Canadian Natural Resources Limited

Size: px
Start display at page:

Download "Canadian Natural Resources Limited"

Transcription

1 Decision D Application for an Order Permitting the Sharing of Records Not Available to the Public Between Canadian Natural Resources Limited and ATCO Power Canada Ltd. July 21, 2017

2 Alberta Utilities Commission Decision D Application for an Order Permitting the Sharing of Records Not Available to the Public Between and ATCO Power Canada Ltd. Application A001 Proceeding July 21, 2017 Published by the: Alberta Utilities Commission Fifth Avenue Place, Fourth Floor, 425 First Street S.W. Calgary, Alberta T2P 3L8 Telephone: Fax: Website:

3 Contents 1 Introduction and background The Commission s authority to allow record sharing Views of the parties Is the proposed sharing of records reasonably necessary? Fair, efficient and openly competitive operation of the market Commission findings Decision... 5 Decision D (July 21, 2017) i

4

5 Alberta Utilities Commission Calgary, Alberta Application for an Order Permitting the Sharing of Records Not Available to the Public Between Canadian Natural Resources Limited and ATCO Power Canada Ltd. Decision D Application A001 Proceeding Introduction and background 1. In its application, 1 (CNRL) has requested preferential sharing of information that is not available to the public with respect to the Muskeg Cogeneration Facility (MKR1), which has a maximum capability of 202 megawatts (MW). CNRL submitted in its application that it was necessary to share records relating to MKR1 with ATCO Power Canada Ltd. (ATCO) because this information was necessary to carry out its business obligations relating to the operation of MKR1. CNRL requested that the term for the order be from May 31, 2017, until the earlier of the termination of contractual arrangements between CNRL and ATCO regarding MKR1 or June 1, On August 10, 2010, pursuant to the provisions of Section 3 of the Fair, Efficient and Open Competition Regulation, the Commission issued an order permitting ATCO to share records with respect to MKR1 with Shell Canada Ltd. (Shell). 3 CNRL submitted that, effective May 31, 2017, Shell transferred and assigned ownership of the Albian Sands Industrial Complex north of Fort McMurray, which includes MKR1 and electrical facilities to serve the energy requirements of the site, to CNRL. Electricity and steam is produced by MKR1 to support industrial processes at the Albian Sands Industrial Complex and electricity produced in excess of site requirements is sold by ATCO through the Alberta power pool. CNRL will continue the operational responsibilities formerly performed by Shell for the Albian Sands Industrial Complex. ATCO, in partnership with SaskPower International Inc., owns MKR1. 3. CNRL originally filed its application, with respect to MKR1, for the preferential sharing of records that are not available to the public with ATCO on May 19, On May 24, 2017, CNRL filed a clarification letter along with a revised application. 4. The Commission issued notice of the application on May 25, The notice specified that the only parties with standing in the proceeding were CNRL and the Market Surveillance Administrator (MSA) and established a process and schedule for the MSA to determine whether it would intervene in the proceeding and to advise the Commission whether it required an evidentiary process. 4 1 Application A Exhibit X0005, Revised preferential sharing of records application registered May 24, 2017, PDF page 5. 3 Decision :Shell Canada Limited and ATCO Power Canada Limited - Preferential Sharing of Records between Shell Canada Limited and ATCO Power Canada Limited, Proceeding 511, Application , August 10, Exhibit X0006, Notice of Application, May 25, Decision D (July 21, 2017) 1

6 Application for an Order Permitting the Sharing of Records Not Available to the Public Between and ATCO Power Canada Ltd. 5. On May 25, 2017, the MSA advised the Commission that it supported the application and did not require further evidentiary process On May 31, 2017, the Commission, citing CNRL s expressed need for expedience and noting that the MSA supported the application, issued an order permitting the sharing of records not available to the public between CNRL and ATCO, as requested by CNRL, on an interim basis. 6 The issuance of this interim order addressed the stated need for expedience and provided the Commission with sufficient time to carry out the necessary analysis required by the statutory framework. 7. On June 15, 2017, the Commission requested additional information from CNRL, including additional details on expected offer prices for MKR1, the expected outage schedule for MKR1, the nature of the information to be shared between CNRL and ATCO, and financial arrangements between ATCO and CNRL CNRL responded to the Commission s request on June 29, 2017, providing additional details on its expected use of $0/MWh offer prices with MKR1, how outages are scheduled for MKR1, the information shared between CNRL and ATCO, and the financial arrangements between CNRL and ATCO. 8 2 The Commission s authority to allow record sharing 9. Section 3(1) of the Fair, Efficient and Open Competition Regulation establishes that a market participant shall not share records that are not available to the public relating to any past, current or future price and quantity offer made to the power pool or for the provision of ancillary services. Section 3(2) establishes instances where records that are not available to the public may be shared. Section 3(3) allows the Commission to issue an order permitting the sharing of records, stating: (3) The Commission may, on application by a market participant that is otherwise prohibited from sharing records referred to under subsection (1), issue an order permitting the sharing of those records on any terms and conditions the Commission considers appropriate where the market participant establishes that (a) the records will not be used for any purpose that does not support the fair, efficient and openly competitive operation of the electricity market, including the conduct referred to in section 2, and (b) the sharing of the records is reasonably necessary for the market participant to carry out its business. 10. In addition to the considerations in Section 3, the Commission must also take into account market share offer control when considering an application to share records. Section 5(5) of the Fair, Efficient and Open Competition Regulation states that a market participant shall not hold offer control in excess of 30 per cent of the total maximum capability of generating units in Alberta. 5 Exhibit X0007, MSA Statement of Intent to Participate, May 25, Order D : Preferential Sharing of Records CNRL ATCO Muskeg Order, Proceeding 22669, Application A001, May 31, Exhibit X0008, AUC Information Request to CNRL round 1, June 15, Exhibit X0009, CNRL Response to IR Round 1, June 29, Decision D (July 21, 2017)

7 Application for an Order Permitting the Sharing of Records Not Available to the Public Between and ATCO Power Canada Ltd. 11. The Commission is also cognizant of the requirement in Section 6 of the Electric Utilities Act that [m]arket participants are to conduct themselves in a manner that supports the fair, efficient and openly competitive operation of the market. 3 Views of the parties 3.1 Is the proposed sharing of records reasonably necessary? 12. CNRL provided a representation from a senior officer in its application that stated the sharing of preferential records described in the application is reasonably necessary for CNRL to carry on its business obligations as joint operator and preferred customer of MKR CNRL has entered into a contractual agreement with ATCO, which, among other things, involves the joint operation of MKR1 by both CNRL and ATCO. Both CNRL and ATCO have on-site personnel that are responsible for the operation of the cogeneration facilities and, hence, require access to operational controls and to dispatch instructions from the Alberta Electric System Operator resulting from the price and quantity pair offers made to the power pool for MKR1 or offers made for the provision of ancillary services. CNRL submitted that all operating information pertaining to MKR1 is subject to shared access with ATCO, and information relating to preferential records is mutually exchanged between CNRL and ATCO as required for the operation of MKR Fair, efficient and openly competitive operation of the market 14. CNRL confirmed that the total market share offer control represented by it and all associates is less than the offer control limit of 30 per cent set out in Section 5(5) of the Fair, Efficient and Open Competition Regulation. CNRL further submitted that ATCO also does not exceed the 30 per cent limit A senior officer of CNRL provided a written representation that indicated the records subject to preferential information sharing will not be used for any purpose that does not support the fair, efficient and openly competitive operation of the Alberta electricity market, including but not limited to the conduct referred to in Section 2 of the Fair, Efficient and Open Competition Regulation. The representation also stated that CNRL has in place a Code of Conduct to ensure internal compliance with the information sharing requirements under the Fair, Efficient and Open Competition Regulation CNRL filed a similar representation from a senior officer at ATCO to confirm that any records shared with ATCO will not be used for any purpose that does not support the fair, efficient and openly competitive operation of the electricity market. The representation also stated that ATCO has in place a Code of Conduct to ensure internal compliance with the information sharing requirements under the Fair, Efficient and Open Competition Regulation Exhibit X0005, Revised preferential sharing of records application, registered May 24, 2017, PDF page Exhibit X0005, Revised preferential sharing of records application, registered May 24, 2017, PDF page Exhibit X0005, Revised preferential sharing of records application, registered May 24, 2017, PDF page Exhibit X0005, Revised preferential sharing of records application, registered May 24, 2017, PDF page 16. Decision D (July 21, 2017) 3

8 Application for an Order Permitting the Sharing of Records Not Available to the Public Between and ATCO Power Canada Ltd. 4 Commission findings 17. The Commission finds that CNRL has demonstrated that the sharing of records is reasonably necessary for it to carry out its business because CNRL lacks the necessary experience and capability to perform real time operator requirements at MKR1 for a generating asset under the ISO rules. 18. CNRL and ATCO have internal compliance programs that require, amongst other things, all employees to comply with laws, rules and regulations, including the Fair, Efficient and Open Competition Regulation regarding the sharing of records, and how such records can and cannot be used. The Commission understands that the employees of each company are required to read and comply with these policies. 19. CNRL has confirmed that a $0/MWh offer block will be used exclusively for MKR1, and that ATCO segregates its outage scheduling function within a different group inside of ATCO to ensure functional segregation from ATCO Calgary s Marketing staff, and that ATCO does not have contractual rights to request additional or less electricity from MKR1 for the power pool and / or ancillary services markets. 20. All offer control figures for all entities involved (both before and after any approval to share records) are less than the offer control limit of 30 per cent set out in Section 5(5) of the Fair, Efficient and Open Competition Regulation. 21. CNRL and ATCO have each made representations that the preferential records relating to MKR1 will not be used for any purpose that does not support the fair, efficient and openly competitive operation of the Alberta electricity market. 22. Based on these measures, the Commission finds that the MKR1 records shared between CNRL and ATCO will not be used for any purpose that does not support the fair, efficient and openly competitive operation of the electricity market, including conduct referred to in Section 2 of the Fair, Efficient and Open Competition Regulation. 23. Having regard to the foregoing, the Commission is prepared to issue an order allowing CNRL to share records not available to the public, with ATCO, subject to the following terms and conditions: a) The order only applies to the sharing of information between CNRL and ATCO relating to price, quantity, and availability information for the 202-MW MKR1 unit with respect to offers in the Alberta electricity and ancillary services markets. b) CNRL must notify the Commission of the termination of the commercial arrangements between CNRL and ATCO within 30 days of the termination of such commercial arrangements. c) CNRL must notify the Commission of any material changes to the information and continued applicability of any representations contained within its application that may affect the compliance of CNRL or ATCO with the Fair, Efficient and Open Competition Regulation within 30 days of the material changes. 4 Decision D (July 21, 2017)

9 Application for an Order Permitting the Sharing of Records Not Available to the Public Between and ATCO Power Canada Ltd. 24. The order shall be effective from the date of this decision until the earlier of the termination of contractual arrangements between CNRL and ATCO regarding MKR1 or June 1, Decision 25. Pursuant to the provisions of Section 3 of the Fair, Efficient and Open Competition Regulation, the Commission grants the application for the sharing of records set out in the following order granted to CNRL and ATCO, which is a separate disposition in this proceeding: Preferential Sharing of Records CNRL ATCO Muskeg Order D Dated on July 21, Alberta Utilities Commission (original signed by) Henry van Egteren Panel Chair (original signed by) Bill Lyttle Commission Member (original signed by) Tracee Collins Commission Member Decision D (July 21, 2017) 5

TransCanada Energy Ltd.

TransCanada Energy Ltd. Decision 22302-D01-2017 Request for Permitting the Sharing of Records Not Available to the Public Between and Pembina Pipeline Corporation May 26, 2017 Alberta Utilities Commission Decision 22302-D01-2017

More information

The University of Calgary

The University of Calgary Decision 23147-D01-2018 Application for an Order Permitting the Sharing of Records Not Available to the Public Between the University of Calgary and URICA Energy Real Time Ltd. January 30, 2018 Alberta

More information

Decision D Balancing Pool

Decision D Balancing Pool Decision 22184-D10-2017 Application for an Order Permitting the Sharing of Records Not Available to the Public Between the, TransAlta Generation Partnership, and Capital Power Generation Services Inc.

More information

Shell Canada Limited and Canadian Natural Resources Limited

Shell Canada Limited and Canadian Natural Resources Limited Decision 22614-D01-2017 Albian Oil Sands Industrial Complex and June 28, 2017 Alberta Utilities Commission Decision 22614-D01-2017 Albian Oil Sands Industrial Complex and Proceeding 22614 Applications

More information

The University of Calgary

The University of Calgary Decision 2014-365 Preferential Sharing of Records between the University of Calgary and URICA Energy Real Time Ltd. December 19, 2014 The Alberta Utilities Commission Decision 2014-365: Preferential Sharing

More information

ENMAX Power Corporation

ENMAX Power Corporation Decision 22756-D01-2017 Tax Agreement with The City of Calgary September 7, 2017 Alberta Utilities Commission Decision 22756-D01-2017 Tax Agreement with The City of Calgary Proceeding 22756 September 7,

More information

Alberta Electric System Operator

Alberta Electric System Operator Decision 23065-D01-2017 Alberta Electric System Operator 2018 Independent System Operator Tariff Update November 28, 2017 Alberta Utilities Commission Decision 23065-D01-2017 Alberta Electric System Operator

More information

Decision D Alberta PowerLine L.P. Tariff Application. January 23, 2018

Decision D Alberta PowerLine L.P. Tariff Application. January 23, 2018 Decision 23161-D01-2018 Alberta PowerLine L.P. Tariff Application January 23, 2018 Alberta Utilities Commission Decision 23161-D01-2018 Alberta PowerLine L.P. Tariff Application Proceeding 23161 January

More information

Decision D ATCO Electric Ltd. Amounts to be Paid Into and Out of Balancing Pool for Chinchaga Power Plant Sale

Decision D ATCO Electric Ltd. Amounts to be Paid Into and Out of Balancing Pool for Chinchaga Power Plant Sale Decision 21833-D01-2016 Amounts to be Paid Into and Out of Balancing Pool for Chinchaga Power Plant Sale December 20, 2016 Alberta Utilities Commission Decision 21833-D01-2016 Proceeding 21833 December

More information

Decision D ATCO Electric Ltd. Compliance Filing to Decision D Capital Tracker True-Up

Decision D ATCO Electric Ltd. Compliance Filing to Decision D Capital Tracker True-Up Decision 23454-D01-2018 ATCO Electric Ltd. Compliance Filing to Decision 22788-D01-2018 2016 Capital Tracker True-Up May 4, 2018 Alberta Utilities Commission Decision 23454-D01-2018 ATCO Electric Ltd.

More information

Daishowa-Marubeni International Ltd.

Daishowa-Marubeni International Ltd. Decision 2011-299 25-MW Condensing Steam Turbine Generator July 8, 2011 The Alberta Utilities Commission Decision 2011-299: 25-MW Condensing Steam Turbine Generator Application No. 1606747 Proceeding ID

More information

ENMAX Power Corporation Distribution and Transmission Deferral Account Reconciliation

ENMAX Power Corporation Distribution and Transmission Deferral Account Reconciliation Decision 23108-D01-2018 2014 Distribution and 2014-2015 Transmission Deferral Account Reconciliation February 27, 2018 Alberta Utilities Commission Decision 23108-D01-2018 2014 Distribution and 2014-2015

More information

Brion Energy Corporation

Brion Energy Corporation Decision 21524-D01-2016 MacKay River Commercial Project Ownership Change for the Sales Oil Pipeline Lease Automated Custody Transfer Site June 14, 2016 Alberta Utilities Commission Decision 21524-D01-2016

More information

Mayerthorpe and District Rural Electrification Association Ltd.

Mayerthorpe and District Rural Electrification Association Ltd. Decision 22692-D01-2018 Mayerthorpe and District Rural Electrification Association Ltd. Varied Code of Conduct Regulation Compliance Plan January 31, 2018 Alberta Utilities Commission Decision 22692-D01-2018

More information

EPCOR Distribution & Transmission Inc.

EPCOR Distribution & Transmission Inc. Decision 22603-D01-2017 June 23, 2017 Alberta Utilities Commission Decision 22603-D01-2017 Proceeding 22603 June 23, 2017 Published by the: Alberta Utilities Commission Fifth Avenue Place, Fourth Floor,

More information

Decision ATCO Electric Ltd. February 1, 2013 Interim Tariff. January 18, 2013

Decision ATCO Electric Ltd. February 1, 2013 Interim Tariff. January 18, 2013 Decision 2013-015 February 1, 2013 Interim Tariff January 18, 2013 The Alberta Utilities Commission Decision 2013-015: February 1, 2013 Interim Tariff Application No. 1609127 Proceeding ID No. 2305 January

More information

Decision D FortisAlberta Inc. Light-Emitting Diode Lighting Conversion Maintenance Multiplier for the City of St.

Decision D FortisAlberta Inc. Light-Emitting Diode Lighting Conversion Maintenance Multiplier for the City of St. Decision 21754-D01-2016 Light-Emitting Diode Lighting Conversion Maintenance Multiplier for the City of St. Albert August 11, 2016 Alberta Utilities Commission Decision 21754-D01-2016 Light-Emitting Diode

More information

ATCO Electric and ATCO Pipelines. Application for ATCO Electric and ATCO Pipelines License Fees

ATCO Electric and ATCO Pipelines. Application for ATCO Electric and ATCO Pipelines License Fees Decision 21571-D01-2016 and ATCO Pipelines 2015-2016 License Fees August 17, 2016 Alberta Utilities Commission Decision 21571-D01-2016 and ATCO Pipelines 2015-2016 License Fees Proceeding 21571 August

More information

ENMAX Energy Corporation

ENMAX Energy Corporation Decision 23006-D01-2018 Regulated Rate Option - Energy Price Setting Plan Monthly Filings for Acknowledgment 2017 Quarter 3 February 7, 2018 Alberta Utilities Commission Decision 23006-D01-2018: Regulated

More information

Canadian Natural Resources Limited

Canadian Natural Resources Limited Decision 21306-D01-2016 Determination of Compensation for 9L66/9L32 Transmission Line Relocation August 16, 2016 Alberta Utilities Commission Decision 21306-D01-2016 Determination of Compensation for 9L66/9L32

More information

Decision D Generic Cost of Capital. Costs Award

Decision D Generic Cost of Capital. Costs Award Decision 21856-D01-2016 Costs Award December 2, 2016 Alberta Utilities Commission Decision 21856-D01-2016 Costs Award Proceeding 21856 December 2, 2016 Published by Alberta Utilities Commission Fifth Avenue

More information

AltaLink Investment Management Ltd. And SNC Lavalin Transmission Ltd. et al.

AltaLink Investment Management Ltd. And SNC Lavalin Transmission Ltd. et al. Decision 3529-D01-2015 AltaLink Investment Management Ltd. And SNC Lavalin Transmission Ltd. et al. Proposed Sale of AltaLink, L.P Transmission Assets and Business to Mid-American (Alberta) Canada Costs

More information

Report to the Minister. For the Year Ending December 31, March 20, 2015

Report to the Minister. For the Year Ending December 31, March 20, 2015 Report to the Minister For the Year Ending December 31, 2014 March 20, 2015 Market Surveillance Administrator 403.705.3181 #500, 400 5th Avenue S.W., Calgary AB T2P 0L6 www.albertamsa.ca Table of Contents

More information

Langdon Waterworks Limited

Langdon Waterworks Limited Decision 20372-D01-2015 May 14, 2015 Alberta Utilities Commission Decision 20372-D01-2015 Proceeding 20372 May 14, 2015 Published by the: Alberta Utilities Commission Fifth Avenue Place, Fourth Floor,

More information

FAIR, EFFICIENT AND OPEN COMPETITION REGULATION

FAIR, EFFICIENT AND OPEN COMPETITION REGULATION Province of Alberta ALBERTA UTILITIES COMMISSION ACT ELECTRIC UTILITIES ACT FAIR, EFFICIENT AND OPEN COMPETITION REGULATION Alberta Regulation 159/2009 Extract Published by Alberta Queen s Printer Alberta

More information

Mackenzie Rural Electrification Association Ltd.

Mackenzie Rural Electrification Association Ltd. Decision 21983-D01-2016 Varied Code of Conduct Regulation Compliance Plan December 14, 2016 Alberta Utilities Commission Decision 21983-D01-2016 Varied Code of Conduct Regulation Compliance Plan Proceeding

More information

EPCOR Distribution & Transmission Inc.

EPCOR Distribution & Transmission Inc. Decision 21229-D01-2016 EPCOR Distribution & Transmission Inc. 2015-2017 Transmission Facility Owner Tariff and 2013 Generic Cost of Capital Compliance Application April 15, 2016 Alberta Utilities Commission

More information

AltaGas Utilities Inc.

AltaGas Utilities Inc. Decision 23898-D01-2018 2019 Annual Performance-Based Regulation Rate Adjustment Filing December 20, 2018 Alberta Utilities Commission Decision 23898-D01-2018 2019 Annual Performance-Based Regulation Rate

More information

Acciona Wind Energy Canada, Inc.

Acciona Wind Energy Canada, Inc. Decision 2013-439 Acciona Wind Energy Canada, Inc. New Dayton Wind Power Project Facility & Substation Costs Award December 11, 2013 The Alberta Utilities Commission Decision 2013-439: Acciona Wind Energy

More information

West Wetaskiwin Rural Electrification Association Ltd.

West Wetaskiwin Rural Electrification Association Ltd. Decision 22067-D01-2016 West Wetaskiwin Rural Electrification Association Ltd. Varied Code of Conduct Regulation Compliance Plan December 21, 2016 Alberta Utilities Commission Decision 22067-D01-2016 West

More information

AltaGas Utilities Inc.

AltaGas Utilities Inc. Decision 2013-465 2014 Annual PBR Rate Adjustment Filing December 23, 2013 The Alberta Utilities Commission Decision 2013-465: 2014 Annual PBR Rate Adjustment Filing Application No. 1609923 Proceeding

More information

EPCOR Energy Alberta GP Inc.

EPCOR Energy Alberta GP Inc. Decision 20633-D01-2016 EPCOR Energy Alberta GP Inc. 2016-2017 Regulated Rate Tariff Application December 20, 2016 Alberta Utilities Commission Decision 20633-D01-2016 EPCOR Energy Alberta GP Inc. 2016-2017

More information

ATCO Electric Ltd. Stage 2 Review of Decision D ATCO Electric Ltd Transmission General Tariff Application

ATCO Electric Ltd. Stage 2 Review of Decision D ATCO Electric Ltd Transmission General Tariff Application Decision 22483-D01-2017 Stage 2 Review of Decision 20272-D01-2016 2015-2017 Transmission General Tariff Application December 6, 2017 Alberta Utilities Commission Decision 22483-D01-2017 Stage 2 Review

More information

ENMAX Power Corporation

ENMAX Power Corporation Decision 22238-D01-2017 ENMAX Power Corporation 2016-2017 Transmission General Tariff Application December 4, 2017 Alberta Utilities Commission Decision 22238-D01-2017 ENMAX Power Corporation 2016-2017

More information

Decision ATCO Electric Ltd. Bonnyville to Bourque Transmission Line Project. Costs Award. October 9, 2013

Decision ATCO Electric Ltd. Bonnyville to Bourque Transmission Line Project. Costs Award. October 9, 2013 Decision 2013-374 Bonnyville to Bourque Transmission Line Project Costs Award October 9, 2013 The Alberta Utilities Commission Decision 2013-374: Bonnyville to Bourque Transmission Line Project Costs Award

More information

Decision D FortisAlberta Inc PBR Capital Tracker True-Up and PBR Capital Tracker Forecast

Decision D FortisAlberta Inc PBR Capital Tracker True-Up and PBR Capital Tracker Forecast Decision 20497-D01-2016 FortisAlberta Inc. 2014 PBR Capital Tracker True-Up and 2016-2017 PBR Capital Tracker Forecast February 20, 2016 Alberta Utilities Commission Decision 20497-D01-2016 FortisAlberta

More information

FOR IMMEDIATE RELEASE

FOR IMMEDIATE RELEASE February 21, 2017 MEDIA RELEASE FOR IMMEDIATE RELEASE Connacher Reports Year-End 2016 Reserves Calgary, Alberta Connacher Oil and Gas Limited ( Connacher or the Company ) announces its year-end reserves

More information

Decision D Rebasing for the PBR Plans for Alberta Electric and Gas Distribution Utilities. First Compliance Proceeding

Decision D Rebasing for the PBR Plans for Alberta Electric and Gas Distribution Utilities. First Compliance Proceeding Decision 22394-D01-2018 Rebasing for the 2018-2022 PBR Plans for February 5, 2018 Alberta Utilities Commission Decision 22394-D01-2018 Rebasing for the 2018-2022 PBR Plans for Proceeding 22394 February

More information

ATCO Gas and Pipelines Ltd. (South)

ATCO Gas and Pipelines Ltd. (South) Decision 2010-170 New Construction Replacement of ATCO Pipelines Existing Southern Extension Pipeline From North of Lacombe to East of Gwynne April 15, 2010 ALBERTA UTILITIES COMMISSION Decision 2010-170:

More information

ATCO Gas and Pipelines Ltd. (South)

ATCO Gas and Pipelines Ltd. (South) Decision 22634-D01-2017 Southwest Calgary Connector Pipeline Project August 9, 2017 Alberta Utilities Commission Decision 22634-D01-2017 Southwest Calgary Connector Pipeline Project Proceeding 22634 Application

More information

Kneehill Rural Electrification Association Ltd.

Kneehill Rural Electrification Association Ltd. Decision 23420-D01-2018 Kneehill Rural Electrification Association Ltd. Varied Code of Conduct Regulation Compliance Plan April 23, 2018 Alberta Utilities Commission Decision 23420-D01-2018 Kneehill Rural

More information

FortisAlberta Inc. Sale and Transfer of the Municipality of Crowsnest Pass Electric Distribution Assets

FortisAlberta Inc. Sale and Transfer of the Municipality of Crowsnest Pass Electric Distribution Assets Decision 21785-D01-2018 Sale and Transfer of the Electric Distribution Assets June 5, 2018 Alberta Utilities Commission Decision 21785-D01-2018 Sale and Transfer of the Electric Distribution System Assets

More information

Investigation into the Use of Concessionary Government Funds by Competitive Affiliates of ENMAX Power Corporation

Investigation into the Use of Concessionary Government Funds by Competitive Affiliates of ENMAX Power Corporation Investigation into the Use of Concessionary Government Funds by Competitive Affiliates of ENMAX Power Corporation November 9, 2010 Market Surveillance Administrator 403.705.3181 #500, 400 5th Avenue S.W.,

More information

Decision D FortisAlberta Inc. Light-Emitting Diode (LED) Lighting Conversion Maintenance Multiplier Filing for 30 Customers in 2018

Decision D FortisAlberta Inc. Light-Emitting Diode (LED) Lighting Conversion Maintenance Multiplier Filing for 30 Customers in 2018 Decision 23730-D01-2018 Light-Emitting Diode (LED) Lighting Conversion Maintenance Multiplier Filing for 30 Customers in 2018 September 7, 2018 Alberta Utilities Commission Decision 23730-D01-2018 Light-Emitting

More information

ATCO Gas and Pipelines Ltd. (South)

ATCO Gas and Pipelines Ltd. (South) Decision 3421-D01-2015 Northeast Calgary Connector Pipeline January 16, 2015 The Alberta Utilities Commission Decision 3421-D01-2015: Northeast Calgary Connector Pipeline Application 1610854 Proceeding

More information

Decision CU Water Limited. Disposition of Assets. April 30, 2010

Decision CU Water Limited. Disposition of Assets. April 30, 2010 Decision 2010-192 Disposition of Assets April 30, 2010 ALBERTA UTILITIES COMMISSION Decision 2010-192: Disposition of Assets Application No. 1606042 Proceeding ID. 569 April 30, 2010 Published by Alberta

More information

Decision The ATCO Utilities. Corporate Costs. March 21, 2013

Decision The ATCO Utilities. Corporate Costs. March 21, 2013 Decision 2013-111 Corporate Costs March 21, 2013 The Alberta Utilities Commission Decision 2013-111: Corporate Costs Application No. 1608510 Proceeding ID No. 1920 March 21, 2013 Published by The Alberta

More information

AltaGas Utilities Inc.

AltaGas Utilities Inc. Decision 21822-D01-2016 AltaGas Utilities Inc. 2016-2017 Unaccounted-For Gas Rider E and Rider H September 1, 2016 Alberta Utilities Commission Decision 21822-D01-2016 AltaGas Utilities Inc. 2016-2017

More information

Report to the Minister March 1, 2011

Report to the Minister March 1, 2011 March 1, 2011 Market Surveillance Administrator 403.705.3181 #500, 400 5th Avenue S.W., Calgary AB T2P 0L6 www.albertamsa.ca March 1, 2011 1 Table of Contents 1 Introduction... 3 2 Offer Behaviour... 3

More information

Alberta Electric System Operator 2017 ISO Tariff Update

Alberta Electric System Operator 2017 ISO Tariff Update Alberta Electric System Operator 2017 ISO Tariff Update Date: October 20, 2016 Prepared by: Alberta Electric System Operator Prepared for: Alberta Utilities Commission Classification: Public Table of Contents

More information

Compliance Review February 9, 2012

Compliance Review February 9, 2012 February 9, 2012 Market Surveillance Administrator 403.705.3181 #500, 400 5th Avenue S.W., Calgary AB T2P 0L6 www.albertamsa.ca The Market Surveillance Administrator is an independent enforcement agency

More information

Decision D Performance-Based Regulation Plans for Alberta Electric and Gas Distribution Utilities.

Decision D Performance-Based Regulation Plans for Alberta Electric and Gas Distribution Utilities. Decision 22082-D01-2017 2018-2022 Performance-Based Regulation Plans for Alberta Electric and Gas Distribution Utilities February 6, 2017 Alberta Utilities Commission Decision 22082-D01-2017 2018-2022

More information

AltaLink Management Ltd.

AltaLink Management Ltd. Decision 21368-D01-2016 Advance Funding Request from the Cooking Lake Opposition Group Advance Funding Award March 14, 2016 Alberta Utilities Commission Decision 21368-D01-2016: Advance Funding Request

More information

AltaLink Management Ltd.

AltaLink Management Ltd. Decision 22025-D03-2017 Red Deer Area Transmission Development Amendment Application June 8, 2017 Decision 22025-D03-2017 Red Deer Area Transmission Development Amendment Application Proceeding 22025 Applications

More information

AltaLink Management Ltd.

AltaLink Management Ltd. Decision 21054-D01-2016 2013-2014 General Tariff Application (Proceeding 2044-Reopened for Midgard Audit) March 7, 2016 Alberta Utilities Commission Decision 21054-D01-2016: Proceeding 21054 March 7,

More information

AltaLink Management Ltd. & EPCOR Distribution & Transmission Inc.

AltaLink Management Ltd. & EPCOR Distribution & Transmission Inc. Decision 2013-280 AltaLink Management Ltd. & EPCOR Distribution & Transmission Inc. Heartland Transmission Project Amendment Structure T176 Repositioning Costs Award July 29, 2013 The Alberta Utilities

More information

Decision Wind Power Inc. Request to Transfer Power Plant Approval No. U November 26, 2008

Decision Wind Power Inc. Request to Transfer Power Plant Approval No. U November 26, 2008 Decision 2008-121 Wind Power Inc. Request to Transfer Power Plant Approval No. U2007-74 November 26, 2008 ALBERTA UTILITIES COMMISSION Decision 2008-121: Wind Power Inc. Request to Transfer Power Plant

More information

FOR IMMEDIATE RELEASE

FOR IMMEDIATE RELEASE April 24, 2018 MEDIA RELEASE FOR IMMEDIATE RELEASE Connacher Reports Year-End 2017 Reserves Calgary, Alberta Connacher Oil and Gas Limited ( Connacher or the Company ) announces its year-end reserves as

More information

Decision ATCO Utilities. Corporate Cost Allocation Methodology. September 20, 2010

Decision ATCO Utilities. Corporate Cost Allocation Methodology. September 20, 2010 Decision 2010-447 Corporate Cost Allocation Methodology September 20, 2010 ALBERTA UTILITIES COMMISSION Decision 2010-447: Corporate Cost Allocation Methodology Application No. 1605473 Proceeding ID. 306

More information

Condensed Interim Financial Statements and Review. Balancing Pool. For the three months ended March 31, 2018 (Unaudited)

Condensed Interim Financial Statements and Review. Balancing Pool. For the three months ended March 31, 2018 (Unaudited) Condensed Interim Financial Statements and Review Balancing Pool For the three months ended March 31, 2018 (Unaudited) NOTICE OF NO AUDITOR S REVIEW OF INTERIM FINANCIAL STATEMENTS The accompanying unaudited

More information

Alberta Electric System Operator, AltaLink Management Ltd. and ENMAX Power Corporation. Foothills Area Transmission Development

Alberta Electric System Operator, AltaLink Management Ltd. and ENMAX Power Corporation. Foothills Area Transmission Development Decision 2013-087 Alberta Electric System Operator, AltaLink Management Ltd. and ENMAX Power Corporation Foothills Area Transmission Development March 12, 2013 The Alberta Utilities Commission Decision

More information

Milner Power Inc. Complaint by Milner Power Inc. Regarding the ISO Transmission Loss Factor Rule and Loss Factor Methodology.

Milner Power Inc. Complaint by Milner Power Inc. Regarding the ISO Transmission Loss Factor Rule and Loss Factor Methodology. Decision 2012-104 Complaint by Regarding the ISO Transmission Loss Factor Rule and Loss Factor Methodology April 16, 2012 The Alberta Utilities Commission Decision 2012-104: Complaint by Regarding the

More information

Consumers Coalition of Alberta

Consumers Coalition of Alberta Decision 22157-D01-2017 Decision on Preliminary Question AltaLink Management Ltd. 2012-2013 Deferral Account Reconciliation Costs Award February 15, 2017 Alberta Utilities Commission Decision 22157-D01-2017

More information

Decision D FortisAlberta Inc Performance-Based Regulation Capital Tracker True-Up. January 11, 2018

Decision D FortisAlberta Inc Performance-Based Regulation Capital Tracker True-Up. January 11, 2018 Decision 22741-D01-2018 FortisAlberta Inc. 2016 Performance-Based Regulation Capital Tracker True-Up January 11, 2018 Alberta Utilities Commission Decision 22741-D01-2018 FortisAlberta Inc. 2016 Performance-Based

More information

CIBC CALGARY FIXED INCOME CONFERENCE. April 11, 2018

CIBC CALGARY FIXED INCOME CONFERENCE. April 11, 2018 CIBC CALGARY FIXED INCOME CONFERENCE April 11, 2018 LEGAL DISCLAIMER Statements made by representatives for ATCO Ltd. and Canadian Utilities Limited and information provided in this presentation may be

More information

Anterra Energy Inc. Condensed Interim Financial Statements FOR THE THREE AND NINE MONTHS ENDED September 30, 2015

Anterra Energy Inc. Condensed Interim Financial Statements FOR THE THREE AND NINE MONTHS ENDED September 30, 2015 Anterra Energy Inc. Condensed Interim Financial Statements FOR THE THREE AND NINE MONTHS ENDED September 30, 2015 NOTICE OF NO AUDITOR REVIEW OF INTERIM FINANCIAL STATEMENTS Under National Instrument 51-102,

More information

NaturEner Energy Canada Inc.

NaturEner Energy Canada Inc. Decision 2009-174 Review and Variance of Alberta Utilities Commission Decision 2009-042 (October 22, 2009) ALBERTA UTILITIES COMMISSION Decision 2009-174, Review and Variance of Alberta Utilities Commission

More information

Alberta Utilities Commission

Alberta Utilities Commission Alberta Utilities Commission In the Matter of the Need for the Kirby North Central Processing Facility Connection And in the matter of the Electric Utilities Act, S.A. 2003, c. E-5.1, the Alberta Utilities

More information

Alberta Utilities Commission

Alberta Utilities Commission Decision 22091-D01-2017 Commission-Initiated Proceeding to Review the Terms and November 9, 2017 Decision 22091-D01-2017 Commission-Initiated Proceeding to Review the Terms and Proceeding 22091 Application

More information

ATCO Gas and Pipelines Ltd.

ATCO Gas and Pipelines Ltd. Decision 2738-D01-2016 Z Factor Application for Recovery of 2013 Southern Alberta Flood Costs March 16, 2016 Alberta Utilities Commission Decision 2738-D01-2016 Z Factor Application for Recovery of 2013

More information

Canadian Natural Resources Limited

Canadian Natural Resources Limited Decision 2009-024 Application for Pool Delineation and Gas Shut-in Athabasca Wabiskaw-McMurray February 24, 2009 ENERGY RESOURCES CONSERVATION BOARD Decision 2009-024:, Application for Pool Delineation

More information

ATCO Pipelines ATCO Gas and Pipelines Ltd. CU Inc. Canadian Utilities Limited

ATCO Pipelines ATCO Gas and Pipelines Ltd. CU Inc. Canadian Utilities Limited Decision 2012-068 Disposition of Surplus Salt Cavern Assets in the Fort Saskatchewan Area March 16, 2012 The Alberta Utilities Commission Decision 2012-068:,,, Disposition of Surplus Salt Cavern Assets

More information

Alberta Energy-Capacity Market Framework Engagement November 2017

Alberta Energy-Capacity Market Framework Engagement November 2017 Questions for discussion The engagement is seeking feedback on the six questions outlined in the table below. Please provide your input on these questions in Table 1 on the next three pages. Please submit

More information

Decision D FortisAlberta Inc.

Decision D FortisAlberta Inc. Decision 23063-D01-2018 Light-Emitting Diode Lighting Conversion Maintenance Multiplier Filing January 30, 2018 Alberta Utilities Commission Decision 23063-D01-2018 Light-Emitting Diode Lighting Conversion

More information

Capital Power Corporation. Halkirk 2 Wind Power Project

Capital Power Corporation. Halkirk 2 Wind Power Project Decision 23255-D01-2018 Capital Power Corporation Halkirk 2 Wind Power Project July 9, 2018 Alberta Utilities Commission Decision 23255-D01-2018 Capital Power Corporation Halkirk 2 Wind Power Project Proceeding

More information

Decision Town of Innisfail. Franchise Agreement with ATCO Gas and Pipelines Ltd. and Amendment to Rider A.

Decision Town of Innisfail. Franchise Agreement with ATCO Gas and Pipelines Ltd. and Amendment to Rider A. Decision 2012-300 Franchise Agreement with ATCO Gas and Pipelines Ltd. and Amendment to Rider A November 9, 2012 The Alberta Utilities Commission Decision 2012-300: Franchise Agreement with ATCO Gas and

More information

City of Edmonton. Natural Gas Franchise Agreement with ATCO Gas and Pipelines Ltd. August 31, Decision

City of Edmonton. Natural Gas Franchise Agreement with ATCO Gas and Pipelines Ltd. August 31, Decision Alberta Energy and Utilities Board Decision 2004-072 Natural Gas Franchise Agreement with ATCO Gas and Pipelines Ltd. August 31, 2004 ALBERTA ENERGY AND UTILITIES BOARD Decision 2004-072: Natural Gas Franchise

More information

Report to the Minister

Report to the Minister For the Year Ending December 31, 2017 April 19, 2018 Taking action to promote effective competition and a culture of compliance and accountability in Albertaʹs electricity and retail natural gas markets

More information

Livingstone Landowners Guild

Livingstone Landowners Guild Decision 20846-D01-2016 Livingstone Landowners Guild Application for Review of Decision 2009-126 Needs Identification Document Application Southern Alberta Transmission System Reinforcement as amended

More information

Canadian Natural Resources Limited

Canadian Natural Resources Limited Decision 2003-081 Lloydminster Field November 4, 2003 ALBERTA ENERGY AND UTILITIES BOARD Decision 2003-081: Application for Special Well Spacing, Lloydminster Field November 4, 2003 Published by Alberta

More information

Sunshine Oilsands Ltd. and Total E&P Canada Ltd.

Sunshine Oilsands Ltd. and Total E&P Canada Ltd. Decision 2009-061 Sunshine Oilsands Ltd. and Total E&P Canada Ltd. Applications for Interim Shut-in of Gas Liege Field Athabasca Oil Sands Area October 15, 2009 ENERGY RESOURCES CONSERVATION BOARD Decision

More information

Compliance Review 2017

Compliance Review 2017 February 27, 2018 Taking action to promote effective competition and a culture of compliance and accountability in Albertaʹs electricity and retail natural gas markets www.albertamsa.ca Table of Contents

More information

AltaLink Management Ltd. ATCO Electric Ltd.

AltaLink Management Ltd. ATCO Electric Ltd. Decision 2012-139 May 22, 2012 The Alberta Utilities Commission Decision 2012-139: and Application Nos. 1607971 and 1608183 Proceeding ID No. 1623 May 22, 2012 Published by The Alberta Utilities Commission

More information

LETTER DECISION. File OF-Tolls-Group1-T November All parties to RH

LETTER DECISION. File OF-Tolls-Group1-T November All parties to RH File OF-Tolls-Group1-T211-2013-05 01 28 November 2014 LETTER DECISION To: All parties to RH-001-2014 TransCanada PipeLines Limited (TransCanada) Application for Approval of 2015 to 2030 Tolls (application)

More information

Q INTERIM REPORT

Q INTERIM REPORT ENMAX CORPORATION Q1 2018 INTERIM REPORT CAUTION TO READER This document contains statements about future events and financial and operating results of ENMAX Corporation and its subsidiaries (ENMAX or

More information

Decision D ATCO Electric Ltd. Micro-generation Determination. September 19, 2018

Decision D ATCO Electric Ltd. Micro-generation Determination. September 19, 2018 Decision 23412-D01-2018 Micro-generation Determination September 19, 2018 Alberta Utilities Commission Decision 23412-D01-2018 Micro-generation Determination Proceeding 23412 Application 23412-A001 September

More information

Decision D EQUS REA LTD.

Decision D EQUS REA LTD. Decision 22293-D01-2017 Application for Orders Amending the Terms and Conditions of Service and Rate Schedules of FortisAlberta Inc. in Respect of Option M Distribution Generation Credit/Charge October

More information

Compliance Review 2016

Compliance Review 2016 February 22, 2017 Taking action to promote effective competition and a culture of compliance and accountability in Albertaʹs electricity and retail natural gas markets www.albertamsa.ca Table of Contents

More information

AltaLink Investment Management Ltd. and SNC Lavalin Transmission Ltd. et al.

AltaLink Investment Management Ltd. and SNC Lavalin Transmission Ltd. et al. Decision 2014-326 AltaLink Investment Management Ltd. and SNC Lavalin Transmission Ltd. et al. Proposed Sale of AltaLink, L.P. Transmission Assets and Business to MidAmerican (Alberta) Canada Holdings

More information

Langdon Waterworks Limited

Langdon Waterworks Limited Decision 2014-240 August 19, 2014 The Alberta Utilities Commission Decision 2014-240: Application No. 1610617 Proceeding No. 3258 August 19, 2014 Published by The Alberta Utilities Commission Fifth Avenue

More information

Connacher Announces Q Results

Connacher Announces Q Results May 29, 2018 MEDIA RELEASE FOR IMMEDIATE RELEASE Connacher Announces Q1 2018 Results Calgary, Alberta - Connacher Oil and Gas Limited ( Connacher or the Company ) announces its financial and operating

More information

Decision ATCO Gas General Rate Application Phase I Compliance Filing to Decision Part B.

Decision ATCO Gas General Rate Application Phase I Compliance Filing to Decision Part B. Decision 2006-083 2005-2007 General Rate Application Phase I Compliance Filing to Decision 2006-004 August 11, 2006 ALBERTA ENERGY AND UTILITIES BOARD Decision 2006-083: 2005-2007 General Rate Application

More information

AltaLink Management Ltd.

AltaLink Management Ltd. Decision 3524-D01-2016 AltaLink Management Ltd. 2015-2016 General Tariff Application May 9, 2016 Alberta Utilities Commission Decision 3524-D01-2016 AltaLink Management Ltd. 2015-2016 General Tariff Application

More information

ENMAX Corporation 2017 Q2 INTERIM REPORT CAUTION TO READER

ENMAX Corporation 2017 Q2 INTERIM REPORT CAUTION TO READER ENMAX Corporation 2017 Q2 INTERIM REPORT ENMAX Corporation CAUTION TO READER This document contains statements about future events and financial and operating results of ENMAX Corporation and its subsidiaries

More information

DIVIDEND REINVESTMENT AND SHARE PURCHASE PLAN

DIVIDEND REINVESTMENT AND SHARE PURCHASE PLAN Prospectus 22FEB200619140411 TRANSCANADA CORPORATION DIVIDEND REINVESTMENT AND SHARE PURCHASE PLAN TransCanada Corporation, by this Prospectus and under its Dividend Reinvestment and Share Purchase Plan

More information

Canadian Natural Resources Limited

Canadian Natural Resources Limited Alberta Energy and Utilities Board Energy Cost Order 2004-07 Canadian Natural Resources Limited Application for an Oil Sands Mine, Bitumen Extraction Plant, and Bitumen Upgrading Plant in the Fort McMurray

More information

ENMAX Energy Corporation

ENMAX Energy Corporation Decision 22054-D01-2017 Regulated Rate Option Tariff Terms and Conditions Amendment Application April 12, 2017 Alberta Utilities Commission Decision 22054-D01-2017 Regulated Rate Option Tariff Terms and

More information

Decision FortisAlberta Inc Phase II Distribution Tariff. January 27, 2014

Decision FortisAlberta Inc Phase II Distribution Tariff. January 27, 2014 Decision 2014-018 FortisAlberta Inc. 2012-2014 Phase II Distribution Tariff January 27, 2014 The Alberta Utilities Commission Decision 2014-018: FortisAlberta Inc. 2012-2014 Phase II Distribution Tariff

More information

TransCanada Pipeline Ventures Ltd. Suncor Energy Inc.

TransCanada Pipeline Ventures Ltd. Suncor Energy Inc. Decision 2009-065 Application to Have the Ventures Pipeline (Oil Sands Pipeline) May 20, 2009 ALBERTA UTILITIES COMMISSION Decision 2009-065: Application to Have the Ventures Pipeline (Oil Sands Pipeline)

More information