1 I hereby certify this to be a true copy of the tabulation of the bids as received and opened. BID OPENING: FRIDAY, September 16,2016 County Engineer \...-/ GrouR 1 - Ke~ Peninsula Highwa~ 1 LUMP SUM Mobilization 2, , , , , , TON Crushed Surfacing Base Course DAY ESC Lead ,000 DOL ErosionlWater Pollution Control LF Beam Guardrail Type 31-9 Ft. Long Post , , , LF Beam Guardrail Type , EACH Beam Guardrail Type 31 Non-Flared Terminal 3, , , , , , EACH Guardrail Reflector Tab LUMP SUM Other Temporary Traffic Control , , HR Other Traffic Control Labor , , , LUMP SUM Traffic Control Supervisor 1, , , , LUMP SUM Utility Coordination , 2, 26 LUMP SUM Trimming and Cleanup 1, , , , ,000 Roadside Cleanup 28 2,000 Minor Change 30 LUMP SUM SPCC Plan Group 1 Total: 31, , , GrouR 2 - Alder Cutoff Road E 1 LUMP SUM Mobilization 6, , , ;-62\.31 10, , TON Select Borrow Incl Haul CY Embankment Compaction TON Crushed Surfacing Base Course , , DAY ESC Lead ,000 DOL ErosionlWater Pollution Control LF Beam Guardrail Type 31-9 Ft Long Post , , , of6
2 Road Safety Program - Guardrail and 218th Avenue EasUCRP 5831 and 5833 Groue 2 - Alder Cutoff Road E Cont EACH Beam Guardrail Type 31 Non-Flared Terminal 3, , , , , , EACH Guardrail Reflector Tab EACH Guardrail Reflector Strip , , , EACH Vactor Post Excavation , , , 21 LUMP SUM Other Temporary Traffic Control 1, 1, , , HR Flaggers , , , HR Other Traffic Control Labor , , , LUMP SUM Traffic Control Supervisor 2, , , , LUMP SUM Utility Coordination 4, , LUMP SUM Trimming and Cleanup 1, , , 4, 27 1,000 DOL Roadside Cleanup 28 2,000 DOL Minor Change 30 LUMP SUM SPCC Plan Group 2 Total: 67, , , Groue 3 - Key Peninsula Hwy E 1 LUMP SUM Mobilization 2, , , , , , TON Crushed Surfacing Base Course DAY ESC Lead ,000 DOL ErosionlWater Pollution Control LF Beam Guardrail Type Ft Long Post , , , EACH Beam Guardrail Type 31 - Non-Flared Terminal 3, , , , , , 14 3 EACH Guardrail Reflector Tab LUMP SUM Other Temporary Traffic Control , , HR Other Traffic Control Labor , , , LUMP SUM Traffic Control Supervisor , , LUMP SUM Utility Coordination , 2, 26 LUMP SUM Trimming and Cleanup 1, , , , ,000 DOL Roadside Cleanup 28 2,000 DOL Minor Change 30 LUMP SUM SPCC Plan Group 3 Total: 26, , , Groue 4 - Waller Road E 1 LUMP SUM Mobilization 7, , , , , , f6
3 Road Safety Program - Guardrail and 218th Avenue East/CRP 5831 and 5833 Group 4 - Waller Road E Cont TON Select Borrow Incl Haul , CY Embankment Compaction TON Crushed Surfacing Base Course DAY ESC Lead ,000 DOL ErosionlWater Pollution Control LF Beam Guardrail Type 31-8 Ft Long Post , , , ,075 LF Beam Guardrail Type Ft Long Post , , , EACH Beam Guardrail Type 31 Non-Flared Terminal 3, , , , , , EACH Guardrail Reflector Tab LUMP SUM Other Temporary Traffic Control 1, 1, 1, , , , HR Flaggers , , , HR Other Traffic Control Labor , , , LUMP SUM Traffic Control Supervisor 3, , , , LUMP SUM Utility Coordination , 2, 26 LUMP SUM Trimming and Cleanup , , , 4, 27 1,000 DOL Roadside Cleanup 28 2,000 DOL Minor Change 29 LUMP SUM FDC Plan , , LUMP SUM SPCC Plan Group 4 Total: 87,14 85, , Group 5 - Rhodes Lake Road E 1 LUMP SUM Mobilization 4, , , , , , TON Crushed Surfacing Base Course , , DAY ESC Lead ,000 DOL ErosionlWater Pollution Control LF Beam Guardrail Type 31-8 Ft Long Post , , , LF Beam Guardrail Type , , , EACH Beam Guardrail Type 31 Non-Flared Terminal 3, , , , , , 14 8 EACH Guardrail Reflector Tab EACH Guardrail Reflector Strip EACH Vactor Post Excavation , , , LUMP SUM Other Temporary Traffic Control 8, , HR Flaggers , , , HR Other Traffic Control Labor , , , LUMP SUM Traffic Control Supervisor 1, , , f6
4 Groue 5 - Rhodes Lake Road E Cont. 25 lump SUM Utility Coordination 6, 6, 26 lump SUM Trimming and Cleanup 1, , , , ,000 DOL Roadside Cleanup 28 2,000 DOL Minor Change 30 lump SUM SPCC Plan Group 5 Total: 50, , , Groue 6 - Orting Kaeowsin H~ E 1 lump SUM Mobilization 3, , , , , , IF Removing Beam Guardrail , , TON Crushed Surfacing Base Course , DAY ESC lead ,000 DOL ErosionlWater Pollution Control 12 4 EACH Beam Guardrail Type 1 Non-Flared Termina 5, 2 3, , , , EACH Guardrail Reflector Tab EACH Guardrail Reflector Strip , , , lump SUM Other Temporary Traffic Control 8, , HR Other Traffic Control labor , , , lump SUM Traffic Control Supervisor 1, , , , lump SUM Utility Coordination , , lump SUM Trimming and Cleanup 3, , ,000 DOL Roadside Cleanup 28 2,000 DOL Minor Change 30 lump SUM SPCC Plan Group 6 Total: 43,30 31, , Groue 7 - Sumner Buckle~ H~ E 1 lump SUM Mobilization 2, 2, 2, , , , IF Removing Beam Guardrail , , TON Crushed Surfacing Base Course , , DAY ESC lead ,000 DOL ErosionlW ater Pollution Control 8 94lF Beam Guardrail Type 31-8 Ft Long Post , , , lF Beam Guardrail Type EACH Beam Guardrail Type 31 Non-Flared Terminal 3, , , , , , 4of6
5 Grou2 7 Sumner Buckle~ HYCl E Cant EACH Guardrail Reflector Tab lump SUM Other Temporary Traffic Control 8, , HR Flaggers , , , HR Other Traffic Control labor , , lump SUM Traffic Control Supervisor , , lump SUM Utility Coordination , , lump SUM Trimming and Cleanup 1, , , , ,000 DOL Roadside Cleanup 28 2,000 DOL Minor Change 30 lump SUM SPCC Plan Group 7 Total: 27, , ,42 GrouR 8 Sehmel Drive NW 1 lump SUM Mobilization , , , , TON Crushed Surfacing Base Course DAY ESC lead ,000 DOL ErosionlWater Pollution Control IF Beam Guardrail Type 31-9 Ft Long Post , , EACH Beam Guardrail Type 31 Non-Flared Terminal 3, , , , , EACH Guardrail Reflector Tab EACH Vactor Post Excavation , , , 21 lump SUM Other Temporary Traffic Control 1, 1, 1, , , , HR Other Traffic Control labor , , , lump SUM Traffic Control Supervisor , , lump SUM Utility Coordination 7, , lump SUM Trimming and Cleanup 1, , , ,000 DOL Roadside Cleanup 28 2,000 DOL Minor Change 30 lump SUM SPCC Plan Group 8 Total: 36, , , GrouR 9-218th Avenue E 1 LUMP SUM Mobilization , , EACH Guardrail Reflector Tab EACH Guardrail Reflector Strip , , , t6
6 Engineer's Estimate ITEM UNIT NO. QUANTITY UNIT ITEM PRICE AMOUNT Group 9-218th Avenue E Cont. 21 LUMP SUM Other Temporary Traffic Control HR Flaggers HR Other Traffic Control Labor LUMP SUM Traffic Control Supervisor LUMP SUM Trimming and Cleanup 27 1,000 DOL Roadside Cleanup DOL Minor Change 30 LUMP SUM SPCC Plan Group 9 Total: 8, (1) Peterson Brothers Inc E Valley Hwy Sumner, WA UNIT PRICE AMOUNT , (2) Dirt & Aggregate Interchange Inc NE Sandy Blvd Fairview, OR UNIT PRICE AMOUNT 4, , , , , 2, 21, Group th Avenue E 1 LUMP SUM 5 8 TON 6 5 DAY 7 1,000 DOL 17 LUMP SUM 18 5,000 DOL 19 LUMP SUM SF 21 LUMP SUM HR HR 24 LUMP SUM 25 LUMP SUM 26 LUMP SUM 27 1,000 DOL 28 2,000 DOL 30 LUMP SUM Mobilization Crushed Surface Base Course ESC Lead ErosionJW ater Pollution Control Dynamic Warning Sign System Electrical Service Connection Fee Permanent Signing Construction Signs Class A Other Temporary Traffic Control Flaggers Other Traffic Control Labor Traffic Control Supervisor Utility Coordination Trimming and Cleanup Roadside Cleanup Minor Change SPCC Plan Group 10 Total: PROJECT TOTAL: 8, , , 8, , , , , , 90, , , , , , , , , , , , , , , , , , , , , , , 7, , , , , , , , , , , , , f6
NE WEST KINGSTON ROAD CULVERT REPLACEMENT
NE WEST KINGSTON ROAD CULVERT REPLACEMENT KITSAP COUNTY MILE POST 1.28 TO 1.44 PUBLIC WORKS BID TABULATION SECTION PREPARED: BLB LENGTH: 0.16 Mile REVISED: DATE: March 7, 2017 SCHEDULE A - ROADWAY IMPROVEMENTS
More informationCITY OF NEWCASTLE COUNCIL MEETING CITY HALL COUNCIL CHAMBERS NEWCASTLE WAY, SUITE 200 DECEMBER 18, CALL TO ORDER
CITY OF NEWCASTLE COUNCIL MEETING CITY HALL COUNCIL CHAMBERS 12835 NEWCASTLE WAY, SUITE 200 DECEMBER 18, 2012 SPECIAL MEETING 12:00 P.M. 1. CALL TO ORDER 2. GENERAL BUSINESS a. AB 12 077 Resolution Authorizing
More informationI. J~ /.. RrECE~VfEfD 9J7J:. 13~ 7b 1/1~ COUNCIL. ~ 1-j r-(lk. 1 1-'> lft:; WHATCOM COUNTY COUNCIL AGENDA BILL
WHATCOM COUNTY COUNCIL AGENDA BILL NO. 2016-248 CLEARANCES Initial Date Date Received in Council Office AxendaDate Assixned to: Originator: James Karcher, P.E. 9J7J:. 1 1-'> lft:; RrECE~VfEfD Division
More informationPART ONE BIDDING REQUIREMENTS
PART ONE BIDDING REQUIREMENTS 1 NOTICE TO CONTRACTORS Office of Ferry County Public Works 350 East Delaware # 8 Republic, WA 99166-9747 Sealed bids will be received by the Board of County Commissioners
More informationBID TAB PROJECT: REPLACEMENT OF ALBON ROAD BRIDGE NO. 606, PID NO BID OPEN: MAY 9, 2012 COMPLETION DATE: NOVEMBER 16, 2012
Page 1 BID TAB PROJECT: REPLACEMENT OF ALBON ROAD BRIDGE NO. 606, PID NO. 87786 BID OPEN: MAY 9, 2012 COMPLETION DATE: NOVEMBER 16, 2012 ROADWAY 1 201 CLEARING AND GRUBBING 1 LUMP $4,500.00 $4,500.00 $10,016.00
More informationCrushed Surfacing Base Course, per ton. Pages 8-8, Special Provisions Section , Materials. This Section is supplemented with the following:
Crushed Surfacing Base Course, per ton. The unit contract price per ton for Crushed Surfacing Top Course and Crushed Surfacing Base Course shall include the cost for all labor, materials, equipment and
More informationSUTTER BUTTER FLOOD CONTROL AGENCY FEATHER RIVER WEST LEVEE PROJECT PROJECT C, CONTRACT NO C BID TABULATION
Bid Schedule A - Feather River West Levee Project C Improvements No. Item Description Quantity Unit Nordic/Magnus Pacific JV Engineer's Estimate Unit Price Total Price Unit Price Total Price A1 Injury
More informationSubject: Addendum No. 1 Project #C CCE Parking Lot Replacement Phase 2 Robert Bishop Drive 4380 Richmond Road, Highland Hills, Ohio 44122
Addendum No. 1 Page One To: From: All Plan Holders of Record CT Consultants, Inc. Gene E. Arters, P.E. on behalf of Cuyahoga Community College Subject: Addendum No. 1 Project #C20166009 CCE Parking Lot
More informationCONTRACTOR'S ESTIMATE PACKAGE REPORT DATE: 12/07/18 HIGHWAY: SH 103 COUNTY: 10/03/2017 ESTIMATE PAID: AWARD DATE: 10/26/2017 ESTIMATE PERIOD:
13,138.91 CONTRACTOR'S ESTIMATE PACKAGE REPORT DATE: 12/07/18 90 19.00 CONTRACT ID: 033606028 PROJECT: STP 2018(156)HES CONTRACT: 10173013 AWARD : $597,891.99 PROJECTED : $600,891.99 ADJ. PROJECTED : $614,030.90
More informationFailure to acknowledge all addenda in the BID may cause rejection of the BID. See Instructions to Bidders.
Addendum #1 409 22nd Ave So PO Box 298 Brookings, SD 57006 Toll Free 1-855-323-6342 www.bannerassociates.com Project: Viborg Utility Improvements - 2017 Bid Date: 11:00 A.M., Local Time, March 15, 2017
More informationTOTAL QUANTITY UNIT COST UNIT
BASE BID DIVISION 1 - GENERAL 1 1070-206-A-0 TRAFFIC CONTROL LS 1 $ 10,000 $ 10,000 $3,000.00 $3,000.00 $5,600.00 $5,600.00 2 2010-108-B-0 CLEARING AND GRUBBING AC 5 $ 9,000 $ 45,000 $7,192.50 $35,962.50
More informationTABLE OF CONTENTS. Table of Contents 3 List of Drawings 1. Procurement Requirements Advertisement for Bids 2
TABLE OF CONTENTS General Requirements Total Pages Table of Contents 3 List of Drawings 1 Procurement Requirements Advertisement for Bids 2 Instruction for Procurement Instructions to Bidders 8 Procurement
More informationGladwin County Road Commission 2016 Hot Mix Asphalt (HMA) Paving. Page 1 of 5
Page 1 of 5 SEALED PROPOSALS (BIDS) WILL BE RECEIVED UNTIL 9:30 A.M., EST, WEDNESDAY, March 9, 2016 Board of County Road Commissioners of the County of Gladwin, 301 South State Street, Gladwin, Michigan
More informationBID TABULATION JAMES STREET TRUNK SEWER IMPROVEMENTS CORALVILLE, IOWA
Bid No. 1 Bid No. 2 Foley Construction Company JB Holland Construction, Inc. 5401 Victoria Avenue 2092 Hwy 9 W Project: Construct the James Street Davenport, IA 52807 Decorah, IA 52101 1.1 Construction
More informationCONTRACT TIME DETERMINATION
CONTRACT TIME DETERMINATION MISSOURI DEPARTMENT OF TRANSPORTATION March 15, 2004 DEFINITIONS Calendar Day: Any day shown on the calendar beginning and ending at midnight. Working Day: A calendar day during
More informationAVERAGE OF BID ITEMS ENGINEERS ESTIMATE
ROADWAY 1 Mobilization 1 LS $ 990,048.50 $ 80,000.00 $ 880,000.00 $ 880,000.00 $ 950,000.00 $ 950,000.00 $ 967,510.00 $ 967,510.00 $ 1,162,684.00 $ 1,162,684.00 2 Maintenance of Traffic ( incl. Pedestrian
More informationSunset Street West Sidewalk Projects Opinion of Anticipated Construction Costs March 12, 2012 Project Summary. Project List
Project Summary Project List Anticipated Construction Cost 1 Sunset/Benton Intersection: Curb Ramp and Sight Distance Improvements $ 18,700 2 Sunset/Oakcrest Intersection: West Right-of-Way Drainage Improvements
More informationPreliminary Budget Cost Estimate-Raft Island RIIA Roads 26952 SY Construction Items Budget Preliminary Temporary Erosion Control/Miscellaneous Work $ 18,500.00 Traffic Control $ 10,000.00 Pulverizing $
More informationDORAN STREET AND BROADWAY/BRAZIL SAFETY AND ACCESS PROJECT PROJECT STUDY REPORT (EQUIVALENT) Appendix I Cost Estimates
DORAN STREET AND BROADWAY/BRAZIL SAFETY AND ACCESS PROJECT PROJECT STUDY REPORT (EQUIVALENT) Appendix I Cost Estimates (Alternative 1 - Doran Overpass) PROJECT DESCRIPTION Limits Doran Street from Commercial
More informationREPLACEMENT OF MERCER COUNTY BRIDGE
ADDENDUM NO. ONE Notice is hereby given that on April 26, 2019 at 11:00 AM (Prevailing time), sealed proposals will be opened and read in public by the Purchasing Department in the Mercer County McDade
More informationDepartment of Public Works Engineering
Department of Public Works Engineering DATE: January 27, 2016 TO: Honorable Chairman and Public Utility Authority Members FROM: Cynthia M. Herrera, MMC, Interim Executive Director/ City Clerk BY: Nathan
More informationADVERTISEMENT FOR BIDS WATER SERVICE LINE REPAIR & METER BOX REPLACEMENT CITY / COUNTY UTILITIES
ADVERTISEMENT FOR BIDS WATER SERVICE LINE REPAIR & METER BOX REPLACEMENT CITY / COUNTY UTILITIES Pursuant to N.C.G.S. 143-131, sealed bid proposals endorsed Water Line & Meter Box Contract FB19188 will
More informationBIDDER'S PROPOSAL TO THE HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
Bidders submitting proposals shall be very careful to follow all requirements in connection therewith. A checklist has been attached for guidance in complying with all phases of the bid process and project.
More information$4, CONTRACTOR'S ESTIMATE PACKAGE REPORT DATE: 08/08/17 -73, FM0317 DISTRICT NAME: Tyler COUNTY: PROJECT: RMC
-73,034.10 CONTRACTOR'S ESTIMATE PACKAGE REPORT DATE: 08/08/17 56 5.00 CONTRACT ID: 629625001 PROJECT: RMC - 629625001 CONTRACT: 02164011 AWARD : $446,216.00 PROJECTED : $446,222.00 ADJ. PROJECTED : $373,187.90
More informationCONTRACTOR'S ESTIMATE PACKAGE REPORT DATE: 09/08/15
68,460.45 CONTRACTOR'S ESTIMATE PACKAGE REPORT DATE: 09/08/15 101 28.00 CONTRACT ID: 207501053 PROJECT: NH 2013(466) CONTRACT: 03133207 AWARD : $3,794,106.27 PROJECTED : $3,958,638.27 ADJ. PROJECTED :
More informationNorth Baker Ave - City Limits to 23rd St NE CRP 949 PROPOSAL
North Baker Ave. - City Limits to 23rd St. NE Bid Documents BD-1 To the Board of County Commissioners Douglas County, Washington Gentlemen: North Baker Ave - City Limits to 23rd St NE CRP 949 PROPOSAL
More informationADDITIONS, MODIFICATIONS, AND/OR DELETIONS TO THE PROPOSAL
II. ADDITIONS, MODIFICATIONS, AND/OR DELETIONS TO THE PROPOSAL ITEM NO. 1: Page P-1, Proposal DELETE the Proposal (pages P-1 through P-9) in its entirety and REPLACE with the attached Proposal (pages P-1R
More informationNew Jersey Department of Transportation DATE : 06/22/10 PAGE : TABULATION OF BIDS
PAGE : 107-1 CONTRACT TIME : 01/24/11 COMPLETION DATE CONTRACT DESCRIPTION : URBAN PROJECT(S) : FS-0022(105) ROUTE 37 FROM ROUTE 70 TO GARDEN STATE PARKWAY RESURFACING CONTRACT NO. 000103080 TOWNSHIP OF
More informationMEETING NOTICE. City Council will be held at 5:30 p.m. in the City Council Chambers. located at 305 Third Avenue East.
CITY OF TWIN FALLS, IDAHO MEETING NOTICE * * * * The Monday, November 19, 2012, regular meeting of the Twin Falls City Council will be held at 5:30 p.m. in the City Council Chambers located at 305 Third
More informationCONTRACTOR'S ESTIMATE PACKAGE REPORT DATE: 08/10/18 HIGHWAY: SH 123 COUNTY: 11/03/2016 ESTIMATE PAID: AWARD DATE: 11/17/2016 ESTIMATE PERIOD:
10,070.68 CONTRACTOR'S ESTIMATE PACKAGE REPORT DATE: 08/10/18 37 5.00 CONTRACT ID: 036605044 PROJECT: STP 2017(285) CONTRACT: 11163011 AWARD : $611,559.93 PROJECTED : $611,559.93 ADJ. PROJECTED : $621,630.61
More informationOPTION A: 2 BITUMINOUS PAVING WITH SHOULDERS OPTION B: SCRATCH COURSE BITUMINOUS PAVING WITHOUT SHOULDERS
SHIAWASSEE COUNTY ROAD COMMISSION PROPOSAL FOR 2018 BITUMINOUS PAVING PROGRAM JUDDVILLE ROAD FROM CLINTON COUNTY LINE (MERIDIAN ROAD) TO GENESSEE COUNTY LINE (M-13) IN SHIAWASSEE COUNTY + / - 22.34 MILES
More informationJANUARY 18, Reference Specifications, Attachment to Form 96 (BID FORM), Bid Proposal: Respectfully submitted,
ADDENDUM NO. 3 TO THE PLANS AND SPECIFICATIONS for STREET AND STORM SEWER IMPROVEMENTS ON HANCOCK AND WASHINGTON STREETS for the FRENCH LICK REDEVELOPMENT COMMISSION ORANGE COUNTY, INDIANA MEI PROJECT
More informationSolicitation No. B RA 2010 Concrete Placement Work Order Construction Contract Package No. 2 PROPOSAL. PROPOSAL OF, a corporation a
Solicitation No. B-09-071-RA 2010 Concrete Placement Work Order Construction Contract Package No. 2 PROPOSAL PROPOSAL OF, a corporation a partnership consisting of and an individual doing business as TO
More informationCONTRACTOR'S ESTIMATE PACKAGE REPORT DATE: 02/09/18 HIGHWAY: FM 1988 COUNTY: 04/07/2015 ESTIMATE PAID: AWARD DATE: 04/30/2015 ESTIMATE PERIOD:
0.00 CONTRACTOR'S ESTIMATE PACKAGE REPORT DATE: 02/09/18 217 10.00 CONTRACT ID: 187601030 PROJECT: BR 1502(017) CONTRACT: 04153032 AWARD : 3,278,223.27 PROJECTED : 3,289,223.27 ADJ. PROJECTED : 3,289,223.27
More informationBID TABULATION BID REQUEST NO
BID TABULATION BID REQUEST NO. 13-1046 1 LOWEST RESPONSIVE BIDDER Dakota Contracting Bidder: Corporation D & G Concrete Bidder: Construction, Inc. Carl V. Carlson Bidder: Company Address: 431 NORTH PHILLIPS
More informationMainelli Wagner & Associates, Inc.
www.mwaeng.com Mainelli Wagner & Associates, Inc. 6920 Van Dorn Street, Suite A, Lincoln, NE 68506 Phone: (402) 421-1717 Fax: (402) 421-6061 February 25, 2019 To Whom It May Concern: The Platte County
More informationKITSAP COUNTY DEPARTMENT OF ADMINISTRATIVE SERVICES PURCHASING OFFICE INFORMAL BID TREE SERVICES ROSTER
KITSAP COUNTY DEPARTMENT OF ADMINISTRATIVE SERVICES PURCHASING OFFICE INFORMAL BID 2018-119 TREE SERVICES ROSTER RESPONSE DEADLINE: Thursday, April 19, 2018, 3:00 p.m. The Kitsap County Purchasing Office
More informationBERRIEN COUNTY ROAD DEPARTMENT PROPOSAL AND SPECIFICATION FOR WEE-CHIK ROAD GUARDRAIL
PROPOSAL AND SPECIFICATION FOR WEE-CHIK ROAD GUARDRAIL 1 PROGRESS CLAUSE: Start work within ten (10) days after receiving notice of award of contract or on the date agreed upon by the Engineer. In no case
More informationCONTRACTOR'S ESTIMATE PACKAGE REPORT DATE: 01/09/19
CONTRACTOR'S ESTIMATE PACKAGE REPORT DATE: 01/09/19 240 0.00 CONTRACT ID: 090249068 PROJECT: STP 2014(119)TE CONTRACT: 08163051 AWARD AMOUNT: $2,150,084.20 PROJECTED AMOUNT: $2,344,277.78 ADJ. PROJECTED
More information2015 Financial Assurance 8/6/2015 Estimate Form (with pre-plat construction)
2015 Financial Assurance 8/6/2015 Estimate Form (with pre-plat construction) Project Information The Glen at Widefield Filing No. 9 PDD File: SF-185 9/25/2018 Project Name Section 1 - Grading and Erosion
More informationINVITATION TO BID. CONTRACT PERIOD: The contract shall cover the County s needs for the period of July 21, 2015 through July 20, 2015.
INVITATION TO BID The Etowah County Commission will, on June 22, 2015 in the Commission Chambers, 1st floor, 800 Forrest Avenue, Gadsden, AL, receive competitive bids on SUPERPAVE BITUMINOUS CONCRETE ASPHALT
More informationOpinion of Probable Cost
Appendix E Opinion of Probable Cost 01054/8410233/14/Rohner_Alt_Analysis_Report Rohner Creek Flood Control, Habitat and Seismic Improvement Project Alternatives Analysis Cost Alternative 1: Improved Channel
More informationCONTRACTOR'S ESTIMATE PACKAGE REPORT DATE: 06/07/17 02/10/2016 ESTIMATE PAID: AWARD DATE: 02/25/2016 ESTIMATE PERIOD: 10/31/2016 % TIME USED:
143,230.65 CONTRACTOR'S ESTIMATE PACKAGE REPORT DATE: 06/07/17 77 4.00 CONTRACT ID: 041902041 PROJECT: STP 2016(746) CONTRACT: 02163223 AWARD : $3,653,777.19 PROJECTED : $3,823,809.19 ADJ. PROJECTED :
More informationBERRIEN COUNTY ROAD DEPARTMENT PROPOSAL AND SPECIFICATION FOR
BERRIEN COUNTY ROAD DEPARTMENT PROPOSAL AND SPECIFICATION FOR 1 BERRIEN COUNTY ROAD DEPARTMENT PROGRESS CLAUSE: Start work within ten (10) days after receiving notice of award of contract or on the date
More informationOKLAHOMA TURNPIKE AUTHORITY
PART A - BASE BID 106 QUALITY CONTROL & ACCEPTANCE LSUM 1.00 $ 70,000.00 $70,000.00 $ 15,735.00 $ 15,735.00 $ 60,000.00 $ 60,000.00 $ 25,000.00 $ 25,000.00 $ 20,000.00 $ 20,000.00 201(A) CLEARING & GRUBBING
More informationCONTRACTOR'S ESTIMATE PACKAGE REPORT DATE: 10/10/18 HIGHWAY: US 82 COUNTY: 02/01/2018 ESTIMATE PAID: AWARD DATE: 02/22/2018 ESTIMATE PERIOD:
CONTRACTOR'S ESTIMATE PACKAGE REPORT DATE: 10/10/18 45 CONTRACT ID: 004501061 PROJECT: NH 2018(556) CONTRACT: 02183025 AWARD : $2,124,211.95 PROJECTED : $2,130,211.95 ADJ. PROJECTED : $2,130,211.95 CONTRACT:
More informationNew Jersey Department of Transportation DATE : 11/16/10 PAGE : TABULATION OF BIDS
PAGE : 131-1 CONTRACT TIME : 11/30/11 COMPLETION DATE CONTRACT DESCRIPTION : URBAN PROJECT(S) : STP-5042(107) ROUTE 129 RESURFACING FROM ROUTE 1 TO LAMBERTON ROAD CONNECTOR CITY OF TRENTON, TOWNSHIP OF
More informationCITY OF TAMPA ADDENDUM 2. April 18, 2018
CITY OF TAMPA Bob Buckhorn, Mayor CONTRACT ADMINISTRATION DEPARTMENT Michael W. Chucran, Director ADDENDUM 2 April 18, 2018 Contract 17-C-00021; Citywide Water Meter Bidders on the above referenced project
More informationMainelli Wagner & Associates, Inc.
www.mwaeng.com Mainelli Wagner & Associates, Inc. 6920 Van Dorn Street, Suite A, Lincoln, NE 68506 Phone: (402) 421-1717 Fax: (402) 421-6061 July 11, 2018 To Whom It May Concern: The Burt County Board
More informationManistee County Road Commission Bid Forms and Requirements for Manistee County 2019 Local County-wide HMA Wedging and Chip Sealing for Various Roads
Page 1 of 4 SEALED PROPOSALS (BIDS) WILL BE RECEIVED UNTIL 3:00 PM, EDT, MONDAY, FEBRUARY 4, 2019 Board of County Road Commissioners of the County of Manistee, 8946 Chippewa Highway, Manistee, Michigan
More informationFor Reference Only - Not for the Purpose of Bidding BP-1. Azucena Street 30-Inch Sewer Project Job No Solicitation No.
Job 11-4518 Solicitation B-12-059-DD PROPOSAL of BID PROPOSAL, a corporation a partnership consisting of an individual doing business as TO THE SAN ANTONIO WATER STEM: Pursuant to Instructions Invitation
More informationActive Construction RV Associates Scarsella JR Hayes
CITY OF PORT ORCHARD PUBLIC WORKS DEPARTMENT TREMONT STREET IMPROVEMENTS SR 16 to Port Orchard Boulevard Opening: 6/6/2017 Fed Aid Proj No: STPUS-6610(004) $ 12,779,179.17 $ 12,855,082.55 $ 12,901,887.92
More informationPART A ROADWAY - BASE BID
May 10, 2016 HEB-MC-61 PART A ROADWAY - BASE BID 202(A) - UNCLASSIFIED EXCAVATION - CY 34,946.00 $ 6.00 209,676.00 $ 7.98 $ 278,869.08 205(A) - TYPE A-SALVAGED TOPSOIL - LSUM 1.00 $ 22,500.00 $ 22,500.00
More informationCITY ENGINEER'S ESTIMATE ITEM DESCRIPTION UNIT QTY. UNIT PRICE ITEM TOTAL UNIT PRICE ITEM TOTAL UNIT PRICE ITEM TOTAL REMOVALS
1 2 3 4 5 6 MOBILIZATION per the General Requirements, Sections 01292 and 01721 ALLOWANCE for Differing Site Condition per the General Requirements, Sections 01212 and 01253 ALLOWANCE for Participating
More informationCONTRACTOR'S ESTIMATE PACKAGE REPORT DATE: 09/08/17 HIGHWAY: SH 29 COUNTY: 01/06/2016 ESTIMATE PAID: AWARD DATE: 01/28/2016 ESTIMATE PERIOD:
0.00 CONTRACTOR'S ESTIMATE PACKAGE REPORT DATE: 09/08/17 31 CONTRACT ID: 033702041 PROJECT: STP 2016(576) CONTRACT: 01163208 AWARD : $1,499,000.00 PROJECTED : $1,520,990.00 ADJ. PROJECTED : $1,520,990.00
More informationBERRIEN COUNTY ROAD DEPARTMENT PROPOSAL AND SPECIFICATION FOR AGGREGATE BASE COURSE MILES
BERRIEN COUNTY ROAD DEPARTMENT PROPOSAL AND SPECIFICATION FOR AGGREGATE BASE COURSE 19.62 MILES 1 BERRIEN COUNTY ROAD DEPARTMENT GENERAL SPECIFICATIONS Except as hereinafter provided by Supplemental Specifications
More informationBID TABULATION PAGE 1 OF 6
BID TABULATION PAGE 1 OF 6 BID PRE-BID ESTIMATE R.G. Huston Company, Inc. Kopplin & Kinas Co., Inc. Cottage Grove, WI Green Lake, WI NO. DESCRIPTION OF WORK QUANT. UNITS UNIT PRICE AMOUNT UNIT PRICE AMOUNT
More informationBERRIEN COUNTY ROAD COMMISSION PROPOSAL AND SPECIFICATION FOR COMMUNITY HALL ROAD GUARDRAIL NEW BUFFALO TOWNSHIP
PROPOSAL AND SPECIFICATION FOR COMMUNITY HALL ROAD GUARDRAIL NEW BUFFALO TOWNSHIP BOARD OF COUNTY ROAD COMMISSIONERS OF THE COUNTY OF BERRIEN 2860 EAST NAPIER AVENUE BENTON HARBOR, MI 49022 1 NOTICE TO
More informationPROJECT NO PID BEL TE21-G990(217) TYPE: SLIDE REPAIR LETTING: 06/07/01 COMPLETION DATE: 09/30/02
AWARDED PROJECT PROJECT NO. 016002 PID. 19109 BEL-7-3.68 TE21-G990(217) TYPE: SLIDE REPAIR LETTING: 06/07/01 COMPLETION DATE: 09/30/02 OHIO DEPARTMENT OF TRANSPORTATION GORDON PROCTOR, DIRECTOR CONTRACT
More informationBID PROPOSAL. PROPOSAL OF, a corporation, a partnership consisting of. an individual doing business as
Description 103 REMOVE, STORE AND REINSTALL EXISTING RETAINING WALL 107.1 EMBANKMENT (FINAL)(DENS CONT)(TY B) 203.1 TACK COAT BID PROPOSAL PROPOSAL OF, a corporation, a partnership consisting of an individual
More informationCANTON COMMUNITY REQUEST FOR BOARD ACTION
CANTON COMMUNITY REQUEST FOR BOARD ACTION MEETING DATE: March 22, 2016 AGENDA ITEM #G-10 ITEM: Consider Approval of a Budget Amendment & Award of a Contract Asphalt Repairs to Hutch Paving, Inc. the Wayne
More informationCONTRACTOR'S ESTIMATE PACKAGE REPORT DATE: 11/09/16 HIGHWAY: COUNTY: 04/07/2015 ESTIMATE PAID: AWARD DATE: 04/30/2015 ESTIMATE PERIOD:
-18,600.75 CONTRACTOR'S ESTIMATE PACKAGE REPORT DATE: 11/09/16 CONTRACT ID: 628405001 PROJECT: RMC - 628405001 CONTRACT: 04154013 AWARD : $597,778.20 PROJECTED : $597,783.20 ADJ. PROJECTED : $579,182.45
More informationTHIS SECTION INTENTIONALLY LEFT BLANK
SUPPLEMENTAL INFORMATION ADDENDUM NO. 2 PROJECT: ITB No. 18-010 2018 Road Resurfacing CONTACT: Fiona Charleton, Purchasing Agent 912-754-2159 fcharleton@effinghamcounty.org DATE ISSUED: May 31, 2018 ITB
More informationRock Chalk Park - Infrastructure Report. July 2013
Rock Chalk Park Infrastructure Report July 2013 The following report is the first monthly report for the construction of infrastructure at Rock Chalk Park. The format follows the sections outlined in the
More informationPROPOSAL AND SPECIFICATIONS FOR HIGHWAY CONSTRUCTION COUNTY LOCAL ROAD SYSTEM
NAME OF CONTRACTOR PROPOSAL AND SPECIFICATIONS FOR HIGHWAY CONSTRUCTION COUNTY LOCAL ROAD SYSTEM PROJECT NO. 4907 1.08 miles of roadway reconstruction including clearing, grade establishment, sand subbase,
More informationRegular. NECESSARY RESOURCES/IMPACTS (OTHER) n/a. Fiscal Impact
CITY COUNCIL AGENDA Meeting Date: 09/16/2013 TITLE: Hatley Way Sidewalk Improvements 2013 Bid Award Responsible Staff: Ron Crumley Backup Material: Backup material attached Digital Presentation: Yes Other
More informationADDENDUM No. 1 January 29, Paving Program Village of Milford
ADDENDUM No. 1 2018 Paving Program Village of Milford The following changes, additions, and/or clarifications to the Contract Documents shall be incorporated in said documents and shall be allowed for
More informationCONTRACTOR'S ESTIMATE PACKAGE REPORT DATE: 12/11/17 HIGHWAY: FM 958 COUNTY: 06/08/2016 ESTIMATE PAID: AWARD DATE: 07/13/2016 ESTIMATE PERIOD:
CONTRACTOR'S ESTIMATE PACKAGE REPORT DATE: 12/11/17 166 CONTRACT ID: 100802018 PROJECT: C 1008-2-18 CONTRACT: 06163219 AWARD : $3,498,600.69 PROJECTED : $3,564,104.69 ADJ. PROJECTED : $3,564,104.69 CONTRACT:
More informationReviax Constracting Corp. DeSantis Construction
Denise Piszkowski, Q.P.A., Purchasing Agent Bid Results for: 2016-B08 Reconstrucion of Preston Drive Submitted By: JTG Construction Black Rock Enterprises Top Line Construction Reviax Constracting Corp.
More informationSEQ & TABULATIONS with MULTIPLE SPs/FUNDING TYPES. December
SEQ & TABULATIONS with MULTIPLE SPs/FUNDING TYPES December 2017-1 Statement of Estimated Quantities (SEQ) Quantities are typically rounded to the nearest whole number. If decimals must be used only go
More informationSpecifications and Bid Forms for. Riprap at Bridge Berm Structure # rd Street, Yankton South Dakota, Yankton County,
Specifications and Bid Forms for Riprap at Bridge Berm Structure #68-134-120 44138 303 rd Street, Yankton South Dakota, Yankton County, 57078 For Yankton County Highway Department 3302 W City Limits Road
More informationCONTRACTOR'S ESTIMATE PACKAGE REPORT DATE: 09/10/18
211,476.00 CONTRACTOR'S ESTIMATE PACKAGE REPORT DATE: 09/10/18 112 27.00 CONTRACT ID: 027104091 PROJECT: NH 2016(724) CONTRACT: 02163035 AWARD AMOUNT: $4,962,242.32 PROJECTED AMOUNT: $4,962,249.32 ADJ.
More information2018 Road Improvements Engineer's Project Number: LK 01 Bid Deadline: May 1, 2018 at 2:00 p.m. local time
TABULATION PAGE 1 OF 6 PRE- ESTIMATE Pitlik and Wick, Inc. CONTRACT A - BASE Highway X (Friedle Road to Dam Road) A1.1 Single Layer Chip Seal 75,100 sq. yds. $ 2.50 $ 187,750.00 $ 1.60 $ 120,160.00 $ 1.19
More informationPART II - Prospect Street 37. 8" Ductile Iron CL52 Water Main 614 lin. ft. $ $ 49, $ $ 43, $ $ 46,050.
BID TABULATION PAGE 1 OF 6 Engineer's Project Number: RI 124 Bid Deadline: Changed via addendum to July 2, 2018 at 2:00 p.m. local time BID PRE-BID ESTIMATE Kruczek Construction, Inc. Musson Bros., Inc.
More informationBoth bids are substantially higher than the engineer s estimate of $362, The attached Bid Abstract shows the bid details.
STAFF REPORT MEETING DATE: September 12, 2017 TO: FROM: City Council David Dammuller, Senior Engineer Chris Blunk, Deputy Public Works Director 922 Machin Avenue Novato, CA 94945 415/ 899-8900 FAX 415/
More informationBid No.: PO Box Cone Rd Asphalt Ave th Ave. E. Dunedin, FL Tampa, FL Tampa, FL Palmetto, FL 34221
Bid : 7379 GENERAL 1 2 3 4 @ unit $ total $ @ unit $ total $ @ unit $ total $ @ unit $ total $ G-1.1 Mobilization 1 LS $ 450,000.00 $ 450,000.00 $ 720,000.00 $ 720,000.00 $ 750,000.00 $ 750,000.00 $ 530,000.00
More informationITB-PW-U Matanzas Woods Parkway Reclaimed Water Main Construction Phase 2
Page 1 of 16 ITB-PW-U-15-02 Matanzas Woods Parkway Reclaimed Water Main Construction Phase 2 ISSUE DATE: January 7, 2015 DUE DATE: January 15, 2015 at 2:00 p.m. SUBJECT: Miscellaneous Changes INTENT: This
More informationCONTRACTOR'S ESTIMATE PACKAGE REPORT DATE: 01/10/17
-33,427.31 CONTRACTOR'S ESTIMATE PACKAGE REPORT DATE: 01/10/17 78 CONTRACT ID: 017605175 PROJECT: NH 2014(292) CONTRACT: 12133220 AWARD AMOUNT: $1,316,346.55 PROJECTED AMOUNT: $1,319,346.55 ADJ. PROJECTED
More informationINSTRUCTIONS TO BIDDERS
1.0 DEFINITIONS. Terms used in these Instructions to Bidders and the Notice Inviting Bids have the meanings assigned to them in the General Conditions, 007000. The term "Bidder" means one who submits a
More informationBERRIEN COUNTY ROAD COMMISSION PROPOSAL AND SPECIFICATION FOR AGGREGATE BASE COURSE 6.75 MILES IN BERRIEN COUNTY
BERRIEN COUNTY ROAD COMMISSION PROPOSAL AND SPECIFICATION FOR AGGREGATE BASE COURSE 6.75 MILES IN BERRIEN COUNTY BOARD OF COUNTY ROAD COMMISSIONERS OF THE COUNTY OF BERRIEN 2860 EAST NAPIER AVENUE BENTON
More informationPRELIMINARY DESIGN OF AIRFIELD COMPONENTS (25%) ESTIMATE OF PROBABLE CONSTRUCTION COST
PRELIMINARY DESIGN OF AIRFIELD COMPONENTS (25%) ESTIMATE OF PROBABLE CONSTRUCTION COST Table of Contents 1. Introduction...2 2. Scope of Estimate...2 3. Subpackage Breakout....2 4. Assumptions Used in
More information2012 WATER & SEWER CONSTRUCTION CONTRACT, PACKAGE IV SAWS WATER JOB. NO /SAWS SEWER JOB NO SOLICITATION #B DD BID PROPOSAL
BID PROPOSAL PROPOSAL OF, a Corporation organized and existing under the laws of the State of, a Partnership consisting of, an Individual doing business as. Enclosed with this bid are (1) Bid Bond, and
More informationREQUEST FOR PROPOSAL. Concrete Work at Grand Ravines County Park
REQUEST FOR PROPOSAL Concrete Work at Grand Ravines County Park July 13, 2018 The Ottawa County Parks and Recreation Commission (OCPRC) is seeking proposals for construction of a concrete stairs and pavement
More informationTabulation of Bids. Counties: ROUTE 94 BLACK CREEK TRIBUTARY CULVERT REPLACEMENT
Page 1 of 20 16 SSSEX ROTE 94 BLACK CREEK TRIBTARY CLVERT REPLACEMENT CONSTRCTION CORP INC. (2) KONKS CORPORATION (3) NORTHEAST REMSCO CONSTRCTION INC Quantity and nits nit Price nit Price nit Price 0001
More informationCECIL COUNTY, MARYLAND. ADDENDUM #3 Bid 18-14: Bohemia Church Road Culvert Replacements XCE1073, XCE1074 & XCE1075
Office of the County Executive Alan J. McCarthy County Executive Department of Finance Purchasing Division Ken Jackson Purchasing/Fleet/Leasing Mgr. Alfred C. Wein, Jr. Purchasing Office Director of Administration
More informationPAYMENT PROVISIONS CONTRACT ADMINISTRATION MANUAL
Fund Encumbrances When a Contract has been officially approved, the funds to cover the Contract amount have been encumbered. This encumbrance is a legal process governed by State laws to ensure money has
More informationOKLAHOMA TURNPIKE AUTHORITY
PART A - BASE BID PART A - BASE BID 106 QUALITY CONTROL & ACCEPTANCE LSUM 1.00 $ 40,000.00 $40,000.00 $ 61,320.82 $ 61,320.82 $ 45,000.00 $ 45,000.00 201(A) CLEARING & GRUBBING LSUM 1.00 $ 150,000.00 $150,000.00
More informationGRAVEL RESURFACING OF ROADS
NOTICE TO BIDDERS Sealed bids will be received by the Board of County Road Commissioners of the County of Gratiot at their office at 200 Commerce Drive, PO Box 187, Ithaca, MI 48847, until 10:00 AM, Tuesday,
More informationCONTRACTOR'S ESTIMATE PACKAGE REPORT DATE: 10/07/16 HIGHWAY: 11/04/2014 ESTIMATE PAID: AWARD DATE: 11/20/2014 ESTIMATE PERIOD:
216,972.00 CONTRACTOR'S ESTIMATE PACKAGE REPORT DATE: 10/07/16 388 6 CONTRACT ID: 627908001 PROJECT: RMC - 627908001 CONTRACT: 11144009 AWARD AMOUNT: $319,350.50 PROJECTED AMOUNT: $319,351.50 ADJ. PROJECTED
More informationSUBDIVISION IMPROVEMENTS AGREEMENT
SUBDIVISION IMPROVEMENTS AGREEMENT THIS AGREEMENT, made between GLEN DEVELOPMENT COMPANY, hereinafter called the "Subdivider," and El Paso County by and through the Board of County Commissioners of El
More informationCONTRACTOR'S ESTIMATE PACKAGE REPORT DATE: 10/06/14
-137,738.34 CONTRACTOR'S ESTIMATE PACKAGE REPORT DATE: 10/06/14 42 CONTRACT ID: 050201208 PROJECT: NH 2012(709) CONTRACT: 08123017 AWARD AMOUNT: $2,342,263.41 PROJECTED AMOUNT: $2,347,563.41 ADJ. PROJECTED
More informationIn this chapter, we will talk about the criteria and procedures for these other types of measurement and payment.
INTRODUCTION Most construction items are measured and paid for by one of the techniques described in the previous chapters. Some items, however, do not fall into any of these categories and are measured
More informationCONTRACTOR'S ESTIMATE PACKAGE REPORT DATE: 08/10/18 HIGHWAY: US 59 COUNTY: 02/02/2017 ESTIMATE PAID: AWARD DATE: 02/23/2017 ESTIMATE PERIOD:
48,793.52 CONTRACTOR'S ESTIMATE PACKAGE REPORT DATE: 08/10/18 69 18.00 CONTRACT ID: 017701102 PROJECT: NH 2017(641) CONTRACT: 02173007 AWARD : $2,215,251.08 PROJECTED : $2,257,251.08 ADJ. PROJECTED : $2,306,044.60
More informationProject No Paving & Seal Coat of 52 nd Street NE
I. TABLE OF CONTENTS I. TABLE OF CONTENTS II. APPROVAL OF ENGINEER III. INFORMATION TO BIDDERS IV. GENERAL PROVISIONS V. SPECIAL PROVISIONS VI. BIDDER S PROPOSAL Project No. 0077 Paving and Seal Coat of
More informationSolicitation/Proposal/Award (Construction) PROPOSAL
SOLICITATION: PL-K-REC-09-001-17-011, Amendment #03. Solicitation/Proposal/Award (Construction) PROPOSAL Offerors shall enter in the space below a Total Lump Sum Cost Proposal. A. Total Lump Sum Cost Proposal:
More informationENGINEER'S ESTIMATE OF PROBABLE COST CCTA I 680 NORTH EXPRESS LANE PROJECT (SOUTHBOUND ONLY) EA 04 4H % PS&E Submittal
Page: 1 of 8 (F) Description 1 050000A CONTRACTOR STAKING LS 1 $ $ 2 070030 LEAD COMPLIANCE PLAN LS 1 $ $ 3 080000A POTHOLING LS 1 $ 50,000.00 $ 50,000.00 4 080050 PROGRESS SCHEDULE (CRITICAL PATH METHOD)
More informationCITY OF YUBA CITY STATE OF CALIFORNIA PUBLIC WORKS DEPARTMENT NOTICE TO CONTRACTORS
CITY OF YUBA CITY STATE OF CALIFORNIA PUBLIC WORKS DEPARTMENT NOTICE TO CONTRACTORS Sealed proposals will be received at the City Clerk s Office, City of Yuba City, located at City Hall, 1201 Civic Center
More information2012 WATER & SEWER ALLEY CONSTRUCTION CONTRACT, PACKAGE I SAWS WATER JOB. NO /SAWS SEWER JOB NO SOLICITATION #B DD
BID PROPOSAL PROPOSAL OF, a Corporation organized and existing under the laws of the State of, a Partnership consisting of, an Individual doing business as. Enclosed with this bid are (1) Bid Bond, and
More informationPROPOSAL FOR IMPROVEMENTS TO OGDEN - HINCKLEY AIRPORT OGDEN, UTAH AIP PROJECT NO
PROPOSAL FOR IMPROVEMENTS TO OGDEN - HINCKLEY AIRPORT OGDEN, UTAH AIP PROJECT NO. 3-49-0024-048-2018 MAIL TO: Ogden City Corporation Purchasing Department 549 Washington Boulevard, Suite 510 Ogden, Utah
More informationEMERGENCY CONTRACT MANUAL
EMERGENCY CONTRACT MANUAL 2012, Commonwealth of Virginia Virginia Department of Transportation February, 2012 TABLE OF CONTENTS Introduction... 3 Requirements... 5 Emergency Authorization Chart... 6 District
More information