1 MISO-PJM Targeted Market Efficiency Project (TMEP) Update Planning Advisory Committee (PAC) 10/18/17 1

2 Objective: Provide an update to stakeholders on MISO-PJM Targeted Market Efficiency Projects (TMEP). Key Takeaways: 1. FERC recently accepted TMEP interregional filings and regional tariff revisions 2. Acceptance Order is subject to a 30 day compliance filing 3. MTEP17 will include the 5 recommended interregional TMEP cost shared upgrades 4. December 2017 MISO and PJM Board approval 2

3 Overview Background MISO and PJM concluded a study earlier this year that recommended 5 interregional upgrade projects, predicated on and anticipating FERC approval of a new project type and criteria, filed in the MISO-PJM Joint Operating Agreement (JOA) and our respective regional tariffs, known as Targeted Market Efficiency Projects (TMEPs). Recent Development October 3, FERC Order accepts the TMEP interregional filings and regional tariff revisions, subject to condition, directing compliance filings within 30 days of the order. 3

4 How does that impact the 5 TMEPs? Approve TMEPs as part of MTEP17: As stated in previous PAC meetings and the March 2017 MISO Board System Planning Committee, upon FERC acceptance, we plan on recommending them for MISO Board approval, which in turn will be this December for MTEP17. Comply with Order: File the requested administrative regional tariff edits and JOA clarification language revisions within 30 days of Order (by November 4). 4

5 30 Day Compliance Directive Interregional JOA Revisions (ER P42, P43): Provide IPSAC an explanation of: i. why RTO s did not evaluate whether a potential TMEP could economically address congestion on a particular congested Reciprocal Coordinated Flowgate ii. why a potential TMEP that MISO and PJM did evaluate was not recommended to the RTOs respective BOD Provide for clarification to stakeholders, but not necessary to delineate in the JOA: i. criteria used to evaluate potential TMEP solutions ii. criteria used to evaluate whether congestion is likely to be persistent iii. where in the process this criteria will be provided to stakeholders Regional: Clean up tariff language that was included in the filing that was rejected in another docket (Attachment FF6 gap filing). 5

6 TMEP Recommended Projects All projects are upgrades to existing equipment. Map ID A B C Facility Burnham - Munster 345kV Bayshore - Monroe 345kV Michigan City - Bosserman 138kV TMEP Reconfigure Munster to ring bus Replace span across river Transmission Owner(s) Total Cost $M Total TMEP Benefit $M Benefit Allocation %PJM / %MISO MISO Cost $M CE - NIPS / ATSI - ITC / Reconductor NIPS - AEP / D Reynolds - Magnetation 138kV Replace switches at Reynolds NIPS / E Roxana - Praxair 138kV Reconductor NIPS / Total /

7 Regional Cost Allocation 7 The MISO regional cost allocation for the MTEP17 TMEPs were presented at the September RECB WG. TMEP Project TPZ Final MISO Cost Allocation (%) Burnham Munster METC 26.63% Burnham Munster ITC 26.28% Burnham Munster DEI 15.62% Burnham Munster NIPS 14.83% Burnham Munster IPL 5.45% Burnham Munster VECT 4.42% Burnham Munster BREC 4.25% Burnham Munster AMIL 1.27% Burnham Munster HE 1.26% Michigan City Bosserman ITC 44.36% Michigan City Bosserman METC 43.33% Michigan City Bosserman DEI 7.26% Michigan City Bosserman NIPS 5.05% TMEP Project TPZ Final MISO Cost Allocation (%) Bayshore - Monroe AMMO 18.55% Bayshore - Monroe DEI 18.47% Bayshore - Monroe AMIL 17.19% Bayshore - Monroe ATC 14.09% Bayshore - Monroe NSP 10.71% Bayshore - Monroe MEC 7.51% Bayshore - Monroe IPL 7.43% Bayshore - Monroe BREC 6.05% Reynolds Magnetation DEI 56.44% Reynolds Magnetation NIPS 37.49% Reynolds Magnetation IPL 6.07% Roxana Praxair TMEP NIPS %

8 Next Steps Date Nov 2 Nov 16 Dec 7 Q Q Activity Submit compliance filing MISO System Planning Committee MTEP17 Review MISO BOD Approval of MTEP17 and Appendix A which will include the 5 Interregional MISO-PJM TMEP projects MISO Transmission Owners and MISO Tariff Pricing collaborating on cost recovery tariff mechanism Cost Allocation reopener at RECB to re-determine appropriate cost allocation after Attachment FF6 (South transition) expires. 8

9 Summary FERC accepts TMEP interregional filings and regional tariff revisions 30 day compliance filing Including the 5 recommended TMEPs in MTEP17 December 2017 Board approval 9

10 Eric Thoms

11 Appendix

12 2016 TMEP Stakeholder Forum History Date Forum Comments February 2016 IPSAC, JCM Continued stakeholder discussion requesting formalizing the targeted ( quick hit ) study process. MISO & PJM agree to streamline targeted study process, benefit determination, and approvals. March 2016 IPSAC Continued update on the study and policy/procedure development. April 2016 IPSAC, PAC Continued update on the study and policy/procedure development. Proposed JOA language. May 2016 IPSAC, JCM Continued update on the study and development of TMEP JOA language. June 2016 IPSAC Continued update on the study and development of TMEP JOA language. July 2016 IPSAC Continued update on the study and development of TMEP JOA language. Aug 2016 IPSAC, JCM, PAC, RECB Continued update on the study and development of TMEP JOA language. Sept 2016 IPSAC, PAC, RECB TMEP study initial results, stakeholder survey results, final JOA language presented. Oct 2016 IPSAC, PAC, RECB Continued review of initial results and JOA language. Targeting end of year JOA filing. Cost Allocation. Nov 2016 JCM, PAC, RECB TMEP study results and JOA language. Targeting end of year JOA filing. Cost Allocation. Dec 2016 IPSAC, PAC, RECB Continued discussion and review of TMEPs results, cost allocation, upcoming filings, etc. 12

13 2017 TMEP Stakeholder Forum History Date Forum Comments Jan 2017 Feb 2017 Mar 2017 Apr 2017 May 2017 IPSAC, PAC, RECB IPSAC, JCM, PAC, RECB PAC, RECB, SPC PAC, JCM, RECB PAC, JCM, RECB Continued discussion and review of TMEPs, cost allocation, upcoming filings, cost allocation. Continued discussion and review of TMEPs, cost allocation, upcoming filings, cost allocation. Continued discussion and review of TMEPs, cost allocation, upcoming filings, cost allocation. TMEP update to the Board s System Planning Committee TMEP JOA/Tariff filing status, study summary, summary of TMEP project benefits MISO and TO s expect will make regional filing end of May Jun 2017 FERC Technical workshop discussing TMEPs. Aug 2017 PAC, JCM MISO and PJM are ready to recommend 5 TMEPs, pending FERC approval of the filings Sept 2017 PAC, RECB Update on TMEP Real Time ECF data effort. Final cost allocation percentages. 13

MISO PJM IPSAC. August 26, PJM IPSAC Meeting, August 26,

MISO PJM IPSAC. August 26, PJM IPSAC Meeting, August 26, MISO PJM IPSAC August 26, 2016 1 Agenda 2 Targeted Market Efficiency Project (TMEP) Study TMEP Proposed JOA Language FERC EL13-88 Filings IPSAC Work Schedule 2 3 Targeted Market Efficiency Project Study

More information

MISO PJM IPSAC. December 2, Revised December 22, PJM IPSAC Meeting, December 2,

MISO PJM IPSAC. December 2, Revised December 22, PJM IPSAC Meeting, December 2, MISO PJM IPSAC December 2, 2016 Revised December 22, 2016 1 Agenda 2 TMEP Final JOA Language Recommended TMEPs Order No. 1000 Compliance Filing Generation Deactivation JOA Language PJM Proposal Window

More information

Cost Allocation Reform Update

Cost Allocation Reform Update Cost Allocation Reform Update Regional Expansion Criteria and Benefits Working Group May 18, 2017 Conditions Precedent for Regional Transmission Investment 1. Increased consensus regarding the issue(s)

More information

MISO Cost Allocation Response. RECBWG February 15, 2018

MISO Cost Allocation Response. RECBWG February 15, 2018 MISO Cost Allocation Response RECBWG February 15, 2018 MISO Cost Allocation Response: February 2018 Context The overall objective of the MISO transmission cost allocation methodology is to align who pays

More information

History of Cost Allocation within MISO RECB TF. January 29, 2015

History of Cost Allocation within MISO RECB TF. January 29, 2015 History of Cost Allocation within MISO RECB TF January 29, 2015 Cost Allocation FERC Orders, Filings, and Rulings Cost allocation for MISO began with Order 2003 which instituted a pro forma Generator Interconnection

More information

Lower Voltage Interregional Economic Projects. RECBWG April 18, 2018

Lower Voltage Interregional Economic Projects. RECBWG April 18, 2018 Lower Voltage Interregional Economic Projects RECBWG April 18, 2018 Interregional Gaps & Inconsistencies 1. No tariff defined cost allocation for sub 345 kv economic projects with PJM 2. Economic projects

More information

161 FERC 61,004 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

161 FERC 61,004 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 161 FERC 61,004 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Neil Chatterjee, Chairman; Cheryl A. LaFleur, and Robert F. Powelson. Midcontinent Independent System

More information

System Load * Days in Month Weighted Load In Month Effective by Month January 2, ,727 February 2, ,665 March 2, ,515

System Load * Days in Month Weighted Load In Month Effective by Month January 2, ,727 February 2, ,665 March 2, ,515 NIPSCO Aggregate 206 True-up Calculations Instructions: Inputs are indicated by light yellow highlighted cells with blue bold font. For "Company Name" be sure to use our standard abbreviations or check

More information

PJM/MISO Cost Allocation For Economic Upgrades

PJM/MISO Cost Allocation For Economic Upgrades PJM/MISO Cost Allocation For Economic Upgrades Stakeholder Meeting Hilton Baltimore BWI, Baltimore MD May 19, 2008 1 Topics for Discussion Background FERC Order / Schedule (RTO Staffs) Review Internal

More information

PJM SERTP Planning Process Overview

PJM SERTP Planning Process Overview PJM SERTP Planning Process Overview Order 1000 Biennial Regional Transmission Plan Review Meeting Presentation 1 of 2 May 8 th, 2018 Georgia Power Corporate Headquarters Atlanta, GA PJM SERTP Interregional

More information

Common stock prices 1. New York Stock Exchange indexes (Dec. 31,1965=50)2. Transportation. Utility 3. Finance

Common stock prices 1. New York Stock Exchange indexes (Dec. 31,1965=50)2. Transportation. Utility 3. Finance Digitized for FRASER http://fraser.stlouisfed.org/ Federal Reserve Bank of St. Louis 000 97 98 99 I90 9 9 9 9 9 9 97 98 99 970 97 97 ""..".'..'.."... 97 97 97 97 977 978 979 980 98 98 98 98 98 98 987 988

More information

MISO SCHEDULE 38 SCHEDULES SCHEDULE 38. MTEP Project Cost Recovery for DEO and DEK

MISO SCHEDULE 38 SCHEDULES SCHEDULE 38. MTEP Project Cost Recovery for DEO and DEK SCHEDULE 38 I. Definitions Any capitalized terms not defined in this Schedule 38 shall have the meaning as defined in Module A of the Tariff. Definitions for this Schedule 38 are as follows: A. ATSI American

More information

FERC EL Settlement Agreement

FERC EL Settlement Agreement FERC EL05-121-009 Settlement Agreement Ray Fernandez Manager, Market Settlements Development Market Settlements Subcommittee June 14, 2018 Settlement Agreement Details Settlement Agreement Details FERC

More information

ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC

ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC 20004-1404

More information

ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC

ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC 20004-1404

More information

FOR RELEASE: MONDAY, MARCH 21 AT 4 PM

FOR RELEASE: MONDAY, MARCH 21 AT 4 PM Interviews with 1,012 adult Americans conducted by telephone by Opinion Research Corporation on March 18-20, 2011. The margin of sampling error for results based on the total sample is plus or minus 3

More information

Southwest Power Pool SEAMS STEERING COMMITTEE MEETING July 8, 2014 Conference Call MINUTES

Southwest Power Pool SEAMS STEERING COMMITTEE MEETING July 8, 2014 Conference Call MINUTES Southwest Power Pool SEAMS STEERING COMMITTEE MEETING July 8, 2014 Conference Call MINUTES Agenda Item 1 Administrative Items Seams Steering Committee (SSC) Chair Paul Malone, NPPD, called the meeting

More information

California ISO Report. Regional Marginal Losses Surplus Allocation Impact Study

California ISO Report. Regional Marginal Losses Surplus Allocation Impact Study California ISO Report Regional Surplus Allocation Impact Study October 6, 2010 Regional Surplus Allocation Impact Study Table of Contents Executive Summary... 3 1 Issue and Background... 3 2 Study Framework...

More information

February 23, 2015 VIA ELECTRONIC FILING

February 23, 2015 VIA ELECTRONIC FILING February 23, 2015 VIA ELECTRONIC FILING The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: Southwest Power Pool, Inc., Docket

More information

Seams Cost Allocation: A Flexible Framework to Support Interregional Transmission Planning (Summary of Final Report)

Seams Cost Allocation: A Flexible Framework to Support Interregional Transmission Planning (Summary of Final Report) Seams Cost Allocation: A Flexible Framework to Support Interregional Transmission Planning (Summary of Final Report) Presented at: SPP RSC Quarterly Meeting Presented by: Johannes Pfeifenberger Delphine

More information

FTR Credit Requirements Prevailing Flow Paths Affected by Transmission System Upgrades

FTR Credit Requirements Prevailing Flow Paths Affected by Transmission System Upgrades FTR Credit Requirements Prevailing Flow Paths Affected by Transmission System Upgrades Hal Loomis Manager, Credit Markets & Reliability Committee December 7, 2017 Credit Risk Exposure Issue Description

More information

ITC Midwest 2014 Attachment O True-Up Presentation. Presenter: David Grover Manager, Transmission Pricing July 8, 2015

ITC Midwest 2014 Attachment O True-Up Presentation. Presenter: David Grover Manager, Transmission Pricing July 8, 2015 2014 Attachment O True-Up Presentation Presenter: David Grover Manager, Transmission Pricing July 8, 2015 Presentation Purpose Discuss the 2014 Annual True-Up posting Walk through the timeline and mechanics

More information

FERC Order 1000: Transmission Planning & Cost Allocation NYISO Compliance Update

FERC Order 1000: Transmission Planning & Cost Allocation NYISO Compliance Update FERC Order 1000: Transmission Planning & Cost Allocation NYISO Compliance Update by John P. Buechler NYISO Executive Regulatory Policy Advisor NPCC Governmental/Regulatory Affairs Advisory Group November

More information

2017 Actual Cost Attachment O, GG and MM Rate Template Presentation

2017 Actual Cost Attachment O, GG and MM Rate Template Presentation 2017 Actual Cost Attachment O, GG and MM Rate Template Presentation Dehn Stevens General Manager Transmission July 19, 2018 Meeting Purpose The purpose of today s meeting is to review the 2017 Attachments

More information

September 30, Part Version Title V LNG Rates

September 30, Part Version Title V LNG Rates Columbia Pipeline Group 5151 San Felipe, Ste 2400, Houston, Texas, USA 77056 Tel: 713.386.3776 slinder@cpg.com Sorana Linder Director, Regulated Services September 30, 2016 Ms. Kimberly D. Bose Federal

More information

Ch. 13 Practice Questions Solution

Ch. 13 Practice Questions Solution Buad 121 Ch. 13 Practice Questions Solution Exercise 13-9 (20 minutes) a. Mar. 10 Machinery... 60,000 Cash... 60,000 Purchased machinery for cash. b. Mar. 10 Machinery... Accounts Payable... 60,000 60,000

More information

Transmission Cost Allocation

Transmission Cost Allocation Transmission Cost Allocation IPSAC February 2, 2010 John P. Buechler NYISO Executive Regulatory Policy Advisor Background FERC Policy has evolved Order 888 No Planning Requirement for ISOs Order 2000 Planning

More information

Historical Pricing PJM COMED, Around the Clock. Cal '15 Cal '16 Cal '17 Cal '18 Cal '19 Cal '20 Cal '21 Cal '22

Historical Pricing PJM COMED, Around the Clock. Cal '15 Cal '16 Cal '17 Cal '18 Cal '19 Cal '20 Cal '21 Cal '22 $50 Historical Pricing PJM COMED, Around the Clock $48 $46 $44 $42 $40 $38 $36 $34 $32 $30 $28 $26 Cal '15 Cal '16 Cal '17 Cal '18 Cal '19 Cal '20 Cal '21 Cal '22 The information presented above was gathered

More information

Settlements and ADR Time Bars. Market Subcommittee February 8, 2018

Settlements and ADR Time Bars. Market Subcommittee February 8, 2018 Settlements and ADR Time Bars Market Subcommittee February 8, 2018 Purpose and Key Takeaways Purpose Update stakeholders on proposed Tariff revisions establishing time limits for disputes, corrections

More information

Stakeholder Survey I Cross Border Cost Allocation for Economic Transmission Projects For Discussion September 24, 2008

Stakeholder Survey I Cross Border Cost Allocation for Economic Transmission Projects For Discussion September 24, 2008 PJM and the Midwest ISO are seeking input from stakeholders on various concepts that have been discussed during the PJM/Midwest ISO Cross-Border meetings for dealing with transmission projects constructed

More information

May 15, Duke Energy Ohio, Inc., and Duke Energy Kentucky, Inc. Formula Rate Annual Update Docket No. ER

May 15, Duke Energy Ohio, Inc., and Duke Energy Kentucky, Inc. Formula Rate Annual Update Docket No. ER Gary A. Morgans 202 429 6234 gmorgans@steptoe.com 1330 Connecticut Avenue, NW Washington, DC 20036-1795 202 429 3000 main www.steptoe.com The Hon. Kimberly D. Bose Secretary Federal Energy Regulatory Commission

More information

Financial & Business Highlights For the Year Ended June 30, 2017

Financial & Business Highlights For the Year Ended June 30, 2017 Financial & Business Highlights For the Year Ended June, 17 17 16 15 14 13 12 Profit and Loss Account Operating Revenue 858 590 648 415 172 174 Investment gains net 5 162 909 825 322 516 Other 262 146

More information

Historical Pricing PJM PSEG, Around the Clock. Cal '15 Cal '16 Cal '17 Cal '18 Cal '19 Cal '20 Cal '21 Cal '22

Historical Pricing PJM PSEG, Around the Clock. Cal '15 Cal '16 Cal '17 Cal '18 Cal '19 Cal '20 Cal '21 Cal '22 $70 Historical Pricing PJM PSEG, Around the Clock $65 $60 $55 $50 $45 $40 $35 $30 $25 Cal '15 Cal '16 Cal '17 Cal '18 Cal '19 Cal '20 Cal '21 Cal '22 The information presented above was gathered and compiled

More information

HUD NSP-1 Reporting Apr 2010 Grantee Report - New Mexico State Program

HUD NSP-1 Reporting Apr 2010 Grantee Report - New Mexico State Program HUD NSP-1 Reporting Apr 2010 Grantee Report - State Program State Program NSP-1 Grant Amount is $19,600,000 $9,355,381 (47.7%) has been committed $4,010,874 (20.5%) has been expended Grant Number HUD Region

More information

NORTHERN INDIANA PUBLIC SERVICE COMPANY Attachment GG True-Up Adjustment For the Year Ended December 31, 2014

NORTHERN INDIANA PUBLIC SERVICE COMPANY Attachment GG True-Up Adjustment For the Year Ended December 31, 2014 NORTHERN INDIANA PUBLIC SERVICE COMPANY Attachment GG True-Up Adjustment For the Year Ended December 31, 2014 Attachment GG Projected Proportion Actual True Up Revenue of Revenues Revenue Interest allocated

More information

June 20, Ms. Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C

June 20, Ms. Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C McGuireWoods LLP 2001 K Street N.W. Suite 400 Washington, DC 20006-1040 Phone: 202.857.1700 Fax: 202.857.1737 www.mcguirewoods.com Julia Dryden English Direct: 202.857.1706 jenglish@mcguirewoods.com Fax:

More information

EIM market monitoring and market issues/performance

EIM market monitoring and market issues/performance EIM market monitoring and market issues/performance Energy Imbalance Market Regional Issues Forum April 6, 2016 Eric Hildebrandt, Director Department of Market Monitoring EIM Market Monitoring Page 2 Mission

More information

Spheria Australian Smaller Companies Fund

Spheria Australian Smaller Companies Fund 29-Jun-18 $ 2.7686 $ 2.7603 $ 2.7520 28-Jun-18 $ 2.7764 $ 2.7681 $ 2.7598 27-Jun-18 $ 2.7804 $ 2.7721 $ 2.7638 26-Jun-18 $ 2.7857 $ 2.7774 $ 2.7690 25-Jun-18 $ 2.7931 $ 2.7848 $ 2.7764 22-Jun-18 $ 2.7771

More information

FERC Order 1000: Transmission Planning & Cost Allocation Framework for NYISO Compliance

FERC Order 1000: Transmission Planning & Cost Allocation Framework for NYISO Compliance FERC Order 1000: Transmission Planning & Cost Allocation Framework for NYISO Compliance by John P Buechler NYISO Executive Regulatory Policy Advisor Joint IPTF/ESPWG Meeting February 27, 2012 Albany, NY

More information

XML Publisher Balance Sheet Vision Operations (USA) Feb-02

XML Publisher Balance Sheet Vision Operations (USA) Feb-02 Page:1 Apr-01 May-01 Jun-01 Jul-01 ASSETS Current Assets Cash and Short Term Investments 15,862,304 51,998,607 9,198,226 Accounts Receivable - Net of Allowance 2,560,786

More information

Informational Filing of Midwest Independent Transmission System Operator, Inc. s Independent Market Monitor

Informational Filing of Midwest Independent Transmission System Operator, Inc. s Independent Market Monitor Potomac Economics, Ltd. 9990 Fairfax Boulevard, Suite 560 Telephone: 703-383-0720 Fairfax, Virginia 22030 Facsimile: 703-383-0796 Honorable Kimberly D. Bose, Secretary Federal Energy Regulatory Commission

More information

FDD FIRM STORAGE SERVICE NORTHERN NATURAL GAS COMPANY

FDD FIRM STORAGE SERVICE NORTHERN NATURAL GAS COMPANY FDD FIRM STORAGE SERVICE NORTHERN NATURAL GAS COMPANY FIRM STORAGE SERVICE OPTIONS Northern s firm storage service is provided pursuant to the FDD Rate Schedule located in Northern s FERC Gas Tariff. The

More information

Development of Economy and Financial Markets of Kazakhstan

Development of Economy and Financial Markets of Kazakhstan Development of Economy and Financial Markets of Kazakhstan National Bank of Kazakhstan Macroeconomic development GDP, real growth, % 116 112 18 14 1 113,5 11,7 216,7223,8226,5 19,8 19,8 19,3 19,619,7 199,

More information

1 Long Term Debt $ 9,298,554 $ (250,000) $ 9,048, Preferred Stock 30,450 30, % 5 Common Equity 250, %

1 Long Term Debt $ 9,298,554 $ (250,000) $ 9,048, Preferred Stock 30,450 30, % 5 Common Equity 250, % SUMMARY SCHEDULE ($000'S) Schedule 1 Page 1 of 1 Line Capitalization HISTORICAL YEAR ENDED 12/31/16 Hybrid Percent Equity Adjusted of Total Cost of Cost of Amount Adjustment Amount Capitalization Capital

More information

Review of Membership Developments

Review of Membership Developments RIPE Network Coordination Centre Review of Membership Developments 7 October 2009/ GM / Lisbon http://www.ripe.net 1 Applications development RIPE Network Coordination Centre 140 120 100 80 60 2007 2008

More information

Electric Price Outlook for Indiana High Load Factor (HLF) customers September 2015

Electric Price Outlook for Indiana High Load Factor (HLF) customers September 2015 Electric Price Outlook for Indiana High Load Factor (HLF) customers September 2015 Price projection Duke Energy Indiana s prices continue to drop for the fourth quarter of 2015. Depending on your total

More information

QUARTERLY FINANCIAL REPORT March 31, 2018

QUARTERLY FINANCIAL REPORT March 31, 2018 California Independent System Operator QUARTERLY FINANCIAL REPORT March 31, 2018 250 Outcropping Way Folsom, CA 95630 (916) 351-4000 CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION QUARTERLY FINANCIAL

More information

FERC Order 1000: Planning for the Right of First Refusal and Planning for Public Policy Status & Implementation in New York

FERC Order 1000: Planning for the Right of First Refusal and Planning for Public Policy Status & Implementation in New York 1 FERC Order 1000: Planning for the Right of First Refusal and Planning for Public Policy Status & Implementation in New York Henry Chao Vice President - System and Resource Planning New York Independent

More information

QUARTERLY FINANCIAL REPORT June 30, 2017

QUARTERLY FINANCIAL REPORT June 30, 2017 California Independent System Operator QUARTERLY FINANCIAL REPORT June 30, 2017 250 Outcropping Way Folsom, CA 95630 (916) 351-4000 CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION QUARTERLY FINANCIAL

More information

2019 Budget and Grid Management Charge Initial Stakeholder Meeting

2019 Budget and Grid Management Charge Initial Stakeholder Meeting 2019 Budget and Grid Management Charge Initial Stakeholder Meeting July 24, 2018 Agenda Topic: Welcome and Introductions Presenter: Kristina Osborne 2019 Budget Process & GMC Rate Outlook April Gordon

More information

Midwest Independent Transmission System Operator, Inc. Duke Energy Ohio, Inc. and Duke Energy Kentucky, Inc. Docket No. ER

Midwest Independent Transmission System Operator, Inc. Duke Energy Ohio, Inc. and Duke Energy Kentucky, Inc. Docket No. ER Lori A. Spence Deputy General Counsel Direct Dial: 317-249-5442 E-mail: lspence@misoenergy.org November 2, 2011 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street,

More information

OTHER DEPOSITS FINANCIAL INSTITUTIONS DEPOSIT BARKAT SAVING ACCOUNT

OTHER DEPOSITS FINANCIAL INSTITUTIONS DEPOSIT BARKAT SAVING ACCOUNT WEIGHTAGES JAN FEB MAR APR MAY JUN JUL AUG SEPT OCT NOV DEC ANNOUNCEMENT DATE 19.Dez.14 27.Jän.15 24.Feb.15 26.Mär.15 27.Apr.15 26.Mai.15 25.Jun.15 28.Jul.15 26.Aug.15 23.Sep.15 27.Okt.15 25.Nov.15 MUDARIB

More information

Filed with the Iowa Utilities Board on May 31, 2017, E STATE OF IOWA DEPARTMENT OF COMMERCE UTILITIES BOARD

Filed with the Iowa Utilities Board on May 31, 2017, E STATE OF IOWA DEPARTMENT OF COMMERCE UTILITIES BOARD STATE OF IOWA DEPARTMENT OF COMMERCE UTILITIES BOARD IN RE: MIDAMERICAN ENERGY IN RE: DOCKET NOS. E-22269, E-22270, AND E-22271 DOCKET NO. E-22279 (consolidated) ITC MIDWEST LLC BRIEF BY THE MIDCONTINENT

More information

PHOENIX ENERGY MARKETING CONSULTANTS INC. HISTORICAL NATURAL GAS & CRUDE OIL PRICES UPDATED TO July, 2018

PHOENIX ENERGY MARKETING CONSULTANTS INC. HISTORICAL NATURAL GAS & CRUDE OIL PRICES UPDATED TO July, 2018 Jan-01 $12.9112 $10.4754 $9.7870 $1.5032 $29.2595 $275.39 $43.78 $159.32 $25.33 Feb-01 $10.4670 $7.8378 $6.9397 $1.5218 $29.6447 $279.78 $44.48 $165.68 $26.34 Mar-01 $7.6303 $7.3271 $5.0903 $1.5585 $27.2714

More information

Calculate Net Annual Transmission Revenue Requirements (ATRR) and Rates for SPP Tariff. Total Transmission A. Zonal Net ATRR 1 Gross ATRR $60,516,589

Calculate Net Annual Transmission Revenue Requirements (ATRR) and Rates for SPP Tariff. Total Transmission A. Zonal Net ATRR 1 Gross ATRR $60,516,589 Page 1 Formula-based Rate Template Calculate Net Annual Transmission Revenue Requirements (ATRR) and Rates for SPP Tariff Line No. Acct Description Notes Total Transmission A. Zonal Net ATRR 1 Gross ATRR

More information

Government Bond Market Development in Myanmar

Government Bond Market Development in Myanmar Government Bond Market Development in Myanmar Daw Si Si Pyone Deputy Director General Treasury Department 11-8-2017 Ministry of Planning and Finance 1 Outlines I. Key Milestones in Development of Treasury

More information

NORTHEASTERN ISO/RTO PLANNING COORDINATION PROTOCOL DESIGNATION OF FILING PARTY

NORTHEASTERN ISO/RTO PLANNING COORDINATION PROTOCOL DESIGNATION OF FILING PARTY NORTHEASTERN ISO/RTO PLANNING COORDINATION PROTOCOL DESIGNATION OF FILING PARTY The Northeastern ISO/RTO Planning Coordination Protocol among PJM Interconnection, L.L.C. ( PJM ), the New York Independent

More information

Long Term Access Goal Final Report Update

Long Term Access Goal Final Report Update Long Term Access Goal 2007-09 Final Report 2008-10 Update SME Version of Presentation for ATC Board of Directors Meeting December 14, 2009 2007-09 and 2008-10 Long Term Goals Access (10%) Reduce congestion

More information

153 FERC 61,249 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER REJECTING TARIFF REVISIONS. (Issued November 30, 2015)

153 FERC 61,249 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER REJECTING TARIFF REVISIONS. (Issued November 30, 2015) 153 FERC 61,249 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Norman C. Bay, Chairman; Cheryl A. LaFleur, Tony Clark, and Colette D. Honorable. Southwest Power Pool,

More information

2011 Budget vs. Actual Status

2011 Budget vs. Actual Status 2011 Budget vs. Actual Status (unaudited d results) ($ in millions, unless otherwise noted) Draft - For Discussion Purposes Only Cheryl Hussey Controller & Asst. Treasurer Budget & Priorities Working Group

More information

Performance Report October 2018

Performance Report October 2018 Structured Investments Indicative Report October 2018 This report illustrates the indicative performance of all Structured Investment Strategies from inception to 31 October 2018 Matured Investment Strategies

More information

Review of Registered Charites Compliance Rates with Annual Reporting Requirements 2016

Review of Registered Charites Compliance Rates with Annual Reporting Requirements 2016 Review of Registered Charites Compliance Rates with Annual Reporting Requirements 2016 October 2017 The Charities Regulator, in accordance with the provisions of section 14 of the Charities Act 2009, carried

More information

Business & Financial Services December 2017

Business & Financial Services December 2017 Business & Financial Services December 217 Completed Procurement Transactions by Month 2 4 175 15 125 1 75 5 2 1 Business Days to Complete 25 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 217 Procurement

More information

Distribution Group Study Process. August 26, 2014

Distribution Group Study Process. August 26, 2014 Distribution Group Study Process August 26, 2014 Agenda Overview Applying for DGSP DGSP Interconnection Process Applicability and Utility Contacts Questions 2 Process Overview Open Window Period Evaluation

More information

September 29, Ms. Kavita Kale Executive Secretary Michigan Public Service Commission 7109 West Saginaw Highway P.O. Box Lansing, MI 48909

September 29, Ms. Kavita Kale Executive Secretary Michigan Public Service Commission 7109 West Saginaw Highway P.O. Box Lansing, MI 48909 A CMS Energy Company September, 0 Ms. Kavita Kale Executive Secretary Michigan Public Service Commission 0 West Saginaw Highway P.O. Box 0 Lansing, MI 0 General Offices: LEGAL DEPARTMENT One Energy Plaza

More information

MONTHLY FINANCIAL REPORT June 2009

MONTHLY FINANCIAL REPORT June 2009 California Independent System Operator MONTHLY FINANCIAL REPORT June 2009 151 Blue Ravine Road Folsom, CA 95630 (916) 351-4000 CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION MONTHLY FINANCIAL REPORT

More information

La Régie de l énergie Demande de Hydro-Québec Dossier R Hydro-Québec tariff application. Evidence of Darrell Bishop

La Régie de l énergie Demande de Hydro-Québec Dossier R Hydro-Québec tariff application. Evidence of Darrell Bishop 1 1 1 1 1 1 1 1 0 1 0 1 0 1 La Régie de l énergie Demande de Hydro-Québec Dossier R-01- Hydro-Québec tariff application Evidence of Darrell Bishop Q1. What is your name and position? My name is Darrell

More information

ITC Holdings Corp. Fourth Quarter & Year End 2013 Investor Call February 27, 2014

ITC Holdings Corp. Fourth Quarter & Year End 2013 Investor Call February 27, 2014 ITC Holdings Corp. Fourth Quarter & Year End 2013 Investor Call February 27, 2014 Safe Harbor Language & Legal Disclosure This presentation contains certain statements that describe our management s beliefs

More information

ATTACHMENTS ATTACHMENT GG NETWORK UPGRADE CHARGE

ATTACHMENTS ATTACHMENT GG NETWORK UPGRADE CHARGE ATTACHMENT GG Network Upgrade Charge ATTACHMENTS 32.0.0 ATTACHMENT GG NETWORK UPGRADE CHARGE 1. Network Upgrade Cost Allocation: This Attachment GG sets forth the method for calculating and collecting

More information

Standard Market Design: FERC Process and Issues

Standard Market Design: FERC Process and Issues Standard Market Design: FERC Process and Issues Richard O Neill and Udi Helman Division of the Chief Economic Advisor, Office of Markets, Tariffs and Rates Federal Energy Regulatory Commission IEEE PES

More information

Order No Transmission Planning and Cost Allocation

Order No Transmission Planning and Cost Allocation Order No. 1000 Transmission Planning and Cost Allocation Thursday, August 18, 2011, 1:00 pm Eastern Panelists: John D. McGrane, Floyd L. Norton, IV, Stephen M. Spina www.morganlewis.com Overview Order

More information

EMPLOYER MUNICIPAL QUARTERLY WITHHOLDING BOOKLET

EMPLOYER MUNICIPAL QUARTERLY WITHHOLDING BOOKLET DIVISION OF TAXATION CITY OF WESTERVILLE P.O. BOX 130 WESTERVILLE, OHIO 43086-0130 IMPORTANT TAX INFORMATION EMPLOYER MUNICIPAL QUARTERLY WITHHOLDING BOOKLET IN ORDER TO INSURE PROPER POSTING OF YOUR WITHHOLDING

More information

Balancing Ratio Determination

Balancing Ratio Determination Balancing Ratio Determination Patrick Bruno Sr. Engineer, Capacity Market Operations Markets Implementation Committee March 7, 2018 www.pjm.com Issue Recap The current rules set the default Market Seller

More information

QUESTION 2. QUESTION 3 Which one of the following is most indicative of a flexible short-term financial policy?

QUESTION 2. QUESTION 3 Which one of the following is most indicative of a flexible short-term financial policy? QUESTION 1 Compute the cash cycle based on the following information: Average Collection Period = 47 Accounts Payable Period = 40 Average Age of Inventory = 55 QUESTION 2 Jan 41,700 July 39,182 Feb 18,921

More information

CONTENTS COMMENTARY CHARTS TABLES GLOSSARY. Section 1: Headline Inflation Section 2: Core Inflation

CONTENTS COMMENTARY CHARTS TABLES GLOSSARY. Section 1: Headline Inflation Section 2: Core Inflation COMMENTARY CONTENTS Section 1: Headline Inflation Section 2: Core Inflation CHARTS 1. National Rates of Inflation, January 2010 April 2013 2. Monthly Changes in the Cost-of-Living Index, January 2010 April

More information

GMARG Meeting. Tuesday 18 th October 2018

GMARG Meeting. Tuesday 18 th October 2018 GMARG Meeting Tuesday 18 th October 2018 Today s Agenda 2 Item Number Description Time Allotted 1 Introduction/confirmation of attendees 5 mins 2 Review of Previous Minutes and Actions 20 mins 3 Eircodes

More information

Operating Reserves Educational Session Part B

Operating Reserves Educational Session Part B Operating Reserves Educational Session Part B Energy Market Uplift Senior Task Force September 17, 2013 Joseph Bowring Joel Romero Luna Operating Reserves Operating reserves can be grouped into five categories:

More information

April 24, 2015 VIA ELECTRONIC FILING

April 24, 2015 VIA ELECTRONIC FILING April 24, 2015 VIA ELECTRONIC FILING The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: Southwest Power Pool, Inc., Docket No.

More information

Big Walnut Local School District

Big Walnut Local School District Big Walnut Local School District Monthly Financial Report for the month ended September 30, 2013 Prepared By: Felicia Drummey Treasurer BIG WALNUT LOCAL SCHOOL DISTRICT SUMMARY OF YEAR TO DATE FINANCIAL

More information

Chapter 6. Solution: Austin Electronics. State of Economy Sales Probability

Chapter 6. Solution: Austin Electronics. State of Economy Sales Probability Chapter 6 Problems 6-1. Austin Electronics expects sales next year to be $900,000 if the economy is strong, $650,000 if the economy is steady, and $375,000 if the economy is weak. The firm believes there

More information

FOR RELEASE: WEDNESDAY, NOVEMBER 17 AT 11:30 AM

FOR RELEASE: WEDNESDAY, NOVEMBER 17 AT 11:30 AM Interviews with 1,014 adult Americans conducted by telephone by Opinion Research Corporation on November 11-14, 2010. The margin of sampling error for results based on the total sample is plus or minus

More information

Supplemental Slides Third Quarter 2018 Earnings. November 1, 2018

Supplemental Slides Third Quarter 2018 Earnings. November 1, 2018 Supplemental Slides Third Quarter 2018 Earnings November 1, 2018 Forward-Looking Statements This presentation contains forward-looking statements within the meaning of federal securities laws. Investors

More information

WESTWOOD LUTHERAN CHURCH Summary Financial Statement YEAR TO DATE - February 28, Over(Under) Budget WECC Fund Actual Budget

WESTWOOD LUTHERAN CHURCH Summary Financial Statement YEAR TO DATE - February 28, Over(Under) Budget WECC Fund Actual Budget WESTWOOD LUTHERAN CHURCH Summary Financial Statement YEAR TO DATE - February 28, 2018 General Fund Actual A B C D E F WECC Fund Actual Revenue Revenue - Faith Giving 1 $ 213 $ 234 $ (22) - Tuition $ 226

More information

Planning in a competitive market environment

Planning in a competitive market environment Planning in a competitive market environment The New York Story Rana Mukerji Senior Vice President - Market Structures New York Independent System Operator Harvard Electricity Policy Group 74 th Plenary

More information

Supplemental Slides Second Quarter 2018 Earnings. August 1, 2018

Supplemental Slides Second Quarter 2018 Earnings. August 1, 2018 Supplemental Slides Second Quarter 2018 Earnings August 1, 2018 Forward-Looking Statements This presentation contains forward-looking statements within the meaning of federal securities laws. Investors

More information

QUARTERLY FINANCIAL REPORT December 31, 2017

QUARTERLY FINANCIAL REPORT December 31, 2017 California Independent System Operator QUARTERLY FINANCIAL REPORT December 31, 2017 Preliminary and Unaudited 250 Outcropping Way Folsom, CA 95630 (916) 351-4000 CALIFORNIA INDEPENDENT SYSTEM OPERATOR

More information

TERMS OF REFERENCE FOR THE INVESTMENT COMMITTEE

TERMS OF REFERENCE FOR THE INVESTMENT COMMITTEE I. PURPOSE The purpose of the Investment Committee (the Committee ) is to recommend to the Board the investment policy, including the asset mix policy and the appropriate benchmark for both ICBC and any

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION New York Independent System Operator, Inc. ) PJM Interconnection, L.L.C. ) Docket Nos. ER17-905-002 ) MOTION FOR LEAVE TO ANSWER

More information

EMPLOYER JEDZ MONTHLY WITHHOLDING BOOKLET

EMPLOYER JEDZ MONTHLY WITHHOLDING BOOKLET BLENDON TOWNSHIP JEDZ C/O CITY OF WESTERVILLE PO BOX 636 WESTERVILLE, OH 43086-0636 IMPORTANT TAX INFORMATION EMPLOYER JEDZ MONTHLY WITHHOLDING BOOKLET IN ORDER TO INSURE PROPER POSTING OF YOUR WITHHOLDING

More information

Statement Guide NEW STATEMENT ACTIVITY SUMMARY

Statement Guide NEW STATEMENT ACTIVITY SUMMARY Statement Guide Online Statement Access in Vantiv iq Starting today, your statements are available in a new location. As a Vantiv ISO merchant, you will benefit from the convenience of online statements

More information

1.2 The purpose of the Finance Committee is to assist the Board in fulfilling its oversight responsibilities related to:

1.2 The purpose of the Finance Committee is to assist the Board in fulfilling its oversight responsibilities related to: Category: BOARD PROCESS Title: Terms of Reference for the Finance Committee Reference Number: AB-331 Last Approved: February 22, 2018 Last Reviewed: February 22, 2018 1. PURPOSE 1.1 Primary responsibility

More information

March 19, MidAmerican Central California Transco, LLC Docket No. ER

March 19, MidAmerican Central California Transco, LLC Docket No. ER 1050 Thomas Jefferson Street, NW Seventh Floor Washington, DC 20007 (202) 298-1800 Phone (202) 338-2416 Fax Douglas W. Smith (202) 298-1902 dws@vnf.com March 19, 2019 Via e-filing Kimberly D. Bose Secretary

More information

Calculate Net Annual Transmission Revenue Requirements (ATRR) and Rates for SPP Tariff. Total Transmission A. Zonal Net ATRR 1 Gross ATRR $48,861,618

Calculate Net Annual Transmission Revenue Requirements (ATRR) and Rates for SPP Tariff. Total Transmission A. Zonal Net ATRR 1 Gross ATRR $48,861,618 Page 1 Formula-based Rate Template Calculate Net Annual Transmission Revenue Requirements (ATRR) and Rates for SPP Tariff Line Acct Description Notes Total Transmission A. Zonal Net ATRR 1 Gross ATRR $48,861,618

More information

NATIONAL SUMMARY OF FIRST-TIME CLAIMANTS FOR UI

NATIONAL SUMMARY OF FIRST-TIME CLAIMANTS FOR UI 2013 JAN 5 553,348 553,348 372,000 372,000 92,383,961 93,647,000 12 555,708 1,109,056 335,000 707,000 92,939,669 93,982,000 19 437,025 1,546,081 330,000 1,037,000 93,376,694 94,312,000 26 369,480 1,915,561

More information

SPP s Regional Review of SPP-MISO Coordinated System Plan Recommended Interregional Projects

SPP s Regional Review of SPP-MISO Coordinated System Plan Recommended Interregional Projects SPP s Regional Review of SPP-MISO Coordinated System Plan Recommended Interregional Projects January 4, 2016 SPP Interregional Relations Table of Contents Executive Summary... 2 Introduction... 5 Stakeholder

More information

Project NEON Interim Finance Committee Rudy Malfabon Director

Project NEON Interim Finance Committee Rudy Malfabon Director Project NEON Interim Finance Committee Rudy Malfabon Director October 22, 2014 1 Project Benefits Safety & Congestion 1,000 crashes per year! Connectivity /Mobility for City Redevelopment Efforts Congestion:

More information

PERFORMANCE METRICS AND PENALTIES STUDY FOR TRANSMISSION SERVICE REQUESTS

PERFORMANCE METRICS AND PENALTIES STUDY FOR TRANSMISSION SERVICE REQUESTS PERFORMANCE METRICS AND PENALTIES STUDY FOR TRANSMISSION SERVICE REQUESTS In this Section: Overview Performance Metrics and Penalties Notification Filing Additional Performance Metrics Penalties for Late

More information

Please scroll to find the 2018 and 2019 global fund holiday calendars.

Please scroll to find the 2018 and 2019 global fund holiday calendars. Please scroll to find the 2018 and 2019 global fund holiday calendars. 2018 Exchange-Traded fund holiday Vanguard Ireland-domiciled ETFs Jan Feb Mar Apr May Jun 1 2 5 12 15 25 9 12 14 15 16 19 28 20 29

More information

Pay or Play Penalties Look-back Measurement Method Examples

Pay or Play Penalties Look-back Measurement Method Examples Brought to you by Sullivan Benefits Pay or Play Penalties Look-back Measurement Method Examples The Affordable Care Act (ACA) imposes a penalty on applicable large employers (ALEs) that do not offer health

More information

Cost Estimation of a Manufacturing Company

Cost Estimation of a Manufacturing Company Cost Estimation of a Manufacturing Company Name: Business: Date: Economics of One Unit: Manufacturing Company (Only complete if you are making a product, such as a bracelet or beauty product) Economics

More information