Preventing Major Accident Events in Construction

Size: px
Start display at page:

Download "Preventing Major Accident Events in Construction"

Transcription

1 Preventing Major Accident Events in Construction

2 Major Accident Prevention (MAP) Program Current Industry Performance & Practices Major Accident Prevention (MAP) Concept Case Study MAP in Practice Future Application Line of Sight MAE hazard management 2

3 Current Industry Performance Worker Fatality Statistics IOGP 2014 Most Common Causes Transport HV / LV (13%) Hit by moving plant / equipment (33%) % fatalities occurred onshore 4 fatalities associated with Australian project activities (shipyards / onshore) Dropped Objects (11%) Fall from Heights (11%) 3

4 MAP Concept A risk based methodology to identify MAE s applicable to construction activities; A corporate register of performance standards (MAE Mandatory controls) for each MAE hazard; A process for supervisors to systematically verify MAE mandatory controls are applied in the field; and A reporting and assurance program line of sight MAE risk management. 4

5 Mapping MAE and Activities Offshore Safety Case MAP Framework Safety Management System Critical Controls MAE Mandatory Controls MAP (Mandatory Control Register) Facility Description (design & control systems) Major Accident Event Analysis (control system failures) Construction Activities (work scopes) Major Accident Event Analysis (Mechanisms of energy release) 5

6 Applying MAE Hazard Management to Project Activities Clough MAE Assessment Matrix Clough MAE Hazard Register Actions to control MAE hazards defined, understood and managed on a daily basis. Map MAEs against Activities Review MAE Hazard Control Sheets Develop Project control ACTIONS Project MAP Register Review & report MAP compliance weekly 6

7 Applying Bow Tie Analysis Understanding MAE Hazards (Applying Bow Tie Analysis) Lifting Operations Example Health Safety Security Environment MAE s Lifting Device Instability Contact with Structure Lifting over Live Services Dropped Load RISK EVENT Lifting Operation accident ACTIVITIES Site Preparation Pipe laying Logistics Work Scopes Specific Control Actions 7

8 Assessing Project MAE Hazards Define MAE that Apply to Work scope MAE Hazard Register Project A CLOUGH ACTIVITIES MAJOR ACCIDENT EVENT HAZARD ACTIVITIES RELEVANT TO PROJECT Working at Height Working in Confined Space Lifting Operations Stored Energy Fire & Explosion Excavation Plant and Mobile Equipment Equipment Driving Vehicles Personnel Transfers Hazardous Materials & Chemicals Logistics YES Fabrication NO Earthworks YES Siteworks YES Concrete YES Piling Onshore YES Piling Offshore YES YES Land Pipelines NO Roadworks YES Railworks NO 8

9 Field Verification and Assurance MAP Checks verify Mandatory Controls Implemented Select MAP Checks Lifting Ops Working at height Stored Energy MAP uses incident analogue events as a communication tool for supervisors Supervisor Field Check Design review Equipment certifications Field inspections Observations MAP is used as the basis of incident investigations Assurance checks by senior site management confirm integrity and quality of MAP checks My guys are much more aware of the hazards, as we use the MAP checks as part of pre-starts. The team now get it and remind me of the things we need to check before starting a lift Lifting Supervisor Mandatory Controls implemented All controls confirmed and implemented Commence work

10 Applying MAE Hazard Management to Project Activities Clough MAE Assessment Matrix Clough MAE Hazard Register MAP is the repository for MAE learnings from analogue events, incidents, hazards and feedback. Map MAEs against Activities Review MAE Hazard Control Sheets Develop Project control ACTIONS Project MAP Register Reporting and MAP compliance Incidents and Hazards Lessons Learned Supervisor Feedback Assurance Audits 10

11 MAP in Action Jetty Project 11

12 Jetty Project HSE Performance High Potential Incidents Lifting operations - average 5 lifting related incidents per month - 4 HPI s including an LTI Stored Energy - Shattered cutting disc, - 3 HPI s over 4 months Decision taken to implement MAP 4 months of project left. 12

13 MAP Checks Rigorous application of MAP Checks Focus on major risk activities:? Working over Water (MAE-MOP-001)? Moving / swinging loads (MAE-MOP-003)? Dropped loads (MAE-LOP-004)? Marine personnel transfer (MAE-MOP-003) Assurance completed by project leaders Quality monitored & feedback by HSE Advisors Jetty Project MAP Checks Demobilisation commenced Jan-15 Feb-15 Mar-15 Apr-15 MAP Check Target 11 checks / month MAE MOP-007 MAE-MOP-006 MAE-MOP-003 MAE-MOP-001 MAE-WAH-003 MAE-WAH-002 MAE-WAH-001 MAE-LOP-004 MAE-LOP-003 MAE-LOP-002 MAE hazards verified in the field 13

14 MAP Results MAP implementation had immediate impact Zero HPI s in final four months of project All lifting incidents reduced from average of 5 per month to zero Key success factors included: Led by Construction Manager & Supt Consistent application of MAP Checks quality of verifications by supervisors in the field Improvement in quality / availability of supporting information Leadership review of MAP Hazard profile target high risk activities Demobilisation commenced Delivering results 14

15 From Concept to Reality A MAE hazard management system for construction which delivers: A risk based methodology to identify MAE s applicable to construction activities; A corporate register of performance standards (MAE Mandatory controls) for each MAE hazard; A process for supervisors to systematically verify MAE mandatory controls are applied in the field; and A reporting and assurance program line of sight MAE risk management. MAP is valued by frontline supervisors now able to directly prevent MAE s and keep their people safe 15

16 Achieving Line of Sight MAE Management MAE Hazard Applied to Activities Mandated ACTIONS Formal Project Assessment Project MAP Register Lessons Learned Weekly Compliance Reporting Incidents and Hazards External Verification of actions Every MAE hazard known, understood & managed 16

17 Future Application MAP concept can be applied to most work activities Currently Clough is expanding application to brownfields and other resource sectors 17

THE JOURNEY. Cementation`s Serious Injury Prevention Program Learnings From Other Organizations and Industries

THE JOURNEY. Cementation`s Serious Injury Prevention Program Learnings From Other Organizations and Industries THE JOURNEY Cementation`s Serious Injury Prevention Program Learnings From Other Organizations and Industries Introduction Cementation recently introduced enhancements to its Serious Injury Prevention

More information

STOP WORK PROCEDURE. Document Number: USPL-COW Document Location: DRM. Document Custodian: HSSE Manager - S&O Renewal Date: 07/08/2019

STOP WORK PROCEDURE. Document Number: USPL-COW Document Location: DRM. Document Custodian: HSSE Manager - S&O Renewal Date: 07/08/2019 STOP WORK PROCEDURE Document Number: -COW-490-003 Document Location: DRM Document Custodian: HSSE Manager - S&O Renewal Date: 07/08/2019 Revision Reason for Sections / Documents Author Date No. revision

More information

Owner: USA Division P3 Project Revision No: 00 Date last revised: 08/15/2013

Owner: USA Division P3 Project Revision No: 00 Date last revised: 08/15/2013 Ethos Practice Owner: USA Division P3 Project Revision No: 00 Date last revised: 08/15/2013 1.0 Applicability This Best Practice applies to all Encana (Company, Division, or BU specific) staff and onsite

More information

Serious Injury & Fatality Reduction Initiative. Kenneth R Frazier American Electric Power

Serious Injury & Fatality Reduction Initiative. Kenneth R Frazier American Electric Power Serious Injury & Fatality Reduction Initiative Kenneth R Frazier American Electric Power Serious Injury and Fatality Reduction Initiative Over the years S&H efforts have been based on the Heinrich triangle.

More information

SCHEDULE D TENANT TECHNICAL PROPOSAL

SCHEDULE D TENANT TECHNICAL PROPOSAL SCHEDULE D TENANT TECHNICAL PROPOSAL SCHEDULE D TENANT TECHNICAL PROPOSALPage 1 of 19 TENANT TECHNICAL PROPOSAL INDEX SCHEDULE TITLE Tick for Appended Items 0.0 INTRODUCTION AND INSTRUCTIONS 1.0 TENDER

More information

linked to the Australian National University s Work health and safety policy and is one of the procedures within the WHS Management System.

linked to the Australian National University s Work health and safety policy and is one of the procedures within the WHS Management System. Purpose This procedure describes how the Australian National University evaluates and monitors contractors work health and safety for all activities performed at the University. This procedure ensures

More information

Beyond Traditional Lagging Indicators. Jorge E. Cortés, HSE Manager for International Operations Helmerich & Payne International Drilling Co.

Beyond Traditional Lagging Indicators. Jorge E. Cortés, HSE Manager for International Operations Helmerich & Payne International Drilling Co. Beyond Traditional Lagging Indicators Jorge E. Cortés, HSE Manager for International Operations Helmerich & Payne International Drilling Co. Presentation Objectives To challenge traditional measure of

More information

Contractor Safety Plan

Contractor Safety Plan Contractor Safety Plan INSTRUCTIONS Scope This form is to be completed by the contractor that has been identified as a major contract. This Plan expires at the completion of the contract work or 12 months

More information

HIGH RISK CONSTRUCTION WORK

HIGH RISK CONSTRUCTION WORK CONTRACTOR WHS SYSTEM STANDARD HIGH RISK CONSTRUCTION WORK EXTERNAL USE ONLY Principles in the Optus Contractor WHS management process CONTRACTOR MANAGEMENT STAGES PRINCIPLES THIS STANDARD REQUISITION

More information

Contractor s Environmental Health & Safety Disclosure

Contractor s Environmental Health & Safety Disclosure Contractor s Environmental Health & Safety Disclosure Company Name: Application Date: Address: Phone#: Fax #: Email : Company Contacts: Name Position Environmental Health & Safety (EHS) Personnel: Name

More information

Risk Management Policy and Strategy

Risk Management Policy and Strategy Risk Management Policy and Strategy Version: 2.1 Bodies consulted: Approved by: Directors and Managers responsible for risk Board of Directors Date Approved: 28 March 2017 Lead Manager: Lead Director:

More information

Putting an end to fatalities: How behaviour-based safety can eliminate serious injuries and fatalities. Daryl Wake Senior Consultant 24 th May, 2016

Putting an end to fatalities: How behaviour-based safety can eliminate serious injuries and fatalities. Daryl Wake Senior Consultant 24 th May, 2016 Putting an end to fatalities: How behaviour-based safety can eliminate serious injuries and fatalities Daryl Wake Senior Consultant 24 th May, 2016 Why is This So Important? Source: OGP Safety Performance

More information

1042 FORUM DRIVE BROUSSARD, LA PHONE: (337) FAX: (337) Products & Services JANUARY 2015

1042 FORUM DRIVE BROUSSARD, LA PHONE: (337) FAX: (337) Products & Services JANUARY 2015 1042 FORUM DRIVE BROUSSARD, LA 70518 PHONE: (337) 231-1323 FAX: (337) 231-1327 Products & Services JANUARY 2015 TABLE OF CONTENTS Description PAGE Industrial Training Classes 3 Industrial Training Classes

More information

Alcumus Health and safety assessment standards

Alcumus Health and safety assessment standards Alcumus Health and safety assessment standards Comply with your assessment duties as a client Gain greater visibility of the anticipated risks throughout your supply chain Document Code: TG-S-01 Version:

More information

Serious Injury and Fatality Prevention. Kathy Meissner VP HSE Division The Catalyst Group of Companies

Serious Injury and Fatality Prevention. Kathy Meissner VP HSE Division The Catalyst Group of Companies Serious Injury and Fatality Prevention Kathy Meissner VP HSE Division The Catalyst Group of Companies Companies A&B - LTIR Reduction Efforts 0.45 This is what Leadership Involvement can do... 0.40 0.35

More information

Guideline for external contractors working on the premise of MANN+HUMMEL

Guideline for external contractors working on the premise of MANN+HUMMEL Guideline for external contractors working on the premise of MANN+HUMMEL 1 Purpose MHG-HS-I-0011 describes the regulations for health, safety and environment for external contractors working on the premise

More information

What Makes Risk Management Work?

What Makes Risk Management Work? What Makes Risk Management Work? Rick Wells Associate, Risk Management MIRARCO Mining Innovation, Sudbury, Canada w w w. m i r a r c o. o r g Agenda Introduction; Risk Assessment vs Risk Management; Issues

More information

Practical steps to reduce Serious Injuries & Fatalities (SIFs)

Practical steps to reduce Serious Injuries & Fatalities (SIFs) Practical steps to reduce Serious Injuries & Fatalities (SIFs) Dr. Dominic Cooper B Safe Management Solutions Inc. Franklin, IN, 46131, USA +1 (317) 736 8980 https://peer leader.com info@bsms inc.com SIF

More information

Carson, CA Inland Star Distribution Centers, Inc. PSM/CalARP

Carson, CA Inland Star Distribution Centers, Inc. PSM/CalARP Carson, CA Inland Star Distribution Centers, Inc. PSM/CalARP CONTRACTOR PROGRAM Revision History Rev. # Description of Change Date Revised By 0 Initial Issues July 2016 PSM RMP Solutions Purpose The purpose

More information

The basics of verification. Richard Nott Lloyd s Register EMEA

The basics of verification. Richard Nott Lloyd s Register EMEA The basics of verification Richard Nott Lloyd s Register EMEA Introductions Richard Nott Manager, Compliance and Engineering Services Lloyd s Register EMEA Agenda The Offshore Installation (Safety Case)

More information

Job Safety Analysis Preparation And Risk Assessment

Job Safety Analysis Preparation And Risk Assessment Job Safety Analysis Preparation And Risk Assessment Sample Only Reference CPL_PCR_JSA_Risk_Assessment Revision Number SAMPLE ONLY Document Owner Sample Date 2015 File Location Procedure Revision Date Major

More information

Management Accountability: The Key to an Effective Safety Program

Management Accountability: The Key to an Effective Safety Program Management Accountability: The Key to an Effective Safety Program Many organizations typically assign responsibility and grant authority to their managers to develop and implement loss prevention / accident

More information

Second quarter results 2011

Second quarter results 2011 Second quarter results 2011 Highlights for the second quarter 2011 General One fatality in the quarter Kvaerner listed on Oslo Børs 8 July 2011 Financing successfully completed Gudrun jacket delivered

More information

Management Commitment. BEST Level 3 Guidance. Actions to Achieve Desired Outcomes

Management Commitment. BEST Level 3 Guidance. Actions to Achieve Desired Outcomes Management Leadership and Employee 1 Involvement Take proactive steps to build on earlier gains to improve the culture, systems, policies, and procedures that support a safe and healthy work environment.

More information

NAS Workshop on Performance- and Management-Based Safety Regulation of the North Sea Oil & Gas Sector

NAS Workshop on Performance- and Management-Based Safety Regulation of the North Sea Oil & Gas Sector NAS Workshop on Performance- and Management-Based Safety Regulation of the North Sea Oil & Gas Sector The Hague, The Netherlands, January 4-5, 2017 North Sea Regulators Panel Denmark Hans Erik Christensen

More information

Gavin Guyan Manager - Well Integrity NOPSEMA. DrillSafe 1 March 2012

Gavin Guyan Manager - Well Integrity NOPSEMA. DrillSafe 1 March 2012 Gavin Guyan Manager - Well Integrity NOPSEMA DrillSafe 1 March 2012 Scope NOPSEMA & Legislation 2012 Wells focus Industry Performance 2011 MODU focus National Regulator Amendments 1 Jan 2012 NOPSA s functions

More information

Investigations The H&P Way The SIF Model

Investigations The H&P Way The SIF Model Investigations The H&P Way The SIF Model Wade Deer A Shift In Philosophy Safety at H&P is no longer the absence of injury Safety is: Controlling And Removing Exposures for self and others Agenda SIF (What

More information

NGC1 - Element 4 - Health and safety management systems 3 - planning January RMS Publishing. Issued to: Single Licence Licence No:

NGC1 - Element 4 - Health and safety management systems 3 - planning January RMS Publishing. Issued to: Single Licence Licence No: Licence details NEBOSH National General Certificate RMS Publishing Victoria House, Lower High Street, Stourbridge DY8 1TA RMS Publishing. Sixth Edition January 2011. All rights reserved. No part of this

More information

Serious Injury and Fatality Prevention. Taylor Abel, P.E. Senior Manager EHS Aug 2, 2017

Serious Injury and Fatality Prevention. Taylor Abel, P.E. Senior Manager EHS Aug 2, 2017 Serious Injury and Fatality Prevention Taylor Abel, P.E. Senior Manager EHS taylor.abel@mosaicco.com Aug 2, 2017 1 Serious Injury & Fatality (SIF) Prevention AGENDA Overview SIF Background Mosaic s SIF

More information

Overview of UK Offshore Oil and Gas Regulation. Andrew Taylor Head, Offshore Environmental Inspectorate DECC Energy Development Unit February 2016

Overview of UK Offshore Oil and Gas Regulation. Andrew Taylor Head, Offshore Environmental Inspectorate DECC Energy Development Unit February 2016 Overview of UK Offshore Oil and Gas Regulation Andrew Taylor Head, Offshore Environmental Inspectorate DECC Energy Development Unit February 2016 1988 Piper Alpha disaster explosion on Occidental s platform

More information

HAZARD IDENTIFICATION AND ASSESSMENT

HAZARD IDENTIFICATION AND ASSESSMENT SOP-28 Preparation: Safety Mgr Authority: President Issuing Dept: Safety Page: Page 1 of 11 Purpose To provide guidelines for identifying, assessing and controlling workplace hazards; To ensure the potential

More information

Health and Safety. Version 5. Category: Corporate. Latest Review Date: December Review Frequency: Annual. Owner: Company Secretary

Health and Safety. Version 5. Category: Corporate. Latest Review Date: December Review Frequency: Annual. Owner: Company Secretary Health and Safety Version 5 Category: Corporate Latest Review Date: December 2016 Review Frequency: Annual Owner: Company Secretary Contributors: H&S Facilitator, Facilities Manager, Customer Service Manager,

More information

General Company Information State:

General Company Information State: Vendor Registration Form The purpose of the Regional Connector Constructor s (RCC) registration process is to ascertain if your firm possesses the necessary experience, financial resources, and commitment

More information

Construction Site Safety and Health Hazards September 25, 2013

Construction Site Safety and Health Hazards September 25, 2013 SMACNA Online Supervisor Safety Course Construction Site Safety and Health Hazards September 25, 2013 Jim Boom Directorate of Construction Occupational Safety and Health Administration SMACNA Webinar Safe

More information

Helmerich & Payne, Inc.

Helmerich & Payne, Inc. Helmerich & Payne, Inc. Agenda Background Introduction to SIF SIF Working Group Analysis Findings Recommendations Conclusion Background While H&P incident rates had remained relatively flat the severity

More information

AIG Global Property Construction Risk Engineering

AIG Global Property Construction Risk Engineering AIG Global Property Construction Risk Engineering AIG is a leading provider of risk management and loss prevention services for Commercial Property, Energy and Construction risks worldwide. Through the

More information

the security of retail payments

the security of retail payments The European Forum on the security of retail payments Pierre Petit Payment Forum Helsinki, 10 May 2012 Outline I. Origin and mandate II. Recommendations for the security of internet payments III. Future

More information

The secret to getting ahead is getting started. Mark Twain

The secret to getting ahead is getting started. Mark Twain Looking back, looking forward A UK perspective The secret to getting ahead is getting started Mark Twain Willis 1 Beauty in numbers 40 10% A turbine was installed offshore on average every 40 hours since

More information

Work Health and Safety Conditions

Work Health and Safety Conditions Work Health and Safety Conditions Table of Contents PURPOSE AND SCOPE... 1 RESPONSIBILITIES... 1 DEFINITIONS, ABBREVIATIONS AND ACRONYMS... 1 GENERAL WH&S & ELECTRICAL SAFETY REQUIREMENTS... 1 Compliance...

More information

Classification Based on Performance Criteria Determined from Risk Assessment Methodology

Classification Based on Performance Criteria Determined from Risk Assessment Methodology OFFSHORE SERVICE SPECIFICATION DNV-OSS-121 Classification Based on Performance Criteria Determined from Risk Assessment Methodology OCTOBER 2008 This document has been amended since the main revision (October

More information

HULCHER CONTRACTOR SAFETY MANAGEMENT PROCESS

HULCHER CONTRACTOR SAFETY MANAGEMENT PROCESS Hulcher Services is initiating a mission to improve safety for its employees, contractors, subcontractors, visitors, and general public. The Hulcher Contractor Safety Management Process (HCSMP) was developed

More information

Health & Safety Policy

Health & Safety Policy Fairfield Village Hall Health & Safety Policy 1 Contents Part 1 General Statement of Policy... 3 Part 2: Organisation of Health and Safety... 4 Part 3 Arrangements and Procedures... 6 3.1 Licence... 6

More information

Risk assessment Policy and Procedures

Risk assessment Policy and Procedures Risk assessment Policy and Procedures 1. Introduction The purpose of risk assessment is to identify hazards and evaluate any associated risks to health and safety arising from Youth Works activities, enabling

More information

Leading Safety for a Distributed Work Force

Leading Safety for a Distributed Work Force Leading Safety for a Distributed Work Force Bob Coates VP Safety Eversource is New England s Largest Energy Delivery Company Eversource serves 3.7 million electric and natural gas customers in Connecticut,

More information

New Work Health & Safety Legislation What does it mean for you as a Business Owner, Director or Executive?

New Work Health & Safety Legislation What does it mean for you as a Business Owner, Director or Executive? New Work Health & Safety Legislation What does it mean for you as a Business Owner, Director or Executive? Session Overview The WHS Act 2011 became law in January 2012. This presentation outlines some

More information

This policy aims to ensure the health, safety and welfare of contractors working on UEL premises and those affected by their work.

This policy aims to ensure the health, safety and welfare of contractors working on UEL premises and those affected by their work. HR Services UEL Health and Safety Handbook Contractor Health and Safety Management Policy This policy is a sub-policy of the main University Health and Safety Policy Statement Introduction The University

More information

Subcontractor / Vendor Prequalification Statement Company Name:

Subcontractor / Vendor Prequalification Statement Company Name: Subcontractor / Vendor Prequalification Statement Company Name: Type of Work Company Performs: State of Incorporation: Date of Incorporation: Street Address (No PO Boxes): City State Zip: Office Number:

More information

The Challenge of Risk Control in a Hydrogen based Economy, Part I

The Challenge of Risk Control in a Hydrogen based Economy, Part I The Challenge of Risk Control in a Hydrogen based Economy, Part I Hans J. Pasman Chemical Risk Management What are the risks, how can we determine them, How can we avoid, how to reduce, when can we be

More information

Safety & Health Manual

Safety & Health Manual Safety & Health Manual Chapter 8 Sub-Contractor Policy 8-1 Sub-Contractor Policy engages the services of sub-contractors and values its relationships with these essential service providers. In the interest

More information

Contractor Guidelines

Contractor Guidelines Contractor Guidelines This Guideline has been written to detail the minimum expectations with regards to contractor safety at Sodexo business units. It is the responsibility of the contractor to understand

More information

Crane Operator & Rental Supplemental Application

Crane Operator & Rental Supplemental Application *Please visit www.allrisks.com/submit-a-risk or contact your current All Risks, Ltd. producer to submit applications. Crane Operator & Rental Supplemental Application te: Applications incomplete or unsigned

More information

POWER CONSTRUCTION COMPANY CCIP PROGRAM SAFETY REQUIREMENTS

POWER CONSTRUCTION COMPANY CCIP PROGRAM SAFETY REQUIREMENTS POWER CONSTRUCTION COMPANY CCIP PROGRAM SAFETY REQUIREMENTS The following requirements apply to all subcontractors including tier subcontractors, vendors, deliveries, visitors and the like (herein known

More information

Contractor s Pollution Liability Application

Contractor s Pollution Liability Application 1550 Bedford Highway, Suite 815 Bedford, NS B4A 1E6 t: 1-877-343-8224 f: 1-877-432-9822 e: accounts@agileuw.ca agileuw.ca Contractor s Pollution Liability Application Applicant Information 1. First Named

More information

(Last amended 18 December 2017, cf. page 4)

(Last amended 18 December 2017, cf. page 4) REGULATIONS RELATING TO MANAGEMENT AND THE DUTY TO PROVIDE INFORMATION IN THE PETROLEUM ACTIVITIES AND AT CERTAIN ONSHORE FACILITIES (THE MANAGEMENT REGULATIONS) (Last amended 18 December 2017, cf. page

More information

Human Capital and Occupational Health & Safety: How do you assess ESG materiality around your most valuable asset?

Human Capital and Occupational Health & Safety: How do you assess ESG materiality around your most valuable asset? Human Capital and Occupational Health & Safety: How do you assess ESG materiality around your most valuable asset? Kathy A. Seabrook, Chair of the Board, Center for Safety and Health Sustainability Darryl

More information

FLNG / LNG FSRU Terminals RISK and INSURANCE ISSUES 7 th July Paul Nicholson Marsh LNG Practice Leader LEG Construction Seminar, London

FLNG / LNG FSRU Terminals RISK and INSURANCE ISSUES 7 th July Paul Nicholson Marsh LNG Practice Leader LEG Construction Seminar, London FLNG / LNG FSRU Terminals RISK and INSURANCE ISSUES 7 th July 2015 Paul Nicholson Marsh LNG Practice Leader LEG Construction Seminar, London Section 1 FLNG - LIQUEFACTION INDUSTRY OVERVIEW FLNG Capacity

More information

Pipeline Regulatory Issues

Pipeline Regulatory Issues Pipeline Regulatory Issues Pete Chace GPS Program Manager (614) 644-8983 Peter.chace@puc.state.oh.us Changes to the GPS Section Staff Expansion Hiring 2 new Gas Pipeline Safety Inspectors. Intent is that

More information

Supplier accreditation instructions

Supplier accreditation instructions Supplier accreditation instructions Synergy s supplier accreditation process has been established to ensure that potential liability risks are managed, internal processes support best practice principles,

More information

Demolition Program Checklist

Demolition Program Checklist Apollo General Insurance Agency, Inc. License Number 0606980 Demolition Program Checklist Information Needed: 5 years currently valued loss runs Narrative on any Losses in Excess of $10,000 Completed questionnaire,

More information

Section 6: Incident Reporting & Investigation

Section 6: Incident Reporting & Investigation 2012 Section 6: Incident Reporting & Investigation Total Oilfield Rentals LP 10/1/2012 This page left blank intentionally. 6.0. Incident Reporting & Investigation Rev B October 1, 2012 Table of Contents

More information

Northwest Construction Consumer Council

Northwest Construction Consumer Council Northwest Construction Consumer Council Safety Challenges for Delivering Capital Construction Projects at Operating Airport and Seaports Alan Norris and John Burdick Port of Seattle Engineering Construction

More information

UNDERGROUND SERVICE STRIKES

UNDERGROUND SERVICE STRIKES UNDERGROUND SERVICE STRIKES GUIDELINES FOR CONSTRUCTION COMPANIES An underground service strike can lead to injury or loss of life and the costs to your business can be substantial. This short guide is

More information

ATTACHMENT C-1 CONTRACTOR QUALIFICATIONS FOR CONSTRUCTION OF ELECTRIC AND NATURAL GAS FACILITIES

ATTACHMENT C-1 CONTRACTOR QUALIFICATIONS FOR CONSTRUCTION OF ELECTRIC AND NATURAL GAS FACILITIES ATTACHMENT C-1 CONTRACTOR QUALIFICATIONS FOR CONSTRUCTION OF ELECTRIC AND NATURAL GAS FACILITIES A. EXPERIENCE QUALIFICATIONS FOR CONTRACTORS INSTALLING ELECTRIC ONLY FACILITIES For the installation of

More information

Accident, Near-Miss Reporting and Investigation Policy

Accident, Near-Miss Reporting and Investigation Policy Accident, Near-Miss Reporting and Investigation Policy Version: V0_2 October 2017 Owner: HR/Corporate Services Approved by: Executive Team Accident and Near-Miss Reporting and 1 October 2017 CONTENTS PAGE

More information

Steps to Prevent Serious Workplace Injuries and Fatalities

Steps to Prevent Serious Workplace Injuries and Fatalities Steps to Prevent Serious Workplace Injuries and Fatalities Karl L. Bossung DEKRA Insight U.S.A. Safety in 21 Years: 9 9 8 8 7 7 TRIR 6 5 4 6 5 4 Fatality Rate 3 3 2 2 1 1 0 0 TRIR (per 200,000 hours) Fatality

More information

Cossio Insurance Agency Fax: PO Box 5987 Greenville SC 29606

Cossio Insurance Agency Fax: PO Box 5987 Greenville SC 29606 DIRECTIONS: 1. Complete the application (all pages) in full by filling in the blue fields. 2. Please fill in all the fields with the correct information. 3. Email the application to apps@cossioinsurance.com

More information

PG&E Corporation. First Quarter Earnings Call. May 2, 2013.

PG&E Corporation. First Quarter Earnings Call. May 2, 2013. PG&E Corporation First Quarter Earnings Call May 2, 2013 This presentation is not complete without the accompanying statements made by management during the webcast conference call held on May 2, 2013.

More information

Introduction to OSHA and OSHA Inspections. Jim Shelton, CAS, Houston North

Introduction to OSHA and OSHA Inspections. Jim Shelton, CAS, Houston North Introduction to OSHA and OSHA Inspections Jim Shelton, CAS, Houston North Introduction to OSHA Occupational Safety and Health Administration Develops and enforces safety and health standards 24 States

More information

Tata AIG General Insurance Company Limited

Tata AIG General Insurance Company Limited PROPOSAL FORM FOR PUBLIC LIABILITY INSURANCE POLICY (INDUSTRIAL RISK) LIABILITY OF THE COMPANY DOES NOT COMMENCE UNTIL THE PROPOSAL HAS BEEN ACCEPTED AND THE PREMIUM PAID THE TERRITORIAL LIMIT AS APPLICABLE

More information

Power Construction Company CCIP Program Safety Requirements

Power Construction Company CCIP Program Safety Requirements Introduction The following safety requirements (herein known as safety requirements) apply to all subcontractors including tier subcontractors, employees, consultants, vendors, deliveries, visitors and

More information

Risk Assessment Policy

Risk Assessment Policy Risk Assessment Policy Updated: April 2018 Date of next Review: April 2019 Policy Lead: Bursar Checked by: Middle Leadership Team 1. INTRODUCTION Beachborough School will have hazards which if not controlled

More information

PG&E Corporation. Fourth Quarter Earnings Call February 21, 2013

PG&E Corporation. Fourth Quarter Earnings Call February 21, 2013 1 PG&E Corporation Fourth Quarter Earnings Call February 21, 2013 This presentation is not complete without the accompanying statements made by management during the webcast conference call held on February

More information

Hazard Identification, Risk Assessment and Control Procedure

Hazard Identification, Risk Assessment and Control Procedure Hazard Identification, Risk Assessment and Control Procedure 1. Purpose To ensure that there is a formal process for hazard identification, risk assessment and control to effectively manage workplace and

More information

2 Risk assessment why?

2 Risk assessment why? 1 2 Risk assessment why? Reduced likelihood of the occurrence of hazardous events/exposures Reduced consequences in terms of adverse effects on yourself and your own health, but also on the surroundings

More information

HYDROSTATIC TEST PLAN

HYDROSTATIC TEST PLAN Engineering and Projects HYDROSTATIC TEST PLAN Terminal Piping Enbridge Pipelines Inc. Tank 80 at Regina Terminal AFE: 1241021C80 Rev Date Status Description Initiator Approver 1 06/12/15 Issued Issued

More information

APPLICATION FOR EXEMPTION OF GOODS EXPORTED FROM TEXAS ("FREEPORT EXEMPTION") FOR 2010

APPLICATION FOR EXEMPTION OF GOODS EXPORTED FROM TEXAS (FREEPORT EXEMPTION) FOR 2010 Division - Freeport Exemption P.O. Box 560367 * Dallas, Texas 75356-0367 www.dallascad.org APPLICATION FOR EXEMPTION OF GOODS EXPORTED FROM TEXAS ("FREEPORT EXEMPTION") FOR 2010 This application covers

More information

Contractor Pre-qualification Questionnaire

Contractor Pre-qualification Questionnaire Contractor Pre-qualification Questionnaire This document shall be used to determine qualifications of contractors who shall work under Anderson Engineering Co., Inc. (AECI). AECI shall use this document

More information

WORKING WITH CONTRACTORS POLICY AND PROCEDURE

WORKING WITH CONTRACTORS POLICY AND PROCEDURE WORKING WITH CONTRACTORS POLICY AND PROCEDURE CROWN SECURITY CONTRACTORS & OSH (i) Preface Contract work is becoming increasingly common in the modern workplace management culture, and has been a feature

More information

OSHA Compliance in the Telecommunications Industry

OSHA Compliance in the Telecommunications Industry OSHA Compliance in the Telecommunications Industry Chad Vivian, CSP Compliance Safety and Health Officer OSHA, Englewood Area Office International Telecommunications Safety Conference September 15, 2010

More information

PIPELINE SMS GROUP TOOLS WEBINAR

PIPELINE SMS GROUP TOOLS WEBINAR API-AOPL PIPELINE SMS INDUSTRY TEAM PIPELINE SMS GROUP TOOLS WEBINAR JUNE 26, 2018 SPEAKERS Bill Byrd: RCP Inc. Sam Minifie: American Petroleum Institute (API) Tony Cockshutt: Enbridge Inc 2 AGENDA Greeting

More information

Regulators Forum. Alberta 2013

Regulators Forum. Alberta 2013 Regulators Forum Alberta 2013 The Statistics Lost-Time Claim Rate by Upstream Oil and Gas Sub-Sector Data Source: WCB Data, Prepared by Research and Analysis Sub-Sector 2007 2008 2009 2010 2011 Upstream

More information

Common stock prices 1. New York Stock Exchange indexes (Dec. 31,1965=50)2. Transportation. Utility 3. Finance

Common stock prices 1. New York Stock Exchange indexes (Dec. 31,1965=50)2. Transportation. Utility 3. Finance Digitized for FRASER http://fraser.stlouisfed.org/ Federal Reserve Bank of St. Louis 000 97 98 99 I90 9 9 9 9 9 9 97 98 99 970 97 97 ""..".'..'.."... 97 97 97 97 977 978 979 980 98 98 98 98 98 98 987 988

More information

Rémi Bourgault Clerk of the Standing Committee on Natural Resources House of Commons 131 Queen Street, Room 6-32 Ottawa, Ontario, K1A 0A6

Rémi Bourgault Clerk of the Standing Committee on Natural Resources House of Commons 131 Queen Street, Room 6-32 Ottawa, Ontario, K1A 0A6 Rémi Bourgault Clerk of the Standing Committee on Natural Resources House of Commons 131 Queen Street, Room 6-32 Ottawa, Ontario, K1A 0A6 25 March 2015 Dear Mr. Bourgault, The Canadian Energy Pipeline

More information

Hazard Identification, Risk Assessment and Control at Gas Inlet Area of Onshore Terminal Yeshaswee Bijalwan 1 Dr. Nehal A Siddique 2

Hazard Identification, Risk Assessment and Control at Gas Inlet Area of Onshore Terminal Yeshaswee Bijalwan 1 Dr. Nehal A Siddique 2 IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 09, 2015 ISSN (online): 2321-0613 Hazard Identification, Risk Assessment and Control at Gas Inlet Area of Onshore Terminal

More information

Serious Injury and Fatality Prevention: A case study. Serious Injury & Fatality (SIF) Prevention

Serious Injury and Fatality Prevention: A case study. Serious Injury & Fatality (SIF) Prevention ASSE MPS Open Call Serious Injury and Fatality Prevention: A case study Taylor Abel, P.E. EHS Senior Manager taylor.abel@mosaicco.com December 13, 2017 1 Serious Injury & Fatality (SIF) Prevention AGENDA

More information

Risk Management Report Guidelines for Diploma and Advanced Diploma of OHS/WHS

Risk Management Report Guidelines for Diploma and Advanced Diploma of OHS/WHS Risk Management Report Guidelines for Diploma and Advanced Diploma of OHS/WHS IMPORTANT INFORMATION THAT WAS PROVIDED DURING YOUR TRAINING JUST TO JOG YOUR MEMORY 1. This is a report and musts be written

More information

AMCHAM KPMG update on VAT of transport & logistic business

AMCHAM KPMG update on VAT of transport & logistic business AMCHAM KPMG update on VAT of transport & logistic business Ho Chi Minh City 18 Mar 2010 TAX AND CORPORATE SERVICES 2009 KPMG Limited, a Vietnamese limited liability company and a member firm of the KPMG

More information

Health & Safety Policy

Health & Safety Policy Health & Safety Policy K4S Security Ltd Imperial Office 2a Heigham Road East Ham London E6 2JG Registered Company Number: 09646212 Policy Date: 12 April 2018 1/14 Contents Page 1.0 General Statement of

More information

Deep Panuke. Third Party Inspection Services Prequalification Questionnaire EOI Z

Deep Panuke. Third Party Inspection Services Prequalification Questionnaire EOI Z 01U 18 Jan 08 Issued for Use J. Frost D. Green D. Riffe R. MacQueen M. Weatherston Rev Date Reason for Issue Prepared Checked Approved Approved Title Third Party Inspection Services Prequalification Questionnaire

More information

Principles and Elements of SMS A Review. Patrick Hudson Leiden University

Principles and Elements of SMS A Review. Patrick Hudson Leiden University Principles and Elements of SMS A Review Patrick Hudson Leiden University Structure Why SMS? The principles Shell s experience The elements Implementation experience Conclusion Why Safety Management Systems?

More information

NEBOSH HSE CERTIFICATE IN PROCESS SAFETY MANAGEMENT

NEBOSH HSE CERTIFICATE IN PROCESS SAFETY MANAGEMENT NEBOSH HSE CERTIFICATE IN PROCESS SAFETY MANAGEMENT Various Dates 2018 Leduc, AB Canada Terrace Safety EXPERT TRAINER David Mattock David Mattock is a graduate in Maritime Studies from Cardiff University.

More information

SUPPLIER EVALUATION QUESTIONNAIRE

SUPPLIER EVALUATION QUESTIONNAIRE Page 1 of 6 Instructions It is Freo Group Limited (FGL) policy that before a business can be engaged or maintained as an Approved Supplier, the following Supplier Evaluation Questionnaire must be completed

More information

SUB CONTRACTOR INDUCTION PACK

SUB CONTRACTOR INDUCTION PACK REQUIREMENTS FOR WORKING ON ROYAL MAIL PREMISES 1. INTRODUCTION AND PURPOSE This document sets out the arrangements that Royal Mail Property & Facilities Solutions Limited and Royal Mail [hereinafter jointly

More information

San Antonio Water System PROJECT CONSTRUCTION PROGRAM HEALTH AND SAFETY PROGRAM

San Antonio Water System PROJECT CONSTRUCTION PROGRAM HEALTH AND SAFETY PROGRAM PROJECT CONSTRUCTION PROGRAM HEALTH AND SAFETY PROGRAM SEPTEMBER 2007 TABLE OF CONTENTS INTRODUCTION... 2 SAFETY RESPONSIBILITIES, AUTHORITY AND ACCOUNTABILITY... 3 REGULATORY AGENCIES... 3 SAWS... 4

More information

CAR WASH FUNDRAiSING Event Notification Form

CAR WASH FUNDRAiSING Event Notification Form CAR WASH FUNDRAiSING Event Notification Form How to obtain Public Liability Insurance cover To obtain Public Liability Insurance for your fundraising event, all sections of this Fundraising Event Notification

More information

SALVAGE/WRECK REMOVAL OF OFFSHORE UNITS

SALVAGE/WRECK REMOVAL OF OFFSHORE UNITS SALVAGE/WRECK REMOVAL OF OFFSHORE UNITS ISU ASSOCIATE MEMBERS DAY LONDON (UK) 16 MARCH, 2016 1 CHEK LAP KOK AIRPORT 1910 1990 2000 2013 2014 2010 2 BOSKALIS DIVISIONS 3 MARKETS/ CLIENTS Harbour Towage

More information

ITW LTD T/A AVERY WEIGH-TRONIX SAFETY, HEALTH AND ENVIRONMENTAL INFORMATION

ITW LTD T/A AVERY WEIGH-TRONIX SAFETY, HEALTH AND ENVIRONMENTAL INFORMATION ITW LTD T/A AVERY WEIGH-TRONIX SAFETY, HEALTH AND ENVIRONMENTAL INFORMATION January 2018 1 Introduction We recognize that as a customer of Avery Weigh-Tronix, you require details of our management of safety,

More information

Subcontractor Approval Form

Subcontractor Approval Form Page 1 of 8 1. General Information Company / Partnership / Individual Name: Address: Telephone: Email: Website: Main Contact Name: Telephone: Email: 2. Financial Information Bank Name: Account Name: Accounts

More information

Significant Revisions for the 2018 NFPA 70E. Keeping People Safe from Electrical Hazards for over 50 Years

Significant Revisions for the 2018 NFPA 70E. Keeping People Safe from Electrical Hazards for over 50 Years Significant Revisions for the 2018 NFPA 70E Keeping People Safe from Electrical Hazards for over 50 Years Today s Presenter Dennis K. Neitzel, CPE, CESCP Director Emeritus, AVO Training Institute NFPA

More information

Marine Terrorism. A re-evaluation of the risks. Tim Allmark Engineering Manager ABS Consulting Europe & Middle East

Marine Terrorism. A re-evaluation of the risks. Tim Allmark Engineering Manager ABS Consulting Europe & Middle East Marine Terrorism A re-evaluation of the risks by Tim Allmark Engineering Manager ABS Consulting Europe & Middle East RUNNING ORDER Introduction ISPS Code Overview Understanding the Context Application

More information