1 FY Capital Improvement Program Detail STREETS Raised Median on Pipeline Avenue S14009 Program Year Initiated: FY Construction Year: FY Project Description: Install raised median on Pipeline Avenue between Chino Hills Parkway and Eucalyptus Avenue. Highway Safety Improvement Program (HSIP) Grant - $315,100; Measure I - $60,500 FY Budget: $375,600 Expenditures to Date: $ 50,300 $425,900 Total Project Estimate: $425, Los Serranos Infrastructure ATP S15008 Program Year Initiated: FY Construction Year: FY Project Description: Construction of sidewalks with access ramps, curb and gutter, and street lights in the Los Serranos neighborhood: Mariposa Avenue, Carmelita Avenue, Fairway Boulevard, Yorba Avenue, Murray Avenue, Esther Street, Ethel Street, Cecelia Street, Avery Street, Pheasant Street, and Quail Street. Active Transportation Program (ATP) Grant - $1,613,200; General Fund Special Project Reserves (Agency Road Trust) - $2,800 FY Budget: $1,616,000 Expenditures to Date: $ 131,000 $1,747,000 Total Project Estimate: $1,747,000

2 STREETS (Continued) Peyton Drive and English Channel Phase 3 S15009 Program Year Initiated: FY Construction Year: FY Project Description: The construction work for the Peyton Drive widening and English Channel improvements was completed in The remaining work to be done includes the environmental mitigation work for the English Channel (a requirement of the regulatory agencies) and an outstanding property acquisition. San Bernardino County Flood Control District Grant - $509,600; Community Facilities District (CFD) 2 - $1,220,200; SANBAG Nexus Grant - $1,000,000 FY Budget: $2,729,800 Expenditures to Date: $5,615,200 $8,345,000 Total Project Estimate: $8,345, Lower Los Serranos Street Light Improvements S16006 Program Year Initiated: FY Project Description: Install street lights, grind and AC cap on Mesa Blvd., Brookview Ct., and Monterey Ave. Community Development Block Grant (CDBG) FY Budget: $272,300 Expenditures to Date: $ 4,800 $277,100 Total Project Estimate: $277,100

3 STREETS (Continued) Fairfield Ranch Road Rehabilitation S17005 Program Year Initiated: FY Project Description: Pavement restoration and re-striping of Fairfield Ranch Road. Community Facilities District (CFD) 10 FY Budget: $394,800 Total Project Estimate: $394, Soquel Canyon Parkway Rehabilitation S17008 Program Year Initiated: FY Project Description: Pavement rehabilitation and re-striping, including buffered bike lane (grind 0.16 and AC overlay). Community Facilities District (CFD) 9 FY Budget: $2,456,600 Expenditures to Date: $ 43,400 $2,500,000 Total Project Estimate: $2,500, Installation of Countdown Pedestrian Signals S17009 Program Year Initiated: FY Project Description: Install signalized timers and pedestrian countdown heads at all signalized intersections city-wide. Highway Safety Improvement Program (HSIP) Grant - $114,400; Measure I - $23,000 FY Budget: $137,400 Total Project Estimate: $137,400

4 STREETS (Continued) Acquisition of Streetlights from SCE S17010 Program Year Initiated: FY Construction Year: FY Project Description: Purchase streetlights from SCE and upgrade the lighting with LED. General Fund FY Budget: $2,751,200 Total Project Estimate: $2,751, Street Improvement Program (Annual FY ) Construction Year: Annual Project Project Description: Annual overlay and/or slurry seal various City streets pursuant to the City s Pavement Management Program. Measure I FY Budget: $1,250,000 Total Project Estimate: $1,250, Sidewalk Replacement Program (Annual FY ) Construction Year: Annual Project Project Description: Annual program to replace damaged sidewalk throughout the City. Measure I FY Budget: $150,000 Total Project Estimate: $150,000

5 STREETS (Continued) Striping Program (Annual FY ) Construction Year: Annual Project Project Description: Annual maintenance of striping and pavement markings throughout the City. Measure I FY Budget: $75,000 Total Project Estimate: $75, Traffic Signal LED Replacement Program (Annual FY ) Construction Year: Annual Project Project Description: This program will systematically replace traffic signal LED lenses over seven years. Sixth year of a seven-year program. Measure I FY Budget: $30,000 Total Project Estimate: $30, Traffic Signal Controller Upgrade Program (Bi-annual FY ) Project Description: Provide funds to systematically replace and/or upgrade traffic signal controllers which are becoming technologically obsolete. Measure I FY Budget: $25,000 Total Project Estimate: $25,000

6 STREETS (Continued) Speed Feedback Signs Project Description: Install two speed feedback signs at Rock Springs Drive and one at Los Serranos Boulevard between Pipeline Avenue and Valle Vista Drive. Gas Tax 7360 Fund FY Budget: $21,000 Total Project Estimate: $21, Pavement Repairs Project Description: Repair subsided pavement area within the streets of Chino Avenue, Eagle Canyon Drive, and Olympic View Drive and repair settled and cracked curb/gutter on Feldspar Drive. Gas Tax 7360 Fund FY Budget: $660,000 Total Project Estimate: $660,000

7 PUBLIC FACILITIES City Yard Rehabilitation Phase 3 F17001 Program Year Initiated: FY Project Description: Replace worn Formica countertops with granite in restrooms and breakroom. Enhance security of storage bins with new openers/doors. Replace burned-out security lighting. Upgrade kitchen. General Fund - $3,700; P&L Administration - $6,900; Water Utility Fund - $15,000; Sewer Utility Fund - $4,400 FY Budget: $30,000 Total Project Estimate: $30,000 City Yard A/C Recovery and Modernization Project Description: Install seven new packaged A/C units to replace units that are at the end of their service life. Re-zone the lobby and conference room to adequately ventilate. Install BACNET energy management integration to improve energy use and scheduling. General Fund - $6,000; P&L Administration - $11,500; Water Utility Fund - $25,000; Sewer Utility Fund - $7,500 FY Budget: $50,000 Total Project Estimate: $50,000 City Yard Gate Upgrade Project Description: Install seven foot tall rolling gate and new gate controller. General Fund - $4,800; P&L Administration - $9,200; Water Utility Fund - $20,000; Sewer Utility Fund - $6,000 FY Budget: $40,000 Total Project Estimate: $40,000

8 PUBLIC FACILITIES (Continued) City Yard Parking Lot Expansion and Slurry Seal Project Description: Install 11 new parking spaces in front lot. Slurry seal all parking area. General Fund - $10,200; P&L Administration - $19,600; Water Utility Fund - $42,500; Sewer Utility Fund - $12,700 FY Budget: $85,000 Total Project Estimate: $85,000 Transfer Station Project Description: Convert one acre of Pinehurst Park to be utilized as a transfer station for the green waste and road repair spoils. Pave, fence, and install bins for storage of materials for the Public Works operations. General Fund - $25,000; P&L Administration - $75,000; Water Utility Fund - $70,000; Sewer Utility Fund - $30,000 FY Budget: $200,000 Total Project Estimate: $200,000 Automatic License Plate Readers Project Description: Installation of Automatic License Plate Readers at approximately 11 intersections. General Fund FY Budget: $1,000,000 Total Project Estimate: $1,000,000

9 PARKS/OPEN SPACE Los Serranos Park Program Year Initiated: FY Project Description: Development of a community park in the Los Serranos neighborhood, including environmental, design, and construction. General Fund - $1,964,300; P&R Facilities Fee - $750,000; Quimby Fund - $750,000; Community Facilities District (CFD) 5 - $130,000 FY Budget: $3,594,300 Expenditures to Date: $ 74,500 $3,668,800 Total Project Estimate: $3,668,800 English Springs Park Restroom Program Year Initiated: FY Project Description: Construction of additional restroom facilities at English Springs Park. Part of the Park Construction Improvement Program. Community Facilities District (CFD) 2 FY Budget: $342,300 Expenditures to Date: $ 7,700 $350,000 Total Project Estimate: $350,000

10 PARK/OPEN SPACE (Continued) Community Park Overflow Parking Lot Project Description: Improve a portion of the lot on the southwest corner of Peyton Drive and Eucalyptus Avenue to accommodate overflow parking from Chino Hill Community Park and install landscape and trail fencing on the northwest and southwest corners of Peyton Drive and Eucalyptus Avenue. Community Facilities District (CFD) 2 FY Budget: $412,000 Total Project Estimate: $412,000 Veteran Park Indentation Project Description: Construct a vehicle indentation for parking on Eucalyptus Avenue. Community Facilities District (CFD) 2 FY Budget: $120,000 Total Project Estimate: $120,000 Grand Avenue Park Artificial Turf Installation Project Description: Convert the existing grass soccer fields into artificial turf. Elements of the project include demo of existing grass, grading, installation of drainage and new base stone, installation of new curbs and header. Community Facilities District (CFD) 1 - $21,400; CFD 2 - $66,900; CFD 4 - $1,436,200; CFD 6 - $214,300; CFD 8 - $61,200 FY Budget: $1,800,000 Total Project Estimate: $1,800,000

11 PARKS/OPEN SPACE (Continued) Torrey Pines Park Rehab Project Description: Remove gazebo and equestrian ring. Add tennis court and playground. Rehab landscaping and parking lot. General Fund FY Budget: $350,000 Total Project Estimate: $350,000 Tree Planting Project Project Description: Plant trees in various locations throughout the City. General Fund Special Project Reserves - $37,600; Protected Tree Replacement Fund - $4,500 FY Budget: $42,100 Total Project Estimate: $42,100

12 WATER Supervisory Control & Data Acquisition System (SCADA) - Water Program Year Initiated: FY Construction Year: Ongoing Project Description: This project will expand/modify the citywide telemetry system for water facilities. Water Facilities Fee Fund FY Budget: $266,000 Expenditures to Date: $510,100 $766,100 Total Project Estimate: $766,100 Well 16 ASR Project W08001 Program Year Initiated: FY Construction Year: FY Project Description: Aquifer Storage Recovery (ASR) at Well 16; includes system connection as necessary. Chino Basin Watermaster Grant - $95,300; Water Utility Fund - $235,600 FY Budget: $330,900 Expenditures to Date: $500,200 $831,100 Total Project Estimate: $831,100 Reservoir No. 18 W11004 Program Year Initiated: FY Project Description: Construct a new domestic water reservoir in the H1 pressure zone. Water Facilities Fee Fund FY Budget: $7,373,600 Expenditures to Date: $ 151,100 $7,524,700 Total Project Estimate: $7,524,700

13 WATER (Continued) Chlorination Station W12004 Program Year Initiated: FY Project Description: Add four hypochlorite stations located at booster facilities. Water Utility Fund FY Budget: $100,000 Total Project Estimate: $100,000 R-19 Electrical W13003 Program Year Initiated: FY Project Description: Bring electrical service to the R-19/R-20 Reservoir site to support cathodic protection. Water Utility Fund FY Budget: $50,000 Total Project Estimate: $50, Saddle Replacement W17001 Program Year Initiated: FY Project Description: Replace approximately 1,156 saddles and service lines on 8 PVC pipeline. Area includes Ficus Street and surrounding streets. Water Utility Fund FY Budget: $2,687,000 Total Project Estimate: $2,687,000

14 RECYCLED WATER R-40 Rehabilitation W13004 Program Year Initiated: FY Project Description: Drain, scrape and repaint interior of Reservoir R-40 and install cathodic protection to preclude future tank damage. Water Utility Fund FY Budget: $150,000 Total Project Estimate: $150,000

15 SEWER Pipeline Avenue Sewer Manhole Access Road D08002 Program Year Initiated: FY Project Description: Construct access road to sewer line manhole from Pipeline Avenue south of Country Club Drive. Sewer Utility Fund FY Budget: $200,000 Expenditures to Date: $ 1,400 $201,400 Total Project Estimate: $201, Butterfield Ranch Lift Station D10001 Program Year Initiated: FY Project Description: Install telemetry system including pump controls and alarming features. Sewer Utility Fund FY Budget: $379,700 Expenditures to Date: $ 20,300 $400,000 Total Project Estimate: $400, Pomona Rincon Lift Station Upgrade D10002 Program Year Initiated: FY Project Description: Upgrade existing facility with new pumps, additional telemetry, level sensing system, flow meter, and modifications to wet well as identified in the Pomona Rincon Lift Station Evaluation Study. Sewer Utility Fund FY Budget: $450,500 Expenditures to Date: $ 35,500 $486,000 Total Project Estimate: $486,000

16 SEWER (Continued) Supervisory Control & Data Acquisition System (SCADA) - Sewer D11002 Program Year Initiated: FY Construction Year: Ongoing Project Description: This project will expand/modify the citywide telemetry system for sewer facilities. Sewer Facilities Fee Fund FY Budget: $1,147,600 Expenditures to Date: $ 62,500 $1,210,100 Total Project Estimate: $1,210, Repair of Sewer on Boys Republic and Grand Avenue D13002 Program Year Initiated: FY Project Description: Correct deficient elevation and routing problem on existing sewer line and re-grout manhole. Sewer Utility Fund FY Budget: $75,000 Total Project Estimate: $75, Video of Sewer Lines Project Description: Multiple years project to video all sewer lines in the City to satisfy legal requirement. This is the first year of the 5-year program. Sewer Utility Fund FY Budget: $500,000 Total Project Estimate: $1,375,000

17 STORM DRAINS Los Serranos Channel Mitigation Project Program Year Initiated: FY Construction Year: Ongoing Project Description: A mitigation project to create nine acres of wildlife habitat. Funding includes mitigation monitoring. General Fund FY Budget: $ 308,300 Expenditures to Date: $1,074,500 $1,382,800 Total Project Estimate: $1,382,800

Capital Improvement Project Profile Fiscal Year

Capital Improvement Project Profile Fiscal Year Capital Improvement Projects Transportation Fund Funding Sources: Measure I TDA Federal-State-County Grants Transportation DIF Transportation Fund 237 Pine Avenue Connection Project ST061 - G7016 - C7011-8745

More information

Capital Projects CAPITAL PROJECTS CAPITAL PROJECTS

Capital Projects CAPITAL PROJECTS CAPITAL PROJECTS Capital Projects CAPITAL PROJECTS CAPITAL PROJECTS 121 REVENUE FUNDS REVENUE FUND REFERENCE NUMBERS AND DESCRIPTIONS: 01 - General Fund This fund is the primary fund for the City. In addition to Capital

More information

BUDGET WORKSHOP CIP PRESENTATION

BUDGET WORKSHOP CIP PRESENTATION BUDGET WORKSHOP CIP PRESENTATION FISCAL YEAR 2016-17 FISCAL YEAR 2017-18 May 23, 2016 1 PRESENTATION OVERVIEW 1)CIP Development Process 2)Funding 3)Recent & Current CIP 4)7-Year proposal 5)Year 1 & 2 proposals

More information

PUBLIC WORKS CIP Quarterly Update Year 17~Volume II

PUBLIC WORKS CIP Quarterly Update Year 17~Volume II Capital Improvement Program Quarterly Report July 2017 2 0 1 7 Department of Public Works PUBLIC WORKS CIP Quarterly Update Year 17~Volume II 1 Introduction The Public Works Department s mission is improvement

More information

TAUSSIG. Annual Report Fiscal Year City of Irvine Community Facilities District No (Great Park) & Associates, Inc.

TAUSSIG. Annual Report Fiscal Year City of Irvine Community Facilities District No (Great Park) & Associates, Inc. DAVID TAUSSIG & Associates, Inc. Annual Report Fiscal Year 2016-2017 City of Irvine Community Facilities District No. 2013-3 (Great Park) September 26, 2017 Public Finance Public Private Partnerships Urban

More information

TAUSSIG. Annual Report Fiscal Year City of Irvine Community Facilities District No (Great Park) & Associates, Inc.

TAUSSIG. Annual Report Fiscal Year City of Irvine Community Facilities District No (Great Park) & Associates, Inc. DAVID TAUSSIG & Associates, Inc. Annual Report Fiscal Year 2014-2015 City of Irvine Community Facilities District No. 2013-3 (Great Park) October 27, 2015 Public Finance Public Private Partnerships Urban

More information

Central Ave Sidewalk/Access Ramps-7th St/Riverside Dr Imp. G Fund 321-TDA Article 3 Grant 322 Fund 322-Measure I

Central Ave Sidewalk/Access Ramps-7th St/Riverside Dr Imp. G Fund 321-TDA Article 3 Grant 322 Fund 322-Measure I Number Fund Description Transportation Group Street Category ST061 Pine Avenue Connection 320 Fund 220 Transfer-B/S/T Citywide 320 Fund 320-SAFETEA-LU-80% 320 Fund 260 Transfer- B/S/T Preserve DIF ST151

More information

Capital Improvement Program. Fiscal Years

Capital Improvement Program. Fiscal Years Capital Improvement Program Fiscal Years 2014-2021 1 Capital Improvement Program Fiscal Years 2014-2021 Agenda Background Significant Accomplishments (2012-2014) Proposed Work Plan (2014-2016) and 7- Year

More information

Capital Improvement Projects

Capital Improvement Projects Capital Improvement Projects CAPITAL IMPROVEMENT PROGRAM Introduction The Capital Improvement Program (CIP) is a coordinated program for maintenance and development of the City infrastructure system. The

More information

Capital Improvement Projects

Capital Improvement Projects Capital Improvement Projects This section highlights the Capital Improvement Program (CIP) projects proposed for FY 2017-2018. Capital projects are designed to enhance the City s infrastructure, extend

More information

City of Chino Five-Year Capital Improvement Program Budget Fiscal Years through

City of Chino Five-Year Capital Improvement Program Budget Fiscal Years through City of Chino Five-Year Capital Improvement Program Budget Fiscal Years 2015-16 through 2019-20 The Five-Year Capital Improvement Program budget for FY15-16 has a new look. The CIP projects have a new

More information

Infrastructure Asset Management. Southwest Chula Vista Civic Association April 26, 2007

Infrastructure Asset Management. Southwest Chula Vista Civic Association April 26, 2007 Infrastructure Asset Management Southwest Chula Vista Civic Association April 26, 2007 Chula Vista s Municipal Infrastructure Pavement* Traffic Signals Alleys Streetlights Parking Lots Street Signs Sidewalks*

More information

SPECIAL COUNCIL MEETING MARCH 6, Capital Improvements

SPECIAL COUNCIL MEETING MARCH 6, Capital Improvements SPECIAL COUNCIL MEETING MARCH 6, 2012 Capital Improvements 1 CAPITAL PROJECTS Review Requests from the Departments for FY 2012-13 Capital Improvements and Machinery & Equipment Discussion and Recommendations

More information

CITY COUNCIL STAFF REPORT

CITY COUNCIL STAFF REPORT CITY COUNCIL STAFF REPORT TO: Honorable Mayor and City Council DATE: March 19, 2018 FROM: PREPARED BY: SUBJECT: Matthew Bronson, City Manager Greg Ray, Public Works Director/City Engineer Capital Improvement

More information

Capital Investment Program (CIP) About CIP

Capital Investment Program (CIP) About CIP Capital Investment Program (CIP) About CIP The Capital Investment Program (CIP) is a multi-year program aimed at upgrading and expanding City facilities, buildings, grounds, streets, parks and roads. The

More information

Public Works and Development Services

Public Works and Development Services City of Commerce Capital Improvement Program Prioritization Policy Public Works and Development Services SOP 101 Version No. 1.0 Effective 05/19/15 Purpose The City of Commerce s (City) Capital Improvement

More information

CAPITAL PROJECTS BUDGET TAB 5

CAPITAL PROJECTS BUDGET TAB 5 CAPITAL PROJECTS BUDGET TAB 5 This page intentionally left blank. 2016-2018 CAPITAL BUDGET 5-1 This page intentionally left blank. City of Walnut Creek 2016-2018 Capital Budget Table of Contents Introduction

More information

CAPITAL IMPROVEMENT PROGRAM SUMMARY

CAPITAL IMPROVEMENT PROGRAM SUMMARY CAPITAL IMPROVEMENT PROGRAM SUMMARY The purpose of the CIP Budget is to serve as a planning tool, which coordinates the financing and scheduling of major projects undertaken by the City. The CIP Budget

More information

City of Clovis Date completed or revised: September 26, 2014

City of Clovis Date completed or revised: September 26, 2014 Date completed or revised: September 26, 2014 Completed by: (print) Renee Mathis The anticipated Fiscal Year 2014-15 revenue allocation for Street Maintenance sub-program: $912,013 X Street Maintenance

More information

Capital Improvement Program

Capital Improvement Program 2015 2016 Capital Improvement Program City of Perris Capital Project Listing Prepared As of December 31, 2015 Prior Year Proposed Carryover Mid-Year Amend 2015-2016 July 1, 2015 2015-2016 Budget Streets

More information

CAPITAL IMPROVEMENT PROJECTS CAPITAL PROJECTS FUND FISCAL YEAR 2013/2014 PROJECTS SCHEDULED FOR CONSTRUCTION. Local Option Sales Tax Funds $ 500,000

CAPITAL IMPROVEMENT PROJECTS CAPITAL PROJECTS FUND FISCAL YEAR 2013/2014 PROJECTS SCHEDULED FOR CONSTRUCTION. Local Option Sales Tax Funds $ 500,000 CAPITAL IMPROVEMENT PROJECTS CAPITAL PROJECTS FUND FISCAL YEAR 2013/2014 PROJECTS SCHEDULED FOR CONSTRUCTION On-Going Pavement Management Program: In 2009/2010 the city completed the initial 3-year plan

More information

City of San Juan Capistrano Age eport

City of San Juan Capistrano Age eport 6/19/2014 C1 City of San Juan Capistrano Age eport TO: FROM: DATE: SUBJECT: Karen P. Brust, City a Cindy Russell, Chief Financial Officer/City Treasure~~ Prepared by: Michelle Bannigan, Assistant Finance

More information

Capital Improvement Program

Capital Improvement Program Capital Improvement Program For Fiscal Year 2017-2018 City of Perris Capital Improvement Projects Summary Code Fund # Name of Project Page "Storm Drain" Projects D002 160 MASTER PLAN PERRIS VALLEY STORM

More information

Region 5 Upcoming Projects for Summer/Fall 2018

Region 5 Upcoming Projects for Summer/Fall 2018 Region 5 Upcoming Projects for Summer/Fall 2018 The budget amount provided does not reflect the construction costs for projects. The amounts may include ROW, engineering, design, and utility costs. The

More information

This page intentionally left blank

This page intentionally left blank 197 This page intentionally left blank 198 Capital Improvement Program PROCEDURE Each year the Capital Improvement Program (CIP) is prepared from project requests submitted by the various departments.

More information

Budget Public Hearing 6/16/2015

Budget Public Hearing 6/16/2015 Agenda Brea Community Benefit Financing Authority Budget FY 2014-15 Operating Budget Successor Agency Budget Brea Public Financing Authority Budget Brea Community Benefit Financing Authority Budget Midbury

More information

2015 Financial Assurance 8/6/2015 Estimate Form (with pre-plat construction)

2015 Financial Assurance 8/6/2015 Estimate Form (with pre-plat construction) 2015 Financial Assurance 8/6/2015 Estimate Form (with pre-plat construction) Project Information The Glen at Widefield Filing No. 9 PDD File: SF-185 9/25/2018 Project Name Section 1 - Grading and Erosion

More information

DRAFT C APITAL I MPROVEMENT P LAN C ITY OF G EORGETOWN, TEXAS S TREETS/ DRAINAGE/AIRPORT F ISCAL Y EAR 201 6

DRAFT C APITAL I MPROVEMENT P LAN C ITY OF G EORGETOWN, TEXAS S TREETS/ DRAINAGE/AIRPORT F ISCAL Y EAR 201 6 C ITY OF G EORGETOWN, TEXAS C APITAL I MPROVEMENT P LAN S TREETS/ DRAINAGE/AIRPORT F ISCAL Y EAR 201 6 Georgetown Transportation Advisory Board April 10, 2015 Table of Contents Introduction... 1 Transportation

More information

CIP. PUBLIC WORKS DEPARTMENT Timm Borden, Director

CIP. PUBLIC WORKS DEPARTMENT Timm Borden, Director PUBLIC WORKS DEPARTMENT Timm Borden, Director CITY HALL 10300 TORRE AVENUE ~ CUPERTINO, CA 95014-3266 (408) 777-3354 ~ FAX (408) 777-3333 CIP 2015-2016 Budget report of the Capital Improvement Program

More information

Carroll County Maryland. Community Investment Plan Request Fiscal Years

Carroll County Maryland. Community Investment Plan Request Fiscal Years Carroll County Maryland Community Investment Plan Request Fiscal Years 2019-2024 PRODUCED BY The Department of Management and Budget Ted Zaleski... Director Deborah Effingham... Chief, Bureau of Budget

More information

Capital Improvement Program

Capital Improvement Program Capital Improvement Program May 14, 2015 KEN KNATZ, P.E. PRINCIPAL CIVIL ENGINEER FY 2015 Current CIP Status Maintenance Projects, $13.9M CIP Projects, $30.5M Total FY 2015 CIP: $44.4 M 2 Courtney s Sand

More information

Projects Receiving New Funding by. Funding Source and Project Number

Projects Receiving New Funding by. Funding Source and Project Number 20172022 Approved Capital Improvement Program s Receiving New Funding by Funding Source and Number 1001 GENERAL FUND A04000100 A07000300 A07000400 CITY CLER AUTOMATION IT EQUIPMENT REPLACEMENT CITYWIDE

More information

CITY OF PARKLAND ANALYSIS OF REVENUES/SOURCES AND EXPENDITURES/USES GENERAL FUND

CITY OF PARKLAND ANALYSIS OF REVENUES/SOURCES AND EXPENDITURES/USES GENERAL FUND GENERAL FUND % Change From 2018 Locally Levied Taxes Property Taxes 16,246,790 17,496,916 17,702,458 21,004,985 3,508,069 20.0% Franchise Fee - Electricity - - 398,767 1,900,000 1,900,000 n/a Franchise

More information

City of SANTA ANA. Proposed Budget Summary FY

City of SANTA ANA. Proposed Budget Summary FY City of SANTA ANA Proposed Budget Summary FY 2015-2016 June 2, 2015 City Manager s Budget Message will be made available on May 29 th, 2015. This Page Intentionally Left Blank Total Annual Budget FY 2015-2016

More information

Proposed Capital Improvement Programs and existing programs

Proposed Capital Improvement Programs and existing programs Proposed Capital Improvement Programs and existing programs The Capital Improvement Program is a listing of proposed and existing projects for the acquisition and construction of general government resources

More information

CITY OF POMONA. Financial Update Community Meetings

CITY OF POMONA. Financial Update Community Meetings CITY OF POMONA Financial Update Community Meetings TONIGHTS PRESENTATION 1 Historical Outlook 2 2019 Operating Budget 3 UFI Recommendations 4 CIP Budget Millions POMONA S HISTORICAL OUTLOOK $110 General

More information

CITY OF CHINO ENGINEERING COST ESTIMATE. Quantity Unit Item Unit Total Cost Price Per Item. LS Traffic Control (5% of construction cost) 5% $

CITY OF CHINO ENGINEERING COST ESTIMATE. Quantity Unit Item Unit Total Cost Price Per Item. LS Traffic Control (5% of construction cost) 5% $ RESOLUTION NO 2015078 STREETS LS Traffic Control (5% of construction cost) 5% $ LS Clear & Grub Site (5% of construction cost) 5% $ EA Tree Removal $ 800.00 $ CY Concrete Removal $ 300.00 $ CY AC Pavement

More information

Local Option Sales Tax Report Card Your Penny At Work. District 4

Local Option Sales Tax Report Card Your Penny At Work. District 4 Local Option Sales Tax Report Card Your Penny At Work District 4 Local Option Sales Tax 2007-2017 Report Card Your Penny At Work Transportation $153,816,450 Public Facilities $50,384,889 Natural Resources/

More information

CITY OFANAHEIM. Community Services Department. FY 2017/18Proposed Budget. June 6, Operating Budget & Capital Improvement Program

CITY OFANAHEIM. Community Services Department. FY 2017/18Proposed Budget. June 6, Operating Budget & Capital Improvement Program CITY OFANAHEIM FY 2017/18Proposed Budget Community Services Department June 6, 2017 Operating Budget & Capital Improvement Program Overview Core Services Proposed Budget Summary Personnel Notable Changes

More information

AGENDA STATUS OF CURRENT YEAR BUDGET FY 19 CURRENT PROJECTIONS REVIEW FIVE-YEAR CAPITAL IMPROVEMENT PROGRAM REVIEW CITY COUNCIL WORK PLAN

AGENDA STATUS OF CURRENT YEAR BUDGET FY 19 CURRENT PROJECTIONS REVIEW FIVE-YEAR CAPITAL IMPROVEMENT PROGRAM REVIEW CITY COUNCIL WORK PLAN AGENDA STATUS OF CURRENT YEAR BUDGET FY 19 CURRENT PROJECTIONS FOCUS ON COSTS CALPERS UPDATE REVIEW FIVE-YEAR CAPITAL IMPROVEMENT PROGRAM REVIEW CITY COUNCIL WORK PLAN ANSWER QUESTIONS ABOUT DEPARTMENT

More information

City of Lake Elsinore, California. Capital Improvement Plan Budget FY to FY

City of Lake Elsinore, California. Capital Improvement Plan Budget FY to FY City of Lake Elsinore, California Capital Improvement Plan Budget FY2016-17 to FY2020-21 1 2 Capital Improvement Plan Budget Fiscal Years 2016-2021 City Council Brian Tisdale, Mayor Robert E. Magee, Mayor

More information

FY 2017 FY 2021 Capital Improvement Program (CIP) Executive Summary

FY 2017 FY 2021 Capital Improvement Program (CIP) Executive Summary FY 2017 FY 2021 Capital Improvement Program (CIP) Executive Summary The adopted FY 2017 FY 2021 CIP is $235.8 million (including prior year expenditures) and is $28 million higher than the previous CIP

More information

City of Pacifica General Fund Budget

City of Pacifica General Fund Budget City of Pacifica 2017-18 General Fund Budget General Government Lorenzo Hines Jr. City Manager s Office May 2, 2017 City of Pacifica 1 General Government 2017-18 DRAFT Budget Mission We strive to manage

More information

Christopher Blunk, Deputy Director Public Works/City Engineer. PRESENTER: Christopher Blunk, Deputy Director Public Works/City Engineer

Christopher Blunk, Deputy Director Public Works/City Engineer. PRESENTER: Christopher Blunk, Deputy Director Public Works/City Engineer STAFF REPORT MEETING DATE: April 10, 2018 TO: FROM: City Council Christopher Blunk, Deputy Director Public Works/City Engineer PRESENTER: Christopher Blunk, Deputy Director Public Works/City Engineer 922

More information

TRANSPORTATION CAPITAL PROGRAM

TRANSPORTATION CAPITAL PROGRAM TRANSPORTATION CAPITAL PROGRAM The transportation capital program for fiscal year 2016 through fiscal year 2020 consists of a variety of transportation construction and maintenance capital projects primarily

More information

Memo. To: Mayor Lee Gray Members of Council City Manager Bill Vance. From: Scott Tourville. Project: 2015 CIP Budget Update CC:

Memo. To: Mayor Lee Gray Members of Council City Manager Bill Vance. From: Scott Tourville. Project: 2015 CIP Budget Update CC: To: Mayor Lee Gray Members of Council City Manager Bill Vance Memo From: Scott Tourville Project: 2015 CIP Budget Update CC: C. Schornack S. Spencer File Date: November 21, 2014 RE: Updated 2015 CIP Plan

More information

Capital Improvement Program

Capital Improvement Program June 1, 2015 EXECUTIVE SUMMARY AND ANALYSIS The proposed 2015-2017 Capital Improvement Program includes an appropriation of $101,522,000 in expenditures over a two year period for Fiscal Years 2015-2016

More information

REVISED ENGINEER'S REPORT ASSESSMENT DISTRICT NO OF THE CITY OF SAN JACINTO

REVISED ENGINEER'S REPORT ASSESSMENT DISTRICT NO OF THE CITY OF SAN JACINTO REVISED ENGINEER'S REPORT ASSESSMENT DISTRICT NO. 2003-1 OF THE CITY OF SAN JACINTO December 11, 2003 REVISED ENGINEER'S REPORT ASSESSMENT DISTRICT NO. 2003-1 CITY OF SAN JACINTO Prepared for CITY OF SAN

More information

UNINCORPORATED CAPITAL

UNINCORPORATED CAPITAL UNINCORPORATED CAPITAL The total funding to be appropriated for the unincorporated capital program in FY13 is $13,665,000. This reflects funds committed to drainage, pavement, sidewalk, and other infrastructure

More information

FY 2016 FY 2020 Capital Improvement Program (CIP) Executive Summary

FY 2016 FY 2020 Capital Improvement Program (CIP) Executive Summary FY 2016 FY 2020 Capital Improvement Program (CIP) Executive Summary The adopted FY 2016 FY 2020 CIP is $205.3 million (including prior year expenditures) and is $2.9 million lower than the previous CIP

More information

PROPOSED TEN-YEAR CAPITAL IMPROVEMENT PLAN

PROPOSED TEN-YEAR CAPITAL IMPROVEMENT PLAN 2017/2018 YEAR 1 ESTIMATED FUND BALANCE 7/1/17 $ 1,795,000 $ - $ 209,000 $ 117,861 $ (333,878) $ (240,844) $ 642,513 $ (113,143) EXPECTED REVENUE ACTIVITY $ 1,014,000 $ 33,473 $ 49,500 $ - $ - $ - $ -

More information

MEASURE B AND MEASURE BB Annual Program Compliance Report Reporting Fiscal Year AGENCY CONTACT INFORMATION

MEASURE B AND MEASURE BB Annual Program Compliance Report Reporting Fiscal Year AGENCY CONTACT INFORMATION MEASURE B AND MEASURE BB Annual Program Compliance Report Reporting Fiscal Year 20172018 AGENCY CONTACT INFORMATION Agency Name: City of Fremont Date: 12/21/2018 Primary Point of Contact Name: Tish Saini

More information

Stephanie Smith, Project EngineerW

Stephanie Smith, Project EngineerW MEMORANDUM v TO: Paul Oehme, Director of Public Works/ City Engineer o FROM: Stephanie Smith, Project EngineerW 7700 Market Boulevard PO Box 147 Chanhassen, MN 55317 Administration Phone: 9522271100 Fax

More information

City of Vacaville FY 2017/2018 CIP Budget, General Plan Consistency and CEQA Review Parks and Recreation

City of Vacaville FY 2017/2018 CIP Budget, General Plan Consistency and CEQA Review Parks and Recreation Parks and Recreation Park & Recreation Housing 14160 Grant Total Fund Balance $3,916,598 $3,916,598 Prior Budget Commitments ($2,770,788) ($2,770,788) Other Budget Commitments ($126,482) ($126,482) Other

More information

RECEIVE A REPORT AND APPROVE PROPOSED PUBLIC ENGAGEMENT POLICIES AND PRACTICES FOR THE PUBLIC

RECEIVE A REPORT AND APPROVE PROPOSED PUBLIC ENGAGEMENT POLICIES AND PRACTICES FOR THE PUBLIC J-17 STAFF REPORT MEETING DATE: October 24, 2017 TO: City Council FROM: Russ Thompson, Public Works Director PRESENTER: Russ Thompson, Public Works Director SUBJECT: RECEIVE A REPORT AND APPROVE PROPOSED

More information

PROJECT COST. Prepared for City of Burlington, Iowa Downtown/Riverfront Revitalization Project

PROJECT COST. Prepared for City of Burlington, Iowa Downtown/Riverfront Revitalization Project PROJECT COST Prepared for City of Burlington, Iowa Downtown/Riverfront Revitalization Project City of Burlington Downtown/Riverfront Revitalization Project TIGER Grant Budget Date: 4/29/2016 Project Budget

More information

CITY COUNCIL FY 2018/2019 BUDGET WORKSHOP

CITY COUNCIL FY 2018/2019 BUDGET WORKSHOP CITY COUNCIL FY 2018/2019 BUDGET WORKSHOP Presented by: David Kelley, City Manager Susie Holmes, Finance Manager Stephen Cramer, Police Chief Mark Rincon, City Engineer Budget Presentation - Outline 1.

More information

BID TABULATION REPORT ABRAM STREET (SH CITY LIMITS) PROJECT No. PWST09016 BID OPENED : April 22, 2014 at 1:30 p.m.

BID TABULATION REPORT ABRAM STREET (SH CITY LIMITS) PROJECT No. PWST09016 BID OPENED : April 22, 2014 at 1:30 p.m. PAVING IMPROVEMENTS 101 Mobilization and Bonds, LS 1 $ 225,000.00 $ 225,000.00 $ 225,000.00 $ 225,000.00 $ 225,000.00 $ 225,000.00 $ 225,000.00 $ 225,000.00 102 Right-of-way Preparation LS 1 $ 365,500.00

More information

Capital Improvement Plan City of Rye, New York

Capital Improvement Plan City of Rye, New York 20182022 Capital Improvement Plan City of Rye, New York Planning and Funding For City Projects For Fiscal Years Ending December 31, 2018 through 2022 September 2017 Capital Improvement Plan 20182022 TABLE

More information

Preliminary Budget Overview General Fund Revenues/Expenditures

Preliminary Budget Overview General Fund Revenues/Expenditures June 11, 2018 Preliminary Budget Overview General Fund Revenues/Expenditures Law Enforcement IT Agency Requests Capital Projects Retirement Costs Capital Projects Water Fund Wastewater Fund Fiscal Year

More information

Building Better Parks: An Asset Management Plan for Parks

Building Better Parks: An Asset Management Plan for Parks Header Title Attachment 1 Building Better Parks: An Asset Management Plan for Parks 2 JULY 2016 INTRODUCTION The s (City) parks inventory is composed of a variety of asset sub-classes that include but

More information

City Council Report 915 I Street, 1 st Floor Sacramento, CA

City Council Report 915 I Street, 1 st Floor Sacramento, CA City Council Report 915 I Street, 1 st Floor Sacramento, CA 95814 www.cityofsacramento.org File ID: 2017-01623 January 9, 2018 Consent Item 04 Title: Mitigation Fee Act Annual Report for the Year Ending

More information

Where the Money Goes (Uses) FY 2011

Where the Money Goes (Uses) FY 2011 Capital Expenditure Analysis The total FY2011 capital budget for the Village of Orland Park is $23,650,283, a 33% decrease from the fiscal year 2010 adopted capital budget of $31,446,027. The decrease

More information

Budget Narrative Page 4. Fiscal Year

Budget Narrative Page 4. Fiscal Year CITY OF CARSON FISCAL YEAR 2017-18 (FY17-18) BUDGET NARRATIVE The reader of this narrative will have a good understanding of the City s budget structure, current budget challenges, and the future budget

More information

SUBDIVISION IMPROVEMENTS AGREEMENT

SUBDIVISION IMPROVEMENTS AGREEMENT SUBDIVISION IMPROVEMENTS AGREEMENT THIS AGREEMENT, made between GLEN DEVELOPMENT COMPANY, hereinafter called the "Subdivider," and El Paso County by and through the Board of County Commissioners of El

More information

CAPITAL IMPROVEMENT PLAN

CAPITAL IMPROVEMENT PLAN CAPITAL IMPROVEMENT PLAN Included in this section of the budget is the following information: General Capital Information CIP Development Process Sources of Funds and Financing Use of Funds Summary by

More information

2015 Budget. Public Works, Parks and Fleet Maintenance Departments

2015 Budget. Public Works, Parks and Fleet Maintenance Departments 2015 Budget Public Works, Parks and Fleet Maintenance Departments Public Works, Parks, & Fleet Maintenance Operations $179,750 $1,759,296 $1,496,292 $792,750 Works Operations Sewer Operations Water Operations

More information

Rock Chalk Park - Infrastructure Report. July 2013

Rock Chalk Park - Infrastructure Report. July 2013 Rock Chalk Park Infrastructure Report July 2013 The following report is the first monthly report for the construction of infrastructure at Rock Chalk Park. The format follows the sections outlined in the

More information

2. fl Concord REPORT TO MAYOR AND COUNCIL/AGENCY BOARD

2. fl Concord REPORT TO MAYOR AND COUNCIL/AGENCY BOARD AGENDA ITEM NO. 2. fl Concord REPORT TO MAYOR AND COUNCIL/AGENCY BOARD TO THE HONORABLE MAYOR AND COUNCIL: DATE: June 22, 2009 Subiect: ADOPTING RESOLUTION NO. 09-53, APPROVING THE CITY'S REVISED PROPOSITION

More information

PROPOSED FISCAL YEARS AND BUDGET WORKSHOP (CONT.)

PROPOSED FISCAL YEARS AND BUDGET WORKSHOP (CONT.) FISCAL YEARS 2012-2013 AND 2013-2014 BUDGET WORKSHOP (CONT.) 1 2 Property Tax Revenue FY 2011/12 FY 2012/13 FY 2013/14 FY 2011/12 Amended Budget Projected Budget Projected Budget As of May 25, 2012 Property

More information

IMPLEMENTATION A. INTRODUCTION C H A P T E R

IMPLEMENTATION A. INTRODUCTION C H A P T E R C H A P T E R 11 IMPLEMENTATION A. INTRODUCTION This chapter addresses implementation of the General Plan. The Plan s seven elements include 206 individual actions. 1 Many are already underway or are on-going.

More information

City of Rancho Cucamonga

City of Rancho Cucamonga City of Rancho Cucamonga Fiscal Year 2018/19 Proposed Budgets Budget Study Session June 7, 2018 Transition to the 21 st Century Are we in the midst of a long recovery or getting closer to the next downturn?

More information

FUNDING SOURCES Restricted vs. Un-Restricted Funding Sources Fund Balances and Projected Funding Availability IBank Loan

FUNDING SOURCES Restricted vs. Un-Restricted Funding Sources Fund Balances and Projected Funding Availability IBank Loan FUNDING SOURCES The following section discusses the major funding sources available to fund projects. ing amounts included in the s column are those that are available for use as of preparation of this

More information

CITY OF ROSEBURG, OREGON TABLE OF CONTENTS ENTERPRISE FUNDS

CITY OF ROSEBURG, OREGON TABLE OF CONTENTS ENTERPRISE FUNDS TABLE OF CONTENTS ENTERPRISE FUNDS Storm Drainage Fund... 121-124 Off Street Parking Fund... 125-126 Airport Fund... 127-131 Water Service Fund... 132-145 STORM DRAINAGE FUND CURRENT OPERATIONS This fund

More information

TRANSPORTATION EXECUTIVE SUMMARY

TRANSPORTATION EXECUTIVE SUMMARY EXECUTIVE SUMMARY The Sacramento County Department of Transportation (SACDOT) is responsible for improving, operating and maintaining the transportation infrastructure of the Unincorporated Area of the

More information

CITY OF JOPLIN FY 2018 PROPOSED BUDGET

CITY OF JOPLIN FY 2018 PROPOSED BUDGET CITY OF JOPLIN FY 2018 PROPOSED BUDGET CITY OF JOPLIN ESTIMATE OF NEEDS PROJECTED FUND BALANCES FOR FISCAL YEAR 2017-2018 Audited Projected Projected Fund Projected 2016-2017 Activity Fund Projected 2017-2018

More information

5-Year Capital Improvement Program 2018/ /2023

5-Year Capital Improvement Program 2018/ /2023 5-Year Capital Improvement Program 2018/2019-2022/2023 City Council Steve Miller, Mayor Jeannie Bruins, Vice Mayor Bret Daniels, Council Member Albert J. Fox, Council Member Jeff Slowey, Council Member

More information

CITY OF SAN JACINTO Capital Improvement Program Project Details

CITY OF SAN JACINTO Capital Improvement Program Project Details UNFUNDED CITY OF SAN JACINTO Capital Improvement Program Project Details Project Title: 2009 Downtown Pavement Rehabilitation Project Description: Pavement rehabilitation in downtown area. Similar to prior

More information

FISCAL YEAR RECOMMENDED BUDGET

FISCAL YEAR RECOMMENDED BUDGET FISCAL YEAR 2017-2018 RECOMMENDED BUDGET JUNE 6, 2017 AGENDA City Manager s Budget Status FY 2017-18 General Fund Recommended Budget FY 2017-18 Recommended Non-General Fund Budget FY 2017-18 Recommended

More information

PUBLIC WORKS - ENGINEERING

PUBLIC WORKS - ENGINEERING PUBLIC WORKS - ENGINEERING 4 DIVISIONS: CAPITAL IMPROVEMENT PROGRAM (CIP) TRAFFIC ENGINEERING DEVELOPMENT ENGINEERING SEWER & STORM DRAIN ENGINEERING 18 FTE s, 2 Hourly s In FY 14/15 Expended approximately

More information

CITY OF BRENTWOOD DEVELOPMENT IMPACT FEE PROGRAM 2015

CITY OF BRENTWOOD DEVELOPMENT IMPACT FEE PROGRAM 2015 CITY OF BRENTWOOD DEVELOPMENT IMPACT FEE PROGRAM 2015 TABLE OF CONTENTS Page Introduction. 1 Program Overview. 1 Fee Summary 2 Land Use Categories and Growth Projections. 3 Administration 5 Community Facilities

More information

The Three Planning Windows of Asset Management John Murray City of Hamilton May 9 th, 2012 CNAM - Montreal. Hamilton Asset Management Plan

The Three Planning Windows of Asset Management John Murray City of Hamilton May 9 th, 2012 CNAM - Montreal. Hamilton Asset Management Plan The Three Planning Windows of Asset Management John Murray City of Hamilton May 9 th, 2012 CNAM - Montreal 1 City of Hamilton Amalgamated - 2001 7 Area Municipalities Population 500,000 The City of Waterfalls

More information

Budget. One. Time Cost. Total

Budget. One. Time Cost. Total Service Enhancements General Fund Town of Los Altos Hills 2018 20 Budget Attachment 2 - Budget Service Enhancements/New Requests CIP and Capital Funds Town wide 15,072,124 (1,364,236) 13,707,888 932,967

More information

Village of Point Edward Asset Management Plan Page 1

Village of Point Edward Asset Management Plan Page 1 The existing infrastructure in the Village of Point Edward is aging and deteriorating. Over the next 50 years, much of the infrastructure will require replacement or rehabilitation. The Asset Management

More information

PRESENTATION OF PROPOSED BUDGET

PRESENTATION OF PROPOSED BUDGET PRESENTATION OF PROPOSED BUDGET CITY COUNCIL MEETING AUGUST 7, 2018 AGENDA Budget Process Budget Drivers and Areas of Focus Budget By Funds Revenues Operating Expenditure Highlights and Variances Tax Rate

More information

CAPITAL IMPROVEMENT PROGRAM BUDGET

CAPITAL IMPROVEMENT PROGRAM BUDGET CAPITAL IMPROVEMENT PROGRAM BUDGET During the Capital Improvement Program budget process, departments submit Project Request Forms for each project. The form captures the costs spent to date, five-year

More information

FUND STRUCTURE. Local Funding Prop s A&C Measure R Traffic Safety Quimby Street Lighting Parking M&O Comm. Invest. General Fund.

FUND STRUCTURE. Local Funding Prop s A&C Measure R Traffic Safety Quimby Street Lighting Parking M&O Comm. Invest. General Fund. A B F Y 2016 2017 S F, CA Budget Guide FUND STRUCTURE All Funds Governmental Major Funds General Fund Retirement Tax Operating Grants Other Special Revenue Funds Capital Grants Capital Projects Self-Sustaining

More information

East of Merle Hay Road

East of Merle Hay Road East of Merle Hay Road Johnston, Iowa 2017 APWA Spring Conference March 2017 Oldest neighborhood in the City Settled in 1846 Narrow rural corridor with aging or non-existent infrastructure Inadequate

More information

AUDIT COMMITTEE OF THE BOARD OF HARBOR COMMISSIONERS CAPITAL IMPROVEMENT PROGRAM REPORT

AUDIT COMMITTEE OF THE BOARD OF HARBOR COMMISSIONERS CAPITAL IMPROVEMENT PROGRAM REPORT AUDIT COMMITTEE THE PORT OF LOS ANGELES Report to the Board of Harbor Commissioners DATE: DECEMBER 10, 2015 TO: SUBJECT: AUDIT COMMITTEE OF THE BOARD OF HARBOR COMMISSIONERS CAPITAL IMPROVEMENT PROGRAM

More information

Fiscal Responsibility to Further Invest in the Future. Executive Committee Department of Finance May 4, 2017

Fiscal Responsibility to Further Invest in the Future. Executive Committee Department of Finance May 4, 2017 Fiscal Responsibility to Further Invest in the Future Executive Committee Department of Finance May 4, 2017 1 Asset Inventory Denver s Assets Parks and Recreation $1.8B Transportation $4.7B Buildings $1.9B

More information

DRAFT PROPOSED BUDGET THE GOOD, THE BAD AND THE UGLY (Part 2) City of Chico May 2, 2017

DRAFT PROPOSED BUDGET THE GOOD, THE BAD AND THE UGLY (Part 2) City of Chico May 2, 2017 DRAFT PROPOSED BUDGET 2017 18 THE GOOD, THE BAD AND THE UGLY (Part 2) City of Chico May 2, 2017 DRAFT PROPOSED BUDGET 2017 18 SCHEDULE May 2 nd Round #2 Community Development Public Works May 16 th Questions

More information

2019 BUDGET MESSAGE. September 18, Honorable Mayor and Town Council Members,

2019 BUDGET MESSAGE. September 18, Honorable Mayor and Town Council Members, 2019 BUDGET MESSAGE September 18, 2018 Honorable Mayor and Town Council Members, On behalf of Town staff, I am pleased to submit the 2019 Budget to Town Council and the community. The budget includes a

More information

CITY. RIALTO W w w. R I a l t o c a. g o v. Fiscal Year 2009/10 Interim Financial Report. 5 months ended November 30, 2009

CITY. RIALTO W w w. R I a l t o c a. g o v. Fiscal Year 2009/10 Interim Financial Report. 5 months ended November 30, 2009 CITY of RIALTO W w w. R I a l t o c a. g o v Fiscal Year 2009/10 Interim Financial Report 5 months ended November 30, 2009 To: The Mayor and City Council City Administrator From: Chief Financial Officer

More information

FY Capital Improvement Plan. Presented For Public Input and Review City Council Meeting September 21, 2015

FY Capital Improvement Plan. Presented For Public Input and Review City Council Meeting September 21, 2015 FY 2016 2020 Capital Improvement Plan Presented For Public Input and Review City Council Meeting September 21, 2015 Presented For City Council Adoption October 5, 2015 This page left blank intentionally

More information

City of San Juan Capistrano Agenda Report

City of San Juan Capistrano Agenda Report City of San Juan Capistrano Agenda Report TO: FROM: DATE: SUBJECT: Planning Commission Development Services Department /.-'""' ~~-" d'"~" {~"~/~,~ / Submitted by: William Ramsey, AICP, Assistant Direct~{

More information

NOTICE OF ELECTION 2021 $10,000, $10,000, $10,000, $10,000,000

NOTICE OF ELECTION 2021 $10,000, $10,000, $10,000, $10,000,000 NOTICE OF ELECTION TO THE QUALIFIED VOTERS OF DEKALB COUNTY, GEORGIA NOTICE IS HEREBY GIVEN that on the 7 th day of November, 2017, an election will be held at the regular polling places in all of the

More information

Capital Improvement Program. FY Adopted Biennial Budget

Capital Improvement Program. FY Adopted Biennial Budget Capital Improvement Program FY 2013-15 Adopted Biennial Budget Program Summary FY 2013-14 through FY 2017-18 Capital Improvement Program Last year the City of Santa Monica developed its first biennial

More information

Baytree Community Development District

Baytree Community Development District Adopted Budget FY 2017 Presented by: Table of Contents 1-10 General Fund 11-12 Capital Projects Fund 13 Pavement Management Fund 14 Community Beautification Fund 15 O&M Assessment Calculation 16 IOB Roadway

More information

City of San Juan Capistrano Agenda Report. 1. Adopt the resolution amending the Operating and Capital Improvement Budgets for Fiscal Year ;

City of San Juan Capistrano Agenda Report. 1. Adopt the resolution amending the Operating and Capital Improvement Budgets for Fiscal Year ; 6/20/2017 City of San Juan Capistrano Agenda Report F1a TO: Honorable Mayor and Members of the City Council FROM: ~n Siegel, City Manager SUBMITTED BY: Ken Al-lmam, Chief Financial Officer P' PREPARED

More information

Project Description & Fund Overview Account Number Fund Name *C* September 2015 Additional Appropriation Mid-Year Adjustment Adjustments Approved by Council as separate actions Proposed & Approved Adjustments

More information