mhrs 7 Mhrs Men - Let's consider a simple project network with three possible durations as shown. alculate the probability of the project being completed in 0 days of less. 1,,5,6,9 1,, 7,8,10 7,10,1 1,16,0 J 5,6, ,,6 H 7,8,10 6 K 6,10,1 I,6,9 9

6 6 -The previous records of a past bids against key competitors is in the following table. Using riedman s model, determine the markup needed to optimize expected profit in bidding against competitors,, and in a new job with an estimated total cost of $,000,000. Job No. 1 ontractor s id price of competitors ($) cost estimate ($) 1,550,000 1,900,000 1,700,000 1,750,000,000,000,000,000,00,000 1,00,000 1,500,000 1,00,000 1,650,000 1,00,000 1,600,000 1,00,000 - If a decision is governed by three main criteria; criterion 1 is times as important as criteria ; criterion is 9 times as important as criterion1; riterion is times as important as criterion, calculate the weights for the three criteria using the HP method. xplain how the consistency ratio is calculated. -In an urgent project, you need to decide from which vendor to buy a particular component. Vendor will supply the components in lots of 1000 for $10 a unit, while Vendor will charge only $9.5 a unit. However, 0% of the time Vendor s lots will contain 10% defectives and 80% of the time they will contain 1% defectives, while Vendor s lots will contain 1% defectives 99% of the time and % defectives 1% of the time. If you encounter a defective component, it will cost you $100 to rework your assemblies. a) raw a decision tree for this decision; and b) using the criterion of expected cost, from which vendor should you purchase the component?

EXERCISE Draw the network diagram. a. Activity Name A B C D E F G H

EXERCISE Draw the network diagram. a. Activity Name A B C D E F G H XRIS. What do you mean by network analysis? xplain with counter examples.. What are the basic differences between PM and PRT analysis of project work?. State the rule of constructing the network diagram..

More information

Lecture 5: Project Management

Lecture 5: Project Management Lecture 5: Management organization structure ritical path method (PM) Time/cost tradeoff PM with three activity it time estimates t Readings: hapter 10 Management series of related jobs usually directed

More information

SCHEDULE CREATION AND ANALYSIS. 1 Powered by POeT Solvers Limited

SCHEDULE CREATION AND ANALYSIS. 1   Powered by POeT Solvers Limited SCHEDULE CREATION AND ANALYSIS 1 www.pmtutor.org Powered by POeT Solvers Limited While building the project schedule, we need to consider all risk factors, assumptions and constraints imposed on the project

More information

Textbook: pp Chapter 11: Project Management

Textbook: pp Chapter 11: Project Management 1 Textbook: pp. 405-444 Chapter 11: Project Management 2 Learning Objectives After completing this chapter, students will be able to: Understand how to plan, monitor, and control projects with the use

More information

Network Analysis Basic Components. The Other View. Some Applications. Continued. Goal of Network Analysis. RK Jana

Network Analysis Basic Components. The Other View. Some Applications. Continued. Goal of Network Analysis. RK Jana Network nalysis RK Jana asic omponents ollections of interconnected linear forms: Lines Intersections Regions (created by the partitioning of space by the lines) Planar (streets, all on same level, vertices

More information

Project Management. Chapter 2 DISCUSSION QUESTIONS

Project Management. Chapter 2 DISCUSSION QUESTIONS hapter Project Management ISUSSION QUSTIONS 1. Software is an essential element for successful management of complex projects. It can provide information on completion performance of critical activities,

More information

CHAPTER 5 STOCHASTIC SCHEDULING

CHAPTER 5 STOCHASTIC SCHEDULING CHPTER STOCHSTIC SCHEDULING In some situations, estimating activity duration becomes a difficult task due to ambiguity inherited in and the risks associated with some work. In such cases, the duration

More information

King Fahd University of Petroleum and Minerals College of Environmental Design CEM 520: Construction Contracting

King Fahd University of Petroleum and Minerals College of Environmental Design CEM 520: Construction Contracting King Fahd University of Petroleum and Minerals College of Environmental Design CEM 520: Construction Contracting Determination of Construction Contract Duration for Public Projects in Saudi Arabia By:

More information

Sheila Belayutham CHAPTER 6 CONTROL

Sheila Belayutham CHAPTER 6 CONTROL CHAPTER 6 CONTROL LEARNING OUTCOME Students will be able to: Understand monitoring and control in construction. Understand the monitoring and control methods in construction. MONITORING & CONTROL It s

More information

Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management

Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management Slide 1 Looking Glass Development, LLC (303) 663-5402 / (888) 338-7447 4610 S. Ulster St. #150 Denver, CO 80237 information@lookingglassdev.com

More information

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ International Project Management prof.dr MILOŠ D. MILOVANČEVIĆ Project time management Project cost management Time in project management process Time is a valuable resource. It is also the scarcest. Time

More information

Introduction. Introduction. Six Steps of PERT/CPM. Six Steps of PERT/CPM LEARNING OBJECTIVES

Introduction. Introduction. Six Steps of PERT/CPM. Six Steps of PERT/CPM LEARNING OBJECTIVES Valua%on and pricing (November 5, 2013) LEARNING OBJECTIVES Lecture 12 Project Management Olivier J. de Jong, LL.M., MM., MBA, CFD, CFFA, AA www.olivierdejong.com 1. Understand how to plan, monitor, and

More information

Poor Man s Approach to Monte Carlo

Poor Man s Approach to Monte Carlo Poor Man s Approach to Monte Carlo Based on the PMI PMBOK Guide Fourth Edition 20 IPDI has been reviewed and approved as a provider of project management training by the Project Management Institute (PMI).

More information

An Application of Mathematical Model to Time-cost Trade off Problem (Case Study)

An Application of Mathematical Model to Time-cost Trade off Problem (Case Study) Australian Journal of Basic and Applied Sciences, 5(7): 208-214, 2011 ISSN 1991-8178 An Application of Mathematical Model to Time-cost Trade off Problem (ase Study) 1 Amin Zeinalzadeh 1 Tabriz Branch,

More information

Project Management Techniques (PMT)

Project Management Techniques (PMT) Project Management Techniques (PMT) Critical Path Method (CPM) and Project Evaluation and Review Technique (PERT) are 2 main basic techniques used in project management. Example: Construction of a house.

More information

UNIVERSITY OF BOLTON SCHOOL OF ENGINEERING. MSc CIVIL ENGINEERING MSc CONSTRUCTION PROJECT MANAGEMENT SEMESTER ONE EXAMINATION 2017/2018

UNIVERSITY OF BOLTON SCHOOL OF ENGINEERING. MSc CIVIL ENGINEERING MSc CONSTRUCTION PROJECT MANAGEMENT SEMESTER ONE EXAMINATION 2017/2018 ENG026 UNIVERSITY OF BOLTON SCHOOL OF ENGINEERING MSc CIVIL ENGINEERING MSc CONSTRUCTION PROJECT MANAGEMENT SEMESTER ONE EXAMINATION 2017/2018 PROJECT MANAGEMENT MODULE NO: CPM7002 Date: 15 January 2018

More information

Contents Cloud or On-Premises Content Introduction Data Dictionary... 23

Contents Cloud or On-Premises Content Introduction Data Dictionary... 23 P6 Data Dictionary Version 17 July 2017 Contents Cloud or On-Premises Content... 19 Introduction... 21 Data Dictionary... 23 % Allocation... 23 Access Level... 23 Access Time... 23 Accounting Variance...

More information

Making sense of Schedule Risk Analysis

Making sense of Schedule Risk Analysis Making sense of Schedule Risk Analysis John Owen Barbecana Inc. Version 2 December 19, 2014 John Owen - jowen@barbecana.com 2 5 Years managing project controls software in the Oil and Gas industry 28 years

More information

PROJECT MANAGEMENT: PERT AMAT 167

PROJECT MANAGEMENT: PERT AMAT 167 PROJECT MANAGEMENT: PERT AMAT 167 PROBABILISTIC TIME ESTIMATES We need three time estimates for each activity: Optimistic time (t o ): length of time required under optimum conditions; Most likely time

More information

Lecture 3 Project Scheduling

Lecture 3 Project Scheduling B10 Lecture Project Scheduling Omar El-Anwar, PhD, PMP Network alculations The purpose of conducting network calculations is to know more about the scheduling of activities: When will each activity start?

More information

Project Planning. Identifying the Work to Be Done. Gantt Chart. A Gantt Chart. Given: Activity Sequencing Network Diagrams

Project Planning. Identifying the Work to Be Done. Gantt Chart. A Gantt Chart. Given: Activity Sequencing Network Diagrams Project Planning Identifying the Work to Be Done Activity Sequencing Network Diagrams Given: Statement of work written description of goals work & time frame of project Work Breakdown Structure Be able

More information

A STUDY OF THE BASIC CONCEPT OF CRASHING CPM NETWORK USING DERIVATIVE MARGINAL COST IN LINEAR PROGRAMMING

A STUDY OF THE BASIC CONCEPT OF CRASHING CPM NETWORK USING DERIVATIVE MARGINAL COST IN LINEAR PROGRAMMING ISSN : 98-X STUDY OF THE BSI ONEPT OF RSHING PM NETWORK USING DERIVTIVE MRGINL OST IN LINER PROGRMMING Ismail H. srul tma Jaya atholic University, Jakarta, Indonesia ismael.aaron@gmail.com BSTRT For crashing

More information

IE 102 Spring Project Management

IE 102 Spring Project Management IE 102 Spring 2018 Project Management 1 Management of Projects Planning - goal setting, defining the project, team organization Scheduling - relates people, money, and supplies to specific activities and

More information

CHAPTER 9: PROJECT MANAGEMENT

CHAPTER 9: PROJECT MANAGEMENT CHAPTER 9: PROJECT MANAGEMENT The aim is to coordinate and plan a single job consisting lots of tasks between which precedence relationships exist Project planning Most popular planning tools are utilized

More information

Project Management Chapter 13

Project Management Chapter 13 Lecture 12 Project Management Chapter 13 Introduction n Managing large-scale, complicated projects effectively is a difficult problem and the stakes are high. n The first step in planning and scheduling

More information

RISK ANALYSIS GUIDE FOR PRIVATE INITIATIVE PROJECTS

RISK ANALYSIS GUIDE FOR PRIVATE INITIATIVE PROJECTS N A T I O N A L C O N C E S S I O N C O U N C I L RISK ANALYSIS GUIDE FOR PRIVATE INITIATIVE PROJECTS PREPARED BY: ENGINEER ÁLVARO BORBON M. PRIVATE INITIATIVE PROGRAM DECEMBER 2008 INDEX Guide Purpose...

More information

INSE 6230 Total Quality Project Management Winter 2018 Quiz I. Max : 70 points. This is a closed book exam. Answer all the questions in the booklet.

INSE 6230 Total Quality Project Management Winter 2018 Quiz I. Max : 70 points. This is a closed book exam. Answer all the questions in the booklet. . Surname, given names: Student Number: INSE 6230 Total Quality Project Management Winter 2018 Quiz I. Max : 70 points This is a closed book exam. Answer all the questions in the booklet. Ensure that your

More information

Optimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur. Lecture - 18 PERT

Optimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur. Lecture - 18 PERT Optimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur Lecture - 18 PERT (Refer Slide Time: 00:56) In the last class we completed the C P M critical path analysis

More information

Project Management. Chapter 2. Copyright 2013 Pearson Education, Inc. publishing as Prentice Hall

Project Management. Chapter 2. Copyright 2013 Pearson Education, Inc. publishing as Prentice Hall Project Management Chapter 2 02-0 1 What is a Project? Project An interrelated set of activities with a definite starting and ending point, which results in a unique outcome for a specific allocation of

More information

THE ACCELERATING OF DURATION AND CHANGE OF COST ON CONSTRUCTION PROJECT IMPLEMENTATION

THE ACCELERATING OF DURATION AND CHANGE OF COST ON CONSTRUCTION PROJECT IMPLEMENTATION International Journal of Civil Engineering and Technology (IJCIET) Volume 10, Issue 01, January 2019, pp. 825-832, Article ID: IJCIET_10_01_075 Available online at http://www.iaeme.com/ijciet/issues.asp?jtype=ijciet&vtype=10&itype=01

More information

Real-World Project Management. Chapter 15

Real-World Project Management. Chapter 15 Real-World Project Chapter 15 Characteristics of Project Unique one-time focus Difficulties arise from originality Subject to uncertainties Unexplained or unplanned events often arise, affecting resources,

More information

Full Monte. Looking at your project through rose-colored glasses? Let s get real.

Full Monte. Looking at your project through rose-colored glasses? Let s get real. Realistic plans for project success. Looking at your project through rose-colored glasses? Let s get real. Full Monte Cost and schedule risk analysis add-in for Microsoft Project that graphically displays

More information

Project planning and creating a WBS

Project planning and creating a WBS 37E01500 Project Management and Consulting Practice Project planning and creating a WBS Matti Rossi Lecture 3, Tue 28.2.2017 Learning objectives Describe the project time management planning tasks, and

More information

GLS UNIVERSITY S FACULTY OF COMMERCE B. COM. SECOND YEAR SEMESTER IV STATISTICS FOR BUSINESS AND MANAGEMENT OBJECTIVE QUESTIONS

GLS UNIVERSITY S FACULTY OF COMMERCE B. COM. SECOND YEAR SEMESTER IV STATISTICS FOR BUSINESS AND MANAGEMENT OBJECTIVE QUESTIONS Q.1 Choose the correct options: GLS UNIVERSITY S FACULTY OF COMMERCE B. COM. SECOND YEAR SEMESTER IV STATISTICS FOR BUSINESS AND MANAGEMENT OBJECTIVE QUESTIONS 2017-18 Unit: 1 Differentiation and Applications

More information

INSE 6230: Assignment 1 - Winter (0% of final grade) 1. The table below provides information about a short IT project.

INSE 6230: Assignment 1 - Winter (0% of final grade) 1. The table below provides information about a short IT project. INSE 6230: Assignment - Winter 208 (0% of final grade). The table below provides information about a short IT project. Activity Predecessors Duration (Months) A - 2 B - 3 C A 4 D A, B 2 E D 2 F B, C, E

More information

WHY ARE PROJECTS ALWAYS LATE?

WHY ARE PROJECTS ALWAYS LATE? WHY ARE PROJECTS ALWAYS LATE? (what can the Project Manager DO about that?) Craig Henderson, MBA, PMP ARVEST Bank Operations Introduction PM Basics FIO GID KISS (Figure it out) (Get it done) (Keep it simple,

More information

Administrative Policy for Procurement, Bidding, Bid Specifications, Consulting, Request For Qualifications (RFQ), and Evaluation Criteria

Administrative Policy for Procurement, Bidding, Bid Specifications, Consulting, Request For Qualifications (RFQ), and Evaluation Criteria CITY OF LARAMIE Policy Title: Administrative Policy for Procurement, Bidding, Bid Specifications, Consulting, Request For Qualifications (RFQ), and Evaluation Criteria Policy Number: 2014-01 Page 1 of

More information

These regulations are issued pursuant to the following Sections of the Municipal Code of Chicago:

These regulations are issued pursuant to the following Sections of the Municipal Code of Chicago: 1. GENERAL PROVISIONS 1.1. Statement of Authority These regulations are issued pursuant to the following Sections of the Municipal Code of Chicago: Section 2-92-410 of the Municipal Code of Chicago establishes

More information

Management Accounting Fundamentals (FMAF)

Management Accounting Fundamentals (FMAF) POST EXM GUIE May 2001 Exam Management ccounting Fundamentals (FMF) IM publishes a Question and nswer booklet for each paper of the May 2001 exam which is essential reading for students and tutors. The

More information

BAE Systems SCAF Presentation June BAE SYSTEMS 2013, all rights reserved Unclassified 31/07/2013 1

BAE Systems SCAF Presentation June BAE SYSTEMS 2013, all rights reserved Unclassified 31/07/2013 1 BAE Systems SCAF Presentation June 2013 BAE SYSTEMS 2013, all rights reserved Unclassified 31/07/2013 1 Agenda An Alternative Approach to Cost and Schedule Integration BAE Systems Commercial Estimating

More information

Outline. Global Company Profile: Bechtel Group. The Importance of Project Management Project Planning Project Scheduling Project Controlling

Outline. Global Company Profile: Bechtel Group. The Importance of Project Management Project Planning Project Scheduling Project Controlling Project Management Outline Global Company Profile: Bechtel Group The Importance of Project Management Project Planning Project Scheduling Project Controlling Outline - Continued Project Management Techniques:

More information

Paper T4. Accounting for Costs. Thursday 9 June Certified Accounting Technician Examination Intermediate Level

Paper T4. Accounting for Costs. Thursday 9 June Certified Accounting Technician Examination Intermediate Level ertified ccounting Technician Examination Intermediate Level ccounting for osts Thursday 9 June 2011 Time allowed: 2 hours This paper is divided into two sections: Section LL 20 questions are compulsory

More information

Mohammed Rafiuddin CEO and General Manager, BIOSI Biohazards Solutions Innovators

Mohammed Rafiuddin CEO and General Manager, BIOSI Biohazards Solutions Innovators Mohammed Rafiuddin CEO and General Manager, BIOSI Biohazards Solutions Innovators Profile of Mohammed Rafiuddin Mohammed is an active member of AACE International since 2006 with 30 years of experience

More information

Project Risk Management

Project Risk Management Project Risk Management Introduction Unit 1 Unit 2 Unit 3 PMP Exam Preparation Project Integration Management Project Scope Management Project Time Management Unit 4 Unit 5 Unit 6 Unit 7 Project Cost Management

More information

UNIT-II Project Organization and Scheduling Project Element

UNIT-II Project Organization and Scheduling Project Element UNIT-II Project Organization and Scheduling Project Element Five Key Elements are Unique. Projects are unique, one-of-a-kind, never been done before. Start and Stop Date. Projects must have a definite

More information

Risk Video #1. Video 1 Recap

Risk Video #1. Video 1 Recap Risk Video #1 Video 1 Recap 1 Risk Video #2 Video 2 Recap 2 Risk Video #3 Risk Risk Management Process Uncertain or chance events that planning can not overcome or control. Risk Management A proactive

More information

M G T 2251 Management Science. Exam 3

M G T 2251 Management Science. Exam 3 M G T 2251 Management Science Exam 3 Professor Chang November 8, 2012 Your Name (Print): ID#: Read each question carefully before you answer. Work at a steady pace, and you should have ample time to finish.

More information

Introduction by Philip Croessmann, V.P., Director of Risk Management Sources of Construction Claims Common Types of Construction Claims Risk

Introduction by Philip Croessmann, V.P., Director of Risk Management Sources of Construction Claims Common Types of Construction Claims Risk Introduction by Philip Croessmann, V.P., Director of Risk Management Sources of Construction Claims Common Types of Construction Claims Risk Management Preconstruction & Construction Managing Construction

More information

19 Decision Making. Expected Monetary Value Expected Opportunity Loss Return-to-Risk Ratio Decision Making with Sample Information

19 Decision Making. Expected Monetary Value Expected Opportunity Loss Return-to-Risk Ratio Decision Making with Sample Information 19 Decision Making USING STATISTICS @ The Reliable Fund 19.1 Payoff Tables and Decision Trees 19.2 Criteria for Decision Making Maximax Payoff Maximin Payoff Expected Monetary Value Expected Opportunity

More information

ADVANCED QUANTITATIVE SCHEDULE RISK ANALYSIS

ADVANCED QUANTITATIVE SCHEDULE RISK ANALYSIS ADVANCED QUANTITATIVE SCHEDULE RISK ANALYSIS DAVID T. HULETT, PH.D. 1 HULETT & ASSOCIATES, LLC 1. INTRODUCTION Quantitative schedule risk analysis is becoming acknowledged by many project-oriented organizations

More information

Paper F2. Management Accounting. Pilot Paper from December 2011 onwards. Fundamentals Pilot Paper Knowledge Module

Paper F2. Management Accounting. Pilot Paper from December 2011 onwards. Fundamentals Pilot Paper Knowledge Module Fundamentals Pilot Paper Knowledge Module Management ccounting Pilot Paper from ecember 2011 onwards Time allowed: 2 hours LL 50 questions are compulsory and MUST be attempted. Formulae Sheet, Present

More information

VIRGINIA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR SECTION 109 MEASUREMENT AND PAYMENT

VIRGINIA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR SECTION 109 MEASUREMENT AND PAYMENT SECTION 102.01 PREQUALIFICATION OF BIDDERS of the Specifications is amended as follows: The eighth paragraph is replaced by the following: When the Contractor's actual progress is more than 10 percent

More information

Paper 1.2. Financial Information for Management PART 1 FRIDAY 10 DECEMBER 2004 QUESTION PAPER. Time allowed 3 hours

Paper 1.2. Financial Information for Management PART 1 FRIDAY 10 DECEMBER 2004 QUESTION PAPER. Time allowed 3 hours Financial Information for Management PRT 1 FRIY 10 EEMER 2004 QUESTION PPER Time allowed 3 hours This paper is divided into two sections Section LL 25 questions are compulsory and MUST be answered Paper

More information

INSE 6230 Total Quality Project Management

INSE 6230 Total Quality Project Management INSE 6230 Total Quality Project Management Lecture 6 Project Risk Management Project risk management is the art and science of identifying, analyzing, and responding to risk throughout the life of a project

More information

6/7/2018. Overview PERT / CPM PERT/CPM. Project Scheduling PERT/CPM PERT/CPM

6/7/2018. Overview PERT / CPM PERT/CPM. Project Scheduling PERT/CPM PERT/CPM /7/018 PERT / CPM BSAD 0 Dave Novak Summer 018 Overview Introduce PERT/CPM Discuss what a critical path is Discuss critical path algorithm Example Source: Anderson et al., 01 Quantitative Methods for Business

More information

Project Planning. Jesper Larsen. Department of Management Engineering Technical University of Denmark

Project Planning. Jesper Larsen. Department of Management Engineering Technical University of Denmark Project Planning jesla@man.dtu.dk Department of Management Engineering Technical University of Denmark 1 Project Management Project Management is a set of techniques that helps management manage large-scale

More information

BSc (Hons) Software Engineering BSc (Hons) Computer Science with Network Security

BSc (Hons) Software Engineering BSc (Hons) Computer Science with Network Security BSc (Hons) Software Engineering BSc (Hons) Computer Science with Network Security Cohorts BCNS/ 06 / Full Time & BSE/ 06 / Full Time Resit Examinations for 2008-2009 / Semester 1 Examinations for 2008-2009

More information

Financial Management & Accounting in Construction (CUE304) FINANCIAL MANAGEMENT. Dr. Ahmed Elyamany

Financial Management & Accounting in Construction (CUE304) FINANCIAL MANAGEMENT. Dr. Ahmed Elyamany 1 Financial Management & Accounting in Construction (CUE304) FINANCIAL MANAGEMENT Dr. Ahmed Elyamany 2 Course Content Project financial management: Cash flow prediction, Cash flow analysis, Cost of finance

More information

Gurukripa s Guideline Answers to Nov 2011 Final Exam Questions Advanced Management Accounting

Gurukripa s Guideline Answers to Nov 2011 Final Exam Questions Advanced Management Accounting Gurukripa s Guideline Answers to Nov 2011 Final Exam Questions Advanced Management Accounting Question No.1 is compulsory (4 X 5 = 20 Marks). Answer any five questions from the remaining six questions

More information

Construction Management

Construction Management Construction Management 1. Which one of the following represents an activity A. excavation for foundation B. curing of concrete C. setting of question paper D. preparation of breakfast 2. Pick up the incorrect

More information

POST GRADUATE DIPLOMA IN APPLIED STATISTICS (PGDAST) 0 Term-End Examination. December, 2015 MSTE : INDUSTRIAL STATISTICS - I

POST GRADUATE DIPLOMA IN APPLIED STATISTICS (PGDAST) 0 Term-End Examination. December, 2015 MSTE : INDUSTRIAL STATISTICS - I No. of Printed Pages : 7 MSTE-001 POST GRADUATE DIPLOMA IN APPLIED STATISTICS (PGDAST) 0 Term-End Examination.7r December, 2015 MSTE - 001 : INDUSTRIAL STATISTICS - I Time : 3 hours Maximum Marks : 50

More information

RISK MANAGEMENT LECTURE 5. Ahmed Elyamany

RISK MANAGEMENT LECTURE 5. Ahmed Elyamany RISK MANAGEMENT LECTURE 5 Ahmed Elyamany 1 RISK SECTION OBJECTIVES Introduce the students to the concepts of risk management and the different tools to analyze risk and estimate time and cost contingencies.

More information

Real Options and Risk Analysis in Capital Budgeting

Real Options and Risk Analysis in Capital Budgeting Real options Real Options and Risk Analysis in Capital Budgeting Traditional NPV analysis should not be viewed as static. This can lead to decision-making problems in a dynamic environment when not all

More information

VIRGINIA DEPARTMENT OF TRANSPORATION SPECIAL PROVISION FOR CPM PROGRESS SCHEDULE FOR CATEGORY III PROJECTS

VIRGINIA DEPARTMENT OF TRANSPORATION SPECIAL PROVISION FOR CPM PROGRESS SCHEDULE FOR CATEGORY III PROJECTS S108C00-0911 VIRGINIA DEPARTMENT OF TRANSPORATION SPECIAL PROVISION FOR CPM PROGRESS SCHEDULE FOR CATEGORY III PROJECTS March 1, 2011 Section 103.06(e) Progress Schedule of the Specifications is deleted

More information

SSC-JE STAFF SELECTION COMMISSION CIVIL ENGINEERING STUDY MATERIAL ESTIMATING, COSTING AND VALUATION

SSC-JE STAFF SELECTION COMMISSION CIVIL ENGINEERING STUDY MATERIAL ESTIMATING, COSTING AND VALUATION 1 ` SSC-JE STAFF SELECTION COMMISSION CIVIL ENGINEERING STUDY MATERIAL SSC-JE Civil Engineering 2 Estimating, Costing and Valuation : Estimate, Glossary of technical terms, Analysis of rates, Methods and

More information

Performance risk evaluation of long term infrastructure projects (PPP-BOT projects) using probabilistic methods

Performance risk evaluation of long term infrastructure projects (PPP-BOT projects) using probabilistic methods EPPM, Singapore, 20-21 Sep 2011 Performance risk evaluation of long term infrastructure projects (PPP-BOT projects) using probabilistic Meghdad Attarzadeh 1 and David K H Chua 2 Abstract Estimation and

More information

Agenda. Lecture 2. Decision Analysis. Key Characteristics. Terminology. Structuring Decision Problems

Agenda. Lecture 2. Decision Analysis. Key Characteristics. Terminology. Structuring Decision Problems Agenda Lecture 2 Theory >Introduction to Making > Making Without Probabilities > Making With Probabilities >Expected Value of Perfect Information >Next Class 1 2 Analysis >Techniques used to make decisions

More information

Project Time-Cost Trade-Off

Project Time-Cost Trade-Off Project Time-Cost Trade-Off 7.1 Introduction In the previous chapters, duration of activities discussed as either fixed or random numbers with known characteristics. However, activity durations can often

More information

MINI GUIDE. Project risk analysis and management

MINI GUIDE. Project risk analysis and management MINI GUIDE Project risk analysis and management Association for Project Management January 2018 Contents Page 3 Introduction What is PRAM? Page 4 Page 7 Page 9 What is involved? Why is it used? When should

More information

6 th September not protectively marked 1

6 th September not protectively marked 1 Establishing Risk Management processes in UK Nuclear New Build - (inc Enterprise Risk Management & Probabilistic Cost & Schedule Risk Analysis processes) 6 th September 2016 not protectively marked 1 Introductions

More information

Allocate and Level Project Resources

Allocate and Level Project Resources Allocate and Level Project Resources Resource Allocation: Defined Resource Allocation is the scheduling of activities and the resources required by those activities while taking into consideration both

More information

CISC 322 Software Architecture

CISC 322 Software Architecture CISC 22 Software Architecture Project Scheduling (PERT/CPM) Ahmed E. Hassan (Edited For Course Presentation, 206) Project A project is a temporary endeavour undertaken to create a "unique" product or service

More information

Computational Finance Least Squares Monte Carlo

Computational Finance Least Squares Monte Carlo Computational Finance Least Squares Monte Carlo School of Mathematics 2019 Monte Carlo and Binomial Methods In the last two lectures we discussed the binomial tree method and convergence problems. One

More information

PROJECT MANAGEMENT COURSE 5: PROJECT TIME MANAGEMENT. G.N. Sandhy Widyasthana

PROJECT MANAGEMENT COURSE 5: PROJECT TIME MANAGEMENT. G.N. Sandhy Widyasthana PROJECT MANAGEMENT COURSE 5: PROJECT TIME MANAGEMENT G.N. Sandhy Widyasthana widyasthana@gmail.com 022 70702020 081 225 702020 1 2 3 Process of identifying the specific actions to be performed to produce

More information

A convenient analytical and visual technique of PERT and CPM prove extremely valuable in assisting the managers in managing the projects.

A convenient analytical and visual technique of PERT and CPM prove extremely valuable in assisting the managers in managing the projects. Introduction Any project involves planning, scheduling and controlling a number of interrelated activities with use of limited resources, namely, men, machines, materials, money and time. The projects

More information

for Major Infrastructure Projects

for Major Infrastructure Projects for Major Infrastructure Projects Presented by: Pedram Daneshmand Senior Associate Director 4 th Annual Contract Selection and Risk for Major Projects, March 2011 Agenda Brief Introduction Project Delivery

More information

CHAPTER 5. Project Scheduling Models

CHAPTER 5. Project Scheduling Models CHAPTER 5 Project Scheduling Models 1 5.1 Introduction A project is a collection of tasks that must be completed in minimum time or at minimal cost. Objectives of Project Scheduling Completing the project

More information

Project Management Fundamentals

Project Management Fundamentals Project Management Fundamentals Course No: B04-003 Credit: 4 PDH Najib Gerges, Ph.D., P.E. Continuing Education and Development, Inc. 9 Greyridge Farm Court Stony Point, NY 10980 P: (877) 322-5800 F: (877)

More information

Expression of Interest ( EOI ) Ref: EOI/2018/OMU/002

Expression of Interest ( EOI ) Ref: EOI/2018/OMU/002 Hong Kong Science and Technology Parks Corporation Adoptive Survey and Consultancy for an Industrial Building at Wang Lee Street Yuen Long Industrial Estate, New Territories (Agreement No. IEBU/CA/015)

More information

CHAPTER 6 PROJECT CASH FLOW

CHAPTER 6 PROJECT CASH FLOW CHAPTER 6 PROJECT CASH FLOW In the previous chapters, techniques for project planning, scheduling, resources management, and timecost trade off have been introduced. This chapter deals with project cash

More information

Project Management. Managing Risk. Clifford F. Gray Eric W. Larson Third Edition. Chapter 7

Project Management. Managing Risk. Clifford F. Gray Eric W. Larson Third Edition. Chapter 7 Project Management THE MANAGERIAL PROCESS Clifford F. Gray Eric W. Larson Third Edition Chapter 7 Managing Risk Copyright 2006 The McGraw-Hill Companies. All rights reserved. PowerPoint Presentation by

More information

Monash University School of Information Management and Systems IMS3001 Business Intelligence Systems Semester 1, 2004.

Monash University School of Information Management and Systems IMS3001 Business Intelligence Systems Semester 1, 2004. Exercise 7 1 : Decision Trees Monash University School of Information Management and Systems IMS3001 Business Intelligence Systems Semester 1, 2004 Tutorial Week 9 Purpose: This exercise is aimed at assisting

More information

Assistance with University Projects? Research Reports? Writing Skills? We have got you covered! www.assignmentstudio.net WhatsApp: +61-424-295050 Toll Free: 1-800-794-425 Email: contact@assignmentstudio.net

More information

The histogram should resemble the uniform density, the mean should be close to 0.5, and the standard deviation should be close to 1/ 12 =

The histogram should resemble the uniform density, the mean should be close to 0.5, and the standard deviation should be close to 1/ 12 = Chapter 19 Monte Carlo Valuation Question 19.1 The histogram should resemble the uniform density, the mean should be close to.5, and the standard deviation should be close to 1/ 1 =.887. Question 19. The

More information

UNIT 5 DECISION MAKING

UNIT 5 DECISION MAKING UNIT 5 DECISION MAKING This unit: UNDER UNCERTAINTY Discusses the techniques to deal with uncertainties 1 INTRODUCTION Few decisions in construction industry are made with certainty. Need to look at: The

More information

SECTION PROJECT SCHEDULES (SMALL PROJECTS DESIGN/BID/BUILD)

SECTION PROJECT SCHEDULES (SMALL PROJECTS DESIGN/BID/BUILD) SECTION 01 32 16.15 PROJECT SCHEDULES (SMALL PROJECTS DESIGN/BID/BUILD) PART 1- GENERAL 1.1 DESCRIPTION: A. The Contractor shall develop a Critical Path Method (CPM) plan and schedule demonstrating fulfillment

More information

AIA Document A201 TM 1997

AIA Document A201 TM 1997 AIA Document A201 TM 1997 General Conditions of the Contract for Construction for the following PROJECT: (Name and location or address): Project University of Maine at Farmington THE OWNER: (Name and address):

More information

CITY OF JOPLIN, MISSOURI

CITY OF JOPLIN, MISSOURI CITY OF JOPLIN, MISSOURI BID PACKAGE 2016-RFP-21 FOR ZER0 TURN MOWER S (2) ATHLETIC COMPLEX JOPLIN Athletic Complex DEPARTMENT 3301 W. FIRST STREET JOPLIN, MO 64801 NOTICE TO BIDDERS The City of Joplin,

More information

Optimal Search for Parameters in Monte Carlo Simulation for Derivative Pricing

Optimal Search for Parameters in Monte Carlo Simulation for Derivative Pricing Optimal Search for Parameters in Monte Carlo Simulation for Derivative Pricing Prof. Chuan-Ju Wang Department of Computer Science University of Taipei Joint work with Prof. Ming-Yang Kao March 28, 2014

More information

How to arrange for financing? Cash Flow = Cash In Cash Out. = Income Expense. = Revenue - Cost

How to arrange for financing? Cash Flow = Cash In Cash Out. = Income Expense. = Revenue - Cost Analysis Contract How much is the total cost? How to arrange for financing? = Cash In Cash Out = Income Expense = Revenue - Cost 29/09/2016 Emad Elbeltagi 2 1 Project Expenses The project cost types: Fixed

More information

REQUEST FOR PROPOSAL Lake Ripley Management District (LRMD)

REQUEST FOR PROPOSAL Lake Ripley Management District (LRMD) REQUEST FOR PROPOSAL Lake Ripley Management District (LRMD) RFP ID Invasive Species Eradication 2016 ISSUE DATE April 26, 2016 SUBMIT BID TO PURPOSE SPECIAL INSTRUCTIONS Lisa Griffin Lake Ripley Management

More information

Management Services Reviewer by Ma. Elenita Balatbat-Cabrera

Management Services Reviewer by Ma. Elenita Balatbat-Cabrera Course Name: Course Title: Instructors: Required Text: Course Description: XMASREV Management Services Review David, Dimalanta and Morales Management Services Reviewer by Ma. Elenita Balatbat-Cabrera This

More information

MATH4143: Scientific Computations for Finance Applications Final exam Time: 9:00 am - 12:00 noon, April 18, Student Name (print):

MATH4143: Scientific Computations for Finance Applications Final exam Time: 9:00 am - 12:00 noon, April 18, Student Name (print): MATH4143 Page 1 of 17 Winter 2007 MATH4143: Scientific Computations for Finance Applications Final exam Time: 9:00 am - 12:00 noon, April 18, 2007 Student Name (print): Student Signature: Student ID: Question

More information

Optimization of Rescheduling and Economy. Analysis of the Implementation of Kwitang Office. Park Building Construction Project in Jakarta

Optimization of Rescheduling and Economy. Analysis of the Implementation of Kwitang Office. Park Building Construction Project in Jakarta Contemporary Engineering Sciences, Vol. 10, 2017, no. 7, 317-333 HIKARI Ltd, www.m-hikari.com https://doi.org/10.12988/ces.2017.712 Optimization of Rescheduling and Economy Analysis of the Implementation

More information

CITY OF HUTCHINSON BID FORM Page 1 of 2

CITY OF HUTCHINSON BID FORM Page 1 of 2 CITY OF HUTCHINSON BID FORM Page 1 of 2 Please quote your delivered prices to the City of Hutchinson on items or services listed below. Consult attached minimum and general specifications for requirements.

More information

SOUTH COLONIE CENTRAL SCHOOL DISTRICT BOARD OF EDUCATION

SOUTH COLONIE CENTRAL SCHOOL DISTRICT BOARD OF EDUCATION Notice to Bidders: The Board of Education of South Colonie Central School District, Albany, New York hereby invites the submission of sealed bids for: ASPHALT MILLING AND PAVING Pursuant to Chapter 472

More information

Advanced Financial Modeling. Unit 2

Advanced Financial Modeling. Unit 2 Advanced Financial Modeling Unit 2 Financial Modeling for Risk Management A Portfolio with 2 assets A portfolio with 3 assets Risk Modeling in a multi asset portfolio Monte Carlo Simulation Two Asset Portfolio

More information

VIRGINIA DEPARTMENT OF TRANSPORATION SPECIAL PROVISION FOR CPM PROGRESS SCHEDULE FOR CATEGORY IV PROJECTS

VIRGINIA DEPARTMENT OF TRANSPORATION SPECIAL PROVISION FOR CPM PROGRESS SCHEDULE FOR CATEGORY IV PROJECTS S108D00-0911 VIRGINIA DEPARTMENT OF TRANSPORATION SPECIAL PROVISION FOR CPM PROGRESS SCHEDULE FOR CATEGORY IV PROJECTS March 1, 2011 Section 103.06(e) Progress Schedule of the Specifications is deleted

More information

Economics Honors Exam 2009 Solutions: Microeconomics, Questions 1-2

Economics Honors Exam 2009 Solutions: Microeconomics, Questions 1-2 Economics Honors Exam 2009 Solutions: Microeconomics, Questions 1-2 Question 1 (Microeconomics, 30 points). A ticket to a newly staged opera is on sale through sealed-bid auction. There are three bidders,

More information

Awarding the new licence to run the National Lottery

Awarding the new licence to run the National Lottery Awarding the new licence to run the National Lottery REPORT BY THE COMPTROLLER AND AUDITOR GENERAL HC 803 Session 2001-2002: 10 May 2002 LONDON: The Stationery Office 10.75 Ordered by the House of Commons

More information