Summary of FERC White Paper on Bulk Power Market Design and Related Aspects of Senate Energy Bill No. S. 14

Size: px
Start display at page:

Download "Summary of FERC White Paper on Bulk Power Market Design and Related Aspects of Senate Energy Bill No. S. 14"

Transcription

1 Summary of FERC White Paper on Bulk Power Market Design and Related Aspects of Senate Energy Bill No. S. 14 Introduction On April 28, 2003, the Federal Energy Regulatory Commission (FERC or Commission) issued a White Paper on bulk power market design in response to numerous comments it received regarding its Notice of Proposed Rulemaking (NOPR) on Standard Market Design (SMD) issued last summer. FERC sets forth in the White Paper how it intends to change several aspects of its proposed SMD for its Final Rule on market design. FERC has changed the name SMD in the White Paper to wholesale power market platform and states that the Final Rule will focus on the formation of Regional Transmission Organizations (RTOs) and Independent System Operators (ISOs). The Final Rule will also ensure that all independent transmission organizations have sound wholesale market rules. ISOs will now have to meet all Order No characteristics and functions except scope and regional configuration. This would permit the California ISO, ISO-New England and the New York ISO to continue with modifications. It would also allow formation of a Southwest Power Pool ISO. FERC intends to build upon the existing rules established in FERC Order No for its Final Rule on market design. For example, under the Final Rule each RTO or ISO would have an independent market monitor for the individual RTO or ISO or for a larger region. This was not required under Order No Market power mitigation measures would at a minimum include rules limiting bidding flexibilities where there is localized market power. The tariff of the RTO or ISO would also include clear market rules designed to prevent market manipulation strategies. While it appears that FERC conceded several points of its SMD in response to its critics, (in particular claiming jurisdiction over the rates for bundled retail transmission service and the Page 1

2 requirement to utilize locational marginal pricing (LMP) for congestion management), upon closer inspection of the White Paper, it appears that FERC has not really conceded much at all since it has incorporated certain backstops into its reconfigured SMD proposal. For example, if a regional state committee for an RTO or ISO is unable to reach a decision on a certain issue, the RTO or ISO is required to file its own proposal with FERC. Related Aspects of Senate Energy Bill No. S. 14 It is important to note that after the release of FERC s White Paper on market design, a comprehensive energy bill (bill) cleared the Senate Energy and Natural Resources (ENR) Committee on April 30, The bill would send the FERC s proposed SMD back to the Commission on remand and prohibit the FERC from making any related rules or orders until at least July 1, According to Senator Pete Domenici, Chairman of the Senate ENR Committee, though the Commission dropped several controversial issues of SMD in its White Paper, the White Paper did not help to win over members of the ENR committee. Besides delaying SMD, the bill also bans round-trip trading, repeals the Public Utility Holding Act (PUHCA), establishes a mandatory electric reliability organization, and obliges FERC to set up an electric information system for public access to the availability and price of wholesale electricity and transmission. The bill also calls for FERC to discuss with state regulators whether competitive markets and RTOs are working in their regions and the potential to phase-in RTOs. It is important to note that the bill retains a utility s obligation under the Public Utility Regulatory Policies Act of 1978 (PURPA) to purchase power from a qualifying facility until such time that the wholesale and retail markets are demonstrated to be competitive and are certified by the FERC. Page 2

3 In addition, the bill directs FERC to ensure that load-serving entities (LSEs) can protect their native load by allowing them to use their firm or financial transmission rights (FTRs) to meet their service obligations. This provision of the bill ensures that transmission rights will follow the load. For example, if an LSE s service obligation is transferred to another LSE, the successor LSE would be entitled to use the firm transmission rights associated with the transferred service obligation. The bill heads to the Senate floor on May 5, 2003 and is expected to be debated for six weeks. The bill may or may not be passed as currently proposed. Though passage of the bill by the full Senate with the provision to delay SMD intact would slow implementation of market design on a national scale, the bill more than likely will not affect progress at the Midwest Independent System Operator (MISO) or in other regions where RTOs and ISOs already exist. However, the bill may delay market design implementation until at least 2005 in the Southeast and West where there is significant opposition to SMD and RTOs. RTOs, ISOs, and Retail Transmission Rates In the April 28 th White Paper, FERC eliminates the proposed SMD requirement that public utilities create or join an Independent Transmission Provider (ITP). Since the Commission recognizes that practically all public utilities have voluntarily joined RTOs or ISOs, the Commission will direct all remaining public utilities to join either an RTO or ISO in the Final Rule. For the Final Rule, FERC is also proposing to drop the requirement of a single tariff for all load (wholesale and retail). The Commission has also dropped its assertion of jurisdiction over the transmission component of bundled retail rates. However, FERC will continue its Page 3

4 existing practice for RTOs and ISOs of distinguishing between the non-price terms 1 and conditions of transmission service and the rates for transmission service. The non-price terms will apply to all users of the grid, including those with obligations to serve bundled retail customers. The transmission component of bundled retail rates will continue to be set at the state level. Phased-In Implementation of Market Design and Regional Differences As it had stated in the press months before the release of the White Paper, FERC will permit implementation of the revised market design plan in phases and allow for regional differences. FERC also states in the White Paper that if an RTO or ISO can demonstrate that the costs of implementing any feature of the wholesale power market platform outweigh the benefits, the Commission will not require implementation of the feature for that particular RTO or ISO. Regional State Committees The Commission intends to change the name of Regional State Advisory Committees (RSACs) in its proposed SMD to regional state committees in the Final Rule and define the responsibilities of the regional state committees more clearly. Each RTO or ISO will be required to provide a regional state committee as a forum for state representatives to participate in the RTO s or ISO s decision making process. The regional state committees would decide such issues as whether the RTO or ISO would use participant funding for transmission expansion, implement postage-stamp or license plate rates, or utilize locational marginal pricing. 1 Non-price terms and condition include matters such as reserving transmission capacity and scheduling transmission service. Page 4

5 The regional state committees would also oversee the allocation of FTRs under LMP based on existing uses of the transmission grid. Whether to implement the direct allocation of FTRs to customers or an auction with revenues allocated to the customers is up to the regional state committees. The FERC is no longer proposing that FTRs must be auctioned. Transmission Issues FERC explicitly states in its White Paper that existing rights to transmission service will be preserved. If necessary to meet this requirement, FERC further states that the RTO or ISO will create counterflow FTRs in order to make the aggregate set of FTRs physically feasible. If this results in a transmission revenue shortfall, FERC states that the shortfall could be recovered through an uplift charge. The recovery of such a revenue shortfall has been an especially important issue at MISO and has been heavily debated, with the MISO staff and a number of shareholders opposed to recovering a revenue shortfall via an uplift charge. However, other stakeholders, including industrial customers, have supported the uplift approach. It should be noted that noticeably absent from the White Paper is any discussion in regard to the release of incumbent FTRs to retail suppliers under retail access. However, as previously noted, this is currently covered in the Senate Energy Bill No. S. 14. In addition, FERC sets forth in its White Paper that to gain access to a wider range of supply choices, RTOs and ISOs should eliminate the payment of multiple access fees across RTO and ISO borders. The Commission suggests that rate mechanisms to minimize cost shifts should be used. In this context, the FERC may permit an export charge where an RTO or ISO has a significant export imbalance with other RTOs or ISOs. Page 5

6 FERC will require each RTO and ISO to have a clear transmission cost recovery policy outlined in its tariff. The Final Rule will give substantial weight to the regional state committees on the determination of the method that will be used to allocate costs of existing and new transmission facilities. The Commission states that regions may differ on the extent to which they want to rely on participant funding of new transmission facilities. FERC s Backstop Provisions Some industrial customers may fear the increased decision making power given to the regional state committees by FERC in the Final Rule. However, a backstop provision FERC intends to include in the Final Rule may alleviate this fear. If a regional state committee of a RTO or ISO cannot agree on a particular issue, FERC states that the RTO or ISO must file its own proposal. Since it is highly unlikely that a regional state committee would reach a unanimous agreement on decisions for issues such as whether to implement LMP for congestion management or whether to implement FTR auctions, this fear of increased decision making power by states is somewhat alleviated by the FERC backstop provision. Energy Markets and Congestion Management Though FERC has dropped its proposed SMD requirement of LMP, FERC is requiring the RTO or ISO to operate a real-time market for energy balancing as well as a day-ahead market and an ancillary services market when the time is appropriate. The RTO or ISO will develop detailed market rules to be included in its Commission filed tariff. FERC will require that any real-time and day-ahead markets be designed to work reliably with the required congestion management system. FERC states that regions should develop an approach to manage congestion that protects against manipulation, uses the grid efficiently, and Page 6

7 promotes the use of the lowest cost generation. While the Commission s preferred approach to congestion management is through the use of LMP, FERC states in its White Paper that other methods may be proposed. However, the RTO or ISO would need to demonstrate to the Commission how the proposed congestion management system would satisfy general principles contained in the Final Rule. These general principles require the congestion management system to: Protect against market manipulation, such as experienced in the California markets; Promote the efficient use of the transmission grid; Promote the use of the lowest cost generation as intended under traditional economic generation dispatch; Assign cost responsibility to those that cause congestion costs and assign the benefits to those that reduce congestion costs; Reduce involuntary transmission service curtailments, e.g., Transmission Line Loading Relief; and Be compatible with congestion management systems used by other RTOs and ISOs in the electrical interconnection, to avoid creating barriers to trade among RTOs and ISOs. It appears that FERC is calling the hands of states that have opposed LMP, forcing them to come up with alternatives to using LMP to manage congestion. Though many states have been critical of LMP, no one has stepped forth with a workable alternative to using LMP to manage congestion. If regional state committees cannot agree on a congestion management proposal, FERC has included a backstop provision that requires the RTO or ISO to file its own proposal with the Commission. Thus, in regions where states have opposed LMP, if those Page 7

8 states cannot agree on a congestion management proposal, the RTO or ISO in that region could very well file a congestion management proposal with FERC that utilizes LMP. However, other congestion management proposals, such as that used in the ERCOT region, could be proposed as well by an ISO or RTO. Resource Adequacy and Regional Planning FERC also plans to change its stance on resource adequacy and regional planning in the Final Rule on market design. FERC will make clear in the Final Rule that state and local governments are the decision makers in these areas and FERC s role is a supporting one. Nothing in the final rule will change state authority over these matters and FERC will not require a minimum level of resource adequacy. States may decide to impose a resource adequacy requirement on utilities serving load or opt to have RTOs or ISOs operate capacity markets. Regardless, the FERC will require a demonstration that measures have been taken to ensure resource adequacy. With regard to regional planning, the final rule will direct RTOs and ISOs to develop a periodic regional transmission plan for submission to relevant state and local siting authorities. Certain core features (independent operation of the grid, establishment of regional state committees and development of a regional plan) will be required at the onset of the wholesale power market platform proposal but RTOs, ISOs and their regional state committees may work out a timetable and budget for the implementation of remaining elements (energy markets, congestion cost allocation and market monitoring). Page 8

9 Technical Conferences and Comments Before FERC issues the Final Rule on market design, the Commission intends to hold regional technical conferences in the near future, to discuss with states and market participants in each region reasonable timetables for addressing wholesale market design issues discussed in the White Paper and ways to tailor the Commission s Final Rule to benefit customers within the region. The Commission will issue notices of the conferences shortly. The Commission will also accept comments on its White Paper, though no comment deadline has yet been set. The Commission has not provided any indication of when it might issue a final rule. BRUBAKER & ASSOCIATES, INC. James R. Dauphinais Brian C. Collins Page 9

Organization of MISO States Response to the Midwest ISO October Hot Topic on Pricing

Organization of MISO States Response to the Midwest ISO October Hot Topic on Pricing Organization of MISO States Response to the Midwest ISO October Hot Topic on Pricing I. Day Ahead and Real Time Energy and Ancillary Services Pricing Prices that Accurately Reflect the Marginal Cost of

More information

Standard Market Design

Standard Market Design Standard Market Design Dynegy s Perspective Characteristics of the Standard Market Design - SMD RTO provides all transmission service and takes on many if not all control area functions. RTO operates an

More information

UNINTENDED CONSEQUENCES OF DELAYING FERC S STANDARD MARKET DESIGN

UNINTENDED CONSEQUENCES OF DELAYING FERC S STANDARD MARKET DESIGN UNINTENDED CONSEQUENCES OF DELAYING FERC S STANDARD MARKET DESIGN By Elizabeth Anne Moler 1 Executive Vice President Government and Environmental Affairs & Public Policy Exelon Corporation As conferees

More information

Standard Market Design: FERC Process and Issues

Standard Market Design: FERC Process and Issues Standard Market Design: FERC Process and Issues Richard O Neill and Udi Helman Division of the Chief Economic Advisor, Office of Markets, Tariffs and Rates Federal Energy Regulatory Commission IEEE PES

More information

Organized Regional Wholesale Markets

Organized Regional Wholesale Markets Organized Regional Wholesale Markets Paul M. Flynn Shareholder Wright & Talisman, P.C. Overview Organized Market Regions Goals of Regional Markets Energy Markets Congestion and Hedges Market Power and

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Keith Casey, Vice President, Market & Infrastructure Development Date: June 14, 2018 Re: Decision on congestion

More information

MISO MODULE D FERC Electric Tariff MARKET MONITORING AND MITIGATION MEASURES MODULES Effective On: November 19, 2013

MISO MODULE D FERC Electric Tariff MARKET MONITORING AND MITIGATION MEASURES MODULES Effective On: November 19, 2013 MISO MODULE D MARKET MONITORING AND MITIGATION MEASURES MODULES 30.0.0 Effective On: November 19, 2013 MISO I INTRODUCTION MODULES 31.0.0 The Market Monitoring and Mitigation Measures of this Module D

More information

Summary of Prior CAISO Filings and Commission Orders Concerning CAISO Market Redesign Efforts

Summary of Prior CAISO Filings and Commission Orders Concerning CAISO Market Redesign Efforts Summary of Prior CAISO Filings and Commission Orders Concerning CAISO Market Redesign Efforts 1. Commission Directives to Submit a Market Redesign Plan The direct origin of the requirement that the CAISO

More information

COMMENTS OF TROUTMAN SANDERS LLP ON THE EUROPEAN REGULATORS GROUP FOR ELECTRICITY AND GAS DRAFT PROPOSAL ON GUIDELINES ON INTER-TSO COMPENSATION

COMMENTS OF TROUTMAN SANDERS LLP ON THE EUROPEAN REGULATORS GROUP FOR ELECTRICITY AND GAS DRAFT PROPOSAL ON GUIDELINES ON INTER-TSO COMPENSATION DRAFT COMMENTS OF TROUTMAN SANDERS LLP ON THE EUROPEAN REGULATORS GROUP FOR ELECTRICITY AND GAS DRAFT PROPOSAL ON GUIDELINES ON INTER-TSO COMPENSATION In response to the ERGEG Draft Proposal on Guidelines

More information

April 11, Tariff Amendments to Increase Efficiency of Congestion Revenue Rights Auctions

April 11, Tariff Amendments to Increase Efficiency of Congestion Revenue Rights Auctions California Independent System Operator Corporation The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 April 11, 2018 Re: California

More information

Stakeholder Survey I Cross Border Cost Allocation for Economic Transmission Projects For Discussion September 24, 2008

Stakeholder Survey I Cross Border Cost Allocation for Economic Transmission Projects For Discussion September 24, 2008 PJM and the Midwest ISO are seeking input from stakeholders on various concepts that have been discussed during the PJM/Midwest ISO Cross-Border meetings for dealing with transmission projects constructed

More information

Comments of Pacific Gas & Electric Company Energy Imbalance Market Draft Tariff Language

Comments of Pacific Gas & Electric Company Energy Imbalance Market Draft Tariff Language Comments of Pacific Gas & Electric Company Energy Imbalance Market Draft Tariff Language Submitted by Company Date Submitted Will Dong Paul Gribik (415) 973-9267 (415) 973-6274 PG&E December 5, 2013 Pacific

More information

Response to Additional Questions for the Record

Response to Additional Questions for the Record Response to Additional Questions for the Record Eric Hildebrandt, Ph.D. Director, Department of Market Monitoring California Independent System Operator Corporation Committee on Energy and Commerce Subcommittee

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Keith Casey, Vice President, Market & Infrastructure Development Date: March 14, 2018 Re: Decision on congestion

More information

9. RELATIONSHIP BETWEEN ISO AND PARTICIPATING TOs. Each Participating TO shall enter into a Transmission Control Agreement with the

9. RELATIONSHIP BETWEEN ISO AND PARTICIPATING TOs. Each Participating TO shall enter into a Transmission Control Agreement with the First Revised Sheet No. 121 ORIGINAL VOLUME NO. I Replacing Original Sheet No. 121 9. RELATIONSHIP BETWEEN ISO AND PARTICIPATING TOs. 9.1 Nature of Relationship. Each Participating TO shall enter into

More information

Resource Adequacy. WPUI April 19, 2018

Resource Adequacy. WPUI April 19, 2018 WPUI April 19, 2018 Resource Adequacy What is the interplay between states resource adequacy power per the Federal Power Act and the RTO s Reliability Coordinator role? Is a state Integrated Resource Plan

More information

EIM Market Monitoring and Market Power Mitigation

EIM Market Monitoring and Market Power Mitigation EIM Market Monitoring and Market Power Mitigation Eric Hildebrandt, Ph.D. Director, Market Monitoring EIM Technical Workshop September 16, 2013 Outline Market monitoring overview Key EIM market design

More information

Northern Tier Transmission Group Cost Allocation Principles Work Group. Straw Proposal. May 29, 2007

Northern Tier Transmission Group Cost Allocation Principles Work Group. Straw Proposal. May 29, 2007 Northern Tier Transmission Group Cost Allocation Principles Work Group Straw Proposal May 29, 2007 NTTG Cost Allocation Principles and Process page 1 INTRODUCTION This paper makes a strawman proposal responsive

More information

CAISO. Settlements & Billing. CRR Hourly Settlement CC 6700

CAISO. Settlements & Billing. CRR Hourly Settlement CC 6700 CAISO Settlements & Billing CRR Hourly Settlement CC 6700 Table of Contents 1. Purpose of Document 3 2. Introduction 3 2.1 Background 3 2.2 Description 4 3. Charge Code Requirements 4 3.1 Business Rules

More information

5.14 Installed Capacity Spot Market Auction and Installed Capacity Supplier Deficiencies LSE Participation in the ICAP Spot Market Auction

5.14 Installed Capacity Spot Market Auction and Installed Capacity Supplier Deficiencies LSE Participation in the ICAP Spot Market Auction 5.14 Installed Capacity Spot Market Auction and Installed Capacity Supplier Deficiencies 5.14.1 LSE Participation in the ICAP Spot Market Auction 5.14.1.1 ICAP Spot Market Auction When the ISO conducts

More information

Appendix B-2. Term Sheet for Tolling Agreements. for For

Appendix B-2. Term Sheet for Tolling Agreements. for For Appendix B-2 Term Sheet for Tolling Agreements for For 2015 Request For Proposals For Long-Term Developmental Combined-Cycle Gas Turbineand Existing Capacity and Energy Resources in WOTAB DRAFT Entergy

More information

March 13, Provisions, Docket No. ER (filed December 13, 2013) ( FCA 9 ORTP Filing ).

March 13, Provisions, Docket No. ER (filed December 13, 2013) ( FCA 9 ORTP Filing ). VIA etariff FILING The Honorable Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, D.C. 20426 March 13, 2014 Re: ISO New England Inc., Docket No. ER14-616-001;

More information

United States House of Representatives. Committee on Energy and Commerce. Subcommittee on Energy

United States House of Representatives. Committee on Energy and Commerce. Subcommittee on Energy United States House of Representatives Committee on Energy and Commerce Subcommittee on Energy Testimony of Vincent P. Duane, Senior Vice President, Law, Compliance & External Relations PJM Interconnection,

More information

Constellation Energy Comments on Proposed OTC Reforms

Constellation Energy Comments on Proposed OTC Reforms Constellation Energy Comments on Proposed OTC Reforms Constellation Energy Key Facts Constellation Energy is a Fortune 500 company (#125 on the 2009 list). Over 26,500 MW 2008 peak load served to retail

More information

ALBERTA MARKET RE-DESIGN CAPACITY MARKET DESIGN AND IMPLEMENTATION

ALBERTA MARKET RE-DESIGN CAPACITY MARKET DESIGN AND IMPLEMENTATION ALBERTA MARKET RE-DESIGN CAPACITY MARKET DESIGN AND IMPLEMENTATION November 30, 2016 www.poweradvisoryllc.com To: Power Advisory Clients and Colleagues From: Kris Aksomitis, Jason Chee-Aloy, Brenda Marshall,

More information

Wholesale Energy Markets Overview. Jeff Klarer Market Strategist

Wholesale Energy Markets Overview. Jeff Klarer Market Strategist Wholesale Energy Markets Overview Jeff Klarer Market Strategist Wisconsin Electric Utility Fuel Rules (PSC-116) Fuel Cost Components Fuel for generation (coal, natural gas, uranium, etc.) Energy market

More information

Major FERC Initiatives

Major FERC Initiatives Major FERC Initiatives 2006-2011 BUSINESS PRACTICE STANDARDS FOR ELECTRIC UTILITIES MAJOR PROPOSALS: RM05-5-000 FERC proposed to incorporate by reference the first set of standards for business practice

More information

Public Utility Regulatory Policies Act (PURPA)

Public Utility Regulatory Policies Act (PURPA) Public Utility Regulatory Policies Act (PURPA) National Association of Regulatory Utility Commissioners Staff Subcommittee on Accounting and Finance September 21, 2016 Overview of PURPA What is PURPA?

More information

Two Critical Barriers to Transmission Development: Siting & Cost Allocation

Two Critical Barriers to Transmission Development: Siting & Cost Allocation Two Critical Barriers to Transmission Development: Siting & Cost Allocation TAPS Conference Portland, Maine October 19, 2009 Ashley C. Brown Executive Director, Harvard Electricity Policy Group John F.

More information

Transmission Cost Allocation

Transmission Cost Allocation Transmission Cost Allocation IPSAC February 2, 2010 John P. Buechler NYISO Executive Regulatory Policy Advisor Background FERC Policy has evolved Order 888 No Planning Requirement for ISOs Order 2000 Planning

More information

Washington Utilities and Transportation Commission

Washington Utilities and Transportation Commission Mission Statement: The UTC protects consumers by ensuring that utility and transportation services are fairly priced, available, reliable, and safe. Washington Utilities and Transportation Commission Beginning

More information

MISO Planning Process. May 31, 2013

MISO Planning Process. May 31, 2013 MISO Planning Process May 31, 2013 MISO Planning Objectives Fundamental Goal The development of a comprehensive expansion plan that meets reliability needs, policy needs, and economic needs MISO Board

More information

ISO/RTO Market Monitoring Structure and Challenges Harvard Electricity Policy Group Sixty-Third Plenary Session

ISO/RTO Market Monitoring Structure and Challenges Harvard Electricity Policy Group Sixty-Third Plenary Session ISO/RTO Market Monitoring Structure and Challenges Harvard Electricity Policy Group Sixty-Third Plenary Session David LaPlante, Vice President, Market Monitoring ISO-New England June 2, 2011 1 Why is Oversight

More information

Financial Transmission and Auction Revenue Rights

Financial Transmission and Auction Revenue Rights Section 13 FTRs and ARRs Financial Transmission and Auction Revenue Rights In an LMP market, the lowest cost generation is dispatched to meet the load, subject to the ability of the transmission system

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 39. Market Power Mitigation Procedures... 2 39.1 Intent Of CAISO Mitigation Measures; Additional FERC Filings... 2 39.2 Conditions For The Imposition Of Mitigation Measures... 2 39.2.1

More information

Coos County Transmission Action Plan & Cost Allocation Methodologies

Coos County Transmission Action Plan & Cost Allocation Methodologies Coos County Transmission Action Plan & Cost Allocation Methodologies Presentation to the NCTC KEMA, Inc. June 17, 2010 Experience you can trust. Agenda Introduction to KEMA Project Objectives Status of

More information

NYISO Posting for FERC Order 890 Describing the NYISO Planning Process

NYISO Posting for FERC Order 890 Describing the NYISO Planning Process NYISO Posting for FERC Order 890 Describing the NYISO Planning Process September 14, 2007 ` NYISO Posting for FERC Order 890 Filing DRAFT Table of Contents Section: Page No: I. Cover Memo - Draft OATT

More information

FERC Order 741: Credit Reforms in Organized Wholesale Electric Markets. Sheri Prevratil Manager, Corporate Credit New York Independent System Operator

FERC Order 741: Credit Reforms in Organized Wholesale Electric Markets. Sheri Prevratil Manager, Corporate Credit New York Independent System Operator FERC Order 741: Credit Reforms in Organized Wholesale Electric Markets Sheri Prevratil Manager, Corporate Credit New York Independent System Operator Credit Policy Working Group June 20, 2011 Background

More information

ISO filed a tariff amendment to implement the rates, terms, and conditions of the ISO s Reliability Coordinator Service

ISO filed a tariff amendment to implement the rates, terms, and conditions of the ISO s Reliability Coordinator Service California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Roger Collanton, Vice President, General Counsel, Chief Compliance Officer, and Corporate Secretary Date:

More information

Southwest Power Pool, Inc. Policy Recommendation for the SPP Board of Directors and Members Committee. March 6, 2018 Mountain West Transmission Group

Southwest Power Pool, Inc. Policy Recommendation for the SPP Board of Directors and Members Committee. March 6, 2018 Mountain West Transmission Group Southwest Power Pool, Inc. Policy for the SPP Board of Directors and Members Committee Policy Area #1 DC Ties March 6, 2018 Mountain West Transmission Group SPP and MWTG anticipate that incorporating the

More information

Comments in FERC Docket No. RM The FGR vs. FTR debate: Facts and Misconceptions

Comments in FERC Docket No. RM The FGR vs. FTR debate: Facts and Misconceptions Comments in FERC Docket No. RM01-12-000 The FGR vs. FTR debate: Facts and Misconceptions Shmuel S. Oren University of California at Berkeley 4119 Etcheverry Hall, Berkeley, CA 94720 oren@ieor.berkeley.edu

More information

PJM Interconnection, L.L.C. ( PJM ), under Section 205 of the Federal Power Act

PJM Interconnection, L.L.C. ( PJM ), under Section 205 of the Federal Power Act PJM Interconnection, L.L.C. 2750 Monroe Boulevard Audubon, PA 19403 March 30, 2018 Elizabeth P. Trinkle Counsel T: (610) 666-4707 F: (610) 666-8211 Elizabeth.Trinkle@pjm.com The Honorable Kimberly D. Bose

More information

New Member Cost Allocation Review Process. Prepared by: COST ALLOCATION WORKING GROUP

New Member Cost Allocation Review Process. Prepared by: COST ALLOCATION WORKING GROUP New Member Cost Allocation Review Process Prepared by: COST ALLOCATION WORKING GROUP TABLE OF CONTENTS 1. HISTORY AND BACKGROUND... 1 2. PURPOSE / GOAL STATEMENT... 3 3. OVERVIEW OF PROCESS... 3 4. NEW

More information

FTR Alignment. Joint Stakeholder Meeting June 6, 2008

FTR Alignment. Joint Stakeholder Meeting June 6, 2008 FTR Alignment Joint Stakeholder Meeting June 6, 2008 Introduction Joint Common Market Initiative As part of the of the Midwest ISO and PJM Joint and Common Market (JCM) process, the Midwest ISO stakeholders

More information

ARR/FTR Market Update: ATC Customer Meeting. August 20, 2009

ARR/FTR Market Update: ATC Customer Meeting. August 20, 2009 ARR/FTR Market Update: ATC Customer Meeting August 20, 2009 Agenda ARR Allocation FTR Annual/Monthly Auction Challenge 2 Allocation Overview 101 Market Participants took part in the 2009-2010 Annual ARR

More information

Power Trading in the Coupled European Markets

Power Trading in the Coupled European Markets Power Trading in the Coupled European Markets Challenges for policy-makers February 2016-1 - Europe Economics is registered in England No. 3477100. Registered offices at Chancery House, 53-64 Chancery

More information

Financial Transmission and Auction Revenue Rights

Financial Transmission and Auction Revenue Rights Section 13 FTRs and ARRs Financial Transmission and Auction Revenue Rights In an LMP market, the lowest cost generation is dispatched to meet the load, subject to the ability of the transmission system

More information

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. ) ) ) ISO New England Inc. ) Docket No. ER ) ) ) )

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. ) ) ) ISO New England Inc. ) Docket No. ER ) ) ) ) UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ISO New England Inc. Docket No. ER19-444-000 MOTION TO INTERVENE AND LIMITED PROTEST OF THE NEW ENGLAND POWER GENERATORS ASSOCIATION, INC.

More information

FERC Update RMEL ~ Keystone 2018

FERC Update RMEL ~ Keystone 2018 FERC Update RMEL ~ Keystone 2018 Bill Derasmo Troutman Sanders william.derasmo@troutman.com May 21, 2018 Introduction Bill Derasmo Partner, Troutman Sanders 20 + years experience with energy regulatory

More information

Stakeholder Comments Template

Stakeholder Comments Template Stakeholder Comments Template Submitted by Company Date Submitted Jaime Rose Gannon jrg@cpuc.ca.gov 415-846-4365 California Public Utilities Commission 3/11/2019 Please use this template to provide your

More information

Participant Funding: The SeTrans Proposal. Bruce Edelston Director, Policy and Planning Southern Company

Participant Funding: The SeTrans Proposal. Bruce Edelston Director, Policy and Planning Southern Company Participant Funding: The SeTrans Proposal Bruce Edelston Director, Policy and Planning Southern Company Presentation to HEPG December 11, 2003 Point Clear, AL 1 SeTrans Participants CLECO Dalton Utilities

More information

Congestion Revenue Rights Auction Efficiency Track 1B Draft Final Proposal

Congestion Revenue Rights Auction Efficiency Track 1B Draft Final Proposal Congestion Revenue Rights Auction Efficiency May 11, 2018 Prepared by: M&IP California Independent System Operator Table of Contents 1 Executive Summary... 3 2 Changes to this proposal... 5 3 Scope of

More information

PJM/MISO Cost Allocation For Economic Upgrades

PJM/MISO Cost Allocation For Economic Upgrades PJM/MISO Cost Allocation For Economic Upgrades Stakeholder Meeting Hilton Baltimore BWI, Baltimore MD May 19, 2008 1 Topics for Discussion Background FERC Order / Schedule (RTO Staffs) Review Internal

More information

Two-Tier Allocation of Bid Cost Recovery

Two-Tier Allocation of Bid Cost Recovery Two-Tier Allocation of Bid Cost Recovery Jordan Curry Market Design & Regulatory Policy Developer December 21, 2015 Agenda Time Topic Presenter 1:00 1:05 Introduction Kim Perez 1:05 2:00 Purpose and Background

More information

SPP New Member Communication and Integration Process. Mountain West Transmission Group. Background Information October 2017

SPP New Member Communication and Integration Process. Mountain West Transmission Group. Background Information October 2017 1 SPP New Member Communication and Integration Process Mountain West Transmission Group Background Information October 2017 Contents Introduction... 2 1. Westside Tariff Design... 2 2. Operational Provisions...

More information

Market Surveillance Committee Activities September By Frank Wolak Chairman of the ISO Market Surveillance Committee

Market Surveillance Committee Activities September By Frank Wolak Chairman of the ISO Market Surveillance Committee Market Surveillance Committee Activities September 2004 By Frank Wolak Chairman of the ISO Market Surveillance Committee Four Opinions in Progress Trading Hubs Solution to the Seller s Choice Contracts

More information

Market Settlements - Advanced

Market Settlements - Advanced Market Settlements - Advanced FTR/ARR Module PJM State & Member Training Dept. PJM 2017 Agenda FTR/ARR Hedging Congestion FTR and ARR Billing Examples PJM 2017 2 Hedging Transmission Congestion PJM 2017

More information

Congestion Revenue Rights (CRR) Clawback Modification. Draft Final Proposal

Congestion Revenue Rights (CRR) Clawback Modification. Draft Final Proposal Congestion Revenue Rights (CRR) Clawback Modification Draft Final Proposal May 16, 2016 CRR Clawback Modification Draft Final Proposal Table of Contents 1 Introduction... 3 2 Stakeholder process and timeline...

More information

History of Cost Allocation within MISO RECB TF. January 29, 2015

History of Cost Allocation within MISO RECB TF. January 29, 2015 History of Cost Allocation within MISO RECB TF January 29, 2015 Cost Allocation FERC Orders, Filings, and Rulings Cost allocation for MISO began with Order 2003 which instituted a pro forma Generator Interconnection

More information

Workshop on Regional Electricity Trade and Market Development

Workshop on Regional Electricity Trade and Market Development Workshop on Regional Electricity Trade and Market Development Cross-border Electricity Trade and Tariffs April 23, 2014 Cross-border Electricity Trade (CBT) Flows within which part of the transmission

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 39. Market Power Mitigation Procedures... 2 39.1 Intent Of CAISO Mitigation Measures; Additional FERC Filings... 2 39.2 Conditions For The Imposition Of Mitigation Measures... 2 39.2.1

More information

ARRs and FTRs MISO Training

ARRs and FTRs MISO Training MISO Training Level 200 Auction Revenue Rights and Financial Transmission Rights Last material update: 07/09/2015 Course Content and Disclaimer 2 Course Description 1 2 3 4 This is a Level 200 overview

More information

Opinion on Congestion Revenue Rights Auction Efficiency, Track 1B. by James Bushnell, Member Scott M. Harvey, Member Benjamin F.

Opinion on Congestion Revenue Rights Auction Efficiency, Track 1B. by James Bushnell, Member Scott M. Harvey, Member Benjamin F. Opinion on Congestion Revenue Rights Auction Efficiency, Track 1B by James Bushnell, Member Scott M. Harvey, Member Benjamin F. Hobbs, Chair Members of the Market Surveillance Committee of the California

More information

Transmission Planning Standards Industry Webinar: Footnote b. January 8, 2012 John Odom, FRCC, Standard Drafting Team Chair

Transmission Planning Standards Industry Webinar: Footnote b. January 8, 2012 John Odom, FRCC, Standard Drafting Team Chair Transmission Planning Standards Industry Webinar: Footnote b January 8, 2012 John Odom, FRCC, Standard Drafting Team Chair Topics Brief history Overview of as posted draft standard Changes since last posting

More information

Ensuring Resource Adequacy in California: An Alternative to Centralized Capacity Markets

Ensuring Resource Adequacy in California: An Alternative to Centralized Capacity Markets Ensuring Resource Adequacy in California: An Alternative to Centralized Capacity Markets Presentation to the CAISO Independent Market Surveillance Committee by the Bilateral Trading Group August 8, 2006

More information

MARCH A report for the. Australian Energy Market Commission

MARCH A report for the. Australian Energy Market Commission MODELS OF INTER-REGIONAL TRANSMISSION CHARGING MARCH 2008 A report for the Australian Energy Market Commission The Brattle Group rue Ducale 83 Bruxelles 1000 Belgium tel: +32.2790.3580 fax: +32.2790.3581

More information

Easier Said Than Done: The Continuing Saga of Transmission Cost Allocation

Easier Said Than Done: The Continuing Saga of Transmission Cost Allocation Easier Said Than Done: The Continuing Saga of Transmission Cost Allocation Presented by: Johannes Pfeifenberger Presented to: Harvard Electricity Policy Group February 24, 2011 www.brattle.com Antitrust/Competition

More information

Regional Transmission Organization Frequently Asked Questions

Regional Transmission Organization Frequently Asked Questions 1. The CRA analysis showed greater trade benefits to the Entergy region from joining SPP rather than joining MISO. Did Entergy re-do the CRA analysis? No. The CRA analysis was a key component of the Entergy

More information

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California Cancelling Revised Cal. PUC Sheet No E*

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California Cancelling Revised Cal. PUC Sheet No E* Southern California Edison Revised Cal. PUC Sheet No. 28371-E Rosemead, California Cancelling Revised Cal. PUC Sheet No. 26736-E* Schedule PE Sheet 1 APPLICABILITY Applicable to all SCE Bundled Service

More information

Transactional Scoping and Approvals

Transactional Scoping and Approvals Noel co-leads the utility practice of the energy industry team. He represents electric utilities and other energy companies before the Federal Energy Regulatory Commission (FERC) and appellate courts,

More information

Two-Tier Real-Time Bid Cost Recovery. Margaret Miller Senior Market and Product Economist Convergence Bidding Stakeholder Meeting October 16, 2008

Two-Tier Real-Time Bid Cost Recovery. Margaret Miller Senior Market and Product Economist Convergence Bidding Stakeholder Meeting October 16, 2008 Two-Tier Real-Time Bid Cost Recovery Margaret Miller Senior Market and Product Economist Convergence Bidding Stakeholder Meeting October 16, 2008 The CAISO has posted an Issue Paper exploring the redesign

More information

Congestion Revenue Rights Settlement Rule

Congestion Revenue Rights Settlement Rule California Independent System Operator Corporation Congestion Revenue Rights Settlement Rule Department of Market Monitoring August 18, 2009 I. Background Under nodal convergence bidding, the California

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Transmission Planning and Cost Allocation ) by Transmission Owning and Operating ) Docket No. RM10-23- 000 Public Utilities ) Comments

More information

February 23, 2015 VIA ELECTRONIC FILING

February 23, 2015 VIA ELECTRONIC FILING February 23, 2015 VIA ELECTRONIC FILING The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: Southwest Power Pool, Inc., Docket

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) California Independent System ) Docket No. ER99-3339-000 Operator Corporation ) ) REQUEST FOR REHEARING OF THE CALIFORNIA INDEPENDENT

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 39. Market Power Mitigation Procedures... 2 39.1 Intent of CAISO Mitigation Measures; Additional FERC Filings... 2 39.2 Conditions for the Imposition of Mitigation Measures... 2 39.2.1

More information

RATES FOR EXPORT TRANSMISSION SERVICE

RATES FOR EXPORT TRANSMISSION SERVICE Page of RATES FOR EXPORT TRANSMISSION.0 INTRODUCTION The OEB has directed Hydro One Transmission to monitor and report to the Board, at the next rate case, on the functioning of the Export Transmission

More information

5.2 Transmission Congestion Credit Calculation Eligibility.

5.2 Transmission Congestion Credit Calculation Eligibility. 5.2 Transmission Congestion Credit Calculation. 5.2.1 Eligibility. (a) Except as provided in Section 5.2.1(b), each FTR Holder shall receive as a Transmission Congestion Credit a proportional share of

More information

Illinois Power Agency Act and Related Legislation

Illinois Power Agency Act and Related Legislation Craig D. Nelson Vice President Regulatory Affairs & Financial Services November 1, 2007 Topics Implications of Illinois Power Agency Act and related changes to Public Utility Act Expected influence on

More information

FERC Order 1000: Transmission Planning & Cost Allocation NYISO Compliance Update

FERC Order 1000: Transmission Planning & Cost Allocation NYISO Compliance Update FERC Order 1000: Transmission Planning & Cost Allocation NYISO Compliance Update by John P. Buechler NYISO Executive Regulatory Policy Advisor NPCC Governmental/Regulatory Affairs Advisory Group November

More information

BEFORE THE CALIFORNIA STATE SENATE THE SELECT COMMITTEE TO INVESTIGATE PRICE MANIPULATION OF THE WHOLESALE ENERGY MARKET

BEFORE THE CALIFORNIA STATE SENATE THE SELECT COMMITTEE TO INVESTIGATE PRICE MANIPULATION OF THE WHOLESALE ENERGY MARKET BEFORE THE CALIFORNIA STATE SENATE THE SELECT COMMITTEE TO INVESTIGATE PRICE MANIPULATION OF THE WHOLESALE ENERGY MARKET PACIFIC GAS AND ELECTRIC COMPANY'S RESPONSE TO MAY 30, 2002 QUESTIONS I. Introduction

More information

Business Practice Manual For The Energy Imbalance Market. Version 78

Business Practice Manual For The Energy Imbalance Market. Version 78 Business Practice Manual For The Energy Imbalance Market Version 78 Revision Date: March 31May 31, 2017 Approval History Approval Date: October 2, 2014 Effective Date: October 2, 2014 BPM Owners: Mike

More information

Standard Market Design: What Went Wrong? What Next?

Standard Market Design: What Went Wrong? What Next? Mary Anne Sullivan is a partner in the Washington, DC, office of Hogan & Hartson LLP and a member of the firm s Energy Group. Her practice focuses on administrative, regulatory, transactional, and litigation

More information

CAISO. Settlements & Billing CRR Auction Transaction Settlement CC 6798

CAISO. Settlements & Billing CRR Auction Transaction Settlement CC 6798 CAISO Settlements & Billing CRR Auction Transaction Settlement CC 6798 Table of Contents 1. Purpose of Document 3 2. Introduction 3 2.1 Background 3 2.2 Description 4 3. Charge Code Requirements 4 3.1

More information

Business Practice Manual For The Energy Imbalance Market. Version 89

Business Practice Manual For The Energy Imbalance Market. Version 89 Business Practice Manual For The Energy Imbalance Market Version 89 Revision Date: Jan 02, 2018May 31, 2017 Approval History Approval Date: October 2, 2014 Effective Date: October 2, 2014 BPM Owners: Mike

More information

ISO Enforcement Protocol

ISO Enforcement Protocol FERC ELECTRIC TARIFF First Revised Sheet No. 858 FIRST REPLACEMENT VOLUME NO. II Superseding Original Sheet No. 858 ISO Enforcement Protocol Issued on: May 20, 2004 FERC ELECTRIC TARIFF Substitute First

More information

DUKE ENERGY OHIO REQUEST FOR PROPOSALS FOR PEAKING/INTERMEDIATE POWER SUPPLY IN RESPONSE TO OHIO SENATE BILL 221

DUKE ENERGY OHIO REQUEST FOR PROPOSALS FOR PEAKING/INTERMEDIATE POWER SUPPLY IN RESPONSE TO OHIO SENATE BILL 221 DUKE ENERGY OHIO REQUEST FOR PROPOSALS FOR PEAKING/INTERMEDIATE POWER SUPPLY IN RESPONSE TO OHIO SENATE BILL 221 DUKE ENERGY OHIO Table of Contents Section Description Page 1.0 Purpose of Request for Proposals

More information

California ISO. Allocating CRR Revenue Inadequacy by Constraint to CRR Holders. October 6, Prepared by: Department of Market Monitoring

California ISO. Allocating CRR Revenue Inadequacy by Constraint to CRR Holders. October 6, Prepared by: Department of Market Monitoring California Independent System Operator Corporation California ISO Allocating CRR Revenue Inadequacy by Constraint to CRR Holders October 6, 2014 Prepared by: Department of Market Monitoring TABLE OF CONTENTS

More information

Capacity Procurement Mechanism Replacement. Second Revised Draft Straw Proposal

Capacity Procurement Mechanism Replacement. Second Revised Draft Straw Proposal Capacity Procurement Mechanism Replacement Second Revised Draft September 25, 2014 Table of Contents 1. Document change tracking... 4 2. Executive summary... 5 3. CPUC Joint Reliability Plan Proceeding...

More information

WHITE PAPER. Financial Transmission Rights (FTR)/ Congestion Revenue Rights (CRR) Analysis Get ahead with ABB Ability PROMOD

WHITE PAPER. Financial Transmission Rights (FTR)/ Congestion Revenue Rights (CRR) Analysis Get ahead with ABB Ability PROMOD WHITE PAPER Financial Transmission Rights (FTR)/ Congestion Revenue Rights (CRR) Analysis Get ahead with ABB Ability PROMOD 2 W H I T E PA P E R F T R / C R R A N A LY S I S Market participants and system

More information

Exploring a New Paradigm for Electricity in Wyoming Regional Markets and Retail Choice. Thor Nelson May 7, 2018

Exploring a New Paradigm for Electricity in Wyoming Regional Markets and Retail Choice. Thor Nelson May 7, 2018 Exploring a New Paradigm for Electricity in Wyoming Regional Markets and Retail Choice Thor Nelson May 7, 2018 Wyoming Industrial Energy Consumers Who is that? The Wyoming Industrial Energy Consumers (

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 28. Inter-SC Trades... 2 28.1 Inter-SC Trades Of Energy... 2 28.1.1 Purpose... 2 28.1.2 Availability Of Inter-SC Trades Of Energy... 2 28.1.3 Submission Of Inter-SC Trades Of Energy...

More information

Historic Fixed Price TCC Extensions

Historic Fixed Price TCC Extensions Historic Fixed Price TCC Extensions Gregory R. Williams MANAGER, TCC MARKET OPERATIONS Business Issues Committee Meeting June 20, 2018, Rensselaer, NY Agenda Historic Fixed Price TCC (HFPTCC) Overview

More information

Can Energy Markets Finance Infrastructure?

Can Energy Markets Finance Infrastructure? Can Energy Markets Finance Infrastructure? September 18th, 2007 QUANTITATIVE TRADING Washington, D.C. (703) 506-3901 DC ENERGY PROPRIETARY RESTRICTED 0 One view of an economically rationale investment

More information

Amendment to extend exceptional dispatch mitigated energy settlement rules and modify residual imbalance energy settlement rules

Amendment to extend exceptional dispatch mitigated energy settlement rules and modify residual imbalance energy settlement rules California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Nancy Saracino, Vice President, General Counsel & Chief Administrative Officer Date: September 7, 2012 Re:

More information

Stakeholder Process: Congestion Revenue Rights Auction Efficiency. Summary of Submitted Comments

Stakeholder Process: Congestion Revenue Rights Auction Efficiency. Summary of Submitted Comments Stakeholder Process: Congestion Revenue Rights Auction Efficiency Attachment A Summary of Submitted Comments Stakeholders submitted four rounds of written comments to the ISO under the congestion revenue

More information

Planning in a competitive market environment

Planning in a competitive market environment Planning in a competitive market environment The New York Story Rana Mukerji Senior Vice President - Market Structures New York Independent System Operator Harvard Electricity Policy Group 74 th Plenary

More information

DECISION GRANTING APPEAL IN PART AND DENYING APPEAL IN PART

DECISION GRANTING APPEAL IN PART AND DENYING APPEAL IN PART Robert C. Arnold Robert I. Hanfling Jack G. Lotis, Vice Chair Joseph H. Petrowski, Chair Jay S. Siegel N E P O O L B O A R D OF R E V I E W In the Matter of the Appeal in: September 19, 2001 Case No. 05-NE-BD-2001

More information

Reliability Must Run (RMR) and Capacity Procurement Mechanism (CPM) Enhancements

Reliability Must Run (RMR) and Capacity Procurement Mechanism (CPM) Enhancements Reliability Must Run (RMR) and Capacity Procurement Mechanism (CPM) Enhancements Submitted by Company Date Submitted Matt Lecar 415-973-7743 melj@pge.com Pacific Gas and Electric Company January 9, 2019

More information

Gray proposed revisions for CEE, Renewable Generator Exemption, Municipal Utilities Exemption

Gray proposed revisions for CEE, Renewable Generator Exemption, Municipal Utilities Exemption Yellow pending revisions filed 8/6/12 in ER12-2414-000 [Compliance revisions filed in response to Commission Order 139 FERC 61,244 (2012) in Docket EL11-42] Green pending revisions filed 10/11/12 in ER13-102-000

More information