NTTG Quarter 4 Stakeholder Meeting. Salt Lake City, Utah December 13, 2016

Size: px
Start display at page:

Download "NTTG Quarter 4 Stakeholder Meeting. Salt Lake City, Utah December 13, 2016"

Transcription

1 NTTG Quarter 4 Stakeholder Meeting Salt Lake City, Utah December 13, 2016

2 NTTG Planning Cycle

3 NTTG Draft Regional Transmission Plan Development 3

4 NTTG Q4 Stakeholder Meeting Agenda 10:30 10:45 WELCOME and AGENDA REVIEW 10:45 12:00 REGIONAL TRANSMISSION PLAN DEVELOPMENT Draft Regional Transmission Plan Process Overview NTTG System Representation and Plan Assumptions Base Case Development and Change Case Selection NTTG Reliability and Stability Analysis 12:00 1:00 LUNCH BREAK 1:00 1:35 1:35 1:50 METRICS EVALUATION AND RESULTS Energy Loss Metric Change in Reserves Metric Capital Cost Metric NTTG DRAFT REGIONAL TRANSMISSION PLAN Project Selection, Impacts on Neighboring Regions, and Cost Allocation Implications 4

5 NTTG Q4 Stakeholder Meeting 1:50 2:00 Agenda (Cont d.) TRANSMISSION USE COMMITTEE Updated POR/POD map 2:00 2:15 WECC ADS UPDATE 2:15 2:35 2:35 3:00 NEIGHBORING PLANNING REGION UPDATES CAISO Gary DeShazo ColumbiaGrid Paul Didsayabutra WestConnect Heidi Pacini NEXT STEPS AND OTHER BUSINESS Upcoming Opportunities for Stakeholder Input 3:00 ADJOURN 5

6 NTTG Draft Regional Transmission Plan Process Overview NTTG Quarter 4 Stakeholder Meeting Salt Lake City, UT December 13, 2016

7 Initial Regional Transmission Plan Evaluation NTTG goal is to select the most efficient or cost effective projects to meet the needs of the region Regional projects will be identified through reliability analysis (power flow) and benefit determination (changes in capital costs, losses, and reserves) Analysis performed on Initial Regional Transmission Plan (IRTP) IRTP without uncommitted projects Evaluation of Alternative Projects 7

8 Initial Regional Transmission Plan Evaluation Base cases for the evaluation have been developed using a production cost model to determine the hours when load and resource conditions are likely to stress the NTTG transmission system Power flow analysis of the Initial Regional Transmission Plan for the chosen hours has been performed to check compliance with the system performance requirements and transmission needs associated with Public Policy Requirements 8

9 NTTG System Representation and Plan Assumptions NTTG Quarter 4 Stakeholder Meeting Salt Lake City, UT December 13, 2016

10 Load Submissions SUBMITTED BY: 2015 Actual Peak Demand (MW) 2024 Summer Load Data Submitted in Q (MW) 2026 Summer Load Data Submitted in Q (MW) Difference (MW) Deseret G&T Included in PacifiCorp East Idaho Power 3,730 4,193 4, NorthWestern 1,790 1,774 1, PacifiCorp 12,634 14,002 13, Portland General 3,958 3,933 3, UAMPS Included in PacifiCorp East TOTAL 22,112 23,902 23,

11 Natural Gas Wind Solar Biomass Oil Geo-thermal Hydro-Electric Coal Nuclear Market* / Other TOTAL Resource Submissions

12 Transmission Additions by 2026 Sponsor From To Voltage Circuit Type Regionally Significant 1 Committed Projects Deseret G&T Idaho Power Bonanza Upalco 138 kv 2 LTP No No New Line Hemingway Boardman/ Longhorn 500 kv 1 LTP & prtp Yes No B2H Project Hemingway Bowmont 230 kv 2 LTP Yes No New Line (associated with Boardman to Hemingway) Bowmont Hubbard 230 kv 1 LTP Yes No New Line (associated with Boardman to Hemingway) Cedar Hill Hemingway 500 kv 1 LTP Yes No Gateway West Segment #9 (joint with PacifiCorp East) Cedar Hill Midpoint 500 kv 1 LTP Yes No Gateway West Segment #10 Midpoint Borah 500 kv 1 LTP Yes No (convert existing from 345 kv operation) King Wood River 138 kv 1 LTP No No Line Reconductor Willis Star 138 kv 1 LTP No No New Line Enbridge SE Alberta DC 1 LTP Yes No MATL 600 MW Back to Back DC Converter Aeolus Clover 500 kv 1 LTP & prtp Yes No Gateway South Project Segment #2 Aeolus Anticline 500 kv 1 LTP & prtp Yes No Gateway West Segments 2&3 Anticline Jim Bridger 500 kv 1 LTP & prtp Yes No 345/500 kv Tie PacifiCorp East PacifiCorp West Portland General Anticline Populus 500 kv 1 LTP & prtp Yes No Gateway West Segment #4 Populus Borah 500 kv 1 LTP Yes No Gateway West Segment #5 Populus Cedar Hill 500 kv 1 LTP Yes No Gateway West Segment #7 Antelope Goshen 345 kv 1 LTP Yes No Nuclear Resource Integration Antelope Borah 345 kv 1 LTP Yes No Nuclear Resource Integration Windstar Aeolus 230 kv 1 LTP & prtp Yes No Gateway West Segment #1W Oquirrh Terminal 345 kv 2 LTP Yes Yes Gateway Central Cedar Hill Hemingway 500 kv 1 LTP Yes No Gateway West Segment #9 (joint with Idaho Power) Wallula McNary 230 kv 1 LTP Yes Yes Gateway West Segment A Blue Lake Gresham 230 kv 1 LTP No No New Line Blue Lake Troutdale 230 kv 1 LTP No No Rebuild Blue Lake Troutdale 230 kv 2 LTP No No New Line Horizon Springville Jct 230 kv 1 LTP No No New Line (Trojan-St Marys-Horizon) Horizon Harborton 230 kv 1 LTP No No New Line (re-terminates Horizon Line) Trojan Harborton 230 kv 1 LTP No No Re-termination to Harborton St Marys Harborton 230 kv 1 LTP No No Re-termination to Harborton Rivergate Harborton 230 kv 1 LTP No No Re-termination to Harborton Trojan Harborton 230 kv 2 LTP No No Re-termination to Harborton 12

13 Gateway Project Submission Gateway Project has been split into 3 subprojects to better match regional plans 1. Segment D and F 2. Segment E.1 (Populus west to Midpoint/Cedar Hill) 3. Segment E.2 (Midpoint/Cedar Hill west to Hemingway) D & F 13

14 Transmission Service Obligations Submitted by MW (1) Start Date POR POD Idaho Power 500/ Northwest IPCo 250/ LaGrande BPASEID Antelope Network PacifiCorp East Miners, Point of Rocks Network (1) Summer/Winter 14

15 Public Policy Requirements Resources submitted to NTTG [or TEPPC] support the following state statutory targets for percentage of renewable energy generation: California 33% by 2020 Montana 15% by 2015 Oregon 25% by 2025 Utah 20% by 2025 Washington 15% by

16 Interregional Project Submissions NTTG received three Interregional Transmission Project (ITP) submittals Cross-Tie Great Basin (SWIP-North) TransWest Express Relevant Planning Regions coordinated and agreed on common ITP interfaces for each region s evaluation of the ITPs 16

17 Cross-Tie Transmission Project Submitted by TransCanyon Clover, UT to Robinson Summit, NV Sponsored Project 500 kv, AC Common ITP Assumptions: Phase Shifters in Gonder Area Series Compensated to Las Vegas Area 500 kv line extended from Harry Allen to Eldorado 1500MW of new wind resource in Wyoming (may test at 2000 MW to align with CAISO studies) 17

18 Cross-Tie 18

19 SWIP-North Transmission Project Submitted by Great Basin Transmission Midpoint, ID to Robinson Summit, NV Sponsored Project 500 kv, AC Common ITP assumptions include: Series Compensated to Las Vegas Area 500 kv line extended from Harry Allen to Eldorado Phase Shifters in Gonder Area 2000 MW of new wind resource in Wyoming 19

20 SWIP-North 20

21 TransWest Express Transmission Project Submitted by TransWest Express Sinclair, WY to Boulder City, NV Sponsored Project 600 kv, DC Common ITP Assumptions: kv interconnections to Wyoming system DC line rated for 1500/2000 MW 2000 MW of new wind resource in Wyoming with balancing CT 21

22 TransWest Express 22

23 Questions? 23

24 Base Case Development and Change Case Selection NTTG Quarter 4 Stakeholder Meeting Salt Lake City, UT December 13, 2016

25 Base Case Development Common Case posted on WECC website on 7/5/2016, Production Cost Modeling ONLY Technical review to improve load, interface definitions Power Flow case not available until mid-august Still needed tuning as it contained duplicate projects Generator mapping needed further massaging 25

26 A Base Case (At last!) August 25, had a power flow case that is workable Continued review of contingency definitions, fix of minor generator mapping errors and topology, load assumptions 26

27 Power Flow Cases Selected Selection of Base Cases A. Peak coincident Summer Load condition B. Peak coincident Winter Load condition C. High westbound Path 8 flows D. Boardman to Hemmingway (Longhorn) 1. High Import flows to Idaho 2. High export flows from Idaho E. Conditions with high flows across the Tot2 path F. High Wyoming Wind condition Conditions where persistent congestion observed 27

28 Change Case Selection Study plan presented a model Change Case matrix which was open to further development by TWG as the study cases were further developed A Modified Matrix was presented at the October Planning Committee meeting seeking comments No comments were received Further changes were identified by TWG 28

29 TWG Case Terminology Base Case Topology represented in PCM model (all CCTA facilities included) prtp Prior Regional Transmission Plan, includes: B2H, Eastern Portion of Gateway West and Gateway South Non-NTTG CCTA facilities irtp Initial Regional Transmission Plan, includes: B2H, McNary-Wallula, Gateway West, Gateway South, Antelope Projects, local Load serving projects Non-NTTG CCTA Facilities 29

30 Revised Change Case Matrix Gateway S* Gateway W* Antelope Projects Cross- Tie B2H* SWIP N TWE Case Case(s): null A B D1 D2 F prtp X X D A B D1 D2 F irtp X X X X A B D1 D2 F CC1 X A B D1 D2 F CC2 X X A D2 E F CC3 X X A D2 E F CC4 X X X A D1 D2 E F CC5 X A B D1 D2 F CC6 X A B D1 D2 F CC7 X A B D1 D2 F CC8 X E+RPS CC9 X X E+RPS CC20 X X X E+RPS CC10 X E+RPS CC11 X X E+RPS CC18 X X X E+RPS CC12 X E+RPS CC13 X X E+RPS CC19 X X X E+RPS CC14 X X X X E+RPS CC15 X X X E+RPS CC16 X X X E+RPS CC17 X X X X X E+RPS CC21 X X A D2 F CC22 X X B D2 F CC23 X X C F * B2H and Alternate P in the prtp are similar to B2H, Gateway S and Gateway W in the Q1 data submittals A B C D irtp without Midpoint-Hemingway #2 and Cedar Hill-Midpoint irtp without Borah-Midpoint Uprate and Populus-Borah irtp without Midpoint-Hemingway #2, Cedar Hill-Midpoint and Populus-Borah irtp without Midpoint-Hemingway #2, Cedar Hill-Midpoint, Populus-Cedar Hill- Hemingway, Populus-Borah and Midpoint-Borah Uprate The change case was run with and without B2H 30

31 NTTG Technical Analysis Once base cases were developed and change cases selected, the following analysis was performed: Reliability (power flow) Stability (dynamics) Economic Metrics (benefits) Energy Losses Change in Reserves Annual Capital Costs Impacts to Neighboring Planning Regions reviewed Further discussion of these analyses is summarized next 31

32 Questions? 32

33 NTTG Reliability/Stability Analysis NTTG Quarter 4 Stakeholder Meeting Salt Lake City, UT December 13, 2016

34 Reliability Analysis Power flow software is used to evaluate transmission reliability under N-0 and N-1 conditions, and Certain credible N-2 contingencies Dynamic analysis is based on selected Power flow cases and the availability of the dynamic models for the projects 34

35 Reliability Analysis Method Tune case to meet flow objectives Adjust reactive to meet voltage targets Testing each case with 418 contingencies Export elements (buses, Lines, transformers, Series Caps) whose limits may potentially be exceeded. Some limits may be exceeded for N-2 contingencies but for not N-1 Powerflow program doesn t distinguish between N-1s or N-2s - (manually reviewed) 100+ cases across the 6 powerflow conditions records where limits may be potentially be exceeded The sheer number of values and cases made comprehending the results difficult. Review methods: Pivot table of cases Graphical 35

36 Graphical Reliability Analysis Compress the data differently: Count the number of limit exceedances in each zone by: High Voltages (1x) Low Voltages (3x) Overloads (5x) Weight Overloads considered more severe than Low Voltages and Low Voltage considered more severe than High Voltages Map Zone labels to Latitude and Longitude Use a web browser application to create Heat Maps using the above data Using Java script and Google Maps 36

37 Graphical Reliability Analysis 37

38 Graphical Reliability Analysis How does the prior RTP perform? 38

39 Graphical Reliability Analysis How does the prior RTP perform? 39

40 Graphical Reliability Analysis How does the prior RTP perform with the High Wind case? 40

41 Graphical Reliability Analysis How does the irtp perform? 41

42 Graphical Reliability Analysis Heavy Summer Case Do the ITPs provide NTTG benefit? Added ITP without new resources TransWest Express Cross-Tie Great Basin 42

43 Graphical Reliability Analysis Heavy Idaho Import Do the ITPs provide NTTG benefit? Added ITP without new resources TransWest Express Cross-Tie Great Basin 43

44 Graphical Reliability Analysis Heavy Idaho Export Do the ITPs provide NTTG benefit? Added ITP without new resources TransWest Express Cross-Tie Great Basin 44

45 Graphical Reliability Analysis High Wyoming Wind Do the ITPs provide NTTG benefit? Added ITP without new resources TransWest Express Cross-Tie Great Basin 45

46 Powerflow Results Three change cases appear to meet NTTG requirements. These cases were evaluated to determine which case would be more efficient or cost effective*. irtp facilities submitted in Q1 Change Case CC21 Excludes Midpoint-Hemingway #2, Cedar Hill-Midpoint Change Case CC23 CC21 but also excludes Populus-Borah * for the requirements submitted in Q1 46

47 Stability Analysis TWG has developed a Dynamic dataset which will be used to test a selected number of powerflow contingencies. Developing the dynamic contingency switching files is under way and is expected to be complete in early Q5 47

48 Questions? 48

49 LUNCH BREAK

50 Metrics Evaluation and Results NTTG Quarter 4 Stakeholder Meeting Salt Lake City, UT December 13, 2016

51 Energy Loss Metric NTTG Quarter 4 Stakeholder Meeting Salt Lake City, UT December 13, 2016

52 Energy Losses Energy Losses The difference between power produced and power delivered at customer meter Primary sources of transmission system losses Resistive losses (heat) Corona discharge losses (noise) Energy Loss Metric Metric captures the change in energy generated to serve a given amount of load 52

53 Energy Loss Calculation Determine NTTG footprint incremental power losses for each Core Case Losses w/o project losses w/project Reduction in losses = benefit Take average of 6 Core Cases, annualize, and multiply by nodal energy price Result = Annual benefit in $ 53

54 Energy Losses: Projects Evaluated 1. irtp w/o Midpoint Cedar Hill and Midpoint Hemingway #2 segments (CC21) 2. irtp w/o Midpoint Cedar Hill, Midpoint Hemingway #2, and Borah - Populus segments (CC23) 54

55 Energy Loss Metric: Change Case 21 Benefit By BA Locational Marginal Price ($MWh) Avg. Δ Loss (MW) Annualized (MWh) Annualized Benefit ($) PacifiCorp $30.21 ($372,286) PGE $33.07 ($482) NorthWestern $25.16 ($303,401) Idaho Power $31.76 ($2,154,433) Total NTTG Benefit ($2,830,603) 55

56 Energy Loss Metric: Change Case 23 Benefit By BA Locational Marginal Price ($MWh) Avg. Δ Loss (MW) Annualized (MWh) Annualized Benefit ($) PacifiCorp $30.21 ($1,056,869) PGE 0 0 $ NorthWestern $25.16 ($326,909) Idaho Power $31.76 ($2,005,579) Total NTTG Benefit ($3,389,357) 56

57 Energy Loss Metric: Production Cost Analysis Production cost modeling software was also used to evaluate annual energy loss The production cost method resulted in lower annual losses when compared to power flow software The TWG will continue to review the differences between the methods in the following quarters 57

58 Energy Loss Metric: Summary and Conclusions TWG has quantified the energy loss benefit for Change Case 21 and Change Case 23 Removing the 500kV segments resulted in higher energy losses The increased energy losses is a negative benefit Magnitude of benefits are dramatically less than Annual Capital Related Cost metric 58

59 Questions? 59

60 Change in Reserve Metric NTTG Quarter 4 Stakeholder Meeting Salt Lake City, UT December 13, 2016

61 Change in Reserve Metric Metric identifies any potential benefit of transmission to lower the reserve capacity costs of two or more parties. Assumptions: incremental load and generation additions for the 10 year planning period Generation Capacity based on a Simple Cycle Frame F class machine ($800/kW) Reserve event energy costs based on the TEPPC 2026 case zonal gas prices 61

62 Change in Reserves Cont. In this study cycle four transmission upgrades were analyzed: Gateway (West & South) SWIP North Boardman to Hemingway Cross-Tie In order to evaluate these five projects, six zones where used: Bozeman, Boise, Portland, Salt Lake, Wyoming, Desert Southwest 62

63 Change in Reserves Cont. Montana-NW Bozeman Portland B2H Boise Gateway W Wyoming enabled by Gateway W Gateway S SWIP Cross-Tie Salt Lake Desert Southwest 63

64 Change in Reserves Cont. Analysis is spreadsheet based The analysis, the six zones create 180 combinations to consider Not all combinations are enabled by the transmission projects 64

65 Change in Reserves Cont. The combinations include: 30 two party/zones 54 three party/zones 60 four party/zones 30 five party/zones 6 six party/zones Factoring the uncommitted capacity of the transmission additions, the combinations drop to 122 viable sets 20 five party 22 two party 36 three party 40 four party 65

66 Change in Reserves Cont. Of the 122 viable combinations, only 34 provide a positive benefit Reserve location Receiving parties Net Annual Savings Source Party Receiving Party Boise Bozeman Portland Desert Southwest $ 2,896,974 $3,340,315 $( 518,088) $ 34,198 $ 40,549 Portland Bozeman $ 891,190 $ 265,373 $ 625,818 Bozeman Portland $ 891,774 $ 626,227 $ 265,546 Wyoming Boise $ 487,683 $1,154,121 $( 666,438) Desert Southwest Boise, Bozeman, Portland, Salt Lake $2,351,315 $2,480,116 $ 676,876 $( 314,778) $( 337,271) $( 153,629) Salt Lake Desert Southwest $ 756,086 $1,576,050 $( 819,964) 66

67 Change in Reserves Cont. If a connection to the Desert Southwest is not available, the number of viable combinations drops to seven. The top five are: Reserve location Receiving parties Net Annual Savings Source Party Receiving Party Boise Bozeman Portland $ 946,473 $2,039,780 $( 946,120) $( 147,187) Portland Bozeman $ 891,190 $ 265,373 $ 625,818 Bozeman Portland $ 891,774 $ 626,227 $ 265,546 Wyoming Bozeman $ 487,683 $1,154,121 $( 666,438) Salt Lake Bozeman $ 483,710 $1,302,563 $( 818,853) 67

68 Change in Reserves Cont. How does the Change in Reserve metric influence the project selection in this planning cycle? All the change cases under consideration are capable of enabling the viable economic reserve combinations for the NTTG footprint. Since the preferred case and alternative case could contain the same benefit value, the Change in Reserve metric does not factor in the decision process. 68

69 Questions? 69

70 Capital Cost Metric NTTG Quarter 4 Stakeholder Meeting Salt Lake City, UT December 13, 2016

71 Capital Cost Evaluation Estimate Project Cost TEPPC Transmission Capital Cost tool Validate Initial Regional Transmission Plan ( irtp ) project capital cost if submitted by project sponsor Attempt to resolve differences if sponsor estimate outside plus or minus 20% of the TEPPC transmission cost calculator estimate calculator Develop the project capital cost estimate if sponsor did not submit project capital cost 71

72 Estimate Project Cost Longhorn Hemingway Example Longhorn-Hemingway Example Estimated Capital Cost 2016$ $ per Mile Estimated Project Cost Line Cost $ 895,901,514 $ 3,036,954 ROW Cost $ 1,278,102 $ 4,333 Longhorn Sub $ 42,228,445 Hemingway Sub $ 29,912,827 AFUDC/Overhead Cost $ 169,631,155 Estimated All Costs $ 1,138,952,042 Miles

73 Validate Project Cost 2016$ Acceptable Range Longhorn-Hemingway Energy Gateway Project 80% $911,161,634 $3,922,453,544 TEPPC Calculator $1,138,952,042 $4,903,066, % $1,366,742,451 $5,883,680,317 irtp Total non- Committed Sponsor Cost Provided $1,220,625,000 Use TEPPC Cost Estimate Used $1,220,625,000 $4,903,066,931 $6,123,691,931 In-service Year

74 Change Case 21 Cost 2016$ CC21 Project Capital Cost irtp Capital Cost $6,123,691,931 Less EGW MidPt-Hemingway $351,384,130 EGW MidPt-Cedar Hill $96,849,280 Less Sum $448,233,410 CC21 Capital Cost $5,675,458,521 EGW Capital Cost 2016$ EGW Project Cost in irtp $4,903,066,931 Less Projects Cost from above $448,233,410 CC21 EGW Project Cost $4,454,833,521 74

75 Change Case 23 Cost 2016$ CC23 Capital Cost irtp Capital Cost $6,123,691,931 Less EGW MidPt-Hemingway $351,384,130 EGW MidPt-Cedar Hill $96,849,280 EGW Populus-Borah $244,421,657 Less Sum $692,655,066 CC21 Capital Costs $5,431,036,864 EGW Capital Cost 2016$ EGW Project Cost in irtp $4,903,066,931 Less Projects Cost from above $692,655,066 CC231 EGW Project Cost $4,210,411,864 75

76 Capital Related Cost ( CRC ) Develop annual CRC for each project in the case being considered irtp Change Cases Use TEPPC s simplified annual CRC model 76

77 Annual CRC Example Longhorn Hemingway Example Capital Cost 2022 Dollars $1,374,622,003 Revenue Requirement Fixed O&M $35,052,861 $35,753,918 $36,468,997 $37,198,377 $37,942,344 Property Tax $13,746,220 $13,402,565 $13,058,909 $12,715,254 $12,371,598 Insurance $7,010,572 $7,150,784 $7,293,799 $7,439,675 $7,588,469 Interest $41,238,660 $39,799,946 $37,627,288 $35,609,573 $33,730,492 Equity Return $75,604,210 $72,966,568 $68,983,360 $65,284,217 $61,839,235 Depreciation $34,365,550 $34,365,550 $34,365,550 $34,365,550 $34,365,550 Tax on Equity Return - before grossup $29,901,465 $28,858,278 $27,282,919 $25,819,908 $24,457,417 Tax Grossup - Equity $19,563,324 $18,880,809 $17,850,115 $16,892,926 $16,001,503 Total Revenue Requirement $256,482,863 $251,178,418 $242,930,937 $235,325,478 $228,296,609 77

78 CRC Process Step 1 Longhorn Hemingway Example Escalate Project Cost the in-service year 2016$ $1,220,625, Escalate $ $1,374,622,003 78

79 CRC Process Step 2 Longhorn Hemingway Example Estimate CRC Project Cost 40 Yr. Annual CRC NPV CRC 2022$ $1,374,622, $ $2,283,608, $256,482, $251,178, $242,930,937 NPV Annual CRC 2062 $128,279,127 79

80 CRC Process Step 3 Longhorn Hemingway Example NPV 2016$ $2,027,779, De-escalate $ $2,283,608,944 80

81 irtp Capital Related Cost irtp non-committed Projects Longhorn- Hemingway Energy Gateway Project irtp Capital Cost Estimate Used $1,220,625,000 $4,903,066,931 $6,123,691,931 Estimated NPV Capital Related Costs $2,027,779,390 $8,145,284,646 $10,173,064,037 81

82 Capital Related Cost Metric 2016$ irtp CC21 CC23 Capital Cost Estimate $6,123,691,931 $5,675,458,521 $5,431,036,864 NPV Cap. Related Cost $10,173,064,037 $9,428,430,369 $9,022,381,667 Diff from irtp -7.3% -4.3% Levelized Cap. Relate Cost $899,115,803 $833,303,586 $797,416,187 Difference from irtp M$ ($65.812) ($101,699,616) 82

83 Economic Assumptions IOU Financing Share Rate Wei Rate Equity 50.00% 11.00% 5.50% Debt 50.00% 6.00% 3.00% Wei Cost Capital Years Economic Life 40 (Discount Rate) 8.50% Annual Escalation U.S. GDP Percent Change 2013 H 1.7% 2014 H 2.4% 2015 H 2.6% 2016 F 1.5% > 2016 F 2.0% 83

84 Increment Cost Sum of 3 metrics for potential irtps Levelized NPV CRC monetized energy losses monetized reserves 84

85 Change Case Metric 2016 M$ Change Case Metric CC21 - irtp CC23 - irtp Levelized Cap. Related Cost ($65.81) ($101.70) NTTG Losses - Monitized $2.83 $3.39 NTTG Reserve - Monitized $0.00 $0.00 Total Difference ($62.98) ($98.31) 85

86 Incremental Cost 2016 M$ Case Difference from irtp Incremental Cost irtp $ CC21 ($62.98) $ CC23 ($98.31) $

87 Questions? 87

88 Draft Regional Transmission Plan Project Selection NTTG Quarter 4 Stakeholder Meeting Salt Lake City, UT December 13, 2016

89 Draft Regional Transmission Plan (DRTP) Based on the reliability and economic considerations previously discussed, the most efficient and costeffective plan based on the studies performed is the Change Case (CC23) plan consisting of: IRTP with the non-committed projects removed, and addition of the following transmission facilities: Boardman/Longhorn Hemingway 500 kv, Gateway West Segment D (Populus Windstar) and Gateway South Segment F (Aeolus Clover) Other selected portions of Gateway West Segment E.1 and E.2; specifically, Populus Cedar Hill 500 kv and Cedar Hill Hemingway 500 kv 89

90 Draft Regional Transmission Plan Impacts on Other Regions In developing the DRTP, using a system model representing the entire Western Interconnection, no negative impacts to other regions were identified. Technical studies indicated that the DRTP would support each of the Interregional Transmission Projects (ITPs) submitted; however, none of the ITPs satisfied a Northern Tier regional need 90

91 Draft Regional Transmission Plan Cost Allocation None of the projects selected into the DRTP will have costs allocated. 91

92 Transmission Use Committee Update NTTG Quarter 4 Stakeholder Meeting Salt Lake City, UT December 13, 2016

93 Transmission Use Committee Members: Michael Flanick - Chair, Northwestern Energy Matt Richard - Vice Chair, Portland General Electric Nathan Powell - Deseret Power Electric Cooperative Beth Ryan - Idaho Power Michael Manarovici - MATL Brian Fritz PacifiCorp 93

94 Purpose of Transmission Use Committee Established to: Increase efficiency of existing member utility transmission systems through commercially reasonable initiatives, and Increase customer knowledge of, and transparency into, the transmission systems of member utilities Membership consists of: Representatives from the transmission provider of each utility or utility cooperative that is a party to the NTTG funding agreement May be extended to include (1) appointed staff representatives from state regulatory utility commissions within the NTTG footprint and (2) representatives appointed by state customer advocacy groups within the NTTG footprint 94

95 POR / POD Map 95

96 NTTG POR/POD Map as of December 1,

97 NTTG POR/POD Common Names List as of December 1, 2016 Common Names List 97

98 Questions? 98

99 Anchor Data Set Development Update NTTG Quarter 4 Stakeholder Meeting Salt Lake City, UT December 13, 2016

100 Neighboring Planning Region Updates NTTG Quarter 4 Stakeholder Meeting Salt Lake City, UT December 13, 2016

101 Neighboring Planning Region Updates CAISO Gary DeShazo ColumbiaGrid Paul Didsayabutra WestConnect Charlie Reinhold 101

102 Next Steps and Opportunities for Stakeholder Input NTTG Quarter 4 Stakeholder Meeting Salt Lake City, UT December 13, 2016

103 Upcoming Q5 Opportunities for Stakeholder Input 103

104 Stakeholder Comments Other Business

105 Thank You!

NTTG REGIONAL TRANSMISSION PLAN. December 30, 2015

NTTG REGIONAL TRANSMISSION PLAN. December 30, 2015 NTTG 2014-2015 REGIONAL TRANSMISSION PLAN December 30, 2015 1 Table of Contents Executive Summary... 3 Introduction... 3 The Northern Tier Transmission Group... 3 Participating Utilities... 4 Purpose of

More information

2011 IRP Public Input Meeting. October 5, Pacific Power Rocky Mountain Power PacifiCorp Energy

2011 IRP Public Input Meeting. October 5, Pacific Power Rocky Mountain Power PacifiCorp Energy 2011 IRP Public Input Meeting October 5, 2010 Pacific Power Rocky Mountain Power PacifiCorp Energy Agenda Morning Session IRP Schedule Update Energy Gateway Transmission Construction Update and Evaluation

More information

ITP Evaluation Process Plan

ITP Evaluation Process Plan ITP Evaluation Process Plan HVDC Conversion Project The goal of the coordinated Interregional Transmission Project (ITP) evaluation process is to achieve consistent planning assumptions and technical data

More information

Transmission Planning Attachment K Public Input Meeting FERC 890, Biennial Cycle 3rd Quarter Meeting

Transmission Planning Attachment K Public Input Meeting FERC 890, Biennial Cycle 3rd Quarter Meeting Transmission Planning Attachment K Public Input Meeting FERC 890, 2010-11 Biennial Cycle 3rd Quarter Meeting October 1, 2010 Agenda Topic Presenter 9:00 9:10 Greetings and Introduction Austin 9:10 9:15

More information

PacifiCorp Transmission Rate Case

PacifiCorp Transmission Rate Case PacifiCorp Transmission Rate Case Customer & Stakeholder Meetings Portland, March 10, 2011 & Salt Lake City, March 16, 2011 2000 PACIFICORP PAGE 2 Agenda Welcome and Introduction Purpose of Meeting and

More information

COLUMBIAGRID GEOMAGNETIC DISTURBANCE DRAFT STUDY REPORT

COLUMBIAGRID GEOMAGNETIC DISTURBANCE DRAFT STUDY REPORT COLUMBIAGRID GEOMAGNETIC DISTURBANCE DRAFT STUDY REPORT (NERC Standard TPL-007-1) Revision 1 February 1, 2018 ColumbiaGrid 8338 NE Alderwood Road, Suite 140 Portland, OR 97220 www.columbiagrid.org (503)

More information

Regional Planning Coordination Group (RPCG) 2024 Common Case Transmission Assumptions (CCTA) June 2, 2014 FINAL

Regional Planning Coordination Group (RPCG) 2024 Common Case Transmission Assumptions (CCTA) June 2, 2014 FINAL Regional Planning Coordination Group (RPCG) 2024 Common Case Transmission Assumptions (CCTA) June 2, 2014 FINAL Executive Summary The Regional Planning Coordination Group (RPCG) aids the Regional Transmission

More information

SPP s Regional Review of SPP-MISO Coordinated System Plan Recommended Interregional Projects

SPP s Regional Review of SPP-MISO Coordinated System Plan Recommended Interregional Projects SPP s Regional Review of SPP-MISO Coordinated System Plan Recommended Interregional Projects January 4, 2016 SPP Interregional Relations Table of Contents Executive Summary... 2 Introduction... 5 Stakeholder

More information

Nevada Power & Sierra Pacific Power d/b/a NV Energy Stakeholders Planning Input Meeting July

Nevada Power & Sierra Pacific Power d/b/a NV Energy Stakeholders Planning Input Meeting July Nevada Power & Sierra Pacific Power d/b/a NV Energy Stakeholders Planning Input Meeting July 2012 1 1. Welcome Introductions 2. IRP filing and results Update on Loads and Resources Renewable Transmission

More information

Stakeholder Comment Matrix Harry Allen-Eldorado 500 kv line project December 12, 2014

Stakeholder Comment Matrix Harry Allen-Eldorado 500 kv line project December 12, 2014 The ISO received comments on the CAISO economic analysis results stakeholder meeting discussion held on November 20, 2014 1 from the following: 1. Bay Area Municipal Transmission group (BAMx) 2. California

More information

Stochastic Loss of Load Study for the 2011 Integrated Resource Plan

Stochastic Loss of Load Study for the 2011 Integrated Resource Plan November 18, 2010 Stochastic Loss of Load Study for the 2011 Integrated Resource Plan INTRODUCTION PacifiCorp evaluates the desired level of capacity planning reserves for each integrated resource plan.

More information

BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION

BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION IN THE MATTER OF THE APPLICATION OF ROCKY MOUNTAIN POWER FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY AND BINDING RATEMAKING TREATMENT FOR NEW WIND

More information

1st Qua u r a ter e M e M e e t e in i g 2nd Qua u r a ter e M e M e e t e in i g

1st Qua u r a ter e M e M e e t e in i g 2nd Qua u r a ter e M e M e e t e in i g 2012 SERTP Welcome SERTP 2012 First RPSG Meeting & Interactive Training Session 1 2012 SERTP The SERTP process is a transmission planning process. Please contact the respective transmission provider for

More information

Mountain West Transmission Group (MWTG) Introduction and Process

Mountain West Transmission Group (MWTG) Introduction and Process Mountain West Transmission Group (MWTG) Introduction and Process October 13 Denver, CO October 16 Little Rock, AR 2 Agenda Overview of SPP Overview of the MWTG Members SPP Process New Member Integration

More information

BEFORE THE PUBLIC SERVICE COMMISSION OF UTAH

BEFORE THE PUBLIC SERVICE COMMISSION OF UTAH R. Jeff Richards (7294) Yvonne R. Hogle (7550) 1407 West North Temple, Suite 320 Salt Lake City, Utah 84116 Telephone: (801) 220-4050 Facsimile: (801) 220-3299 Email: robert.richards@pacificorp.com yvonne.hogle@pacificorp.com

More information

All Source Request for Proposal Bid Conference. October 22, 2008

All Source Request for Proposal Bid Conference. October 22, 2008 All Source Request for Proposal Bid Conference October 22, 2008 Agenda Overview of All Source Request for Proposal Schedule and timeline Resource Alternatives Delivery Points Bid Fee (s) Fixed and Index

More information

10-YEAR COSTS AND BENEFITS TO SPP MEMBERS OF INTEGRATING MOUNTAIN WEST TRANSMISSION GROUP Quantitative Analysis of Costs and Benefits

10-YEAR COSTS AND BENEFITS TO SPP MEMBERS OF INTEGRATING MOUNTAIN WEST TRANSMISSION GROUP Quantitative Analysis of Costs and Benefits 10-YEAR COSTS AND BENEFITS TO SPP MEMBERS OF INTEGRATING MOUNTAIN WEST TRANSMISSION GROUP Quantitative Analysis of Costs and Benefits Published on March 19, 2018 By SPP Staff REVISION HISTORY DATE OR VERSION

More information

APPENDIX B: WHOLESALE AND RETAIL PRICE FORECAST

APPENDIX B: WHOLESALE AND RETAIL PRICE FORECAST Seventh Northwest Conservation and Electric Power Plan APPENDIX B: WHOLESALE AND RETAIL PRICE FORECAST Contents Introduction... 3 Key Findings... 3 Background... 5 Methodology... 7 Inputs and Assumptions...

More information

SPP New Member Communication and Integration Process. Mountain West Transmission Group. Background Information October 2017

SPP New Member Communication and Integration Process. Mountain West Transmission Group. Background Information October 2017 1 SPP New Member Communication and Integration Process Mountain West Transmission Group Background Information October 2017 Contents Introduction... 2 1. Westside Tariff Design... 2 2. Operational Provisions...

More information

2019 Integrated Resource Plan (IRP) Public Input Meeting January 24, 2019

2019 Integrated Resource Plan (IRP) Public Input Meeting January 24, 2019 1 2019 Integrated Resource Plan (IRP) Public Input Meeting January 24, 2019 Agenda January 24 9:00am-9:30am pacific Capacity-Contribution Values for Energy-Limited Resources 9:30am-11:30am pacific Coal

More information

Project Coordination and Path Rating

Project Coordination and Path Rating Document name Category Project Coordination, Path Rating and Progress Report Processes ( ) Regional Reliability Standard ( ) Regional Criteria ( ) Policy (X) Guideline ( ) Report or other ( ) Charter Document

More information

Western Area Power Administration-Rocky Mountain Region

Western Area Power Administration-Rocky Mountain Region Western Area Power Administration-Rocky Mountain Region Revision Date CURRENT BUSINESS PRACTICES Effective Date: October 1, 2017 Business Practices Revision Table (Changes to the business rules for this

More information

Wyoming Office of Consumer Advocate (OCA)

Wyoming Office of Consumer Advocate (OCA) Wyoming Office of Consumer Advocate (OCA) 2019-2020 Biennium Strategic Plan Results Statement Wyoming has a diverse economy that provides a livable income and ensures wage equality. Wyoming natural resources

More information

EIPC Roll-Up Report & Scenarios

EIPC Roll-Up Report & Scenarios EIPC Roll-Up Report & Scenarios Zach Smith Director, Transmission Planning New York Independent System Operator IPTF/EGCWG/ESPWG Meeting January 6, 2014 2013 New York Independent System Operator, Inc.

More information

WestConnect Planning. Tri-State Offices Westminster, CO April 20, 2016

WestConnect Planning. Tri-State Offices Westminster, CO April 20, 2016 WestConnect Planning Management Committee (PMC) Tri-State Offices Westminster, CO April 20, 2016 1 Welcome & Introductions Blane Taylor, PMC Chair, TSGT 2 Antitrust Statement Reminder Blane Taylor, PMC

More information

APS/SRP Stakeholder Meeting For Transmission Planning

APS/SRP Stakeholder Meeting For Transmission Planning APS/SRP Stakeholder Meeting For Transmission Planning FERC Order 890 SRP Attachment K APS Attachment E SRP Facility Scottsdale, AZ December 15 th, 2017 9:00 11:00 A.M. Agenda 1. Welcome, Introductions,

More information

Western Interconnection Unscheduled Flow Mitigation Plan, (WIUFMP)

Western Interconnection Unscheduled Flow Mitigation Plan, (WIUFMP) Western Interconnection Unscheduled Flow Mitigation Plan, (WIUFMP) Purpose: The purpose of the Western Interconnection Unscheduled Flow Mitigation Plan (WIUFMP) is to mitigate flows on Qualified Paths

More information

Ian McKay Chair Transmission Expansion Planning and Policy Committee (204)

Ian McKay Chair Transmission Expansion Planning and Policy Committee (204) Date: December 23, 2015 Ian McKay Chair Transmission Expansion Planning and Policy Committee (204) 430-1950 i.mckay@shaw.ca To: Subject: Reliability Planning Stakeholders 2016 TEPPC Study Program Open

More information

Final Draft 2012 Request for Proposals. Oregon Public Utility Commission Workshop August 16, 2006

Final Draft 2012 Request for Proposals. Oregon Public Utility Commission Workshop August 16, 2006 Final Draft 2012 Request for Proposals Oregon Public Utility Commission Workshop August 16, 2006 Agenda Regulatory overview and schedule Order No 06-446 (UM 1182) Key Features of the 2012 Request for Proposal

More information

Cost Allocation Principles for Seams Transmission Expansion Projects

Cost Allocation Principles for Seams Transmission Expansion Projects Cost Allocation Principles for Seams Transmission Expansion Projects SPP s seams agreements currently contain requirements for SPP to develop coordinated system plans with its neighbors. The extent and

More information

Integrated Resource Plan IRP Public Input Meeting June 28-29, 2018

Integrated Resource Plan IRP Public Input Meeting June 28-29, 2018 1 Integrated Resource Plan 2019 IRP Public Input Meeting June 28-29, 2018 Agenda June 28, 2018 Confidential Discussion Introductions Model Overview (System Optimizer / Planning and Risk) Lunch Break (1

More information

BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON

BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON ORDER NO. 18 17 ENTERED MAY 23 2018 BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON LC68 In the Matter of IDAHO POWER COMPANY, ORDER 2017 Integrated Resource Plan. DISPOSITION: 2017 IRP ACKNOWLEDGED WITH

More information

4.1 Transmission Owners that maintain the transmission paths in Attachment B.

4.1 Transmission Owners that maintain the transmission paths in Attachment B. A. Introduction 1. Title: Transmission Maintenance 2. Number: FAC-501-WECC-2 3. Purpose: To ensure the Transmission Owner of a transmission path identified in Attachment B, Major WECC Transfer Paths in

More information

WestConnect Planning Management Committee (PMC) LADWP Offices Los Angeles, CA July 20, 2016

WestConnect Planning Management Committee (PMC) LADWP Offices Los Angeles, CA July 20, 2016 WestConnect Planning Management Committee (PMC) LADWP Offices Los Angeles, CA July 20, 2016 1 Welcome & Introductions Blane Taylor, PMC Chair, Tri-State G&T 2 Antitrust Statement Reminder Blane Taylor,

More information

New Member Cost Allocation Review Process. Prepared by: COST ALLOCATION WORKING GROUP

New Member Cost Allocation Review Process. Prepared by: COST ALLOCATION WORKING GROUP New Member Cost Allocation Review Process Prepared by: COST ALLOCATION WORKING GROUP TABLE OF CONTENTS 1. HISTORY AND BACKGROUND... 1 2. PURPOSE / GOAL STATEMENT... 3 3. OVERVIEW OF PROCESS... 3 4. NEW

More information

Memorandum. This memorandum does not require Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum does not require Board action. EXECUTIVE SUMMARY California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Eric Hildebrandt, Executive Director, Market Monitoring Date: November 7, 2018 Re: Department of Market Monitoring

More information

Contingency Reserve Cost Allocation. Draft Final Proposal

Contingency Reserve Cost Allocation. Draft Final Proposal Contingency Reserve Cost Allocation Draft Final Proposal May 27, 2014 Contingency Reserve Cost Allocation Draft Final Proposal Table of Contents 1 Introduction... 3 2 Changes to Straw Proposal... 3 3 Plan

More information

BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON

BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON LC 50 ORDER NO. 10-392 ENTERED 10/11/10 In the Matter of IDAHO POWER COMPANY ORDER 2009 Integrated Resource Plan. DISPOSITION: PLAN ACKNOWLEDGED WITH REQUIREMENTS

More information

Alberta Utilities Commission

Alberta Utilities Commission Alberta Utilities Commission In the Matter of the Need for 138 kv and 240 kv Transmission System Development in the Red Deer Region And in the matter of the Electric Utilities Act, S.A. 2003, c. E-5.1,

More information

APS/SRP Stakeholder Meeting For Transmission Planning

APS/SRP Stakeholder Meeting For Transmission Planning APS/SRP Stakeholder Meeting For Transmission Planning FERC Order 890 SRP Attachment K APS Attachment E SRP Facility Scottsdale, AZ December 15 th, 2017 9:00 11:00 A.M. Agenda 1. Welcome, Introductions,

More information

Impacts of Marginal Loss Implementation in ERCOT

Impacts of Marginal Loss Implementation in ERCOT Impacts of Marginal Loss Implementation in ERCOT 2018 Reference Scenario Results PREPARED BY Metin Celebi Bruce Tsuchida Rebecca Carroll Colin McIntyre Ariel Kaluzhny October 11, 2017 Copyright 2017 The

More information

Information Document Available Transfer Capability and Transfer Path Management ID # R

Information Document Available Transfer Capability and Transfer Path Management ID # R Information Documents are not authoritative. Information Documents are for information purposes only and are intended to provide guidance. In the event of any discrepancy between an Information Document

More information

July 31, 2017 Via Electronic Filing

July 31, 2017 Via Electronic Filing 414 Nicollet Mall Minneapolis, 55401 July 31, 2017 Via Electronic Filing Mr. William Grant Deputy Commissioner, Division of Energy Resources Minnesota Department of Commerce 85 7 th Place East, Suite 500

More information

TAC FIX IMPACT MODEL DETAILED OVERVIEW

TAC FIX IMPACT MODEL DETAILED OVERVIEW TAC FIX IMPACT MODEL DETAILED OVERVIEW Contents Goal of Spreadsheet... 2 Drivers of transmission investment... 2 Note About Terminology... 3 Core Assumptions... 3 Load served locally for an example IOU,

More information

KEY FINDINGS AND RESOURCE STRATEGY

KEY FINDINGS AND RESOURCE STRATEGY KEY FINDINGS AND RESOURCE STRATEGY The Council s Power Plan Goal - Ensure an adequate, efficient and affordable regional power system Major Components Forecast of regional electricity demand over the next

More information

BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION SOUTHWESTERN PUBLIC SERVICE COMPANY S UNOPPOSED RESPONSE TO STAFF S COMMENTS

BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION SOUTHWESTERN PUBLIC SERVICE COMPANY S UNOPPOSED RESPONSE TO STAFF S COMMENTS BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION IN THE MATTER OF SOUTHWESTERN ) PUBLIC SERVICE COMPANY S 2018 ) INTEGRATED RESOURCE PLAN FOR ) NEW MEXICO. ) CASE NO. 18-00215-UT ) SOUTHWESTERN PUBLIC

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 36. Congestion Revenue Rights... 3 36.1 Overview Of CRRs And Procurement Of CRRs... 3 36.2 Types Of CRR Instruments... 3 36.2.1 CRR Obligations... 3 36.2.2 CRR Options... 3 36.2.3 Point-To-Point

More information

WECC Criterion TPL-001-WECC-CRT-3.1

WECC Criterion TPL-001-WECC-CRT-3.1 WECC Criterion TPL-001-WECC-CRT-3.1 A. Introduction 1. Title: Transmission System Planning Performance 2. Number: TPL-001-WECC-CRT-3.1 3. Purpose: To facilitate coordinated near-term and long-term transmission

More information

Rocky Mountain Power Exhibit RMP (JRS-1S) Docket No ER-15 Witness: Joelle R. Steward BEFORE THE WYOMING PUBLIC SERVICE COMMISSION

Rocky Mountain Power Exhibit RMP (JRS-1S) Docket No ER-15 Witness: Joelle R. Steward BEFORE THE WYOMING PUBLIC SERVICE COMMISSION Exhibit RMP (JRS-1S) BEFORE THE WYOMING PUBLIC SERVICE COMMISSION ROCKY MOUNTAIN POWER Exhibit Accompanying Supplemental Direct Testimony of Joelle R. Steward June 2015 Exhibit RMP (JRS-1S) Page 1 of 34

More information

The cost allocation principles and methodologies in this Attachment Y cover only

The cost allocation principles and methodologies in this Attachment Y cover only 31.5 Cost Allocation and Cost Recovery 31.5.1 The Scope of Attachment Y Cost Allocation 31.5.1.1 Regulated Responses The cost allocation principles and methodologies in this Attachment Y cover only regulated

More information

Southwest Power Pool, Inc. Policy Recommendation for the SPP Board of Directors and Members Committee. March 6, 2018 Mountain West Transmission Group

Southwest Power Pool, Inc. Policy Recommendation for the SPP Board of Directors and Members Committee. March 6, 2018 Mountain West Transmission Group Southwest Power Pool, Inc. Policy for the SPP Board of Directors and Members Committee Policy Area #1 DC Ties March 6, 2018 Mountain West Transmission Group SPP and MWTG anticipate that incorporating the

More information

Informational Filing of Midwest Independent Transmission System Operator, Inc. s Independent Market Monitor

Informational Filing of Midwest Independent Transmission System Operator, Inc. s Independent Market Monitor Potomac Economics, Ltd. 9990 Fairfax Boulevard, Suite 560 Telephone: 703-383-0720 Fairfax, Virginia 22030 Facsimile: 703-383-0796 Honorable Kimberly D. Bose, Secretary Federal Energy Regulatory Commission

More information

BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION ) ) ) ) ) ) ) ) ) ) ) DIRECT TESTIMONY WILLIAM A. GRANT. on behalf of

BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION ) ) ) ) ) ) ) ) ) ) ) DIRECT TESTIMONY WILLIAM A. GRANT. on behalf of BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION IN THE MATTER OF SOUTHWESTERN PUBLIC SERVICE COMPANY S APPLICATION FOR REVISION OF ITS RETAIL RATES UNDER ADVICE NOTICE NO., SOUTHWESTERN PUBLIC SERVICE

More information

Portland General Electric Reports 2017 Financial Results and Initiates 2018 Earnings Guidance

Portland General Electric Reports 2017 Financial Results and Initiates 2018 Earnings Guidance February 16, 2018 Portland General Electric Reports 2017 Financial Results and Initiates 2018 Earnings Guidance Full-year 2017 financial results on target excluding the effects of the Tax Cuts and Jobs

More information

2018 Business Plan and Budget Supplemental Information May 1, 2017

2018 Business Plan and Budget Supplemental Information May 1, 2017 2018 Business Plan and Budget Supplemental Information May 1, 2017 Today we posted our 2018 Business Plan and Budget (BP&B) for stakeholder comment. WECC staff had productive dialogue with the members

More information

J.P. Morgan Comments on CAISO Straw Proposal on Data Release & Accessibility Phase 1: Transmission Constraints

J.P. Morgan Comments on CAISO Straw Proposal on Data Release & Accessibility Phase 1: Transmission Constraints J.P. Morgan Comments on CAISO Straw Proposal on Data Release & Accessibility Phase 1: Transmission Constraints Submitted by Company Date Submitted Steve Greenleaf (916) 802-5420 J.P. Morgan December 16,

More information

FERC Order 890 APS Attachment E SRP Attachment K

FERC Order 890 APS Attachment E SRP Attachment K APS/SRP 2 nd Quarter Stakeholder FERC Order 890 APS Attachment E SRP Attachment K APS Deer Valley Facility Phoenix, Arizona June 14, 2018 9 AM -12 PM Agenda 1. Welcome, Introductions, and Stakeholder Meeting

More information

AC TRANSMISSION PUBLIC POLICY TRANSMISSION NEEDS PROJECT SOLICITATION Response due April 29, 2016

AC TRANSMISSION PUBLIC POLICY TRANSMISSION NEEDS PROJECT SOLICITATION Response due April 29, 2016 10 Krey Boulevard Rensselaer, NY 12144 AC TRANSMISSION PUBLIC POLICY TRANSMISSION NEEDS PROJECT SOLICITATION Response due April 29, 2016 Dear NYISO Stakeholder or Interested Party: February 29, 2016 With

More information

WECC Guideline: UNSCHEDULED FLOW REDUCTION GUIDELINE

WECC Guideline: UNSCHEDULED FLOW REDUCTION GUIDELINE The content of this document is an excerpt of the WECC Unscheduled Flow Mitigation Plan Document posted on www.wecc.biz. Introduction WECC : UNSCHEDULED FLOW REDUCTION GUIDELINE The combination of Scheduled

More information

Request for Proposals. Renewable Resources (2016R RFP) ISSUED: Monday, April 11, DUE DATE: Friday, May 20, :00 PM PPT

Request for Proposals. Renewable Resources (2016R RFP) ISSUED: Monday, April 11, DUE DATE: Friday, May 20, :00 PM PPT Request for Proposals Renewable Resources (2016R RFP) ISSUED: Monday, April 11, 2016 DUE DATE: Friday, May 20, 2016 5:00 PM PPT 2016R RFP Responses: PacifiCorp RFP 2016R Attention: Origination 825 NE Multnomah,

More information

Transmission Transitions: Potential Cost Savings Offered by Competitive Planning

Transmission Transitions: Potential Cost Savings Offered by Competitive Planning Transmission Transitions: Potential Cost Savings Offered by Competitive Planning Discussion Paper PRESENTED AT NRRI Webinar PREPARED BY Johannes Pfeifenberger Judy Chang Akarsh Sheilendranath PREPARED

More information

BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER. Direct Testimony of Michael G. Wilding

BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER. Direct Testimony of Michael G. Wilding Rocky Mountain Power Docket No. 18-035-01 Witness: Michael G. Wilding BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER Direct Testimony of Michael G. Wilding March 2018 1

More information

FERC and the Recent ROE Giveaway

FERC and the Recent ROE Giveaway FERC and the Recent ROE Giveaway R. Mihai Cosman CPUC Energy Division mr2@cpuc.ca.gov 415-355-5504 Energy Policy Act of 2005 Congress determined that there is a need for rate incentives to encourage investment

More information

MISO Planning Process. May 31, 2013

MISO Planning Process. May 31, 2013 MISO Planning Process May 31, 2013 MISO Planning Objectives Fundamental Goal The development of a comprehensive expansion plan that meets reliability needs, policy needs, and economic needs MISO Board

More information

Flexible Capacity Requirements for 2019 through 2021

Flexible Capacity Requirements for 2019 through 2021 Flexible Capacity Requirements for 2019 through 2021 Clyde Loutan - Principal, Renewable energy Integration Amber Motley - Manager, Short Term Forecasting Stakeholder Conference Call January 29 th, 2018

More information

WASN Operations Business Procedure OASIS COVER PAGE

WASN Operations Business Procedure OASIS COVER PAGE No. COVER PAGE This page will be removed when final document is posted Western Area Power Administration Sierra Nevada Region () Business Practice/ covering Sierra Nevada Regional procedures is being updated.

More information

TNUoS Tariffs in 10 minutes March 2018

TNUoS Tariffs in 10 minutes March 2018 TNUoS s in 10 minutes March 2018 An overview of TNUoS tariffs This information paper provides an overview of National Grid s Transmission Network Use of System (TNUoS) tariffs, applicable to transmission

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Docket No. ER

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Docket No. ER UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PacifiCorp Docket No. ER16-193-000 MOTION TO INTERVENE AND COMMENTS OF THE WESTERN POWER TRADING FORUM Pursuant to Rules 211, 212

More information

Portland General Electric Reports First Quarter 2009 Earnings Results

Portland General Electric Reports First Quarter 2009 Earnings Results Portland General Electric Reports First Quarter 2009 Earnings Results Reaffirms 2009 Earnings Guidance PORTLAND, Ore., May 04, 2009 (BUSINESS WIRE) -- Portland General Electric Company (NYSE:POR) today

More information

NERC TPL Standard Overview

NERC TPL Standard Overview NERC TPL-001-4 Standard Overview Attachment K Quarter 3 Stakeholder s Meeting September 29, 2016 1 Background New NERC TPL Standard 2016 TPL Plan and Status Update 2015 Planning Assessment Results Compliance

More information

1. MARS Base Case Model Assumptions

1. MARS Base Case Model Assumptions 1. MARS Base Case Model Assumptions 1.1 Load s Peak Load Load Shape Load Forecast Uncertainty 2014 IRM Model Assumptions October 1, 2013 forecast NYCA: 33,655 MW NYC: 11,740 MW Long Island 5,461 MW Multiple

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Transmission Planning and Cost Allocation ) by Transmission Owning and Operating ) Docket No. RM10-23- 000 Public Utilities ) Comments

More information

OREGON STANDARD AVOIDED COST RATES AVOIDED COST PURCHASES FROM ELIGIBLE QUALIFYING FACILITIES Page 1

OREGON STANDARD AVOIDED COST RATES AVOIDED COST PURCHASES FROM ELIGIBLE QUALIFYING FACILITIES Page 1 S ELIGIBLE QUALIFYING FACILITIES Page 1 Available To owners of Qualifying Facilities making sales of electricity to the Company in the State of Oregon. Applicable For power purchased from Base Load and

More information

Transmission Loss Factor Methodology

Transmission Loss Factor Methodology Transmission Loss Factor Methodology Discussion Paper Operations & Reliability Draft February 9, 2005 Table of Contents 1. Introduction...3 1.1 Legislative Direction.....3 1.2 Goal and Objectives... 3

More information

Injection / Withdrawal CARP

Injection / Withdrawal CARP Injection / Withdrawal CARP Decisions Note: To inform the RECB Stakeholders at their upcoming September 30 th meeting, this version of the Decision Tree contains the decisions made by CARP (in bold/italics)

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA COMMENTS OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA COMMENTS OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Rulemaking to Develop an Electricity Integrated Resource Planning Framework and to Coordinate and Refine Long-Term Procurement

More information

RR16 - Page 1 of

RR16 - Page 1 of DOCKET NO. APPLICATION OF SOUTHWESTERN PUBLIC SERVICE COMPANY FOR AUTHORITY TO CHANGE RATES PUBLIC UTILITY COMMISSION OF TEXAS DIRECT TESTIMONY of ARTHUR P. FREITAS on behalf of SOUTHWESTERN PUBLIC SERVICE

More information

Seams Cost Allocation: A Flexible Framework to Support Interregional Transmission Planning (Summary of Final Report)

Seams Cost Allocation: A Flexible Framework to Support Interregional Transmission Planning (Summary of Final Report) Seams Cost Allocation: A Flexible Framework to Support Interregional Transmission Planning (Summary of Final Report) Presented at: SPP RSC Quarterly Meeting Presented by: Johannes Pfeifenberger Delphine

More information

For the Efficiency Maine Trust October 15, 2009 Eric Belliveau, Optimal Energy Inc.

For the Efficiency Maine Trust October 15, 2009 Eric Belliveau, Optimal Energy Inc. DSM Economics For the Efficiency Maine Trust October 15, 2009 Eric Belliveau, Optimal Energy Inc. DSM Economics - Overview Why? Basics of Economics Benefits Costs Economic Test Overviews Economics of Sample

More information

transmission system. This project is referred to in the Transition Agreement as the Transmission Interconnection.

transmission system. This project is referred to in the Transition Agreement as the Transmission Interconnection. 2 Application of Valley Electric Association, Inc. to the California Independent System Operator Corporation to Become a Participating Transmission Owner June 21, 2012 Valley Electric Association, Inc.

More information

SPP PLANNING AND COST ALLOCATION OVERVIEW

SPP PLANNING AND COST ALLOCATION OVERVIEW Benefit/Cost Ratio Primer 101 for the Regional Allocation Review Task Force August 4, 2011 1 SPP PLANNING AND COST ALLOCATION OVERVIEW 2 1 Transmission = 10% Retail Electricity Rates Transmission enables

More information

West Coast Utilities Conference. March 21-22, 2018 Las Vegas, Nevada

West Coast Utilities Conference. March 21-22, 2018 Las Vegas, Nevada West Coast Utilities Conference March 21-22, 2018 Las Vegas, Nevada Forward-Looking Statements In addition to the historical information contained in this presentation, this presentation contains (and

More information

Roadshow Presentation

Roadshow Presentation Roadshow Presentation April 2010 Tonbridge Power Inc. The Waterpark Place 20 Bay Street, 11 th Floor Toronto, ON t: 416.850.2150 f: 416.850.1985 1 www.tonbridgepower.com Disclaimer This presentation and

More information

November 5, Re: Tariff Advice No Revisions to Schedule 98, Residential and Small Farm Energy Credit

November 5, Re: Tariff Advice No Revisions to Schedule 98, Residential and Small Farm Energy Credit LISA D. NORDSTROM Lead Counsel lnordstrom@idahopower.com November 5, 2013 Attention: Filing Center Public Utility Commission of Oregon 550 Capitol Street NE, Suite 215 P.O. Box 2148 Salem, Oregon 97308-2148

More information

MTEP16 Futures Development Workshop 1/15/15

MTEP16 Futures Development Workshop 1/15/15 MTEP16 Futures Development Workshop 1/15/15 Overview Objectives MTEP16 proposed futures Uncertainty variables definitions Next steps 2 Objective Ensure MTEP16 Futures are effective and are developed in

More information

SPP s Operating Region

SPP s Operating Region SPP s Operating Region Current 77,366 MW of generating capacity 46,136 MW of peak demand 48,930 miles transmission: 69 kv 12,569 miles 115 kv 10,239 miles 138 kv 9,691 miles 161 kv 5,049 miles 230 kv 3,889

More information

CRR Auction Analysis Report

CRR Auction Analysis Report Report November 21, 2017 Prepared by: MQRI California Independent System Operator The following ISO staff contributed to this report: Danielle Tavel Abhishek Hundiwale Jie Duan Nongchao Guo Jim McClain

More information

WECC Standard PRC-STD Protective Relay and Remedial Action Scheme Misoperation

WECC Standard PRC-STD Protective Relay and Remedial Action Scheme Misoperation A. Introduction 1. Title: Protective Relay and Remedial Action Scheme 2. Number: PRC-STD-003-1 3. Purpose: Regional Reliability Standard to ensure all transmission and generation Protection System s affecting

More information

PNW/Canada to Northern California WECC Regional Planning. Stakeholder Kickoff December 12, 2006

PNW/Canada to Northern California WECC Regional Planning. Stakeholder Kickoff December 12, 2006 PNW/Canada to Northern California WECC Regional Planning Stakeholder Kickoff December 12, 2006 1 Agenda Presenter 11:00 a.m. Introductions Steve Metague 11:15 a.m. Project Manager Presentation Steve Metague

More information

2017 Integrated Resource Plan. Portfolio Development Detail September 8, 2016

2017 Integrated Resource Plan. Portfolio Development Detail September 8, 2016 2017 Integrated Resource Plan Portfolio Development Detail September 8, 2016 1 2017 Portfolio Development Process Vol. III Analysis Core Portfolios (Targeted Resource Classes) Cost and Risk (Broader Range

More information

MEMORANDUM. July 29, Power Committee. Massoud Jourabchi. SUBJECT: Financial Assumptions for the Seventh Power Plan

MEMORANDUM. July 29, Power Committee. Massoud Jourabchi. SUBJECT: Financial Assumptions for the Seventh Power Plan Bill Bradbury Chair Oregon Henry Lorenzen Oregon W. Bill Booth Idaho James A. Yost Idaho Jennifer Anders Vice Chair Montana Pat Smith Montana Tom Karier Washington Phil Rockefeller Washington July 29,

More information

Estimating Capacity Benefits of the AC Transmission Public Policy Projects

Estimating Capacity Benefits of the AC Transmission Public Policy Projects Memorandum TO: NYISO Board of Directors FROM: David B. Patton and Pallas LeeVanSchaick DATE: RE: Estimating Capacity Benefits of the AC Transmission Public Policy Projects A. Introduction In the second

More information

Bank of America Merrill Lynch

Bank of America Merrill Lynch Bank of America Merrill Lynch Texas Mini-Conference Dallas, TX September 27, 2018 Forward-Looking Statements In addition to the historical information contained in this presentation, this presentation

More information

Oregon John A. Kitzhaber, MD, Governor

Oregon John A. Kitzhaber, MD, Governor Oregon John A. Kitzhaber, MD, Governor Public Utility Commission 0 Capitol St NE, Suite Mailing Address: PO Box Salem, OR 0- Consumer Services -00--0 Local: (0) -00 Administrative Services (0) - March,

More information

April 6, 2018 VIA OVERNIGHT MAIL. Sheri Young, Secretary of the Board National Energy Board th Avenue SW Calgary, Alberta T2R 0A8

April 6, 2018 VIA OVERNIGHT MAIL. Sheri Young, Secretary of the Board National Energy Board th Avenue SW Calgary, Alberta T2R 0A8 !! April 6, 2018 VIA OVERNIGHT MAIL Sheri Young, Secretary of the Board National Energy Board 517 10 th Avenue SW Calgary, Alberta T2R 0A8 Re: North American Electric Reliability Corporation Dear Ms. Young:

More information

June 9, Filing of CAISO Rate Schedule No. 92 Powerex EIM Implementation Agreement Docket No. ER

June 9, Filing of CAISO Rate Schedule No. 92 Powerex EIM Implementation Agreement Docket No. ER California Independent System Operator Corporation The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 June 9, 2017 Re: California Independent

More information

WECC Process for Risk-Based Compliance Oversight Inherent Risk Assessment and Compliance Oversight Plan

WECC Process for Risk-Based Compliance Oversight Inherent Risk Assessment and Compliance Oversight Plan WECC Process for Risk-Based Compliance Oversight Inherent Risk Assessment and Compliance Oversight Plan WECC Entity Oversight Effective Date: April 1, 2017 155 North 400 West, Suite 200 Salt Lake City,

More information

Local Market Power Mitigation Enhancements

Local Market Power Mitigation Enhancements Local Market Power Mitigation Enhancements Revised Straw Proposal Stakeholder Web Conference November 28, 2018 10:00 am - 1:00 pm Market Design Policy Agenda Time Topic Presenter 10:00 10:05 Welcome and

More information

Summary of Ratepayer-Funded Electric Efficiency Impacts, Budgets, and Expenditures

Summary of Ratepayer-Funded Electric Efficiency Impacts, Budgets, and Expenditures Summary of Ratepayer-Funded Electric Efficiency Impacts, Budgets, and Expenditures IEE Brief January 2012 Summary of Ratepayer-Funded Electric Efficiency Impacts, Budgets and Expenditures (2010-2011)

More information

Portland General Electric Company Sheet No SCHEDULE 201 QUALIFYING FACILITY 10 MW or LESS AVOIDED COST POWER PURCHASE INFORMATION

Portland General Electric Company Sheet No SCHEDULE 201 QUALIFYING FACILITY 10 MW or LESS AVOIDED COST POWER PURCHASE INFORMATION Portland General Electric Company Sheet No. 201-1 PURPOSE SCHEDULE 201 QUALIFYING FACILITY 10 MW or LESS AVOIDED COST POWER PURCHASE INFORMATION To provide information about Standard Avoided Costs and

More information