AltaLink Management Ltd.

Size: px
Start display at page:

Download "AltaLink Management Ltd."

Transcription

1 Decision 3524-D AltaLink Management Ltd General Tariff Application May 9, 2016

2 Alberta Utilities Commission Decision 3524-D AltaLink Management Ltd General Tariff Application Proceeding 3524 Application May 9, 2016 Published by the: Alberta Utilities Commission Fifth Avenue Place, Fourth Floor, 425 First Street S.W. Calgary, Alberta T2P 3L8 Telephone: Fax: Website:

3 Contents 1 Decision Introduction, procedural schedules and motions Expertise of intervener witnesses Forecasting methodology/process and key assumptions Forecast parameters and assumptions Escalations Contractor escalation rates Capital escalation rates General inflation escalation rates Compensation Market assessment Base pay Union Non-union escalators Executive escalators Pension and benefits Short-term incentive plan Long-term incentive plan Full-time equivalents (FTEs) Vacancy rates O&M expenses Overview total operating expenses (O&M) and total administration and general expenses (A&G) Overview USA 567 right-of-way payments USA vegetation management USA 920 administrative and general salaries USA 923 outside services employed Taxes other than income taxes Transmission depreciation Views of parties Consideration of specific depreciation concepts and methodologies Use of peer groups as comparators in depreciation studies Use of gradualism and moderation and its relation to the UAD decision Necessity of re-examining current depreciation methodologies: the average life group procedure Necessity for the separation of certain accounts into subaccount categories and the requirement for independent life and net salvage studies Average service life and Iowa survivor curve adjustments Account 354 transmission towers and fixtures Account 355 transmission poles and fixtures Account 356 transmission overhead conductors and devices Decision 3524-D (May 9, 2016) i

4 6.3.4 Account general plant computer hardware and Account general plant computer software Remaining depreciation study accounts Net salvage per cent adjustments Account 352 transmission structures and improvements Account 353 transmission station equipment Account transmission system communication and control Account 354 transmission towers and fixtures Account 355 transmission poles and fixtures Account 356 transmission overhead conductors and devices Remaining depreciation study accounts Additional net salvage observations of Commission Member Lyttle Summary of approvals Transmission income taxes Overview Income tax rates Treatment of DAIC for tax purposes Transmission revenue offsets Capital Capital direct assign (DA) Scope of the assessment of direct assign project forecasts within the GTA Uncertainty adjusted forecasting methodology EPCm rate differential estimate Use of 1.5 multiplier for EPCm service costs in direct assign forecasts Alleged failure to enforce labour/material supply contracts Other matters related to direct assign project forecasts Use of risk registers for direct assign projects Capital replacement and upgrades Facility capital costs Facility project common matters General facility maintenance Equipment Storage projects FTSB Relocation project Control Centre Upgrades project Information technology capital expenditures Terms and conditions Transmission necessary working capital Allowance for working capital Financing Financing plan subordinated debt Tariff relief and credit metric support Credit metric support FFO-to-debt ratio Temporary increase in equity thickness of three per cent and one per cent. 177 ii Decision 3524-D (May 9, 2016)

5 13.2 Rate relief proposals Discontinuance of CWIP-in-rate base treatment for direct assign capital projects Refund of previously collected CWIP-in-rate base Discontinuation of FIT and the refund of the previously collected FIT liability No cost capital Self-insurance reserve Future income tax liability balance Pension/post-retirement benefit Rainbow reserve Hearing cost reserve Deferral and reserve accounts Order Appendix 1 Proceeding participants Appendix 2 Oral hearing registered appearances Appendix 3 Summary of Commission directions Appendix 4 Procedural events Appendix 5 Abbreviations List of tables Table 1. Summary of major AltaLink forecast parameters... 7 Table 2. Summary of major AltaLink forecast parameters (October 16, 2015)... 8 Table 3. AltaLink portfolio escalation by PPS cost category breakdown Table 4. AltaLink total company operating expenses Table 5. AltaLink total company - FTEs year-end summary Table 6. Total company operating expenses Table 7. AltaLink total company FTEs year-end summary Table 8. AltaLink corrected normalizing analysis Table 9. USA 567 annual structure payment expenses Table 10. USA 920 administrative and general salaries Table 11. USA 920 administrative and general salaries FTEs Decision 3524-D (May 9, 2016) iii

6 Table 12. USA 920 administrative and general salaries Table 13. USA 920 administrative and general salaries FTEs Table 14. USA 923 outside services employed Table 15. USA 923 outside services employed Table 16. USA 923 major cost categories Table 17. Schedule of transmission depreciation and amortization expense Table 18. Comparison of impact of depreciation proposals based on forecast plant balances as of December 31, 2015 and Table 19. Summary of approved and proposed depreciation parameters Table 20. Comparison of net salvage per cents Table 21. Schedule of transmission computer system costs Table 22. Summary of recent net salvage statistics for Account 355 transmission poles and fixtures Table 23. Summary of proposed and approved estimated average service lives, Iowa curves and net salvage per cents Table 24. Revenue offsets Table 25. Non-affiliate revenues - discrepancy Table 26. Direct assign capital forecast adjustments from EPCm rate differentials Table 27. Facilities projects capital expenditure summary Table 28. AltaLink East Relocation project forecast versus actuals breakdown Table 29. Forecast general facility maintenance expenditures Table 30. Forecast Head Office Plaza expenditures Table 31. Forecast field office building maintenance Table field office building maintenance forecast versus actual variance analysis Table 33. Forecast material storage project expenditures Table 34. IT capital expenditures summary Table 35. IT Hardware/Other projects Table 36. IT Software (SAP) projects iv Decision 3524-D (May 9, 2016)

7 Table 37. SAP software forecast versus actual analysis Table 38. Non-SAP IT expenditures Table 39. SAP software forecast versus actual analysis Table 40. Summary of the impact of proposed tariff relief and modified capital structure Decision 3524-D (May 9, 2016) v

8

9 Alberta Utilities Commission Calgary, Alberta Decision 3524-D AltaLink Management Ltd. Proceeding General Tariff Application Application Decision 1. The Alberta Utilities Commission found that some of the factors underpinning AltaLink Management Ltd. s (AltaLink or AML) applied-for revenue requirement for the test years were not reasonable and, therefore, the revenue requirement is not approved as applied-for. 2. The Commission approved, in part, AltaLink s application for tariff relief and credit metric support. The Commission accepted: The use of subordinated debt. The discontinuance of the collection of construction work-in progress (CWIP) in rate base amounts and the return to allowance for funds used during construction (AFUDC ) accounting effective January 1, The refund to customers of the CWIP in rate base amounts for capital projects for the years 2012 to The application of the future income tax (FIT) method for calculating income taxes for 2015 and the flow-through method for calculating income taxes for The main areas where the Commission disagreed with AltaLink were: credit metric measures including the deemed equity component of the capital structure, escalation rates, net salvage rates and particular facility and information technology capital costs. The Commission held that AltaLink had not supported its forecast escalation rates using the latest information reflecting the current trend in the Alberta economy. Nor had AltaLink established that the application of principles of gradualism and moderation should be discontinued when establishing net salvage rates. AltaLink was directed to use the Commission-determined escalation and net salvage rates and to remove the capital costs for specific facility and information technology items from its revenue requirement where the Commission found the reasonableness of these costs had not been demonstrated. 4. AltaLink has been recovering rates on an interim basis for 2015 pursuant to Decision 3504-D and for 2016 pursuant to Decision D The final rates approved by the Commission in this decision for each of 2015 and 2016 will be less than the interim rates currently in place, resulting in a refund to AltaLink s customer, the Alberta Electric System 1 2 Decision 3504-D : AltaLink Management Ltd., 2015 Interim Transmission Facility Owner Tariff, Proceeding 3504, Application , January 26, Decision D : AltaLink Management Ltd., 2016 Interim Transmission Facility Owner Tariff, Proceeding 21168, December 23, Decision 3524-D (May 9, 2016) 1

10 Operator (AESO), the timing and quantum of which will be determined in AltaLink s compliance filing. 5. The Commission ordered AltaLink to refile its application by July 25, 2016 to reflect the Commission's findings and conclusions set out in this decision. At the time of the refiling, the Commission expects that the full impact of this decision on the revenue requirement of AltaLink will be known and, hence, final rates for the test years (except for the direct assigned capital deferral account (DACDA) forecast expenditures) can be set, following completion of the Commission's assessment of whether the refiling is in compliance with this decision. 2 Introduction, procedural schedules and motions 6. On November 18, 2014, AltaLink, in its capacity as General Partner of AltaLink L.P., filed an application with the Commission for approval of its: Revenue requirements for the years 2015 and 2016 in the amounts of $810.5 million and $1,001.6 million, respectively. Tariff as set out in Section 1.4 of the application, including the terms and conditions of service. Deferral accounts for the test period as requested in Section 31.8 of the application. Reserve accounts for the test period as requested in Section 31.7 of the application. 7. The Commission assigned Proceeding 3524 to the application and issued notice on November 19, In accordance with the deadline set out in the notice, statements of intent to participate (SIPs) in Proceeding 3524 were received on or before December 2, The following parties registered SIPs with the Commission: the Alberta Direct Connect Consumers Association (ADC) the Alberta Electric System Operator (AESO) ATCO Electric Ltd. (ATCO Electric) The City of Calgary (Calgary) the Consumers Coalition of Alberta (CCA) the Industrial Power Consumers Association of Alberta (IPCAA) the Office of the Utilities Consumer Advocate (UCA) 8. The ADC, the CCA and IPCAA participated and presented evidence on their own behalf and jointly as members of the Ratepayer Group (RPG). 2 Decision 3524-D (May 9, 2016)

11 9. AltaLink submitted updates and errata filings to its application on: December 10, 2014, in response to Directive 4 from Decision December 15, 2014, in response to the directive at paragraph 276 of Decision January 9, 2015, an errata filing 6 to Figure of the application 10. The Commission issued a process letter on December 10, 2014, establishing the following initial proceeding steps: Process step Deadline Information requests to AltaLink 2 p.m., Tuesday, January 20, 2015 Information responses from AltaLink 2 p.m., Tuesday, February 10, 2015 Submissions from parties on further process 2 p.m., Thursday, February 19, AltaLink filed substantive updates to its original application in June and again, in October As a result of the AltaLink updates, interveners updated their evidence. 12. AltaLink filed rebuttal evidence on December 1, 2015, and the oral hearing was held at the Commission s hearing room in Calgary from December 8 to 17, Written argument was filed on January 18, 2016, and written reply argument on February 9, Consequently, the Commission considers the record for Proceeding 3524 to have closed in February 9, Before the oral hearing for this proceeding, the Commission issued 12 procedural rulings and rulings on evidence in response to requests and motions from both the applicant, AltaLink, and the intervener parties. Particulars of the motions and rulings have been summarized and provided in Appendix 4 to this decision. 14. In reaching the determinations set out within this decision, the Commission has considered all relevant materials comprising the record of this proceeding, including the evidence, argument and reply argument provided by each party. Accordingly, references in this decision to specific parts of the record are intended to assist the reader in understanding the Commission s reasoning relating to a particular matter and should not be taken as an indication that the Commission did not consider all relevant portions of the record with respect to that matter. 2.1 Expertise of intervener witnesses 15. On December 1, 2015, the Commission advised parties that it was not necessary for counsel to request that their respective witnesses be qualified as expert witnesses with regard to their pre-filed written evidence or testimony in the hearing. The Commission further advised that it would continue to assess the weight to be ascribed to witnesses evidence and that opposing Decision : AltaLink Investment Management Ltd. and SNC Lavalin Transmission Ltd. et al., Proposed Sale of AltaLink, L.P. Transmission Assets and Business to MidAmerican (Alberta) Canada Holdings Corporation, Proceeding 3250, Applications , and , November 28, Exhibit AML Exhibit AML Exhibit 3524-X0002. Decision 3524-D (May 9, 2016) 3

12 counsel could examine a witness qualifications, the credibility of the evidence provided and opine on the weight to be given to the evidence The argument and reply argument submissions of AltaLink and the RPG specifically addressed this issue, particularly as applied to witnesses appearing on behalf of the RPG, principally, Mr. de Palezieux and Mr. Tusa. 17. Mr. de Palezieux appeared as a witness for the RPG and presented evidence regarding AltaLink s forecast escalation rates and was responsible for inflation issues and Appendix A to the RPG s pre-filed written evidence. 8 AltaLink argued that Mr. de Palezieux s evidence should be rejected as he holds only a bachelor s degree, has no relevant experience after graduation in 2014 and was not advanced as an expert by the RPG on any subject matter Mr. Tusa, of FTI Consulting Inc. (FTI), appeared as a witness for the RPG and was presented as an expert to provide evidence regarding AltaLink s uncertainty adjusted forecast of capital expenditures and additions, the capital forecast reduction attributable to the engineering, procurement, construction management (EPCm) rate differential, and the appropriateness of the two-times multiplier AltaLink submitted that although Mr. Tusa purported to have provided expert evidence on these matters, he has no qualifications in any of these areas. He does not hold a degree in engineering and is not licensed as an engineer. He is not an economist and holds no degree in economics, math, or statistics and has no experience in forecasting labour market conditions. Further, he has never been qualified to provide an expert opinion on macroeconomic conditions or the state of the economy. 20. AltaLink stated, relying on Decision 3110-D , 11 that the purpose of expert evidence is to assist the trier of fact in reaching a conclusion by applying a particular scientific skill not shared by the judge or the jury to a set of facts and then by expressing an opinion as to what conclusions may be drawn as a result. 12 AltaLink argued that FTI failed to satisfy this criteria as FTI s evidence was mostly irrelevant to the issues, FTI has no specialized training in the matters before the Commission and it advanced several opinions on contractual terms and contractual enforcement that Mr. Tusa was not competent to provide. In particular, with regard to Mr. Tusa s evidence regarding the contractual arrangements that AltaLink has with its EPCm contractor, or the contractual arrangements between its EPCm contractor and various subcontractors, the Alberta Court of Appeal stated in Dow Chemical Inc. v. Shell Chemicals Canada Ltd. 13 that a party cannot call expert evidence on the general meaning of a contract or its terms. AltaLink also referred to the Alberta Court of Appeal decision in Canadian National Railway Co. v. Volker Stevin Contracting Ltd. 14 in which the court determined that it was improper for the trial judge to rely on the evidence of scientific and engineering witnesses on Exhibit 3524-X0678. Transcript, Volume 8, pages Exhibit 3524-X0771, AltaLink argument, PDF page 100. Transcript, Volume 8, page Decision 3110-D : Market Surveillance Administrator, Market Surveillance Administrator allegations against TransAlta Corporation et al., Mr. Nathan Kaiser and Mr. Scott Connelly, Proceeding 3110, Application , Phase 1, July 27, Exhibit 3524-X0771, AltaLink argument, PDF page 95. Dow Chemical Inc. v. Shell Chemicals Canada Ltd., 2010 ABCA 126 at paragraphs Canadian National Railway Co. v. Volker Stevin Contracting Ltd., 1991 ABCA 287 (CanLII). 4 Decision 3524-D (May 9, 2016)

13 how to interpret specific clauses in a contract, as these are matters that must be submitted to the court for determination. 21. By comparison, AltaLink submitted that it was entitled to rely on the evidence of its experts, PricewaterhouseCoopers LLP (PwC) and PowerAdvocate as this evidence had been prepared by recognized experts in their respective fields. 22. The RPG argued in reply that AltaLink s challenge to the admissibility of FTI s evidence should be rejected on the basis it is too late to purport to challenge the admissibility of evidence in closing argument. It contended that Mr. Tusa s expertise in respect of scheduling, project cost assessment and change order analysis was not challenged by AltaLink and that if AltaLink had concerns about the admissibility of this evidence, it should have raised such concern prior to final argument. It submitted that AltaLink s allegation that FTI breached the duties of an expert, by referring to clauses and purchase orders for prior AltaLink projects in its report, was without merit because all Mr. Tusa did was refer to standard clauses of construction contracts dealing with the question of who will be responsible for cost overruns caused by delays. The RPG submitted that Mr. Tusa s business experience and understanding of such clauses should be considered to be relevant evidence, and helpful to the Commission. 23. The RPG argued that the case law cited by AltaLink in support of its view regarding FTI s testimony could be distinguished as these cases concerned a civil action for breach of contract, where the outcome of the case turned on the interpretation of the contracts. As such, the cited cases were not relevant to a rate setting proceeding. Moreover, the Commission was not bound by the rules of evidence applicable to judicial proceedings and Commission proceedings frequently allow witnesses to describe their business understanding of key contracts so long as no legal opinion is offered. Commission findings 24. The Commission will not disregard the evidence of Mr. Tusa or Mr. de Palezieux. Rather, in the findings that follow, and consistent with its December 1, 2015 direction, will assess the weight to be ascribed to these witnesses evidence having considered their qualifications, background and relevant experience in relation to the areas to which they provided evidence, and considering the persuasiveness of their evidence. 3 Forecasting methodology/process and key assumptions 25. AltaLink set out its forecasting methodology and process in Section 1.8 of the application. It stated that its application is consistent with the Uniform System of Accounts/Minimum Filing Requirements (USA/MFR) Consensus document and accords with the direction in paragraph 124 of Decision [ 15 ] AltaLink further explained: It had implemented zero-based budgeting several years ago Decision : AltaLink Management Ltd., General Tariff Application, Proceeding 1021, Application , November 18, Exhibit AML-3524, application, page 1-11, paragraph 50. Decision 3524-D (May 9, 2016) 5

14 Each department assessed all activities required to be performed to meet the objectives necessary to its statutory duties and obligations during the test period. Departmental reassessments established the full-time equivalents (FTE) and contractor levels required to carry out forecast workloads and general operating expenses (GOE). 27. Guidelines, as described in Section of the application, were established for each of the operating departments by the finance department. Those guidelines were followed in the preparation of each department s 17 forecast and those forecasts were then adjusted by the general forecasting parameters and rolled up to form the forecast for the company. 28. Once the activities for the general tariff application (GTA) test years were forecast, AltaLink assessed the activities to determine which costs should be capitalized as required by its capitalization policy. It further explained that both International Financial Reporting Standards (IFRS) and its capitalization policy dictated that no indirectly attributable internal labour costs or costs in support of capital projects were to be included in the capital program. Subsequently, AltaLink compared its 2015 and 2016 forecasts against its 2013 actuals and 2014 management update and, additionally, examined its capital and operating expenses in its compliance filing to assess the consistency and range of reasonableness of its forecast AltaLink also included as Appendix 1-C, a table listing each of the positions at AltaLink by functional group as directed in Decision and Decision No parties made any comments specific to the forecasting methodology in final argument or reply argument. Commission findings 31. Direction 1 from Decision stated: 1. The Commission must have full visibility of the process by which AltaLink converts its department-level forecasts into the FTEs requested in individual O&M [operating and maintenance] USA accounts. The Commission directs AltaLink to clearly and precisely set out the following information in an updated FTE forecast in the refiling: the name of each AltaLink staff position, specified at the most detailed level possible, by department a clear identification of the AltaLink cost centre (not USA account) for each AltaLink staff position for each AltaLink staff position, the specific allocation that has been applied between O&M and capital, expressed as a percentage for each AltaLink staff position allocated wholly or partially to O&M, the USA to which the FTE is assigned... Paragraph Chief Executive Officer, Chief Financial Officer, Chief Operating Officer, Projects, Customer Service, Communications and Stakeholder Engagement, Law and Regulatory, Corporate Development and Human Resources were the departments cited. Exhibit AML-3524, application, pages 1-13 to 1-14, paragraphs Decision : AltaLink Management Ltd., General Tariff Application, Proceeding 2044, Application , November 12, Decision : AltaLink Management Ltd. Refiling Pursuant to Decision and Decision , Proceeding 3024, Application , September 8, 2014, paragraph Decision 3524-D (May 9, 2016)

15 32. Further, in Decision the Commission stated: 22. No interested parties specifically commented on AltaLink s response to Directive 1 in argument or reply. This notwithstanding, the Commission makes the following additional findings with respect to AltaLink s response to Directive 1. First, the Commission finds that the breakdown of full-time equivalents (FTEs) by position by cost centre and showing the operating and maintenance (O&M) versus capital split applied for each position indicated in Attachment B-01 of Section B of the refiling application complies in full with Directive 1. Second, the Commission finds that the information provided in Attachment B-01 would be of significant assistance in processing future AltaLink GTAs. Accordingly, the Commission directs AltaLink to provide a breakdown of individual job classifications and FTEs, disaggregated by cost centre for each appliedfor test year in AltaLink s next GTA The Commission continues to find the information provided in Appendix 1-C of the application to be of assistance and directs AltaLink to continue to provide this information in future GTAs. 3.1 Forecast parameters and assumptions 34. AltaLink s revenue requirement forecast for the test period relied on the assumptions outlined in Table in Section of the application. The escalators applied by AltaLink in Table are reproduced, in part, as follows: Table 1. Labour escalation Summary of major AltaLink forecast parameters (%) Salary and wages (labour) Union Non-union Executive Contractor General inflation Capital escalation Source: Exhibit AML-3524, application, Table AltaLink did not change these forecast parameters in its June 1, 2015 amendment 23 but did provide the following update in its October 16, 2015 update filing: Decision , Appendix 3 Summary of Commission directions. Decision , paragraph 22. Exhibit 3524-X0299, June update. Exhibit 3524-X0418, October 2015 update. Decision 3524-D (May 9, 2016) 7

16 Table 2. Summary of major AltaLink forecast parameters (October 16, 2015) Labour escalation (%) Salary and wages (labour) Union Non-union Executive Contractor General inflation Capital escalation Source: Exhibit 3524-X0418, October 2015 update, Table The forecasts in Table were prepared by each department using constant 2014 dollars and inflationary increases were subsequently added. General inflation was based on the Alberta Government s Economic Outlook for the test years. 25 Escalation rates for 2015 were updated on August 28, 2014, based on the Economic Trends quarterly update published by the Alberta Treasury Board and Finance. It further explained that: Escalation factors have been specifically forecast for other expenses such as salaries, benefits, contracted manpower, insurance, property taxes, ASP [annual structure payments] and capital projects as described below: salary and benefits escalation is based on analysis which is discussed in Section 1.8.5; in certain cases, contracted manpower costs are based on the forecast of market rates in specific contractor categories. Where specific market rate information was not available at the time of forecast, those areas of contracted manpower are adjusted similarly to labour escalation; General Operating Expense (GOE) escalation is based on general inflation rates and usage rates. Office expense, staff expense and building-related costs are escalated using the general inflation rates noted above; ASP and details of escalation can be found in Section and in Appendix 12.1 of this Application; property and business taxes as well as insurance costs are escalated based on industry specific rates, as described in Sections 5.4 and of this Application; and capital project forecasts were escalated as provided in Section 10.2 of this Application Escalations 37. AltaLink set out its labour overview in Section of its application. In that and subsequent subsections, AltaLink indicated there to be a supply shortage of qualified employees to meet the demand of available positions both in the Alberta labour market and the electric utility industry across Canada. It is forecast to worsen over the coming years Exhibit AML-3524, application, Section 1.8.4, paragraph 90. Exhibit AML-3524, application, paragraph 56. Capital escalators were mentioned in Section 10.2 but details were not provided in that section. Further discussion on this topic is at Section of this decision. Exhibit AML-3524, application, paragraph 92 and paragraphs of the application cite sources such as the 2013 Annual Alberta Labour Market Review, Alberta s Occupational Demand and Supply Outlook 8 Decision 3524-D (May 9, 2016)

17 38. This section of the decision addresses contractor, general inflation and capital escalators. Escalators regarding union, non-union and executive employees are discussed in the compensation section of this decision Contractor escalation rates 39. AltaLink initially forecast contractor escalation rates of 5.45 per cent for 2015 and 5.22 per cent for It subsequently revised these rates to 4.90 per cent for 2015 and 2.00 per cent for AltaLink determines its forecast for contractor escalation rates: based on the forecast of market rates in specific contractor categories. Where specific market rate information was not available at the time of forecast, those areas of contracted manpower are adjusted similarly to labour escalation; When it updated its contractor escalation rates, AltaLink stated: For many years, AltaLink has used the blended employee labour escalation rate as a forecast for operating expense related contractor escalation rates where specific market rate information is not available. Operating expense contractors primarily provide labour and as a result, they would be subject to the same escalation pressures as AltaLink would be for employees. AltaLink will revise the contracted manpower escalation rates as follows and will provide updated forecast schedules: 2015 reduction from 5.45% to 4.9% 2016 reduction from 5.22% to 4.27% The RPG opposed the escalation rates proposed by AltaLink and argued that AltaLink should make reasonable efforts, due to the economic downturn, to seek lower contractor rates. It submitted that: AltaLink s contractor employees face similar labor forces as AltaLink s non-union and executive employees. Contractor companies across the province, particularly construction and engineering firms, are under pressure to cut prices for their customers and are laying off many workers. Much like all the rest of AltaLink s labor categories, the labor supply for the contractor market is increasing due to the Alberta economic circumstances and is putting downward pressure on compensation. The Ratepayer Group recommends escalation rates of 0.7% in 2015 and 2.2% in and the Power in Motion Labour Market Information Study Full Report (2012 Update), each indicating expected labour shortages in coming years. Exhibit AML-3524, application, Table , paragraph 55. In paragraph 56 of Exhibit AML-3524, for contractor rates AltaLink stated: in certain cases, contracted manpower costs are based on the forecast of market rates in specific contractor categories. Where specific market rate information was not available at the time of forecast, those areas of contracted manpower are adjusted similarly to labour escalation. Exhibit 3524-X0418, October 2015 update, Table , paragraph 80. Exhibit AML-3524, application, paragraph 56. Exhibit 3524-X0039, PDF page 7, response to AML-AUC-2015Jan20-002(b). Exhibit 3524-X0671, RPG revised evidence, paragraph 179. Decision 3524-D (May 9, 2016) 9

18 43. The RPG s recommended contractor escalation rates of 0.7 per cent for 2015 and 2.2 per cent for 2016 were based on the Conference Board of Canada s forecast Alberta Wage and Salary escalation (summer 2015). 33 Commission findings 44. In Decision the Commission stated the following: 37. The CCA noted that the 4.81 per cent contractor escalation rate was derived as a weighted average of different salary escalation rates for AltaLink union, non-union, and executive staff, and expressed concern that AltaLink had not provided any independent support for its contracted manpower escalator. The CCA expressed specific concern that AltaLink s approach of using a blended weighted average of salary escalation rates, for different types of AltaLink staff, reflected AltaLink s internal staff escalation practices, including progression related increases for union staff and adjustments for non-union staff designed to achieve market compensation levels. Accordingly, rather than reflecting AltaLink s internal salary structure, the CCA submitted that AltaLink should be directed to use contracted manpower escalation rates for both O&M and capital in a range between 3.5 per cent and 3.75 per cent. 42. The Commission shares some of the CCA s concerns that AltaLink s proposed escalator for contracted manpower may be excessive. In particular, it is not clear to the Commission that agreed-upon escalators arising from union labour agreements with AltaLink apply to the market for contracted manpower. The Commission also considers that the increases included in AltaLink s salary escalator for non-union labour do not apply to the market for contractor services. In view of the foregoing, the Commission considers that an escalator of 3.75 per cent per year, which is at the high end of the range proposed by the CCA, is reasonable. AltaLink is directed to make adjustments to all contracted manpower forecasts that relied upon AltaLink s proposed 4.81 per cent escalator at the time of its refiling. 45. The Commission continues to have the same concerns expressed in Decision It is not persuaded that increases included in AltaLink s salary escalator for non-union labour or union negotiated increases properly apply to the market for contractor services. Further, AltaLink has failed to provide a breakdown of how it established its contractor escalation rates as between specific market rates and its own labour escalation rates. AltaLink explained that it determines its forecast of contracted manpower costs by reviewing both the forecast of market rates in specific contractor categories and, where specific market rate information is not available at the time of forecast, adjusting those areas of contracted manpower to labour escalation. 34 However, it did not explain or provide a breakdown of how the aggregate contractor escalator was calculated as between market rates and its own labour escalator. The only information provided was AltaLink s own internal escalator rates for labour, which for non-union base pay annual increases, included a 2.0 per cent 35 escalation to achieve market median target total direct compensation and a further 1.0 per cent 36 to represent progression increases. As AltaLink s labour rates include adjustments for progression and movement to the market median, the Commission finds that neither of these amounts should be included in the determination of proper escalation rates for contractors Exhibit 3524-X0778, RPG argument, paragraphs Exhibit AML-3524, application, paragraph 56. Exhibit AML-3524, application, Table Exhibit AML-3524, application, Table Decision 3524-D (May 9, 2016)

19 46. The Commission accepts the submissions of the RPG regarding the decline in the Alberta economy, the increase in unemployment, and the increase in the supply of contractor labour. Based on the updated evidence, the Commission considers that the extent of labour shortages identified in AltaLink s initial forecast does not exist today. 47. Removing 3.0 per cent from AltaLink s updated escalation rates 37 for contractors to account for AltaLink s internal adjustments for progression and movement to market median, results in contractor escalation rates of 1.90 per cent for 2015 and 1.27 per cent for These rates are similar to those forecast by the Conference Board of Canada s forecast Alberta Wage and Salary escalation from summer AltaLink is directed to reflect contractor escalation rates of 1.90 per cent for 2015 and 1.27 per cent for 2016 in its compliance filing Capital escalation rates 48. AltaLink presented its forecast capital project escalation rates in Table of its original application and provided an explanation for escalating capital projects in Section 10.2 of its application Section 10.2 of the original application forecast capital escalation rates of 5.4 per cent for 2015 and 6.5 per cent for These forecasts were determined by PowerAdvocate, whom AltaLink engaged for this purpose. 39 AltaLink did not adjust these rates when it updated its application in October of Section 10.2 of the revised application does not refer to these rates but only to a single rate of 3.2 per cent that is used to adjust expenditures delayed from 2015 to 2016 for expected annual inflation in 2016, referring to updates provided in IR AML- CCA-2015MAY01-092(a) In AML-CCA-2015MAY01-092(a), AltaLink stated that it had completed its update of escalation rates for DA (direct assign) projects, and that the updated three-year compound annual growth rate (CAGR) for AltaLink s capital portfolio was 3.4 per cent and the annual five-year portfolio escalation CAGR was 3.9 per cent. 42 For the source of these rates, AltaLink referred to the updated escalation study produced by PowerAdvocate, dated June 16, 2015, that it provided as an attachment to the IR See paragraph 110. Exhibit AML-3524, application, paragraph 56. Exhibit AML-3524, PDF page 3043 (Appendix 19-D). Exhibit 3524-X0418, October 2015 update, paragraph 82. Exhibit 3524-X0418, October 2015 update, paragraph 620. Exhibit 3524-X0317, PDF page 19. Exhibit 3524-X0317, PDF pages (AltaLink Capital Project Escalation Planning: 2015 Update). Decision 3524-D (May 9, 2016) 11

20 51. The updated escalation study by PowerAdvocate included the following summary table: Table 3. AltaLink portfolio escalation by PPS cost category breakdown Category % of AltaLink portfolio Projected YOY escalation (%) 3-year escalation (4Q Q 2017) 3-year CAGR 5-year escalation (4Q Q 2019) Labour Materials Distributed cost Owner cost Other cost Portfolio Source: Exhibit 3524-X0317, PDF page The three-year and five-year CAGRs referred to by AltaLink appear in the last row of Table 3 above in the third last and last columns, respectively. These CAGRs are obtained by compounding and then geometrically averaging the Projected YOY Escalation values in the last row of the table, for 2015, 2016 and 2017 in the three-year CAGR, and for 2015, 2016, 2017, 2018 and 2019 in the five-year CAGR. The specific 2016 escalator value of 3.2 per cent that AltaLink stated it used for escalating costs shifted from 2015 to 2016, appears in the fourth column of the last row of this table. The corresponding 2015 escalator in the third column of the last row is 2.3 per cent. 53. As Table 3 indicates, for each year, escalators are obtained for labour, materials, distributed cost, owner cost, and other cost; these escalators for each category are weighted by the percentage shares in the second column of the table to obtain the overall (or portfolio) escalator for that year. The methodology used to obtain forecasts of escalators for the various categories is not explained by PowerAdvocate in its report. PowerAdvocate does, however, provide a number of assumptions or conclusions that underlie its forecasts. These include: 5-year CAGR Recent market conditions will cause reduced rates of escalation in 2015; however, the transmission industry should gradually recover by Slowdowns in materials and labour in 2015 and 2016 drive low escalation rates; afterwards, the industry should recover along with escalation rates. 45 WTI [West Texas Intermediate spot oil] prices should remain in the $50-60 range over the next couple of months, but should rebound to higher prices in the long term. 46 As CAD and oil prices are highly correlated, they should strengthen together, which would reduce prices for items procured outside of Canada. 47 The weak Canadian dollar has widened the gap between CAD and USD commodity prices; however, the gap should close if oil prices rebound Exhibit 3524-X0317, PDF page 24. Exhibit 3524-X0317, PDF page 25. Exhibit 3524-X0317, PDF page 28. Exhibit 3524-X0317, PDF page Decision 3524-D (May 9, 2016)

21 54. In its report, PowerAdvocate explained that it developed a customized index to reflect the elasticity more accurately and to identify the cost drivers of Alberta s construction labour market. 49 Power Advocate s Alberta custom constrained labour market index was composed of direct labour costs (60 per cent), demand market premium costs (30 per cent) and equipment costs (10 per cent). In turn, each of these categories comprised a number of other indexes. The construction equipment rental index comprised (i) the Producer Price Index (PPI) for construction, transportation, mining and forestry equipment rental and leasing, Canada; (ii) an index for diesel fuel at self-service filling stations in Calgary; and (iii) the Consumer Price Index (CPI) for transportation. The weights for these three components were not specified. The demand market premium index comprised indexes of (i) electric power engineering construction in Canada (7.5 per cent of the 30 per cent weight) and (ii) in Alberta (7.5 per cent), (iii) total capital expenditure on construction in Canada (2.5 per cent) and (iv) in Alberta (7.5 per cent), (v) transmission and distribution (T&D) labour demand in Alberta (2.5 per cent), and (vi) highvoltage (HV) lineman demand in Canada (2.5 per cent). The direct labour costs index, also referred to as the weekly take-home pay index, is designed to track the escalation of the cost of labour to the subcontractor (excluding per diem and subcontractor fees, which are reflected in the demand market premium index). 50 It includes labourer straight time pay, labourer overtime pay, and additional direct costs to the subcontractor calculated as a fixed percentage of the base wage (e.g., overhead, burden, 10 per cent Alberta wage bonus, taxes and other miscellaneous). The weekly take-home pay is calculated as the sum of two components: (i) the sum of wages and supplements multiplied by average weekly hours worked excluding overtime (for utility system construction in Alberta), and (ii) the sum of wages and supplements multiplied by average weekly overtime hours worked (for utility system construction in Alberta) multiplied by 1.5. None of the specific data series that are used in formulating these indexes were specified, although in terms of wage rates, a graph showing growth in an index of Alberta construction union wages is included in the report Less detail was provided by PowerAdvocate in its report concerning the other cost categories included in Table 3. Specific details of the component indexes, sources for any of the data, including data for the labour indexes, or the method used to obtain forecasts of any of the series underlying the escalators, or the escalators themselves, were not provided. 56. In its evidence, the RPG stated that due to current Alberta labor market conditions, it believed that labour escalation rate components within AltaLink s capital escalation rate would be no greater than forecast wage inflation in the province. 52 Therefore, the escalation rates for labour in Table 3 for 2015 and 2016, of 4.4 per cent and 2.2 per cent respectively, should be replaced with 0.7 per cent and 2.2 per cent respectively, in accordance with the Conference Board of Canada s Summer 2015 forecast of Alberta Wage and Salary escalations. The RPG also stated that most of the other component escalation rates within AltaLink s capital escalation rate, including materials, distributed cost, owner costs, and other costs, included some elements of labour work on projects among other costs. 53 Since these components of capital escalation rates were mixed by nature and, given the current labour market and downward trending Alberta economy, it recommended that, in line with Alberta CPI rates forecast by the government of Exhibit 3524-X0317, PDF page 30. Exhibit 3524-X0317, PDF page 38. Exhibit 3524-X0317, PDF page 41. Exhibit 3524-X0317, PDF page 40. Exhibit 3524-X0670, RPG revised evidence, Appendix A, paragraph 72, PDF page 95. Exhibit 3524-X0670, RPG revised evidence, Appendix A, paragraph 73, PDF page 95. Decision 3524-D (May 9, 2016) 13

22 Alberta in its first quarter 2015 fiscal update, materials, distributed cost, owner costs, and other escalation rates of 0.9 per cent and 1.7 per cent be used in 2015 and 2016, respectively. The RPG also performed a cost breakdown based on portfolio (transmission, substation, telecom)/ category/subcategory; all with associated weights. This cost breakdown, using AltaLink s original escalators for each portfolio/category/subcategory, 54 approximately reproduced AltaLink s original overall escalators of 5.4 per cent and 6.5 per cent for 2015 and Using the same technique, but with its recommended escalators of 0.7 per cent and 2.2 per cent for 2015 and 2016 for labour, and 0.9 per cent and 1.7 per cent for all other categories, yielded the RPG s recommended capital escalation rates of 0.66 per cent for 2015 and 1.86 per cent for In its evidence, FTI also considered AltaLink s revised capital escalation rates of 2.3 per cent for 2015 and 3.2 per cent for 2016 to be unreasonable, given current market/ economic conditions for labour, material, and distributed costs. 56 Using the same approach as the RPG, FTI replaced the labour, material and distributed cost escalation rates used in AltaLink s weighted portfolio escalation rate model with elements reflecting current market and economic conditions, as provided by Statistics Canada and economic data from the Conference Board of Canada s Provincial Outlook Economic Forecast for summer When current market and economic escalation rates were applied to AltaLink s weighted average portfolio model, capital escalations for 2015 and 2016 were 0.95 per cent and 1.84 per cent, respectively. 58. AltaLink submitted rebuttal evidence in response to the recommendations of the RPG and FTI. AltaLink explained that its methodology was reflective of the market, specifically considered the exact items that are most pertinent to AltaLink s capital program, and could be substantiated through publically-available indices. 57 AltaLink stated further that in recommending escalations based on the CPI, FTI and RPG were confusing general inflation with the very specific cost escalations associated with the construction of transmission capital projects, and further, escalation related to transmission construction is fundamentally different than generic consumer inflation. 58 For labour costs, AltaLink argued that 2015 forecast expenditures were based on July actuals to date and, therefore, were reflective of actual labour costs, while 2016 forecast expenditures reflect a labour forecast based on relevant and publicallyavailable indices. 59 AltaLink also took issue with the FTI claim that an economic downturn in Alberta had put downward pressure on labour costs, arguing that employers rarely, if ever, make cuts to nominal wages In its argument, AltaLink also responded to the use of the Electric Utility Construction Price Index (EUCPI), an index produced by Statistics Canada that was suggested as an alternative during questioning from the Commission. 61 AltaLink stated that the EUCPI is not representative of AltaLink s specific transmission system portfolio, the transmission line systems Exhibit 3524-X0087, PDF page 5, AML-CCA-2015JAN20-035REV. Exhibit 3524-X0670, RPG revised evidence, Appendix A, paragraph 74, PDF pages Exhibit 3524-X0673, FTI revised evidence, page 27. Exhibit 3524-X0679, AltaLink rebuttal, paragraph 553. Exhibit 3524-X0679, AltaLink rebuttal, paragraph 556. Exhibit 3524-X0679, AltaLink rebuttal, paragraph 561. Exhibit 3524-X0679, AltaLink rebuttal, paragraph 562. Transcript, Volume 7, pages 1340 and Decision 3524-D (May 9, 2016)

ENMAX Power Corporation

ENMAX Power Corporation Decision 22238-D01-2017 ENMAX Power Corporation 2016-2017 Transmission General Tariff Application December 4, 2017 Alberta Utilities Commission Decision 22238-D01-2017 ENMAX Power Corporation 2016-2017

More information

Consumers Coalition of Alberta

Consumers Coalition of Alberta Decision 22157-D01-2017 Decision on Preliminary Question AltaLink Management Ltd. 2012-2013 Deferral Account Reconciliation Costs Award February 15, 2017 Alberta Utilities Commission Decision 22157-D01-2017

More information

EPCOR Energy Alberta GP Inc.

EPCOR Energy Alberta GP Inc. Decision 20633-D01-2016 EPCOR Energy Alberta GP Inc. 2016-2017 Regulated Rate Tariff Application December 20, 2016 Alberta Utilities Commission Decision 20633-D01-2016 EPCOR Energy Alberta GP Inc. 2016-2017

More information

ATCO Electric Ltd. Stage 2 Review of Decision D ATCO Electric Ltd Transmission General Tariff Application

ATCO Electric Ltd. Stage 2 Review of Decision D ATCO Electric Ltd Transmission General Tariff Application Decision 22483-D01-2017 Stage 2 Review of Decision 20272-D01-2016 2015-2017 Transmission General Tariff Application December 6, 2017 Alberta Utilities Commission Decision 22483-D01-2017 Stage 2 Review

More information

Decision D FortisAlberta Inc PBR Capital Tracker True-Up and PBR Capital Tracker Forecast

Decision D FortisAlberta Inc PBR Capital Tracker True-Up and PBR Capital Tracker Forecast Decision 20497-D01-2016 FortisAlberta Inc. 2014 PBR Capital Tracker True-Up and 2016-2017 PBR Capital Tracker Forecast February 20, 2016 Alberta Utilities Commission Decision 20497-D01-2016 FortisAlberta

More information

AltaLink Investment Management Ltd. And SNC Lavalin Transmission Ltd. et al.

AltaLink Investment Management Ltd. And SNC Lavalin Transmission Ltd. et al. Decision 3529-D01-2015 AltaLink Investment Management Ltd. And SNC Lavalin Transmission Ltd. et al. Proposed Sale of AltaLink, L.P Transmission Assets and Business to Mid-American (Alberta) Canada Costs

More information

EPCOR Distribution & Transmission Inc.

EPCOR Distribution & Transmission Inc. Decision 21229-D01-2016 EPCOR Distribution & Transmission Inc. 2015-2017 Transmission Facility Owner Tariff and 2013 Generic Cost of Capital Compliance Application April 15, 2016 Alberta Utilities Commission

More information

Decision D FortisAlberta Inc Performance-Based Regulation Capital Tracker True-Up. January 11, 2018

Decision D FortisAlberta Inc Performance-Based Regulation Capital Tracker True-Up. January 11, 2018 Decision 22741-D01-2018 FortisAlberta Inc. 2016 Performance-Based Regulation Capital Tracker True-Up January 11, 2018 Alberta Utilities Commission Decision 22741-D01-2018 FortisAlberta Inc. 2016 Performance-Based

More information

AltaGas Utilities Inc.

AltaGas Utilities Inc. Decision 2013-465 2014 Annual PBR Rate Adjustment Filing December 23, 2013 The Alberta Utilities Commission Decision 2013-465: 2014 Annual PBR Rate Adjustment Filing Application No. 1609923 Proceeding

More information

EPCOR Distribution & Transmission Inc.

EPCOR Distribution & Transmission Inc. Decision 3539-D01-2015 EPCOR Distribution & Transmission Inc. 2015-2017 Transmission Facility Owner Tariff October 21, 2015 Alberta Utilities Commission Decision 3539-D01-2015: EPCOR Distribution & Transmission

More information

AltaGas Utilities Inc.

AltaGas Utilities Inc. Decision 23898-D01-2018 2019 Annual Performance-Based Regulation Rate Adjustment Filing December 20, 2018 Alberta Utilities Commission Decision 23898-D01-2018 2019 Annual Performance-Based Regulation Rate

More information

Decision D Rebasing for the PBR Plans for Alberta Electric and Gas Distribution Utilities. First Compliance Proceeding

Decision D Rebasing for the PBR Plans for Alberta Electric and Gas Distribution Utilities. First Compliance Proceeding Decision 22394-D01-2018 Rebasing for the 2018-2022 PBR Plans for February 5, 2018 Alberta Utilities Commission Decision 22394-D01-2018 Rebasing for the 2018-2022 PBR Plans for Proceeding 22394 February

More information

Decision D ATCO Electric Ltd. Compliance Filing to Decision D Capital Tracker True-Up

Decision D ATCO Electric Ltd. Compliance Filing to Decision D Capital Tracker True-Up Decision 23454-D01-2018 ATCO Electric Ltd. Compliance Filing to Decision 22788-D01-2018 2016 Capital Tracker True-Up May 4, 2018 Alberta Utilities Commission Decision 23454-D01-2018 ATCO Electric Ltd.

More information

Alberta Electric System Operator

Alberta Electric System Operator Decision 23065-D01-2017 Alberta Electric System Operator 2018 Independent System Operator Tariff Update November 28, 2017 Alberta Utilities Commission Decision 23065-D01-2017 Alberta Electric System Operator

More information

Decision D Generic Cost of Capital. Costs Award

Decision D Generic Cost of Capital. Costs Award Decision 21856-D01-2016 Costs Award December 2, 2016 Alberta Utilities Commission Decision 21856-D01-2016 Costs Award Proceeding 21856 December 2, 2016 Published by Alberta Utilities Commission Fifth Avenue

More information

ATCO Gas and Pipelines Ltd.

ATCO Gas and Pipelines Ltd. Decision 2738-D01-2016 Z Factor Application for Recovery of 2013 Southern Alberta Flood Costs March 16, 2016 Alberta Utilities Commission Decision 2738-D01-2016 Z Factor Application for Recovery of 2013

More information

ENMAX Power Corporation Distribution and Transmission Deferral Account Reconciliation

ENMAX Power Corporation Distribution and Transmission Deferral Account Reconciliation Decision 23108-D01-2018 2014 Distribution and 2014-2015 Transmission Deferral Account Reconciliation February 27, 2018 Alberta Utilities Commission Decision 23108-D01-2018 2014 Distribution and 2014-2015

More information

Decision The ATCO Utilities. Corporate Costs. March 21, 2013

Decision The ATCO Utilities. Corporate Costs. March 21, 2013 Decision 2013-111 Corporate Costs March 21, 2013 The Alberta Utilities Commission Decision 2013-111: Corporate Costs Application No. 1608510 Proceeding ID No. 1920 March 21, 2013 Published by The Alberta

More information

AltaLink Management Ltd General Tariff Application

AltaLink Management Ltd General Tariff Application Decision 21413-D01-2016 2015-2016 General Tariff Application July 7, 2016 Alberta Utilities Commission Decision 21413-D01-2016 2015-2016 General Tariff Application Proceeding 21413 July 7, 2016 Published

More information

AltaLink Management Ltd.

AltaLink Management Ltd. Decision 21054-D01-2016 2013-2014 General Tariff Application (Proceeding 2044-Reopened for Midgard Audit) March 7, 2016 Alberta Utilities Commission Decision 21054-D01-2016: Proceeding 21054 March 7,

More information

AltaLink, L.P. (unaudited)

AltaLink, L.P. (unaudited) Condensed Interim Financial Statements (unaudited) For the three months ended March 31, 2014 and 2013 CONDENSED INTERIM FINANCIAL STATEMENTS Statement of Financial Position (unaudited) As at Notes March

More information

Decision D Alberta PowerLine L.P. Tariff Application. January 23, 2018

Decision D Alberta PowerLine L.P. Tariff Application. January 23, 2018 Decision 23161-D01-2018 Alberta PowerLine L.P. Tariff Application January 23, 2018 Alberta Utilities Commission Decision 23161-D01-2018 Alberta PowerLine L.P. Tariff Application Proceeding 23161 January

More information

Decision ATCO Gas General Rate Application Phase I Compliance Filing to Decision Part B.

Decision ATCO Gas General Rate Application Phase I Compliance Filing to Decision Part B. Decision 2006-083 2005-2007 General Rate Application Phase I Compliance Filing to Decision 2006-004 August 11, 2006 ALBERTA ENERGY AND UTILITIES BOARD Decision 2006-083: 2005-2007 General Rate Application

More information

Financial Statements. AltaLink, L.P. Years ended December 31, 2010 and 2009

Financial Statements. AltaLink, L.P. Years ended December 31, 2010 and 2009 Financial Statements FINANCIAL STATEMENTS INDEPENDENT AUDITOR S REPORT To the Partners of We have audited the accompanying financial statements of, which comprise the balance sheets as at December 31,

More information

Statement of Financial Position (unaudited)

Statement of Financial Position (unaudited) Condensed Interim Financial Statements (unaudited) For the three months ended March 31, 2015 and 2014 CONDENSED INTERIM FINANCIAL STATEMENTS Statement of Financial Position (unaudited) As at Notes March

More information

Alberta Utilities Commission

Alberta Utilities Commission Decision 22091-D01-2017 Commission-Initiated Proceeding to Review the Terms and November 9, 2017 Decision 22091-D01-2017 Commission-Initiated Proceeding to Review the Terms and Proceeding 22091 Application

More information

Decision D ATCO Electric Ltd Transmission General Tariff Application. Costs Award

Decision D ATCO Electric Ltd Transmission General Tariff Application. Costs Award Decision 21747-D01-2017 January 30, 2017 Alberta Utilities Commission Decision 21747-D01-2017 Proceeding 21747 January 30, 2017 Published by Alberta Utilities Commission Fifth Avenue Place, Fourth Floor,

More information

Decision D ATCO Electric Ltd. Amounts to be Paid Into and Out of Balancing Pool for Chinchaga Power Plant Sale

Decision D ATCO Electric Ltd. Amounts to be Paid Into and Out of Balancing Pool for Chinchaga Power Plant Sale Decision 21833-D01-2016 Amounts to be Paid Into and Out of Balancing Pool for Chinchaga Power Plant Sale December 20, 2016 Alberta Utilities Commission Decision 21833-D01-2016 Proceeding 21833 December

More information

AltaLink Management Ltd.

AltaLink Management Ltd. Decision 22612-D01-2018 November 13, 2018 Alberta Utilities Commission Decision 22612-D01-2018 to PiikaniLink L.P. and KainaiLink L.P. and the Proceeding 22612 Applications 22612-A001, 22612-A002, 22612-A003,

More information

Decision FortisAlberta Inc Phase II Distribution Tariff. January 27, 2014

Decision FortisAlberta Inc Phase II Distribution Tariff. January 27, 2014 Decision 2014-018 FortisAlberta Inc. 2012-2014 Phase II Distribution Tariff January 27, 2014 The Alberta Utilities Commission Decision 2014-018: FortisAlberta Inc. 2012-2014 Phase II Distribution Tariff

More information

Decision D Performance-Based Regulation Plans for Alberta Electric and Gas Distribution Utilities.

Decision D Performance-Based Regulation Plans for Alberta Electric and Gas Distribution Utilities. Decision 22082-D01-2017 2018-2022 Performance-Based Regulation Plans for Alberta Electric and Gas Distribution Utilities February 6, 2017 Alberta Utilities Commission Decision 22082-D01-2017 2018-2022

More information

Decision ATCO Utilities. Corporate Cost Allocation Methodology. September 20, 2010

Decision ATCO Utilities. Corporate Cost Allocation Methodology. September 20, 2010 Decision 2010-447 Corporate Cost Allocation Methodology September 20, 2010 ALBERTA UTILITIES COMMISSION Decision 2010-447: Corporate Cost Allocation Methodology Application No. 1605473 Proceeding ID. 306

More information

Statement of Financial Position (unaudited)

Statement of Financial Position (unaudited) Condensed Interim Financial Statements (unaudited) For the three and nine months ended and CONDENSED INTERIM FINANCIAL STATEMENTS Statement of Financial Position (unaudited) As at Notes December 31, ASSETS

More information

We believe that the audit evidence we have obtained in our audits is sufficient and appropriate to provide a basis for our audit opinion.

We believe that the audit evidence we have obtained in our audits is sufficient and appropriate to provide a basis for our audit opinion. Financial Statements For the years ended 2017 and 2016 Deloitte LLP 700, 850 2 Street SW Calgary, AB T2P 0R8 Canada Tel: 403-267-1700 Fax: 587-774-5379 www.deloitte.ca INDEPENDENT AUDITOR S REPORT To the

More information

FORTISALBERTA INC. MANAGEMENT S DISCUSSION AND ANALYSIS

FORTISALBERTA INC. MANAGEMENT S DISCUSSION AND ANALYSIS FORTISALBERTA INC. MANAGEMENT S DISCUSSION AND ANALYSIS November 5, 2014 The following ( MD&A ) of FortisAlberta Inc. (the Corporation ) should be read in conjunction with the following: (i) the unaudited

More information

AltaLink Investment Management Ltd. and SNC Lavalin Transmission Ltd. et al.

AltaLink Investment Management Ltd. and SNC Lavalin Transmission Ltd. et al. Decision 2014-326 AltaLink Investment Management Ltd. and SNC Lavalin Transmission Ltd. et al. Proposed Sale of AltaLink, L.P. Transmission Assets and Business to MidAmerican (Alberta) Canada Holdings

More information

ATCO Gas and Pipelines Ltd. (South)

ATCO Gas and Pipelines Ltd. (South) Decision 3421-D01-2015 Northeast Calgary Connector Pipeline January 16, 2015 The Alberta Utilities Commission Decision 3421-D01-2015: Northeast Calgary Connector Pipeline Application 1610854 Proceeding

More information

Canadian Natural Resources Limited

Canadian Natural Resources Limited Decision 22669-D03-2017 Application for an Order Permitting the Sharing of Records Not Available to the Public Between Canadian Natural Resources Limited and ATCO Power Canada Ltd. July 21, 2017 Alberta

More information

AltaGas Utilities Inc.

AltaGas Utilities Inc. Decision 23623-D01-2018 AltaGas Utilities Inc. 2017 Capital Tracker True-Up Application December 18, 2018 Alberta Utilities Commission Decision 23623-D01-2018 AltaGas Utilities Inc. 2017 Capital Tracker

More information

Nova Scotia Company and TE-TAU, Inc.

Nova Scotia Company and TE-TAU, Inc. Alberta Energy and Utilities Board Decision 2004-025 3057246 Nova Scotia Company and TE-TAU, Inc. Request for Relief Under Section 101(2) of the PUB Act March 16, 2004 ALBERTA ENERGY AND UTILITIES BOARD

More information

Canadian Natural Resources Limited

Canadian Natural Resources Limited Decision 21306-D01-2016 Determination of Compensation for 9L66/9L32 Transmission Line Relocation August 16, 2016 Alberta Utilities Commission Decision 21306-D01-2016 Determination of Compensation for 9L66/9L32

More information

Alberta Electric System Operator 2018 ISO Tariff Application

Alberta Electric System Operator 2018 ISO Tariff Application Alberta Electric System Operator 2018 ISO Tariff Application Date: September 14, 2017 Table of Contents 1 Application... 6 1.1 Background... 6 1.2 Organization of application... 6 1.3 Relief requested...

More information

Decision D FortisAlberta Inc. Light-Emitting Diode Lighting Conversion Maintenance Multiplier for the City of St.

Decision D FortisAlberta Inc. Light-Emitting Diode Lighting Conversion Maintenance Multiplier for the City of St. Decision 21754-D01-2016 Light-Emitting Diode Lighting Conversion Maintenance Multiplier for the City of St. Albert August 11, 2016 Alberta Utilities Commission Decision 21754-D01-2016 Light-Emitting Diode

More information

MANAGEMENT S REPORT. Financial Statements December 31, 2011

MANAGEMENT S REPORT. Financial Statements December 31, 2011 Financial Statements December 31, 2011 MANAGEMENT S REPORT The accompanying financial statements of FortisAlberta Inc. (the Corporation ) have been prepared by management, who are responsible for the integrity

More information

AltaGas Utilities Inc.

AltaGas Utilities Inc. Decision 23740-D01-2018 AltaGas Utilities Inc. 2018-2019 Unaccounted-For Gas Rider E and Rider H October 25, 2018 Alberta Utilities Commission Decision 23740-D01-2018 AltaGas Utilities Inc. 2018-2019 Unaccounted-For

More information

Alberta Electric System Operator 2017 ISO Tariff Update

Alberta Electric System Operator 2017 ISO Tariff Update Alberta Electric System Operator 2017 ISO Tariff Update Date: October 20, 2016 Prepared by: Alberta Electric System Operator Prepared for: Alberta Utilities Commission Classification: Public Table of Contents

More information

E.ON Climate & Renewables Canada Ltd. Grizzly Bear Creek Wind Power Project

E.ON Climate & Renewables Canada Ltd. Grizzly Bear Creek Wind Power Project Decision 21513-D01-2016 Grizzly Bear Creek Wind Power Project July 21, 2016 Alberta Utilities Commission Decision 21513-D01-2016 Grizzly Bear Creek Wind Power Project Proceeding 21513 July 21, 2016 Published

More information

2011 Generic Cost of Capital

2011 Generic Cost of Capital Decision 2011-474 2011 Generic Cost of Capital December 8, 2011 The Alberta Utilities Commission Decision 2011-474: 2011 Generic Cost of Capital Application No. 1606549 Proceeding ID No. 833 December 8,

More information

Financial Statements For the years ended December 31, 2015 and 2014

Financial Statements For the years ended December 31, 2015 and 2014 FORTISALBERTA INC. Financial Statements MANAGEMENT S REPORT The accompanying annual financial statements of FortisAlberta Inc. (the Corporation ) have been prepared by management, who are responsible for

More information

ENMAX Energy Corporation

ENMAX Energy Corporation Decision 22054-D01-2017 Regulated Rate Option Tariff Terms and Conditions Amendment Application April 12, 2017 Alberta Utilities Commission Decision 22054-D01-2017 Regulated Rate Option Tariff Terms and

More information

ATCO Electric and ATCO Pipelines. Application for ATCO Electric and ATCO Pipelines License Fees

ATCO Electric and ATCO Pipelines. Application for ATCO Electric and ATCO Pipelines License Fees Decision 21571-D01-2016 and ATCO Pipelines 2015-2016 License Fees August 17, 2016 Alberta Utilities Commission Decision 21571-D01-2016 and ATCO Pipelines 2015-2016 License Fees Proceeding 21571 August

More information

TransCanada Energy Ltd.

TransCanada Energy Ltd. Decision 22302-D01-2017 Request for Permitting the Sharing of Records Not Available to the Public Between and Pembina Pipeline Corporation May 26, 2017 Alberta Utilities Commission Decision 22302-D01-2017

More information

Alberta Electric System Operator Amended 2018 ISO Tariff Application

Alberta Electric System Operator Amended 2018 ISO Tariff Application Alberta Electric System Operator Amended 2018 ISO Tariff Application Date: August 17, 2018 Table of Contents 1 Application... 6 1.1 Background... 6 1.2 Organization of application... 7 1.3 Relief requested...

More information

Langdon Waterworks Limited

Langdon Waterworks Limited Decision 20372-D01-2015 May 14, 2015 Alberta Utilities Commission Decision 20372-D01-2015 Proceeding 20372 May 14, 2015 Published by the: Alberta Utilities Commission Fifth Avenue Place, Fourth Floor,

More information

St NW, Edmonton, AB T5H 0E8 Canada epcor.com

St NW, Edmonton, AB T5H 0E8 Canada epcor.com 2000 10423 101 St NW, Edmonton, AB T5H 0E8 Canada epcor.com May 1, 2018 Alberta Utilities Commission 10th Floor, 10055 106 Street Edmonton, AB T5J 2Y2 Attention: Mr. Blair Miller Executive Director, Rates

More information

Decision D FortisAlberta Inc. Light-Emitting Diode (LED) Lighting Conversion Maintenance Multiplier Filing for 30 Customers in 2018

Decision D FortisAlberta Inc. Light-Emitting Diode (LED) Lighting Conversion Maintenance Multiplier Filing for 30 Customers in 2018 Decision 23730-D01-2018 Light-Emitting Diode (LED) Lighting Conversion Maintenance Multiplier Filing for 30 Customers in 2018 September 7, 2018 Alberta Utilities Commission Decision 23730-D01-2018 Light-Emitting

More information

Langdon Waterworks Limited

Langdon Waterworks Limited Decision 2014-240 August 19, 2014 The Alberta Utilities Commission Decision 2014-240: Application No. 1610617 Proceeding No. 3258 August 19, 2014 Published by The Alberta Utilities Commission Fifth Avenue

More information

FortisAlberta Inc. Sale and Transfer of the Municipality of Crowsnest Pass Electric Distribution Assets

FortisAlberta Inc. Sale and Transfer of the Municipality of Crowsnest Pass Electric Distribution Assets Decision 21785-D01-2018 Sale and Transfer of the Electric Distribution Assets June 5, 2018 Alberta Utilities Commission Decision 21785-D01-2018 Sale and Transfer of the Electric Distribution System Assets

More information

EPCOR Distribution & Transmission Inc.

EPCOR Distribution & Transmission Inc. Decision 22603-D01-2017 June 23, 2017 Alberta Utilities Commission Decision 22603-D01-2017 Proceeding 22603 June 23, 2017 Published by the: Alberta Utilities Commission Fifth Avenue Place, Fourth Floor,

More information

Decision TykeWest Limited. Setting of Fees for a Common Carrier Order. July 15, 2009

Decision TykeWest Limited. Setting of Fees for a Common Carrier Order. July 15, 2009 Decision 2009-106 Setting of Fees for a Common Carrier Order July 15, 2009 ALBERTA UTILITIES COMMISSION Decision 2009-106: Setting of Fees for a Common Carrier Order Application No. 1567541 July 15, 2009

More information

Decision EUB Proceeding

Decision EUB Proceeding Decision 2007-017 Implementation of the Uniform System of Accounts and Minimum Filing Requirements for Alberta s Electric Transmission and Distribution Utilities March 6, 2007 ALBERTA ENERGY AND UTILITIES

More information

Shell Canada Limited and Canadian Natural Resources Limited

Shell Canada Limited and Canadian Natural Resources Limited Decision 22614-D01-2017 Albian Oil Sands Industrial Complex and June 28, 2017 Alberta Utilities Commission Decision 22614-D01-2017 Albian Oil Sands Industrial Complex and Proceeding 22614 Applications

More information

ENMAX POWER CORPORATION Distribution AUC Rule 005: ANNUAL OPERATIONS FINANCIAL AND OPERATING REPORTING For the Year Ended December 31, 2017 $M

ENMAX POWER CORPORATION Distribution AUC Rule 005: ANNUAL OPERATIONS FINANCIAL AND OPERATING REPORTING For the Year Ended December 31, 2017 $M ENMAX POWER CORPORATION Distribution AUC Rule 005: ANNUAL OPERATIONS FINANCIAL AND OPERATING REPORTING For the Year Ended December 31, 2017 $M TABLE OF CONTENTS Schedule Schedule Name Page Sch 1 Summary

More information

Livingstone Landowners Guild

Livingstone Landowners Guild Decision 20846-D01-2016 Livingstone Landowners Guild Application for Review of Decision 2009-126 Needs Identification Document Application Southern Alberta Transmission System Reinforcement as amended

More information

JULY 22, Readers should also read the "Forward-Looking Information" legal advisory contained at the end of this MD&A.

JULY 22, Readers should also read the Forward-Looking Information legal advisory contained at the end of this MD&A. MANAGEMENT S DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND RESULTS OF OPERATIONS JULY 22, 2008 INTRODUCTION The following Management s Discussion and Analysis (MD&A) is the responsibility of AltaLink,

More information

Decision ATCO Electric Ltd. February 1, 2013 Interim Tariff. January 18, 2013

Decision ATCO Electric Ltd. February 1, 2013 Interim Tariff. January 18, 2013 Decision 2013-015 February 1, 2013 Interim Tariff January 18, 2013 The Alberta Utilities Commission Decision 2013-015: February 1, 2013 Interim Tariff Application No. 1609127 Proceeding ID No. 2305 January

More information

Audited Financial Statements For the years ended December 31, 2017 and 2016

Audited Financial Statements For the years ended December 31, 2017 and 2016 FORTISALBERTA INC. Audited Financial Statements MANAGEMENT S REPORT The accompanying 2017 Financial Statements of FortisAlberta Inc. (the Corporation ) have been prepared by management, who are responsible

More information

2013 Generic Cost of Capital

2013 Generic Cost of Capital Decision 2191-D01-2015 2013 Generic Cost of Capital March 23, 2015 Alberta Utilities Commission Decision 2191-D01-2015 2013 Generic Cost of Capital Proceeding 2191 Application 1608918-1 March 23, 2015

More information

Filing Guidelines for Ontario Power Generation Inc.

Filing Guidelines for Ontario Power Generation Inc. Ontario Energy Board Commission de l énergie de l Ontario EB-2009-0331 Filing Guidelines for Ontario Power Generation Inc. Setting Payment Amounts for Prescribed Generation Facilities Issued: July 27,

More information

Yukon Electrical's submissions in reply to each of the IRs disputed by UCG are set out below.

Yukon Electrical's submissions in reply to each of the IRs disputed by UCG are set out below. lidbennett.jones Bennett Jones LLP 4500 Bankers Hall East, 855-2nd Street SW Calgary, Alberta, Canada T2P 4K7 Tel: 403.298.31 00 Fax: 403.265.7219 Allison M. Sears Direct Line: 403.298.3681 e-mail: searsa@bellnetljones.colll

More information

Alberta Electric System Operator

Alberta Electric System Operator Decision 2007-106 Alberta Electric System Operator 2007 General Tariff Application December 21, 2007 ALBERTA ENERGY AND UTILITIES BOARD Decision 2007-106: Alberta Electric System Operator 2007 General

More information

EPCOR Energy Alberta GP Inc. AUC RULE 005: ANNUAL REGULATED RATE TARIFF (RRT) FINANCIAL AND OPERATIONAL RESULTS FOR THE YEAR ENDED DECEMBER 31, 2016

EPCOR Energy Alberta GP Inc. AUC RULE 005: ANNUAL REGULATED RATE TARIFF (RRT) FINANCIAL AND OPERATIONAL RESULTS FOR THE YEAR ENDED DECEMBER 31, 2016 EPCOR Energy Alberta GP Inc. AUC RULE 005: ANNUAL REGULATED RATE TARIFF (RRT) FINANCIAL AND OPERATIONAL RESULTS FOR THE YEAR ENDED DECEMBER 31, 2016 TABLE OF CONTENTS Schedule Description A Purpose of

More information

Collaborative Process

Collaborative Process Alberta Energy and Utilities Board Utility Cost Order 2006-065 Uniform System of Accounts and Minimum Filing Requirements Cost Awards ALBERTA ENERGY AND UTILITIES BOARD Utility Cost Order 2006-065 Uniform

More information

ATCO Pipelines ATCO Gas and Pipelines Ltd. CU Inc. Canadian Utilities Limited

ATCO Pipelines ATCO Gas and Pipelines Ltd. CU Inc. Canadian Utilities Limited Decision 2012-068 Disposition of Surplus Salt Cavern Assets in the Fort Saskatchewan Area March 16, 2012 The Alberta Utilities Commission Decision 2012-068:,,, Disposition of Surplus Salt Cavern Assets

More information

ENMAX Energy Corporation

ENMAX Energy Corporation Decision 23006-D01-2018 Regulated Rate Option - Energy Price Setting Plan Monthly Filings for Acknowledgment 2017 Quarter 3 February 7, 2018 Alberta Utilities Commission Decision 23006-D01-2018: Regulated

More information

ENMAX Energy Corporation

ENMAX Energy Corporation Decision 22510-D01-2017 2016-2018 Energy Price Setting Plan Compliance Filing October 30, 2017 Alberta Utilities Commission Decision 22510-D01-2017 2016-2018 Energy Price Setting Plan Compliance Filing

More information

Audited Financial Statements For the years ended December 31, 2018 and 2017

Audited Financial Statements For the years ended December 31, 2018 and 2017 FORTISALBERTA INC. Audited Financial Statements Deloitte LLP 700, 850 2 Street SW Calgary, AB T2P 0R8 Canada Independent Auditor s Report Tel: 403-267-1700 Fax: 587-774-5379 www.deloitte.ca To the Shareholder

More information

AltaLink Management Ltd.

AltaLink Management Ltd. Decision 22025-D03-2017 Red Deer Area Transmission Development Amendment Application June 8, 2017 Decision 22025-D03-2017 Red Deer Area Transmission Development Amendment Application Proceeding 22025 Applications

More information

MANAGEMENT S DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND RESULTS OF OPERATIONS

MANAGEMENT S DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND RESULTS OF OPERATIONS MANAGEMENT S DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND RESULTS OF OPERATIONS For the three and twelve months ended February 8, 2011 The following discussion and analysis of financial condition

More information

Decision D ATCO Electric Ltd. Hughes 2030S Substation. Costs Award

Decision D ATCO Electric Ltd. Hughes 2030S Substation. Costs Award Decision 22406-D01-2017 Hughes 2030S Substation June 9, 2017 Alberta Utilities Commission Decision 22406-D01-2017 Hughes 2030S Substation Proceeding 22406 June 9, 2017 Published by Alberta Utilities Commission

More information

The University of Calgary

The University of Calgary Decision 23147-D01-2018 Application for an Order Permitting the Sharing of Records Not Available to the Public Between the University of Calgary and URICA Energy Real Time Ltd. January 30, 2018 Alberta

More information

Capital Power Corporation. Halkirk 2 Wind Power Project

Capital Power Corporation. Halkirk 2 Wind Power Project Decision 23255-D01-2018 Capital Power Corporation Halkirk 2 Wind Power Project July 9, 2018 Alberta Utilities Commission Decision 23255-D01-2018 Capital Power Corporation Halkirk 2 Wind Power Project Proceeding

More information

Earnings Conference Call Fourth Quarter 2018 February 21, 2019

Earnings Conference Call Fourth Quarter 2018 February 21, 2019 Earnings Conference Call Fourth Quarter 2018 February 21, 2019 02 Safe Harbor Some of the matters discussed in this news release may contain forward-looking statements that are subject to certain risks,

More information

EPCOR Distribution & Transmission Inc. (Distribution) SUMMARY OF REVENUE REQUIREMENT FOR THE YEAR ENDED DECEMBER 31, 2008 ($000s)

EPCOR Distribution & Transmission Inc. (Distribution) SUMMARY OF REVENUE REQUIREMENT FOR THE YEAR ENDED DECEMBER 31, 2008 ($000s) SUMMARY OF REVENUE REQUIREMENT SCHEDULE 1 Line Cross- 2008 2008 2007 Var. Actual to Var. Var. Actual to Var. Explanation No. Description Reference Actual Approved Fcst Actual Approved Fcst % Prior Year

More information

Decision CU Water Limited. Disposition of Assets. April 30, 2010

Decision CU Water Limited. Disposition of Assets. April 30, 2010 Decision 2010-192 Disposition of Assets April 30, 2010 ALBERTA UTILITIES COMMISSION Decision 2010-192: Disposition of Assets Application No. 1606042 Proceeding ID. 569 April 30, 2010 Published by Alberta

More information

FORTISALBERTA INC. MANAGEMENT S DISCUSSION AND ANALYSIS

FORTISALBERTA INC. MANAGEMENT S DISCUSSION AND ANALYSIS FORTISALBERTA INC. MANAGEMENT S DISCUSSION AND ANALYSIS April 30, 2018 The following ( MD&A ) of FortisAlberta Inc. (the Corporation ) should be read in conjunction with the following: (i) the unaudited

More information

APPENDIX IX ATTACHMENT 1 FORMULA RATE PROTOCOLS

APPENDIX IX ATTACHMENT 1 FORMULA RATE PROTOCOLS APPENDIX IX ATTACHMENT 1 FORMULA RATE PROTOCOLS 1. INTRODUCTION SCE shall calculate its Base Transmission Revenue Requirement ( Base TRR ), as defined in Section 3.6 of the main definitions section of

More information

NaturEner Energy Canada Inc.

NaturEner Energy Canada Inc. Decision 2009-174 Review and Variance of Alberta Utilities Commission Decision 2009-042 (October 22, 2009) ALBERTA UTILITIES COMMISSION Decision 2009-174, Review and Variance of Alberta Utilities Commission

More information

AltaLink Management Ltd.

AltaLink Management Ltd. Decision 21368-D01-2016 Advance Funding Request from the Cooking Lake Opposition Group Advance Funding Award March 14, 2016 Alberta Utilities Commission Decision 21368-D01-2016: Advance Funding Request

More information

ENMAX Power Corporation

ENMAX Power Corporation Decision 22756-D01-2017 Tax Agreement with The City of Calgary September 7, 2017 Alberta Utilities Commission Decision 22756-D01-2017 Tax Agreement with The City of Calgary Proceeding 22756 September 7,

More information

CANADIAN UTILITIES LIMITED FOR THE YEAR ENDED DECEMBER 31, CONSOLIDATED FINANCIAL STATEMENTS

CANADIAN UTILITIES LIMITED FOR THE YEAR ENDED DECEMBER 31, CONSOLIDATED FINANCIAL STATEMENTS CANADIAN UTILITIES LIMITED CONSOLIDATED FINANCIAL STATEMENTS FOR THE YEAR ENDED DECEMBER 31, 2014 CANADIAN UTILITIES LIMITED 2014 CONSOLIDATED FINANCIAL STATEMENTS February 19, 2015 Independent Auditor

More information

Granite State Electric Company Financial Statements For the years ended March 31, 2011 and March 31, 2010

Granite State Electric Company Financial Statements For the years ended March 31, 2011 and March 31, 2010 Granite State Electric Company Financial Statements For the years ended March 31, 2011 and March 31, 2010 GRANITE STATE ELECTRIC COMPANY TABLE OF CONTENTS Page No. Report of Independent Auditors 2 Balance

More information

Filing Guidelines for Ontario Power Generation Inc.

Filing Guidelines for Ontario Power Generation Inc. Ontario Energy Board Commission de l énergie de l Ontario EB-2009-0331 Filing Guidelines for Ontario Power Generation Inc. Setting Payment Amounts for Prescribed Generation Facilities Issued: July 27,

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF COLORADO * * * * * ) ) ) ) ) ) ) UNANIMOUS COMPREHENSIVE SETTLEMENT AGREEMENT

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF COLORADO * * * * * ) ) ) ) ) ) ) UNANIMOUS COMPREHENSIVE SETTLEMENT AGREEMENT Page 1 of 28 BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF COLORADO * * * * * IN THE MATTER OF THE APPLICATION OF PUBLIC SERVICE COMPANY OF COLORADO FOR AUTHORIZATION TO REVISE THE DEPRECIATION

More information

BEFORE THE FLORIDA PUBLIC SERVICE COMMISSION

BEFORE THE FLORIDA PUBLIC SERVICE COMMISSION BEFORE THE FLORIDA PUBLIC SERVICE COMMISSION DOCKET NO. 000-EI IN RE: TAMPA ELECTRIC COMPANY S PETITION FOR AN INCREASE IN BASE RATES AND MISCELLANEOUS SERVICE CHARGES REBUTTAL TESTIMONY OF JEFFREY S.

More information

Compliance Review 2017

Compliance Review 2017 February 27, 2018 Taking action to promote effective competition and a culture of compliance and accountability in Albertaʹs electricity and retail natural gas markets www.albertamsa.ca Table of Contents

More information

Report to the Minister. For the Year Ending December 31, March 20, 2015

Report to the Minister. For the Year Ending December 31, March 20, 2015 Report to the Minister For the Year Ending December 31, 2014 March 20, 2015 Market Surveillance Administrator 403.705.3181 #500, 400 5th Avenue S.W., Calgary AB T2P 0L6 www.albertamsa.ca Table of Contents

More information

Exhibit B SCE General Rate Case Decision CPUC D (Relevant Portions)

Exhibit B SCE General Rate Case Decision CPUC D (Relevant Portions) Exhibit B SCE General Rate Case Decision CPUC D.15-11-021 (Relevant Portions) statistics justify ASLs up to 69 years. Finally, TURN suggests that aluminum conductor can last far longer than the ASLs considered

More information

Canadian Hydro Developers, Inc.

Canadian Hydro Developers, Inc. Decision 2005-070 Request for Review and Variance of Decision Contained in EUB Letter Dated April 14, 2003 Respecting the Price Payable for Power from the Belly River, St. Mary and Waterton Hydroelectric

More information