1 Memorandum TO: FROM: CC: Patrick C. Scheidel, Town Manager and the Selectboard Dennis E. Lutz, P.E., Public Works Director and Town Engineer Doug Fisher, Finance Director Trevor Lashua, Assistant Town Manager Mark Berry, Parks and Recreation Director Randy Viens, Assessor Cheryl Moomey, Town Clerk Charles Cole, Fire Chief Susan Overfield, Head Librarian Dana Farley, Community Development Director Brad LaRose, Acting Chief of Police DATE: 25 October 2011 SUBJECT: Status of Current Capital Projects ISSUE: The issue is whether or not the Selectboard needs further information or desires input into the current status of all Capital Projects funded in FYE2012 as part of the FYE2012 to FYE2016 approved Capital Plan. DISCUSSION AND COSTS: Attached to this memo is a copy of the approved Capital Budget for FYE2012. All financial balances reflect the amount in accounts as of June 30, 2010, unless noted otherwise. A discussion follows, including both carryover projects from previous years and current year projects: BUILDINGS: 1. New Town Office - Capital Funds were obligated in FYE12 in the amount of $60,000 for future project use No work is currently underway on a new Town office building. There is $583,030 set aside for future improvements/construction as of June 30, 2011 with another $60,000 to be added in June of 2012, bringing the total at that time to over $640, Vault Expansion-- No budget expenditure was proposed in FYE12 Records preservation funds totaled $419,314 as of June 30, The vault space is still anticipated to have between a 2 and 3year available life. Construction of a new vault has been postponed indefinitely pending future decisions on a new building or improvements/expansion at 81 Main Street. 3. Renovation of 81 Main Street for Police Capital Funds were obligated in FYE12 in the amount of $60,000 for future project use 1
2 The second phase work of a Police Facility building committee established by the Selectboard has been underway since late summer. The current plan is to wrap up studies and have their recommendations to the Selectboard by the end of the calendar year. There is $577,943 set aside for this project as of 30 June With the addition of the $60,000 in FYE12, this account should have a balance in excess of $673,943 by the end of June Highway garage area improvements (two- bay highway garage expansion) ($360,000) -- Capital Funds were obligated in FYE12 in the amount of $10,000 for future project use No work is currently underway on improvements to the Highway garage. The current plan is to preserve and set aside funds for either a future expansion of the facility or interior separation work for vehicle maintenance. A total of $3,664 was available as of 30 June Library Deferred Maintenance ($27,000), land acquisition ($31,000) and added storage space ($54,000) for a total of $112, Capital Funds were obligated in the amount of $13,000 in FYE12 Price quotes are in the process of being obtained for deferred maintenance work in the library during FYE12. There are carryover funds totaling $7,450, enabling a total amount of $20,450 for expenditure. The projects include flooring restoration work (carpet and tile). 6. Memorial Hall Improvements including new seating platforms ($80,000) and space for a small food service area ($11,501) for a total of $91,501. Capital Funds were obligated in the amount of $30,000 in FYE12 The Town obtained a Vermont Arts Council Cultural Facilities grant in the amount of $20,000. In addition, the sum of $41,501 was available from the Capital Fund as of June 30, 2011.The total available was therefore $91,501. Staging has been purchased and installed ($31,957) as well as new seats ($32,034). The floor in the main auditorium was redone ($5,000) and the interior repainted ($5,825). In addition, an electrician was hired to update small portions of the interior electrical system ($600). The purchase of some limited additional staging is being planned as well as the potential for a small kitchen area is being investigated. The current amount of available funds is approximately $16,000 for the added work items. 7. Community Recreation Facility (study estimated at $75,000). No Capital Funds were obligated in FYE12 This project was identified in the 2004 Recreational Needs Assessment but not funded in recent Capital Plans. In the 2011 Recreational Needs Assessment, a facility feasibility study was identified with a timeframe beyond the current Capital Budget planning timeline to allow for resolution of Police and Town office space needs. 2
3 8. Energy funds for energy-savings projects at existing buildings, streets and other Town infrastructure including matching funds for Town energy grants. Capital Funds were obligated in the amount of $28,117 for FYE12 The sum of $6,832 was carried over from FYE11, after funds were used to convert signals and Town street lights to LED fixtures on Susie Wilson and Kellogg Road. The plan was to use the total available funds of $34,949 to complete the conversion of streetlights owned by others in the corridor to LED lighting. This project is currently on hold pending work on a more comprehensive street lighting plan for the community. The streetlight inventory is still in progress as a precursor to the full study anticipated in calendar year Until such time as the comprehensive plan is completed, the funds will remain unspent. 9. Historic Water Tower Repairs (Fort Ethan Allen) Capital Funds were obligated in the amount of $16,500 for FYE12 As of June 30, 2011, this project had an account balance of $16,034. With the inclusion of the added $16,500 from FYE12 funds, there will be sufficient funds to do the design work in FYE12 for remedial repairs. It is projected that the actual first phase of repairs could begin sometime early in FYE13, with the addition of an estimated $20,000 in FYE13 Capital Funds. HIGHWAYS 1. Sand Hill Road Rehabilitation from Allen Martin Drive to Founders Road.Capital Funds were obligated in the amount of $31,380 for FYE12 The project is funded from FYE11 Capital Funds ($158,700), FYE12 Capital Funds ($31,380) and a VTRANS Class 2 Paving grant in the amount of $79,920 for a total available of $269,280. Dirt-Tech Construction was awarded the competitive bid at a bid price of $207,168. A number of change orders have been issued to expand the work to include more areas needing reconstruction/repaving and it is anticipated that the final contract price will be close to the estimated funds available. All work will be completed in the fall of 2011 except for the final top-coat, which will be done in the spring of Gravel Roads Capital Funds were obligated in the amount of $31,000 for FYE12 The gravel roads account had a balance of $35,788 as of June 30, 2011, with $11,179 expended in FYE11. Expenditures from the account were lower in FYE11 because funds were obtained via FEMA disaster grants and used in lieu of Town funds on select gravel roads. With the $31,000 in FYE12 funding, the plan is for a major expenditure on gravel roads in the spring/summer of
4 3. Valleyview Drive Reconstruction from VT Route 117 to #5 Valleyview Capital Funds were obligated in the amount of $85,000 for FYE12 The project was completed in the late summer of 2011 at a total cost of $90,673. The cost overrun of $5,673 was covered by residual Capital road construction funds from prior years. 4. BixbyHill/VT128 Intersection. Capital Funds were obligated in the amount of $25,000 for FYE12 The project is scheduled for construction in the late spring of The project was originally estimated at $25,000 but the scope of work has changed to include not only intersection improvements but also sidewalk, curbing and storm water system changes along VT Route 128 and on a portion of Alder Lane. A revised estimate is now $45,000. The needed $20,000 will be taken from residual Capital road construction funds from prior years. 5. Intersection Actuation Control at Essex Way and the Circ Highway Ramps. Capital Funds were obligated in the amount of $30,000 for FYE12 Timing changes were made to the intersection based on an analysis by Patti Coburn, P.E., Lamoureux and Dickinson. These changes have improved traffic flow during the peak hour but the changes only represent a limited fix. The solution is to provide new hardware for the intersection to include video detection equipment and a switch in controllers. The limitations of the existing controllers were not anticipated and this change will increase the project cost to $50, Allen Martin Parkway No Capital Funds were obligated in FYE12 This project is on hold at this time pending the evaluation of alternative Circumferential Highway Projects and potential future funding as part of a regional transportation solution. 7. Construction of the David Drive Traffic Light (Susie Wilson Road/David Drive Signals and other Susie Wilson Road Improvements Capital Funds were obligated in the amount of $36,028 for FYE12 The signal project has been completed and the funds set aside in FYE12 will complete the final payment on the project. The Susie Wilson Road developer fees will continue to be collected for work within the corridor. 4
5 8. Transit Improvements at Susie Wilson Road and VT15 The sum of $40,000 was provided to the Town by Lowe s for transit improvements in the corridor The Town provided the funds to CCTA for bus shelters in connection with the new traffic signal and revised bus route in the area of the east gate of Fort Ethan Allen. This account will be closed out. 9. Gentes Road Bridge Capital Funds were obligated in the amount of $25,000 for FYE12 The sum of $25,000 was set aside for this project in FYE11 and another $25,000 in FYE12. A scoping study is nearing completion on the condition of the bridge and potential alternatives as well as a separate study on whether the bridge needs to be closed. Planning funds from the CCMPO (CCRPC) mostly cover both studies. After a public hearing is held on the studies, it will be a Selectboard decision as to how to proceed with the bridge. It is clear that some local funds will have to be expended for immediate repairs to ensure that the bridge remains open. It is anticipated that the $50,000 set aside so far will not cover the cost of these repairs. 10. Added Project During FYE12.Susie Wilson Bypass partial grind and overlay During the winter and spring of , the top layer of pavement failed on the southern 1/2 of the roadway, resulting in many pancaked potholes. The Town approached VTRANS with the proposal to partially reduce the Class 2 paving grant on Sand Hill Road and direct grant funds to fix the problem on Susie Wilson Bypass. A grant was awarded at 80% of the total project cost of $48,355. The Town share in the amount of $9,671 will be taken from residual Capital road construction funds from prior years. WATERLINES: 1. Pinecrest Drive to the Village at VT2A Capital Funds were obligated in the amount of $25,000 for FYE12 No budget expenditure was made in FYE2011 or will be made in FYE Douglas to Willoughby. No Capital Funds were obligated in FYE12 No budget expenditure was made in FYE2011 or will be made in FYE Sand Hill Road waterline size increase and addition of pressure reducing valves planning and design. Capital Funds were obligated in the amount of $10,000 for FYE12 5
6 Funds were set-aside in FYE12 for the purpose of creating a fund for initiating planning and design of the needed changes to the system. The amount budgeted in FYE12 is not sufficient to begin the work. Additional funds on the order of another $15,000 will be needed in FYE13 for the planning and design work to move forward. 4. Water Storage tank in the lower service area for improved flow and pressure in the Susie Wilson Road/Kellogg Road/VT2A area of Town (study phase only) No Capital Funds were obligated in FYE12 Preliminary study funds were obligated in FYE11 in the amount of $20,000. No work was initiated on this study in FYE11. The study effort is planned to begin in the spring of SEWERS: 1. Painesville Area - No Capital Funds were obligated in FYE12 The Selectboard made a decision in September of 2007 to not proceed with this project based upon the high cost to users without added Town funding for the growth aspect of the project or additional road restoration. A portion of the project will be built by Gabe Handy if he decides to move forward with his approved apartment complex on Pinecrest Drive. It is unclear as to when or if his project will move forward in the future. 2. Cemetery Road..No Capital Funds were obligated in FYE12 No work was done on this project in FYE11 and none is planned for FYE12. The project may or may not move forward depending upon the potential user s indication of a willingness to pay for the sewer extension. HEAVY EQUIPMENT VEHICLES: 1. Highway Equipment Vehicles Expenditures Budgeted at $81,000 in FYE12 with $140,000 received from the Operating Fund In FYE12, the actual expenditure was $144,599, based on a decision to fund the purchase of vehicles in a single year rather than through a two-year loan/lease program. The Highway Equipment Replacement Fund has been revised to reflect this change. It will result in a deficit in the account at the end of FYE12 of $62,680 due to a negative balance at the end of FYE11. Over the course of a number of years, this account will fluctuate from a positive to a negative balance. If funded at an annual level of $175,000 from the Highway Equipment Operating Account, the fund will be self-sustaining. Interest will be charged in the negative balance years to reflect the cost of borrowed money. New 7 cy dump truck $144,599 6
7 2.Fire Department Equipment Vehicles... Capital Funds were obligated in the amount of $40,000 for FYE12 with another $10,000 transferred from the Fire Department Equipment Operating Account This is the first of four $50,000 annual contributions towards the Village of Essex Junction s purchase of a 100 aerial (a.k.a. ladder) truck. The contributions, governed by a memorandum of understanding signed by the Selectboard and Village Trustees in August 2011, will be in amounts totaling $50,000 per year for four years (an amount not to exceed $200,000 total). The truck will be a quint, a multi-functional fire vehicle with a fire pump, water tank, hose, and ground ladders in addition to the 100 ladder or platform. Contribution towards 100 aerial truck $50, Parks and Recreation Capital Park Equipment Plan Funded through the Operating Budget at $15,000 with $7,913 for expenditure in FYE12 and $7,087 obligated for future purchases A Capital Equipment Plan (CEP) for the replacement of park equipment and vehicles was approved starting in the FYE07 Budget. The funding for the CEP is from the Operating Budget. Expenditures planned for FYE12 include: 4x4 gator w/dump body for trail work at Indian Brook and other sites not accessible by vehicles..$7, Senior Bus Funded through an Operating Fund Transfer to the Capital Fund The Senior Bus Capital Account had a balance of $15,365 as of June 30, 2011, with another $4,000 transferred into the account in FYE12 (total available is $19,365). The van purchased in 2006 is scheduled to be replaced in FYE12 at an estimated cost of $60,000. A grant through CCTA will be available to pay 90% of the cost. The Town portion is expected to be $6,000. PARK FACILITIES: 1. Park Asset Replacement Plan...Capital Funds were obligated in the amount of $45,000 for FYE12 A Parks Asset Replacement Plan was approved starting in the FYE07 Budget. Funding for the plan is from the Capital Budget. The account had a balance of $92,933 as of June 30, A total of $8,540 will be used from the account balance for funding of projects in FYE2012. Projects are underway and include: Sand Hill Park playground replacement $53,940 7
8 2. Foster Road Park and Founders Field Improvements Capital Funds were obligated in the amount of $25,000 for FYE12 Additional funds are estimated as being needed in FYE13 in the amount of $25,000 for work on these projects to move forward. 3. Milfoil Mitigation at Indian Brook. Capital Funds were obligated in the amount of $10,000 for FYE12 Milfoil Mitigation includes the development of an integrated management plan and funding for the implementation of the plan. A total of $3,000 was provided from the Operating Budget and $10,000 from the Capital Budget for future milfoil mitigation.. 4. Indian Brook Dam Repairs. Capital Funds were obligated in the amount of $9,000 for FYE12 Funding for Indian Brook Dam repairs include $3,000 from the Operating Budget and $9,000 from the Capital Budget for future repairs and maintenance of the dam. A consulting engineer is currently developing an operational and maintenance plan based on inspection of the dam, valves and gate. A plan with timeline and budget is expected this fall. A total of $4,000 has been expended in FYE12 for the study of existing conditions and development of a management plan. An outline of the plan and projected expenses are expected in Nov/Dec of Tree Farm Purchase No Capital Funds were obligated in FYE12 The voters approved the purchase of the State Tree Farm property on January 21, Funding sources are the proceeds from the sale of Town owned property in the amount of $159,511 and $21,189 of previously designated Capital funds. The transfer of property is still not concluded, but is targeted to be by the end of the calendar year. Legal documents to implement the transfer are in the final stages of development. NOTE: Parks and Recreation Projects 6 through 9 came from the results of the 2004 Recreation Needs Survey. These projects were not identified in the 2011 survey and will be removed from the Capital Project schedule in FYE Youth Softball Field No Capital Funds were obligated in FYE12 and no Budget Expenditure was proposed 7. Basketball Court No Capital Funds were obligated in FYE12 and no Budget Expenditure was Proposed 8. Regulation Ballfield.. No Capital Funds were obligated in FYE12 and no Budget Expenditure was Proposed 9. Twenty Acres of Developed Recreation Land No Capital Funds were obligated in FYE12 and no Budget Expenditure was Proposed 8
9 PATHS AND WALKS: 1. Vermont Route 15 from the Circ Highway to the Miniature Golf Course..No Capital Funds were obligated in FYE12 and no Budget Expenditure was Proposed This account has $3,000 in residual funds; no action is being taken on this project at this time due to other priorities and the lack of sufficient funds to implement a solution. 2. Conceptual Design of a path/walk along VT Route 2A from Old Colchester Road to Pinecrest and north on Pinecrest to the intersection with Suffolk Lane Capital Funds were obligated in the amount of $7,500 for FYE12 A bike/pedestrian path grant was obtained from VTRANS in the amount of $52,500 against a total conceptual design project cost of $70,000. In FYE11, a total of $10,000 was budgeted in the Capital Plan for this project and $8,385 was spent on the design work in that fiscal year. The remaining funds will be spent completing the conceptual design in FYE12. At this time, there is no identified funding source for construction of the walkway.. 3. Scoping/Design of a pedestrian path/linear park from Susie Wilson Road to Pearl Street Park.. Capital Funds were obligated in the amount of $12,000 for FYE12 A grant was applied for in FYE2012 but the Town was unsuccessful in obtaining the grant. VTRANS has since changed the requirements for the grants to only accept proposals for combined design and construction of paths and walks. In the past, the Town was able to segment projects and reduce costs by separating the design phase from the construction phase. Given the cost of this project and the restricted service area, no forward progress is being sought at this time on the project. STORM WATER Construction Projects/NPDES Phase 2 Permit Compliance planning needed to meet existing/new State storm water permit requirements and to repair existing storm water systems not included in the Operating Budget.. Capital Funds were obligated in the amount of $60,000 for FYE12 The purpose of this account is to create a fund for use on major repair of existing storm water systems and for permit compliance under the soon-to-be released NPDES Phase 2 Revised Storm water Permit. There is $124,583 in the account as of June 30, RECOMMENDATION: It is recommended that the Selectboard review and provide input on this status report. A proposed Capital Plan for FYE will be presented to the Selectboard in early January of 2012 as per the Budget schedule. 9
10 10
1. Highway garage area improvements (two-bay highway garage expansion) ($415,615); Capital Funds were budgeted in FYE18 in the amount of $7,000.
Memorandum TO: FROM: CC: Patrick C. Scheidel, Municipal Manager and the Selectboard Dennis E. Lutz, P.E., Public Works Director Greg Duggan, Deputy Town Manager Ally Vile, Parks and Recreation Director
More informationCITY OF WILLIAMSBURG MEMORANDUM. Mayor and City Council Planning Commission. From: Andrew O Trivette, Assistant City Manager
CITY OF WILLIAMSBURG MEMORANDUM To: Mayor and City Council Planning Commission From: Andrew O Trivette, Assistant City Manager Date: Thursday, January 11, 2018 RE: Capital Improvements for FY18 Status
More informationFiscal Responsibility to Further Invest in the Future. Executive Committee Department of Finance May 4, 2017
Fiscal Responsibility to Further Invest in the Future Executive Committee Department of Finance May 4, 2017 1 Asset Inventory Denver s Assets Parks and Recreation $1.8B Transportation $4.7B Buildings $1.9B
More informationCapital Budgeting and Programming
Capital Budgeting and Programming Presented by the Southern Windsor County Regional Planning Commission with support from the Vermont Agency of Commerce and Community Development and the US Department
More informationPolice Department & Court Your Tax Dollars at Work
1 Police Department & Court Your Tax Dollars at Work A Safe and Secure Community New York State Accredited Police Agency with a staff of 40 full time and 5 part time professional and dedicated sworn police
More informationDRA F T 11/25/15. Anticipated fiscal year of purchase/completion: To be determined (possible bond vote in 2016)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 Introduction An important part of financial management is the study and
More informationCapital Improvement Program Fund
Capital Improvement Program Fund The Capital Improvement Program Fund provides funding for streets, public buildings (both governmental and school facilities), land, and other capital assets. Capital Improvement
More informationFY 16 - FY 18 Capital Fund Revenues
FY 16 - FY 18 Capital Fund Revenues Fiscal Year $ Change 2016 2017 2018 FY 17 to Revenue Source Budget Budget Budget FY 18 Local Transfer from General Fund $3,136,950 $2,977,556 $6,087,130 $3,109,574 Local
More informationInfrastructure and Capital Projects Planning and Funding
Infrastructure and Capital Projects Planning and Funding September 6, 2018 Preview of FY 2020 2024 CIP process Why are we here? Overview Current Assets Overview and Highlights of Adopted FY 2019 2023 CIP
More informationUtilities and Facilities Planning and Capital Budgeting and Programming
Utilities and Facilities Planning and Capital Budgeting and Programming Presented by the Two Rivers-Ottauquechee Regional Commission with support from the Vermont Agency of Commerce and Community Development
More informationCITY OF PORT MOODY 2012 CAPITAL & OPERATING BUDGET SUMMARY
2012 & OPERATING BUDGET SUMMARY ACCOUNT 4710 4790 4727 4728 4724 4721 4771 4700 4712 4774 4772 4701 4736 TOTAL LIFE CYCLE MRN ASSET DEPARTMENT EXP. TAXATION SURPLUS RESERVE RESERVE RESERVE RESERVE RESERVE
More informationCity of Falls Church
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 Meeting Date: 10-8-14 (Work Session) City of Falls Church Title: ORDINANCE TO AMEND ORDINANCE 1918 AND ORDINANCE 1919, REGARDING
More informationFY 2017 FY 2021 Capital Improvement Program (CIP) Executive Summary
FY 2017 FY 2021 Capital Improvement Program (CIP) Executive Summary The adopted FY 2017 FY 2021 CIP is $235.8 million (including prior year expenditures) and is $28 million higher than the previous CIP
More informationCapital Improvement Program Fund
Capital Improvement Program Fund Capital Improvement Program (CIP) Overview The Capital Improvement Program provides funding for streets, public buildings (both governmental and school facilities), land,
More informationFunding Source: Highway Safety Improvement Program (HSIP) Grant - $315,100; Measure I - $60,500
FY 2017-18 Capital Improvement Program Detail STREETS Raised Median on Pipeline Avenue S14009 Program Year Initiated: FY 2013-14 Construction Year: FY 2016-17 Project Description: Install raised median
More informationGuelph/Eramosa 2016 Budget Presentation. Thursday, February 18, 2016
Guelph/Eramosa 2016 Budget Presentation Thursday, February 18, 2016 1 Our Township We cover 292 km 2 and provide services to 12,380 residents The Township is responsible for maintaining: 225 km of roads
More informationTOWN OF SHELBURNE, VERMONT AUDIT REPORT JUNE 30, 2017
AUDIT REPORT AUDIT REPORT TABLE OF CONTENTS Page # Independent Auditor s Report 1-3 Management s Discussion and Analysis 4-12 Basic Financial Statements: Statement of Net Position Exhibit A 13 Statement
More informationCity of Hartford Capital Improvement Program Share Total Project Cost. General Obligation Debt
2019 Summary of Costs ~ Governmental Funds Law Enforcement Number Priority 2019 Share Total Cost General Obligation Term Borrowings Grants & Aids Trusts & Donations Retained Earnings Police Patrol Vehicle
More informationCITY OF ROSEBURG, OREGON TABLE OF CONTENTS ENTERPRISE FUNDS
TABLE OF CONTENTS ENTERPRISE FUNDS Storm Drainage Fund... 121-124 Off Street Parking Fund... 125-126 Airport Fund... 127-131 Water Service Fund... 132-145 STORM DRAINAGE FUND CURRENT OPERATIONS This fund
More informationThings you do every day
Things you do every day are made possible by the City of Madison. Drinking Water Madison Water Utility Walking Down the Sidewalk Engineering Street design, construction Sidewalks Storm sewers Sanitary
More informationCity of Cornwall 2014 Capital Report First Quarter
C33093 '12 Nick Kaneb Dr Extension - Marleau to 10th St -2012 approved funding 75,000 55,749 19,251 0 Apr-14 notice of completion issued, final public review underway C33097 '13 Tenth St to Virginia to
More informationSection III.C. Capital Investments Plan
Section III.C. Capital Investments Plan Section III.C. Capital Investments Plan 61 The capital facilities of local governments are essential to meeting the service needs of the community in an efficient
More informationVERMONT AGENCY OF TRANSPORTATION. FY2016 Budget. Sue Minter, Secretary of Transportation House Transportation Committee
VERMONT AGENCY OF TRANSPORTATION FY2016 Budget Sue Minter, Secretary of Transportation House Transportation Committee February 19, 2015 FY2016 Budget 1 Five Year Budget History $ millions $658.1 $653.1
More informationReserves and Reserve Funds
Reserves and Reserve Funds Table of Contents 1 Overview... 2 2 Forecast Changes... 4 2.1 Operating Reserves and Reserve Funds... 5 3 Capital Reserve Funds... 8 3.1 Capital Highlights... 9 3.2 10 Year Forecast
More informationThe Three Planning Windows of Asset Management John Murray City of Hamilton May 9 th, 2012 CNAM - Montreal. Hamilton Asset Management Plan
The Three Planning Windows of Asset Management John Murray City of Hamilton May 9 th, 2012 CNAM - Montreal 1 City of Hamilton Amalgamated - 2001 7 Area Municipalities Population 500,000 The City of Waterfalls
More informationSPECIAL MEETING AGENDA CITY OF FREDERICKSBURG CITY COUNCIL. JULY 11, :00 PM Law Enforcement Center, 1601 E. Main St.
SPECIAL MEETING AGENDA CITY OF FREDERICKSBURG CITY COUNCIL JULY 11, 2017 4:00 PM Law Enforcement Center, 1601 E. Main St. 1. Call to Order 2. Consider Institution of Annexation Proceedings of Frieden Development
More informationTOWN OF COLLINGWOOD ASSET MANAGEMENT PLAN
TOWN OF COLLINGWOOD ASSET MANAGEMENT PLAN JUNE 24, 2014 EXECUTIVE SUMMARY CONTENTS Page (i) 1. INTRODUCTION 1.1 Overview 1-1 1.2 Plan Development 1-1 1.3 Maintaining the Asset Management Plan 1-2 1.4
More informationReserves & Reserve Funds Business Plan & 2016 Budget
Reserves & Reserve Funds 2018 Business Plan & Budget Table of Contents Executive Summary of Reserves and Reserve Funds... 3 Overview... 4 Forecast Changes... 6 Operating Reserves and Reserve Funds... 7
More informationCity of Pittsburg Five Year Capital Improvements Plan
General Fund Roadways Roadways account for forty three percent of the plan total and are the largest category at over $26.8 million. Planned improvements include annual street resurfacing, Silverback Way,
More informationBudget Summary by Function
Budget Summary by Function Your budget shows the 2014, 2015, 2016 approved budgets, the 2017 department request and 2017 city manager proposed. The numbers below reflect percentages based on the city manager
More informationTOWN OF RYE BUDGET COMMITTEE 2016 BUDGET WORK SESSION Thursday, December 8, :30 p.m. Rye Town Hall
TOWN OF RYE BUDGET COMMITTEE 2016 BUDGET WORK SESSION Thursday, December 8, 2016 6:30 p.m. Rye Town Hall Members Present: Chairman Paul Goldman, Jaci Grote, Peggy Balboni, Ray Jarvis, Mae Bradshaw, School
More informationBuilding Detail and Buy-in For Your Long-Term Multi-Asset Investment Plan
Building Detail and Buy-in For Your Long-Term Multi-Asset Investment Plan Michael E. Trickey, P.Eng., PE Senior Asset Management Consultant Urban Systems Limited 250-762-2517 mtrickey@urban-systems.com
More informationFY 2016 FY 2020 Capital Improvement Program (CIP) Executive Summary
FY 2016 FY 2020 Capital Improvement Program (CIP) Executive Summary The adopted FY 2016 FY 2020 CIP is $205.3 million (including prior year expenditures) and is $2.9 million lower than the previous CIP
More informationFINANCIAL ACTION SUMMARY
City of Woodinville, WA Report to the City Council 17301 133 rd Avenue NE, Woodinville, WA 98072 www.ci.woodinville.wa.us To: Honorable City Council Date: 02/06/2018 By: Blaine Fritts, Finance Director;
More informationCIP. February,
2018-2022 CIP February, 21 2017 Agenda Biennial Budget 2018/2019 Budget Calendar 2018-2022 CIP Process Prioritized List of Projects Biennial Budgeting Strategic Culture in Olathe Strategic Culture in Olathe
More informationManheim Central School District 66%
Manheim Borough 2018/2019 Budget Summary Report James R. Fisher, PE, CBO Chief Administrative Officer, Borough Manager, Treasurer Council and staff continue to place an emphasis on maintaining and improving
More informationStephanie Smith, Project EngineerW
MEMORANDUM v TO: Paul Oehme, Director of Public Works/ City Engineer o FROM: Stephanie Smith, Project EngineerW 7700 Market Boulevard PO Box 147 Chanhassen, MN 55317 Administration Phone: 9522271100 Fax
More informationPublic Works and Development Services
City of Commerce Capital Improvement Program Prioritization Policy Public Works and Development Services SOP 101 Version No. 1.0 Effective 05/19/15 Purpose The City of Commerce s (City) Capital Improvement
More informationCAPITAL IMPROVEMENT PROJECTS CAPITAL PROJECTS FUND FISCAL YEAR 2013/2014 PROJECTS SCHEDULED FOR CONSTRUCTION. Local Option Sales Tax Funds $ 500,000
CAPITAL IMPROVEMENT PROJECTS CAPITAL PROJECTS FUND FISCAL YEAR 2013/2014 PROJECTS SCHEDULED FOR CONSTRUCTION On-Going Pavement Management Program: In 2009/2010 the city completed the initial 3-year plan
More informationCapital Investment Program (CIP) About CIP
Capital Investment Program (CIP) About CIP The Capital Investment Program (CIP) is a multi-year program aimed at upgrading and expanding City facilities, buildings, grounds, streets, parks and roads. The
More informationManheim Borough 2017/2018 Budget Summary Report
Manheim Borough 2017/2018 Budget Summary Report James R. Fisher, PE, CBO Chief Administrative Officer, Borough Manager, Treasurer 2017 has been a year of building on the changes that occurred in 2015/2016.
More informationThis page intentionally left blank
197 This page intentionally left blank 198 Capital Improvement Program PROCEDURE Each year the Capital Improvement Program (CIP) is prepared from project requests submitted by the various departments.
More informationCITY OF SALEM FINANCIAL SUMMARY
CITY OF SALEM FINANCIAL SUMMARY Through Q2 / FY 2015-16 Financial summaries through the second quarter of each year complement development of both the five-year forecast for the General Fund and the upcoming
More informationVILLAGE OF NEW MARYLAND 2015 GENERAL OPERATING FUND BUDGET. 1. Total Budget - Total Page 17 $4,466,360
1. Total Budget - Total Page 17 $4,466,360 2. Less: Non-Tax Revenue - Total Page 7 $311,392 3. Net Budget $4,154,968 4. Less: Community Funding and Equalization Grant $6,108 5. Warrant to be Raised by
More informationCity of Mountlake Terrace. Fourth Quarter 2014 Financial Report April 2, 2015
City of Mountlake Terrace Fourth Quarter 2014 Financial Report April 2, 2015 1 Overview Reviewing the City s finances on a regular basis, and posting the review on the City s website, highlights the City
More informationManheim Borough 2017/2018 Budget Summary Report
Manheim Borough 2017/2018 Budget Summary Report 2017 has been a year of building on the changes that occurred in 2015/2016. Council and staff have placed an emphasis on maintaining and improving the efficient
More informationCity of Des Moines. Citizen Engagement Capital Improvement Program. November 29, 2016
City of Des Moines Citizen Engagement Capital Improvement Program November 29, 2016 Goals of Citizen Engagement Goal Focus on service levels Department definitions of adequate service and opportunities
More informationChapter 6: Financial Resources
Chapter 6: Financial Resources Introduction This chapter presents the project cost estimates, revenue assumptions and projected revenues for the Lake~Sumter MPO. The analysis reflects a multi-modal transportation
More informationBylaw No The Capital Reserve Bylaw. Codified to Bylaw No (December 18, 2017)
Bylaw No. 6774 The Capital Reserve Bylaw Codified to Bylaw No. 9476 (December 18, 2017) Page 1 Bylaw No. 6774 The Capital Reserve Bylaw The Council of The City of Saskatoon enacts: Purpose 1. The purpose
More informationAGENDA STATUS OF CURRENT YEAR BUDGET FY 19 CURRENT PROJECTIONS REVIEW FIVE-YEAR CAPITAL IMPROVEMENT PROGRAM REVIEW CITY COUNCIL WORK PLAN
AGENDA STATUS OF CURRENT YEAR BUDGET FY 19 CURRENT PROJECTIONS FOCUS ON COSTS CALPERS UPDATE REVIEW FIVE-YEAR CAPITAL IMPROVEMENT PROGRAM REVIEW CITY COUNCIL WORK PLAN ANSWER QUESTIONS ABOUT DEPARTMENT
More informationMemorandum City of Lawrence City Manager s Office
Memorandum City Manager s Office TO: FROM: Date: CC: Lawrence Cultural Arts Commission Diane Stoddard, Assistant City Manager September 4, 2014 David L. Corliss, City Manager Casey Toomay, Assistant City
More informationTOWN OF SPRINGFIELD, VERMONT FINANCIAL STATEMENTS JUNE 30, 2016
TOWN OF SPRINGFIELD, VERMONT FINANCIAL STATEMENTS JUNE 30, 2016 C O N T E N T S Page INDEPENDENT AUDITOR'S REPORT 1 and 2 Management s discussion and analysis 4-17 Basic financial statements: Government-wide
More informationCapital Improvement Plan City of Rye, New York
20182022 Capital Improvement Plan City of Rye, New York Planning and Funding For City Projects For Fiscal Years Ending December 31, 2018 through 2022 September 2017 Capital Improvement Plan 20182022 TABLE
More informationThe 2018 Budget Table of Contents
The Budget Table of Contents General Purposes Budget (approved March 27, ) General Purposes Budget Table of Contents Schedule A General Purposes Budget Expense Summary Schedule B General Purposes Budget
More informationCity of Worthington. Five-Year Capital Improvements Program
City of Worthington Five-Year Capital Improvements Program 2012-2016 Adopted December 5, 2011 RESOLUTION NO. 35-2011 Approving the 2012 Capital Improvement Program for the City of Worthington. WHEREAS,
More informationOFFICE OF THE STATE AUDITOR Instructions for the Annual Financial Reporting Form
New This Year (Year-End 2015 Reporting) As the Office of the State Auditor (OSA) continues to utilize the Annual Financial Reporting Form (Form), changes and improvements are made to strive for accurate
More informationTRANSPORTATION CAPITAL PROGRAM
TRANSPORTATION CAPITAL PROGRAM The transportation capital program for fiscal year 2016 through fiscal year 2020 consists of a variety of transportation construction and maintenance capital projects primarily
More informationCAPITAL IMPROVEMENT PROGRAM K-1
Fund # begins with a Fund Type Fund Type Description/Restrictions 1 General The City's principal operating fund, which is supported by taxes and fees and which, generally, has no restrictions on its use.
More informationProposed 2014 Budget and Plan
and Special Council February 18, 2014 Financial Sustainability Always a Key Priority Agenda Purpose Budget objective & principles Proposed budget overview Property taxes in perspective Q & A 2 Purpose
More informationRevenue Sharing Program Guidelines
Revenue Sharing Program Guidelines For further information, contact Local VDOT Manager or Local Assistance Division Virginia Department of Transportation 1401 East Broad Street Richmond, Virginia 23219
More informationMJEMORANJDUM GENERAL FUND. finance Department. DATE: August 26, 2015 TO: Steven A. Preston, City Manager FROM: Thomas C. Marston, Finance Director
finance Department MJEMORANJDUM DATE: August 26, 2015 TO: FROM: Steven A. Preston, City Manager Thomas C. Marston, Finance Director SUBJECT: Quarterly Budget Update- July through June (Pre-closing) 2015
More informationREQUIRED SUPPLEMENTARY INFORMATION
REQUIRED SUPPLEMENTARY INFORMATION TOWN OF SCITUATE, RHODE ISLAND Required Supplementary Information - Pension Plans and OPEB Plans Schedule of Funding Progress (1) "Unaudited" Actuarial Actuarial Actuarial
More informationTOWN OF DEEP RIVER ADOPTED FINAL BUDGET FOR FISCAL YEAR SUMMARY TOTALS 15-May-17
ADOPTED FINAL BUDGET FOR FISCAL YEAR 2017-2018 SUMMARY TOTALS 15-May-17 APPROPRIATED ADOPTED REVENUES Tax Revenues $13,229,459 $13,582,755 $14,458,750 $875,995 6.45% All Other Town Revenue $1,002,127 $545,100
More informationCapital Improvement Program. Fiscal Years
Capital Improvement Program Fiscal Years 2014-2021 1 Capital Improvement Program Fiscal Years 2014-2021 Agenda Background Significant Accomplishments (2012-2014) Proposed Work Plan (2014-2016) and 7- Year
More informationTown Manager FY 09 Budget
Town Manager FY 09 Budget Presentation March 8, 2008 Annual Town Meeting Overview Fiscal 2009 Budget $56,900,443 3.78% Increase over FY 08 Creation of Citizen s Working Group Exposure to Current Economic
More informationTOWN OF SMITHERS. Councillor Brienesse, Chair, called the meeting to order (8:34 a.m.).
TOWN OF SMITHERS MINUTES OF THE FINANCE COMMITTEE MEETING HELD IN THE COUNCIL CHAMBERS, 1027 ALDOUS STREET, SMITHERS, B.C. ON MONDAY, JANUARY 15, 2018, AT 8:30 A.M. Council Present: Phil Brienesse, Councillor/Chair
More informationCity of Marathon, Florida
City of Marathon, Florida Five Year Capital Improvements Program Fiscal Years 2016-2020 City of Marathon Five Year Capital Improvements Program Table of Contents Fiscal Year 2016 2020 LETTER OF TRANSMITTAL...
More informationTraffic Impact Analysis Guidelines Methodology
York County Government Traffic Impact Analysis Guidelines Methodology Implementation Guide for Section 154.037 Traffic Impact Analysis of the York County Code of Ordinances 11/1/2017 TABLE OF CONTENTS
More informationMEMORANDUM. Attached for your review is the quarterly budget update for third quarter of the fiscal year.
Finance Department MEMORANDUM DATE: TO: FROM: April30, 2015 Steven A. Preston, City Manager ~ Thomas C. Marston, Finance Director'-\""~ SUBJECT: Quarterly Budget Update- July through March 2015 Attached
More informationRock Chalk Park - Infrastructure Report. July 2013
Rock Chalk Park Infrastructure Report July 2013 The following report is the first monthly report for the construction of infrastructure at Rock Chalk Park. The format follows the sections outlined in the
More informationLocal Option Sales Tax Report Card Your Penny At Work. District 4
Local Option Sales Tax Report Card Your Penny At Work District 4 Local Option Sales Tax 2007-2017 Report Card Your Penny At Work Transportation $153,816,450 Public Facilities $50,384,889 Natural Resources/
More informationHEMSON C o n s u l t i n g L t d
DEVELOPMENT CHARGES BACKGROUND STUDY Town of Gravenhurst C o n s u l t i n g L t d April, 2014 TABLE OF CONTENTS EXECUTIVE SUMMARY... 1 I INTRODUCTION... 7 II A TOWN-WIDE UNIFORM CHARGE APPROACH TO ALIGN
More informationCAPITAL IMPROVEMENT PROGRAM SUMMARY
CAPITAL IMPROVEMENT PROGRAM SUMMARY The purpose of the CIP Budget is to serve as a planning tool, which coordinates the financing and scheduling of major projects undertaken by the City. The CIP Budget
More information2017 Capital Budget. Budget Committee of the Whole. Tuesday, November 1, 2016
2017 Capital Budget Budget Committee of the Whole Tuesday, November 1, 2016 Objectives Capital Planning & Process 2017 Draft Capital Budget 2018-2027 Capital Forecast Funding Implications Operating Impacts
More informationSAMPLE BALLOT NOT FOR OFFICIAL USE
3 in 1! Bike Lanes for Safety and Convenience! $ 117,000 Increase striping and marking of bicycle lanes and routes along selected streets. LOCATIONS: Various locations throughout Vallejo determined by
More informationCity of Saratoga Springs
City of Saratoga Springs Proposed Capital Program 2019 2024 Submitted by Mayor Meg Kelly and the 2019 Capital Program Committee Office of the Mayor City Hall 474 Broadway, Saratoga Springs, NY 12866 518.587.3550
More informationSECTION 6: CAPITAL IMPROVEMENT DETAIL
SECTION 6: CAPITAL IMPROVEMENT DETAIL Summary... 1 General Government... 2 Public Safety... 6 Public Works... 12 Recreation and Leisure... 18 Education... 24 SUMMARY TOTALS CAPITAL IMPROVEMENT PLAN AND
More informationCity of Mountlake Terrace. Second Quarter 2016 Financial Report September 19, 2016
City of Mountlake Terrace Second Quarter 2016 Financial Report September 19, 2016 1 Overview Reviewing the City s finances on a regular basis, and posting the review on the City s website, highlights the
More informationCHAPTER 4 1 Transportation Financial Analysis
CHAPTER 4 1 Transportation Financial Analysis COMPASS commissioned a financial analysis, finalized in 2012, to support the CIM 2040 update. The analysis, Financial Forecast for the Funding of Transportation
More informationPUBLIC WORKS DEPARTMENT FY16 BUDGET
PUBLIC WORKS DEPARTMENT FY16 BUDGET Respectfully submitted by: Joseph Bettis Jr., Director of Public Works PUBLIC WORKS DEPARTMENT 18 SEPARATE BUDGETS REGISTRY OF DEEDS PARKING TICKET DEPARTMENT TOWN HALL
More informationVillage of Point Edward Asset Management Plan Page 1
The existing infrastructure in the Village of Point Edward is aging and deteriorating. Over the next 50 years, much of the infrastructure will require replacement or rehabilitation. The Asset Management
More informationFiscal Year Proposed Budget
Fiscal Year 2017-2018 Proposed Budget GFOA Budget Presentation Award Recognizes budget documents of the very highest quality that reflect best practices for clearly communicating budget information. Recently
More informationTAUSSIG. Annual Report Fiscal Year City of Irvine Community Facilities District No (Great Park) & Associates, Inc.
DAVID TAUSSIG & Associates, Inc. Annual Report Fiscal Year 2014-2015 City of Irvine Community Facilities District No. 2013-3 (Great Park) October 27, 2015 Public Finance Public Private Partnerships Urban
More informationCAPITAL IMPROVEMENT PROGRAM K-1
Fund # begins with a Fund Type Fund Type Description/Restrictions 1 General The City's principal operating fund, which is supported by taxes and fees and which, generally, has no restrictions on its use.
More informationM E M O R A N D U M March 3, 2015
FINANCIAL SERVICES GROUP Office of the General Manager M E M O R A N D U M March 3, 2015 TO: CC: FROM: SUBJECT: Mayor and Council Penny Ballem, City Manager Sadhu Johnston, Deputy City Manager Janice MacKenzie,
More informationSPECIAL COUNCIL MEETING MARCH 6, Capital Improvements
SPECIAL COUNCIL MEETING MARCH 6, 2012 Capital Improvements 1 CAPITAL PROJECTS Review Requests from the Departments for FY 2012-13 Capital Improvements and Machinery & Equipment Discussion and Recommendations
More informationThe City of Owen Sound Asset Management Plan
The City of Owen Sound Asset Management Plan December 013 Adopted by Council March 4, 014 TABLE OF CONTENTS 1 EXECUTIVE SUMMARY... 1 INTRODUCTION....1 Vision.... What is Asset Management?....3 Link to
More informationBUDGET & INFRASTRUCTURE COMMITTEE MINUTES OF MONDAY, DECEMBER 11, 2017
BUDGET & INFRASTRUCTURE COMMITTEE MINUTES OF MONDAY, DECEMBER 11, 2017 To take a close look at our budget process and develop a new model for how we fund infrastructure. PRESENT: Mayor Greg Moore Councillor
More informationHighlights From The Approved 2013 Budget Budget in Brief
Highlights From The Approved 2013 Budget 2013 Budget in Brief Preparing for the FUTURE: The City of Brandon is committed to building a sustainable future. Our 2013 budget process was improved in many ways,
More informationDEBT SERVICE REQUIREMENTS
DEBT SERVICE REQUIREMENTS BACKGROUND In North Carolina, an agency known as the Local Government Commission, the LGC, oversees local government bonded debt. The LGC must approve all bonded debt of local
More informationCarroll County Maryland. Community Investment Plan Request Fiscal Years
Carroll County Maryland Community Investment Plan Request Fiscal Years 2019-2024 PRODUCED BY The Department of Management and Budget Ted Zaleski... Director Deborah Effingham... Chief, Bureau of Budget
More informationCITY OF WEST PLAINS, MISSOURI BASIC FINANCIAL STATEMENTS. Year Ended March 31, 2017
BASIC FINANCIAL STATEMENTS Year Ended TABLE OF CONTENTS INDEPENDENT AUDITORS' REPORT... 4 MANAGEMENT S DISCUSSION AND ANALYSIS... 8 BASIC FINANCIAL STATEMENTS Statement of Net Position... 16 Statement
More informationStatus of City Council Goals for 2017 As of 3/29/2018
Status of City Council Goals for 2017 As of 3/29/2018 2017 Goals Desired Outcomes Objectives Implementation Approaches and Status Review and enhance City Council guiding principles for The cultural norms
More informationFebruary 2, :30P.M. Municipal Operations Centre
OF THE TOWN OF ST. MARYS February 2, 2015 5:30P.M. Municipal Operations Centre Mayor Strathdee Councillor Osborne Councillor Van Galen Councillor Winter Councillor Pope Councillor Hainer Councillor Craigmile
More informationNorth Berwick Board of Selectmen's Minutes: November 6, 2007 NORTH BERWICK BOARD OF SELECTMEN MINUTES NOVEMBER 6, 2007
1 North Berwick Board of Selectmen's Minutes: November 6, 2007 NORTH BERWICK BOARD OF SELECTMEN MINUTES NOVEMBER 6, 2007 Present: Chairman Moulton, Selectman Danforth, Selectman Bourbon and Selectman Folsom.
More informationOverview of Funding Sources
Overview of Funding Sources 0 Transportation 0 Transportation Sales Tax 0 License Tax 0 G.O. Bonds 0 CIP Sales Tax 0 General Fund 0 Public Safety, Facilities, Buildings 0 G.O. Bonds 0 General Fund 0 Stormwater
More informationCity of Shaker Heights 2018 Proposed Budget Part Budget Overview. Joint Council Finance Committee Work Session November 27, 2017
City of Shaker Heights 2018 Proposed Budget Part 2 2018 Budget Overview Joint Council Finance Committee Work Session November 27, 2017 2018 Operating Budget Summary Summary of 2018 budget parameters 2018
More informationIMPLEMENTATION A. INTRODUCTION C H A P T E R
C H A P T E R 11 IMPLEMENTATION A. INTRODUCTION This chapter addresses implementation of the General Plan. The Plan s seven elements include 206 individual actions. 1 Many are already underway or are on-going.
More informationMAY 13, 2013 ANNUAL TOWN MEETING TOWN OF MILLIS COMMONWEALTH OF MASSACHUSETTS
MAY 13, 2013 ANNUAL TOWN MEETING TOWN OF MILLIS COMMONWEALTH OF MASSACHUSETTS NORFOLK, SS. GREETING: To either of the constables of the Town of Millis in said county, in the name of the Commonwealth of
More informationTAUSSIG. Annual Report Fiscal Year City of Irvine Community Facilities District No (Great Park) & Associates, Inc.
DAVID TAUSSIG & Associates, Inc. Annual Report Fiscal Year 2016-2017 City of Irvine Community Facilities District No. 2013-3 (Great Park) September 26, 2017 Public Finance Public Private Partnerships Urban
More information