BAE Systems SCAF Presentation June BAE SYSTEMS 2013, all rights reserved Unclassified 31/07/2013 1

Size: px
Start display at page:

Download "BAE Systems SCAF Presentation June BAE SYSTEMS 2013, all rights reserved Unclassified 31/07/2013 1"

Transcription

1 BAE Systems SCAF Presentation June 2013 BAE SYSTEMS 2013, all rights reserved Unclassified 31/07/2013 1

2 Agenda An Alternative Approach to Cost and Schedule Integration BAE Systems Commercial Estimating Approach to Risk Opportunity and Uncertainty Evaluation An Overview of the Slipping and Sliding Technique A Real-Life Example 2

3 Cost & Schedule Integration Things that Dreams are made of At the risk of being controversial, perhaps we should start by setting the cat amongst the pigeons. Note: No real pigeons have been harmed in the making of this presentation 3

4 Cost Analysis Cost & Schedule Integration Stuff that Dreams are made of Schedule Analysis Let s be honest if it was easy we d all be doing it, but we re not conclusion: it isn t easy Integrated Cost & Schedule Analysis Schedule elements may require correlation Cost elements may require correlation Both may require cross-correlation Do we even understand it? We will all have heard the old saying Time is Money, and there is some truth in that So we should be looking at Integrated Cost and Schedule Analysis why aren t we? It needs investment: Can we afford to? Can we afford not to? 4

5 Is there a simpler alternative? In line with good estimating practice, we advocate using more than one approach, method and/or technique to evaluate the potential range of cost outcomes Top-down approach to pick up the unknowns and avoid duplication Takes a view of the schedule risk and pro-rata the rate of spend affected (Time costs money, resources are unlikely to be re-deployed) Commercial/Financial uplift factors (escalation etc) Bottom-up approach based on authorised Risk Registers Use of Monte Carlo Simulation - statistical technique to allow multiple variables and probabilities to be modelled Balanced view of Top-down and Bottom-up approaches By its very nature the Top-down approach ( worst-case view) should be greater than Bottom-up approach If not, or if there is a significant difference either way, it could indicate that either one or other approach is too immature, or overly optimistic or pessimistic 5

6 Cost Top-down Approach What is it? Schedule Risk Resources/Cost can be scaled in direct proportional to the increase in programme duration This implies a standing army effect if risks materialise Approach can be justified through a number of general principles: Baseline Task Top-Down Variability Resources utilised by a proposal are scoped on the baseline programme. Task Schedule Resources are generally internally re-deployed within a contract Task Task Risks generally manifest themselves as programme slippage Uplift Factors Task Task Task Task These cover issues not sufficiently covered by the schedule risk assessment Task Task Examples include Escalation 6

7 Using Monte Carlo to make a Price Recommendation 100% 80% 60% Our bottom-up approach to estimating looks at modelling risk, opportunity and uncertainty around the Most Likely values 40% 20% 0% We always look to price based on values which have a higher level of Confidence Min: Max: Probability: 100% Sensible Level of Confidence for Bid Audience Quiz: Why do we do that? Min: Max: Probability: 100% We don t trust our own estimates? We are so totally risk-averse? We know that our customers will knock us down? The schedule may slip? The sum of the Most Likely Values are not the most likely values? Monte Carlo Output is misleading? 7

8 Generating an Estimate Recommendation Bottom-up Uncertainty Assessment Undefined or Unclear Task Definition Emergent Baseline Task Performance There are known knowns. To These know are that things we we know know what we that know, we know. Undefined and that Risks we do not know what we do not know, that There is are true known knowledge. unknowns. or the That is to say, there are Confucius things Unknown that we Unknowns now know we don t know. Top-down Reality Check Clearly Defined Baseline Estimate Defined Baseline Tasks Will Occur But there are also unknown unknowns. These are things we do not know Risk & we don t know. Opportunity Register Donald Rumsfeld United States Secretary of Defense Likelihood of Task Occurrence May or May Not Occur Bottom-up Risk & Opportunity Assessment 8

9 Making A Recommendation - Interim For internal clearance, generally prior to price formulation and submission, we provide a high level summary of the cost build up: Confidence Level Million Confidence Optimistic Range % Pessimistic Range % Recommendation % Bottom-up Functional Request Risk Modelling 50% Confidence level Cost Build Up Million % of Total ERF Returns % Technical Risk Contingency % Management Contingency % Balancing Number for Total Total % maybe we could do better Whatever happened to that Top-down Assessment we made? 9

10 Likelihood of Occurrence Taking a Balanced View Top-Down Evaluation Baseline Task Top-Down Variability Schedule? Cost Bottom-Up Confidence Level S Optimistic Opportunities and Uncertainties S Pessimistic Risks and Uncertainties 0 Potential Outcomes Cost Baseline Task Bottom-Up Evaluation Baseline Uncertainty Risk & Opportunity Register Based 10

11 Slipping & Sliding - A Pragmatic Judgement Aide Confidence Level of the Final Agreement a Reality Check Confidence levels and intervals are calculated as outputs from the Monte Carlo modelling exercise. However, it should be remembered that the Confidence Level generated through Monte Carlo Analysis is overstated Reality is that the true value at any Confidence Level above the Mode will be greater than calculated, because The value returned by Monte Carlo is only based on the analysis of the inputs It excludes any consideration of things that have not been considered Unknown Unknowns Pessimism Bias It assumes the baseline programme The Top-down Method is inherently pessimistic in nature It assumes that if the one task slips, everything slips - there is no recovery However, it does create headroom for those unknown unknowns Reality is likely to be somewhere between the two views Optimism Bias 11

12 Slipping & Sliding - A Pragmatic Aid to Judgement What is it? Slipping & Sliding is a simple technique we developed on the fly in support of an Estimating Practitioner Training Course on Risk Opportunity & Uncertainty Trainees wanted more guidance on making that Judgement Call And thus, a training exercise was born that we called Slipping & Sliding for reasons that will become abundantly clear The rational is: We assume that we have made an honest and reasonable assessment of the Top-down approach to cost variability based on a conservative view of the schedule risk (higher Confidence Level) We know that the approach is inherently pessimistic We assume that we have made an honest and reasonable assessment of the Bottom-up approach to Risk, Opportunity and Uncertainty using Monte Carlo We know that it does not include any explicit provision for the Rumsfeld Factor, Unknown Unknowns The approach is inherently optimistic Reality lies somewhere between the optimistic and pessimistic view of life 12

13 Slipping & Sliding - A Pragmatic Aid to Judgement Bottom-up Risk & Opportunity First Pass: 70% Confidence on Uncertainty 50% Confidence on Risk & Opportunity Functional Requests Baseline Programme Top-down Assessment (80%SRA) So, in this particular case: 70% Confidence Level + 50% Confidence Level Risk Opportunity & 60% Confidence level which all fits nicely inside the Top-down assessment, which is inherently pessimistic Bottom-up Uncertainty Bottom-up Risk, Opportunity & Uncertainty (for statistical validity)

14 Slipping & Sliding - A Pragmatic Aid to Judgement Bottom-up Risk & Opportunity Top-down Assessment (80%SRA) Functional Requests Baseline Programme Bottom-up Uncertainty So, in this particular case: Our Bottom-up Risk Opportunity & 60% Confidence level May only be equivalent to around the 40% Confidence Level of our Top-down Approach Bottom-up Risk, Opportunity & Uncertainty (for statistical validity)

15 Slipping & Sliding - A Pragmatic Aid to Judgement Bottom-up Risk & Opportunity Top-down Assessment (80%SRA) Functional Requests Baseline Programme Bottom-up Uncertainty whereas our Top-down 50% Confidence level may be equivalent to around the 72% Confidence Level on our Bottom-up Approach Bottom-up Risk, Opportunity & Uncertainty (for statistical validity)

16 Slipping & Sliding - A Pragmatic Aid to Judgement Bottom-up Risk & Opportunity Functional Requests Baseline Programme Bottom-up Uncertainty Top-down Assessment (80%SRA) } Adjustment for inherent Optimism Bias in the bottom-up approach Bottom-up Risk, Opportunity & Uncertainty (for statistical validity) Case 1 Ratio of Top-down to Bottom-up Approaches: Greater than but close to one Conclusion? The two approaches are reasonably consistent with one another

17 Slipping & Sliding - A Pragmatic Aid to Judgement Bottom-up Risk & Opportunity Top-down Assessment (80%SRA) Case Ratio of Top-down to Bottom-up Approaches: Significantly greater than one Functional Requests Baseline Programme Bottom-up Uncertainty Conclusion? The two approaches are not consistent with one another, either: the top-down is overly pessimistic or, the bottom-up is too immature Bottom-up Risk, Opportunity & Uncertainty (for statistical validity)

18 Slipping & Sliding - A Pragmatic Aid to Judgement Bottom-up Risk & Opportunity Top-down Assessment (80%SRA) Case 3 Ratio of Top-down to Bottom-up Approaches: Less than one Functional Requests Baseline Programme Bottom-up Uncertainty Conclusion? The two approaches are not consistent with one another an optimistic value cannot be greater than a pessimistic value. Either: the top-down is overly optimistic or, the bottom-up is too immature Bottom-up Risk, Opportunity & Uncertainty (for statistical validity)

19 Making A Recommendation - Revisited Following consideration of the inherent Optimism Bias in the Bottom-up Approach, we can modify our high level summary of the cost build up: Bottom-up Functional Request Risk Modelling 50% Confidence level Balancing Number for Total Confidence Level Million Confidence Optimistic Range % Pessimistic Range % Recommendation % Cost Build Up Million % of Total ERF Returns % Technical Risk Contingency % Management Contingency % Total % the inherent adjustment is held within Management Reserve or a higher Technical Risk Contingency 19

20 Slipping & Sliding - A Pragmatic Aid to Judgement Does it work in Practice? We do not claim it to be a perfect substitute for holistic Cost and Schedule Integration The technique is not a perfect solution but none are We re looking for reasonable accuracy not unreasonable precision It does not replace estimating judgement it can guide the thought process in making a judgement To narrow the range or eliminate the extremes To reject or rework a particular approach It provides a degree of Quality Control in our approach to generating three-point estimates Proof of the Pudding as they say is in the eating Let s look at an example 20

21 21

22 Example Based on Real Data Salient Details Small to Medium sized upgrade to a Military fast-jet Navigation System Programme covers: Design Development Test & Integration Upgrade to 47 Aircraft on a Return To Works programme Initial Support Baseline duration 70 months Baseline Cost (excluding risk and other contingencies) million 5 Key Risks mainly covering clearance aspects of the upgrade in particular integration with other systems 22

23 Example Based on Real Data Schedule Analysis - Details Total Baseline Duration 70 months Design 24 months Development 21 months Test & Integration 24 months Upgrade to 47 Aircraft 28 months Initial Support 25 months Significant concurrency over Design Development and Test & Integration 67 activities referenced 20 key schedule drivers identified 3-Point Estimates provided for the duration of all key schedule drivers 5 risks identified 3-Point Duration Estimates provided for the all risks 24 logical links made between activities 23

24 Example Based on Real Data Schedule Analysis - Level 1 Bar Chart Programme Year Month D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S Months From ITP Design Develpoment Test & Integration Upgrade to 47 Aircraft Initial Support Using the dataset generated a Monte Carlo Analysis of the schedule was undertaken 24

25 Confidence Levels Example Based on Real Data Schedule Analysis - Monte Carlo Output % Confidence Level % increase in programme duration 12.26% Confidence Level Months Programme Duration (months) 25

26 Example Based on Real Data Schedule Analysis - Monte Carlo Output Deterministic Duration of 70 months has only a 12.26% confidence level of being achieved Reference confidence Levels: 10% Confidence Level months 50% Confidence Level months 90% Confidence Level months Additional Point of Interest 80% Confidence Level months Duration increase of 14.5% against the Baseline Programme 26

27 Example Based on Real Data Cost Analysis - Details Baseline Cost (excluding risk and other contingencies) Programme Management million Design million Development Test & Integration million Purchases million Production Upgrade to 47 Aircraft million Initial Support million Grand Total million 5 risks identified 3-Point Cost Estimates provided for the all risks Full risk exposure (all risks happen at full value) million 27

28 Example Based on Real Data Cost Analysis - Details Programme Management Design Development Test & Integration Purchases Production Upgrade to 47 Aircraft Initial Support 28

29 Example Based on Real Data Cost Analysis Top-down ( Million) The Top-down cost evaluation will arbitrarily use an 80% Confidence Level Schedule months 14.4% increase over 70 month programme Top-down Cost Analysis Lets Call It Option 1 Factor All Costs All Costs = x 14.4% = Option 2 Factor In-House Costs In-house Costs = x 14.4% = Purchased Items = = Total = Option 3 Factor Development Integration & Test Costs Development = x 14.4% = Other In-house = = Purchased Items = = Total =

30 Example Based on Real Data Cost Analysis Bottom-up Baseline Cost (excluding risk and other contingencies) million 3-Point Cost Estimates provided for the all Baseline cost drivers Absolute minimum million Most Likely million Absolute maximum million 3-Point Cost Estimates provided for the all risks Absolute minimum million (No risks occur!) Expected Value million (Finance Like it!) Absolute maximum million (Big Number!) Monte Carlo Analysis Uncertainty Analysis (sensitivity around the Baseline Estimate) Risk and Opportunity Analysis (against the Risk Register) Risk Opportunity and Uncertainty Analysis (all data) 30

31 Example Based on Real Data Cost Analysis Monte Carlo Output Uncertainty 31

32 Example Based on Real Data Cost Analysis Monte Carlo Output Risk (and Opportunities) 32

33 Example Based on Real Data Cost Analysis Monte Carlo Output Risk Opportunity and Uncertainty 33

34 Example Based on Real Data Cost Analysis Summary Outputs (Interim View) Confidence Level Million Confidence Optimistic Range % Pessimistic Range % Recommendation % Bottom-up Functional Request Risk Modelling 50% Confidence level Balancing Number for Total Cost Build Up Million % ERF Returns % Technical Risk Contingency % Management Contingency % Total % 34

35 Example Based on Real Data Cost Analysis Monte Carlo Outputs Confidence Level Uncertainty K Risk K ROU K 0% 26,358-26,393 1% 27,062-27,273 5% 27,535-27,771 10% 27,812-28,064 15% 27,997-28,256 20% 28,140-28,404 25% 28, ,549 30% 28, ,677 35% 28, ,786 40% 28, ,898 45% 28, ,018 50% 28, ,130 55% 28, ,243 60% 29, ,359 65% 29, ,483 70% 29, ,605 75% 29, ,736 80% 29, ,890 85% 29, ,071 90% 29, ,315 95% 30, ,642 99% 30,710 1,223 31, % 31,788 1,783 32,377 To Excel Slipping & Sliding Template 35

36 Example Based on Real Data 36

37 Example Based on Real Data Cost Analysis Summary Outputs Bottom-up Approach Top-down From Excel Slipping & Sliding Template Uncertainty Risk/Opp ROU Stretched Equivalent % 50% 79% 50% 37

38 Example Based on Real Data Cost Analysis Summary Outputs (Revised View) Confidence Level Million Confidence Optimistic Range % Pessimistic Range % Recommendation % Bottom-up Functional Request Risk Modelling 50% Confidence level Balancing Number for Total Cost Build Up Million % ERF Returns % Technical Risk Contingency % Management Contingency % Total % 38

39 Example Based on Real Data Integrated Cost and Schedule Using all the previous datasets we can actually do a proper Integrated Monte Carlo Cost and Schedule Analysis We have the technology! 39

40 Cost Including Risk ( K) Example Based on Real Data Integrated Cost and Schedule 31,000 30,000 29,000 28,000 27,000 26,000 25,000 24, Duration (Months) 40

41 Example Based on Real Data Potential Cost Outcome ( Million) Estimates We could Use Top-down Option 1 Crude factor applied to the whole costs = Option 2 Crude factor applied to in-house costs = Option 3 Crude factor applied to Development activities = Bottom-up Risk Opportunity and 80% confidence Level = Slipping and Sliding Risk Opportunity and 50% confidence Level = Finance View Most Likely estimate plus Expected value (Most Likely) = Most Likely estimate plus Expected value (Max) = Integrated Cost and Schedule Pick a dot in middle of the scatter plot! =

42 Example Based on Real Data Actual Cost Outcome So what really happened then! Headline Cost out-turn using agreed pricing rates = However we did not do what the original programme said! There were problems with the RAF delivering aircraft to the factory not a risk identified excluded from the proposal as GFE Return To Works (RTW) programme changed to a Contractor Working Party (CWP) CWP do not attract the same charging rate as RTW CWP use RAF facilities Free of Charge and is therefore cheaper Actual costs based on CWP undertaking work =

43 Example Based on Real Data Actual Cost Outcome Cost Centre Baseline Estimate M Outturn Cost M Programme Management Baseline Cost Design Development Test & Integration Purchases Production Upgrade to 47 A/C Initial Support Grand Total

44 Example Based on Real Data Baseline Estimate Outturn Cost M Programme Management Design Development Test & Integration Purchases Production Upgrade to 47 A/C Initial Support 44

45 Cost Including Risk ( K) Example Based on Real Data Integrated Cost and Schedule 31,000 30,000 29,000 28,000 27,000 26,000 25,000 24, Duration (Months) 45

46 Slipping & Sliding - A Pragmatic Aid to Judgement Conclusion Cost and Schedule Integration the Right Thing to do High degree of correlation between them Heat Maps look good but do they really help? Still suffer from optimism bias Do not allow for the Rumsfeld Factor! Slipping and Sliding Technique is a quick and easy alternative to bridge the gap between optimism and pessimism bias Makes some allowance for the Rumsfeld Factor Easier to interpret than a Heat Map It is not a replacement for Judgement it s an aid Opportunities for improvement Cross-match several points? Slip and Slid between 20:80 or 50:80 Confidence levels (instead of 0:80 or 0:75) 46

BAE Systems Risk Opportunity & Uncertainty Modelling ACostE North West Region 4th September 2013

BAE Systems Risk Opportunity & Uncertainty Modelling ACostE North West Region 4th September 2013 BAE Systems Risk Opportunity & Uncertainty Modelling ACostE North West Region 4th September 2013 BAE SYSTEMS PLC 2011 All Rights Reserved The copyright in this document, which contains information of a

More information

Making sense of Schedule Risk Analysis

Making sense of Schedule Risk Analysis Making sense of Schedule Risk Analysis John Owen Barbecana Inc. Version 2 December 19, 2014 John Owen - jowen@barbecana.com 2 5 Years managing project controls software in the Oil and Gas industry 28 years

More information

Full Monte. Looking at your project through rose-colored glasses? Let s get real.

Full Monte. Looking at your project through rose-colored glasses? Let s get real. Realistic plans for project success. Looking at your project through rose-colored glasses? Let s get real. Full Monte Cost and schedule risk analysis add-in for Microsoft Project that graphically displays

More information

Use of the Risk Driver Method in Monte Carlo Simulation of a Project Schedule

Use of the Risk Driver Method in Monte Carlo Simulation of a Project Schedule Use of the Risk Driver Method in Monte Carlo Simulation of a Project Schedule Presented to the 2013 ICEAA Professional Development & Training Workshop June 18-21, 2013 David T. Hulett, Ph.D. Hulett & Associates,

More information

Integrated Cost Schedule Risk Analysis Using the Risk Driver Approach

Integrated Cost Schedule Risk Analysis Using the Risk Driver Approach Integrated Cost Schedule Risk Analysis Using the Risk Driver Approach Qatar PMI Meeting February 19, 2014 David T. Hulett, Ph.D. Hulett & Associates, LLC 1 The Traditional 3-point Estimate of Activity

More information

SCAF Workshop Integrated Cost and Schedule Risk Analysis. Tuesday 15th November 2016 The BAWA Centre, Filton, Bristol

SCAF Workshop Integrated Cost and Schedule Risk Analysis. Tuesday 15th November 2016 The BAWA Centre, Filton, Bristol The following presentation was given at: SCAF Workshop Integrated Cost and Schedule Risk Analysis Tuesday 15th November 2016 The BAWA Centre, Filton, Bristol Released for distribution by the Author www.scaf.org.uk/library

More information

Fundamentals of Project Risk Management

Fundamentals of Project Risk Management Fundamentals of Project Risk Management Introduction Change is a reality of projects and their environment. Uncertainty and Risk are two elements of the changing environment and due to their impact on

More information

Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management

Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management Slide 1 Looking Glass Development, LLC (303) 663-5402 / (888) 338-7447 4610 S. Ulster St. #150 Denver, CO 80237 information@lookingglassdev.com

More information

White Paper. Risk Assessment

White Paper. Risk Assessment Risk Assessment The assessment of risk is a very personal process, what is acceptable to one person may be far too risky for another to consider. The appreciation and assessment of risk and a person's

More information

for Major Infrastructure Projects

for Major Infrastructure Projects for Major Infrastructure Projects Presented by: Pedram Daneshmand Senior Associate Director 4 th Annual Contract Selection and Risk for Major Projects, March 2011 Agenda Brief Introduction Project Delivery

More information

Integrating Contract Risk with Schedule and Cost Estimates

Integrating Contract Risk with Schedule and Cost Estimates Integrating Contract Risk with Schedule and Cost Estimates Breakout Session # B01 Donald E. Shannon, Owner, The Contract Coach December 14, 2015 2:15pm 3:30pm 1 1 The Importance of Estimates Estimates

More information

Project Risk Management

Project Risk Management Project Risk Management Introduction Unit 1 Unit 2 Unit 3 PMP Exam Preparation Project Integration Management Project Scope Management Project Time Management Unit 4 Unit 5 Unit 6 Unit 7 Project Cost Management

More information

Risk Approach to Prioritising Maintenance Risk Factors for Value Management

Risk Approach to Prioritising Maintenance Risk Factors for Value Management Transport Research Laboratory Risk Approach to Prioritising Maintenance Risk Factors for Value Management by R Abell CPR966 2/462_155 CLIENT PROJECT REPORT Transport Research Laboratory CLIENT PROJECT

More information

Learning Le cy Document

Learning Le cy Document PROGRAMME CONTROL Quantitative Risk Assessment Procedure Document Number: CR-XRL-Z9-GPD-CR001-50004 Document History: Revision Prepared Date: Author: Reviewed by: Approved by: Reason for Issue 1.0 15-06-2015

More information

ADVANCED QUANTITATIVE SCHEDULE RISK ANALYSIS

ADVANCED QUANTITATIVE SCHEDULE RISK ANALYSIS ADVANCED QUANTITATIVE SCHEDULE RISK ANALYSIS DAVID T. HULETT, PH.D. 1 HULETT & ASSOCIATES, LLC 1. INTRODUCTION Quantitative schedule risk analysis is becoming acknowledged by many project-oriented organizations

More information

MINI GUIDE. Project risk analysis and management

MINI GUIDE. Project risk analysis and management MINI GUIDE Project risk analysis and management Association for Project Management January 2018 Contents Page 3 Introduction What is PRAM? Page 4 Page 7 Page 9 What is involved? Why is it used? When should

More information

A CRITIQUE OF INITIAL BUDGET ESTIMATING PRACTICE

A CRITIQUE OF INITIAL BUDGET ESTIMATING PRACTICE A CRITIQUE OF INITIAL BUDGET ESTIMATING PRACTICE Sidney Newton The University of New South Wales, Australia s.newton@unsw.edu.au Budget estimating practice has not changed fundamentally since cost planning

More information

Making Risk Management Tools More Credible: Calibrating the Risk Cube

Making Risk Management Tools More Credible: Calibrating the Risk Cube Making Risk Management Tools More Credible: Calibrating the Risk Cube SCEA 2006 Washington, DC Richard L. Coleman, Jessica R. Summerville, Megan E. Dameron Northrop Grumman Corporation 0 Outline! The General

More information

Mohammed Rafiuddin CEO and General Manager, BIOSI Biohazards Solutions Innovators

Mohammed Rafiuddin CEO and General Manager, BIOSI Biohazards Solutions Innovators Mohammed Rafiuddin CEO and General Manager, BIOSI Biohazards Solutions Innovators Profile of Mohammed Rafiuddin Mohammed is an active member of AACE International since 2006 with 30 years of experience

More information

Risk Management User Guide. Prepared By: Neville Turbit Version Feb /01/2009 Risk Management User Guide Page 1 of 36

Risk Management User Guide. Prepared By: Neville Turbit Version Feb /01/2009 Risk Management User Guide Page 1 of 36 Risk Management User Guide Prepared By: Neville Turbit Version 1.0 1 Feb 09 22/01/2009 Risk Management User Guide Page 1 of 36 Table of Contents Document Origin...2 Change History...2 Risk Guidelines...

More information

Project Management. Session 5 Budgets and Estimation Andre Samuel

Project Management. Session 5 Budgets and Estimation Andre Samuel Project Management Session 5 Budgets and Estimation Andre Samuel This Session Budgets and Estimation Estimation Principles Estimation Techniques Cost Estimating Estimation Principles Prediction of project

More information

Association for Project Management 2008

Association for Project Management 2008 Contents List of tables vi List of figures vii Foreword ix Acknowledgements x 1. Introduction 1 2. Understanding and describing risks 4 3. Purposes of risk prioritisation 12 3.1 Prioritisation of risks

More information

How Do You Calculate Cash Flow in Real Life for a Real Company?

How Do You Calculate Cash Flow in Real Life for a Real Company? How Do You Calculate Cash Flow in Real Life for a Real Company? Hello and welcome to our second lesson in our free tutorial series on how to calculate free cash flow and create a DCF analysis for Jazz

More information

CAPITAL MANAGEMENT - THIRD QUARTER 2010

CAPITAL MANAGEMENT - THIRD QUARTER 2010 CAPITAL MANAGEMENT - THIRD QUARTER 2010 CAPITAL MANAGEMENT The purpose of the Bank s capital management practice is to ensure that the Bank has sufficient capital at all times to cover the risks associated

More information

EARNED VALUE MANAGEMENT AND RISK MANAGEMENT : A PRACTICAL SYNERGY INTRODUCTION

EARNED VALUE MANAGEMENT AND RISK MANAGEMENT : A PRACTICAL SYNERGY INTRODUCTION EARNED VALUE MANAGEMENT AND RISK MANAGEMENT : A PRACTICAL SYNERGY Dr David Hillson PMP FAPM FIRM, Director, Risk Doctor & Partners david@risk-doctor.com www.risk-doctor.com INTRODUCTION In today s uncertain

More information

Risk vs. Uncertainty: What s the difference?

Risk vs. Uncertainty: What s the difference? Risk vs. Uncertainty: What s the difference? 2016 ICEAA Professional Development and Training Workshop Mel Etheridge, CCEA 2013 MCR, LLC Distribution prohibited without express written consent of MCR,

More information

Measurement of Market Risk

Measurement of Market Risk Measurement of Market Risk Market Risk Directional risk Relative value risk Price risk Liquidity risk Type of measurements scenario analysis statistical analysis Scenario Analysis A scenario analysis measures

More information

NEGOTIATION REVIEW. Negotiating Risk By Roger Greenfield. thegappartnership.com

NEGOTIATION REVIEW. Negotiating Risk By Roger Greenfield. thegappartnership.com NEGOTIATION REVIEW Negotiating Risk By Roger Greenfield contact@thegappartnership.com thegappartnership.com Negotiating risk Risk: one of the most under valued variables available during contract negotiations.

More information

California Department of Transportation(Caltrans)

California Department of Transportation(Caltrans) California Department of Transportation(Caltrans) Probabilistic Cost Estimating using Crystal Ball Software "You cannot exactly predict an uncertain future" Presented By: Jack Young California Department

More information

2.6 STEP SIX: Assess Risks and Adjust for Optimism Bias

2.6 STEP SIX: Assess Risks and Adjust for Optimism Bias 2.6 STEP SIX: Assess Risks and Adjust for Optimism Bias 2.6.1 In appraisals, there is always likely to be some difference between what is expected and what eventually happens, because of biases unwittingly

More information

Are Your Risk Tolerance and LDI Glide Path in Sync?

Are Your Risk Tolerance and LDI Glide Path in Sync? Are Your Risk Tolerance and LDI Glide Path in Sync? Wesley Phoa, LDI Portfolio Manager, Capital Group Luke Farrell, LDI Investment Specialist, Capital Group The Plan Sponsor s Mission Dual accountability

More information

Integrated Cost Schedule Risk Analysis Using the Risk Driver Approach

Integrated Cost Schedule Risk Analysis Using the Risk Driver Approach Integrated Cost Schedule Risk Analysis Using the Risk Driver Approach David T. Hulett, Ph.D. Hulett & Associates 24rd Annual International IPM Conference Bethesda, Maryland 29 31 October 2012 (C) 2012

More information

Oil & Gas Valuation Case Study: Ultra Petroleum [UPL] and its Acquisition of the Uinta Basin Acreage SHORT Recommendation

Oil & Gas Valuation Case Study: Ultra Petroleum [UPL] and its Acquisition of the Uinta Basin Acreage SHORT Recommendation Oil & Gas Valuation Case Study: Ultra Petroleum [UPL] and its Acquisition of the Uinta Basin Acreage SHORT Recommendation NOTES AND DISCLAIMERS: First, please do not construe this as investment advice.

More information

Acritical aspect of any capital budgeting decision. Using Excel to Perform Monte Carlo Simulations TECHNOLOGY

Acritical aspect of any capital budgeting decision. Using Excel to Perform Monte Carlo Simulations TECHNOLOGY Using Excel to Perform Monte Carlo Simulations By Thomas E. McKee, CMA, CPA, and Linda J.B. McKee, CPA Acritical aspect of any capital budgeting decision is evaluating the risk surrounding key variables

More information

Alternative VaR Models

Alternative VaR Models Alternative VaR Models Neil Roeth, Senior Risk Developer, TFG Financial Systems. 15 th July 2015 Abstract We describe a variety of VaR models in terms of their key attributes and differences, e.g., parametric

More information

A Scenario-Based Method (SBM) for Cost Risk Analysis

A Scenario-Based Method (SBM) for Cost Risk Analysis A Scenario-Based Method (SBM) for Cost Risk Analysis Cost Risk Analysis Without Statistics!! September 2008 Paul R Garvey Chief Scientist, Center for Acquisition and Systems Analysis 2008 The MITRE Corporation

More information

The University of Leeds Guidelines on Investment Decision Making: Building and Refurbishment Projects

The University of Leeds Guidelines on Investment Decision Making: Building and Refurbishment Projects The University of Leeds Guidelines on Investment Decision Making: Building and Refurbishment Projects Advice may be obtained from Clive Smith (Treasury Manager) E-mail: c.r.smith@adm.leeds.ac.uk Introduction

More information

Inflation Cost Risk Analysis to Reduce Risks in Budgeting

Inflation Cost Risk Analysis to Reduce Risks in Budgeting Inflation Cost Risk Analysis to Reduce Risks in Budgeting Booz Allen Hamilton Michael DeCarlo Stephanie Jabaley Eric Druker Biographies Michael J. DeCarlo graduated from the University of Maryland, Baltimore

More information

Overview of Today s Discussion. Don t Let EVM Data Mislead You. Steve Sheamer. Brief Overview of EVM Concepts. Why you can t trust BACs or EACs

Overview of Today s Discussion. Don t Let EVM Data Mislead You. Steve Sheamer. Brief Overview of EVM Concepts. Why you can t trust BACs or EACs Overview of Today s Discussion Brief Overview of EVM Concepts Don t Let EVM Data Mislead You Steve Sheamer Why you can t trust BACs or EACs Why EVM progress is often overstated Why you need to account

More information

Decommissioning Basis of Estimate Template

Decommissioning Basis of Estimate Template Decommissioning Basis of Estimate Template Cost certainty and cost reduction June 2017, Rev 1.0 2 Contents Introduction... 4 Cost Basis of Estimate... 5 What is a Basis of Estimate?... 5 When to prepare

More information

MASONIC BUDGET PLANNING. MWPHGL Office of the Grand Inspector

MASONIC BUDGET PLANNING. MWPHGL Office of the Grand Inspector MASONIC BUDGET PLANNING MWPHGL Office of the Grand Inspector 1 Introduction The objective of this class is to help you create a efficient budget and market your events MWPHGL Office of the Grand Inspector

More information

Understanding the Results of an Integrated Cost/Schedule Risk Analysis James Johnson, NASA HQ Darren Elliott, Tecolote Research Inc.

Understanding the Results of an Integrated Cost/Schedule Risk Analysis James Johnson, NASA HQ Darren Elliott, Tecolote Research Inc. Understanding the Results of an Integrated Cost/Schedule Risk Analysis James Johnson, NASA HQ Darren Elliott, Tecolote Research Inc. 1 Abstract The recent rise of integrated risk analyses methods has created

More information

SCHEDULE CREATION AND ANALYSIS. 1 Powered by POeT Solvers Limited

SCHEDULE CREATION AND ANALYSIS. 1   Powered by POeT Solvers Limited SCHEDULE CREATION AND ANALYSIS 1 www.pmtutor.org Powered by POeT Solvers Limited While building the project schedule, we need to consider all risk factors, assumptions and constraints imposed on the project

More information

Managing Project Risk DHY

Managing Project Risk DHY Managing Project Risk DHY01 0407 Copyright ESI International April 2007 All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted, in any form or

More information

STOCHASTIC COST ESTIMATION AND RISK ANALYSIS IN MANAGING SOFTWARE PROJECTS

STOCHASTIC COST ESTIMATION AND RISK ANALYSIS IN MANAGING SOFTWARE PROJECTS STOCHASTIC COST ESTIMATION AND RISK ANALYSIS IN MANAGING SOFTWARE PROJECTS Dr A.M. Connor Software Engineering Research Lab Auckland University of Technology Auckland, New Zealand andrew.connor@aut.ac.nz

More information

CHAPTER 12 APPENDIX Valuing Some More Real Options

CHAPTER 12 APPENDIX Valuing Some More Real Options CHAPTER 12 APPENDIX Valuing Some More Real Options This appendix demonstrates how to work out the value of different types of real options. By assuming the world is risk neutral, it is ignoring the fact

More information

The 2015 SCAF Annual Conference

The 2015 SCAF Annual Conference The following presentation was given at: The 2015 SCAF Annual Conference Tuesday 15th September 2015 The QEII Conference Centre, Westminster, London Released for distribution by the Author www.scaf.org.uk/library

More information

February 2010 Office of the Deputy Assistant Secretary of the Army for Cost & Economics (ODASA-CE)

February 2010 Office of the Deputy Assistant Secretary of the Army for Cost & Economics (ODASA-CE) U.S. ARMY COST ANALYSIS HANDBOOK SECTION 12 COST RISK AND UNCERTAINTY ANALYSIS February 2010 Office of the Deputy Assistant Secretary of the Army for Cost & Economics (ODASA-CE) TABLE OF CONTENTS 12.1

More information

Descriptive Statistics (Devore Chapter One)

Descriptive Statistics (Devore Chapter One) Descriptive Statistics (Devore Chapter One) 1016-345-01 Probability and Statistics for Engineers Winter 2010-2011 Contents 0 Perspective 1 1 Pictorial and Tabular Descriptions of Data 2 1.1 Stem-and-Leaf

More information

STOCHASTIC COST ESTIMATION AND RISK ANALYSIS IN MANAGING SOFTWARE PROJECTS

STOCHASTIC COST ESTIMATION AND RISK ANALYSIS IN MANAGING SOFTWARE PROJECTS Full citation: Connor, A.M., & MacDonell, S.G. (25) Stochastic cost estimation and risk analysis in managing software projects, in Proceedings of the ISCA 14th International Conference on Intelligent and

More information

CEVP Cost Estimate Validation Process

CEVP Cost Estimate Validation Process CEVP Cost Estimate Validation Process CSVA Conference 2004 Monica Bielenberg, P.E. Program Manager Why an Estimate is Not a Number Estimates are uncertain... Ultimate project cost and schedule cannot be

More information

RISK ANALYSIS GUIDE FOR PRIVATE INITIATIVE PROJECTS

RISK ANALYSIS GUIDE FOR PRIVATE INITIATIVE PROJECTS N A T I O N A L C O N C E S S I O N C O U N C I L RISK ANALYSIS GUIDE FOR PRIVATE INITIATIVE PROJECTS PREPARED BY: ENGINEER ÁLVARO BORBON M. PRIVATE INITIATIVE PROGRAM DECEMBER 2008 INDEX Guide Purpose...

More information

ALM as a tool for Malaysian business

ALM as a tool for Malaysian business Actuarial Partners Consulting Sdn Bhd Suite 17-02 Kenanga International Jalan Sultan Ismail 50250 Kuala Lumpur, Malaysia +603 2161 0433 Fax +603 2161 3595 www.actuarialpartners.com ALM as a tool for Malaysian

More information

Risk Management Strategy January NHS Education for Scotland RISK MANAGEMENT STRATEGY

Risk Management Strategy January NHS Education for Scotland RISK MANAGEMENT STRATEGY NHS Education for Scotland RISK MANAGEMENT STRATEGY January 2016 1 Contents 1. NES STATEMENT ON RISK MANAGEMENT 2 RISK MANAGEMENT STRATEGY 3 RISK MANAGEMENT STRUCTURES 4 RISK MANAGEMENT PROCESSES 5 RISK

More information

Project Theft Management,

Project Theft Management, Project Theft Management, by applying best practises of Project Risk Management Philip Rosslee, BEng. PrEng. MBA PMP PMO Projects South Africa PMO Projects Group www.pmo-projects.co.za philip.rosslee@pmo-projects.com

More information

Optimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur. Lecture - 18 PERT

Optimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur. Lecture - 18 PERT Optimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur Lecture - 18 PERT (Refer Slide Time: 00:56) In the last class we completed the C P M critical path analysis

More information

Solvency Opinion Scenario Analysis

Solvency Opinion Scenario Analysis Financial Advisory Services Insights Solvency Opinion Scenario Analysis C. Ryan Stewart A scenario analysis is a common procedure within the cash flow test performed as part of a fraudulent transfer or

More information

KPMG Major Projects Advisory Project Leadership Series: Budgeting, Estimating, and Contingency Management for Construction Projects

KPMG Major Projects Advisory Project Leadership Series: Budgeting, Estimating, and Contingency Management for Construction Projects KPMG Global Energy Institute KPMG International KPMG Major Projects Advisory Project Leadership Series: Budgeting, Estimating, and Contingency Management for Construction Projects Construction projects

More information

Validating TIP$TER Can You Trust Its Math?

Validating TIP$TER Can You Trust Its Math? Validating TIP$TER Can You Trust Its Math? A Series of Tests Introduction: Validating TIP$TER involves not just checking the accuracy of its complex algorithms, but also ensuring that the third party software

More information

Synchronize Your Risk Tolerance and LDI Glide Path.

Synchronize Your Risk Tolerance and LDI Glide Path. Investment Insights Reflecting Plan Sponsor Risk Tolerance in Glide Path Design May 201 Synchronize Your Risk Tolerance and LDI Glide Path. Summary What is the optimal way for a defined benefit plan to

More information

the debate concerning whether policymakers should try to stabilize the economy.

the debate concerning whether policymakers should try to stabilize the economy. 22 FIVE DEBATES OVER MACROECONOMIC POLICY LEARNING OBJECTIVES: By the end of this chapter, students should understand: the debate concerning whether policymakers should try to stabilize the economy. the

More information

Decision Analysis under Uncertainty. Christopher Grigoriou Executive MBA/HEC Lausanne

Decision Analysis under Uncertainty. Christopher Grigoriou Executive MBA/HEC Lausanne Decision Analysis under Uncertainty Christopher Grigoriou Executive MBA/HEC Lausanne 2007-2008 2008 Introduction Examples of decision making under uncertainty in the business world; => Trade-off between

More information

Project Management Certificate Program

Project Management Certificate Program Project Management Certificate Program Risk Management Terry Skaggs ( Denver class) skaggst@centurytel.net 719-783-0880 Lee Varra-Nelson (Fort Collins class) lvarranelson@q.com 970-407-9744 or 970-215-4949

More information

Developing a reserve range, from theory to practice. CAS Spring Meeting 22 May 2013 Vancouver, British Columbia

Developing a reserve range, from theory to practice. CAS Spring Meeting 22 May 2013 Vancouver, British Columbia Developing a reserve range, from theory to practice CAS Spring Meeting 22 May 2013 Vancouver, British Columbia Disclaimer The views expressed by presenter(s) are not necessarily those of Ernst & Young

More information

Market Risk Life Insurers Compared to Banks Rob Daly & Anton Kapel

Market Risk Life Insurers Compared to Banks Rob Daly & Anton Kapel Market Risk Life Insurers Compared to Banks Rob Daly & Anton Kapel Copyright 2006, the Tillinghast business of Towers Perrin. All rights reserved. A licence to publish is granted to the Institute of Actuaries

More information

The Risky Business of. Risk Management

The Risky Business of. Risk Management The Risky Business of Risk Management 1 About Me: Jan Holt, PMP Project Management Professional (PMP) since 2005 Project Management Institute (PMI) Michiana Chapter President PMP Prep Class Instructor

More information

RISK MANAGEMENT POLICY

RISK MANAGEMENT POLICY RISK MANAGEMENT POLICY TABLE OF CONTENTS PAGE 1. BACKGROUND 3 2. MATERIAL BUSINESS RISK 3 3. RISK TOLERANCE 4 4. OUTLINE OF ARTEMIS RESOURCE LIMITED S RISK MANAGEMENT POLICY 5 5. RISK MANAGEMENT ROLES

More information

A Proven Way to Budget Clients Spending

A Proven Way to Budget Clients Spending A Proven Way to Budget Clients Spending May 29, 2017 by Ken Steiner To better serve and retain retired or soon-to-be retired clients, advisors should use the actuarial budget benchmark (ABB), an annual

More information

Numerical Methods in Option Pricing (Part III)

Numerical Methods in Option Pricing (Part III) Numerical Methods in Option Pricing (Part III) E. Explicit Finite Differences. Use of the Forward, Central, and Symmetric Central a. In order to obtain an explicit solution for the price of the derivative,

More information

Structure & Learning Objectives

Structure & Learning Objectives U1 Structure & Learning Objectives In this part of the course, we will study the newly revamped IMF framework for public debt sustainability in market-access countries A historical overview of debt-to-gdp

More information

Cost Effectiveness Analysis

Cost Effectiveness Analysis Cost Effectiveness Analysis Dan Levine Institute for Defense Analyses January 25, 2001 Slide 1 TOPICS Decision-making and cost effectiveness Methodology Example Theoretical foundations Elaboration of methodology

More information

Recognizing and Mitigating Risk in Acquisition Programs

Recognizing and Mitigating Risk in Acquisition Programs Professional Development Institute June 1-3, 2016 Recognizing and Mitigating Risk in Acquisition Programs D e b r a E. H a h n d e b b i e. h a h n @ d a u. m i l 703-805- 2830 1 Exercise 1 1. Define risk

More information

Funding DB pension schemes: Getting the numbers right

Funding DB pension schemes: Getting the numbers right Aon Hewitt Consulting Retirement & Investment Funding DB pension schemes: Risk. Reinsurance. Human Resources. Funding DB pension schemes: Executive summary There is considerable debate in the UK pensions

More information

McDowell s Special Market Report Using the TradersCoach.com Software Tools

McDowell s Special Market Report Using the TradersCoach.com Software Tools McDowell s Special Market Report Using the TradersCoach.com Software Tools JULY 2018: Welcome to this month s Market Report! This written report is going to forecast the Dow Jones Industrial Average (hereafter

More information

Cost Risk and Uncertainty Analysis

Cost Risk and Uncertainty Analysis MORS Special Meeting 19-22 September 2011 Sheraton Premiere at Tysons Corner, Vienna, VA Mort Anvari Mort.Anvari@us.army.mil 1 The Need For: Without risk analysis, a cost estimate will usually be a point

More information

A Project Management Guide for Researchers

A Project Management Guide for Researchers A Project Management Guide for Researchers Prepared by: Research Grant and Contract Services January 2018 Copyright 2018 Memorial University of Newfoundland Table of Contents 1.0 Introduction... 4 2.0

More information

UNIVERSITY OF TOLEDO INTERNAL AUDIT DEPARTMENT DEVELOP BUDGETS

UNIVERSITY OF TOLEDO INTERNAL AUDIT DEPARTMENT DEVELOP BUDGETS The following control objectives provide a basis for strengthening your control environment for the process of developing budgets. When you select an objective, you will access a list of the associated

More information

Three Components of a Premium

Three Components of a Premium Three Components of a Premium The simple pricing approach outlined in this module is the Return-on-Risk methodology. The sections in the first part of the module describe the three components of a premium

More information

ITIL Practitioner Course 06 - Use Metrics & Measurement

ITIL Practitioner Course 06 - Use Metrics & Measurement ITIL Practitioner Course 06 - Use Metrics & Measurement Course Slide 1 Use Metrics & Measurement CSFs, KPIs & Improvement Analyze CSFs & KPIs in context Assessments Design a Report Slide 2 Learning Objectives

More information

John and Margaret Boomer

John and Margaret Boomer Retirement Lifestyle Plan Includes Insurance and Estate - Using Projected Returns John and Margaret Boomer Prepared by : Sample Report June 06, 2012 Table Of Contents IMPORTANT DISCLOSURE INFORMATION 1-9

More information

Single Source Contract Regulations 2014 Guidance Chapter 3 Pricing a Qualifying Defence Contract: The Cost Element

Single Source Contract Regulations 2014 Guidance Chapter 3 Pricing a Qualifying Defence Contract: The Cost Element Single Source Contract Regulations 2014 Guidance Chapter 3 Pricing a Qualifying Defence Contract: The Cost Element Purpose 1. The guidance in this chapter relates to a Qualifying Defence Contract (QDC)

More information

Equitable Life Assurance Society Things you should have known about your annuity, but didn t know enough to ask!

Equitable Life Assurance Society Things you should have known about your annuity, but didn t know enough to ask! SECTION 3 Equitable Life Assurance Society Things you should have known about your annuity, but didn t know enough to ask! 3.1) Introductions One of the obvious problems facing all annuitants is understanding

More information

Vanguard Global Capital Markets Model

Vanguard Global Capital Markets Model Vanguard Global Capital Markets Model Research brief March 1 Vanguard s Global Capital Markets Model TM (VCMM) is a proprietary financial simulation engine designed to help our clients make effective asset

More information

It's the mistakes that count!

It's the mistakes that count! It's the mistakes that count! Adrian Cowderoy City University London, England Adrian Cowderoy (Europe) Reading, England This is an account of how to improve existing estimation practices. It is based on

More information

What s Working and Not Working for 401(k) Small Plan Participants

What s Working and Not Working for 401(k) Small Plan Participants What s Working and Not Working for 401(k) Small Plan Participants The Guardian Small Plan 401(k) RetireWell StudySM 2.0 GUARDIAN RETIREMENT SOLUTIONS FOR PLAN SPONSORS Who Did We Survey? Methodology Guardian

More information

CAPITAL MANAGEMENT - FOURTH QUARTER 2009

CAPITAL MANAGEMENT - FOURTH QUARTER 2009 CAPITAL MANAGEMENT - FOURTH QUARTER 2009 CAPITAL MANAGEMENT The purpose of the Bank s capital management practice is to ensure that the Bank has sufficient capital at all times to cover the risks associated

More information

Hale and Associates Phone: Fax: CA License #0G30788

Hale and Associates Phone: Fax: CA License #0G30788 Hale and Associates Phone: 317-986-6785 Fax: 317-986-6787 www.haleandassociates.net CA License #0G30788 OVERVIEW Most people marvel at the lighthouse. A simple structure that has played such a big role

More information

The Equipment Plan 2017 to 2027

The Equipment Plan 2017 to 2027 A picture of the National Audit Office logo Report by the Comptroller and Auditor General Ministry of Defence The Equipment Plan 2017 to 2027 HC 717 SESSION 2017 2019 31 JANUARY 2018 4 Key facts The Equipment

More information

// Measuring Risk Exposure through Risk Range Certainty (RRC) Overcoming the Shortcomings of Schedule Confidence Levels

// Measuring Risk Exposure through Risk Range Certainty (RRC) Overcoming the Shortcomings of Schedule Confidence Levels // Measuring Risk Exposure through Risk Range Certainty (RRC) Overcoming the Shortcomings of Schedule Confidence Levels Dr. Dan Patterson, PMP CEO & President, Acumen October 2009 www.projectacumen.com

More information

Risk Analysis in Investment Appraisal

Risk Analysis in Investment Appraisal Risk Analysis in Investment Appraisal by Savvakis C. Savvides Published in Project Appraisal, Volume 9 Number 1, pages 3-18, March 1994 Beech Tree Publishing 1994 Reprinted with permission ABSTRACT * This

More information

Market Risk: FROM VALUE AT RISK TO STRESS TESTING. Agenda. Agenda (Cont.) Traditional Measures of Market Risk

Market Risk: FROM VALUE AT RISK TO STRESS TESTING. Agenda. Agenda (Cont.) Traditional Measures of Market Risk Market Risk: FROM VALUE AT RISK TO STRESS TESTING Agenda The Notional Amount Approach Price Sensitivity Measure for Derivatives Weakness of the Greek Measure Define Value at Risk 1 Day to VaR to 10 Day

More information

THE PMP EXAM PREP COURSE

THE PMP EXAM PREP COURSE THE PMP EXAM PREP COURSE Session 3 PMI, PMP and PMBOK are registered marks of the Project Management Institute, Inc. www.falcontraining.co.nz Agenda 9:00 10:15 10:15 10:30 10:30 12:00 12:00 12:45 12:45

More information

AUSTRALIAN CONSUMER LAW REVIEW

AUSTRALIAN CONSUMER LAW REVIEW AUSTRALIAN CONSUMER LAW REVIEW SUBMISSION MAY 2016 CONTENTS EXECUTIVE SUMMARY... 3 NEGATIVE IMPACTS... 5 ENGINEERING AND ARCHITECTURAL FIRMS... 5 INSURANCE MARKETS... 5 MACRO ECONOMIC... 7 SMALL BUSINESS...

More information

3/15/2018 CHAPTER 5. PROJECT MANAGEMENT. Prepared by: Dr. Maria Elisa Linda T. Cruz

3/15/2018 CHAPTER 5. PROJECT MANAGEMENT. Prepared by: Dr. Maria Elisa Linda T. Cruz CHAPTER 5. BUDGETING CHAPTER AND 1 INTRODUCTION COST ESTIMATION TO PROJECT MANAGEMENT Prepared by: Dr. Maria Elisa Linda T. Cruz Prepared by: Dr. Maria Elisa Linda T. Cruz 1 Chapter 5. Topics 5.1 Estimating

More information

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ International Project Management prof.dr MILOŠ D. MILOVANČEVIĆ Project time management Project cost management Time in project management process Time is a valuable resource. It is also the scarcest. Time

More information

Homeowners Ratemaking Revisited

Homeowners Ratemaking Revisited Why Modeling? For lines of business with catastrophe potential, we don t know how much past insurance experience is needed to represent possible future outcomes and how much weight should be assigned to

More information

Earned Value Management. Danielle Kellogg. Hodges University

Earned Value Management. Danielle Kellogg. Hodges University Earned Value Management 1 EARNED VALUE MANAGEMENT Earned Value Management Danielle Kellogg Hodges University Earned Value Management 2 Abstract Earned Value Management has been used with enterprise-level

More information

Management Reserve Defined

Management Reserve Defined Management Reserve Defined Management Reserve (MR) is defined in EIA 748 Earned Value Management Systems, the commercial standard for EVMS, as An amount of the total budget withheld for management control

More information

Monte Carlo Simulation: Don t Gamble Away Your Project Success Maurice (Mo) Klaus January 31, 2012

Monte Carlo Simulation: Don t Gamble Away Your Project Success Maurice (Mo) Klaus January 31, 2012 MBB Webcast Series Monte Carlo Simulation: Don t Gamble Away Your Project Success Maurice (Mo) Klaus January 31, 2012 Agenda Welcome Introduction of MBB Webcast Series Larry Goldman, MoreSteam.com Monte

More information

Effective Corporate Budgeting

Effective Corporate Budgeting Effective Corporate Budgeting in 8 Easy Steps This ebook will offer 8 easy and easy and proven steps for improving your corporate budgeting and planning process. You will see that by making a few small

More information