A CRITIQUE OF INITIAL BUDGET ESTIMATING PRACTICE

Size: px
Start display at page:

Download "A CRITIQUE OF INITIAL BUDGET ESTIMATING PRACTICE"

Transcription

1 A CRITIQUE OF INITIAL BUDGET ESTIMATING PRACTICE Sidney Newton The University of New South Wales, Australia Budget estimating practice has not changed fundamentally since cost planning was introduced some five decades ago. It continues to provide reasonable accuracy and confidence in the budgets for the majority of projects. As new projects seek to do things differently, on a different scale and unlike almost anything that has gone before, the practice of budget estimating based on traditional cost planning principles must be called into question. This paper presents a critical review of current initial budget estimating models and highlights the extent of the uncertainty and the lack of improvement in estimating accuracy over time. The argument that technical explanations (estimating error) or psychological explanations (optimism bias) are the basis for inaccurate cost estimates is rejected. Instead, a more objective and simplified statistical model is outlined reference class forecasting. KEYWORDS: initial budget estimates, estimating accuracy, reference class forecasting. INTRODUCTION Cost overruns, time delays and contract terminations are likely to be a growing challenge for the construction industry in the current economic climate. Fortunately, we have a generally well-established process of cost planning specifically developed to contain and control design, procurement and construction decisions effectively in project cost terms (Ferry et al, 1999). Around that broad process of cost planning has grown a range of cost estimating techniques, modifications and extensions to the basic cost planning process, and a wealth of the standardised cost data necessary to satisfy the basic principles of cost planning. The basic principles of cost planning were established at the outset, requiring: a frame of reference; a method of checking; and a means of remedial action (RICS, 1969). These principles have generally persevered, and cost planning is now recognised as an important management tool for any significant construction project. However, projects develop through various stages from inception to completion. Smith and Jaggar (2007, p.81), for example, use the RIBA Plan of Work to illustrate how the application of cost planning changes depending on the particular stage the project has reached, specifically: Pre-stage A: Establishing the Need establish the budget. Stage A: Options Appraisal cost of preferred solution. Stage B: Strategic Briefing target cost. Stage C: Outline Proposals prepare initial cost plan. Stage D: Detailed Proposals firm cost plan. Stage E: Final Proposals cost checks, design against cost plan. Stage F: Production Information final cost checks of design against cost plan. The stages listed here represent but one way of breaking down the pre-construction process, and are not necessarily discrete stages in any particular sense. However, they usefully 271

2 illustrate how the focus and outcome of cost planning does change over the course of a project. In particular, that the nature of the cost planning process in the early stages (when the specifics of a project are not clearly known) is distinctly different to that of the later stages (when more accuracy and higher fidelity is both required and possible). Of particular interest to this paper is the very earliest stage. In Plan of Work terms, the Prestage A: Establishing a Need. In any terms, however, the focus at that stage of the cost planning process is on the establishment of an initial budget estimate figure. It is at this earliest stage of the project that the specificity of what is to be constructed is at its broadest and most poorly defined, and the accuracy of the cost estimating technique likely to be at its most variable. Ashworth (2008, p.251) presents the usual levels of cost estimating accuracy achieved in practice, across all construction types, as follows: Table 1: Estimate Classification and Accuracy (from Ashworth, 2008, p.251) Estimate Purpose Accuracy Order of magnitude Feasibility studies 25-40% Factor estimate Early stage assessment 15-25% Office estimate Preliminary budget 10-15% Definitive estimate Final budget 5-10% Final estimate Prior to tender 5% In other words, at the earliest stage there is the maximum potential discrepancy between the budget figure estimate and the final project cost, and this discrepancy can be between 25 and 40%. What can be confusing about such accuracy predictions is the lack of consistency in what actually is being estimated: is it the lowest tender price, the total construction costs, or the overall project costs. Clearly, the accuracy variations will change depending on how far into the overall project the cost estimate is forecasting, but the earliest stage/maximum potential discrepancy relationship will always tend to hold. There have been several studies seeking to determine which factors most contribute to such a substantial potential variation in cost, or the accuracy with which such cost variation can be estimated (see for example, Aibinu and Pasco, 2008; and Serpell, 2005). The focus of this paper, however, is not so much on the factors that contribute to problems of accuracy, but rather, critically to review the alternative cost estimating approaches typically employed at the earliest stages of a project: the, so-called, Initial Budget Estimate models in current use. The objective of the review is to determine which cost estimating approach might best be used in the earliest stages of a project, when the intention is to estimate the overall project costs, or Outturn Cost. Determining the utility of competing budget estimating methods is now critically important, not least because project uncertainties at the earliest stages are unlikely to be mitigated any time soon. Indeed project uncertainties and are most likely actually to increase: economic conditions have become extremely volatile; the complexity of construction is increasing progressively as projects are required to become more innovative in order to satisfy a new order of constraints and expectations from environmental and social perspectives; financing 272

3 and risk management margins are being tightened, and the relative significance of traditional cost drivers has become almost chaotic and certainly unstable among various other factors also likely to increase uncertainty. INITIAL BUDGET ESTIMATE MODELS IN CURRENT USE It is, generally speaking, the purpose of any budget estimating model to provide as realistic an indication as possible of the final project cost (Outturn Cost), for a given project proposal. Every current form of model begins by generating an initial, best estimate of the final project cost (Base Estimate) for the project as it is conceived at that stage of the project development. The different models then employ different methods to estimate an amount to be added to the Base Estimate to allow for the inevitable uncertainty that is inherent in any estimating process. This amount is then the Uplift which is applied to the Base Estimate. Thus, ideally: Base Estimate + Uplift = Outturn Cost The three (3) generic model types most typically being used for budget estimating purposes are: Model 1: Deterministic Contingency Allowances Model 2: Quantitative Risk Analysis Model 3: Optimism Bias The Base Estimate is determined using one of a variety of preliminary estimating techniques, such as: functional unit pricing (where the cost is calculated on a per bed, per student, or other operational unit basis); area unit costing (where the cost is calculated on a per square metre of gross floor area or other measure of space provision); and/or elemental cost estimating (where consistent building elements such as foundations, frame, roof, etc., are costed individually). Model 1: Deterministic contingency allowances This is the traditional approach and variations of this model are used extensively. The level of experience and estimating competence are always important factors in the accuracy of the Base Estimate. They are particularly critical factors in determining the Uplift to apply in adjusting the Base Estimate for uncertainty using a deterministic contingency allowance. In this model the Uplift is determined through expert judgement and applied as a deterministic contingency added to the deterministic Base Estimate. Three (3) major types of contingency allowance are normally considered: estimating inaccuracy an allowance is added for the potential inaccuracy of the Base Estimate due to factors such as the lack of precedents and relevant cost data, the experience of the estimator, etc. Indications from a recent survey (Aibinu and Pasco, 2008) suggest that a contingency allowance of about 20% of the Base Estimate should be applied to take account of potential estimating inaccuracy in general. project uncertainty an allowance is added for the inevitable adjustments that occur as a project develops and becomes more resolved. At an early stage the Base Estimate may be generated on little more than a functional specification and a range of assumptions. Those assumptions are tested as specific scope, design and construction decisions are made. In line with the figures generated by Ashworth (2008, p.251), in 273

4 addition to the allowance for estimating inaccuracy, project uncertainty might require a further contingency allowance of up to 20% (maximum range of 40%, less 20% for estimating inaccuracy) of the Base Estimate. project complexity the contingency allowances for estimating inaccuracy and project uncertainty presented above are factors for all projects. The inherent complexity of a project has an aggravating effect on these normal factors. For particularly large, complex, innovative and high-profile projects a further contingency allowance may be appropriate. Given the other Uplift components are taken as averages, and complex projects tend to be at the top-end of potential cost overruns, an additional contingency for known project complexity of up to 35% might be reasonable. In very broad terms, that figure is determined from other research reported by The Allen Consulting Group (2007), The Tax Payers Alliance (2007), and Flyvbjerg et al (2002). It is apparent from the above that at the preliminary stages of a project, an overall contingency allowance of perhaps 75% (20% + 20% + 35%) of the Base Estimate might reasonably be applied. As the scope, design and construction details of a project develop, the level of confidence in the estimating accuracy and project certainty will improve, and the impact of project complexity will be mitigated. This method has the benefit of being relatively simple to apply and having a broad base of application. However, it does depend directly on the level of experience in the cost estimating technique and competency in risk analysis and management procedures. In any event it does remain a highly subjective approach, susceptible to inconsistent or biased judgement on the level of contingency to apply. The bias can be reduced by having multiple experts or an experienced team providing varied and independent opinion. It is problematic where a high level of confidence is required of the Initial Budget Estimate, as there is no indication on the degree of variation that might occur around the averages used. Thus, ultimately it is a deterministic (single figure) approach and, given the vagaries that attend the determination of an appropriate contingency amount, significantly higher levels of Uplift may be necessary where higher levels of certainty are required. Model 2: Quantitative risk analysis This model is used extensively in many government agencies and other large clients with consistent and ongoing construction needs. Its use has grown significantly in recent years, especially on particularly large-scale and/or complex projects. Sometimes it is possible to anticipate the circumstances that give rise to variability in outcome deterministically, but most often only a range of possible outcomes can be anticipated. In those circumstances the Base Estimate needs to incorporate an assessment of the risk and the confidence that attends such a forecast. The most significant benefit of making an explicit assessment of risk and confidence is that effective sensitivity analysis and planning control are then possible. This can further mitigate the inevitable uncertainty that attends a budget forecast. The most common form of quantitative risk analysis employs a three-point estimating practice based on Monte Carlo simulation (MoD, 2007). In that case, rather than a single cost estimate for each element of the overall Base Estimate, each element estimate comprises a range of possible costs defined by a Minimum and a Maximum, with the Most Likely element estimate located somewhere between those two extremes. The Minimum is an optimistic estimate of what might be the outcome if everything goes as well as could be 274

5 hoped. The Maximum is a pessimistic estimate that assumes what can go wrong, will go wrong (within reason). The Most-Likely estimate is the single figure estimate otherwise included in a deterministic estimating approach. The output of this method provides a cumulative probability (s-curve) distribution of the potential Outturn Costs. In most cases the distribution can be analysed further to determine the key factors driving the distribution (and variability). The actual Initial Budget Estimate is then selected from the probability distribution depending on the level of confidence expected/required at that stage of the project and the risk aversion of the budgeting authority. Typically: 10% Confidence represents a lean estimate, achieved only if most of the likely risks fail to materialise 50% Confidence represents the best estimate given that some risks will materialise and some will not, and 90% Confidence represents a value that could be reached if several unlikely risks all materialise together. This method has the benefit of providing a robust analysis and planning tool for risk management. It provides an explicit measure of confidence in the Initial Budget Estimate and indicates the general level of uncertainty applicable to that figure. More so even than for Model 1, it is critical that the quantitative risk analysis method be developed by a team of individuals and stakeholders, each bringing a slightly different perspective and expertise to the three-point estimating process. In addition, the technique does demand a specialist competence, training and experience to be applied effectively as with all statistical techniques, poor quality input data leads to poor quality output. It is also important that the method be employed as part of a broader framework of project risk management. There is the danger of biases and correlations going unnoticed in this technique, as it is a relatively blackbox process. However, these concerns are best allayed through correct application of the technique and a process of effective sensitivity testing. Model 3: Optimism bias Optimism Bias is a concept used to explain the tendency of people to be over-optimistic about the outcome of planned actions (Flyvbjerg et al, 2002). This includes over-estimating the likelihood of positive events and under-estimating the likelihood of negative events. Optimism bias arises in relation to estimates of costs and benefits and duration of tasks. It must be accounted for explicitly in appraisals, if they are to be realistic. Optimism bias typically results in cost overruns, benefit shortfalls and project delays. The UK government explicitly acknowledges that optimism bias is a problem in planning and budgeting (HM Treasury, 2003), but different departments have differing interpretations on the level of optimism bias to apply. For example, DEFRA (Dept of Environment Food and Regional Affairs) encourage the use a 50% optimism bias; Lancaster City Council use 60% initially; and Northern Ireland Building Procurement recommend an allowance of 35-40%. The UK Treasury itself has set optimum bias uplifts for projects as a whole and broken down for a variety of project characteristics. For smaller, less complex projects the optimism bias can be used directly as a general risk adjustment (as a direct alternative to the deterministic contingency allowances of Model 1). In all other situations the calculated optimism bias is 275

6 used as a top-down assessment of risk, and compared directly with a bottom-up calculation of risk from one of the quantitative risk analysis techniques of Model 2. Data collection from past experiences is an essential part of the optimism bias calculation process. HM Treasury (2003) suggests budgetary adjustments be based on experiential data from past projects and adjusted as required for the unique characteristics of the target project. For example, Figure 1 illustrates how an optimism bias adjustment to the Base Estimate is constructed and compared with an s-curve derived using some form of quantitative risk analysis model. Ideally, the Initial Budget Estimate so determined should be in the immediate vicinity of the 50 percentile confidence figure indicated by the s-curve. A traffic light marking system has been developed to aid this comparison. If the comparison result does not lie within the "Green" zone of the traffic light, then all calculations and assumptions should be reviewed. TRAFFIC LIGHT COMPARISON INITIAL BUDGET ESTIMATE Optimism Bias Uplift Base Estimate 10% 50% 90% CONFIDENCE LEVEL Figure 1: An Optimism Bias Uplifted Base Estimate Comparison (based on MoD, 2008) The advantages of this method are that it is relatively simple to understand and provides a consistent basis for comparison and benchmarking. However, the quality of the result directly reflects the accuracy of the tables of figures established for optimism bias. As indicated above, recommended values for optimism bias do vary and they will, in any case, require a large and robust data set to get even approximately right. As with all models, the final application is improved to the extent that empiricism and expertise are applied to the mitigating factors. The danger is always that such apparently simple models become more tempting for inexperienced users to apply. Guidelines are therefore particularly important with the optimism bias approach. Discussion of the current models The basic tenet of an effective cost planning process is to give primacy to the specific project under consideration. The more that is known about the current project (specific features and circumstances), then the more accurate the cost estimate is likely to be and the more effective the cost planning process becomes as a consequence. What this has tended to do is to 276

7 privilege traditional methods, where there is a familiarity with the process and its various tolerances and where extensive data sets already exist. But what is clear from the model descriptions provided above, is that the degree of variation around the potential contingency allowance, cost uncertainty and optimism bias figures used is substantial. If the Uplift amount might vary from 25%-75% for innovative projects under Model 1, or 35%-60% under Model 3, then the growing economic uncertainty is just further cause for concern. According to the Tax Payers Alliance (2007) a UK lobby group the total net cost of overruns in 305 public sector capital projects for the preceding 2 years was approximately US$35 billion. Despite the advent of improved estimating techniques and models, however, many studies conclude that estimating accuracy has improved only slightly, if at all (Aibinu and Pasco, 2008; Cheung et al, 2008; Flyvbjerg, 2007a). Flyvbjerg (2007a) goes on to reject the arguments that claim technical explanations (estimating error) or psychological explanations (optimism bias) are the basis for inaccurate cost estimates. Instead, Flyvbjerg shows that strategic misrepresentation on political and economic grounds (such as knowingly underestimating costs in order to gain national funding) is the stronger driver of poor estimating performance. What this suggests is that the fundamental premise of budget estimating as currently applied, where Uplift is determined through informed and specific insight into the particular project and its immediate context, might itself represent the real barrier to improved cost estimating performance. Could there be a tyranny of insight in operation here? It is unlikely (if not implausible) that the real culprit here is the application of specific project knowledge. More reasonably, if the genuine driver of poor budget estimate performance is a political-economic one, the real culprit may be the attachment to the project and its funding success that typically accompanies a more intimate understanding of the project. What may be required is a budget estimating model that displaces the need for insight and specific project knowledge with objectivity and distance. A FUNDAMENTALLY DIFFERENT INITIAL BUDGET ESTIMATE MODEL FOR MAJOR PROJECTS The clear distinction of this method is the way in which it provides an outside view on a specific project (how it sits within a context of a similar set of previous projects), where other methods look at a project from the inside (taking account of the specifics of the project, be that from a top-down or a bottom-up perspective). The advantage of this outside view is that all of the subjective elements associated with other methods of calculating an appropriate Uplift are dispelled. Being a statistical approach, a significant number of similar previous projects have to have been analysed in terms of their cost overruns, which may be particularly problematic for projects in smaller construction markets. It is also the case that as the project progresses, typically budget uncertainty is reduced. In order to arrive at a valid Total Budget Estimate at a later stage than the preliminary stage, Uplifts should normally be adjusted progressively downwards. According to Flyvbjerg (2007b), The Dutch econometrician Henri Theil (1961) liked to study the accuracy of forecasts. Once he did a study of accuracy in Dutch weather forecasts. Much to his surprise he found that if the weather forecasting service, instead of doing its forecasts, had simply played an automated recording stating every day that "the weather 277

8 tomorrow will be like the weather today," then the accuracy of predicted weather would have been higher than the accuracy actually achieved with the weather forecasts. Extending this anecdote, Flyvbjerg et al have proposed a fundamentally different initial budget estimating model from those currently used. Effectively, the model takes the position that the Uplift required to be applied to a new project will be like the Uplift that characterises recent projects of a related type. The model is called Reference Class Forecasting. Model 4: Reference class forecasting This model is a recent development in Europe, and was recently endorsed by the American Planning Association. Reference class forecasting takes a statistical view of any given project, based on a comparison of the Initial Budget Estimate and the final Outturn Costs derived from a set of related previous projects. It does not try to predict specific uncertainties, but rather simply places a given project in the statistical distribution generated from the reference set. Any approach that calls on human judgement and intervention in the estimating process is going to be biased in some direction and to some extent. Reference class forecasting, by making the assessment objective and statistical in nature, is a method for removing the bias from an Initial Budget Estimate or at least the Uplift component of same. Reference class forecasting requires the following three steps in order to determine the most appropriate Uplift to apply to a given Base Estimate: a relevant set of reference projects are identified from past data sources. The set must be broad enough to be statistically meaningful but narrow enough to be truly comparable with the particular project under consideration. a probability distribution for the selected reference set is generated. This requires access to credible, empirical data for a sufficient number of projects within the reference set to make statistically meaningful conclusions. comparing the specific project with the reference set distribution, in order to establish the most likely Uplift to apply to the particular project. Undoubtedly simple statistics, based on historical precedent, will fail to predict the extreme outcomes that lie outside the original set of precedents. However, for the vast majority of other cases the statistical approach will produce more accurate results because the model avoids having to allow separately for psychological and systemic biases such as optimism bias. Figure 2 illustrates how a reference class forecast is used to uplift a Base Estimate. The reference class forecast is presented in the form of an s-curve that represents the actual cost overruns as a percentage of the original Base Estimate, determined from a reference set of past projects. The Initial Budget Estimate figure is then determined by selecting the required level of confidence (percentage of projects within a given cost overrun) and reading off the required Uplift from the actual cost overrun axis. This Uplift is then applied to the current Base Estimate. For example, in 2004 the first instance of reference class forecasting was used by Ove Arup to demonstrate that an original budget estimate of 320 million for a proposed Edinburgh Tram Line project was likely to be conservative. Their forecast at the 50 th percentile was 357 million (Flyvbjerg, 2006). 278

9 ACTUAL COST OVERRUN AS A % OF BASE ESTIMATE (Uplift) 60% 45% 30% 45% Uplift required for 50% Confidence 0% -10% Base Estimate 0% 50% 100% PERCENTAGE OF REFERENCE SET PROJECTS WITHIN (LESS THAN) THAT COST OVERRUN Figure 2: A Reference Class Forecast CONCLUSIONS A critical review of current initial budget estimating models has highlighted the extent of the uncertainty and the lack of improvement in estimating accuracy over time. There seems no end to the growing number and substantial financial impact of project cost overruns. At a time when uncertainty is increasing, other models must be considered. The argument that technical explanations (estimating error) or psychological explanations (optimism bias) are the basis for inaccurate cost estimates has been rejected. Instead, a more objective and simplified statistical model has been outlined reference class forecasting. The clear distinction of reference class forecasting is the way in which it provides an outside view on a specific project, where other methods look at a project from the inside. The advantage of this outside view is that all of the subjective elements associated with other methods of calculating an appropriate Uplift are dispelled. The limitations of this approach, being a statistical approach, are that a significant number of similar previous projects have to have been analysed in terms of their cost overruns. This may be particularly problematic for smaller construction market contexts. It is also the case that the approach only works when the bias that causes the inaccuracy is not deliberate. In that circumstance the potential for reference class forecasting is low. 279

10 REFERENCES Aibinu, A. A. and Pasco, T. (2008) The accuracy of pre-tender building cost estimates in Australia, Construction Management and Economics, 26(12), Ashworth, A. (2008) Pre-Contract Studies: Development Economics, Tendering and Estimating (3 rd Edition). Oxford: Blackwell Publishing. Cheung, F. K. T., Wong, M. W. L. and Skitmore, M. (2008) A study of clients' and estimators' tolerance towards estimating errors, Construction Management and Economics, 26(4), Ferry, D. J., Brandon, P. S., and Ferry, J. D. (1999) Cost Planning of Buildings (7 th Edition). Oxford: Blackwell Science. Flyvbjerg, B. (2006) From nobel prize to project management: getting risks right, Project Management Journal, 37(3), Flyvbjerg, B. (2007a) Policy and planning for large-infrastructure projects: problems, causes, cures, Environment and Planning B: Planning and Design, 34, Flyvbjerg, B. (2007b) Truth and Lies About Megaprojects: Inaugural Speech, available at: Flyvbjerg, B., Holm, M. S. and Buhl, S. (2002) Underestimating costs in public works projects: error or lie?, Journal of the American Planning Association, 68(3), HM Treasury (2003) The Green Book: Appraisal and Evaluation in Central Government, London: TSO. MoD (2007) Three-Point Estimates Overview, available at: MoD (2008) Policy, Information and Guidance on the Risk Management Aspects of UK MOD Defence Acquisition: Version November 2008, available at: RICS (1969) Building Cost Information Service (BCIS) Standard Form of Cost Analysis: Principles, Instructions and Definitions. London: Royal Institution of Chartered Surveyors. Serpell, A. F. (2005) Improving conceptual cost estimating performance. AACE International Transactions, EST.13, 1-6. Smith, J. And Jaggar, D. (2007) Building Cost Planning for the Design Team. Oxford: Elsevier. The Allen Consulting Group (2007) Performance of PPPs and Traditional Procurement in Australia: Final Report. Available at: The Tax Payers Alliance (2007) Beyond the Dome: Government Projects 23 Billion Over Budget, available at: 280

Decommissioning Basis of Estimate Template

Decommissioning Basis of Estimate Template Decommissioning Basis of Estimate Template Cost certainty and cost reduction June 2017, Rev 1.0 2 Contents Introduction... 4 Cost Basis of Estimate... 5 What is a Basis of Estimate?... 5 When to prepare

More information

BAE Systems Risk Opportunity & Uncertainty Modelling ACostE North West Region 4th September 2013

BAE Systems Risk Opportunity & Uncertainty Modelling ACostE North West Region 4th September 2013 BAE Systems Risk Opportunity & Uncertainty Modelling ACostE North West Region 4th September 2013 BAE SYSTEMS PLC 2011 All Rights Reserved The copyright in this document, which contains information of a

More information

2.6 STEP SIX: Assess Risks and Adjust for Optimism Bias

2.6 STEP SIX: Assess Risks and Adjust for Optimism Bias 2.6 STEP SIX: Assess Risks and Adjust for Optimism Bias 2.6.1 In appraisals, there is always likely to be some difference between what is expected and what eventually happens, because of biases unwittingly

More information

BAE Systems SCAF Presentation June BAE SYSTEMS 2013, all rights reserved Unclassified 31/07/2013 1

BAE Systems SCAF Presentation June BAE SYSTEMS 2013, all rights reserved Unclassified 31/07/2013 1 BAE Systems SCAF Presentation June 2013 BAE SYSTEMS 2013, all rights reserved Unclassified 31/07/2013 1 Agenda An Alternative Approach to Cost and Schedule Integration BAE Systems Commercial Estimating

More information

Fundamentals of Project Risk Management

Fundamentals of Project Risk Management Fundamentals of Project Risk Management Introduction Change is a reality of projects and their environment. Uncertainty and Risk are two elements of the changing environment and due to their impact on

More information

Programmatic Risk Management in Space Projects

Programmatic Risk Management in Space Projects r bulletin 103 august 2000 Programmatic Risk Management in Space Projects M. Belingheri, D. von Eckardstein & R. Tosellini ESA Directorate of Manned Space and Microgravity, ESTEC, Noordwijk, The Netherlands

More information

BEYOND THE 4% RULE J.P. MORGAN RESEARCH FOCUSES ON THE POTENTIAL BENEFITS OF A DYNAMIC RETIREMENT INCOME WITHDRAWAL STRATEGY.

BEYOND THE 4% RULE J.P. MORGAN RESEARCH FOCUSES ON THE POTENTIAL BENEFITS OF A DYNAMIC RETIREMENT INCOME WITHDRAWAL STRATEGY. BEYOND THE 4% RULE RECENT J.P. MORGAN RESEARCH FOCUSES ON THE POTENTIAL BENEFITS OF A DYNAMIC RETIREMENT INCOME WITHDRAWAL STRATEGY. Over the past decade, retirees have been forced to navigate the dual

More information

Probabilistic Benefit Cost Ratio A Case Study

Probabilistic Benefit Cost Ratio A Case Study Australasian Transport Research Forum 2015 Proceedings 30 September - 2 October 2015, Sydney, Australia Publication website: http://www.atrf.info/papers/index.aspx Probabilistic Benefit Cost Ratio A Case

More information

RISK ANALYSIS AND CONTINGENCY DETERMINATION USING EXPECTED VALUE TCM Framework: 7.6 Risk Management

RISK ANALYSIS AND CONTINGENCY DETERMINATION USING EXPECTED VALUE TCM Framework: 7.6 Risk Management AACE International Recommended Practice No. 44R-08 RISK ANALYSIS AND CONTINGENCY DETERMINATION USING EXPECTED VALUE TCM Framework: 7.6 Risk Management Acknowledgments: John K. Hollmann, PE CCE CEP (Author)

More information

PUBLIC SPENDING IN SCOTLAND: RELATIVITIES AND PRIORITIES

PUBLIC SPENDING IN SCOTLAND: RELATIVITIES AND PRIORITIES PUBLIC SPENDING IN SCOTLAND: RELATIVITIES AND PRIORITIES Prof JD Gallagher CB FRSE 17 September 2017 Working Paper 2017-01 A Gwilym Gibbon Centre for Public Policy Working Paper Public Spending in Scotland:

More information

Technical note: Project cost contingency

Technical note: Project cost contingency Creating value from uncertainty Broadleaf Capital International Pty Ltd ABN 24 054 021 117 www.broadleaf.com.au Technical note: Project cost contingency Project cost contingency setting is an important

More information

SCOTTISH FUNDING COUNCIL CAPITAL PROJECTS DECISION POINT PROCESS

SCOTTISH FUNDING COUNCIL CAPITAL PROJECTS DECISION POINT PROCESS SCOTTISH FUNDING COUNCIL CAPITAL PROJECTS DECISION POINT PROCESS Incorporating amendments by Scottish Futures Trust (Proposals for Decision Points 2 5 Only) Executive summary... 1 Section 1: Introduction

More information

National PPP Forum Benchmarking Study, Phase II

National PPP Forum Benchmarking Study, Phase II National PPP Forum Benchmarking Study, Phase II Report on the performance of PPP projects in Australia when compared with a representative sample of traditionally procured infrastructure projects Released:

More information

SECTION II.7 MANAGING PROJECT RISKS

SECTION II.7 MANAGING PROJECT RISKS SECTION II.7 MANAGING PROJECT RISKS 1. WHAT ARE RISK ANALYSIS AND RISK MANAGEMENT? Any uncertainty in the scope of the Project, the cost of delivery and time scale for delivery, will present either a risk

More information

Information Technology Project Management, Sixth Edition

Information Technology Project Management, Sixth Edition Management, Sixth Edition Prepared By: Izzeddin Matar. Note: See the text itself for full citations. Understand what risk is and the importance of good project risk management Discuss the elements involved

More information

Report for the Edinburgh Tram Inquiry

Report for the Edinburgh Tram Inquiry Report for the Edinburgh Tram Inquiry Prepared by Prof. Bent Flyvbjerg* and Dr. Alexander Budzier *Lead author; all opinions expressed in this report are the opinions of the lead author and he accepts

More information

The CreditRiskMonitor FRISK Score

The CreditRiskMonitor FRISK Score Read the Crowdsourcing Enhancement white paper (7/26/16), a supplement to this document, which explains how the FRISK score has now achieved 96% accuracy. The CreditRiskMonitor FRISK Score EXECUTIVE SUMMARY

More information

The Financial Reporter

The Financial Reporter Article from: The Financial Reporter December 2004 Issue 59 Rethinking Embedded Value: The Stochastic Modeling Revolution Carol A. Marler and Vincent Y. Tsang Carol A. Marler, FSA, MAAA, currently lives

More information

ADVANCED QUANTITATIVE SCHEDULE RISK ANALYSIS

ADVANCED QUANTITATIVE SCHEDULE RISK ANALYSIS ADVANCED QUANTITATIVE SCHEDULE RISK ANALYSIS DAVID T. HULETT, PH.D. 1 HULETT & ASSOCIATES, LLC 1. INTRODUCTION Quantitative schedule risk analysis is becoming acknowledged by many project-oriented organizations

More information

SCAF Workshop Integrated Cost and Schedule Risk Analysis. Tuesday 15th November 2016 The BAWA Centre, Filton, Bristol

SCAF Workshop Integrated Cost and Schedule Risk Analysis. Tuesday 15th November 2016 The BAWA Centre, Filton, Bristol The following presentation was given at: SCAF Workshop Integrated Cost and Schedule Risk Analysis Tuesday 15th November 2016 The BAWA Centre, Filton, Bristol Released for distribution by the Author www.scaf.org.uk/library

More information

Available online at ScienceDirect. Procedia Engineering 123 (2015 ) Creative Construction Conference 2015 (CCC2015)

Available online at  ScienceDirect. Procedia Engineering 123 (2015 ) Creative Construction Conference 2015 (CCC2015) Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 123 (2015 ) 574 580 Creative Construction Conference 2015 (CCC2015) A method for estimating contingency based on project complexity

More information

Managing the Uncertainty: An Approach to Private Equity Modeling

Managing the Uncertainty: An Approach to Private Equity Modeling Managing the Uncertainty: An Approach to Private Equity Modeling We propose a Monte Carlo model that enables endowments to project the distributions of asset values and unfunded liability levels for the

More information

Full Monte. Looking at your project through rose-colored glasses? Let s get real.

Full Monte. Looking at your project through rose-colored glasses? Let s get real. Realistic plans for project success. Looking at your project through rose-colored glasses? Let s get real. Full Monte Cost and schedule risk analysis add-in for Microsoft Project that graphically displays

More information

METHODOLOGY For Risk Assessment and Management of PPP Projects

METHODOLOGY For Risk Assessment and Management of PPP Projects METHODOLOGY For Risk Assessment and Management of PPP Projects December 26, 2013 The publication was produced for review by the United States Agency for International Development. It was prepared by Environmental

More information

T o o l k i t f o r P u b l i c - P r i v a t e P a r t n e r s h i p s i n r o a d s & H i g h w a y s. Advantages of PPP

T o o l k i t f o r P u b l i c - P r i v a t e P a r t n e r s h i p s i n r o a d s & H i g h w a y s. Advantages of PPP Advantages of PPP A key advantage of having the private sector provide public services is that it allows public administrators to concentrate on planning, policy and regulation. The private sector, in

More information

IAASB CAG REFERENCE PAPER IAASB CAG Agenda (December 2005) Agenda Item I.2 Accounting Estimates October 2005 IAASB Agenda Item 2-B

IAASB CAG REFERENCE PAPER IAASB CAG Agenda (December 2005) Agenda Item I.2 Accounting Estimates October 2005 IAASB Agenda Item 2-B PROPOSED INTERNATIONAL STANDARD ON AUDITING 540 (REVISED) (Clean) AUDITING ACCOUNTING ESTIMATES AND RELATED DISCLOSURES (OTHER THAN THOSE INVOLVING FAIR VALUE MEASUREMENTS AND DISCLOSURES) (Effective for

More information

Understanding goal-based investing

Understanding goal-based investing Understanding goal-based investing By Joao Frasco, Chief Investment Officer, STANLIB Multi-Manager This article will explain our thinking behind goal-based investing. It is important to understand that

More information

White Paper. Risk Assessment

White Paper. Risk Assessment Risk Assessment The assessment of risk is a very personal process, what is acceptable to one person may be far too risky for another to consider. The appreciation and assessment of risk and a person's

More information

A Second Runway for Gatwick Appendix. A21 Programme Risk Management

A Second Runway for Gatwick Appendix. A21 Programme Risk Management A Second Runway for Gatwick Appendix A21 Programme Risk Management London Gatwick Airport Expansion Airport Commission Programme Risk Management Report Turner & Townsend 7 Savoy Court London WC2R 0EX

More information

RISK MANAGEMENT OF THE NATIONAL DEBT

RISK MANAGEMENT OF THE NATIONAL DEBT RISK MANAGEMENT OF THE NATIONAL DEBT Evaluation of the 2012-2015 policies 19 JUNE 2015 1 Contents 1 Executive Summary... 4 1.1 Introduction to the policy area... 4 1.2 Results... 5 1.3 Interest rate risk

More information

CAPITAL MANAGEMENT - THIRD QUARTER 2010

CAPITAL MANAGEMENT - THIRD QUARTER 2010 CAPITAL MANAGEMENT - THIRD QUARTER 2010 CAPITAL MANAGEMENT The purpose of the Bank s capital management practice is to ensure that the Bank has sufficient capital at all times to cover the risks associated

More information

Pricing Cost Assurance and Analysis Service (CAAS) Estimates Constraints

Pricing Cost Assurance and Analysis Service (CAAS) Estimates Constraints Pricing Cost Assurance and Analysis Service (CAAS) Estimates Constraints None. Authoritative Guidance Summary 1. Cost Assurance and Analysis Service (CAAS) provide a range of services for the Defence Equipment

More information

Survival guide to challenging costs in major projects

Survival guide to challenging costs in major projects challenging costs About this guide This publication outlines some of the challenges in estimating and managing costs that we have observed in our work on major projects. It offers Accounting Officers and

More information

Association for Project Management 2008

Association for Project Management 2008 Contents List of tables vi List of figures vii Foreword ix Acknowledgements x 1. Introduction 1 2. Understanding and describing risks 4 3. Purposes of risk prioritisation 12 3.1 Prioritisation of risks

More information

Using Monte Carlo Analysis in Ecological Risk Assessments

Using Monte Carlo Analysis in Ecological Risk Assessments 10/27/00 Page 1 of 15 Using Monte Carlo Analysis in Ecological Risk Assessments Argonne National Laboratory Abstract Monte Carlo analysis is a statistical technique for risk assessors to evaluate the uncertainty

More information

EARNED VALUE MANAGEMENT AND RISK MANAGEMENT : A PRACTICAL SYNERGY INTRODUCTION

EARNED VALUE MANAGEMENT AND RISK MANAGEMENT : A PRACTICAL SYNERGY INTRODUCTION EARNED VALUE MANAGEMENT AND RISK MANAGEMENT : A PRACTICAL SYNERGY Dr David Hillson PMP FAPM FIRM, Director, Risk Doctor & Partners david@risk-doctor.com www.risk-doctor.com INTRODUCTION In today s uncertain

More information

Making sense of Schedule Risk Analysis

Making sense of Schedule Risk Analysis Making sense of Schedule Risk Analysis John Owen Barbecana Inc. Version 2 December 19, 2014 John Owen - jowen@barbecana.com 2 5 Years managing project controls software in the Oil and Gas industry 28 years

More information

TEACHERS RETIREMENT BOARD. REGULAR MEETING Item Number: 7 CONSENT: ATTACHMENT(S): 1. DATE OF MEETING: November 8, 2018 / 60 mins

TEACHERS RETIREMENT BOARD. REGULAR MEETING Item Number: 7 CONSENT: ATTACHMENT(S): 1. DATE OF MEETING: November 8, 2018 / 60 mins TEACHERS RETIREMENT BOARD REGULAR MEETING Item Number: 7 SUBJECT: Review of CalSTRS Funding Levels and Risks CONSENT: ATTACHMENT(S): 1 ACTION: INFORMATION: X DATE OF MEETING: / 60 mins PRESENTER(S): Rick

More information

SCHEDULE CREATION AND ANALYSIS. 1 Powered by POeT Solvers Limited

SCHEDULE CREATION AND ANALYSIS. 1   Powered by POeT Solvers Limited SCHEDULE CREATION AND ANALYSIS 1 www.pmtutor.org Powered by POeT Solvers Limited While building the project schedule, we need to consider all risk factors, assumptions and constraints imposed on the project

More information

Presented at the 2012 SCEA/ISPA Joint Annual Conference and Training Workshop -

Presented at the 2012 SCEA/ISPA Joint Annual Conference and Training Workshop - Applying the Pareto Principle to Distribution Assignment in Cost Risk and Uncertainty Analysis James Glenn, Computer Sciences Corporation Christian Smart, Missile Defense Agency Hetal Patel, Missile Defense

More information

COMMON APPRAISAL FRAMEWORK FOR TRANSPORT PROJECTS AND PROGRAMMES

COMMON APPRAISAL FRAMEWORK FOR TRANSPORT PROJECTS AND PROGRAMMES COMMON APPRAISAL FRAMEWORK FOR TRANSPORT PROJECTS AND PROGRAMMES March 2016 OVERVIEW OF 2016 COMMON APPRAISAL FRAMEWORK This guidance document replaces the 2009 Guidelines on a Common Appraisal Framework

More information

Comment letter on ED/2015/3 Conceptual Framework for Financial Reporting

Comment letter on ED/2015/3 Conceptual Framework for Financial Reporting Tel +44 (0)20 7694 8871 15 Canada Square mark.vaessen@kpmgifrg.com London E14 5GL United Kingdom Mr Hans Hoogervorst International Accounting Standards Board 1 st Floor 30 Cannon Street London EC4M 6XH

More information

Risk Approach to Prioritising Maintenance Risk Factors for Value Management

Risk Approach to Prioritising Maintenance Risk Factors for Value Management Transport Research Laboratory Risk Approach to Prioritising Maintenance Risk Factors for Value Management by R Abell CPR966 2/462_155 CLIENT PROJECT REPORT Transport Research Laboratory CLIENT PROJECT

More information

The Review and Follow-up Process Key to Effective Budgetary Control

The Review and Follow-up Process Key to Effective Budgetary Control The Review and Follow-up Process Key to Effective Budgetary Control J. C. Cam ill us This article draws from the research finding that the effectiveness of management control systems is influenced more

More information

ALM as a tool for Malaysian business

ALM as a tool for Malaysian business Actuarial Partners Consulting Sdn Bhd Suite 17-02 Kenanga International Jalan Sultan Ismail 50250 Kuala Lumpur, Malaysia +603 2161 0433 Fax +603 2161 3595 www.actuarialpartners.com ALM as a tool for Malaysian

More information

Independent auditors report to the members of Savills plc

Independent auditors report to the members of Savills plc to the members of Savills plc Report on the financial statements Our opinion In our opinion: Savills plc s Group financial statements and Company financial statements (the financial statements ) give a

More information

Introduction to Risk for Project Controls

Introduction to Risk for Project Controls Introduction to Risk for Project Controls By Eukeni Urrechaga, PE Quick view at Project Controls Project Controls, like project management, is much an art as it is a science. The secret of good project

More information

Active Asset Allocation in the UK: The Potential to Add Value

Active Asset Allocation in the UK: The Potential to Add Value 331 Active Asset Allocation in the UK: The Potential to Add Value Susan tiling Abstract This paper undertakes a quantitative historical examination of the potential to add value through active asset allocation.

More information

Overview Strategic report Corporate governance Financial statements Shareholder information

Overview Strategic report Corporate governance Financial statements Shareholder information Financial statements 64 Independent Auditors report to the members of 70 Consolidated Income Statement 71 Consolidated Statement of Comprehensive Income 72 Consolidated Balance Sheet 73 Consolidated Statement

More information

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. cover_test.indd 1-2 4/24/09 11:55:22

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. cover_test.indd 1-2 4/24/09 11:55:22 cover_test.indd 1-2 4/24/09 11:55:22 losure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized 1 4/24/09 11:58:20 What is an actuary?... 1 Basic actuarial

More information

TAXREP 22/14 (ICAEW REPRESENTATION 56/14)

TAXREP 22/14 (ICAEW REPRESENTATION 56/14) TAXREP 22/14 (ICAEW REPRESENTATION 56/14) ICAEW TAX REPRESENTATION REVIEW OF EXISTING VAT LEGISLATION ON PUBLIC BODIES AND TAX EXEMPTIONS IN THE PUBLIC INTEREST ICAEW welcomes the opportunity to comment

More information

HMRC Consultation: Large Business compliance enhancing our risk assessment approach Response by the Chartered Institute of Taxation

HMRC Consultation: Large Business compliance enhancing our risk assessment approach Response by the Chartered Institute of Taxation HMRC Consultation: Large Business compliance enhancing our risk assessment approach Response by the Chartered Institute of Taxation 1 Introduction 1.1 This consultation document is examining how HM Revenue

More information

Lazard Insights. The Art and Science of Volatility Prediction. Introduction. Summary. Stephen Marra, CFA, Director, Portfolio Manager/Analyst

Lazard Insights. The Art and Science of Volatility Prediction. Introduction. Summary. Stephen Marra, CFA, Director, Portfolio Manager/Analyst Lazard Insights The Art and Science of Volatility Prediction Stephen Marra, CFA, Director, Portfolio Manager/Analyst Summary Statistical properties of volatility make this variable forecastable to some

More information

Chapter 7: Risk. Incorporating risk management. What is risk and risk management?

Chapter 7: Risk. Incorporating risk management. What is risk and risk management? Chapter 7: Risk Incorporating risk management A key element that agencies must consider and seamlessly integrate into the TAM framework is risk management. Risk is defined as the positive or negative effects

More information

Making it add up. A constructive critique of the EITI Reporting Guidelines and Source Book

Making it add up. A constructive critique of the EITI Reporting Guidelines and Source Book A constructive critique of the EITI Reporting Guidelines and Source Book Is the EITI Adding Up? Since its inception in 2003, the Extractive Industries Transparency Initiative (EITI) has recorded some important

More information

Cost Forecasting: Where Do We Get It Wrong (and Why)? Matt Bassford Director, Defence & Security Programme

Cost Forecasting: Where Do We Get It Wrong (and Why)? Matt Bassford Director, Defence & Security Programme Cost Forecasting: Where Do We Get It Wrong (and Why)? Matt Bassford Director, Defence & Security Programme This presentation draws on RAND s experience of defence analysis in the US, UK, and Europe A global

More information

Group Independent Auditors Report to the Members of Croda International Plc

Group Independent Auditors Report to the Members of Croda International Plc Group Independent Auditors Report to the Members of Report on the Group financial statements Our opinion In our opinion, s Group financial statements (the financial statements ): give a true and fair view

More information

Improving Risk Quality to Drive Value

Improving Risk Quality to Drive Value Improving Risk Quality to Drive Value Improving Risk Quality to Drive Value An independent executive briefing commissioned by Contents Foreword.................................................. 2 Executive

More information

Comment Does the economics of moral hazard need to be revisited? A comment on the paper by John Nyman

Comment Does the economics of moral hazard need to be revisited? A comment on the paper by John Nyman Journal of Health Economics 20 (2001) 283 288 Comment Does the economics of moral hazard need to be revisited? A comment on the paper by John Nyman Åke Blomqvist Department of Economics, University of

More information

MAXIMISE THE LEVEL OF SERVICE USING CROSS ASSET PORTFOLIO RENEWALS MANAGEMENT

MAXIMISE THE LEVEL OF SERVICE USING CROSS ASSET PORTFOLIO RENEWALS MANAGEMENT Mason, Rangamuwa, Henning Page 1 of 15 MAXIMISE THE LEVEL OF SERVICE USING CROSS ASSET PORTFOLIO RENEWALS MANAGEMENT Michael Mason 1, Siri Rangamuwa 1, Theunis F. P Henning 2 Corresponding Author: Michael

More information

Solvency Opinion Scenario Analysis

Solvency Opinion Scenario Analysis Financial Advisory Services Insights Solvency Opinion Scenario Analysis C. Ryan Stewart A scenario analysis is a common procedure within the cash flow test performed as part of a fraudulent transfer or

More information

JULY 2017 HM Treasury

JULY 2017 HM Treasury JULY 2017 HM Treasury Whole of Government Accounts 2015-16 Our vision is to help the nation spend wisely. Our public audit perspective helps Parliament hold government to account and improve public services.

More information

Equitable Financial Evaluation Method for Public-Private Partnership Projects *

Equitable Financial Evaluation Method for Public-Private Partnership Projects * TSINGHUA SCIENCE AND TECHNOLOGY ISSN 1007-0214 20/25 pp702-707 Volume 13, Number 5, October 2008 Equitable Financial Evaluation Method for Public-Private Partnership Projects * KE Yongjian ( ), LIU Xinping

More information

THE TAX GAP FOR CORPORATION TAX

THE TAX GAP FOR CORPORATION TAX PAPER 3 THE TAX GAP FOR CORPORATION TAX Oxford Universi ty Centre for Business Taxation 3 rd December 2012 In summer 2012 the National Audit Office (NAO) commissioned the Oxford University Centre for Business

More information

Full reference to published version: Bent Flyvbjerg, Chi-keung Hon, and Wing Huen Fok, 2016, "Reference Class Forecasting for Hong Kong s Major Roadworks Projects," Proceedings of the Institution of Civil

More information

Integrated Cost Schedule Risk Analysis Using the Risk Driver Approach

Integrated Cost Schedule Risk Analysis Using the Risk Driver Approach Integrated Cost Schedule Risk Analysis Using the Risk Driver Approach Qatar PMI Meeting February 19, 2014 David T. Hulett, Ph.D. Hulett & Associates, LLC 1 The Traditional 3-point Estimate of Activity

More information

Intro Public-Private Partnership (P3) Finance Course

Intro Public-Private Partnership (P3) Finance Course Intro Public-Private Partnership (P3) Finance Course Identifying P3 Projects and Knowing the Atmosphere Kylee Anastasi Director, Capital Projects and Infrastructure Advisory PricewaterhouseCoopers LLP

More information

Target Date Glide Paths: BALANCING PLAN SPONSOR GOALS 1

Target Date Glide Paths: BALANCING PLAN SPONSOR GOALS 1 PRICE PERSPECTIVE In-depth analysis and insights to inform your decision-making. Target Date Glide Paths: BALANCING PLAN SPONSOR GOALS 1 EXECUTIVE SUMMARY We believe that target date portfolios are well

More information

TRANSFER PRICING IN THE WATER INDUSTRY REGULATORY ACCOUNTING GUIDELINE 5.03

TRANSFER PRICING IN THE WATER INDUSTRY REGULATORY ACCOUNTING GUIDELINE 5.03 TRANSFER PRICING IN THE WATER INDUSTRY REGULATORY ACCOUNTING GUIDELINE 5.03 Ofwat Issued April 1997 Revised March 2000 1 TRANSFER PRICING IN THE WATER INDUSTRY REGULATORY ACCOUNTING GUIDELINE CONTENTS

More information

Reference class forecasting for Hong Kong s major roadworks projects

Reference class forecasting for Hong Kong s major roadworks projects Proceedings of the Institution of Civil Engineers http://dx.doi.org/10.1680/jcien.15.00075 Paper 1500075 Received 15/10/2015 Accepted 25/04/2016 Keywords: Economics & finance/infrastructure planning/ Risk

More information

Measurable value creation through an advanced approach to ERM

Measurable value creation through an advanced approach to ERM Measurable value creation through an advanced approach to ERM Greg Monahan, SOAR Advisory Abstract This paper presents an advanced approach to Enterprise Risk Management that significantly improves upon

More information

Technical Guide. Issue: forecasting a successful outcome with cash flow modelling. To us there are no foreign markets. TM

Technical Guide. Issue: forecasting a successful outcome with cash flow modelling. To us there are no foreign markets. TM Technical Guide To us there are no foreign markets. TM The are a unique investment solution, providing a powerful tool for managing volatility and risk that can complement any wealth strategy. Our volatility-led

More information

Integrated Cost-Schedule Risk Analysis Improves Cost Contingency Calculation ICEAA 2017 Workshop Portland OR June 6 9, 2017

Integrated Cost-Schedule Risk Analysis Improves Cost Contingency Calculation ICEAA 2017 Workshop Portland OR June 6 9, 2017 Integrated Cost-Schedule Risk Analysis Improves Cost Contingency Calculation ICEAA 2017 Workshop Portland OR June 6 9, 2017 David T. Hulett, Ph.D., FAACE Hulett & Associates, LLC David.hulett@projectrisk

More information

Aon Retirement and Investment. Aon Investment Research and Insights. Dangers Ahead? Navigating hazards using scenario analysis.

Aon Retirement and Investment. Aon Investment Research and Insights. Dangers Ahead? Navigating hazards using scenario analysis. Aon Retirement and Investment Aon Investment Research and Insights Dangers Ahead? Navigating hazards using scenario analysis March 2018 Table of contents Executive summary....1 Introduction...1 Scenario

More information

OVERVIEW OF DETAILED APPRAISAL PROCESS

OVERVIEW OF DETAILED APPRAISAL PROCESS Section 3 OVERVIEW OF DETAILED APPRAISAL PROCESS 3.1 Introduction The detailed appraisal stage aims to provide a basis for a decision on whether to proceed with a project in principle or not. It includes

More information

The Vasicek adjustment to beta estimates in the Capital Asset Pricing Model

The Vasicek adjustment to beta estimates in the Capital Asset Pricing Model The Vasicek adjustment to beta estimates in the Capital Asset Pricing Model 17 June 2013 Contents 1. Preparation of this report... 1 2. Executive summary... 2 3. Issue and evaluation approach... 4 3.1.

More information

Project Theft Management,

Project Theft Management, Project Theft Management, by applying best practises of Project Risk Management Philip Rosslee, BEng. PrEng. MBA PMP PMO Projects South Africa PMO Projects Group www.pmo-projects.co.za philip.rosslee@pmo-projects.com

More information

Responsible Investment

Responsible Investment June 2015 Schroders Responsible Investment Global and International Equities At Schroders, Responsible principles drive our investment decisions and the way we manage funds. From choosing the right assets

More information

What is the impact of ORR s inflation proposals on Network Rail?

What is the impact of ORR s inflation proposals on Network Rail? What is the impact of ORR s inflation proposals on Network Rail? Note prepared for Network Rail September 3rd 2012 1 Introduction and summary There is a well-established precedent for using some form of

More information

NEGOTIATION REVIEW. Negotiating Risk By Roger Greenfield. thegappartnership.com

NEGOTIATION REVIEW. Negotiating Risk By Roger Greenfield. thegappartnership.com NEGOTIATION REVIEW Negotiating Risk By Roger Greenfield contact@thegappartnership.com thegappartnership.com Negotiating risk Risk: one of the most under valued variables available during contract negotiations.

More information

Flyvbjerg, Bent. Accountable Megaproject Decision-making

Flyvbjerg, Bent. Accountable Megaproject Decision-making Name: Title: Organization: Country: Flyvbjerg, Bent Professor Aalborg University Denmark Accountable Megaproject Decision-making Accountable Megaproject Decision Making Principles of Governance of Major

More information

The Inexact Science of Risk Assessment (and Implications for Risk Management)

The Inexact Science of Risk Assessment (and Implications for Risk Management) Human and Ecological Risk Assessment: Vol. 4, No. 2, pp. 245-251 (1998) The Inexact Science of Risk Assessment (and Implications for Risk Management) Susan Felter and Michael Dourson Toxicology Excellence

More information

Cost Risk Assessment Building Success and Avoiding Surprises Ken L. Smith, PE, CVS

Cost Risk Assessment Building Success and Avoiding Surprises Ken L. Smith, PE, CVS Cost Risk Assessment Building Success and Avoiding Surprises Ken L. Smith, PE, CVS 360-570-4415 2015 HDR, Inc., all rights reserved. Addressing Cost and Schedule Concerns Usual Questions Analysis Needs

More information

Value for Money Analysis: Choosing the Best Project Delivery Method. Ken L. Smith, PE, CVS -HDR Engineering, Inc.

Value for Money Analysis: Choosing the Best Project Delivery Method. Ken L. Smith, PE, CVS -HDR Engineering, Inc. Value for Money Analysis: Choosing the Best Project Delivery Method Ken L. Smith, PE, CVS -HDR Engineering, Inc. 1 Overview What is a VfM analysis Why is it used Key VfM components and principles Life

More information

ICAEW REPRESENTATION 196/16

ICAEW REPRESENTATION 196/16 ICAEW REPRESENTATION 196/16 Consultation Paper: Public Sector Specific Financial Instruments ICAEW welcomes the opportunity to comment on the Public Sector Specific Financial Instruments consultation published

More information

Investment strategy selection should take a long-term view

Investment strategy selection should take a long-term view DB PENSIONS WHITEPAPER Author Rudolf Puchy Moody s Analytics Research Contact Us For further information, please contact our customer service team: Americas +1.212.553.1653 clientservices@moodys.com Europe

More information

RISK MITIGATION IN FAST TRACKING PROJECTS

RISK MITIGATION IN FAST TRACKING PROJECTS Voorbeeld paper CCE certificering RISK MITIGATION IN FAST TRACKING PROJECTS Author ID # 4396 June 2002 G:\DACE\certificering\AACEI\presentation 2003 page 1 of 17 Table of Contents Abstract...3 Introduction...4

More information

Project Risk Management

Project Risk Management Project Skills Team FME www.free-management-ebooks.com ISBN 978-1-62620-986-4 Copyright Notice www.free-management-ebooks.com 2014. All Rights Reserved ISBN 978-1-62620-986-4 The material contained within

More information

Title of the Paper: Integrating Management and cost management to arrive at a realistic Estimate at Completion Theme: Project Management leadership -> To accelerate Economic Growth Keywords: Cost overrun,

More information

Better to be good and on time than perfect and late: replacing incurred loss by expected loss

Better to be good and on time than perfect and late: replacing incurred loss by expected loss 19 October 2018 ESMA 32-67-510 Better to be good and on time than perfect and late: replacing incurred loss by expected loss Banco de España CEMFI FSI High-Level Conference The new bank provisioning standards:

More information

The Capital Expenditure Decision

The Capital Expenditure Decision 1 2 October 1989 The Capital Expenditure Decision CONTENTS 2 Paragraphs INTRODUCTION... 1-4 SECTION 1 QUANTITATIVE ESTIMATES... 5-44 Fixed Investment Estimates... 8-11 Working Capital Estimates... 12 The

More information

Project Risk Management. Prof. Dr. Daning Hu Department of Informatics University of Zurich

Project Risk Management. Prof. Dr. Daning Hu Department of Informatics University of Zurich Project Risk Management Prof. Dr. Daning Hu Department of Informatics University of Zurich Learning Objectives Understand what risk is and the importance of good project risk management Discuss the elements

More information

Chapter 2 Department of Supply and Services Public-Private Partnership: Eleanor W. Graham Middle School and Moncton North School

Chapter 2 Department of Supply and Services Public-Private Partnership: Eleanor W. Graham Middle School and Moncton North School Department of Supply and Services - Public-Private Partnership: Chapter 2 Department of Supply and Services Public-Private Partnership: Eleanor W. Graham Middle School and Moncton North School Contents

More information

NEW ZEALAND SOCIETY OF ACTUARIES PROFESSIONAL STANDARD NO. 91 ECONOMIC VALUATIONS MANDATORY STATUS EFFECTIVE DATE 1 JULY 2010

NEW ZEALAND SOCIETY OF ACTUARIES PROFESSIONAL STANDARD NO. 91 ECONOMIC VALUATIONS MANDATORY STATUS EFFECTIVE DATE 1 JULY 2010 NEW ZEALAND SOCIETY OF ACTUARIES PROFESSIONAL STANDARD NO. 91 ECONOMIC VALUATIONS MANDATORY STATUS EFFECTIVE DATE 1 JULY 2010 1. Introduction... 2 2. Effective Date... 3 3. Definitions... 3 4. Professional

More information

B.29[19a] Matters arising from our audits of the long-term plans

B.29[19a] Matters arising from our audits of the long-term plans B.29[19a] Matters arising from our audits of the 2018-28 long-term plans Photo acknowledgement: istock LazingBee B.29[19a] Matters arising from our audits of the 2018-28 long-term plans Presented to the

More information

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ International Project Management prof.dr MILOŠ D. MILOVANČEVIĆ Project time management Project cost management Time in project management process Time is a valuable resource. It is also the scarcest. Time

More information

1 of 14 4/27/2009 7:45 AM

1 of 14 4/27/2009 7:45 AM 1 of 14 4/27/2009 7:45 AM Chapter 7 - Network Models in Project Management INTRODUCTION Most realistic projects that organizations like Microsoft, General Motors, or the U.S. Defense Department undertake

More information

MINI GUIDE. Project risk analysis and management

MINI GUIDE. Project risk analysis and management MINI GUIDE Project risk analysis and management Association for Project Management January 2018 Contents Page 3 Introduction What is PRAM? Page 4 Page 7 Page 9 What is involved? Why is it used? When should

More information

Approach to Assessing Capital Expenditure for Price Reviews

Approach to Assessing Capital Expenditure for Price Reviews Approach to Assessing Capital Expenditure for Price Reviews January 2018 This document examines approaches to assessing capital expenditure (Capex) in general and what has been specifically employed by

More information

INSIGHTS. The Factor Landscape. August rocaton.com. 2017, Rocaton Investment Advisors, LLC

INSIGHTS. The Factor Landscape. August rocaton.com. 2017, Rocaton Investment Advisors, LLC INSIGHTS The Factor Landscape August 2017 203.621.1700 2017, Rocaton Investment Advisors, LLC EXECUTIVE SUMMARY Institutional investors have shown an increased interest in factor investing. Much of the

More information