Nevada Power & Sierra Pacific Power d/b/a NV Energy Stakeholders Planning Input Meeting July

Size: px
Start display at page:

Download "Nevada Power & Sierra Pacific Power d/b/a NV Energy Stakeholders Planning Input Meeting July"

Transcription

1 Nevada Power & Sierra Pacific Power d/b/a NV Energy Stakeholders Planning Input Meeting July

2 1. Welcome Introductions 2. IRP filing and results Update on Loads and Resources Renewable Transmission Initiative 3. WestConnect SWAT/SPPG Study Results FERC Order Customer and Stakeholder Input 5. Customer and Stakeholder Planned Projects (TBD) (Proposed projects) 6. Additional Items 7. Closing Comments 2

3 1. Nevada Power Filed its 2012 Integrated Resource Plan (IRP) covering the period on June 29, The 2012 IRP was designated as Docket

4 1. ON Line Transmission Project 2. Renewable Transmission Initiative 3. Harry Allen 500/230 kv Transformer 4. WestConnect 4

5 Project was approved by the PUCN in the Nevada Power 2009 IRP Filing and the Sierra 8 th Amendment to the 2007 IRP. NVE / LS ON Line Financial closing occurred on 2/11/11 5

6 SCOPE 235-mile 500 kv transmission line Robinson-Harry Allen Robinson Summit 500/345 kv substation Falcon-Gonder Fold Series compensation on the existing Falcon Gonder 345 kv line Harry Allen Terminal SPPC and NPC Balancing areas will be consolidated post ON- Line Original ON-Line project scheduled in service December

7 Wind Induced Vibration Issues In early December 2011 high sustained winds damaged several tubular guyed V towers Several potential tower modifications are currently undergoing testing In-service date of the project has been delayed to December 2013

8 The Harry Allen 500/230 kv transformer is the preferred alternative to provide additional capacity from the 500 kv system to the 230 kv system Project is preferred over the Sunrise Tap project, Thunderbird 500/230 kv substation, or Northwest 2 nd transformer and Northwest HA Line. Project would include the following elements: 1. 1,500 MVA 525/230 kv Autotransformer at Harry Allen MVA 230/138 kv Autotransformer at Clark Substation MVA 230/138 kv Autotransformer at Faulkner Substation

9 NPC is not recommending the installation of the Harry Allen 500/230 kv transformer at this time Project can be delayed with changes in operating procedures including Crystal PST operation, redispatch of Clark generation and Lenzie generation RAS Need for the project will be driven by: 1. Increases in load growth 2. Replacement of generation inside load pocket with external resources 3. New Transmission Service Agreements 4. Additional external renewable resources delivered 5. into the Las Vegas load pocket.

10 WestConnect Action Plan Funding 1. The WestConnect Steering Committee is a group of 17 transmission owners in the Southwest who have joined together for the following purposes: Continue investigation of cost effective transmission enhancements to serve wholesale markets. Pursue required regulatory approvals for transmission enhancements. Work cooperatively with other western grid organizations and market participants. 2. NPC has requested PUCN approval of funding for the continued participation in WestConnect. 10

11 kv Sunrise Tap Project 2. North Las Vegas VARS Project 3. Brooks 230/138/12 kv Substation 4. McDonald 230/138 kv Transformer 5. Darling 230/12 kv Substation 6. Southeast No. 2, 230/12 kv Substation 7. Northwest Second 500/230 kv transformer 11

12 1. Sierra Pacific filed its 2010 Integrated Resource Plan (IRP) covering the period on July 1, The 2010 IRP was designated as Docket The Public Utilities Commission Of Nevada (PUCN) issued its order on the IRP on 12/10/10 12

13 1. Fallon 230 kv Reinforcement 2. Bordertown to Cal Sub 120 kv Line 3. WestConnect Action Plan Funding 4. Blackhawk Project Request Cancelation 5. Blackhawk Mira Loma Line Request Cancelation 6. Blackhawk 345 kv Capacitor Request Cancelation 7. Plumas Sierra Interconnection Request Cancelation 13

14 Fallon 230 kv Reinforcement 1. The Fallon 230 kv reinforcement project original project scope included a 230 kv transmission line from the existing Salt Wells tap location on the Ft. Churchill Austin 230 kv line to the new Greenwave substation in Fallon. 2. Project would have interconnected two new geothermal projects and provide additional capacity to Fallon area loads. 3. Scope of the project has been reevaluated due to the cancellation of one geothermal project LGIA and a reduction in the Fallon area load growth. 4. Revised project scope includes construction of Pony Express switching station and acquisition of 230 kv transmission line from Austin-Frontier 230 kv line tap to Pony Express. 14

15 Bordertown to Cal Sub 120 kv Line 1. The project was approved by the PUCN in 2007 and includes the construction of a 345/120 kv transformer at Bordertown Substation and a new 120 kv line from Bordertown substation to California Substation. 2. Project would provide additional transmission support to the West Reno transmission system for outages of a North Valley Road transformer and N-1-1 outages of the 120 kv transmission system. 3. To date Sierra has not obtained the required permits for this line and permitting work is continuing. The in-service date for this project has been moved from 2012 to

16 Request to Cancel Previously Approved Projects 1. Due to the decrease in the forecast load growth Sierra requested and received PUCN approval to cancel the following previously approved transmission projects: Blackhawk Project Blackhawk Mira Loma Line Blackhawk 345 kv Capacitor Plumas Sierra Interconnection 16

17 HOT WEATHER ENERGY PERCENT PEAK PERCENT PEAK PERCENT Year (GWH) GROWTH (MW) GROWTH (MW) GROWTH ,659 5, , % 5, % 5, , % 5, % 5, % , % 5, % 5, % , % 5, % 5, % , % 5, % 5, % , % 5, % 5, % , % 5, % 6, % , % 5, % 6, % , % 5, % 6, % , % 5, % 6, % 17

18 HOT WEATHER ENERGY PERCENT PEAK PERCENT PEAK PERCENT Year (GWH) GROWTH (MW) GROWTH (MW) GROWTH ,728 1, , % 1, % 1, , % 1, % 1, % , % 1, % 1, % , % 1, % 1, % , % 1, % 1, % , % 1, % 1, % , % 1, % 1, % , % 1, % 1, % , % 1, % 1, % , % 1, % 1, % , % 1, % 1, % 18

19 Recorded Forecast Daily Temperatures 20-yr average Temps Difference w/ Fcst (MW) Date Hour Max Min (MW) Max Min MW % Diff South 5,761 7/11/2012 5:00 PM , % North 1,618 7/11/2012 5:00 PM , % Note: The air conditioner load management program was not operated in the South on 7/11/2012. The forecast assumes operation of the system. If operated that day, the peak would have been about 5,680 MW. 19

20 Combined Loads in Control Area of NPC, Boulder City, CRC- BMI, City of LV SB211, LVVWD, Lincoln, Overton, East Side / Newport, SB 211, Valley Electric, City of Henderson PEAK PERCENT YEAR (MW) GROWTH % % % % % % % % % % 20

21 Required by Assembly Bill 387 Process developed under PUCN Docket Identifies transmission plans and costs to access RETAAC/PUCN approved renewable energy zones NV Energy is required to file an RECTP in each triennial Integrated Resource Plan CREZTP was filed June 29, 2012 in the NPC IRP This RECTP integrates ON Line, RETAAC/PUCN, Western SOI, SWAT and SSPG work into comprehensive design. 21

22 The CREZTP is a conceptual plan to provide the transmission required to interconnect each of the renewable energy zones forecast by RETAAC. Elements of the plan include: Construct the ON Line Project Permit Harry Allen Northwest and Northwest Amargosa 500 kv lines. Permit Harry Allen Eldorado 500 kv line. Future elements could include construction of the West Side Tieline and required collector lines. Estimated cost of the RECTP is $4.3 billion. 22

23 Transmission proposed from four Points of Receipt (1-4) to three Points of Delivery (A-C) ~ 600 miles of potential EHV lines. Significant response on Sept. 16th, 2011 Study agreements sent Nov. 1st, 2011 Agreements due by Dec. 15th, 2011

24 Studies completed and given to participants April 27, 2012 Permitting and construction costs estimated have been completed RTI process has been concluded. Customer commitments were insufficient to fund Phase 2

25 2011 TEPPC / TAS Study Request 2011 TEPPC / TAS/SWG status 25

26 2012 Study Request Projects

27 Three studies are being requested in response to requests from the Nevada Energy Assistance Corporation - a SSPG stakeholder. The studies requested are as follows: 1. A new 345/230 kv 1000 MW tie line from Northern Nevada to Northern California. This study is similar to last year s SSPG request but the resource mix and topology for this study differs from the 2011 request. 2. A new 500 kv tie line for MW delivered from Northern Nevada into Southern California via a new line paralleling the existing Pacific DC line. 3. A new 345 kv tie line for 600 MW delivered from Northern Nevada into Southern California via a new line to the IPP DC line in Utah. 27

28 High capacity factor of N. NV Geothermal energy No need for following resources Short distance from California Potential expedited in-service date The SSPG expects these projects will be highly competitive with other projects included in the TEPPC 2010 Study Report and study programs. Expected Completion by TEPPC Q4 2013

29 Eastern terminus of LMUD Interconnection from 2011 SSPG Study Project constructed at 345 kv 29

30 Project constructed at 500 kv 30

31 Project constructed at 345 or 500 kv 31

32

33 Arizona Public Service El Paso Electric Imperial Irrigation District NV Energy Public Service Company of New Mexico Salt River Project Southwest Transmission Cooperative Tucson Electric Power Company Tri-State Generation & Transmission Western Area Power Administration Desert Southwest

34 Ten year plans are under development Project names, dates, and routes are still subject to change from information presented today Only high-level summary information is presented. Please contact utilities directly for more information

35 35

36 36 SWAT Transmission Projects Updated 9/14/11 Transmission MW Proposed Proposed Type of SWAT Project Name NOTES # ckts Voltage Capacity Length in-service Status Construction ubcommittesponsor ON Line (One Nevada Transmission Line)-Stage I 1 500kV in construction NC SSPG/EVSG NV Energy/ SWIP/ON Line-Stage II (Southwest Intertie Project) 1 500kV in development NC EVSG NV Energy/ West Side Tie 1 500kV in permitting NC SSPG/EVSG NV Energy NV Energy Self Build Robinson - Harry Allen 500 kv Line 1 500kV permitted NC EVSG NV Energy RTI Westside Tie 345 kv (Armagosa-Esmeralda-Tracy) 1 345kV In permitting NC SSPG NV Energy TCP Amargosa-Black Hawk REMOVE - DUPLICATION OF "WEST SIDE TIE" 1 500kV In permitting NC SSPG NV Energy RTI Zone 4 to Harry Allen 1 500kV In permitting NC EVSG NV Energy Bighorn-Eldorado 1 500kV In permitting NC EVSG NV Energy TCP (Transmission Corridor Project, Northwest - Amargosa Collector Sub) 1 500kV In permitting NC EVSG NV Energy TCP (Transmission Corridor Project, Northwest - Harry Allen) 1 500kV In permitting NC EVSG NV Energy TCP (Transmission Corridor Project, Harry Allen - Eldorado) 1 500kV In permitting NC EVSG NV Energy

37 NVE Request to WECC Planning Coordination Committee and Technical Studies Subcommittee 1) Cancel and remove from the three Phase Rating Process the ON Line rating (currently in Phase II) submitted by NV Energy 2) Initiate a new expedited review process and create a PCRG for the purpose of modifying the existing Path # 81 ( Centennial ) rating to comprise the existing southern Nevada interface between NVES and the Eldorado Valley.

38 NW (BPA) ID-NW (#14) COI (#66) CA (PG&E) PGE-SPP (#24) ALTURAS (#76) SPPC ID-SPP (#16) IN/PAV- GON (#32) ID (IPC) UTAH (PAC) C (#20) MDW- LBNS (#15) ON Line NPC RB-HA (#35) Cry-HA (#77) TOT 2B (#78/79) CENT/S. CUTPLANE CA/AZ (SCE/LA/WAPA/APS) Figure 1: ON Line versus major WECC Paths 38

39 Requires transmission planning at the regional level to consider and evaluate possible transmission alternatives and produce a regional plan Requires the cost of transmission solutions chosen to meet regional transmission needs to be allocated fairly to beneficiaries. 39

40 Public utility transmission providers are required to participate in a regional transmission planning process that satisfies Order No. 890 principles and produces a regional transmission plan. Local and regional transmission planning processes must consider transmission needs driven by public policy requirements established by state or federal laws or regulations. Public utility transmission providers in each pair of neighboring transmission planning regions must coordinate to determine if more efficient or cost effective solutions are available. 40

41 Each transmission planning region must produce a regional transmission plan reflecting solutions that meet the region s needs more efficiently or cost effectively. Stakeholders must have an opportunity to participate in identifying and evaluating potential solutions to regional needs. 41

42 Regional transmission planning process must have a regional cost allocation method for a new transmission facility selected in the regional transmission plan for purposes of cost allocation. Cost allocation method must satisfy six cost allocation principles. Neighboring transmission planning regions must have a common interregional cost allocation method for a new interregional transmission facility that the regions select. Cost allocation method must satisfy six similar interregional cost allocation principles. 42

43 Participant funding of new transmission facilities is permitted, but is not allowed as the regional or interregional cost allocation method. 43

44 Cost allocation method must meet six principles (PP ) : Costs allocated roughly commensurate with benefits No involuntary cost allocation to non-beneficiaries If benefit-cost ratio is used, must not be so high to exclude facilities with significant net benefits (can t exceed unless FERC approves higher ratio) Costs allocated solely within region or regions unless those outside voluntarily assume costs Method and data requirements must be transparent Different method may be chosen for different types of facilities ( e.g., reliability, congestion relief, public policy) 44

45 Bottoms up-top down process. The bottoms-up incorporates a roll-up of local TO plan (local projects) and a WestConnect reliability assessment of TO plans. The bottoms-up would be in combination with a top-down approach which utilizes the WECC TEPPC scenario analysis and incorporating a WestConnect verification and project-by-project analysis based on the WECC Board approved TEPPC results to identify regional efficient and cost effective solutions. 45

46 Calculation of reliability benefits will be based on required compliance with NERC TPL transmission planning standards. If a system is compliant with NERC TPL standards during the 10 year planning horizon they will not be allocated costs for reliability improvements. Individual TOs have the ultimate responsibility to ensure the reliability of their systems. Local plans submitted by each TO should be compliant with NERC TPL standards. Therefore, the local TO will have the ability to approve or deny changes to local reliability projects. If a TO agrees to replace a local project with a regional project that is more efficient and cost effective calculation of benefits and allocation of costs will be based on the cost of alternatives to comply with the standards. 46

47 Calculation of Economic Benefits will be based on regional production cost savings. Hurdle rate should be calculated to ensure that, on a bilateral basis, the transactions modeled are likely to occur (including transmission rates, losses, and an adequate margin). Production cost analysis will need to calculate benefits for each company. WestConnect will establish a B/C ratio of 1.25 for a project to be considered economically-justified and receive cost allocation. Cost of economic projects will be allocated based on the benefits that each Company receives. 47

48 Public Policy Requirements will be included in the evaluation of reliability and economic projects, if applicable. Legislated Public Policy Requirements shall be included in the system models used for the transmission system studies. The impact of potential future public policy requirements may be evaluated through scenario analysis. The costs of projects required to satisfy the public policy requirements shall be allocated to the entities that will access the resources enabled by the project in order to meet their public policy requirements 48

49 In developing the most efficient plan for the region, it is possible for the plan to jointly consider different types of benefits when approving projects for inclusion in the regional plan. A transmission system addition may result in multiply categories of benefits; Reliability & Economic Benefits, Reliability & Public Policy Benefits, Economic & Public Policy Benefits or Reliability, Economic & Public Policy Benefits. Under the WestConnect cost allocation procedure all categories of benefits shall be considered. The total project benefit shall be the sum of the benefits from each benefit category. 49

50 Customer and Stakeholder Input on Transmission Study Plan Customer and Stakeholder Proposals for Transmission Study Plan Customer and Stakeholder Planned Projects 50

51 51

52 52

NTTG REGIONAL TRANSMISSION PLAN. December 30, 2015

NTTG REGIONAL TRANSMISSION PLAN. December 30, 2015 NTTG 2014-2015 REGIONAL TRANSMISSION PLAN December 30, 2015 1 Table of Contents Executive Summary... 3 Introduction... 3 The Northern Tier Transmission Group... 3 Participating Utilities... 4 Purpose of

More information

4.1 Transmission Owners that maintain the transmission paths in Attachment B.

4.1 Transmission Owners that maintain the transmission paths in Attachment B. A. Introduction 1. Title: Transmission Maintenance 2. Number: FAC-501-WECC-2 3. Purpose: To ensure the Transmission Owner of a transmission path identified in Attachment B, Major WECC Transfer Paths in

More information

Transmission Planning Attachment K Public Input Meeting FERC 890, Biennial Cycle 3rd Quarter Meeting

Transmission Planning Attachment K Public Input Meeting FERC 890, Biennial Cycle 3rd Quarter Meeting Transmission Planning Attachment K Public Input Meeting FERC 890, 2010-11 Biennial Cycle 3rd Quarter Meeting October 1, 2010 Agenda Topic Presenter 9:00 9:10 Greetings and Introduction Austin 9:10 9:15

More information

NV Energy, Inc. Operating Companies Open Access Transmission Tariff History of Changes and Filings

NV Energy, Inc. Operating Companies Open Access Transmission Tariff History of Changes and Filings 2/1/2010 Name Change Filing Cover Sheet none ER10-710-000 3/31/2010 3/3/2010 This is a housekeeping filing to change the name of the OATT from the Sierra Pacific 172,195,206C,227, Resources Operating Companies

More information

FERC Order 890 APS Attachment E SRP Attachment K

FERC Order 890 APS Attachment E SRP Attachment K APS/SRP 2 nd Quarter Stakeholder FERC Order 890 APS Attachment E SRP Attachment K APS Deer Valley Facility Phoenix, Arizona June 14, 2018 9 AM -12 PM Agenda 1. Welcome, Introductions, and Stakeholder Meeting

More information

ITP Evaluation Process Plan

ITP Evaluation Process Plan ITP Evaluation Process Plan HVDC Conversion Project The goal of the coordinated Interregional Transmission Project (ITP) evaluation process is to achieve consistent planning assumptions and technical data

More information

1st Qua u r a ter e M e M e e t e in i g 2nd Qua u r a ter e M e M e e t e in i g

1st Qua u r a ter e M e M e e t e in i g 2nd Qua u r a ter e M e M e e t e in i g 2012 SERTP Welcome SERTP 2012 First RPSG Meeting & Interactive Training Session 1 2012 SERTP The SERTP process is a transmission planning process. Please contact the respective transmission provider for

More information

SPP New Member Communication and Integration Process. Mountain West Transmission Group. Background Information October 2017

SPP New Member Communication and Integration Process. Mountain West Transmission Group. Background Information October 2017 1 SPP New Member Communication and Integration Process Mountain West Transmission Group Background Information October 2017 Contents Introduction... 2 1. Westside Tariff Design... 2 2. Operational Provisions...

More information

APS/SRP Stakeholder Meeting For Transmission Planning

APS/SRP Stakeholder Meeting For Transmission Planning APS/SRP Stakeholder Meeting For Transmission Planning FERC Order 890 SRP Attachment K APS Attachment E SRP Facility Scottsdale, AZ December 15 th, 2017 9:00 11:00 A.M. Agenda 1. Welcome, Introductions,

More information

Stakeholder Comment Matrix Harry Allen-Eldorado 500 kv line project December 12, 2014

Stakeholder Comment Matrix Harry Allen-Eldorado 500 kv line project December 12, 2014 The ISO received comments on the CAISO economic analysis results stakeholder meeting discussion held on November 20, 2014 1 from the following: 1. Bay Area Municipal Transmission group (BAMx) 2. California

More information

APS/SRP Stakeholder Meeting For Transmission Planning

APS/SRP Stakeholder Meeting For Transmission Planning APS/SRP Stakeholder Meeting For Transmission Planning FERC Order 890 SRP Attachment K APS Attachment E SRP Facility Scottsdale, AZ December 15 th, 2017 9:00 11:00 A.M. Agenda 1. Welcome, Introductions,

More information

FORM 10-K SIERRA PACIFIC RESOURCES /NV/ - SRP. Exhibit: Filed: March 16, 2005 (period: December 31, 2004)

FORM 10-K SIERRA PACIFIC RESOURCES /NV/ - SRP. Exhibit: Filed: March 16, 2005 (period: December 31, 2004) FORM 10-K SIERRA PACIFIC RESOURCES /NV/ - SRP Exhibit: Filed: March 16, 2005 (period: December 31, 2004) Annual report which provides a comprehensive overview of the company for the past year PART I 3

More information

WECC Standard PRC-STD Protective Relay and Remedial Action Scheme Misoperation

WECC Standard PRC-STD Protective Relay and Remedial Action Scheme Misoperation A. Introduction 1. Title: Protective Relay and Remedial Action Scheme 2. Number: PRC-STD-003-1 3. Purpose: Regional Reliability Standard to ensure all transmission and generation Protection System s affecting

More information

Project Coordination and Path Rating

Project Coordination and Path Rating Document name Category Project Coordination, Path Rating and Progress Report Processes ( ) Regional Reliability Standard ( ) Regional Criteria ( ) Policy (X) Guideline ( ) Report or other ( ) Charter Document

More information

MISO Planning Process. May 31, 2013

MISO Planning Process. May 31, 2013 MISO Planning Process May 31, 2013 MISO Planning Objectives Fundamental Goal The development of a comprehensive expansion plan that meets reliability needs, policy needs, and economic needs MISO Board

More information

NV Energy, Inc. Operating Companies Open Access Transmission Tariff History of OATT Changes and Filings

NV Energy, Inc. Operating Companies Open Access Transmission Tariff History of OATT Changes and Filings Early 2014 NAESB-WEQ Standards for Section 4.2 RM05-5-022 The Notice of Proposed Rulemaking in this docket was issued on July 18, 2013. Approximate Business Practices and Communication Comments have been

More information

Order No Transmission Planning and Cost Allocation

Order No Transmission Planning and Cost Allocation Order No. 1000 Transmission Planning and Cost Allocation Thursday, August 18, 2011, 1:00 pm Eastern Panelists: John D. McGrane, Floyd L. Norton, IV, Stephen M. Spina www.morganlewis.com Overview Order

More information

2003 Annual Report on Market Issues and Performance

2003 Annual Report on Market Issues and Performance 2003 Annual Report on Market Issues and Performance Board of Governors Meeting April 22, 2004 Greg Cook Manager of Market Monitoring Issues in 2003-04 CALIFORNIA ISO and FERC: Continue to work through

More information

BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION SOUTHWESTERN PUBLIC SERVICE COMPANY S UNOPPOSED RESPONSE TO STAFF S COMMENTS

BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION SOUTHWESTERN PUBLIC SERVICE COMPANY S UNOPPOSED RESPONSE TO STAFF S COMMENTS BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION IN THE MATTER OF SOUTHWESTERN ) PUBLIC SERVICE COMPANY S 2018 ) INTEGRATED RESOURCE PLAN FOR ) NEW MEXICO. ) CASE NO. 18-00215-UT ) SOUTHWESTERN PUBLIC

More information

transmission system. This project is referred to in the Transition Agreement as the Transmission Interconnection.

transmission system. This project is referred to in the Transition Agreement as the Transmission Interconnection. 2 Application of Valley Electric Association, Inc. to the California Independent System Operator Corporation to Become a Participating Transmission Owner June 21, 2012 Valley Electric Association, Inc.

More information

SPP s Regional Review of SPP-MISO Coordinated System Plan Recommended Interregional Projects

SPP s Regional Review of SPP-MISO Coordinated System Plan Recommended Interregional Projects SPP s Regional Review of SPP-MISO Coordinated System Plan Recommended Interregional Projects January 4, 2016 SPP Interregional Relations Table of Contents Executive Summary... 2 Introduction... 5 Stakeholder

More information

Lower Voltage Interregional Economic Projects. RECBWG April 18, 2018

Lower Voltage Interregional Economic Projects. RECBWG April 18, 2018 Lower Voltage Interregional Economic Projects RECBWG April 18, 2018 Interregional Gaps & Inconsistencies 1. No tariff defined cost allocation for sub 345 kv economic projects with PJM 2. Economic projects

More information

TRANSMISSION OWNER ZONAL PLACEMENT PROCESS

TRANSMISSION OWNER ZONAL PLACEMENT PROCESS TRANSMISSION OWNER ZONAL PLACEMENT PROCESS Published July 2017 CONTENTS Section 1: Introduction, Scope & Steps... 1 Subsection A: Introduction To Zonal Placement... 1 Subsection B: Scope... 1 Subsection

More information

SOUTHERN CALIFORNIA EDISON COMPANY TRANSMISSION OWNER TARIFF

SOUTHERN CALIFORNIA EDISON COMPANY TRANSMISSION OWNER TARIFF Southern California Edison Company FERC Electric Tariff, Second Revised Volume No. 6 Title Page SOUTHERN CALIFORNIA EDISON COMPANY TRANSMISSION OWNER TARIFF Issued on: December 23, 2002 Effective: January

More information

2011 IRP Public Input Meeting. October 5, Pacific Power Rocky Mountain Power PacifiCorp Energy

2011 IRP Public Input Meeting. October 5, Pacific Power Rocky Mountain Power PacifiCorp Energy 2011 IRP Public Input Meeting October 5, 2010 Pacific Power Rocky Mountain Power PacifiCorp Energy Agenda Morning Session IRP Schedule Update Energy Gateway Transmission Construction Update and Evaluation

More information

COLUMBIAGRID GEOMAGNETIC DISTURBANCE DRAFT STUDY REPORT

COLUMBIAGRID GEOMAGNETIC DISTURBANCE DRAFT STUDY REPORT COLUMBIAGRID GEOMAGNETIC DISTURBANCE DRAFT STUDY REPORT (NERC Standard TPL-007-1) Revision 1 February 1, 2018 ColumbiaGrid 8338 NE Alderwood Road, Suite 140 Portland, OR 97220 www.columbiagrid.org (503)

More information

NTTG Quarter 4 Stakeholder Meeting. Salt Lake City, Utah December 13, 2016

NTTG Quarter 4 Stakeholder Meeting. Salt Lake City, Utah December 13, 2016 NTTG Quarter 4 Stakeholder Meeting Salt Lake City, Utah December 13, 2016 NTTG 2016-2017 Planning Cycle 2016 2017 2 NTTG Draft Regional Transmission Plan Development 3 NTTG Q4 Stakeholder Meeting Agenda

More information

December 23, By etariff Filing Hon. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426

December 23, By etariff Filing Hon. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426 December 23, 2014 By etariff Filing Hon. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426 Re: Nevada Power Company and Sierra Pacific Power Company,

More information

Western Interconnection Unscheduled Flow Mitigation Plan, (WIUFMP)

Western Interconnection Unscheduled Flow Mitigation Plan, (WIUFMP) Western Interconnection Unscheduled Flow Mitigation Plan, (WIUFMP) Purpose: The purpose of the Western Interconnection Unscheduled Flow Mitigation Plan (WIUFMP) is to mitigate flows on Qualified Paths

More information

January 17, via etariff

January 17, via etariff CLIFFORD S. SIKORA 202.274.2950 telephone Clifford.Sikora@troutmansanders.com TROUTMAN SANDERS LLP Attorneys at Law 401 9th Street, N. W., Suite 1000 Washington, D.C. 20004-2134 202.274.2950 telephone

More information

Southern California Edison Company s Testimony on Tehachapi Renewable Transmission Project (TRTP)

Southern California Edison Company s Testimony on Tehachapi Renewable Transmission Project (TRTP) Application Nos.: Exhibit No.: Witnesses James A. Cuillier Gary L. Allen (U -E) Southern California Edison Company s Testimony on Tehachapi Renewable Transmission Project (TRTP) Cost Recovery And Renewable

More information

October 30, 2014 VIA ELECTRONIC FILING

October 30, 2014 VIA ELECTRONIC FILING October 30, 2014 VIA ELECTRONIC FILING Ms. Erica Hamilton, Commission Secretary British Columbia Utilities Commission Box 250, 900 Howe Street Sixth Floor Vancouver, B.C. V6Z 2N3 RE: North American Electric

More information

Regional Planning Coordination Group (RPCG) 2024 Common Case Transmission Assumptions (CCTA) June 2, 2014 FINAL

Regional Planning Coordination Group (RPCG) 2024 Common Case Transmission Assumptions (CCTA) June 2, 2014 FINAL Regional Planning Coordination Group (RPCG) 2024 Common Case Transmission Assumptions (CCTA) June 2, 2014 FINAL Executive Summary The Regional Planning Coordination Group (RPCG) aids the Regional Transmission

More information

WestConnect Planning Management Committee (PMC) LADWP Offices Los Angeles, CA July 20, 2016

WestConnect Planning Management Committee (PMC) LADWP Offices Los Angeles, CA July 20, 2016 WestConnect Planning Management Committee (PMC) LADWP Offices Los Angeles, CA July 20, 2016 1 Welcome & Introductions Blane Taylor, PMC Chair, Tri-State G&T 2 Antitrust Statement Reminder Blane Taylor,

More information

Western Area Power Administration-Rocky Mountain Region

Western Area Power Administration-Rocky Mountain Region Western Area Power Administration-Rocky Mountain Region Revision Date CURRENT BUSINESS PRACTICES Effective Date: October 1, 2017 Business Practices Revision Table (Changes to the business rules for this

More information

APPENDIX B: WHOLESALE AND RETAIL PRICE FORECAST

APPENDIX B: WHOLESALE AND RETAIL PRICE FORECAST Seventh Northwest Conservation and Electric Power Plan APPENDIX B: WHOLESALE AND RETAIL PRICE FORECAST Contents Introduction... 3 Key Findings... 3 Background... 5 Methodology... 7 Inputs and Assumptions...

More information

Transmission Transitions: Potential Cost Savings Offered by Competitive Planning

Transmission Transitions: Potential Cost Savings Offered by Competitive Planning Transmission Transitions: Potential Cost Savings Offered by Competitive Planning Discussion Paper PRESENTED AT NRRI Webinar PREPARED BY Johannes Pfeifenberger Judy Chang Akarsh Sheilendranath PREPARED

More information

BHP 2019 Projected Net Revenue Requirement Meeting. October 18, :00 PM MDT Black Hills Energy 7001 Mt Rushmore Rd Rapid City, SD 57702

BHP 2019 Projected Net Revenue Requirement Meeting. October 18, :00 PM MDT Black Hills Energy 7001 Mt Rushmore Rd Rapid City, SD 57702 BHP 2019 Projected Net Revenue Requirement Meeting October 18, 2018 2:00 PM MDT Black Hills Energy 7001 Mt Rushmore Rd Rapid City, SD 57702 Agenda Introductions CUS Transmission System Overview Black Hills

More information

WECC Guideline: UNSCHEDULED FLOW REDUCTION GUIDELINE

WECC Guideline: UNSCHEDULED FLOW REDUCTION GUIDELINE The content of this document is an excerpt of the WECC Unscheduled Flow Mitigation Plan Document posted on www.wecc.biz. Introduction WECC : UNSCHEDULED FLOW REDUCTION GUIDELINE The combination of Scheduled

More information

Memorandum. This memorandum does not require Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum does not require Board action. EXECUTIVE SUMMARY California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Eric Hildebrandt, Executive Director, Market Monitoring Date: November 7, 2018 Re: Department of Market Monitoring

More information

Northern Tier Transmission Group Cost Allocation Principles Work Group. Straw Proposal. May 29, 2007

Northern Tier Transmission Group Cost Allocation Principles Work Group. Straw Proposal. May 29, 2007 Northern Tier Transmission Group Cost Allocation Principles Work Group Straw Proposal May 29, 2007 NTTG Cost Allocation Principles and Process page 1 INTRODUCTION This paper makes a strawman proposal responsive

More information

10-day Formal Comment Period with a 5-day Additional Ballot (if necessary), pursuant to a Standards Committee authorized waiver.

10-day Formal Comment Period with a 5-day Additional Ballot (if necessary), pursuant to a Standards Committee authorized waiver. Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

Bank of America Energy & Power Conference November 16, 2004

Bank of America Energy & Power Conference November 16, 2004 Bank of America Energy & Power Conference November 16, 2004 Forward-Looking Statements This document may contain forward-looking statements within the meaning of the safe harbor of the Private Securities

More information

Transmission Planning Process and Study Methodology John Lucas. Transmission Planning & Engineering Department Leader

Transmission Planning Process and Study Methodology John Lucas. Transmission Planning & Engineering Department Leader Transmission Planning Process and Study Methodology John Lucas Transmission Planning & Engineering Department Leader Phoenix, May4. 2009 Planning - Calendar & Methodology WECC/TEPPC WestConnect Planning

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Transmission Planning and Cost Allocation ) by Transmission Owning and Operating ) Docket No. RM10-23- 000 Public Utilities ) Comments

More information

45-day Comment and Initial Ballot day Final Ballot. April, BOT Adoption. May, 2015

45-day Comment and Initial Ballot day Final Ballot. April, BOT Adoption. May, 2015 Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

April 6, 2018 VIA OVERNIGHT MAIL. Sheri Young, Secretary of the Board National Energy Board th Avenue SW Calgary, Alberta T2R 0A8

April 6, 2018 VIA OVERNIGHT MAIL. Sheri Young, Secretary of the Board National Energy Board th Avenue SW Calgary, Alberta T2R 0A8 !! April 6, 2018 VIA OVERNIGHT MAIL Sheri Young, Secretary of the Board National Energy Board 517 10 th Avenue SW Calgary, Alberta T2R 0A8 Re: North American Electric Reliability Corporation Dear Ms. Young:

More information

Ian McKay Chair Transmission Expansion Planning and Policy Committee (204)

Ian McKay Chair Transmission Expansion Planning and Policy Committee (204) Date: December 23, 2015 Ian McKay Chair Transmission Expansion Planning and Policy Committee (204) 430-1950 i.mckay@shaw.ca To: Subject: Reliability Planning Stakeholders 2016 TEPPC Study Program Open

More information

WestConnect Planning. Tri-State Offices Westminster, CO April 20, 2016

WestConnect Planning. Tri-State Offices Westminster, CO April 20, 2016 WestConnect Planning Management Committee (PMC) Tri-State Offices Westminster, CO April 20, 2016 1 Welcome & Introductions Blane Taylor, PMC Chair, TSGT 2 Antitrust Statement Reminder Blane Taylor, PMC

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents Appendix F Rate Schedules... 2 Schedule 1... 2 Grid Management Charge... 2 Part A Monthly Calculation of Grid Management Charge (GMC)... 2 Part B Quarterly Adjustment, If Required...

More information

5 Inter-Zonal Congestion Management Markets

5 Inter-Zonal Congestion Management Markets 5 Inter-Zonal Congestion Management Markets 5.1 Inter-Zonal Congestion Management Congestion occurs when the physical limits of a line, or inter-tie, prohibits load from being served with the least cost

More information

MISO Cost Allocation Response. RECBWG February 15, 2018

MISO Cost Allocation Response. RECBWG February 15, 2018 MISO Cost Allocation Response RECBWG February 15, 2018 MISO Cost Allocation Response: February 2018 Context The overall objective of the MISO transmission cost allocation methodology is to align who pays

More information

REBUTTAL TESTIMONY OF NEIL MILLAR ON BEHALF OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION

REBUTTAL TESTIMONY OF NEIL MILLAR ON BEHALF OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION Application No.: --00 Exhibit No.: Witness: Neil Millar In the Matter of the Application of SOUTHERN CALIFORNIA EDISON COMPANY (UE) for a Certificate of Public Convenience and Necessity for the West of

More information

Mountain West Transmission Group (MWTG) Introduction and Process

Mountain West Transmission Group (MWTG) Introduction and Process Mountain West Transmission Group (MWTG) Introduction and Process October 13 Denver, CO October 16 Little Rock, AR 2 Agenda Overview of SPP Overview of the MWTG Members SPP Process New Member Integration

More information

10-YEAR COSTS AND BENEFITS TO SPP MEMBERS OF INTEGRATING MOUNTAIN WEST TRANSMISSION GROUP Quantitative Analysis of Costs and Benefits

10-YEAR COSTS AND BENEFITS TO SPP MEMBERS OF INTEGRATING MOUNTAIN WEST TRANSMISSION GROUP Quantitative Analysis of Costs and Benefits 10-YEAR COSTS AND BENEFITS TO SPP MEMBERS OF INTEGRATING MOUNTAIN WEST TRANSMISSION GROUP Quantitative Analysis of Costs and Benefits Published on March 19, 2018 By SPP Staff REVISION HISTORY DATE OR VERSION

More information

APS/SRP Stakeholder Meeting For Transmission Planning FERC Order 890 OATT Attachment K (APS Attachment E)

APS/SRP Stakeholder Meeting For Transmission Planning FERC Order 890 OATT Attachment K (APS Attachment E) APS/SRP Stakeholder Meeting For Transmission Planning FERC Order 890 OATT Attachment K (APS Attachment E) APS Transmission Planning SRP Transmission Planning Phoenix, Arizona Agenda 1. Welcome, Introductions,

More information

153 FERC 61,249 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER REJECTING TARIFF REVISIONS. (Issued November 30, 2015)

153 FERC 61,249 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER REJECTING TARIFF REVISIONS. (Issued November 30, 2015) 153 FERC 61,249 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Norman C. Bay, Chairman; Cheryl A. LaFleur, Tony Clark, and Colette D. Honorable. Southwest Power Pool,

More information

,QWHU]RQDO&RQJHVWLRQ0DQDJHPHQW

,QWHU]RQDO&RQJHVWLRQ0DQDJHPHQW ,QWHU]RQDO&RQJHVWLRQ0DQDJHPHQW 0DUNHW Ã 6XPPDU\ÃRIÃÃ,QWHU]RQDOÃ&RQJHVWLRQÃ0DQDJHPHQWÃ 0DUNHWÃ 5.1.1 Overview Under the current zonal model, the CAISO manages congestion in the forward market only on major

More information

Procedure for ERO Support of Frequency Response and Frequency Bias Setting Standard

Procedure for ERO Support of Frequency Response and Frequency Bias Setting Standard Procedure for ERO Support of Frequency Response and Frequency Bias Setting Standard NERC Report Title Report Date I Table of Contents Preface... iii Introduction...iiv Chapter 1: Event Selection Process...

More information

SPP REPORT ON TLR EVENTS FROM FEBRUARY 13 MARCH 4, 2002

SPP REPORT ON TLR EVENTS FROM FEBRUARY 13 MARCH 4, 2002 SPP REPORT ON TLR EVENTS FROM FEBRUARY 13 MARCH 4, 2002 On seven occasions between February 13 and March 4, 2002, SPP initiated a TLR on the MorStiSooNor flow gate, #5067, that included firm service curtailments.

More information

PACIFIC GAS AND ELECTRIC COMPANY. TRANSMISSION OWNER TARIFF Sixth Revised Volume 5

PACIFIC GAS AND ELECTRIC COMPANY. TRANSMISSION OWNER TARIFF Sixth Revised Volume 5 TRANSMISSION OWNER TARIFF Sixth Revised Volume 5 First Revised Sheet No. 1 Superseding Original Sheet No. 1 TABLE OF CONTENTS 1. PREAMBLE.... 4 1.1 Transmission Access for Self-Sufficient Participating

More information

EIPC Roll-Up Report & Scenarios

EIPC Roll-Up Report & Scenarios EIPC Roll-Up Report & Scenarios Zach Smith Director, Transmission Planning New York Independent System Operator IPTF/EGCWG/ESPWG Meeting January 6, 2014 2013 New York Independent System Operator, Inc.

More information

WECC Criterion TPL-001-WECC-CRT-3.1

WECC Criterion TPL-001-WECC-CRT-3.1 WECC Criterion TPL-001-WECC-CRT-3.1 A. Introduction 1. Title: Transmission System Planning Performance 2. Number: TPL-001-WECC-CRT-3.1 3. Purpose: To facilitate coordinated near-term and long-term transmission

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Docket No. ER

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Docket No. ER UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PacifiCorp Docket No. ER16-193-000 MOTION TO INTERVENE AND COMMENTS OF THE WESTERN POWER TRADING FORUM Pursuant to Rules 211, 212

More information

Southwest Power Pool, Inc. Policy Recommendation for the SPP Board of Directors and Members Committee. March 6, 2018 Mountain West Transmission Group

Southwest Power Pool, Inc. Policy Recommendation for the SPP Board of Directors and Members Committee. March 6, 2018 Mountain West Transmission Group Southwest Power Pool, Inc. Policy for the SPP Board of Directors and Members Committee Policy Area #1 DC Ties March 6, 2018 Mountain West Transmission Group SPP and MWTG anticipate that incorporating the

More information

132 FERC 61,067 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

132 FERC 61,067 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 132 FERC 61,067 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Jon Wellinghoff, Chairman; Marc Spitzer, Philip D. Moeller, John R. Norris, and Cheryl A. LaFleur. California

More information

Stakeholder Meeting for GridLiance West LLC 2019 Annual Formula Rate Projection. November 7, :00pm CST

Stakeholder Meeting for GridLiance West LLC 2019 Annual Formula Rate Projection. November 7, :00pm CST Stakeholder Meeting for GridLiance West LLC 2019 Annual Formula Rate Projection November 7, 2018 2:00pm CST Agenda Introduction GridLiance West LLC (GridLiance) Background Transmission Formula Rate Template

More information

Title Page Southern California Edison Company Tariff Title: Transmission Owners Tariff Tariff Record Title: First Revised Service Agreement No. 39 FER

Title Page Southern California Edison Company Tariff Title: Transmission Owners Tariff Tariff Record Title: First Revised Service Agreement No. 39 FER Title Page Southern California Edison Company Tariff Title: Transmission Owners Tariff Tariff Record Title: First Revised Service Agreement No. 39 FERC FPA Electric Tariff INTERCONNECTION FACILITIES AGREEMENT

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Keith Casey, Vice President, Market & Infrastructure Development Date: March 14, 2018 Re: Decision on congestion

More information

Information Document Available Transfer Capability and Transfer Path Management ID # R

Information Document Available Transfer Capability and Transfer Path Management ID # R Information Documents are not authoritative. Information Documents are for information purposes only and are intended to provide guidance. In the event of any discrepancy between an Information Document

More information

BES Definition Implementation Guidance

BES Definition Implementation Guidance BES Definition Implementation Guidance August 25, 2014 3353 Peachtree Road NE Suite 600, North Tower Atlanta, GA 30326 NERC BES Definition Implementation Guidance June 23, 2014 404-446-2560 www.nerc.com

More information

TUCSON ELECTRIC POWER COMPANY. Transmission Reliability Margin Implementation Document (TRMID)

TUCSON ELECTRIC POWER COMPANY. Transmission Reliability Margin Implementation Document (TRMID) A UniSource Energy Company TUCSON ELECTRIC POWER COMPANY Transmission Reliability Margin Implementation Document (TRMID) Approved by: Effective Date: /c Version 1 Based on North American Electric Reliability

More information

Southwest Power Pool s Balanced Portfolio Approach for Economic Upgrades

Southwest Power Pool s Balanced Portfolio Approach for Economic Upgrades Southwest Power Pool s Balanced Portfolio Approach for Economic Upgrades Presentation by Michael Proctor Chief Economist, Missouri PSC Harvard Electricity Policy Group Chicago, Illinois October 2, 2008

More information

New Member Cost Allocation Review Process. Prepared by: COST ALLOCATION WORKING GROUP

New Member Cost Allocation Review Process. Prepared by: COST ALLOCATION WORKING GROUP New Member Cost Allocation Review Process Prepared by: COST ALLOCATION WORKING GROUP TABLE OF CONTENTS 1. HISTORY AND BACKGROUND... 1 2. PURPOSE / GOAL STATEMENT... 3 3. OVERVIEW OF PROCESS... 3 4. NEW

More information

Impacts of RTO Market Expansion Joint Action

Impacts of RTO Market Expansion Joint Action N O R T H E R N C A L I F O R N I A P O W E R A G E N C Y Impacts of RTO Market Expansion Joint Action Randy S. Howard January 7, 2019 NCPA Overview California joint powers agency founded in 1968 16 members

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Pacific Gas and Electric Company ) Docket No.

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Pacific Gas and Electric Company ) Docket No. UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Pacific Gas and Electric Company ) Docket No. EL16-47-000 REQUEST FOR REHEARING OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR The

More information

The following Information Requests pertain to the spreadsheet file Attachment_H- 1_Formula_Rate_2015_-Run_1_posted_ _(effective_ ) :

The following Information Requests pertain to the spreadsheet file Attachment_H- 1_Formula_Rate_2015_-Run_1_posted_ _(effective_ ) : TGST 1-1: Refer to PNM S 2014 FERC Form 1 page 207, line 50, Account 353 Station Equipment, please provide a description of significant projects ($5 million or more) contributing to the increase of approximately

More information

Economic Benefit Analysis of the Navajo Generating Station to the Central Arizona Water Conservation District and Its Customers

Economic Benefit Analysis of the Navajo Generating Station to the Central Arizona Water Conservation District and Its Customers ENERGY VENTURES ANALYSIS JANUARY 2018 Economic Benefit Analysis of the Navajo Generating Station to the Central Arizona Water Conservation District and Its Customers January 2018 Prepared by: ENERGY VENTURES

More information

MISO PJM IPSAC. December 2, Revised December 22, PJM IPSAC Meeting, December 2,

MISO PJM IPSAC. December 2, Revised December 22, PJM IPSAC Meeting, December 2, MISO PJM IPSAC December 2, 2016 Revised December 22, 2016 1 Agenda 2 TMEP Final JOA Language Recommended TMEPs Order No. 1000 Compliance Filing Generation Deactivation JOA Language PJM Proposal Window

More information

Cost Allocation Reform Update

Cost Allocation Reform Update Cost Allocation Reform Update Regional Expansion Criteria and Benefits Working Group May 18, 2017 Conditions Precedent for Regional Transmission Investment 1. Increased consensus regarding the issue(s)

More information

156 FERC 61,118 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER ON PETITION FOR DECLARATORY ORDER. (Issued August 19, 2016)

156 FERC 61,118 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER ON PETITION FOR DECLARATORY ORDER. (Issued August 19, 2016) 156 FERC 61,118 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Norman C. Bay, Chairman; Cheryl A. LaFleur, Tony Clark, and Colette D. Honorable. DesertLink, LLC Docket

More information

2018 Business Plan and Budget Supplemental Information May 1, 2017

2018 Business Plan and Budget Supplemental Information May 1, 2017 2018 Business Plan and Budget Supplemental Information May 1, 2017 Today we posted our 2018 Business Plan and Budget (BP&B) for stakeholder comment. WECC staff had productive dialogue with the members

More information

FERC Order 1000: Transmission Planning & Cost Allocation Framework for NYISO Compliance

FERC Order 1000: Transmission Planning & Cost Allocation Framework for NYISO Compliance FERC Order 1000: Transmission Planning & Cost Allocation Framework for NYISO Compliance by John P Buechler NYISO Executive Regulatory Policy Advisor Joint IPTF/ESPWG Meeting February 27, 2012 Albany, NY

More information

Rate Schedules and Seams Agreements Tariff

Rate Schedules and Seams Agreements Tariff Rate Schedules and Seams Agreements Tariff Southwest Power Pool Rate Schedules and Seams Agreements Tariff Document Generated On: 8/20/2015 Southwest Power Pool - Rate Schedules and Seams Agreements Tariff

More information

PacifiCorp Transmission Rate Case

PacifiCorp Transmission Rate Case PacifiCorp Transmission Rate Case Customer & Stakeholder Meetings Portland, March 10, 2011 & Salt Lake City, March 16, 2011 2000 PACIFICORP PAGE 2 Agenda Welcome and Introduction Purpose of Meeting and

More information

The second effective date allows entities time to comply with Requirements R1, R2, R4, R5, R6, and R7.

The second effective date allows entities time to comply with Requirements R1, R2, R4, R5, R6, and R7. Effective Dates Generator Owners There are two effective dates associated with this standard. The first effective date allows Generator Owners time to develop documented maintenance strategies or procedures

More information

NERC Abbreviated Notice of Penalty regarding Sierra Pacific Power Company, FERC Docket No. NP

NERC Abbreviated Notice of Penalty regarding Sierra Pacific Power Company, FERC Docket No. NP January 31, 2011 Ms. Kimberly Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426 Re: NERC Abbreviated Notice of Penalty regarding Sierra Pacific Power Company,

More information

T-D Interconnections: Best Value Planning White Paper January 2016

T-D Interconnections: Best Value Planning White Paper January 2016 T-D Interconnections: Best Value Planning White Paper Updated January 2016 1. Purpose This paper defines the process and criteria that together constitute joint best value planning (BVP) between ATC and

More information

2015 Modification Assessment Cost and Accounting Report March 1, 2017

2015 Modification Assessment Cost and Accounting Report March 1, 2017 2015 Modification Assessment Cost and Accounting Report March 1, 2017 Prepared by: Raeann Quadro California Independent System Operator Table of Contents 1. Executive Summary 1.1. Purpose and Scope 1.2.

More information

Transmission Solutions: Potential Cost Savings Offered by Competitive Planning Processes

Transmission Solutions: Potential Cost Savings Offered by Competitive Planning Processes Transmission Solutions: Potential Cost Savings Offered by Competitive Planning Processes Discussion Paper PRESENTED TO PREPARED BY Johannes Pfeifenberger Judy Chang Akarsh Sheilendranath PREPARED FOR:

More information

Long-Term Reliability Assessment

Long-Term Reliability Assessment Long-Term Reliability Assessment Key Findings and Long-Term Issues John Moura, Director of Reliability Assessment Topics Covered Today Background on NERC s Long-Term Reliability Assessment Emerging and

More information

California ISO. Q Report on Market Issues and Performance. February 14, Department of Market Monitoring

California ISO. Q Report on Market Issues and Performance. February 14, Department of Market Monitoring California Independent System Operator Corporation California ISO Q4 2017 Report on Market Issues and Performance February 14, 2018 Department of Market Monitoring TABLE OF CONTENTS Executive summary...

More information

NERC TPL Standard Overview

NERC TPL Standard Overview NERC TPL-001-4 Standard Overview Attachment K Quarter 3 Stakeholder s Meeting September 29, 2016 1 Background New NERC TPL Standard 2016 TPL Plan and Status Update 2015 Planning Assessment Results Compliance

More information

Network Loss Factor Methodology

Network Loss Factor Methodology Network Loss Factor Methodology 2011-2012 Date: 28 February 2011 Table of Contents 1. Introduc t ion...1 2. Ba ckground...1 3. Definit ions a nd Abbrev iat ions...2 4. N etwork Energ y L oss es...3 4.1

More information

BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION ) ) ) ) ) ) ) ) ) ) ) DIRECT TESTIMONY WILLIAM A. GRANT. on behalf of

BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION ) ) ) ) ) ) ) ) ) ) ) DIRECT TESTIMONY WILLIAM A. GRANT. on behalf of BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION IN THE MATTER OF SOUTHWESTERN PUBLIC SERVICE COMPANY S APPLICATION FOR REVISION OF ITS RETAIL RATES UNDER ADVICE NOTICE NO., SOUTHWESTERN PUBLIC SERVICE

More information

Supplemental Report on the NCTPC 2006 Collaborative Transmission Plan

Supplemental Report on the NCTPC 2006 Collaborative Transmission Plan Supplemental Report on the NCTPC 2006 Collaborative Transmission Plan 04/26/07 Table of Contents I. Executive Summary...3 II. Introduction...4 III. 1,200 MW Resource Supply Option Study Increased Imports

More information

Roadshow Presentation

Roadshow Presentation Roadshow Presentation April 2010 Tonbridge Power Inc. The Waterpark Place 20 Bay Street, 11 th Floor Toronto, ON t: 416.850.2150 f: 416.850.1985 1 www.tonbridgepower.com Disclaimer This presentation and

More information

AC TRANSMISSION PUBLIC POLICY TRANSMISSION NEEDS PROJECT SOLICITATION Response due April 29, 2016

AC TRANSMISSION PUBLIC POLICY TRANSMISSION NEEDS PROJECT SOLICITATION Response due April 29, 2016 10 Krey Boulevard Rensselaer, NY 12144 AC TRANSMISSION PUBLIC POLICY TRANSMISSION NEEDS PROJECT SOLICITATION Response due April 29, 2016 Dear NYISO Stakeholder or Interested Party: February 29, 2016 With

More information

SPP TLR (TEMPORARY

SPP TLR (TEMPORARY SPP TLR 5 Investigation Report Flowgate 15369 (TEMPORARY 11) Plant X Sundown 230 kv Line for the Loss of Tolk Yoakum 230 kv Line TLR Level 5: February 1, 2009 Report Issued: March 11, 2009 1. Description

More information

Title Page Southern California Edison Company Tariff Title: Rate Schedule Tariff Record Title: Rate Schedule FERC No. 425 FERC FPA Electric Tariff AMENDED AND RESTATED ELDORADO SYSTEM OPERATINGAGREEMENT

More information