1 Decision D EPCOR Energy Alberta GP Inc Regulated Rate Tariff Application December 20, 2016

2 Alberta Utilities Commission Decision D EPCOR Energy Alberta GP Inc Regulated Rate Tariff Application Proceeding December 20, 2016 Published by the: Alberta Utilities Commission Fifth Avenue Place, Fourth Floor, 425 First Street S.W. Calgary, Alberta T2P 3L8 Telephone: Fax: Website:

3 Contents 1 Introduction Forecast revenue requirement and monthly non-energy charges Compliance with Commission directions Issues Corporate vacancy rate Salary escalations Operating costs Customer service costs Late payment charges Tax and deferral accounts Bad debt deferral Depreciation and return Weighted average cost of capital Interest during construction and allowance for funds used during construction Risk compensation Other matters Price schedules and terms and conditions Errors and omissions Order Appendix 1 Proceeding participants Appendix 2 Summary of Commission directions List of tables Table 1. Forecast non-energy RRT revenue requirements for 2016 and Table 2. Forecast monthly non-energy charges for 2016 and Table 3. Historical approved and actual non-union salary escalators... 9 Table 4. Variance between forecast and actual customer service costs Decision D (December 20, 2016) i

4

5 Alberta Utilities Commission Calgary, Alberta EPCOR Energy Alberta GP Inc. Decision D Regulated Rate Tariff Application Proceeding Introduction 1. On July 16, 2015, EPCOR Energy Alberta GP Inc. (EEA) filed an application with the Alberta Utilities Commission requesting approval of its non-energy regulated rate tariffs (RRT) for service provided by EEA to eligible customers in the EPCOR Distribution & Transmission Inc. (EDTI) and FortisAlberta Inc. (FAI) service territories, for the period from January 1, 2016 to December 31, 2017 (the test period or the test years). EEA also requested confidential treatment of Alberta Limited Partnership s, operating as ENCOR, customer site counts. EEA stated that the public release of this information would prejudice ENCOR s position in the competitive retail market by enabling competitors to gain insight into the effectiveness and potential future direction of ENCOR s marketing strategies. 2. On July 21, 2015, the Commission issued a notice of application. Any party who wished to intervene in the proceeding was requested to submit a statement of intent to participate (SIP) to the Commission by the participation closing deadline of August 7, The Commission received SIPs from the Consumers Coalition of Alberta (CCA) and the Office of the Utilities Consumer Advocate (UCA). 3. The CCA and the UCA requested that the Commission establish a process including written information requests (IRs), argument and reply argument. The CCA indicated that it would be able to determine whether or not it objected to the application after reviewing EEA s IR responses. The UCA indicated that it would be able to comment on the need for further process after reviewing EEA s IR responses. 4. On August 7, 2015, EEA filed a motion requesting approval to initiate a negotiated settlement process in respect of EEA s RRT application. 5. The Commission issued a letter on August 12, 2015, allowing parties the opportunity to comment on EEA s confidentiality request and motion to pursue a negotiated settlement by August 17, 2015, and allowing EEA to reply to those comments by August 21, Comments were received from the CCA and the UCA on August 17, EEA filed its reply comments on August 21, The CCA agreed that it is reasonable for the Commission to grant confidential treatment of ENCOR s site counts. 8. The UCA stated that it had concerns about the nature and quantum of confidentiality requests received by the Commission. The UCA further stated that EEA s request for confidential treatment ought to be denied because EEA had failed to demonstrate that exceptional circumstances exist to rebut the presumption in favour of the open-court principle in Commission proceedings. In particular, the UCA argued that EEA had failed to describe the nature of the information for which confidential treatment was sought with the specificity Decision D (December 20, 2016) 1

6 necessary to support its claim as to the harm that would result from public disclosure of the information. 9. EEA responded that it is obvious that ENCOR s site counts are commercially sensitive and confidential, and that the UCA s arguments to the contrary are without merit. EEA stated that the nature and quantum of confidentiality requests received by the Commission are not applicable to this proceeding as EEA has only made one confidentiality request of a limited nature. 10. On September 1, 2015, the Commission issued a ruling granting confidential treatment to certain portions of the document containing the ENCOR site counts and directing EEA to file a redacted version of the document on the public record of this proceeding. 11. The ruling also approved EEA s request to pursue a negotiated settlement process, after a round of IRs and IR responses, and directed EEA to provide an update on the status of negotiations no later than November 16, The deadline to file an update on the status of negotiations was subsequently extended to November 26, 2015, and later to December 4, EEA filed an update on December 4, 2015, indicating that parties had failed to reach a negotiated settlement. On January 6, 2016, EEA filed responses to a number of IRs asked by the UCA and the CCA during the negotiated settlement process. 12. On January 11, 2016, EEA submitted a supplementary filing outlining its proposed non-energy risk compensation for 2016 and There were a number of deadline extensions and process additions throughout the proceeding. The Commission maintained a written process to assess the application, which resulted in the schedule below: Process step Date IRs to EEA September 21, 2015 Information responses from EEA October 7, 2015 Commencement of negotiated settlement process October 15, 2016 Update on status of negotiated settlement process December 4, 2016 EEA to file information responses after negotiations January 6, 2016 EEA to file supplemental filing on risk compensation January 11, 2016 IRs to EEA on supplemental filing January 19, 2016 Information responses from EEA January 28, 2016 Intervener evidence March 4, 2016 IRs to interveners March 18, 2016 Information responses from interveners April 1, 2016 Rebuttal evidence April 12, 2016 Argument April 29, 2016 Reply argument May 13, The Commission considers that the close of record for this proceeding was May 13, Decision D (December 20, 2016)

7 15. On September 27, 2016, the Commission issued a letter notifying parties that the original panel for this proceeding had recused themselves upon becoming aware of institutional circumstances that they determined gave rise to reasonable apprehension of bias. A new panel was appointed to consider the record and make the determinations herein. 16. In reaching the determinations set out within this decision, the new panel has considered all relevant materials comprising the record of this proceeding, including the evidence, argument and reply argument. Accordingly, references in this decision to specific parts of the record are intended to assist the reader in understanding the Commission s reasoning relating to a particular matter and should not be taken as an indication that the Commission did not consider all relevant portions of the record with respect to that matter. 2 Forecast revenue requirement and monthly non-energy charges 17. EEA applied for approval of its non-energy RRT revenue requirement and rates for service to eligible customers in the EDTI service area and the FAI service area for the period from January 1, 2016 to December 31, The forecast non-energy RRT revenue requirements for the 2016 and 2017 test years, included in the application, are set out in Table 1 below: Table 1. Forecast non-energy RRT revenue requirements for 2016 and decision 2014 actual 2015 decision 2015 updated forecast 2016 forecast 2017 forecast $ million The forecast monthly non-energy charges, as set out in financial Schedule 5 of the application, are reproduced in the table below: Table 2. Forecast monthly non-energy charges for 2016 and 2017 Customer type FAI service area 2016 forecast 2017 forecast $ per site per month Residential Farm Irrigation Small commercial Oil & gas Lighting EDTI service area Residential Small commercial Lighting Decision D (December 20, 2016) 3

8 19. EEA requested approval of the following: Continuation of a hearing cost reserve and short-term incentive deferral accounts. Price schedules, including miscellaneous fees and credits. Terms and conditions of service. 20. In the sections that follow, the Commission considers the issues that were raised by parties or that arose upon the Commission s review of the application, and provides its findings on EEA s application. Subject to the findings and directions outlined in this decision, the Commission approves EEA s: Forecast customer site counts Operating costs Corporate services costs Property taxes Hearing cost deferral account Depreciation expense 3 Compliance with Commission directions 21. Appendix D to the application contains EEA s descriptions of its treatment of Direction 21 from Decision and directions 1, 7, 8, 9, 12, 13, 14 and 16 from Decision The Commission has reviewed EEA s proposed treatment of Direction 21 from Decision and Direction 1, which deals with disallowed EPCOR Utilities Inc. (EUI) investment costs, Direction 7 (quarterly revenue updates for bad debt), Direction 9 (effect of acquisitions), Direction 13 (forward interest rate curve analysis), Direction 14 (return margin) and Direction 16 (ENCOR operating costs) from Decision EEA s responses to these directions are complete and the Commission considers that, for the purposes of this application, EEA has complied with these directions. 23. EEA s proposed treatment of Direction 8 from Decision , regarding late payment charge forecasting is discussed in Section of this decision. EEA s proposed treatment of Direction 12 from Decision , regarding EEA s capital structure is discussed in Section of this decision. 1 2 Decision : EPCOR Distribution & Transmission Inc., 2012 Phase I and II Distribution Tariff, 2012 Transmission Facility Owner Tariff, Proceeding 1596, Application , October 5, Decision : EPCOR Energy Alberta GP Inc., Non-Energy Regulated Rate Tariffs, Proceeding 2986, Application , November 4, Decision D (December 20, 2016)

9 4 Issues 4.1 Corporate vacancy rate 24. In response to a Commission IR, EEA updated its global vacancy rate to 4.5 per cent. 3 This vacancy rate is applied to all contact centre full-time equivalents (FTEs) that are not customer service consultants, and to all other EEA FTEs other than customer service consultants. 25. EEA stated that this vacancy rate is not applied to EUI corporate employees because EUI does not track FTEs. Instead, EUI monitors employees on a headcount basis In evidence submitted on behalf of the UCA, Ms. Radway stated that regulated utilities including AltaLink L.P. (AltaLink), ATCO Electric Ltd. and FAI show the FTEs for corporate staff in their Schedule 25.5 Corporate Manpower Full Time Equivalents, and that a vacancy rate is applied for corporate employees. ATCO Electric, AltaLink and FAI apply the same vacancy rate as applied to either transmission FTEs or distribution FTEs as they do for corporate employees. 27. Ms. Radway stated that there are vacancies within EUI, just as there are within EEA. Ms. Radway cited EEA s application in which two positions within information services application support were vacant for a period of time in For that period, the forecast direct assigned cost for information services application support was $1.57 million, while the actual was $1.19 million. Not accounting for the vacancies resulted in over-forecasting in the amount of $0.38 million. 28. Ms. Radway noted that, although EUI is an unregulated entity, it does allocate some of its corporate costs to EEA and EDTI, both of which are regulated entities. Because some corporate costs are allocated to regulated entities, Ms. Radway recommended that a 4.5 per cent vacancy rate should apply to all corporate equivalent headcounts for EUI and there should be a corresponding reduction in salary costs, including all benefits and incentive costs for the regulated entities. Because the vacancy rate for corporate services may differ from EDTI and EEA, Ms. Radway recommended that the vacancy rate could be tracked to ensure an accurate forecast of corporate services, union and benefits and incentives costs for future test years In its rebuttal evidence, EEA stated that Ms. Radway s recommendation is flawed and inaccurate, and must be rejected. Since EUI uses headcount, it cannot accurately forecast a vacancy rate. Due to the finance optimization project, which is anticipated to be complete in 2016, EUI can now accurately monitor and track its actual corporate services vacancies. With this newly available data, EEA can commit to providing the actual vacancy rate for corporate services employees for 2016 and 2017, and then applying a forecast vacancy rate for all corporate headcount equivalents for the next test period EEA stated that the global vacancy rate is calculated based on actual vacancy rates from previous years and is not transferrable to EUI personnel. EUI corporate services and EEA are distinctly different businesses with different operations and personnel types. Most of EEA s Exhibit X0062, information responses, EEA-AUC-2015OCT07-004, tables and , PDF pages Exhibit X0073, information responses, EEA-UCA-2015OCT07-020(a) and (b), PDF page 75. Exhibit X0130, evidence of Shelley Radway, paragraphs A40 and A41, PDF page 28. Exhibit X0143, EEA rebuttal evidence, paragraph A90, PDF page 64. Decision D (December 20, 2016) 5

10 personnel are unionized entry-level positions, while corporate services staff are mostly management and professional positions. Some of these corporate services positions are rarely vacant and when the departure of an incumbent is announced, an overlapping transition period is often used EEA also submitted that AltaLink, ATCO Electric and FAI apply vacancy rates to FTEs, not to headcounts. EUI is not a regulated entity and is, therefore, not required to make FTE calculations. EUI, therefore, does not have historical information available upon which to forecast corporate vacancies accurately. If it were to calculate a vacancy rate, it would be calculated based on a point in time during the year because EUI does not track FTEs The UCA argued that EUI s shared services salary and labour costs for 2016 and 2017 are $30.4 million and $31.44 million, respectively. Reducing those values by 4.5 per cent would equate to $1.37 million for 2016 and $1.41 million for This is equivalent to calculating the total salary and labour costs, and dividing them by the total headcount to determine the average cost per headcount. The same results would be obtained by applying the 4.5 per cent reduction to the headcount and multiplying that value by the average cost per headcount The UCA argued that it is not necessary for EEA to track its FTEs for a vacancy rate to apply to EUI for the test years. 34. In reply argument, the UCA cited EEA s statements regarding the finance optimization project and forecasting a corporate vacancy rate in future test years, and then argued that EEA seems to recognize that applying a vacancy rate to corporate employees is appropriate and necessary. The UCA argued that EEA relies heavily on the fact that EUI is not required to track corporate FTEs, and indicated that the other utilities mentioned by Ms. Radway apply corporate vacancy rates that mirror those applied to the companies transmission and distribution employees. 10 Commission findings 35. EEA argued that a corporate services vacancy rate cannot be calculated and forecast because EUI tracks headcounts rather than FTEs. EEA provided an example to support its assertion that any corporate services vacancy rate calculation would be based on a single point in time. In the example provided, a vacancy calculation is only calculated on a single day during the test year. The Commission finds that EEA does not adequately explain why such calculations could not be made throughout the year to determine an average vacancy rate for the year. There is not sufficient evidence to suggest that an alternative method could not be employed by which a vacancy rate could be calculated for corporate services. EEA has not demonstrated that a vacancy rate specific to corporate services cannot be calculated for regulatory purposes. 36. Furthermore, given the evidence presented by Ms. Radway regarding vacancies in information services application support and given EEA s proposal to track corporate vacancies during 2016 and 2017, vacancies do exist within EUI corporate services and the application of a vacancy rate to those costs is supported Exhibit X0143, EEA rebuttal evidence, paragraph A91, PDF page 65. Exhibit X0143, EEA rebuttal evidence, paragraph A92, PDF page 65. Exhibit X0147, UCA argument, paragraph 63, PDF page 16. Exhibit X0150, UCA reply argument, paragraph 90, PDF page Decision D (December 20, 2016)

11 37. The Commission accepts EEA s explanation of the differences between EEA personnel and EUI corporate services personnel for the purposes of determining a vacancy rate. The Commission agrees that these differences suggest that the global vacancy rate may not be directly applicable to EEA s corporate services costs. However, EEA has not provided any evidence that would allow the Commission to determine a non-zero vacancy rate for EUI corporate services personnel. 38. In the absence of evidence to support a vacancy rate that should apply to EUI s corporate services allocated to EEA, the Commission considers that the global vacancy rate of 4.5 per cent should be applied to the EUI corporate services costs allocated to EEA. Accordingly, the Commission directs EEA to include a 4.5 per cent vacancy rate for EUI s corporate services costs allocated to EEA in the compliance filing. 4.2 Salary escalations 39. Consistent with previous applications, EUI engaged Towers Watson to prepare a report on the competitiveness of EEA s, EDTI s and EUI s unionized and non-unionized positions and to recommend the level of escalation for EEA s non-union salaries for 2016 and For 2016 and 2017, Towers Watson recommended a range of escalation for non-union salaries of three per cent to four per cent According to EEA, the lower end of the range recommended by Towers Watson is generally consistent with factors applied prior to the decline in oil prices and the higher end reflects potential increases if oil prices return to historical norms. The recommendation was based on projections that the Canadian economy is expected to rebound by the end of 2015 and return to full productivity in Based on Towers Watson s analysis, EEA originally forecast escalation for non-union salaries at four per cent for 2016 and 2017, which represents growth in Alberta with oil prices returning to historical levels. However, in its rebuttal evidence, EEA revised this forecast down to three per cent, which EEA stated aligns with the three per cent escalator approved for EDTI in Decision 3539-D Views of the parties 42. In evidence submitted on behalf of the UCA, Ms. Radway cited the Towers Watson memorandum, in which Towers Watson stated that the projected range is highly sensitive to the economic recovery assumptions noted above and the range may decrease if oil prices and overall economic growth do not increase as anticipated Ms. Radway stated that Towers Watson s recommendation was predicated on oil prices returning to historical norms, which has not happened, and that the low end of the Towers Watson range may be too high. Ms. Radway further stated that the Economic Outlook for the Exhibit X0003, application, paragraph 128, PDF page 47. Exhibit X0003, application, paragraph 129, PDF page 47. Decision 3539-D : EPCOR Distribution & Transmission Inc., Transmission Facility Owner Tariff, Proceeding 3539, Application , October 21, Exhibit X0130, evidence of Shelley Radway, paragraph A26, PDF page 18. Decision D (December 20, 2016) 7

12 Government of Alberta s Budget shows that for , weekly earnings will increase by 2.4 per cent. 44. Ms. Radway noted that, for the last three years, EEA has awarded salary escalators 0.3 per cent lower than the lowest number of the range recommended by Towers Watson. As a result, Ms. Radway proposed a salary escalation rate of 2.7 per cent The UCA argued that a three-year average is commonly used to test the reliability of forecasts and this time frame is consistent with EEA s own forecasting methodology for vacancy rates EEA stated that only the high end of the escalator range recommended by Towers Watson was predicated on oil prices returning to historical norms. EEA also stated that it is important to note that there is not a direct relationship between oil prices and EEA s salary escalation forecasts. In its report, Towers Watson considered the effect of the decline in oil prices and observed a more moderate approach taken within the utility sector relative to the oil and gas sector EEA also stated that the weekly earnings forecast in the Economic Outlook for the Government of Alberta s Budget 2015 is not a reasonable comparator to EEA s non-union salary escalation. The weekly earnings indicator is the gross taxable payroll divided by the number of employees for all employees across Alberta. The weekly earnings includes overtime that is not applicable to EEA s non-union employees and part-time hours, which will drive down the weekly earnings. It also includes all industries, such as oil and gas companies, which are not included in EEA s comparator companies EEA examined six years of data from 2010 to 2015 to show that EEA has, on average, awarded a salary escalation 0.1 per cent above the low end of the ranges recommended by Towers Watson. 20 Commission findings 49. Table 3 below illustrates the approved non-union salary escalators and the actual escalators for the years 2004 to 2015, as provided by EEA in its application and IR responses: Government of Alberta, Budget 2015, Fiscal Plan , Economic Outlook, October 27, Exhibit X0130, evidence of Shelley Radway, paragraphs A27 and A28, PDF page 18. Exhibit X0150, UCA reply argument, paragraph 70, PDF page 19. Exhibit X0143, EEA rebuttal evidence, paragraph A65, PDF page 47. Exhibit X0143, EEA rebuttal evidence, paragraph A66, PDF page 48. Exhibit X0143, EEA rebuttal evidence, paragraph A67, PDF page 49. Exhibit X0003, application, Table , PDF page 48; Exhibit X0062, information responses, Table EEA-AUC-2015OCT , PDF page Decision D (December 20, 2016)

13 Table 3. Historical approved and actual non-union salary escalators AUC/EUB (1) approved (%) EEA actual Note 1: EUB Alberta Energy and Utilities Board. 50. As shown in the table above, from 2007 onwards, with the exception of 2010, EEA has consistently implemented actual non-union salary escalators lower than those approved by the Commission and its predecessor, the Alberta Energy and Utilities Board (the board). These data also show a declining trend in actual salary escalators awarded by EEA from 2012 to In its memorandum on non-union salary escalation factors, Towers Watson stated that the decline in 2015 salary budgets and the continued economic uncertainty make it difficult to provide a firm estimate of 2016 and 2017 salary escalators. Towers Watson further stated that it anticipates 2016 salary escalators will increase from depressed 2015 levels because of a positive outlook for Towers Watson asserted that the salary escalator range it projected is highly sensitive to Towers Watson s economic recovery assumptions and that the range may decrease if oil prices and overall economic growth do not increase as anticipated Given Towers Watson s stated uncertainty with regard to its projections, the positive outlook that those projections are predicated on and the current economic climate in Alberta, the Commission finds that the three to four per cent range recommended by Towers Watson is no longer reflective of salary escalators, given the current climate in Alberta, and does not constitute a reasonable salary escalator to be applied to the test years. 53. For the reasons discussed above, the Commission accepts the UCA s proposed 2.7 per cent non-union salary escalator for 2016 and 2017, and directs EEA to update its non-union salary escalators to 2.7 per cent for both 2016 and 2017 in the compliance filing. 4.3 Operating costs Customer service costs 54. EEA applied for customer service costs of $21.69 million and $21.97 million for 2016 and 2017, respectively. Those totals were composed of client services costs of $7.78 million for 2016 and $7.72 million for 2017; technical training and communications costs of $1.11 million 22 Exhibit X0022, Appendix I, PDF page 50. Decision D (December 20, 2016) 9

14 for 2016 and $1.13 million for 2017; and information services costs of $4.86 million for 2016 and $4.82 million for Views of the parties 55. In her evidence, filed on behalf of the UCA, Ms. Radway stated that EEA has a history of over-forecasting client services, technical training and communications, and information services for 2012, 2013 and Ms. Radway used the data provided by EEA to show the over-forecast percentage in 2012, 2013 and 2014 for each of the three customer service cost areas and provided an average over these three years. The variances are reproduced in Table 4, below: Table 4. Variance between forecast and actual customer service costs Year Average Client services Technical training and communications Information services Source: Exhibit X0130, UCA evidence of Ms. Radway, Table 1, PDF page Ms. Radway commented that the pattern continues for 2015, but that 2015 was not included in the calculations because updated forecast data were only available for the first quarter of Ms. Radway noted that while the individual subcategories that comprise each of the cost categories within customer services costs may not show evidence of over-forecasting, this is not the case when looking at the total categories where annual over-forecasting becomes readily apparent. If the sum of the individual forecasts consistently demonstrates over-forecasting, then Ms. Radway stated that the total must be adjusted for the test years. 59. For client services, Ms. Radway acknowledged that site count variance needed to be accounted for in an analysis of the historical variances. Ms. Radway adjusted for the site count variance by dividing the forecast and actual client services costs by the forecast and actual site counts, respectively. After adjusting for site counts, Ms. Radway s result showed an average variance of 10.0 per cent over the years 2012 through Ms. Radway did not propose a site count adjustment specifically for technical training and communications and information services Based on her analysis, Ms. Radway recommended reducing EEA s 2016 and 2017 forecasts for client services by 10.0 per cent, for technical training and communications by 12.1 per cent, and for information services by 9.7 per cent. 25 (%) Exhibit X0003, application, Table 3.1-1, PDF page 60. Exhibit X0130, evidence of Shelley Radway, paragraphs A10 and A11, PDF page 7. Exhibit X0130, evidence of Shelley Radway, paragraph A15, PDF page Decision D (December 20, 2016)

15 61. Ms. Radway referenced three instances in which the Commission reduced forecast costs for test years based on a history of under- or over-forecasting. In Decision , 26 the Commission reduced AltaLink s general operating and maintenance expense; in Decision , the Commission reduced EEA s utility affiliates site counts; and in Decision D , 27 the Commission reduced ATCO Pipelines costs for capital projects In rebuttal evidence, EEA submitted that Ms. Radway s analysis is flawed and misleading, and it does not address the detailed reasons provided by EEA for historical variances from forecast. As such, EEA stated that Ms. Radway s recommendations should be rejected for the following reasons: 29 (a) For 2012 and 2013, Ms. Radway uses EEA s forecast amounts rather than decision amounts, which included reductions to EEA s forecasts. For example, in Decision , 30 the Commission made several determinations reducing EEA s customer service costs. 31 (b) Ms. Radway ignores organizational transfers of positions within EEA that reflect a shifting of costs between categories. For example, the transfer of webmail costs and the customer relations manager from client services to billing services resulted in decreased client services costs of $0.29 million in 2013 and $0.10 million in 2014, with corresponding increases in billing services. 32 (c) Ms. Radway s approach double counts the impact of historical variances because EEA s forecasts incorporate historical results. EEA provided its global vacancy rate as an example of how historical variances are incorporated into forecasts. (d) Ms. Radway ignores the underlying causes of variances and does not account for unusual or one-time events, such as EEA s contact centre consolidation project and higher than anticipated attrition in 2014, that will not affect the current test period. 33 (e) Ms. Radway does not provide any reasons for the expectation that historical variances will occur again. The occurrence of a variance does not mean that the variance will occur again. (f) Ms. Radway has not demonstrated any flaws in EEA s forecasting methodology, or that her recommendation will result in a more accurate forecast Decision : AltaLink Management Ltd., General Tariff Application, Proceeding 2044, Application , November 12, Decision 3577-D : ATCO Pipelines, General Rate Application, Proceeding 3577, Application , February 29, Exhibit X0130, evidence of Shelley Radway, paragraph A14, PDF page 9. Exhibit X0143, EEA rebuttal evidence, paragraph A49, PDF page 31. Decision : EPCOR Energy Alberta Inc., Regulated Rate Tariffs, Proceeding 1872, Application , March 21, Exhibit X0143, EEA rebuttal evidence, paragraph A52, PDF page 34. Exhibit X0143, EEA rebuttal evidence, paragraph A54, PDF page 36. Exhibit X0143, EEA rebuttal evidence, paragraph A49, PDF page 32. Decision D (December 20, 2016) 11

16 (g) Ms. Radway s approach is inconsistent with forecast cost-of-service ratemaking, which allows the applicant to keep the benefits of improvements during the test years and then pass those benefits on to customers in future test periods The UCA argued that the cost transfers from client services to billing services were already accounted for in the costs provided in EEA s application, that EEA continues to overforecast even after accounting for historical variances in forecasts and that the onus is not on Ms. Radway to provide an explanation for why historical variances will reoccur. 35 The UCA argued further that Ms. Radway s approach is consistent with cost-of-service regulation since it ensures that the resulting savings are passed on to customers in subsequent test periods. 36 Commission findings 64. The Commission acknowledges the conflicting positions of EEA and the UCA with regard to the reasonableness of EEA s customer service cost forecasts. The Commission has taken these viewpoints into account and considers that the issue of over-forecasting is adequately addressed in Section 4.6 below and additional findings are not required in this section of the decision Late payment charges 65. In Decision , the Commission approved EEA s proposed trend methodology for forecasting late payment charges, but provided the following direction: 193. While the Commission accepts EEA s proposed method to forecast late payment charges, the Commission does have concerns regarding the applicability of this method for forecasting and whether it is an adequate measure from which to forecast late payment charges. The Commission, therefore, directs EEA to include in its next nonenergy application, in addition to the method approved in this decision, an analysis of alternative methods of forecasting late payment charges. The methods examined should include, but not necessarily be limited to, a trend line to historical actual late payment charges methodology and a two-step methodology based on: (i) the percentage of bills, out of the total number of bills issued, to which late payment fees have been charged; and (ii) the amount or portion the late payment charges represent on those bills. 66. For the current application, EEA undertook a review of its late payment charges forecasting method and evaluated 20 different alternatives using historical data from 2006 to 2014 in order to evaluate the percentage error for each alternative. 67. EEA found that the two-step methodology suggested by the Commission was not reliable because there is not a one-to-one ratio between sites and customer accounts. The same was found in EEA s analysis of a methodology based on the percentage of billed sites by rate class. 68. EEA also reviewed a trend methodology, as approved in Decision , three different historical average methods (three-year average, four-year average, and historical simple average using data from 2006 to 2014), and a weighted average of the three most recent years, which was previously used by EEA for bad debt forecasting. Each of these five methodologies Exhibit X0143, EEA rebuttal evidence, paragraph A49, PDF page 31. Exhibit X0147, UCA argument, paragraphs 4-9, PDF page 4. Exhibit X0150, UCA reply argument, paragraph 20, PDF page Decision D (December 20, 2016)

17 was investigated using monthly and annual data, and using billed revenues and settled revenues for a total of 20 alternatives. 69. EEA s analysis showed that the alternatives using monthly data and billed revenues produced lower average percentage errors than the alternatives using annual data and settled revenues. For the EDTI service area, the four-year average produced the lowest percentage error, while for the FAI service area, the historical simple average produced the lowest average percentage error. 70. EEA then performed the same analysis with the data for the EDTI and FAI service areas combined. In this analysis, the historical simple average using monthly data produced the lowest average percentage error. 71. Based on the results of the analyses, EEA proposed to change its late payment charge forecasting methodology to a historical simple average method calculated using monthly data. 37 As a check on the reasonableness of this proposal, EEA compared the 2016 and 2017 forecasts using this methodology to forecasts prepared using the most accurate methodology for each service area. 72. For the EDTI service area, 2016 and 2017 forecasts using the proposed historical simple average were $3.50 million and $3.73 million, respectively. Forecasts using a four-year average were $3.48 million and $3.71 million, respectively, demonstrating a variance of only $0.02 million for each test year. 38 Commission findings 73. The Commission considers that EEA has provided a sufficient review of alternative late payment charge forecasting methodologies and accepts the results of EEA s analyses. 74. Accordingly, the Commission approves EEA s late payment charge forecasting methodology using a historical simple average method calculated using monthly data, as proposed in the application. The Commission considers that in providing the various alternatives for calculating forecasts of late payment penalties, EEA has complied with the Commission s direction at paragraph 193 of Decision Tax and deferral accounts 75. EEA applied for the continuation of a hearing cost reserve account, and the continuation of a deferral account for short-term incentive costs. 39 Following the guidance of the Commission in Decision , EEA applied to include, as part of the hearing cost reserve account, any incremental depreciation and debt costs related to regulatory projects driven by regulatory initiatives that occur during 2016 and EEA indicated that it has not forecast any costs of this type for 2016 and No comments were received on these two accounts from the CCA or the UCA Exhibit X0003, application, paragraph 544, PDF page 169. Exhibit X0003, application, paragraph 546, PDF page 170. Exhibit X0003, application, paragraph 1191, PDF page 413. Exhibit X0003, application, paragraph 1193, PDF pages Decision D (December 20, 2016) 13

18 Commission findings 77. As noted by EEA in the application, 41 the hearing cost reserve account and the short-term incentive costs deferral account were established in previous years and have been in existence for a number of years. The addition of the incremental depreciation and debt costs related to regulatory projects was reasonably the result of a Commission consideration in Decision There is no reason provided on the record to change the treatment of these two accounts during 2016 and 2017 and, therefore, the Commission approves their continued use in 2016 and Bad debt deferral 78. Referring to the bad debt risk, site counts risk and cost risk underlying EEA s request for non-energy risk compensation, as described further in Section 4.5 of this decision, the Commission asked EEA if deferral accounts related to any of these risks would mitigate risk to customers as well as to EEA. The Commission also asked EEA to explain why it had not requested deferral account treatment for site counts, bad debts and all remaining costs, but instead had requested non-energy risk compensation In response, EEA indicated that the use of a deferral account would be a way to mitigate these three risks to customers and EEA. EEA added that these three risks are not an exhaustive list of all the business risks that EEA faces. Using the criteria identified by the Commission in Decision for the establishment of deferral accounts, EEA provided an evaluation of whether site counts risk, bad debt risk and cost risk met these criteria. EEA indicated that only bad debt risk satisfies all of the Commission s criteria for deferral account treatment. 44 EEA stated that based on the Commission s denial of a bad debt deferral account in Decision , it did not request deferral account treatment for bad debts as part of this application In the same response, EEA proposed the same bad debt deferral account mechanism as it proposed in its non-energy RRT application. 46 This deferral account mechanism subjects 50 per cent of the variance between the actual and forecast bad debt expenses to deferral, with EEA retaining the remaining 50 per cent of the variance. EEA added that if this deferral account is provided, then its non-energy risk compensation would be reduced from 0.50 per cent to 0.42 per cent The CCA submitted that, based on a historical analysis of actual and forecast cost levels, the approval of a bad debt deferral account would decrease the risk of negative outcomes for EEA and increase the positive risk to EEA. The CCA added that the negative outcomes of bad debt would no longer be dragging down the net positive effect of variances in site counts and other costs Exhibit X0003, application, paragraph 1191, PDF page 413. Exhibit X0108, EEA-AUC-2016JAN19-001(b) and (c), PDF pages 1-2. Decision : ATCO Utilities Pension Common Matters, Proceeding 226, Application , April 30, Exhibit X0114, information responses, EEA-AUC-2016JAN28-001(b), PDF pages 4-7. Exhibit X0114, information responses, EEA-AUC-2016JAN28-001(c), PDF page 9. Proceeding Exhibit X0114, information responses, EEA-AUC-2016JAN28-001(c), PDF page 8. Exhibit X0129, evidence of Jan Thygesen, paragraph 24, PDF page Decision D (December 20, 2016)

19 82. The UCA described two concerns with the introduction of a bad debt deferral account. The first concern is the reduction of the incentive to control bad debt levels, and the second is that EEA will have less risk compared to other regulated rate option (RRO) providers. 49 The UCA submitted that EEA has updated its methodology for forecasting bad debt expense in each of the last three RRT applications, and these refinements have reduced the forecast errors. The UCA stated that EEA is able to forecast its bad debt expense The UCA indicated that over the last five years, EEA has the least amount of forecast error for bad debt expense compared to the other RRO providers; namely, Direct Energy Regulated Services (DERS) and ENMAX Energy Corporation (EEC). 51 The UCA stated that DERS and EEC do not have bad debt deferral accounts. It added that if EEA has a bad debt deferral account, which reduces EEA s forecast risk compared to DERS and EEC, and EEA continues to obtain a return compensation figure that is equivalent to the return compensation figures for DERS and EEC, then EEA will be overcompensated The UCA recommended that the request for a bad debt deferral account be denied In its rebuttal evidence, 54 as well as its written argument, 55 EEA stated that it was not amending its application to apply for a bad debt deferral account. EEA included the following clarification about its response to the Commission s IR regarding a deferral account for bad debt expense: To clarify, in EEA-AUC-2016JAN28-001(b), EEA was asked whether a deferral account would mitigate bad debt risk (amongst other risks) and, if so, how the deferral account would function. In response to this question, EEA explained how it would propose that such a deferral account would function. EEA was not, however, amending its Application to apply for a bad debt deferral account. 56 Commission findings 86. Before EEA submitted its clarification to the response to the Commission s IR EEA- AUC-2016JAN28-001(b), the Commission s understanding was the same as that of both the UCA and the CCA, in that, EEA was amending its application and proposing a bad debt deferral account. However, based on the clarification in EEA s rebuttal evidence and written argument, it is clear to the Commission that EEA is not applying for a bad debt deferral account. The Commission considers that no finding is required because EEA is not proposing a bad debt deferral account Exhibit X0130, evidence of Shelley Radway, paragraph A37, PDF page 25. Exhibit X0130, evidence of Shelley Radway, paragraph A37, PDF page 26. Exhibit X0130, evidence of Shelley Radway, paragraph A37, PDF page 26. Exhibit X0130, evidence of Shelley Radway, paragraph A37, PDF page 27. Exhibit X0130, evidence of Shelley Radway, paragraph A38, PDF page 27. Exhibit X0143, EEA rebuttal evidence, PDF page 59. Exhibit X0149, EEA written argument, paragraph 133, PDF page 69. Exhibit X0143, EEA rebuttal evidence, PDF page 59. Decision D (December 20, 2016) 15

20 4.5 Depreciation and return Weighted average cost of capital 87. EEA did not request any return on equity with respect to its rate base through its nonenergy rates for 2016 and However, EEA indicated that it still requires an approved forecast for its weighted average cost of capital (WACC). This WACC figure is used for calculating the return on capital component for purposes of determining corporate asset usage fees. 58 EEA calculated a WACC for 2016 and 2017 of 6.01 per cent, based on a debt to equity ratio of 61/39, a return on equity figure of 8.30 per cent, and a cost of debt figure of 4.55 per cent. 59 The 61/39 debt to equity ratio is a change from previous years, for which EEA used a capital structure of 100 per cent debt to calculate WACC EEA referred to Decision in which the Commission accepted that EEA operates as a stand-alone entity, 61 and a subsequent direction from that decision for EEA to explore its capital structure as part of the current application, and to explain the proposed change in the debt to equity ratio. 89. EEA proposed the 61/39 debt to equity ratio based on Decision , 62 as this was the last time the Commission approved EEA s capital structure prior to the 100 per cent deemed debt for EEA Referring to Decision 2191-D , 64 the 2013 Generic Cost of Capital (GCOC) decision, the Commission asked EEA in an IR if the one per cent reduction to the equity ratios approved for all the utilities involved in that proceeding should be reflected in EEA s proposed debt to equity ratio. In response, EEA considered that the one per cent reduction should be applied, and EEA proposed to incorporate such a change in the compliance filing if the Commission agreed to the change. EEA advised that the effect of such a change would be an increase in the revenue requirement for 2016 and 2017 of approximately $10,000 in each year. 65 Commission findings 91. The Commission issued Decision D on the 2016 GCOC proceeding on October 7, The awarded return on equity and capital structures from that proceeding are applicable for the years 2016 and The Commission considers that the figures from the decision on the 2016 GCOC proceeding are the most up to date and should be incorporated into EEA s 2016 and 2017 RRT, because these figures will apply to the same test years. Therefore, the Commission directs EEA to incorporate any applicable results from Decision D , into its compliance filing Exhibit X0003, application, paragraph 1325, PDF page 452. Exhibit X0003, application, paragraph 1135, PDF page 370. (0.39*.083) + (0.61*.0455). Exhibit X0003, application, paragraph 1325, PDF page 452. Decision , paragraph 230, PDF page 55. Decision : 2009 Generic Cost of Capital, Proceeding 85, Application , November 12, Exhibit X0007, Appendix D, paragraph 17, PDF page 7. Decision 2191-D : 2013 Generic Cost of Capital, Proceeding 2191, Application , March 23, Exhibit X0062, information responses, EEA-AUC-2015OCT07-035(b), PDF page 100. Decision D : 2016 Generic Cost of Capital, Proceeding 20622, October 7, Decision D (December 20, 2016)

21 4.5.2 Interest during construction and allowance for funds used during construction 92. EEA currently maintains two concurrent calculations of capitalized interest For regulatory purposes, EEA currently capitalizes interest charges for capital projects using the allowance for funds used during construction (AFUDC) methodology. The AFUDC methodology involves calculating the capitalized interest by applying EEA s WACC to the midyear balance of capital work-in-progress For external financial reporting purposes, EEA calculates capitalized interest using the interest during construction (IDC) methodology, in accordance with the requirements of the International Financial Reporting Standards. The IDC methodology uses EEA s cost of debt rate multiplied by capital work-in-progress for any capital project exceeding both a minimum capital threshold of $0.5 million and a duration of six months As part of its application, EEA proposed to adopt IDC for regulatory purposes. EEA stated this would be administratively more efficient because it would result in EEA maintaining a single set of accounting records. EEA submitted that this change would not have a material effect on its revenue requirement, because it has minimal capital assets. 70 It provided information showing the effect on revenue requirement resulting from the use of IDC compared to AFUDC. For the years 2010 to 2015, the combined revenue requirements would have decreased by approximately $10,000 if IDC had been used instead of AFUDC. For the forecast years included in the application, the combined revenue requirements are approximately $10,000 greater as a result of using IDC instead of AFUDC The UCA recommended that there be no change for the accounting treatment for AFUDC and that only the interest on the debt portion of the capital structure be included in costs. The UCA recommended further that the AFUDC for corporate asset usage fees only include the interest costs The UCA indicated that EEA has adopted a 61/39 debt to equity ratio as its capital structure and as such, EEA collects interest costs for debt for its working capital and reserve activity based on this structure. However, as the UCA added, EEA recovers its WACC of 6.01 per cent through its return for corporate asset usage fees The UCA submitted that since the return compensation determined for EEA in Decision 2941-D is considered all inclusive, there should be no return on equity for either AFUDC or the return portion of the corporate asset usage fees. 75 The UCA submitted that, in Exhibit X0003, application, paragraph 1302, PDF page 445. Exhibit X0003, application, paragraph 1301, PDF page 445. Exhibit X0003, application, paragraph 1301, PDF page 445. Exhibit X0003, application, paragraph 1303, PDF page 445. Exhibit X0003, application, tables and 7.1-2, PDF page 446. Exhibit X0130, evidence of Shelley Radway, PDF page 24. Exhibit X0130, evidence of Shelley Radway, PDF page 21. Decision 2941-D : Direct Energy Regulated Services, ENMAX Energy Corporation and EPCOR Energy Alberta GP Inc., Regulated Rate Tariff and Energy Price Setting Plans Generic Proceeding: Part B Final Decision, Proceeding 2941, Application , March 10, Exhibit X0130, evidence of Shelley Radway, paragraph A33, PDF pages Decision D (December 20, 2016) 17

ENMAX Power Corporation

ENMAX Power Corporation Decision 22238-D01-2017 ENMAX Power Corporation 2016-2017 Transmission General Tariff Application December 4, 2017 Alberta Utilities Commission Decision 22238-D01-2017 ENMAX Power Corporation 2016-2017

More information

Decision D FortisAlberta Inc PBR Capital Tracker True-Up and PBR Capital Tracker Forecast

Decision D FortisAlberta Inc PBR Capital Tracker True-Up and PBR Capital Tracker Forecast Decision 20497-D01-2016 FortisAlberta Inc. 2014 PBR Capital Tracker True-Up and 2016-2017 PBR Capital Tracker Forecast February 20, 2016 Alberta Utilities Commission Decision 20497-D01-2016 FortisAlberta

More information

AltaGas Utilities Inc.

AltaGas Utilities Inc. Decision 2013-465 2014 Annual PBR Rate Adjustment Filing December 23, 2013 The Alberta Utilities Commission Decision 2013-465: 2014 Annual PBR Rate Adjustment Filing Application No. 1609923 Proceeding

More information

Decision D Rebasing for the PBR Plans for Alberta Electric and Gas Distribution Utilities. First Compliance Proceeding

Decision D Rebasing for the PBR Plans for Alberta Electric and Gas Distribution Utilities. First Compliance Proceeding Decision 22394-D01-2018 Rebasing for the 2018-2022 PBR Plans for February 5, 2018 Alberta Utilities Commission Decision 22394-D01-2018 Rebasing for the 2018-2022 PBR Plans for Proceeding 22394 February

More information

AltaGas Utilities Inc.

AltaGas Utilities Inc. Decision 23898-D01-2018 2019 Annual Performance-Based Regulation Rate Adjustment Filing December 20, 2018 Alberta Utilities Commission Decision 23898-D01-2018 2019 Annual Performance-Based Regulation Rate

More information

Decision The ATCO Utilities. Corporate Costs. March 21, 2013

Decision The ATCO Utilities. Corporate Costs. March 21, 2013 Decision 2013-111 Corporate Costs March 21, 2013 The Alberta Utilities Commission Decision 2013-111: Corporate Costs Application No. 1608510 Proceeding ID No. 1920 March 21, 2013 Published by The Alberta

More information

Alberta Utilities Commission

Alberta Utilities Commission Decision 22091-D01-2017 Commission-Initiated Proceeding to Review the Terms and November 9, 2017 Decision 22091-D01-2017 Commission-Initiated Proceeding to Review the Terms and Proceeding 22091 Application

More information

EPCOR Distribution & Transmission Inc.

EPCOR Distribution & Transmission Inc. Decision 21229-D01-2016 EPCOR Distribution & Transmission Inc. 2015-2017 Transmission Facility Owner Tariff and 2013 Generic Cost of Capital Compliance Application April 15, 2016 Alberta Utilities Commission

More information

ATCO Electric Ltd. Stage 2 Review of Decision D ATCO Electric Ltd Transmission General Tariff Application

ATCO Electric Ltd. Stage 2 Review of Decision D ATCO Electric Ltd Transmission General Tariff Application Decision 22483-D01-2017 Stage 2 Review of Decision 20272-D01-2016 2015-2017 Transmission General Tariff Application December 6, 2017 Alberta Utilities Commission Decision 22483-D01-2017 Stage 2 Review

More information

EPCOR Distribution & Transmission Inc.

EPCOR Distribution & Transmission Inc. Decision 3539-D01-2015 EPCOR Distribution & Transmission Inc. 2015-2017 Transmission Facility Owner Tariff October 21, 2015 Alberta Utilities Commission Decision 3539-D01-2015: EPCOR Distribution & Transmission

More information

AltaLink Investment Management Ltd. And SNC Lavalin Transmission Ltd. et al.

AltaLink Investment Management Ltd. And SNC Lavalin Transmission Ltd. et al. Decision 3529-D01-2015 AltaLink Investment Management Ltd. And SNC Lavalin Transmission Ltd. et al. Proposed Sale of AltaLink, L.P Transmission Assets and Business to Mid-American (Alberta) Canada Costs

More information

ENMAX Power Corporation Distribution and Transmission Deferral Account Reconciliation

ENMAX Power Corporation Distribution and Transmission Deferral Account Reconciliation Decision 23108-D01-2018 2014 Distribution and 2014-2015 Transmission Deferral Account Reconciliation February 27, 2018 Alberta Utilities Commission Decision 23108-D01-2018 2014 Distribution and 2014-2015

More information

ENMAX Energy Corporation

ENMAX Energy Corporation Decision 22054-D01-2017 Regulated Rate Option Tariff Terms and Conditions Amendment Application April 12, 2017 Alberta Utilities Commission Decision 22054-D01-2017 Regulated Rate Option Tariff Terms and

More information

Decision ATCO Utilities. Corporate Cost Allocation Methodology. September 20, 2010

Decision ATCO Utilities. Corporate Cost Allocation Methodology. September 20, 2010 Decision 2010-447 Corporate Cost Allocation Methodology September 20, 2010 ALBERTA UTILITIES COMMISSION Decision 2010-447: Corporate Cost Allocation Methodology Application No. 1605473 Proceeding ID. 306

More information

Decision D ATCO Electric Ltd. Compliance Filing to Decision D Capital Tracker True-Up

Decision D ATCO Electric Ltd. Compliance Filing to Decision D Capital Tracker True-Up Decision 23454-D01-2018 ATCO Electric Ltd. Compliance Filing to Decision 22788-D01-2018 2016 Capital Tracker True-Up May 4, 2018 Alberta Utilities Commission Decision 23454-D01-2018 ATCO Electric Ltd.

More information

Decision D Generic Cost of Capital. Costs Award

Decision D Generic Cost of Capital. Costs Award Decision 21856-D01-2016 Costs Award December 2, 2016 Alberta Utilities Commission Decision 21856-D01-2016 Costs Award Proceeding 21856 December 2, 2016 Published by Alberta Utilities Commission Fifth Avenue

More information

Decision D FortisAlberta Inc Performance-Based Regulation Capital Tracker True-Up. January 11, 2018

Decision D FortisAlberta Inc Performance-Based Regulation Capital Tracker True-Up. January 11, 2018 Decision 22741-D01-2018 FortisAlberta Inc. 2016 Performance-Based Regulation Capital Tracker True-Up January 11, 2018 Alberta Utilities Commission Decision 22741-D01-2018 FortisAlberta Inc. 2016 Performance-Based

More information

ENMAX Energy Corporation

ENMAX Energy Corporation Decision 23006-D01-2018 Regulated Rate Option - Energy Price Setting Plan Monthly Filings for Acknowledgment 2017 Quarter 3 February 7, 2018 Alberta Utilities Commission Decision 23006-D01-2018: Regulated

More information

EPCOR Distribution & Transmission Inc.

EPCOR Distribution & Transmission Inc. Decision 22603-D01-2017 June 23, 2017 Alberta Utilities Commission Decision 22603-D01-2017 Proceeding 22603 June 23, 2017 Published by the: Alberta Utilities Commission Fifth Avenue Place, Fourth Floor,

More information

Decision FortisAlberta Inc Phase II Distribution Tariff. January 27, 2014

Decision FortisAlberta Inc Phase II Distribution Tariff. January 27, 2014 Decision 2014-018 FortisAlberta Inc. 2012-2014 Phase II Distribution Tariff January 27, 2014 The Alberta Utilities Commission Decision 2014-018: FortisAlberta Inc. 2012-2014 Phase II Distribution Tariff

More information

ATCO Gas and Pipelines Ltd.

ATCO Gas and Pipelines Ltd. Decision 2738-D01-2016 Z Factor Application for Recovery of 2013 Southern Alberta Flood Costs March 16, 2016 Alberta Utilities Commission Decision 2738-D01-2016 Z Factor Application for Recovery of 2013

More information

Decision D Performance-Based Regulation Plans for Alberta Electric and Gas Distribution Utilities.

Decision D Performance-Based Regulation Plans for Alberta Electric and Gas Distribution Utilities. Decision 22082-D01-2017 2018-2022 Performance-Based Regulation Plans for Alberta Electric and Gas Distribution Utilities February 6, 2017 Alberta Utilities Commission Decision 22082-D01-2017 2018-2022

More information

Consumers Coalition of Alberta

Consumers Coalition of Alberta Decision 22157-D01-2017 Decision on Preliminary Question AltaLink Management Ltd. 2012-2013 Deferral Account Reconciliation Costs Award February 15, 2017 Alberta Utilities Commission Decision 22157-D01-2017

More information

Decision ATCO Gas General Rate Application Phase I Compliance Filing to Decision Part B.

Decision ATCO Gas General Rate Application Phase I Compliance Filing to Decision Part B. Decision 2006-083 2005-2007 General Rate Application Phase I Compliance Filing to Decision 2006-004 August 11, 2006 ALBERTA ENERGY AND UTILITIES BOARD Decision 2006-083: 2005-2007 General Rate Application

More information

Decision ATCO Electric Ltd. February 1, 2013 Interim Tariff. January 18, 2013

Decision ATCO Electric Ltd. February 1, 2013 Interim Tariff. January 18, 2013 Decision 2013-015 February 1, 2013 Interim Tariff January 18, 2013 The Alberta Utilities Commission Decision 2013-015: February 1, 2013 Interim Tariff Application No. 1609127 Proceeding ID No. 2305 January

More information

AltaLink Management Ltd.

AltaLink Management Ltd. Decision 22612-D01-2018 November 13, 2018 Alberta Utilities Commission Decision 22612-D01-2018 to PiikaniLink L.P. and KainaiLink L.P. and the Proceeding 22612 Applications 22612-A001, 22612-A002, 22612-A003,

More information

AltaLink Management Ltd.

AltaLink Management Ltd. Decision 3524-D01-2016 AltaLink Management Ltd. 2015-2016 General Tariff Application May 9, 2016 Alberta Utilities Commission Decision 3524-D01-2016 AltaLink Management Ltd. 2015-2016 General Tariff Application

More information

Decision D FortisAlberta Inc. Light-Emitting Diode Lighting Conversion Maintenance Multiplier for the City of St.

Decision D FortisAlberta Inc. Light-Emitting Diode Lighting Conversion Maintenance Multiplier for the City of St. Decision 21754-D01-2016 Light-Emitting Diode Lighting Conversion Maintenance Multiplier for the City of St. Albert August 11, 2016 Alberta Utilities Commission Decision 21754-D01-2016 Light-Emitting Diode

More information

EPCOR Energy Alberta GP Inc. AUC RULE 005: ANNUAL REGULATED RATE TARIFF (RRT) FINANCIAL AND OPERATIONAL RESULTS FOR THE YEAR ENDED DECEMBER 31, 2016

EPCOR Energy Alberta GP Inc. AUC RULE 005: ANNUAL REGULATED RATE TARIFF (RRT) FINANCIAL AND OPERATIONAL RESULTS FOR THE YEAR ENDED DECEMBER 31, 2016 EPCOR Energy Alberta GP Inc. AUC RULE 005: ANNUAL REGULATED RATE TARIFF (RRT) FINANCIAL AND OPERATIONAL RESULTS FOR THE YEAR ENDED DECEMBER 31, 2016 TABLE OF CONTENTS Schedule Description A Purpose of

More information

Decision D ATCO Electric Ltd. Amounts to be Paid Into and Out of Balancing Pool for Chinchaga Power Plant Sale

Decision D ATCO Electric Ltd. Amounts to be Paid Into and Out of Balancing Pool for Chinchaga Power Plant Sale Decision 21833-D01-2016 Amounts to be Paid Into and Out of Balancing Pool for Chinchaga Power Plant Sale December 20, 2016 Alberta Utilities Commission Decision 21833-D01-2016 Proceeding 21833 December

More information

Alberta Electric System Operator

Alberta Electric System Operator Decision 23065-D01-2017 Alberta Electric System Operator 2018 Independent System Operator Tariff Update November 28, 2017 Alberta Utilities Commission Decision 23065-D01-2017 Alberta Electric System Operator

More information

St NW, Edmonton, AB T5H 0E8 Canada epcor.com

St NW, Edmonton, AB T5H 0E8 Canada epcor.com 2000 10423 101 St NW, Edmonton, AB T5H 0E8 Canada epcor.com May 1, 2018 Alberta Utilities Commission 10th Floor, 10055 106 Street Edmonton, AB T5J 2Y2 Attention: Mr. Blair Miller Executive Director, Rates

More information

Decision D Alberta PowerLine L.P. Tariff Application. January 23, 2018

Decision D Alberta PowerLine L.P. Tariff Application. January 23, 2018 Decision 23161-D01-2018 Alberta PowerLine L.P. Tariff Application January 23, 2018 Alberta Utilities Commission Decision 23161-D01-2018 Alberta PowerLine L.P. Tariff Application Proceeding 23161 January

More information

ENMAX Energy Corporation

ENMAX Energy Corporation Decision 22510-D01-2017 2016-2018 Energy Price Setting Plan Compliance Filing October 30, 2017 Alberta Utilities Commission Decision 22510-D01-2017 2016-2018 Energy Price Setting Plan Compliance Filing

More information

ATCO Gas and Pipelines Ltd. (South)

ATCO Gas and Pipelines Ltd. (South) Decision 3421-D01-2015 Northeast Calgary Connector Pipeline January 16, 2015 The Alberta Utilities Commission Decision 3421-D01-2015: Northeast Calgary Connector Pipeline Application 1610854 Proceeding

More information

AltaGas Utilities Inc.

AltaGas Utilities Inc. Decision 23740-D01-2018 AltaGas Utilities Inc. 2018-2019 Unaccounted-For Gas Rider E and Rider H October 25, 2018 Alberta Utilities Commission Decision 23740-D01-2018 AltaGas Utilities Inc. 2018-2019 Unaccounted-For

More information

2013 Generic Cost of Capital

2013 Generic Cost of Capital Decision 2191-D01-2015 2013 Generic Cost of Capital March 23, 2015 Alberta Utilities Commission Decision 2191-D01-2015 2013 Generic Cost of Capital Proceeding 2191 Application 1608918-1 March 23, 2015

More information

2011 Generic Cost of Capital

2011 Generic Cost of Capital Decision 2011-474 2011 Generic Cost of Capital December 8, 2011 The Alberta Utilities Commission Decision 2011-474: 2011 Generic Cost of Capital Application No. 1606549 Proceeding ID No. 833 December 8,

More information

ATCO Electric and ATCO Pipelines. Application for ATCO Electric and ATCO Pipelines License Fees

ATCO Electric and ATCO Pipelines. Application for ATCO Electric and ATCO Pipelines License Fees Decision 21571-D01-2016 and ATCO Pipelines 2015-2016 License Fees August 17, 2016 Alberta Utilities Commission Decision 21571-D01-2016 and ATCO Pipelines 2015-2016 License Fees Proceeding 21571 August

More information

Decision D FortisAlberta Inc. Light-Emitting Diode (LED) Lighting Conversion Maintenance Multiplier Filing for 30 Customers in 2018

Decision D FortisAlberta Inc. Light-Emitting Diode (LED) Lighting Conversion Maintenance Multiplier Filing for 30 Customers in 2018 Decision 23730-D01-2018 Light-Emitting Diode (LED) Lighting Conversion Maintenance Multiplier Filing for 30 Customers in 2018 September 7, 2018 Alberta Utilities Commission Decision 23730-D01-2018 Light-Emitting

More information

EPCOR Energy Services (Alberta) Ltd.

EPCOR Energy Services (Alberta) Ltd. Alberta Energy and Utilities Board Decision 2002-112 EPCOR Energy Services (Alberta) Ltd. 2003 Regulated Rate Option Settlement Agreement December 20, 2002 ALBERTA ENERGY AND UTILITIES BOARD Decision 2002-112:

More information

FortisAlberta Inc. Sale and Transfer of the Municipality of Crowsnest Pass Electric Distribution Assets

FortisAlberta Inc. Sale and Transfer of the Municipality of Crowsnest Pass Electric Distribution Assets Decision 21785-D01-2018 Sale and Transfer of the Electric Distribution Assets June 5, 2018 Alberta Utilities Commission Decision 21785-D01-2018 Sale and Transfer of the Electric Distribution System Assets

More information

Canadian Natural Resources Limited

Canadian Natural Resources Limited Decision 22669-D03-2017 Application for an Order Permitting the Sharing of Records Not Available to the Public Between Canadian Natural Resources Limited and ATCO Power Canada Ltd. July 21, 2017 Alberta

More information

AltaGas Utilities Inc.

AltaGas Utilities Inc. Decision 23623-D01-2018 AltaGas Utilities Inc. 2017 Capital Tracker True-Up Application December 18, 2018 Alberta Utilities Commission Decision 23623-D01-2018 AltaGas Utilities Inc. 2017 Capital Tracker

More information

ENMAX Power Corporation

ENMAX Power Corporation Decision 22756-D01-2017 Tax Agreement with The City of Calgary September 7, 2017 Alberta Utilities Commission Decision 22756-D01-2017 Tax Agreement with The City of Calgary Proceeding 22756 September 7,

More information

AltaLink Management Ltd.

AltaLink Management Ltd. Decision 21054-D01-2016 2013-2014 General Tariff Application (Proceeding 2044-Reopened for Midgard Audit) March 7, 2016 Alberta Utilities Commission Decision 21054-D01-2016: Proceeding 21054 March 7,

More information

Collaborative Process

Collaborative Process Alberta Energy and Utilities Board Utility Cost Order 2006-065 Uniform System of Accounts and Minimum Filing Requirements Cost Awards ALBERTA ENERGY AND UTILITIES BOARD Utility Cost Order 2006-065 Uniform

More information

AltaLink Investment Management Ltd. and SNC Lavalin Transmission Ltd. et al.

AltaLink Investment Management Ltd. and SNC Lavalin Transmission Ltd. et al. Decision 2014-326 AltaLink Investment Management Ltd. and SNC Lavalin Transmission Ltd. et al. Proposed Sale of AltaLink, L.P. Transmission Assets and Business to MidAmerican (Alberta) Canada Holdings

More information

ATCO Pipelines ATCO Gas and Pipelines Ltd. CU Inc. Canadian Utilities Limited

ATCO Pipelines ATCO Gas and Pipelines Ltd. CU Inc. Canadian Utilities Limited Decision 2012-068 Disposition of Surplus Salt Cavern Assets in the Fort Saskatchewan Area March 16, 2012 The Alberta Utilities Commission Decision 2012-068:,,, Disposition of Surplus Salt Cavern Assets

More information

Decision D EQUS REA LTD.

Decision D EQUS REA LTD. Decision 22293-D01-2017 Application for Orders Amending the Terms and Conditions of Service and Rate Schedules of FortisAlberta Inc. in Respect of Option M Distribution Generation Credit/Charge October

More information

Decision EUB Proceeding

Decision EUB Proceeding Decision 2007-017 Implementation of the Uniform System of Accounts and Minimum Filing Requirements for Alberta s Electric Transmission and Distribution Utilities March 6, 2007 ALBERTA ENERGY AND UTILITIES

More information

Canadian Natural Resources Limited

Canadian Natural Resources Limited Decision 21306-D01-2016 Determination of Compensation for 9L66/9L32 Transmission Line Relocation August 16, 2016 Alberta Utilities Commission Decision 21306-D01-2016 Determination of Compensation for 9L66/9L32

More information

E.ON Climate & Renewables Canada Ltd. Grizzly Bear Creek Wind Power Project

E.ON Climate & Renewables Canada Ltd. Grizzly Bear Creek Wind Power Project Decision 21513-D01-2016 Grizzly Bear Creek Wind Power Project July 21, 2016 Alberta Utilities Commission Decision 21513-D01-2016 Grizzly Bear Creek Wind Power Project Proceeding 21513 July 21, 2016 Published

More information

Decision D Balancing Pool

Decision D Balancing Pool Decision 22184-D10-2017 Application for an Order Permitting the Sharing of Records Not Available to the Public Between the, TransAlta Generation Partnership, and Capital Power Generation Services Inc.

More information

Senior Manager, Government and Regulatory Affairs Direct Energy Marketing Limited

Senior Manager, Government and Regulatory Affairs Direct Energy Marketing Limited December 22, 2017 Decision 23226-D01-2017 Direct Energy Marketing Limited Suite 501, 525 Eighth Ave. S.W. Calgary, Alta. T2P 1G1 Attention: Ms. Nicole Black Senior Manager, Government and Regulatory Affairs

More information

West Wetaskiwin Rural Electrification Association Ltd.

West Wetaskiwin Rural Electrification Association Ltd. Decision 22067-D01-2016 West Wetaskiwin Rural Electrification Association Ltd. Varied Code of Conduct Regulation Compliance Plan December 21, 2016 Alberta Utilities Commission Decision 22067-D01-2016 West

More information

Nova Scotia Company and TE-TAU, Inc.

Nova Scotia Company and TE-TAU, Inc. Alberta Energy and Utilities Board Decision 2004-025 3057246 Nova Scotia Company and TE-TAU, Inc. Request for Relief Under Section 101(2) of the PUB Act March 16, 2004 ALBERTA ENERGY AND UTILITIES BOARD

More information

AltaLink Management Ltd. & EPCOR Distribution & Transmission Inc.

AltaLink Management Ltd. & EPCOR Distribution & Transmission Inc. Decision 2013-280 AltaLink Management Ltd. & EPCOR Distribution & Transmission Inc. Heartland Transmission Project Amendment Structure T176 Repositioning Costs Award July 29, 2013 The Alberta Utilities

More information

Alberta Electric System Operator 2017 ISO Tariff Update

Alberta Electric System Operator 2017 ISO Tariff Update Alberta Electric System Operator 2017 ISO Tariff Update Date: October 20, 2016 Prepared by: Alberta Electric System Operator Prepared for: Alberta Utilities Commission Classification: Public Table of Contents

More information

Decision D ATCO Electric Ltd Transmission General Tariff Application. Costs Award

Decision D ATCO Electric Ltd Transmission General Tariff Application. Costs Award Decision 21747-D01-2017 January 30, 2017 Alberta Utilities Commission Decision 21747-D01-2017 Proceeding 21747 January 30, 2017 Published by Alberta Utilities Commission Fifth Avenue Place, Fourth Floor,

More information

Decision D FortisAlberta Inc.

Decision D FortisAlberta Inc. Decision 23063-D01-2018 Light-Emitting Diode Lighting Conversion Maintenance Multiplier Filing January 30, 2018 Alberta Utilities Commission Decision 23063-D01-2018 Light-Emitting Diode Lighting Conversion

More information

Langdon Waterworks Limited

Langdon Waterworks Limited Decision 20372-D01-2015 May 14, 2015 Alberta Utilities Commission Decision 20372-D01-2015 Proceeding 20372 May 14, 2015 Published by the: Alberta Utilities Commission Fifth Avenue Place, Fourth Floor,

More information

AltaLink Management Ltd.

AltaLink Management Ltd. Decision 22025-D03-2017 Red Deer Area Transmission Development Amendment Application June 8, 2017 Decision 22025-D03-2017 Red Deer Area Transmission Development Amendment Application Proceeding 22025 Applications

More information

Livingstone Landowners Guild

Livingstone Landowners Guild Decision 20846-D01-2016 Livingstone Landowners Guild Application for Review of Decision 2009-126 Needs Identification Document Application Southern Alberta Transmission System Reinforcement as amended

More information

Mayerthorpe and District Rural Electrification Association Ltd.

Mayerthorpe and District Rural Electrification Association Ltd. Decision 22692-D01-2018 Mayerthorpe and District Rural Electrification Association Ltd. Varied Code of Conduct Regulation Compliance Plan January 31, 2018 Alberta Utilities Commission Decision 22692-D01-2018

More information

FORTISALBERTA INC. MANAGEMENT S DISCUSSION AND ANALYSIS

FORTISALBERTA INC. MANAGEMENT S DISCUSSION AND ANALYSIS FORTISALBERTA INC. MANAGEMENT S DISCUSSION AND ANALYSIS November 5, 2014 The following ( MD&A ) of FortisAlberta Inc. (the Corporation ) should be read in conjunction with the following: (i) the unaudited

More information

TransCanada Energy Ltd.

TransCanada Energy Ltd. Decision 22302-D01-2017 Request for Permitting the Sharing of Records Not Available to the Public Between and Pembina Pipeline Corporation May 26, 2017 Alberta Utilities Commission Decision 22302-D01-2017

More information

Decision CU Water Limited. Disposition of Assets. April 30, 2010

Decision CU Water Limited. Disposition of Assets. April 30, 2010 Decision 2010-192 Disposition of Assets April 30, 2010 ALBERTA UTILITIES COMMISSION Decision 2010-192: Disposition of Assets Application No. 1606042 Proceeding ID. 569 April 30, 2010 Published by Alberta

More information

INVESTOR PRESENTATION JUNE 2018

INVESTOR PRESENTATION JUNE 2018 INVESTOR PRESENTATION JUNE 2018 LEGAL DISCLAIMER Statements made by representatives for ATCO Ltd. and Canadian Utilities Limited and information provided in this presentation may be considered forward-looking

More information

AltaLink Management Ltd.

AltaLink Management Ltd. Decision 20986-D01-2016 Southwest Calgary Ring Road Transmission Project August 31, 2016 Alberta Utilities Commission Decision 20986-D01-2016 Southwest Calgary Ring Road Transmission Project Proceeding

More information

Capital Power Corporation. Halkirk 2 Wind Power Project

Capital Power Corporation. Halkirk 2 Wind Power Project Decision 23255-D01-2018 Capital Power Corporation Halkirk 2 Wind Power Project July 9, 2018 Alberta Utilities Commission Decision 23255-D01-2018 Capital Power Corporation Halkirk 2 Wind Power Project Proceeding

More information

INVESTOR PRESENTATION JUNE 2018

INVESTOR PRESENTATION JUNE 2018 INVESTOR PRESENTATION JUNE 2018 LEGAL DISCLAIMER Statements made by representatives for ATCO Ltd. and Canadian Utilities Limited and information provided in this presentation JUNE be considered forward-looking

More information

AltaGas Utilities Inc.

AltaGas Utilities Inc. Decision 21822-D01-2016 AltaGas Utilities Inc. 2016-2017 Unaccounted-For Gas Rider E and Rider H September 1, 2016 Alberta Utilities Commission Decision 21822-D01-2016 AltaGas Utilities Inc. 2016-2017

More information

NaturEner Energy Canada Inc.

NaturEner Energy Canada Inc. Decision 2009-174 Review and Variance of Alberta Utilities Commission Decision 2009-042 (October 22, 2009) ALBERTA UTILITIES COMMISSION Decision 2009-174, Review and Variance of Alberta Utilities Commission

More information

Service area. EPCOR Distribution & Transmission Inc. a) Subject to rules b), c), d), and e),

Service area. EPCOR Distribution & Transmission Inc. a) Subject to rules b), c), d), and e), 9. TRANSMISSION 9.1 Facility Projects 9.1.1 Eligible TFO 9.1.1.1 Eligibility by Service Area Subject to rule 9.1.1.2 b), c), d), and e) each service area shall have one TFO eligible to apply for the construction

More information

Financial Statements. AltaLink, L.P. Years ended December 31, 2010 and 2009

Financial Statements. AltaLink, L.P. Years ended December 31, 2010 and 2009 Financial Statements FINANCIAL STATEMENTS INDEPENDENT AUDITOR S REPORT To the Partners of We have audited the accompanying financial statements of, which comprise the balance sheets as at December 31,

More information

2009 Generic Cost of Capital

2009 Generic Cost of Capital Decision 2009-216 2009 Generic Cost of Capital November 12, 2009 ALBERTA UTILITIES COMMISSION Decision 2009-216: 2009 Generic Cost of Capital Application No. 1578571 Proceeding ID. 85 November 12, 2009

More information

ORDER NUMBER G IN THE MATTER OF the Utilities Commission Act, RSBC 1996, Chapter 473. and

ORDER NUMBER G IN THE MATTER OF the Utilities Commission Act, RSBC 1996, Chapter 473. and Suite 410, 900 Howe Street Vancouver, BC Canada V6Z 2N3 bcuc.com P: 604.660.4700 TF: 1.800.663.1385 F: 604.660.1102 ORDER NUMBER G-48-19 IN THE MATTER OF the Utilities Commission Act, RSBC 1996, Chapter

More information

AltaLink Management Ltd. and EPCOR Distribution & Transmission Inc.

AltaLink Management Ltd. and EPCOR Distribution & Transmission Inc. Decision 2012-124 Decision on Request for Review and Variance of AUC Decision 2011-436 Heartland Transmission Project May 14, 2012 The Alberta Utilities Commission Decision 2012-124: Decision on Request

More information

Decision TykeWest Limited. Setting of Fees for a Common Carrier Order. July 15, 2009

Decision TykeWest Limited. Setting of Fees for a Common Carrier Order. July 15, 2009 Decision 2009-106 Setting of Fees for a Common Carrier Order July 15, 2009 ALBERTA UTILITIES COMMISSION Decision 2009-106: Setting of Fees for a Common Carrier Order Application No. 1567541 July 15, 2009

More information

Audited Financial Statements For the years ended December 31, 2017 and 2016

Audited Financial Statements For the years ended December 31, 2017 and 2016 FORTISALBERTA INC. Audited Financial Statements MANAGEMENT S REPORT The accompanying 2017 Financial Statements of FortisAlberta Inc. (the Corporation ) have been prepared by management, who are responsible

More information

ENMAX Corporation 2017 Q2 INTERIM REPORT CAUTION TO READER

ENMAX Corporation 2017 Q2 INTERIM REPORT CAUTION TO READER ENMAX Corporation 2017 Q2 INTERIM REPORT ENMAX Corporation CAUTION TO READER This document contains statements about future events and financial and operating results of ENMAX Corporation and its subsidiaries

More information

Compliance Review 2017

Compliance Review 2017 February 27, 2018 Taking action to promote effective competition and a culture of compliance and accountability in Albertaʹs electricity and retail natural gas markets www.albertamsa.ca Table of Contents

More information

Canadian Hydro Developers, Inc.

Canadian Hydro Developers, Inc. Decision 2005-070 Request for Review and Variance of Decision Contained in EUB Letter Dated April 14, 2003 Respecting the Price Payable for Power from the Belly River, St. Mary and Waterton Hydroelectric

More information

DECISION and Order E and Letter L-15-16

DECISION and Order E and Letter L-15-16 IN THE MATTER OF FortisBC Energy Inc. 2015 Price Risk Management DECISION and Order E-10-16 and Letter L-15-16 June 17, 2016 Before: D. A. Cote, Commissioner/Panel Chair B. A. Magnan, Commissioner R. D.

More information

Langdon Waterworks Limited

Langdon Waterworks Limited Decision 2014-240 August 19, 2014 The Alberta Utilities Commission Decision 2014-240: Application No. 1610617 Proceeding No. 3258 August 19, 2014 Published by The Alberta Utilities Commission Fifth Avenue

More information

The University of Calgary

The University of Calgary Decision 23147-D01-2018 Application for an Order Permitting the Sharing of Records Not Available to the Public Between the University of Calgary and URICA Energy Real Time Ltd. January 30, 2018 Alberta

More information

FORTISALBERTA INC. MANAGEMENT S DISCUSSION AND ANALYSIS

FORTISALBERTA INC. MANAGEMENT S DISCUSSION AND ANALYSIS FORTISALBERTA INC. MANAGEMENT S DISCUSSION AND ANALYSIS April 30, 2018 The following ( MD&A ) of FortisAlberta Inc. (the Corporation ) should be read in conjunction with the following: (i) the unaudited

More information

Yukon Electrical's submissions in reply to each of the IRs disputed by UCG are set out below.

Yukon Electrical's submissions in reply to each of the IRs disputed by UCG are set out below. lidbennett.jones Bennett Jones LLP 4500 Bankers Hall East, 855-2nd Street SW Calgary, Alberta, Canada T2P 4K7 Tel: 403.298.31 00 Fax: 403.265.7219 Allison M. Sears Direct Line: 403.298.3681 e-mail: searsa@bellnetljones.colll

More information

Shell Canada Limited and Canadian Natural Resources Limited

Shell Canada Limited and Canadian Natural Resources Limited Decision 22614-D01-2017 Albian Oil Sands Industrial Complex and June 28, 2017 Alberta Utilities Commission Decision 22614-D01-2017 Albian Oil Sands Industrial Complex and Proceeding 22614 Applications

More information

Daishowa-Marubeni International Ltd.

Daishowa-Marubeni International Ltd. Decision 2011-299 25-MW Condensing Steam Turbine Generator July 8, 2011 The Alberta Utilities Commission Decision 2011-299: 25-MW Condensing Steam Turbine Generator Application No. 1606747 Proceeding ID

More information

The University of Calgary

The University of Calgary Decision 2014-365 Preferential Sharing of Records between the University of Calgary and URICA Energy Real Time Ltd. December 19, 2014 The Alberta Utilities Commission Decision 2014-365: Preferential Sharing

More information

Investigation into the Use of Concessionary Government Funds by Competitive Affiliates of ENMAX Power Corporation

Investigation into the Use of Concessionary Government Funds by Competitive Affiliates of ENMAX Power Corporation Investigation into the Use of Concessionary Government Funds by Competitive Affiliates of ENMAX Power Corporation November 9, 2010 Market Surveillance Administrator 403.705.3181 #500, 400 5th Avenue S.W.,

More information

IN THE MATTER OF AND DECISION. July 29, Before:

IN THE MATTER OF AND DECISION. July 29, Before: IN THE MATTER OF PACIFIC NORTHERN GAS LTD. AND AN APPLICATION TO RECAPITALIZE UNDER AN INCOME TRUST OWNERSHIP STRUCTURE DECISION July 29, 2004 Before: L.A. Boychuk, Panel Chair and Commissioner N.F. Nicholls,

More information

THE DEFERRAL ACCOUNT BALANCES APPLICATIONS

THE DEFERRAL ACCOUNT BALANCES APPLICATIONS Before the Alberta Energy and Utilities Board in THE DEFERRAL ACCOUNT BALANCES APPLICATIONS Deferral Accounts Carrying Cost Evidence of William J. Demcoe Willbren & Co. Ltd. John D. McCormick J. D. McCormick

More information

AltaLink Management Ltd.

AltaLink Management Ltd. Decision 21368-D01-2016 Advance Funding Request from the Cooking Lake Opposition Group Advance Funding Award March 14, 2016 Alberta Utilities Commission Decision 21368-D01-2016: Advance Funding Request

More information

Mackenzie Rural Electrification Association Ltd.

Mackenzie Rural Electrification Association Ltd. Decision 21983-D01-2016 Varied Code of Conduct Regulation Compliance Plan December 14, 2016 Alberta Utilities Commission Decision 21983-D01-2016 Varied Code of Conduct Regulation Compliance Plan Proceeding

More information

Acciona Wind Energy Canada, Inc.

Acciona Wind Energy Canada, Inc. Decision 2013-439 Acciona Wind Energy Canada, Inc. New Dayton Wind Power Project Facility & Substation Costs Award December 11, 2013 The Alberta Utilities Commission Decision 2013-439: Acciona Wind Energy

More information

Decision ATCO Electric Ltd. Bonnyville to Bourque Transmission Line Project. Costs Award. October 9, 2013

Decision ATCO Electric Ltd. Bonnyville to Bourque Transmission Line Project. Costs Award. October 9, 2013 Decision 2013-374 Bonnyville to Bourque Transmission Line Project Costs Award October 9, 2013 The Alberta Utilities Commission Decision 2013-374: Bonnyville to Bourque Transmission Line Project Costs Award

More information