1 APS/SRP Stakeholder Meeting For Transmission Planning FERC Order 890 OATT Attachment K (APS Attachment E) APS Transmission Planning SRP Transmission Planning Phoenix, Arizona

2 Agenda 1. Welcome, Introductions, and Meeting Overview 2. Status of Action Items-6/24/10 Joint APS/SRP 4 th Quarter Public Planning Meeting 3. SRP Planning a. SRP Planning Calendar & Methodology b. Proposed SRP Ten-Year Plan c. SRP Transmission Projects for Renewable Generation d. Interconnection Requests and Transmission Service Requests e. Requests Received for Economic Planning Studies f. Stakeholders invited to submit requests for additional transmission studies g. Comments/Questions 4. APS Planning a. APS Planning Calendar & Methodology b. APS Ten-Year Plan and Renewable Transmission Projects Draft c Study Assumptions d. Interconnection Requests and Transmission Service Requests e. Requests received for Economic Planning Studies f. Stakeholders invited to submit requests for additional transmission studies g. Comments/Questions 5. Current Activities Update 6. Stakeholder Questions/Comments 7. Action Items 2

3 Welcome Introductions Meeting Overview 3

4 2. Status of Action Items APS/SRP will try to find a way to provide Joint Participant information in some other way than being part of queues. Ownership information, unless otherwise made public such as though a public filing, belongs to each individual owners: SRP has no right or duty to post such data on the SRP OASIS. Request APS and SRP to explore the possibility of coordinating Stakeholder meetings with Resource meetings. Ongoing 4

5 3.a. SRP Planning Calendar & Methodology WECC/TEPPC/WestConnect Planning Calendar SRP Planning Calendar Planning Process/Methodology 5

6 2010 Synchronized Study Plan WECC PCC / WECC - TEPPC / WESTCONNECT WECC TEPPC Economic Studies Submittal Deadline for 2010 WECC/PCC Annual Study Program Completed Base Cases Preparation For 10yr Plan Deadline for submitting request for 2011 Economic Studies WECC / TEPPC 10yr Plan Study results WECC / TEPPC Economic Studies Submittal Deadline for 2011 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan 10yr Planning studies Filing w/acc BTA study results Even # years 2 nd Qtr Stakeholder Meeting Study Work 10yr plans Subregional SWAT groups Westconnect Group WECC PCC WECC-TEPPC SWAT Study results WestConnect Study results 4 th Qtr Stakeholder Meeting TEPPC Results including Economics studies WestConnect Plan Approved SWAT Study Plans Approved 6

7 Jan. Feb. Mar. Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Planning Calendar for Ten-Year Planning Cycle SRP Transmission Planning 10 Yr Plan 10yr Plan Filed with ACC by Jan. 31 SRP Corporate Load Forecast Develop 10yr base cases from AZ seed cases 10yr. Plan study effort Determination of projects, timings, and scope SRP Corporate Load Forecast Post Summer 10yr. Plan New load forecast sensitivity Stakeholder Input WestConnect Coordinated base case development 10yr. Plans filed by others Arizona Utilities coordinated seed case development from WestConnect cases 2 nd Quarter Stakeholder Meeting Stakeholder input on studies, request study alternatives, updates on current projects Sep. 1 Network Transmission Customers and all other Transmission Customers Load & Resource Forecast Oct. 31 Deadline to submit Economic Study Requests for 4 th Quarter Meeting review 4 th Quarter Stakeholder Meeting Review draft of current 10yr plan, discussion Economic Study requests, receive stakeholder input Other Subregional Coordination Activities Throughout the Year APS/SRP Coordination Meeting SRP/WAPA Coordination Meeting WestConnect Meetings SWAT Meetings o CATS-EHV o CATS-HV o CRT o AZ/NM o SATS o o Renewables Short-circuit Working Group 7

8 Exhibit 1 SRP Attachment K Transmission Planning Process Economic What Type of Study? 1 Reliability Regional Transmission Provider Evaluation Local 2 High priority Transmission Provider Economic Study Not high priority Does Transmission Provider s system meet NERC/WECC criteria? No Transmission Provider determines facilities needed with Stakeholder input Study results documented in a report and reviewed by Customer and Transmission Provider Yes TEPPC evaluates with Stakeholder input Customer Choice of Study at Customer s expense Does Transmission Provider s system meet local reliability criteria? No Transmission Provider determines facilities needed with Stakeholder input TEPPC determines high priority, performs study TEPPC determines not high priority Yes Transmission Provider coordinates with Sub- Regional Planning Group 1. Generator Interconnection Request studies are performed pursuant to the Large Generator Interconnection Procedure contained in the Transmission Provider s Open Access Transmission Tariff (OATT). Transmission Service Requests are also performed pursuant to OATT procedures. 2. All requests for economic planning studies received by the Transmission Provider are forwarded to TEPPC for inclusion in the TEPPC Master List. TEPPC will evaluate only those requests that have regional impacts. 8

9 3.a SRP Planning - Calendar & Methodology Assumptions and Methodology Types of Studies Performed Proposed Ten Year Plan 9

10 3.a Study Assumptions/Methodology Coordinated Base Cases (Seed Cases) NERC Compliance Studies 2013 APS/SRP 2013 coordinated case 2017 APS/SRP 2017 coordinated case BTA Studies 2020 WECC 2020 HS coordinated case 69kV transmission models incorporated Most up-to-date forecasts for peak summer loads 10

11 3.a Study Assumptions/Methodology NERC Compliance Studies Cases 2013 & 2017 Summer Peak & Off-peak Cases 2013 & 2017 Off-peak Cases are Low Load (winter conditions) and High Import (shoulder cases with low generation in the Phoenix Metro Area). Following analysis are conducted: Thermal analysis Post-Transient Transient Stability 11

12 Planning Methodology NERC STANDARD Type of Studies Completed TPL-001 (N-0) Thermal Transient Stability Post-transient 2013 Peak X 2013 Low Load X 2013 High Import X 2017 Peak X 2017 Low Load X 2017 High Import X 2017 All-in X TPL-002 (N-1) Thermal Transient Stability Post-transient 2013 Peak X X X 2013 Low Load X X X 2013 High Import X X X 2017 Peak X X X 2017 Low Load X X X 2017 High Import X X X 12

13 Planning Methodology NERC STANDARD Type of Studies Completed TPL-003 (N-2) Thermal Transient Stability Post-transient 2013 Bus outages X X X 2013 Contingency of towers X X X 2013 Stuck breaker X X X 2013 Common Corridor X X X 2013 N-1-1 X X X 2017 Bus outages X X X 2017 Contingency of towers X X X 2017 Stuck breaker X X X 2017 Common Corridor X X X 2017 N-1-1 X X X TPL-004 (N-X) Thermal Transient Stability Post-transient 2013 Substations with generation X X 2013 Common Corridor/Substation without generation Note: TPL-003 studies were performed on Peak, Low Load & High Import cases X X 13

14 3.b SRP Ten Year Plan Projects Draft 14

15 NAVAJO GS MOENKOPI NORTH GILA (APS) MARKETPLACE McCULLOUGH NEVADA 2014 MEAD DELANY PALO VERDE HASSAYAMPA Sun Valley (APS) PINAL WEST YAVAPAI MORGAN(APS) 2016 RUDD JOJOBA (, place holder for CATS only, no current SRP plans) 2014 WESTWING KYRENE DUGAS (APS) BROWNING SAGUARO SANTA ROSA ABEL CHOLLA (APS) SUGARLOAF (APS) PINNACLE PEAK (APS) RS PINAL CENTRAL 2014 SILVER KING SUNZIA (SPG) 2015 CORONADO Central New Mexico EXISTING 500kV SUBSTATION FUTURE 500kV SUBSTATION EXISTING LINES FUTURE LINES TORTOLITA (TEP) SALT RIVER PROJECT 500kV SYSTEM 15

16 2011: Browning-Pinal Central 500kV (it will be energized as Randolph-Browning 230kV until 2014) 2013: Palo Verde-Delany 500kV 2014: Delany-Sun Valley 500kV Hassayampa-N.Gila 500kV line Pinal West-Pinal Central 500kV Pinal Central 500/230kV substation 2016: Sun Valley-Morgan 500kV 2021: Pinal Central-Abel #2 500kV SALT RIVER PROJECT 500kV SYSTEM 16

17 BRANDOW PINNACLE PEAK THUNDERSTONE GOLDFIELD ROGERS BROWNING SANTAN To CORBELL SALT RIVER PROJECT EASTERN 230kV SYSTEM BALL/RS DINOSAUR To SCHRADER 2019 PFISTER/RS RS21 RS20 LOOP IN TO SILVER KING TO SILVER KING ABEL/RS RS23 DOUBLE CIRCUIT, PHASE TIED LINE EXISTING 230kV CIRCUIT DESERT BASIN 2014 CATSHV PINAL CENTRAL 2014 RANDOLPH SWITCHYARD 2011 FUTURE 230kV CIRCUIT EXISTING 230kV SUBSTATIONS FUTURE 230kV SUBSTATIONS GENERATING STATION 17

18 2011: Dinosaur-Abel-Randolph 230kV 2014: Desert Basin-Pinal Central 230kV line Pinal Central - Randolph 230kV line 2019: Pfister(RS24) 230/69kV substation Abel-Pfister(RS24)-Schrader 230kV Abel-Pfister(RS24)-Santan 230kV SALT RIVER PROJECT EASTERN 230kV SYSTEM 18

19 SALT RIVER PROJECT WESTERN 230kV SYSTEM TO W.A.P.A. PINNACLE PEAK TO APS PINNACLE PEAK WESTWING W.A.P.A. LIBERTY (W.A.P.A.) RUDD W.A.P.A. AGUA FRIA WHITE TANKS ORME DEER VALLEY (APS) ALEXANDER SRP PINNACLE PEAK PAPAGO RS25 BRANDOW TO APS OCOTILLO CORBELL WARD W.A.P.A. ROGERS RS26 THUNDERSTONE SANTAN To GOLDFIELD To BROWNING ANDERSON KYRENE BALL/RS17 DOUBLE CIRCUIT, PHASE TIED LINE KNOX EXISTING 230kV CIRCUIT SCHRADER FUTURE 230kV CIRCUIT To PFISTER/RS24 EXISTING 230kV SUBSTATIONS FUTURE 230kV SUBSTATIONS GENERATING STATION 19

20 MORMON FLAT HORSE MESA ROOSEVELT STEWART MOUNTAIN FRAZIER SILVER KING 230 TO SILVER KING 500kV GOLDFIELD 230kV 115kV (230kV) PINTO VALLEY MIAMI MOONSHINE PINAL TO THUNDERSTONE (230kV) RS20 230kV CARREL (230kV) SPURLOCK SEE DETAIL SUPERIOR CARLOTTA TRASK OAK FLAT KNOLL ELLISON DETAIL RAY MORRIS KEARNY SUPERIOR 230KV SUPERIOR 115KV COOLIDGE (W.A.P.A.) BONNEYBROOK (APS) NEW HAYDEN ASARC0 TO APACHE (AEPCO) HAYDEN FUTURE SUBSTATION EXISTING SUBSTATION GENERATING STATION FUTURE LINE EXISTING LINE SALT RIVER PROJECT EASTERN MINING AREA SYSTEM 20

21 Electric System Additions/Upgrades Equipment Year Abel 1 st 230/69kV transformer 2011 Kyrene 3 rd 500/230kV transformer 2012 Rudd 1 st 230/69kV transformer 2013 Pinal Central 1 st & 2 nd 500/230kV transformers 2014 Schrader 3 rd 230/69kV transformer 2015 Pfister (RS-24) 1 st 230/69kV transformer

22 SRP Changes from 2010 to kV Projects 2015 SunZia Project Delayed from 2013/ Pinal Central Abel #2 Delayed from kV Projects 2019 Pfister(RS24) 230kV Transmission Project Delayed from 2018/2019 RS26 230kV Project Delayed from

23 3.c. SRP Planning Transmission Projects for Renewable Generation Pinal West Pinal Central 500kV line Pinal Central Tortolita 500kV line Palo Verde Delany 500kV line 23

24 24

25 SRP Planning - Study Requests Generation Interconnection Requests Transmission Interconnection Requests Transmission Service Requests Economic Study Requests 25

26 3.d. SRP Planning Study Requests Generation Interconnection Requests listed at the next slide are for SRP solely owned transmission. The generation interconnecting in SRP s queue is: 4 Natural Gas Projects 2011 MW 3 Wind Projects 1200 MW 10 Solar Projects 245 MW 26

27 4 Natural Gas projects MW 2 Wind projects MW The joint The interconnection joint interconnection requests requests are listed are listed on SRP on SRP OASIS OASIS website 27

28 3.d. SRP Planning - Study Requests Currently there are no Transmission Interconnection Requests under study 28

29 3.d. SRP Planning - Study Requests Currently there are no Transmission Service Requests under study 29

30 3.e. SRP Planning - Study Requests Currently there are no Economic Study Requests 30

31 3.f. Stakeholders Requests SRP invites Stakeholders to submit request for additional transmission studies 31

32 3.g. SRP Planning Comments & Questions Stakeholder comments/questions on 2010 Study Results or 2011 Study Requests Requests can be made at any time to: 32

33 4.a. APS Planning Calendar & Methodology WECC/TEPPC/WestConnect Planning Calendar APS Planning Calendar Planning Process/Methodology 33

34 2010 Synchronized Study Plan WECC PCC / WECC - TEPPC / WESTCONNECT WECC TEPPC Economic Studies Submittal Deadline for 2010 WECC/PCC Annual Study Program Completed Base Cases Preparation For 10yr Plan Deadline for submitting request for 2011 Economic Studies WECC / TEPPC 10yr Plan Study results WECC / TEPPC Economic Studies Submittal Deadline for 2011 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan 10yr Planning studies Filing w/acc BTA study results Even # years 2 nd Qtr Stakeholder Meeting Study Work 10yr plans Subregional SWAT groups Westconnect Group WECC PCC WECC-TEPPC SWAT Study results WestConnect Study results 4 th Qtr Stakeholder Meeting TEPPC Results including Economics studies WestConnect Plan Approved SWAT Study Plans Approved 34

35 Jan. Feb. Mar. Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Planning Calendar for Ten-Year Planning Cycle APS Transmission Planning 10 Yr Plan 10yr Plan Filed with ACC by Jan. 31 APS Corporate Load Forecast Develop 10yr base cases from AZ seed cases 10yr. Plan study effort Determination of projects, timings, and scope APS Corporate Load Forecast Post Summer 10yr. Plan New load forecast sensitivity Stakeholder Input WestConnect Coordinated base case development 10yr. Plans filed by others Arizona Utilities coordinated seed case development from WestConnect cases 2 nd Quarter Stakeholder Meeting Stakeholder input on studies, request study alternatives, updates on current projects Sep. 1 Network Transmission Customers and all other Transmission Customers Load & Resource Forecast Oct. 31 Deadline to submit Economic Study Requests for 4 th Quarter Meeting review 4 th Quarter Stakeholder Meeting Review draft of current 10yr plan, discussion Economic Study requests, receive stakeholder input Other Subregional Coordination Activities Throughout the Year APS/SRP Coordination Meeting APS/WAPA Coordination Meeting WestConnect Meetings SWAT Meetings o CATS-EHV o CATS-HV o CRT o AZ/NM o SATS o o Renewables Short-circuit Working Group 35

36 Exhibit 1 APS Attachment E Transmission Planning Process Economic What Type of Study? 1 Reliability Regional Transmission Provider Evaluation Local 2 High priority Transmission Provider Economic Study Not high priority Does Transmission Provider s system meet NERC/WECC criteria? No Transmission Provider determines facilities needed with Stakeholder input Study results documented in a report and reviewed by Customer and Transmission Provider Yes TEPPC evaluates with Stakeholder input Customer Choice of Study at Customer s expense Does Transmission Provider s system meet local reliability criteria? No Transmission Provider determines facilities needed with Stakeholder input TEPPC determines high priority, performs study TEPPC determines not high priority Yes Transmission Provider coordinates with Sub- Regional Planning Group 1. Generator Interconnection Request studies are performed pursuant to the Large Generator Interconnection Procedure contained in the Transmission Provider s Open Access Transmission Tariff (OATT). Transmission Service Requests are also performed pursuant to OATT procedures. 2. All requests for economic planning studies received by the Transmission Provider are forwarded to TEPPC for inclusion in the TEPPC Master List. TEPPC will evaluate only those requests that have regional impacts. 36

37 4.b. APS Ten Year Plan Projects Draft- Plans not finalized until mid/end of January 37

38 2010: Morgan 500/230kV substation (In- Service) Morgan-Pinnacle Peak 500kV & 230kV lines (In-Service) 2012: Youngs Canyon 345/69kV substation 2013: Delany-Palo Verde 500kV line 2014: Delany-Sun Valley 500kV line Hassayampa-N.Gila 500kV line D. Basin-Pinal Central 230kV line Pinal Central-Sundance 230kV line Mazatzal 345/69kV substation Bagdad 115kV relocation 2015: TS12 230/69kV substation 2016: Sun Valley-Morgan 500kV line 38

39 39

40 2010: Morgan-Raceway 230kV (in-service) : Raceway-Pinnacle Peak 230kV (inservice) 2013: Scatter Wash 230/69kV substation 2014: Sun Valley-Trilby Wash 230kV 2015: Trilby Wash-Palm Valley 230kV 40

41 41

42 2014: Palo Verde Hub-North Gila 500kV #2 line North Gila-TS8 230kV line 42

43 Project Timing Changes- Preliminary 2010 to 2011 changes Project Name Previous in-service date Scatter Wash 230/69kV substation Mazatzal 345/69kV substation TS12 230/69kV substation Delany-Palo Verde 500kV line New in-service date * It should be noted that in-service dates shown in this table are based on load projects, not potential interconnections. New generation interconnections may accelerate the in-service date. 43

44 4.b. APS Planning Transmission Projects for Renewable Generation 1) Palo Verde to Delany 500kV 2) Palo Verde to North Gila 500kV 3A) Palo Verde to Valley Load (Liberty) 3B) Gila Bend to Valley Load (Liberty) 4) Delany to Blythe 500kV 44

45 45

46 4.c. 2010/2011 Study Assumptions Coordinated Base Cases (Seed Cases) SATS 2012 case WECC 2015HS WestConnect case 69kV transmission models incorporated Most up-to-date forecasts for peak summer loads 46

47 4.c NERC/WECC Reliability Studies Summer Peak cases TPL-001 & TPL-002 Thermal analysis (All 10 years) Post-Transient (All 10 years) Transient Stability (2013 & 2019) TPL-003 & TPL-004 (2013 & 2019) Maximum Load Serving Capability for Phx & Yuma (All 10 years) TPL-001 & TPL-002 Thermal and Post Transient Low Load case (2014) Thermal, Transient Stability, & Post Transient TPL-001 thru TPL

48 2010 NERC/WECC Studies NERC STANDARD APS TPL Planning Methodology: Summer STUDIES COMPLETED TPL -001(n-0) Thermal Transient Stability Post Transient 2013 SIL X 2013 PEAK X 2019 SIL X 2019 PEAK X TPL-002 (n-1) 2013 SIL (Lines, xfmrs, gens) X X 2013 PEAK (Lines, xfmrs, gens) X X X 2013 MLSC (Lines, xfmrs, gens) X X 2019 SIL (Lines, xfmrs, gens) X X 2019 PEAK (Lines, xfmrs, gens) X X X 2019 MLSC (Lines, xfmrs, gens) X X TPL-003 (n-2) 2013 Stuck Breaker/Breaker Failure X X X 2013 N-1-1 X X X 2013 Bus Section X X X 2019 Stuck Breaker/Breaker Failure X X X 2019 N-1-1 X X X 2019 Bus Section X X X TPL-004 (n-xx) 2013 Major Substations With/Without Generation X X X 2013 Stuck Breaker/Breaker Failure X X X 2013 Common Corridor X X X 2019 Major Substations With/Without Generation X X X 2019 Stuck Breaker/Breaker Failure X X X 2019 Common Corridor X X X 48

49 2010 NERC/WECC Studies APS TPL Planning Methodology: WINTER SEASON - Low load NERC STANDARD STUDIES COMPLETED TPL -001(n-0) Thermal Transient Stability Post Transient 2013 WINTER - Low load X TPL-002 (n-1) 2013 TRANSMISSION LINE X X X 2013 XFMR X X 2013 GENERATION X X 2013 REACTORS X X TPL-003 (n-2) 2013 Stuck Breaker X X X 2013 N-1-1 X X X TPL-004 (n-xx) 2013 Loss of All Generation Units at a Station X X X 2013 Common Corridor X X X 49

50 4.d. Interconnection & Study Requests Generation Interconnection requests APS OASIS contains Generation Interconnection Queue (as of 12/8/10) 69 Solar projects MW 14 Wind projects MW 2 Others (Coal, NG, Biomass, etc.) MW 4 Transmission Interconnection Requests Currently 3 Transmission Service Requests waiting to begin study Currently no Economic Study Requests 50

51 4.e&f. Stakeholder Study Requests Study requests can be taken at today s meeting Study requests can be made at any time to: apstransmission@aps.com 51

52 4.g. Comments & Question Comments?????? Questions!!!!!!!!!! 52

53 5. Current Activities Updates NERC Compliance Reliability Standard MOD- 029 Rated System Path Methodology 53

54 6. Stakeholder Questions and Comments Open discussion Reference Material WestConnect APS OASIS SRP OASIS 54

55 7. Action Items Review any action items identified for follow up Information addressing action items to be posted on APS and/or SRP OASIS and WestConnect website 55

APS/SRP Stakeholder Meeting For Transmission Planning

APS/SRP Stakeholder Meeting For Transmission Planning APS/SRP Stakeholder Meeting For Transmission Planning FERC Order 890 SRP Attachment K APS Attachment E SRP Facility Scottsdale, AZ December 15 th, 2017 9:00 11:00 A.M. Agenda 1. Welcome, Introductions,

More information

APS/SRP Stakeholder Meeting For Transmission Planning

APS/SRP Stakeholder Meeting For Transmission Planning APS/SRP Stakeholder Meeting For Transmission Planning FERC Order 890 SRP Attachment K APS Attachment E SRP Facility Scottsdale, AZ December 15 th, 2017 9:00 11:00 A.M. Agenda 1. Welcome, Introductions,

More information

FERC Order 890 APS Attachment E SRP Attachment K

FERC Order 890 APS Attachment E SRP Attachment K APS/SRP 2 nd Quarter Stakeholder FERC Order 890 APS Attachment E SRP Attachment K APS Deer Valley Facility Phoenix, Arizona June 14, 2018 9 AM -12 PM Agenda 1. Welcome, Introductions, and Stakeholder Meeting

More information

Transmission Planning Process and Study Methodology John Lucas. Transmission Planning & Engineering Department Leader

Transmission Planning Process and Study Methodology John Lucas. Transmission Planning & Engineering Department Leader Transmission Planning Process and Study Methodology John Lucas Transmission Planning & Engineering Department Leader Phoenix, May4. 2009 Planning - Calendar & Methodology WECC/TEPPC WestConnect Planning

More information

West Coast Utilities Seminar December 13, 2007

West Coast Utilities Seminar December 13, 2007 West Coast Utilities Seminar December 13, 2007 Forward Looking Statements This presentation contains forward-looking statements based on current expectations, and neither Pinnacle West Capital Corporation

More information

Bank of America Energy & Power Conference November 16, 2004

Bank of America Energy & Power Conference November 16, 2004 Bank of America Energy & Power Conference November 16, 2004 Forward-Looking Statements This document may contain forward-looking statements within the meaning of the safe harbor of the Private Securities

More information

Transmission Planning Attachment K Public Input Meeting FERC 890, Biennial Cycle 3rd Quarter Meeting

Transmission Planning Attachment K Public Input Meeting FERC 890, Biennial Cycle 3rd Quarter Meeting Transmission Planning Attachment K Public Input Meeting FERC 890, 2010-11 Biennial Cycle 3rd Quarter Meeting October 1, 2010 Agenda Topic Presenter 9:00 9:10 Greetings and Introduction Austin 9:10 9:15

More information

1st Qua u r a ter e M e M e e t e in i g 2nd Qua u r a ter e M e M e e t e in i g

1st Qua u r a ter e M e M e e t e in i g 2nd Qua u r a ter e M e M e e t e in i g 2012 SERTP Welcome SERTP 2012 First RPSG Meeting & Interactive Training Session 1 2012 SERTP The SERTP process is a transmission planning process. Please contact the respective transmission provider for

More information

DELIVERING SUPERIOR SHAREHOLDER VALUE. Morgan Stanley Utilities Conference March 9, 2012

DELIVERING SUPERIOR SHAREHOLDER VALUE. Morgan Stanley Utilities Conference March 9, 2012 DELIVERING SUPERIOR SHAREHOLDER VALUE Morgan Stanley Utilities Conference March 9, 2012 FORWARD-LOOKING STATEMENTS 2 This presentation contains forward-looking statements based on current expectations.

More information

DELIVERING SUPERIOR SHAREHOLDER VALUE. Investor and Analyst Meetings June 1-3, 2011

DELIVERING SUPERIOR SHAREHOLDER VALUE. Investor and Analyst Meetings June 1-3, 2011 DELIVERING SUPERIOR SHAREHOLDER VALUE Investor and Analyst Meetings June 1-3, 2011 FORWARD-LOOKING STATEMENTS 2 This presentation contains forward-looking statements based on current expectations, including

More information

DELIVERING SUPERIOR SHAREHOLDER VALUE. Investor Meetings August 10 12, 2011

DELIVERING SUPERIOR SHAREHOLDER VALUE. Investor Meetings August 10 12, 2011 DELIVERING SUPERIOR SHAREHOLDER VALUE Investor Meetings August 10 12, 2011 FORWARD-LOOKING STATEMENTS 2 This presentation contains forward-looking statements based on current expectations, including statements

More information

DELIVERING SUPERIOR SHAREHOLDER VALUE. Wellington Shields & Co. West Coast Utilities Seminar March 23, 2011

DELIVERING SUPERIOR SHAREHOLDER VALUE. Wellington Shields & Co. West Coast Utilities Seminar March 23, 2011 DELIVERING SUPERIOR SHAREHOLDER VALUE Wellington Shields & Co. West Coast Utilities Seminar March 23, 2011 FORWARD-LOOKING STATEMENTS 2 This presentation contains forward-looking statements based on current

More information

Flexible Capacity Requirements for 2019 through 2021

Flexible Capacity Requirements for 2019 through 2021 Flexible Capacity Requirements for 2019 through 2021 Clyde Loutan - Principal, Renewable energy Integration Amber Motley - Manager, Short Term Forecasting Stakeholder Conference Call January 29 th, 2018

More information

FOURTH QUARTER AND FULL-YEAR 2016 RESULTS. February 24, 2017

FOURTH QUARTER AND FULL-YEAR 2016 RESULTS. February 24, 2017 FOURTH QUARTER AND FULL-YEAR 2016 RESULTS February 24, 2017 FORWARD LOOKING STATEMENTS AND NON-GAAP FINANCIAL MEASURES This presentation contains forward-looking statements based on current expectations,

More information

Regional Planning Coordination Group (RPCG) 2024 Common Case Transmission Assumptions (CCTA) June 2, 2014 FINAL

Regional Planning Coordination Group (RPCG) 2024 Common Case Transmission Assumptions (CCTA) June 2, 2014 FINAL Regional Planning Coordination Group (RPCG) 2024 Common Case Transmission Assumptions (CCTA) June 2, 2014 FINAL Executive Summary The Regional Planning Coordination Group (RPCG) aids the Regional Transmission

More information

FIRST QUARTER 2016 RESULTS. April 29, 2016

FIRST QUARTER 2016 RESULTS. April 29, 2016 FIRST QUARTER 2016 RESULTS April 29, 2016 FORWARD LOOKING STATEMENTS AND NON-GAAP FINANCIAL MEASURES This presentation contains forward-looking statements based on current expectations, including statements

More information

ITC Midwest 2014 Attachment O True-Up Presentation. Presenter: David Grover Manager, Transmission Pricing July 8, 2015

ITC Midwest 2014 Attachment O True-Up Presentation. Presenter: David Grover Manager, Transmission Pricing July 8, 2015 2014 Attachment O True-Up Presentation Presenter: David Grover Manager, Transmission Pricing July 8, 2015 Presentation Purpose Discuss the 2014 Annual True-Up posting Walk through the timeline and mechanics

More information

DRAFT REQUEST FOR PROPOSALS BY THE ARIZONA POWER AUTHORITY FOR SCHEDULING SERVICES AND/OR USE OF HOOVER DAM DYNAMIC SIGNAL.

DRAFT REQUEST FOR PROPOSALS BY THE ARIZONA POWER AUTHORITY FOR SCHEDULING SERVICES AND/OR USE OF HOOVER DAM DYNAMIC SIGNAL. DRAFT REQUEST FOR PROPOSALS BY THE ARIZONA POWER AUTHORITY FOR SCHEDULING SERVICES AND/OR USE OF HOOVER DAM DYNAMIC SIGNAL March 31, 2017 Summary The Arizona Power Authority ( Authority ) recently signed

More information

ITP Evaluation Process Plan

ITP Evaluation Process Plan ITP Evaluation Process Plan HVDC Conversion Project The goal of the coordinated Interregional Transmission Project (ITP) evaluation process is to achieve consistent planning assumptions and technical data

More information

FIRST QUARTER 2014 RESULTS. May 2, 2014

FIRST QUARTER 2014 RESULTS. May 2, 2014 FIRST QUARTER 2014 RESULTS May 2, 2014 FORWARD LOOKING STATEMENTS AND NON-GAAP FINANCIAL MEASURES This presentation contains forward-looking statements based on current expectations, including statements

More information

Long-Term Reliability Assessment

Long-Term Reliability Assessment Long-Term Reliability Assessment Key Findings and Long-Term Issues John Moura, Director of Reliability Assessment Topics Covered Today Background on NERC s Long-Term Reliability Assessment Emerging and

More information

FORM F4 BUSINESS ACQUISITION REPORT. Karl W. Smith Executive Vice President, Chief Financial Officer (709)

FORM F4 BUSINESS ACQUISITION REPORT. Karl W. Smith Executive Vice President, Chief Financial Officer (709) FORM 51-102F4 BUSINESS ACQUISITION REPORT ITEM 1 IDENTITY OF COMPANY 1.1 Name and Address of Company Fortis Inc. ( Fortis or the Corporation ) Suite 1201, 139 Water Street St. John s, Newfoundland and

More information

NERC TPL Standard Overview

NERC TPL Standard Overview NERC TPL-001-4 Standard Overview Attachment K Quarter 3 Stakeholder s Meeting September 29, 2016 1 Background New NERC TPL Standard 2016 TPL Plan and Status Update 2015 Planning Assessment Results Compliance

More information

SECOND QUARTER 2017 RESULTS. August 3, 2017

SECOND QUARTER 2017 RESULTS. August 3, 2017 SECOND QUARTER 2017 RESULTS August 3, 2017 FORWARD LOOKING STATEMENTS AND NON-GAAP FINANCIAL MEASURES This presentation contains forward-looking statements based on current expectations, including statements

More information

DELIVERING SUPERIOR SHAREHOLDER VALUE. Investor Meetings March April 2014

DELIVERING SUPERIOR SHAREHOLDER VALUE. Investor Meetings March April 2014 DELIVERING SUPERIOR SHAREHOLDER VALUE Investor Meetings March April 2014 FORWARD LOOKING STATEMENTS This presentation contains forward-looking statements based on current expectations, including statements

More information

FERC EL Settlement Agreement

FERC EL Settlement Agreement FERC EL05-121-009 Settlement Agreement Ray Fernandez Manager, Market Settlements Development Market Settlements Subcommittee June 14, 2018 Settlement Agreement Details Settlement Agreement Details FERC

More information

PJM SERTP Planning Process Overview

PJM SERTP Planning Process Overview PJM SERTP Planning Process Overview Order 1000 Biennial Regional Transmission Plan Review Meeting Presentation 1 of 2 May 8 th, 2018 Georgia Power Corporate Headquarters Atlanta, GA PJM SERTP Interregional

More information

Management Comments. February 12, 2015

Management Comments. February 12, 2015 Management Comments February 12, 2015 Average Bill, Not Average Cost of Service Court Rich: according to this Exhibit 6, 62.4 percent of the people in E-23 are paying less than the average cost of service,

More information

Wages & Salary Allocation Factor 1 Transmission Wages Expense p b 18,901,839

Wages & Salary Allocation Factor 1 Transmission Wages Expense p b 18,901,839 Page 1 of 29 Arizona Public Service Company Formula Rate Appendix A Notes Instruction 2014 Shaded cells are input cells Allocators Wages & Salary Allocation Factor 1 Transmission Wages Expense p354.21.b

More information

UNITED STATES SECURITIES AND EXCHANGE COMMISSION WASHINGTON, D.C FORM 10-K

UNITED STATES SECURITIES AND EXCHANGE COMMISSION WASHINGTON, D.C FORM 10-K UNITED STATES SECURITIES AND EXCHANGE COMMISSION WASHINGTON, D.C. 20549 FORM 10-K (Mark One) xannual REPORT PURSUANT TO SECTION 13 OR 15(d) OF THE SECURITIES EXCHANGE ACT OF 1934 For the fiscal year ended

More information

WECC Criterion TPL-001-WECC-CRT-3.1

WECC Criterion TPL-001-WECC-CRT-3.1 WECC Criterion TPL-001-WECC-CRT-3.1 A. Introduction 1. Title: Transmission System Planning Performance 2. Number: TPL-001-WECC-CRT-3.1 3. Purpose: To facilitate coordinated near-term and long-term transmission

More information

ATLANTIC CITY ELECTRIC COMPANY BPU NJ

ATLANTIC CITY ELECTRIC COMPANY BPU NJ Attachment 1 Attachment 1 Page 1 of 3 ATLANTIC CITY ELECTRIC COMPANY BPU NJ No. 11 Electric Service - Section IV Revised Sheet Replaces Revised Sheet No. 60 RIDER (BGS) Basic Generation Service (BGS) Basic

More information

Distribution Group Study Process. August 26, 2014

Distribution Group Study Process. August 26, 2014 Distribution Group Study Process August 26, 2014 Agenda Overview Applying for DGSP DGSP Interconnection Process Applicability and Utility Contacts Questions 2 Process Overview Open Window Period Evaluation

More information

Economic Benefit Analysis of the Navajo Generating Station to the Central Arizona Water Conservation District and Its Customers

Economic Benefit Analysis of the Navajo Generating Station to the Central Arizona Water Conservation District and Its Customers ENERGY VENTURES ANALYSIS JANUARY 2018 Economic Benefit Analysis of the Navajo Generating Station to the Central Arizona Water Conservation District and Its Customers January 2018 Prepared by: ENERGY VENTURES

More information

Memorandum. This memorandum does not require Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum does not require Board action. EXECUTIVE SUMMARY California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Eric Hildebrandt, Executive Director, Market Monitoring Date: November 7, 2018 Re: Department of Market Monitoring

More information

2017 Annual Update to the PSE Formula Rate

2017 Annual Update to the PSE Formula Rate 2017 Annual Update to the PSE Formula Rate PSE Transmission Customer Meeting Lynn Dillender Federal and Regional Policy Chelsey Neil Supervisor Transmission Services July 20, 2017 Agenda Formula Rate Annual

More information

TUCSON ELECTRIC POWER COMPANY. Transmission Reliability Margin Implementation Document (TRMID)

TUCSON ELECTRIC POWER COMPANY. Transmission Reliability Margin Implementation Document (TRMID) A UniSource Energy Company TUCSON ELECTRIC POWER COMPANY Transmission Reliability Margin Implementation Document (TRMID) Approved by: Effective Date: /c Version 1 Based on North American Electric Reliability

More information

FOURTH QUARTER AND FULL-YEAR 2017 RESULTS. February 23, 2018

FOURTH QUARTER AND FULL-YEAR 2017 RESULTS. February 23, 2018 FOURTH QUARTER AND FULL-YEAR 2017 RESULTS February 23, 2018 FORWARD LOOKING STATEMENTS AND NON-GAAP FINANCIAL MEASURES This presentation contains forward-looking statements based on current expectations,

More information

PALO VERDE - MORGAN 500kV TRANSMISSION PROJECT

PALO VERDE - MORGAN 500kV TRANSMISSION PROJECT Agenda Number 4. Attachment. Draft 10-4-11 PALO VERDE - MORGAN 500kV TRANSMISSION PROJECT JOINT PARTICIPATION AGREEMENT BETWEEN ARIZONA PUBLIC SERVICE COMPANY AND CENTRAL ARIZONA WATER CONSERVATION DISTRICT

More information

Year Assessment Preliminary Study Design

Year Assessment Preliminary Study Design 2015 10-Year Assessment Preliminary Study Design October 15, 2014 Stakeholder and Customer Webcast atcllc.com Purpose Solicit pre-study Comments 2015 Assessment Process 2015 Assessment Assumptions Public

More information

2003 Annual Report on Market Issues and Performance

2003 Annual Report on Market Issues and Performance 2003 Annual Report on Market Issues and Performance Board of Governors Meeting April 22, 2004 Greg Cook Manager of Market Monitoring Issues in 2003-04 CALIFORNIA ISO and FERC: Continue to work through

More information

NTTG REGIONAL TRANSMISSION PLAN. December 30, 2015

NTTG REGIONAL TRANSMISSION PLAN. December 30, 2015 NTTG 2014-2015 REGIONAL TRANSMISSION PLAN December 30, 2015 1 Table of Contents Executive Summary... 3 Introduction... 3 The Northern Tier Transmission Group... 3 Participating Utilities... 4 Purpose of

More information

FOURTH QUARTER AND FULL-YEAR 2018 RESULTS. February 22, 2019

FOURTH QUARTER AND FULL-YEAR 2018 RESULTS. February 22, 2019 FOURTH QUARTER AND FULL-YEAR 208 RESULTS February 22, 209 FORWARD LOOKING STATEMENTS AND NON-GAAP FINANCIAL MEASURES This presentation contains forward-looking statements based on current expectations,

More information

Nevada Power & Sierra Pacific Power d/b/a NV Energy Stakeholders Planning Input Meeting July

Nevada Power & Sierra Pacific Power d/b/a NV Energy Stakeholders Planning Input Meeting July Nevada Power & Sierra Pacific Power d/b/a NV Energy Stakeholders Planning Input Meeting July 2012 1 1. Welcome Introductions 2. IRP filing and results Update on Loads and Resources Renewable Transmission

More information

2011 Budget Initial Stakeholder Call

2011 Budget Initial Stakeholder Call 2011 Budget Initial Stakeholder Call Michael Epstein Director of Financial Planning June 23, 2010 Agenda TOPIC PRESENTER Introduction Steve Berberich Budget principles & strategic initiatives Steve Berberich

More information

BHP 2019 Projected Net Revenue Requirement Meeting. October 18, :00 PM MDT Black Hills Energy 7001 Mt Rushmore Rd Rapid City, SD 57702

BHP 2019 Projected Net Revenue Requirement Meeting. October 18, :00 PM MDT Black Hills Energy 7001 Mt Rushmore Rd Rapid City, SD 57702 BHP 2019 Projected Net Revenue Requirement Meeting October 18, 2018 2:00 PM MDT Black Hills Energy 7001 Mt Rushmore Rd Rapid City, SD 57702 Agenda Introductions CUS Transmission System Overview Black Hills

More information

4.1 Transmission Owners that maintain the transmission paths in Attachment B.

4.1 Transmission Owners that maintain the transmission paths in Attachment B. A. Introduction 1. Title: Transmission Maintenance 2. Number: FAC-501-WECC-2 3. Purpose: To ensure the Transmission Owner of a transmission path identified in Attachment B, Major WECC Transfer Paths in

More information

Spheria Australian Smaller Companies Fund

Spheria Australian Smaller Companies Fund 29-Jun-18 $ 2.7686 $ 2.7603 $ 2.7520 28-Jun-18 $ 2.7764 $ 2.7681 $ 2.7598 27-Jun-18 $ 2.7804 $ 2.7721 $ 2.7638 26-Jun-18 $ 2.7857 $ 2.7774 $ 2.7690 25-Jun-18 $ 2.7931 $ 2.7848 $ 2.7764 22-Jun-18 $ 2.7771

More information

Project Coordination and Path Rating

Project Coordination and Path Rating Document name Category Project Coordination, Path Rating and Progress Report Processes ( ) Regional Reliability Standard ( ) Regional Criteria ( ) Policy (X) Guideline ( ) Report or other ( ) Charter Document

More information

Review of Registered Charites Compliance Rates with Annual Reporting Requirements 2016

Review of Registered Charites Compliance Rates with Annual Reporting Requirements 2016 Review of Registered Charites Compliance Rates with Annual Reporting Requirements 2016 October 2017 The Charities Regulator, in accordance with the provisions of section 14 of the Charities Act 2009, carried

More information

PEAK RELIABILITY COORDINATOR FUNDING

PEAK RELIABILITY COORDINATOR FUNDING PEAK RELIABILITY COORDINATOR FUNDING Straw Proposal May 8, 2015 Assessment of 2 Peak Reliability Coordinator Charges Straw Proposal Table of Contents 1 Introduction... 3 2 Background... 3 3 Plan for Stakeholder

More information

UNITED STATES SECURITIES AND EXCHANGE COMMISSION Washington, D.C FORM 8-K

UNITED STATES SECURITIES AND EXCHANGE COMMISSION Washington, D.C FORM 8-K UNITED STATES SECURITIES AND EXCHANGE COMMISSION Washington, D.C. 20549 FORM 8-K CURRENT REPORT Pursuant to Section 13 or 15(d) of the Securities Exchange Act of 1934 Date of report (Date of earliest event

More information

Portland General Electric Company Sheet No SCHEDULE 201 QUALIFYING FACILITY 10 MW or LESS AVOIDED COST POWER PURCHASE INFORMATION

Portland General Electric Company Sheet No SCHEDULE 201 QUALIFYING FACILITY 10 MW or LESS AVOIDED COST POWER PURCHASE INFORMATION Portland General Electric Company Sheet No. 201-1 PURPOSE SCHEDULE 201 QUALIFYING FACILITY 10 MW or LESS AVOIDED COST POWER PURCHASE INFORMATION To provide information about Standard Avoided Costs and

More information

10-YEAR COSTS AND BENEFITS TO SPP MEMBERS OF INTEGRATING MOUNTAIN WEST TRANSMISSION GROUP Quantitative Analysis of Costs and Benefits

10-YEAR COSTS AND BENEFITS TO SPP MEMBERS OF INTEGRATING MOUNTAIN WEST TRANSMISSION GROUP Quantitative Analysis of Costs and Benefits 10-YEAR COSTS AND BENEFITS TO SPP MEMBERS OF INTEGRATING MOUNTAIN WEST TRANSMISSION GROUP Quantitative Analysis of Costs and Benefits Published on March 19, 2018 By SPP Staff REVISION HISTORY DATE OR VERSION

More information

Large Commercial Rate Simplification

Large Commercial Rate Simplification Large Commercial Rate Simplification Presented to: Key Account Luncheon Red Lion Hotel Presented by: Mark Haddad Assistant Director/CFO October 19, 2017 Most Important Information First There is no rate

More information

Key IRS Interest Rates After PPA

Key IRS Interest Rates After PPA Key IRS Rates - After PPA - thru 2011 Page 1 of 10 Key IRS Interest Rates After PPA (updated upon release of figures in IRS Notice usually by the end of the first full business week of the month) Below

More information

5 Inter-Zonal Congestion Management Markets

5 Inter-Zonal Congestion Management Markets 5 Inter-Zonal Congestion Management Markets 5.1 Inter-Zonal Congestion Management Congestion occurs when the physical limits of a line, or inter-tie, prohibits load from being served with the least cost

More information

FDD FIRM STORAGE SERVICE NORTHERN NATURAL GAS COMPANY

FDD FIRM STORAGE SERVICE NORTHERN NATURAL GAS COMPANY FDD FIRM STORAGE SERVICE NORTHERN NATURAL GAS COMPANY FIRM STORAGE SERVICE OPTIONS Northern s firm storage service is provided pursuant to the FDD Rate Schedule located in Northern s FERC Gas Tariff. The

More information

COLUMBIAGRID GEOMAGNETIC DISTURBANCE DRAFT STUDY REPORT

COLUMBIAGRID GEOMAGNETIC DISTURBANCE DRAFT STUDY REPORT COLUMBIAGRID GEOMAGNETIC DISTURBANCE DRAFT STUDY REPORT (NERC Standard TPL-007-1) Revision 1 February 1, 2018 ColumbiaGrid 8338 NE Alderwood Road, Suite 140 Portland, OR 97220 www.columbiagrid.org (503)

More information

D. RSCP SUPPLIER PAYMENTS AND CUSTOMER RATES

D. RSCP SUPPLIER PAYMENTS AND CUSTOMER RATES 32 RSCP SUPPLIER PAYMENTS AND CUSTOMER RATES D. RSCP SUPPLIER PAYMENTS AND CUSTOMER RATES This summary is provided for bidder convenience only. Any statements herein describing BGS- RSCP rates or supplier

More information

Operations Manager Responsible for the TRMID for the WAPA-RMR Transmission Operator (TOP) function.

Operations Manager Responsible for the TRMID for the WAPA-RMR Transmission Operator (TOP) function. 1.0 PURPOSE This document serves to promote the consistent and reliable calculation, verification, preservation, and use of Transmission Reliability Margin (TRM) to support analysis and system operations.

More information

ARR/FTR Market Update: ATC Customer Meeting. August 20, 2009

ARR/FTR Market Update: ATC Customer Meeting. August 20, 2009 ARR/FTR Market Update: ATC Customer Meeting August 20, 2009 Agenda ARR Allocation FTR Annual/Monthly Auction Challenge 2 Allocation Overview 101 Market Participants took part in the 2009-2010 Annual ARR

More information

WESTWOOD LUTHERAN CHURCH Summary Financial Statement YEAR TO DATE - February 28, Over(Under) Budget WECC Fund Actual Budget

WESTWOOD LUTHERAN CHURCH Summary Financial Statement YEAR TO DATE - February 28, Over(Under) Budget WECC Fund Actual Budget WESTWOOD LUTHERAN CHURCH Summary Financial Statement YEAR TO DATE - February 28, 2018 General Fund Actual A B C D E F WECC Fund Actual Revenue Revenue - Faith Giving 1 $ 213 $ 234 $ (22) - Tuition $ 226

More information

EIPC Roll-Up Report & Scenarios

EIPC Roll-Up Report & Scenarios EIPC Roll-Up Report & Scenarios Zach Smith Director, Transmission Planning New York Independent System Operator IPTF/EGCWG/ESPWG Meeting January 6, 2014 2013 New York Independent System Operator, Inc.

More information

,QWHU]RQDO&RQJHVWLRQ0DQDJHPHQW

,QWHU]RQDO&RQJHVWLRQ0DQDJHPHQW ,QWHU]RQDO&RQJHVWLRQ0DQDJHPHQW 0DUNHW Ã 6XPPDU\ÃRIÃÃ,QWHU]RQDOÃ&RQJHVWLRQÃ0DQDJHPHQWÃ 0DUNHWÃ 5.1.1 Overview Under the current zonal model, the CAISO manages congestion in the forward market only on major

More information

2011 IRP Public Input Meeting. October 5, Pacific Power Rocky Mountain Power PacifiCorp Energy

2011 IRP Public Input Meeting. October 5, Pacific Power Rocky Mountain Power PacifiCorp Energy 2011 IRP Public Input Meeting October 5, 2010 Pacific Power Rocky Mountain Power PacifiCorp Energy Agenda Morning Session IRP Schedule Update Energy Gateway Transmission Construction Update and Evaluation

More information

NEAS ENERGY - Route to Market

NEAS ENERGY - Route to Market NEAS ENERGY - Route to Market Overview Wholesale Power Market developments Revenue Profiles Secured and Unsecured FIT CFD v ROC PPA Key terms and conditions PPA Backstop PPA Cash flows for CfD and ROC

More information

PJM & MISO Assumptions and Criteria for Testing of New Resources

PJM & MISO Assumptions and Criteria for Testing of New Resources & Assumptions and Criteria for Testing of New Resources 1 Introduction These slides provide a description and comparison of the assumptions and criteria used by and during the study of customer proposed

More information

PEAK RELIABILITY COORDINATOR FUNDING. Draft Final Proposal. May 28, 2015

PEAK RELIABILITY COORDINATOR FUNDING. Draft Final Proposal. May 28, 2015 PEAK RELIABILITY COORDINATOR FUNDING Draft Final Proposal May 28, 2015 2 Assessment of Peak Reliability Coordinator Charges Draft Final Proposal Table of Contents 1 Introduction... 3 2 Background... 3

More information

UNS Electric, Inc. Rates for Transmission Service For June 1, 2016 Through May 31, 2017 Data For Period Ending December 31, 2015

UNS Electric, Inc. Rates for Transmission Service For June 1, 2016 Through May 31, 2017 Data For Period Ending December 31, 2015 UNS Electric, Inc. Rates for Transmission Service For June 1, 2016 Through May 31, 2017 Data For Period Ending December 31, 2015 Mohave Total Line Division Division Company 1 2016 Revenue Requirements

More information

Board of Directors Meeting. August 25, 2016

Board of Directors Meeting. August 25, 2016 Board of Directors Meeting August 25, 2016 July 2016 Operating Report August 25, 2016 July Operational Results Category July Variance 2016 Variance Municipal Demand (MW) 1.1% (2.3%) Municipal Energy (MWh)

More information

4TH QUARTER AND FULL-YEAR 2013 RESULTS. February 21, 2014

4TH QUARTER AND FULL-YEAR 2013 RESULTS. February 21, 2014 4TH QUARTER AND FULL-YEAR 2013 RESULTS February 21, 2014 FORWARD LOOKING STATEMENTS AND NON-GAAP FINANCIAL MEASURES This presentation contains forward-looking statements based on current expectations,

More information

WECC Standard PRC-STD Protective Relay and Remedial Action Scheme Misoperation

WECC Standard PRC-STD Protective Relay and Remedial Action Scheme Misoperation A. Introduction 1. Title: Protective Relay and Remedial Action Scheme 2. Number: PRC-STD-003-1 3. Purpose: Regional Reliability Standard to ensure all transmission and generation Protection System s affecting

More information

January 2015 Monthly Financial Report PREPARED BY

January 2015 Monthly Financial Report PREPARED BY January 2015 Monthly Financial Report PREPARED BY Financial Accounting & Reporting Division City of Phoenix Monthly Financial Report January 2015 Table of Contents by Programs Page Performance Status

More information

UNITED STATES SECURITIES AND EXCHANGE COMMISSION WASHINGTON, D.C FORM 10-Q

UNITED STATES SECURITIES AND EXCHANGE COMMISSION WASHINGTON, D.C FORM 10-Q UNITED STATES SECURITIES AND EXCHANGE COMMISSION WASHINGTON, D.C. 20549 (Mark One) FORM 10-Q QUARTERLY REPORT PURSUANT TO SECTION 13 OR 15(d) OF THE SECURITIES EXCHANGE ACT OF 1934 For the quarterly period

More information

XML Publisher Balance Sheet Vision Operations (USA) Feb-02

XML Publisher Balance Sheet Vision Operations (USA) Feb-02 Page:1 Apr-01 May-01 Jun-01 Jul-01 ASSETS Current Assets Cash and Short Term Investments 15,862,304 51,998,607 9,198,226 Accounts Receivable - Net of Allowance 2,560,786

More information

MISO PJM IPSAC. December 2, Revised December 22, PJM IPSAC Meeting, December 2,

MISO PJM IPSAC. December 2, Revised December 22, PJM IPSAC Meeting, December 2, MISO PJM IPSAC December 2, 2016 Revised December 22, 2016 1 Agenda 2 TMEP Final JOA Language Recommended TMEPs Order No. 1000 Compliance Filing Generation Deactivation JOA Language PJM Proposal Window

More information

Mountain West Transmission Group (MWTG) Introduction and Process

Mountain West Transmission Group (MWTG) Introduction and Process Mountain West Transmission Group (MWTG) Introduction and Process October 13 Denver, CO October 16 Little Rock, AR 2 Agenda Overview of SPP Overview of the MWTG Members SPP Process New Member Integration

More information

Development of Economy and Financial Markets of Kazakhstan

Development of Economy and Financial Markets of Kazakhstan Development of Economy and Financial Markets of Kazakhstan National Bank of Kazakhstan Macroeconomic development GDP, real growth, % 116 112 18 14 1 113,5 11,7 216,7223,8226,5 19,8 19,8 19,3 19,619,7 199,

More information

Long Term Access Goal Final Report Update

Long Term Access Goal Final Report Update Long Term Access Goal 2007-09 Final Report 2008-10 Update SME Version of Presentation for ATC Board of Directors Meeting December 14, 2009 2007-09 and 2008-10 Long Term Goals Access (10%) Reduce congestion

More information

El Paso Electric Company Marketing Tour September 2015

El Paso Electric Company Marketing Tour September 2015 El Paso Electric Company Marketing Tour September 2015 Safe Harbor Statement 2 This presentation includes statements that may constitute forward-looking statements made pursuant to the safe harbor provisions

More information

NSTAR ELECTRIC COMPANY d/b/a EVERSOURCE ENERGY SUMMARY OF ELECTRIC SERVICE DELIVERY RATES. M.D.P.U. No E Page 1 of 10

NSTAR ELECTRIC COMPANY d/b/a EVERSOURCE ENERGY SUMMARY OF ELECTRIC SERVICE DELIVERY RATES. M.D.P.U. No E Page 1 of 10 Page 1 of 10 No. Code Area Component Distribution Rate Adjust (1) Distribution Decoupling Transition Transmission (2) System Benefits Recon. Total EEC Energy Delivery R-1 7 A1/A5 ALL Customer $7.00 $7.00

More information

WECC Guideline: UNSCHEDULED FLOW REDUCTION GUIDELINE

WECC Guideline: UNSCHEDULED FLOW REDUCTION GUIDELINE The content of this document is an excerpt of the WECC Unscheduled Flow Mitigation Plan Document posted on www.wecc.biz. Introduction WECC : UNSCHEDULED FLOW REDUCTION GUIDELINE The combination of Scheduled

More information

Western Electricity Coordinating Council

Western Electricity Coordinating Council Western Electricity Coordinating Council WILLIAM MITTELSTADT, TOM CHAIR DISTURBANCE MONITORING WORK GROUP BONNEVILLE POWER ADMINISTRATION PARKWAY PLAZA (MAIL CENTER) 8100 N.E. PARKWAY VANCOUVER, WA 98662

More information

Ms. Roni Reese Senior Contracts Analyst California Independent System Operator Corporation 151 Blue Ravine Road Folsom, CA 95630

Ms. Roni Reese Senior Contracts Analyst California Independent System Operator Corporation 151 Blue Ravine Road Folsom, CA 95630 Ms. Roni Reese January 10, 2008 Page 1 January 10, 2008 Ms. Roni Reese Senior Contracts Analyst California Independent System Operator Corporation 151 Blue Ravine Road Folsom, CA 95630 Re: Startrans IO,

More information

April 29, CAISO Service Agreement No. 3788, Large Generator Interconnection Agreement

April 29, CAISO Service Agreement No. 3788, Large Generator Interconnection Agreement California Independent System Operator Corporation April 29, 2016 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: California

More information

Key Compliance Trends

Key Compliance Trends Key Compliance Trends Key Compliance Trends Trend # 1: The number of violations received each month exceeds the total monthly violations processed Monthly BOTCC approvals are increasing The use of the

More information

Title Page Southern California Edison Company Tariff Title: Transmission Owners Tariff Tariff Record Title: First Revised Service Agreement No. 39 FER

Title Page Southern California Edison Company Tariff Title: Transmission Owners Tariff Tariff Record Title: First Revised Service Agreement No. 39 FER Title Page Southern California Edison Company Tariff Title: Transmission Owners Tariff Tariff Record Title: First Revised Service Agreement No. 39 FERC FPA Electric Tariff INTERCONNECTION FACILITIES AGREEMENT

More information

2012 SRP ANNUAL REPORT

2012 SRP ANNUAL REPORT 2012 SRP ANNUAL REPORT ABOUT SRP SRP (Salt River Project) provides reliable, fairly priced electricity and water to more than 2 million people living in central Arizona. As one of the nation s largest

More information

SUPPORT DOCUMENTATION

SUPPORT DOCUMENTATION SUPPORT DOCUMENTATION 89 UTILITY PROVIDER RATES AND CHARGES 90 Utility Providers Residential Rates and Charges As of November 2017 ELECTRICITY Source: Arizona Public Service (APS) 800-253-9405 www.aps.com*

More information

Key Compliance Trends Item 2.A

Key Compliance Trends Item 2.A Key Compliance Trends Item 2.A Key Compliance Trends The number of violations received each month exceeds the total monthly violations approved by the BOTCC or dismissed, but the BOTCC approved violations

More information

Calculate Net Annual Transmission Revenue Requirements (ATRR) and Rates for SPP Tariff. Total Transmission A. Zonal Net ATRR 1 Gross ATRR $60,516,589

Calculate Net Annual Transmission Revenue Requirements (ATRR) and Rates for SPP Tariff. Total Transmission A. Zonal Net ATRR 1 Gross ATRR $60,516,589 Page 1 Formula-based Rate Template Calculate Net Annual Transmission Revenue Requirements (ATRR) and Rates for SPP Tariff Line No. Acct Description Notes Total Transmission A. Zonal Net ATRR 1 Gross ATRR

More information

NSTAR ELECTRIC COMPANY d/b/a EVERSOURCE ENERGY SUMMARY OF ELECTRIC SERVICE DELIVERY RATES. M.D.P.U. No C Page 1 of 10

NSTAR ELECTRIC COMPANY d/b/a EVERSOURCE ENERGY SUMMARY OF ELECTRIC SERVICE DELIVERY RATES. M.D.P.U. No C Page 1 of 10 Page 1 of 10 No. Code Area Component Distribution Rate Adjust (1) Distribution Decoupling Transition Transmission (2) System Benefits Recon. Total EEC Energy Delivery R-1 7 A1/A5 ALL Customer $7.00 $7.00

More information

Alberta Utilities Commission

Alberta Utilities Commission Alberta Utilities Commission In the Matter of the Need for the Jenner Wind Energy Connection And in the matter of the Electric Utilities Act, S.A. 2003, c. E-5.1, the Alberta Utilities Commission Act,

More information

AC TRANSMISSION PUBLIC POLICY TRANSMISSION NEEDS PROJECT SOLICITATION Response due April 29, 2016

AC TRANSMISSION PUBLIC POLICY TRANSMISSION NEEDS PROJECT SOLICITATION Response due April 29, 2016 10 Krey Boulevard Rensselaer, NY 12144 AC TRANSMISSION PUBLIC POLICY TRANSMISSION NEEDS PROJECT SOLICITATION Response due April 29, 2016 Dear NYISO Stakeholder or Interested Party: February 29, 2016 With

More information

Alberta Utilities Commission

Alberta Utilities Commission Alberta Utilities Commission In the Matter of the Need for the Grizzly Bear Creek Wind Power Plant Connection And in the matter of the Electric Utilities Act, S.A. 2003, c. E-5.1, the Alberta Utilities

More information

WASN Operations Business Procedure OASIS COVER PAGE

WASN Operations Business Procedure OASIS COVER PAGE No. COVER PAGE This page will be removed when final document is posted Western Area Power Administration Sierra Nevada Region () Business Practice/ covering Sierra Nevada Regional procedures is being updated.

More information

T-D Interconnections: Best Value Planning White Paper January 2016

T-D Interconnections: Best Value Planning White Paper January 2016 T-D Interconnections: Best Value Planning White Paper Updated January 2016 1. Purpose This paper defines the process and criteria that together constitute joint best value planning (BVP) between ATC and

More information

2019 Budget and Grid Management Charge Initial Stakeholder Meeting

2019 Budget and Grid Management Charge Initial Stakeholder Meeting 2019 Budget and Grid Management Charge Initial Stakeholder Meeting July 24, 2018 Agenda Topic: Welcome and Introductions Presenter: Kristina Osborne 2019 Budget Process & GMC Rate Outlook April Gordon

More information

U.S. Natural Gas Storage Charts

U.S. Natural Gas Storage Charts U.S. Natural Gas Storage Charts BMO Capital Markets Commodity Products Group November 26, 214 Total U.S. Natural Gas in Storage 5, Total Stocks This Week 3432 4, 3, 2, 1, Reported On: November 26, 214

More information