Project Connect. July 11, 2012
|
|
- Gervase Harmon
- 6 years ago
- Views:
Transcription
1 Project Connect July 11, 2012
2 Introduction Meeting Minutes Approval Project Status Report IV&V Update by Ernst & Young Other Business Public Comments Review of Actions from Meeting Scheduling of Next Meeting August 8 Adjourn Project Connect 2
3 Project Update Budget and Timeline Current and Upcoming Activities Risks and Issues Key Project Dates Project Connect 3
4 Per agreed upon plan, Deloitte provided its Corrective Action Plan (CAP) on June 8, 2012 Upon review significant issues were noted The schedule was increased to 10 months (an October 2013 implementation) It did not sufficiently address the underlying issues with the ufacts Framework There was a significant increase in pricing for the 33 open Change Requests ($7.8M) Based upon those factors DEO rejected the CAP on June 13, 2012 Providing Deloitte 10 days to correct and resubmit Project Connect 4
5 After thoughtful consideration, and mindful of DEO s investment to date and risk associated with continuing the project as is, DEO issued Deloitte a letter of its intent to terminate the contract for cause on June 15, 2012 DEO did not get the deal it bargained for Original timeline will be significantly exceeded by 10 months ufacts Framework is not a viable, proven solution Deloitte has 30 days to address its failures and demonstrate the reasonable likelihood of a successful, timely project completion Project Connect 5
6 Over the last three weeks, significant, collaborative progress has been made to address DEO s concerns On June 22, 2012 the Design Deliverables (Functional, Database, and Data Conversion) have been approved and accepted Progress continues to be made in development as well as requirements validation for the Change Requests that are critical for Go Live Project Connect 6
7 Discussions have been held to address the key project issues Mitigating the risk associated with ufacts Addressing the additional cost of the extension Agreeing to a time and materials with a cap for the outstanding change requests DEO and Deloitte are currently in final discussions, anticipating that all issues will be addressed and resolutions codified as Amendment 7 to the contract Project Connect 7
8 Project Connect 8
9 Original Project Contingency & Management Reserves Budget $9,957,039 Supplemental Budget Requests (SBRs) for TOP and SIDES $1,082,350 Reemployment and Eligibility Assessment (REA) Grant - Workforce Integration (Allocated Portion) $150,123 Total Funds Available $11,189,512 Funding Previously Approved ($3,627,037) Additional cost of HW/SW for TOP (295,779) Faneuil Scope Changes (Workforce) ($31,158) 28 Additional Functional Change Requests - Amendment 7* ($4,100,000) Total Funds Allocated ($8,053,974) Contingency & Management Reserves Balance $3,135,538 Pending Change Requests: - Unemployment Appeals Commission - Additional Workforce Integration Effort - Disaster Recovery Hardware Session Legislation * Time & Materials not to exceed Project Connect 9
10 Total REA Funds Available $2,006,250 (For Workforce Integration) Allocated North Highland ($118,965) Allocated Operational Support Staff ($31,158) Total Funds Allocated $150,123 Unallocated REA Funds Balance $1,856,127 Planned Allocations: Workforce Integration Development (Deloitte) and potentially a Workforce Portal (TBD) Project Connect 10
11 Base Budget $52,841,655 Management Reserve Allocation $6,821,501 SBR $1,082,350 REA $150,123 Updated Budget $60,895,629 As discussed once Contingency & Management Reserve funds have been approved for an expenditure (from previous slide), these funds will be moved to the appropriate budget category for tracking. Project Connect 11
12 Project Funding - Cumulative by Quarter Budgeted: Forecast: Variance: $60,895,629 $59,066,026 $ 1,829,603 Millions FY11 Q1 FY11 Q2 FY11 Q3 FY11 Q4 FY12 Q1 FY12 Q2 FY12 Q3 FY12 Q4 FY13 Q1 FY13 Q2 FY13 Q3 FY13 Q4 FY14 Q1 FY14 Q2 Budget Committed Forecast Project Connect 12
13 Overall Project Budget & Estimated Variance Original Budget Allocated Contingency & Management Reserves Supplemental Budget Requests REA Grant Updated Project Budget Estimate at Completion Project Variance Project Funding OPS 92,400 86, , ,987 17,863 Expenses 6,864, ,864,194 6,046, ,202 OCO (Hardware) 483, , ,224 7,016 Contracted Services Project Management & Support Project Management Office 2,377, ,377,200 1,715, ,930 Project & Operational Support 1,526, , ,158 2,116,952 2,053,963 62,988 Outside Legal 95, , ,448 (8,448) ITN Development 526, , ,700 13,950 Business Transition 1,456, , ,965 1,854,324 2,079,251 (224,927) Other Contracted Services 45, ,000 96,290 (51,290) Total Project Management & Support 6,026, , ,123 7,015,125 6,560, ,203 IV&V Services 2,005, ,005,798 2,005,798 0 Benefits Realization Strategy 255, , ,276 21,551 Organizational Change Management 679, , ,355 35,395 System Integrator (SI) Services 28,061,156 5,331,238 1,082, ,474,744 34,373, ,958 SI Hardware & Maintenance 2,543, , ,863,453 2,842,449 21,005 SI Software & Maintenance 5,706, , ,951,953 5,720, ,715 Project Reserves 122, , ,695 Project Funding Totals 52,841,655 6,821,501 1,082, ,123 60,895,629 59,066,026 1,829,603 Cotingency/Management Reserves 9,957,039 3,135, ,856,127 Remaining unallocated Total Project Funding 62,798,694 9,957,039 1,082,350 2,006,250 Project Connect 13
14 PROJECT Cumulative through June 2012 June 2012 July 2012 Budget Committed Variance Budget Committed Budget Forecast Project Funding OPS 130, ,382 20,978 17,765 15,745 17,765 21,595 Expenses 5,820,357 4,729,227 1,091,130 96,275 61,458 75,775 44,346 OCO (Hardware) 483, , , , Contracted Services 0 0 Project Management & Support 4,963,105 4,731, , , ,137 70,000 32,000 IV&V Services 1,462,473 1,399,861 62,612 46,456 46, , ,413 Benefits Realization Strategy 216, ,676 21,551 7,920 6,188 86,917 81,917 Organizational Change Management 552, ,520 84,730 38,700 52,920 42,880 21,496 System Integrator (SI) Services 12,075,391 3,311,701 8,763, , ,805 46,456 46,456 SI Hardware & Maintenance 2,833,453 1,240,214 1,593, , ,456 41,456 SI Software & Maintenance 5,951,953 5,433, , , ,000 5,000 Project Reserves 89, ,889 3, Project Funding Totals 34,578,699 21,733,201 12,845, , , , ,678 Project Connect 14
15 Design Deliverables were signed-off and accepted Treasury Offset Program Design was signedoff and accepted Continuing to refine Workforce integration Scope and Requirements Definition for Connect Organizational Design and Organizational Change Management continue on track Project Connect 15
16 Total Functional CRs Received 164 Withdrawn (73) Deferred (1) Total CRs In Process 90 Amendment 7 28 Approved DEO Development 16 Pending Analysis - Critical 8 Pending Analysis Non-Critical 38 Project Connect 16
17 Risk #35 Organizational Design Activities Beginning to align recommended Organization Design Five other open risks being actively monitored Three deal with compliance with statutes and legislative changes Project Connect 17
18 Issue #6 Missed Design Phase Gate Monitored via the CAP Issue #7 Engagement with Geographic Solutions Contract will need to be modified to address integration requirements Short-term (FLUID) and long-term (Connect) approaches identified and approval process proceeding Issue #8 Corrective Action Plan (CAP) Contract calls for this to be tracked as an Issue Project Connect 18
19 July 20 August 8 September 12 September 28 CAP Resolution ESC Meeting ESC Meeting Interim Development Phase Gate Project Connect 19
20 Project Connect 20
21 Introduction Meeting Minutes Approval Project Status Report IV&V Update By Ernst & Young Other Business Public Comments Review of Actions from Meeting Scheduling of Next Meeting August 8 Adjourn Project Connect 21
22 Unemployment Compensation Project Independent Verification and Validation Monthly Assessment Report Summary 09 July 2012
23 Topics for discussion General IV&V overview Overall risk state and trending Key indicators Overall project performance Projected milestone slippage Upcoming IV&V activities Supporting information Summary of changes IV&V ratings summary Open deficiencies Project milestones Open technology facets Page 23
24 General IV&V overview Overall IV&V risk state: Amber The UC Project Team continues to work on addressing the deficiencies identified by the IV&V Team. A revised integrated master schedule (IMS) is being used to manage the project. The control account structure previously used has been replaced by a detailed schedule. The new IMS has been baselined and includes a new project timeline. Based on the current schedule performance index (SPI), the Develop Phase Gate is projected to be completed on time. All subsequent phase gates are projected to be completed on time. Delays in the project will require contract modifications and/or additional funding for DEO, PMO and IV&V personnel to continue to support the project. No new deficiencies identified since the last report. Page 24
25 Overall risk state and trending Program Risk state of UC Project As of 09 July 2012 Governance Risk state with trending Program Resource management Cost management P2 P1 Performance management Time management P4 Change management P5 P4 Functionality T1 Technical architecture P3 Operations support Risk adjusted financials T2 P6 Non-functional requirements P5 Risk management P9 Business objectives and value alignment Quality management P8 B2 Business process P7 Organization design B3 Communication P3 T3 P9 P6 P8 P7 P2 P1 B3 B2 T1 B1 B6 T5 B5 T4 B4 B9 T4 High-level system architecture T3 B1 Benefits tracking B6 T8 T7 B7 B8 Functional requirements T5 Legacy integration Cost, benefit and risk B5 Reporting and value monitoring T7 Requirements mapping T6 B4 Investment governance and approval B9 Technology T8 Stabilization T9 B7 Compliance and regulatory B8 Business Technology T2 T6 T9 Risk state with trending Business Indicates that the area being assessed has critical issues that will result in significant risk to the project most likely resulting in either the inability to achieve the outcomes, inability to meet the projected schedule, or a significant cost over-run. Requires immediate action. Indicates that the area being assessed has issues that need to be resolved; inefficiencies exist. Current process/method can be used with refinement. Indicates that the area being assessed did not have significant issues to report. Continued monitoring should be performed. Indicates that the area being assessed has incomplete information available for a conclusive finding or is not applicable. Page 25
26 Key indicators Indicator Value Comment Is the project approach sound? Yes Is the project on time? Yes Based on the current SPI, the project is on time. Is the project on budget? No Delays in the project will require contract modifications and/or additional funding for DEO, PMO and IV&V personnel to continue to support the project. Is scope being managed so there is no scope creep? Yes The work being completed as part of the UC project is within the scope of the project as defined for the UC modernization project. What are the project s future risks? N/A The UC Project Team is actively working to address the deficiencies identified by the IV&V Team. Are the project s risks increasing or decreasing? Are there new or emerging technological solutions that will affect the project s technology assumptions? Decreasing No The UC Project Team is actively working to address the deficiencies identified by the IV&V Team. New and emerging technologies were considered in the Feasibility Study. None have an adverse effect on the project s technological assumptions. Page 26
27 Overall project performance UC project performance 1.30 CPI Behind schedule and underspent Ahead of schedule and underspent SPI = 1.04 CPI = 1.07 SPI Behind schedule and overspent 0.70 Ahead of schedule and overspent Page 27
28 Projected milestone slippage UC projected milestone slippage Implementation 0 UAT 0 Develop 0 Jun 2012 Design 0 Define 0 Planning Number of calendar days Page 28
29 Upcoming IV&V activities Participate in UC meetings IV&V review meetings with the UC Project Team Executive Steering Committee meetings Review integrated master schedule and associated project performance reports Deliverable review schedule is as follows: Deliverable Planned finish Actual finish Comment UC3-06A, Project Management Documents 24 August September 2011 Complete UC3-06B, Requirements Validation 19 August August 2011 Complete UC3-06C, Design Documents UC3-06D, Development UC3-06E, Testing UC3-06F, Data Conversion UC3-06G, Training UC3-06H, Implementation Schedule being revised Schedule being revised Schedule being revised Schedule being revised Schedule being revised Schedule being revised Page 29
30 Summary of changes Supporting information Item Deficiencies addressed New deficiencies Risk ratings Maturity ratings Interviews conducted Artifacts received Description D12 The current control account structure is insufficient for determining accurate project performance. No new deficiencies identified since the last report P3 Resource management changed from Green (no issues) to Amber (issues and inefficiencies). P4 Time management changed from Red (critical issued) to Amber (issues and inefficiencies). P5 Performance management changed from Red (critical issued) to Amber (issues and inefficiencies). P4 Time management changed from Level 2 (repeatable) to Level 4 (managed). P5 Performance management changed from Level 1 (initial) to Level 3 (defined). No interviews conducted since the last report. Artifacts received include corrective action plan (CAP) materials, deliverables, resource management, schedule information, status reports, and other items. Page 30
31 IV&V ratings summary Supporting information 30 IV&V cube facet ratings and open deficiencies per month Number Critical Issues Inefficiencies No Issues Not Evaluated Open Deficiencies Page 31
32 Open deficiencies Supporting information No. Areas Deficiency Implications Recommendations D11 P3: Resource management P4: Time management P5: Performance management The IMS and associated subsidiary schedules are insufficient to properly manage and control the project. Inability to effectively manage schedule and cost. Unable to establish true visibility and determine forecasting capability to schedule and cost performance in achieving project expectations. Inability to ascertain and analytically support a point of view for current and forecasted project performance. Misalignment of or incorrect project health perceptions. Lack of transparency on the project status and value for the business, stakeholders, and sponsors, leading to poor decision making and potentially providing a false sense of confidence. Inaccurate and unreliable data leading to unwanted surprises. Modify the work breakdown structure (WBS) for the development schedule and the IMS so they are identical. Revise the development schedule to address the items identified in the schedule analysis. Create appropriate linkages between the IMS and the development schedule so the development schedule becomes part of the IMS. Use a single IMS which includes all subsidiary schedules as the basis for managing the project and reporting progress. Use the IMS to generate the headcount plan for the project. Page 32
33 UC project milestones WBS Title Completion date Supporting information Original Scheduled Planned Projected Actual Planning Interim Gate 04/29/ /29/ /29/ /29/ /29/ Planning Phase Gate 06/17/ /17/ /17/ /17/ /17/ Define Interim Gate 1 06/24/ /24/ /29/ /29/ /29/ Define Interim Gate 2 07/15/ /15/ /15/ /15/ /19/ Define Phase Gate 08/05/ /05/ /05/ /05/ /05/2011 Design Interim Gate 1 10/28/ /28/2011 Design Interim Gate 2 12/02/ /02/2011 Design Interim Gate 3 12/02/ /02/ Design Phase Gate 12/16/ /29/ /29/ Develop Interim Gate 1 05/11/ /18/ /18/ /18/ Develop Interim Gate 2 07/13/ /04/ /04/ /04/ Develop Phase Gate 08/03/ /18/ /18/ /18/ UAT Phase Gate 11/16/ /25/ /25/ /25/ Implementation Phase Gate 12/14/ /15/ /15/ /15/2013 Late Page 33
34 Open technology facets Supporting information Facet Expectations Project deliverable Planned completion T2 : Operations support An organizational structure and support strategy to manage the new implementation is in place. Tools exist for tracking performance of application at object levels. A maintenance strategy is developed to manage modification, migration, and retirement of products according to the release strategy. Ongoing knowledge transfer, as systems are developed. A detailed training strategy exists for training the different categories of business and technical users of the system for them to be able to adopt to the system and use it more effectively. Training documents are in place. Training strategy is agreed upon, communicated and being executed. Trainers are qualified via agreed upon selection process PMP Human Resource Management and Staffing Plan 3.14 PMP Knowledge Management Plan 5 Validated Requirements Document 24 Operations Documentation 06/07/11 06/07/11 06/24/11 07/15/11 08/05/11 11/30/12 26 Training Plan 07/27/12 27 Training (execution) Various 28 Production System Implementation Plan 08/03/12 Training materials are standard across all modules and functions and are capturing an adequate level of detail. 30 System Operations and Maintenance Plan 12/14/12 Page 34
35 Open technology facets (continued) Supporting information Facet Expectations Project deliverable Planned completion T6 : Legacy integration A decommissioning document must exist for legacy systems with an associated communication plan to users of affected systems. Query only databases must exist for accessing queries based on historical data. Date range for the historical data is agreed upon with business users. Data extracted from legacy systems is validated by business users. A data erasure plan exists for scrubbing data from legacy systems that will be decommissioned. 4 Data Conversion Plan 07/08/11 9 Data Conversion Design 12/09/11 19 Test Plan (Data Conversion) Test Results (Data Conversion) 03/02/12 09/28/12 DEO IT plans TBD T9 : Stabilization An extended team has been defined across the organization and is working as an extension of the project team. Tasks have been assigned and key metrics are in place to monitor progress. 30 System Maintenance and Operations Plan KPIs 12/14/12 Long-term sustainability plans are in place to keep support and maintenance of the implementation viable. Long-term vendor contracts are implemented to maintain the system in the absence of an in-house capability to maintain the system. A vendor management body is established to maintain the relationship with vendors to facilitate smooth delivery of outsourced services. 12-month Warranty Period 12-months Operations Support and Maintenance Agreement Executed contracts and license agreements Page 35
36 Introduction Meeting Minutes Approval Project Status Report IV&V Update by Ernst & Young Other Business Public Comments Review of Actions from Meeting Scheduling of Next Meeting June 13 Adjourn Project Connect 36
37 FY11/12 Spend Plan Graph FY11/12 Spend Plan Details Project Connect 37
38 FY Project Funding - Cumulative by Month 25 Millions Budgeted: $ 23,216,480 Forecast: 10,967,670 Variance: $ 12,248, Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 FY Budget Allocation Committed Forecast Project Connect 38
39 OPS FY Budget Allocation and Spend by Month - Q1 & Q2 July 2011 August 2011 September 2011 October 2011 November 2011 December 2011 Budget Committed Budget Committed Budget Committed Budget Committed Budget Committed Budget Committed Funding 3,800 3,644 3,800 3,449 3,800 2,723 3,800 3,140 3,800 3,484 3,800 3,811 Expenses Funding 775, ,509 3,465,952 3,120,445 49,775 45,665 56,495 47,036 49,775 42,969 71,303 55,024 OCO Funding Contracted Services Project Management & Support 226, , , , , , , , , , , ,224 IV&V Services 46,456 46,456 77,762 76,012 46,456 48,206 46,456 46,456 46,456 46,456 46,456 46,456 Benefits Realization Strategy 9,320 5,515 9, ,320 1,815 9, , ,320 0 Organizational Change Management 25,500 18,270 25,500 26,550 25,500 29,040 38,700 27,990 38,700 20,550 38,700 14,550 System Integrator (SI) Services 0 0 1,630,482 1,630, ,397, , ,805 4,082, ,805 SI Hardware & Maintenance 243, , SI Software & Maintenance ,986 0 Project Reserves 5, , , , , ,084 0 Total Contracted Services 556, ,344 1,972,697 1,978, , ,320 1,712, , , ,753 4,447, ,034 Total Budget Allocation & Spend 1,336,099 1,169,497 5,442,449 5,102, , ,707 1,773, , , ,205 4,522, ,869 Project Connect 39
40 OPS FY Budget Allocation and Spend by Month - Q3 & Q4 January 2012 February 2012 March 2012 April 2012 May 2012 June 2012 Budget Committed Budget Committed Budget Committed Budget Committed Budget Committed Budget Committed Funding 3,800 3,735 15,770 16,215 18,430 14,955 17,765 15,294 18,430 16,537 17,765 15,745 Expenses Funding 74,353 33,179 71,303 30, ,003 35,953 79,275 33,510 96,275 35,435 96,275 61,458 OCO Funding ,000 10, ,147 23,555 40, ,629 Contracted Services Project Management & Support 224, , , , , , , , , , , ,137 IV&V Services 46,456 46,456 46,456 46,456 77,762 46,456 77,762 46,456 46,456 46,456 46,456 46,456 Benefits Realization Strategy 7, ,920 6,205 7,920 27,225 7,920 27,820 7,920 24,090 7,920 6,188 Organizational Change Management 40,150 20,250 38,700 25,860 38,700 52,590 38,700 47,085 38,700 49,215 38,700 52,920 System Integrator (SI) Services 122, , , , , , , ,805 3,529, , , ,805 SI Hardware & Maintenance ,282, , ,032 0 SI Software & Maintenance , ,747 0 Project Reserves 3, , , , , ,285 0 Total Contracted Services 445, , , ,811 1,893, , , ,723 3,915, , , ,505 Total Budget Allocation & Spend 523, , , ,443 2,469, , , ,526 4,030, , , ,337 Project Connect 40
41 Deloitte Amendment 5 TOP $ 1,634,009 TOP Hardware & Software 239,389 Deloitte Amendment 6 SIDES $709,579 Change Request Support - NH $279,345 Organizational Redesign Consultant $86,450 UC IT Staff Augmentation (Sogeti) $56,000 NH Business Transition Services/Workforce Integration $118,965 TOP, UAC, Project Support (Sogeti) $503,300 Funding Previously Approved $3,627,037 Project Connect 41
Project Connect. May 9, 2012
Project Connect May 9, 2012 Introduction Meeting Minutes Approval Project Status Report IV&V Update by Ernst & Young Other Business Public Comments Review of Actions from Meeting Scheduling of Next Meeting
More informationProject Connect Connect January 11, 2012
Project Connect January 11, 2012 Introduction Meeting Minutes Approval Project Status Report IV&V Update By Ernst & Young Other Business Public Comments Review of Actions from Meeting Scheduling of Next
More informationProject Connect. September 14, 2011
Project Connect September 14, 2011 Introduction Meeting Minutes Approval Project Status Report IV&V Update By Ernst & Young Other Business Public Comments Review of Actions from Meeting Schedule Next Meeting
More informationProject Connect. November 14, 2012
Project Connect November 14, 2012 Introduction Meeting Minutes Approval Project Status Report IV&V Update by Ernst & Young Other Business Public Comments Review of Actions from Meeting Scheduling of Next
More informationProject Connect. August 10, 2011
Project Connect August 10, 2011 Introduction Meeting Minutes Approval Project Status Report IV&V Update By Ernst & Young Other Business Public Comments Review of Actions from Meeting Schedule Next Meeting
More informationProject Connect Executive Steering Committee Update. April 10, 2013
Project Connect Executive Steering Committee Update April 10, 2013 Agenda Introduction Meeting Minutes Approval Project Status Report IV&V Update by Ernst & Young Other Business Public Comments Review
More informationProject Connect. June 22, 2011
Project Connect June 22, 2011 Introduction Meeting Minutes Approval Project Status Report IV&V Update By Ernst & Young Other Business Public Comments Review of Actions from Meeting Schedule Next Meeting
More informationProject Connect Executive Steering Committee Update. August 14, 2013
Project Connect Executive Steering Committee Update August 14, 2013 Agenda Introduction Meeting Minutes Approval Project Status Report Other Business Public Comments Review of Actions from Meeting Scheduling
More informationProject CONNECT Executive Steering Committee Update. February 26, 2014
Project CONNECT Executive Steering Committee Update February 26, 2014 Agenda Introduction Meeting Minutes Approval Project Status Report Other Business Public Comments Review of Actions from Meeting Scheduling
More informationExecutive Steering Committee Medicaid Eligibility System Project. October 24, 2014
Executive Steering Committee Medicaid Eligibility System Project October 24, 2014 Minutes -2- Federal Partner Update -3- Account Transfers Federally Facilitated Marketplace (FFM) As of October 20, 249,417
More informationWork Program Integration Initiative (WPII)
Florida Department of TRANSPORTATION Work Program Integration Initiative (WPII) Florida PALM Executive Steering Committee Meeting February 27, 2019 Florida Department of Transportation Agenda Overview
More informationEarned Value Management An Overview March 2014
Earned Value Management An Overview March 2014 SAVE International Cascadia Chapter Introduction What is Earned Value? Why is Earned Value important? What is required? Earned Value Definitions & Process
More informationExecutive Steering Committee Meeting. Department of Revenue Building 2, Room 1250 September 28, 2016
Executive Steering Committee Meeting Department of Revenue Building 2, Room 1250 Roll Call and Opening Remarks Facilitator: Robert (Budd) Kneip, Chair Review of September 14, Meeting Minutes Facilitator:
More informationCounty of Orange IT Quarterly Status Report Risk Assessment. Fiscal Year rd Quarter, January - March
CEO, Office of the CIO Program Management Office County of Orange IT Quarterly Status Report Risk Assessment Fiscal Year 2008-09 3rd Quarter, January - March Introduction The purpose of this report is
More informationEARNED VALUE MANAGEMENT. Is it worth the effort?
EARNED VALUE MANAGEMENT Is it worth the effort? Session Objectives Examples of earned value in use. Why don t more Project Managers use EMV? Road Map to EVA Maturity? What you need to know? How is our
More informationMANAGING FOR RESULTS: An Implementation Plan for the City of Portland
MANAGING FOR RESULTS: An Implementation Plan for the City of Portland Office of Management and Finance City Auditor s Office Bureau of Planning City of Portland, Oregon June, 2003 Managing for Results
More informationEARNED VALUE AS A RISK ASSESSMENT TOOL
EARNED VALUE AS A RISK ASSESSMENT TOOL Introduction Earned Value Definition: Employment of a Single Management Control System Providing Accurate, Consistent, Reliable, and Timely Data That Management at
More informationBilling and Collection Agent Report For period ending January 31, To NANC
Billing and Collection Agent Report For period ending January 31, 2016 To NANC February 4, 2016 NANPA FUND STATEMENT OF FINANCIAL POSITION JANUARY 31, 2016 Assets Cash Balance in bank account $ 3,587,973
More informationReview of Community Pharmacy Payments for 2012/13
Review of Community Pharmacy Payments for 2012/13 Corporate Finance March 2014 Contents Glossary of Terms 1 1. Executive Summary 3 2. Introduction 6 3. CPSA Overview 7 4. Annual Adjustment Summary 13 5.
More informationOregon Department of Justice
Oregon Department of Justice Ellen F. Rosenblum, Attorney General Oregon Department of Justice Division of Child Support Oregon Child Support System Project Presentation to Joint Emergency Board Interim
More informationHSCIC Financial Management and Reporting
HSCIC Financial Management and Reporting Author: Rebecca Giles/Carl Vincent Date 24 th February 2014 1 Copyright 2014, Health and Social Care Information Centre. Contents Contents 2 Introduction 3 Current
More informationThe First Steps in Implementing a Simplified Earned Value Management System
2007 Joint ISPA/SCEA National Conference & Workshop June 12-15, 2007 The First Steps in Implementing a Simplified Earned Value Management System Dorothy Tiffany, CPA, PMP NASA/GSFC EVM System Interface
More informationCitizens Property Insurance Corporation Core Insurance Solution Update. v ISAC
Citizens Property Insurance Corporation Core Insurance Solution Update v.09.12.14 ISAC Delivery Update Topics: Personal Lines Claims and Policy/Billing Status Update Schedule Overview Budget Highlights
More informationI - PROJECT STATUS OVERVIEW
Project Sponsor: Status Report : Start : Project Manager: Project R&C Category: End : I - PROJECT STATUS OVERVIEW A. Overview of project progress during reporting period: B. SPI & CPI (for
More informationBilling and Collection Agent Report For period ending August 31, 2016 To B&C Working Group September 15, 2016
Billing and Collection Agent Report For period ending August 31, 2016 To B&C Working Group September 15, 2016 Welch LLP - Chartered Professional Accountants 123 Slater Street, 3 rd floor, Ottawa, ON K1P
More informationDeloitte Shared Services, GBS & BPO Conference
Deloitte Shared Services, GBS & BPO Conference Focus 9: Delivering operational transfer pricing within a GBS environment Rachel Taylor, Rajeev Samaranayake and James Tooley, Deloitte 21-22 November 2017
More informationStatus of the Implementation of the Child Welfare Component of the North Carolina Families Accessing Services through Technology (NC FAST) System
Status of the Implementation of the Child Welfare Component of the North Carolina Families Accessing Services through Technology (NC FAST) System Report to the Joint Legislative Oversight Committee on
More informationBilling and Collection Agent Report For period ending September 30, To NANC
Billing and Collection Agent Report For period ending September 30, 2010 To NANC October 14, 2010 STATEMENT OF FINANCIAL POSITION September 30, 2010 Assets Cash Balance in bank account $ 2,926,706 Receivable
More informationA Case for Project Revenue Management. Peter Varani PMP
A Case for Project Revenue Management Peter Varani PMP A Case for Project Revenue Management PMBOK GUIDE (4 th edition) Cost 845 Revenue 3 Unisys Annual Report (2008) Cost 174 Revenue 152 2 Balanced Approach
More informationHOPE NOW. Snapshot Industry Extrapolations and HAMP Metrics
Snapshot Industry Extrapolations and HAMP Metrics Three Month Q2-215 Q3-215 Q4-215 Q1-216 Q2-216 Jun-16 Jul-16 Aug-16 Total Completed Modifications 119,658 97,773 84,798 86,167 1,198 41,872 34,815 36,6
More informationBilling and Collection Agent Report For period ending April 30, To NANC
Billing and Collection Agent Report For period ending April 30, 2011 To NANC May 17, 2011 STATEMENT OF FINANCIAL POSITION April 30, 2011 Assets Cash Balance in bank account $ 1,824,073 Receivable from
More informationCommon Agricultural Policy Futures programme
Common Agricultural Policy Futures programme Further update EMBARGOED UNTIL 00.01 HOURS THURSDAY 15 JUNE 2017 Prepared by Audit Scotland June 2017 Auditor General for Scotland The Auditor General s role
More informationFrom Suspicion to Invaluable Transition of Two Project Managers
From Suspicion to Invaluable Transition of Two Project Managers June 2010 Shilpi Kumar & Sunita Raman Agenda Unisys and HOLMES 2 Nature of Projects and Roles Why EVA? How? EVA in Development Projects Transition
More informationApprove Assure Note. Board of Directors Meeting Report 31 July Agenda item 254/13. Title. Sponsoring Director. Authors.
Board of Directors Meeting Report 31 July 213 Agenda item 254/13 Title Quarter One Cost Improvement Programme Update Sponsoring Director Jacqueline Totterdell Chief Executive Authors Purpose Liam Slattery
More informationRisk Management User Guide. Prepared By: Neville Turbit Version Feb /01/2009 Risk Management User Guide Page 1 of 36
Risk Management User Guide Prepared By: Neville Turbit Version 1.0 1 Feb 09 22/01/2009 Risk Management User Guide Page 1 of 36 Table of Contents Document Origin...2 Change History...2 Risk Guidelines...
More information2011 Budget Initial Stakeholder Call
2011 Budget Initial Stakeholder Call Michael Epstein Director of Financial Planning June 23, 2010 Agenda TOPIC PRESENTER Introduction Steve Berberich Budget principles & strategic initiatives Steve Berberich
More informationOracle. Project Portfolio Management Cloud Using Project Performance Reporting. Release 13 (update 18B)
Oracle Project Portfolio Management Cloud Release 13 (update 18B) Release 13 (update 18B) Part Number E94696-05 Copyright 2011-2018, Oracle and/or its affiliates. All rights reserved. Authors: Sandeep
More informationBilling and Collection Agent Report For period ending January 31, To B&C Working Group
Billing and Collection Agent Report For period ending January 31, 2018 To B&C Working Group February 5, 2018 NANPA FUND STATEMENT OF FINANCIAL POSITION January 31, 2018 Assets Cash in bank $ 4,550,060
More informationBilling and Collection Agent Report For period ending April 30, To FCC Contract Oversight Sub Committee
Billing and Collection Agent Report For period ending April 30, 2018 To FCC Contract Oversight Sub Committee May 10, 2018 NANPA FUND STATEMENT OF FINANCIAL POSITION April 30, 2018 Assets Cash in bank $
More informationResource Allocation, Management, and Planning Steering Committee #7
Resource Allocation, Management, and Planning Steering #7 August 28, 2018 1 Agenda Huron is pleased to partner with WKU on this resource allocation, management, and planning ( RAMP ) initiative. Our goals
More informationPortfolio Project Performance Reporting. Client Case Study
Portfolio Project Performance Reporting Client Case Study MetaPM 2016 The Challenge MetaPM s client need a mechanism to enable them to balance, reprioritise and provide recommendations (backed up by data)
More informationDepartment of Homeland Security Office of Inspector General
Department of Homeland Security Office of Inspector General Immigration and Customs Enforcement Information Technology Management Progresses But Challenges Remain OIG-10-90 May 2010 Office of Inspector
More informationGate Value Method Overview document
Gate Value Method Overview document Version 7 Dated 7 th May 2009 Author: Martin Vaughan Note: This document has been prepared by Core Consulting Group to explain the Gate Value Method. While any person
More informationEarned Schedule .EMERGING PRACTICE. Eleanor Haupt IPPM. ASC/FMCE Wright-Patterson AFB OH ANL327
Integrated Project Performance Management.EMERGING PRACTICE. Earned Schedule Eleanor Haupt ASC/FMCE Wright-Patterson AFB OH eleanor.haupt@wpafb.af.mil 937-656-5482 ANL327 1 Required Legal Notices ***CAUTION***.EMERGING
More informationDurham Orange Joint Staff Working Group Meeting Agenda October 10, :30 pm 4:00 pm Durham City Hall, Transportation 4B
Durham Orange Joint Staff Working Group Meeting Agenda October 10, 2018 2:30 pm 4:00 pm Durham City Hall, Transportation 4B 1. Call to Order/Roll Call 2. Election Chair Position 3. Open Issues a. FY2019
More informationFiscal Year 2018 Project 1 Annual Budget
Fiscal Year 2018 Project 1 Annual Budget Table of Contents Table Page Summary 3 Summary of Costs Table 1 4 Treasury Related Expenses Table 2 5 Summary of Full Time Equivalent Table 3 6 Positions Cost-to-Cash
More informationhealthcare; 6. To play an active and influential role in shaping SE London and London wide X commissioning.
GOVERNING BODY Title of paper: Finance Update Month 4 Date of meeting: 5 th September 2018 Presented by: David Maloney Title: Chief Finance Officer & email contact: D.Maloney@nhs.net Prepared by: Nick
More informationPrepared by DCMA Lockheed Martin Fort Worth
Joint Strike Fighter Lightning II Monthly Assessment Report Prepared by DCMA Lockheed Martin Fort Worth January 2010 THIS DOCUMENT CONTAINS CONTRACTOR INFORMATION WHICH MAY BE PROPRIETARY AND PROTECTED
More information2019 Budget and Grid Management Charge Initial Stakeholder Meeting
2019 Budget and Grid Management Charge Initial Stakeholder Meeting July 24, 2018 Agenda Topic: Welcome and Introductions Presenter: Kristina Osborne 2019 Budget Process & GMC Rate Outlook April Gordon
More informationHOPE NOW. Snapshot Industry Extrapolations and HAMP Metrics
Snapshot Industry Extrapolations and HAMP Metrics Three Month Q4-2016 Q1-2017 Q2-2017 Q3-2017 Q4-2017 Oct-17 Nov-17 Dec-17 Total Completed Modifications 85,357 89,213 78,302 54,318 56,355 19,400 18,819
More informationSCOA Integrated Consultative Forum feedback from the City of Cape Town. 18 & 19 September 2014
SCOA Integrated Consultative Forum feedback from the City of Cape Town 18 & 19 September 2014 AGENDA 1. Piloting Project Plan 1.1 High level project plan - Metros 1.2 Challenges and inhibiting factors
More informationOffice of Audit and Evaluation. Audit of Major Capital Project Management
Office of Audit and Evaluation Audit of Major Capital Project Management August 2018 TABLE OF CONTENTS EXECUTIVE SUMMARY AND CONCLUSION...I 1.0 INTRODUCTION... 1 2.0 BACKGROUND AND CONTEXT... 1 3.0 AUDIT
More informationEconomic and Revenue Update
Economic and Revenue Update A Briefing for the Money Committees Aubrey L. Layne, Jr. Secretary of Finance Commonwealth of Virginia www.finance.virginia.gov January 2018 Topics for Discussion National and
More informationONTARIO-MICHIGAN BORDER TRANSPORTATION PARTNERSHIP Planning/Need and Feasibility Study. 1. Work Accomplished This Period (4 Weeks)
ONTARIO-MICHIGAN BORDER TRANSPORTATION PARTNERSHIP Planning/Need and Feasibility Study MONTHLY PROGRESS REPORT #19 Period Ending September 30, 2003 1. Work Accomplished This Period (4 Weeks) Strategic
More informationCalifornia ISO. Flexible Ramping Product Uncertainty Calculation and Implementation Issues. April 18, 2018
California Independent System Operator Corporation California ISO Flexible Ramping Product Uncertainty Calculation and Implementation Issues April 18, 2018 Prepared by: Kyle Westendorf, Department of Market
More informationImplementing the DSRIP Finance Function
Implementing the DSRIP Finance Function DSRIP Support Team February 27, 2015 February 2015 2 Contents Developing the DSRIP Finance Function Defining The Vision Responsibilities/Structural Considerations
More informationACA Reporting E-File Errors, Penalties & Exchange Notices
ACA Reporting E-File Errors, Penalties & Exchange Notices Agenda 1). Who is ACA Reporting Service? (quickly) 2). Setting the ACA Reporting Stage 3). The Process Leading up to E-Filing 4). E-Filing through
More informationCreating Internal Transparency to Forecast Workforce Needs
Creating Internal Transparency to Forecast Workforce Needs Robert D. Motion Director, Workforce Planning & Strategy Intelligence, Information & Services November 17, 201 Copyright 201 Raytheon Company.
More informationArkansas Works Overview. Work And Community Engagement Requirement
1 Arkansas Works Overview Work And Community Engagement Requirement Arkansas Works Populations & Work and Community Engagement Requirement 2 Arkansas Works enrollees will fall into three categories for
More informationEarned Value and PRINCE2 Alex Davis. Programme Manager Close Combat Programme Support Office Ministry of Defence
Earned Value and PRINCE2 Alex Davis Programme Manager Close Combat Programme Support Office Ministry of Defence PRINCE2 is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom
More informationOracle. Project Portfolio Management Cloud Using Project Performance Reporting. Release 13 (update 17D)
Oracle Project Portfolio Management Cloud Release 13 (update 17D) Release 13 (update 17D) Part Number E89308-02 Copyright 2011-2017, Oracle and/or its affiliates. All rights reserved. Authors: Sandeep
More information3.35 Debt Relief Program. Introduction. Scope and Objectives
Introduction The Department of Municipal and Provincial Affairs is responsible for matters relating to local government, municipal financing, assessment, urban and rural planning, development and engineering,
More informationReview of Membership Developments
RIPE Network Coordination Centre Review of Membership Developments 7 October 2009/ GM / Lisbon http://www.ripe.net 1 Applications development RIPE Network Coordination Centre 140 120 100 80 60 2007 2008
More informationMonth 10 Finance Report
TAUNTON & SOMERSET NHS FOUNDATION TRUST Month 10 Finance Report Report to: Trust Board on 24 February 2016 Purpose of the Report: The purpose of the report is to update the Board on the Month 10 financial
More informationHow Performance Management and Beyond Budgeting are Transforming DFW Airport
How Performance Management and Beyond Budgeting are Transforming DFW Airport Beyond Budgeting Annual Conference April 25, Chris Poinsatte, EVP and CFO Dallas Fort Worth International Airport Finance Challenges
More informationEarned Schedule Analysis
Integrated Project Performance Management.EMERGING PRACTICE. Earned Schedule Analysis A Better Set of Schedule Metrics Eleanor Haupt President PMI College of Performance Management Walt Lipke Member PMI
More informationSelf-Assessment Questions for Module 07 Project Cost Management
Self-Assessment Questions for Module 07 Project Cost Management Question 1: Which of the following regarding Analogous Estimating and Parametric Estimating is incorrect? A.) Parametric Estimating uses
More informationIntroduction to Project Management. Modeling after NYS ITS
Introduction to Project Management Modeling after NYS ITS What is Project Management? Project management is the application of knowledge, skills, tools and techniques to project activities to meet project
More informationUpdates & Milestones re: Peak Demand Reduction. EEAC Consultants (with PA contributions) (Revised, 3/13/17)
Updates & Milestones re: Peak Demand Reduction EEAC Consultants (with PA contributions) (Revised, 3/13/17) Key Work Streams in 2016-2018 Following the Analytical Framework Cost-Effectiveness Framework
More informationImplementing a New Compensation Plan How did it go? Progress and Pitfalls
Implementing a New Compensation Plan How did it go? Progress and Pitfalls J. Michael Scalzone, MD, MHCM Executive Vice President Medical Affairs The Guthrie Clinic Presentation Overview About The Guthrie
More informationPerformance Management Accountability Meeting Data as of October, 2012
Performance Management Accountability Meeting Data as of October, 2012 Richard A. Davey, Secretary & CEO Office of Performance Management and Innovation Celia J. Blue, Assistant Secretary November 27,
More information[Project Title] Project Scope Statement
[Project Title] Project Scope Statement Prepared by: Version: Date: Project Sponsor: Project Manager: Senior Manager: Approval Signatures Project Sponsor Project Manager Senior Manager/s Other Stakeholder
More informationPMP. Preparation Training. Cost Management. Your key in Successful Project Management. Cost Management Processes. Chapter 7 6/7/2005
PMP Preparation Training Your key in Successful Project Management Akram Al-Najjar, PMP Cost Management Processes Chapter 7 Cost Management Slide 2 1 AGENDA What is Cost Management? Cost Management Processes
More informationBilling and Collection Agent Report For period ending November 30, To FCC Contract Oversight Sub Committee
Billing and Collection Agent Report For period ending November 30, 2018 To FCC Contract Oversight Sub Committee December 10, 2018 NANPA FUND STATEMENT OF FINANCIAL POSITION November 30, 2018 Assets Cash
More information4/14/2017. Unit 7 Slide Lectures of 19/20/21 April 2017 PROJECT PROGRESS AND PROJECT PERFORMANCE ASSESSMENT (CH. 13)
PROJECT AND COMMUNICATION MANAGEMENT Academic Year 2016/2017 PROJECT PROGRESS AND PROJECT PERFORMANCE ASSESSMENT (CH. 13) Unit 7 Slide 7.2.1 Lectures of 19/20/21 April 2017 Structure of a Project Monitoring
More informationBUDGET WORKING GROUP
BUDGET WORKING GROUP 1 Presenters Xavier Calvez ICANN CFO Cyrus Namazi ICANN VP DNS Industry Engagement Becky Nash ICANN VP Finance Jessica Castillo ICANN Project Coordinator 2 Budget Working Group - Part
More informationXML Publisher Balance Sheet Vision Operations (USA) Feb-02
Page:1 Apr-01 May-01 Jun-01 Jul-01 ASSETS Current Assets Cash and Short Term Investments 15,862,304 51,998,607 9,198,226 Accounts Receivable - Net of Allowance 2,560,786
More informationThe Financial Reporting Checklists Every Firm should be Doing
The Financial Reporting Checklists Every Firm should be Doing Presented by Rebecca Kelley, CPA Maggie Kennedy, CPA FM34 4/5/2017 3:00 PM - 4:15 PM The handouts and presentations attached are copyright
More informationMONITORING REPORT FOR THE COMMUNITY PHARMACY SERVICES AGREEMENT (CPSA) Report for: May 2018 Reporting on: March 2018
MONITORING REPORT FOR THE COMMUNITY PHARMACY SERVICES AGREEMENT (CPSA) Report for: May 2018 Reporting on: HEADLINE MEASURES Patient Centric Active LTC Patient Registrations Growth Initial Items Growth
More informationHOUSING AUTHORITY REPORT
HOUSING AUTHORITY REPORT DATE ISSUED: January 20, 2012 REPORT NO: HAR12-013 ATTENTION: SUBJECT: Chair and Members of the Housing Authority of the City of San Diego For the Agenda of February 28, 2012 COUNCIL
More informationAnnual Report OVERVIEW OF MAJOR INFORMATION RESOURCES PROJECTS REPORTED TO THE QUALITY ASSURANCE TEAM. December 2017 to November 2018
Annual Report OVERVIEW OF MAJOR INFORMATION RESOURCES PROJECTS REPORTED TO THE QUALITY ASSURANCE TEAM December 2017 to November 2018 Quality Assurance Team Comptroller of Public Accounts Department of
More informationTERMS OF REFERENCE FOR THE FINANCE AND AUDIT COMMITTEE
I. PURPOSE A. The primary function of the Finance and Audit Committee (the Committee ) is to assist the Board in fulfilling its oversight responsibilities by reviewing: i) the accuracy of financial information
More informationORANGE UNIFIED SCHOOL DISTRICT Measure S Bond Program September 2017 Monthly Progress Report
ORANGE UNIFIED SCHOOL DISTRICT Measure S Bond Program September 2017 Monthly Progress Report PERIOD COVERED: September 1 30, 2017 FISCAL YEAR FY 2017 2018 PROGRESS REPORT NO. PR 03 1718 003 PREPARED BY:
More informationOracle Project Portfolio Management Cloud Using Project Performance Reporting
Oracle Project Portfolio Management Cloud Using Project Performance Reporting Release 9 This guide also applies to on-premise implementations Oracle Project Portfolio Management Cloud Part Number E53157-01
More informationFY18 Operating Plan and Budget. Xavier Calvez, Becky Nash, Taryn Presley
FY18 Operating Plan and Budget Xavier Calvez, Becky Nash, Taryn Presley Introduction Meet the Planning Team Xavier Calvez Project Sponsor Becky Nash Project Owner Taryn Presley Project Manager and Budget
More informationAlameda Health System
Alameda Health System Status Report Long Term Financial Planning Compliance with the Permanent Agreement March 9, 2015 Dan Boggan, Jr., Interim CEO David Cox, CFO 1 AHS Monthly Report Cash, Accounts Payable,
More informationAgenda (Items may be taken out of order) D. Active Construction Project Status Report (for receive and file only)
I. ROLL CALL LOS ANGELES COMMUNITY COLLEGE DISTRICT BOARD OF TRUSTEES FACILITIES MASTER PLANNING & OVERSIGHT COMMITTEE Educational Services Center Board Room 770 Wilshire Boulevard Los Angeles, CA 90017
More informationINSE 6230 Total Quality Project Management
Lecture 5 Project Cost Management Project cost management introduction Estimating costs Budget Earned Value Management (EVM) EVM projections 2 IT projects have a poor track record for meeting budget goals
More informationBudget Process Overview and Cost Allocation Methodology
Budget Process Overview and Cost Allocation Methodology 1 Cost Allocation Agreement Guiding Principles Operate a consolidated regional public transportation system within and between the Participating
More informationOracle Project Portfolio Management Cloud Using Project Performance Reporting
Oracle Project Portfolio Management Cloud Using Project Performance Reporting Release 10 This guide also applies to on-premise implementations Oracle Project Portfolio Management Cloud Part Number E61454-02
More informationNYISO Capital Budgeting Process. Draft 01/13/03
NYISO Capital Budgeting Process Draft 01/13/03 1 1.0 INTRODUCTION An effective, capital budgeting process is essential to ensure sound capital investment decisions. This report details a recommended approach
More informationFINANCIAL RESULTS AND COMPANY OVERVIEW Second-Quarter Performance
FINANCIAL RESULTS AND COMPANY OVERVIEW 08 Second-Quarter Performance September 5 th, 08 Disclaimer Forward-Looking Statements and Preliminary Results This presentation includes forward-looking statements
More informationMONTHLY FINANCIAL REPORT June 2009
California Independent System Operator MONTHLY FINANCIAL REPORT June 2009 151 Blue Ravine Road Folsom, CA 95630 (916) 351-4000 CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION MONTHLY FINANCIAL REPORT
More informationCumulative trends Problems and issues since last report
Project Progress Report Format Progress since last report Current status of project 1. Schedule 2. Cost 3. Scope Cumulative trends Problems and issues since last report 1. Actions and resolution of earlier
More informationLRD IWTF Projects Update Inland Waterway Users Board
LRD IWTF Projects Update Inland Waterway Users Board MS. JEANINE HOEY, PE, PMP CHIEF, E&C Division Pittsburgh District 13 Dec 2016 The views, opinions and findings contained in this report are those of
More informationBig Walnut Local School District
Big Walnut Local School District Monthly Financial Report for the month ended September 30, 2013 Prepared By: Felicia Drummey Treasurer BIG WALNUT LOCAL SCHOOL DISTRICT SUMMARY OF YEAR TO DATE FINANCIAL
More informationEarning Value From Risk
Earning Value From Risk Ron Higuera March 1999 rph@cise.cmu.edu Agenda Overview Earned Value Overview Risk Management Investment Strategy Summary 2 Presentation Objective Relate risk management and earned
More informationFinancial & Business Highlights For the Year Ended June 30, 2017
Financial & Business Highlights For the Year Ended June, 17 17 16 15 14 13 12 Profit and Loss Account Operating Revenue 858 590 648 415 172 174 Investment gains net 5 162 909 825 322 516 Other 262 146
More informationHUD NSP-1 Reporting Apr 2010 Grantee Report - New Mexico State Program
HUD NSP-1 Reporting Apr 2010 Grantee Report - State Program State Program NSP-1 Grant Amount is $19,600,000 $9,355,381 (47.7%) has been committed $4,010,874 (20.5%) has been expended Grant Number HUD Region
More informationLog of Contract Variations. All approved Contract Variations since the start of the contract are shown below.
Log of Contract Variations All approved Contract Variations since the start contract are shown below. CR093 CR088 CR087 CR086 CR085 CR084 CR081 CR079 CR078 CR077 Commitment /Variation Print Gain-share
More information