EIPC Roll-Up Report & Scenarios

Size: px
Start display at page:

Download "EIPC Roll-Up Report & Scenarios"

Transcription

1 EIPC Roll-Up Report & Scenarios Zach Smith Director, Transmission Planning New York Independent System Operator IPTF/EGCWG/ESPWG Meeting January 6, New York Independent System Operator, Inc. All Rights Reserved. DRAFT FOR DISCUSSION PURPOSES ONLY

2 Agenda Background Roll-Up Model and Assumptions Roll-Up Results and Report Sample Scenarios for Study in 2014 Schedule for Stakeholder Input on Scenarios to be Studied 2013 New York Independent System Operator, Inc. All Rights Reserved. DRAFT FOR DISCUSSION PURPOSES ONLY 2

3 Background Initial EIPC Scope of Activities adopted Dec 2009 Non-grant work in 2013 Roll-up analysis of the Planning Authority s (PA) plans to find possible changes that will improve their efficiency and effectiveness Result of this analysis available for consideration in regional and inter-regional planning processes Perform a defined number of scenarios/sensitivities against the roll-up model Separate from the DOE-funded Gas-Electric System Interface Study 2013 New York Independent System Operator, Inc. All Rights Reserved. DRAFT FOR DISCUSSION PURPOSES ONLY 3

4 Planning Authority responsibilities Create and modify steady-state load-flow models Develop 2018 and 2023 summer peak models Prepare 2018 and 2023 roll-up documentation Conduct steady-state load-flow analysis Identify any reliability enhancements needed Gap Analysis Perform transfer analysis Prepare roll-up report 2013 New York Independent System Operator, Inc. All Rights Reserved. DRAFT FOR DISCUSSION PURPOSES ONLY 4

5 Model Assumptions Overview Case Snapshot of summer peak conditions (2018 and 2023) Secured for N-1 Load Forecast Each PA provided baseline forecasts consistent with its regional plan NYISO: 50/50, includes energy efficiency Economic growth and conservation modeled consistent with regional plans Varies across the Eastern Interconnection (EI) 2013 New York Independent System Operator, Inc. All Rights Reserved. DRAFT FOR DISCUSSION PURPOSES ONLY 5

6 Model Assumptions Overview Scheduled Area Interchange Long-term firm transmission service between Balancing Authorities is modeled Interchanges are generally consistent with ERAG MMWG Generation Dispatch Base case generation dispatch is set according to the internal assumptions and procedures of each PA Generally uses economic dispatch or typical market dispatch for peak conditions 2013 New York Independent System Operator, Inc. All Rights Reserved. DRAFT FOR DISCUSSION PURPOSES ONLY 6

7 Model Assumptions Overview New Transmission Projects PAs have agreed to the following terms to describe the status of future transmission projects: Planned The project has completed the respective PA s planning process, including any applicable regional planning process approvals (for example, ISO or RTO approvals), but specific contractual obligations have not been committed to, or regulatory approvals obtained. Proposed The project has been proposed but not yet completed the respective PA s planning process nor received applicable regional planning process approvals New York Independent System Operator, Inc. All Rights Reserved. DRAFT FOR DISCUSSION PURPOSES ONLY 7

8 Model Assumptions Overview New Transmission Projects NYISO includes the following transmissions projects as: Planned Firm transmission projects as listed in the 2013 Gold Book. Proposed Transmission associated with proposed generation projects. Includes Attachment Facilities, System Upgrade Facilities and System Deliverability Upgrades 2013 New York Independent System Operator, Inc. All Rights Reserved. DRAFT FOR DISCUSSION PURPOSES ONLY 8

9 Model Assumptions Overview New Generation Projects PAs have agreed to the following terms to describe the status of future generation projects: Committed The resource has completed the interconnection request process, or has obtained applicable transmission service. Proposed The resource has been proposed and included in the planning process, but does not have applicable transmission service. NYISO included generation projects consistent with RNA base case inclusion rules New York Independent System Operator, Inc. All Rights Reserved. DRAFT FOR DISCUSSION PURPOSES ONLY 9

10 Interregional Gap Analysis PAs analyzed their system to determine if the coordinated plan had any gaps such as: Pre-existing system conditions Adverse impacts due to neighboring PA plans No gaps reported for NYISO Potential issues identified by MISO, PJM, and SPP 2013 New York Independent System Operator, Inc. All Rights Reserved. DRAFT FOR DISCUSSION PURPOSES ONLY 10

11 Inter-Area Enhancements PAs examine projects near their borders and coordinate with neighbors on combined system enhancements to address any gaps identified. Some conceptual upgrades are being considered by MISO New York Independent System Operator, Inc. All Rights Reserved. DRAFT FOR DISCUSSION PURPOSES ONLY 11

12 Linear Transfer Analysis Objective is to demonstrate how much additional power can be reliably moved between areas Analyzed 5,000 MW incremental transfers between selected areas This is in addition to the firm transfers already included in the Roll-Up case Monitored the following (100 kv and above): N-0 branch overloads N-1 branch overloads Also included NPCC design-criteria contingencies 2013 New York Independent System Operator, Inc. All Rights Reserved. DRAFT FOR DISCUSSION PURPOSES ONLY 12

13 Defined Areas and Transfers Planning Coordinators in Each Area Transfers Performed 2013 New York Independent System Operator, Inc. All Rights Reserved. DRAFT FOR DISCUSSION PURPOSES ONLY 13

14 Transfer Results for Northeast Table ES-3: 2018 Linear Transfer Results Source Sink FCITC (MW) Lim. PA Con. PA B C 2,800 PENELEC-PJM NYISO/PENELEC-PJM C B 1,800 NYISO NYISO C D 1,400 NYISO NYISO D C 1,900 PENELEC-PJM NYISO/PENELEC-PJM Table ES-4: 2023 Linear Transfer Results Source Sink FCITC (MW) Lim. PA Con. PA B C 3,400 PENELEC-PJM N/A C B 1,800 NYISO NYISO C D 1,500 NYISO NYISO D C 2,100 PENELEC-PJM N/A 2013 New York Independent System Operator, Inc. All Rights Reserved. DRAFT FOR DISCUSSION PURPOSES ONLY 14

15 Roll-Up Report Report posted December 6, Stakeholder comments due January 31, New York Independent System Operator, Inc. All Rights Reserved. DRAFT FOR DISCUSSION PURPOSES ONLY 15

16 Scenarios for Study in 2014 Principles and Guidelines Document Sample Scenarios Posted on EIPC Website Schedule for Stakeholder Input on Scenarios to be Studied 2013 New York Independent System Operator, Inc. All Rights Reserved. DRAFT FOR DISCUSSION PURPOSES ONLY 16

17 Scenario Principles and Guidelines Document posted on EIPC website Describes the types of scenarios that will be analyzed in 2014 Provides a sample format for stakeholders to use in providing their ideas on possible scenarios to be studied 2013 New York Independent System Operator, Inc. All Rights Reserved. DRAFT FOR DISCUSSION PURPOSES ONLY 17

18 Principles and Guidelines Document All scenarios will be run as changes to the Base Plan (Roll-up Cases) Purpose is to develop high-level transmission build-outs that provide information relevant to the scenarios suggested such as Federal and/or regional policy development Scenarios should not be duplicative of any other local or regional planning efforts or transmission requests subject to analysis under the OATT provisions of any party 2013 New York Independent System Operator, Inc. All Rights Reserved. DRAFT FOR DISCUSSION PURPOSES ONLY 18

19 Principles and Guidelines Document The assumptions defining a scenario should be provided by the stakeholder sponsors in sufficient detail to allow analysis by EIPC EIPC members will work with stakeholders to identify any restrictions, exceptions or gaps in the definition of assumptions Changes to the Roll-up Cases resulting from the scenario assumptions will be determined by the EIPC members based on their individual assessments and input from Stakeholders 2013 New York Independent System Operator, Inc. All Rights Reserved. DRAFT FOR DISCUSSION PURPOSES ONLY 19

20 Number of Scenarios Up to 3 scenarios per biennial study cycle, with a 10 year study horizon A scenario is a consistent set of input assumptions defining a future state which may vary from the base roll-up case May require additional sensitivities May include seasonal analyses using a different roll-up model (e.g. off-peak or shoulder peak model) The magnitude of the effort involved to analyze the scenario may reduce the number of scenarios that can be considered in each study cycle 2013 New York Independent System Operator, Inc. All Rights Reserved. DRAFT FOR DISCUSSION PURPOSES ONLY 20

21 Sample Scenario 1 Scenario Title: Inter-Regional Capabilities and Constraints during Winter Conditions Scenario Submitted by: Example Scenario 1 Study Case: 2018 Winter Peak 2013 New York Independent System Operator, Inc. All Rights Reserved. DRAFT FOR DISCUSSION PURPOSES ONLY 21

22 Sample Scenario 1 General Description and Premise This scenario would assess the Eastern Interconnection s ability to transfer large amounts of power among regions of interest during winter peak conditions The 2018 model year would incorporate the generation retirements and other system changes associated with the implementation of the EPA MATS rules. Winter operations are growing in complexity as gas-fired generation, renewables, and demand-side options continue to increase as percentage of the overall generation mix. This scenario would provide both an assessment of interregional capabilities and constraints for 2018 winter conditions, and also would provide suitable modeling to enable independent analysis by transmission planners and other industry analysts New York Independent System Operator, Inc. All Rights Reserved. DRAFT FOR DISCUSSION PURPOSES ONLY 22

23 Sample Scenario 1 Questions to be Answered Based on Power Flow Analysis: What constraints arise when renewables, gas generation, etc. are transferred during winter conditions? These are important so the EIPC can understand the objective of the study Modeling Parameters: Provides the details of what is to be studied Resource Modifications: Details how resources change in the scenario to be studied 2013 New York Independent System Operator, Inc. All Rights Reserved. DRAFT FOR DISCUSSION PURPOSES ONLY 23

24 Sample Scenario 2 Scenario Title: Inter-Regional Capabilities and Constraints during Spring Peak Conditions Scenario Submitted by: Example Scenario 2 Study Case: 2018 Spring Peak 2013 New York Independent System Operator, Inc. All Rights Reserved. DRAFT FOR DISCUSSION PURPOSES ONLY 24

25 Sample Scenario 2 General Description and Premise This scenario would assess the Eastern Interconnection s ability to transfer large amounts of power among regions of interest during spring peak conditions. The 2018 model year would incorporate the generation retirements and other system changes associated with the implementation of the EPA MATS rules. Spring operations are growing in complexity as gas-fired generation, renewables, and demand-side options continue to increase as percentage of the overall generation mix. Generation resources are more likely to be off-line due to lower loads and due to maintenance outages. Wind resources generally have higher capacity factors while solar resources have shorter production hours than summer but higher than winter New York Independent System Operator, Inc. All Rights Reserved. DRAFT FOR DISCUSSION PURPOSES ONLY 25

26 Sample Scenario 2 Questions to be Answered Based on Power Flow Analysis: What constraints arise when renewables, gas generation, etc. are transferred during spring conditions? Modeling Parameters: Provides the details of what is to be studied Resource Modifications: Details how resources change in the scenario to be studied 2013 New York Independent System Operator, Inc. All Rights Reserved. DRAFT FOR DISCUSSION PURPOSES ONLY 26

27 Next Steps EIPC Schedule December 2013 to February 2014 Regional meetings to discuss stakeholder feedback on possible scenarios and selection January 31, 2014 Stakeholder input on possible scenarios due February 26, 2014 EIPC Webinar to discuss stakeholder feedback on scenario options and finalize scenarios to be studied in New York Independent System Operator, Inc. All Rights Reserved. DRAFT FOR DISCUSSION PURPOSES ONLY 27

28 Next Steps EIPC Schedule March 7, 2014 Stakeholder final comments on the scenarios due to regional process March 2014 EIPC consideration of comments on scenario selection and final determination of scenarios March 28, 2014 Final scenario descriptions and 2014 schedule posted March 31, 2014 EIPC PAs begin work on scenarios 2013 New York Independent System Operator, Inc. All Rights Reserved. DRAFT FOR DISCUSSION PURPOSES ONLY 28

29 EIPC Supporting Activities CEII: Continue to make EIPC models available to those who have completed the EIPC CEII process NYISO stakeholders use NYISO CEII Request Form and NDA Website: Continue to host the EIPC website Review current EIPC website and recommended modifications as appropriate Post material from both grant and non-grant EIPC activities 2013 New York Independent System Operator, Inc. All Rights Reserved. DRAFT FOR DISCUSSION PURPOSES ONLY 29

30 2013 New York Independent System Operator, Inc. All Rights Reserved. DRAFT FOR DISCUSSION PURPOSES ONLY 30

Cost Allocation Principles for Seams Transmission Expansion Projects

Cost Allocation Principles for Seams Transmission Expansion Projects Cost Allocation Principles for Seams Transmission Expansion Projects SPP s seams agreements currently contain requirements for SPP to develop coordinated system plans with its neighbors. The extent and

More information

EIPC GAS-ELECTRIC SYSTEM INTERFACE STUDY

EIPC GAS-ELECTRIC SYSTEM INTERFACE STUDY EIPC GAS-ELECTRIC SYSTEM INTERFACE STUDY Status Update Mark Babula Principal Engineer System Planning ISO New England Inc. NPCC Governmental/Regulatory Affairs Advisory Group December 3, 2013 Table of

More information

1. MARS Base Case Model Assumptions

1. MARS Base Case Model Assumptions 1. MARS Base Case Model Assumptions 1.1 Load s Peak Load Load Shape Load Forecast Uncertainty 2014 IRM Model Assumptions October 1, 2013 forecast NYCA: 33,655 MW NYC: 11,740 MW Long Island 5,461 MW Multiple

More information

Assumption Matrix. Electric System Planning Working Group April 5, 2012 Rensselaer, N.Y.

Assumption Matrix. Electric System Planning Working Group April 5, 2012 Rensselaer, N.Y. 2012 RNA Assumption Matrix Howard Tarler Manager, Long Term Planning New York Independent System Operator Electric System Planning Working Group April 5, 2012 Rensselaer, N.Y. 2012 New York Independent

More information

NORTHEASTERN ISO/RTO PLANNING COORDINATION PROTOCOL DESIGNATION OF FILING PARTY

NORTHEASTERN ISO/RTO PLANNING COORDINATION PROTOCOL DESIGNATION OF FILING PARTY NORTHEASTERN ISO/RTO PLANNING COORDINATION PROTOCOL DESIGNATION OF FILING PARTY The Northeastern ISO/RTO Planning Coordination Protocol among PJM Interconnection, L.L.C. ( PJM ), the New York Independent

More information

PJM & MISO Assumptions and Criteria for Testing of New Resources

PJM & MISO Assumptions and Criteria for Testing of New Resources & Assumptions and Criteria for Testing of New Resources 1 Introduction These slides provide a description and comparison of the assumptions and criteria used by and during the study of customer proposed

More information

Real-Time Reserves. Vince Stefanowicz Sr. Lead Engineer, Generation Operating Committee May 1, PJM 2018

Real-Time Reserves. Vince Stefanowicz Sr. Lead Engineer, Generation Operating Committee May 1, PJM 2018 Real-Time Reserves Vince Stefanowicz Sr. Lead Engineer, Generation Operating Committee May 1, 2018 Timeline / Work Plan OC (3/6/18) Education OC (4/3/18) Education Feedback OC (5/1/18) Review Analysis

More information

NYISO Posting for FERC Order 890 Describing the NYISO Planning Process

NYISO Posting for FERC Order 890 Describing the NYISO Planning Process NYISO Posting for FERC Order 890 Describing the NYISO Planning Process September 14, 2007 ` NYISO Posting for FERC Order 890 Filing DRAFT Table of Contents Section: Page No: I. Cover Memo - Draft OATT

More information

1st Qua u r a ter e M e M e e t e in i g 2nd Qua u r a ter e M e M e e t e in i g

1st Qua u r a ter e M e M e e t e in i g 2nd Qua u r a ter e M e M e e t e in i g 2012 SERTP Welcome SERTP 2012 First RPSG Meeting & Interactive Training Session 1 2012 SERTP The SERTP process is a transmission planning process. Please contact the respective transmission provider for

More information

New Member Cost Allocation Review Process. Prepared by: COST ALLOCATION WORKING GROUP

New Member Cost Allocation Review Process. Prepared by: COST ALLOCATION WORKING GROUP New Member Cost Allocation Review Process Prepared by: COST ALLOCATION WORKING GROUP TABLE OF CONTENTS 1. HISTORY AND BACKGROUND... 1 2. PURPOSE / GOAL STATEMENT... 3 3. OVERVIEW OF PROCESS... 3 4. NEW

More information

EE in System Forecasting

EE in System Forecasting EE in System Forecasting NEEP Forum Annual Meeting, Washington, DC December 12, 2012 Paul Peterson www.synapse-energy.com 2012 Synapse Energy Economics Inc. All rights reserved. Synapse Energy Economics

More information

Installed Capacity (ICAP) Market

Installed Capacity (ICAP) Market Installed Capacity (ICAP) Market Amanda Carney Associate Market Design Specialist, Capacity Market Design, NYISO New York Market Orientation Course (NYMOC) October 16-19, 2018 Rensselaer, NY 1 ICAP Market

More information

PJM SERTP Planning Process Overview

PJM SERTP Planning Process Overview PJM SERTP Planning Process Overview Order 1000 Biennial Regional Transmission Plan Review Meeting Presentation 1 of 2 May 8 th, 2018 Georgia Power Corporate Headquarters Atlanta, GA PJM SERTP Interregional

More information

NPCC 2017 MARITIMES AREA INTERIM REVIEW OF RESOURCE ADEQUACY

NPCC 2017 MARITIMES AREA INTERIM REVIEW OF RESOURCE ADEQUACY NPCC 2017 MARITIMES AREA INTERIM REVIEW OF RESOURCE ADEQUACY NEW BRUNSWICK POWER CORP. NOVA SCOTIA POWER INC. MARITIME ELECTRIC COMPANY, LIMITED NORTHERN MAINE ISA, INC. Approved by RCC December 5, 2017

More information

History of Cost Allocation within MISO RECB TF. January 29, 2015

History of Cost Allocation within MISO RECB TF. January 29, 2015 History of Cost Allocation within MISO RECB TF January 29, 2015 Cost Allocation FERC Orders, Filings, and Rulings Cost allocation for MISO began with Order 2003 which instituted a pro forma Generator Interconnection

More information

Year Assessment Preliminary Study Design

Year Assessment Preliminary Study Design 2015 10-Year Assessment Preliminary Study Design October 15, 2014 Stakeholder and Customer Webcast atcllc.com Purpose Solicit pre-study Comments 2015 Assessment Process 2015 Assessment Assumptions Public

More information

FERC Order 1000: Transmission Planning & Cost Allocation Framework for NYISO Compliance

FERC Order 1000: Transmission Planning & Cost Allocation Framework for NYISO Compliance FERC Order 1000: Transmission Planning & Cost Allocation Framework for NYISO Compliance by John P Buechler NYISO Executive Regulatory Policy Advisor Joint IPTF/ESPWG Meeting February 27, 2012 Albany, NY

More information

MISO Planning Process. May 31, 2013

MISO Planning Process. May 31, 2013 MISO Planning Process May 31, 2013 MISO Planning Objectives Fundamental Goal The development of a comprehensive expansion plan that meets reliability needs, policy needs, and economic needs MISO Board

More information

FERC Order 1000: Transmission Planning & Cost Allocation NYISO Compliance Update

FERC Order 1000: Transmission Planning & Cost Allocation NYISO Compliance Update FERC Order 1000: Transmission Planning & Cost Allocation NYISO Compliance Update by John P. Buechler NYISO Executive Regulatory Policy Advisor NPCC Governmental/Regulatory Affairs Advisory Group November

More information

Generation Retirement Scenario Special Assessment Update

Generation Retirement Scenario Special Assessment Update Generation Retirement Scenario Special Assessment Update John Moura, Director, Reliability Assessments and Technical Committees Member Representatives Committee Meeting November 6, 2018 Assessment Objectives

More information

Transmission Cost Allocation

Transmission Cost Allocation Transmission Cost Allocation IPSAC February 2, 2010 John P. Buechler NYISO Executive Regulatory Policy Advisor Background FERC Policy has evolved Order 888 No Planning Requirement for ISOs Order 2000 Planning

More information

Cricket Valley Energy Project: Security- Constrained Economic Dispatch Analysis

Cricket Valley Energy Project: Security- Constrained Economic Dispatch Analysis GE Energy Cricket Valley Energy Project: Security- Constrained Economic Dispatch Analysis Prepared for: GE Energy Global Development and Strategic Initiatives Prepared by: Energy Consulting (May 20, 2011

More information

SPP s Regional Review of SPP-MISO Coordinated System Plan Recommended Interregional Projects

SPP s Regional Review of SPP-MISO Coordinated System Plan Recommended Interregional Projects SPP s Regional Review of SPP-MISO Coordinated System Plan Recommended Interregional Projects January 4, 2016 SPP Interregional Relations Table of Contents Executive Summary... 2 Introduction... 5 Stakeholder

More information

Generation Retirement Scenario

Generation Retirement Scenario Generation Retirement Scenario Special Reliability Assessment December 18, 2018 NERC Report Title Report Date I Table of Contents Preface... iii Executive Summary... v Key Findings... vii Recommendations...

More information

Rate Schedules and Seams Agreements Tariff

Rate Schedules and Seams Agreements Tariff Rate Schedules and Seams Agreements Tariff Southwest Power Pool Rate Schedules and Seams Agreements Tariff Document Generated On: 8/20/2015 Southwest Power Pool - Rate Schedules and Seams Agreements Tariff

More information

Long-Term Reliability Assessment

Long-Term Reliability Assessment Long-Term Reliability Assessment Key Findings and Long-Term Issues John Moura, Director of Reliability Assessment Topics Covered Today Background on NERC s Long-Term Reliability Assessment Emerging and

More information

Estimating Capacity Benefits of the AC Transmission Public Policy Projects

Estimating Capacity Benefits of the AC Transmission Public Policy Projects Memorandum TO: NYISO Board of Directors FROM: David B. Patton and Pallas LeeVanSchaick DATE: RE: Estimating Capacity Benefits of the AC Transmission Public Policy Projects A. Introduction In the second

More information

Seams Cost Allocation: A Flexible Framework to Support Interregional Transmission Planning (Summary of Final Report)

Seams Cost Allocation: A Flexible Framework to Support Interregional Transmission Planning (Summary of Final Report) Seams Cost Allocation: A Flexible Framework to Support Interregional Transmission Planning (Summary of Final Report) Presented at: SPP RSC Quarterly Meeting Presented by: Johannes Pfeifenberger Delphine

More information

FTR Alignment. Joint Stakeholder Meeting June 6, 2008

FTR Alignment. Joint Stakeholder Meeting June 6, 2008 FTR Alignment Joint Stakeholder Meeting June 6, 2008 Introduction Joint Common Market Initiative As part of the of the Midwest ISO and PJM Joint and Common Market (JCM) process, the Midwest ISO stakeholders

More information

Stakeholder Survey I Cross Border Cost Allocation for Economic Transmission Projects For Discussion September 24, 2008

Stakeholder Survey I Cross Border Cost Allocation for Economic Transmission Projects For Discussion September 24, 2008 PJM and the Midwest ISO are seeking input from stakeholders on various concepts that have been discussed during the PJM/Midwest ISO Cross-Border meetings for dealing with transmission projects constructed

More information

NPCC Regional Reliability Reference Directory # 5 Reserve

NPCC Regional Reliability Reference Directory # 5 Reserve NPCC Regional Reliability Reference Directory # 5 Task Force on Coordination of Operations Revision Review Record: December 2 nd, 2010 October 11 th, 2012 Adopted by the Members of the Northeast Power

More information

April 6, 2018 VIA OVERNIGHT MAIL. Sheri Young, Secretary of the Board National Energy Board th Avenue SW Calgary, Alberta T2R 0A8

April 6, 2018 VIA OVERNIGHT MAIL. Sheri Young, Secretary of the Board National Energy Board th Avenue SW Calgary, Alberta T2R 0A8 !! April 6, 2018 VIA OVERNIGHT MAIL Sheri Young, Secretary of the Board National Energy Board 517 10 th Avenue SW Calgary, Alberta T2R 0A8 Re: North American Electric Reliability Corporation Dear Ms. Young:

More information

TABLE OF CONTENTS ARTICLE ONE: RECITALS... 5 ARTICLE TWO: ABBREVIATIONS, ACRONYMS, AND DEFINITIONS... 6 ARTICLE THREE: OPERATING COMMITTEE...

TABLE OF CONTENTS ARTICLE ONE: RECITALS... 5 ARTICLE TWO: ABBREVIATIONS, ACRONYMS, AND DEFINITIONS... 6 ARTICLE THREE: OPERATING COMMITTEE... TABLE OF CONTENTS ARTICLE ONE: RECITALS... 5 ARTICLE TWO: ABBREVIATIONS, ACRONYMS, AND DEFINITIONS... 6 2.1 Abbreviations and Acronyms... 6 2.2 Definitions... 7 2.3 Rules of Construction... 10 ARTICLE

More information

Planning in a competitive market environment

Planning in a competitive market environment Planning in a competitive market environment The New York Story Rana Mukerji Senior Vice President - Market Structures New York Independent System Operator Harvard Electricity Policy Group 74 th Plenary

More information

Transmission Loss Factor Methodology

Transmission Loss Factor Methodology Transmission Loss Factor Methodology Discussion Paper Operations & Reliability Draft February 9, 2005 Table of Contents 1. Introduction...3 1.1 Legislative Direction.....3 1.2 Goal and Objectives... 3

More information

MISO PJM IPSAC. August 26, PJM IPSAC Meeting, August 26,

MISO PJM IPSAC. August 26, PJM IPSAC Meeting, August 26, MISO PJM IPSAC August 26, 2016 1 Agenda 2 Targeted Market Efficiency Project (TMEP) Study TMEP Proposed JOA Language FERC EL13-88 Filings IPSAC Work Schedule 2 3 Targeted Market Efficiency Project Study

More information

PJM/MISO Cost Allocation For Economic Upgrades

PJM/MISO Cost Allocation For Economic Upgrades PJM/MISO Cost Allocation For Economic Upgrades Stakeholder Meeting Hilton Baltimore BWI, Baltimore MD May 19, 2008 1 Topics for Discussion Background FERC Order / Schedule (RTO Staffs) Review Internal

More information

BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION SOUTHWESTERN PUBLIC SERVICE COMPANY S UNOPPOSED RESPONSE TO STAFF S COMMENTS

BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION SOUTHWESTERN PUBLIC SERVICE COMPANY S UNOPPOSED RESPONSE TO STAFF S COMMENTS BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION IN THE MATTER OF SOUTHWESTERN ) PUBLIC SERVICE COMPANY S 2018 ) INTEGRATED RESOURCE PLAN FOR ) NEW MEXICO. ) CASE NO. 18-00215-UT ) SOUTHWESTERN PUBLIC

More information

NERC TPL Standard Overview

NERC TPL Standard Overview NERC TPL-001-4 Standard Overview Attachment K Quarter 3 Stakeholder s Meeting September 29, 2016 1 Background New NERC TPL Standard 2016 TPL Plan and Status Update 2015 Planning Assessment Results Compliance

More information

Balance-of-Period TCC Auction

Balance-of-Period TCC Auction Balance-of-Period TCC Auction Proposed Credit Policy Sheri Prevratil Manager, Corporate Credit New York Independent System Operator Credit Policy Working Group May 29, 2015 2000-2015 New York Independent

More information

September 30th, 2013 Dave and TFSS, Please find attached final responses to the clarification requests on the NPCC Regional Standard for Automatic UFLS PRC -006-NPCC-1 as reviewed and approved during the

More information

Appendix B-2. Term Sheet for Tolling Agreements. for For

Appendix B-2. Term Sheet for Tolling Agreements. for For Appendix B-2 Term Sheet for Tolling Agreements for For 2015 Request For Proposals For Long-Term Developmental Combined-Cycle Gas Turbineand Existing Capacity and Energy Resources in WOTAB DRAFT Entergy

More information

Cost Allocation Reform Update

Cost Allocation Reform Update Cost Allocation Reform Update Regional Expansion Criteria and Benefits Working Group May 18, 2017 Conditions Precedent for Regional Transmission Investment 1. Increased consensus regarding the issue(s)

More information

ITP Evaluation Process Plan

ITP Evaluation Process Plan ITP Evaluation Process Plan HVDC Conversion Project The goal of the coordinated Interregional Transmission Project (ITP) evaluation process is to achieve consistent planning assumptions and technical data

More information

Defining Generator Outage States DRAFT Tariff Proposed Amendments. Shaded material in blue text is updated since the 2/12/14 BIC.

Defining Generator Outage States DRAFT Tariff Proposed Amendments. Shaded material in blue text is updated since the 2/12/14 BIC. Defining Generator Outage States DRAFT Tariff Proposed Amendments Shaded material in blue text is updated since the 2/12/14 BIC. This version includes proposed amendments to Attachment H to the Services

More information

NTTG REGIONAL TRANSMISSION PLAN. December 30, 2015

NTTG REGIONAL TRANSMISSION PLAN. December 30, 2015 NTTG 2014-2015 REGIONAL TRANSMISSION PLAN December 30, 2015 1 Table of Contents Executive Summary... 3 Introduction... 3 The Northern Tier Transmission Group... 3 Participating Utilities... 4 Purpose of

More information

MOD Demand and Energy Data. Darrel Richardson, NERC Senior Standards Developer Jeff Rooker, SPP RE Lead Compliance Engineer May 12, 2016

MOD Demand and Energy Data. Darrel Richardson, NERC Senior Standards Developer Jeff Rooker, SPP RE Lead Compliance Engineer May 12, 2016 MOD-031-2 Demand and Energy Data Darrel Richardson, NERC Senior Standards Developer Jeff Rooker, SPP RE Lead Compliance Engineer May 12, 2016 Administrative Items NERC Antitrust Guidelines It is NERC s

More information

FTR Credit Requirements Prevailing Flow Paths Affected by Transmission System Upgrades

FTR Credit Requirements Prevailing Flow Paths Affected by Transmission System Upgrades FTR Credit Requirements Prevailing Flow Paths Affected by Transmission System Upgrades Hal Loomis Manager, Credit Markets & Reliability Committee December 7, 2017 Credit Risk Exposure Issue Description

More information

Information Document Available Transfer Capability and Transfer Path Management ID # R

Information Document Available Transfer Capability and Transfer Path Management ID # R Information Documents are not authoritative. Information Documents are for information purposes only and are intended to provide guidance. In the event of any discrepancy between an Information Document

More information

MTEP16 Futures Development Workshop 1/15/15

MTEP16 Futures Development Workshop 1/15/15 MTEP16 Futures Development Workshop 1/15/15 Overview Objectives MTEP16 proposed futures Uncertainty variables definitions Next steps 2 Objective Ensure MTEP16 Futures are effective and are developed in

More information

Lower Voltage Interregional Economic Projects. RECBWG April 18, 2018

Lower Voltage Interregional Economic Projects. RECBWG April 18, 2018 Lower Voltage Interregional Economic Projects RECBWG April 18, 2018 Interregional Gaps & Inconsistencies 1. No tariff defined cost allocation for sub 345 kv economic projects with PJM 2. Economic projects

More information

NYISO 2009 Comprehensive Reliability Plan (CRP)

NYISO 2009 Comprehensive Reliability Plan (CRP) NYISO 2009 Comprehensive Reliability Plan (CRP) John P. Buechler NYISO Executive Regulatory Policy Advisor NPCC Governmental & Regulatory Affairs Advisory Group Meeting May 21, 2009 NYC Overview: 2009

More information

Long Run Marginal Cost (LRMC)

Long Run Marginal Cost (LRMC) Long Run Marginal Cost (LRMC) Ryan Steele Power Supply Planning Specialist Agenda & Objectives Preliminary Discussion PART I Provide a historic overview of FBC s LRMC Highlights from BC Hydro s stated

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION New York Independent System Operator, Inc. ) PJM Interconnection, L.L.C. ) Docket Nos. ER17-905-002 ) MOTION FOR LEAVE TO ANSWER

More information

SPP New Member Communication and Integration Process. Mountain West Transmission Group. Background Information October 2017

SPP New Member Communication and Integration Process. Mountain West Transmission Group. Background Information October 2017 1 SPP New Member Communication and Integration Process Mountain West Transmission Group Background Information October 2017 Contents Introduction... 2 1. Westside Tariff Design... 2 2. Operational Provisions...

More information

10-YEAR COSTS AND BENEFITS TO SPP MEMBERS OF INTEGRATING MOUNTAIN WEST TRANSMISSION GROUP Quantitative Analysis of Costs and Benefits

10-YEAR COSTS AND BENEFITS TO SPP MEMBERS OF INTEGRATING MOUNTAIN WEST TRANSMISSION GROUP Quantitative Analysis of Costs and Benefits 10-YEAR COSTS AND BENEFITS TO SPP MEMBERS OF INTEGRATING MOUNTAIN WEST TRANSMISSION GROUP Quantitative Analysis of Costs and Benefits Published on March 19, 2018 By SPP Staff REVISION HISTORY DATE OR VERSION

More information

MISO Cost Allocation Response. RECBWG February 15, 2018

MISO Cost Allocation Response. RECBWG February 15, 2018 MISO Cost Allocation Response RECBWG February 15, 2018 MISO Cost Allocation Response: February 2018 Context The overall objective of the MISO transmission cost allocation methodology is to align who pays

More information

MEMORANDUM OF UNDERSTANDING

MEMORANDUM OF UNDERSTANDING MEMORANDUM OF UNDERSTANDING This Memorandum of Understanding ( MOU ) is made effective as of January 30, 2019 among Central Maine Power Company, a Maine corporation with offices located at 83 Edison Drive,

More information

2019 Integrated Resource Plan (IRP) Public Input Meeting January 24, 2019

2019 Integrated Resource Plan (IRP) Public Input Meeting January 24, 2019 1 2019 Integrated Resource Plan (IRP) Public Input Meeting January 24, 2019 Agenda January 24 9:00am-9:30am pacific Capacity-Contribution Values for Energy-Limited Resources 9:30am-11:30am pacific Coal

More information

2018 ERO Enterprise Metrics

2018 ERO Enterprise Metrics 2018 ERO Enterprise Metrics Metrics In support of the ERO Enterprise s goals, there are six reliability metrics to measure achievement of a highly reliable and secure bulk power system (BPS). There is

More information

PEAK RELIABILITY COORDINATOR FUNDING

PEAK RELIABILITY COORDINATOR FUNDING PEAK RELIABILITY COORDINATOR FUNDING Straw Proposal May 8, 2015 Assessment of 2 Peak Reliability Coordinator Charges Straw Proposal Table of Contents 1 Introduction... 3 2 Background... 3 3 Plan for Stakeholder

More information

Proposal for FERC Fee Recovery

Proposal for FERC Fee Recovery Proposal for FERC Fee Recovery Cheryl Hussey Vice President & Chief Financial Officer New York Independent System Operator Chris Russell Manager Customer Settlements New York Independent System Operator

More information

PRC Remedial Action Schemes

PRC Remedial Action Schemes PRC-012-2 Remedial Action Schemes A. Introduction 1. Title: Remedial Action Schemes 2. Number: PRC-012-2 3. Purpose: To ensure that Remedial Action Schemes (RAS) do not introduce unintentional or unacceptable

More information

Southwest Power Pool, Inc. Policy Recommendation for the SPP Board of Directors and Members Committee. March 6, 2018 Mountain West Transmission Group

Southwest Power Pool, Inc. Policy Recommendation for the SPP Board of Directors and Members Committee. March 6, 2018 Mountain West Transmission Group Southwest Power Pool, Inc. Policy for the SPP Board of Directors and Members Committee Policy Area #1 DC Ties March 6, 2018 Mountain West Transmission Group SPP and MWTG anticipate that incorporating the

More information

AC TRANSMISSION PUBLIC POLICY TRANSMISSION NEEDS PROJECT SOLICITATION Response due April 29, 2016

AC TRANSMISSION PUBLIC POLICY TRANSMISSION NEEDS PROJECT SOLICITATION Response due April 29, 2016 10 Krey Boulevard Rensselaer, NY 12144 AC TRANSMISSION PUBLIC POLICY TRANSMISSION NEEDS PROJECT SOLICITATION Response due April 29, 2016 Dear NYISO Stakeholder or Interested Party: February 29, 2016 With

More information

CASA-1000 Project List of FAQs

CASA-1000 Project List of FAQs 1. What is the objective of the project? CASA-1000 Project List of FAQs The objective of the CASA-1000 project is to provide for the export of the available summer electricity surpluses from Tajikistan

More information

The cost allocation principles and methodologies in this Attachment Y cover only

The cost allocation principles and methodologies in this Attachment Y cover only 31.5 Cost Allocation and Cost Recovery 31.5.1 The Scope of Attachment Y Cost Allocation 31.5.1.1 Regulated Responses The cost allocation principles and methodologies in this Attachment Y cover only regulated

More information

Mountain West Transmission Group (MWTG) Introduction and Process

Mountain West Transmission Group (MWTG) Introduction and Process Mountain West Transmission Group (MWTG) Introduction and Process October 13 Denver, CO October 16 Little Rock, AR 2 Agenda Overview of SPP Overview of the MWTG Members SPP Process New Member Integration

More information

Flexible Capacity Procurement. Market and Infrastructure Policy Issue Paper

Flexible Capacity Procurement. Market and Infrastructure Policy Issue Paper Flexible Capacity Procurement Market and Infrastructure Policy Issue Paper January 27, 2012 Discussion Paper Table of Contents 1 Introduction... 3 2 Background... 4 2.1 ISO Renewable Integration Studies...

More information

Filed with the Iowa Utilities Board on May 31, 2017, E STATE OF IOWA DEPARTMENT OF COMMERCE UTILITIES BOARD

Filed with the Iowa Utilities Board on May 31, 2017, E STATE OF IOWA DEPARTMENT OF COMMERCE UTILITIES BOARD STATE OF IOWA DEPARTMENT OF COMMERCE UTILITIES BOARD IN RE: MIDAMERICAN ENERGY IN RE: DOCKET NOS. E-22269, E-22270, AND E-22271 DOCKET NO. E-22279 (consolidated) ITC MIDWEST LLC BRIEF BY THE MIDCONTINENT

More information

NYISO 2018 BUDGET OVERVIEW

NYISO 2018 BUDGET OVERVIEW NYISO 2018 BUDGET OVERVIEW Alan Ackerman Customized Energy Solutions Chair, Budget & Priorities Working Group Management Committee October 25, 2017 Rensselaer, NY This presentation is unchanged from the

More information

2017 Metrics with Historical Data

2017 Metrics with Historical Data 2017 Metrics with Historical Data Metrics In support of the ERO Enterprise s goals, there are six reliability metrics to measure progress on reliability improvement. There is also one metric to measure

More information

D. RSCP SUPPLIER PAYMENTS AND CUSTOMER RATES

D. RSCP SUPPLIER PAYMENTS AND CUSTOMER RATES 32 RSCP SUPPLIER PAYMENTS AND CUSTOMER RATES D. RSCP SUPPLIER PAYMENTS AND CUSTOMER RATES This summary is provided for bidder convenience only. Any statements herein describing BGS- RSCP rates or supplier

More information

REPORT TO THE PUBLIC UTILITIES BOARD

REPORT TO THE PUBLIC UTILITIES BOARD REPORT TO THE PUBLIC UTILITIES BOARD CURTAILABLE RATE PROGRAM APRIL 1, 2011 MARCH 31, 2012 JULY 2012 TABLE OF CONTENTS Page No. SUMMARY... 1 BACKGROUND... 1 PERFORMANCE FOR 2011/12... 3 Curtailment Options...3

More information

APS/SRP Stakeholder Meeting For Transmission Planning

APS/SRP Stakeholder Meeting For Transmission Planning APS/SRP Stakeholder Meeting For Transmission Planning FERC Order 890 SRP Attachment K APS Attachment E SRP Facility Scottsdale, AZ December 15 th, 2017 9:00 11:00 A.M. Agenda 1. Welcome, Introductions,

More information

Special Pricing Rule Updates

Special Pricing Rule Updates Special Pricing Rule Updates Michael DeSocio Manager, Energy Market Design New York Independent System Operator Business Issues Committee September 18, 2013 NYISO KCC Conference Center 2013 New York Independent

More information

Transmission Planning Standards Industry Webinar: Footnote b. January 8, 2012 John Odom, FRCC, Standard Drafting Team Chair

Transmission Planning Standards Industry Webinar: Footnote b. January 8, 2012 John Odom, FRCC, Standard Drafting Team Chair Transmission Planning Standards Industry Webinar: Footnote b January 8, 2012 John Odom, FRCC, Standard Drafting Team Chair Topics Brief history Overview of as posted draft standard Changes since last posting

More information

FERC Order 1000: Planning for the Right of First Refusal and Planning for Public Policy Status & Implementation in New York

FERC Order 1000: Planning for the Right of First Refusal and Planning for Public Policy Status & Implementation in New York 1 FERC Order 1000: Planning for the Right of First Refusal and Planning for Public Policy Status & Implementation in New York Henry Chao Vice President - System and Resource Planning New York Independent

More information

PEAK RELIABILITY COORDINATOR FUNDING. Draft Final Proposal. May 28, 2015

PEAK RELIABILITY COORDINATOR FUNDING. Draft Final Proposal. May 28, 2015 PEAK RELIABILITY COORDINATOR FUNDING Draft Final Proposal May 28, 2015 2 Assessment of Peak Reliability Coordinator Charges Draft Final Proposal Table of Contents 1 Introduction... 3 2 Background... 3

More information

Comments of Pacific Gas & Electric Company Energy Imbalance Market Draft Tariff Language

Comments of Pacific Gas & Electric Company Energy Imbalance Market Draft Tariff Language Comments of Pacific Gas & Electric Company Energy Imbalance Market Draft Tariff Language Submitted by Company Date Submitted Will Dong Paul Gribik (415) 973-9267 (415) 973-6274 PG&E December 5, 2013 Pacific

More information

Regional Transmission Organization Frequently Asked Questions

Regional Transmission Organization Frequently Asked Questions 1. The CRA analysis showed greater trade benefits to the Entergy region from joining SPP rather than joining MISO. Did Entergy re-do the CRA analysis? No. The CRA analysis was a key component of the Entergy

More information

NERC Probabilistic Assessment

NERC Probabilistic Assessment NERC Probabilistic Assessment Addendum to the 2012 Long-Term Reliability Assessment June 2013 1 of 35 3353 Peachtree Road NE Suite 600, North Tower Atlanta, GA 30326 404-446-2560 Table of Contents Introduction...

More information

ATC Customer Benefit Metric

ATC Customer Benefit Metric ATC Customer Benefit Metric Marty Smith ATC Economic Planning April 5, 2012 Helping to keep the lights on, businesses running and communities strong Background ATC has used the Customer Benefit (CB) Metric

More information

SCHEDULE 85 COGENERATION AND SMALL POWER PRODUCTION STANDARD CONTRACT RATES

SCHEDULE 85 COGENERATION AND SMALL POWER PRODUCTION STANDARD CONTRACT RATES IDAHO POWER COMPANY FOURTH REVISED SHEET NO. 85-1 THIRD REVISED SHEET NO. 85-1 AVAILABILITY Service under this schedule is available for power delivered to the Company's control area within the State of

More information

Implementation of BAL Dede Subakti

Implementation of BAL Dede Subakti Implementation of BAL-002-2 Dede Subakti Agenda Background information Impact assessment Issue statement Implementation options Request for comments Page 2 Background Information NERC BAL-002-2 was approved

More information

Two-Tier Real-Time Bid Cost Recovery. Margaret Miller Senior Market and Product Economist Convergence Bidding Stakeholder Meeting October 16, 2008

Two-Tier Real-Time Bid Cost Recovery. Margaret Miller Senior Market and Product Economist Convergence Bidding Stakeholder Meeting October 16, 2008 Two-Tier Real-Time Bid Cost Recovery Margaret Miller Senior Market and Product Economist Convergence Bidding Stakeholder Meeting October 16, 2008 The CAISO has posted an Issue Paper exploring the redesign

More information

Constellation Energy Comments on Proposed OTC Reforms

Constellation Energy Comments on Proposed OTC Reforms Constellation Energy Comments on Proposed OTC Reforms Constellation Energy Key Facts Constellation Energy is a Fortune 500 company (#125 on the 2009 list). Over 26,500 MW 2008 peak load served to retail

More information

ICForecast: Strategic Power Outlook. Q Sample

ICForecast: Strategic Power Outlook. Q Sample ICForecast: Strategic Power Outlook Q1 2015 - Sample 2015 ICF International, Inc. Any views or opinions expressed in this paper are solely those of the author(s) and do not necessarily represent those

More information

10-day Formal Comment Period with a 5-day Additional Ballot (if necessary), pursuant to a Standards Committee authorized waiver.

10-day Formal Comment Period with a 5-day Additional Ballot (if necessary), pursuant to a Standards Committee authorized waiver. Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

Organization of MISO States Response to the Midwest ISO October Hot Topic on Pricing

Organization of MISO States Response to the Midwest ISO October Hot Topic on Pricing Organization of MISO States Response to the Midwest ISO October Hot Topic on Pricing I. Day Ahead and Real Time Energy and Ancillary Services Pricing Prices that Accurately Reflect the Marginal Cost of

More information

Gaps in Current Reserve Pricing Methodology

Gaps in Current Reserve Pricing Methodology Gaps in Current Reserve Pricing Methodology Lisa Morelli Manager, Real-Time Market Operations Energy Price Formation Senior Task Force March 29, 2018 Gap 1: Reserve Zone Modeling Current modeling of Mid-Atlantic

More information

Northern Tier Transmission Group Cost Allocation Principles Work Group. Straw Proposal. May 29, 2007

Northern Tier Transmission Group Cost Allocation Principles Work Group. Straw Proposal. May 29, 2007 Northern Tier Transmission Group Cost Allocation Principles Work Group Straw Proposal May 29, 2007 NTTG Cost Allocation Principles and Process page 1 INTRODUCTION This paper makes a strawman proposal responsive

More information

Procedure for ERO Support of Frequency Response and Frequency Bias Setting Standard

Procedure for ERO Support of Frequency Response and Frequency Bias Setting Standard Procedure for ERO Support of Frequency Response and Frequency Bias Setting Standard NERC Report Title Report Date I Table of Contents Preface... iii Introduction...iiv Chapter 1: Event Selection Process...

More information

NYISO Technical Bulletins A list of retired TBs with links is at the link below

NYISO Technical Bulletins A list of retired TBs with links is at the link below NEW YORK INDEPENDENT SYSTEM OPERATOR NYISO Technical Bulletins A list of retired TBs with links is at the link below date of this document = 5/27/2011; most recent changes have dates in red TB # Version

More information

SPP PLANNING AND COST ALLOCATION OVERVIEW

SPP PLANNING AND COST ALLOCATION OVERVIEW Benefit/Cost Ratio Primer 101 for the Regional Allocation Review Task Force August 4, 2011 1 SPP PLANNING AND COST ALLOCATION OVERVIEW 2 1 Transmission = 10% Retail Electricity Rates Transmission enables

More information

2011 IRP Public Input Meeting. October 5, Pacific Power Rocky Mountain Power PacifiCorp Energy

2011 IRP Public Input Meeting. October 5, Pacific Power Rocky Mountain Power PacifiCorp Energy 2011 IRP Public Input Meeting October 5, 2010 Pacific Power Rocky Mountain Power PacifiCorp Energy Agenda Morning Session IRP Schedule Update Energy Gateway Transmission Construction Update and Evaluation

More information

Coos County Transmission Action Plan & Cost Allocation Methodologies

Coos County Transmission Action Plan & Cost Allocation Methodologies Coos County Transmission Action Plan & Cost Allocation Methodologies Presentation to the NCTC KEMA, Inc. June 17, 2010 Experience you can trust. Agenda Introduction to KEMA Project Objectives Status of

More information

NYISO s Compliance Filing to Order 745: Demand Response. Wholesale Energy Markets

NYISO s Compliance Filing to Order 745: Demand Response. Wholesale Energy Markets NYISO s Compliance Filing to Order 745: Demand Response Compensation in Organized Wholesale Energy Markets (Docket RM10-17-000) Donna Pratt NYISO Manager, Demand Response Products Market Issues Working

More information

MISO PJM IPSAC. December 2, Revised December 22, PJM IPSAC Meeting, December 2,

MISO PJM IPSAC. December 2, Revised December 22, PJM IPSAC Meeting, December 2, MISO PJM IPSAC December 2, 2016 Revised December 22, 2016 1 Agenda 2 TMEP Final JOA Language Recommended TMEPs Order No. 1000 Compliance Filing Generation Deactivation JOA Language PJM Proposal Window

More information

45-day Comment and Initial Ballot day Final Ballot. April, BOT Adoption. May, 2015

45-day Comment and Initial Ballot day Final Ballot. April, BOT Adoption. May, 2015 Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information