Integrated Cost Schedule Risk Analysis Using the Risk Driver Approach

Size: px
Start display at page:

Download "Integrated Cost Schedule Risk Analysis Using the Risk Driver Approach"

Transcription

1 Integrated Cost Schedule Risk Analysis Using the Risk Driver Approach Qatar PMI Meeting February 19, 2014 David T. Hulett, Ph.D. Hulett & Associates, LLC 1

2 The Traditional 3-point Estimate of Activity Duration Uncertainty Typical schedule risk analysis starts with the activity that is impacted by risks Estimates the 3-point estimate for optimistic, most likely and pessimistic duration Creates a probability distribution for activity duration Performs Monte Carlo simulation What causes the most overall schedule risk? These questions are answered in the 3-point estimate approach by looking to the impacted activities: Sensitivity to activity durations Criticality of activity durations 2

3 Some Problems with Traditional Approach Can tell which activities are crucial, but not directly which risks are driving Makes poor use of the Risk Register that is usually available Cannot decompose the overall schedule risk into its components BY RISK Ability to assign the risk to its specific risk drivers helps with communication of risk causes and risk mitigation 3

4 Risk Drivers: Start with the Risks Themselves Drive the schedule risk by the risks already analyzed in the Risk Register Root Causes For each risk, specify: Probability it will occur Impact on time if it does Activities it will affect Starting with the risks themselves gives us benefits Links qualitative analysis to the quantitative analysis Estimates the impact of specific risks for prioritized mitigation purposes Correlations between activities happen automatically never have to guess at these coefficients again, never get impossible matrices 4

5 Simple Example of Risk Register Risks Use the Risk Factors feature in Pertmaster 8.7 A few other simulation packages have this capability Collect probability and impact data on risks Load the risks Assign risks to schedule activities 5

6 Risk Factors Mechanics (1) The risk factor is assigned to one or several activities, affecting their durations by a multiplicative factor E.g., the factor may be.90 for optimistic, 1.0 for most likely and 1.25 for pessimistic These factors multiply the schedule durations of the activities to which they are assigned Risks can be assigned to one or more activities Activity durations can be influenced by one or more risks 6

7 Risk Factors Mechanics (2) Risk Factors are assigned a probability of occurring on any iteration. When the risk occurs, the factor used is chosen at random from the 3-point estimate and operates on all activities to which it is assigned When not occurring on an iteration the risk factor takes the value 1.0, a neutral value When an activity is influenced by more than one risk, their factors are multiplied together, if they happen, on any iteration if they are specified to be in series 7

8 Risk Factor Probability is 100%, Factor can be + or - Entire Plan : Duration 100% 115 Here the Ranges are based on deviations + and from the Plan. Probability is 100% Hits % % % % % % % % % % % % % 99 30% 99 Cumulative Frequency For the examples we use an activity with 100 days in the schedule % 98 20% 97 15% % 95 5% Distribution (start of interval) 0% 90 8

9 Assigning a Probability Less than 100% The essence of a risk is its uncertainty in two dimensions: Uncertainty of its occurrence, specified by a probability Uncertainty of its impact, specified by a range of durations If the risk may or may not occur, we specify the probability that it will occur The risk occurs and affects the activities it is assigned to on X% of the iterations, chosen at random, the multiplicative factor used is chosen at random from the range of data input by the user On (1 X)% of the iterations, Factor takes 1.0 value 9

10 Assigning a Probability Less than 100% Spike contains 40% of the probability Hits Entire Plan : Duration 100% % % % % % % % % % % % % % 100 Cumulative Frequency Hits Entire Plan : Duration 100% % % % % % % % % % % % % % 100 Cumulative Frequency Spike contains 70% of the probability % % % % % % % % % % 99 5% 100 5% Distribution (start of interval) 0% Distribution (start of interval) 0% 90 10

11 Assigning More than One Risk to an Activity If more than one risk is acting on an activity, the resulting ranges are the multiplication of the percentages This is reality an activity is often affected by multiple risks Two cases are shown next: When both risks are 100% likely to occur When both risks are < 100% likely to occur In each case, the computer simulation creates the uncertainty range on an activity s duration it is not estimated 11

12 Parallel and Series Risks Additive used with Risk Register Risk 1 20 days Risk 2 12 days 20 days for risk recovery If these two risks are parallel, they can be recovered simultaneously Risk 1 20 days Risk 2 12 days 32 days for risk recovery If these two risks are series, they can not be recovered simultaneously so the duration is longer 12

13 Parallel and Series Risks Multiplicative Used with Risk Drivers (RiskFactors) Risk factor Risk factor Use 1.2 Factor, the largest factor only If these two risks are parallel, they can be recovered simultaneously Risk factor Risk factor If these two risks are series, they can not be recovered simultaneously Use (1.2 x 1.05 = 1.26) Factor, multiply the two 13

14 Two Risks affect One Activity using Factors that Occur 100% - placed in Series Entire Plan : Duration 100% % % % % 123 Risks in series, P80 is 123 days Hits % % % % % % % % % 111 Cumulative Frequency 80 30% % % % % 104 5% Distribution (start of interval) 0% 92 14

15 Two Risks affect One Activity using Factors that Occur 100% - in Parallel Entire Plan : Duration 100% % % % % % % % 116 Risks in parallel, P80 is 119 days Hits % % % % % % % 110 Cumulative Frequency % % % % 106 5% Distribution (start of interval) 0%

16 Two Risks with Less than 100% Probability Affecting one Activity Risks in Series The spike at 100 days represents (1) the likelihood that neither risk occurs [60% x 50% = 30%] plus (2) the chance that 100 days is picked when one or both occur. Hits Entire Plan : Duration 100% % % % % % % % % % % % % % % % % % % 99 5% 96 Cumulative Frequency Distribution (start of interval) 0% 90 16

17 Two Risks with Less than 100% Probability Affecting one Activity Risks in Parallel With one risk s having a minimum range of 100%, it cannot be less than 100 days Hits Entire Plan : Duration 100% % % % % % % % % % % % % 100 Cumulative Frequency % % % % % % 100 5% Distribution (start of interval) 0%

18 Risk Factors Model How Correlation Occurs Coefficients are Calculated (1) Risk 1: Risk Probability =.5, Range.95, 1.05, 1.15 Activity 1 Activity 2 Correlation = 100% 18

19 Scatter showing 100% Correlation 19

20 Risk Factors Model How Correlation Occurs Coefficients are Calculated (2) Risk 3: Risk Probability =.25, Range.8,.95, 1.05 Risk 1: Risk Probability =.5, Range.95, 1.05, 1.15 Risk 2: Risk Probability =.45, Range 1.0, 1.10, 1.20 Activity 1 Activity 2 Correlation = 37% Correlation is modeled as it is caused in the project Correlation coefficients are generated, not guessed 20

21 Scatter showing 37% Correlation 21

22 Sensitivity to the Risk Factors Risk 1 is more important since it affects both Activity A and Activity B 22

23 Integrated Cost and Schedule Risk Analysis Risk Project Schedule Risk Schedule Risk Burn Rate per day Cost Risk Time Independent Costs Time-Dependent Costs Project Cost Risk 23

24 Use a Case Study to Illustrate the Integration of Cost and Schedule Risk Case Study is a simplified schedule of an off-shore gas production project including approval process, drilling, fabrication of the jacket and the topsides (modules), installation of same, and commissioning. Use Risk Drivers approach Results include: Schedule risk and cost risk histograms and cumulative distributions Prioritizing risks to time and to cost Scatter diagram of cost and time Probabilistic cash flow 24

25 How the Impact Ranges work on Different Resources to show Cost Risk (1) The resources are either time dependent or time independent Time Dependent resources such as labor and rented equipment (barges, tower cranes) vary according to: Schedule risk multiplied by the burn rate per day Burn rate is uncertain if the risk exhibits a range So time dependent resources costs vary: By the duration uncertainty even if the burn rate is fixed By the uncertain burn rate even if durations are fixed By both uncertain duration and uncertain burn rate, a cross-product 25

26 How the Impact Ranges work on Different Resources to show Cost Risk (2) Time-independent resources such as procured raw materials and equipment, perhaps some subcontracts The total estimated cost is varied by the range on a risk with its probability Time independent resources costs: May vary even if the duration of Fab and Deliver activities is fixed If they have no cost impact ranges they do not vary even if Fab and Deliver activities durations are variable 26

27 Offshore Gas Production: Integrating Schedule and Cost Risk Analysis 27

28 Resources and Cost Total Project = $1,473 million Resources are added to the activities PMT = Project Management Team Detail = Detailed Engineering PROC = Procurement FAB = Fabrication DRILL = Drilling INST = Installation HUC = Hook-Up and Commissioning We could have LOE costs such as PMT placed on a hammock in PRA 28

29 Inherent Variation and Duration Estimating Uncertainty The estimate is that durations are underestimated The range, on all activities, is 95% 105% - 115% of the estimated duration, indicating some bias in the assumptions and / or estimating Different activity types could have different reference ranges for their inherent variation Inherent variation is not susceptible to risk mitigation it is always with us and must be recognized 29

30 Schedule Risk with Inherent uncertainty Offshore Gas Production Project Entire Plan : Finish Date 100% 05 Aug % 05 Jul 16 90% 28 Jun % 23 Jun 16 Hits % 19 Jun 16 75% 15 Jun 16 70% 13 Jun 16 65% 10 Jun 16 60% 07 Jun 16 55% 04 Jun 16 50% 01 Jun 16 45% 30 May 16 40% 27 May 16 Cumulative Frequency Baseline schedule date is 20MAR16 P-80 is 19JUN % 25 May 16 30% 22 May % 19 May % 16 May % 12 May 16 10% 07 May % 29 Apr Apr Jun Aug 16 Distribution (start of interval) 0% 31 Mar 16 30

31 Cost Risk with Inherent Uncertainty Offshore Gas Production Project Entire Plan : Cost 100% $1,534, % $1,518, % $1,514, % $1,511, Hits % $1,509, % $1,507, % $1,506, % $1,504, % $1,503, % $1,501, % $1,500, % $1,498, % $1,497, Cumulative Frequency Baseline cost is $1,473 million Cost at the P-80 is $1,509 million 35% $1,496, % $1,494, % $1,492, % $1,491, % $1,488, % $1,486, % $1,482, $1,470, $1,480, $1,490, $1,500, $1,510, $1,520, $1,530, Distribution (start of interval) 0% $1,465,

32 Risk Drivers Used Schedule Impact Ranges Cost Impact Ranges Schedule Impact Ranges Cost Impact Ranges Risk Name Min Most Most Max Min Likely Likely Max Probability 1 Company's Engineers may vary in Experience 90% 110% 130% 95% 100% 110% 85% 2 MTO, Specs may not be ready for ITB 100% 105% 125% 100% 105% 110% 60% 3 May have trouble interfacing phases 100% 110% 120% 90% 105% 115% 40% 4 Subsea conditions may not be as expected 95% 100% 115% 95% 100% 110% 20% 5 LLE suppliers may be busy 80% 95% 110% 95% 105% 115% 20% 6 Quality engineers at Fabricators may be inexperienced 100% 100% 100% 100% 105% 110% 60% 7 Scope growth may be greater than expected 105% 110% 125% 100% 105% 110% 60% 8 HUC resources may not be as experienced as needed 100% 115% 130% 95% 105% 115% 20% These data are derived during in-depth interviews with project participants and others. The interviews focus on the Risk Register risks that are designated high risk for time and cost. Use Primavera risk Analysis Risk Factor capability 32

33 Assignment of Risk Drivers to Activities Risk Driver Market Costs for Bulks/Equipment Volatile Experienced HUC resources availability Activity Assignment DETAIL FAB PROC INSTAL HUC DRILL PMT APPROVAL X X X X X Company's Engineers' experience X X X X X X X X Schedule Maturity X X X X X X X MTO, Specifications may not be ready ITB X X X Problems interfacing Phases X X X X Cost Estimate inaccurate / immature X X X X X X X Fabricators and Suppliers may be busy X X Quality engineers may be FAB, Suppliers Scope Growth may be more than expected X X X X 33

34 Some Risks are Parallel and Some Series If several risks are assigned to any task we may put some in parallel (can be recovered simultaneously) and some in series (recovery will take all resources so cannot be recovered simultaneously with other risks) In this case, risks 6 and 7 have been placed in series 34

35 Schedule Risk Analysis Results Schedule Risk Analysis Date Results for First Gas Baseline Date 20-Mar-16 Risk Analysis Results P-5 P-50 P-80 P-95 2-Jul-16 4-Nov-16 6-Jan Mar-17 Months from Baseline Duration Results To First Gas Days Baseline Duration 1,906 Risk Analysis Results P-5 P-50 P-80 P-95 2,010 2,135 2,198 2,265 Percentage from Baseline 5% 12% 15% 19% 35

36 Risks and Inherent Uncertainty Completion Date First Gas First Gas Baseline Date = 20MAR Offshore Gas Production Project First Gas : Finish Date 100% 19 Jul 17 95% 14 Mar 17 90% 14 Feb 17 85% 22 Jan 17 80% 06 Jan 17 Date with Inherent uncertainty was 19JUN16 P-80 with all risks added is 6Jan months Hits % 24 Dec 16 70% 11 Dec 16 65% 30 Nov 16 60% 20 Nov 16 55% 13 Nov 16 50% 04 Nov 16 45% 26 Oct 16 40% 17 Oct 16 35% 08 Oct 16 30% 29 Sep 16 25% 18 Sep 16 20% 06 Sep 16 15% 22 Aug 16 10% 31 Jul 16 Cumulative Frequency 5% 02 Jul Apr Aug Nov Feb Jun 17 Distribution (start of interval) 0% 22 Apr 16 36

37 Risks and Inherent Uncertainty Schedule Duration to First Gas Baseline Duration to First Gas = 1,020 days Offshore Gas Production Project Entire Plan : Duration 100% % % % % % % % 2161 Hits % % % % % 2117 Cumulative Frequency 35% % % % % % % Distribution (start of interval) 0%

38 Prioritize Risks that Cause Schedule Contingency to the P-80 All Risks In Specific Risks Taken Out in Order Explain the Schedule Contingency to the P-80 P-80 Date Take Risks Out: 6-Jan-17 Days Saved % of Contingency Company's engineers may vary in experience 14-Nov % MTO, Specs may not be ready for the ITB 5-Oct % Scope growth may be more than expected 1-Jul % May have problems interfacing phases 24-Jun % HUC resources may not be experienced 19-Jun % Uncertainty Duration Estimating 20-Mar % Total Contingency % The order of risks is the best order at each step in this table. However, because of the schedule s structure some Days Saved values show inversion. 38

39 Picture of Taking Risks out in Priority Order 100% 90% Variation:91 Variation:5 Variation:7 Variation:96 Variation:40 Variation:51 80% 70% 60% 50% 40% Cumulative Probability 30% Variation:58 Variation:3 Variation:5 Variation:19 Variation:35 Variation:50 20% 10% 0% Mar May Jun Aug Oct Nov Jan Mar Apr Jun 17 39

40 Summary Cost Risk Analysis Results Cost Risk Analysis Total Project $ millions Baseline Cost 1,473 P-5 P-50 P-80 P-95 Risk Analysis Results 1,541 1,667 1,736 1,808 Dollars from Baseline Percent from Baseline 5% 13% 18% 23% 40

41 Where is the Cost Risk by Resource Cost Contingency Breakdown by Resource $ millions Resource Baseline P-80 % Contingency Project Management Team % Engineering % Installation % Fabrication % Hook Up & Commissioning % Procurement % Drilling % TOTAL PROJECT 1, % Cost Contingency Breakdown by Type of Resource $ millions Type Baseline P-80 % Contingency Materials (Equipment, raw materials) % Labor (including rented equipment) % 41

42 Risks and Inherent Uncertainty Cost Risk Analysis Results Baseline Cost $1,473 million 400 Offshore Gas Production Project Entire Plan : Cost 100% $1,945, % $1,808, % $1,776, % $1,752, With inherent uncertainty P-80 is $1,509 million Adding Risk Drivers P-80 Cost $1,736 million 18% contingency Hits % $1,735, % $1,719, % $1,707, % $1,695, % $1,685, % $1,676, % $1,666, % $1,655, % $1,645, % $1,635, % $1,624, % $1,612, Cumulative Frequency 20% $1,599, % $1,585, % $1,567, % $1,541, $1,500, $1,600, $1,700, $1,800, $1,900, Distribution (start of interval) 0% $1,449,

43 Analysis of the Sources of Cost Contingency Source of Cost Contingency at the P-80 Total Cost Contingency Total Cost All-Risks 1,736 Baseline Cost 1, Contribution to Contingency Take Out all Schedule Risks 1, Take Out all Cost Risks 1, Interaction of Cost/Schedule Risks 2 Total Contingency % of the risk to cost comes from risk to schedule, common finding 43

44 Priority Risks to Cost Measured at P-80 Prioritize Risks to Cost at the P-80 $ millions Total Project, All Risks 1,736 Baseline cost 1,473 Take Out Risk Events one at a time: $ millions saved % of total contingency Scope Growth may be more than expected 1, % Company's Engineers' may be inexperienced 1, % MTO, Specifications may not be ready ITB 1, % Quality engineers may be FAB, Suppliers 1, % Problems interfacing Phases 1, % LLE Suppliers may be busy 1, % Experienced HUC resources availability 1, % Subsea conditions may not be as expected 1, % Take out the 3-point estimates Schedule duration estimate are uncertain 1, % % 44

45 Graphical Effect of Taking the Risks out One at a Time in Priority Order 100% 90% Variation:$36, Variation:$1, Variation:$2, Variation:$5, Variation:$6, Variation:$24, Variation:$73, Variation:$54, Variation:$57, % 70% 60% 50% 40% Cumulative Probability 30% Variation:$17, Variation:$1, Variation:$ Variation:$1, Variation:$3, Variation:$9, Variation:$19, Variation:$33, Variation:$39, % 10% $1,500, $1,550, $1,600, $1,650, $1,700, $1,750, $1,800, $1,850, $1,900, % 45

46 In this case study Cost and Schedule are Correlated 51% Offshore Gas Production Project Deterministic Point Inside both limits Outside both limits 11% 7% 82% $1,900, $1,850, $1,800, Entire Plan: Cost $1,750, $1,741, $1,700, $1,650, % $1,600, PLAN $1,550, $1,500, % $1,450, Jan Apr Jun Aug Sep Nov Jan Feb Apr Jun 17 Entire Plan: Finish 11% 70% of the risk is in lower-left quadrant 46

47 Probabilistic Cash Flow Resource Flow for Cost Filter: Entire Plan Scheduled P80 2,000,000 1,800,000 1,600,000 terministic Cost: $1,473, Deterministic Finish: 20 Mar 16 1,400,000 1,200,000 1,000, , , ,000 Cumulative Cumulative Monthly Cash Flow - P-80 - Planned 200, Jan Apr Aug Nov Feb May Sep Dec Mar Jul Oct Jan Apr Aug Nov Feb Jun 17 Time 0 47

48 Analysis of a Risk Mitigation Scenario Risk Mitigation Scenario Schedule Impact Cost Impact First Probabi Most Most Gas Low High Low High lity Likely Likely Date Risk to be Mitigated Company's Engineers may be inexperienced Proposed Mitigation: Increase Salaries for company Engineers to competitive levels Company's Engineers may be inexperienced Spending $35 million for Engineers salary is assessed to reduce the probability of this risk from 85% to 20%. Because the schedule slippage is 53 days less than before, there is $21 million we do not need to reserve and so the net cost impact of the mitigation at the P-80 is offset by $21 million, for a net cost of $14 million. Before Mitigation 85% 90% 110% 130% 95% 100% 110% After Mitigation 6-Jan % 90% 100% 110% Nov- 16 Project Cost ($ million) Improvement Cost of proposed Mitigation 35 Net Improvement from Mitigation ,735 1,714 48

49 NASA Joint Confidence Level (JCL) defined For implementation of each major program segment, all space flight and information technology programs are to be baselined or rebaselined and budgeted in accordance with the following: a) There is a 70 percent probability (or a different probability that is approved by the decision authority) of achieving the stated life cycle cost and launch schedule b) Projects are to be baselined or rebaselined and budgeted at confidence level consistent with the program s confidence level 49

50 JCL is determined by the joint distribution of cost and schedule Integrated cost-schedule simulation is a perfect tool since it provides a scatter diagram of time and cost pairs that are consistent scenarios given the plan and the risks Find points where time and cost are jointly satisfied at P-70 50

51 JCL Results are on Indicated Contour Line 79% $58,000,000 9% 12% $56,000,000 $54,000,000 Joint time-cost probability = 70% $52,000,000 $50,000,000 Entire Plan: Cost $48,000,000 $46,000,000 $44,000,000 $42,000,000 $46,103,883 79% $40,000,000 $38,000,000 $36,000,000 $34,000,000 $32,000,000 70% 04 Jan 13 9% 02 Aug Sep Nov Dec Feb Apr May 13 Entire Plan: Finish Time Cost correlation is 69% 51

52 THANK YOU! 52

53 Integrated Cost Schedule Risk Analysis Using the Risk Driver Approach Qatar PMI Meeting February 19, 2014 David T. Hulett, Ph.D. Hulett & Associates, LLC 53

Integrated Cost Schedule Risk Analysis Using the Risk Driver Approach

Integrated Cost Schedule Risk Analysis Using the Risk Driver Approach Integrated Cost Schedule Risk Analysis Using the Risk Driver Approach David T. Hulett, Ph.D. Hulett & Associates 24rd Annual International IPM Conference Bethesda, Maryland 29 31 October 2012 (C) 2012

More information

Use of the Risk Driver Method in Monte Carlo Simulation of a Project Schedule

Use of the Risk Driver Method in Monte Carlo Simulation of a Project Schedule Use of the Risk Driver Method in Monte Carlo Simulation of a Project Schedule Presented to the 2013 ICEAA Professional Development & Training Workshop June 18-21, 2013 David T. Hulett, Ph.D. Hulett & Associates,

More information

(RISK.03) Integrated Cost and Schedule Risk Analysis: A Draft AACE Recommended Practice. Dr. David T. Hulett

(RISK.03) Integrated Cost and Schedule Risk Analysis: A Draft AACE Recommended Practice. Dr. David T. Hulett (RISK.03) Integrated Cost and Schedule Risk Analysis: A Draft AACE Recommended Practice Dr. David T. Hulett Author Biography David T. Hulett, Hulett & Associates, LLC Degree: Ph.D. University: Stanford

More information

Integrated Cost-Schedule Risk Analysis Improves Cost Contingency Calculation ICEAA 2017 Workshop Portland OR June 6 9, 2017

Integrated Cost-Schedule Risk Analysis Improves Cost Contingency Calculation ICEAA 2017 Workshop Portland OR June 6 9, 2017 Integrated Cost-Schedule Risk Analysis Improves Cost Contingency Calculation ICEAA 2017 Workshop Portland OR June 6 9, 2017 David T. Hulett, Ph.D., FAACE Hulett & Associates, LLC David.hulett@projectrisk

More information

David T. Hulett, Ph.D, Hulett & Associates, LLC # Michael R. Nosbisch, CCC, PSP, Project Time & Cost, Inc. # 28568

David T. Hulett, Ph.D, Hulett & Associates, LLC # Michael R. Nosbisch, CCC, PSP, Project Time & Cost, Inc. # 28568 David T. Hulett, Ph.D, Hulett & Associates, LLC # 27809 Michael R. Nosbisch, CCC, PSP, Project Time & Cost, Inc. # 28568 Integrated Cost-Schedule Risk Analysis 1 February 25, 2012 1 Based on AACE International

More information

THE JOURNAL OF AACE INTERNATIONAL - THE AUTHORITY FOR TOTAL COST MANAGEMENT TM

THE JOURNAL OF AACE INTERNATIONAL - THE AUTHORITY FOR TOTAL COST MANAGEMENT TM COST THE JOURNAL OF AACE INTERNATIONAL - THE AUTHORITY FOR TOTAL COST MANAGEMENT TM November/December 2012 ENGINEERING www.aacei.org INTEGRATED COST-SCHEDULE RISK ANALYSIS ESTIMATE ACCURACY: DEALING WITH

More information

Project Cost Risk Analysis: The Risk Driver Approach Prioritizing Project Risks and Evaluating Risk Responses

Project Cost Risk Analysis: The Risk Driver Approach Prioritizing Project Risks and Evaluating Risk Responses Project Cost Risk Analysis: The Risk Driver Approach Prioritizing Project Risks and Evaluating Risk Responses David T. Hulett, Ph.D. Keith Hornbacher, MBA Waylon T. Whitehead Hulett & Associates, LLC Los

More information

Making sense of Schedule Risk Analysis

Making sense of Schedule Risk Analysis Making sense of Schedule Risk Analysis John Owen Barbecana Inc. Version 2 December 19, 2014 John Owen - jowen@barbecana.com 2 5 Years managing project controls software in the Oil and Gas industry 28 years

More information

ADVANCED QUANTITATIVE SCHEDULE RISK ANALYSIS

ADVANCED QUANTITATIVE SCHEDULE RISK ANALYSIS ADVANCED QUANTITATIVE SCHEDULE RISK ANALYSIS DAVID T. HULETT, PH.D. 1 HULETT & ASSOCIATES, LLC 1. INTRODUCTION Quantitative schedule risk analysis is becoming acknowledged by many project-oriented organizations

More information

Schedule Risk Analysis Simplified 1

Schedule Risk Analysis Simplified 1 WHITE PAPER Schedule Risk Analysis Simplified 1 by David T. Hulett, Ph. D. Table of Contents Critical Path Method Scheduling - Some Important Reservations...1 Three Steps to a Successful Schedule Risk

More information

Project Risk Management

Project Risk Management Project Risk Management Introduction Unit 1 Unit 2 Unit 3 PMP Exam Preparation Project Integration Management Project Scope Management Project Time Management Unit 4 Unit 5 Unit 6 Unit 7 Project Cost Management

More information

Fundamentals of Project Risk Management

Fundamentals of Project Risk Management Fundamentals of Project Risk Management Introduction Change is a reality of projects and their environment. Uncertainty and Risk are two elements of the changing environment and due to their impact on

More information

Understanding the Results of an Integrated Cost/Schedule Risk Analysis James Johnson, NASA HQ Darren Elliott, Tecolote Research Inc.

Understanding the Results of an Integrated Cost/Schedule Risk Analysis James Johnson, NASA HQ Darren Elliott, Tecolote Research Inc. Understanding the Results of an Integrated Cost/Schedule Risk Analysis James Johnson, NASA HQ Darren Elliott, Tecolote Research Inc. 1 Abstract The recent rise of integrated risk analyses methods has created

More information

NTEGRATEDCOSTANDSCHEDULE

NTEGRATEDCOSTANDSCHEDULE E 57R09 SA M PL I NTEGRATEDCOSTANDSCHEDULE RI SKANAL YSI SUSI NGMONTE CARLOSI MULATI ONOFACPM MODEL AACE International Recommended Practice No. 57R-09 INTEGRATED COST AND SCHEDULE RISK ANALYSIS USING MONTE

More information

PROJECT RISK MANAGEMENT: CONTEXT, TOOLS AND REAL WORLD APPLICATIONS. Mairav Mintz, PE, CCM Sagar Khadka, DRMP, FAACE

PROJECT RISK MANAGEMENT: CONTEXT, TOOLS AND REAL WORLD APPLICATIONS. Mairav Mintz, PE, CCM Sagar Khadka, DRMP, FAACE PROJECT RISK MANAGEMENT: CONTEXT, TOOLS AND REAL WORLD http://pmsymposium.umd.edu 1 APPLICATIONS Mairav Mintz, PE, CCM Sagar Khadka, DRMP, FAACE 2018 Project Management Symposium Friday, May 11, 2018 9:45am

More information

// Measuring Risk Exposure through Risk Range Certainty (RRC) Overcoming the Shortcomings of Schedule Confidence Levels

// Measuring Risk Exposure through Risk Range Certainty (RRC) Overcoming the Shortcomings of Schedule Confidence Levels // Measuring Risk Exposure through Risk Range Certainty (RRC) Overcoming the Shortcomings of Schedule Confidence Levels Dr. Dan Patterson, PMP CEO & President, Acumen October 2009 www.projectacumen.com

More information

Risk Video #1. Video 1 Recap

Risk Video #1. Video 1 Recap Risk Video #1 Video 1 Recap 1 Risk Video #2 Video 2 Recap 2 Risk Video #3 Risk Risk Management Process Uncertain or chance events that planning can not overcome or control. Risk Management A proactive

More information

Re-engineering Project Budgeting and Management of Risk

Re-engineering Project Budgeting and Management of Risk Re-engineering Project Budgeting and Management of Risk Session 9: Risk Management Colin Cropley Managing Director, Risk Integration Management Pty Ltd Milan 20, 21 and 22 October 2014 Re-Engineering Total

More information

The First Steps in Implementing a Simplified Earned Value Management System

The First Steps in Implementing a Simplified Earned Value Management System 2007 Joint ISPA/SCEA National Conference & Workshop June 12-15, 2007 The First Steps in Implementing a Simplified Earned Value Management System Dorothy Tiffany, CPA, PMP NASA/GSFC EVM System Interface

More information

Manager Comparison Report June 28, Report Created on: July 25, 2013

Manager Comparison Report June 28, Report Created on: July 25, 2013 Manager Comparison Report June 28, 213 Report Created on: July 25, 213 Page 1 of 14 Performance Evaluation Manager Performance Growth of $1 Cumulative Performance & Monthly s 3748 3578 348 3238 368 2898

More information

After complete studying this chapter, You should be able to

After complete studying this chapter, You should be able to Chapter 10 Project Management Ch10: What Is Project Management? After complete studying this chapter, You should be able to Define key terms like Project, Project Management, Discuss the main characteristics

More information

Project Assessment Exercise

Project Assessment Exercise Project Assessment Exercise www.spmbook.com We have been assigned the task of assessing the project status of a project, whose Gantt chart is presented in Illustration 1, where: 1. we are currently at

More information

MINI GUIDE. Project risk analysis and management

MINI GUIDE. Project risk analysis and management MINI GUIDE Project risk analysis and management Association for Project Management January 2018 Contents Page 3 Introduction What is PRAM? Page 4 Page 7 Page 9 What is involved? Why is it used? When should

More information

What are the Essential Features of a Good Economic Scenario Generator? AFIR Munich September 11, 2009

What are the Essential Features of a Good Economic Scenario Generator? AFIR Munich September 11, 2009 What are the Essential Features of a Good Economic Scenario Generator? Hal Pedersen (University of Manitoba) with Joe Fairchild (University of Kansas), Chris K. Madsen (AEGON N.V.), Richard Urbach (DFA

More information

XML Publisher Balance Sheet Vision Operations (USA) Feb-02

XML Publisher Balance Sheet Vision Operations (USA) Feb-02 Page:1 Apr-01 May-01 Jun-01 Jul-01 ASSETS Current Assets Cash and Short Term Investments 15,862,304 51,998,607 9,198,226 Accounts Receivable - Net of Allowance 2,560,786

More information

The Not-So-Geeky World of Statistics

The Not-So-Geeky World of Statistics FEBRUARY 3 5, 2015 / THE HILTON NEW YORK The Not-So-Geeky World of Statistics Chris Emerson Chris Sweet (a/k/a Chris 2 ) 2 Who We Are Chris Sweet JPMorgan Chase VP, Outside Counsel & Engagement Management

More information

STOCHASTIC COST ESTIMATION AND RISK ANALYSIS IN MANAGING SOFTWARE PROJECTS

STOCHASTIC COST ESTIMATION AND RISK ANALYSIS IN MANAGING SOFTWARE PROJECTS STOCHASTIC COST ESTIMATION AND RISK ANALYSIS IN MANAGING SOFTWARE PROJECTS Dr A.M. Connor Software Engineering Research Lab Auckland University of Technology Auckland, New Zealand andrew.connor@aut.ac.nz

More information

AACE International 48th Annual Meeting Washington, DC June 2004 DEVELOPING & MANAGING CONTIGENCY ON THE BASIS OF RISK. Robert Tichacek, P.E.

AACE International 48th Annual Meeting Washington, DC June 2004 DEVELOPING & MANAGING CONTIGENCY ON THE BASIS OF RISK. Robert Tichacek, P.E. AACE International 48th Annual Meeting Washington, DC June 2004 DEVELOPING & MANAGING CONTIGENCY ON THE BASIS OF RISK Robert Tichacek, P.E. Presentation Outline Review of Basic Project Risk Management

More information

Cost Estimation of a Manufacturing Company

Cost Estimation of a Manufacturing Company Cost Estimation of a Manufacturing Company Name: Business: Date: Economics of One Unit: Manufacturing Company (Only complete if you are making a product, such as a bracelet or beauty product) Economics

More information

RISK MANAGEMENT. Budgeting, d) Timing, e) Risk Categories,(RBS) f) 4. EEF. Definitions of risk probability and impact, g) 5. OPA

RISK MANAGEMENT. Budgeting, d) Timing, e) Risk Categories,(RBS) f) 4. EEF. Definitions of risk probability and impact, g) 5. OPA RISK MANAGEMENT 11.1 Plan Risk Management: The process of DEFINING HOW to conduct risk management activities for a project. In Plan Risk Management, the remaining FIVE risk management processes are PLANNED

More information

Review of Registered Charites Compliance Rates with Annual Reporting Requirements 2016

Review of Registered Charites Compliance Rates with Annual Reporting Requirements 2016 Review of Registered Charites Compliance Rates with Annual Reporting Requirements 2016 October 2017 The Charities Regulator, in accordance with the provisions of section 14 of the Charities Act 2009, carried

More information

SmallBizU WORKSHEET 1: REQUIRED START-UP FUNDS. Online elearning Classroom. Item Required Amount ($) Fixed Assets. 1 -Buildings $ 2 -Land $

SmallBizU WORKSHEET 1: REQUIRED START-UP FUNDS. Online elearning Classroom. Item Required Amount ($) Fixed Assets. 1 -Buildings $ 2 -Land $ WORKSHEET 1: REQUIRED START-UP FUNDS Item Required Amount () Fixed Assets 1 -Buildings 2 -Land 3 -Initial Inventory 4 -Equipment 5 -Furniture and Fixtures 6 -Vehicles 7 Total Fixed Assets Working Capital

More information

Security Analysis: Performance

Security Analysis: Performance Security Analysis: Performance Independent Variable: 1 Yr. Mean ROR: 8.72% STD: 16.76% Time Horizon: 2/1993-6/2003 Holding Period: 12 months Risk-free ROR: 1.53% Ticker Name Beta Alpha Correlation Sharpe

More information

Factor Leave Accruals. Accruing Vacation and Sick Leave

Factor Leave Accruals. Accruing Vacation and Sick Leave Factor Leave Accruals Accruing Vacation and Sick Leave Factor Leave Accruals As part of the transition of non-exempt employees to biweekly pay, the UC Office of the President also requires standardization

More information

Balance-of-Period TCC Auction

Balance-of-Period TCC Auction Balance-of-Period TCC Auction Proposed Credit Policy Sheri Prevratil Manager, Corporate Credit New York Independent System Operator Credit Policy Working Group May 29, 2015 2000-2015 New York Independent

More information

Exam 1 Problem Solving Questions Review

Exam 1 Problem Solving Questions Review Exam 1 Problem Solving Questions Review SECTION 1 The following data were obtained from a recent quarterly report for Dell Computer (in millions): Net revenue $8,028 Cost of revenue $6,580 Inventories:

More information

Leading Economic Indicator Nebraska

Leading Economic Indicator Nebraska Nebraska Monthly Economic Indicators: December 20, 2017 Prepared by the UNL College of Business Administration, Bureau of Business Research Author: Dr. Eric Thompson Leading Economic Indicator...1 Coincident

More information

Figure 1: Change in LEI-N August 2018

Figure 1: Change in LEI-N August 2018 Nebraska Monthly Economic Indicators: September 26, 2018 Prepared by the UNL College of Business, Bureau of Business Research Author: Dr. Eric Thompson Leading Economic Indicator...1 Coincident Economic

More information

Spheria Australian Smaller Companies Fund

Spheria Australian Smaller Companies Fund 29-Jun-18 $ 2.7686 $ 2.7603 $ 2.7520 28-Jun-18 $ 2.7764 $ 2.7681 $ 2.7598 27-Jun-18 $ 2.7804 $ 2.7721 $ 2.7638 26-Jun-18 $ 2.7857 $ 2.7774 $ 2.7690 25-Jun-18 $ 2.7931 $ 2.7848 $ 2.7764 22-Jun-18 $ 2.7771

More information

Chapter-8 Risk Management

Chapter-8 Risk Management Chapter-8 Risk Management 8.1 Concept of Risk Management Risk management is a proactive process that focuses on identifying risk events and developing strategies to respond and control risks. It is not

More information

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc.

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. For the PMP Exam using PMBOK Guide 5 th Edition PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. 1 Contacts Name: Khaled El-Nakib, MSc, PMP, PMI-RMP URL: http://www.khaledelnakib.com

More information

OTHER DEPOSITS FINANCIAL INSTITUTIONS DEPOSIT BARKAT SAVING ACCOUNT

OTHER DEPOSITS FINANCIAL INSTITUTIONS DEPOSIT BARKAT SAVING ACCOUNT WEIGHTAGES JAN FEB MAR APR MAY JUN JUL AUG SEPT OCT NOV DEC ANNOUNCEMENT DATE 19.Dez.14 27.Jän.15 24.Feb.15 26.Mär.15 27.Apr.15 26.Mai.15 25.Jun.15 28.Jul.15 26.Aug.15 23.Sep.15 27.Okt.15 25.Nov.15 MUDARIB

More information

HUD NSP-1 Reporting Apr 2010 Grantee Report - New Mexico State Program

HUD NSP-1 Reporting Apr 2010 Grantee Report - New Mexico State Program HUD NSP-1 Reporting Apr 2010 Grantee Report - State Program State Program NSP-1 Grant Amount is $19,600,000 $9,355,381 (47.7%) has been committed $4,010,874 (20.5%) has been expended Grant Number HUD Region

More information

Unit 9: Risk Management (PMBOK Guide, Chapter 11)

Unit 9: Risk Management (PMBOK Guide, Chapter 11) (PMBOK Guide, Chapter 11) Some exam takers may be unfamiliar with the basic concepts of probability, expected monetary value, and decision trees. This unit will review all these concepts so that you should

More information

Full Monte. Looking at your project through rose-colored glasses? Let s get real.

Full Monte. Looking at your project through rose-colored glasses? Let s get real. Realistic plans for project success. Looking at your project through rose-colored glasses? Let s get real. Full Monte Cost and schedule risk analysis add-in for Microsoft Project that graphically displays

More information

Business & Financial Services December 2017

Business & Financial Services December 2017 Business & Financial Services December 217 Completed Procurement Transactions by Month 2 4 175 15 125 1 75 5 2 1 Business Days to Complete 25 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 217 Procurement

More information

FDD FIRM STORAGE SERVICE NORTHERN NATURAL GAS COMPANY

FDD FIRM STORAGE SERVICE NORTHERN NATURAL GAS COMPANY FDD FIRM STORAGE SERVICE NORTHERN NATURAL GAS COMPANY FIRM STORAGE SERVICE OPTIONS Northern s firm storage service is provided pursuant to the FDD Rate Schedule located in Northern s FERC Gas Tariff. The

More information

Pandemics, Catastrophic Trends and Capital Issues

Pandemics, Catastrophic Trends and Capital Issues Pandemics, Catastrophic Trends and Capital Issues John P. Cookson, F.S.A. Milliman, Inc. -0- Tail Risk Pandemic is the prime example Other risks could combine to reach this level Pandemic combines with

More information

Financial & Business Highlights For the Year Ended June 30, 2017

Financial & Business Highlights For the Year Ended June 30, 2017 Financial & Business Highlights For the Year Ended June, 17 17 16 15 14 13 12 Profit and Loss Account Operating Revenue 858 590 648 415 172 174 Investment gains net 5 162 909 825 322 516 Other 262 146

More information

Ho Ho Quantitative Portfolio Manager, CalPERS

Ho Ho Quantitative Portfolio Manager, CalPERS Portfolio Construction and Risk Management under Non-Normality Fiduciary Investors Symposium, Beijing - China October 23 rd 26 th, 2011 Ho Ho Quantitative Portfolio Manager, CalPERS The views expressed

More information

Leading Economic Indicator Nebraska

Leading Economic Indicator Nebraska Nebraska Monthly Economic Indicators: July 24, 2015 Prepared by the UNL College of Business Administration, Department of Economics Authors: Dr. Eric Thompson, Dr. William Walstad Leading Economic Indicator...1

More information

Performance risk evaluation of long term infrastructure projects (PPP-BOT projects) using probabilistic methods

Performance risk evaluation of long term infrastructure projects (PPP-BOT projects) using probabilistic methods EPPM, Singapore, 20-21 Sep 2011 Performance risk evaluation of long term infrastructure projects (PPP-BOT projects) using probabilistic Meghdad Attarzadeh 1 and David K H Chua 2 Abstract Estimation and

More information

FOR RELEASE: MONDAY, MARCH 21 AT 4 PM

FOR RELEASE: MONDAY, MARCH 21 AT 4 PM Interviews with 1,012 adult Americans conducted by telephone by Opinion Research Corporation on March 18-20, 2011. The margin of sampling error for results based on the total sample is plus or minus 3

More information

1: Product Profitability Analysis - Exercise

1: Product Profitability Analysis - Exercise 1: Product Profitability Analysis - Exercise PRODUCT TOTAL Filter Bolt Drum PRICE ( ) 12 6 15 COST ( ) 8 3 12 ANNUAL SALES ( ) 1,440k 1,800k 2,500k 5,740k AVERAGE STOCK ( ) 210k 850k 240k 1,300k 1 Typical

More information

Beginning Date: January 2016 End Date: June Managers in Zephyr: Benchmark: Morningstar Short-Term Bond

Beginning Date: January 2016 End Date: June Managers in Zephyr: Benchmark: Morningstar Short-Term Bond Beginning Date: January 2016 End Date: June 2018 Managers in Zephyr: Benchmark: Manager Performance January 2016 - June 2018 (Single Computation) 11200 11000 10800 10600 10400 10200 10000 9800 Dec 2015

More information

STOCHASTIC COST ESTIMATION AND RISK ANALYSIS IN MANAGING SOFTWARE PROJECTS

STOCHASTIC COST ESTIMATION AND RISK ANALYSIS IN MANAGING SOFTWARE PROJECTS Full citation: Connor, A.M., & MacDonell, S.G. (25) Stochastic cost estimation and risk analysis in managing software projects, in Proceedings of the ISCA 14th International Conference on Intelligent and

More information

Beginning Date: January 2016 End Date: September Managers in Zephyr: Benchmark: Morningstar Short-Term Bond

Beginning Date: January 2016 End Date: September Managers in Zephyr: Benchmark: Morningstar Short-Term Bond Beginning Date: January 2016 End Date: September 2018 Managers in Zephyr: Benchmark: Manager Performance January 2016 - September 2018 (Single Computation) 11400 - Yorktown Funds 11200 11000 10800 10600

More information

BAE Systems SCAF Presentation June BAE SYSTEMS 2013, all rights reserved Unclassified 31/07/2013 1

BAE Systems SCAF Presentation June BAE SYSTEMS 2013, all rights reserved Unclassified 31/07/2013 1 BAE Systems SCAF Presentation June 2013 BAE SYSTEMS 2013, all rights reserved Unclassified 31/07/2013 1 Agenda An Alternative Approach to Cost and Schedule Integration BAE Systems Commercial Estimating

More information

Energy Yield Reconciliation in Monthly O&M Reports

Energy Yield Reconciliation in Monthly O&M Reports Energy Yield Reconciliation in Monthly O&M Reports Claire Puttock, Lee Cameron & Alex Clerc April 15, 2016 EWEA Technology Workshop, Bilbao Contents Introduction to variance explanation Motivation Key

More information

Review of Membership Developments

Review of Membership Developments RIPE Network Coordination Centre Review of Membership Developments 7 October 2009/ GM / Lisbon http://www.ripe.net 1 Applications development RIPE Network Coordination Centre 140 120 100 80 60 2007 2008

More information

A Comparative Assessment of the PERT vs Monte Carlo simulation for. Schedule Risk Assessment

A Comparative Assessment of the PERT vs Monte Carlo simulation for. Schedule Risk Assessment A Comparative Assessment of the PERT vs Monte Carlo simulation for Schedule Risk Assessment Abstract... 2 Introduction... 3 Methods... 6 Case 1: Schedule With an Insensitive Critical Path... 7 PERT Results

More information

CS/Tremont Hedge Fund Index Performance Review

CS/Tremont Hedge Fund Index Performance Review In fact, the S&P500 volatility 1 on average was 2.58x that of the HFI s. Using over fifteen years of data, we found that S&P500 s volatility to be on average 2.5x that of the HFI s. II. ANALYSIS The Beryl

More information

Contract Certainty Subscription Market Progress Update for FSA

Contract Certainty Subscription Market Progress Update for FSA Programme Office Contract Certainty Subscription Market Progress Update for FSA 19th September 2006 Dane Douetil, Chair Market Reform Group The Market is making progress in line with expectations 100%

More information

PROJECT MANAGEMENT: PERT AMAT 167

PROJECT MANAGEMENT: PERT AMAT 167 PROJECT MANAGEMENT: PERT AMAT 167 PROBABILISTIC TIME ESTIMATES We need three time estimates for each activity: Optimistic time (t o ): length of time required under optimum conditions; Most likely time

More information

Project Management Certificate Program

Project Management Certificate Program Project Management Certificate Program Risk Management Terry Skaggs ( Denver class) skaggst@centurytel.net 719-783-0880 Lee Varra-Nelson (Fort Collins class) lvarranelson@q.com 970-407-9744 or 970-215-4949

More information

Managing Project Risk DHY

Managing Project Risk DHY Managing Project Risk DHY01 0407 Copyright ESI International April 2007 All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted, in any form or

More information

Affordability Assessments to Support Strategic Planning and Decisions at NASA

Affordability Assessments to Support Strategic Planning and Decisions at NASA Affordability Assessments to Support Strategic Planning and Decisions at NASA Debra Emmons 1 Marcus Lobbia 2 Torrey Radcliffe 2 Robert Bitten 1 1 Civil and Commercial Operations 2 7 March 21 The Aerospace

More information

Energy Price Processes

Energy Price Processes Energy Processes Used for Derivatives Pricing & Risk Management In this first of three articles, we will describe the most commonly used process, Geometric Brownian Motion, and in the second and third

More information

The Cost Monitoring of Construction Projects Through Earned Value Analysis

The Cost Monitoring of Construction Projects Through Earned Value Analysis 211 International Conference on Economics and Finance Research IPEDR vol.4 (211) (211) IACSIT Press, Singapore The Cost Monitoring of Construction Projects Through Earned Value Analysis Mohd Faris Khamidi

More information

LCS International, Inc. PMP Review. Chapter 6 Risk Planning. Presented by David J. Lanners, MBA, PMP

LCS International, Inc. PMP Review. Chapter 6 Risk Planning. Presented by David J. Lanners, MBA, PMP PMP Review Chapter 6 Risk Planning Presented by David J. Lanners, MBA, PMP These slides are intended to be used only in settings where each viewer has an original copy of the Sybex PMP Study Guide book.

More information

Risk Management: World s Shortest Tutorial

Risk Management: World s Shortest Tutorial Risk Management: World s Shortest Tutorial Neumann Computer Society of Budapest: June 8, 2004 Copyright 2004 by Tom DeMarco: The Atlantic Systems Guild RISK MANAGEMENT... nothing but the beef: three reasons

More information

Understanding the Principles of Investment Planning Stochastic Modelling/Tactical & Strategic Asset Allocation

Understanding the Principles of Investment Planning Stochastic Modelling/Tactical & Strategic Asset Allocation Understanding the Principles of Investment Planning Stochastic Modelling/Tactical & Strategic Asset Allocation John Thompson, Vice President & Portfolio Manager London, 11 May 2011 What is Diversification

More information

Affordable Care Act Implementation Alert

Affordable Care Act Implementation Alert CONTENTS > What is the PCORI Fee? What is the purpose of the PCORI fee? > What are the reporting and payment requirements? > How is the PCORI fee calculated? > What is the role of AmeriHealth Administrators?

More information

Rent vs. Own Analysis

Rent vs. Own Analysis Rent vs. Own Analysis Initial Assumptions After-tax rate of return on investments Marginal Federal tax rate Estimated annual appreciation of home Estimated purchase price of home 5% Down payment on home

More information

1Q of FY ending December 31, (0.2) (1.9) 11.3 (0.2) (0.2) (0.2) (0.2) (1.2) (89.2) 0.1

1Q of FY ending December 31, (0.2) (1.9) 11.3 (0.2) (0.2) (0.2) (0.2) (1.2) (89.2) 0.1 August 6, ISEKI & CO., LTD. Supplementary Information to Consolidated Financial Results (April 1, June 30, ) I. Consolidated business results for the three months ended June 30, (Billions of yen, %) Year-on

More information

Using projections to manage your programs

Using projections to manage your programs Using projections to manage your programs To project total provider reimbursements To do what ifs based on caseloads or other metrics To project amounts of admin & support available for spending Based

More information

Leading Economic Indicator Nebraska

Leading Economic Indicator Nebraska Nebraska Monthly Economic Indicators: September 20, 2017 Prepared by the UNL College of Business Administration, Bureau of Business Research Author: Dr. Eric Thompson Leading Economic Indicator...1 Coincident

More information

Cost Risk Assessment Building Success and Avoiding Surprises Ken L. Smith, PE, CVS

Cost Risk Assessment Building Success and Avoiding Surprises Ken L. Smith, PE, CVS Cost Risk Assessment Building Success and Avoiding Surprises Ken L. Smith, PE, CVS 360-570-4415 2015 HDR, Inc., all rights reserved. Addressing Cost and Schedule Concerns Usual Questions Analysis Needs

More information

Firm Frequency Response Market Information for Apr-16

Firm Frequency Response Market Information for Apr-16 Firm Frequency Response Market Information for Apr-16 FFR Market Information 211 Monthly Report Published Feb-16 Key points This Market Information Report is relevant for tenders submitted in Mar- 16 for

More information

Leading Economic Indicator Nebraska

Leading Economic Indicator Nebraska Nebraska Monthly Economic Indicators: June 21, 2017 Prepared by the UNL College of Business Administration, Bureau of Business Research Author: Dr. Eric Thompson Leading Economic Indicator...1 Coincident

More information

EARNED VALUE AS A RISK ASSESSMENT TOOL

EARNED VALUE AS A RISK ASSESSMENT TOOL EARNED VALUE AS A RISK ASSESSMENT TOOL Introduction Earned Value Definition: Employment of a Single Management Control System Providing Accurate, Consistent, Reliable, and Timely Data That Management at

More information

Analyze the Market for a Seasonal Bias. It is recommended never to buck the seasonal nature of a market. What is a Seasonal Trend?

Analyze the Market for a Seasonal Bias. It is recommended never to buck the seasonal nature of a market. What is a Seasonal Trend? The seasonal trend in a market is our way of taking the fundamental price action of a market...and then chart it year-by-year. Analyze the Market for a Seasonal Bias STEP 5 Using Track n Trade Pro charting

More information

Leading Economic Indicator Nebraska

Leading Economic Indicator Nebraska Nebraska Monthly Economic Indicators: October 24, 2018 Prepared by the UNL College of Business, Bureau of Business Research Author: Dr. Eric Thompson Leading Economic Indicator...1 Coincident Economic

More information

Leading Economic Indicator Nebraska

Leading Economic Indicator Nebraska Nebraska Monthly Economic Indicators: July 29, 2016 Prepared by the UNL College of Business Administration, Department of Economics Authors: Dr. Eric Thompson, Dr. William Walstad Leading Economic Indicator...1

More information

Executive Summary. July 17, 2015

Executive Summary. July 17, 2015 Executive Summary July 17, 2015 The Revenue Estimating Conference adopted interest rates for use in the state budgeting process. The adopted interest rates take into consideration current benchmark rates

More information

Introduction by Philip Croessmann, V.P., Director of Risk Management Sources of Construction Claims Common Types of Construction Claims Risk

Introduction by Philip Croessmann, V.P., Director of Risk Management Sources of Construction Claims Common Types of Construction Claims Risk Introduction by Philip Croessmann, V.P., Director of Risk Management Sources of Construction Claims Common Types of Construction Claims Risk Management Preconstruction & Construction Managing Construction

More information

April 2018 Data Release

April 2018 Data Release April 2018 Data Release The Home Purchase Sentiment Index (HPSI) is a composite index designed to track consumers housing-related attitudes, intentions, and perceptions, using six questions from the National

More information

Use of EVM Trends to Forecast Cost Risks 2011 ISPA/SCEA Conference, Albuquerque, NM

Use of EVM Trends to Forecast Cost Risks 2011 ISPA/SCEA Conference, Albuquerque, NM Use of EVM Trends to Forecast Cost Risks 2011 ISPA/SCEA Conference, Albuquerque, NM presented by: (C)2011 MCR, LLC Dr. Roy Smoker MCR LLC rsmoker@mcri.com (C)2011 MCR, LLC 2 OVERVIEW Introduction EVM Trend

More information

Dividend Growth as a Defensive Equity Strategy August 24, 2012

Dividend Growth as a Defensive Equity Strategy August 24, 2012 Dividend Growth as a Defensive Equity Strategy August 24, 2012 Introduction: The Case for Defensive Equity Strategies Most institutional investment committees meet three to four times per year to review

More information

Global Tactical Asset Allocation

Global Tactical Asset Allocation Global Tactical Asset Allocation This material is solely for informational purposes to be viewed in conjunction with this presentation. The information presented should not be construed as representative

More information

Leading Economic Indicator Nebraska

Leading Economic Indicator Nebraska Nebraska Monthly Economic Indicators: June 17, 2016 Prepared by the UNL College of Business Administration, Department of Economics Authors: Dr. Eric Thompson, Dr. William Walstad Leading Economic Indicator...1

More information

QUESTION 2. QUESTION 3 Which one of the following is most indicative of a flexible short-term financial policy?

QUESTION 2. QUESTION 3 Which one of the following is most indicative of a flexible short-term financial policy? QUESTION 1 Compute the cash cycle based on the following information: Average Collection Period = 47 Accounts Payable Period = 40 Average Age of Inventory = 55 QUESTION 2 Jan 41,700 July 39,182 Feb 18,921

More information

Introduction to VIX Futures. Russell Rhoads, CFA Instructor The Options Institute

Introduction to VIX Futures. Russell Rhoads, CFA Instructor The Options Institute Introduction to VIX Futures Russell Rhoads, CFA Instructor The Options Institute CBOE Disclaimer Options and futures involve risks and are not suitable for all investors. Prior to buying or selling options,

More information

Economic analysis of safety risks in construction

Economic analysis of safety risks in construction Safety and Security Engineering IV 51 Economic analysis of safety risks in construction F. M. Almeida Santos 1, A. R. Costa 2 & A. Soeiro 3 1 Tabique Engenharia Lda, Braga, Portugal 2 Ordem dos Engenheiros

More information

A Study on Risk Analysis in Construction Project

A Study on Risk Analysis in Construction Project A Study on Risk Analysis in Construction Project V. Rathna Devi M.E. Student, Department of civil engineering, Velammal Engineering College, Tamil Nadu, India ---------------------------------------------------------------------***--------------------------------------------------------------------

More information

Looking at a Variety of Municipal Valuation Metrics

Looking at a Variety of Municipal Valuation Metrics Looking at a Variety of Municipal Valuation Metrics Muni vs. Treasuries, Corporates YEAR MUNI - TREASURY RATIO YEAR MUNI - CORPORATE RATIO 200% 80% 175% 150% 75% 70% 65% 125% Average Ratio 0% 75% 50% 60%

More information

SOUTHERN AFRICA GROWTH INCENTIVE PROGRAMME (GIP)

SOUTHERN AFRICA GROWTH INCENTIVE PROGRAMME (GIP) SOUTHERN AFRICA GROWTH INCENTIVE PROGRAMME (GIP) PERFORMANCE YEAR (PY) 20/ The presentation contains IP protected works; it is intended for ABOs use only; the content of the presentation should not be

More information

January 2018 Data Release

January 2018 Data Release January 2018 Data Release The Home Purchase Sentiment Index (HPSI) is a composite index designed to track consumers housing-related attitudes, intentions, and perceptions, using six questions from the

More information

An Examination of the Predictive Abilities of Economic Derivative Markets. Jennifer McCabe

An Examination of the Predictive Abilities of Economic Derivative Markets. Jennifer McCabe An Examination of the Predictive Abilities of Economic Derivative Markets Jennifer McCabe The Leonard N. Stern School of Business Glucksman Institute for Research in Securities Markets Faculty Advisor:

More information

Big Walnut Local School District

Big Walnut Local School District Big Walnut Local School District Monthly Financial Report for the month ended September 30, 2013 Prepared By: Felicia Drummey Treasurer BIG WALNUT LOCAL SCHOOL DISTRICT SUMMARY OF YEAR TO DATE FINANCIAL

More information