Canadian Hydro Developers, Inc.

Size: px
Start display at page:

Download "Canadian Hydro Developers, Inc."

Transcription

1 Decision Request for Review and Variance of Decision Contained in EUB Letter Dated April 14, 2003 Respecting the Price Payable for Power from the Belly River, St. Mary and Waterton Hydroelectric Plants For the 11 th and Subsequent Years of Their Contracts July 6, 2005

2 ALBERTA ENERGY AND UTILITIES BOARD Decision : Review and Variance of Decision contained in EUB Letter dated April 14, 2003 Application No July 6, 2005 Published by Alberta Energy and Utilities Board Avenue SW Calgary, Alberta T2P 3G4 Telephone: (403) Fax: (403) Web site:

3 Contents 1 INTRODUCTION AND BACKGROUND Details of the Application EUB Process CRITERIA AND SCOPE OF REVIEW LEGISLATIVE REGIME EUB APRIL 14, 2003 DECISION SHOULD THE APRIL 2003 DECISION BE VARIED? Definition of Avoided Cost Is the SPRD Act Avoided Cost Concept Now Obsolete in Alberta s Restructured Industry? Review Panel Conclusion on Whether the April 2003 Decision Should be Varied ORDER EUB Decision (July 6, 2005) i

4

5 ALBERTA ENERGY AND UTILITIES BOARD Calgary Alberta CANADIAN HYDRO DEVELOPERS, INC. REQUEST FOR REVIEW AND VARIANCE OF DECISION Decision CONTAINED IN EUB LETTER DATED APRIL 14, 2003 Application No INTRODUCTION AND BACKGROUND By letter dated November 6, 2002, Canadian Hydro Developers Inc. (Canadian Hydro or CHD) requested the Alberta Energy and Utilities Board (EUB or Board) to set the price applicable to the Belly River Hydro Electric Plant contract for the 11 th and subsequent years of the contract. Canadian Hydro sought direction on the process the Board would use to determine utility avoided cost and on cost recovery in respect of that process. By letter dated April 14, 2003 (April 2003 Decision), the Board advised Canadian Hydro that because integrated utility companies no longer existed in Alberta s restructured electric industry the concept of utility avoided cost, as it related to electric energy generation, was no longer relevant or applicable in Alberta s deregulated generation environment. The Board considered section 4(3)(a) of the Small Power Research and Development Act, RSA 2000, c. S-9 (SPRD Act) to be obsolete and, consequently, the only possible choice for setting small power production contract (SPP Contract) prices in the 11 th and subsequent years was the method prescribed in section 4(3)(b) of the SPRD Act. The Board also advised Canadian Hydro that, while section 4(3) of the SPRD Act requires the Board to set the SPP Contract price for the 11 th and subsequent years of the contract, it did not prescribe a process for making a price determination. Given the Board s view on the obsolescence of utility avoided generation cost in Alberta s restructured electric industry, the Board considered that no process was needed in the circumstances. By letter dated May 14, 2003, Canadian Hydro filed Application (Application) with the EUB requesting that the Board review and vary (R&V) certain aspects of the April 2003 Decision. 1.1 Details of the Application In the Application, Canadian Hydro submitted that the Board made procedural and substantive errors. Canadian Hydro noted that the Board issued the April 2003 Decision without providing Canadian Hydro, or any other parties, an opportunity to present submissions and without providing notice to any parties that the Board intended to make a decision regarding the SPP Contract price. Canadian Hydro submitted that in doing so, the Board made numerous procedural errors in violation of the rules of natural justice, which included: failing to give notice, including failing to comply with the Board s Rules of Practice to issue a Notice of Application or Notice of Hearing, and not providing a copy of the application to parties whose rights may be affected by a decision of the Board EUB Decision (July 6, 2005) 1

6 failing to allow Canadian Hydro a reasonable opportunity to know the case against it, the issues the Board was considering, and the facts upon which the Board was going to base its decision failing to allow Canadian Hydro an opportunity to submit argument on the issues and failing to respond to its request for procedural directions failing to allow all affected parties the right to be heard on this issue Canadian Hydro submitted that the Board made substantive errors in determining that utility avoided cost no longer existed. Canadian Hydro argued that the Board incorrectly relied on and interpreted the Small Power Inquiry, PUB Report E88001, ERCB Report 88-A, February 29, 1988 (the Small Power Inquiry Report) in reaching its decision on the meaning of utility avoided costs. Canadian Hydro submitted that the Board erred in law and jurisdiction by failing to follow the recommendations and methodology set out in the Small Power Inquiry Report. Canadian Hydro also argued that the Board erred in law in taking into account matters relating to industry restructuring that could not have been in the mind of the legislature when the SPRD Act was enacted. Further, Canadian Hydro submitted that weight should be given to the fact that the pricing provisions of the SPRD Act have not been amended since deregulation. Canadian Hydro also argued that the Board s decision had the effect of retroactively changing the SPP Contracts without jurisdiction. Canadian Hydro referred to s of the Electric Utilities Act S.A. 2003, c. E-5.1 (EUA) in support of this proposition and argued that the intent of this provision was that contracts should continue to be paid by the Balancing Pool. Canadian Hydro considered that the Board acted without jurisdiction by failing to set the SPP Contract price in accordance with the requirements of the SPRD Act. That is, either using utility avoided costs or the indexed price under section 4(3)(b). Canadian Hydro submitted that it would be prejudiced and would suffer damages because it will be deprived of the benefit following from the alternative pricing mechanisms contained in the SPRD Act. 1.2 EUB Process For the Application, the Board employed the two-step process that it normally uses when dealing with an R&V application. On March 4, 2004, the Board requested submissions from interested parties on the Application. This was to assist the Board in determining the R&V Phase 1 process question of whether a review should be undertaken based on whether the applicant established significant doubt as to the correctness of the decision according to the provisions of section 126(2) of the EUA and section 46 of the Board s Rules of Practice. The Board received a submission from the Industrial Power Consumers Association of Alberta (IPCAA). Letters were also received from the Balancing Pool, which advised it had no comment at that time, but wished to remain involved in the process, and from the FIRM Group of Customers who indicated they supported IPCAA s position. 2 EUB Decision (July 6, 2005)

7 By letter dated August 16, 2004, the Board advised interested parties to the Application that the Board had granted CHD s request for a review and was proceeding to the second stage (Phase 2) of the R&V process. The division of the Board assigned to review and decide Phase 2 of the Application (Review Panel) consisted of Board Member B. T. McManus, Q. C. (Presiding Member), Board Member R. G. Lock, P.Eng., and acting Board Member R. C. Clark. The Review Panel determined that the Phase 2 review would be conducted by way of a written process and that it would be helpful to receive submissions related to utility avoided cost in the restructured Alberta electric industry. The original schedule for submissions and reply submissions was significantly delayed due to the need for Board rulings on a number of procedural motions relating to the amount of Phase 1 information that should be used in Phase 2 and who should be responsible for participants costs. Following the Board procedural rulings, the Review Panel established the following schedule in a letter dated March 1, 2005 to complete the record of the proceeding. CHD Amendment or Refiling of its Phase II submission March 11, 2005 Submissions from Interested Parties March 29, 2005 Reply Submission from CHD, if any April 12, 2005 The Review Panel received Phase 2 submissions from CHD, the Balancing Pool, IPCAA and the FIRM Group of Customers on March 29, 2005 and a Reply Submission from CHD on April 12, Accordingly, the Review Panel considers that the record of this proceeding closed on April 12, This decision addresses the Review Panel s Phase 2 findings and determinations with respect to the Application. 2 CRITERIA AND SCOPE OF REVIEW To assist it in addressing the R&V Phase 2 question of whether the April 2003 Decision should be varied and, if so, how it should be varied, the Review Panel sought submissions from interested parties on the following questions: 1. Whether utility avoided cost as contemplated in the Small Power Research and Development Act exists in the context of the restructured Alberta electric industry. 2. If yes, how should utility avoided cost be determined. The Review Panel recognizes that the two questions posed to interested parties are interrelated. If the first question is answered in the negative, there is no need to address the second one. EUB Decision (July 6, 2005) 3

8 One of the criticisms of the April 2003 Decision was that the Board s determination was reached without the benefit of input from Canadian Hydro and other interested parties. The Review Panel will review the Board s determination in the April 2003 Decision with the full benefit of the submissions filed in response to the Board s request to determine whether the April 2003 Decision should be varied. In arriving at its decision the Review Panel must be guided by the provisions of section 126(2)(d) of the EUA, which states: 126(2) Any person affected by an order approving a tariff may ask the Board to review the order (d) if, in the Board s opinion, the order contains an error of fact or law, and if the request for a review on that ground is filed with the Board not later than 90 days after the making of the order. The Review Panel notes that Canadian Hydro filed the Application within the 90-day timeframe and that subsection (d) further requires that the Review Panel must find an error of fact or law before it can vary the determination in the April 2003 Decision. 3 LEGISLATIVE REGIME Subsequent to the enactment of the SPRD Act in 1989, some public utilities and small power producers entered into SPP Contracts pursuant to the SPRD Act. Where the term of an SPP Contract exceeds 10 years, section 4(3) of the SPRD Act obliges the EUB to set the price payable under the contract for the 11 th and subsequent years as follows: (3) Where the term of a small power production contract is greater than 10 years, the Public Utilities Board shall, during the 10th year of the contract, review and adjust the price payable for power delivered under the contract so that the price payable for the 11th year and subsequent years of the contract will be the greater of a) the utility avoided cost, and b) the price that would be payable during the 10 th year of the contract if determined under subsection (1)(b)(ii). Subsection 4(1)(b)(ii) of the SPRD Act applies primarily to SPP Contracts that have not yet reached the 11 th year of their contract term and the subsection states that a SPP Contract must: b) provide that the public utility is to pay to the small power producer in respect of power delivered under the contract for the first 10 years of the contract an amount per kilowatt hour determined by one of the following options: (ii) $ per kilowatt hour for power delivered in 1990 and, for power delivered in 1991 and subsequent years, a price per kilowatt hour based on $ and adjusted annually for inflation in the manner prescribed in the regulations. 4 EUB Decision (July 6, 2005)

9 The Small Power Research and Development Regulation, AR 336/88 (Regulation) provides the escalation factor used in subsection 4(1)(b)(ii). It states: 5.1 For the purposes of section 3(1)(b)(ii) (now s. 4) of the Act, the annual adjustment of the price for inflation shall be calculated on January 1 of each year by increasing the price for the previous calendar year by a percentage equal to the rate of inflation for that previous calendar year for Alberta as shown in the Alberta Consumer Price Index, All Items, published by Statistics Canada. Alberta Energy has been setting the price annually for the subsection 4(1)(b)(ii) escalated price option. In January 2005, the 2005 escalated price was set at 6.94 cents per kilowatt-hour. The Independent Power and Small Power Regulation, AR 285/95 and AR177/2000 were both passed to continue the SPP Contracts in the restructured industry environment. These regulations specify inter alia that the SPRD generators are to be deemed to have a standing offer of zero for any electric energy offered into the pool, and that additional incremental costs associated with a generator having to upgrade its metering, or any other reasonable costs that are incurred by the SPRD generator as a result of the coming into force of the EUA, or the regulations or amendments to the regulations would be paid by the Balancing Pool. The more recent Independent Power and Small Power Regulation AR 111/2003, which superseded and repealed AR 285/95, sets out among other things the financial obligations of the Balancing Pool to the utility that is the counterparty to SPP Contracts such as those held by CHD. Where the contract price exceeds the pool price in an hour, the Balancing Pool pays the difference to the utility. Where the contract price is less than the pool price in an hour, the Balancing Pool recovers the difference from the utility. Settlement is done on a monthly basis. The Balancing Pool is also responsible for paying the utility costs for administration of the SPP Contracts. 4 EUB APRIL 14, 2003 DECISION By letter dated November 6, 2002, CHD requested that the Board set the price under the Belly River contract for the 11 th year and subsequent years as required under the SPRD Act. Subsequently, by letter dated February 3, 2003, CHD requested the Board to also set the price for the St. Mary and Waterton contracts held by CHD. In response to CHD s request, the Board interpreted the words utility avoided costs contained in section 4(3)(a) of the SPRD Act. The Board s interpretation had regard for the structure of the electric industry at the time that the SPRD Act was enacted, and regard also for subsequent changes to the electric industry that occurred in the 1990s and early 2000s. On this basis, the Board found that legislative changes had rendered section 4(3)(a) of the SPRD Act meaningless and obsolete. Notwithstanding the Board s finding that section 4(3)(a) of the SPRD Act had no force or effect, the Board was still required by the SPRD Act to make a determination respecting price for the 11 th year and subsequent years of the CHD SPP Contracts. Therefore, the Board proceeded to do so according to the remaining price option defined by section 4(3)(b) of the SPRD Act. The Board declared the price for the 11 th and subsequent years of the CHD SPP Contracts to be the EUB Decision (July 6, 2005) 5

10 price that would be payable during the 10 th year of the contract, if determined under subsection 4(1)(b)(ii) of the SPRD Act 1. The Review Panel will now review the Board s determination with the benefit of the fullness of the Phase 2 submissions to determine whether the April 2003 Decision should be varied. 5 SHOULD THE APRIL 2003 DECISION BE VARIED? Before the Review Panel can vary the determination in the April 2003 Decision it must find that the Board made an error of fact or law in concluding that the concept of utility avoided cost contained in section 4(3)(a) of the SPRD Act was obsolete and, therefore, that section had no force or effect even though it continues to exist as law. To determine whether utility avoided cost as contemplated in the SPRD Act continues to exist in Alberta s restructured electric industry, the Review Panel must first clarify the meaning of this concept. 5.1 Definition of Avoided Cost In this regard, the SPRD Act is not very helpful. Although the SPRD Act requires the Board to use the utility avoided cost as one of the parameters in determining the price payable under an SPP Contract for the 11 th and subsequent years of the contract, the SPRD Act does not provide a definition of utility avoided cost. The Review Panel must therefore look to other sources to determine a reasonable definition of the term utility avoided cost that is used in the SPRD Act. One logical place to look for such a definition is in the Small Power Inquiry Report that was issued prior to the enactment of the SPRD Act and on which the SPRD Act is purportedly based. In that report, the PUB and ERCB 2 defined the term avoided cost as follows: The Boards accept that SPPs should receive fair value for the energy and capacity they would provide to the AIS as a substitute for what utilities would likely impose in their absence. In broad terms, this is commonly referred to as avoided cost. 3 CHD provided these additional definitions of avoided cost in its submission: and The cost the utility would incur but for the existence of an independent generator or other energy service option. Avoided cost rates have been used as the power purchase price utilities offer independent suppliers (Qualifying Facilities or QFs) 4 "Avoided Cost" is essentially the marginal cost for a public utility to produce one more unit of power. Because QFs reduce the utility's need to produce this additional power This was clarified in a letter from the EUB dated April 15, The Small Power Inquiry was held in 1988 pursuant to Order in Council 211/87 that requested the Public Utilities Board (PUB) and the Energy Resources Conservation Board (ERCB) to inquire into, report upon, and make such recommendations as were necessary or advisable respecting electricity generation by small producers. Page 10, Small Power Inquiry, ERCB Report 88-A and PUB Report E88001, February 29, EUB Decision (July 6, 2005)

11 themselves, the price utilities pay for QF power has been set to the avoided, or marginal, cost. In California, the utilities' avoided costs are determined by the California Public Utilities Commission (CPUC) in public hearings. These prices are designed to simulate a "market price" for energy, and have helped make utilities more efficient in their operations. 5 Although the language is different in the three definitions above, the Review Panel considers all of these definitions to be similar in concept. Central to these definitions is the notion that the cost to be avoided is the cost related to energy and capacity that a utility company would otherwise provide. This is understandable given that these definitions were created in an environment where regulated utilities owned significant generation assets and had an obligation to provide service to end-use customers. This was certainly true at the time of the Small Power Inquiry into small power generation in For purposes of this Application, the Review Panel will adopt the essence of the definitions of utility avoided cost noted above. The Review Panel must now assess whether these definitions and the avoided cost concept they embody have endured the passage of time and more particularly the passage of the EUA in 1995, which deregulated the generation sector of the Alberta electric industry and removed generation from the definition of an electric utility. 5.2 Is the SPRD Act Avoided Cost Concept Now Obsolete in Alberta s Restructured Industry? The April 2003 Decision addressed this question as follows: Deregulation has resulted in industry restructuring and has brought competition to the Province s electric utility industry to replace regulation in the areas of electric energy production and retail markets. This has resulted in the elimination of the regulated market that bound together producer and consumer via the regulated integrated utilities. The market has been opened to independent power producers and independent retailers. For utilities this has meant that the traditional right and obligation to provide electric energy to all of their customers within each of their respective distribution service areas has been eliminated. It was the combination of that right and obligation to serve that provided the impetus for utilities to construct and operate generation facilities or otherwise contract for energy from other wholesale utility suppliers, subject to long-term contracts. Absent the regulated market, regulated utilities have ceased to plan, own or invest in generation facilities or to contract for the long-term supply of electric energy. Respecting customers, large industrial and commercial consumers have since January 1, 2001, wholly obtained their electrical energy supply in the deregulated market. The nonresidential Regulated Rate Option (RRO) for small industrial and commercial customers is scheduled to expire December 31, 2003, to be followed by the RRO for residential and farm customers on December 31, Respecting producers, determination of utility avoided cost 6 for pricing purposes, as reflected in the SPRD Act, was based on determination of Alberta Integrated System Page 10, Small Power Inquiry, ERCB Report 88-A and PUB Report E88001, February 29, 1988 EUB Decision (July 6, 2005) 7

12 (AIS) long-term avoided costs in a completely regulated world as existed prior to 1996 and 2001, when the first and second rounds of deregulation and restructuring were implemented in Alberta. Consequently, for pricing purposes, utility avoided cost has been eliminated with the elimination of regulated electric energy planning, investment and production. Electric energy pricing is now market driven not cost driven. Thus, the concept of utility avoided cost has neither meaning nor application in the deregulated markets that now exist for both producers and consumers in Alberta. Submissions received from interveners indicated support for the Board s assessment in the April 2003 Decision and the conclusion that avoided cost was an obsolete concept in the restructured Alberta electric industry, thereby making it currently impossible to determine utility avoided cost for purposes of section 4(3)(a) of the SPRD Act. The Balancing Pool submitted that because of changes to the Alberta electric industry since the enactment of the SPRD Act, the concept of utility avoided cost, as the term is used in the SPRD Act, does not exist in Alberta s restructured industry. As such, utility avoided cost cannot be calculated. The Balancing Pool submitted that the Board s April 2003 Decision that the concept of utility avoided cost was obsolete was correct and need not be varied. IPCAA submitted that, in the April 2003 Decision, the Board carried out its statutory duties properly and fairly and arrived at the only reasonable alternative given today s environment. In IPCAA s view, it was not necessary to embark on what would be a lengthy, expensive and unnecessary hearing to define a term which no longer has reasonable meaning in Alberta due to changes that have occurred in the industry, particularly when a simple and clear alternative was provided in the SPRD Act. IPCAA submitted that the Board must apply some reasonableness test and if it does, trying to define utility avoided costs in today s environment fails that test. IPCAA submitted that the Application should be dismissed. The FIRM Customers agreed with IPCAA that utility avoided cost, as contemplated in the SPRD Act, does not exist in the context of the restructured Alberta industry because of industry changes that occurred subsequent to the enactment of the SPRD Act. The FIRM Customers submitted that the Application should be dismissed. The Review Panel finds persuasive the Board s analysis and the submissions of the interveners with respect to the existence of avoided cost, as contemplated in the SPRD Act, in the current Alberta market environment. The Board s reasoning was sound and the conclusions reached were reasonable and logical. There is no doubt that since the enactment of the SPRD Act in 1989, there has been a major reduction to the scope of the integrated utilities functions, particularly in the area of generation. In the Review Panel s view, this is cause in and of itself to seriously question whether utility avoided cost currently exists in Alberta with respect to the provision of energy and capacity to the Alberta electricity market. As noted previously, at the foundation of the avoided cost definitions is the notion that the cost to be avoided is the cost related to energy and capacity that a utility company would otherwise provide as a result of an obligation to provide such services. The EUA has created an 8 EUB Decision (July 6, 2005)

13 environment in which the market decides when new generation should be added. This has relieved the former integrated utilities from their obligation to provide energy and capacity for the benefit of the Alberta electricity consumers and for incurring costs to meet such obligations. This diminished role of the former integrated utilities in the Alberta electricity market is also reflected in the EUA by the exclusion of the ownership of generation in the definition of an electric utility. As a utility no longer has a need to incur generating capacity and energy costs, the cost that is contemplated to be avoided in the definitions, and by inference the SPRD Act, no longer exists. CHD submitted that utility avoided cost is a concept that had a recognized meaning at the time the contracts were entered into, and one that is still used in the industry and specifically recognized in the restructured industry structure in Alberta. In support of this position, CHD cited the Independent Assessment Team s determination of the Power Purchase Arrangements in Decisions U99913 and U99073 and the use of a proxy plant methodology in Decision for assessing a discretionary amount under Article 24.3(f) respecting 2001 compensation, which was similar to the proxy plant method proposed by the PUB and ERCB in the Small Power Inquiry Report. CHD appears to imply that the use in recent proceedings of parameters, assumptions, and methodology similar to those used to determine utility long run avoided costs in the Small Power Inquiry Report is proof that the utility avoided cost concept contemplated in the SPRD Act still exists in today s environment. The Review Panel notes that none of the proceedings cited by CHD dealt with either the concept or determination of utility avoided cost. Moreover, the use of the methodology in the instances cited was being applied to totally different concepts. The Review Panel cannot accept that the mere application of the methodology used to give effect to the utility avoided cost concept in the Small Power Inquiry is proof that utility avoided cost still exists. CHD also argued that because section 4(3)(a) of the SPRD Act continues to exist as law despite changes to the SPRD Act, then the concept of utility avoided cost under the SPRD Act must be presumed to continue to exist in today s environment. With respect, the Review Panel disagrees. There have been other instances when specific provisions of an Act have outlived their usefulness, but continued beyond the point where they were no longer relevant before they were eventually repealed. For example, in Decision the Board came to a similar conclusion with respect to the interpretation of a section of the Public Utilities Act and found that it had been rendered meaningless by subsequent changes to the Municipal Government Act. Consequential changes to a particular act or provision in the act resulting from changes to another act or due to the enactment of new legislation, sometimes get overlooked and the obsolete sections are repealed at a later point in time. Indeed, it is a recognized principle of statutory interpretation that legislative provisions may be rendered obsolete such that they have no force or effect because the facts that supported their adoption no longer exist or there are no longer any facts to which they can apply even though the provision in question has not yet been repealed or amended by the legislature. 7 The Review Panel notes that while there were consequential changes to the SPRD Act resulting from the enactment of the EUA, these changes appeared to be focused on the short term question of the continuation and administration of the SPP Contracts during the first 10 years of the contract term. The Review Panel considers that the 7 Sullivan and Driedger on the Construction of Statutes, 4 th ed., Ruth Sullivan (2002, Butterworths), p EUB Decision (July 6, 2005) 9

14 short-term focus of the SPRD Act amendment may be indicative of the fact that not much attention, if any, was given to the longer term pricing provisions contained in section 4(3). Accordingly, the Review Panel does not find CHD s argument regarding the continued existence of the concept of utility avoided cost in section 4(3)(a) to be persuasive. In the Review Panel s view, a provision within an act can continue as law even though the facts that originally supported its inclusion may no longer exist. In that case, it is not possible to give effect to the provisions of the section. The Review Panel believes this to be the case with section 4(3)(a) of the SPRD Act as a result of the enactment of the EUA subsequent to the enactment of the SPRD Act. CHD also argued that in failing to set a price for the SPP Contracts based on utility avoided cost, the Board has frustrated the SPP Contracts and the intent of the SPRD Act. With regard to the SPP Contracts themselves, CHD submitted that the price setting method in the SPRD Act requires a determination of the greater of the two prices, not a choice between them. Failing to set a price based on utility avoided cost frustrates the SPP Contracts because the contract price can no longer be determined as intended by the parties, which CHD submits was to allow small power producers to get the benefit of a pricing mechanism that ensured the compensation for the power produced by them remained current over the life of the SPP Contracts with terms greater than 10 years. In regard to the intent of the SPRD Act, CHD argued that the Board imposed its own view of the appropriate pricing mechanism, contrary to section 4(3). As a result, the legislative intent of encouraging investment by small power developers in the industry has been frustrated because the price-setting incentive mechanism in section 4(3) of the SPRD Act is no longer available. CHD further argued that the Board failed to apply a liberal or remedial interpretation that would best attain the objectives of the SPRD Act by failing or refusing to determine the utility avoided cost when setting the price of the SPP Contract. In response to CHD s arguments, the Balancing Pool submitted that CHD s discussion was irrelevant as it incorrectly proceeded on the assumption that utility avoided cost does exist in the deregulated environment. The Balancing Pool argued that the Board, in its April 2003 Decision, did not refuse to abide by the plain meaning of section 4(3)(a) of the SPRD Act because the Board determined that the concept of utility avoided cost was obsolete. Having made that determination, the Board could not employ a concept that no longer existed, and therefore, the Board did not fail to properly interpret the SPRD Act. The Review Panel agrees with CHD that in construing legislation, the Board is to apply ordinary principles of statutory interpretation. These include giving statutory language its plain and ordinary meaning having regard to its context, and applying a broad purposive approach. The Board must also interpret provisions in different enactments with similar subject matter so as to avoid conflict between them. In this case, the Board was faced with a provision in the SPRD Act that it had to interpret, giving consideration to the legislative scheme in the EUA which establishes the overall scheme under which small power producers operate pursuant to the SPRD Act. If the Review Panel were to find that utility avoided cost existed, the Review Panel agrees with CHD that it would be an error if it did not consider this in accordance with section 4(3) of the SPRD Act. However, for the reasons articulated above, the Review Panel has determined that utility avoided cost does not 10 EUB Decision (July 6, 2005)

15 exist in light of the EUA and the resulting changes to the electric industry. The Review Panel does not agree with CHD that applying a broad, liberal and remedial approach to interpreting the SPRD Act requires the Board to necessarily ascribe some meaning to section 4(3)(a). CHD is essentially asking the Review Panel to come up with new parameters for the determination of utility avoided cost since the parameters no longer exist for determining utility avoided cost in the manner intended at the time the SPRD Act was enacted. The Review Panel is of the view that to ascribe a new meaning to utility avoided cost would go beyond applying a liberal and remedial interpretation and would be tantamount to rewriting the legislation. Therefore, setting the price based on section 4(3)(a) is not a option that can be exercised by the Board. 5.3 Review Panel Conclusion on Whether the April 2003 Decision Should be Varied The Review Panel finds that, notwithstanding the lack of input from CHD and other interested parties, the reasoning in the April 2003 Decision was sound and the conclusions reached were reasonable. The Review Panel finds that the concept of utility avoided cost as contemplated in the SPRD Act has not survived the changes to the Alberta electric industry that have occurred since the SPRD Act came into force. This concept is no longer relevant or meaningful in the current restructured Alberta electricity market. Therefore, even though section 4(3)(a) of the SPRD Act continues as law, it has no force or effect because the facts supporting it no longer exist. As a practical matter, section 4(3)(a) of the SPRD Act is not available to the Board as an option when setting the price payable under a SPP Contract for the 11 th year and subsequent years of such contracts. With the inability to apply section 4(3)(a) of the SPRD Act, the only recourse for the Board to discharge its responsibilities under section 4(3) of the SPRD Act is by way of section 4(3)(b). In the April 2003 Decision, the Board applied section 4(3)(b) of the SPRD Act and declared a price for the 11 th and subsequent years of the CHD SPP Contracts. For all of these reasons, the Review Panel sees no need to vary the Board s April 2003 Decision respecting the price for the 11 th year and subsequent years under the Belly River, St. Mary and Waterton contracts held by CHD. EUB Decision (July 6, 2005) 11

16 6 ORDER For and subject to the reasons set out in this Decision, IT IS HEREBY ORDERED THAT Canadian Hydro s request to vary EUB Decision dated April 14, 2003 is denied. Dated in Calgary, Alberta on July 6, ALBERTA ENERGY AND UTILITIES BOARD (original signed by) B. T. McManus, Q.C. Presiding Member (original signed by) R. G. Lock, P.Eng. Member (original signed by) R. C. Clark Acting Member 12 EUB Decision (July 6, 2005)

Decision ATCO Gas General Rate Application Phase I Compliance Filing to Decision Part B.

Decision ATCO Gas General Rate Application Phase I Compliance Filing to Decision Part B. Decision 2006-083 2005-2007 General Rate Application Phase I Compliance Filing to Decision 2006-004 August 11, 2006 ALBERTA ENERGY AND UTILITIES BOARD Decision 2006-083: 2005-2007 General Rate Application

More information

Nova Scotia Company and TE-TAU, Inc.

Nova Scotia Company and TE-TAU, Inc. Alberta Energy and Utilities Board Decision 2004-025 3057246 Nova Scotia Company and TE-TAU, Inc. Request for Relief Under Section 101(2) of the PUB Act March 16, 2004 ALBERTA ENERGY AND UTILITIES BOARD

More information

EPCOR Energy Services (Alberta) Ltd.

EPCOR Energy Services (Alberta) Ltd. Alberta Energy and Utilities Board Decision 2002-112 EPCOR Energy Services (Alberta) Ltd. 2003 Regulated Rate Option Settlement Agreement December 20, 2002 ALBERTA ENERGY AND UTILITIES BOARD Decision 2002-112:

More information

ALBERTA PUBLIC LANDS APPEAL BOARD REPORT

ALBERTA PUBLIC LANDS APPEAL BOARD REPORT Appeal No. PLAB 15-0023-RD2 ALBERTA PUBLIC LANDS APPEAL BOARD REPORT Decision Date: June 19, 2017 IN THE MATTER OF sections 119(d), 121, and 124 of the Public Lands Act, R.S.A. 2000, c. P-40, and sections

More information

Alberta Utilities Commission

Alberta Utilities Commission Decision 22091-D01-2017 Commission-Initiated Proceeding to Review the Terms and November 9, 2017 Decision 22091-D01-2017 Commission-Initiated Proceeding to Review the Terms and Proceeding 22091 Application

More information

Investigation into the Use of Concessionary Government Funds by Competitive Affiliates of ENMAX Power Corporation

Investigation into the Use of Concessionary Government Funds by Competitive Affiliates of ENMAX Power Corporation Investigation into the Use of Concessionary Government Funds by Competitive Affiliates of ENMAX Power Corporation November 9, 2010 Market Surveillance Administrator 403.705.3181 #500, 400 5th Avenue S.W.,

More information

Canadian Natural Resources Limited

Canadian Natural Resources Limited Decision 2009-024 Application for Pool Delineation and Gas Shut-in Athabasca Wabiskaw-McMurray February 24, 2009 ENERGY RESOURCES CONSERVATION BOARD Decision 2009-024:, Application for Pool Delineation

More information

ARBITRATION ACT NO. 4 OF 1995 LAWS OF KENYA

ARBITRATION ACT NO. 4 OF 1995 LAWS OF KENYA LAWS OF KENYA ARBITRATION ACT NO. 4 OF 1995 Revised Edition 2012 [2010] Published by the National Council for Law Reporting with the Authority of the Attorney-General www.kenyalaw.org [Rev. 2012] No.

More information

CANADIAN FOREST OIL LTD. SECTION 39 REVIEW OF DISPOSAL APPROVAL 2011 ABERCB 011 PROVOST FIELD Proceeding No

CANADIAN FOREST OIL LTD. SECTION 39 REVIEW OF DISPOSAL APPROVAL 2011 ABERCB 011 PROVOST FIELD Proceeding No ENERGY RESOURCES CONSERVATION BOARD Calgary Alberta CANADIAN FOREST OIL LTD. SECTION 39 REVIEW OF DISPOSAL APPROVAL 2011 ABERCB 011 PROVOST FIELD Proceeding No. 1669823 DECISION The Energy Resources Conservation

More information

ENMAX Energy Corporation

ENMAX Energy Corporation Decision 22054-D01-2017 Regulated Rate Option Tariff Terms and Conditions Amendment Application April 12, 2017 Alberta Utilities Commission Decision 22054-D01-2017 Regulated Rate Option Tariff Terms and

More information

Order No. 126/18. September 18, 2018 (Amended)

Order No. 126/18. September 18, 2018 (Amended) AN APPLICATION BY MANITOBA HYDRO TO REVIEW AND VARY ORDER 59/18 TIME-OF-USE RATE DIRECTIVE 29 AND REVIEW AND VARY ORDER 59/18 TECHNICAL CONFERENCE ON RETAINED EARNINGS DIRECTIVE 9 PURSUANT TO THE PUBLIC

More information

Page: 1 PROVINCE OF PRINCE EDWARD ISLAND IN THE SUPREME COURT - APPEAL DIVISION

Page: 1 PROVINCE OF PRINCE EDWARD ISLAND IN THE SUPREME COURT - APPEAL DIVISION Page: 1 PROVINCE OF PRINCE EDWARD ISLAND IN THE SUPREME COURT - APPEAL DIVISION Citation: Trigen v. IBEW & Ano. 2002 PESCAD 16 Date: 20020906 Docket: S1-AD-0930 Registry: Charlottetown BETWEEN: AND: TRIGEN

More information

MEG Energy Corporation

MEG Energy Corporation Decision 2006-057 Construct and Operate a 25-kV Electrical Distribution System June 15, 2006 ALBERTA ENERGY AND UTILITIES BOARD Decision 2006-057: Construct and Operate a 25-kV Electrical Distribution

More information

Livingstone Landowners Guild

Livingstone Landowners Guild Decision 20846-D01-2016 Livingstone Landowners Guild Application for Review of Decision 2009-126 Needs Identification Document Application Southern Alberta Transmission System Reinforcement as amended

More information

Calgary Office th Ave. SW, Suite 900 Calgary, AB, Canada T2P 4V1

Calgary Office th Ave. SW, Suite 900 Calgary, AB, Canada T2P 4V1 Calgary Office 1000 5 th Ave. SW, Suite 900 Calgary, AB, Canada T2P 4V1 phone: 403-705-0202 fax: 403-264-8399 email: brobinson@ecojustice.ca www.ecojustice.ca August 24, 2010 Energy Resources Conservation

More information

Environmental Appeal Board

Environmental Appeal Board Environmental Appeal Board Fourth Floor 747 Fort Street Victoria British Columbia Telephone: (250) 387-3464 Facsimile: (250) 356-9923 DECISION NO. 2010-EMA-007(a) In the matter of an appeal under section

More information

Collaborative Process

Collaborative Process Alberta Energy and Utilities Board Utility Cost Order 2006-065 Uniform System of Accounts and Minimum Filing Requirements Cost Awards ALBERTA ENERGY AND UTILITIES BOARD Utility Cost Order 2006-065 Uniform

More information

IN THE COURT OF APPEAL. ARCELORMITTAL POINT LISAS LIMITED (formerly CARIBBEAN ISPAT LIMITED) Appellant AND

IN THE COURT OF APPEAL. ARCELORMITTAL POINT LISAS LIMITED (formerly CARIBBEAN ISPAT LIMITED) Appellant AND TRINIDAD AND TOBAGO IN THE COURT OF APPEAL Civil Appeal No: 211 of 2009 BETWEEN ARCELORMITTAL POINT LISAS LIMITED (formerly CARIBBEAN ISPAT LIMITED) Appellant AND STEEL WORKERS UNION OF TRINIDAD AND TOBAGO

More information

NaturEner Energy Canada Inc.

NaturEner Energy Canada Inc. Decision 2009-174 Review and Variance of Alberta Utilities Commission Decision 2009-042 (October 22, 2009) ALBERTA UTILITIES COMMISSION Decision 2009-174, Review and Variance of Alberta Utilities Commission

More information

AltaLink Investment Management Ltd. And SNC Lavalin Transmission Ltd. et al.

AltaLink Investment Management Ltd. And SNC Lavalin Transmission Ltd. et al. Decision 3529-D01-2015 AltaLink Investment Management Ltd. And SNC Lavalin Transmission Ltd. et al. Proposed Sale of AltaLink, L.P Transmission Assets and Business to Mid-American (Alberta) Canada Costs

More information

IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c. 15, (Schedule B);

IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c. 15, (Schedule B); Ontari o Energy Board Commission de l énergie de l Ontario IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c. 15, (Schedule B); AND IN THE MATTER OF an application by PowerStream Inc. for

More information

Decision ATCO Utilities. Corporate Cost Allocation Methodology. September 20, 2010

Decision ATCO Utilities. Corporate Cost Allocation Methodology. September 20, 2010 Decision 2010-447 Corporate Cost Allocation Methodology September 20, 2010 ALBERTA UTILITIES COMMISSION Decision 2010-447: Corporate Cost Allocation Methodology Application No. 1605473 Proceeding ID. 306

More information

Page: 1 PROVINCE OF PRINCE EDWARD ISLAND PRINCE EDWARD ISLAND COURT OF APPEAL

Page: 1 PROVINCE OF PRINCE EDWARD ISLAND PRINCE EDWARD ISLAND COURT OF APPEAL Page: 1 PROVINCE OF PRINCE EDWARD ISLAND PRINCE EDWARD ISLAND COURT OF APPEAL Citation: Doiron v. Island Regulatory and Appeals Commission 2011 PECA 9 Date: 20110603 Docket: S1-CA-1205 Registry: Charlottetown

More information

Decision D ATCO Electric Ltd. Amounts to be Paid Into and Out of Balancing Pool for Chinchaga Power Plant Sale

Decision D ATCO Electric Ltd. Amounts to be Paid Into and Out of Balancing Pool for Chinchaga Power Plant Sale Decision 21833-D01-2016 Amounts to be Paid Into and Out of Balancing Pool for Chinchaga Power Plant Sale December 20, 2016 Alberta Utilities Commission Decision 21833-D01-2016 Proceeding 21833 December

More information

Table of Contents Section Page

Table of Contents Section Page Arbitration Regulations 2015 Table of Contents Section Page Part 1 : General... 1 1. Title... 1 2. Legislative authority... 1 3. Application of the Regulations... 1 4. Date of enactment... 1 5. Date of

More information

STATE OF NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION DE STEEL S POND HYDRO, INC. Complaint by Steel s Pond Hydro, Inc. against Eversource Energy

STATE OF NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION DE STEEL S POND HYDRO, INC. Complaint by Steel s Pond Hydro, Inc. against Eversource Energy STATE OF NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION DE 15-372 STEEL S POND HYDRO, INC. Complaint by Steel s Pond Hydro, Inc. against Eversource Energy Order Denying Motion for Rehearing O R D E R N O. 25,849

More information

Noteworthy Decision Summary. Decision: WCAT Panel: Herb Morton Decision Date: August 6, 2004

Noteworthy Decision Summary. Decision: WCAT Panel: Herb Morton Decision Date: August 6, 2004 Decision Number: -2004-04157 Noteworthy Decision Summary Decision: -2004-04157 Panel: Herb Morton Decision Date: August 6, 2004 What constitutes a reviewable decision respecting compensation Review Division

More information

POLICY STATEMENT TO REGULATION RESPECTING INVESTMENT FUNDS

POLICY STATEMENT TO REGULATION RESPECTING INVESTMENT FUNDS POLICY STATEMENT TO REGULATION 81-102 RESPECTING INVESTMENT FUNDS PART 1 PURPOSE 1.1. Purpose The purpose of this Policy is to state the views of the Canadian securities regulatory authorities on various

More information

Environmental Appeal Board

Environmental Appeal Board Environmental Appeal Board Fourth Floor 747 Fort Street Victoria British Columbia V8W 3E9 Telephone: (250) 387-3464 Facsimile: (250) 356-9923 Mailing Address: PO Box 9425 Stn Prov Govt Victoria BC V8W

More information

North Parcels: Plan A1, Block 63, Lots 1-20 South Parcels: Plan A1, Block 63, Lots 21-40, and the buildings located thereon.

North Parcels: Plan A1, Block 63, Lots 1-20 South Parcels: Plan A1, Block 63, Lots 21-40, and the buildings located thereon. ALBERTA ENERGY AND UTILITIES BOARD Calgary, Alberta ATCO GAS AND PIPELINES LTD. DISPOSITION OF CALGARY STORES BLOCK AND DISTRIBUTION OF NET PROCEEDS PART 2 Decision 2002-037 Application No. 1247130 File

More information

Financial Statements For the years ended December 31, 2015 and 2014

Financial Statements For the years ended December 31, 2015 and 2014 FORTISALBERTA INC. Financial Statements MANAGEMENT S REPORT The accompanying annual financial statements of FortisAlberta Inc. (the Corporation ) have been prepared by management, who are responsible for

More information

M A N I T O B A Order No. 44/11 THE PUBLIC UTILITIES BOARD ACT THE MANITOBA PUBLIC INSURANCE ACT

M A N I T O B A Order No. 44/11 THE PUBLIC UTILITIES BOARD ACT THE MANITOBA PUBLIC INSURANCE ACT M A N I T O B A Order No. 44/11 THE PUBLIC UTILITIES BOARD ACT THE MANITOBA PUBLIC INSURANCE ACT THE CROWN CORPORATIONS PUBLIC REVIEW AND ACCOUNTABILITY ACT March 31, 2011 Before: Graham Lane, CA, Chairman

More information

ATCO Electric Ltd. Stage 2 Review of Decision D ATCO Electric Ltd Transmission General Tariff Application

ATCO Electric Ltd. Stage 2 Review of Decision D ATCO Electric Ltd Transmission General Tariff Application Decision 22483-D01-2017 Stage 2 Review of Decision 20272-D01-2016 2015-2017 Transmission General Tariff Application December 6, 2017 Alberta Utilities Commission Decision 22483-D01-2017 Stage 2 Review

More information

ARBITRATION ACT 2005 REVISED 2011 REGIONAL RESOLUTION GLOBAL SOLUTION

ARBITRATION ACT 2005 REVISED 2011 REGIONAL RESOLUTION GLOBAL SOLUTION ARBITRATION ACT 2005 REVISED 2011 REGIONAL RESOLUTION GLOBAL SOLUTION According to Section 3(1) of the Arbitration (Amendment) Act 2018 [Act A1563] and the Ministers appointment of the date of coming

More information

BALANCING POOL REGULATION

BALANCING POOL REGULATION Province of Alberta ELECTRIC UTILITIES ACT BALANCING POOL REGULATION Alberta Regulation 158/2003 With amendments up to and including Alberta Regulation 160/2017 Office Consolidation Published by Alberta

More information

Provident Energy Ltd.

Provident Energy Ltd. Alberta Energy and Utilities Board Energy Cost Order 2005-002 Applications for Licences for a Well and Battery Cost Awards ALBERTA ENERGY AND UTILITIES BOARD Energy Cost Order 2005-002 Applications for

More information

IN THE MATTER OF the Ontario Energy Board Act 1998, S.O.1998, c.15, (Schedule B);

IN THE MATTER OF the Ontario Energy Board Act 1998, S.O.1998, c.15, (Schedule B); Ontario Energy Board Commission de l Énergie de l Ontario RP-2003-0249 IN THE MATTER OF the Ontario Energy Board Act 1998, S.O.1998, c.15, (Schedule B); AND IN THE MATTER OF an Application pursuant to

More information

BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON

BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON ORDER NO. 10-132 ENTERED 04/07/10 BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON UM 1401 In the Matter of PUBLIC UTILITY COMMISSION OF OREGON Investigation into Interconnection of PURPA Qualifying Facilities

More information

to bid their secured debt at the auction.

to bid their secured debt at the auction. Seventh Circuit Disagrees With Philadelphia Newspapers And Finds That Credit Bidding Required For Asset Sales In Bankruptcy Plans By Josef Athanas, Caroline Reckler, Matthew Warren and Andrew Mellen the

More information

Condensed Interim Financial Statements and Review. Balancing Pool. For the three months ended March 31, 2018 (Unaudited)

Condensed Interim Financial Statements and Review. Balancing Pool. For the three months ended March 31, 2018 (Unaudited) Condensed Interim Financial Statements and Review Balancing Pool For the three months ended March 31, 2018 (Unaudited) NOTICE OF NO AUDITOR S REVIEW OF INTERIM FINANCIAL STATEMENTS The accompanying unaudited

More information

Article 9. Export Subsidy Commitments. 1. The following export subsidies are subject to reduction commitments under this Agreement:

Article 9. Export Subsidy Commitments. 1. The following export subsidies are subject to reduction commitments under this Agreement: 1 ARTICLE 9... 1 1.1 Text of Article 9... 1 1.2 Article 9.1(a)... 3 1.2.1 "direct subsidies, including payments-in-kind"... 3 1.2.2 "governments or their agencies"... 3 1.2.3 "contingent on export performance"...

More information

Yugraneft v. Rexx Management: Limitation periods under the New York Convention A Case Comment by Paul M. Lalonde & Mark Hines*

Yugraneft v. Rexx Management: Limitation periods under the New York Convention A Case Comment by Paul M. Lalonde & Mark Hines* Yugraneft v. Rexx Management: Limitation periods under the New York Convention A Case Comment by Paul M. Lalonde & Mark Hines* Prepared for the Canadian Bar Association National Section on International

More information

2014 Bill 9. Second Session, 28th Legislature, 63 Elizabeth II THE LEGISLATIVE ASSEMBLY OF ALBERTA BILL 9

2014 Bill 9. Second Session, 28th Legislature, 63 Elizabeth II THE LEGISLATIVE ASSEMBLY OF ALBERTA BILL 9 2014 Bill 9 Second Session, 28th Legislature, 63 Elizabeth II THE LEGISLATIVE ASSEMBLY OF ALBERTA BILL 9 PUBLIC SECTOR PENSION PLANS AMENDMENT ACT, 2014 THE PRESIDENT OF TREASURY BOARD AND MINISTER OF

More information

CITATION: H.M. The Queen in Right of Ontario v. Axa Insurance Canada, 2017 ONSC 3414 COURT FILE NO.: CV DATE: ONTARIO

CITATION: H.M. The Queen in Right of Ontario v. Axa Insurance Canada, 2017 ONSC 3414 COURT FILE NO.: CV DATE: ONTARIO CITATION: H.M. The Queen in Right of Ontario v. Axa Insurance Canada, 2017 ONSC 3414 COURT FILE NO.: CV-16-553910 DATE: 20170601 ONTARIO SUPERIOR COURT OF JUSTICE IN THE MATTER of the Insurance Act, R.S.O.

More information

STATE OF NORTH CAROLINA UTILITIES COMMISSION RALEIGH DOCKET NO. ER-100, SUB 0

STATE OF NORTH CAROLINA UTILITIES COMMISSION RALEIGH DOCKET NO. ER-100, SUB 0 STATE OF NORTH CAROLINA UTILITIES COMMISSION RALEIGH DOCKET NO. ER-100, SUB 0 BEFORE THE NORTH CAROLINA UTILITIES COMMISSION In the Matter of Rulemaking Proceeding to Implement ) ORDER ADOPTING Session

More information

WORLD TRADE ORGANIZATION

WORLD TRADE ORGANIZATION WORLD TRADE ORGANIZATION WT/DS46/AB/RW 21 July 2000 (00-2990) Original: English BRAZIL EXPORT FINANCING PROGRAMME FOR AIRCRAFT RECOURSE BY CANADA TO ARTICLE 21.5 OF THE DSU AB-2000-3 Report of the Appellate

More information

FREEHOLD MINERAL RIGHTS TAX ACT

FREEHOLD MINERAL RIGHTS TAX ACT Province of Alberta FREEHOLD MINERAL RIGHTS TAX ACT Revised Statutes of Alberta 2000 Chapter F-26 Current as of November 30, 2015 Office Consolidation Published by Alberta Queen s Printer Alberta Queen

More information

ENTERED TAWANA C. MARSHALL, CLERK THE DATE OF ENTRY IS ON THE COURT'S DOCKET

ENTERED TAWANA C. MARSHALL, CLERK THE DATE OF ENTRY IS ON THE COURT'S DOCKET Case 14-42974-rfn13 Doc 45 Filed 01/08/15 Entered 01/08/15 15:22:05 Page 1 of 12 U.S. BANKRUPTCY COURT NORTHERN DISTRICT OF TEXAS ENTERED TAWANA C. MARSHALL, CLERK THE DATE OF ENTRY IS ON THE COURT'S DOCKET

More information

WORKPLACE SAFETY AND INSURANCE APPEALS TRIBUNAL DECISION NO. 1679/11

WORKPLACE SAFETY AND INSURANCE APPEALS TRIBUNAL DECISION NO. 1679/11 WORKPLACE SAFETY AND INSURANCE APPEALS TRIBUNAL DECISION NO. 1679/11 BEFORE: G. Dee : Vice-Chair M. Christie: Member representative of Employers M. Ferarri : Member representative of Workers HEARING: August

More information

ENVIRONMENTAL ALBERTA APPEALS BOARD. Dems on. Preliminary. Appeal No : _ ID1. Properties

ENVIRONMENTAL ALBERTA APPEALS BOARD. Dems on. Preliminary. Appeal No : _ ID1. Properties ALBERTA APPEALS BOARD ENVIRONMENTAL THE MATTER OF sections 91, 92, and 95 of the IN Protection and Enhancement Act, R.S.A. 2000, c. Environmental THE MATTER OF an appeal filed by Alberta Foothills IN Ltd.

More information

ATCO Pipelines ATCO Gas and Pipelines Ltd. CU Inc. Canadian Utilities Limited

ATCO Pipelines ATCO Gas and Pipelines Ltd. CU Inc. Canadian Utilities Limited Decision 2012-068 Disposition of Surplus Salt Cavern Assets in the Fort Saskatchewan Area March 16, 2012 The Alberta Utilities Commission Decision 2012-068:,,, Disposition of Surplus Salt Cavern Assets

More information

THE PUBLIC UTILITIES BOARD, ALBERTA

THE PUBLIC UTILITIES BOARD, ALBERTA THE PUBLIC UTILITIES BOARD, ALBERTA DECISION C91023 re: CITY OF CALGARY AND CANADIAN WESTERN NATURAL GAS COMPANY LIMITED In the matter of an Application by the City of Calgary for an Order of the Board

More information

2011 BCSECCOM 197. Mutual Fund Dealers Association of Canada Tony Tung-Yuan Lin. Section 28 of the Securities Act, RSBC 1996, c.

2011 BCSECCOM 197. Mutual Fund Dealers Association of Canada Tony Tung-Yuan Lin. Section 28 of the Securities Act, RSBC 1996, c. Mutual Fund Dealers Association of Canada Tony Tung-Yuan Lin Section 28 of the Securities Act, RSBC 1996, c. 418 Hearing and Review Panel Brent W. Aitken Bradley Doney Don Rowlatt Vice Chair Commissioner

More information

EPCOR Energy Alberta GP Inc.

EPCOR Energy Alberta GP Inc. Decision 20633-D01-2016 EPCOR Energy Alberta GP Inc. 2016-2017 Regulated Rate Tariff Application December 20, 2016 Alberta Utilities Commission Decision 20633-D01-2016 EPCOR Energy Alberta GP Inc. 2016-2017

More information

Province of Alberta ALBERTA HOUSING ACT. Revised Statutes of Alberta 2000 Chapter A-25. Current as of July 1, Office Consolidation

Province of Alberta ALBERTA HOUSING ACT. Revised Statutes of Alberta 2000 Chapter A-25. Current as of July 1, Office Consolidation Province of Alberta ALBERTA HOUSING ACT Revised Statutes of Alberta 2000 Current as of July 1, 2015 Office Consolidation Published by Alberta Queen s Printer Alberta Queen s Printer Suite 700, Park Plaza

More information

Alberta Electric System Operator

Alberta Electric System Operator Decision 2007-106 Alberta Electric System Operator 2007 General Tariff Application December 21, 2007 ALBERTA ENERGY AND UTILITIES BOARD Decision 2007-106: Alberta Electric System Operator 2007 General

More information

IN THE OREGON TAX COURT MAGISTRATE DIVISION Municipal Tax ) ) I. INTRODUCTION

IN THE OREGON TAX COURT MAGISTRATE DIVISION Municipal Tax ) ) I. INTRODUCTION IN THE OREGON TAX COURT MAGISTRATE DIVISION Municipal Tax JOHN A. BOGDANSKI, Plaintiff, v. CITY OF PORTLAND, State of Oregon, Defendant. TC-MD 130075C DECISION OF DISMISSAL I. INTRODUCTION This matter

More information

Indexed as: Ontario (Regional Assessment Commissioner, Region Number 13) v. Downtown Oshawa Property Owners' Assn.

Indexed as: Ontario (Regional Assessment Commissioner, Region Number 13) v. Downtown Oshawa Property Owners' Assn. Page 1 Indexed as: Ontario (Regional Assessment Commissioner, Region Number 13) v. Downtown Oshawa Property Owners' Assn. The Regional Assessment Commissioner, Region Number 13 and The Corporation of the

More information

ALBERTA ENVIRONMENTAL APPEAL BOARD. Decision

ALBERTA ENVIRONMENTAL APPEAL BOARD. Decision Appeal Nos. 01-113 and 01-115-D ALBERTA ENVIRONMENTAL APPEAL BOARD Decision Date of Decision June 15, 2002 IN THE MATTER OF sections 91, 92, and 95 of the Environmental Protection and Enhancement Act,

More information

AltaGas Utilities Inc.

AltaGas Utilities Inc. Decision 23898-D01-2018 2019 Annual Performance-Based Regulation Rate Adjustment Filing December 20, 2018 Alberta Utilities Commission Decision 23898-D01-2018 2019 Annual Performance-Based Regulation Rate

More information

SUBSTITUTE FOR SENATE BILL NO. 437

SUBSTITUTE FOR SENATE BILL NO. 437 SUBSTITUTE FOR SENATE BILL NO. A bill to amend PA, entitled "An act to provide for the regulation and control of public and certain private utilities and other services affected with a public interest

More information

AGRICULTURE FINANCIAL SERVICES ACT

AGRICULTURE FINANCIAL SERVICES ACT Province of Alberta AGRICULTURE FINANCIAL SERVICES ACT Revised Statutes of Alberta 2000 Chapter A-12 Current as of December 15, 2017 Office Consolidation Published by Alberta Queen s Printer Alberta Queen

More information

1. Company/Organization/Individual named in the determination ( Appellant ) Name Address Postal Code

1. Company/Organization/Individual named in the determination ( Appellant ) Name Address Postal Code APPEAL FORM (Form 1) This Appeal Form, along with the required attachments, must be delivered to the Employment Standards Tribunal within the appeal period. See Rule 18(3) of the Tribunal s Rules of Practice

More information

ALBERTA ENERGY AND UTILITIES BOARD Calgary Alberta

ALBERTA ENERGY AND UTILITIES BOARD Calgary Alberta ALBERTA ENERGY AND UTILITIES BOARD Calgary Alberta IMPERIAL OIL RESOURCES LIMITED APPLICATION TO CONSTRUCT AND OPERATE THE THICKSILVER PIPELINE PROJECT A BLENDED BITUMEN PIPELINE AND ASSOCIATED SURFACE

More information

ATCO Gas and Pipelines Ltd.

ATCO Gas and Pipelines Ltd. Decision 2738-D01-2016 Z Factor Application for Recovery of 2013 Southern Alberta Flood Costs March 16, 2016 Alberta Utilities Commission Decision 2738-D01-2016 Z Factor Application for Recovery of 2013

More information

4. CHAPTER 4: LEGALITY OF THE ASSISTANCE TO BANKORP/ABSA

4. CHAPTER 4: LEGALITY OF THE ASSISTANCE TO BANKORP/ABSA 39 4. CHAPTER 4: LEGALITY OF THE ASSISTANCE TO BANKORP/ABSA (First term of reference: to determine whether the S A Reserve Bank, in providing financial assistance to Bankorp, has contravened the provisions

More information

ALBERTA TREASURY BRANCHES REGULATION

ALBERTA TREASURY BRANCHES REGULATION Province of Alberta ALBERTA TREASURY BRANCHES ACT ALBERTA TREASURY BRANCHES REGULATION Alberta Regulation 187/1997 With amendments up to and including Alberta Regulation 239/2009 Office Consolidation Published

More information

WCAT Decision Number: WCAT

WCAT Decision Number: WCAT Noteworthy Decision Summary Decision: WCAT-2010-00928 Panel: J. Callan Decision Date: March 30, 2010 Section 7 of the Workers Compensation Act Appeal Regulation Invoice for Expense Tariff Occupational

More information

COMMONWEALTH OF MASSACHUSETTS APPEALS COURT. NORTHEASTERN UNIVERSITY & others 1. vs. COMMISSIONER OF REVENUE.

COMMONWEALTH OF MASSACHUSETTS APPEALS COURT. NORTHEASTERN UNIVERSITY & others 1. vs. COMMISSIONER OF REVENUE. NOTICE: Summary decisions issued by the Appeals Court pursuant to its rule 1:28, as amended by 73 Mass. App. Ct. 1001 (2009), are primarily directed to the parties and, therefore, may not fully address

More information

Audited Financial Statements For the years ended December 31, 2017 and 2016

Audited Financial Statements For the years ended December 31, 2017 and 2016 FORTISALBERTA INC. Audited Financial Statements MANAGEMENT S REPORT The accompanying 2017 Financial Statements of FortisAlberta Inc. (the Corporation ) have been prepared by management, who are responsible

More information

IN THE SUPREME COURT OF FLORIDA CASE NO.: SC SERVICE INSURANCE COMPANY, Appellant, vs. OFFICE OF INSURANCE REGULATION AND

IN THE SUPREME COURT OF FLORIDA CASE NO.: SC SERVICE INSURANCE COMPANY, Appellant, vs. OFFICE OF INSURANCE REGULATION AND IN THE SUPREME COURT OF FLORIDA CASE NO.: SC11-299 SERVICE INSURANCE COMPANY, Appellant, vs. OFFICE OF INSURANCE REGULATION AND THE FINANCIAL SERVICES COMMISSION, Appellees. BRIEF ON JURISDICTION OF APPELLEES

More information

HOSPITAL APPEAL BOARD. In the matter of DR. IMRAN SAMAD. And

HOSPITAL APPEAL BOARD. In the matter of DR. IMRAN SAMAD. And HOSPITAL APPEAL BOARD In the matter of DR. IMRAN SAMAD And PROVINCIAL HEALTH SERVICES AUTHORITY and THE CHILDREN S AND WOMEN S HEALTH CENTRE OF BRITISH COLUMBIA DECISION ON DISCLOSURE OF DOCUMENTS On January

More information

Decision D Rebasing for the PBR Plans for Alberta Electric and Gas Distribution Utilities. First Compliance Proceeding

Decision D Rebasing for the PBR Plans for Alberta Electric and Gas Distribution Utilities. First Compliance Proceeding Decision 22394-D01-2018 Rebasing for the 2018-2022 PBR Plans for February 5, 2018 Alberta Utilities Commission Decision 22394-D01-2018 Rebasing for the 2018-2022 PBR Plans for Proceeding 22394 February

More information

LANDMARK CASE BCE INC. V DEBENTUREHOLDERS

LANDMARK CASE BCE INC. V DEBENTUREHOLDERS BCE INC. V. 1976 DEBENTUREHOLDERS CURRICULUM LINKS: Canadian and International Law, Grade 12, University Preparation (CLN4U) Understanding Canadian Law, Grade 11, University/College Preparation (CLU3M)

More information

In the Missouri Court of Appeals Western District

In the Missouri Court of Appeals Western District In the Missouri Court of Appeals Western District ACCIDENT FUND INSURANCE COMPANY; E.J. CODY COMPANY, INC., Respondents-Appellants, v. ROBERT CASEY, EMPLOYEE/DOLORES MURPHY, Appellant-Respondent. WD80470

More information

Decision TykeWest Limited. Setting of Fees for a Common Carrier Order. July 15, 2009

Decision TykeWest Limited. Setting of Fees for a Common Carrier Order. July 15, 2009 Decision 2009-106 Setting of Fees for a Common Carrier Order July 15, 2009 ALBERTA UTILITIES COMMISSION Decision 2009-106: Setting of Fees for a Common Carrier Order Application No. 1567541 July 15, 2009

More information

WT/DS316/AB/RW - 256

WT/DS316/AB/RW - 256 - 256 5.775. Accordingly, we modify the Panel's conclusion in paragraph 6.1817 of the Panel Report, and find instead that the United States has established that the "product effects" of the LA/MSF subsidies

More information

Consumers Coalition of Alberta

Consumers Coalition of Alberta Decision 22157-D01-2017 Decision on Preliminary Question AltaLink Management Ltd. 2012-2013 Deferral Account Reconciliation Costs Award February 15, 2017 Alberta Utilities Commission Decision 22157-D01-2017

More information

Glencoe Resources Ltd.

Glencoe Resources Ltd. Energy Cost Order 2012-006 Glencoe Resources Ltd. Application for Well Licence Chigwell Field Cost Awards July 16, 2012 ENERGY RESOURCES CONSERVATION BOARD Energy Cost Order 2012-006: Glencoe Resources

More information

IN THE COURT OF APPEAL OF NEW ZEALAND CA256/05. ANTHONY ARBUTHNOT Respondent. William Young P, Arnold and Ellen France JJ

IN THE COURT OF APPEAL OF NEW ZEALAND CA256/05. ANTHONY ARBUTHNOT Respondent. William Young P, Arnold and Ellen France JJ IN THE COURT OF APPEAL OF NEW ZEALAND CA256/05 BETWEEN AND THE CHIEF EXECUTIVE OF THE DEPARTMENT OF WORK AND INCOME Appellant ANTHONY ARBUTHNOT Respondent Hearing: 24 August 2006 Court: Counsel: William

More information

151 FERC 61,045 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

151 FERC 61,045 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 151 FERC 61,045 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Norman C. Bay, Chairman; Philip D. Moeller, Cheryl A. LaFleur, Tony Clark, and Colette D. Honorable.

More information

Canadian Natural Resources Limited

Canadian Natural Resources Limited Decision 21306-D01-2016 Determination of Compensation for 9L66/9L32 Transmission Line Relocation August 16, 2016 Alberta Utilities Commission Decision 21306-D01-2016 Determination of Compensation for 9L66/9L32

More information

In The Supreme Court of Belize A.D., 2010

In The Supreme Court of Belize A.D., 2010 In The Supreme Court of Belize A.D., 2010 Civil Appeal No. 2 In the Matter of an Appeal pursuant to section 43 (1) of the Income and Business Tax Act, CAP 55 of the Laws of Belize 2000 In the Matter of

More information

BETWEEN AWARD AND IN THE MATTER OF THE ARBITRATION ACT AND IN THE MATTER OF AN ARBITRATOR CO-OPERATORS GENERAL INSURANCE COMPANY

BETWEEN AWARD AND IN THE MATTER OF THE ARBITRATION ACT AND IN THE MATTER OF AN ARBITRATOR CO-OPERATORS GENERAL INSURANCE COMPANY IN THE MATTER OF THE INSURANCE ACT R.SO. 1990 C.18 S.275 AND REGULATION 6664 OF R.R.O. 1990 S.9 AND IN THE MATTER OF THE ARBITRATION ACT 1991 SC. 1991 C.17 AND IN THE MATTER OF AN ARBITRATOR BETWEEN CO-OPERATORS

More information

Decision D FortisAlberta Inc Performance-Based Regulation Capital Tracker True-Up. January 11, 2018

Decision D FortisAlberta Inc Performance-Based Regulation Capital Tracker True-Up. January 11, 2018 Decision 22741-D01-2018 FortisAlberta Inc. 2016 Performance-Based Regulation Capital Tracker True-Up January 11, 2018 Alberta Utilities Commission Decision 22741-D01-2018 FortisAlberta Inc. 2016 Performance-Based

More information

Canadian Natural Resources Limited

Canadian Natural Resources Limited Alberta Energy and Utilities Board Energy Cost Order 2004-07 Canadian Natural Resources Limited Application for an Oil Sands Mine, Bitumen Extraction Plant, and Bitumen Upgrading Plant in the Fort McMurray

More information

ADMINISTRATIVE DECISION

ADMINISTRATIVE DECISION STATE OF ARKANSAS DEPARTMENT OF FINANCE AND ADMINISTRATION OFFICE OF HEARINGS & APPEALS ADMINISTRATIVE DECISION IN THE MATTER OF ACCT. NO.: REFUND CLAIM DISALLOWANCE (Other Tobacco Products) DOCKET NO.:

More information

Decision D FortisAlberta Inc PBR Capital Tracker True-Up and PBR Capital Tracker Forecast

Decision D FortisAlberta Inc PBR Capital Tracker True-Up and PBR Capital Tracker Forecast Decision 20497-D01-2016 FortisAlberta Inc. 2014 PBR Capital Tracker True-Up and 2016-2017 PBR Capital Tracker Forecast February 20, 2016 Alberta Utilities Commission Decision 20497-D01-2016 FortisAlberta

More information

Four Winds Energy Services Ltd.

Four Winds Energy Services Ltd. Decision 2009-067 Four Winds Energy Services Ltd. Appeal of ERCB High Risk Enforcement Action 1 November 10, 2009 ENERGY RESOURCES CONSERVATION BOARD Decision 2009-067: Four Winds Energy Services Ltd.,

More information

Decision D EQUS REA LTD.

Decision D EQUS REA LTD. Decision 22293-D01-2017 Application for Orders Amending the Terms and Conditions of Service and Rate Schedules of FortisAlberta Inc. in Respect of Option M Distribution Generation Credit/Charge October

More information

THE COMMERCIAL ARBITRATION LAW OF THE KINGDOM OF CAMBODIA

THE COMMERCIAL ARBITRATION LAW OF THE KINGDOM OF CAMBODIA KINGDOM OF CAMBODIA NATION RELIGION KING THE COMMERCIAL ARBITRATION LAW OF THE KINGDOM OF CAMBODIA Adopted by The NATIONAL ASSEMBLY Phnom Penh, March 6 th, 2006 THE COMMERCIAL ARBITRATION LAW OF THE KINGDOM

More information

FLEMMING & SON CONSTRUCTION (WEST MIDLANDS) LIMITED. -and- THE COMMISSIONERS FOR HER MAJESTY S REVENUE AND CUSTOMS JUDGE KEVIN POOLE BEVERLEY TANNER

FLEMMING & SON CONSTRUCTION (WEST MIDLANDS) LIMITED. -and- THE COMMISSIONERS FOR HER MAJESTY S REVENUE AND CUSTOMS JUDGE KEVIN POOLE BEVERLEY TANNER [12] UKFTT (TC) TC01900 Appeal numbers: TC/11/01493 TC/11/08678 Income tax construction industry scheme deductions from payments to subcontractors sums representing materials cost not to be subject to

More information

OFFICE OF THE DIRECTOR OF ARBITRATIONS. STATE FARM MUTUAL AUTOMOBILE INSURANCE COMPANY Appellant. and APPEAL ORDER

OFFICE OF THE DIRECTOR OF ARBITRATIONS. STATE FARM MUTUAL AUTOMOBILE INSURANCE COMPANY Appellant. and APPEAL ORDER Appeal P-013860 OFFICE OF THE DIRECTOR OF ARBITRATIONS STATE FARM MUTUAL AUTOMOBILE INSURANCE COMPANY Appellant and SHAWN P. LUNN Respondent BEFORE: COUNSEL: David R. Draper, Director s Delegate David

More information

NEWFOUNDLAND AND LABRADOR BOARD OF COMMISSIONERS OF PUBLIC UTILITIES AN ORDER OF THE BOARD NO. P.U. 17(2018)

NEWFOUNDLAND AND LABRADOR BOARD OF COMMISSIONERS OF PUBLIC UTILITIES AN ORDER OF THE BOARD NO. P.U. 17(2018) NEWFOUNDLAND AND LABRADOR BOARD OF COMMISSIONERS OF PUBLIC UTILITIES AN ORDER OF THE BOARD NO. P.U. (0) 0 0 IN THE MATTER OF the Electrical Power Control Act,, SNL, Chapter E-. (the EPCA ) and the Public

More information

FEED-IN TARIFF CONTRACT (FIT CONTRACT)

FEED-IN TARIFF CONTRACT (FIT CONTRACT) FEED-IN TARIFF CONTRACT (FIT CONTRACT) Version 1.5.1 (July 15, 2011) CONTRACT IDENTIFICATION # FIT REFERENCE # FIT- FIT- CONTRACT DATE SUPPLIER SUPPLIER S ADDRESS SUPPLIER INFORMATION GROSS NAMEPLATE CAPACITY

More information

Highpine Oil & Gas Ltd. (formerly Vaquero Energy Ltd.)

Highpine Oil & Gas Ltd. (formerly Vaquero Energy Ltd.) Alberta Energy and Utilities Board Energy Cost Order 2005-009 (formerly Vaquero Energy Ltd.) Application for a Oil Effluent Pipeline Chip Lake Field Cost Awards ALBERTA ENERGY AND UTILITIES BOARD Energy

More information

IN THE COURT OF APPEAL [1] HONOURABLE ATTORNEY-GENERAL [2] THE HONOURABLE EDZEL THOMAS [3] MINISTER OF LABOUR

IN THE COURT OF APPEAL [1] HONOURABLE ATTORNEY-GENERAL [2] THE HONOURABLE EDZEL THOMAS [3] MINISTER OF LABOUR 1 GRENADA IN THE COURT OF APPEAL CIVIL APPEAL NO.8 1995 BETWEEN: LIBERTY CLUB LIMITED v Appellant [1] HONOURABLE ATTORNEY-GENERAL [2] THE HONOURABLE EDZEL THOMAS [3] MINISTER OF LABOUR Before: The Hon.

More information