Decision D ATCO Electric Ltd. Compliance Filing to Decision D Capital Tracker True-Up

Size: px
Start display at page:

Download "Decision D ATCO Electric Ltd. Compliance Filing to Decision D Capital Tracker True-Up"

Transcription

1 Decision D ATCO Electric Ltd. Compliance Filing to Decision D Capital Tracker True-Up May 4, 2018

2 Alberta Utilities Commission Decision D ATCO Electric Ltd. Compliance Filing to Decision D Capital Tracker True-Up Proceeding May 4, 2018 Published by the: Alberta Utilities Commission Eau Claire Tower, 1400, 600 Third Avenue S.W. Calgary, Alberta T2P 0G5 Telephone: Fax: Website:

3 Contents 1 Decision Introduction and procedural background Compliance with Commission directions Direction 1: Project descriptions of all non-capital tracker projects and programs Direction 4: 2016 actual capital additions for the Fort McMurray North Service Building Project Directions 5 and 7: Accounting test requirements of Criterion 1 and Criterion actual K factor Direction 11: Refund of the amount resulting from this compliance filing Order... 7 Appendix 1 Proceeding participants... 9 Appendix 2 Commission directions from Decision D List of tables Table K factor true-up... 4 Decision D (May 4, 2018) i

4

5 Alberta Utilities Commission Calgary, Alberta ATCO Electric Ltd. Compliance Filing to Decision D Decision D Capital Tracker True-Up Proceeding Decision 1. This decision provides the Alberta Utilities Commission s determination of ATCO Electric Ltd. s (ATCO Electric or AE) compliance with the Commission s directions issued in Decision D For the reasons outlined in this decision, the Commission determines that ATCO Electric has complied with the Commission s directions and approves ATCO Electric s 2016 K factor adjustment as applied for in the present compliance filing. The Commission approves the 2016 K factor true-up adjustment of $3.4 million arising from this decision to be included in ATCO Electric s 2019 performance-based regulation (PBR) rates, which will be established in the 2019 annual PBR rate adjustment filing due September 10, Introduction and procedural background 2. On February 23, 2018, the Commission issued Decision D , dealing with ATCO Electric s 2016 capital tracker true-up application. The decision included a direction to ATCO Electric to file a compliance filing by March 28, On March 28, 2018, ATCO Electric submitted its compliance filing with the Commission. The Commission issued a notice of application on April 5, 2018, providing an opportunity for interested parties who may be affected by the compliance filing to provide their statements of intent to participate (SIPs) by April 12, The Commission received SIPs from the Consumers Coalition of Alberta and the Office of the Utilities Consumer Advocate (UCA). 4. On April 11, 2018, ATCO Electric responded to a clarification information request (IR) that was issued by the Commission on April 5, On April 13, 2018, the Commission established a procedural schedule granting the Consumers Coalition of Alberta and the UCA an opportunity to test the application with a round of IRs to ATCO Electric. On April 19, 2018, the UCA advised the Commission that it would not be filing any IRs and did not see the need for any further process. After receiving ATCO Electric s responses to its IRs, the Consumers Coalition of Alberta advised the Commission on April 30, 2018, that it also did not see a need for any further process. 6. The Commission considers the record for this proceeding to have closed on April 30, 2018, when ATCO Electric and the Consumers Coalition of Alberta filed their submissions on the need for further process. 1 Decision D : ATCO Electric Ltd., 2016 Performance-Based Regulation Capital Tracker True-Up, Proceeding 22788, February 23, Decision D (May 4, 2018) 1

6 7. In reaching the determinations set out in this decision, the Commission has considered all relevant materials comprising the record of this proceeding, as well as related PBR and capital tracker decisions. Accordingly, reference in this decision to specific parts of the record are intended to assist the reader in understanding the Commission s reasoning relating to a particular matter and should not be taken as an indication that the Commission did not consider all relevant portions of the record with respect to this matter. 3 Compliance with Commission directions 8. In Decision D , the Commission issued 12 directions. Direction 12 directed ATCO Electric to file this compliance filing by March 28, Five other directions related to this compliance filing. The Commission has reproduced all 12 directions in Appendix 2 to this decision, and addresses ATCO Electric s response to the five relevant directions, directions 1, 4, 5, 7 and 11, in turn, in the sections that follow. 9. ATCO Electric also filed schedules 2 in the compliance filing that contain the results of the updated accounting test calculations and information required to demonstrate compliance with the Commission s directions. 3.1 Direction 1: Project descriptions of all non-capital tracker projects and programs 10. In its 2016 capital tracker true-up application, ATCO Electric did not provide descriptions of its non-capital tracker projects and programs that adequately described the nature and purpose of the proposed project or program for understanding project or program groupings. Therefore, at paragraph 22 of Decision D , the Commission directed ATCO Electric to provide these project descriptions. 11. In response to this direction, ATCO Electric provided descriptions of its non-capital tracker projects and programs in Appendix B of the compliance filing. 3 Commission findings 12. The Commission has reviewed the non-capital tracker projects or programs descriptions provided by ATCO Electric and is satisfied that the descriptions meet the minimum filing requirements set out in Appendix 3, part 3a of Decision 3558-D Therefore, the Commission finds that ATCO Electric has complied with the Commission s direction in Decision D at paragraph Direction 4: 2016 actual capital additions for the Fort McMurray North Service Building Project 13. In Decision D , the Commission determined that the existing building space available in the Fort McMurray area was sufficient to maintain service quality in 2016 and, therefore, that the new Fort McMurray North Service Building was not required in Accordingly, the Commission denied capital tracker treatment of the 2016 actual capital 2 Exhibit X0002, application, Appendix A. 3 Exhibit X0001, application, Appendix B. 4 Decision 3558-D : Distribution Performance-Based Regulation Commission-Initiated Proceeding to Consider Modifications to the Minimum Filing Requirements for Capital Tracker Applications, Proceeding 3558, Application , April 8, Decision D (May 4, 2018)

7 additions for this project and directed ATCO Electric to remove the 2016 capital additions related to the Fort McMurray North Service Building Project from the Buildings, Structures and Leasehold Improvements Program In the compliance filing, ATCO Electric removed actual capital additions of $20.2 million associated with the Fort McMurray North Service Building Project. 6 Commission findings 15. The Commission has reviewed the supporting schedules provided by ATCO Electric in the compliance filing and is satisfied that ATCO Electric correctly removed the actual 2016 capital addition amounts denied for capital tracker treatment from the Buildings, Structures and Leasehold Improvements Program in its accounting test model. The Commission finds that ATCO Electric has complied with the Commission s direction in Decision D at paragraph Directions 5 and 7: Accounting test requirements of Criterion 1 and Criterion At paragraph 145 of Decision D , the Commission directed ATCO Electric to revise its accounting test for 2016, based on the actual capital additions that were subject to adjustment and Commission directions in other sections of Decision D Further, at paragraphs 145 and 156 of the same decision, the Commission directed ATCO Electric to use the revised accounting test for 2016 to reassess whether its programs included in the 2016 trueup satisfy the accounting test requirement of Criterion 1 and the two-tiered materiality test requirement of Criterion In the compliance filing, ATCO Electric indicated that it revised its 2016 accounting test to reflect the directions set out in Decision D and confirmed that the programs included in the 2016 true-up continue to satisfy the accounting test requirement of Criterion 1 and the two-tiered materiality requirement of Criterion 3. 7 Commission findings 18. The Commission has reviewed ATCO Electric s updated accounting test calculations and finds that ATCO Electric has updated its accounting test schedules to reflect the directions set out in Decision D Further, the Commission has reviewed ATCO Electric s reassessment of its 2016 capital tracker programs, and is satisfied that ATCO Electric s capital tracker programs continue to satisfy the accounting test requirements of Criterion 1 as well as the materiality requirements of Criterion 3. Therefore, the Commission finds that ATCO Electric has complied with the directions set out at paragraphs 145 and 156 of Decision D Accordingly, the Commission finds that each and all of ATCO Electric s programs included in the 2016 true-up, as shown in Table 1 below, satisfy the requirements of the first and third criteria for capital tracker treatment. 5 Decision D , paragraphs Exhibit X0002, application, Appendix A, Schedule 8-1, lines 50 and 180; Schedule 8-3, lines 6, 25 and Exhibit X0001, application, paragraphs 7-8. Decision D (May 4, 2018) 3

8 actual K factor 20. Having made the above changes to respond to the Commission s directions from Decision D , ATCO Electric recalculated its actual K factor for Table 1 below compares ATCO Electric s applied-for forecast 2016 K factor amounts, the actual 2016 K factor amounts applied for in Proceeding and the updated K factor amounts calculated in the compliance filing for each capital tracker program. As shown in Table 1, the removal of the Fort McMurray North Service Building Project 2016 capital additions proposed to be included in the Buildings, Structures and Leasehold Improvements Program resulted in a total 2016 actual K factor that is $0.5 million lower than the K factor applied for in Proceeding Table 1 also shows that the reduction in the K factor for the Buildings, Structures and Leasehold Improvements Program is offset by an increase of $0.1 million in the 2016 actual K factors for two programs, which was driven by changes to the income tax component. 22. In response to the Commission IR requesting clarification of the calculation of the tax component of the revenue requirement that determines the K factor, ATCO Electric explained why a decrease in capital additions in one program could increase the K factor in other programs. The calculated income tax is equal to the return and depreciation, less tax deductions, multiplied by the tax rate. Consistent with the methodology used to allocate capital cost allowance (CCA) in its capital tracker proceedings, ATCO Electric direct assigns CCA where possible and then allocates the remaining amount. This allocation methodology results in less CCA being allocated to the capital tracker programs, because a decrease in capital additions for one or more capital tracker programs results in a decrease in CCA available for the allocation. Less CCA being allocated to these programs reduces the total tax deductions available and increases the tax component of the revenue requirement used in the accounting test, which, in turn, increases the total revenue requirement and thus the K factor. 8 Table K factor true-up Capital tracker program 2016 approved forecast K factor actual K factor Proceeding actual K factor compliance filing 11 Variance A B C D=C-B ($ million) 1 Distribution to Transmission Contributions Information Technology Related Tools and Instruments Transportation Equipment Third-Party Driven Relocations New Extensions Exhibit X0008, AE-AUC-2018APR Decision D : ATCO Electric Ltd., 2014 True-Up and Forecast PBR Capital Trackers Compliance Filing, Proceeding 21516, August 4, 2016, Table Decision D , Table Exhibit X0001, application, Table Decision D (May 4, 2018)

9 Capital tracker program 2016 approved forecast K factor actual K factor Proceeding actual K factor compliance filing 11 Variance A B C D=C-B ($ million) 7 Overhead Line Rebuilds, Replacement, and Life Extension Wood Pole Replacements, and Life Extension Reliability Wild Fires Mitigation Underground Rebuilds, Replacements and Life Extension 12 Buildings, Structures & Leasehold Improvements (0.7) Total (0.5) Note: Totals may not match summation of each individual program due to rounding. Commission findings 23. In Decision D , based on the project assessment under Criterion 1, the Commission approved the need, scope, level, timing and the prudence of actual capital additions for each project or program that ATCO Electric included in the 2016 true-up, except for the capital additions related to the Fort McMurray North Service Building Project in the Buildings, Structures and Leasehold Improvements Program. Because this adjustment would affect actual 2016 costs for certain projects or programs, the Commission indicated it could not make a determination in that decision as to whether all of ATCO Electric s programs included in the 2016 true-up satisfy the project assessment requirement of Criterion Further, the Commission found the general form of ATCO Electric s accounting test model to be reasonable and consistent with the methodology approved in Decision However, because ATCO Electric s accounting test for 2016 needed to be revised, the Commission could not make a determination in that decision as to whether all of ATCO Electric s programs included in the 2016 true-up satisfied the accounting test requirement of Criterion 1 and accordingly, whether all of ATCO Electric s programs satisfied Criterion 1 in their entirety. 14 Similarly, the Commission indicated that it could not determine in that decision whether all of ATCO Electric s programs included in the 2016 true-up satisfied the materiality test requirement of Criterion In previous sections of this decision, the Commission determined that ATCO Electric has complied with directions 1, 4, 5, 7 and 12, as set out in Decision D Based on the Commission s review of ATCO Electric s capital tracker projects or programs included in the 2016 true-up, and its acceptance of the compliance filing calculations, the Commission finds the revised actual capital additions in 2016 to be prudent for each capital tracker project or program included in the 2016 true-up. Further, the Commission is satisfied that the methodology used to 12 Decision D , paragraph Decision : Distribution Performance-Based Regulation, 2013 Capital Tracker Applications, Proceeding 2131, Application , December 6, Decision D , paragraphs 141 and Decision D , paragraph 155. Decision D (May 4, 2018) 5

10 calculate the tax component of the revenue requirement in the accounting test is consistent with the methodology used in prior capital tracker proceedings. 26. In light of the above, the Commission finds that each and all of ATCO Electric s projects or programs included in the 2016 true-up, as part of this compliance filing, satisfy the requirements of each of the criteria for capital tracker treatment on an actual basis. Therefore, the Commission approves capital tracker treatment for these projects or programs and finds the resulting K factor calculations for 2016, as provided in the compliance filing, to be reasonable. 27. Based on the foregoing, the Commission approves, on an actual basis, the 2016 K factor of $47.6 million, as calculated in the compliance filing. 5 Direction 11: Refund of the amount resulting from this compliance filing 28. At paragraph 184 of Decision D , the Commission gave the following direction: 184. The Commission directs ATCO Electric to propose a method to refund the difference between the approved 2016 K factor forecast amount of $51.0 million and the approved 2016 K factor final true-up amount that will be reviewed by the Commission in the compliance filing to this decision. 29. In Decision D , 16 the Commission approved, on an interim basis, ATCO Electric s 2016 PBR rates which included a 2016 K factor placeholder amount of $43.4 million. 17 In Decision D , the Commission approved a 2016 K factor forecast of $51.0 million. 18 In Decision D , 19 the Commission directed ATCO Electric to include the difference between the approved 2016 K factor forecast and the 2016 K factor placeholder amount, which is equal to $7.6 million, in its 2017 PBR rates. 20 In this decision, the Commission has approved a 2016 K factor of $47.6 million on an actual basis, which is $3.4 million less than the 2016 K factor amount of $51.0 million collected in 2016 and 2017 PBR rates. Therefore, the 2016 K factor true-up amount arising from this decision is negative $3.4 million. 30. ATCO Electric proposed to include the $3.4 million 2016 K factor adjustment in its 2019 annual PBR rate adjustment filing. 21 Commission findings 31. The Commission finds ATCO Electric s proposal to include the approved 2016 K factor true-up amount of $3.4 million arising from this decision in its 2019 annual PBR rate adjustment filing to be reasonable, with the refund period to be determined as part of that proceeding. 16 Decision D : ATCO Electric Ltd., 2016 Annual Performance-based Regulation Rate Adjustment Filing, Proceeding 20822, December 17, Decision D , paragraph Decision D , paragraph Decision D : ATCO Electric Ltd., 2017 Annual Performance-Based Regulation Rate Adjustment Filing, Proceeding 21978, December 23, Decision D , paragraph Exhibit X0001, application, paragraph Decision D (May 4, 2018)

11 Accordingly, the 2016 K factor final true-up amount of $3.4 million arising from this decision is approved and shall be included as part of a proceeding to establish ATCO Electric s 2019 PBR rates. 6 Order 32. It is hereby ordered that: (1) The 2016 actual K factor of $47.6 million is approved. (2) The 2016 K factor adjustment amount of $3.4 million arising from this decision is approved and shall be included as part of a proceeding to establish ATCO Electric Ltd. s 2019 performance-based regulation rates. Dated on May 4, Alberta Utilities Commission (original signed by) Neil Jamieson Commission Member Decision D (May 4, 2018) 7

12

13 Appendix 1 Proceeding participants Name of organization (abbreviation) Company name of counsel or representative ATCO Electric Ltd. (ATCO Electric) Consumers Coalition of Alberta Office of the Utilities Consumer Advocate (UCA) Alberta Utilities Commission Commission panel N. Jamieson, Commission Member Commission staff J. Graham (Commission counsel) A. Corsi Decision D (May 4, 2018) 9

14 Appendix 2 Commission directions from Decision D (return to text) Direction 1 The Commission has also reviewed ATCO Electric s capital tracker schedules, which include its non-capital tracker projects, and finds that ATCO Electric has generally complied with the Commission s directions in Appendix 3 of Decision 3558-D , with one exception. In Appendix 3, part 3a of Decision 3558-D , the Commission directed the distribution utilities to provide descriptions of all non-capital tracker projects and programs that adequately describe, for understanding project or program groupings, the nature and purpose of the proposed project or program. Given that ATCO Electric did not provide these descriptions in the application, the Commission directs ATCO Electric to provide project descriptions of all non-capital tracker projects and programs that adequately describe the nature and purpose of the proposed project or program in the compliance filing to this decision and in its 2017 true-up capital tracker application. 2 The Commission evaluated the ATCO Electric business cases, engineering studies, cost related information, and related evidence and argument against each of the project assessment minimum filing requirements. In this decision, the Commission comments only on those aspects of the minimum filing requirements that it considers were not sufficiently addressed by ATCO Electric s evidence or were otherwise raised as an issue in the proceeding. In the 2017 capital tracker true-up application, ATCO Electric is directed to continue to provide similar information with respect to each of the minimum filing requirements, including updated business cases, engineering studies and cost-related information, including actual costs by cost category and unit costs, in sufficient detail to allow an evaluation of the prudence of its incurred costs. 3 The Commission has reviewed ATCO Electric s project management policies and procedures and finds that ATCO Electric has complied with the direction set out at paragraph 52 of Decision D The Commission directs ATCO Electric to continue to provide this information in its 2017 capital tracker trueup application. 4 Accordingly, the Commission directs ATCO Electric to remove the 2016 capital additions related to the Fort McMurray North Service Building Project from the Buildings, Structures and Leasehold Improvements Program in its compliance filing to this decision. Reference paragraph from Decision D Reference to ATCO Electric s response in the application, Exhibit X Appendix B Not applicable related to the 2017 capital tracker application Not applicable related to the 2017 capital tracker application Appendix A, paragraphs 7 and Decision D (May 4, 2018)

15 Direction 5 For the same reason, the Commission cannot make a determination in this decision as to whether all of ATCO Electric s programs or projects included in the 2016 true-up satisfy the accounting test requirement of Criterion 1. The Commission directs ATCO Electric, in its compliance filing to this decision, to revise its accounting test for 2016, based on the directions set out in the previous sections of this decision, and reassess whether the capital tracker projects or programs included in the 2016 true-up satisfy the accounting test requirement of Criterion 1. 6 The Commission directs ATCO Electric, in its 2017 capital tracker true-up application, to address whether the driver for any of the previously approved forecast programs or projects has changed and, in the event that the driver of the project or program has changed since the forecast project or program was approved, to identify such projects and programs and to provide evidentiary support that each project or program continues to satisfy the requirements of Criterion 2, as previously directed at paragraph 502 of Decision 3218-D Given these findings, the Commission directs ATCO Electric, in its compliance filing to this decision, to reassess whether its programs or projects included in the 2016 true-up satisfy the two-tiered materiality test requirement of Criterion 3. For this reassessment, ATCO Electric will use the 2016 threshold amounts approved in this decision. 8 Because the Commission stated at paragraph 48 of Decision , that a company may apply for capital tracker treatment of capital expenditures after the capital additions are made, in Section 7 of this decision, the Commission approved projects proposed for capital tracker treatment on an actual basis, for which there were no Commission-approved forecasts. However, to aid the Commission and parties in evaluating such projects for prudence, in its 2017 capital tracker true-up application ATCO Electric is directed to include internal approved cost estimates for all projects or programs without an approved forecast that are proposed for capital tracker treatment on an actual basis The cost estimates should provide clear context identifying the project, relevant management signatures and dates. Reference paragraph from Decision D Reference to ATCO Electric s response in the application, Exhibit X0001 Appendix A, paragraph 5 Not applicable related to the 2017 capital tracker application Appendix A, paragraph 6 Not applicable related to the 2017 capital tracker application Decision D (May 4, 2018) 11

16 Direction 9 Regarding customer contributions, the Commission finds that the CCA has not sufficiently supported its concern. The Commission however agrees that this is a Terms and Conditions of Service issue, and specifically a maximum investment level issue, and considers that there is merit in having ATCO Electric provide a more detailed explanation. Accordingly, ATCO Electric is directed, in its next application dealing with its Terms and Conditions of Service or maximum investment levels, to explain how the length of investment term is determined, how much, if any, influence customers can have on it, and what safeguards are in place to protect customers from the concern the CCA has outlined. 10 In the 2017 true-up capital tracker application, ATCO Electric is directed to continue to provide similar information to that provided in its 2014, 2015 and 2016 true-up capital tracker applications, with respect to each of the minimum filing requirements, including updated business cases, engineering studies and cost-related information, with actual costs by cost category and unit costs, in sufficient detail to allow an evaluation of the prudence of its incurred costs. ATCO Electric is further directed to file its capital tracker business cases and updates, as filed in proceedings 3218, 20555, and this proceeding, for the programs and projects for which ATCO Electric is applying in its 2017 true-up capital tracker applications. 11 The Commission directs ATCO Electric to propose a method to refund the difference between the approved 2016 K factor forecast amount of $51.0 million and the approved 2016 K factor final trueup amount that will be reviewed by the Commission in the compliance filing to this decision. 12 ATCO Electric Ltd. is directed to file a compliance filing application in accordance with the directions contained within this decision on or before March 28, Reference paragraph from Decision D Reference to ATCO Electric s response in the application, Exhibit X0001 Not applicable related to a future application Not applicable related to the 2017 capital tracker application 184 Paragraph (1) Paragraph 2 12 Decision D (May 4, 2018)

Decision D FortisAlberta Inc PBR Capital Tracker True-Up and PBR Capital Tracker Forecast

Decision D FortisAlberta Inc PBR Capital Tracker True-Up and PBR Capital Tracker Forecast Decision 20497-D01-2016 FortisAlberta Inc. 2014 PBR Capital Tracker True-Up and 2016-2017 PBR Capital Tracker Forecast February 20, 2016 Alberta Utilities Commission Decision 20497-D01-2016 FortisAlberta

More information

Decision D FortisAlberta Inc Performance-Based Regulation Capital Tracker True-Up. January 11, 2018

Decision D FortisAlberta Inc Performance-Based Regulation Capital Tracker True-Up. January 11, 2018 Decision 22741-D01-2018 FortisAlberta Inc. 2016 Performance-Based Regulation Capital Tracker True-Up January 11, 2018 Alberta Utilities Commission Decision 22741-D01-2018 FortisAlberta Inc. 2016 Performance-Based

More information

AltaGas Utilities Inc.

AltaGas Utilities Inc. Decision 23898-D01-2018 2019 Annual Performance-Based Regulation Rate Adjustment Filing December 20, 2018 Alberta Utilities Commission Decision 23898-D01-2018 2019 Annual Performance-Based Regulation Rate

More information

Decision D Alberta PowerLine L.P. Tariff Application. January 23, 2018

Decision D Alberta PowerLine L.P. Tariff Application. January 23, 2018 Decision 23161-D01-2018 Alberta PowerLine L.P. Tariff Application January 23, 2018 Alberta Utilities Commission Decision 23161-D01-2018 Alberta PowerLine L.P. Tariff Application Proceeding 23161 January

More information

AltaGas Utilities Inc.

AltaGas Utilities Inc. Decision 23623-D01-2018 AltaGas Utilities Inc. 2017 Capital Tracker True-Up Application December 18, 2018 Alberta Utilities Commission Decision 23623-D01-2018 AltaGas Utilities Inc. 2017 Capital Tracker

More information

Decision D Rebasing for the PBR Plans for Alberta Electric and Gas Distribution Utilities. First Compliance Proceeding

Decision D Rebasing for the PBR Plans for Alberta Electric and Gas Distribution Utilities. First Compliance Proceeding Decision 22394-D01-2018 Rebasing for the 2018-2022 PBR Plans for February 5, 2018 Alberta Utilities Commission Decision 22394-D01-2018 Rebasing for the 2018-2022 PBR Plans for Proceeding 22394 February

More information

EPCOR Distribution & Transmission Inc.

EPCOR Distribution & Transmission Inc. Decision 22603-D01-2017 June 23, 2017 Alberta Utilities Commission Decision 22603-D01-2017 Proceeding 22603 June 23, 2017 Published by the: Alberta Utilities Commission Fifth Avenue Place, Fourth Floor,

More information

Decision D ATCO Electric Ltd. Amounts to be Paid Into and Out of Balancing Pool for Chinchaga Power Plant Sale

Decision D ATCO Electric Ltd. Amounts to be Paid Into and Out of Balancing Pool for Chinchaga Power Plant Sale Decision 21833-D01-2016 Amounts to be Paid Into and Out of Balancing Pool for Chinchaga Power Plant Sale December 20, 2016 Alberta Utilities Commission Decision 21833-D01-2016 Proceeding 21833 December

More information

Decision ATCO Electric Ltd. February 1, 2013 Interim Tariff. January 18, 2013

Decision ATCO Electric Ltd. February 1, 2013 Interim Tariff. January 18, 2013 Decision 2013-015 February 1, 2013 Interim Tariff January 18, 2013 The Alberta Utilities Commission Decision 2013-015: February 1, 2013 Interim Tariff Application No. 1609127 Proceeding ID No. 2305 January

More information

ATCO Electric Ltd. Stage 2 Review of Decision D ATCO Electric Ltd Transmission General Tariff Application

ATCO Electric Ltd. Stage 2 Review of Decision D ATCO Electric Ltd Transmission General Tariff Application Decision 22483-D01-2017 Stage 2 Review of Decision 20272-D01-2016 2015-2017 Transmission General Tariff Application December 6, 2017 Alberta Utilities Commission Decision 22483-D01-2017 Stage 2 Review

More information

AltaGas Utilities Inc.

AltaGas Utilities Inc. Decision 23740-D01-2018 AltaGas Utilities Inc. 2018-2019 Unaccounted-For Gas Rider E and Rider H October 25, 2018 Alberta Utilities Commission Decision 23740-D01-2018 AltaGas Utilities Inc. 2018-2019 Unaccounted-For

More information

AltaGas Utilities Inc.

AltaGas Utilities Inc. Decision 2013-465 2014 Annual PBR Rate Adjustment Filing December 23, 2013 The Alberta Utilities Commission Decision 2013-465: 2014 Annual PBR Rate Adjustment Filing Application No. 1609923 Proceeding

More information

Decision D FortisAlberta Inc. Light-Emitting Diode Lighting Conversion Maintenance Multiplier for the City of St.

Decision D FortisAlberta Inc. Light-Emitting Diode Lighting Conversion Maintenance Multiplier for the City of St. Decision 21754-D01-2016 Light-Emitting Diode Lighting Conversion Maintenance Multiplier for the City of St. Albert August 11, 2016 Alberta Utilities Commission Decision 21754-D01-2016 Light-Emitting Diode

More information

ATCO Gas and Pipelines Ltd.

ATCO Gas and Pipelines Ltd. Decision 2738-D01-2016 Z Factor Application for Recovery of 2013 Southern Alberta Flood Costs March 16, 2016 Alberta Utilities Commission Decision 2738-D01-2016 Z Factor Application for Recovery of 2013

More information

Decision ATCO Utilities. Corporate Cost Allocation Methodology. September 20, 2010

Decision ATCO Utilities. Corporate Cost Allocation Methodology. September 20, 2010 Decision 2010-447 Corporate Cost Allocation Methodology September 20, 2010 ALBERTA UTILITIES COMMISSION Decision 2010-447: Corporate Cost Allocation Methodology Application No. 1605473 Proceeding ID. 306

More information

ENMAX Power Corporation

ENMAX Power Corporation Decision 22756-D01-2017 Tax Agreement with The City of Calgary September 7, 2017 Alberta Utilities Commission Decision 22756-D01-2017 Tax Agreement with The City of Calgary Proceeding 22756 September 7,

More information

ENMAX Power Corporation

ENMAX Power Corporation Decision 22238-D01-2017 ENMAX Power Corporation 2016-2017 Transmission General Tariff Application December 4, 2017 Alberta Utilities Commission Decision 22238-D01-2017 ENMAX Power Corporation 2016-2017

More information

EPCOR Energy Alberta GP Inc.

EPCOR Energy Alberta GP Inc. Decision 20633-D01-2016 EPCOR Energy Alberta GP Inc. 2016-2017 Regulated Rate Tariff Application December 20, 2016 Alberta Utilities Commission Decision 20633-D01-2016 EPCOR Energy Alberta GP Inc. 2016-2017

More information

Langdon Waterworks Limited

Langdon Waterworks Limited Decision 20372-D01-2015 May 14, 2015 Alberta Utilities Commission Decision 20372-D01-2015 Proceeding 20372 May 14, 2015 Published by the: Alberta Utilities Commission Fifth Avenue Place, Fourth Floor,

More information

Canadian Natural Resources Limited

Canadian Natural Resources Limited Decision 22669-D03-2017 Application for an Order Permitting the Sharing of Records Not Available to the Public Between Canadian Natural Resources Limited and ATCO Power Canada Ltd. July 21, 2017 Alberta

More information

EPCOR Distribution & Transmission Inc.

EPCOR Distribution & Transmission Inc. Decision 21229-D01-2016 EPCOR Distribution & Transmission Inc. 2015-2017 Transmission Facility Owner Tariff and 2013 Generic Cost of Capital Compliance Application April 15, 2016 Alberta Utilities Commission

More information

FortisAlberta Inc. Sale and Transfer of the Municipality of Crowsnest Pass Electric Distribution Assets

FortisAlberta Inc. Sale and Transfer of the Municipality of Crowsnest Pass Electric Distribution Assets Decision 21785-D01-2018 Sale and Transfer of the Electric Distribution Assets June 5, 2018 Alberta Utilities Commission Decision 21785-D01-2018 Sale and Transfer of the Electric Distribution System Assets

More information

Decision D FortisAlberta Inc. Light-Emitting Diode (LED) Lighting Conversion Maintenance Multiplier Filing for 30 Customers in 2018

Decision D FortisAlberta Inc. Light-Emitting Diode (LED) Lighting Conversion Maintenance Multiplier Filing for 30 Customers in 2018 Decision 23730-D01-2018 Light-Emitting Diode (LED) Lighting Conversion Maintenance Multiplier Filing for 30 Customers in 2018 September 7, 2018 Alberta Utilities Commission Decision 23730-D01-2018 Light-Emitting

More information

Alberta Electric System Operator

Alberta Electric System Operator Decision 23065-D01-2017 Alberta Electric System Operator 2018 Independent System Operator Tariff Update November 28, 2017 Alberta Utilities Commission Decision 23065-D01-2017 Alberta Electric System Operator

More information

Decision The ATCO Utilities. Corporate Costs. March 21, 2013

Decision The ATCO Utilities. Corporate Costs. March 21, 2013 Decision 2013-111 Corporate Costs March 21, 2013 The Alberta Utilities Commission Decision 2013-111: Corporate Costs Application No. 1608510 Proceeding ID No. 1920 March 21, 2013 Published by The Alberta

More information

AltaLink Investment Management Ltd. And SNC Lavalin Transmission Ltd. et al.

AltaLink Investment Management Ltd. And SNC Lavalin Transmission Ltd. et al. Decision 3529-D01-2015 AltaLink Investment Management Ltd. And SNC Lavalin Transmission Ltd. et al. Proposed Sale of AltaLink, L.P Transmission Assets and Business to Mid-American (Alberta) Canada Costs

More information

Decision D Performance-Based Regulation Plans for Alberta Electric and Gas Distribution Utilities.

Decision D Performance-Based Regulation Plans for Alberta Electric and Gas Distribution Utilities. Decision 22082-D01-2017 2018-2022 Performance-Based Regulation Plans for Alberta Electric and Gas Distribution Utilities February 6, 2017 Alberta Utilities Commission Decision 22082-D01-2017 2018-2022

More information

ATCO Gas and Pipelines Ltd. (South)

ATCO Gas and Pipelines Ltd. (South) Decision 3421-D01-2015 Northeast Calgary Connector Pipeline January 16, 2015 The Alberta Utilities Commission Decision 3421-D01-2015: Northeast Calgary Connector Pipeline Application 1610854 Proceeding

More information

ENMAX Power Corporation Distribution and Transmission Deferral Account Reconciliation

ENMAX Power Corporation Distribution and Transmission Deferral Account Reconciliation Decision 23108-D01-2018 2014 Distribution and 2014-2015 Transmission Deferral Account Reconciliation February 27, 2018 Alberta Utilities Commission Decision 23108-D01-2018 2014 Distribution and 2014-2015

More information

Alberta Utilities Commission

Alberta Utilities Commission Decision 22091-D01-2017 Commission-Initiated Proceeding to Review the Terms and November 9, 2017 Decision 22091-D01-2017 Commission-Initiated Proceeding to Review the Terms and Proceeding 22091 Application

More information

Decision FortisAlberta Inc Phase II Distribution Tariff. January 27, 2014

Decision FortisAlberta Inc Phase II Distribution Tariff. January 27, 2014 Decision 2014-018 FortisAlberta Inc. 2012-2014 Phase II Distribution Tariff January 27, 2014 The Alberta Utilities Commission Decision 2014-018: FortisAlberta Inc. 2012-2014 Phase II Distribution Tariff

More information

EPCOR Distribution & Transmission Inc.

EPCOR Distribution & Transmission Inc. Decision 3539-D01-2015 EPCOR Distribution & Transmission Inc. 2015-2017 Transmission Facility Owner Tariff October 21, 2015 Alberta Utilities Commission Decision 3539-D01-2015: EPCOR Distribution & Transmission

More information

Shell Canada Limited and Canadian Natural Resources Limited

Shell Canada Limited and Canadian Natural Resources Limited Decision 22614-D01-2017 Albian Oil Sands Industrial Complex and June 28, 2017 Alberta Utilities Commission Decision 22614-D01-2017 Albian Oil Sands Industrial Complex and Proceeding 22614 Applications

More information

ENMAX Energy Corporation

ENMAX Energy Corporation Decision 23006-D01-2018 Regulated Rate Option - Energy Price Setting Plan Monthly Filings for Acknowledgment 2017 Quarter 3 February 7, 2018 Alberta Utilities Commission Decision 23006-D01-2018: Regulated

More information

Kneehill Rural Electrification Association Ltd.

Kneehill Rural Electrification Association Ltd. Decision 23420-D01-2018 Kneehill Rural Electrification Association Ltd. Varied Code of Conduct Regulation Compliance Plan April 23, 2018 Alberta Utilities Commission Decision 23420-D01-2018 Kneehill Rural

More information

Consumers Coalition of Alberta

Consumers Coalition of Alberta Decision 22157-D01-2017 Decision on Preliminary Question AltaLink Management Ltd. 2012-2013 Deferral Account Reconciliation Costs Award February 15, 2017 Alberta Utilities Commission Decision 22157-D01-2017

More information

AltaGas Utilities Inc.

AltaGas Utilities Inc. Decision 21822-D01-2016 AltaGas Utilities Inc. 2016-2017 Unaccounted-For Gas Rider E and Rider H September 1, 2016 Alberta Utilities Commission Decision 21822-D01-2016 AltaGas Utilities Inc. 2016-2017

More information

TransCanada Energy Ltd.

TransCanada Energy Ltd. Decision 22302-D01-2017 Request for Permitting the Sharing of Records Not Available to the Public Between and Pembina Pipeline Corporation May 26, 2017 Alberta Utilities Commission Decision 22302-D01-2017

More information

Decision D Generic Cost of Capital. Costs Award

Decision D Generic Cost of Capital. Costs Award Decision 21856-D01-2016 Costs Award December 2, 2016 Alberta Utilities Commission Decision 21856-D01-2016 Costs Award Proceeding 21856 December 2, 2016 Published by Alberta Utilities Commission Fifth Avenue

More information

Decision ATCO Electric Ltd. Bonnyville to Bourque Transmission Line Project. Costs Award. October 9, 2013

Decision ATCO Electric Ltd. Bonnyville to Bourque Transmission Line Project. Costs Award. October 9, 2013 Decision 2013-374 Bonnyville to Bourque Transmission Line Project Costs Award October 9, 2013 The Alberta Utilities Commission Decision 2013-374: Bonnyville to Bourque Transmission Line Project Costs Award

More information

Decision ATCO Gas General Rate Application Phase I Compliance Filing to Decision Part B.

Decision ATCO Gas General Rate Application Phase I Compliance Filing to Decision Part B. Decision 2006-083 2005-2007 General Rate Application Phase I Compliance Filing to Decision 2006-004 August 11, 2006 ALBERTA ENERGY AND UTILITIES BOARD Decision 2006-083: 2005-2007 General Rate Application

More information

The University of Calgary

The University of Calgary Decision 23147-D01-2018 Application for an Order Permitting the Sharing of Records Not Available to the Public Between the University of Calgary and URICA Energy Real Time Ltd. January 30, 2018 Alberta

More information

ATCO Electric and ATCO Pipelines. Application for ATCO Electric and ATCO Pipelines License Fees

ATCO Electric and ATCO Pipelines. Application for ATCO Electric and ATCO Pipelines License Fees Decision 21571-D01-2016 and ATCO Pipelines 2015-2016 License Fees August 17, 2016 Alberta Utilities Commission Decision 21571-D01-2016 and ATCO Pipelines 2015-2016 License Fees Proceeding 21571 August

More information

ATCO Pipelines ATCO Gas and Pipelines Ltd. CU Inc. Canadian Utilities Limited

ATCO Pipelines ATCO Gas and Pipelines Ltd. CU Inc. Canadian Utilities Limited Decision 2012-068 Disposition of Surplus Salt Cavern Assets in the Fort Saskatchewan Area March 16, 2012 The Alberta Utilities Commission Decision 2012-068:,,, Disposition of Surplus Salt Cavern Assets

More information

Decision CU Water Limited. Disposition of Assets. April 30, 2010

Decision CU Water Limited. Disposition of Assets. April 30, 2010 Decision 2010-192 Disposition of Assets April 30, 2010 ALBERTA UTILITIES COMMISSION Decision 2010-192: Disposition of Assets Application No. 1606042 Proceeding ID. 569 April 30, 2010 Published by Alberta

More information

Canadian Natural Resources Limited

Canadian Natural Resources Limited Decision 21306-D01-2016 Determination of Compensation for 9L66/9L32 Transmission Line Relocation August 16, 2016 Alberta Utilities Commission Decision 21306-D01-2016 Determination of Compensation for 9L66/9L32

More information

ENMAX Energy Corporation

ENMAX Energy Corporation Decision 22054-D01-2017 Regulated Rate Option Tariff Terms and Conditions Amendment Application April 12, 2017 Alberta Utilities Commission Decision 22054-D01-2017 Regulated Rate Option Tariff Terms and

More information

AltaLink Management Ltd.

AltaLink Management Ltd. Decision 21054-D01-2016 2013-2014 General Tariff Application (Proceeding 2044-Reopened for Midgard Audit) March 7, 2016 Alberta Utilities Commission Decision 21054-D01-2016: Proceeding 21054 March 7,

More information

Langdon Waterworks Limited

Langdon Waterworks Limited Decision 2014-240 August 19, 2014 The Alberta Utilities Commission Decision 2014-240: Application No. 1610617 Proceeding No. 3258 August 19, 2014 Published by The Alberta Utilities Commission Fifth Avenue

More information

Decision D FortisAlberta Inc.

Decision D FortisAlberta Inc. Decision 23063-D01-2018 Light-Emitting Diode Lighting Conversion Maintenance Multiplier Filing January 30, 2018 Alberta Utilities Commission Decision 23063-D01-2018 Light-Emitting Diode Lighting Conversion

More information

AltaLink Management Ltd.

AltaLink Management Ltd. Decision 3524-D01-2016 AltaLink Management Ltd. 2015-2016 General Tariff Application May 9, 2016 Alberta Utilities Commission Decision 3524-D01-2016 AltaLink Management Ltd. 2015-2016 General Tariff Application

More information

West Wetaskiwin Rural Electrification Association Ltd.

West Wetaskiwin Rural Electrification Association Ltd. Decision 22067-D01-2016 West Wetaskiwin Rural Electrification Association Ltd. Varied Code of Conduct Regulation Compliance Plan December 21, 2016 Alberta Utilities Commission Decision 22067-D01-2016 West

More information

Mackenzie Rural Electrification Association Ltd.

Mackenzie Rural Electrification Association Ltd. Decision 21983-D01-2016 Varied Code of Conduct Regulation Compliance Plan December 14, 2016 Alberta Utilities Commission Decision 21983-D01-2016 Varied Code of Conduct Regulation Compliance Plan Proceeding

More information

Daishowa-Marubeni International Ltd.

Daishowa-Marubeni International Ltd. Decision 2011-299 25-MW Condensing Steam Turbine Generator July 8, 2011 The Alberta Utilities Commission Decision 2011-299: 25-MW Condensing Steam Turbine Generator Application No. 1606747 Proceeding ID

More information

Decision D ATCO Electric Ltd. Micro-generation Determination. September 19, 2018

Decision D ATCO Electric Ltd. Micro-generation Determination. September 19, 2018 Decision 23412-D01-2018 Micro-generation Determination September 19, 2018 Alberta Utilities Commission Decision 23412-D01-2018 Micro-generation Determination Proceeding 23412 Application 23412-A001 September

More information

AltaLink Management Ltd.

AltaLink Management Ltd. Decision 22612-D01-2018 November 13, 2018 Alberta Utilities Commission Decision 22612-D01-2018 to PiikaniLink L.P. and KainaiLink L.P. and the Proceeding 22612 Applications 22612-A001, 22612-A002, 22612-A003,

More information

AltaLink Investment Management Ltd. and SNC Lavalin Transmission Ltd. et al.

AltaLink Investment Management Ltd. and SNC Lavalin Transmission Ltd. et al. Decision 2014-326 AltaLink Investment Management Ltd. and SNC Lavalin Transmission Ltd. et al. Proposed Sale of AltaLink, L.P. Transmission Assets and Business to MidAmerican (Alberta) Canada Holdings

More information

Collaborative Process

Collaborative Process Alberta Energy and Utilities Board Utility Cost Order 2006-065 Uniform System of Accounts and Minimum Filing Requirements Cost Awards ALBERTA ENERGY AND UTILITIES BOARD Utility Cost Order 2006-065 Uniform

More information

ATCO Gas and Pipelines Ltd. (South)

ATCO Gas and Pipelines Ltd. (South) Decision 22634-D01-2017 Southwest Calgary Connector Pipeline Project August 9, 2017 Alberta Utilities Commission Decision 22634-D01-2017 Southwest Calgary Connector Pipeline Project Proceeding 22634 Application

More information

The University of Calgary

The University of Calgary Decision 2014-365 Preferential Sharing of Records between the University of Calgary and URICA Energy Real Time Ltd. December 19, 2014 The Alberta Utilities Commission Decision 2014-365: Preferential Sharing

More information

AltaLink Management Ltd.

AltaLink Management Ltd. Decision 22025-D03-2017 Red Deer Area Transmission Development Amendment Application June 8, 2017 Decision 22025-D03-2017 Red Deer Area Transmission Development Amendment Application Proceeding 22025 Applications

More information

Mayerthorpe and District Rural Electrification Association Ltd.

Mayerthorpe and District Rural Electrification Association Ltd. Decision 22692-D01-2018 Mayerthorpe and District Rural Electrification Association Ltd. Varied Code of Conduct Regulation Compliance Plan January 31, 2018 Alberta Utilities Commission Decision 22692-D01-2018

More information

CANADIAN UTILITIES LIMITED 2013 MANAGEMENT S DISCUSSION AND ANALYSIS

CANADIAN UTILITIES LIMITED 2013 MANAGEMENT S DISCUSSION AND ANALYSIS CANADIAN UTILITIES LIMITED MANAGEMENT S DISCUSSION AND ANALYSIS FOR THE YEAR ENDED DECEMBER 31, 2013 This Management's Discussion and Analysis (MD&A) is meant to help readers understand key financial events

More information

Alberta Electric System Operator, AltaLink Management Ltd. and ENMAX Power Corporation. Foothills Area Transmission Development

Alberta Electric System Operator, AltaLink Management Ltd. and ENMAX Power Corporation. Foothills Area Transmission Development Decision 2013-087 Alberta Electric System Operator, AltaLink Management Ltd. and ENMAX Power Corporation Foothills Area Transmission Development March 12, 2013 The Alberta Utilities Commission Decision

More information

Alberta Electric System Operator 2017 ISO Tariff Update

Alberta Electric System Operator 2017 ISO Tariff Update Alberta Electric System Operator 2017 ISO Tariff Update Date: October 20, 2016 Prepared by: Alberta Electric System Operator Prepared for: Alberta Utilities Commission Classification: Public Table of Contents

More information

Financial Statements For the years ended December 31, 2015 and 2014

Financial Statements For the years ended December 31, 2015 and 2014 FORTISALBERTA INC. Financial Statements MANAGEMENT S REPORT The accompanying annual financial statements of FortisAlberta Inc. (the Corporation ) have been prepared by management, who are responsible for

More information

Decision D Balancing Pool

Decision D Balancing Pool Decision 22184-D10-2017 Application for an Order Permitting the Sharing of Records Not Available to the Public Between the, TransAlta Generation Partnership, and Capital Power Generation Services Inc.

More information

ENMAX Energy Corporation

ENMAX Energy Corporation Decision 22510-D01-2017 2016-2018 Energy Price Setting Plan Compliance Filing October 30, 2017 Alberta Utilities Commission Decision 22510-D01-2017 2016-2018 Energy Price Setting Plan Compliance Filing

More information

Capital Power Corporation. Halkirk 2 Wind Power Project

Capital Power Corporation. Halkirk 2 Wind Power Project Decision 23255-D01-2018 Capital Power Corporation Halkirk 2 Wind Power Project July 9, 2018 Alberta Utilities Commission Decision 23255-D01-2018 Capital Power Corporation Halkirk 2 Wind Power Project Proceeding

More information

Audited Financial Statements For the years ended December 31, 2017 and 2016

Audited Financial Statements For the years ended December 31, 2017 and 2016 FORTISALBERTA INC. Audited Financial Statements MANAGEMENT S REPORT The accompanying 2017 Financial Statements of FortisAlberta Inc. (the Corporation ) have been prepared by management, who are responsible

More information

Decision D ATCO Electric Ltd. Hughes 2030S Substation. Costs Award

Decision D ATCO Electric Ltd. Hughes 2030S Substation. Costs Award Decision 22406-D01-2017 Hughes 2030S Substation June 9, 2017 Alberta Utilities Commission Decision 22406-D01-2017 Hughes 2030S Substation Proceeding 22406 June 9, 2017 Published by Alberta Utilities Commission

More information

E.ON Climate & Renewables Canada Ltd. Grizzly Bear Creek Wind Power Project

E.ON Climate & Renewables Canada Ltd. Grizzly Bear Creek Wind Power Project Decision 21513-D01-2016 Grizzly Bear Creek Wind Power Project July 21, 2016 Alberta Utilities Commission Decision 21513-D01-2016 Grizzly Bear Creek Wind Power Project Proceeding 21513 July 21, 2016 Published

More information

Audited Financial Statements For the years ended December 31, 2018 and 2017

Audited Financial Statements For the years ended December 31, 2018 and 2017 FORTISALBERTA INC. Audited Financial Statements Deloitte LLP 700, 850 2 Street SW Calgary, AB T2P 0R8 Canada Independent Auditor s Report Tel: 403-267-1700 Fax: 587-774-5379 www.deloitte.ca To the Shareholder

More information

AltaLink Management Ltd. ATCO Electric Ltd.

AltaLink Management Ltd. ATCO Electric Ltd. Decision 2012-139 May 22, 2012 The Alberta Utilities Commission Decision 2012-139: and Application Nos. 1607971 and 1608183 Proceeding ID No. 1623 May 22, 2012 Published by The Alberta Utilities Commission

More information

Decision D ATCO Electric Ltd Transmission General Tariff Application. Costs Award

Decision D ATCO Electric Ltd Transmission General Tariff Application. Costs Award Decision 21747-D01-2017 January 30, 2017 Alberta Utilities Commission Decision 21747-D01-2017 Proceeding 21747 January 30, 2017 Published by Alberta Utilities Commission Fifth Avenue Place, Fourth Floor,

More information

AltaLink Management Ltd.

AltaLink Management Ltd. Decision 20986-D01-2016 Southwest Calgary Ring Road Transmission Project August 31, 2016 Alberta Utilities Commission Decision 20986-D01-2016 Southwest Calgary Ring Road Transmission Project Proceeding

More information

Decision Town of Innisfail. Franchise Agreement with ATCO Gas and Pipelines Ltd. and Amendment to Rider A.

Decision Town of Innisfail. Franchise Agreement with ATCO Gas and Pipelines Ltd. and Amendment to Rider A. Decision 2012-300 Franchise Agreement with ATCO Gas and Pipelines Ltd. and Amendment to Rider A November 9, 2012 The Alberta Utilities Commission Decision 2012-300: Franchise Agreement with ATCO Gas and

More information

ATCO Gas and Pipelines Ltd. (South)

ATCO Gas and Pipelines Ltd. (South) Decision 2010-170 New Construction Replacement of ATCO Pipelines Existing Southern Extension Pipeline From North of Lacombe to East of Gwynne April 15, 2010 ALBERTA UTILITIES COMMISSION Decision 2010-170:

More information

2013 Generic Cost of Capital

2013 Generic Cost of Capital Decision 2191-D01-2015 2013 Generic Cost of Capital March 23, 2015 Alberta Utilities Commission Decision 2191-D01-2015 2013 Generic Cost of Capital Proceeding 2191 Application 1608918-1 March 23, 2015

More information

Acciona Wind Energy Canada, Inc.

Acciona Wind Energy Canada, Inc. Decision 2013-439 Acciona Wind Energy Canada, Inc. New Dayton Wind Power Project Facility & Substation Costs Award December 11, 2013 The Alberta Utilities Commission Decision 2013-439: Acciona Wind Energy

More information

Decision D EQUS REA LTD.

Decision D EQUS REA LTD. Decision 22293-D01-2017 Application for Orders Amending the Terms and Conditions of Service and Rate Schedules of FortisAlberta Inc. in Respect of Option M Distribution Generation Credit/Charge October

More information

FORTISALBERTA INC. Unaudited Interim Financial Statements For the three and six months ended June 30, 2013

FORTISALBERTA INC. Unaudited Interim Financial Statements For the three and six months ended June 30, 2013 FORTISALBERTA INC. Unaudited Interim Financial Statements For the three and six months ended 2013 BALANCE SHEETS (UNAUDITED) As at (all amounts in thousands of Canadian dollars) 2013 December 31, 2012

More information

Livingstone Landowners Guild

Livingstone Landowners Guild Decision 20846-D01-2016 Livingstone Landowners Guild Application for Review of Decision 2009-126 Needs Identification Document Application Southern Alberta Transmission System Reinforcement as amended

More information

TAX NEWSLETTER. April 2016

TAX NEWSLETTER. April 2016 TAX NEWSLETTER April 2016 PROPOSED AMENDMENTS TO DONATION RULES FOR ESTATES THE DIVIDEND TAX CREDIT TAXATION AND PARTNERSHIPS LOW-INTEREST EMPLOYEE LOANS REPLACEMENT PROPERTY RULES AROUND THE COURTS However,

More information

AltaLink Management Ltd. & EPCOR Distribution & Transmission Inc.

AltaLink Management Ltd. & EPCOR Distribution & Transmission Inc. Decision 2013-280 AltaLink Management Ltd. & EPCOR Distribution & Transmission Inc. Heartland Transmission Project Amendment Structure T176 Repositioning Costs Award July 29, 2013 The Alberta Utilities

More information

ORDER NUMBER G IN THE MATTER OF the Utilities Commission Act, RSBC 1996, Chapter 473. and

ORDER NUMBER G IN THE MATTER OF the Utilities Commission Act, RSBC 1996, Chapter 473. and Suite 410, 900 Howe Street Vancouver, BC Canada V6Z 2N3 bcuc.com P: 604.660.4700 TF: 1.800.663.1385 F: 604.660.1102 ORDER NUMBER G-48-19 IN THE MATTER OF the Utilities Commission Act, RSBC 1996, Chapter

More information

Canadian Natural Resources Limited

Canadian Natural Resources Limited Alberta Energy and Utilities Board Energy Cost Order 2004-07 Canadian Natural Resources Limited Application for an Oil Sands Mine, Bitumen Extraction Plant, and Bitumen Upgrading Plant in the Fort McMurray

More information

Parties are invited to make submissions on IR responses and the additional topics to be issued by the Panel. ACTION DATE (2014)

Parties are invited to make submissions on IR responses and the additional topics to be issued by the Panel. ACTION DATE (2014) ERICA HAMILTON COMMISSION SECRETARY Commission.Secretary@bcuc.com web site: http://www.bcuc.com SIXTH FLOOR, 900 HOWE STREET, BOX 250 VANCOUVER, BC CANADA V6Z 2N3 TELEPHONE: (604) 660-4700 BC TOLL FREE:

More information

EPCOR Energy Services (Alberta) Ltd.

EPCOR Energy Services (Alberta) Ltd. Alberta Energy and Utilities Board Decision 2002-112 EPCOR Energy Services (Alberta) Ltd. 2003 Regulated Rate Option Settlement Agreement December 20, 2002 ALBERTA ENERGY AND UTILITIES BOARD Decision 2002-112:

More information

ENMAX Corporation 2017 Q2 INTERIM REPORT CAUTION TO READER

ENMAX Corporation 2017 Q2 INTERIM REPORT CAUTION TO READER ENMAX Corporation 2017 Q2 INTERIM REPORT ENMAX Corporation CAUTION TO READER This document contains statements about future events and financial and operating results of ENMAX Corporation and its subsidiaries

More information

Q INTERIM REPORT

Q INTERIM REPORT ENMAX CORPORATION Q1 2018 INTERIM REPORT CAUTION TO READER This document contains statements about future events and financial and operating results of ENMAX Corporation and its subsidiaries (ENMAX or

More information

Decision TykeWest Limited. Setting of Fees for a Common Carrier Order. July 15, 2009

Decision TykeWest Limited. Setting of Fees for a Common Carrier Order. July 15, 2009 Decision 2009-106 Setting of Fees for a Common Carrier Order July 15, 2009 ALBERTA UTILITIES COMMISSION Decision 2009-106: Setting of Fees for a Common Carrier Order Application No. 1567541 July 15, 2009

More information

2014 ABAER 007. Inter Pipeline Ltd. Application for a Pipeline Licence Edmonton/Fort Saskatchewan Area. June 23, 2014

2014 ABAER 007. Inter Pipeline Ltd. Application for a Pipeline Licence Edmonton/Fort Saskatchewan Area. June 23, 2014 2014 ABAER 007 Inter Pipeline Ltd. Application for a Pipeline Licence Edmonton/Fort Saskatchewan Area June 23, 2014 ALBERTA ENERGY REGULATOR Decision 2014 ABAER 007: Inter Pipeline Ltd., Application for

More information

Toronto Hydro-Electric System Limited ( Toronto Hydro ) Incremental Capital Module ( ICM ) True-up Application OEB File No.

Toronto Hydro-Electric System Limited ( Toronto Hydro ) Incremental Capital Module ( ICM ) True-up Application OEB File No. Andrew J. Sasso Director, Regulatory Affairs Telephone:.. Toronto Hydro-Electric System Limited Facsimile:..0 Carlton Street regulatoryaffairs@torontohydro.com Toronto, ON MB K www.torontohydro.com March,

More information

Unaudited Condensed Interim Financial Statements For the three and nine months ended September 30, 2018

Unaudited Condensed Interim Financial Statements For the three and nine months ended September 30, 2018 FORTISALBERTA INC. Unaudited Condensed Interim Financial Statements For the three and nine months ended 2018 FORTISALBERTA INC. CONDENSED INTERIM BALANCE SHEETS (UNAUDITED) As at (all amounts in thousands

More information

Horse Creek Water Services Inc.

Horse Creek Water Services Inc. Decision 21340-D01-2017 Horse Creek Water Services Inc. 2016 General Rate Application October 20, 2017 Alberta Utilities Commission Decision 21340-D01-2017 Horse Creek Water Services Inc. 2016 General

More information

FORTISALBERTA INC. MANAGEMENT S DISCUSSION AND ANALYSIS

FORTISALBERTA INC. MANAGEMENT S DISCUSSION AND ANALYSIS FORTISALBERTA INC. MANAGEMENT S DISCUSSION AND ANALYSIS November 5, 2014 The following ( MD&A ) of FortisAlberta Inc. (the Corporation ) should be read in conjunction with the following: (i) the unaudited

More information

NaturEner Energy Canada Inc.

NaturEner Energy Canada Inc. Decision 2009-174 Review and Variance of Alberta Utilities Commission Decision 2009-042 (October 22, 2009) ALBERTA UTILITIES COMMISSION Decision 2009-174, Review and Variance of Alberta Utilities Commission

More information

Q INTERIM REPORT

Q INTERIM REPORT ENMAX CORPORATION Q2 2018 INTERIM REPORT CAUTION TO READER This document contains statements about future events and financial and operating results of ENMAX Corporation and its subsidiaries (ENMAX or

More information