Affordability Assessments to Support Strategic Planning and Decisions at NASA
|
|
- Nigel Shaw
- 6 years ago
- Views:
Transcription
1 Affordability Assessments to Support Strategic Planning and Decisions at NASA Debra Emmons 1 Marcus Lobbia 2 Torrey Radcliffe 2 Robert Bitten 1 1 Civil and Commercial Operations 2 7 March 21 The Aerospace Corporation 29
2 Agenda Introduction Need for Affordability Analysis Project Cost and Schedule Assessments Affordability Analysis Process Strategic Analysis Tool Needed to Support Long Term Decision Making Process Supporting the Review of U.S. Human Space Flight Plans Assessment of Integrated Options Summary 2
3 Introduction 3
4 Need for Affordability Analysis Forty NASA Robotic Science Missions Experienced 27% Cost and 22% Schedule Growth during Development Schedule Ratio within cost and schedule within 1% overrun Cost Ratio Results indicate a correlation between cost and schedule growth for dataset investigated 4
5 Cumulative Probability Need for Affordability Analysis (continued) 77 Historical NASA Projects Demonstrated ~51% Cost Growth from Formulation Start to Launch A % average cost growth corresponds to 17% confidence on lognormal approximation to data. 17%-tile = % historical cost growth (no reserves). 51% average cost growth corresponds to mean of lognormal approximation to data. Mean = 51% historical cost growth. Cumulative Probability Function of Cost Growth for 77 Historical NASA Projects (Human Space Flight (HSF), Non-HSF, Ground ) B 1% 9% Mean historical cost growth 8% 7% 6% B Historical data-77 missions Lognormal "Historical data -77 missions" 5% 4% 3% 2% A 1% % -1% -5% % 5% 1% 15% 2% 25% 3% A B Cost Growth (Includes cost and schedule uncertainty effects ) 5
6 Project Cost and Schedule Assessments Strategic-level affordability analysis requires a credible baseline Primary tenets of cost estimating employed by Aerospace: Use Multiple Methods Ensures that no one model/database biases the estimate Industry Standard Methods (NAFCOM, NICM, PRICE, SEER, etc.) Aerospace Developed Models (SSCM, SOSCM, LVCM, etc.) Use Analogy Based Estimating Ties cost to systems that have been built with known cost Allows contractor specific performance to be addressed Forces both independent estimate and project to look at the cost and complexity of new concepts with respect to previously built hardware Use Both System Level and Lower Level Approaches Ensures that lower level approaches do not omit elements or underestimate overall cost relative to system level complexity 6
7 Affordability Analysis Process 7
8 Strategic Analysis Tool Needed to Support Long Term Decision Making Process Sand Chart Tool (SCT) Objectives Support long-term strategic planning and analysis from cost, budget, and affordability viewpoints Benefits Ability to simulate all elements of a program or all missions within a portfolio Long-term program/portfolio analysis 1-2 years Ability to analyze multiple program/portfolio changes simultaneously Quantitative results to support strategic decisions Changes in mission launch dates to fit new program content Assess Figures of Merit Likelihood of X number of missions launched by 22x Likelihood of portfolio cost over time Likelihood of mission launch dates Likelihood of individual mission s cost or schedule breach Affordability analysis is a way to inform strategic planning and avoid Mt. Everest peaks beyond expected budgets 8
9 Confidence Level Confidence Level Cost, RY$M Affordability Analysis A Real World View Organizational inputs - Mission Directorates - Programs, Projects Launch Development Development Funding Cost Risk S- Technical Missions Readiness Duration Cost Profile Curve Specs. Date Astrophysics GLAST weiler brief Budget + CAD PBudget + CAD P Budget + CAD PBudget + CAD Projection Planck weiler brief Budget Budget Budget Budget Herschel weiler brief Budget Budget Budget Budget Kepler weiler brief Budget Budget Budget Budget HST-S4 weiler brief Budget projecbudget Budget projecbudget + + project + + projection WISE weiler brief Budget Budget Budget Budget SOFIA weiler brief Budget PBudget Budget PBudget (incl. Flights) + CAD + CAD P + CAD + CAD Projection SOFIA Flights weiler brief Analysis Analysis Analysis Analysis JWST weiler brief Budget + YBudget + YeBudget + YBudget + Last Last Last Last Year Projection NuStar weiler brief Budget Budget Budget Budget JDEM weiler brief Cap+Budget Cap+Budget Cap+Budget Cap+Budget ExoP-M1 weiler brief Quickcost Quickcost Quickcost Quickcost Astro-1 weiler brief Quickcost Quickcost Quickcost Quickcost Astro-2 weiler brief SID Input SID Input SID Input SID Input ExoP-M2 weiler brief Quickcost Quickcost Quickcost Quickcost EP-2 weiler brief Quickcost Quickcost Quickcost Quickcost ExoP-L1 weiler brief Quickcost Quickcost Quickcost Quickcost HST-D weiler brief IPAO IPAO IPAO IPAO EP-3 weiler brief Quickcost Quickcost Quickcost Quickcost Astro-3 weiler brief Quickcost Quickcost Quickcost Quickcost Restricted Launch Window? Linkages? Sand Chart Tool 2, 18, 16, 14, 12, 1, 8, 6, 4, 2, Fiscal Year Sand Chart Tool is one part of the analysis process data collection and analyst input are also very important IOCb - ISS - Orion IOCb - ISS - Ares I IOCb - ISS - EVA IOCb - ISS - Ground IOCb - ISS - Mission IOCb - ISS - SCIP IOCb - ISS - Discrete Risks - Fixed - ISS - Orion - Fixed - ISS - Ares I - Fixed - ISS - EVA - Fixed - ISS - Ground - Fixed - ISS - GO STS Standing Army - Fixed - ISS - Mission - Fixed - ISS - MO STS Standing Army - Fixed - ISS - Discrete Risks - Variable - ISS - Orion - Variable - ISS - Ares I - Variable - ISS - Ground IOCb - Lunar - Orion IOCb - Lunar - Ares V IOCb - Lunar - EVA IOCb - Lunar - Altair IOCb - Lunar - Ground IOCb - Lunar - Mission IOCb - Lunar - SCIP IOCb - Lunar - Discrete Risks - Fixed - Lunar - Ares V - Fixed - Lunar - EVA - Fixed - Lunar - Altair - Fixed - Lunar - Ground - Fixed - Lunar - SCIP - Variable - Lunar - Ares V - Variable - Lunar - EVA - Variable - Lunar - Altair - Variable - Lunar - Ground - Fixed - Lunar - Discrete Risks IOCb - Post - Lunar - Surface Systems IOCb - Post - Lunar - Outpost Wedge Fixed - All - PI - Fixed - Early Lunar Development Budget Available 1% Budget Available (w / Rolled-Over Reserves) 9% 8% 7% 6% 5% 1% Confidence Level Estimate - IOC 4% 3% 9% 8% 7% 6% 5% 4% 3% 2% 1% % Program Budget w/ Reseves 65% $19 $21 $23 $25 $27 $29 $31 TY $B Interpretation and vetting of data inputs Before After Algorithms and penalty functions informed by historical data and past studies 9 2% 1% Reference "Business as Usual" % Feedback Loop Number of Missions Implemented by 225 Interpretation and understanding of analysis
10 Percent Likelihood RY$M Cost, RY$M Cost, RY$M Cost, RY$M Cost, RY$M Confidence Level Confidence Level Confidence Level Confidence Level RY$M SCT Designed to Evaluate Scenarios for Given Program/ Portfolio or Develop Plan Given Individual Elements 2, 18, 16, 14, 12, 1, 8, 6, 4, 2, 2, 16, 1, 6, 4, 2, 1% 9% 8% 7% 6% 5% 4% 3% 2% 1% 2, 18, 16, 14, 14, 12, 1, 8, % 1% 2% 3% , 12, 8, 6, 4, 1% 9% 8% 7% 6% 5% 4% 3% 2% 1% 1% 9% 8% 7% 6% 5% 4% 3% 2% 2, 18, 16, 14, 12, 1, 8, 6, 4, 1% 9% 8% 7% 6% 5% 4% 3% % 1% Project 2% Cost, $M % 1% Project Cost, $M % Project Cost, $M year delay in HLR % Date 1% 9% 8% 7% 6% 5% 4% Project Cost, $M , Fiscal Year , Fiscal Year Fiscal Year Fiscal Year Baseline No HSF Gap IOCb - ISS - Orion IOCb - ISS - Ares I IOCb - ISS - EVA IOCb - ISS - Ground IOCb - ISS - Mission IOCb - ISS - SCIP IOCb - ISS - Discrete Risks - Fixed - ISS - Orion - Fixed - ISS - Ares I - Fixed IOCb - ISS ISS - EVA Orion - Fixed IOCb - ISS ISS - Ground Ares I - Fixed IOCb - ISS ISS - GO EVA STS Standing Army - Fixed IOCb - ISS - Mission Ground - Fixed IOCb - ISS - MO Mission STS Standing Army - Fixed IOCb - ISS - Discrete SCIP Risks - Variable IOCb - ISS - ISS - Discrete - Orion Risks - Variable - Fixed - ISS - - ISS Ares - Orion I - Variable - Fixed - ISS - - ISS Ground - Ares I IOCb Lunar - Fixed - Orion ISS EVA IOCb Lunar - Fixed - Ares V ISS Ground IOCb Lunar - Fixed - EVA ISS GO STS Standing Army IOCb Lunar - Altair IOCb Lunar - Ground IOCb Lunar - Mission IOCb Lunar - Fixed IOCb - SCIP - ISS ISS - Mission Orion IOCb Lunar - Fixed IOCb - Discrete - ISS ISS Risks - MO Ares STS I Standing Army - Fixed - Fixed IOCb Lunar - - ISS ISS Ares - Discrete EVA V Risks - Fixed - Variable IOCb - ISS Lunar EVA - ISS - Ground - Orion - Fixed - Variable IOCb - ISS Lunar Altair - ISS - Mission - Ares I - Fixed - Variable IOCb - ISS Lunar Ground - ISS - SCIP - Ground - Fixed IOCb Lunar Lunar IOCb - - ISS SCIP Orion - Discrete Risks - Variable IOCb Lunar - Fixed - Lunar - Ares - - Ares V ISS - Orion V - Variable IOCb Lunar - Fixed - Lunar - EVA - ISS - Ares I IOCb Lunar Cx - - Fixed - IOCb Altair - ISS ISS - EVA Orion IOCb Lunar Cx - - Fixed - IOCb Ground - ISS ISS - Ground Ares I IOCb Lunar Cx - - Fixed - IOCb Mission - EVA - ISS ISS - GO EVA STS Standing Army - Variable IOCb Lunar - Cx Lunar - - Fixed - IOCb SCIP - Altair - ISS - Mission Ground - Variable IOCb Lunar - Cx Lunar - - Fixed - IOCb Discrete - Ground - ISS Risks - MO Mission STS Standing Army - Fixed - Fixed Lunar - Fixed Lunar IOCb Discrete - - ISS Ares Risks - Discrete SCIP V Risks IOCb Post - Fixed Lunar - Variable Lunar IOCb Surface - ISS EVA - Systems ISS - Discrete - Orion Risks IOCb Post - Fixed Lunar - Variable Lunar Outpost - Fixed Altair - Wedge ISS - - ISS Ares - Orion I Fixed - All - PI - Fixed - Variable Lunar - Fixed Ground - ISS - - ISS Ground - Ares I - Fixed - Fixed Early IOCb Lunar Lunar - Development Fixed - SCIP Orion - ISS - EVA - Variable IOCb Lunar - Lunar - Fixed - Ares - Ares - V ISS V - Ground - Variable IOCb Lunar - Lunar - Fixed - EVA - EVA - ISS - GO STS Standing Army - Variable IOCb Lunar - Lunar - Altair - Altair - Variable IOCb Lunar - Lunar - Ground - Ground - Fixed IOCb Lunar Lunar - Discrete Mission Risks IOCb Post IOCb Lunar Lunar - Fixed - Surface SCIP - ISS - Mission Systems IOCb Post IOCb Lunar Lunar - Fixed - Outpost Discrete - ISS Wedge Risks - MO STS Standing Army Fixed Cx All PI Fixed - - Fixed Lunar - - ISS Ares - Discrete V Risks - Fixed - Fixed - Early Variable Lunar Development EVA - ISS - Orion - Fixed - Variable Lunar Altair - ISS - Ares I - Fixed - Variable Lunar Ground - ISS - Ground - Fixed IOCb - Lunar Lunar - SCIP Orion - Variable IOCb - Lunar - Lunar - Ares - Ares V V - Variable IOCb - Lunar - Lunar - EVA IOCb - Lunar - Altair IOCb - Lunar - Ground IOCb - Lunar - Mission - EVA - Variable IOCb - Lunar - Lunar - SCIP - Altair - Variable IOCb - Lunar - Lunar - Discrete - Ground Risks - Fixed - Fixed Lunar - Lunar Discrete - Ares Risks V IOCb Post - Fixed Lunar - - Lunar Surface - EVA Systems IOCb Post - Fixed Lunar - - Lunar Outpost - Altair Wedge Fixed - All - - PI Fixed - Lunar - Ground - Fixed - - Fixed Early - Lunar Lunar Development - SCIP - Variable - Lunar - Ares V - Variable - Lunar - EVA - Variable - Lunar - Altair - Variable - Lunar - Ground - Fixed - Lunar - Discrete Risks IOCb - Post - Lunar - Surface Systems IOCb - Post - Lunar - Outpost Wedge Fixed - All - PI - Fixed - Early Lunar Development Budget Available Budget Available Input: baseline plan, cost likelihood curves, program linkages Perform Monte Carlo probabilistic analysis Budget Available Evaluation Budget Available Budget Available (w / Rolled-Over Reserves) Budget Available (w / Rolled-Over Reserves) Budget Available (w / Rolled-Over Reserves) Budget Available (w / Rolled-Over Reserves) Output: schedule likelihood curves, # of missions complete, etc Fiscal Year Apply Stretch Algorithms Fiscal Year Planning Planetary Science - Planetary Science Research Planetary Science - Discovery Planetary Science - Mars Exploration Planetary Science - Technology Planetary Science - MSL 211 LRD Planetary Science - Juno Planetary Science - MoO-3 Planetary Science - ExoMars Input: baseline plan, program linkages Planetary Science - Disc-12 Planetary Science - MoO-4 Planetary Science - NewFront3 Planetary Science - Mars 216 Planetary Science - Mars 218 Planetary Science - MoO-6 Planetary Science - MoO-7 Planetary Science - MSL 211 LRD Planetary Science - GRAIL Output: New strawman plan that fits budget available Planetary Science - Juno Planetary Science - MoO-3 Planetary Science - ExoMars Planetary Science - Disc-12 Planetary Science - MoO-4 Planetary Science - NewFront3 Planetary Science - Mars 216 Planetary Science - Mars 218 Planetary Science - MoO-6 Planetary Science - MoO-7 Planetary Science - LADEE Planetary Science - ILN-1/ILN-2 Planetary Science - MAVEN (Mars Scout2) Planetary Science - Disc-13 Planetary Science - MoO-5 Planetary Science - ILN-3/ILN-4 Planetary Science - Disc-14 Planetary Science - ILN-5/ILN-6 Planetary Science - Disc-15 Planetary Science - NewFront4 Planetary Science - Mars 222 Planetary Science - Lunar 7 Planetary Science - MoO-8 Planetary Science - Mars 224 Planetary Science - Mars 226 Planetary Science - Lunar Science Program Planetary Science - New Frontiers Planetary Science - Outer Planets Planetary Science - Chndraayn1 (M3) Planetary Science - GRAIL Planetary Science - LADEE Planetary Science - ILN-1/ILN-2 Planetary Science - MAVEN (Mars Scout2) Planetary Science - Disc-13 Planetary Science - MoO-5 Planetary Science - ILN-3/ILN-4 Planetary Science - Disc-14 Planetary Science - ILN-5/ILN-6 Planetary Science - Disc-15 Planetary Science - NewFront4 Planetary Science - Mars 222 Planetary Science - Lunar 7 Planetary Science - MoO-8 Planetary Science - Mars 224 Planetary Science - Mars 226 Planetary Science - Disc-16 Planetary Science - Disc-17 Planetary Science - Lunar-8 Planetary Science - MoO-9 Planetary Science - NewFront5 Planetary Science - MoO-1 Planetary Science - MoO-11 Planetary Science - Lunar 9 Planetary Science - MHP Budget Planetary Science - Planetary Science Research Planetary Science - Lunar Science Program Planetary Science - Discovery Planetary Science - New Frontiers Planetary Science - Mars Exploration Planetary Science - Outer Planets Planetary Science - Technology Planetary Science - Chndraayn1 (M3) Planetary Science - Lunar-8 Planetary Science - Disc-16 Planetary Science - MoO-9 Planetary Science - Disc-17 Planetary Science - NewFront5 Planetary Science - MoO-1 Planetary Science - MoO-11 Planetary Science - Lunar 9 Planetary Science - MHP Budget
11 Cost Cost Cost Cost, FYxx$M FYxx$M Cost Cost SCT Applies Real World Penalties to Projects Based on Performance of Other Elements in Portfolio With Cost Overruns Included Adjusted to Fit Budget 4, 35, Threat - ISS Retirement $1B in Threat - SOMD ISS thru 22 Threat - ISS Upmass through 216 Threat - SSP Transition and Retire $2.8B ARD - Aeronautics Research SM D - Science ESM D - Advanced Capabilities SOM D - Space and Flight Support (SFS) SOM D - ISS SOM D - STS 3, 25, 2, 15, 1, 5, Year - Lunar - Outpost Wedge Historical - - Lunar - SCIP Historical - - Lunar - PI Historical - - Lunar - Mission Historical - - Lunar - Ground Historical - - Lunar - Surface Systems Historical - - Lunar - Lander Historical - - Lunar - EVA Historical - - Lunar - Ares V Historical - - Lunar - Ares II Historical - - Lunar - Orion Historical - IOC - Lunar - SCIP Historical - IOC - Lunar - PI Historical - IOC - Lunar - M ission Historical - IOC - Lunar - Ground Historical - IOC - Lunar - Lander Historical - IOC - Lunar - EVA Historical - IOC - Lunar - Ares V Historical - IOC - Lunar - Ares II Historical - IOC - Lunar - Orion Historical - - ISS - PI Historical - - ISS - Mission Historical - - ISS - Ground Historical - - ISS - EVA Historical - - ISS - Ares II Historical - - ISS - Orion Historical - IOC - ISS - SCIP Historical - IOC - ISS - PI Historical - IOC - ISS - M ission Historical - IOC - ISS - Ground Historical - IOC - ISS - EVA Historical - IOC - ISS - Ares II Historical - IOC - ISS - Orion Annual Budget Available (w/ Rolled-Over Reserves) Annual Budget Available (Initial) Apply Penalties Year Before After Shift project that just started right one year to fit under wedge Year Penalty 1: Delay Start Before After Hold project at Phase A/B funding to fit under wedge Year Penalty 2: Phase A/B Hold Before After Budget reduced for several projects, and added back later (with an inefficiency factor) Year Penalty 3: Funding Reduction Simulation of Program Manager responses to budget constraints based on historical experience 11
12 Sand Chart Tool Other Ground Rules and Assumptions Many Assumptions are Different than for other Cost-Risk Tools Cost draws are applied using based on historical experience Linked cost-schedule model where cost draws affect schedule S-curve input is truncated at baseline cost Assumed that projects will never give back allocated funding Schedule linkages enforced between projects Holds applied when some projects are waiting for others to finish Caps on spending ramp rates, limited look ahead, etc. yield cases where delays occur even when funding is available Projects are penalized when necessary to fit available funding Funding reduction applied to all projects when necessary Functional vs. statistical correlation Budget constraints and schedule linkages can correlate projects 12
13 Supporting the Review of U.S. Human Space Flight Plans 13
14 Future of U.S. Human Spaceflight in the Upcoming Decades Formulated in Terms of Five Key Questions 1. What should be the future of the Space Shuttle? 2. What should be the future of the International Space Station (ISS)? 3. On what should the next heavy-lift launch vehicle be based? 4. How should crews be carried to low-earth orbit? 5. What is the most practicable strategy for exploration beyond low- Earth orbit? 14
15 Affordability Analysis for U.S Human Space Flight Review Performed affordability analysis of various integrated options Identified when capabilities could be realized based on budget constraints Incorporated historical risk impact on realizing cost and schedule Workforce / industrial-base like impacts modeled with assumptions for carrying costs during schedule stretch-outs, when appropriate Several steps in process Develop baseline for each scenario Lunar mission scenarios Flexible path / deep space mission scenarios Fit content to budget cases FY1 President s Budget Less Constrained budget with additional $3B/year Determine cost and schedule to various capabilities Initial crew launch capability Heavy lift launch vehicle 15
16 Summary of Integrated Options Evaluated by Review of HSF Committee 16
17 Methodology Overview: Review of Human Space Flight (HSF) 1. Point Estimate Without Reserve 2. Cost-Risk Curve Informed by Historical Program Experience 3. Starting Project Budget Profiles and Schedule Dependencies 5. Program Budget Under Funding Constraints 4. Assembled Program Architecture Budgets 17
18 $ in M $ in M Notional Sand Chart Used for Program Assessment 2, 18, Total Program Cost shown at 65 th percent likelihood. Calculated project cost in excess of initial point estimate, is aggregated and redistributed to each project proportionally. 16, Two Budget Scenarios: FY1 and Less Constrained 14, 12, 1, ISS Other Non-Program elements Lunar Surface Systems Other Program elements Dotted colors represent operations costs Outpost 8, 6, 4, 2, STS LEO Launch Vehicle Crew Module Ground Heavy Launch Vehicle 18 Lander FY9 FY1 FY11 FY12 FY13 FY14 FY15 FY16 FY17 FY18 FY19 FY2 FY21 FY22 FY23 FY24 FY25 FY26 FY27 FY28 Program.6 IC dates shown as range from.4hlr 5 th to 8 th percent likelihood LEO Capability IC HLR Shuttle Retirement ISS Retirement Schedule Outputs Constraints Outpost 29 FY9 21 FY1 211 FY FY12 FY FY FY FY FY FY FY FY2 22 FY FY FY FY FY FY FY FY FY FY3 23
19 Summary 19
20 Summary Aerospace s affordability analysis process: Can help verify the feasibility of large portfolios in budget-constrained environments Provides quantitative results that can be used to iterate with decision-makers and improve portfolio robustness In support of the U.S. Review of HSF Plans Committee: Established tools/methodologies enabled quick-turnaround results Historical performance of NASA s past projects was used to tie cost-growth risk to reality in-lieu of more detailed and time-consuming estimates This process allowed many different scenarios to be analyzed in a short period of time, with the ability to look at how changes in portfolio content, budget lines, etc. led to differences in realizing defined objectives 2
21 Thank you The Aerospace Corporation 29
22 Backup The Aerospace Corporation 29
23 What is Sand Chart Tool? Sand Chart Tool (SCT) is an Excel-based model for analyzing the cost vs. available budget of a portfolio of programs and projects Strategically re-plan a portfolio Insights gained from Re-plan prior to execution understanding the portfolio execution lead Evaluate the execution of a portfolio to better strategic plans from a more tactical perspective Impact of potential cost-overruns Interactions of linked projects SCT is one piece of a larger Sand Chart process Analyst in the loop required to integrate/interpret data sources, ensure consistency, and sanity check results 23
24 Sand Chart Tool Planning vs. Evaluation Modes Different modes capture the Strategic vs. Tactical perspectives 24
25 Level Confidence Level Cost Evaluation Mode Modeling of Cost Growth Draws performed on both size of cost growth and date cost growth is realized Perform Random Draw on Cost S-curve Is Cost > Baseline? No Use Baseline Cost/Schedule Funding Profile Yes Time 1% 9% 8% 7% 6% 5% 4% 3% 2% 1% Cost Growth $ Baseline Cost Random Draw Cost Perform Draw To Determine Where Cost Growth Occurs Development Programs Phase C Growth Phase C/D Cost Growth Production/ Proportional Cost Growth % Cost Project Cost, $M Apply cost growth to program Phase C Phase D 25
26 Jan, 29 Feb, 29 Mar, 29 Apr, 29 May, 29 Jun, 29 Jul, 29 Aug, 29 Sep, 29 Oct, 29 Nov, 29 Dec, 29 Jan, 21 Feb, 21 Jan, 29 Feb, 29 Mar, 29 Apr, 29 May, 29 Jun, 29 Jul, 29 Aug, 29 Sep, 29 Oct, 29 Nov, 29 Dec, 29 Jan, 21 RY$M Jan, 29 Feb, 29 Mar, 29 Apr, 29 May, 29 Jun, 29 Jul, 29 Aug, 29 Sep, 29 Oct, 29 Nov, 29 Dec, 29 RY$M Jan, 29 Feb, 29 Mar, 29 Apr, 29 May, 29 Jun, 29 Jul, 29 Aug, 29 Sep, 29 Oct, 29 Nov, 29 Dec, 29 Jan, 21 Feb, 21 Mar, 21 Apr, 21 May, 21 Jun, 21 Jul, 21 Aug, 21 RY$M RY$M RY$M RY$M Planning Mode Stretch Algorithm START 4 2 FINISH Fiscal Year Interpolation of program costs Fiscal Year Temporal scaling complete Temporal scaling of program to fit budget 26
27 Planning Mode vs. Evaluation Mode Analysis Tool Mode Planning Evaluation Analysis Type Deterministic Monte Carlo Purpose Usage Scenarios Primary Modeling Assumptions Input Output Simulate how planned milestone dates shift due to changes in budgeting assumptions - Sensitivity and what-if studies - Developing re-planned baseline budget (input to evaluation mode) - No cost penalties for stretching or compressing budgets - No ramp rate limits - Parallel independent programs all stretched together (some might be delayed in real world) - program and reserve budget profiles, wedge constraints - Start date shifts (optional) - Cost S-curve mean, std dev - Desired project CLs (re-scales baseline budget profiles) Budget sand chart stretched/compressed to fit budget constraints Simulate actual program spending to determine impacts of cost growth, parallel programs, ramp-up limits, reserve carry-over, etc. on confidence of achieving portfolio milestones - Determining confidence level of achieving portfolio milestones - Optimizing reserve strategy - Illustrating impact of managing parallel programs in a budget-constrained environment - Random draws on project cost-risk (before penalties) truncated at budgeted CL - Uncorrelated cost draws - Look ahead, critical path, and re-baseline penalties - Program and reserve budget profiles, wedge constraints - Cost S-curve mean, std dev - Ramp rate limits - Schedule linkages - Algorithm settings (e.g. allow funding reduction, etc.) S-curve distributions of program costs and schedule milestones Run time Fast (seconds) Slow (minutes to hours) 27
28 Flowchart of SCT Planning Mode Uses simple temporal-scaling algorithm to stretch/compress programs to fit budget constraint Implicitly maintains schedule phasing between linked development programs Deterministic algorithm (i.e. no Monte Carlo or optimization performed) Input data Interpolate budgets Re-scale budget profiles to specified confidence levels Shift start dates Shift/exclude next Shift program Stretch/compress remaining Stretch programs Remove Exclude programs Yes Any Shift program s left? No Output results Stretch/compress remaining Stretch program Remove Exclude program 28
29 Flowchart of SCT Evaluation Mode Input data Perform cost draws Internal cost and schedule growth Simulates Program Manager response to overbudget situations Internal cost growth modeled using Monte Carlo analysis Note that Schedule Linkages are also checked during the Budget Execution Simulation after any changes to program cost profiles or schedules (this check is not shown on the flowchart for simplicity) Over baseline cost? No Compare cost and budget for current time step Under budget? Yes Yes Perform schedule draws Modify baseline cost profiles Potential for start date acceleration Budget Execution Simulation Yes Accelerate start date No Apply Penalty 1 No Under budget? No Yes Potential for Phase D compression Yes Compress Phase D Apply Penalty 2 No Under budget? No Yes Advance to next time step Apply Penalty 3 29
Assessing the Impact of Confidence Levels in Funding and Budgeting NASA Science Missions
Presented at the 217 ICEAA Professional Development & Training Workshop www.iceaaonline.com/portland217 Assessing the Impact of Confidence Levels in Funding and Budgeting NASA Science Missions Robert Bitten
More informationPresentation to the Board on Physics and Astronomy. Dr. Paul Hertz Chief Scientist, Science Mission Directorate NASA.
1 Presentation to the Board on Physics and Astronomy Dr. Paul Hertz Chief Scientist, Science Mission Directorate NASA April 22, 2006 Credit: NASA/WMAP Science Team 2 3 Credit: NASA/WMAP Science Team 5
More informationIntegrated Cost Schedule Risk Analysis Using the Risk Driver Approach
Integrated Cost Schedule Risk Analysis Using the Risk Driver Approach David T. Hulett, Ph.D. Hulett & Associates 24rd Annual International IPM Conference Bethesda, Maryland 29 31 October 2012 (C) 2012
More informationNASA Constellation Confidence Level Estimate Using ACEIT
NASA Constellation Confidence Level Estimate Using ACEIT Kelley Cyr Constellation Program Cost Estimating Team Lead 2 nd Annual ACEIT User Conference Topics Background Why do a confidence assessment Cx
More informationIntegrated Cost Schedule Risk Analysis Using the Risk Driver Approach
Integrated Cost Schedule Risk Analysis Using the Risk Driver Approach Qatar PMI Meeting February 19, 2014 David T. Hulett, Ph.D. Hulett & Associates, LLC 1 The Traditional 3-point Estimate of Activity
More informationUse of the Risk Driver Method in Monte Carlo Simulation of a Project Schedule
Use of the Risk Driver Method in Monte Carlo Simulation of a Project Schedule Presented to the 2013 ICEAA Professional Development & Training Workshop June 18-21, 2013 David T. Hulett, Ph.D. Hulett & Associates,
More informationFOR OFFICIAL USE ONLY 1
TO: Donald Trump, President CC: Mike Pence, Vice President; Chairman, National Space Council Scott Pace, Executive Secretary, National Space Council Mick Mulvaney, Director, Office of Management and Budget
More information(RISK.03) Integrated Cost and Schedule Risk Analysis: A Draft AACE Recommended Practice. Dr. David T. Hulett
(RISK.03) Integrated Cost and Schedule Risk Analysis: A Draft AACE Recommended Practice Dr. David T. Hulett Author Biography David T. Hulett, Hulett & Associates, LLC Degree: Ph.D. University: Stanford
More informationMaking sense of Schedule Risk Analysis
Making sense of Schedule Risk Analysis John Owen Barbecana Inc. Version 2 December 19, 2014 John Owen - jowen@barbecana.com 2 5 Years managing project controls software in the Oil and Gas industry 28 years
More informationPlanetary Science Division Program Status
Planetary Science Division Program Status Presentation to the LPSC James L. Green Director, Planetary Science Division March 1, 2010 1 Outline Administrative Matters Recent Accomplishments Presidents FY11
More informationFederal Budget Landscape and Portfolio Planning
Federal Budget Landscape and Portfolio Planning New Telescope Meeting September 4-6, 2012 Princeton, NJ Jon A. Morse Rensselaer Polytechnic Institute 6 September 2012 R&D in the Federal Budget 2 R&D in
More informationBudget Manager Meeting. February 20, 2018
Budget Manager Meeting February 20, 2018 Meeting Agenda DISCUSSION DRAFT NOT FOR DISTRIBUTION Budget Office Current Year Forecast Process Endowment Payout Control Charts FY19 Target Meetings Delphi Project
More informationUnderstanding the Results of an Integrated Cost/Schedule Risk Analysis James Johnson, NASA HQ Darren Elliott, Tecolote Research Inc.
Understanding the Results of an Integrated Cost/Schedule Risk Analysis James Johnson, NASA HQ Darren Elliott, Tecolote Research Inc. 1 Abstract The recent rise of integrated risk analyses methods has created
More informationManager Comparison Report June 28, Report Created on: July 25, 2013
Manager Comparison Report June 28, 213 Report Created on: July 25, 213 Page 1 of 14 Performance Evaluation Manager Performance Growth of $1 Cumulative Performance & Monthly s 3748 3578 348 3238 368 2898
More informationFinancial & Business Highlights For the Year Ended June 30, 2017
Financial & Business Highlights For the Year Ended June, 17 17 16 15 14 13 12 Profit and Loss Account Operating Revenue 858 590 648 415 172 174 Investment gains net 5 162 909 825 322 516 Other 262 146
More informationFrom Suspicion to Invaluable Transition of Two Project Managers
From Suspicion to Invaluable Transition of Two Project Managers June 2010 Shilpi Kumar & Sunita Raman Agenda Unisys and HOLMES 2 Nature of Projects and Roles Why EVA? How? EVA in Development Projects Transition
More informationProject Connect Connect January 11, 2012
Project Connect January 11, 2012 Introduction Meeting Minutes Approval Project Status Report IV&V Update By Ernst & Young Other Business Public Comments Review of Actions from Meeting Scheduling of Next
More informationEARNED VALUE MANAGEMENT. Is it worth the effort?
EARNED VALUE MANAGEMENT Is it worth the effort? Session Objectives Examples of earned value in use. Why don t more Project Managers use EMV? Road Map to EVA Maturity? What you need to know? How is our
More informationCONSTRUCTION CLAIMS MANAGEMENT & EOT DELAYS ANALYSIS. Presented by : Hany Ismail, MSc, PMP
CONSTRUCTION CLAIMS MANAGEMENT & EOT DELAYS ANALYSIS Presented by : Hany Ismail, MSc, PMP CONSTRUCTION CLAIMS MANAGEMENT EOT DELAYS ANALYSIS LESSON 7 TIME IMPACT WINDOW DELAY ANALYSIS TECHNIQUE TIME IMPACT
More informationAbsolute Return Fixed Income: Taking A Different Approach
August 2015 Absolute Return Fixed Income: Taking A Different Approach Executive Summary Historically low global fixed income yield levels present a conundrum for today s fixed income investors. Increasing
More informationNASA Implementation of JCL Policy
NASA Implementation of JCL Policy James Johnson and Charles Hunt NASA Headquarters, Cost Analysis Division ISPA/SCEA 2011 Abstract For the past two years NASA has been implementing Joint Cost and Schedule
More informationBeginning Date: January 2016 End Date: June Managers in Zephyr: Benchmark: Morningstar Short-Term Bond
Beginning Date: January 2016 End Date: June 2018 Managers in Zephyr: Benchmark: Manager Performance January 2016 - June 2018 (Single Computation) 11200 11000 10800 10600 10400 10200 10000 9800 Dec 2015
More informationAdvanced Budgeting Workshop. Contents are subject to change. For the latest updates visit
Advanced Budgeting Workshop Page 1 of 8 Why Attend 'Advanced Budgeting Workshop' is the second level course in budgeting after Meirc's 'Effective Budgeting and Cost ' course. It goes beyond the theory
More informationBeginning Date: January 2016 End Date: September Managers in Zephyr: Benchmark: Morningstar Short-Term Bond
Beginning Date: January 2016 End Date: September 2018 Managers in Zephyr: Benchmark: Manager Performance January 2016 - September 2018 (Single Computation) 11400 - Yorktown Funds 11200 11000 10800 10600
More informationEARNED VALUE AS A RISK ASSESSMENT TOOL
EARNED VALUE AS A RISK ASSESSMENT TOOL Introduction Earned Value Definition: Employment of a Single Management Control System Providing Accurate, Consistent, Reliable, and Timely Data That Management at
More informationUnderstanding the Principles of Investment Planning Stochastic Modelling/Tactical & Strategic Asset Allocation
Understanding the Principles of Investment Planning Stochastic Modelling/Tactical & Strategic Asset Allocation John Thompson, Vice President & Portfolio Manager London, 11 May 2011 What is Diversification
More informationProject Connect. August 10, 2011
Project Connect August 10, 2011 Introduction Meeting Minutes Approval Project Status Report IV&V Update By Ernst & Young Other Business Public Comments Review of Actions from Meeting Schedule Next Meeting
More informationProject Connect. November 14, 2012
Project Connect November 14, 2012 Introduction Meeting Minutes Approval Project Status Report IV&V Update by Ernst & Young Other Business Public Comments Review of Actions from Meeting Scheduling of Next
More informationReview of Membership Developments
RIPE Network Coordination Centre Review of Membership Developments 7 October 2009/ GM / Lisbon http://www.ripe.net 1 Applications development RIPE Network Coordination Centre 140 120 100 80 60 2007 2008
More informationADVANCED QUANTITATIVE SCHEDULE RISK ANALYSIS
ADVANCED QUANTITATIVE SCHEDULE RISK ANALYSIS DAVID T. HULETT, PH.D. 1 HULETT & ASSOCIATES, LLC 1. INTRODUCTION Quantitative schedule risk analysis is becoming acknowledged by many project-oriented organizations
More informationProject Risk Analysis. Neil Dunkerley 17 th May 2012
Project Risk Analysis Neil Dunkerley 17 th May 2012 About EC Harris EC Harris is a leading global Built Asset Consultancy, helping clients make the most from their investment and expenditure in built assets.
More informationEarned Schedule Analysis
Integrated Project Performance Management.EMERGING PRACTICE. Earned Schedule Analysis A Better Set of Schedule Metrics Eleanor Haupt President PMI College of Performance Management Walt Lipke Member PMI
More informationHUD NSP-1 Reporting Apr 2010 Grantee Report - New Mexico State Program
HUD NSP-1 Reporting Apr 2010 Grantee Report - State Program State Program NSP-1 Grant Amount is $19,600,000 $9,355,381 (47.7%) has been committed $4,010,874 (20.5%) has been expended Grant Number HUD Region
More informationCertificate in Advanced Budgeting and Forecasting
Certificate in Advanced Budgeting and Forecasting Page 1 of 12 Why Attend This course is the second level course in budgeting after Meirc's 'Effective Budgeting and Cost Control' course. It goes beyond
More informationProject Connect. July 11, 2012
Project Connect July 11, 2012 Introduction Meeting Minutes Approval Project Status Report IV&V Update by Ernst & Young Other Business Public Comments Review of Actions from Meeting Scheduling of Next Meeting
More informationProject Connect Executive Steering Committee Update. April 10, 2013
Project Connect Executive Steering Committee Update April 10, 2013 Agenda Introduction Meeting Minutes Approval Project Status Report IV&V Update by Ernst & Young Other Business Public Comments Review
More informationEarned Schedule .EMERGING PRACTICE. Eleanor Haupt IPPM. ASC/FMCE Wright-Patterson AFB OH ANL327
Integrated Project Performance Management.EMERGING PRACTICE. Earned Schedule Eleanor Haupt ASC/FMCE Wright-Patterson AFB OH eleanor.haupt@wpafb.af.mil 937-656-5482 ANL327 1 Required Legal Notices ***CAUTION***.EMERGING
More informationDavid T. Hulett, Ph.D, Hulett & Associates, LLC # Michael R. Nosbisch, CCC, PSP, Project Time & Cost, Inc. # 28568
David T. Hulett, Ph.D, Hulett & Associates, LLC # 27809 Michael R. Nosbisch, CCC, PSP, Project Time & Cost, Inc. # 28568 Integrated Cost-Schedule Risk Analysis 1 February 25, 2012 1 Based on AACE International
More informationCreating Internal Transparency to Forecast Workforce Needs
Creating Internal Transparency to Forecast Workforce Needs Robert D. Motion Director, Workforce Planning & Strategy Intelligence, Information & Services November 17, 201 Copyright 201 Raytheon Company.
More informationProject Connect. June 22, 2011
Project Connect June 22, 2011 Introduction Meeting Minutes Approval Project Status Report IV&V Update By Ernst & Young Other Business Public Comments Review of Actions from Meeting Schedule Next Meeting
More informationScarcity Pricing using ORDC for reserves and Pricing Run for Out- Of-Market Actions
Scarcity Pricing using ORDC for reserves and Pricing Run for Out- Of-Market Actions David Maggio, Sai Moorty, Pamela Shaw ERCOT Public Agenda 1. History of the Operating Reserve Demand Curves (ORDC) at
More informationThe EM Budget. Intergovernmental Meeting with the US Department of Energy December 12-14, Terry Tyborowski
The EM Budget Intergovernmental Meeting with the US Department of Energy December 12-14, 2012 Terry Tyborowski Office of Environmental Management Deputy Assistant Secretary for Program Planning and Budget
More informationProject Connect. May 9, 2012
Project Connect May 9, 2012 Introduction Meeting Minutes Approval Project Status Report IV&V Update by Ernst & Young Other Business Public Comments Review of Actions from Meeting Scheduling of Next Meeting
More informationCertificate in Advanced Budgeting and Forecasting
Certificate in Advanced Budgeting and Forecasting Page 1 of 9 Why Attend This course is the second level course in budgeting after Meirc's 'Effective Budgeting and Cost ' course. It goes beyond the theory
More informationPrice Inconsistency Market Enhancements. Revised Straw Proposal
Price Inconsistency Market Enhancements Revised Straw Proposal August 2, 2012 Price Inconsistency Market Enhancements Table of Contents 1 Introduction... 3 2 Plan for Stakeholder Engagement... 3 3 Background...
More informationForecasting More Profits For You and Your Clients
Forecasting More Profits For You and Your Clients Presenter: Christian Wielage Accountants/Business Advisors Entrepreneurs Small Businesses Non-profits Introduction: About me Christian Wielage Prior to
More informationGLAST Large Area Telescope: Project Status Overview. Gamma-ray Large Area Space Telescope
Gamma-ray Large Area Space Telescope GLAST Large Area Telescope: Project Status Overview Lowell A. Klaisner Stanford Linear Accelerator Center Project Manager Klaisner@slac.stanford.edu 650-926-2726 1
More informationConstruction of the #7 Line Subway Extension Project New York September 17, 2018
Construction of the #7 Line Subway Extension Project New York September 17, 2018 Saibal Basuroy, PMP Project Controls Director, Hill International Inc. Disclaimer This presentation is protected by US and
More informationIntroduction by Philip Croessmann, V.P., Director of Risk Management Sources of Construction Claims Common Types of Construction Claims Risk
Introduction by Philip Croessmann, V.P., Director of Risk Management Sources of Construction Claims Common Types of Construction Claims Risk Management Preconstruction & Construction Managing Construction
More informationPlanetary R&A. Drs. Colleen Hartman & Paul Mahaffy 8/16/2016 1
Planetary R&A Drs. Colleen Hartman & Paul Mahaffy 8/16/2016 1 Trends Planetary R&A proposal submissions and selections No statistically significant change in the number of Planetary proposals submitted
More informationModelling the Zero Coupon Yield Curve:
Modelling the Zero Coupon Yield Curve: A regression based approach February,2010 12 th Global Conference of Actuaries Srijan Sengupta Section 1: Introduction What is the zero coupon yield curve? Its importance
More informationAdvanced Asset/Liability Management
Advanced Asset/Liability Management WBA BOLT Summer Leadership Summit June 14, 2018 Presented by: Marc Gall, Vice President mgall@bokf.com 1 Agenda Asset/Liability Management Summary Developing Assumptions
More informationXML Publisher Balance Sheet Vision Operations (USA) Feb-02
Page:1 Apr-01 May-01 Jun-01 Jul-01 ASSETS Current Assets Cash and Short Term Investments 15,862,304 51,998,607 9,198,226 Accounts Receivable - Net of Allowance 2,560,786
More informationCost Risk Assessment Building Success and Avoiding Surprises Ken L. Smith, PE, CVS
Cost Risk Assessment Building Success and Avoiding Surprises Ken L. Smith, PE, CVS 360-570-4415 2015 HDR, Inc., all rights reserved. Addressing Cost and Schedule Concerns Usual Questions Analysis Needs
More informationProject Management Professional (PMP) Exam Prep Course 06 - Project Time Management
Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management Slide 1 Looking Glass Development, LLC (303) 663-5402 / (888) 338-7447 4610 S. Ulster St. #150 Denver, CO 80237 information@lookingglassdev.com
More informationProving and Tracking Damages of your Claim
Proving and Tracking Damages of your Claim J. Mark Dungan October 6, 2017 1 Schedules: Back to Basics I. CPM Scheduling Basics II. The Baseline Schedule III. The Schedule Update IV. Delay Analysis V. Proving
More informationArkansas Works Overview. Work And Community Engagement Requirement
1 Arkansas Works Overview Work And Community Engagement Requirement Arkansas Works Populations & Work and Community Engagement Requirement 2 Arkansas Works enrollees will fall into three categories for
More informationExploring the Formation of Inflation Expectations in Jamaica: A Pragmatic Approach
Exploring the Formation of Inflation Expectations in Jamaica: A Pragmatic Approach Presented at he 46 th Annual Monetary Studies Conference By: Ralston Henry Table of Contents Motivation Stylized Facts
More informationInvestment DANA FIXED INCOME STRATEGIES.
Investment DANA Advisors THE WISE CHOICE HERITAGE A strong family culture Since our founding in 1980, Dana has remained independent and Employee-owned. Our investment firm is built on trust, integrity,
More informationThe Compelling Case for Value
The Compelling Case for Value July 2, 2018 SOLELY FOR THE USE OF INSTITUTIONAL INVESTORS AND PROFESSIONAL ADVISORS 0 Jan-75 Jan-77 Jan-79 Jan-81 Jan-83 Jan-85 Jan-87 Jan-89 Jan-91 Jan-93 Jan-95 Jan-97
More informationBetter Budgeting Practices
Better Budgeting Practices Presentation to the NCSL YNP s Next-Gen Legislators Pre-Conference December 9, 2015 Luke E. Martel Director of Strategic Initiatives Presentation Outline State Budgeting 101
More informationR o l l i n g F o r e c a s t i n g :
R o l l i n g F o r e c a s t i n g : A S t r a t e g y f o r E f f e c t i v e F i n a n c i a l M a n a g e m e n t Debra Miller Vice President Client Success January 22, 2016 Discussion Topics Overview
More informationPREVENTING PROGRAM MANAGEMENT PITFALLS USING PORTFOLIO ESTIMATING
PREVENTING PROGRAM MANAGEMENT PITFALLS USING PORTFOLIO ESTIMATING Nicholas Morales, MCR LLC. Christopher Dewberry, Dept. of Navy ICEAA 2016 Professional Development & Training Workshop Atlanta, GA 7-10
More informationFULL YEAR REPORT, 2017 TELEPHONE/AUDIO CONFERENCE 8 FEBRUARY 2018, AT CET TOMMY ANDERSSON, PRESIDENT AND CEO HELENA WENNERSTRÖM, EVP AND CFO
TELEPHONE/AUDIO CONFERENCE 8 FEBRUARY 2018, AT 15.30 CET TOMMY ANDERSSON, PRESIDENT AND CEO HELENA WENNERSTRÖM, EVP AND CFO DIRECT LINK AUDIOCAST: HTTPS://TV.STREAMFABRIKEN.COM/BULTEN Q4 2017 TELECONFERENCE:
More informationBalance-of-Period TCC Auction
Balance-of-Period TCC Auction Proposed Credit Policy Sheri Prevratil Manager, Corporate Credit New York Independent System Operator Credit Policy Working Group May 29, 2015 2000-2015 New York Independent
More informationfor Major Infrastructure Projects
for Major Infrastructure Projects Presented by: Pedram Daneshmand Senior Associate Director 4 th Annual Contract Selection and Risk for Major Projects, March 2011 Agenda Brief Introduction Project Delivery
More informationSecurity Analysis: Performance
Security Analysis: Performance Independent Variable: 1 Yr. Mean ROR: 8.72% STD: 16.76% Time Horizon: 2/1993-6/2003 Holding Period: 12 months Risk-free ROR: 1.53% Ticker Name Beta Alpha Correlation Sharpe
More informationFDD FIRM STORAGE SERVICE NORTHERN NATURAL GAS COMPANY
FDD FIRM STORAGE SERVICE NORTHERN NATURAL GAS COMPANY FIRM STORAGE SERVICE OPTIONS Northern s firm storage service is provided pursuant to the FDD Rate Schedule located in Northern s FERC Gas Tariff. The
More informationAACE International 48th Annual Meeting Washington, DC June 2004 DEVELOPING & MANAGING CONTIGENCY ON THE BASIS OF RISK. Robert Tichacek, P.E.
AACE International 48th Annual Meeting Washington, DC June 2004 DEVELOPING & MANAGING CONTIGENCY ON THE BASIS OF RISK Robert Tichacek, P.E. Presentation Outline Review of Basic Project Risk Management
More informationSpheria Australian Smaller Companies Fund
29-Jun-18 $ 2.7686 $ 2.7603 $ 2.7520 28-Jun-18 $ 2.7764 $ 2.7681 $ 2.7598 27-Jun-18 $ 2.7804 $ 2.7721 $ 2.7638 26-Jun-18 $ 2.7857 $ 2.7774 $ 2.7690 25-Jun-18 $ 2.7931 $ 2.7848 $ 2.7764 22-Jun-18 $ 2.7771
More informationDown, Set, Hut! Quarterbacking your LDI Program. Martin Jaugietis, CFA Managing Director, LDI Solutions, Russell Investments
Down, Set, Hut! Quarterbacking your LDI Program Martin Jaugietis, CFA Managing Director, LDI Solutions, Russell Investments Funded Ratios (%) The end zone is getting closer funding levels have improved
More informationDivision of Bond Finance Interest Rate Calculations. Revenue Estimating Conference Interest Rates Used for Appropriations, including PECO Bond Rates
Division of Bond Finance Interest Rate Calculations Revenue Estimating Conference Interest Rates Used for Appropriations, including PECO Bond Rates November 16, 2018 Division of Bond Finance Calculation
More informationCOMMITTEE ON SCIENCE U.S. HOUSE OF REPRESENTATIVES HEARING CHARTER. NASA s FY 2006 Budget Proposal
COMMITTEE ON SCIENCE U.S. HOUSE OF REPRESENTATIVES HEARING CHARTER NASA s FY 2006 Budget Proposal February 17, 2005 10:00 a.m. to 12:00 p.m. 2318 Rayburn House Office Building Purpose: On Thursday, February
More informationAPPLICATION FOR EXEMPTION OF GOODS EXPORTED FROM TEXAS ("FREEPORT EXEMPTION") FOR 2010
Division - Freeport Exemption P.O. Box 560367 * Dallas, Texas 75356-0367 www.dallascad.org APPLICATION FOR EXEMPTION OF GOODS EXPORTED FROM TEXAS ("FREEPORT EXEMPTION") FOR 2010 This application covers
More informationBig Walnut Local School District
Big Walnut Local School District Monthly Financial Report for the month ended September 30, 2013 Prepared By: Felicia Drummey Treasurer BIG WALNUT LOCAL SCHOOL DISTRICT SUMMARY OF YEAR TO DATE FINANCIAL
More informationThe Cost Monitoring of Construction Projects Through Earned Value Analysis
211 International Conference on Economics and Finance Research IPEDR vol.4 (211) (211) IACSIT Press, Singapore The Cost Monitoring of Construction Projects Through Earned Value Analysis Mohd Faris Khamidi
More informationDividend Growth as a Defensive Equity Strategy August 24, 2012
Dividend Growth as a Defensive Equity Strategy August 24, 2012 Introduction: The Case for Defensive Equity Strategies Most institutional investment committees meet three to four times per year to review
More informationEnergy Price Processes
Energy Processes Used for Derivatives Pricing & Risk Management In this first of three articles, we will describe the most commonly used process, Geometric Brownian Motion, and in the second and third
More informationPSRS/PEERS Update April 2018
PSRS/PEERS Update April 2018 1 Quick Facts PSRS/PEERS benefit is an important source of financial security for members and retirees. PSRS/PEERS Quick Facts: Over 260,000 active, inactive, retirees and
More informationExecutive Summary. July 17, 2015
Executive Summary July 17, 2015 The Revenue Estimating Conference adopted interest rates for use in the state budgeting process. The adopted interest rates take into consideration current benchmark rates
More informationStatus of the Implementation of the Child Welfare Component of the North Carolina Families Accessing Services through Technology (NC FAST) System
Status of the Implementation of the Child Welfare Component of the North Carolina Families Accessing Services through Technology (NC FAST) System Report to the Joint Legislative Oversight Committee on
More information1.2 The purpose of the Finance Committee is to assist the Board in fulfilling its oversight responsibilities related to:
Category: BOARD PROCESS Title: Terms of Reference for the Finance Committee Reference Number: AB-331 Last Approved: February 22, 2018 Last Reviewed: February 22, 2018 1. PURPOSE 1.1 Primary responsibility
More informationCredit Scoring. from Concept to Reality. Credit & Collections Conference Boston: June 11 th, 2007
Credit Scoring from Concept to Reality Credit & Collections Conference Boston: June 11 th, 2007 2 Agenda 1) Developing & Launching the Credit Scoring Plan Tom Kritzer Navistar Financial Corporation 2)
More informationAttachment JEM 4 Hearing Exhibit 116 Page 1 of 11] Residential Sales 5,817,938 90,842,431 96,660,368. Normal HDD
Residential Sales Page 1 of 11] F=C*(D E)*B H=G F B C D E F G H Month HDD Coefficient Customers HDD Normal HDD Weather Impact Actual Billed WN Billed Jan-16 0.011693 1,256,043 1,183 1,102 1,193,343 18,806,509
More informationResearch Accounting & Analysis University of Washington Operational Performance Dashboard
Research Accounting & Analysis University of Washington Operational Performance Dashboard September 26 Quarter 1 - Fiscal Year 7 Grant and Contract Accounting Mission As a professional accounting team,
More informationA Study on Risk Analysis in Construction Project
A Study on Risk Analysis in Construction Project V. Rathna Devi M.E. Student, Department of civil engineering, Velammal Engineering College, Tamil Nadu, India ---------------------------------------------------------------------***--------------------------------------------------------------------
More informationRETURN TO ROME Dr. Kenneth F. Smith, PMP Project Management Fundamentals 1
RETURN TO ROME Project Management Fundamentals 1 Work - Milestones Plan: MS 4 Four Day Rome Project S-Curve Work vs Time Actual vs. Plan MS 3 MS 2 MS 1 = Plan = Actual Cumulative Milestones Completed 0
More informationExam 1 Problem Solving Questions Review
Exam 1 Problem Solving Questions Review SECTION 1 The following data were obtained from a recent quarterly report for Dell Computer (in millions): Net revenue $8,028 Cost of revenue $6,580 Inventories:
More informationOHIO STATE UNIVERSITY EXTENSION. County Budgets
County Budgets This course will cover finding information to create calendar year budgets, including running advanced ereports and using historical budget templates. 6/18/15 cfaesfinance.osu.edu Agenda
More informationThe First Steps in Implementing a Simplified Earned Value Management System
2007 Joint ISPA/SCEA National Conference & Workshop June 12-15, 2007 The First Steps in Implementing a Simplified Earned Value Management System Dorothy Tiffany, CPA, PMP NASA/GSFC EVM System Interface
More informationPortfolio Management Package Insights A quarterly briefing with best practices and thought leadership concepts from your Portfolio Management Package
Portfolio Management Package Insights A quarterly briefing with best practices and thought leadership concepts from your Portfolio Management Package (PMP) team Contents 1. New Special Handling Code (First
More informationDirector s Comments. Presentation to California State Lottery Commission May 24, Director s Report 6A
Director s Comments Presentation to California State Lottery Commission May 24, 2012 Director s Report 6A Overview General Business Update Governor s Appointments Recent Lottery Organizational Changes
More informationIndian Sovereign Yield Curve using Nelson-Siegel-Svensson Model
Indian Sovereign Yield Curve using Nelson-Siegel-Svensson Model Of the three methods of valuing a Fixed Income Security Current Yield, YTM and the Coupon, the most common method followed is the Yield To
More informationSIX MONTHS REPORT, JAN JUN 2018
SIX MONTHS REPORT, JAN JUN 2018 TELEPHONE/AUDIO CONFERENCE 11 JULY 2018, AT 11.00 CET TOMMY ANDERSSON, PRESIDENT AND CEO HELENA WENNERSTRÖM, EVP AND CFO DIRECT LINK AUDIOCAST: HTTPS://TV.STREAMFABRIKEN.COM/BULTEN
More informationLRD IWTF Projects Update Inland Waterways Users Board
LRD IWTF Projects Update Inland Waterways Users Board MS. JEANINE HOEY, PE, PMP CHIEF, E&C Division Pittsburgh District 13 Dec 2016 The views, opinions and findings contained in this report are those of
More informationBig Walnut Local School District
Big Walnut Local School District Monthly Financial Report for the month ended September 30, 2012 Prepared By: Felicia Drummey Treasurer BIG WALNUT LOCAL SCHOOL DISTRICT SUMMARY OF YEAR-TO-DATE FINANCIAL
More informationProject Theft Management,
Project Theft Management, by applying best practises of Project Risk Management Philip Rosslee, BEng. PrEng. MBA PMP PMO Projects South Africa PMO Projects Group www.pmo-projects.co.za philip.rosslee@pmo-projects.com
More informationSMD Cost/Schedule Performance Study Summary Overview. Brad Perry, Cindy Bruno
SMD Cost/Schedule Performance Study Summary Overview Brad Perry, Cindy Bruno NASA Science Support Office Mark Jacobs, Monica Doyle, Shawn Hayes Mike Stancati, Wayne Richie, John Rogers Science Applications
More informationResource Planning with Uncertainty for NorthWestern Energy
Resource Planning with Uncertainty for NorthWestern Energy Selection of Optimal Resource Plan for 213 Resource Procurement Plan August 28, 213 Gary Dorris, Ph.D. Ascend Analytics, LLC gdorris@ascendanalytics.com
More informationA Study in Cyclicals: Energy Stocks and the Causeway Curve
A Study in Cyclicals: Energy Stocks and the Causeway Curve > JULY 2017 NEWSLETTER In Causeway s view, the energy industry offers the potential for improved profitability from operating efficiencies, enhanced
More information