Alberta Electric System Operator, AltaLink Management Ltd. and ENMAX Power Corporation. Foothills Area Transmission Development

Size: px
Start display at page:

Download "Alberta Electric System Operator, AltaLink Management Ltd. and ENMAX Power Corporation. Foothills Area Transmission Development"

Transcription

1 Decision Alberta Electric System Operator, AltaLink Management Ltd. and ENMAX Power Corporation Foothills Area Transmission Development March 12, 2013

2

3 The Alberta Utilities Commission Decision : Alberta Electric System Operator, AltaLink Management Ltd. And ENMAX Power Corporation Foothills Area Transmission Development Applications Nos , , , Proceeding ID No March 12, 2013 Published by The Alberta Utilities Commission Fifth Avenue Place, Fourth Floor, 425 First Street S.W. Calgary, Alberta T2P 3L8 Telephone: Fax: Web site: AUC Decision (March 12, 2013) i

4 Contents 1 INTRODUCTION ADVANCE AND INTERIM FUNDING REQUESTS Mattson Group CERC The Stenbeck Group The McLaren and Carlson Group COMMISSION RULING Qualification of Local Intervener Costs Interim and Awards Mattson Group CERC The Stenbeck Group The McLaren and Carlson Group ORDER... 7 ii AUC Decision (March 12, 2013)

5 The Alberta Utilities Commission Calgary, Alberta Alberta Electric System Operator AltaLink Management Ltd. ENMAX Power Corporation Foothills Area Transmission Development Decision Proceeding ID No Introduction 1. In the Foothills Area Transmission Development proceeding, Proceeding ID 2001, the Alberta Utilities Commission (AUC or the Commission) is considering eight applications. These include: two applications filed by the Alberta Electric System Operator (AESO), five facility applications filed by AltaLink Management Ltd. (AltaLink) and one facility application filed by ENMAX Power Corporation (ENMAX). 2. The AESO filed need Application No with the AUC on July 5, 2012, requesting approval of the needs identification document for the proposed 240-kilovolt (kv) and 138-kV transmission system expansion in the vicinities of southeast Calgary, Okotoks and High River. The AESO also filed Application No on September 21, 2012, seeking approval to amend the existing NID approval for the Southern Alberta Transmission Reinforcement (SATR). 3. AltaLink filed three facility applications on July 12, 2012: Application No for the Langdon to Janet project; Application No for the North Foothills Transmission Project; and Application No for the Foothills 138-kV Transmission Project. On September 25, 2012, AltaLink filed two additional facility applications; Application No for the South Foothill Transmission Project and Application No for the Windy Flats 138- kv Project. 4. ENMAX filed facility Application No with the AUC on July 13, 2012, requesting approval to modify ENMAX No. 25 substation and ENMAX No. 65 substation. 2 Advance and Interim Funding Requests 2.1 Mattson Group 5. On January 29, 2013, Carscallen LLP filed a request for interim costs and advance funding on behalf of its clients, the Mattson Group, a group of six local interveners along the preferred route of the Janet to Langdon Transmission Project. The Mattson Group is represented by Michael B. Niven, Q.C., Lindsay Grice and Nicholas Ramessar of Carscallen LLP. The Mattson Group submitted an interim funding request for legal fees and disbursements incurred to date in the amount of $23, The Mattson Group has retained Mr. Jack Halpern of the The Louis Berger Group (LBG) to provide his expert opinion on routing issues in relation to the Langdon to Janet Transmission Project. Mr. Halpern s anticipated fees are $9, AUC Decision (March 12, 2013) 1

6 2.2 CERC 7. On February 1, 2013, Ackroyd LLP filed a request for advance funding on behalf of its client, the Committee for East Route Conservation 1 (CERC). CERC is represented by Richard C. Secord of Ackroyd LLP. CERC submitted a budget of $103, for Mr. Secord s legal fees and disbursements. 8. CERC and another intervener group, the Stenbeck Group (as defined below), jointly retained Mr. Robert A. Berrien of Berrien Associates Ltd. as an expert consultant to address the issue of routing and route impact planning. Mr. Berrien s total anticipated costs are $95, CERC and the Stenbeck Group have agreed to share Mr. Berrien s retainer. CERC has also retained Mr. Cliff Wallis of Cottonwood Consultants Ltd., Mr. Ed McDonald of JetPro Consultants Inc. and Mr. Greg Donaldson of Brown & Associates Planning Group. Mr. Wallis was retained to provide his expert opinion on the effect of the South Foothills Transmission Project on the environment in the Claresholm area. Mr. Wallis anticipated costs are $30, Mr. McDonald was retained to provide an expert opinion on the effect of the Claresholm Airport in relation to the applicant s decision not to route the transmission line west of Claresholm. Mr. McDonald s anticipated costs are $11, Mr. Donaldson was retained to provide his expert opinion on the effect of using land use planning considerations in relation to the applicant s decision not to route the transmission line west of Claresholm. Mr. Donaldson s anticipated costs are $23, The Stenbeck Group 9. On February 5, 2013, Stenbeck Law Office filed a request for advance funding on behalf of its clients, Bow Vista Farms Ltd., Louise Klatzel-Mudry/McHugh Family Landowners, Terry Thomson, Fredrick Thomson and Western Sky Land Trust (collectively, the Stenbeck Group). The Stenbeck Group is represented by Scott Stenbeck of the Stenbeck Law Office. The Stenbeck Group submitted a budget of $170, for legal fees and disbursements. The budget includes legal fees for Mr. Stenbeck and junior counsel from the Nyman Law Office. 10. As set out above, CERC and the Stenbeck Group have jointly retained Mr. Berrien and have agreed to share Mr. Berrien s retainer. 2.4 The McLaren and Carlson Group 11. On March 1, 2013, Peacock Linder & Halt LLP filed a request for interim funding on behalf of its clients, Mr. and Mrs. McLaren and Ms. Carlson (collectively, the McLaren and Carlson Group). The McLaren and Carlson Group is represented by Johanna C. Price of Peacock Linder & Halt LLP. The McLaren and Carlson Group submitted an interim funding request for legal fees and disbursements incurred to date in the amount of $13, The McLaren and Carlson Group has retained Mr. Robert Telford of McNally Land Services Ltd. to provide an expert opinion on routing issues in relation to the Langdon to Janet Transmission Project. The McLaren and Carlson Group are not seeking advance funding for Mr. Telford s services at this time. 1 An updated list CERC s members can be found in Proceeding ID 2001, Exhibit AUC Decision (March 12, 2013)

7 3 Commission Ruling 3.1 Qualification of Local Intervener Costs 13. Section 22 of the Alberta Utilities Commission Act provides that the Commission may award costs to persons or groups of persons that meet the definition of local intervener. That provision reads in part as follows: 22 (1) For purposes of this section, local intervener means a person or group or associations of persons who in the opinion of the Commission, (a) has an interest in, and (b) is in actual occupation of or is entitled to occupy land that is or may be directly and adversely affected by a decision or order of the Commission in or as a result of a hearing or other proceeding of the Commission on an application to construct or operate a hydro development, power plant or transmission line under the Hydro and Electric Energy Act or as a gas utility pipeline under the Gas Utilities Act, but unless otherwise authorized by the Commission does not include a person or group or associations of persons whose business interest may include a hydro development, power plant or transmission line or gas utility pipeline. (2) The Commission may make rules respecting the payment of costs to a local intervener for participation in any hearing or other proceeding of the Commission. 14. The Commission finds that members of the Mattson Group, CERC, the Stenbeck Group and the McLaren and Carlson Group have demonstrated that they have interests in land that is or may be affected by the Commission s decision on one or more of the above-mentioned applications and are local interveners as defined in Section 22(1) of the Alberta Utilities Commission Act. Accordingly, these groups qualify to claim local intervener costs on behalf of their respective members who own or reside upon lands that may be affected by the Commission s decision on one of the above-mentioned applications. 15. Section 2 of AUC Rule 009: Rules on Local Intervener Costs (AUC Rule 009), provides that the Commission may make an award of advance funding upon the request of a local intervener and reads as follows: 2.1 A local intervener who intends to take part in a hearing or other proceeding may, at any time during the hearing or other proceeding, make a request to the Commission for an advance of funds in accordance with the scale of costs set out in Appendix A and submit a budget in accordance with Appendix B. 2.2 The Commission may award an advance of funds to a local intervener if the local intervener demonstrates a need for financial assistance to address relevant issues in the hearing or other proceeding. 2.3 If the Commission awards an advance of funds to a local intervener under subsection 2.2, the Commission may advance the funds to the local intervener and AUC Decision (March 12, 2013) 3

8 (i) (ii) set out the terms for repayment of the advance to the Commission by the local intervener, or direct the applicant to reimburse the Commission for the funds advanced to the local intervener, or direct the applicant to advance funds to the local intervener and set out the terms for repayment of the advance to the applicant by the intervener. 16. Section 4 of AUC Rule 009 provides that the Commission may make an award of interim funding upon the request of a local intervener and reads as follows: 4.1 A local intervener may apply to the Commission for an award of interim costs incurred in a hearing or other proceeding by filing an interim costs claim. 4.2 A local intervener may only claim interim costs in accordance with the scale of costs set out in Appendix A. 4.3 The Commission may award interim costs to a local intervener if the Commission is of the opinion that the costs are reasonable and directly and necessarily related to the hearing or other proceeding, the hearing or other proceeding in which interim costs are claimed is lengthy, and the local intervener has demonstrated a need for financial assistance to continue to address relevant issues in the hearing or other proceeding. 4.4 If the Commission awards interim costs to a local intervener under subsection 4.3, the Commission may pay the interim costs to the local intervener and (i) (ii) set out terms for repayment of the interim costs to the Commission by the local intervener if the Commission varies or denies costs on a claim for costs filed by the local intervener at the close of the proceeding, or direct the applicant to reimburse the Commission for the interim costs paid to the local intervener, or direct the applicant to pay the interim costs to the local intervener and set out terms for repayment of the interim costs to the applicant by the local intervener if the Commission varies or denies costs on the claim for costs filed by the local intervener at the close of the hearing or other proceeding. 4 AUC Decision (March 12, 2013)

9 17. The Commission is satisfied that the Mattson Group, CERC, the Stenbeck Group and the McLaren and Carlson Group have all demonstrated a need for financial assistance. The Commission also finds that the combined applications qualify as a lengthy proceeding and as such, substantiate the Commission s consideration of interim funding requests. 3.2 Interim and Awards 18. Historically, the Commission and its predecessor the Alberta Energy and Utilities Board have awarded between 30 and 50 per cent of an intervener s projected costs as advance funding. 19. In giving this advance and interim funding, the Commission makes no determination on the value of any intervener s participation. Any intervener organization that accepts advance funding pursuant to this order accepts the risk that, if its final cost award relating to the proceeding is denied in its entirety or less than the amount of the advance funding directed in this order, it will be required to repay the entire amount awarded or the difference. 20. In making its final cost award, the Commission will expect to be satisfied that all fees and disbursements claimed relate to the proceeding and conform to the Scale of Costs adopted by the Commission. The Commission will also consider the effectiveness of the participation, its relevance to the issues, and whether the costs of the participation were necessary and reasonable Mattson Group 21. The Commission has reviewed the Mattson Group s interim funding request for legal fees and disbursements in regard to the tasks undertaken by Carscallen LLP to date. The Commission finds that the costs claimed are reasonable and directly relevant to the proceeding. The Commission approves the Mattson Group s interim funding request of $23, The Commission finds that the issues to be addressed by LBG are relevant to the Janet to Langdon Transmission Project. Furthermore, the estimate of $9, appears to be reasonable given the tasks to be performed by the expert consultant and the scope and nature of the issues to be addressed in this proceeding. The Commission approves 40 per cent of the budgeted amount CERC 23. The Commission has reviewed the budget filed by Ackroyd LLP for anticipated legal fees to be incurred during the course of this proceeding. The Commission finds that the estimated costs claimed are reasonable and directly relevant to the proceeding. The Commission is prepared to approve 40 per cent of the estimated legal fees. 24. The Commission has reviewed the request for advance funding filed by Ackroyd LLP with respect to Mr. Berrien s estimated budget. The Commission has reviewed the breakdown of preparation and hearing attendance time provided by Mr. Berrien in addition to the hourly rates for the services of Mr. Berrien and his technical and secretarial staff. The Commission understands that Mr. Berrien s estimated cost includes services that will be provided to the Stenbeck Group. Overall, the Commission finds that Mr. Berrien s estimate may be high given the length of the proceeding and the scope and nature of the the issues to be addressed. However, the Commission is prepared to approve 30 per cent of the budgeted amount at the present time and will consider this issue further in its final costs decision. 25. The Commission has reviewed the request for advance funding with respect to Mr. Wallis participation as an expert on environmental matters. The Commission finds that the AUC Decision (March 12, 2013) 5

10 budget appears to be reasonable given the tasks to be performed by the expert consultant and the scope and nature of the issues to be addressed in this proceeding. The Commission approves 40 per cent of the budgeted amount. 26. The Commission has reviewed the request for advance funding for Mr. McDonald s participation in the proceeding. The Commission has also reviewed AltaLink s letter dated March 1, 2013 regarding the need for Mr. McDonald s services. AltaLink stated that the Claresholm Airport advisor had no concerns with a route paralleling the existing 911L west of Claresholm. AltaLink indicated that the presence of the airport did not preclude it from siting the transmission line along this route and as a result, requested that the AUC deny any costs pertaining to this expert. The Commission has reviewed Ackroyd LLP s request for advance funding as well as AltaLink s response. Based on the submissions, the Commission finds that it will be in a better position to make a determination on this issue upon hearing from Mr. McDonald during the course of the hearing. As such, the Commission denies an award of advance funding with respect to Mr. McDonald s services and reserves its final decision on costs until the proceeding has concluded. 27. The Commission has reviewed the request for advance funding with respect to Mr. Donaldson. The Commission finds that the budget appears to be reasonable given the scope and nature of the issues to be addressed in this proceeding. In conformity with the percentage approved for the other experts, the Commission approves 40 per cent of the budgeted amount The Stenbeck Group 28. The Commission has reviewed the budget filed by the Stenbeck Law Office for anticipated legal fees to be incurred during the course of the proceeding. In comparison to the estimated fees submitted by CERC, the Commission finds that the anticipated legal fees may be disproportionate to the scope of the Stenbeck Group s interventions. However, the Commission is prepared to approve 30 per cent of the budgeted amount at the present time and will consider this issue further in its final costs decision. 29. The Commission is in receipt of the Stenbeck Group s letter dated March 3, 2013 confirming that it is not claiming advance funding for Mr. Berrien as part of its advance funding submission The McLaren and Carlson Group 30. The Commission has reviewed the McLaren and Carlson Group s interim funding request for legal fees and disbursements in regard to the tasks undertaken by Peacock Linder & Halt LLP to date. The Commission finds that the costs claimed are reasonable and directly relevant to the proceeding. The Commission approves the McLaren and Carlson Group s interim funding request of $13, The McLaren and Carlson Group is not requesting an award of advance funding for the services of its expert, Mr. Robert Telford. 6 AUC Decision (March 12, 2013)

11 4 Order 32. It is hereby ordered that: (1) AltaLink Management Ltd. shall pay advance intervener costs and interim costs in the amount of $27, to the Mattson Group. Payment shall be made to Carscallen LLP, Attention: Michael B Niven, Q.C. at 1500, Street S.W. Calgary, Alberta, T2P 2Y3. (2) AltaLink Management Ltd. shall pay advance intervener costs in the amount of $91, to CERC. Payment shall be made to Ackroyd LLP, Attention: Richard C. Secord at 1500 First Edmonton Place, Jasper Avenue, Edmonton, Alberta, T5J 3S9. (3) AltaLink Management Ltd. shall pay advance intervener costs in the amount of $51, to the Stenbeck Group. Payment shall be made to the Stenbeck Law Office, Attention: Scott C. Stenbeck, at Suite 204, 1741 Dunmore Road SE, Medicine Hat, Alberta, T1A 1Z8. (4) AltaLink Management Ltd. shall pay interim costs in the amount of $13, to the McLaren and Carlson Group. Payment shall be made to Peacock Linder & Halt LLP, Attention: Johanna C. Price at Suite 850, Avenue S.W., Calgary, Alberta, T2P 4H2. Dated on March 12, The Alberta Utilities Commission (original signed by) Anne Michaud Panel Chair (original signed by) Neil Jamieson Commission Member (original signed by) Ian Harvie Acting Commission Member AUC Decision (March 12, 2013) 7

AltaLink Management Ltd.

AltaLink Management Ltd. Decision 21368-D01-2016 Advance Funding Request from the Cooking Lake Opposition Group Advance Funding Award March 14, 2016 Alberta Utilities Commission Decision 21368-D01-2016: Advance Funding Request

More information

AltaLink Management Ltd. ATCO Electric Ltd.

AltaLink Management Ltd. ATCO Electric Ltd. Decision 2012-139 May 22, 2012 The Alberta Utilities Commission Decision 2012-139: and Application Nos. 1607971 and 1608183 Proceeding ID No. 1623 May 22, 2012 Published by The Alberta Utilities Commission

More information

Decision ATCO Electric Ltd. Bonnyville to Bourque Transmission Line Project. Costs Award. October 9, 2013

Decision ATCO Electric Ltd. Bonnyville to Bourque Transmission Line Project. Costs Award. October 9, 2013 Decision 2013-374 Bonnyville to Bourque Transmission Line Project Costs Award October 9, 2013 The Alberta Utilities Commission Decision 2013-374: Bonnyville to Bourque Transmission Line Project Costs Award

More information

Acciona Wind Energy Canada, Inc.

Acciona Wind Energy Canada, Inc. Decision 2013-439 Acciona Wind Energy Canada, Inc. New Dayton Wind Power Project Facility & Substation Costs Award December 11, 2013 The Alberta Utilities Commission Decision 2013-439: Acciona Wind Energy

More information

Capital Power Corporation. Halkirk 2 Wind Power Project

Capital Power Corporation. Halkirk 2 Wind Power Project Decision 23255-D01-2018 Capital Power Corporation Halkirk 2 Wind Power Project July 9, 2018 Alberta Utilities Commission Decision 23255-D01-2018 Capital Power Corporation Halkirk 2 Wind Power Project Proceeding

More information

AltaLink Management Ltd. & EPCOR Distribution & Transmission Inc.

AltaLink Management Ltd. & EPCOR Distribution & Transmission Inc. Decision 2013-280 AltaLink Management Ltd. & EPCOR Distribution & Transmission Inc. Heartland Transmission Project Amendment Structure T176 Repositioning Costs Award July 29, 2013 The Alberta Utilities

More information

E.ON Climate & Renewables Canada Ltd. Grizzly Bear Creek Wind Power Project

E.ON Climate & Renewables Canada Ltd. Grizzly Bear Creek Wind Power Project Decision 21513-D01-2016 Grizzly Bear Creek Wind Power Project July 21, 2016 Alberta Utilities Commission Decision 21513-D01-2016 Grizzly Bear Creek Wind Power Project Proceeding 21513 July 21, 2016 Published

More information

AltaLink Management Ltd.

AltaLink Management Ltd. Decision 2012-115 Western Alberta Transmission Line April 27, 2012 The Alberta Utilities Commission Decision 2012-115: Western Alberta Transmission Line Application Nos. 1607884, 1607983, 1608011, 1608050,

More information

AltaLink Management Ltd.

AltaLink Management Ltd. Decision 20926-D01-2016 Transmission Line 423L March 15, 2016 Alberta Utilities Commission Decision 20926-D01-2016: Transmission Line 423L Proceeding 20926 March 15, 2016 Published by Alberta Utilities

More information

Langdon Waterworks Limited

Langdon Waterworks Limited Decision 20372-D01-2015 May 14, 2015 Alberta Utilities Commission Decision 20372-D01-2015 Proceeding 20372 May 14, 2015 Published by the: Alberta Utilities Commission Fifth Avenue Place, Fourth Floor,

More information

Decision ATCO Electric Ltd. February 1, 2013 Interim Tariff. January 18, 2013

Decision ATCO Electric Ltd. February 1, 2013 Interim Tariff. January 18, 2013 Decision 2013-015 February 1, 2013 Interim Tariff January 18, 2013 The Alberta Utilities Commission Decision 2013-015: February 1, 2013 Interim Tariff Application No. 1609127 Proceeding ID No. 2305 January

More information

ENMAX Power Corporation

ENMAX Power Corporation Decision 22756-D01-2017 Tax Agreement with The City of Calgary September 7, 2017 Alberta Utilities Commission Decision 22756-D01-2017 Tax Agreement with The City of Calgary Proceeding 22756 September 7,

More information

Decision D Alberta PowerLine L.P. Tariff Application. January 23, 2018

Decision D Alberta PowerLine L.P. Tariff Application. January 23, 2018 Decision 23161-D01-2018 Alberta PowerLine L.P. Tariff Application January 23, 2018 Alberta Utilities Commission Decision 23161-D01-2018 Alberta PowerLine L.P. Tariff Application Proceeding 23161 January

More information

Daishowa-Marubeni International Ltd.

Daishowa-Marubeni International Ltd. Decision 2011-299 25-MW Condensing Steam Turbine Generator July 8, 2011 The Alberta Utilities Commission Decision 2011-299: 25-MW Condensing Steam Turbine Generator Application No. 1606747 Proceeding ID

More information

ENMAX Energy Corporation

ENMAX Energy Corporation Decision 23006-D01-2018 Regulated Rate Option - Energy Price Setting Plan Monthly Filings for Acknowledgment 2017 Quarter 3 February 7, 2018 Alberta Utilities Commission Decision 23006-D01-2018: Regulated

More information

AltaLink Management Ltd.

AltaLink Management Ltd. Decision 22025-D03-2017 Red Deer Area Transmission Development Amendment Application June 8, 2017 Decision 22025-D03-2017 Red Deer Area Transmission Development Amendment Application Proceeding 22025 Applications

More information

TransCanada Energy Ltd.

TransCanada Energy Ltd. Decision 22302-D01-2017 Request for Permitting the Sharing of Records Not Available to the Public Between and Pembina Pipeline Corporation May 26, 2017 Alberta Utilities Commission Decision 22302-D01-2017

More information

Decision D ATCO Electric Ltd. Hughes 2030S Substation. Costs Award

Decision D ATCO Electric Ltd. Hughes 2030S Substation. Costs Award Decision 22406-D01-2017 Hughes 2030S Substation June 9, 2017 Alberta Utilities Commission Decision 22406-D01-2017 Hughes 2030S Substation Proceeding 22406 June 9, 2017 Published by Alberta Utilities Commission

More information

Brion Energy Corporation

Brion Energy Corporation Decision 21524-D01-2016 MacKay River Commercial Project Ownership Change for the Sales Oil Pipeline Lease Automated Custody Transfer Site June 14, 2016 Alberta Utilities Commission Decision 21524-D01-2016

More information

ENMAX Power Corporation Distribution and Transmission Deferral Account Reconciliation

ENMAX Power Corporation Distribution and Transmission Deferral Account Reconciliation Decision 23108-D01-2018 2014 Distribution and 2014-2015 Transmission Deferral Account Reconciliation February 27, 2018 Alberta Utilities Commission Decision 23108-D01-2018 2014 Distribution and 2014-2015

More information

Decision D Generic Cost of Capital. Costs Award

Decision D Generic Cost of Capital. Costs Award Decision 21856-D01-2016 Costs Award December 2, 2016 Alberta Utilities Commission Decision 21856-D01-2016 Costs Award Proceeding 21856 December 2, 2016 Published by Alberta Utilities Commission Fifth Avenue

More information

Livingstone Landowners Guild

Livingstone Landowners Guild Decision 20846-D01-2016 Livingstone Landowners Guild Application for Review of Decision 2009-126 Needs Identification Document Application Southern Alberta Transmission System Reinforcement as amended

More information

Decision D ATCO Electric Ltd. Amounts to be Paid Into and Out of Balancing Pool for Chinchaga Power Plant Sale

Decision D ATCO Electric Ltd. Amounts to be Paid Into and Out of Balancing Pool for Chinchaga Power Plant Sale Decision 21833-D01-2016 Amounts to be Paid Into and Out of Balancing Pool for Chinchaga Power Plant Sale December 20, 2016 Alberta Utilities Commission Decision 21833-D01-2016 Proceeding 21833 December

More information

AltaLink Investment Management Ltd. And SNC Lavalin Transmission Ltd. et al.

AltaLink Investment Management Ltd. And SNC Lavalin Transmission Ltd. et al. Decision 3529-D01-2015 AltaLink Investment Management Ltd. And SNC Lavalin Transmission Ltd. et al. Proposed Sale of AltaLink, L.P Transmission Assets and Business to Mid-American (Alberta) Canada Costs

More information

Provident Energy Ltd.

Provident Energy Ltd. Alberta Energy and Utilities Board Energy Cost Order 2005-002 Applications for Licences for a Well and Battery Cost Awards ALBERTA ENERGY AND UTILITIES BOARD Energy Cost Order 2005-002 Applications for

More information

AltaLink Management Ltd.

AltaLink Management Ltd. Decision 21054-D01-2016 2013-2014 General Tariff Application (Proceeding 2044-Reopened for Midgard Audit) March 7, 2016 Alberta Utilities Commission Decision 21054-D01-2016: Proceeding 21054 March 7,

More information

Highpine Oil & Gas Ltd. (formerly Vaquero Energy Ltd.)

Highpine Oil & Gas Ltd. (formerly Vaquero Energy Ltd.) Alberta Energy and Utilities Board Energy Cost Order 2005-009 (formerly Vaquero Energy Ltd.) Application for a Oil Effluent Pipeline Chip Lake Field Cost Awards ALBERTA ENERGY AND UTILITIES BOARD Energy

More information

Decision D Balancing Pool

Decision D Balancing Pool Decision 22184-D10-2017 Application for an Order Permitting the Sharing of Records Not Available to the Public Between the, TransAlta Generation Partnership, and Capital Power Generation Services Inc.

More information

The University of Calgary

The University of Calgary Decision 23147-D01-2018 Application for an Order Permitting the Sharing of Records Not Available to the Public Between the University of Calgary and URICA Energy Real Time Ltd. January 30, 2018 Alberta

More information

West Wetaskiwin Rural Electrification Association Ltd.

West Wetaskiwin Rural Electrification Association Ltd. Decision 22067-D01-2016 West Wetaskiwin Rural Electrification Association Ltd. Varied Code of Conduct Regulation Compliance Plan December 21, 2016 Alberta Utilities Commission Decision 22067-D01-2016 West

More information

ATCO Gas and Pipelines Ltd. (South)

ATCO Gas and Pipelines Ltd. (South) Decision 2010-170 New Construction Replacement of ATCO Pipelines Existing Southern Extension Pipeline From North of Lacombe to East of Gwynne April 15, 2010 ALBERTA UTILITIES COMMISSION Decision 2010-170:

More information

AltaLink Management Ltd.

AltaLink Management Ltd. Decision 2012-327 Western Alberta Transmission Line Project December 6, 2012 The Alberta Utilities Commission Decision 2012-327: Western Alberta Transmission Line Project Application No. 1607067 Proceeding

More information

ATCO Electric and ATCO Pipelines. Application for ATCO Electric and ATCO Pipelines License Fees

ATCO Electric and ATCO Pipelines. Application for ATCO Electric and ATCO Pipelines License Fees Decision 21571-D01-2016 and ATCO Pipelines 2015-2016 License Fees August 17, 2016 Alberta Utilities Commission Decision 21571-D01-2016 and ATCO Pipelines 2015-2016 License Fees Proceeding 21571 August

More information

Alberta Electric System Operator

Alberta Electric System Operator Decision 23065-D01-2017 Alberta Electric System Operator 2018 Independent System Operator Tariff Update November 28, 2017 Alberta Utilities Commission Decision 23065-D01-2017 Alberta Electric System Operator

More information

Montana Alberta Tie Ltd. and AltaLink Management Ltd.

Montana Alberta Tie Ltd. and AltaLink Management Ltd. Decision 2013-195 Montana Alberta Tie Ltd. and AltaLink Management Ltd. MATL 230-Kv International Merchant Power Lines Final Design and Time Extension for MATL Project Facilities May 24, 2013 The Alberta

More information

Mayerthorpe and District Rural Electrification Association Ltd.

Mayerthorpe and District Rural Electrification Association Ltd. Decision 22692-D01-2018 Mayerthorpe and District Rural Electrification Association Ltd. Varied Code of Conduct Regulation Compliance Plan January 31, 2018 Alberta Utilities Commission Decision 22692-D01-2018

More information

Mackenzie Rural Electrification Association Ltd.

Mackenzie Rural Electrification Association Ltd. Decision 21983-D01-2016 Varied Code of Conduct Regulation Compliance Plan December 14, 2016 Alberta Utilities Commission Decision 21983-D01-2016 Varied Code of Conduct Regulation Compliance Plan Proceeding

More information

EPCOR Distribution & Transmission Inc.

EPCOR Distribution & Transmission Inc. Decision 22603-D01-2017 June 23, 2017 Alberta Utilities Commission Decision 22603-D01-2017 Proceeding 22603 June 23, 2017 Published by the: Alberta Utilities Commission Fifth Avenue Place, Fourth Floor,

More information

Decision D Performance-Based Regulation Plans for Alberta Electric and Gas Distribution Utilities.

Decision D Performance-Based Regulation Plans for Alberta Electric and Gas Distribution Utilities. Decision 22082-D01-2017 2018-2022 Performance-Based Regulation Plans for Alberta Electric and Gas Distribution Utilities February 6, 2017 Alberta Utilities Commission Decision 22082-D01-2017 2018-2022

More information

Decision D FortisAlberta Inc. Light-Emitting Diode Lighting Conversion Maintenance Multiplier for the City of St.

Decision D FortisAlberta Inc. Light-Emitting Diode Lighting Conversion Maintenance Multiplier for the City of St. Decision 21754-D01-2016 Light-Emitting Diode Lighting Conversion Maintenance Multiplier for the City of St. Albert August 11, 2016 Alberta Utilities Commission Decision 21754-D01-2016 Light-Emitting Diode

More information

Alberta Utilities Commission

Alberta Utilities Commission Alberta Utilities Commission In the Matter of the Need for the Al Rothbauer 321S Substation And in the matter of the Electric Utilities Act, S.A. 2003, c. E-5.1, the Alberta Utilities Commission Act, S.A.

More information

ATCO Electric Ltd. Stage 2 Review of Decision D ATCO Electric Ltd Transmission General Tariff Application

ATCO Electric Ltd. Stage 2 Review of Decision D ATCO Electric Ltd Transmission General Tariff Application Decision 22483-D01-2017 Stage 2 Review of Decision 20272-D01-2016 2015-2017 Transmission General Tariff Application December 6, 2017 Alberta Utilities Commission Decision 22483-D01-2017 Stage 2 Review

More information

ATCO Gas and Pipelines Ltd. (South)

ATCO Gas and Pipelines Ltd. (South) Decision 3421-D01-2015 Northeast Calgary Connector Pipeline January 16, 2015 The Alberta Utilities Commission Decision 3421-D01-2015: Northeast Calgary Connector Pipeline Application 1610854 Proceeding

More information

Shell Canada Limited and Canadian Natural Resources Limited

Shell Canada Limited and Canadian Natural Resources Limited Decision 22614-D01-2017 Albian Oil Sands Industrial Complex and June 28, 2017 Alberta Utilities Commission Decision 22614-D01-2017 Albian Oil Sands Industrial Complex and Proceeding 22614 Applications

More information

Decision The ATCO Utilities. Corporate Costs. March 21, 2013

Decision The ATCO Utilities. Corporate Costs. March 21, 2013 Decision 2013-111 Corporate Costs March 21, 2013 The Alberta Utilities Commission Decision 2013-111: Corporate Costs Application No. 1608510 Proceeding ID No. 1920 March 21, 2013 Published by The Alberta

More information

The University of Calgary

The University of Calgary Decision 2014-365 Preferential Sharing of Records between the University of Calgary and URICA Energy Real Time Ltd. December 19, 2014 The Alberta Utilities Commission Decision 2014-365: Preferential Sharing

More information

Langdon Waterworks Limited

Langdon Waterworks Limited Decision 2014-240 August 19, 2014 The Alberta Utilities Commission Decision 2014-240: Application No. 1610617 Proceeding No. 3258 August 19, 2014 Published by The Alberta Utilities Commission Fifth Avenue

More information

Decision D ATCO Electric Ltd. Compliance Filing to Decision D Capital Tracker True-Up

Decision D ATCO Electric Ltd. Compliance Filing to Decision D Capital Tracker True-Up Decision 23454-D01-2018 ATCO Electric Ltd. Compliance Filing to Decision 22788-D01-2018 2016 Capital Tracker True-Up May 4, 2018 Alberta Utilities Commission Decision 23454-D01-2018 ATCO Electric Ltd.

More information

Bumper Development Corporation Ltd.

Bumper Development Corporation Ltd. Alberta Energy and Utilities Board Energy Cost Order 2004-13 Bumper Development Corporation Ltd. Review of Well Licence No. 0287658 Davey Field Cost Awards ALBERTA ENERGY AND UTILITIES BOARD Energy Cost

More information

Enbridge Battle Sands 594S Substation Connection Needs Identification Document

Enbridge Battle Sands 594S Substation Connection Needs Identification Document APPENDIX C AESO PIP Enbridge Battle Sands 594S Substation Connection Needs Identification Document 1.0 Participant Involvement Program (PIP) From June to October 2015, the AESO conducted a Participant

More information

Decision ATCO Utilities. Corporate Cost Allocation Methodology. September 20, 2010

Decision ATCO Utilities. Corporate Cost Allocation Methodology. September 20, 2010 Decision 2010-447 Corporate Cost Allocation Methodology September 20, 2010 ALBERTA UTILITIES COMMISSION Decision 2010-447: Corporate Cost Allocation Methodology Application No. 1605473 Proceeding ID. 306

More information

Canadian Natural Resources Limited

Canadian Natural Resources Limited Decision 22669-D03-2017 Application for an Order Permitting the Sharing of Records Not Available to the Public Between Canadian Natural Resources Limited and ATCO Power Canada Ltd. July 21, 2017 Alberta

More information

ENMAX Power Corporation

ENMAX Power Corporation Decision 22238-D01-2017 ENMAX Power Corporation 2016-2017 Transmission General Tariff Application December 4, 2017 Alberta Utilities Commission Decision 22238-D01-2017 ENMAX Power Corporation 2016-2017

More information

Kneehill Rural Electrification Association Ltd.

Kneehill Rural Electrification Association Ltd. Decision 23420-D01-2018 Kneehill Rural Electrification Association Ltd. Varied Code of Conduct Regulation Compliance Plan April 23, 2018 Alberta Utilities Commission Decision 23420-D01-2018 Kneehill Rural

More information

ATCO Gas and Pipelines Ltd.

ATCO Gas and Pipelines Ltd. Decision 2738-D01-2016 Z Factor Application for Recovery of 2013 Southern Alberta Flood Costs March 16, 2016 Alberta Utilities Commission Decision 2738-D01-2016 Z Factor Application for Recovery of 2013

More information

Canadian Natural Resources Limited

Canadian Natural Resources Limited Alberta Energy and Utilities Board Energy Cost Order 2004-07 Canadian Natural Resources Limited Application for an Oil Sands Mine, Bitumen Extraction Plant, and Bitumen Upgrading Plant in the Fort McMurray

More information

Collaborative Process

Collaborative Process Alberta Energy and Utilities Board Utility Cost Order 2006-065 Uniform System of Accounts and Minimum Filing Requirements Cost Awards ALBERTA ENERGY AND UTILITIES BOARD Utility Cost Order 2006-065 Uniform

More information

Consumers Coalition of Alberta

Consumers Coalition of Alberta Decision 22157-D01-2017 Decision on Preliminary Question AltaLink Management Ltd. 2012-2013 Deferral Account Reconciliation Costs Award February 15, 2017 Alberta Utilities Commission Decision 22157-D01-2017

More information

Decision Town of Innisfail. Franchise Agreement with ATCO Gas and Pipelines Ltd. and Amendment to Rider A.

Decision Town of Innisfail. Franchise Agreement with ATCO Gas and Pipelines Ltd. and Amendment to Rider A. Decision 2012-300 Franchise Agreement with ATCO Gas and Pipelines Ltd. and Amendment to Rider A November 9, 2012 The Alberta Utilities Commission Decision 2012-300: Franchise Agreement with ATCO Gas and

More information

Decision D Rebasing for the PBR Plans for Alberta Electric and Gas Distribution Utilities. First Compliance Proceeding

Decision D Rebasing for the PBR Plans for Alberta Electric and Gas Distribution Utilities. First Compliance Proceeding Decision 22394-D01-2018 Rebasing for the 2018-2022 PBR Plans for February 5, 2018 Alberta Utilities Commission Decision 22394-D01-2018 Rebasing for the 2018-2022 PBR Plans for Proceeding 22394 February

More information

AltaLink Management Ltd.

AltaLink Management Ltd. Decision 20986-D01-2016 Southwest Calgary Ring Road Transmission Project August 31, 2016 Alberta Utilities Commission Decision 20986-D01-2016 Southwest Calgary Ring Road Transmission Project Proceeding

More information

AltaGas Utilities Inc.

AltaGas Utilities Inc. Decision 21822-D01-2016 AltaGas Utilities Inc. 2016-2017 Unaccounted-For Gas Rider E and Rider H September 1, 2016 Alberta Utilities Commission Decision 21822-D01-2016 AltaGas Utilities Inc. 2016-2017

More information

Immediate Attention for Piikani Nation Members

Immediate Attention for Piikani Nation Members Immediate Attention for Piikani Nation Members IMPORTANT INFORMATION Altalink L.P., Transfer of Specific Assets to PiikaniLink L.P. and associated 2017-2018 General Tariff Application. AUC Proceeding 22612

More information

Dominion Exploration Canada Ltd.

Dominion Exploration Canada Ltd. Alberta Energy and Utilities Board Energy Cost Order 2006-007 Dominion Exploration Canada Ltd. Applications for Well Licences Pembina Field Cost Awards ALBERTA ENERGY AND UTILITIES BOARD Energy Cost Order

More information

Alberta Utilities Commission

Alberta Utilities Commission Alberta Utilities Commission In the Matter of the Need for the Jenner Wind Energy Connection And in the matter of the Electric Utilities Act, S.A. 2003, c. E-5.1, the Alberta Utilities Commission Act,

More information

Alberta Utilities Commission

Alberta Utilities Commission Alberta Utilities Commission In the Matter of the Need for the Riverview Wind Power Plant Connection And in the matter of the Electric Utilities Act, S.A. 2003, c. E-5.1, the Alberta Utilities Commission

More information

Alberta Utilities Commission

Alberta Utilities Commission Alberta Utilities Commission In the Matter of the Need for the Irma Wind Power Project Connection And in the matter of the Electric Utilities Act, S.A. 2003, c. E-5.1, the Alberta Utilities Commission

More information

2014 ABAER 007. Inter Pipeline Ltd. Application for a Pipeline Licence Edmonton/Fort Saskatchewan Area. June 23, 2014

2014 ABAER 007. Inter Pipeline Ltd. Application for a Pipeline Licence Edmonton/Fort Saskatchewan Area. June 23, 2014 2014 ABAER 007 Inter Pipeline Ltd. Application for a Pipeline Licence Edmonton/Fort Saskatchewan Area June 23, 2014 ALBERTA ENERGY REGULATOR Decision 2014 ABAER 007: Inter Pipeline Ltd., Application for

More information

Decision D FortisAlberta Inc PBR Capital Tracker True-Up and PBR Capital Tracker Forecast

Decision D FortisAlberta Inc PBR Capital Tracker True-Up and PBR Capital Tracker Forecast Decision 20497-D01-2016 FortisAlberta Inc. 2014 PBR Capital Tracker True-Up and 2016-2017 PBR Capital Tracker Forecast February 20, 2016 Alberta Utilities Commission Decision 20497-D01-2016 FortisAlberta

More information

Glencoe Resources Ltd.

Glencoe Resources Ltd. Energy Cost Order 2012-006 Glencoe Resources Ltd. Application for Well Licence Chigwell Field Cost Awards July 16, 2012 ENERGY RESOURCES CONSERVATION BOARD Energy Cost Order 2012-006: Glencoe Resources

More information

EPCOR Distribution & Transmission Inc.

EPCOR Distribution & Transmission Inc. Decision 21229-D01-2016 EPCOR Distribution & Transmission Inc. 2015-2017 Transmission Facility Owner Tariff and 2013 Generic Cost of Capital Compliance Application April 15, 2016 Alberta Utilities Commission

More information

April 13, Via

April 13, Via ENMAX Corporation 141 50 Avenue SE Calgary, AB T2G 4S7 Tel (403) 514-3000 enmax.com April 13, 2007 Via Email Ms. Brenda Ambrosi Vancouver, BC V7X 1V5 Dear Ms. Ambrosi: Re: Network Economy Business Practices

More information

Alberta Utilities Commission

Alberta Utilities Commission Alberta Utilities Commission In the Matter of the Need for the Kirby North Central Processing Facility Connection And in the matter of the Electric Utilities Act, S.A. 2003, c. E-5.1, the Alberta Utilities

More information

Canadian Natural Resources Limited

Canadian Natural Resources Limited Decision 21306-D01-2016 Determination of Compensation for 9L66/9L32 Transmission Line Relocation August 16, 2016 Alberta Utilities Commission Decision 21306-D01-2016 Determination of Compensation for 9L66/9L32

More information

Decision CU Water Limited. Disposition of Assets. April 30, 2010

Decision CU Water Limited. Disposition of Assets. April 30, 2010 Decision 2010-192 Disposition of Assets April 30, 2010 ALBERTA UTILITIES COMMISSION Decision 2010-192: Disposition of Assets Application No. 1606042 Proceeding ID. 569 April 30, 2010 Published by Alberta

More information

Alberta Utilities Commission

Alberta Utilities Commission Alberta Utilities Commission In the Matter of the Need for 138 kv and 240 kv Transmission System Development in the Red Deer Region And in the matter of the Electric Utilities Act, S.A. 2003, c. E-5.1,

More information

ATCO Gas and Pipelines Ltd. (South)

ATCO Gas and Pipelines Ltd. (South) Decision 22634-D01-2017 Southwest Calgary Connector Pipeline Project August 9, 2017 Alberta Utilities Commission Decision 22634-D01-2017 Southwest Calgary Connector Pipeline Project Proceeding 22634 Application

More information

Alberta Utilities Commission

Alberta Utilities Commission Decision 22091-D01-2017 Commission-Initiated Proceeding to Review the Terms and November 9, 2017 Decision 22091-D01-2017 Commission-Initiated Proceeding to Review the Terms and Proceeding 22091 Application

More information

AltaGas Utilities Inc.

AltaGas Utilities Inc. Decision 2013-465 2014 Annual PBR Rate Adjustment Filing December 23, 2013 The Alberta Utilities Commission Decision 2013-465: 2014 Annual PBR Rate Adjustment Filing Application No. 1609923 Proceeding

More information

Report to the Minister March 1, 2011

Report to the Minister March 1, 2011 March 1, 2011 Market Surveillance Administrator 403.705.3181 #500, 400 5th Avenue S.W., Calgary AB T2P 0L6 www.albertamsa.ca March 1, 2011 1 Table of Contents 1 Introduction... 3 2 Offer Behaviour... 3

More information

ENVIRONMENTAL ALBERTA APPEALS BOARD. Dems on. Preliminary. Appeal No : _ ID1. Properties

ENVIRONMENTAL ALBERTA APPEALS BOARD. Dems on. Preliminary. Appeal No : _ ID1. Properties ALBERTA APPEALS BOARD ENVIRONMENTAL THE MATTER OF sections 91, 92, and 95 of the IN Protection and Enhancement Act, R.S.A. 2000, c. Environmental THE MATTER OF an appeal filed by Alberta Foothills IN Ltd.

More information

AltaLink Management Ltd. and EPCOR Distribution & Transmission Inc.

AltaLink Management Ltd. and EPCOR Distribution & Transmission Inc. Decision 2012-124 Decision on Request for Review and Variance of AUC Decision 2011-436 Heartland Transmission Project May 14, 2012 The Alberta Utilities Commission Decision 2012-124: Decision on Request

More information

EPCOR Energy Alberta GP Inc.

EPCOR Energy Alberta GP Inc. Decision 20633-D01-2016 EPCOR Energy Alberta GP Inc. 2016-2017 Regulated Rate Tariff Application December 20, 2016 Alberta Utilities Commission Decision 20633-D01-2016 EPCOR Energy Alberta GP Inc. 2016-2017

More information

Decision D FortisAlberta Inc Performance-Based Regulation Capital Tracker True-Up. January 11, 2018

Decision D FortisAlberta Inc Performance-Based Regulation Capital Tracker True-Up. January 11, 2018 Decision 22741-D01-2018 FortisAlberta Inc. 2016 Performance-Based Regulation Capital Tracker True-Up January 11, 2018 Alberta Utilities Commission Decision 22741-D01-2018 FortisAlberta Inc. 2016 Performance-Based

More information

ALBERTA ENVIRONMENTAL APPEALS BOARD. Decision. Date of Decision December 18, 2014

ALBERTA ENVIRONMENTAL APPEALS BOARD. Decision. Date of Decision December 18, 2014 Appeal Nos. 14-003-006-IC ALBERTA ENVIRONMENTAL APPEALS BOARD Decision Date of Decision December 18, 2014 IN THE MATTER OF sections 91, 92, 95, and 96 of the Environmental Protection and Enhancement Act,

More information

AltaLink Management Ltd.

AltaLink Management Ltd. Decision 22612-D01-2018 November 13, 2018 Alberta Utilities Commission Decision 22612-D01-2018 to PiikaniLink L.P. and KainaiLink L.P. and the Proceeding 22612 Applications 22612-A001, 22612-A002, 22612-A003,

More information

Decision D FortisAlberta Inc. Light-Emitting Diode (LED) Lighting Conversion Maintenance Multiplier Filing for 30 Customers in 2018

Decision D FortisAlberta Inc. Light-Emitting Diode (LED) Lighting Conversion Maintenance Multiplier Filing for 30 Customers in 2018 Decision 23730-D01-2018 Light-Emitting Diode (LED) Lighting Conversion Maintenance Multiplier Filing for 30 Customers in 2018 September 7, 2018 Alberta Utilities Commission Decision 23730-D01-2018 Light-Emitting

More information

Decision TykeWest Limited. Setting of Fees for a Common Carrier Order. July 15, 2009

Decision TykeWest Limited. Setting of Fees for a Common Carrier Order. July 15, 2009 Decision 2009-106 Setting of Fees for a Common Carrier Order July 15, 2009 ALBERTA UTILITIES COMMISSION Decision 2009-106: Setting of Fees for a Common Carrier Order Application No. 1567541 July 15, 2009

More information

FortisAlberta Inc. Sale and Transfer of the Municipality of Crowsnest Pass Electric Distribution Assets

FortisAlberta Inc. Sale and Transfer of the Municipality of Crowsnest Pass Electric Distribution Assets Decision 21785-D01-2018 Sale and Transfer of the Electric Distribution Assets June 5, 2018 Alberta Utilities Commission Decision 21785-D01-2018 Sale and Transfer of the Electric Distribution System Assets

More information

Alberta Utilities Commission

Alberta Utilities Commission Alberta Utilities Commission In the Matter of the Need for the ATCO Power Heartland Generating Station Connection And in the matter of the Electric Utilities Act, S.A. 2003, c. E-5.1, the Alberta Utilities

More information

ALBERTA ENVIRONMENTAL APPEAL BOARD. Discontinuance of Proceedings

ALBERTA ENVIRONMENTAL APPEAL BOARD. Discontinuance of Proceedings Appeal No. 03-020-DOP ALBERTA ENVIRONMENTAL APPEAL BOARD Discontinuance of Proceedings Date of Discontinuance of Proceedings September 25, 2003 IN THE MATTER OF sections 91, 92 and 95 of the Environmental

More information

City of Edmonton. Natural Gas Franchise Agreement with ATCO Gas and Pipelines Ltd. August 31, Decision

City of Edmonton. Natural Gas Franchise Agreement with ATCO Gas and Pipelines Ltd. August 31, Decision Alberta Energy and Utilities Board Decision 2004-072 Natural Gas Franchise Agreement with ATCO Gas and Pipelines Ltd. August 31, 2004 ALBERTA ENERGY AND UTILITIES BOARD Decision 2004-072: Natural Gas Franchise

More information

AltaGas Utilities Inc.

AltaGas Utilities Inc. Decision 23898-D01-2018 2019 Annual Performance-Based Regulation Rate Adjustment Filing December 20, 2018 Alberta Utilities Commission Decision 23898-D01-2018 2019 Annual Performance-Based Regulation Rate

More information

Court of Queen s Bench

Court of Queen s Bench Notice to Disclose Court of Queen s Bench Notice to Disclose / Application Instructions Notice to Disclose / Application Before you Begin: You must have a court file in the Court of Queen s Bench to use

More information

Decision D FortisAlberta Inc.

Decision D FortisAlberta Inc. Decision 23063-D01-2018 Light-Emitting Diode Lighting Conversion Maintenance Multiplier Filing January 30, 2018 Alberta Utilities Commission Decision 23063-D01-2018 Light-Emitting Diode Lighting Conversion

More information

NOTICE OF REVISED APPLICATION

NOTICE OF REVISED APPLICATION Ontario Energy Board Commission de l énergie de l Ontario EB-2012-0451 NOTICE OF REVISED APPLICATION Enbridge Gas Distribution Inc. has requested to revise its application for approval to build two segments

More information

Decision Wind Power Inc. Request to Transfer Power Plant Approval No. U November 26, 2008

Decision Wind Power Inc. Request to Transfer Power Plant Approval No. U November 26, 2008 Decision 2008-121 Wind Power Inc. Request to Transfer Power Plant Approval No. U2007-74 November 26, 2008 ALBERTA UTILITIES COMMISSION Decision 2008-121: Wind Power Inc. Request to Transfer Power Plant

More information

Alberta Energy-Capacity Market Framework Engagement November 2017

Alberta Energy-Capacity Market Framework Engagement November 2017 Questions for discussion The engagement is seeking feedback on the six questions outlined in the table below. Please provide your input on these questions in Table 1 on the next three pages. Please submit

More information

INVESTOR PRESENTATION JUNE 2018

INVESTOR PRESENTATION JUNE 2018 INVESTOR PRESENTATION JUNE 2018 LEGAL DISCLAIMER Statements made by representatives for ATCO Ltd. and Canadian Utilities Limited and information provided in this presentation may be considered forward-looking

More information