Decision Wind Power Inc. Request to Transfer Power Plant Approval No. U November 26, 2008

Size: px
Start display at page:

Download "Decision Wind Power Inc. Request to Transfer Power Plant Approval No. U November 26, 2008"

Transcription

1 Decision Wind Power Inc. Request to Transfer Power Plant Approval No. U November 26, 2008

2 ALBERTA UTILITIES COMMISSION Decision : Wind Power Inc. Request to Transfer Power Plant Approval No. U Application No November 26, 2008 Published by Alberta Utilities Commission Fifth Avenue Place, 4th Floor, Street SW Calgary, Alberta T2P 3L8 Telephone: (403) Fax: (403) Web site:

3 Contents 1 INTRODUCTION BACKGROUND DISCUSSION OF ISSUES Ability of CRR LP to hold Approval DECISION... 3 AUC Decision (November 26, 2008) i

4

5 ALBERTA UTILITIES COMMISSION Calgary Alberta WIND POWER INC. REQUEST TO TRANSFER Decision POWER PLANT APPROVAL NO. U Application No INTRODUCTION Wind Power Inc. (WPI) filed a letter of enquiry with the Alberta Utilities Commission (the Commission) on March 27, 2008, regarding a proposed change of ownership of the Castle Rock Ridge Wind Plant. WPI currently holds Power Plant Approval U , and seeks to transfer the approval from WPI to Castle Rock Ridge Limited Partnership (CRR LP). 2 BACKGROUND The original WPI project (known as the Castle Rock Ridge Wind Plant) was initially approved in early 2002, to be located in an area north of Pincher Station and south of the Old Man River. The original approval was for 56 ENERCON model E66 wind turbines, each rated at 1.8 MW. Since the original approval of the project, WPI has twice applied for, and received, regulatory approvals for modifications to the project. The first application for modification occured in 2005, when WPI applied to install more modern wind turbines. Subsequently, in 2007, WPI applied for a second capacity increase due to new technologies developed by the turbine manufacturer, which resulted in turbine increases from 2 MW to 2.3 MW. Also, a number of turbines were removed from the original project.with these latest modifications, the project would have 50 turbines and a total installed capacity of 115 MW. However, WPI has yet to start construction of the project due to insufficient transmission capacity out of the Pincher Creek area. On March 27, 2008, WPI filed a letter of enquiry with the Commission regarding a proposed change of ownership of the Castle Rock Ridge Wind Plant - for which WPI held Power Plant Approval U from WPI to CRR LP. WPI indicated that upon transfer, CRR LP would have all legal rights and obligations for the project. WPI indicated that it was partnering with CRR LP to build the project. As a result, the project assets are being transferred and assigned to CRR LP and CRR LP is financing, building, and will own the facility. WPI indicated that Castle Rock Ridge Limited Partnership is a limited partnership formed between several wholly-owned subsidiaries of Enel North America, Inc. One of these subsidiaries, Enel Alberta Wind Inc., is the General Partner of the CRR LP. The Commission issued a letter to WPI on April 11, 2008, requesting further information regarding the organizational structure of the participants, financial statements, details of the financing arrangements, information regarding the assumption of liability and confirmation that WPI sought the transfer of the approval to a limited partnership (LP), not a corporation. On July 14, 2008, WPI submitted its responses to the Commission s information requests and confirmed that CRR LP was the intended transferee of Approval U AUC Decision (November 26, 2008) 1

6 Transfer of Power Plant Approval No. U Wind Power Inc. 3 DISCUSSION OF ISSUES 3.1 Ability of CRR LP to hold Approval The application filed by WPI required that the Commission determine whether CRR LP was eligible to hold Approval U Section 11 of the Hydro and Electric Energy Act (HEEA), which sets out the requirements for Commission approval of power plants as defined in that Act, reads as follows: 11 No person shall construct or operate a power plant unless the Commission, by order, has approved the construction and operation of the power plant. [emphasis added] Person is defined in HEEA as: (j) person includes a municipal corporation or other corporation. 1 While the use of the word includes usually implies an expansive interpretation, in this case, the fact that the definition lists types of corporations suggests that a narrower interpretation is intended. 2 Notably, the legislature chose not to explicitly include partnerships, limited or otherwise, in the definition of person in the HEEA. 3 Alberta s Partnership Act 4 (Partnership Act) does not define an LP as a person nor does it explicitly grant LPs the powers of a person. This is in contrast to the Business Corporations Act which specifically provides that a corporation has the rights, powers and privileges of a natural person 5 (i.e. an individual). Notably, subsection 55(3) of the Partnership Act requires that the general partner of an LP (which must be a person), and not the LP, be registered at the land titles registry as owner of any interest of the LP in real property. An LP, like a corporation, is a creature of statute - created by the filing of documentation prescribed by statute. Unlike a corporation however, an LP is generally not considered a separate legal entity; rather, an LP acts through its general partner The Interpretation Act (RSA 2000 Chapter I-8) also has an inclusive definition for person: (nn) person includes a corporation and the heirs, executors, administrators or other legal representatives of a person. Applying the principle of noscitur a sociis: This is a well-known rule of interpretation: a term or expression cannot be interpreted without taking surrounding terms into account. The meaning of a term is revealed by its association with other terms: it is known by its associates (noscitur a sociis). This general principle is most often applied in interpreting terms that are part of a list. (see Québec Inc. v. Quebec (Régie des permis d'alcool) [1996] S.C.J. No. 112 at para 195) Unlike, for example, the definition of person in the Business Corporations Act: (x) person includes an individual, partnership, association, body corporate, trustee, executor, administrator or legal representative. RSA 2000 Ch P-3 Business Corporations Act, RSA 2000 Ch B-9, section 16(1). See Kucor Construction & Developments & Associates v. Canada Life Assurance Co., [1998] O.J. No (Ont. C.A.) at para 26: The concept that neither a general, nor a limited partnership, is a legal entity has been long accepted by Canadian and English law and, no doubt, is why a limited partnership is required by law to have a general partner through which it normally acts: Limited Partnerships Act, ss. 2(2), 8 and AUC Decision (November 26, 2008)

7 Transfer of Power Plant Approval No. U Wind Power Inc. 4 DECISION The HEEA is silent as to whether an LP may be considered a person for the purposes of holding an approval under section 11 of that Act. However, the Commission is satisfied that the legal status of an LP at common law is sufficiently limited to require that a general partner which does have the status of a person - must hold the approval under section 11 of the HEEA on behalf of the LP. The Commission therefore denies the application by Wind Power Inc. to transfer Power Plant Approval U from Wind Power Inc. to Castle Rock Ridge Limited Partnership, but will consider an amended application by WPI, to transfer Power Plant Approval U from Wind Power Inc. to Enel Alberta Wind Inc., in its capacity as general partner of the Castle Rock Ridge Limited Partnership. Dated in Calgary, Alberta on November 26, ALBERTA UTILITIES COMMISSION (original signed by) Carolyn Dahl Rees Vice-Chair AUC Decision (November 26, 2008) 3

Livingstone Landowners Guild

Livingstone Landowners Guild Decision 20846-D01-2016 Livingstone Landowners Guild Application for Review of Decision 2009-126 Needs Identification Document Application Southern Alberta Transmission System Reinforcement as amended

More information

Acciona Wind Energy Canada, Inc.

Acciona Wind Energy Canada, Inc. Decision 2013-439 Acciona Wind Energy Canada, Inc. New Dayton Wind Power Project Facility & Substation Costs Award December 11, 2013 The Alberta Utilities Commission Decision 2013-439: Acciona Wind Energy

More information

Decision CU Water Limited. Disposition of Assets. April 30, 2010

Decision CU Water Limited. Disposition of Assets. April 30, 2010 Decision 2010-192 Disposition of Assets April 30, 2010 ALBERTA UTILITIES COMMISSION Decision 2010-192: Disposition of Assets Application No. 1606042 Proceeding ID. 569 April 30, 2010 Published by Alberta

More information

Shell Canada Limited and Canadian Natural Resources Limited

Shell Canada Limited and Canadian Natural Resources Limited Decision 22614-D01-2017 Albian Oil Sands Industrial Complex and June 28, 2017 Alberta Utilities Commission Decision 22614-D01-2017 Albian Oil Sands Industrial Complex and Proceeding 22614 Applications

More information

Brion Energy Corporation

Brion Energy Corporation Decision 21524-D01-2016 MacKay River Commercial Project Ownership Change for the Sales Oil Pipeline Lease Automated Custody Transfer Site June 14, 2016 Alberta Utilities Commission Decision 21524-D01-2016

More information

Alberta Utilities Commission

Alberta Utilities Commission Alberta Utilities Commission In the Matter of the Need for the Riverview Wind Power Plant Connection And in the matter of the Electric Utilities Act, S.A. 2003, c. E-5.1, the Alberta Utilities Commission

More information

Daishowa-Marubeni International Ltd.

Daishowa-Marubeni International Ltd. Decision 2011-299 25-MW Condensing Steam Turbine Generator July 8, 2011 The Alberta Utilities Commission Decision 2011-299: 25-MW Condensing Steam Turbine Generator Application No. 1606747 Proceeding ID

More information

Decision D Alberta PowerLine L.P. Tariff Application. January 23, 2018

Decision D Alberta PowerLine L.P. Tariff Application. January 23, 2018 Decision 23161-D01-2018 Alberta PowerLine L.P. Tariff Application January 23, 2018 Alberta Utilities Commission Decision 23161-D01-2018 Alberta PowerLine L.P. Tariff Application Proceeding 23161 January

More information

AltaLink Management Ltd.

AltaLink Management Ltd. Decision 22025-D03-2017 Red Deer Area Transmission Development Amendment Application June 8, 2017 Decision 22025-D03-2017 Red Deer Area Transmission Development Amendment Application Proceeding 22025 Applications

More information

EPCOR Distribution & Transmission Inc.

EPCOR Distribution & Transmission Inc. Decision 22603-D01-2017 June 23, 2017 Alberta Utilities Commission Decision 22603-D01-2017 Proceeding 22603 June 23, 2017 Published by the: Alberta Utilities Commission Fifth Avenue Place, Fourth Floor,

More information

Canadian Natural Resources Limited

Canadian Natural Resources Limited Decision 22669-D03-2017 Application for an Order Permitting the Sharing of Records Not Available to the Public Between Canadian Natural Resources Limited and ATCO Power Canada Ltd. July 21, 2017 Alberta

More information

Decision D FortisAlberta Inc. Light-Emitting Diode Lighting Conversion Maintenance Multiplier for the City of St.

Decision D FortisAlberta Inc. Light-Emitting Diode Lighting Conversion Maintenance Multiplier for the City of St. Decision 21754-D01-2016 Light-Emitting Diode Lighting Conversion Maintenance Multiplier for the City of St. Albert August 11, 2016 Alberta Utilities Commission Decision 21754-D01-2016 Light-Emitting Diode

More information

AltaLink Management Ltd. & EPCOR Distribution & Transmission Inc.

AltaLink Management Ltd. & EPCOR Distribution & Transmission Inc. Decision 2013-280 AltaLink Management Ltd. & EPCOR Distribution & Transmission Inc. Heartland Transmission Project Amendment Structure T176 Repositioning Costs Award July 29, 2013 The Alberta Utilities

More information

Mayerthorpe and District Rural Electrification Association Ltd.

Mayerthorpe and District Rural Electrification Association Ltd. Decision 22692-D01-2018 Mayerthorpe and District Rural Electrification Association Ltd. Varied Code of Conduct Regulation Compliance Plan January 31, 2018 Alberta Utilities Commission Decision 22692-D01-2018

More information

AltaLink Investment Management Ltd. And SNC Lavalin Transmission Ltd. et al.

AltaLink Investment Management Ltd. And SNC Lavalin Transmission Ltd. et al. Decision 3529-D01-2015 AltaLink Investment Management Ltd. And SNC Lavalin Transmission Ltd. et al. Proposed Sale of AltaLink, L.P Transmission Assets and Business to Mid-American (Alberta) Canada Costs

More information

AltaGas Utilities Inc.

AltaGas Utilities Inc. Decision 21822-D01-2016 AltaGas Utilities Inc. 2016-2017 Unaccounted-For Gas Rider E and Rider H September 1, 2016 Alberta Utilities Commission Decision 21822-D01-2016 AltaGas Utilities Inc. 2016-2017

More information

Mackenzie Rural Electrification Association Ltd.

Mackenzie Rural Electrification Association Ltd. Decision 21983-D01-2016 Varied Code of Conduct Regulation Compliance Plan December 14, 2016 Alberta Utilities Commission Decision 21983-D01-2016 Varied Code of Conduct Regulation Compliance Plan Proceeding

More information

ENMAX Power Corporation

ENMAX Power Corporation Decision 22756-D01-2017 Tax Agreement with The City of Calgary September 7, 2017 Alberta Utilities Commission Decision 22756-D01-2017 Tax Agreement with The City of Calgary Proceeding 22756 September 7,

More information

TransCanada Energy Ltd.

TransCanada Energy Ltd. Decision 22302-D01-2017 Request for Permitting the Sharing of Records Not Available to the Public Between and Pembina Pipeline Corporation May 26, 2017 Alberta Utilities Commission Decision 22302-D01-2017

More information

ENMAX Energy Corporation

ENMAX Energy Corporation Decision 23006-D01-2018 Regulated Rate Option - Energy Price Setting Plan Monthly Filings for Acknowledgment 2017 Quarter 3 February 7, 2018 Alberta Utilities Commission Decision 23006-D01-2018: Regulated

More information

Alberta Utilities Commission

Alberta Utilities Commission Alberta Utilities Commission In the Matter of the Need for the Kirby North Central Processing Facility Connection And in the matter of the Electric Utilities Act, S.A. 2003, c. E-5.1, the Alberta Utilities

More information

ENMAX Power Corporation Distribution and Transmission Deferral Account Reconciliation

ENMAX Power Corporation Distribution and Transmission Deferral Account Reconciliation Decision 23108-D01-2018 2014 Distribution and 2014-2015 Transmission Deferral Account Reconciliation February 27, 2018 Alberta Utilities Commission Decision 23108-D01-2018 2014 Distribution and 2014-2015

More information

The University of Calgary

The University of Calgary Decision 23147-D01-2018 Application for an Order Permitting the Sharing of Records Not Available to the Public Between the University of Calgary and URICA Energy Real Time Ltd. January 30, 2018 Alberta

More information

Investigation into the Use of Concessionary Government Funds by Competitive Affiliates of ENMAX Power Corporation

Investigation into the Use of Concessionary Government Funds by Competitive Affiliates of ENMAX Power Corporation Investigation into the Use of Concessionary Government Funds by Competitive Affiliates of ENMAX Power Corporation November 9, 2010 Market Surveillance Administrator 403.705.3181 #500, 400 5th Avenue S.W.,

More information

ATCO Gas and Pipelines Ltd. (South)

ATCO Gas and Pipelines Ltd. (South) Decision 2010-170 New Construction Replacement of ATCO Pipelines Existing Southern Extension Pipeline From North of Lacombe to East of Gwynne April 15, 2010 ALBERTA UTILITIES COMMISSION Decision 2010-170:

More information

Decision D ATCO Electric Ltd. Amounts to be Paid Into and Out of Balancing Pool for Chinchaga Power Plant Sale

Decision D ATCO Electric Ltd. Amounts to be Paid Into and Out of Balancing Pool for Chinchaga Power Plant Sale Decision 21833-D01-2016 Amounts to be Paid Into and Out of Balancing Pool for Chinchaga Power Plant Sale December 20, 2016 Alberta Utilities Commission Decision 21833-D01-2016 Proceeding 21833 December

More information

Canadian Hydro Developers, Inc.

Canadian Hydro Developers, Inc. Decision 2005-070 Request for Review and Variance of Decision Contained in EUB Letter Dated April 14, 2003 Respecting the Price Payable for Power from the Belly River, St. Mary and Waterton Hydroelectric

More information

Decision ATCO Electric Ltd. February 1, 2013 Interim Tariff. January 18, 2013

Decision ATCO Electric Ltd. February 1, 2013 Interim Tariff. January 18, 2013 Decision 2013-015 February 1, 2013 Interim Tariff January 18, 2013 The Alberta Utilities Commission Decision 2013-015: February 1, 2013 Interim Tariff Application No. 1609127 Proceeding ID No. 2305 January

More information

Veresen Inc. Suite 440, Livingston Place Tel (403) rrd Avenue S.W. Fax (403)

Veresen Inc. Suite 440, Livingston Place Tel (403) rrd Avenue S.W. Fax (403) Veresen Inc. Suite 440, Livingston Place Tel (403) 296-0140 222 3rrd Avenue S.W. Fax (403) 213-3648 Calgary, Alberta T2P 0B4 www.vereseninc.com February 25, 2011 RE: 2010 INCOME TAX FORMS T5013 and Relevé

More information

ATCO Electric Ltd. Stage 2 Review of Decision D ATCO Electric Ltd Transmission General Tariff Application

ATCO Electric Ltd. Stage 2 Review of Decision D ATCO Electric Ltd Transmission General Tariff Application Decision 22483-D01-2017 Stage 2 Review of Decision 20272-D01-2016 2015-2017 Transmission General Tariff Application December 6, 2017 Alberta Utilities Commission Decision 22483-D01-2017 Stage 2 Review

More information

Decision D FortisAlberta Inc.

Decision D FortisAlberta Inc. Decision 23063-D01-2018 Light-Emitting Diode Lighting Conversion Maintenance Multiplier Filing January 30, 2018 Alberta Utilities Commission Decision 23063-D01-2018 Light-Emitting Diode Lighting Conversion

More information

ATCO Pipelines ATCO Gas and Pipelines Ltd. CU Inc. Canadian Utilities Limited

ATCO Pipelines ATCO Gas and Pipelines Ltd. CU Inc. Canadian Utilities Limited Decision 2012-068 Disposition of Surplus Salt Cavern Assets in the Fort Saskatchewan Area March 16, 2012 The Alberta Utilities Commission Decision 2012-068:,,, Disposition of Surplus Salt Cavern Assets

More information

Decision D Balancing Pool

Decision D Balancing Pool Decision 22184-D10-2017 Application for an Order Permitting the Sharing of Records Not Available to the Public Between the, TransAlta Generation Partnership, and Capital Power Generation Services Inc.

More information

BILL 211 ALBERTA PERSONAL INCOME TAX (SCHOOL TAX CREDIT) AMENDMENT ACT, Bill 211. Fourth Session, 25th Legislature, 53 Elizabeth II

BILL 211 ALBERTA PERSONAL INCOME TAX (SCHOOL TAX CREDIT) AMENDMENT ACT, Bill 211. Fourth Session, 25th Legislature, 53 Elizabeth II 2004 Bill 211 Fourth Session, 25th Legislature, 53 Elizabeth II THE LEGISLATIVE ASSEMBLY OF ALBERTA BILL 211 ALBERTA PERSONAL INCOME TAX (SCHOOL TAX CREDIT) AMENDMENT ACT, 2004 MR. VANDERMEER First Reading.................................................

More information

The University of Calgary

The University of Calgary Decision 2014-365 Preferential Sharing of Records between the University of Calgary and URICA Energy Real Time Ltd. December 19, 2014 The Alberta Utilities Commission Decision 2014-365: Preferential Sharing

More information

Decision D Rebasing for the PBR Plans for Alberta Electric and Gas Distribution Utilities. First Compliance Proceeding

Decision D Rebasing for the PBR Plans for Alberta Electric and Gas Distribution Utilities. First Compliance Proceeding Decision 22394-D01-2018 Rebasing for the 2018-2022 PBR Plans for February 5, 2018 Alberta Utilities Commission Decision 22394-D01-2018 Rebasing for the 2018-2022 PBR Plans for Proceeding 22394 February

More information

Nova Scotia Company and TE-TAU, Inc.

Nova Scotia Company and TE-TAU, Inc. Alberta Energy and Utilities Board Decision 2004-025 3057246 Nova Scotia Company and TE-TAU, Inc. Request for Relief Under Section 101(2) of the PUB Act March 16, 2004 ALBERTA ENERGY AND UTILITIES BOARD

More information

Decision ATCO Utilities. Corporate Cost Allocation Methodology. September 20, 2010

Decision ATCO Utilities. Corporate Cost Allocation Methodology. September 20, 2010 Decision 2010-447 Corporate Cost Allocation Methodology September 20, 2010 ALBERTA UTILITIES COMMISSION Decision 2010-447: Corporate Cost Allocation Methodology Application No. 1605473 Proceeding ID. 306

More information

AltaGas Utilities Inc.

AltaGas Utilities Inc. Decision 2013-465 2014 Annual PBR Rate Adjustment Filing December 23, 2013 The Alberta Utilities Commission Decision 2013-465: 2014 Annual PBR Rate Adjustment Filing Application No. 1609923 Proceeding

More information

Langdon Waterworks Limited

Langdon Waterworks Limited Decision 20372-D01-2015 May 14, 2015 Alberta Utilities Commission Decision 20372-D01-2015 Proceeding 20372 May 14, 2015 Published by the: Alberta Utilities Commission Fifth Avenue Place, Fourth Floor,

More information

Alberta Electric System Operator, AltaLink Management Ltd. and ENMAX Power Corporation. Foothills Area Transmission Development

Alberta Electric System Operator, AltaLink Management Ltd. and ENMAX Power Corporation. Foothills Area Transmission Development Decision 2013-087 Alberta Electric System Operator, AltaLink Management Ltd. and ENMAX Power Corporation Foothills Area Transmission Development March 12, 2013 The Alberta Utilities Commission Decision

More information

Alberta Utilities Commission

Alberta Utilities Commission Alberta Utilities Commission In the Matter of the Need for the Irma Wind Power Project Connection And in the matter of the Electric Utilities Act, S.A. 2003, c. E-5.1, the Alberta Utilities Commission

More information

ATCO Electric and ATCO Pipelines. Application for ATCO Electric and ATCO Pipelines License Fees

ATCO Electric and ATCO Pipelines. Application for ATCO Electric and ATCO Pipelines License Fees Decision 21571-D01-2016 and ATCO Pipelines 2015-2016 License Fees August 17, 2016 Alberta Utilities Commission Decision 21571-D01-2016 and ATCO Pipelines 2015-2016 License Fees Proceeding 21571 August

More information

Form F1 REPORT OF EXEMPT DISTRIBUTION

Form F1 REPORT OF EXEMPT DISTRIBUTION Form 45-106F1 REPORT OF EXEMPT DISTRIBUTION This is the form required under section 6.1 of National Instrument 45-106 for a report of exempt distribution. Issuer/underwriter information Item 1: State the

More information

FORM F1 REPORT OF EXEMPT DISTRIBUTION

FORM F1 REPORT OF EXEMPT DISTRIBUTION FORM 45-106F1 REPORT OF EXEMPT DISTRIBUTION This is the form required under section 6.1 of National Instrument 45-106 for a report of exempt distribution. Issuer information Item 1: State the full name

More information

Alberta Utilities Commission

Alberta Utilities Commission Alberta Utilities Commission In the Matter of the Need for the ATCO Power Heartland Generating Station Connection And in the matter of the Electric Utilities Act, S.A. 2003, c. E-5.1, the Alberta Utilities

More information

Audited Financial Statements For the years ended December 31, 2017 and 2016

Audited Financial Statements For the years ended December 31, 2017 and 2016 FORTISALBERTA INC. Audited Financial Statements MANAGEMENT S REPORT The accompanying 2017 Financial Statements of FortisAlberta Inc. (the Corporation ) have been prepared by management, who are responsible

More information

PEMBINA PIPELINE CORPORATION. Premium Dividend and Dividend Reinvestment Plan QUESTIONS AND ANSWERS

PEMBINA PIPELINE CORPORATION. Premium Dividend and Dividend Reinvestment Plan QUESTIONS AND ANSWERS PEMBINA PIPELINE CORPORATION Premium Dividend and Dividend Reinvestment Plan QUESTIONS AND ANSWERS The following series of questions and answers explains some of the key features of the Premium Dividend

More information

Decision ATCO Electric Ltd. Bonnyville to Bourque Transmission Line Project. Costs Award. October 9, 2013

Decision ATCO Electric Ltd. Bonnyville to Bourque Transmission Line Project. Costs Award. October 9, 2013 Decision 2013-374 Bonnyville to Bourque Transmission Line Project Costs Award October 9, 2013 The Alberta Utilities Commission Decision 2013-374: Bonnyville to Bourque Transmission Line Project Costs Award

More information

ATCO Gas and Pipelines Ltd.

ATCO Gas and Pipelines Ltd. Decision 2738-D01-2016 Z Factor Application for Recovery of 2013 Southern Alberta Flood Costs March 16, 2016 Alberta Utilities Commission Decision 2738-D01-2016 Z Factor Application for Recovery of 2013

More information

Dividend Reinvestment and Share Purchase Plan. Offering Circular April 1, 2010

Dividend Reinvestment and Share Purchase Plan. Offering Circular April 1, 2010 Dividend Reinvestment and Share Purchase Plan Offering Circular April 1, 2010 April 1, 2010 Table of Contents Summary... 1 Price... 1 The Plan... 2 Shares Offered... 2 Eligible Participants... 2 Eligible

More information

and TRUSTEE S REPORT TO THE CREDITORS ON PRELIMINARY ADMINISTRATION

and TRUSTEE S REPORT TO THE CREDITORS ON PRELIMINARY ADMINISTRATION Deloitte Restructuring Inc. La Tour Deloitte 1190 Avenue des Canadiens-de-Montréal Suite 500 Montreal QC H3B 0M7 Canada Phone: 514-393-7115 Fax: 514-390-4103 www.deloitte.ca C A N A D A PROVINCE OF QUEBEC

More information

Alberta Utilities Commission

Alberta Utilities Commission Decision 22091-D01-2017 Commission-Initiated Proceeding to Review the Terms and November 9, 2017 Decision 22091-D01-2017 Commission-Initiated Proceeding to Review the Terms and Proceeding 22091 Application

More information

ROYAL ALEXANDRA HOSPITAL FOUNDATION PRIVACY POLICY

ROYAL ALEXANDRA HOSPITAL FOUNDATION PRIVACY POLICY ROYAL ALEXANDRA HOSPITAL FOUNDATION PRIVACY POLICY 1. INTRODUCTION 1.1 The Royal Alexandra Hospital Foundation (the Foundation ) is committed to safeguarding the personal information provided to us by

More information

ATCO Gas and Pipelines Ltd. (South)

ATCO Gas and Pipelines Ltd. (South) Decision 22634-D01-2017 Southwest Calgary Connector Pipeline Project August 9, 2017 Alberta Utilities Commission Decision 22634-D01-2017 Southwest Calgary Connector Pipeline Project Proceeding 22634 Application

More information

TAX INSTRUCTION LETTER

TAX INSTRUCTION LETTER TAX INSTRUCTION LETTER To: Former holders of common shares of Reliable Energy Ltd. ("Reliable") who exchanged their common shares of Reliable directly with Crescent Point Energy Corp. ("CPEC") for common

More information

Dividend Reinvestment Plan QUESTIONS AND ANSWERS

Dividend Reinvestment Plan QUESTIONS AND ANSWERS Dividend Reinvestment Plan QUESTIONS AND ANSWERS The following series of questions and answers explains some of the key features of the Dividend Reinvestment Plan of Canadian Utilities Limited (the "Corporation")

More information

Multilateral CSA Notice of Adoption of Multilateral Instrument Protection of Minority Security Holders in Special Transactions

Multilateral CSA Notice of Adoption of Multilateral Instrument Protection of Minority Security Holders in Special Transactions Multilateral CSA Notice of Adoption of Multilateral Instrument 61-101 Protection of Minority Security Holders in Special Transactions July 20, 2017 Introduction The Alberta Securities Commission (the ASC),

More information

PEMBINA PIPELINE CORPORATION. Premium Dividend and Dividend Reinvestment Plan QUESTIONS AND ANSWERS

PEMBINA PIPELINE CORPORATION. Premium Dividend and Dividend Reinvestment Plan QUESTIONS AND ANSWERS PEMBINA PIPELINE CORPORATION Premium Dividend and Dividend Reinvestment Plan QUESTIONS AND ANSWERS The following series of questions and answers explains some of the key features of the Premium Dividend

More information

Province of Alberta ALBERTA HOUSING ACT. Revised Statutes of Alberta 2000 Chapter A-25. Current as of July 1, Office Consolidation

Province of Alberta ALBERTA HOUSING ACT. Revised Statutes of Alberta 2000 Chapter A-25. Current as of July 1, Office Consolidation Province of Alberta ALBERTA HOUSING ACT Revised Statutes of Alberta 2000 Current as of July 1, 2015 Office Consolidation Published by Alberta Queen s Printer Alberta Queen s Printer Suite 700, Park Plaza

More information

Canadian Natural Resources Limited

Canadian Natural Resources Limited Decision 21306-D01-2016 Determination of Compensation for 9L66/9L32 Transmission Line Relocation August 16, 2016 Alberta Utilities Commission Decision 21306-D01-2016 Determination of Compensation for 9L66/9L32

More information

Alberta Utilities Commission

Alberta Utilities Commission Alberta Utilities Commission In the Matter of the Need for the Grizzly Bear Creek Wind Power Plant Connection And in the matter of the Electric Utilities Act, S.A. 2003, c. E-5.1, the Alberta Utilities

More information

Kneehill Rural Electrification Association Ltd.

Kneehill Rural Electrification Association Ltd. Decision 23420-D01-2018 Kneehill Rural Electrification Association Ltd. Varied Code of Conduct Regulation Compliance Plan April 23, 2018 Alberta Utilities Commission Decision 23420-D01-2018 Kneehill Rural

More information

ACCREDITED INVESTOR CERTIFICATE (To be completed by Accredited Investors only)

ACCREDITED INVESTOR CERTIFICATE (To be completed by Accredited Investors only) ACCREDITED INVESTOR CERTIFICATE (To be completed by Accredited Investors only) TO: STEWART S VERTICAL FARMS INC. (the "Issuer") ACCREDITED INVESTOR (DEFINED IN NI 45-106): The undersigned, who is interested

More information

The Alberta Lawyers Insurance Association. Non-consolidated Financial Statements June 30, 2009

The Alberta Lawyers Insurance Association. Non-consolidated Financial Statements June 30, 2009 The Alberta Lawyers Insurance Association Non-consolidated Financial Statements PricewaterhouseCoopers LLP Chartered Accountants 111 5 Avenue SW, Suite 3100 Calgary, Alberta Canada T2P 5L3 Telephone +1

More information

West Wetaskiwin Rural Electrification Association Ltd.

West Wetaskiwin Rural Electrification Association Ltd. Decision 22067-D01-2016 West Wetaskiwin Rural Electrification Association Ltd. Varied Code of Conduct Regulation Compliance Plan December 21, 2016 Alberta Utilities Commission Decision 22067-D01-2016 West

More information

Calgary Office th Ave. SW, Suite 900 Calgary, AB, Canada T2P 4V1

Calgary Office th Ave. SW, Suite 900 Calgary, AB, Canada T2P 4V1 Calgary Office 1000 5 th Ave. SW, Suite 900 Calgary, AB, Canada T2P 4V1 phone: 403-705-0202 fax: 403-264-8399 email: brobinson@ecojustice.ca www.ecojustice.ca August 24, 2010 Energy Resources Conservation

More information

Report of Management. Auditors Report

Report of Management. Auditors Report Report of Management The consolidated financial statements and all the information in the 2007 annual report are the responsibility of management. The financial statements have been prepared in accordance

More information

PERSONS WITH DEVELOPMENTAL DISABILITIES FOUNDATION ACT

PERSONS WITH DEVELOPMENTAL DISABILITIES FOUNDATION ACT Province of Alberta PERSONS WITH DEVELOPMENTAL DISABILITIES FOUNDATION ACT Revised Statutes of Alberta 2000 Current as of January 1, 2002 Published by Alberta Queen s Printer Alberta Queen s Printer 7

More information

DIVIDEND REINVESTMENT PLAN

DIVIDEND REINVESTMENT PLAN DIVIDEND REINVESTMENT PLAN PURPOSE The Dividend Reinvestment Plan (the "Plan") provides eligible holders ("Shareholders") of common shares ("Shares") of TransAlta Renewables Inc. (the "Corporation") the

More information

EARLY CHILDHOOD SERVICES REGULATION

EARLY CHILDHOOD SERVICES REGULATION Province of Alberta SCHOOL ACT EARLY CHILDHOOD SERVICES REGULATION Alberta Regulation 31/2002 With amendments up to and including Alberta Regulation 133/2015 Office Consolidation Published by Alberta Queen

More information

ENMAX Energy Corporation

ENMAX Energy Corporation Decision 22054-D01-2017 Regulated Rate Option Tariff Terms and Conditions Amendment Application April 12, 2017 Alberta Utilities Commission Decision 22054-D01-2017 Regulated Rate Option Tariff Terms and

More information

Capital Power Corporation. Halkirk 2 Wind Power Project

Capital Power Corporation. Halkirk 2 Wind Power Project Decision 23255-D01-2018 Capital Power Corporation Halkirk 2 Wind Power Project July 9, 2018 Alberta Utilities Commission Decision 23255-D01-2018 Capital Power Corporation Halkirk 2 Wind Power Project Proceeding

More information

FortisAlberta Inc. Sale and Transfer of the Municipality of Crowsnest Pass Electric Distribution Assets

FortisAlberta Inc. Sale and Transfer of the Municipality of Crowsnest Pass Electric Distribution Assets Decision 21785-D01-2018 Sale and Transfer of the Electric Distribution Assets June 5, 2018 Alberta Utilities Commission Decision 21785-D01-2018 Sale and Transfer of the Electric Distribution System Assets

More information

Decision Town of Innisfail. Franchise Agreement with ATCO Gas and Pipelines Ltd. and Amendment to Rider A.

Decision Town of Innisfail. Franchise Agreement with ATCO Gas and Pipelines Ltd. and Amendment to Rider A. Decision 2012-300 Franchise Agreement with ATCO Gas and Pipelines Ltd. and Amendment to Rider A November 9, 2012 The Alberta Utilities Commission Decision 2012-300: Franchise Agreement with ATCO Gas and

More information

Information Bulletin. In this issue. Ontario Presents its 2017 Economic Statement and Introduces New Budget Measures Bill

Information Bulletin. In this issue. Ontario Presents its 2017 Economic Statement and Introduces New Budget Measures Bill Aon Hewitt Retirement and Investment Information Bulletin November 20, 2017 In this issue Ontario Pension Reform Continues 2 Defined Benefit Plans New Funding Framework Funding and Governance Policies

More information

Extractive Sector Transparency Measures Act Annual Report

Extractive Sector Transparency Measures Act Annual Report Extractive Sector Transparency Measures Act Annual Report Reporting Year From: 01/01/16 To: 12/31/16 Subsidiary Reporting Entities (if necessary) Attestation: Please check one of the boxes below and provide

More information

AltaLink Management Ltd.

AltaLink Management Ltd. Decision 21368-D01-2016 Advance Funding Request from the Cooking Lake Opposition Group Advance Funding Award March 14, 2016 Alberta Utilities Commission Decision 21368-D01-2016: Advance Funding Request

More information

SECURITIES AND EXCHANGE COMMISSION WASHINGTON, D.C FORM 6-K. TransCanada PipeLines Limited (Translation of Registrant s Name into English)

SECURITIES AND EXCHANGE COMMISSION WASHINGTON, D.C FORM 6-K. TransCanada PipeLines Limited (Translation of Registrant s Name into English) SECURITIES AND EXCHANGE COMMISSION WASHINGTON, D.C. 20549 FORM 6-K REPORT OF FOREIGN PRIVATE ISSUER PURSUANT TO RULE 13a-16 OR 15d-16 OF THE SECURITIES EXCHANGE ACT OF 1934 For the month of March 2006

More information

Extractive Sector Transparency Measures Act - Annual Report

Extractive Sector Transparency Measures Act - Annual Report Extractive Sector Transparency Measures Act - Annual Report Reporting Entity Name Reporting Year From 2017-01-01 To: 2017-12-31 Reporting Entity ESTMA Identification Number Other Subsidiaries Included

More information

AltaLink Management Ltd.

AltaLink Management Ltd. Decision 21054-D01-2016 2013-2014 General Tariff Application (Proceeding 2044-Reopened for Midgard Audit) March 7, 2016 Alberta Utilities Commission Decision 21054-D01-2016: Proceeding 21054 March 7,

More information

ALTAGAS LTD. Premium Dividend, Dividend Reinvestment and Optional Cash Purchase Plan QUESTIONS AND ANSWERS

ALTAGAS LTD. Premium Dividend, Dividend Reinvestment and Optional Cash Purchase Plan QUESTIONS AND ANSWERS ALTAGAS LTD. Premium Dividend, Dividend Reinvestment and Optional Cash Purchase Plan QUESTIONS AND ANSWERS The following series of questions and answers explains some of the key features of the Premium

More information

Decision D ATCO Electric Ltd. Compliance Filing to Decision D Capital Tracker True-Up

Decision D ATCO Electric Ltd. Compliance Filing to Decision D Capital Tracker True-Up Decision 23454-D01-2018 ATCO Electric Ltd. Compliance Filing to Decision 22788-D01-2018 2016 Capital Tracker True-Up May 4, 2018 Alberta Utilities Commission Decision 23454-D01-2018 ATCO Electric Ltd.

More information

SECOND QUARTER 2017 CONFERENCE CALL & WEBCAST. August 4, 2017

SECOND QUARTER 2017 CONFERENCE CALL & WEBCAST. August 4, 2017 SECOND QUARTER 2017 CONFERENCE CALL & WEBCAST August 4, 2017 FORWARD-LOOKING INFORMATION To inform readers of the Corporation's future prospects, this document contains forward-looking information within

More information

ALBERTA SECURITIES COMMISSION BLANKET ORDER Citation: Re Blanket Order , 2017 ABASC 9 Date:

ALBERTA SECURITIES COMMISSION BLANKET ORDER Citation: Re Blanket Order , 2017 ABASC 9 Date: ALBERTA SECURITIES COMMISSION BLANKET ORDER 91-507 Citation: Re Blanket Order 91-507, 2017 ABASC 9 Date: 20170123 Over-the-Counter Trades in Derivatives Definitions 1. Terms defined in the Securities Act

More information

ecc,1/1-04-er 2o1.-0 ARTICLES OF ARRANGEMENT 3. Name of Corporation: 4. Corporate Access Number:

ecc,1/1-04-er 2o1.-0 ARTICLES OF ARRANGEMENT 3. Name of Corporation: 4. Corporate Access Number: iii I 11 II 10000607102675851 ARTICLES OF ARRANGEMENT Business Corporations Act Sections 193 3. Name of Corporation: 4. Corporate Access Number: BIG ROCK BREWERY INC. 3. The Articles of the Corporation

More information

NaturEner Energy Canada Inc.

NaturEner Energy Canada Inc. Decision 2009-174 Review and Variance of Alberta Utilities Commission Decision 2009-042 (October 22, 2009) ALBERTA UTILITIES COMMISSION Decision 2009-174, Review and Variance of Alberta Utilities Commission

More information

ALTAGAS INCOME TRUST

ALTAGAS INCOME TRUST Introduction ALTAGAS INCOME TRUST Premium Distribution TM, Distribution Reinvestment and Optional Unit Purchase Plan of AltaGas Income Trust for Holders of Trust Units This Premium Distribution TM, Distribution

More information

PROGRESS ENERGY RESOURCES CORP. DIVIDEND REINVESTMENT PLAN

PROGRESS ENERGY RESOURCES CORP. DIVIDEND REINVESTMENT PLAN PROGRESS ENERGY RESOURCES CORP. DIVIDEND REINVESTMENT PLAN PURPOSE The Dividend Reinvestment Plan (the "Plan") provides eligible holders ("Shareholders") of common shares ("Shares") of Progress Energy

More information

The Saskatchewan Gazette

The Saskatchewan Gazette THE SASKATCHEWAN GAZETTE, MAY 8, 2015 349 The Saskatchewan Gazette PUBLISHED WEEKLY BY AUTHORITY OF THE QUEEN S PRINTER/Publiée chaque semaine sous l autorité de l Imprimeur de la Reine PART II/PARTIE

More information

We believe that the audit evidence we have obtained in our audits is sufficient and appropriate to provide a basis for our audit opinion.

We believe that the audit evidence we have obtained in our audits is sufficient and appropriate to provide a basis for our audit opinion. Financial Statements For the years ended 2017 and 2016 Deloitte LLP 700, 850 2 Street SW Calgary, AB T2P 0R8 Canada Tel: 403-267-1700 Fax: 587-774-5379 www.deloitte.ca INDEPENDENT AUDITOR S REPORT To the

More information

ENMAX Power Corporation

ENMAX Power Corporation Decision 22238-D01-2017 ENMAX Power Corporation 2016-2017 Transmission General Tariff Application December 4, 2017 Alberta Utilities Commission Decision 22238-D01-2017 ENMAX Power Corporation 2016-2017

More information

CERTIFICATE AMALGAMATION

CERTIFICATE AMALGAMATION CORPORATE ACCESS NUMBER: 2021406448 BUSINESS CORPORATIONS ACT CERTIFICATE OF AMALGAMATION BAYTEX ENERGY LTD. IS THE RESULT OF AN AMALGAMATION FILED ON 2018/09/01. Amalgamate Alberta Corporation - Registration

More information

AltaGas Utilities Inc.

AltaGas Utilities Inc. Decision 23898-D01-2018 2019 Annual Performance-Based Regulation Rate Adjustment Filing December 20, 2018 Alberta Utilities Commission Decision 23898-D01-2018 2019 Annual Performance-Based Regulation Rate

More information

ENBRIDGE INCOME FUND HOLDINGS INC. DIVIDEND REINVESTMENT AND SHARE PURCHASE PLAN

ENBRIDGE INCOME FUND HOLDINGS INC. DIVIDEND REINVESTMENT AND SHARE PURCHASE PLAN ENBRIDGE INCOME FUND HOLDINGS INC. DIVIDEND REINVESTMENT AND SHARE PURCHASE PLAN Introduction Enbridge Income Fund Holdings Inc. (the "Corporation ) has established this dividend reinvestment and share

More information

The Alberta Lawyers Insurance Association. Non-consolidated Financial Statements December 31, 2013

The Alberta Lawyers Insurance Association. Non-consolidated Financial Statements December 31, 2013 The Alberta Lawyers Insurance Association Non-consolidated Financial Statements 2013 April 23, 2014 Independent Auditor s Report To the Directors of the Alberta Lawyers Insurance Association We have audited

More information

Alberta Electric System Operator

Alberta Electric System Operator Decision 23065-D01-2017 Alberta Electric System Operator 2018 Independent System Operator Tariff Update November 28, 2017 Alberta Utilities Commission Decision 23065-D01-2017 Alberta Electric System Operator

More information

The Alberta Lawyers Insurance Association. Non-consolidated Financial Statements June 30, 2010

The Alberta Lawyers Insurance Association. Non-consolidated Financial Statements June 30, 2010 The Alberta Lawyers Insurance Association Non-consolidated Financial Statements June 30, 2010 PricewaterhouseCoopers LLP Chartered Accountants 111 5 Avenue SW, Suite 3100 Calgary, Alberta Canada T2P 5L3

More information

The Alberta Lawyers Insurance Association. Non-consolidated Financial Statements December 31, 2014

The Alberta Lawyers Insurance Association. Non-consolidated Financial Statements December 31, 2014 The Alberta Lawyers Insurance Association Non-consolidated Financial Statements December 31, February 26 2015 Independent Auditor s Report To the Directors of the Alberta Lawyers Insurance Association

More information