Decision D Alberta PowerLine L.P. Tariff Application. January 23, 2018

Size: px
Start display at page:

Download "Decision D Alberta PowerLine L.P. Tariff Application. January 23, 2018"

Transcription

1 Decision D Alberta PowerLine L.P. Tariff Application January 23, 2018

2 Alberta Utilities Commission Decision D Alberta PowerLine L.P. Tariff Application Proceeding January 23, 2018 Published by the: Alberta Utilities Commission Fifth Avenue Place, Fourth Floor, 425 First Street S.W. Calgary, Alberta T2P 3L8 Telephone: Fax: Website:

3 Alberta Utilities Commission Calgary, Alberta Alberta PowerLine L.P. Decision D Tariff Application Proceeding Introduction 1. On November 30, 2017, Alberta PowerLine L.P. (Alberta PowerLine) submitted a tariff application as owner of the Fort McMurray West 500-kilovolt (kv) Transmission (WFMAC) Project. 2. On December 1, 2017, the Alberta Utilities Commission issued a notice of application that required interested parties to submit a statement of intent to participate (SIP) by December 15, The Commission received SIPs from the Office of the Utilities Consumer Advocate (UCA), the Consumers Coalition of Alberta (CCA), and the Alberta Electric System Operator (AESO). The UCA reserved the right to actively participate should it be deemed necessary. The CCA intended to review the application to determine whether any further process was warranted and advised that it would actively participate if issues were raised that were of interest to the CCA. The AESO indicated that it generally supported the application and did not intend to actively participate unless an issue was identified that could impact its roles and responsibilities under the Electric Utilities Act. 4. Based on the comments provided by parties and a review of the application, the Commission determined 1 that the application was to be considered by way of a notice-only process as outlined in Commission Bulletin The Commission considers the close of record for this proceeding to be December 15, In reaching the determinations set out within this decision, the Commission has considered all relevant materials comprising the record of this proceeding. Accordingly, references in this decision to specific parts of the record are intended to assist the reader in understanding the Commission s reasoning related to a particular matter and should not be taken as an indication that the Commission did not consider all relevant portions of the record with respect to a particular matter. 1 Exhibit X0009, AUC process letter dated December 22, Bulletin , Performance standards for processing rate-related applications, March 26, Decision D (January 23, 2018) 1

4 2 Background 6. Alberta PowerLine submitted that the legislature of Alberta has designated the WFMAC Project as critical transmission infrastructure 3 (CTI) under Part 2.1 and Section 4 of the schedule of the Electric Utilities Act. 7. Under subsections 24.2(2) and 24.2(3) of the Transmission Regulation, the Independent System Operator (ISO) (which operates as the AESO) must develop and obtain Commission approval for a competitive process to determine who is eligible to apply to the Commission for the construction and operation of CTI. In Proceeding 1449, the Commission considered the AESO s application for approval of a competitive process. In Decision , 4 the Commission approved the AESO s competitive process with conditions. 8. In May 2013, the AESO initiated the Commission-approved competitive process and, in December 2014, Alberta PowerLine was selected as the successful bidder for the WFMAC Project In Proceeding 20130, Alberta PowerLine applied to construct and operate the WFMAC Project, with its general partner Alberta PowerLine General Partner Ltd. (as incorporated under the Business Corporations Act) holding the approval, if granted, in accordance with Section 23 of the Hydro and Electric Energy Act. 6 In Decision D , 7 the Commission, pursuant to sections 14, 15 and 19 of the Hydro and Electric Energy Act, approved the application for the WFMAC Project and granted Alberta PowerLine General Partner Ltd. permits and licences to construct the applied-for transmission facilities subject to a number of conditions. As set out in that decision, the Commission found the following facilities to be CTI as defined in the Electric Utilities Act and approved these facilities for the WFMAC Project: Alberta PowerLine s 500-kV transmission line 12L41, including the repeater sites, from AltaLink Management Ltd. s transmission line 1241L to Livock 939S Substation, following the west route option and Alberta PowerLine s west route amendments. Alberta PowerLine s 500-kV transmission line 12L44, from Livock 939S Substation to Thickwood Hills 951S Substation, following the common route and common route variation 1. Alberta PowerLine s 500-kV switchyard at Livock 939S Substation. Alberta PowerLine s Thickwood Hills 951S Substation. A connection order between Alberta PowerLine s 12L41 and AltaLink Management Ltd. s transmission line 1241L. 3 According to Section 1(1)(f.1) of the Electric Utilities Act, critical transmission infrastructure means a transmission facility designated under the Schedule as critical transmission infrastructure. 4 Decision : Alberta Electric System Operator, Competitive Process Pursuant to Section 24.2(2) of the Transmission Regulation Part B: Final Determination, February 14, Exhibit X0002, Attachment 01 - Application Text Final, paragraph 3. 6 Exhibit X0648, APL-AUC-2016FEB01-001, PDF page 2. 7 Decision D : Alberta PowerLine General Partner Ltd., Fort McMurray West 500-Kilovolt Transmission Project, February 10, Decision D (January 23, 2018)

5 A connection order between Alberta PowerLine s Thickwood Hills 951S Substation to ATCO Electric Ltd. s Thickwood Hills 951S Substation. 8 3 Application 10. Alberta PowerLine submitted that pursuant to Section 37 of the Electric Utilities Act, each owner of an electric transmission facility must submit to the Commission for approval a tariff setting out the rates to be paid by the AESO for the use of the owner s transmission facility. Alberta PowerLine requested approval of the terms and conditions and pricing of the arrangements resulting from the competitive process as set out in the project agreement, except for any payments that exceed the materiality thresholds in the project agreement and that require Commission approval, commencing on the energization date of the WFMAC Project and continuing until the expiry of the term of the project agreement. 11. Alberta PowerLine attached the project agreement as Appendix 1 of the application. The project agreement, dated September 28, 2017, is between the ISO, operating as the AESO, and Alberta PowerLine. The target energization date for the WFMAC Project is June 27, The expiry of the term of the project agreement is the earlier of the 35th anniversary of the target energization date and the 90th day following the 35th anniversary of the energization date. 12. Alberta PowerLine explained that the payments owing to Alberta PowerLine for designing, building, financing and maintaining the applicable transmission facilities are determined by the project agreement. The project agreement provides for monthly payments from the AESO to Alberta PowerLine over the operating period of the project agreement. The monthly payment schedule is set out in Appendix 1, Schedule 11, of the application. Alberta PowerLine advised that the monthly payments are equal to the sum of a capital, operations and maintenance (O&M), and insurance payment. Alberta PowerLine indicated that there are mechanisms that may result in adjustments to the monthly payments (price adjustment mechanisms), such as annual adjustments to monthly O&M payments for inflation. 13. In addition to the monthly payments and the price adjustment mechanisms described above, Alberta PowerLine explained that the project agreement sets out comprehensive mechanisms to address certain events that may arise over the operating term. Alberta PowerLine submitted that the project agreement provides that if circumstances give rise to a payment in excess of materiality thresholds in the project agreement, such payments will be subject to review and final approval by the Commission. 14. Alberta PowerLine advised that the Transmission Regulation sets out the scope of the Commission s review of this application. Alberta PowerLine submitted that once the Commission approves a competitive process pursuant to subsections 24.2(2) and (3) of the Transmission Regulation, the Commission must consider the resulting arrangements as prudent pursuant to subsection 24.2(4) of the Transmission Regulation. In this case, Alberta PowerLine advised that the resulting arrangement is the project agreement. In Alberta PowerLine s view, the Commission must consider the provisions of the project agreement, 8 Decision D , paragraph Exhibit X0001, Alberta PowerLine Tariff Application, Project Agreement, PDF page 43. Decision D (January 23, 2018) 3

6 include the payments, price adjustment mechanisms, and other provisions governing the terms and conditions of service, as prudent. 15. Alberta PowerLine also cited the Commission s findings in Decision as support for its submissions regarding the scope of the review: 51. Section 24.2(3) of the Transmission Regulation requires the AESO to obtain the approval of the Commission prior to the AESO implementing any competitive process that it develops. Further, Section 24.2(4) of the Transmission Regulation directs the Commission to consider any resulting arrangements as prudent. The Commission must therefore be satisfied that the form and content of the competitive process will yield a result determined by competitive market forces. It is the operation of competitive market forces that justifies the removal of a regulatory assessment of prudence. 52. Once a successful bidder is chosen, that bidder becomes a TFO [transmission facility owner] and the monopoly supplier of the transmission services for the new transmission facility during the life of the contract. The arrangements that were included in the bid and were the basis of the acceptance of that bid, would include a financial bid and would pass through the competitive bid prices to customers in the form of rates which the Commission would have to consider to be prudent In its SIP, the AESO submitted that the provisions of the project agreement between the AESO and Alberta PowerLine for the WFMAC Project, including the payments and price adjustment mechanisms, are deemed prudent pursuant to Section 24.2(4) of the Transmission Regulation. Commission findings 17. Under Section 37 of the Electric Utilities Act, each owner of an electric transmission facility must submit to the Commission for approval a tariff application setting out the rates to be paid by the AESO for the use of the owner s transmission facility. An owner is defined in Section 1(jj) of the Electric Utilities Act as follows: (jj) owner, in respect of a generating unit, a transmission facility or an electric distribution system, means the owner, operator, manager or lessee of that unit, facility or system, or any person who is acting as an agent for the owner, operator, manager or lessee, and in the event that one of those persons becomes bankrupt or insolvent, includes any trustee, liquidator or receiver appointed in respect of the bankruptcy or insolvency; 18. The project agreement defines tariff application as any application submitted by Project Co to the AUC pursuant to Section 37 of the Act for the approval of a Project Co Tariff. Project Co is defined in the preamble of the project agreement as Alberta PowerLine. As noted in the preamble of the project agreement, Alberta PowerLine is responsible for developing, designing, building, owning, financing, operating and maintaining certain transmission facilities in relation to the WFMAC Project. Accordingly, the Commission finds Alberta PowerLine to be an owner pursuant to the Electric Utilities Act. 10 Decision : Alberta Electric System Operator, Competitive Process Pursuant to Section 24.2(2) of the Transmission Regulation, Part A: Statutory Interpretation, Proceeding 1449, Application , February 27, Decision , paragraphs Decision D (January 23, 2018)

7 19. Regarding the scope of the Commission s jurisdiction in this application, under Subsection 24.2(4) of the Transmission Regulation: (4) Where the Commission approves a competitive process developed under subsection (2), the Commission must consider any resulting arrangements, including any changes requiring the Commission s approval or determination pursuant to section 24.3(3) or (4), as prudent. 20. In Decision , the Commission approved the AESO s competitive process with conditions. The AESO initiated the Commission-approved competitive process and selected Alberta PowerLine as the successful bidder for the WFMAC Project. The AESO and Alberta PowerLine then entered into a project agreement for the WFMAC Project, which includes payment provisions, price adjustment mechanism provisions, and other provisions governing the terms and conditions of service between Alberta PowerLine and the AESO. Accordingly, pursuant to Section 24.2(4) of the Transmission Regulation, the Commission finds that the project agreement between the AESO and Alberta PowerLine is a resulting arrangement from a Commission-approved competitive process developed under Subsection 24.2(2) of the Transmission Regulation, and therefore the Commission considers the project agreement to be prudent. 21. For clarity, the Commission has not received an application pursuant to subsections 24.3(3) or (4) of the Transmission Regulation, and is not making any approvals or determinations in this decision in relation to these provisions. Dated on January 23, Alberta Utilities Commission (original signed by) Mark Kolesar Vice-Chair Decision D (January 23, 2018) 5

8

9 Appendix 1 Proceeding participants Name of organization (abbreviation) Company name of counsel or representative Alberta PowerLine L.P. (Alberta PowerLine) Bennett Jones LLP Alberta Electric System Operator (AESO) Office of the Utilities Consumer Advocate (UCA) Consumers Coalition of Alberta (CCA) Alberta Utilities Commission Commission panel M. Kolesar, Vice-Chair Commission staff J. Graham (Commission counsel) L. Mullen D. Ward M. Kopp-van Egteren Decision D (January 23, 2018) 1

Decision D ATCO Electric Ltd. Compliance Filing to Decision D Capital Tracker True-Up

Decision D ATCO Electric Ltd. Compliance Filing to Decision D Capital Tracker True-Up Decision 23454-D01-2018 ATCO Electric Ltd. Compliance Filing to Decision 22788-D01-2018 2016 Capital Tracker True-Up May 4, 2018 Alberta Utilities Commission Decision 23454-D01-2018 ATCO Electric Ltd.

More information

EPCOR Distribution & Transmission Inc.

EPCOR Distribution & Transmission Inc. Decision 22603-D01-2017 June 23, 2017 Alberta Utilities Commission Decision 22603-D01-2017 Proceeding 22603 June 23, 2017 Published by the: Alberta Utilities Commission Fifth Avenue Place, Fourth Floor,

More information

Alberta Electric System Operator

Alberta Electric System Operator Decision 23065-D01-2017 Alberta Electric System Operator 2018 Independent System Operator Tariff Update November 28, 2017 Alberta Utilities Commission Decision 23065-D01-2017 Alberta Electric System Operator

More information

ATCO Electric Ltd. Stage 2 Review of Decision D ATCO Electric Ltd Transmission General Tariff Application

ATCO Electric Ltd. Stage 2 Review of Decision D ATCO Electric Ltd Transmission General Tariff Application Decision 22483-D01-2017 Stage 2 Review of Decision 20272-D01-2016 2015-2017 Transmission General Tariff Application December 6, 2017 Alberta Utilities Commission Decision 22483-D01-2017 Stage 2 Review

More information

EPCOR Distribution & Transmission Inc.

EPCOR Distribution & Transmission Inc. Decision 21229-D01-2016 EPCOR Distribution & Transmission Inc. 2015-2017 Transmission Facility Owner Tariff and 2013 Generic Cost of Capital Compliance Application April 15, 2016 Alberta Utilities Commission

More information

Decision D FortisAlberta Inc. Light-Emitting Diode Lighting Conversion Maintenance Multiplier for the City of St.

Decision D FortisAlberta Inc. Light-Emitting Diode Lighting Conversion Maintenance Multiplier for the City of St. Decision 21754-D01-2016 Light-Emitting Diode Lighting Conversion Maintenance Multiplier for the City of St. Albert August 11, 2016 Alberta Utilities Commission Decision 21754-D01-2016 Light-Emitting Diode

More information

Decision ATCO Electric Ltd. February 1, 2013 Interim Tariff. January 18, 2013

Decision ATCO Electric Ltd. February 1, 2013 Interim Tariff. January 18, 2013 Decision 2013-015 February 1, 2013 Interim Tariff January 18, 2013 The Alberta Utilities Commission Decision 2013-015: February 1, 2013 Interim Tariff Application No. 1609127 Proceeding ID No. 2305 January

More information

Decision D ATCO Electric Ltd. Amounts to be Paid Into and Out of Balancing Pool for Chinchaga Power Plant Sale

Decision D ATCO Electric Ltd. Amounts to be Paid Into and Out of Balancing Pool for Chinchaga Power Plant Sale Decision 21833-D01-2016 Amounts to be Paid Into and Out of Balancing Pool for Chinchaga Power Plant Sale December 20, 2016 Alberta Utilities Commission Decision 21833-D01-2016 Proceeding 21833 December

More information

Decision D FortisAlberta Inc Performance-Based Regulation Capital Tracker True-Up. January 11, 2018

Decision D FortisAlberta Inc Performance-Based Regulation Capital Tracker True-Up. January 11, 2018 Decision 22741-D01-2018 FortisAlberta Inc. 2016 Performance-Based Regulation Capital Tracker True-Up January 11, 2018 Alberta Utilities Commission Decision 22741-D01-2018 FortisAlberta Inc. 2016 Performance-Based

More information

Canadian Natural Resources Limited

Canadian Natural Resources Limited Decision 22669-D03-2017 Application for an Order Permitting the Sharing of Records Not Available to the Public Between Canadian Natural Resources Limited and ATCO Power Canada Ltd. July 21, 2017 Alberta

More information

ENMAX Energy Corporation

ENMAX Energy Corporation Decision 23006-D01-2018 Regulated Rate Option - Energy Price Setting Plan Monthly Filings for Acknowledgment 2017 Quarter 3 February 7, 2018 Alberta Utilities Commission Decision 23006-D01-2018: Regulated

More information

AltaLink Investment Management Ltd. And SNC Lavalin Transmission Ltd. et al.

AltaLink Investment Management Ltd. And SNC Lavalin Transmission Ltd. et al. Decision 3529-D01-2015 AltaLink Investment Management Ltd. And SNC Lavalin Transmission Ltd. et al. Proposed Sale of AltaLink, L.P Transmission Assets and Business to Mid-American (Alberta) Canada Costs

More information

ENMAX Power Corporation

ENMAX Power Corporation Decision 22238-D01-2017 ENMAX Power Corporation 2016-2017 Transmission General Tariff Application December 4, 2017 Alberta Utilities Commission Decision 22238-D01-2017 ENMAX Power Corporation 2016-2017

More information

Decision D FortisAlberta Inc PBR Capital Tracker True-Up and PBR Capital Tracker Forecast

Decision D FortisAlberta Inc PBR Capital Tracker True-Up and PBR Capital Tracker Forecast Decision 20497-D01-2016 FortisAlberta Inc. 2014 PBR Capital Tracker True-Up and 2016-2017 PBR Capital Tracker Forecast February 20, 2016 Alberta Utilities Commission Decision 20497-D01-2016 FortisAlberta

More information

Daishowa-Marubeni International Ltd.

Daishowa-Marubeni International Ltd. Decision 2011-299 25-MW Condensing Steam Turbine Generator July 8, 2011 The Alberta Utilities Commission Decision 2011-299: 25-MW Condensing Steam Turbine Generator Application No. 1606747 Proceeding ID

More information

AltaGas Utilities Inc.

AltaGas Utilities Inc. Decision 23898-D01-2018 2019 Annual Performance-Based Regulation Rate Adjustment Filing December 20, 2018 Alberta Utilities Commission Decision 23898-D01-2018 2019 Annual Performance-Based Regulation Rate

More information

AltaLink Management Ltd.

AltaLink Management Ltd. Decision 22025-D03-2017 Red Deer Area Transmission Development Amendment Application June 8, 2017 Decision 22025-D03-2017 Red Deer Area Transmission Development Amendment Application Proceeding 22025 Applications

More information

AltaLink Management Ltd.

AltaLink Management Ltd. Decision 21368-D01-2016 Advance Funding Request from the Cooking Lake Opposition Group Advance Funding Award March 14, 2016 Alberta Utilities Commission Decision 21368-D01-2016: Advance Funding Request

More information

Decision D Rebasing for the PBR Plans for Alberta Electric and Gas Distribution Utilities. First Compliance Proceeding

Decision D Rebasing for the PBR Plans for Alberta Electric and Gas Distribution Utilities. First Compliance Proceeding Decision 22394-D01-2018 Rebasing for the 2018-2022 PBR Plans for February 5, 2018 Alberta Utilities Commission Decision 22394-D01-2018 Rebasing for the 2018-2022 PBR Plans for Proceeding 22394 February

More information

TransCanada Energy Ltd.

TransCanada Energy Ltd. Decision 22302-D01-2017 Request for Permitting the Sharing of Records Not Available to the Public Between and Pembina Pipeline Corporation May 26, 2017 Alberta Utilities Commission Decision 22302-D01-2017

More information

ATCO Electric and ATCO Pipelines. Application for ATCO Electric and ATCO Pipelines License Fees

ATCO Electric and ATCO Pipelines. Application for ATCO Electric and ATCO Pipelines License Fees Decision 21571-D01-2016 and ATCO Pipelines 2015-2016 License Fees August 17, 2016 Alberta Utilities Commission Decision 21571-D01-2016 and ATCO Pipelines 2015-2016 License Fees Proceeding 21571 August

More information

Alberta Utilities Commission

Alberta Utilities Commission Alberta Utilities Commission In the Matter of the Need for the Kirby North Central Processing Facility Connection And in the matter of the Electric Utilities Act, S.A. 2003, c. E-5.1, the Alberta Utilities

More information

The University of Calgary

The University of Calgary Decision 23147-D01-2018 Application for an Order Permitting the Sharing of Records Not Available to the Public Between the University of Calgary and URICA Energy Real Time Ltd. January 30, 2018 Alberta

More information

FortisAlberta Inc. Sale and Transfer of the Municipality of Crowsnest Pass Electric Distribution Assets

FortisAlberta Inc. Sale and Transfer of the Municipality of Crowsnest Pass Electric Distribution Assets Decision 21785-D01-2018 Sale and Transfer of the Electric Distribution Assets June 5, 2018 Alberta Utilities Commission Decision 21785-D01-2018 Sale and Transfer of the Electric Distribution System Assets

More information

ENMAX Power Corporation Distribution and Transmission Deferral Account Reconciliation

ENMAX Power Corporation Distribution and Transmission Deferral Account Reconciliation Decision 23108-D01-2018 2014 Distribution and 2014-2015 Transmission Deferral Account Reconciliation February 27, 2018 Alberta Utilities Commission Decision 23108-D01-2018 2014 Distribution and 2014-2015

More information

AltaGas Utilities Inc.

AltaGas Utilities Inc. Decision 21822-D01-2016 AltaGas Utilities Inc. 2016-2017 Unaccounted-For Gas Rider E and Rider H September 1, 2016 Alberta Utilities Commission Decision 21822-D01-2016 AltaGas Utilities Inc. 2016-2017

More information

ENMAX Power Corporation

ENMAX Power Corporation Decision 22756-D01-2017 Tax Agreement with The City of Calgary September 7, 2017 Alberta Utilities Commission Decision 22756-D01-2017 Tax Agreement with The City of Calgary Proceeding 22756 September 7,

More information

Decision D Generic Cost of Capital. Costs Award

Decision D Generic Cost of Capital. Costs Award Decision 21856-D01-2016 Costs Award December 2, 2016 Alberta Utilities Commission Decision 21856-D01-2016 Costs Award Proceeding 21856 December 2, 2016 Published by Alberta Utilities Commission Fifth Avenue

More information

AltaLink Management Ltd.

AltaLink Management Ltd. Decision 21054-D01-2016 2013-2014 General Tariff Application (Proceeding 2044-Reopened for Midgard Audit) March 7, 2016 Alberta Utilities Commission Decision 21054-D01-2016: Proceeding 21054 March 7,

More information

AltaLink Management Ltd. & EPCOR Distribution & Transmission Inc.

AltaLink Management Ltd. & EPCOR Distribution & Transmission Inc. Decision 2013-280 AltaLink Management Ltd. & EPCOR Distribution & Transmission Inc. Heartland Transmission Project Amendment Structure T176 Repositioning Costs Award July 29, 2013 The Alberta Utilities

More information

Alberta Electric System Operator, AltaLink Management Ltd. and ENMAX Power Corporation. Foothills Area Transmission Development

Alberta Electric System Operator, AltaLink Management Ltd. and ENMAX Power Corporation. Foothills Area Transmission Development Decision 2013-087 Alberta Electric System Operator, AltaLink Management Ltd. and ENMAX Power Corporation Foothills Area Transmission Development March 12, 2013 The Alberta Utilities Commission Decision

More information

Alberta Utilities Commission

Alberta Utilities Commission Alberta Utilities Commission In the Matter of the Need for the Irma Wind Power Project Connection And in the matter of the Electric Utilities Act, S.A. 2003, c. E-5.1, the Alberta Utilities Commission

More information

AltaLink Management Ltd.

AltaLink Management Ltd. Decision 22612-D01-2018 November 13, 2018 Alberta Utilities Commission Decision 22612-D01-2018 to PiikaniLink L.P. and KainaiLink L.P. and the Proceeding 22612 Applications 22612-A001, 22612-A002, 22612-A003,

More information

Canadian Natural Resources Limited

Canadian Natural Resources Limited Decision 21306-D01-2016 Determination of Compensation for 9L66/9L32 Transmission Line Relocation August 16, 2016 Alberta Utilities Commission Decision 21306-D01-2016 Determination of Compensation for 9L66/9L32

More information

Shell Canada Limited and Canadian Natural Resources Limited

Shell Canada Limited and Canadian Natural Resources Limited Decision 22614-D01-2017 Albian Oil Sands Industrial Complex and June 28, 2017 Alberta Utilities Commission Decision 22614-D01-2017 Albian Oil Sands Industrial Complex and Proceeding 22614 Applications

More information

ATCO Gas and Pipelines Ltd.

ATCO Gas and Pipelines Ltd. Decision 2738-D01-2016 Z Factor Application for Recovery of 2013 Southern Alberta Flood Costs March 16, 2016 Alberta Utilities Commission Decision 2738-D01-2016 Z Factor Application for Recovery of 2013

More information

Alberta Utilities Commission

Alberta Utilities Commission Decision 22091-D01-2017 Commission-Initiated Proceeding to Review the Terms and November 9, 2017 Decision 22091-D01-2017 Commission-Initiated Proceeding to Review the Terms and Proceeding 22091 Application

More information

Decision ATCO Utilities. Corporate Cost Allocation Methodology. September 20, 2010

Decision ATCO Utilities. Corporate Cost Allocation Methodology. September 20, 2010 Decision 2010-447 Corporate Cost Allocation Methodology September 20, 2010 ALBERTA UTILITIES COMMISSION Decision 2010-447: Corporate Cost Allocation Methodology Application No. 1605473 Proceeding ID. 306

More information

AltaGas Utilities Inc.

AltaGas Utilities Inc. Decision 2013-465 2014 Annual PBR Rate Adjustment Filing December 23, 2013 The Alberta Utilities Commission Decision 2013-465: 2014 Annual PBR Rate Adjustment Filing Application No. 1609923 Proceeding

More information

The University of Calgary

The University of Calgary Decision 2014-365 Preferential Sharing of Records between the University of Calgary and URICA Energy Real Time Ltd. December 19, 2014 The Alberta Utilities Commission Decision 2014-365: Preferential Sharing

More information

Decision D Balancing Pool

Decision D Balancing Pool Decision 22184-D10-2017 Application for an Order Permitting the Sharing of Records Not Available to the Public Between the, TransAlta Generation Partnership, and Capital Power Generation Services Inc.

More information

ATCO Gas and Pipelines Ltd. (South)

ATCO Gas and Pipelines Ltd. (South) Decision 3421-D01-2015 Northeast Calgary Connector Pipeline January 16, 2015 The Alberta Utilities Commission Decision 3421-D01-2015: Northeast Calgary Connector Pipeline Application 1610854 Proceeding

More information

Alberta Utilities Commission

Alberta Utilities Commission Alberta Utilities Commission In the Matter of the Need for the Riverview Wind Power Plant Connection And in the matter of the Electric Utilities Act, S.A. 2003, c. E-5.1, the Alberta Utilities Commission

More information

EPCOR Energy Alberta GP Inc.

EPCOR Energy Alberta GP Inc. Decision 20633-D01-2016 EPCOR Energy Alberta GP Inc. 2016-2017 Regulated Rate Tariff Application December 20, 2016 Alberta Utilities Commission Decision 20633-D01-2016 EPCOR Energy Alberta GP Inc. 2016-2017

More information

Decision ATCO Electric Ltd. Bonnyville to Bourque Transmission Line Project. Costs Award. October 9, 2013

Decision ATCO Electric Ltd. Bonnyville to Bourque Transmission Line Project. Costs Award. October 9, 2013 Decision 2013-374 Bonnyville to Bourque Transmission Line Project Costs Award October 9, 2013 The Alberta Utilities Commission Decision 2013-374: Bonnyville to Bourque Transmission Line Project Costs Award

More information

ENMAX Energy Corporation

ENMAX Energy Corporation Decision 22054-D01-2017 Regulated Rate Option Tariff Terms and Conditions Amendment Application April 12, 2017 Alberta Utilities Commission Decision 22054-D01-2017 Regulated Rate Option Tariff Terms and

More information

Livingstone Landowners Guild

Livingstone Landowners Guild Decision 20846-D01-2016 Livingstone Landowners Guild Application for Review of Decision 2009-126 Needs Identification Document Application Southern Alberta Transmission System Reinforcement as amended

More information

West Wetaskiwin Rural Electrification Association Ltd.

West Wetaskiwin Rural Electrification Association Ltd. Decision 22067-D01-2016 West Wetaskiwin Rural Electrification Association Ltd. Varied Code of Conduct Regulation Compliance Plan December 21, 2016 Alberta Utilities Commission Decision 22067-D01-2016 West

More information

Mackenzie Rural Electrification Association Ltd.

Mackenzie Rural Electrification Association Ltd. Decision 21983-D01-2016 Varied Code of Conduct Regulation Compliance Plan December 14, 2016 Alberta Utilities Commission Decision 21983-D01-2016 Varied Code of Conduct Regulation Compliance Plan Proceeding

More information

Alberta Electric System Operator 2017 ISO Tariff Update

Alberta Electric System Operator 2017 ISO Tariff Update Alberta Electric System Operator 2017 ISO Tariff Update Date: October 20, 2016 Prepared by: Alberta Electric System Operator Prepared for: Alberta Utilities Commission Classification: Public Table of Contents

More information

Alberta Utilities Commission

Alberta Utilities Commission Alberta Utilities Commission In the Matter of the Need for the ATCO Power Heartland Generating Station Connection And in the matter of the Electric Utilities Act, S.A. 2003, c. E-5.1, the Alberta Utilities

More information

Decision The ATCO Utilities. Corporate Costs. March 21, 2013

Decision The ATCO Utilities. Corporate Costs. March 21, 2013 Decision 2013-111 Corporate Costs March 21, 2013 The Alberta Utilities Commission Decision 2013-111: Corporate Costs Application No. 1608510 Proceeding ID No. 1920 March 21, 2013 Published by The Alberta

More information

Acciona Wind Energy Canada, Inc.

Acciona Wind Energy Canada, Inc. Decision 2013-439 Acciona Wind Energy Canada, Inc. New Dayton Wind Power Project Facility & Substation Costs Award December 11, 2013 The Alberta Utilities Commission Decision 2013-439: Acciona Wind Energy

More information

Langdon Waterworks Limited

Langdon Waterworks Limited Decision 20372-D01-2015 May 14, 2015 Alberta Utilities Commission Decision 20372-D01-2015 Proceeding 20372 May 14, 2015 Published by the: Alberta Utilities Commission Fifth Avenue Place, Fourth Floor,

More information

Brion Energy Corporation

Brion Energy Corporation Decision 21524-D01-2016 MacKay River Commercial Project Ownership Change for the Sales Oil Pipeline Lease Automated Custody Transfer Site June 14, 2016 Alberta Utilities Commission Decision 21524-D01-2016

More information

Mayerthorpe and District Rural Electrification Association Ltd.

Mayerthorpe and District Rural Electrification Association Ltd. Decision 22692-D01-2018 Mayerthorpe and District Rural Electrification Association Ltd. Varied Code of Conduct Regulation Compliance Plan January 31, 2018 Alberta Utilities Commission Decision 22692-D01-2018

More information

Consumers Coalition of Alberta

Consumers Coalition of Alberta Decision 22157-D01-2017 Decision on Preliminary Question AltaLink Management Ltd. 2012-2013 Deferral Account Reconciliation Costs Award February 15, 2017 Alberta Utilities Commission Decision 22157-D01-2017

More information

AltaGas Utilities Inc.

AltaGas Utilities Inc. Decision 23740-D01-2018 AltaGas Utilities Inc. 2018-2019 Unaccounted-For Gas Rider E and Rider H October 25, 2018 Alberta Utilities Commission Decision 23740-D01-2018 AltaGas Utilities Inc. 2018-2019 Unaccounted-For

More information

BMO Infrastructure & Utilities Conference February 8, 2018 Toronto

BMO Infrastructure & Utilities Conference February 8, 2018 Toronto BMO Infrastructure & Utilities Conference February 8, 2018 Toronto LEGAL DISCLAIMER Statements made by representatives for ATCO Ltd. and Canadian Utilities Limited and information provided in this presentation

More information

INVESTOR PRESENTATION JUNE 2018

INVESTOR PRESENTATION JUNE 2018 INVESTOR PRESENTATION JUNE 2018 LEGAL DISCLAIMER Statements made by representatives for ATCO Ltd. and Canadian Utilities Limited and information provided in this presentation may be considered forward-looking

More information

INVESTOR PRESENTATION JUNE 2018

INVESTOR PRESENTATION JUNE 2018 INVESTOR PRESENTATION JUNE 2018 LEGAL DISCLAIMER Statements made by representatives for ATCO Ltd. and Canadian Utilities Limited and information provided in this presentation JUNE be considered forward-looking

More information

Decision D FortisAlberta Inc.

Decision D FortisAlberta Inc. Decision 23063-D01-2018 Light-Emitting Diode Lighting Conversion Maintenance Multiplier Filing January 30, 2018 Alberta Utilities Commission Decision 23063-D01-2018 Light-Emitting Diode Lighting Conversion

More information

Alberta Utilities Commission

Alberta Utilities Commission Alberta Utilities Commission In the Matter of the Need for the Jenner Wind Energy Connection And in the matter of the Electric Utilities Act, S.A. 2003, c. E-5.1, the Alberta Utilities Commission Act,

More information

Alberta Electric System Operator Amended 2018 ISO Tariff Application

Alberta Electric System Operator Amended 2018 ISO Tariff Application Alberta Electric System Operator Amended 2018 ISO Tariff Application Date: August 17, 2018 Table of Contents 1 Application... 6 1.1 Background... 6 1.2 Organization of application... 7 1.3 Relief requested...

More information

EPCOR Distribution & Transmission Inc.

EPCOR Distribution & Transmission Inc. Decision 3539-D01-2015 EPCOR Distribution & Transmission Inc. 2015-2017 Transmission Facility Owner Tariff October 21, 2015 Alberta Utilities Commission Decision 3539-D01-2015: EPCOR Distribution & Transmission

More information

Decision D Performance-Based Regulation Plans for Alberta Electric and Gas Distribution Utilities.

Decision D Performance-Based Regulation Plans for Alberta Electric and Gas Distribution Utilities. Decision 22082-D01-2017 2018-2022 Performance-Based Regulation Plans for Alberta Electric and Gas Distribution Utilities February 6, 2017 Alberta Utilities Commission Decision 22082-D01-2017 2018-2022

More information

Kneehill Rural Electrification Association Ltd.

Kneehill Rural Electrification Association Ltd. Decision 23420-D01-2018 Kneehill Rural Electrification Association Ltd. Varied Code of Conduct Regulation Compliance Plan April 23, 2018 Alberta Utilities Commission Decision 23420-D01-2018 Kneehill Rural

More information

AltaLink Management Ltd. ATCO Electric Ltd.

AltaLink Management Ltd. ATCO Electric Ltd. Decision 2012-139 May 22, 2012 The Alberta Utilities Commission Decision 2012-139: and Application Nos. 1607971 and 1608183 Proceeding ID No. 1623 May 22, 2012 Published by The Alberta Utilities Commission

More information

Decision D FortisAlberta Inc. Light-Emitting Diode (LED) Lighting Conversion Maintenance Multiplier Filing for 30 Customers in 2018

Decision D FortisAlberta Inc. Light-Emitting Diode (LED) Lighting Conversion Maintenance Multiplier Filing for 30 Customers in 2018 Decision 23730-D01-2018 Light-Emitting Diode (LED) Lighting Conversion Maintenance Multiplier Filing for 30 Customers in 2018 September 7, 2018 Alberta Utilities Commission Decision 23730-D01-2018 Light-Emitting

More information

Alberta Utilities Commission

Alberta Utilities Commission Alberta Utilities Commission In the Matter of the Need for the Grizzly Bear Creek Wind Power Plant Connection And in the matter of the Electric Utilities Act, S.A. 2003, c. E-5.1, the Alberta Utilities

More information

Alberta Electric System Operator 2018 ISO Tariff Application

Alberta Electric System Operator 2018 ISO Tariff Application Alberta Electric System Operator 2018 ISO Tariff Application Date: September 14, 2017 Table of Contents 1 Application... 6 1.1 Background... 6 1.2 Organization of application... 6 1.3 Relief requested...

More information

CIBC CALGARY FIXED INCOME CONFERENCE. April 11, 2018

CIBC CALGARY FIXED INCOME CONFERENCE. April 11, 2018 CIBC CALGARY FIXED INCOME CONFERENCE April 11, 2018 LEGAL DISCLAIMER Statements made by representatives for ATCO Ltd. and Canadian Utilities Limited and information provided in this presentation may be

More information

Immediate Attention for Piikani Nation Members

Immediate Attention for Piikani Nation Members Immediate Attention for Piikani Nation Members IMPORTANT INFORMATION Altalink L.P., Transfer of Specific Assets to PiikaniLink L.P. and associated 2017-2018 General Tariff Application. AUC Proceeding 22612

More information

Decision CU Water Limited. Disposition of Assets. April 30, 2010

Decision CU Water Limited. Disposition of Assets. April 30, 2010 Decision 2010-192 Disposition of Assets April 30, 2010 ALBERTA UTILITIES COMMISSION Decision 2010-192: Disposition of Assets Application No. 1606042 Proceeding ID. 569 April 30, 2010 Published by Alberta

More information

AltaGas Utilities Inc.

AltaGas Utilities Inc. Decision 23623-D01-2018 AltaGas Utilities Inc. 2017 Capital Tracker True-Up Application December 18, 2018 Alberta Utilities Commission Decision 23623-D01-2018 AltaGas Utilities Inc. 2017 Capital Tracker

More information

Decision Wind Power Inc. Request to Transfer Power Plant Approval No. U November 26, 2008

Decision Wind Power Inc. Request to Transfer Power Plant Approval No. U November 26, 2008 Decision 2008-121 Wind Power Inc. Request to Transfer Power Plant Approval No. U2007-74 November 26, 2008 ALBERTA UTILITIES COMMISSION Decision 2008-121: Wind Power Inc. Request to Transfer Power Plant

More information

E.ON Climate & Renewables Canada Ltd. Grizzly Bear Creek Wind Power Project

E.ON Climate & Renewables Canada Ltd. Grizzly Bear Creek Wind Power Project Decision 21513-D01-2016 Grizzly Bear Creek Wind Power Project July 21, 2016 Alberta Utilities Commission Decision 21513-D01-2016 Grizzly Bear Creek Wind Power Project Proceeding 21513 July 21, 2016 Published

More information

Langdon Waterworks Limited

Langdon Waterworks Limited Decision 2014-240 August 19, 2014 The Alberta Utilities Commission Decision 2014-240: Application No. 1610617 Proceeding No. 3258 August 19, 2014 Published by The Alberta Utilities Commission Fifth Avenue

More information

Decision FortisAlberta Inc Phase II Distribution Tariff. January 27, 2014

Decision FortisAlberta Inc Phase II Distribution Tariff. January 27, 2014 Decision 2014-018 FortisAlberta Inc. 2012-2014 Phase II Distribution Tariff January 27, 2014 The Alberta Utilities Commission Decision 2014-018: FortisAlberta Inc. 2012-2014 Phase II Distribution Tariff

More information

ATCO Gas and Pipelines Ltd. (South)

ATCO Gas and Pipelines Ltd. (South) Decision 22634-D01-2017 Southwest Calgary Connector Pipeline Project August 9, 2017 Alberta Utilities Commission Decision 22634-D01-2017 Southwest Calgary Connector Pipeline Project Proceeding 22634 Application

More information

Report to the Minister. For the Year Ending December 31, March 20, 2015

Report to the Minister. For the Year Ending December 31, March 20, 2015 Report to the Minister For the Year Ending December 31, 2014 March 20, 2015 Market Surveillance Administrator 403.705.3181 #500, 400 5th Avenue S.W., Calgary AB T2P 0L6 www.albertamsa.ca Table of Contents

More information

Enbridge Battle Sands 594S Substation Connection Needs Identification Document

Enbridge Battle Sands 594S Substation Connection Needs Identification Document APPENDIX C AESO PIP Enbridge Battle Sands 594S Substation Connection Needs Identification Document 1.0 Participant Involvement Program (PIP) From June to October 2015, the AESO conducted a Participant

More information

2011 Generic Cost of Capital

2011 Generic Cost of Capital Decision 2011-474 2011 Generic Cost of Capital December 8, 2011 The Alberta Utilities Commission Decision 2011-474: 2011 Generic Cost of Capital Application No. 1606549 Proceeding ID No. 833 December 8,

More information

Senior Manager, Government and Regulatory Affairs Direct Energy Marketing Limited

Senior Manager, Government and Regulatory Affairs Direct Energy Marketing Limited December 22, 2017 Decision 23226-D01-2017 Direct Energy Marketing Limited Suite 501, 525 Eighth Ave. S.W. Calgary, Alta. T2P 1G1 Attention: Ms. Nicole Black Senior Manager, Government and Regulatory Affairs

More information

Alberta Energy-Capacity Market Framework Engagement November 2017

Alberta Energy-Capacity Market Framework Engagement November 2017 Questions for discussion The engagement is seeking feedback on the six questions outlined in the table below. Please provide your input on these questions in Table 1 on the next three pages. Please submit

More information

ATCO Gas and Pipelines Ltd. (South)

ATCO Gas and Pipelines Ltd. (South) Decision 2010-170 New Construction Replacement of ATCO Pipelines Existing Southern Extension Pipeline From North of Lacombe to East of Gwynne April 15, 2010 ALBERTA UTILITIES COMMISSION Decision 2010-170:

More information

2015 Deferral Account Reconciliation Application Consultation Meeting. LaRhonda Papworth, Regulatory May 3, Calgary

2015 Deferral Account Reconciliation Application Consultation Meeting. LaRhonda Papworth, Regulatory May 3, Calgary 2015 Deferral Account Reconciliation Application Consultation Meeting LaRhonda Papworth, Regulatory May 3, 2016 - Calgary Agenda Objectives and scope (slides 3-4) Deferral account reconciliation application

More information

AltaLink Management Ltd.

AltaLink Management Ltd. Decision 20986-D01-2016 Southwest Calgary Ring Road Transmission Project August 31, 2016 Alberta Utilities Commission Decision 20986-D01-2016 Southwest Calgary Ring Road Transmission Project Proceeding

More information

AltaLink Management Ltd.

AltaLink Management Ltd. Decision 3524-D01-2016 AltaLink Management Ltd. 2015-2016 General Tariff Application May 9, 2016 Alberta Utilities Commission Decision 3524-D01-2016 AltaLink Management Ltd. 2015-2016 General Tariff Application

More information

AltaLink Investment Management Ltd. and SNC Lavalin Transmission Ltd. et al.

AltaLink Investment Management Ltd. and SNC Lavalin Transmission Ltd. et al. Decision 2014-326 AltaLink Investment Management Ltd. and SNC Lavalin Transmission Ltd. et al. Proposed Sale of AltaLink, L.P. Transmission Assets and Business to MidAmerican (Alberta) Canada Holdings

More information

APPENDIX E. Red Deer Region Transmission Development. Economic Comparison

APPENDIX E. Red Deer Region Transmission Development. Economic Comparison APPENDIX E Red Deer Region Transmission Development Economic Comparison Introduction. Using capital costs provided by the legal owner of transmission facilities (TFO), AltaLink, the AESO has conducted

More information

Alberta Utilities Commission

Alberta Utilities Commission Alberta Utilities Commission In the Matter of the Need for the Al Rothbauer 321S Substation And in the matter of the Electric Utilities Act, S.A. 2003, c. E-5.1, the Alberta Utilities Commission Act, S.A.

More information

Service area. EPCOR Distribution & Transmission Inc. a) Subject to rules b), c), d), and e),

Service area. EPCOR Distribution & Transmission Inc. a) Subject to rules b), c), d), and e), 9. TRANSMISSION 9.1 Facility Projects 9.1.1 Eligible TFO 9.1.1.1 Eligibility by Service Area Subject to rule 9.1.1.2 b), c), d), and e) each service area shall have one TFO eligible to apply for the construction

More information

Collaborative Process

Collaborative Process Alberta Energy and Utilities Board Utility Cost Order 2006-065 Uniform System of Accounts and Minimum Filing Requirements Cost Awards ALBERTA ENERGY AND UTILITIES BOARD Utility Cost Order 2006-065 Uniform

More information

Alberta Utilities Commission

Alberta Utilities Commission Alberta Utilities Commission In the Matter of the Need for 138 kv and 240 kv Transmission System Development in the Red Deer Region And in the matter of the Electric Utilities Act, S.A. 2003, c. E-5.1,

More information

Decision D ATCO Electric Ltd Transmission General Tariff Application. Costs Award

Decision D ATCO Electric Ltd Transmission General Tariff Application. Costs Award Decision 21747-D01-2017 January 30, 2017 Alberta Utilities Commission Decision 21747-D01-2017 Proceeding 21747 January 30, 2017 Published by Alberta Utilities Commission Fifth Avenue Place, Fourth Floor,

More information

ATCO Pipelines ATCO Gas and Pipelines Ltd. CU Inc. Canadian Utilities Limited

ATCO Pipelines ATCO Gas and Pipelines Ltd. CU Inc. Canadian Utilities Limited Decision 2012-068 Disposition of Surplus Salt Cavern Assets in the Fort Saskatchewan Area March 16, 2012 The Alberta Utilities Commission Decision 2012-068:,,, Disposition of Surplus Salt Cavern Assets

More information

AltaLink Management Ltd. and EPCOR Distribution & Transmission Inc.

AltaLink Management Ltd. and EPCOR Distribution & Transmission Inc. Decision 2012-124 Decision on Request for Review and Variance of AUC Decision 2011-436 Heartland Transmission Project May 14, 2012 The Alberta Utilities Commission Decision 2012-124: Decision on Request

More information

Decision D ATCO Electric Ltd. Hughes 2030S Substation. Costs Award

Decision D ATCO Electric Ltd. Hughes 2030S Substation. Costs Award Decision 22406-D01-2017 Hughes 2030S Substation June 9, 2017 Alberta Utilities Commission Decision 22406-D01-2017 Hughes 2030S Substation Proceeding 22406 June 9, 2017 Published by Alberta Utilities Commission

More information