Project Connect Executive Steering Committee Update. August 14, 2013

Size: px
Start display at page:

Download "Project Connect Executive Steering Committee Update. August 14, 2013"

Transcription

1 Project Connect Executive Steering Committee Update August 14, 2013

2 Agenda Introduction Meeting Minutes Approval Project Status Report Other Business Public Comments Review of Actions from Meeting Scheduling of Next Meeting September 11 Adjourn 2

3 Project Status Report Budget and Timeline Project Update Current and Upcoming Activities Risks and Issues Key Project Dates 3

4 Project Timeline 4

5 Budget & EAC Summary Overall Project Budget & Estimated Variance Rebaselined Budget Allocated Contingency & Management Reserves Supplemental Budget Requests REA Grant Updated Project Budget Estimate at Completion Project Variance Project Funding OPS 217, , ,870 (51,100) Expenses 7,240,310 2,448, ,689,004 9,901,449 (212,444) OCO (Hardware) 1,441,425 (905,527) , , ,089 Contracted Services Project Management & Support Project Management Office 2,019, ,019,270 1,996,790 22,480 Project & Operational Support 3,694,500 (1,420,155) 648, ,474 3,042,669 2,875, ,879 Outside Legal 230, , ,960 1,692 ITN Development 512, , ,700 0 Business Transition 3,945,916 99, ,730 4,179,847 4,165,393 14,453 Other Contracted Services 164, , , ,648 (25,858) Total Project Management & Support 10,567,828 (1,152,955) 648, ,204 10,317,927 10,138, ,646 IV&V Services 2,019, ,019,940 2,026,065 (6,125) Benefits Realization Strategy 239,391 1, , ,391 1,915 Organizational Change Management 467,520 8, , ,520 8,383 System Integrator (SI) Services 28,285,557 3,528, ,925 1,054,586 33,630,772 33,678,531 (47,760) SI Hardware & Software 9,095,608 (828,563) 0 0 8,267,045 8,203,495 63,550 Project Reserves 122, , ,695 Project Funding Totals 59,698,044 3,100,651 1,410,775 1,308,790 65,518,259 65,313, ,849 Contingency/Management Reserves 3,100, ,460 <- Geographic Solutions, WF Integration PM Total Project Funding 62,798,694 2,006,250 & Misc. Deloitte CRs 5

6 Budget Tracking Project Funding - Cumulative by Quarter 70,000,000 60,000,000 50,000,000 Budgeted: Forecast: $65,518,259 65,313,411 Variance: $ 204,848 40,000,000 30,000,000 20,000,000 10,000,000 0 FY11 Q1 FY11 Q2 FY11 Q3 FY11 Q4 FY12 Q1 FY12 Q2 FY12 Q3 FY12 Q4 FY13 Q1 FY13 Q2 FY13 Q3 FY13 Q4 FY14 Q1 FY14 Q2 FY14 Q3 FY14 Q4 FY 15 Q1 FY 15 Q2 Budget Forecast Committed 6

7 Management Reserve Allocation Current Management Reserve $0 Current Budget Positive Variance $204,849 Available Budget $204,849 Management Reserve & Positive Variance Allocations Final Four Critical Change Requests ($378,423) Software Licenses for New Staff ($415,589) 7

8 Management Reserve Allocation Potential Savings SIDES Contingency $489,889 Outside Legal $100,000 Rent/Supplies $40,000 Potential Allocations RAAC Scanners ($100,166) RAAC Order Conversion/Web Access (TBD) 8

9 Amendment 12 4 Critical Change Requests for the Go Live Release 1.0 #217.1 EUC/RES Interface Workaround #279 EUC Quarter Change Enhancements #282 Agent Assisted Claims #283 New I&A Fact Findings 9

10 Software Licenses Amendment licenses for FileNet (All Connect Users) 160 Net New Users True-up 1,171 Total Connect Users 71 licenses for Genesys (Connect Telephony Environment) 101 Net New Users less 30 spare licenses 5 licenses for Business Objects (Ad Hoc Query) 33 licenses for Brava (Redaction Tool) 10

11 Amendment 12 Includes 54 Post-Go Live Change Requests 9 Change Requests for Release 1.1 December Change Requests for Release 1.2 March Change Requests for Release 2.0 June 2014 Description Cost Release 1.1 Change Requests $1,582,490 Release 1.2 Change Requests $3,200,775 Release 2.0 Change Requests $1,934,476 Total Cost $6,717,741 11

12 High-level Timeline Weekdays M-Su -> 8/11-8/18 8/19-8/25 8/26-9/1 9/2-9/8 9/9-9/15 9/16-9/22 9/23-9/29 9/30-10/6 UAT Test Scripts DEO Preliminary Go/No Go External Communications Outreach Production IVR Rollout UAT Defects Closeout ESC Steering Committee UAT Phase Gate & DEO Final Go/No Go Regression Testing/Code Freeze Legacy Down & Processing Conversion Image Loads Backups/Validations/Batches Connect Live! 12

13 User Acceptance Testing As of August 6 th DEO has executed 2,689 scripts and was slightly ahead of plan to execute all 3,704 scripts by Friday Total scripts reduced from 3,778 due to automation and final reconciliation Of the 2,689 scripts executed, 2425 scripts passed (90%), 264 failed of which 67 scripts are blocked 13

14 UAT Defect Summary Defects Functional Track OPEN BREAKDOWN GRAND TOTAL CLOSED OPEN DEV IN_BUILD SME TEST Claims Monetary Issues & Adjudication Payment & Charging Reports Collections Appeals Program Integrity Infrastructure Framework (Security) Other (CCS) Grand Total 2,871 2,092 (73%) (25%) 123 (16%) 461 (59%) Severity Grand Total CLOSED OPEN DEV OPEN BREAKDOWN IN_BUILD SME TEST % Closed % Open 1-Fatal (9%) % 16% 2-Severe 1,376 1, (42%) % 24% 3-Medium (39%) % 37% 4-Low (10%) % 34% Grand Total 2,871 2,

15 UAT Defect Trend OVERALL: The graph depicts the number of defects reducing over time by UAT Completion. UAT exit criteria is 0 SEV1s, 25 SEV2s, and 95% overall pass rate 1000 Defect Trend Planned vs. Actual Planned Defect Resolution Planned New Defects Planned Cumulative Defects Actual Defect Resolution Actual New Defects Actual Cumulative Defects Jul 8-Jul 15-Jul 22-Jul 29-Jul 5-Aug 12-Aug 19-Aug 26-Aug 2-Sep 9-Sep Week Ending 1-Jul 8-Jul 15-Jul 22-Jul 29-Jul 5-Aug 12-Aug 19-Aug 26-Aug 2-Sep 9-Sep Planned Open Actual Open Actual Open in DEV Actual Open in TEST Planned Identified Actual Identified Planned Fix by DEV Actual Fix by DEV Planned Close by TEST Actual Closed by TEST

16 Operational Readiness OVERALL: Kicked off on August 5 with approximately 100 operational scenarios to walk through over the ensuing 4 weeks. Planning Plan is to address 25 operational scenarios per week distributed across business units Scenario to be identified by level of priority, thus prioritizing higher volume & business critical scenarios initially Process SMEs & Business Unit Leads will work 2 hours each day Business Unit Lead will be guided by SME to understand and review the operational scenario flow Output Document operational process changes & assess need for supplemental material Identification of potential change requests Identification of application defects 16

17 IVR Rollout Status VoIP/IVR for the Contact Center on track for an early rollout on August 26 End user training for early cutover started last week in Orlando Training continues in Ft. Lauderdale and Tallahassee 17

18 Project Status Train the Trainer completed and End User Training officially kicked off last week! Enhanced Claimant Authentication (LexisNexis) development activities proceeding Will need to be integrated into UAT The LexisNexis contract is in final review and approval process 18

19 Development Activity Status Amendment 10/11/12 Release 1.0 Change Requests (18) underway for October 1 Go Live This is of particular concern to ensure this work is completed in time to integrate into UAT RAAC Bridge Design artifacts complete Document review and development is in progress Test scenarios are also being documented 19

20 Conversion Continuing to identify and fix legacy data issues Addressing the converted data impacts to batches and schedules Closing out conversion defects Completing A&C reports, validation queries and executing interfaces 20

21 Communications Status Claimants Employers and Third Party Administrators Workforce Boards and One Stops Governor s Office and Legislators Media RA Staff Partner Agencies Advocates Business Groups 21

22 Implementation Planning Developed War Room Plan Preparing Contact Lists & Communications Channels Defining Roles & Responsibilities Implementation Plan Submitted Deloitte Contract Deliverable 24 22

23 War Room Support Process Internal Staff Staff will work through on-site support Super Users, who have Functional Leads for escalation. Leads interact with the War Room to further escalate question and/or issues for resolution. Provide answers to support resources Assess issue as user error or system based Determine severity and open tickets for system and process issues Monitor process related tickets in Implementation Queue Contact SMEs to resolve process issues Centralize all communication items Send out regular support communications Receive conversion issue updates from conversion team War Room SMEs Question/Escalation Answers and ticket updates: Daily Status Calls Emergency messages Internal Users Question On Site Support (Super Users) Question/Escalation On Site Support Leads Reach out to site support (Super Users) with questions Call the IT Help Desk directly only for local infrastructure issues (equipment & software problems) & password resets Answer Provide first tier of support Escalate issues to Leads Communicate issue resolution to staff Answer/Updates Calls the War Room to report issues / Communicate issue resolution to Super Users & staff

24 Super Users Super Users Super Users Operating The War Room The War Room is a business focused knowledge center and hub to expedite business and system-wide issue resolution, communication of updates and FAQs. Lead Lead Lead Executive Communication Desk War Room SMEs Updates Issue Breakouts e.g. Claims Executives, Site Managers & DEO Communications Office e.g. Technical War Room SMEs Open bridge 30 minutes prior to call center open and close one hour after centers stop receiving calls Detailed problem solving/triage will be moved to a breakout room session Only Leads allowed to call to bridge Unauthorized callers will be redirected to appropriate contacts Calls will be managed in a controlled order of calls received Wherever possible, answers will be provided during the call, including process, training and technical All calls will be logged in ALM, regardless of issue Updates project web site as appropriate One moderator controls and facilitates call flow Issue Breakouts Used to bring working teams together to perform deep dive analysis/triage of issues Leads (and/or Super Users as needed) will call in to separate issue breakout bridges Held in separate conference rooms Executive Communication Desk Dedicated number for executive team to call for updates at any time Hourly update calls will be conducted to communicate updates Does not provide communications externally /publicly Wherever possible, answers will be provided during the call, but may need to validate with SMEs first

25 Key War Room Resources The Training Room in Northwood Centre will be used for the War Room. SMEs, IT Help Desk Rep, Security Admin, Deloitte IT, Facilitator: Angela Support Bridge 850 XXX XXXX Extra SMEs Extra SMEs On Site Support Leads (authorized callers to bridge): Tallahassee Contact Center Adjudication Appeals (Caldwell) Appeals (Winewood) Benefits Operations (Winewood) Program Integrity (Winewood) Benefit Payment (Winewood) Central Intake (Collins) Orlando Contact Center Adjudication Ft. Lauderdale Contact Center Adjudication Appeals Jacksonville Adjudication Appeals CONNECT SMEs (monitoring the bridge): Contact Center Adjudication Appeals BPC Benefit Operations Program Integrity Central Intake & Any Global/Correspondence Hourly Update Bridge 850 XXX XXXX Executive Communications: DEO War Room Management: DEO & Deloitte

26 Change Requests Total Functional CRs Received 298 Withdrawn/Closed (141) Total CRs 157 Amendment 7/8/9/10/11 62 Amendment DEO Development Rel. 1.0 & On Hold Non-Critical 10 Total CRs

27 Current Project Risks Open risks actively being monitored Risk #29 Availability of External System Resources Risk #42 Early Close Test was not approved Risk #43 DEO Backup Solution for Connect Risk #44 Remaining Workaround Impacts Risk #45 Timing of Post-Go Live CRs Risk #46 Support Plan for One Stop Centers 27

28 Current Project Issues Open Issues actively being managed Issue #11 Legacy System Changes Continues to require close coordination Issue #13 LexisNexis Contract Working to get a contract in place Issue #14 Quality of IVR Recorded Scripts Working with vendor to resolve quality issues Issue #15 Central Intake Move Move schedule in early September 28

29 Go Live Checkpoints Area Project Activities Contract Obligations Remaining Development Status IVR Rollout Update SME/Lead Assessment Operational Readiness Training Readiness Communications Conversion Implementation Planning Post Go Live Support Readiness Responsibility McCullion Tahaliyani (Defects) Tahaliyani Tahaliyani/McCullion Clendenning/Smith Smith/Bakas Smith/Bakas Russell Tahaliyani Tahaliyani Tahaliyani/McCullion 29

30 Key Project Dates August 1-31 Operational Readiness Testing August 23 Preliminary Go Live Go/No Go Decision August 26 Early Cutover IVR/Call Center Go Live! August 30 Amendment 10/11/12 Dev/Test Phase Gate September 11 ESC Meeting September 16 User Acceptance Test Phase Gate and Final Connect Go Live Go/No Go Decision October 1 GO LIVE! October 9 ESC Meeting 30

31 Questions? 31

32 Agenda Introduction Meeting Minutes Approval Project Status Report IV&V Update by Ernst & Young Other Business Public Comments Review of Actions from Meeting Scheduling of Next Meeting August 14 Adjourn 32

33 Project CONNECT Independent Verification and Validation Monthly Assessment Report Summary 07 August 2013

34 Topics for discussion General IV&V overview Overall risk state and trending Key indicators Overall project performance Projected milestone slippage Upcoming IV&V activities Supporting information Summary of changes IV&V ratings summary Open deficiencies Project milestones Open technology facets Page 34

35 General IV&V overview Overall IV&V risk state: Green The Project CONNECT Team has satisfactorily addressed all deficiencies identified by the IV&V Team. The project is within the prescribed control limits. Based on the current schedule performance index (SPI), the User Acceptance Testing Phase Gate is projected to be completed one (1) day late. No new deficiencies identified since the last report. Next IV&V monthly assessment report will be published on 7 October Page 35

36 Overall risk state and trending Risk state of Project CONNECT Risk state with trending Program Governance As of 07 August 2013 Program Cost management P1 Time management Functionality Technical architecture Functional requirements Resource management T1 T4 T7 P3 Operations support High-level system architecture Requirements mapping P2 Risk adjusted financials T2 T5 P6 Non-functional requirements Legacy integration Performance management P5 Risk management T3 T6 P9 B1 Business objectives and value alignment Cost, benefit and risk B4 P4 Quality management P8 B2 B5 Business process Benefits tracking Investment governance and approval Change management P7 Organization design B3 Communication B6 Reporting and value monitoring B9 P9 P6 P8 P3 P5 P7 P2 P4 T3 P1 B3 B2 T6 T1 B1 B6 T5 B5 T4 B4 B9 T8 B8 T7 B7 Technology T8 Stabilization T9 B7 Compliance and regulatory B8 Business Technology T2 T9 Risk state with trending Business Indicates that the area being assessed has critical issues that will result in significant risk to the project most likely resulting in either the inability to achieve the outcomes, inability to meet the projected schedule, or a significant cost over-run. Requires immediate action. Indicates that the area being assessed has issues that need to be resolved; inefficiencies exist. Current process/method can be used with refinement. Indicates that the area being assessed did not have significant issues to report. Continued monitoring should be performed. Indicates that the area being assessed has incomplete information available for a conclusive finding or is not applicable. Page 36

37 Key indicators Indicator Value Comment Is the project approach sound? Yes Is the project on time? Yes The project is within the prescribed control limits. Is the project on budget? Yes Is scope being managed so there is no scope creep? Yes The work being completed as part of the project is within the scope of the project as defined for Project CONNECT. What are the project s future risks? N/A The Project CONNECT Team has satisfactorily addressed all deficiencies identified by the IV&V Team. Are the project s risks increasing or decreasing? Are there new or emerging technological solutions that will affect the project s technology assumptions? Decreasing No The Project CONNECT Team has satisfactorily addressed all deficiencies identified by the IV&V Team. New and emerging technologies were considered in the Feasibility Study. None have an adverse effect on the project s technological assumptions. Page 37

38 Overall project performance Behind schedule and underspent SPI Behind schedule and overspent As of 26 July: SPI = 1.00 CPI = 0.96 Green area indicates within tolerance of +/- 5% for both SPI and CPI. Amber area indicates review is required and corrective actions may be necessary. PC project performance CPI Ahead of schedule and underspent Ahead of schedule and overspent Red area indicates out-oftolerance and corrective actions are necessary. This chart shows the SPI and CPI plotted as points against the tolerance ranges set up for the project. SPI is equal to 1.00 and trending flat: The project is on schedule. Tasks are being completed in the time originally scheduled. CPI is equal to 0.96 and trending flat: The project is on budget. The effort required to complete tasks is equal to the original budget. Conclusions: The project is within the prescribed control limits. The project is on schedule and on budget. Page 38

39 Projected milestone slippage Implementation Phase Gate UAT Phase Gate Development/Test Phase Gate Remaining Development Interim 2 Gate PC projected milestone slippage This chart shows the projected completion dates for future milestones based on historical performance using the schedule performance index (SPI). Conclusions: Core Development Interim 1 Gate Interim Development Interim Gate Design Phase Gate Design Interim Gate 3 Design Interim Gate 2 Design Interim Gate Schedule re-baselined July 2013 May 2013 Mar 2013 Jan 2013 The project is within the prescribed control limits. All future milestones are projected to be completed one (1) day behind schedule. Define Phase Gate Define Interim Gate Dec 2012 Nov 2012 Define Interim Gate 1 0 Planning Phase Gate 0 Planning Interim Gate Number of calendar days Page 39

40 Upcoming IV&V activities Participate in PC meetings IV&V review meetings with the PC Project Team Executive Steering Committee meetings Review integrated master schedule and associated project performance reports Deliverable review schedule is as follows: Deliverable Planned finish Actual finish Comment UC3-06A, Project Management Documents 24 August September 2011 Complete UC3-06B, Requirements Validation 19 August August 2011 Complete UC3-06C, Design Documents UC3-06D, Development Canceled Canceled PC-06E, Testing 21 August August 2012 Complete PC-06F, Data Conversion PC-06G, Training Canceled Canceled PC-06H, Implementation 07 October 2013 Page 40

41 Summary of changes Supporting information Item Description Deficiencies addressed New deficiencies Risk ratings Maturity ratings Interviews conducted Artifacts received There are no open deficiencies. No new deficiencies identified since the last report No risk rating changes since the last report. No maturity rating changes since the last report. No interviews conducted since the last report. Artifacts received include deliverable expectation documents, Executive Steering Committee (ESC) meeting materials, finance updates, other items, phase gate approval and deliverables, schedule, staffing model, and status reports. Page 41

42 IV&V ratings summary Number IV&V cube facet ratings and open deficiencies per month Supporting information This chart shows a summary of the IV&V cube facet ratings (red, amber, green and grey), and open deficiencies per month for the past several months. The number of cube facet risk ratings has been zero (0) since September The number of open deficiencies has been zero (0) since September Conclusions: There are no significant project risks. 5 0 Nov-12 Dec-12 Jan-13 Mar-13 May-13 Jul-13 Critical Issues Inefficiencies No Issues Not Evaluated Open Deficiencies Page 42

43 Open deficiencies No. Areas Deficiency Implications Recommendations None None None None Supporting information There are no open IV&V deficiencies with Project CONNECT. Page 43

44 Project milestones WBS Title Completion date Supporting information Original Scheduled Planned Projected Actual Design Phase Gate 12/16/ /29/ /29/ /29/ /29/ Amendment 7 CRs Design 11/02/ /02/ /28/ Amendment 8 CRs Design 01/07/ /07/ /16/ Interim Development Interim Gate Core Development Interim 1 Gate Remaining Development Interim 2 Gate Development/Test Phase Gate (includes Amendments 7 and 8) 09/28/ /28/ /26/ /26/ /25/ /25/ /23/ /21/ /11/ /11/ /12/ /12/ /28/ /28/ /28/ /28/ UAT Phase Gate 11/16/ /16/ /16/ /17/ Implementation Phase Gate (includes Amendments 7 and 8) 12/14/ /15/ /15/ /16/2013 Late Page 44

45 Open technology facets Supporting information Facet Expectations Project deliverable Planned completion Status T2 : Operations support An organizational structure and support strategy to manage the new implementation is in place. Tools exist for tracking performance of application at object levels. A maintenance strategy is developed to manage modification, migration, and retirement of products according to the release strategy. Ongoing knowledge transfer, as systems are developed. A detailed training strategy exists for training the different categories of business and technical users of the system for them to be able to adopt to the system and use it more effectively. Training documents are in place PMP Human Resource Management and Staffing Plan 3.14 PMP Knowledge Management Plan 5 Validated Requirements Document 24 Operations Documentation 06/17/11 Complete 06/17/11 Complete 06/24/11 07/15/11 08/05/11 08/30/13 Complete 26 Training Plan 12/07/12 Complete 27 Training (execution) 10/10/13 Training strategy is agreed upon, communicated and being executed. Trainers are qualified via agreed upon selection process. Training materials are standard across all modules and functions and are capturing an adequate level of detail. 28 Production System Implementation Plan 30 System Operations and Maintenance Plan 08/10/13 08/28/13 Page 45

46 Open technology facets (continued) Supporting information Facet Expectations Project deliverable Planned completion Status T9 : Stabilization An extended team has been defined across the organization and is working as an extension of the project team. Tasks have been assigned and key metrics are in place to monitor progress. 30 System Maintenance and Operations Plan KPIs 08/28/13 Long-term sustainability plans are in place to keep support and maintenance of the implementation viable. Long-term vendor contracts are implemented to maintain the system in the absence of an inhouse capability to maintain the system. A vendor management body is established to maintain the relationship with vendors to facilitate smooth delivery of outsourced services. 12-month Warranty Period 12-months Operations Support and Maintenance Agreement Executed contracts and license agreements Page 46

47 Agenda Introduction Meeting Minutes Approval Project Status Report IV&V Update by Ernst & Young Other Business Public Comments Review of Actions from Meeting Scheduling of Next Meeting September 11 Adjourn 47

48 Attachments FY13/14 + Spend Plan Graph FY13/14 + Spend Plan Details 48

49 FY13/14 + Spend Plan Graph 30 FY Project Funding - Cumulative by Month to End of Warranty Period Budgeted: $ 25,067,802 Forecast: 24,862,954 Variance: $ 204,848 KPI payments } Millions Warranty Period Begins Jul-13 Aug-13 Sep-13 Oct-13 Nov-13 Dec-13 Jan-14 Feb-14 Mar-14 Apr-14 May-14 Jun-14 Jul-14 Aug-14 Sep-14 Oct-14 FY Budget Forecast Committed 49

50 FY13/14 + Spend Plan Details FY Budget Allocation and Spend by Month - Q1 & Q2 Jul-13 Aug-13 Sep-13 Oct-13 Nov-13 Dec-13 Budget Committed Budget Forecast Budget Forecast Budget Forecast Budget Forecast Budget Forecast OPS Funding 3,800 15,022 3,800 3,800 3,800 3,800 3,800 3,800 3,800 3,800 3,800 3,800 Expenses Funding 66,284 80, , , , ,395 66, ,466 67, , , ,667 OCO Funding Contracted Services Project Management & Support 226, , , , , , , , , , ,029 88,812 IV&V Services 77,762 75, ,750 46,456 44, , ,750 46,456 44,206 Benefits Realization Strategy , , , , Organizational Change Management System Integrator (SI) Services 4,039,600 4,015, , ,255 2,725,233 4,669,763 2,480,471 2,962, , ,966 SI Hardware & Maintenance SI Software & Maintenance Project Reserves Total Contracted Services 4,343,641 4,408, ,029 1,183, , ,746 2,909,262 4,930,854 2,677,175 3,168, , ,984 Total Budget Allocation & Spend 4,413,725 4,503, ,413 1,670, ,149 1,070,941 2,979,927 5,209,121 2,748,078 3,292, , ,450 50

51 FY13/14 + Spend Plan Details FY Budget Allocation and Spend by Month - Q3 & Q4 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 to Oct-14 Budget Committed Budget Committed Budget Committed Budget Committed Budget Forecast Budget Forecast OPS Funding 3,800 3,800 2,600 2,600 2,600 2,600 2,600 2, Expenses Funding 66, ,871 58, ,938 34,049 89,514 34, ,703 21,500 76, , ,869 OCO Funding Contracted Services Project Management & Support 184,029 88,812 16,000 31,211 16,000 31,211 16,000 31, IV&V Services Benefits Realization Strategy Organizational Change Management System Integrator (SI) Services 203, , , , ,628 1,047, , , , ,628 3,712,292 3,794,197 SI Hardware & Maintenance SI Software & Maintenance Project Reserves Total Contracted Services 387, , , , ,628 1,078, , , , ,628 3,712,292 3,794,197 Total Budget Allocation & Spend 458, , , , ,277 1,170, ,277 1,211, , ,711 3,819,792 4,466,066 51

Project Connect Executive Steering Committee Update. April 10, 2013

Project Connect Executive Steering Committee Update. April 10, 2013 Project Connect Executive Steering Committee Update April 10, 2013 Agenda Introduction Meeting Minutes Approval Project Status Report IV&V Update by Ernst & Young Other Business Public Comments Review

More information

Project Connect. November 14, 2012

Project Connect. November 14, 2012 Project Connect November 14, 2012 Introduction Meeting Minutes Approval Project Status Report IV&V Update by Ernst & Young Other Business Public Comments Review of Actions from Meeting Scheduling of Next

More information

Project Connect Connect January 11, 2012

Project Connect Connect January 11, 2012 Project Connect January 11, 2012 Introduction Meeting Minutes Approval Project Status Report IV&V Update By Ernst & Young Other Business Public Comments Review of Actions from Meeting Scheduling of Next

More information

Project Connect. May 9, 2012

Project Connect. May 9, 2012 Project Connect May 9, 2012 Introduction Meeting Minutes Approval Project Status Report IV&V Update by Ernst & Young Other Business Public Comments Review of Actions from Meeting Scheduling of Next Meeting

More information

Project Connect. July 11, 2012

Project Connect. July 11, 2012 Project Connect July 11, 2012 Introduction Meeting Minutes Approval Project Status Report IV&V Update by Ernst & Young Other Business Public Comments Review of Actions from Meeting Scheduling of Next Meeting

More information

Project Connect. September 14, 2011

Project Connect. September 14, 2011 Project Connect September 14, 2011 Introduction Meeting Minutes Approval Project Status Report IV&V Update By Ernst & Young Other Business Public Comments Review of Actions from Meeting Schedule Next Meeting

More information

Project Connect. August 10, 2011

Project Connect. August 10, 2011 Project Connect August 10, 2011 Introduction Meeting Minutes Approval Project Status Report IV&V Update By Ernst & Young Other Business Public Comments Review of Actions from Meeting Schedule Next Meeting

More information

Project CONNECT Executive Steering Committee Update. February 26, 2014

Project CONNECT Executive Steering Committee Update. February 26, 2014 Project CONNECT Executive Steering Committee Update February 26, 2014 Agenda Introduction Meeting Minutes Approval Project Status Report Other Business Public Comments Review of Actions from Meeting Scheduling

More information

Project Connect. June 22, 2011

Project Connect. June 22, 2011 Project Connect June 22, 2011 Introduction Meeting Minutes Approval Project Status Report IV&V Update By Ernst & Young Other Business Public Comments Review of Actions from Meeting Schedule Next Meeting

More information

Executive Steering Committee Medicaid Eligibility System Project. October 24, 2014

Executive Steering Committee Medicaid Eligibility System Project. October 24, 2014 Executive Steering Committee Medicaid Eligibility System Project October 24, 2014 Minutes -2- Federal Partner Update -3- Account Transfers Federally Facilitated Marketplace (FFM) As of October 20, 249,417

More information

Work Program Integration Initiative (WPII)

Work Program Integration Initiative (WPII) Florida Department of TRANSPORTATION Work Program Integration Initiative (WPII) Florida PALM Executive Steering Committee Meeting February 27, 2019 Florida Department of Transportation Agenda Overview

More information

Status of the Implementation of the Child Welfare Component of the North Carolina Families Accessing Services through Technology (NC FAST) System

Status of the Implementation of the Child Welfare Component of the North Carolina Families Accessing Services through Technology (NC FAST) System Status of the Implementation of the Child Welfare Component of the North Carolina Families Accessing Services through Technology (NC FAST) System Report to the Joint Legislative Oversight Committee on

More information

EARNED VALUE AS A RISK ASSESSMENT TOOL

EARNED VALUE AS A RISK ASSESSMENT TOOL EARNED VALUE AS A RISK ASSESSMENT TOOL Introduction Earned Value Definition: Employment of a Single Management Control System Providing Accurate, Consistent, Reliable, and Timely Data That Management at

More information

Citizens Property Insurance Corporation Core Insurance Solution Update. v ISAC

Citizens Property Insurance Corporation Core Insurance Solution Update. v ISAC Citizens Property Insurance Corporation Core Insurance Solution Update v.09.12.14 ISAC Delivery Update Topics: Personal Lines Claims and Policy/Billing Status Update Schedule Overview Budget Highlights

More information

Oregon Department of Justice

Oregon Department of Justice Oregon Department of Justice Ellen F. Rosenblum, Attorney General Oregon Department of Justice Division of Child Support Oregon Child Support System Project Presentation to Joint Emergency Board Interim

More information

Smart Metering Entity (SME) Licence Order Working Group

Smart Metering Entity (SME) Licence Order Working Group Smart Metering Entity (SME) Licence Order Working Group Meeting # 8 September 8 th, 2016 Call-In Numbers: Local: (416) 915-8942 Toll Free: 1 855 244-8680 Agenda Review and approval of the minutes from

More information

Budget Process Tools: Introduction to CalPlanning FY

Budget Process Tools: Introduction to CalPlanning FY Budget Process Tools: Introduction to CalPlanning FY2018-19 HCP (Human Capital Planning) CalPlan CalRptg HCPRptg Smart View Introduction to CalPlanning September 2017 1 Agenda 1 2 3 4 CalPlanning Tools

More information

Fiscal Year th Quarter Report Quarterly Report of Actual Traffic and Revenue For period ending August 31, 2017

Fiscal Year th Quarter Report Quarterly Report of Actual Traffic and Revenue For period ending August 31, 2017 Fiscal Year 2017 4 th Quarter Report Quarterly Report of Actual Traffic and Revenue For period ending August 31, 2017 Footer Text Date Table of Contents Section Page Number Notes and Observations 3-4 Significant

More information

Billing and Collection Agent Report For period ending January 31, To NANC

Billing and Collection Agent Report For period ending January 31, To NANC Billing and Collection Agent Report For period ending January 31, 2016 To NANC February 4, 2016 NANPA FUND STATEMENT OF FINANCIAL POSITION JANUARY 31, 2016 Assets Cash Balance in bank account $ 3,587,973

More information

REQUEST FOR PROPOSALS THREE YEAR CONTRACT FOR MERCHANT SERVICES BID NO: ADDENDUM 2

REQUEST FOR PROPOSALS THREE YEAR CONTRACT FOR MERCHANT SERVICES BID NO: ADDENDUM 2 REQUEST FOR PROPOSALS THREE YEAR CONTRACT FOR MERCHANT SERVICES BID NO: 17-14107 ADDENDUM 2 BIDS DUE: June 29, 2017 @ 3:00 PM Central Time To report suspected ethics violations impacting the San Antonio

More information

A Case for Project Revenue Management. Peter Varani PMP

A Case for Project Revenue Management. Peter Varani PMP A Case for Project Revenue Management Peter Varani PMP A Case for Project Revenue Management PMBOK GUIDE (4 th edition) Cost 845 Revenue 3 Unisys Annual Report (2008) Cost 174 Revenue 152 2 Balanced Approach

More information

From Suspicion to Invaluable Transition of Two Project Managers

From Suspicion to Invaluable Transition of Two Project Managers From Suspicion to Invaluable Transition of Two Project Managers June 2010 Shilpi Kumar & Sunita Raman Agenda Unisys and HOLMES 2 Nature of Projects and Roles Why EVA? How? EVA in Development Projects Transition

More information

2019 Budget and Grid Management Charge Initial Stakeholder Meeting

2019 Budget and Grid Management Charge Initial Stakeholder Meeting 2019 Budget and Grid Management Charge Initial Stakeholder Meeting July 24, 2018 Agenda Topic: Welcome and Introductions Presenter: Kristina Osborne 2019 Budget Process & GMC Rate Outlook April Gordon

More information

EARNED VALUE MANAGEMENT. Is it worth the effort?

EARNED VALUE MANAGEMENT. Is it worth the effort? EARNED VALUE MANAGEMENT Is it worth the effort? Session Objectives Examples of earned value in use. Why don t more Project Managers use EMV? Road Map to EVA Maturity? What you need to know? How is our

More information

Billing and Collection Agent Report For period ending August 31, 2016 To B&C Working Group September 15, 2016

Billing and Collection Agent Report For period ending August 31, 2016 To B&C Working Group September 15, 2016 Billing and Collection Agent Report For period ending August 31, 2016 To B&C Working Group September 15, 2016 Welch LLP - Chartered Professional Accountants 123 Slater Street, 3 rd floor, Ottawa, ON K1P

More information

Billing and Collection Agent Report For period ending September 30, To NANC

Billing and Collection Agent Report For period ending September 30, To NANC Billing and Collection Agent Report For period ending September 30, 2010 To NANC October 14, 2010 STATEMENT OF FINANCIAL POSITION September 30, 2010 Assets Cash Balance in bank account $ 2,926,706 Receivable

More information

Customer Integration Testing Strategy

Customer Integration Testing Strategy Customer Integration Testing Strategy Investor Reporting Change Initiative Updated: November 2017 Background As part of the Investor Reporting Change Initiative (IRCI), Freddie Mac is making updates to

More information

Billing and Collection Agent Report For period ending April 30, To NANC

Billing and Collection Agent Report For period ending April 30, To NANC Billing and Collection Agent Report For period ending April 30, 2011 To NANC May 17, 2011 STATEMENT OF FINANCIAL POSITION April 30, 2011 Assets Cash Balance in bank account $ 1,824,073 Receivable from

More information

Impact of VAT Compliance on Business. Pierre Arman Market Lead for Tax & Accounting Thomson Reuters MENA Qatar Chamber of Commerce February 2018

Impact of VAT Compliance on Business. Pierre Arman Market Lead for Tax & Accounting Thomson Reuters MENA Qatar Chamber of Commerce February 2018 Impact of VAT Compliance on Business Pierre Arman Market Lead for Tax & Accounting Thomson Reuters MENA Qatar Chamber of Commerce February 2018 Agenda Preparing for VAT in the GCC Lessons learned in 2017

More information

Earned Value Management An Overview March 2014

Earned Value Management An Overview March 2014 Earned Value Management An Overview March 2014 SAVE International Cascadia Chapter Introduction What is Earned Value? Why is Earned Value important? What is required? Earned Value Definitions & Process

More information

Executive Steering Committee Meeting. Department of Revenue Building 2, Room 1250 September 28, 2016

Executive Steering Committee Meeting. Department of Revenue Building 2, Room 1250 September 28, 2016 Executive Steering Committee Meeting Department of Revenue Building 2, Room 1250 Roll Call and Opening Remarks Facilitator: Robert (Budd) Kneip, Chair Review of September 14, Meeting Minutes Facilitator:

More information

County of Orange IT Quarterly Status Report Risk Assessment. Fiscal Year rd Quarter, January - March

County of Orange IT Quarterly Status Report Risk Assessment. Fiscal Year rd Quarter, January - March CEO, Office of the CIO Program Management Office County of Orange IT Quarterly Status Report Risk Assessment Fiscal Year 2008-09 3rd Quarter, January - March Introduction The purpose of this report is

More information

Nevada Health Link. Creation of the Nevada Health Link. July 31, Operated by the Silver State Health Insurance Exchange

Nevada Health Link. Creation of the Nevada Health Link. July 31, Operated by the Silver State Health Insurance Exchange Nevada Health Link Operated by the Silver State Health Insurance Exchange Creation of the Nevada Health Link July 31, 2013 Agenda 1. What is an online marketplace? Elements of the Nevada Health Link web

More information

PMP. Preparation Training. Cost Management. Your key in Successful Project Management. Cost Management Processes. Chapter 7 6/7/2005

PMP. Preparation Training. Cost Management. Your key in Successful Project Management. Cost Management Processes. Chapter 7 6/7/2005 PMP Preparation Training Your key in Successful Project Management Akram Al-Najjar, PMP Cost Management Processes Chapter 7 Cost Management Slide 2 1 AGENDA What is Cost Management? Cost Management Processes

More information

The First Steps in Implementing a Simplified Earned Value Management System

The First Steps in Implementing a Simplified Earned Value Management System 2007 Joint ISPA/SCEA National Conference & Workshop June 12-15, 2007 The First Steps in Implementing a Simplified Earned Value Management System Dorothy Tiffany, CPA, PMP NASA/GSFC EVM System Interface

More information

The Market Expectations System: An Important Tool for Policy Support and Forecasting

The Market Expectations System: An Important Tool for Policy Support and Forecasting The Market Expectations System: An Important Tool for Policy Support and Forecasting Renato Jansson Rosek October 2013 I. Historical Background II. Main Features of the System III. Reports IV. Use in Policy

More information

I - PROJECT STATUS OVERVIEW

I - PROJECT STATUS OVERVIEW Project Sponsor: Status Report : Start : Project Manager: Project R&C Category: End : I - PROJECT STATUS OVERVIEW A. Overview of project progress during reporting period: B. SPI & CPI (for

More information

ASX S APPROACH TO RELEASE MANAGEMENT

ASX S APPROACH TO RELEASE MANAGEMENT ASX S APPROACH TO RELEASE MANAGEMENT INTRODUCTION The Australian Securities Exchange (ASX) is mindful of the heightened regulatory, technical and operational challenges faced by Participants in a rapidly

More information

T R A N S F O R M AT I O N A L I N I T I AT I V E S U P D AT E B O A R D O F S U P E R V I S O R S M E E T I N G J U N E 7,

T R A N S F O R M AT I O N A L I N I T I AT I V E S U P D AT E B O A R D O F S U P E R V I S O R S M E E T I N G J U N E 7, T R A N S F O R M AT I O N A L I N I T I AT I V E S U P D AT E B O A R D O F S U P E R V I S O R S M E E T I N G J U N E 7, 2 0 1 7 SIGNIFICANT PROGRESS ACCOMPLISHED IMPROVE LONG-TERM STRUCTURAL REALIGNMENT

More information

Oracle. Project Portfolio Management Cloud Using Project Performance Reporting. Release 13 (update 17D)

Oracle. Project Portfolio Management Cloud Using Project Performance Reporting. Release 13 (update 17D) Oracle Project Portfolio Management Cloud Release 13 (update 17D) Release 13 (update 17D) Part Number E89308-02 Copyright 2011-2017, Oracle and/or its affiliates. All rights reserved. Authors: Sandeep

More information

WRIA 1 Program Coordination

WRIA 1 Program Coordination WRIA 1 Program Coordination WRIA 1 Management Team Meeting Date: October 12, 2016 Time: 10:00am-12:00pm Location: Garden Room, Civic Center Annex, 322 N. Commercial, Bellingham, WA 98225 ADMINISTRATIVE

More information

Oracle. Project Portfolio Management Cloud Using Project Performance Reporting. Release 13 (update 18B)

Oracle. Project Portfolio Management Cloud Using Project Performance Reporting. Release 13 (update 18B) Oracle Project Portfolio Management Cloud Release 13 (update 18B) Release 13 (update 18B) Part Number E94696-05 Copyright 2011-2018, Oracle and/or its affiliates. All rights reserved. Authors: Sandeep

More information

Budget Manager Meeting. February 20, 2018

Budget Manager Meeting. February 20, 2018 Budget Manager Meeting February 20, 2018 Meeting Agenda DISCUSSION DRAFT NOT FOR DISTRIBUTION Budget Office Current Year Forecast Process Endowment Payout Control Charts FY19 Target Meetings Delphi Project

More information

Capital Improvement Program Update

Capital Improvement Program Update Finance & Administration Committee Information Item III-A May 12, 2011 Capital Improvement Program Update Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information

More information

Executive Expectations of Project Managers

Executive Expectations of Project Managers Executive Expectations of Project Managers Bruce Leidal, PMP Chief Information Officer Carestream Health, Inc. April 1, 2010 Page 1 Before understanding Executive Expectations, let s understand Executives

More information

UNCLASSIFIED. R-1 ITEM NOMENCLATURE PE F: Financial Management Information Systems (FMIS)

UNCLASSIFIED. R-1 ITEM NOMENCLATURE PE F: Financial Management Information Systems (FMIS) Exhibit R-2, RDT&E Budget Item Justification: PB 2012 Air Force DATE: February 2011 COST ($ in Millions) FY 2010 FY 2013 FY 2014 FY 2015 FY 2016 To Program Element 53.972 49.816 101.317-101.317 98.673

More information

Smart Metering Entity (SME) Licence Order Working Group

Smart Metering Entity (SME) Licence Order Working Group Smart Metering Entity (SME) Licence Order Working Group Meeting # 9 October 27 th, 2016 Call-In Numbers: Local: (416) 915-8942 Toll Free: 1 855 244-8680 Agenda Review and approval of the minutes from Meeting

More information

Integrated Trading & Clearing (ITaC) Dress Rehearsal Feedback

Integrated Trading & Clearing (ITaC) Dress Rehearsal Feedback Integrated Trading & Clearing (ITaC) Dress Rehearsal Feedback 16 March 2018 1 Agenda ITaC - What s changing? ITaC Project Update High Level Timelines and Key Dates Mandatory Market Dress Rehearsals General

More information

Gate Value Method Overview document

Gate Value Method Overview document Gate Value Method Overview document Version 7 Dated 7 th May 2009 Author: Martin Vaughan Note: This document has been prepared by Core Consulting Group to explain the Gate Value Method. While any person

More information

PENSION SYSTEM RESUMPTION (PSR) RECOVERY PLAN PROJECT

PENSION SYSTEM RESUMPTION (PSR) RECOVERY PLAN PROJECT NASCIO AWARD NOMINATION FOR DIGITAL GOVERNMENT: GOVERNMENT TO BUSINESS (G TO B) PENSION SYSTEM RESUMPTION (PSR) RECOVERY PLAN PROJECT CALIFORNIA PUBLIC EMPLOYEES RETIREMENT SYSTEM INITIATED MARCH 2010

More information

KAREN E. RUSHING. Audit of Building Permit Fees

KAREN E. RUSHING. Audit of Building Permit Fees KAREN E. RUSHING Clerk of the Circuit Court and County Comptroller Audit of Building Permit Fees Audit Services Jeanette L. Phillips, CPA, CGFO, CIG Director of Internal Audit and Inspector General David

More information

Billing and Collection Agent Report For period ending January 31, To B&C Working Group

Billing and Collection Agent Report For period ending January 31, To B&C Working Group Billing and Collection Agent Report For period ending January 31, 2018 To B&C Working Group February 5, 2018 NANPA FUND STATEMENT OF FINANCIAL POSITION January 31, 2018 Assets Cash in bank $ 4,550,060

More information

Billing and Collection Agent Report For period ending April 30, To FCC Contract Oversight Sub Committee

Billing and Collection Agent Report For period ending April 30, To FCC Contract Oversight Sub Committee Billing and Collection Agent Report For period ending April 30, 2018 To FCC Contract Oversight Sub Committee May 10, 2018 NANPA FUND STATEMENT OF FINANCIAL POSITION April 30, 2018 Assets Cash in bank $

More information

Washington State Health Benefit Exchange Level II Grant Application Budget Narrative. 1. Budget Request Overview

Washington State Health Benefit Exchange Level II Grant Application Budget Narrative. 1. Budget Request Overview Washington State Health Benefit Exchange Level II Grant Application Budget Narrative 1. Budget Request Overview The total Exchange establishment budget request for the 2012 2014 establishment period is

More information

Key Milestones & Decisions

Key Milestones & Decisions Key Milestones & Decisions Prepared: August 11, 2017 Key Milestone Timeline June 25, 2015 House Bill 2960 signed into law by Governor Kate Brown Q3 2015 Sep Appointment of Board Members; Executive Director

More information

Oregon Public Employees Retirement System

Oregon Public Employees Retirement System Oregon Public Employees Retirement System 2017-19 Governor s Budget Phase II Presentation Joint Ways & Means Committee General Government Subcommittee Steven Patrick Rodeman Executive Director Jordan Masanga

More information

PEOPLESOFT APPLICATION ROAD MAP PROJECT THE WAY FORWARD

PEOPLESOFT APPLICATION ROAD MAP PROJECT THE WAY FORWARD PEOPLESOFT APPLICATION ROAD MAP PROJECT THE WAY FORWARD Phase 2 The HABIT Program HCM Automation and Business Information Transformation Program October 16, 2014 Agenda Summary of The Program Program Timeline

More information

Open Enrollment Readiness

Open Enrollment Readiness Open Enrollment Readiness VICKI COATES Deputy Executive Director and Chief Operating Officer MARISSA WOLTMANN Director of Policy and Applied Research Board of Directors Meeting, September 13, 2018 Open

More information

Portfolio Project Performance Reporting. Client Case Study

Portfolio Project Performance Reporting. Client Case Study Portfolio Project Performance Reporting Client Case Study MetaPM 2016 The Challenge MetaPM s client need a mechanism to enable them to balance, reprioritise and provide recommendations (backed up by data)

More information

Integrated Trading and Clearing (ITaC) Client Forum

Integrated Trading and Clearing (ITaC) Client Forum Integrated Trading and Clearing (ITaC) Client Forum 1 August 2018 1 Agenda ITaC Key Dates ITaC End-To-End (ETE) Testing update Observations Commissions Balancing thresholds in the daily EoD process Questions?

More information

Resource Allocation, Management, and Planning Steering Committee #7

Resource Allocation, Management, and Planning Steering Committee #7 Resource Allocation, Management, and Planning Steering #7 August 28, 2018 1 Agenda Huron is pleased to partner with WKU on this resource allocation, management, and planning ( RAMP ) initiative. Our goals

More information

TITLE OF REPORT: QIPP Programme Update Month 7. Kelly Knowles Head of Strategic Financial Planning. Annette Walker Chief Finance Officer

TITLE OF REPORT: QIPP Programme Update Month 7. Kelly Knowles Head of Strategic Financial Planning. Annette Walker Chief Finance Officer NHS BOLTON CLINICAL COMMISSIONING GROUP Public Board Meeting AGENDA ITEM NO: 13 Date of Meeting: 25 th November 2016 TITLE OF REPORT: QIPP Programme Update Month 7 AUTHOR: PRESENTED BY: PURPOSE OF PAPER:

More information

Earned Schedule Analysis

Earned Schedule Analysis Integrated Project Performance Management.EMERGING PRACTICE. Earned Schedule Analysis A Better Set of Schedule Metrics Eleanor Haupt President PMI College of Performance Management Walt Lipke Member PMI

More information

Prepared by DCMA Lockheed Martin Fort Worth

Prepared by DCMA Lockheed Martin Fort Worth Joint Strike Fighter Lightning II Monthly Assessment Report Prepared by DCMA Lockheed Martin Fort Worth January 2010 THIS DOCUMENT CONTAINS CONTRACTOR INFORMATION WHICH MAY BE PROPRIETARY AND PROTECTED

More information

ORANGE UNIFIED SCHOOL DISTRICT Measure S Bond Program September 2017 Monthly Progress Report

ORANGE UNIFIED SCHOOL DISTRICT Measure S Bond Program September 2017 Monthly Progress Report ORANGE UNIFIED SCHOOL DISTRICT Measure S Bond Program September 2017 Monthly Progress Report PERIOD COVERED: September 1 30, 2017 FISCAL YEAR FY 2017 2018 PROGRESS REPORT NO. PR 03 1718 003 PREPARED BY:

More information

INSE 6230 Total Quality Project Management

INSE 6230 Total Quality Project Management Lecture 5 Project Cost Management Project cost management introduction Estimating costs Budget Earned Value Management (EVM) EVM projections 2 IT projects have a poor track record for meeting budget goals

More information

Danny Elder - KIDASA Software, Inc.

Danny Elder - KIDASA Software, Inc. 1 Danny Elder - KIDASA Software, Inc. 1 Email sales@kidasa.com for a keycode to use Milestones Professional Until 12/31/2013 SWIM LANE CHART ACTIVITIES Program Facilities 1 2 3 4 5 6 7 8 9 10 11 12 13

More information

Updates & Milestones re: Peak Demand Reduction. EEAC Consultants (with PA contributions) (Revised, 3/13/17)

Updates & Milestones re: Peak Demand Reduction. EEAC Consultants (with PA contributions) (Revised, 3/13/17) Updates & Milestones re: Peak Demand Reduction EEAC Consultants (with PA contributions) (Revised, 3/13/17) Key Work Streams in 2016-2018 Following the Analytical Framework Cost-Effectiveness Framework

More information

GLAST Large Area Telescope: Project Status Overview. Gamma-ray Large Area Space Telescope

GLAST Large Area Telescope: Project Status Overview. Gamma-ray Large Area Space Telescope Gamma-ray Large Area Space Telescope GLAST Large Area Telescope: Project Status Overview Lowell A. Klaisner Stanford Linear Accelerator Center Project Manager Klaisner@slac.stanford.edu 650-926-2726 1

More information

Use of EVM Trends to Forecast Cost Risks 2011 ISPA/SCEA Conference, Albuquerque, NM

Use of EVM Trends to Forecast Cost Risks 2011 ISPA/SCEA Conference, Albuquerque, NM Use of EVM Trends to Forecast Cost Risks 2011 ISPA/SCEA Conference, Albuquerque, NM presented by: (C)2011 MCR, LLC Dr. Roy Smoker MCR LLC rsmoker@mcri.com (C)2011 MCR, LLC 2 OVERVIEW Introduction EVM Trend

More information

Project NEON Interim Finance Committee Rudy Malfabon Director

Project NEON Interim Finance Committee Rudy Malfabon Director Project NEON Interim Finance Committee Rudy Malfabon Director October 22, 2014 1 Project Benefits Safety & Congestion 1,000 crashes per year! Connectivity /Mobility for City Redevelopment Efforts Congestion:

More information

Plan Management Stakeholder Committee May 5, 2016

Plan Management Stakeholder Committee May 5, 2016 Plan Management Stakeholder Committee May 5, 2016 Welcome and Introductions Standing Agenda Meeting Minutes Approval Feedback From the Field Provider Directory Improvement Strategy Chapter 4, Section G,

More information

ONTARIO-MICHIGAN BORDER TRANSPORTATION PARTNERSHIP Planning/Need and Feasibility Study. 1. Work Accomplished This Period (4 Weeks)

ONTARIO-MICHIGAN BORDER TRANSPORTATION PARTNERSHIP Planning/Need and Feasibility Study. 1. Work Accomplished This Period (4 Weeks) ONTARIO-MICHIGAN BORDER TRANSPORTATION PARTNERSHIP Planning/Need and Feasibility Study MONTHLY PROGRESS REPORT #19 Period Ending September 30, 2003 1. Work Accomplished This Period (4 Weeks) Strategic

More information

Self-Assessment Questions for Module 07 Project Cost Management

Self-Assessment Questions for Module 07 Project Cost Management Self-Assessment Questions for Module 07 Project Cost Management Question 1: Which of the following regarding Analogous Estimating and Parametric Estimating is incorrect? A.) Parametric Estimating uses

More information

CSR for BC & OT and GBS

CSR for BC & OT and GBS Tripartite 2015 Meeting Session 3: State of Play CSR for BC & OT and GBS Toshiro Arima, IACS EG/GBS Chair Seoul, 1 CSR for BC & OT and GBS Stability Period for year after entry into force with no Rule

More information

HOPE NOW. Snapshot Industry Extrapolations and HAMP Metrics

HOPE NOW. Snapshot Industry Extrapolations and HAMP Metrics Snapshot Industry Extrapolations and HAMP Metrics Three Month Q2-215 Q3-215 Q4-215 Q1-216 Q2-216 Jun-16 Jul-16 Aug-16 Total Completed Modifications 119,658 97,773 84,798 86,167 1,198 41,872 34,815 36,6

More information

Construction of the #7 Line Subway Extension Project New York September 17, 2018

Construction of the #7 Line Subway Extension Project New York September 17, 2018 Construction of the #7 Line Subway Extension Project New York September 17, 2018 Saibal Basuroy, PMP Project Controls Director, Hill International Inc. Disclaimer This presentation is protected by US and

More information

Integrated Planning, Monitoring and Reporting

Integrated Planning, Monitoring and Reporting 1. Purpose This procedure describes the integrated planning, monitoring and ing cycle of the European Chemicals Agency, including the preparation of the Single Programming Document (SPD). This procedure

More information

Middlesbrough Universal Credit conference 3 rd October 2018

Middlesbrough Universal Credit conference 3 rd October 2018 Middlesbrough Universal Credit conference 3 rd October 2018 Middlesbrough Universal Credit conference 3 rd October 2018 Welcome from Chris Smith Executive Director of Service Delivery and Development,

More information

HSCIC Financial Management and Reporting

HSCIC Financial Management and Reporting HSCIC Financial Management and Reporting Author: Rebecca Giles/Carl Vincent Date 24 th February 2014 1 Copyright 2014, Health and Social Care Information Centre. Contents Contents 2 Introduction 3 Current

More information

DALLAS COUNTY DISTRICT COURT ADMINISTRATION

DALLAS COUNTY DISTRICT COURT ADMINISTRATION DALLAS COUNTY DISTRICT COURT ADMINISTRATION April 14, 2009 BRIEFING MEMORANDUM TO: FROM: Honorable Commissioners Court Duane Allen Gallup ADR Coordinator SUBJECT: ADR Program & Dispute Mediation Services

More information

Olmsted Locks & Dam. Inland Waterways Users Board MR. DAVID DALE, PE, PMP, SES. DIRECTOR, Programs Great Lakes & Ohio River Division 25 February 2015

Olmsted Locks & Dam. Inland Waterways Users Board MR. DAVID DALE, PE, PMP, SES. DIRECTOR, Programs Great Lakes & Ohio River Division 25 February 2015 Olmsted Locks & Dam Inland Waterways Users Board MR. DAVID DALE, PE, PMP, SES DIRECTOR, Programs Great Lakes & Ohio River Division 25 February 2015 US Army Corps of Engineers BUILDING STRONG Agenda Status

More information

Durham Orange Joint Staff Working Group Meeting Agenda October 10, :30 pm 4:00 pm Durham City Hall, Transportation 4B

Durham Orange Joint Staff Working Group Meeting Agenda October 10, :30 pm 4:00 pm Durham City Hall, Transportation 4B Durham Orange Joint Staff Working Group Meeting Agenda October 10, 2018 2:30 pm 4:00 pm Durham City Hall, Transportation 4B 1. Call to Order/Roll Call 2. Election Chair Position 3. Open Issues a. FY2019

More information

2018 IRS ACA Reporting Reviewing, Correcting, and Certifying Your Forms 1095-C

2018 IRS ACA Reporting Reviewing, Correcting, and Certifying Your Forms 1095-C Revised Jan. 17, 2019 2018 IRS ACA Reporting Reviewing, Correcting, and Certifying Your Forms 1095-C SB-25770-XXXX Need Help? You are welcome to call your consultant with any questions at 800-654-8489

More information

BUDGET WORKING GROUP

BUDGET WORKING GROUP BUDGET WORKING GROUP 1 Presenters Xavier Calvez ICANN CFO Cyrus Namazi ICANN VP DNS Industry Engagement Becky Nash ICANN VP Finance Jessica Castillo ICANN Project Coordinator 2 Budget Working Group - Part

More information

Integrated Trading and Clearing (ITaC) Project Forum

Integrated Trading and Clearing (ITaC) Project Forum Integrated Trading and Clearing (ITaC) Project Forum 3 October 2018 1 Agenda ITaC Key Dates ITaC Dress Rehearsal 15 September 2018 results feedback Market Dress Rehearsal 6 October 2018 Questions? 2 ITaC

More information

THE PMP EXAM PREP COURSE

THE PMP EXAM PREP COURSE THE PMP EXAM PREP COURSE Session 3 PMI, PMP and PMBOK are registered marks of the Project Management Institute, Inc. www.falcontraining.co.nz Agenda 9:00 10:15 10:15 10:30 10:30 12:00 12:00 12:45 12:45

More information

Introduction to Project Management. Modeling after NYS ITS

Introduction to Project Management. Modeling after NYS ITS Introduction to Project Management Modeling after NYS ITS What is Project Management? Project management is the application of knowledge, skills, tools and techniques to project activities to meet project

More information

Oracle Project Portfolio Management Cloud Using Project Performance Reporting

Oracle Project Portfolio Management Cloud Using Project Performance Reporting Oracle Project Portfolio Management Cloud Using Project Performance Reporting Release 9 This guide also applies to on-premise implementations Oracle Project Portfolio Management Cloud Part Number E53157-01

More information

Status Report & Budget Proposal. May 23, 2013

Status Report & Budget Proposal. May 23, 2013 2012-13 Status & 2013-14 Budget Proposal May 23, 2013 Covered California Budget Cycle Transitioning from calendar year budget, based on spending plan linked to approved federal grants, to an annual budget

More information

HOPE NOW. Snapshot Industry Extrapolations and HAMP Metrics

HOPE NOW. Snapshot Industry Extrapolations and HAMP Metrics Snapshot Industry Extrapolations and HAMP Metrics Three Month Q4-2016 Q1-2017 Q2-2017 Q3-2017 Q4-2017 Oct-17 Nov-17 Dec-17 Total Completed Modifications 85,357 89,213 78,302 54,318 56,355 19,400 18,819

More information

Fiscal Year nd Quarter Report Quarterly Report of Actual Traffic and Toll Revenue For period ending February 28, 2018

Fiscal Year nd Quarter Report Quarterly Report of Actual Traffic and Toll Revenue For period ending February 28, 2018 Fiscal Year 2018 2 nd Quarter Report Quarterly Report of Actual Traffic and Toll Revenue For period ending February 28, 2018 Footer Text Date Table of Contents Section Page Number Disclaimer 3 Notes and

More information

City of Menifee Development Code Update

City of Menifee Development Code Update City of Menifee June 13, 2018 5:00 PM Agenda Purpose of Project Schedule and Milestones Audit Report Summary Annotated Outline Approach City Council/Planning Commission and Public Feedback Next Steps Project

More information

Earned Value and PRINCE2 Alex Davis. Programme Manager Close Combat Programme Support Office Ministry of Defence

Earned Value and PRINCE2 Alex Davis. Programme Manager Close Combat Programme Support Office Ministry of Defence Earned Value and PRINCE2 Alex Davis Programme Manager Close Combat Programme Support Office Ministry of Defence PRINCE2 is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom

More information

JSE Market Communication Session. 8 June 2016

JSE Market Communication Session. 8 June 2016 JSE Market Communication Session 8 June 2016 Agenda Market Activity Update Services Feedback Integrated Trading and Clearing (ITaC) update T+3 update Debt Instrument System Questions 2 Market Activity

More information

IFRS 15 Implementation in the technology and telecommunication industry

IFRS 15 Implementation in the technology and telecommunication industry International Financial Reporting Standards Der 15. IFRS Kongress 2016 in Berlin IFRS 15 Implementation in the technology and telecommunication industry Michael Brücks Deutsche Telekom AG Andreas Grote

More information

Agenda (Items may be taken out of order) D. Active Construction Project Status Report (for receive and file only)

Agenda (Items may be taken out of order) D. Active Construction Project Status Report (for receive and file only) I. ROLL CALL LOS ANGELES COMMUNITY COLLEGE DISTRICT BOARD OF TRUSTEES FACILITIES MASTER PLANNING & OVERSIGHT COMMITTEE Educational Services Center Board Room 770 Wilshire Boulevard Los Angeles, CA 90017

More information

Department of Industrial Engineering

Department of Industrial Engineering Department of Industrial Engineering Engineering Project Management Presented By Dr. Abed Schokry Chapter 15: Cost Control Learning Outcomes After completing this chapter students should be able to: Define

More information

Oracle Fusion Applications Project Management, Project Performance Reporting Guide. 11g Release 1 (11.1.3) Part Number E

Oracle Fusion Applications Project Management, Project Performance Reporting Guide. 11g Release 1 (11.1.3) Part Number E Oracle Fusion Applications Project Management, Project Performance Reporting Guide 11g Release 1 (11.1.3) Part Number E22601-03 December 2011 Oracle Fusion Applications Project Management, Project Performance

More information

How to use this dashboard

How to use this dashboard EQC Performance Dashboard - July 218 How to use this dashboard This dashboard shows a monthly snapshot of EQC's progress across its operational spectrum as well as how we track in relation to the performance

More information