1 MISO Cost Allocation Response RECBWG February 15, 2018
2 MISO Cost Allocation Response: February 2018 Context The overall objective of the MISO transmission cost allocation methodology is to align who pays with who benefits over time from a regional transmission expansion perspective. MISO s cost allocation response is an incremental step forward, with some items needing more discussion. MISO will continue to work with stakeholders to achieve the overall objective and finalize the proposal. This response represents several potential changes that address identified cost allocation issues, seeks to improve the alignment of costs and benefits for future regional transmission projects, and considers the diverse positions of stakeholders. MISO is targeting filing any tariff changes by the third quarter of 2018, with an effective date of January 1, This is commensurate with the MISO South transition period expiring at the end of Unchanged Elements Multi-Value Projects (MVP): No changes Market Efficiency Projects (MEP): Benefit based allocation to all zones in MISO Benefit/Cost ratio that is greater than or equal to 1.25 Minimum cost threshold of $5M Recommended Changes to MEP Cost Allocation Lower MEP voltage threshold to 230kV Eliminate 20% postage stamp component from MEP cost allocation Create a tariff structure that allows for the inclusion of additional quantifiable benefit metrics as developed through the stakeholder process Develop new/modify existing provisions of the tariff to ensure reliability is not negatively affected as a result of other cost allocation changes (e.g., such as lowering the voltage threshold) MEP Elements for Further Discussion Develop MISO regional cost allocation for interregional economic projects down to 100kV on the PJM and SPP seams Develop criteria for defining Cost Allocation Zones Develop local allocation methodology for lower voltage economic projects, i.e., economic other : Clarify the process for this category of project Begin with aspects of the Local Efficiency Project concept as presented by Certain TOs
3 Focus of Cost Allocation Reforms
4 The objective of MISO transmission cost allocation methodologies is to align as best as possible who pays with who benefits over time from regional transmission expansion 4
5 Conditions Precedent for Regional Transmission Investment 1. Aligned interests regarding the issue(s) for regional transmission solutions to collectively address (i.e. increased policy consensus), 2. A robust business case for the project(s), 3. Clearly defined cost allocation methods that closely align who pays with who benefits, and 4. Cost recovery mechanisms that reduce financial risk 5
6 Guiding Principles for Transmission Cost Allocation Review Improve alignment of benefits and costs Eliminate cost allocation gaps with neighbors Clearly define cost allocation for all projects that are an outcome of the MISO regional transmission planning process (i.e. the MTEP) Ensure cost allocation is not an impediment to beneficial transmission investment (e.g. subregional MVPs, sub 345kV interregional economic projects) 6
7 Focus of Cost Allocation Review Reflects Desire to Improve Matching of Costs and Benefits Define Cost Allocation of Sub 345kV Economic Projects Improve cost/benefit matching through cost allocation Address confusion regarding current practice (direct assignment to constructing TO pricing zone) Change to cost allocation? Cost allocation gaps with neighboring planning regions can create a barrier to valuable transmission investment Potential 206 complaint if not addressed MISO-PJM interregional planning and cost allocation complaint is illustrative Refine Cost Allocation for Multi Value Projects Transmission has multiple benefits in addition to adjusted production cost Capturing more benefits improves benefit/cost alignment Portfolio requirement makes it impossible to address sub-regional issues with MVPs A change in the portfolio requirement will require a change in cost allocation (i.e. more granular allocation) 7
8 MISO Cost Allocation Response
9 MISO Cost Allocation Response* Unchanged Elements Multi-Value Projects (MVP): No changes Market Efficiency Project Benefit based allocation to all zones in MISO Benefit/Cost Ratio that is greater than or equal to 1.25 Minimum cost threshold of $5M Recommended Changes to Market Efficiency Project Cost Allocation Develop new/modify existing provisions of the tariff to ensure reliability is not negatively affected as a result of other cost allocation changes (such as lowering the voltage threshold) Create a tariff structure that allows for the inclusion of additional quantifiable benefit metrics as developed through the stakeholder process Eliminate 20% postage stamp component from MEP Cost Allocation Lower MEP voltage threshold to 230kV Market Efficiency Project Elements for Further Discussion Develop MISO regional cost allocation for interregional economic projects down to 100kV, PJM and SPP seam Develop criteria for defining Cost Allocation Zones Develop local allocation methodology for lower voltage economic projects, i.e., economic other Clarify the process for this category of project Begin with Local Efficiency Project concept as presented by Certain TOs * Reflects post transition period status quo 9
10 Unchanged Elements
11 No change to MVP Cost Allocation Stakeholders generally support a wait and see approach Cost allocation across the MISO footprint align with the portfolio requirement and widespread benefits received Other proposed changes to MEP address MISO concerns regarding the MVP category 11
12 MEP Allocation of costs to benefitting zones MISO will allocate the cost of MEP based on the distribution of applicable quantifiable metrics to all zones in the MISO footprint Criteria and definition of zones to be further evaluated 12
13 MEP Retain existing B/C and Cost thresholds Project must meet a minimum B/C ratio of 1.25 The Benefit/Cost Ratio of 1.25 appropriately captures future uncertainty without being overly conservative The MISO planning and cost allocation process incorporates a series of metrics to account for future uncertainties Project cost must exceed $5M 13
14 Recommended Changes to Market Efficiency Project Cost Allocation
15 Lower MEP voltage threshold to 230kV Aligns with the principle that Market Efficiency Projects provide regional cost allocation for "larger" projects more likely to have benefits across multiple pricing zones Takes an important incremental step of bringing congestion planning into better alignment between MISO South and MISO Midwest Based on system designs, 230 kv is the predominant EHV (regional) voltage class (mileage) in South Similar to 345 kv in MISO Classic, 230 kv in MISO South is closest to the sweet spot for effective mitigation of congestion providing regional (extra-lpz) benefits at lower costs than highest voltages in regions (500 kv/765 kv). Provides separation between regional economic projects from local projects needed for local needs (i.e. sub 230kV projects) 15
16 230kV and Above Transmission 16
17 345kV and Above Transmission 17
18 200kV-300kV Transmission 18
19 Create a tariff structure that allows for the inclusion of additional quantifiable benefit metrics as developed through the stakeholder process Transmission provides economic benefits beyond Adjusted Production Cost Quantifying those benefits will improve the alignment of who benefits with who pays MISO will focus its efforts on the four MVP metrics currently in the tariff plus the benefit resulting from changes to the Midwest-South contract path limit Targeting inclusion of deferred/avoided reliability project benefit and contract path benefits in 2018 Inclusion of other metrics (i.e. capacity based metrics and others) occur over time as they are developed through the stakeholder process 19
20 Example Allocation of costs to benefitting Cost Allocation Zones Example of Cost Allocation Zones Four zone system Project cost $1M Total Benefits $450 M Four calculated benefit metrics Zone Benefit Metrics A B C D Total Benefits % 28% 22% 17% 33% Cost Allocation ($M)
21 Eliminate 20% postage stamp component from MEP cost allocation Postage stamp is a means of recognizing that transmission provides benefits that are not otherwise captured and that who benefits will change over the long life of the investment Capturing additional quantifiable metrics addresses, in part, the purpose of the postage stamp Significant stakeholder support, including the OMS majority position, support elimination of the postage stamp component 21
22 Develop new/modify existing provisions of the tariff to ensure reliability is not negatively affected as a result of other cost allocation changes (e.g., such as lowering the voltage threshold) Lowering the voltage threshold for MEP may result in projects needed for reliability going through the developer selection process Extended timeline may put reliability or compliance at risk Largely mitigated by setting MEP voltage at 230kV Options include but are not limited to in service date/need by thresholds or eliminating BRP->MEP cost allocation hierarchy 22
23 Market Efficiency Project Elements for Further Discussion
24 Develop MISO regional cost allocation for interregional economic projects down to 100kV, PJM and SPP seam PJM and Southwest Power Pool (SPP), respectively, regionally cost share lower voltage economic projects Per FERC directive interregional MEP with PJM is set at 100kV MISO will address the cost allocation gap for interregional MEP with SPP for projects between 100 and 230kV MISO will evaluate with stakeholders alternatives that address this issue 24
25 Develop criteria for Cost Allocation Zone definition Historically, Cost Allocation Zones (CAZ) used for MEP cost allocation aligned with Local Resource Zones used for Resource Adequacy Changes to CAZ definition have been driven by state regulatory agency requests on an ad hoc basis MISO will work with stakeholders to develop a set of criteria and process for future CAZ modifications Stakeholder support for more granular zones (i.e. Transmission Pricing Zones) What is an ideal size for cost allocation zones? 25
26 Local zone allocation for lower voltage economic projects, i.e. economic other The MISO planning process is not limited by the voltage criteria for regional cost allocation. It is important to clarify and define the process and cost allocation treatment for economic projects that do not meet the MEP criteria (i.e. Economic-Other ) Use the concepts proposed in the November 2017 RECBWG meeting as a starting point for further discussions Defined process Business case development Cost allocation certainty 26
27 Schedule and Workplan
28 Schedule Apr Introduced decision for comprehensive review Sept Finalize issue summary paper, lays out a high level work plan Jan RECB prioritizes issues Feb MISO creates work plan for high priority issues through 2016 Dec MISO presents MEP cost allocation strawman Q1-Q Evaluate two key issues: Sub 345kV MEP projects, MVP 100% postage stamp Feb MISO to present cost allocation response Q1-Q Develop and file tariff changes Issues Summary Paper Q Present Strawman Dec 2016 Present MISO Cost Allocation Response Feb 2018 Effective no later than 1/1/2019 Stakeholder Issues Review Q2-Q Issues Evaluation and risk management Q1-Q File reforms at FERC Q
29 Appendix
30 Granularity of Cost Allocation Local Resource Zone Pricing Zone Local Balancing Authority MISO map of: Local Resource Zones (LRZs) Pricing Zones (TPZs) Local Balancing Authorities (LBAs) 30
31 Allocation of costs to benefitting Cost Allocation Zones Local Resource Zone Transmission Pricing Zone(s) 1 DPC, GRE, MDU, MP, NSP, OTP, SMP 2 ATC 3 ITCM, MEC, MPW 4 AMIL, CWLP, SIPC 5 AMMO, CWLD 6 BREC, DEI, HE, IPL, NIPS, VECT 7 METC, ITC 8 EATO 9 CLCE, ELTO, ENTO, LAFA 10 EMTO, SME 11 ETTO 31 * See FERC filing ER18-364, Map of MEP Cost Allocation Pricing Zone Boundaries
32 MISO Regional Cost Allocation Project Type Description Allocation to Beneficiaries Multi-Value Project Market Efficiency Project Baseline Reliability Project Generation Interconnection Project Transmission Delivery Service Project Participant Funded Address energy policy laws and/or provide widespread benefits across footprint Reduce market congestion when benefits are 1.25 in excess of costs NERC Reliability Criteria Interconnection Request Transmission Service Request Projects that are funded by the project requestor, often not the TO. The requestor funds the project (i.e. pays up front through a contribution in aid of construction (CIAC), which excludes the project from a TO s rate base and zonal rates. 100% postage stamp to load 345 kv and above: 80% distributed to Local Resource Zones commensurate with expected benefit, 20% postage stamp to load; 100 kv to 344 kv (IMEPs with PJM only): TBD 100% allocated to local Transmission Pricing Zone Primarily paid for by requestor; 345 kv and above 10% postage stamp to load. Generally paid for by Transmission Customer; Transmission Owner can elect to roll-in into local Transmission Pricing Zone rates The requestor funds the project (i.e. pays up front through a contribution in aid of construction (CIAC), which excludes the project from a TO s rate base and zonal rates. Other Project that does not qualify for other cost allocation mechanisms. Can be driven by reliability, economics, public policy or some combination of the three. The costs of these projects are recovered in zonal rate. 32
33 MISO-PJM Interregional Cost Allocation Cost Allocation Methodology Project Type Description Project Requirements RTO Project Share MISO Allocation Targeted Market Efficiency Project (TMEP) Alleviates historical M2M congestion in both RTOs $20 million; In Service by 3 rd Summer Peak after approval Ratio of each RTO s Day Ahead and Excess Congestion Fund congestion, offset by historical M2M payments MISO portion allocated to MISO beneficiaries using historical nodal load congestion contribution data aggregated up to the TPZ level Interregional Market Efficiency Project (IMEP) Reduces market congestion in both RTOs Qualifies as MEP or MVP* in MISO and economic transmission enhancement or expansion in PJM; Gen GLDF of 5% or greater in each RTO MISO: 100% APC PJM: Double 345 kv+: 50% APC, 50% NLP; 100 kv Single 345 kv: 100% NLP MISO portion allocated the same as a regional MEP (80% APC to LRZs/20% Postage stamp). Note: For MISO-PJM IMEP only, voltage threshold is 100 kv Interregional Reliability Project (IRP) Displaces reliability projects in both RTOs Qualifies as BRP or MVP** in MISO and BRP in PJM Ratio of avoided project costs in each RTO Costs assigned based on the allocation of the avoided regional project Cross-Border Baseline Reliability Project (CBBRP) Needed to efficiently meet reliability criteria Qualifies as BRP in MISO or PJM DFAX of RTO generation to respective RTO load Wholly MISO: project is allocated like a BRP (100% to local TPZ); Wholly PJM: TBD Interregional Public Policy Project (IPPP) Displaces public policy projects in both RTOs Qualifies as MVP*** in MISO and economic or reliability project in PJM Ratio of avoided project costs in each RTO Costs assigned based on the allocation of the avoided regional project * Meeting Criteria 2 or 3 ** Meeting Criterion 3 *** Meeting Criterion 1 33 Note: Per the MISO-PJM JOA, projects that could qualify as an IRP and CBBRP will be cost allocated as an IRP
34 MISO-SPP Interregional Cost Allocation Cost Allocation Methodology Project Type* Description and Requirements RTO Project Share MISO Cost Allocation Reliability Necessary to meet NERC reliability criteria; Displaces reliability projects in both RTOs APC + Avoided Cost MISO portion allocated to local TPZ(s) Wholly MISO or MISO-SPP Tie: 345 kv+ Allocated as a MISO MEP: 80% APC to LRZs, 20% Postage Stamp Economic Project that alleviates market congestion in both RTOs 100% APC Wholly SPP: 345 kv+ MISO-SPP Tie: <345 kv Allocated 100% APC to benefiting LRZs (No Postage Stamp) Allocated 100% to the local TPZ(s) Wholly MISO: <345 KV Allocated 100% to the local TPZ(s) Wholly SPP: <345 kv No MISO cost allocation mechanism Public Policy Displaces public policy projects in both RTOs Avoided Cost Costs assigned based on the allocation of the avoided regional project *Refers to the primary project driver 34
35 MISO-SERTP Interregional Cost Allocation Cost Allocation Methodology Project Type Description and Requirements RTO Project Share MISO Cost Allocation MISO-SERTP Interregional Project Displaces a reliability, economic or public policy driven project(s) and meets the following requirements: Interconnects to transmission facilities in both SERTP and MISO regions Combined B/C ratio > 1.25* Meets criteria for inclusion in the respective regional plans Ratio of avoided project cost Costs assigned based on the allocation of the avoided regional project *Benefits are quantified by the total avoided cost of projects displaced by the interregional project 35
Cost Allocation Reform Update
Cost Allocation Reform Update Regional Expansion Criteria and Benefits Working Group May 18, 2017 Conditions Precedent for Regional Transmission Investment 1. Increased consensus regarding the issue(s)
More informationHistory of Cost Allocation within MISO RECB TF. January 29, 2015
History of Cost Allocation within MISO RECB TF January 29, 2015 Cost Allocation FERC Orders, Filings, and Rulings Cost allocation for MISO began with Order 2003 which instituted a pro forma Generator Interconnection
More informationLower Voltage Interregional Economic Projects. RECBWG April 18, 2018
Lower Voltage Interregional Economic Projects RECBWG April 18, 2018 Interregional Gaps & Inconsistencies 1. No tariff defined cost allocation for sub 345 kv economic projects with PJM 2. Economic projects
More informationMISO-PJM Targeted Market Efficiency Project (TMEP) Update. Planning Advisory Committee (PAC) 10/18/17
MISO-PJM Targeted Market Efficiency Project (TMEP) Update Planning Advisory Committee (PAC) 10/18/17 1 Objective: Provide an update to stakeholders on MISO-PJM Targeted Market Efficiency Projects (TMEP).
More informationMISO PJM IPSAC. December 2, Revised December 22, PJM IPSAC Meeting, December 2,
MISO PJM IPSAC December 2, 2016 Revised December 22, 2016 1 Agenda 2 TMEP Final JOA Language Recommended TMEPs Order No. 1000 Compliance Filing Generation Deactivation JOA Language PJM Proposal Window
More informationMISO Planning Process. May 31, 2013
MISO Planning Process May 31, 2013 MISO Planning Objectives Fundamental Goal The development of a comprehensive expansion plan that meets reliability needs, policy needs, and economic needs MISO Board
More informationCost Allocation Principles for Seams Transmission Expansion Projects
Cost Allocation Principles for Seams Transmission Expansion Projects SPP s seams agreements currently contain requirements for SPP to develop coordinated system plans with its neighbors. The extent and
More informationMVP Postage Stamp Cost Allocation and Portfolio Requirement Regional Expansion Criteria and Benefits Working Group. September 28, 2017
MVP Postage Stamp Cost Allocation and Portfolio Requirement Regional Expansion Criteria and Benefits Working Group September 28, 2017 What is a Multi Value Project? A Multi Value Project is one or more
More informationMISO PJM IPSAC. August 26, PJM IPSAC Meeting, August 26,
MISO PJM IPSAC August 26, 2016 1 Agenda 2 Targeted Market Efficiency Project (TMEP) Study TMEP Proposed JOA Language FERC EL13-88 Filings IPSAC Work Schedule 2 3 Targeted Market Efficiency Project Study
More informationPJM/MISO Cost Allocation For Economic Upgrades
PJM/MISO Cost Allocation For Economic Upgrades Stakeholder Meeting Hilton Baltimore BWI, Baltimore MD May 19, 2008 1 Topics for Discussion Background FERC Order / Schedule (RTO Staffs) Review Internal
More informationStakeholder Survey I Cross Border Cost Allocation for Economic Transmission Projects For Discussion September 24, 2008
PJM and the Midwest ISO are seeking input from stakeholders on various concepts that have been discussed during the PJM/Midwest ISO Cross-Border meetings for dealing with transmission projects constructed
More informationTransmission Cost Allocation
Transmission Cost Allocation IPSAC February 2, 2010 John P. Buechler NYISO Executive Regulatory Policy Advisor Background FERC Policy has evolved Order 888 No Planning Requirement for ISOs Order 2000 Planning
More informationSeams Cost Allocation: A Flexible Framework to Support Interregional Transmission Planning (Summary of Final Report)
Seams Cost Allocation: A Flexible Framework to Support Interregional Transmission Planning (Summary of Final Report) Presented at: SPP RSC Quarterly Meeting Presented by: Johannes Pfeifenberger Delphine
More informationSouthwest Power Pool s Balanced Portfolio Approach for Economic Upgrades
Southwest Power Pool s Balanced Portfolio Approach for Economic Upgrades Presentation by Michael Proctor Chief Economist, Missouri PSC Harvard Electricity Policy Group Chicago, Illinois October 2, 2008
More informationSystem Load * Days in Month Weighted Load In Month Effective by Month January 2, ,727 February 2, ,665 March 2, ,515
NIPSCO Aggregate 206 True-up Calculations Instructions: Inputs are indicated by light yellow highlighted cells with blue bold font. For "Company Name" be sure to use our standard abbreviations or check
More informationRenewable Generation, Transmission and the Energy Marketplace
Renewable Generation, Transmission and the Energy Marketplace Portfolio Development and Business Case October 25, 2012 Overview Multi Value Projects reflect the transformation of the MISO planning process
More information2018/2019 Planning Resource Auction Results. Resource Adequacy Subcommittee May 9, 2018
2018/2019 Planning Resource Auction Results Resource Adequacy Subcommittee May 9, 2018 Overview Auction Results Summary Year Over Year Comparison Additional Details on PRMR and Supply 2 2018/2019 Auction
More informationRegional Transmission Organization Frequently Asked Questions
1. The CRA analysis showed greater trade benefits to the Entergy region from joining SPP rather than joining MISO. Did Entergy re-do the CRA analysis? No. The CRA analysis was a key component of the Entergy
More information153 FERC 61,249 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER REJECTING TARIFF REVISIONS. (Issued November 30, 2015)
153 FERC 61,249 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Norman C. Bay, Chairman; Cheryl A. LaFleur, Tony Clark, and Colette D. Honorable. Southwest Power Pool,
More informationSPP New Member Communication and Integration Process. Mountain West Transmission Group. Background Information October 2017
1 SPP New Member Communication and Integration Process Mountain West Transmission Group Background Information October 2017 Contents Introduction... 2 1. Westside Tariff Design... 2 2. Operational Provisions...
More informationTRANSMISSION OWNER ZONAL PLACEMENT PROCESS
TRANSMISSION OWNER ZONAL PLACEMENT PROCESS Published July 2017 CONTENTS Section 1: Introduction, Scope & Steps... 1 Subsection A: Introduction To Zonal Placement... 1 Subsection B: Scope... 1 Subsection
More informationPJM SERTP Planning Process Overview
PJM SERTP Planning Process Overview Order 1000 Biennial Regional Transmission Plan Review Meeting Presentation 1 of 2 May 8 th, 2018 Georgia Power Corporate Headquarters Atlanta, GA PJM SERTP Interregional
More informationNew Member Cost Allocation Review Process. Prepared by: COST ALLOCATION WORKING GROUP
New Member Cost Allocation Review Process Prepared by: COST ALLOCATION WORKING GROUP TABLE OF CONTENTS 1. HISTORY AND BACKGROUND... 1 2. PURPOSE / GOAL STATEMENT... 3 3. OVERVIEW OF PROCESS... 3 4. NEW
More informationFTR Credit Requirements Prevailing Flow Paths Affected by Transmission System Upgrades
FTR Credit Requirements Prevailing Flow Paths Affected by Transmission System Upgrades Hal Loomis Manager, Credit Markets & Reliability Committee December 7, 2017 Credit Risk Exposure Issue Description
More information161 FERC 61,004 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION
161 FERC 61,004 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Neil Chatterjee, Chairman; Cheryl A. LaFleur, and Robert F. Powelson. Midcontinent Independent System
More information1st Qua u r a ter e M e M e e t e in i g 2nd Qua u r a ter e M e M e e t e in i g
2012 SERTP Welcome SERTP 2012 First RPSG Meeting & Interactive Training Session 1 2012 SERTP The SERTP process is a transmission planning process. Please contact the respective transmission provider for
More informationBenefits Determination and Cost Allocation
Benefits Determination and Cost Allocation Johannes Pfeifenberger Transmission Executive Forum West 2012 Meeting Public Policy Objectives through Transmission Investment San Diego, CA October 22, 2012
More informationSPP PLANNING AND COST ALLOCATION OVERVIEW
Benefit/Cost Ratio Primer 101 for the Regional Allocation Review Task Force August 4, 2011 1 SPP PLANNING AND COST ALLOCATION OVERVIEW 2 1 Transmission = 10% Retail Electricity Rates Transmission enables
More informationCONTEMPORARY TRANSMISSION ISSUES:
CONTEMPORARY TRANSMISSION ISSUES: COST ALLOCATION SESSION 1:00 PM Wisconsin Public Utility Institute May 26, 2010 Panelist: Greg Levesque, Manager - Regional Relations & Policy, ATC, Don Neumeyer, Engineer,
More informationNorthern Tier Transmission Group Cost Allocation Principles Work Group. Straw Proposal. May 29, 2007
Northern Tier Transmission Group Cost Allocation Principles Work Group Straw Proposal May 29, 2007 NTTG Cost Allocation Principles and Process page 1 INTRODUCTION This paper makes a strawman proposal responsive
More informationRegional Cost Allocation Review (RCAR II) July 11, 2016 SPP Regional Cost Allocation Review Report for RCAR II
Regional Cost Allocation Review (RCAR II) July 11, 2016 SPP Regional Cost Allocation Review Report for RCAR II 1 Table of Contents EXECUTIVE SUMMARY...5 BACKGROUND...7 SECTION 1: OVERVIEW OF THE RARTF
More informationTransmission Investment Trends and Planning Challenges
Transmission Investment Trends and Planning Challenges Presented at: EEI Transmission and Wholesale Markets School Presented by: Johannes Pfeifenberger Madison, WI August 8, 2012 Copyright 2012 The Brattle
More informationSouthwest Power Pool, Inc. Policy Recommendation for the SPP Board of Directors and Members Committee. March 6, 2018 Mountain West Transmission Group
Southwest Power Pool, Inc. Policy for the SPP Board of Directors and Members Committee Policy Area #1 DC Ties March 6, 2018 Mountain West Transmission Group SPP and MWTG anticipate that incorporating the
More informationEIPC Roll-Up Report & Scenarios
EIPC Roll-Up Report & Scenarios Zach Smith Director, Transmission Planning New York Independent System Operator IPTF/EGCWG/ESPWG Meeting January 6, 2014 2013 New York Independent System Operator, Inc.
More informationInjection / Withdrawal CARP
Injection / Withdrawal CARP Decisions Note: To inform the RECB Stakeholders at their upcoming September 30 th meeting, this version of the Decision Tree contains the decisions made by CARP (in bold/italics)
More informationMemo to the MOPC and Board of Directors Highway-Byway Cost Allocation
Memo to the MOPC and Board of Directors Highway-Byway Cost Allocation SPP believes that the proposed Highway-Byway cost allocation methodology will promote new transmission construction by allocating:
More informationOctober 8, SPP Regional Cost Allocation Review Report
Regional Cost Allocation Review October 8, 2013 SPP Regional Cost Allocation Review Report 1 Table of Contents EXECUTIVE SUMMARY...5 BACKGROUND...7 SECTION 1: OVERVIEW OF THE RARTF AND RCAR REVIEW...8
More information2018 Budget. Stakeholder Presentation. October 10, atcllc.com
2018 Budget Stakeholder Presentation October 10, 2017 atcllc.com Welcome & Overview Welcome Randy Karls ROE Complaints Brian Drumm Budget Overview Kevin Szalacinski ATC Network MISO Other charges Asset
More informationRate Schedules and Seams Agreements Tariff
Rate Schedules and Seams Agreements Tariff Southwest Power Pool Rate Schedules and Seams Agreements Tariff Document Generated On: 8/20/2015 Southwest Power Pool - Rate Schedules and Seams Agreements Tariff
More informationMTEP16 Futures Development Workshop 1/15/15
MTEP16 Futures Development Workshop 1/15/15 Overview Objectives MTEP16 proposed futures Uncertainty variables definitions Next steps 2 Objective Ensure MTEP16 Futures are effective and are developed in
More informationMountain West Transmission Group (MWTG) Introduction and Process
Mountain West Transmission Group (MWTG) Introduction and Process October 13 Denver, CO October 16 Little Rock, AR 2 Agenda Overview of SPP Overview of the MWTG Members SPP Process New Member Integration
More informationNORTHEASTERN ISO/RTO PLANNING COORDINATION PROTOCOL DESIGNATION OF FILING PARTY
NORTHEASTERN ISO/RTO PLANNING COORDINATION PROTOCOL DESIGNATION OF FILING PARTY The Northeastern ISO/RTO Planning Coordination Protocol among PJM Interconnection, L.L.C. ( PJM ), the New York Independent
More informationPJM & MISO Assumptions and Criteria for Testing of New Resources
& Assumptions and Criteria for Testing of New Resources 1 Introduction These slides provide a description and comparison of the assumptions and criteria used by and during the study of customer proposed
More informationITC Midwest 2014 Attachment O True-Up Presentation. Presenter: David Grover Manager, Transmission Pricing July 8, 2015
2014 Attachment O True-Up Presentation Presenter: David Grover Manager, Transmission Pricing July 8, 2015 Presentation Purpose Discuss the 2014 Annual True-Up posting Walk through the timeline and mechanics
More informationResource Adequacy Locational Reforms. August 2017
Resource Adequacy Locational Reforms August 2017 1 Purpose & Key Takeaways Key Takeaways: Purpose: Discuss locational proposal and updated draft Tariff language, focusing on recent stakeholder feedback
More informationBEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION SOUTHWESTERN PUBLIC SERVICE COMPANY S UNOPPOSED RESPONSE TO STAFF S COMMENTS
BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION IN THE MATTER OF SOUTHWESTERN ) PUBLIC SERVICE COMPANY S 2018 ) INTEGRATED RESOURCE PLAN FOR ) NEW MEXICO. ) CASE NO. 18-00215-UT ) SOUTHWESTERN PUBLIC
More informationSPP s Regional Review of SPP-MISO Coordinated System Plan Recommended Interregional Projects
SPP s Regional Review of SPP-MISO Coordinated System Plan Recommended Interregional Projects January 4, 2016 SPP Interregional Relations Table of Contents Executive Summary... 2 Introduction... 5 Stakeholder
More informationATTACHMENTS ATTACHMENT GG NETWORK UPGRADE CHARGE
ATTACHMENT GG Network Upgrade Charge ATTACHMENTS 32.0.0 ATTACHMENT GG NETWORK UPGRADE CHARGE 1. Network Upgrade Cost Allocation: This Attachment GG sets forth the method for calculating and collecting
More information2017 Actual Cost Attachment O, GG and MM Rate Template Presentation
2017 Actual Cost Attachment O, GG and MM Rate Template Presentation Dehn Stevens General Manager Transmission July 19, 2018 Meeting Purpose The purpose of today s meeting is to review the 2017 Attachments
More informationFTR Alignment. Joint Stakeholder Meeting June 6, 2008
FTR Alignment Joint Stakeholder Meeting June 6, 2008 Introduction Joint Common Market Initiative As part of the of the Midwest ISO and PJM Joint and Common Market (JCM) process, the Midwest ISO stakeholders
More informationStandard Market Design: FERC Process and Issues
Standard Market Design: FERC Process and Issues Richard O Neill and Udi Helman Division of the Chief Economic Advisor, Office of Markets, Tariffs and Rates Federal Energy Regulatory Commission IEEE PES
More informationCOMMENTS OF TROUTMAN SANDERS LLP ON THE EUROPEAN REGULATORS GROUP FOR ELECTRICITY AND GAS DRAFT PROPOSAL ON GUIDELINES ON INTER-TSO COMPENSATION
DRAFT COMMENTS OF TROUTMAN SANDERS LLP ON THE EUROPEAN REGULATORS GROUP FOR ELECTRICITY AND GAS DRAFT PROPOSAL ON GUIDELINES ON INTER-TSO COMPENSATION In response to the ERGEG Draft Proposal on Guidelines
More informationEasier Said Than Done: The Continuing Saga of Transmission Cost Allocation
Easier Said Than Done: The Continuing Saga of Transmission Cost Allocation Presented by: Johannes Pfeifenberger Presented to: Harvard Electricity Policy Group February 24, 2011 www.brattle.com Antitrust/Competition
More informationSPP-AECI Joint Projects
SPP-AECI Joint Projects 1 Morgan Transformer Project Addition of a new 400 MVA 345/161 kv Transformer at AECI s Morgan substation and an uprate of the 161 kv line between Morgan and Brookline Located in
More informationFiled with the Iowa Utilities Board on May 31, 2017, E STATE OF IOWA DEPARTMENT OF COMMERCE UTILITIES BOARD
STATE OF IOWA DEPARTMENT OF COMMERCE UTILITIES BOARD IN RE: MIDAMERICAN ENERGY IN RE: DOCKET NOS. E-22269, E-22270, AND E-22271 DOCKET NO. E-22279 (consolidated) ITC MIDWEST LLC BRIEF BY THE MIDCONTINENT
More informationYear Assessment Preliminary Study Design
2015 10-Year Assessment Preliminary Study Design October 15, 2014 Stakeholder and Customer Webcast atcllc.com Purpose Solicit pre-study Comments 2015 Assessment Process 2015 Assessment Assumptions Public
More informationTransmission System Expansion Cost Allocation Alternatives for Renewable Resources. Cost Allocation Working Group March 26, 2008 OG&E Ver 2 3/20/8
Transmission System Expansion Cost Allocation Alternatives for Renewable Resources Cost Allocation Working Group March 26, 2008 OG&E Ver 2 3/20/8 Page 1 Why Page 2 Page 1 of 11 Basic Principles Wind generation
More informationCalculate Net Annual Transmission Revenue Requirements (ATRR) and Rates for SPP Tariff. Total Transmission A. Zonal Net ATRR 1 Gross ATRR $60,516,589
Page 1 Formula-based Rate Template Calculate Net Annual Transmission Revenue Requirements (ATRR) and Rates for SPP Tariff Line No. Acct Description Notes Total Transmission A. Zonal Net ATRR 1 Gross ATRR
More information10-YEAR COSTS AND BENEFITS TO SPP MEMBERS OF INTEGRATING MOUNTAIN WEST TRANSMISSION GROUP Quantitative Analysis of Costs and Benefits
10-YEAR COSTS AND BENEFITS TO SPP MEMBERS OF INTEGRATING MOUNTAIN WEST TRANSMISSION GROUP Quantitative Analysis of Costs and Benefits Published on March 19, 2018 By SPP Staff REVISION HISTORY DATE OR VERSION
More informationCost Allocation for Transmission Infrastructure
USAID/NARUC East Africa Regional Regulatory Partnership Exchange: Cost Allocation for Transmission Infrastructure Andrew Greene Massachusetts Dept. of Public Utilities Energy Facilities Siting Board Dar
More informationResource Adequacy. WPUI April 19, 2018
WPUI April 19, 2018 Resource Adequacy What is the interplay between states resource adequacy power per the Federal Power Act and the RTO s Reliability Coordinator role? Is a state Integrated Resource Plan
More informationNYISO Posting for FERC Order 890 Describing the NYISO Planning Process
NYISO Posting for FERC Order 890 Describing the NYISO Planning Process September 14, 2007 ` NYISO Posting for FERC Order 890 Filing DRAFT Table of Contents Section: Page No: I. Cover Memo - Draft OATT
More informationBEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION ) ) ) ) ) ) ) ) ) ) ) DIRECT TESTIMONY WILLIAM A. GRANT. on behalf of
BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION IN THE MATTER OF SOUTHWESTERN PUBLIC SERVICE COMPANY S APPLICATION FOR REVISION OF ITS RETAIL RATES UNDER ADVICE NOTICE NO., SOUTHWESTERN PUBLIC SERVICE
More informationSummary of FERC White Paper on Bulk Power Market Design and Related Aspects of Senate Energy Bill No. S. 14
Summary of FERC White Paper on Bulk Power Market Design and Related Aspects of Senate Energy Bill No. S. 14 Introduction On April 28, 2003, the Federal Energy Regulatory Commission (FERC or Commission)
More informationAGENDA. 1. Call to Order and Administrative Items... Mike Wise. 2. Review of SPC s Policy Decision (4-Step Process)... Paul Suskie
Southwest Power Pool, Inc. STRATEGIC PLANNING COMMITTEE MEETING Friday, June 2, 2017 9:00 AM 3 PM AEP Office, 8 th Floor Renaissance Tower, Dallas, Texas AGENDA 1. Call to Order and Administrative Items...
More informationThe cost allocation principles and methodologies in this Attachment Y cover only
31.5 Cost Allocation and Cost Recovery 31.5.1 The Scope of Attachment Y Cost Allocation 31.5.1.1 Regulated Responses The cost allocation principles and methodologies in this Attachment Y cover only regulated
More informationSettlements and ADR Time Bars. Market Subcommittee February 8, 2018
Settlements and ADR Time Bars Market Subcommittee February 8, 2018 Purpose and Key Takeaways Purpose Update stakeholders on proposed Tariff revisions establishing time limits for disputes, corrections
More informationUNITED STATES SECURITIES AND EXCHANGE COMMISSION WASHINGTON, D.C FORM 10-Q
(Mark One) UNITED STATES SECURITIES AND EXCHANGE COMMISSION WASHINGTON, D.C. 20549 FORM 10-Q QUARTERLY REPORT PURSUANT TO SECTION 13 OR 15(d) OF THE SECURITIES EXCHANGE ACT OF 1934 For the Quarterly Period
More informationFERC Order 1000: Planning for the Right of First Refusal and Planning for Public Policy Status & Implementation in New York
1 FERC Order 1000: Planning for the Right of First Refusal and Planning for Public Policy Status & Implementation in New York Henry Chao Vice President - System and Resource Planning New York Independent
More informationITC Holdings Corp. Investor Meetings. March 2015
ITC Holdings Corp. Investor Meetings March 2015 Safe Harbor Language & Legal Disclosure This presentation contains certain statements that describe our management s beliefs concerning future business conditions
More informationITC Holdings Corp. Fourth Quarter & Year End 2013 Investor Call February 27, 2014
ITC Holdings Corp. Fourth Quarter & Year End 2013 Investor Call February 27, 2014 Safe Harbor Language & Legal Disclosure This presentation contains certain statements that describe our management s beliefs
More informationITC Holdings Corp. Investor Meetings. January 2015
ITC Holdings Corp. Investor Meetings January 2015 Safe Harbor Language & Legal Disclosure This presentation contains certain statements that describe our management s beliefs concerning future business
More informationLong-Term Reliability Assessment
Long-Term Reliability Assessment Key Findings and Long-Term Issues John Moura, Director of Reliability Assessment Topics Covered Today Background on NERC s Long-Term Reliability Assessment Emerging and
More informationFive-Minute Settlements Education
Five-Minute Settlements Education Disclaimer PJM has made all efforts possible to accurately document all information in this presentation. The information seen here does not supersede the PJM Operating
More informationOrder No Transmission Planning and Cost Allocation
Order No. 1000 Transmission Planning and Cost Allocation Thursday, August 18, 2011, 1:00 pm Eastern Panelists: John D. McGrane, Floyd L. Norton, IV, Stephen M. Spina www.morganlewis.com Overview Order
More informationCalculate Net Annual Transmission Revenue Requirements (ATRR) and Rates for SPP Tariff. Total Transmission A. Zonal Net ATRR 1 Gross ATRR $48,861,618
Page 1 Formula-based Rate Template Calculate Net Annual Transmission Revenue Requirements (ATRR) and Rates for SPP Tariff Line Acct Description Notes Total Transmission A. Zonal Net ATRR 1 Gross ATRR $48,861,618
More informationUNITED STATES SECURITIES AND EXCHANGE COMMISSION WASHINGTON, D.C FORM 10-Q
(Mark One) UNITED STATES SECURITIES AND EXCHANGE COMMISSION WASHINGTON, D.C. 20549 FORM 10-Q QUARTERLY REPORT PURSUANT TO SECTION 13 OR 15(d) OF THE SECURITIES EXCHANGE ACT OF 1934 For the Quarterly Period
More informationProposal for FERC Fee Recovery
Proposal for FERC Fee Recovery Cheryl Hussey Vice President & Chief Financial Officer New York Independent System Operator Chris Russell Manager Customer Settlements New York Independent System Operator
More informationALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC
The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC 20004-1404
More informationRe: Analysis of NERC Standard Process Results, Fourth Quarter 2013 Docket Nos. RR , RR
VIA ELECTRONIC FILING January 29, 2014 Ms. Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, D.C. 20426 Dear Ms. Bose: Re: Analysis of NERC Standard Process
More informationFinancial Transmission and Auction Revenue Rights
Section 13 FTRs and ARRs Financial Transmission and Auction Revenue Rights In an LMP market, the lowest cost generation is dispatched to meet the load, subject to the ability of the transmission system
More informationPROPOSAL FOR COST ESTIMATION REVIEW PROCESS FOR SPP TRANSMISSION
PROPOSAL FOR COST ESTIMATION REVIEW PROCESS FOR SPP REGIONALLY FUNDED TRANSMISSION Presented on behalf of SPP s Transmission Owners SPP Strategic Planning Committee Meeting December 3, 2010 REGIONALLY
More informationBEFORE THE MINNESOTA OFFICE OF ADMINISTRATIVE HEARINGS 600 North Robert Street St. Paul, MN 55101
BEFORE THE MINNESOTA OFFICE OF ADMINISTRATIVE HEARINGS 00 North Robert Street St. Paul, MN 1 FOR THE MINNESOTA PUBLIC UTILITIES COMMISSION th Place East, Suite 0 St Paul MN 1-1 IN THE MATTER OF THE APPLICATION
More informationBEFORE THE MINNESOTA OFFICE OF ADMINISTRATIVE HEARINGS 600 North Robert Street St. Paul, MN 55101
BEFORE THE MINNESOTA OFFICE OF ADMINISTRATIVE HEARINGS 00 North Robert Street St. Paul, MN 1 FOR THE MINNESOTA PUBLIC UTILITIES COMMISSION th Place East, Suite 0 St Paul MN 1-1 IN THE MATTER OF THE APPLICATION
More informationTransactional Scoping and Approvals
Noel co-leads the utility practice of the energy industry team. He represents electric utilities and other energy companies before the Federal Energy Regulatory Commission (FERC) and appellate courts,
More informationCongestion Revenue Rights Settlement Rule
California Independent System Operator Corporation Congestion Revenue Rights Settlement Rule Department of Market Monitoring August 18, 2009 I. Background Under nodal convergence bidding, the California
More informationOrganization of MISO States Response to the Midwest ISO October Hot Topic on Pricing
Organization of MISO States Response to the Midwest ISO October Hot Topic on Pricing I. Day Ahead and Real Time Energy and Ancillary Services Pricing Prices that Accurately Reflect the Marginal Cost of
More informationUNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Southwest Power Pool, Inc. ) Docket No. ER
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Southwest Power Pool, Inc. ) Docket No. ER16- -000 PETITION OF SOUTHWEST POWER POOL, INC. FOR TARIFF WAIVER Pursuant to Rule 207(a)(5)
More informationSPP Staff Proposal on TO Zonal Placement. April 20, 2017
SPP Staff Proposal on TO Zonal Placement April 20, 2017 Outline I. II. III. IV. V. VI. Background of the Staff s Proposal Paul Suskie Examples of New TO additions Carl Monroe SPC Motion & Updated Staff
More informationREPORT TO THE PUBLIC UTILITIES BOARD
REPORT TO THE PUBLIC UTILITIES BOARD CURTAILABLE RATE PROGRAM APRIL 1, 2011 MARCH 31, 2012 JULY 2012 TABLE OF CONTENTS Page No. SUMMARY... 1 BACKGROUND... 1 PERFORMANCE FOR 2011/12... 3 Curtailment Options...3
More informationCosts and Revenue Offsets Item # Description
Item # CUS-13 Costs and Description Total Cost Allocation - Total cost (PV of 40-year ATRR's ) are listed as $7,382M on ESWG slide 3. Could we get a breakdown (listing) of how this total was determined.
More informationFebruary 23, 2015 VIA ELECTRONIC FILING
February 23, 2015 VIA ELECTRONIC FILING The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: Southwest Power Pool, Inc., Docket
More informationCongestion Revenue Rights Auction Efficiency Track 1B Draft Final Proposal
Congestion Revenue Rights Auction Efficiency May 11, 2018 Prepared by: M&IP California Independent System Operator Table of Contents 1 Executive Summary... 3 2 Changes to this proposal... 5 3 Scope of
More informationLSE Perspective on FTR and ARR Surplus Funds. Jeff Whitehead Direct Energy
LSE Perspective on FTR and ARR Surplus Funds Jeff Whitehead Direct Energy Congestion Revenue Entitlement Transmission Customers paid and continue to pay the embedded cost of the transmission system Transmission
More informationFERC Order 1000: Transmission Planning & Cost Allocation Framework for NYISO Compliance
FERC Order 1000: Transmission Planning & Cost Allocation Framework for NYISO Compliance by John P Buechler NYISO Executive Regulatory Policy Advisor Joint IPTF/ESPWG Meeting February 27, 2012 Albany, NY
More informationInformational Filing of Midwest Independent Transmission System Operator, Inc. s Independent Market Monitor
Potomac Economics, Ltd. 9990 Fairfax Boulevard, Suite 560 Telephone: 703-383-0720 Fairfax, Virginia 22030 Facsimile: 703-383-0796 Honorable Kimberly D. Bose, Secretary Federal Energy Regulatory Commission
More informationCongestion Revenue Rights (CRR) Clawback Modification. Draft Final Proposal
Congestion Revenue Rights (CRR) Clawback Modification Draft Final Proposal May 16, 2016 CRR Clawback Modification Draft Final Proposal Table of Contents 1 Introduction... 3 2 Stakeholder process and timeline...
More informationFERC EL Settlement Agreement
FERC EL05-121-009 Settlement Agreement Ray Fernandez Manager, Market Settlements Development Market Settlements Subcommittee June 14, 2018 Settlement Agreement Details Settlement Agreement Details FERC
More informationPlanning in a competitive market environment
Planning in a competitive market environment The New York Story Rana Mukerji Senior Vice President - Market Structures New York Independent System Operator Harvard Electricity Policy Group 74 th Plenary
More information10-day Formal Comment Period with a 5-day Additional Ballot (if necessary), pursuant to a Standards Committee authorized waiver.
Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed
More information