1 Public Disclosure Authorized AFRICA Ghana Environment & Natural Resources Global Practice IBRD/IDA Investment Project Financing FY 2012 Seq No: 12 ARCHIVED on 03-May-2018 ISR31271 Implementing Agencies: Fishery Commission, Ministry of Fisheries and Aquaculture Development Public Disclosure Authorized Key Dates Key Project Dates Bank Approval Date:14-Jul-2011 Planned Mid Term Review Date:22-Jan-2015 Original Closing Date:31-Dec-2017 Project Development Objectives Effectiveness Date:12-Jun-2012 Actual Mid-Term Review Date:12-Jan-2015 Revised Closing Date:29-Jun-2018 Public Disclosure Authorized Project Development Objective (from Project Appraisal Document) The Project Development Objective is to support the sustainable management of Ghana s fish and aquatic resources by: (i) strengthening the country s capacity to sustainably govern and manage the fisheries; (ii) reducing illegal fishing; (iii) increasing the valueand profitability generated by the fish resources and the proportion of that value captured by the country; and (iv) developing aquaculture. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Global Environmental Objective (from Project Appraisal Document) The objective is to sustainably increase the overall wealth generated by the exploitation of Ghana's fisheries resources, and the proportion of that wealth captured by the country. Public Disclosure Authorized Has the Global Environmental Objective been changed since Board Approval of the Project Objective? Yes Board Approved Revised Global Environmental Objective (If project is formally restructured) The objective is to sustainably increase the overall wealth generated by the exploitation of Ghana's fisheries resources, and the proportion of that wealth captured by the country. Components Name Component 1: Good Governance and Sustainable Management of the Fisheries. Page 1 of 14

2 Component 2: Reduction of Illegal Fishing. Component 3: Increasing the Contribution of the Fish Resources to the National Economy. Component 4: Aquaculture Development. Component 5: Regional Coordination, Monitoring and Evaluation and Project Management. Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Moderately Satisfactory Moderately Unsatisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Unsatisfactory Overall Risk Rating Substantial Substantial Implementation Status and Key Decisions The project has made some progress since last October. Component 1: (a) More licensing conditions have been added for the industrial trawlers (30% license fee increase, airtime and observer cost covered by trawlers). A committee of three legal experts is going to be formed to develop a comprehensive licensing scheme. As of date, 71 trawlers have been issued a fishing license, which represents a continuous reduction of fishing effort in the trawler sector; (b) A new Fishery Act has been drafted and stakeholder consultation initiated. (c) The study on Total Allowable Catches (TAC) has been completed by local scientists and is pending international expert s review and verification (d) The Co-Management Policy has been reviewed and completed but is pending submission to cabinet for approval; (e) The pilot co-management sites have not been established and the very limited time before project closing will not allow for the planned co-management system to be established. The Focus now is on setting up improved smoke ovens and raising awareness of sustainable fisheries practices, organized by the communication specialist. (f) The Marine Protected Area (MPA) strategy has been developed but consultations with stakeholders need to be finalized in order to validate the strategy and submit it to cabinet for approval; (g) implementation of the compensation scheme for alternative livelihood for directly affected crews and fish mongers is in progress. District Assemblies have selected sites for establishment of the iodization and plastic pelleting equipment in Central Region, Western, Volta and Grater Accra. The Alternative Livelihoods Compensation Management Board will review applications based on the established criteria. The activity is planned to start in early May. (h) The Marine Canoe Frame survey is completed and 14,319 canoes were registered and 9,103 have been embossed. (i) A Two month closed season for industrial travelers was enforced during January and February The report on the effects of the closed season is being finalized by the Fisheries Commission. (j) An app has been developed for digitalization of data collection. Fourteen (14) units are currently being used and tested. Plans are for more units to be purchased and more officers will be trained on the application and use of the app. Component 2: (a) Since 1 March 2018, the FEU has achieved 100% observer coverage for industrial trawlers; (b) An app digitalizing the observer report has been developed, and roll-out is pending the purchase of tablets and observer training; (c) The Long-term Monitoring, Control and Surveillance (MCS) strategy meant to ensure financial sustainability of these activities has been developed and is undergoing revisions; (d) A regional Vessel Monitoring System (VMS) analysis training, supported by Iceland, is planned to take place by end of May. The purpose of the training is to support the MSCs to be more efficient and enhance use the VMS data to conduct more user-friendly analysis and maps for management purposes, decision making and enforcement. Component 3: Ghana has a very rough and tricky terrain for building landing sites. The limited project funding does not allow for massive construction. Finally, three sites where being considered: Mumford, Teshie, and Anloga. (a) Angola will be the only landing site supported by the project with rehabilitation work ongoing, including better sanitation conditions. The work has been initiated and it will be completed before the project closing; (b) Piloting of 250 improved smoking ovens in 10 fishing communities and dry racks is being implemented and planned to be concluded before project closing. Some sensitization/training on the new oven design and racks, improved fish handling, fisheries regulations, group dynamics and small business management are ongoing and a draft handbook has been developed. (d) The following civil works are ongoing: Rehabilitation of the Koforidua and Kumasi fish health laboratories are completed and yet to be handed over to the Fisheries Commission. Rehabilitation of the Tarkoradi Fish Health Laboratory is almost completed. Rehabilitation of Rehabilitation of the Tarkoradi Fish Health Laboratory is almost completed. in Akosombo and Ashiaman are ongoing. All these are expected to be completed by project closing. Component 4: Aquaculture has been driven by the private sector without much support from the government or the project. Where the Bank could help (and has helped) is in the area of quality and safety standards. The 2016 tilapia disease outbreak in the Lake Volta region clearly showed the Page 2 of 14

3 need for certification, which the project is supporting. Water monitoring training has been conducted and equipment is purchased, but pending protocol development. (a) The Certification protocol for both hatchery and farms has been developed and currently the Fish Health Unit staff are on the field sensitizing farmers and inspecting farms for certification. It is expected that farms that meet the requisite criteria will receive certification before project closing; (b) The Zoning report was completed. Two stakeholder consultations have been conducted but the report is not submitted to the Fishery Commission yet; (c) Training for the small-scale farmers on farming technologies have been carried out. More trainings are planned to benefit a total of 100 farmers; (d) Protocol on water quality testing has been developed. Training is yet to be conducted for Fisheries Commission staff including using quality testing kits; (f) Fish Health policy has been submitted for Cabinet approved; The project will close in June 2018, as scheduled. The modalities for further support to the sector are under discussion. Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance -- Substantial Substantial Macroeconomic -- Low Low Sector Strategies and Policies -- Substantial Substantial Technical Design of Project or Program -- Moderate Moderate Institutional Capacity for Implementation and Sustainability -- Substantial Substantial Fiduciary -- Moderate Moderate Environment and Social -- Substantial Substantial Stakeholders -- Moderate Moderate Other Overall -- Substantial Substantial Results Project Development Objective Indicators PHINDPDOTBL Fisheries management plan of the marine fisheries sector of Ghana implemented (Yes/No, Custom) Value N Y Y Y Date 01-Jul Sep Dec Jun-2018 The project continues to implement the Fishery Management Plan, including 1) Third Closed season was observed for two months at the beginning of Additional closed seasons during the project period include November 2016, February & March It is however expected that the periods selected for closed seasons in future Page 3 of 14

4 should be based on scientific evidence to allow for breeding and growth of fish. 2) Industrial fishing effort reduction: The trawler vessel numbered 67 as of 2010 (baseline in PAD). The highest number recorded during the project implementation period was 103 (early 2017). Efforts from the project contributed to reducing the number to 76 by the end of December The number of trawler vessels licensed by April 23, 2018 is 71. 3) Stock assessment: The project has conducted one stock assessment. Another stock assessment was conducted by Nansen in The preliminary conclusion is that the biomass is in bad shape. 4) A web based fisheries registry with 100% registration of industrial and semi industrial vessels has been established and is functional. 5) A new licensing scheme which involves quarterly licensing of vessels has been established. This allows for better monitoring of trawler activities. However, the licensing conditions need strengthening (new licensing regime) with better enforcement. 6) The Observer programme has been established and made functional. In 2018, there has been 100% observer coverage for all trawler vessels fishing at the sea. PHINDPDOTBL Average infraction reported per unit of enforcement activity (Number, Custom) Value Date 14-Jul Sep Dec Jun-2018 By the end of Dec 2017, the records showed a total of 107 infractions. For 2018, so far only 22 infractions were observed, including 13 semi industrial vessels and 9 canoes committed infractions at the western border. Infractions included light fishing, fishing without license, fishing with monofilament net and child labor. The infractions have been reported to the Takoradi Harbour Police for further investigation. By project closing, the result might be smaller than the target. This could come from (i) not enough enforcement or prosecution; or (ii) the probability of infraction is much reduced because of increased enforcement and therefore fewer infractions are done in fear of prosecution. The ICR will provide further analysis. PHINDPDOTBL Scoring on aquaculture enabling environment: 1. Disease control 2. Policy framework (Number, Custom) Value Date 30-Jun Sep Apr Jun-2018 The Fish health policy has been submitted to cabinet for approval (0.5). The aquaculture policy was developed by a consultant, but was not satisfactory after review and consultation. A committee is being set up to take the comments and finalize the policy Page 4 of 14

5 for final approval. Protocols for certification of fish farms and hatcheries have been developed and validated (1). Sensitization on the protocols is ongoing among fish farmers and hatchery operators. The Fish Health Unit (FHU) team is currently performing farm inspections to initiate the certification process. Farms inspected by the FHU are being supported to upgrade to meet the standard requirement of the protocols. The final target may not be met because there will not be enough time for the aquaculture policy to be approved by Cabinet. However, the draft could be finished by then. The total score for this indicator could be 2.5 by closing. PHINDPDOTBL Direct project beneficiaries (Number, Custom) Value 233, , , , Date 14-Jul Sep Apr Jun-2018 Direct beneficiaries include farmers and staff that have received various forms of trainings, NAFPTA members that have also received capacity development, fishermen whose canoes were registered and embossed, observers trained and engaged by the Fishery Commission, number of fishermen and traders reached with messages on illegal fishing, etc. The final target will not be met as the original target was too high, which included all the fishermen and fish processors in Ghana. PHINDPDOTBL Female beneficiaries (Percentage, Custom Supplement) Value PHINDPDOTBL Number of fish health labs established (Number, Custom) Value Date 07-Jul Sep Apr Jun-2018 Page 5 of 14

6 PHINDGEOTBL The Accra Fish Health Laboratory is established and fully functional. Rehabilitation of the Koforidua and Kumasi fish health laboratories is completed and yet to be handed over to the Fisheries Commission. The Laboratories are yet to be equipped to be able to function. Rehabilitation of the Tarkoradi Fish Health Laboratory is almost completed. A training program has been scheduled by the Fish Health Unit to build capacity for laboratory operations and management. Overall Global Environmental Objective Indicators Pl. refer to PDO Indicators (same indicators) (Number, Custom) Value Date Overall PHGEOCMTS Intermediate Results Indicators Marine fishing canoes that are registered and embossed (disaggregated motorized and non-motorized) (Number, Custom) Value 11, , , , Date 14-Jul Sep Apr Jun-2018 Total number of canoes registered is 14,319. The total number of active canoes is however less than this number because some fishermen have replaced their canoes and will register with a new number. Therefore, there is a double counting issue, to an extent. There is a need to clean up the data to establish the actual number of existing marine canoes. Embossment was done for over 9000 canoes, which is 100%. The marine canoe fishermen association has mentioned they would officially cap the total number after embossment. Those that are not embossed, will not get registered again. However, there has not been any official Page 6 of 14

7 announcement yet. This final target could be met if an official announcement is issued. The ICR will follow up on this matter. Number of licensed industrial and semi-industrial vessels (disaggregated industrial and semi-industrial) (Number, Custom) Value Date 14-Jul Oct Apr Jun-2018 There was a 2-month closed season observed from January 1 to Feb 28, Because of this, the new license expiration date is the end of June. By now, 71 license have been issued. No semi-industrial vessels were licensed because they could not meet the requirement for obtaining insurances for their vessels. Number of communities supported with enhanced means of livelihoods to promote stakeholder-based co-management of fisheries resources (Number, Custom) Value Date 14-Jul Sep Sep Jun-2018 The co-management firm recruitment was delayed and this activity will not be carried out before project closing. However, many community campaigns have been conducted and there are ongoing improved smoking oven and drying rack pilots in different communities. The impact on the communities will be assessed during the ICR preparation. Page 7 of 14

8 Fishing Vessel Registration and Licensing Guidelines prepared by Fisheries Commission (Yes/No, Custom) Value N Y Y Y Date 07-Jul Sep Apr Jun-2018 This has been developed and approved. Fisheries Management Plan developed and submitted to Cabinet for approval (Yes/No, Custom) Value N Y Y Y Date 07-Jul Sep Apr Dec-2017 The FMP has been developed and approved by Cabinet. It is under implementation now. Framework and strategy for establishment of Marine protected areas (MPAs) prepared and submitted to the cabinet for approval (Yes/No, Custom) Value N N N Y Date 07-Jul Jun Apr Jun-2018 The final draft has been shared with the WB and pending finalization by the Ministry before submitting to Cabinet. This could be achieved before project closing. Page 8 of 14

9 Number of fisheries watch committees established and functional (Number, Custom) Value Date 14-Jul Jun Apr Dec fisheries watch committees have been established and are functional. The activities of the groups led to the arrest and successful prosecution of twenty-four (24) persons at the Ada Circuit Court. This has spurred individuals and groups in other communities to get involved in fisheries enforcement in local communities. E.g. Fishermen in Teshie and Nungua have eliminated light fishing in their community. The final target may not be achieved before project closing because there won't be enough time to set up proper fisheries watch committees; however, as noted above, there is a ripple effect that appears to be achieving the same goal. The ICR will elaborate further in these matters. Fishing enforcement unit established as described in 202 fisheries act (Text, Custom) Value No Yes Yes Yes Date 14-Jul Sep Apr Dec-2017 Achieved in Satellite based fishing vessel monitoring system is in place for the 200 mile exclusive economic zone and monitoring 24 hrs/day (Text, Custom) Value No Yes Yes Yes Date 14-Jul Sep Apr Jun-2018 Achieve. Page 9 of 14

10 Average daily operation of vessel monitoring system (Hours, Custom) Value Date 07-Jul Jun Apr Dec /7 operation of VMS. Annual law enforcement activities: (Number, Custom) Value , Date 14-Jul Sep Dec Jun-2018 The target has been met. By the end of 2017, a total of 1003 law enforcement activities were conducted, including 875 quayside inspections, 29 beach combing in 9 fishing communities, 27 sea patrols covering 480hrs and 72 observer missions were carried out during the year. The end target for this year may be smaller because it will be measured at project closing in June Page 10 of 14

11 Construction of improved smoke ovens for fish (Number, Custom) Value Date 14-Jul Sep Apr Jun-2018 This activity was delayed and has just started. So far, 3 have been built in Elima, Cape Coast and Moree. The target could be met if the project can find more contractors to scale this up as the demand is very high. National association of fish processors and traders established and functional (Yes/No, Custom) Value N Y Y Y Date 07-Jul Sep Apr Jun-2018 Established already. Zoning plan for Lake Volta developed (Yes/No, Custom) Value N Y Y Y Date 14-Jul Sep Sep Jun-2018 The Zoning report was completed. Two stakeholder consultations have been conducted. Final document is yet to be submitted to the Fisheries Commission Page 11 of 14

12 An electronic #dashboard# of key environmental, social and economic fisheries statistics established at the Secretariat of the Fisheries Commission and linked to the CSRP, and publicly accessible (Yes/No, Custom) Value N Y Y Y Date 14-Jul Sep Apr Jun-2018 This dashboard has been developed by the Sub-Regional Fishery Commission (SRFC) and is collecting data from each country to do analysis. Early warning system on disease outbreak established and functional (Yes/No, Custom) Value N N N Y Date 07-Jul Sep Apr Jun-2018 This will be not be achieved as there is no time to set it up before closing. The planned 18 month extension was shrunk to 6 months. This is one of the deliverables which won't be achieved because of this unexpected change. Database for disease of economic importance established and functional (Yes/No, Custom) Value N N N Y Date 07-Jul Sep Apr Jun-2018 This indicator will not be met because there is not enough time due to the unexpected extension period shrink. Meanwhile, because the disease outbreak was serious and there has not been an independent diagnosis study completed to map the issue and solutions, so the WB has supported an alternative activity which is more urgent. This could be achieved if the Project can identify a good candidate who can come to Ghana quickly. Page 12 of 14

13 Aquaculture policy developed and submitted to relevant authority for approval (Yes/No, Custom) Value N N N Y Date 07-Jul Sep Apr Jun-2018 An aquaculture policy was developed by a consultant. However, after review and consultation, FC rejected the final draft. Currently, a threepeople committee was set up to finalize the policy by taking into account of the consultation comments. This target could be achieved by project closing. Fish Health policy developed and submitted to the Cabinet for approval (Yes/No, Custom) Value N N Y Y Date 07-Jul Sep Apr Jun-2018 Fish health policy has been developed and submitted for Cabinet approval. Overall Some of the indicators not be achieved because during the last mission, an 18-month extension was envisioned if the government met the conditions. However, because the government failed to meet the agreed goals, only 6-month extension was approved to close some critical activities. Due to this unexpected change, there won't be enough time to achieve those targets. Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed P IDA Effective USD % P TF Effective USD % Page 13 of 14

14 Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P IDA Effective 14-Jul Jan Jun Dec Jun-2018 P TF Effective 27-Jan Jan Jun Dec Jun-2018 Cumulative Disbursements Restructuring History Level 2 Approved on 27-Jun-2017,Level 2 Approved on 26-Dec-2017 Related Project(s) P Ghana - West Africa Regional Fisheries Program (GEF) Page 14 of 14

The World Bank. Ghana - West Africa Regional Fisheries Program (P124775) Key Dates. Project Development Objectives. Components

The World Bank. Ghana - West Africa Regional Fisheries Program (P124775) Key Dates. Project Development Objectives. Components Public Disclosure Authorized AFRICA Ghana Environment & Natural Resources Global Practice IBRD/IDA Specific Investment Loan FY 2012 Seq No: 11 ARCHIVED on 23-Oct-2017 ISR27812 Implementing Agencies: Fishery

More information

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report Public Disclosure Authorized Public Disclosure Copy AFRICA Ghana Environment & Natural Resources Global Practice IBRD/IDA Specific Investment Loan FY 2012 Seq No: 9 ARCHIVED on 15-Sep-2016 ISR24903 Implementing

More information

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report Public Disclosure Authorized Public Disclosure Copy AFRICA Ghana Environment & Natural Resources Global Practice IBRD/IDA Specific Investment Loan FY 2012 Seq No: 8 ARCHIVED on 29-Feb-2016 ISR22549 Implementing

More information

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report Public Disclosure Authorized Public Disclosure Copy AFRICA Ghana Environment & Natural Resources Global Practice IBRD/IDA Specific Investment Loan FY 2012 Seq No: 7 ARCHIVED on 10-Aug-2015 ISR18623 Implementing

More information

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report Public Disclosure Authorized AFRICA Africa Agriculture and Rural Development Global Practice IBRD/IDA Adaptable Program Loan FY 2010 Seq No: 9 ARCHIVED on 25-Feb-2015 ISR17730 Implementing Agencies: Commission

More information

The World Bank. Ghana: Energy Development and Access Project (P074191) Key Dates. Project Development Objectives. Components

The World Bank. Ghana: Energy Development and Access Project (P074191) Key Dates. Project Development Objectives. Components Public Disclosure Authorized Public Disclosure Copy AFRICA Ghana Energy & Extractives Global Practice IBRD/IDA Specific Investment Loan FY 2008 Seq No: 17 ARCHIVED on 29-Jun-2017 ISR28824 Implementing

More information

The World Bank. Ghana: Energy Development and Access Project (P074191) Key Dates. Project Development Objectives. Components

The World Bank. Ghana: Energy Development and Access Project (P074191) Key Dates. Project Development Objectives. Components Public Disclosure Authorized AFRICA Ghana Energy & Extractives Global Practice IBRD/IDA Investment Project Financing FY 2008 Seq No: 19 ARCHIVED on 29-Jun-2018 ISR32934 Implementing Agencies: Electricity

More information

The World Bank Pacific Islands Regional Oceanscape Program - Tuvalu (P151780)

The World Bank Pacific Islands Regional Oceanscape Program - Tuvalu (P151780) Public Disclosure Authorized EAST ASIA AND PACIFIC Tuvalu Environment & Natural Resources Global Practice IBRD/IDA Investment Project Financing FY 2015 Seq No: 6 ARCHIVED on 08-Dec-2017 ISR30682 Implementing

More information

Montenegro Institutional Development and Agriculture Strengthening (MIDAS) (P107473)

Montenegro Institutional Development and Agriculture Strengthening (MIDAS) (P107473) Public Disclosure Authorized EUROPE AND CENTRAL ASIA Montenegro Agriculture Global Practice IBRD/IDA Specific Investment Loan FY 2009 Seq No: 13 ARCHIVED on 12-Apr-2016 ISR23062 Implementing Agencies:

More information

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report Public Disclosure Authorized AFRICA Africa Environment & Natural Resources Global Practice IBRD/IDA Adaptable Program Loan FY 2009 Seq No: 13 ARCHIVED on 29-Dec-2016 ISR26629 Implementing Agencies: Ministry

More information

Public Disclosure Copy

Public Disclosure Copy AFRICA Western Africa Finance, Competitiveness and Innovation Global Practice IBRD/IDA Investment Project Financing FY 2018 Seq No: 2 ARCHIVED on 11-Jun-2018 ISR32159 Implementing Agencies: CRRH, BOAD,

More information

The World Bank Burkina Faso Donsin Transport Infrastructure Project (P120960)

The World Bank Burkina Faso Donsin Transport Infrastructure Project (P120960) Public Disclosure Authorized AFRICA Burkina Faso Transport & ICT Global Practice IBRD/IDA Investment Project Financing FY 2013 Seq No: 11 ARCHIVED on 29-Dec-2017 ISR30740 Implementing Agencies: MOAD, Government

More information

Montenegro Institutional Development and Agriculture Strengthening (MIDAS) (P107473)

Montenegro Institutional Development and Agriculture Strengthening (MIDAS) (P107473) Public Disclosure Authorized EUROPE AND CENTRAL ASIA Montenegro Agriculture Global Practice IBRD/IDA Specific Investment Loan FY 2009 Seq No: 15 ARCHIVED on 26-May-2017 ISR27925 Implementing Agencies:

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized EUROPE AND CENTRAL ASIA Uzbekistan Water Global Practice IBRD/IDA Investment Project Financing FY 2013 Seq No: 11 ARCHIVED on 12-Jan-2018 ISR30620 Implementing Agencies: Republic

More information

Key Dates. Global Development Objectives. Components. Overall Ratings

Key Dates. Global Development Objectives. Components. Overall Ratings Public Disclosure Authorized AFRICA Cameroon Environment & Natural Resources Global Practice Global Environment Project Specific Investment Loan FY 2012 Seq No: 10 ARCHIVED on 19-Apr-2017 ISR27535 Implementing

More information

Jordan Ozone Depleting Substances HCFC Phase-Out Project (ODS3) (P127702)

Jordan Ozone Depleting Substances HCFC Phase-Out Project (ODS3) (P127702) Public Disclosure Authorized Public Disclosure Copy MIDDLE EAST AND NORTH AFRICA Jordan Environment & Natural Resources Global Practice Montreal Protocol Specific Investment Loan FY 2013 Seq No: 9 ARCHIVED

More information

Key Dates. Project Development Objectives. Components. Overall Ratings

Key Dates. Project Development Objectives. Components. Overall Ratings Public Disclosure Authorized AFRICA Madagascar Finance, Competitiveness and Innovation Global Practice IBRD/IDA Investment Project Financing FY 2018 Seq No: 1 ARCHIVED on 08-Jun-2018 ISR32759 Implementing

More information

The World Bank Jamaica Strategic Public Sector Transformation (P146688)

The World Bank Jamaica Strategic Public Sector Transformation (P146688) Public Disclosure Authorized LATIN AMERICA AND CARIBBEAN Jamaica Governance Global Practice IBRD/IDA Investment Project Financing FY 2015 Seq No: 7 ARCHIVED on 28-Jun-2018 ISR32761 Implementing Agencies:

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized EUROPE AND CENTRAL ASIA Armenia Energy & Extractives Global Practice Recipient Executed Activities Investment Project Financing FY 2015 Seq No: 1 ARCHIVED on 24-Sep-2015 ISR20717

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized EUROPE AND CENTRAL ASIA Serbia Transport Global Practice IBRD/IDA Specific Investment Loan FY 2013 Seq No: 4 ARCHIVED on 24-Jun-2015 ISR17421 Implementing Agencies: Public

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized EUROPE AND CENTRAL ASIA Georgia Transport & ICT Global Practice IBRD/IDA Investment Project Financing FY 2015 Seq No: 5 ARCHIVED on 09-Feb-2017 ISR25380 Implementing Agencies:

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized AFRICA Burkina Faso Social Protection & Labor Global Practice IBRD/IDA Investment Project Financing FY 2014 Seq No: 10 ARCHIVED on 23-Dec-2017 ISR29874 Implementing Agencies:

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized AFRICA Liberia Transport & ICT Global Practice IBRD/IDA Specific Investment Loan FY 2011 Seq No: 11 ARCHIVED on 10-Nov-2016 ISR24991 Implementing Agencies: Infrastructure Implementation

More information

The World Bank. Key Dates. Project Development Objectives. Components. Overall Ratings. Public Disclosure Authorized

The World Bank. Key Dates. Project Development Objectives. Components. Overall Ratings. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Copy AFRICA Ethiopia Social Protection & Labor Global Practice IBRD/IDA Sector Investment and Maintenance Loan FY 2013 Seq No: 12 ARCHIVED on 09-Oct-2015

More information

The World Bank Ghana - PPP Project (P125595)

The World Bank Ghana - PPP Project (P125595) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized AFRICA Ghana Finance & Markets Global Practice IBRD/IDA Adaptable Program Loan FY 2012

More information

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized AFRICA Nigeria Governance Global Practice IBRD/IDA Specific Investment Loan FY 2012 Seq

More information

Public Disclosure Copy

Public Disclosure Copy SOUTH ASIA Bangladesh Financial Management Global Practice Recipient Executed Activities Technical Assistance Loan FY 2011 Seq No: 4 ARCHIVED on 26-Feb-2015 ISR18034 Implementing Agencies: Key Dates Key

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized LATIN AMERICA AND CARIBBEAN Argentina Social Protection & Labor Global Practice IBRD/IDA Specific Investment Loan FY 2009 Seq No: 14 ARCHIVED on 16-Jun-2016 ISR23892 Implementing

More information

Zambia Kafue Town - Muzuma - Victoria Falls Regional Transmission Line Reinforcement Project

Zambia Kafue Town - Muzuma - Victoria Falls Regional Transmission Line Reinforcement Project Public Disclosure Authorized Zambia Kafue Town - Muzuma - Victoria Falls Regional Transmission Line Reinforcement Project (P124351) AFRICA Africa Energy and Mining Global Practice IBRD/IDA Specific Investment

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized EAST ASIA AND PACIFIC Indonesia Social, Urban, Rural and Resilience Global Practice Global Practice IBRD/IDA Specific Investment Loan FY 2013 Seq No: 9 ARCHIVED on 22-Jun-2017

More information

Public Disclosure Copy. Implementation Status & Results Report Improving Maternal and Child Health through Integrated Social Services (P123706)

Public Disclosure Copy. Implementation Status & Results Report Improving Maternal and Child Health through Integrated Social Services (P123706) Public Disclosure Authorized LATIN AMERICA AND CARIBBEAN Haiti Health, Nutrition & Population Global Practice IBRD/IDA Investment Project Financing FY 2013 Seq No: 10 ARCHIVED on 29-Jun-2018 ISR32902 Implementing

More information

MicroSmall&Medium Enterprise and Large Enterprise Supply Chain Finance (P157691)

MicroSmall&Medium Enterprise and Large Enterprise Supply Chain Finance (P157691) EUROPE AND CENTRAL ASIA Turkey Finance, Competitiveness and Innovation Global Practice IBRD/IDA Investment Project Financing FY 2016 Seq No: 6 ARCHIVED on 26-Nov-2018 ISR34378 Implementing Agencies: Türkiye

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized EUROPE AND CENTRAL ASIA Georgia Transport & ICT Global Practice IBRD/IDA Investment Project Financing FY 2015 Seq No: 6 ARCHIVED on 11-Sep-2017 ISR28869 Implementing Agencies:

More information

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report Public Disclosure Authorized Public Disclosure Copy EAST ASIA AND PACIFIC China Energy & Extractives Global Practice IBRD/IDA Financial Intermediary Loan FY 2008 Seq No: 11 ARCHIVED on 16-Dec-2015 ISR21909

More information

The World Bank Emergency 2007 Cyclone Recovery and Restoration Project (P111272)

The World Bank Emergency 2007 Cyclone Recovery and Restoration Project (P111272) Public Disclosure Authorized SOUTH ASIA Bangladesh Social, Urban, Rural and Resilience Global Practice Global Practice IBRD/IDA Emergency Recovery Loan FY 2009 Seq No: 14 ARCHIVED on 31-Dec-2015 ISR21491

More information

West Bank and Gaza: Finance for Jobs (P151089)

West Bank and Gaza: Finance for Jobs (P151089) MIDDLE EAST AND NORTH AFRICA West Bank and Gaza Finance & Markets Global Practice Special Financing Investment Project Financing FY 2016 Seq No: 1 ARCHIVED on 18-Apr-2016 ISR23000 Implementing Agencies:

More information

The World Bank Palestinian Recovery & Development Plan MDTF (P110690)

The World Bank Palestinian Recovery & Development Plan MDTF (P110690) Public Disclosure Authorized MIDDLE EAST AND NORTH AFRICA West Bank and Gaza Recipient Executed Activities Adaptable Program Loan FY 2008 Seq No: 6 ARCHIVED on 21-Mar-2017 ISR27335 Implementing Agencies:

More information

Key Dates. Project Development Objectives. Components. Overall Ratings. Implementation Status and Key Decisions

Key Dates. Project Development Objectives. Components. Overall Ratings. Implementation Status and Key Decisions Public Disclosure Authorized AFRICA Africa Water Global Practice IBRD/IDA Investment Project Financing FY 2015 Seq No: 3 ARCHIVED on 27-Jun-2016 ISR22945 Implementing Agencies: Zambezi River Authority

More information

Road Sector Development Project (P149322)

Road Sector Development Project (P149322) Public Disclosure Authorized EUROPE AND CENTRAL ASIA Ukraine Transport & Digital Development Global Practice IBRD/IDA Investment Project Financing FY 2016 Seq No: 6 ARCHIVED on 20-Jun-2018 ISR32806 Implementing

More information

Saint Lucia Health System Strengthening Project (P166783)

Saint Lucia Health System Strengthening Project (P166783) LATIN AMERICA AND CARIBBEAN St. Lucia Health, Nutrition & Population Global Practice IBRD/IDA Investment Project Financing FY 2019 Seq No: 1 ARCHIVED on 26-Dec-2018 ISR35158 Implementing Agencies: Ministry

More information

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report Public Disclosure Authorized EAST ASIA AND PACIFIC Vietnam Transport Global Practice IBRD/IDA Specific Investment Loan FY 2008 Seq No: 12 ARCHIVED on 24-Feb-2015 ISR18063 Implementing Agencies: Hanoi Urban

More information

Public Disclosure Copy. Implementation Status & Results Report Revenue Mobilization Program for Results: VAT Improvement Program (VIP) (P129770)

Public Disclosure Copy. Implementation Status & Results Report Revenue Mobilization Program for Results: VAT Improvement Program (VIP) (P129770) Public Disclosure Authorized SOUTH ASIA Bangladesh Governance Global Practice IBRD/IDA Program-for-Results FY 2014 Seq No: 7 ARCHIVED on 05-Jun-2017 ISR28344 Implementing Agencies: National Board of Revenue,

More information

Public Disclosure Copy. Name Previous Rating Current Rating

Public Disclosure Copy. Name Previous Rating Current Rating Public Disclosure Authorized AFRICA Kenya Social Protection & Labor Global Practice IBRD/IDA Program-for-Results FY 2014 Seq No: 8 ARCHIVED on 30-Oct-2017 ISR28662 Implementing Agencies: Department for

More information

The World Bank Research and Innovation in Science and Technology Project (P121842)

The World Bank Research and Innovation in Science and Technology Project (P121842) Public Disclosure Authorized EAST ASIA AND PACIFIC Indonesia Education Global Practice IBRD/IDA Specific Investment Loan FY 2013 Seq No: 7 ARCHIVED on 07-Dec-2016 ISR25509 Implementing Agencies: Ministry

More information

The World Bank Mozambique Public Financial Management for Results Program (P124615)

The World Bank Mozambique Public Financial Management for Results Program (P124615) Public Disclosure Authorized AFRICA Mozambique Governance Global Practice IBRD/IDA Program-for-Results FY 2014 Seq No: 6 ARCHIVED on 29-Jun-2017 ISR28952 Implementing Agencies: Ministry of Economy and

More information

Public Disclosure Copy

Public Disclosure Copy EAST ASIA AND PACIFIC China Energy & Extractives Global Practice IBRD/IDA Investment Project Financing FY 2011 Seq No: 12 ARCHIVED on 27-Nov-2017 ISR28052 Implementing Agencies: Ministry of Fiance, Shandong

More information

TR Third Access to Finance for SMEs (SME III) (P130864)

TR Third Access to Finance for SMEs (SME III) (P130864) EUROPE AND CENTRAL ASIA Turkey Finance, Competitiveness and Innovation Global Practice IBRD/IDA Investment Project Financing FY 2013 Seq No: 9 ARCHIVED on 17-Oct-2018 ISR34297 Implementing Agencies: T.

More information

Debt Management Strengthening Programme at Ministry of Finance, Government of Pakistan (P161451)

Debt Management Strengthening Programme at Ministry of Finance, Government of Pakistan (P161451) SOUTH ASIA Pakistan Macroeconomics, Trade and Investment Global Practice Recipient Executed Activities Investment Project Financing FY 2017 Seq No: 2 ARCHIVED on 27-Jun-2018 ISR33129 Implementing Agencies:

More information

The World Bank Indonesia Power Transmission Development Project (P117323)

The World Bank Indonesia Power Transmission Development Project (P117323) Public Disclosure Authorized EAST ASIA AND PACIFIC Indonesia Energy & Extractives Global Practice IBRD/IDA Investment Project Financing FY 2011 Seq No: 13 ARCHIVED on 28-Dec-2017 ISR30911 Implementing

More information

The World Bank Mauritania Public Sector Governance Project (P146804)

The World Bank Mauritania Public Sector Governance Project (P146804) Public Disclosure Authorized AFRICA Mauritania Governance Global Practice IBRD/IDA Investment Project Financing FY 2016 Seq No: 4 ARCHIVED on 27-Feb-2018 ISR31581 Implementing Agencies: Ministry of Economy

More information

The World Bank NP: Strengthening the Office of the Auditor General (P127040)

The World Bank NP: Strengthening the Office of the Auditor General (P127040) Public Disclosure Authorized SOUTH ASIA Nepal Financial Management Global Practice Recipient Executed Activities Specific Investment Loan FY 2012 Seq No: 3 ARCHIVED on 20-Feb-2015 ISR18017 Implementing

More information

Bangladesh Insurance Sector Development Project (P156823)

Bangladesh Insurance Sector Development Project (P156823) SOUTH ASIA Bangladesh Finance, Competitiveness and Innovation Global Practice IBRD/IDA Investment Project Financing FY 2017 Seq No: 4 ARCHIVED on 11-Oct-2018 ISR34079 Implementing Agencies: PEOPLE'S REPUBLIC

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized MIDDLE EAST AND NORTH AFRICA Lebanon Social Protection & Labor Global Practice Recipient Executed Activities Investment Project Financing FY 2014 Seq No: 5 ARCHIVED on 09-Jan-2017

More information

The World Bank IN Swachh Bharat Mission Support Operation (P153251)

The World Bank IN Swachh Bharat Mission Support Operation (P153251) Public Disclosure Authorized SOUTH ASIA India Water Global Practice IBRD/IDA Program-for-Results FY 2016 Seq No: 2 ARCHIVED on 05-Feb-2017 ISR24559 Implementing Agencies: Public Disclosure Authorized Program

More information

Mozambique -Roads and Bridges Management and Maintenance Program - Phase II (P083325)

Mozambique -Roads and Bridges Management and Maintenance Program - Phase II (P083325) AFRICA Mozambique Transport & Digital Development Global Practice IBRD/IDA Investment Project Financing FY 2007 Seq No: 24 ARCHIVED on 29-Aug-2018 ISR33744 Implementing Agencies: ROAD FUND (Fundo de Estradas),

More information

The World Bank Kenya Cash Transfer for Orphans and Vulnerable Children (P111545)

The World Bank Kenya Cash Transfer for Orphans and Vulnerable Children (P111545) Public Disclosure Authorized AFRICA Kenya Social Protection & Labor Global Practice IBRD/IDA Specific Investment Loan FY 2009 Seq No: 17 ARCHIVED on 21-Jun-2017 ISR28380 Implementing Agencies: Ministry

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized SOUTH ASIA India Governance Global Practice IBRD/IDA Investment Project Financing FY 2016 Seq No: 1 ARCHIVED on 06-May-2016 ISR23129 Implementing Agencies: Department of Public

More information

The World Bank CG Rep. Skills Development for Employability Project (P128628)

The World Bank CG Rep. Skills Development for Employability Project (P128628) Public Disclosure Authorized AFRICA Congo, Republic of Education Global Practice IBRD/IDA Investment Project Financing FY 2014 Seq No: 8 ARCHIVED on 17-Jun-2017 ISR27973 Implementing Agencies: Ministry

More information

The World Bank Pakistan Punjab Jobs and Competitiveness Program for Results (P155963)

The World Bank Pakistan Punjab Jobs and Competitiveness Program for Results (P155963) Public Disclosure Authorized SOUTH ASIA Pakistan Trade & Competitiveness Global Practice IBRD/IDA Program-for-Results FY 2016 Seq No: 3 ARCHIVED on 14-Aug-2017 ISR28997 Implementing Agencies: Government

More information

Public Disclosure Copy. Implementation Status & Results Report CAPE VERDE - Recovery and Reform of the Electricity Sector Project (P115464)

Public Disclosure Copy. Implementation Status & Results Report CAPE VERDE - Recovery and Reform of the Electricity Sector Project (P115464) Public Disclosure Authorized AFRICA Cabo Verde Energy & Extractives Global Practice IBRD/IDA Specific Investment Loan FY 2012 Seq No: 10 ARCHIVED on 23-Oct-2017 ISR29430 Implementing Agencies: Unidade

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized AFRICA Congo, Republic of Social Protection & Labor Global Practice IBRD/IDA Investment Project Financing FY 2014 Seq No: 4 ARCHIVED on 07-Jan-2016 ISR22324 Implementing Agencies:

More information

The World Bank MW: Mining Governance and Growth Support Project (P120825)

The World Bank MW: Mining Governance and Growth Support Project (P120825) Public Disclosure Authorized AFRICA Malawi Energy & Extractives Global Practice IBRD/IDA Investment Project Financing FY 2011 Seq No: 10 ARCHIVED on 05-Jan-2018 ISR28752 Implementing Agencies: Government

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized LATIN AMERICA AND CARIBBEAN Brazil Agriculture Global Practice IBRD/IDA Specific Investment Loan FY 2012 Seq No: 9 ARCHIVED on 29-Feb-2016 ISR22351 Implementing Agencies: SEDAR

More information

Results-Based Rural Water Supply and Sanitation Under the National Target Program (P127435)

Results-Based Rural Water Supply and Sanitation Under the National Target Program (P127435) Public Disclosure Authorized EAST ASIA AND PACIFIC Vietnam Water Global Practice Requesting Unit: EACVF Responsible Unit: GWA02 IBRD/IDA Program-for-Results Financing FY 2013 Team Leader(s): Lilian Pena

More information

The World Bank. Key Dates. Project Development Objectives. Components. Overall Ratings. Implementation Status and Key Decisions

The World Bank. Key Dates. Project Development Objectives. Components. Overall Ratings. Implementation Status and Key Decisions Public Disclosure Authorized Public Disclosure Copy AFRICA South Sudan Health, Nutrition & Population Global Practice Special Financing Emergency Recovery Loan FY 2012 Seq No: 7 ARCHIVED on 23-Dec-2015

More information

The World Bank Indonesia Infrastructure Guarantee Fund Project (P118916)

The World Bank Indonesia Infrastructure Guarantee Fund Project (P118916) Public Disclosure Authorized EAST ASIA AND PACIFIC Indonesia Finance & Markets Global Practice IBRD/IDA Investment Project Financing FY 2013 Seq No: 10 ARCHIVED on 24-Dec-2017 ISR31037 Implementing Agencies:

More information

Innovative Access to Finance (P147183)

Innovative Access to Finance (P147183) Public Disclosure Authorized EUROPE AND CENTRAL ASIA Turkey Finance, Competitiveness and Innovation Global Practice IBRD/IDA Investment Project Financing FY 2015 Seq No: 7 ARCHIVED on 07-Mar-2018 ISR31622

More information

Public Disclosure Copy. Implementation Status & Results Report Dominican Republic DRM Development Policy Loan with a Cat DDO (P159351)

Public Disclosure Copy. Implementation Status & Results Report Dominican Republic DRM Development Policy Loan with a Cat DDO (P159351) LATIN AMERICA AND CARIBBEAN Dominican Republic Social, Urban, Rural and Resilience Global Practice Global Practice IBRD/IDA Development Policy Lending FY 2018 Seq No: 1 ARCHIVED on 26-Jan-2018 ISR31220

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized EUROPE AND CENTRAL ASIA Turkey Finance & Markets Global Practice IBRD/IDA Investment Project Financing FY 2013 Seq No: 8 ARCHIVED on 16-Oct-2017 ISR29893 Implementing Agencies:

More information

PNG - Small and Medium Enterprise Access to Finance Project (P120707)

PNG - Small and Medium Enterprise Access to Finance Project (P120707) EAST ASIA AND PACIFIC Papua New Guinea Finance, Competitiveness and Innovation Global Practice IBRD/IDA Investment Project Financing FY 2011 Seq No: 14 ARCHIVED on 13-Dec-2018 ISR34953 Implementing Agencies:

More information

Public Disclosure Copy

Public Disclosure Copy AFRICA Uganda Transport Global Practice IBRD/IDA Specific Investment Loan FY 2010 Seq No: 10 ARCHIVED on 24-Feb-2015 ISR17943 Implementing Agencies: Uganda National Roads Authority Key Dates Key Project

More information

The World Bank Municipal Services Improvement (P096481)

The World Bank Municipal Services Improvement (P096481) Public Disclosure Authorized EUROPE AND CENTRAL ASIA Macedonia, former Yugoslav Republic of Urban Development Global Practice IBRD/IDA Specific Investment Loan FY 2009 Seq No: 15 ARCHIVED on 15-Jun-2015

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized AFRICA Ghana Poverty and Equity Global Practice IBRD/IDA Investment Project Financing FY 2012 Seq No: 10 ARCHIVED on 09-Mar-2018 ISR31489 Implementing Agencies: Ghana Statistical

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized AFRICA Congo, Democratic Republic of Transport & ICT Global Practice IBRD/IDA Specific Investment Loan FY 2010 Seq No: 14 ARCHIVED on 17-Oct-2017 ISR29443 Implementing Agencies:

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized AFRICA Togo Agriculture and Rural Development Global Practice IBRD/IDA Specific Investment Loan FY 2011 Seq No: 8 ARCHIVED on 16-Jan-2015 ISR17841 Implementing Agencies: General

More information

Public Disclosure Copy

Public Disclosure Copy LATIN AMERICA AND CARIBBEAN Honduras Energy & Extractives Global Practice Recipient Executed Activities Technical Assistance Loan FY 2014 Seq No: 1 ARCHIVED on 16-Oct-2015 ISR20092 Implementing Agencies:

More information

Key Dates. Global Environmental Objectives. Components. Overall Ratings

Key Dates. Global Environmental Objectives. Components. Overall Ratings Public Disclosure Authorized EAST ASIA AND PACIFIC Philippines Environment & Natural Resources Global Practice Global Environment Project Specific Investment Loan FY 2010 Seq No: 10 ARCHIVED on 20-May-2016

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized AFRICA Ghana Finance & Markets Global Practice IBRD/IDA Adaptable Program Loan FY 2012 Seq : 7 ARCHIVED on 27-Aug-2015 ISR20184 Implementing Agencies: Public Investment Department,

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized AFRICA Sudan Social Protection & Labor Global Practice Recipient Executed Activities Investment Project Financing FY 2016 Seq No: 2 ARCHIVED on 28-Jun-2017 ISR28599 Implementing

More information

Public Disclosure Copy

Public Disclosure Copy EAST ASIA AND PACIFIC Solomon Islands Energy & Extractives Global Practice IBRD/IDA Investment Project Financing FY 2009 Seq No: 14 ARCHIVED on 16-May-2018 ISR32246 Implementing Agencies: Ministry of Finance

More information

Improving Maternal and Child Health through Integrated Social Services (P123706)

Improving Maternal and Child Health through Integrated Social Services (P123706) Public Disclosure Authorized LATIN AMERICA AND CARIBBEAN Haiti Health, Nutrition & Population Global Practice IBRD/IDA Investment Project Financing FY 2013 Seq No: 11 ARCHIVED on 31-Dec-2018 ISR35476 Implementing

More information

Public Disclosure Copy. Name Previous Rating Current Rating

Public Disclosure Copy. Name Previous Rating Current Rating Public Disclosure Authorized AFRICA Kenya Social Protection Global Practice IBRD/IDA Program-for-Results FY 2014 Seq No: 3 ARCHIVED on 26-Dec-2014 ISR17662 Implementing Agencies: Program Development Objectives

More information

The World Bank Transport Connectivity and Asset Management Project (P132833)

The World Bank Transport Connectivity and Asset Management Project (P132833) SOUTH ASIA Sri Lanka Transport & ICT Global Practice IBRD/IDA Specific Investment Loan FY 2016 Seq No: 3 ARCHIVED on 31-Aug-2017 ISR29065 Implementing Agencies: Democratic Socialist Republic of Sri Lanka,

More information

The World Bank Recife Swap Education and Public Management (P126372)

The World Bank Recife Swap Education and Public Management (P126372) Public Disclosure Authorized LATIN AMERICA AND CARIBBEAN Brazil Education Global Practice IBRD/IDA Specific Investment Loan FY 2012 Seq No: 5 ARCHIVED on 19-Dec-2014 ISR17241 Implementing Agencies: Public

More information

The World Bank Kenya Infrastructure Finance/PPP project (P121019)

The World Bank Kenya Infrastructure Finance/PPP project (P121019) Public Disclosure Authorized AFRICA Kenya Financial Systems Practice Global Practice IBRD/IDA Adaptable Program Loan FY 2013 Seq No: 4 ARCHIVED on 22-Dec-2014 ISR17114 Implementing Agencies: Public Private

More information

Public Disclosure Copy

Public Disclosure Copy AFRICA Uganda Transport & ICT Global Practice IBRD/IDA Specific Investment Loan FY 2010 Seq No: 11 ARCHIVED on 17-Aug-2015 ISR20352 Implementing Agencies: Uganda National Roads Authority (UNRA) Key Dates

More information

Public Disclosure Copy. Implementation Status & Results Report CO Rio Bogota Environmental Recuperation and Flood Control Project (P111479)

Public Disclosure Copy. Implementation Status & Results Report CO Rio Bogota Environmental Recuperation and Flood Control Project (P111479) Public Disclosure Authorized LATIN AMERICA AND CARIBBEAN Colombia Water Global Practice IBRD/IDA Specific Investment Loan FY 2011 Seq No: 12 ARCHIVED on 30-Jun-2017 ISR27693 Implementing Agencies: Corporacion

More information

Public Disclosure Copy

Public Disclosure Copy SOUTH ASIA India Finance & Markets Global Practice IBRD/IDA Financial Intermediary Loan FY 2013 Seq No: 8 ARCHIVED on 11-Nov-2016 ISR25496 Implementing Agencies: National Housing Bank, National Housing

More information

The World Bank Revenue Administration Modernization Project (P130202)

The World Bank Revenue Administration Modernization Project (P130202) Public Disclosure Authorized EUROPE AND CENTRAL ASIA Romania Governance Global Practice IBRD/IDA Investment Project Financing FY 2013 Seq No: 10 ARCHIVED on 06-Feb-2018 ISR31261 Implementing Agencies:

More information

West Bengal PRI (P105990)

West Bengal PRI (P105990) Public Disclosure Authorized SOUTH ASIA India Social, Urban, Rural and Resilience Global Practice Global Practice IBRD/IDA Specific Investment Loan FY 2010 Seq No: 11 ARCHIVED on 30-Jun-2016 ISR23953 Implementing

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized SOUTH ASIA Afghanistan Governance Global Practice Recipient Executed Activities Technical Assistance Loan FY 2011 Seq No: 12 ARCHIVED on 15-May-2017 ISR28000 Implementing Agencies:

More information

The World Bank Indonesia Power Transmission Development Project (P117323)

The World Bank Indonesia Power Transmission Development Project (P117323) Public Disclosure Authorized EAST ASIA AND PACIFIC Indonesia Energy & Extractives Global Practice IBRD/IDA Specific Investment Loan FY 2011 Seq No: 7 ARCHIVED on 07-Jul-2015 ISR18557 Implementing Agencies:

More information

The World Bank Kabul Urban Transport Efficiency Improvement Project (P131864)

The World Bank Kabul Urban Transport Efficiency Improvement Project (P131864) Public Disclosure Authorized SOUTH ASIA Afghanistan Transport & Digital Development Global Practice Recipient Executed Activities Investment Project Financing FY 2014 Seq No: 8 ARCHIVED on 09-Feb-2018

More information

The World Bank Bangladesh Ghorashal Unit 4 Repowering Project (P128012)

The World Bank Bangladesh Ghorashal Unit 4 Repowering Project (P128012) Public Disclosure Authorized SOUTH ASIA Bangladesh Energy & Extractives Global Practice IBRD/IDA Investment Project Financing FY 2016 Seq No: 3 ARCHIVED on 24-Apr-2017 ISR27761 Implementing Agencies: Public

More information

The World Bank DRC Multi-modal Transport (P092537)

The World Bank DRC Multi-modal Transport (P092537) AFRICA Congo, Democratic Republic of Transport Global Practice IBRD/IDA Specific Investment Loan FY 2010 Seq No: 10 ARCHIVED on 06-Mar-2015 ISR17792 Implementing Agencies: Key Dates Key Project Dates Board

More information

West Bengal Institutional Strengthening of Gram Panchayats Program II (P159427)

West Bengal Institutional Strengthening of Gram Panchayats Program II (P159427) Public Disclosure Authorized SOUTH ASIA India Social, Urban, Rural and Resilience Global Practice Global Practice Requesting Unit: SACIN Responsible Unit: GSU12 IBRD/IDA Program-for-Results FY 2017 Team

More information

Public Disclosure Copy. Implementation Status & Results Report Uganda Reproductive, Maternal and Child Health Services Improvement Project (P155186)

Public Disclosure Copy. Implementation Status & Results Report Uganda Reproductive, Maternal and Child Health Services Improvement Project (P155186) Public Disclosure Authorized AFRICA Uganda Health, Nutrition & Population Global Practice IBRD/IDA Investment Project Financing FY 2017 Seq No: 3 ARCHIVED on 20-Dec-2017 ISR30454 Implementing Agencies:

More information

The World Bank Integrated Disaster Risk Management and Resilience Program (P144539)

The World Bank Integrated Disaster Risk Management and Resilience Program (P144539) Public Disclosure Authorized MIDDLE EAST AND NORTH AFRICA Morocco Social, Urban, Rural and Resilience Global Practice Global Practice IBRD/IDA Program-for-Results FY 2016 Seq No: 3 ARCHIVED on 08-Aug-2017

More information

The World Bank Albania-Enhancing Quality of Financial Reporting (EQ-FINREP) (P152567)

The World Bank Albania-Enhancing Quality of Financial Reporting (EQ-FINREP) (P152567) EUROPE AND CENTRAL ASIA Albania Governance Global Practice Recipient Executed Activities Investment Project Financing FY 2015 Seq No: 2 ARCHIVED on 17-Oct-2017 ISR29727 Implementing Agencies: Key Dates

More information

Public Disclosure Copy. Implementation Status & Results Report Savings and Credit Sector Consolidation and Financial Inclusion Project (P123367)

Public Disclosure Copy. Implementation Status & Results Report Savings and Credit Sector Consolidation and Financial Inclusion Project (P123367) LATIN AMERICA AND CARIBBEAN Mexico Finance & Markets Global Practice IBRD/IDA Specific Investment Loan FY 2012 Seq No: 7 ARCHIVED on 18-Sep-2015 ISR20306 Implementing Agencies: Key Dates Key Project Dates

More information