Township of Georgian Bay Water & Sewer Capacity Allocation Strategy. MacTier. November, Jointly prepared by the
|
|
- Gyles Evans
- 5 years ago
- Views:
Transcription
1 Appendix II Township of Georgian Bay 2008 Water & Sewer Capacity Allocation Strategy MacTier November, 2009 Jointly prepared by the Township of Georgian Bay and The District Municipality of Muskoka
2 A. A. INTRODUCTION INTRODUCTION Maximizing the efficient use of water and sewage capacity in MacTier is an important component of the future physical and financial planning for both the Township of Georgian Bay and The District Municipality of Muskoka. Therefore, a Water and Sewage Capacity Allocation Strategy has been prepared for the consideration of, and use by both Township and Muskoka Councils in order to address the allocation of the existing and future water and sewage capacity for MacTier. This strategy would satisfy the requirement contained in Section H.10 of the Muskoka Official Plan as well as Section (a) and of the Provincial Policy Statement (PPS, 2005). The primary focus of this Capacity Allocation Strategy is to track and manage sewer and water servicing capacity in a manner that provides for continued growth in all land use categories (commercial, industrial, residential and institutional). A formally adopted strategy also adds the element of equity and fairness to the process of capacity estimation and allocation. It clarifies for the development community and public at large, how a finite public resource will be managed to ensure maximum benefits to the Township and Muskoka. The successful administration of the strategy will require the on-going participation of the Township of Georgian Bay and The District Municipality of Muskoka since both have an equal interest in ensuring that servicing capacity exists, and is managed on an ongoing basis to provide for reasonable growth in the Township s urban centres. Currently, sufficient development commitments are in place for both water and sewage capacity to provide for growth within MacTier. The present use based on flows of the water treatment facility is approximately 63%, while the use based on flows of the sewage treatment facility is approximately 13%. If the existing servicing commitments are taken into account (this excludes partial approvals such as draft approved subdivisions), the MacTier water treatment facility would be operating at 78% capacity and the sewage treatment facility would be operating at 29% capacity. B. STRATEGY STRATEGY BASIS BASIS Function of the strategy In order to provide for continued development opportunities, it is critical to ensure that over time, inactive projects do not hold capacity allocation while other development approvals are delayed pending receipt of limited servicing capacity. Planning approvals will proceed through the usual process. However, approvals will be granted in a manner that ensures servicing capacity is allocated to those projects or portions of projects, which will proceed to actual construction within a reasonable time frame. The performance requirements, which are tied to development approvals, are intended to prevent a few large proposals from holding capacity allocation over time, and thereby precluding other proposals from proceeding. Purpose of the Strategy 1. To provide and maintain a strategy for a managed approach to capacity estimation and allocation. 2. To facilitate the continued servicing of development in all land use types. 3. To provide clear identification as to whom and under what conditions capacity will be allocated.
3 4. To deal equitably and reasonably with the development sector with maximum benefits to the entire community. 5. To provide a clear basis for the allocation of sewer and water capacity. 6. To encourage the efficient provision and staging of services within the Township and promote conservation within the total system. Principles of the Strategy 1. Continued development and movement of projects including all land use types through the development approval process will be facilitated (provided there is capacity). 2. Reasonable assignment of capacity at one time (ie. 20 ERUs or less) will be allocated in a way that ensures it is used up within a reasonable time frame and cannot be held without performance. 3. Capacity will be reserved for public or community related projects (e.g. a community centre), and projects, which are deemed to be in the public interest. C. STRATEGY C. STRATEGY Strategy Components The Water and Sewer Capacity Allocation Strategy is composed of several components including: the estimation and tracking of capacity; the capacity allocation procedure (CAP); conservation measures; and associated infrastructure planning. Capacity tracking tables are used to monitor reserve capacity in relation to planning and development approvals. The Water & Sewer Capacity Tracking Tables (2008) and the plant capacity estimates, resources, methodology and assumptions used to update the sewage and water tracking tables are attached as Appendix A. The Capacity Allocation Procedure (CAP) identifies under what conditions capacity will be assigned. The CAP is described in terms of the categories established in the tracking tables, and is monitored as the tables are updated on an annual basis. Reserve capacity can be preserved or expanded through the implementation of conservation measures, and consequently this is an important element of the strategy. Finally, the allocation strategy identifies at what point associated infrastructure planning related to water and sewer capacity should be triggered. Administration of the Strategy A technical working group comprised of Muskoka and Township of Georgian Bay planning and engineering staff representatives advise Muskoka and Township Councils, as is required on an ongoing basis, with respect to the administration of the strategy. The servicing capacity situation within the Township of Georgian Bay changes over time, and consequently, the strategy is not intended to be a static document rather, additional modifications may be required in the future to reflect changing circumstances.
4 Estimation of Capacity Early in each year, available plant servicing capacity is estimated by subtracting the average flow of the previous three years from the design capacity of the water or sewage treatment facility. The annual maximum day pump records for the previous three years are averaged to establish a representative existing demand with respect to water. For sewage treatment capacity, annual average day records for the previous three years are averaged to establish a representative existing demand. For simplicity and ease of understanding, capacity is referred to in terms of equivalent residential units (ERUs), which is a calculation of the capacity that is required for a single family residential unit. Using the recorded flows for water and sewer described above, an estimate of commitments is based on 2.0 m 3 /d per ERU for water demands and on 1.0 m 3 /d per ERU for sewage flows. The specific ERU calculations are included in Appendix A. This estimation of capacity deals with the capacity of water and sewage treatment facilities, and does not take the capacity of the water distribution and sewage collection systems into account. The capacity within these systems may also affect the ability to service a particular area of the MacTier urban centre. Development Tracking Tables The tracking tables identify the reserve capacity in each facility and the servicing commitments related to specific development proposals. A servicing capacity commitment is made when an agreement with the District of Muskoka assigning capacity is executed when final approval of a project is granted, or when a holding provision is removed and the project can proceed to construction. The tracking tables have been divided into categories, which indicate the level of servicing commitment to, and allocation status for individual projects in terms of the associated planning approval and the ability to obtain a building permit. The servicing allocation necessary for each project is identified on the tracking tables and the type of use is also recorded. Category 1 projects have servicing capacity commitments and can proceed or have proceeded to construction. Category 2 includes projects which have partial planning approval, but which have not been allocated capacity. Category 3 includes planning applications that are under consideration. The Allocation Reserve is the capacity that exists once existing flows and Category 1 commitments have been taken into account and is the reserve from which capacity can be allocated. The allocation reserve is identified at the end of Category 1 on the tracking tables. The technical working group updates the water and sewer development tracking tables. The technical working group also estimates the capacity and commitments identified in the tracking tables. The tracking tables are revised by removing those developments that are constructed and occupied during the preceding year. They are also updated to reflect changes in planning status and to add new proposals. The methodology used to update the tracking tables is summarized in Appendix A. The updated tracking tables are provided for both Muskoka and Township Councils as well as to other groups, or individuals upon request. E. D. CAPACITY ALLOCATION ALLOCATION PROCEDURE PROCEDURES Capacity Allocation Procedures have been designed for use over time as available sewage and water capacity changes. The amount of available capacity for allocation determines which allocation procedure should be implemented at any one time.
5 A Capacity Allocation Procedure (CAP) is implemented until 95% of the design capacity is committed in order to ensure that allocation of capacity is tracked and managed in a way that will provide for continued growth in all sectors over time. This procedure is also intended to ensure that allocation of capacity and the granting of development approvals is not hampered by projects, which do not proceed to construction. A Limited Capacity Allocation Procedure (LCAP) is applied in situations where available capacity is limited, and would be initiated when 95% of the design capacity is committed (actual flows and Category 1 projects). The procedures and criteria for assigning capacity are set out as follows for each category of development. Category 1 Definition: Projects which have a capacity commitment including: (i) Identified existing vacant lots of record (ERUs are allocated in accordance with current zoning); (ii) Registered and draft approved plans of subdivision and condominium descriptions with registered sewer and water servicing agreements; (iii) Special projects (ie. redevelopment projects which do not require any zone change); and (iv) The Special Community Reserve, illustrated at the bottom of the Category 1 tracking chart, which represents a special reserve to be held and used for projects that are publicly initiated, or deemed to be in the public interest. Capacity Allocation Procedure (CAP) (i) Existing lots and projects with capacity allocation identified in agreements with the District of Muskoka and that are eligible for building permits may proceed to develop. (ii) Capacity may be assigned from the Special Community Reserve by Township Council to community special projects or development projects that benefit and are in the public or community interest (such as affordable housing, community facilities, and education facilities). (iii) The capacity of the water and sewage treatment plants, including any capacity drawn from the special community reserve, shall not be exceeded. Distribution of capacity to each land use category will be monitored by the technical working group. Reports will be provided to Township Council, as required and will include identification of the level of commitment in each land use sector in order to assist Township and District Councils in ensuring that an appropriate balance is achieved. Limited Capacity Allocation Procedure (LCAP) (i) Provided there is sufficient capacity in the water and sewage treatment plants, projects with an agreement assigning capacity, and existing lots that are eligible for building permits, may proceed to develop. (ii) Development that has a servicing commitment and is not expected to proceed with immediate construction may be requested to defer connection (through the use of agreements or the holding category) until additional capacity is available (e.g. through infrastructure changes). (Projects which defer connection would move to Category 2). Any
6 capacity recovered due to connection deferral may be returned to the Category 1 allocation reserve for re-distribution. Down zoning may be considered where development is not expected to proceed. (iii) Properties may be down zoned or placed in a holding category so that the ERU allocation can be transferred to another property owned by the same individual. This procedure must be carefully applied and equity must be achieved. Any transfer must not assign additional development rights or result in an unfair advantage to any individual or company. (Properties down zoned or subject to a holding provision would be moved to Category 2). (iv) Capacity may be allocated from the allocation reserve to minor residential infill proposals (including severances and zoning by-laws) within the areas now serviced and designated for urban use, provided that the net increase is not greater than 1 ERU or 1 additional residential lot per property, per year. (v) Capacity allocation for projects other than the minor residential infilling identified above, which would be constructed prior to the commissioning of the new plant, will require individual review and approval by the Township and the District of Muskoka. The technical working committee will review the individual requests and make recommendations to Township Council respecting allocation. Community projects, projects that are in the public interest and any other circumstances Township Council identifies, may warrant allocation. Allocation to commercial, industrial and community projects will take priority. Performance requirements would also be necessary in these situations. (vi) The Category 1 special community reserve shall not be exceeded. Assignment of capacity will be monitored by the technical working group and reports will be provided to Township Council and District Council, as required. Reports will include identification of the level of commitment in each land use sector. Category 2 Definition: Projects, or parts of projects with partial planning approvals, but which have not been assigned a capacity allocation, and includes: (i) Draft approved plans of subdivision and condominium descriptions which do not have a registered servicing agreement and therefore have not assigned a capacity allocation; (ii) Applications for consent; (iii) Properties zoned for use, but which require a servicing agreement or the removal of the holding category; (iv) Applications or proposals under appeal; and (v) Projects which require greater allocation than is currently available. Capacity Allocation Procedure (CAP): Plans of Subdivision/Condominium Descriptions (i) As specified in the conditions of draft approval, the individual phases of plans of subdivision or condominium descriptions or applications for the lifting of part lot control or holding provisions, will proceed to final approval in phases. In order to ensure that the remaining capacity in the water and sewage treatment plants is equitably allocated to development proposals throughout MacTier, the District agreements assigning capacity will generally
7 assign not more than 20 ERUs per phase of a development proposal. Subsequent phase(s) will not be allocated further capacity until the preceding phase has been registered, it has been serviced by municipal water and sewer, and the proponent has satisfactorily demonstrated to the District of Muskoka and the Township that construction is proceeding. (ii) As specified in conditions of draft approval, final approval will be dependent upon the availability of water and sewage treatment plant capacity. (iii) Holding provisions may be applied to phases of, or blocks within, a plan of subdivision that do not have servicing allocation, but may wish to proceed with zoning approval. Consents (i) A condition of a provisional decision to grant consent will be required which states that an agreement assigning capacity must be completed prior to final approval of the proposal. Zoning By-laws and Amendments (i) For projects other than residential infill or projects requiring a minor amount of capacity, a holding provision will be incorporated in a zoning by-law which could be lifted once an agreement assigning capacity has been registered against the title of the lands. This would provide reasonable assurance that the project will proceed once capacity is allocated. Limited Capacity Allocation Procedure (LCAP): (i) Unless Township Council has granted a special allocation, final approval of plans of subdivision or condominium descriptions, the lifting of part lot control and the removal of holding categories shall not proceed until the works necessary to provide sufficient capacity are commissioned and a servicing agreement has been signed. The conditions of draft approval shall detail this requirement. (ii) Requests for an extension to draft approval will be reviewed and draft approval may be permitted to lapse where capacity is not expected to be taken up and is preventing other projects from proceeding. (iii) Limited development proposals (ie. consent, zoning amendment, or part lot control applications) may proceed provided that the net allocation increase is not greater than 4 ERUs, per property, per year. (iv) Redevelopment proposals which do not require an increased ERU allocation, but which require a planning approval, may proceed. Performance guarantees will be required, where appropriate. (v) The holding category will be used for re-zonings (other than residential infill or limited development requiring a minor amount of capacity) in order to facilitate phasing and/or to defer final allocation until construction is to proceed and ensure performance. The holding provision would be removed when there is sufficient capacity in the water and sewage treatment plants, an agreement assigning capacity has been signed, a satisfactory site plan is submitted and a building permit and associated fee is submitted in order to ensure that capacity will not be held by development that is not proceeding.
8 Category 3 Definition: Development applications without planning approval or allocation including: (i) Official Plan Amendment (OPA) applications requiring approval or OPAs with further requirements; (ii) Applications for plans of subdivision or condominium descriptions which have been deemed complete applications; (iii) Development applications under consideration (consents, zoning by-law, etc.); and (iv) Developments that would require an expansion of the existing facilities in order to obtain sufficient capacity. Capacity Allocation Procedure (CAP): Plans of Subdivision or Condominium Descriptions (i) Where capacity is available, plans of subdivision or condominium descriptions may proceed to draft approval, provided that the plan or description is phased. Phasing will be determined according to individual circumstances taking into account matters such as economic viability, on and off site servicing requirements, ability to construct, amongst other matters (generally not more than 20 ERUs per phase). (ii) As specified in the conditions of draft approval, the individual phases of plans of subdivision or condominium descriptions or applications for the lifting of part lot control or holding provisions, will proceed to final approval in phases. A District agreement assigning capacity requiring performance and including securities for each phase will be required as a condition of approval. (Once the draft approval is granted the plan would move to a Category 2 project). Agreements assigning capacity may also deal with those situations where a plan of subdivision of condominium description includes a future development block or blocks that are proposed to develop by part lot control. Alternatively, a holding provision in the zoning bylaw may also be used if the block is to proceed via part lot control or other means. In either case, the holding category would not be removed until Muskoka has confirmed that there is available capacity in the water and sewage treatment plants, capacity is allocated through an agreement assigning capacity and the previous phase of the development is completed. Supplemental agreements or the removal of the holding category will not occur until Muskoka confirms available capacity and evidence has been provided that the preceding phase of development has been completed to the satisfaction of the Township and the District of Muskoka. (iii) Where a plan of subdivision or condominium description will proceed in one phase, the conditions of draft approval will require that the municipal agreements assigning capacity contain performance clauses applicable from the date of allocation of capacity (performance required in a specified time period generally in one to two years with 100% securities). Holding categories may be implemented, where appropriate, to ensure performance. The measures outlined in (ii) above may be used in order to ensure that an appropriate assignment of allocation occurs. Zoning By-laws and Amendments (i) Zoning by-laws and by-law amendments will include provisions to limit the type of use, area zoned and/or square footage of a development in order to establish basic ERU allocation and eliminate as of right high water users and sewage generators.
9 (ii) Holding categories will be implemented where there is a reasonable expectation that the development will proceed or as detailed above. Other (i) Allocation to projects which are proposed on the basis of a single water or sewage service will only be permitted in accordance with Section H.7 of the Muskoka Official Plan. Limited Capacity Allocation Procedure (LCAP): (i) Limited development proposals (ie. consent, zoning amendment, or part lot control applications) may proceed provided that the net allocation increase is not greater than 4 ERUs, per property, per year. (ii) Redevelopment proposals which do not require an increased ERU allocation, but which require a planning approval, may proceed. Performance guarantees will be required, where appropriate. (iii) Unless Township Council has granted a special allocation, draft or final approval of plans of subdivision or condominium descriptions that do not have existing services and the removal of holding categories shall not proceed until the works necessary to provide sufficient capacity are commissioned and an agreement assigning capacity has been executed. (iv) The holding category will be used for rezonings (other than residential infill or limited development requiring a minor amount of capacity) in order to facilitate phasing and/or to defer final allocation until construction is to proceed and ensure performance. The holding provision would be removed when there is sufficient capacity in the water and sewage treatment plants, an agreement assigning capacity has been signed, a satisfactory site plan is submitted and a building permit and associated fee is submitted in order to ensure that capacity will not be held by development that is not proceeding. E. F. CONSERVATION CONSERVATION Conservation measures are an integral part of any allocation strategy, since these measures can be successful in acquiring additional reserve capacity, or extending existing capacity. Conservation efforts should be implemented, to ensure that water and sewer facilities are used in the most efficient manner possible. Options currently being considered or are currently in use include: Ensuring the water and sewage rate structure encourages conservation and reuse; Identifying and promoting conservation opportunities for new and renovation projects at the time building permits are being processed; and Eliminating roof and foundation drainage discharge to the sanitary system. Conservation measures such as these can ensure the efficient use of available capacity so that sufficient capacity is available over time to accommodate growth. Conservation methods will be investigated on an on-going basis and recommendations will be provided for the consideration of both Councils.
10 G. F. ASSOCIATED ASSOCIATED INFRASTRUCTURE INFRASTRUCTURE PLANNING PLANNING Areas to be Serviced Servicing schedules which illustrate the extent of the area to be serviced have been included in the Township Official Plan. Associated servicing policies are also included in the Township Official Plan and are implemented through the planning process. Facilities Expansion Generally, at the time that the facility flow is at 80% of the design capacity and sufficient demand for servicing capacity is demonstrated in the tracking tables, the preparation of an Environmental Assessment (EA) or a system optimization study would be initiated to provide for additional capacity. The actual facility flow and servicing commitments (Category 1), must not exceed 100% of design capacity and, as a target, the summary of the actual facility flows plus Category 1 and the planning approvals in Category 2, should not represent more than 150% of the design capacity.
11 APPENDIX A Sewer and Water Tracking Tables (2008) MacTier Introduction The following is a summary of the plant capacity estimates, resources, methodology and technical assumptions used to update the sewer and water tracking tables for the community of MacTier for the year Sewer and water capacity is expressed in terms of "Equivalent Residential Units" (ERUs). Generally, the three year average of recorded flows is used and an estimate of commitments is based on a maximum daily flow of 2.0 m3/day per ERU for water demand and an average daily flow of 1.0 m3/day per ERU for sewage flows. Note On The Rated Capacity Of Treatment Plants The Ministry of the Environment expresses the rated capacity of a water treatment plant in terms of the maximum daily flow that it can produce. The Ministry expresses the rated capacity of a sewage treatment plant in terms of the average daily flow that it can receive. Flow Records Water Treatment Plant Sewage Treatment Plant Record Flow (m3/day) Flow (m3/day) Year Average Maximum Average , Average A 91 B Calculation of Water Consumption Per ERU a) Consumption for an average day = 260 Lpcd C b) Allowance for system losses = 15% D c) Peaking factor - average day to = 2.25 E maximum day - based on MOE Guidelines for facility capacity - for a water plant serving a population between 2,000 and 3,000 d) ERU occupancy - Ontario census average = 3 persons per unit F and DMM housing report average is approximately 2.8 ppu - assume for a new single detached dwelling
12 e) ERU water consumption expressed in = 2 m3/d/eru G terms of maximum day demand (=Cx(1+D)xExF/1000) Derivation of Sewage Flows Per ERU a) Portion of properties served by water = 20% H that are also served by sewers. b) Number of water ERUs served by sewers = 90 ERU J (=HxA/G) c) ERU sewage flow expressed in = 1.0 m3/d/eru K terms of average daily flow (=B/J) Calculation of Reserve Water Plant Capacity a) Design capacity per Certificate of Approval = 1,428 m3/d L b) Design capacity in ERUs (=L/G) = 714 ERU M c) Reserve capacity (=L-A) = 532 m3/d N d) Reserve capacity in ERUs (=N/G) = 266 ERU P e) Plant capacity consumed (=A/L) = 63% Q Calculation of Reserve Sewage Plant Capacity a) Design capacity per Certificate of Approval = 691 m3/d R b) Design capacity in ERUs (=R/K) = 691 ERU S c) Reserve capacity (=R-B) = 600 m3/d T d) Reserve capacity in ERUs (=T/K) = 600 ERU U e) Plant capacity consumed (=B/R) = 13% V
13 APPENDIX B Sewer and Water Capacity Tracking Tables (2008) Township of Georgian Bay (MacTier) Resources The following is a list of resource information used to update the MacTier Water and Sewage Tracking Tables. The MacTier sewage and water flow rate tables, updated for the year of 2008, were provided by the Muskoka Engineering and Public Works Department; A property assessment map of the MacTier Urban Area, updated to June, 2009, showing developed properties, vacant properties and the location of existing piped sewage and water services; Correspondence with Township planning staff regarding current zoning on properties; and Muskoka s in-house development application files for zoning by-law amendments, draft and final plans of subdivision/condominium. Methodology: Each individual vacant property shown on the property assessment map for the MacTier Urban Centre was compared with the digital zoning map to determine zone, number and area of vacant lots/lands. Zoning By-law Amendment, Official Plan Amendment and Subdivision files were reviewed and updated under the relevant categories and sub-categories of the tracking tables. Category 1 Calculations: Single detached dwellings (R1, R2, R4, RU): The total number of ERU s for vacant Residential (R1, R4, RU) zoned lots are calculated using a general allowance of 1 ERU per lot: R1/R4/RU = total # vacant lots x 1 ERU Multiple Residential (RM1, RM2, RM3, RM4): There are no vacant multiple residential properties in MacTier: Institutional Lands (I, I-3): The total number of ERU s for Institutional (I) lots has been calculated with a general allowance of 5 ERU s per acre: I = Total acreage of vacant Institutional land x 5 ERU s per acre Commercial lands (C1, C2, C3, CT-1, CT-2, CM1, CM2, CM3, CM4): The total number of ERU s for Commercial (C2) lots has been calculated using a general allowance of 5 ERU s per acre:
14 C2 = Total acreage of vacant commercial land x 5 ERU s. Industrial Lands (M, MX): There are no vacant industrial properties in MacTier. Category 2 and 3: Categories 2 and 3 consist of the following: Category 2 i. Draft approved plans of Subdivision/Condominium requiring an agreement and with no allocation. Ii. Zoned properties with Holding or requiring an agreement and with no allocation. iii. Proposals under appeal. iv. Special projects. Category 3.i. ii. iii. iv. Development applications. Plans of Subdivision/Condominium in circulation. O.P.A. applications or O.P.A. with further required agreement, but with capacity expansion. Development requiring capacity expansion.
15 MACTIER CAPACITY TRACKING SUMMARY PAGE SEWAGE TREATMENT PLANT CATEGORY 1 PRESENT CAPACITY 13.17% GENERAL NOTES THREE YEAR AVERAGE (ERU'S) 91 TOTAL PLANT CAPACITY (ERU'S) CURRENT RESERVE ERU's IDENTIFICATION DESCRIPTION/COMMENT R/S R/M R/A I C M TOTALS % of CATEGORY LEGEND R1, R4 and RU Vacant Lots Cat. 1 (i): Existing Vacant Lots % R/S = single detached dwellings RM-1 Zones Cat. 1 (i): Vacant lands (none) % RM-2, RM-3, RM-4 Zones Cat. 1 (i): Vacant lands (none) % R/M = row or town house, semi-detached, duplex, converted dwelling, maisonette R/A = fourplex, apartment unit (Expressed in Equilavent ERU's at 0.6ERU/unit) Commercial Zones Cat. 1 (i): Vacant 5.0 ERU/acre % I = institutional Industrial Zones Cat. 1 (i): Vacant lands (none) % C = commercial Institutional Zones Cat. 1 (i): Vacant 5.0 ERU/acre % M = industrial APPROVED DEVELOPMENTS Cat. 1 (ii) % SUBCATEGORIES Special Projects Cat. 1 (iii) % i) Identified Existing Lots Local Improvements Cat. 1(iv) % ii) Site Specific Zoning B/L Amendments iii) Special Projects Sub-Total Category iv) Approved Local Improvements SPECIAL COMMUNITY RESERVE % R/S R/M R/A I C M TOTAL 493 TOTALS - CATEGORY % TOTAL REMAINING ERU'S CAPACITY WITH ALL CATEGORY 1
16 MACTIER CAPACITY TRACKING SUMMARY PAGE SEWAGE TREATMENT PLANT CATEGORY 2 & 3 PRESENT CAPACITY 13.17% GENERAL NOTES THREE YEAR AVERAGE (ERU'S) 91 TOTAL PLANT CAPACITY (ERU'S) CURRENT RESERVE ERU's RESERVE ERU'S + CATEGORY ONE CATEGORY 2 CATEGORY ONE LEGEND IDENTIFICATION DESCRIPTION/COMMENT R/S R/M R/A I C M TOTALS % of CATEGORY 1 Draft Approved Plans % Zoning w/h - Other % R/S = single detached dwellings R/M = row or town house, semi-detached, duplex, converted dwelling, maisonette R/A = fourplex, apartment unit (Expressed in Equilavent ERU's at 0.6ERU/unit) Build-Out Proposals % I = institutional TOTALS C = commercial M = industrial CATEGORY 3 SUBCATEGORIES i) Identified Existing Lots IDENTIFICATION DESCRIPTION/COMMENT R/S R/M R/A I C M TOTALS ii) Site Specific Zoning B/L Amendments All Proposed Developments TOTALS iii) Special Projects iv) Approved Local Improvements R/S R/M R/A I C M TOTALS 475 REMAINING ERU'S - CATEGORIES 1 & 2 CUMULATIVE TOTALS CATEGORY 1 & % % CAPACITY R/S R/M R/A I C M TOTALS 475 REMAINING ERU'S - ALL CATEGORIES TOTALS - ALL CATEGORIES % % CAPACITY
17 MACTIER SEWAGE TREATMENT PLANT CATEGORY ONE - COMMITTED DEVELOPMENTS VACANT LANDS WITH NO SPECIFIC DENSITY NOTES TOTAL CAPACITY 691 CUMULATIVE TOTAL RM 1 LANDS (acres) 0 No such vacant lands exists 3 YEAR AVERAGE MAXIMUM ERU'S PER DAY 91 CUMULATIVE TOTAL RM4 LANDS 0 No such vacant lands exists OPERATING CAPACITY & 3 YEAR AVERAGE 13.17% CUMULATIVE TOTAL COMMERCIAL LANDS Estimated based on 5 ERU's per acre AVAILALBLE ERU'S BASED ON 3 YEAR AVERAGE 600 CUMULATIVE TOTAL INDUSTRIAL LANDS 0 No such vacant lands exists CUMULATIVE TOTAL OF AVAILABLE ERU'S - CATEGORY CUMULATIVE TOTAL INSTITUTIONAL LANDS 5 Estimated based on 5 ERU's per acre EXISTING VACANT LANDS DESCRIPTION/COMMENTS TYPE INFORMATION SOURCE R/S R/M R/A eru I C M TOT AVAILABLE ERU'S % CAPACITY Vacant R1, R4 and RU lands Cat. 1(i) - Determined from assessment and zoning maps % Vacant RM1 Lands with no specific density (No such vacant lands exist) Cat. 1(i) - Determined from assessment and zoning maps % Vacant RM2, RM3, RM4 Lands with no specific density (No such vacant lands exist) Cat. 1(i) - Determined from assessment and zoning maps % Vacant Commercial Lands with no specific density (at 5 ERU's/acre) Cat. 1(i) - Determined from assessment and zoning maps % Vacant Industrial Lands with no specific density (No such vacant lands exis) Cat. 1(i) - Determined from assessment and zoning maps % Vacant Institutional Lands with no specific density (at 5 ERU's/acre) Cat. 1(i) - Determined from assessment and zoning maps % SERVICING AGREEMENT/DEVELOPMENT APPROVAL DESCRIPTION/COMMENTS SPECIAL COMMUNITY RESERVE 10 ERUs for Special Municipal Projects % % % % % % LOCAL IMPROVEMENTS DESCRIPTION/COMMENTS % % % % % CUMULATIVE TOTALS FOR CATEGORY ONE R/S R/M R/A eru I C M TOT AVAILABLE ERU'S % CAPACITY NOTE: R/A COLUMN INDICATES NUMBER OF DWELLING UNITS - eru COLUMN INDICATES ERU 0.6 ERU / PER UNIT %
18 TOTAL CAPACITY YEAR AVERAGE ERU'S PER DAY 91 OPERATING CAPACITY AFTER CATEGORY % AVAILALBLE ERU'S BASED ON 3 YEAR AVERAGE 600 CUMULATIVE TOTAL OF AVAILABLE ERU'S - CATEGORY MACTIER SEWAGE TREATMENT PLANT CATEGORY TWO - DRAFT APPROVED & OTHER PROPOSED DEVELOPMENTS DRAFT APPROVED PLANS SUB/CONDO DESCRIPTION/COMMENTS R/S R/M R/A eru I C M TOT AVAILABLE ERU'S % CAPACITY S Stewart Lake, Draft Approved Subdivision R % BY-LAWS WITH HOLDING & OTHER PROJECTS DESCRIPTION/COMMENTS CUMULATIVE TOTALS FOR CATEGORIES ONE AND TWO R/S R/M R/A eru I C M TOT AVAILABLE ERU'S % CAPACITY NOTE: R/A COLUMN INDICATES NUMBER OF DWELLING UNITS - eru COLUMN INDICATES ERU 0.6 ERU / PER UNIT %
19 TOTAL CAPACITY YEAR AVERAGE ERU'S PER DAY 91 OPERATING CAPACITY AFTER CATEGORY 1 & % AVAILALBLE ERU'S BASED ON 3 YEAR AVERAGE 600 CUMULATIVE TOTAL - CATEGORIES 1 AND MACTIER PLANT CATEGORY THREE - PREMILINARY & CONCEPT DEVELOPMENTS FILE/APPLICATION DESCRIPTION/COMMENTS R/S R/M R/A eru I C M TOT AVAILABLE ERU'S % CAPACITY CUMULATIVE TOTALS FOR ALL CATEGORIES R/S R/M R/A eru I C M TOT AVAILABLE ERU'S % CAPACITY NOTE: R/A COLUMN INDICATES NUMBER OF DWELLING UNITS - eru COLUMN INDICATES ERU 0.6 ERU / PER UNIT
20 MACTIER CAPACITY TRACKING SUMMARY PAGE WATER TREATMENT PLANT CATEGORY 1 PRESENT CAPACITY 62.75% GENERAL NOTES THREE YEAR AVERAGE (ERU'S) 448 TOTAL PLANT CAPACITY (ERU'S) CURRENT RESERVE ERU's IDENTIFICATION DESCRIPTION/COMMENT R/S R/M R/A I C M TOTALS % of CATEGORY LEGEND R1, R4, RU Vacant Lots Cat. 1 (i): Existing Vacant Lots % R/S = single detached dwellings RM-1 Zone Cat. 1 (i): Vacant lands (none) % RM-2, RM-3, RM-4 Zones Cat. 1 (i): Vacant lands (none) % R/M = row or town house, semi-detached, duplex, converted dwelling, maisonette R/A = fourplex, apartment unit (Expressed in Equilavent ERU's at 0.6ERU/unit) Commercial Zones Cat. 1 (i): Vacant 5.0 ERU/acre % I = institutional Industrial Zones Cat. 1 (i): Vacant lands (none) % C = commercial Institutional Zones Cat. 1 (i): Vacant 5.0 ERU/acre % M = industrial APPROVED DEVELOPMENTS Cat. 1 (ii) % SUBCATEGORIES Special Projects Cat. 1 (iii) % i) Identified Existing Lots Local Improvements Cat. 1(iv) % ii) Site Specific Zoning B/L Amendments iii) Special Projects Sub-Total Category iv) Approved Local Improvements SPECIAL COMMUNITY RESERVE % R/S R/M R/A I C M TOTAL 159 TOTALS - CATEGORY % TOTAL REMAINING ERU'S CAPACITY WITH ALL CATEGORY 1
21 MACTIER CAPACITY TRACKING SUMMARY PAGE WATER TREATMENT PLANT CATEGORY 2 & 3 PRESENT CAPACITY 62.75% GENERAL NOTES THREE YEAR AVERAGE (ERU'S) 448 TOTAL PLANT CAPACITY (ERU'S) CURRENT RESERVE ERU's RESERVE ERU'S + CATEGORY ONE CATEGORY 2 CATEGORY ONE LEGEND IDENTIFICATION DESCRIPTION/COMMENT R/S R/M R/A I C M TOTALS % of CATEGORY 1 Draft Approved Plans % Zoning w/h - Other % R/S = single detached dwellings R/M = row or town house, semi-detached, duplex, converted dwelling, maisonette R/A = fourplex, apartment unit (Expressed in Equilavent ERU's at 0.6ERU/unit) Build-Out Proposals % I = institutional TOTALS C = commercial M = industrial CATEGORY 3 SUBCATEGORIES i) Identified Existing Lots IDENTIFICATION DESCRIPTION/COMMENT R/S R/M R/A I C M TOTALS ii) Site Specific Zoning B/L Amendments All Proposed Developments TOTALS iii) Special Projects iv) Approved Local Improvements R/S R/M R/A I C M TOTALS 141 REMAINING ERU'S - CATEGORIES 1 & 2 CUMULATIVE TOTALS CATEGORY 1 & % % CAPACITY R/S R/M R/A I C M TOTALS 141 REMAINING ERU'S - ALL CATEGORIES TOTALS - ALL CATEGORIES % % CAPACITY
22 MACTIER WATER TREATMENT PLANT CATEGORY ONE VACANT LANDS WITH NO SPECIFIC DENSITY NOTES TOTAL CAPACITY 714 CUMULATIVE TOTAL RM 1 LANDS (acres) 0 No such vacant lands exists 3 YEAR AVERAGE MAXIMUM ERU'S PER DAY 448 CUMULATIVE TOTAL RM2, RM3, RM4 LANDS 0 No such vacant lands exists OPERATING CAPACITY & 3 YEAR AVERAGE 62.75% CUMULATIVE TOTAL COMMERCIAL LANDS Estimated based on 5 ERU's per acre AVAILALBLE ERU'S BASED ON 3 YEAR AVERAGE 266 CUMULATIVE TOTAL INDUSTRIAL LANDS 0 No such vacant lands exists CUMULATIVE TOTAL OF AVAILABLE ERU'S - CATEGORY CUMULATIVE TOTAL INSTITUTIONAL LANDS 5 Estimated based on 5 ERU's per acre EXISTING VACANT LANDS DESCRIPTION/COMMENTS TYPE INFORMATION SOURCE R/S R/M R/A eru I C M TOT AVAILABLE ERU'S % CAPACITY Vacant R1, R4 and RU lands Cat. 1(i) - Determined from assessment and zoning maps % Vacant RM1 Lands with no specific density (No such vacant lands exist) Cat. 1(i) - Determined from assessment and zoning maps % Vacant RM4 Lands with no specific density (No such vacant lands exist) Cat. 1(i) - Determined from assessment and zoning maps % Vacant Commercial Lands with no specific density (at 5 ERU's/acre) Cat. 1(i) - Determined from assessment and zoning maps % Vacant Industrial Lands with no specific density (No such vacant lands exists) Cat. 1(i) - Determined from assessment and zoning maps % Vacant Institutional Lands with no specific density (at 5 ERU's/acre) Cat. 1(i) - Determined from assessment and zoning maps % APPROVED ZONING WITH NO HOLDING DESCRIPTION/COMMENTS SPECIAL COMMUNITY RESERVE 10 ERUs for Special Municipal Projects % % % % % % % LOCAL IMPROVEMENTS DESCRIPTION/COMMENTS % % % % % CUMULATIVE TOTALS FOR CATEGORY ONE R/S R/M R/A eru I C M TOT AVAILABLE ERU'S % CAPACITY NOTE: R/A COLUMN INDICATES NUMBER OF DWELLING UNITS - eru COLUMN INDICATES ERU 0.6 ERU / PER UNIT %
23 MACTIER WATER TREATMENT PLANT CATEGORY TWO - DRAFT APPROVED & OTHER PROPOSED DEVELOPMENTS TOTAL CAPACITY YEAR AVERAGE ERU'S PER DAY 448 OPERATING CAPACITY AFTER CATEGORY % AVAILALBLE ERU'S BASED ON 3 YEAR AVERAGE 266 CUMULATIVE TOTAL OF AVAILABLE ERU'S - CATEGORY DRAFT APPROVED PLANS SUB/CONDO DESCRIPTION/COMMENTS R/S R/M R/A eru I C M TOT AVAILABLE ERU'S % CAPACITY S Stewart Lake, Draft Approved Subdivision R % BY-LAWS WITH HOLDING & OTHER PROJECTS DESCRIPTION/COMMENTS CUMULATIVE TOTALS FOR CATEGORIES ONE AND TWO R/S R/M R/A eru I C M TOT AVAILABLE ERU'S % CAPACITY NOTE: R/A COLUMN INDICATES NUMBER OF DWELLING UNITS - eru COLUMN INDICATES ERU 0.6 ERU / PER UNIT %
24 MACTIER WATER TREATMENT PLANT CATEGORY THREE - PRELIMINARY PROPOSALS & CONCEPT DEVELOPMENTS TOTAL CAPACITY YEAR AVERAGE ERU'S PER DAY 448 OPERATING CAPACITY AFTER CATEGORY 1 & % AVAILALBLE ERU'S BASED ON 3 YEAR AVERAGE 266 CUMULATIVE TOTAL - CATEGORIES 1 AND FILE/APPLICATION DESCRIPTION/COMMENTS R/S R/M R/A eru I C M TOT AVAILABLE ERU'S % CAPACITY CUMULATIVE TOTALS FOR ALL CATEGORIES R/S R/M R/A eru I C M TOT AVAILABLE ERU'S % CAPACITY NOTE: R/A COLUMN INDICATES NUMBER OF DWELLING UNITS - eru COLUMN INDICATES ERU 0.6 ERU / PER UNIT
Town of Grand Valley Wastewater Treatment Capacity Allocation Policy Adopted by resolution
Town of Grand Valley Wastewater Treatment Capacity Allocation Policy Adopted by resolution 2016-12-3 WHEREAS the Town of Grand Valley ( Town ) has constructed a Waste Water Treatment Plant ( WWTP ) to
More informationGROWTH MANAGEMENT STRATEGY
GROWTH MANAGEMENT STRATEGY THE COUNTY OF HALIBURTON May 21, 2014 TABLE OF CONTENTS 1.0 INTRODUCTION... 1 2.0 MEDIUM AND HIGH DENSITY HOUSING ALLOCATION... 2 2.1 Medium and High Option 1 Existing Distribution...
More informationDevelopment Charge Bylaw Directions
Clause 8 in Report No. 17 of Committee of the Whole was adopted, without amendment, by the Council of The Regional Municipality of York at its meeting held on November 17, 2016. 8 Committee of the Whole
More information5 Draft 2017 Development Charge Background Study and Proposed Bylaw
Clause 5 in Report No. 3 of Committee of the Whole was adopted, without amendment, by the Council of The Regional Municipality of York at its meeting held on February 16, 2017. 5 Draft 2017 Development
More informationOran Park and Turner Road Precincts Section 94 Contributions Plan
Oran Park and Turner Road Precincts Section 94 Contributions Plan Prepared for The Council of Camden Contents Page Number 1. Summary 1 1.1 Overview of this Plan 1 1.2 Works schedule and contribution rates
More informationDEVELOPMENT CHARGES BACKGROUND STUDY
DEVELOPMENT CHARGES BACKGROUND STUDY Town of Innisfil C o n s u l t i n g L t d. July 19, 2018 TABLE OF CONTENTS EXECUTIVE SUMMARY... 1 I PURPOSE OF THE DEVELOPMENT CHARGES BACKGROUND STUDY... 6 A. INTRODUCTION
More informationMuskoka Treasurers Report
TO: FROM: SUBJECT: Muskoka Lower-Tier Councils Muskoka Treasurers Vacancy Rebate and Reduction Program RECOMMENDATION 1. That the lower-tier municipalities in the District of Muskoka endorse the concept
More informationCITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF SEPTEMBER 26, 2017
Item 6, Report No. 8, of the Finance, Administration and Audit Committee, which was adopted without amendment by the Council of the City of Vaughan on September 26, 2017. 6 DEVELOPMENT SERVICES FEE STRUCTURE
More informationTHE REGIONAL MUNICIPALITY OF PEEL BY-LAW NUMBER
THE REGIONAL MUNICIPALITY OF PEEL BY-LAW NUMBER 12-2017 A by-law to adopt Amendment Number 27 to the Region of Peel Official Plan in order to revise and add policies in respect of health and the built
More informationCITY OF SAULT STE. MARIE 2016 DEVELOPMENT CHARGES BACKGROUND STUDY. Draft for Public Circulation and Comment
CITY OF SAULT STE. MARIE 2016 DEVELOPMENT CHARGES BACKGROUND STUDY Draft for Public Circulation and Comment JUNE 8, 2016 CONTENTS Page 1. INTRODUCTION 1.1 Purpose of this Document 1-1 1.2 Development Charges
More informationUpper Warrell Creek Road Developer Contributions Plan August 2013
Developer Contributions Plan August 2013 Nambucca Shire Council Administration Centre 44 Princess Street Macksville Contents Part A: Introduction, Operation and Administration of the Plan 1. Introduction
More informationTown of Oakville Development Charge Background Study. Consolidated Report. In association with
Development Charge Background Study Consolidated Report This report consolidates the December 22,2017 Background Study, the February 8, 2018 Addendum 1 Report, and the February 23, 2018 Addendum 2 Report
More informationTOWN OF AURORA DEVELOPMENT CHARGE BACKGROUND STUDY AND PROPOSED BY-LAW OFFICE CONSOLIDATION MARCH 12, (As Amended April 8 th, 2014)
TOWN OF AURORA DEVELOPMENT CHARGE BACKGROUND STUDY AND PROPOSED BY-LAW OFFICE CONSOLIDATION MARCH 12, 2014 (As Amended April 8 th, 2014) CONTENTS Page EXECUTIVE SUMMARY (i) 1. INTRODUCTION 1.1 Purpose
More informationCanterbury Development Contributions Plan 2013
Canterbury Development Contributions Plan 2013 Adopted by Council: 5 December 2013 Effective from: 17 December 2013 Jim Montague PSM GENERAL MANAGER City Planning Division Contents Page Number 1. Plan
More informationDEVELOPMENT CHARGES BACKGROUND STUDY
DEVELOPMENT CHARGES BACKGROUND STUDY Town of New Tecumseth C o n s u l t i n g L t d. May 29, 2013 Amended June 18, 2014 TABLE OF CONTENTS EXECUTIVE SUMMARY... 1 I INTRODUCTION... 10 II THE METHODOLOGY
More informationTOWNSHIP OF WEST LINCOLN
TOWNSHIP OF WEST LINCOLN April 18, 2016 dfa DFA Infrastructure International Inc. dfa DFA Infrastructure International Inc. 664-B Vine Street St. Catharines Ontario Canada L2M 7L8 Telephone: (905) 938-0965
More informationCITY OF CORNWALL DEVELOPMENT FEES REVIEW STUDY
CITY OF CORNWALL DEVELOPMENT FEES REVIEW STUDY SEPTEMBER 28, 2012 CONTENTS Page 1. INTRODUCTION 1.1 Introduction 1-1 1.2 Legislative Context for User Fees Review 1-1 2. ACTIVITY BASED COSTING USER FEE
More informationIMPLEMENTATION GUIDE: SCHOOL SITE ACQUISITION CHARGE
IMPLEMENTATION GUIDE: SCHOOL SITE ACQUISITION CHARGE British Columbia Ministry of Education February 2000 CONTENTS 1. INTRODUCTION 1.1 Summary 1 1.2 Limited Objective 1 1.3 Principles of the New Legislation
More informationOntario Municipal Board Commission des affaires municipales de l Ontario
Ontario Municipal Board Commission des affaires municipales de l Ontario ISSUE DATE: December 15, 2017 CASE NO(S).: PL150686 PROCEEDING COMMENCED UNDER subsection 34(19) of the Planning Act, R.S.O. 1990,
More informationBackground. Request for Decision. Proposed Changes to City's Development Charges By-Law and Rates. Recommendation. Presented: Tuesday, Apr 29, 2014
Presented To: City Council Request for Decision Proposed Changes to City's Development Charges By-Law and Rates Presented: Tuesday, Apr 29, 2014 Report Date Wednesday, Apr 23, 2014 Type: Presentations
More informationAREAWIDE WATER QUALITY MANAGEMENT PLAN AMENDMENT PROCESS
AREAWIDE WATER QUALITY MANAGEMENT PLAN AMENDMENT PROCESS (Revised and Approved June 28, 2007) The Areawide Water Quality Management Plan (Regional Plan) adopted by the North Front Range Water Quality Planning
More informationCity of Kingston Report to Council Report Number
To: From: Resource Staff: City of Kingston Report to Council Report Number 18-070 Mayor and Members of Council Date of Meeting: Subject: Executive Summary: Lanie Hurdle, Commissioner, Community Services
More informationTo establish a policy that guides City assessment review activities to help ensure stability and accuracy of the assessment base.
EFFECTIVE: June 1, 2007 REPLACES: new PAGE: 1 of 13 POLICY STATEMENT: To establish a policy that guides City assessment review activities to help ensure stability and accuracy of the assessment base. PURPOSE:
More informationPlanning and Building Table of Contents
Planning and Building Table of Contents PLANNING AND BUILDING...SECTION K Departmental Overview... K-1 Budget Forecast... K-2 Budget Highlights Operating... K-3 Organization Chart... K-4 Human Resources
More informationToukley District Development Contributions Plan No 6
Toukley District Development Contributions Plan No 6 September 2013 Table of Contents Contents 1 Administration and Operation of this Plan 5 1.1 Introduction 5 1.2 Relationship to Other Plans 5 1.3 Area
More informationREGIONAL DEVELOPMENT CHARGE BACKGROUND STUDY
Executive Summary 2018 Development Charge Background Study March 27, 2018 Page 1. REGION OF DURHAM REGIONAL DEVELOPMENT CHARGE BACKGROUND STUDY Prepared by: THE REGIONAL MUNICIPALITY OF DURHAM AND WATSON
More information3 YORK REGION 2031 POPULATION AND EMPLOYMENT FORECASTS
3 YORK REGION 2031 POPULATION AND EMPLOYMENT FORECASTS The Planning and Economic Development Committee recommends: 1. Receipt of the presentation by Paul Bottomley, Manager, Growth Management Economy and
More informationHEMSON GROWTH FORECAST
GROWTH FORECASTS 17 III GROWTH FORECAST This section provides the basis for the growth forecasts used in calculating the development charges and provides a summary of the forecast results. The growth forecast
More informationPolicy for the Deferral of Payment of Development Charges & Planning Application Fees within the Urban Centres
Policy for the Deferral of Payment of Development Charges & Planning Application Fees within the Urban Centres Adopted by Council June 18, 2012 Updated May 7, 2018 [Pick the date] 1 P a g e Table of Contents
More informationBritannia Village Flood Control Project
Britannia Village Flood Control Project Summary of Background Information February 2011 Contents 1) Flood Risks in the Village 2) Alternative Flood Risk Management Approaches Status Quo The Proposed Remedial
More informationOrange Development Contributions Plan 2015
Orange Development Contributions Plan 2015 Adopted by on 3 November 2015 F1783 0.0% Orange Development Contributions Plan 2015 Prepared for By GLN Planning Pty Ltd ABN 39 585 269 237 Level 10, 66 King
More informationDirect (Section 94) Development Contribution Plan Amendment 8
Direct (Section 94) Development Contribution Plan 2011 Page 1 This page has been left blank intentionally Page 2 Contents 1 Executive Summary 1.1 Fairfield 1.2 Basis of Plan 1.3 Scale of future development
More informationCITY CLERK. Further Report - Wellesley Central Health Corporation Wellesley Street East (Toronto Centre-Rosedale, Ward 27)
CITY CLERK Consolidated Clause in Report 6, which was considered by City Council on July 19, 20, 21 and 26, 2005. 74 Further Report - Wellesley Central Health Corporation - 146-160 Wellesley Street East
More informationCITY OF KINGSTON AND KINGSTON CMA POPULATION, HOUSING AND EMPLOYMENT PROJECTIONS
CITY OF KINGSTON AND KINGSTON CMA POPULATION, HOUSING AND EMPLOYMENT PROJECTIONS September 2013 CITY OF KINGSTON AND KINGSTON CMA POPULATION, HOUSING AND EMPLOYMENT PROJECTIONS HIGHLIGHTS OF THE REPORT
More informationMinimum Elements of a Local Comprehensive Plan
Minimum Elements of a Local Comprehensive Plan Background OKI is an association of local governments, business organizations and community groups serving more than 180 cities, villages, and townships in
More informationExpression of Interest. Development Charges Rebate Program City of Kingston
where history and innovation thrive Expression of Interest City of Kingston Please submit one original response and a digital copy on a CD/DVD or USB Drive in a sealed envelope clearly labeled with the
More informationHEMSON C o n s u l t i n g L t d
DEVELOPMENT CHARGES BACKGROUND STUDY Town of Gravenhurst C o n s u l t i n g L t d April, 2014 TABLE OF CONTENTS EXECUTIVE SUMMARY... 1 I INTRODUCTION... 7 II A TOWN-WIDE UNIFORM CHARGE APPROACH TO ALIGN
More informationSubject: City of St. Louis Park Beltline Boulevard Station Redevelopment Area Comprehensive Plan Amendment, Review File No.
Committee Report Business Item No. 2017-54 Community Development Committee For the Metropolitan Council meeting of March 8, 2017 Subject: City of St. Louis Park Beltline Boulevard Station Redevelopment
More informationDevelopment Contributions Policy 2018: Springvale Urban Expansion Area and Otamatea West
Development Contributions Policy 2018: Urban Expansion Area and West 1 P a g e Development Contributions Policy 2018: Urban Expansion Area and West Originator: Damien Wood, Development Engineer Contact
More information2017 WATER AND WASTEWATER IMPACT FEE STUDY CITY OF AZLE, TEXAS
2017 WATER AND WASTEWATER IMPACT FEE STUDY CITY OF AZLE, TEXAS JULY 2017 Prepared by: Weatherford Office Address: 1508 Santa Fe Drive, Suite 203 Weatherford, Texas 76086 (817) 594-9880 www.jacobmartin.com
More informationFull OPA application fee plus ZBA application Base Fee. Full SUB application fee plus 75% of ZBA application Base Fee
Town of Halton Hills Planning & Sustainability Fees Effective July 1, 2018 Combined Applications Fee Calculation Official Plan Amendment and Zoning By-law Amendment Applications received concurrently Zoning
More informationResidential Permits R-2, R-3, R-4, and U Occupancies 2018 Building Permit Valuation/Fee Schedule
Residential Permits R-2, R-3, R-4, and U Occupancies 2018 Building Permit Valuation/Fee Schedule The base valuation to determine permit fees for residential buildings and additions are based on a dollar
More informationAppendix A Housing Sites Inventory
City of Beverly Hills General Plan 2008 2014 Draft Housing Element Update Appendix A Housing Sites Inventory The State requires jurisdictions to identify sites for the development of housing within the
More informationCAPITAL IMPROVEMENTS ELEMENT
Goals, Objectives and Policies CAPITAL IMPROVEMENTS ELEMENT GOAL 9.1.: USE SOUND FISCAL POLICIES TO PROVIDE ADEQUATE PUBLIC FACILITIES TO ALL RESIDENTS WITHIN THE CITY. FISCAL POLICIES MUST PROTECT INVESTMENTS
More informationChapter CONCURRENCY
Chapter 14.28 CONCURRENCY Sections: 14.28.010 Purpose. 14.28.020 Development exempt from project concurrency review. 14.28.030 Concurrency facilities and services. 14.28.040 Project concurrency review.
More informationChapter 849 WATER AND SEWAGE SERVICES
Chapter 849 WATER AND SEWAGE SERVICES ARTICLE I Rebates 849-1. Definitions. 849-2. Application form. 849-3. Rebate on portion of surcharge on water rates for sewage service. 849-4. Submission of detailed
More informationTAUSSIG DEVELOPMENT IMPACT FEE JUSTIFICATION STUDY CITY OF ESCALON. Public Finance Public Private Partnerships Urban Economics Clean Energy Bonds
DAVID TAUSSIG & ASSOCIATES, INC. DEVELOPMENT IMPACT FEE JUSTIFICATION STUDY CITY OF ESCALON B. C. SEPTEMBER 12, 2016 Public Finance Public Private Partnerships Urban Economics Clean Energy Bonds Prepared
More informationInfrastructure, Development and Enterprise Services Development Priorities Plan Summary
Staff Report To Service Area City Council Infrastructure, Development and Enterprise Services Date Monday, February 12, 2018 Subject 2018 Development Priorities Plan Summary Report Number IDE 2018-14 Recommendation
More informationSteering Committee Meeting #6. Development Charge & Impost Fee Background Study. Summary Notes
Steering Committee Meeting #6 Development Charge & Impost Fee Background Study Summary Notes Steering Committee Meeting #6 was held on May 21 st, 2014 in the Loyalist Room, City Hall. The following briefly
More informationSection 94A Development Contribution Plans Land within the Cronulla Centre May 2008
s Land within the Cronulla Centre May 2008 Email ssc@ssc.nsw.gov.au www.sutherland.nsw.gov.au Table of Contents PART A LEVY SUMMARY 3 PART B EXPECTED DEVELOPMENT AND DEMAND FOR PUBLIC FACILITIES 3 1. INTRODUCTION
More informationCity of Pickering 2017 Development Charges Background Study
City of Pickering 2017 Development Charges Background Study Office Consolidation Incorporating the Background Study (October 5, 2017) as Amended and Approved by Council on December 11, 2017 Prepared January
More informationCITY OF GUELPH DEVELOPMENT CHARGE BACKGROUND STUDY. Consolidated Report. Includes: Development Charge Background Study, Dated: November 1, 2013
CITY OF GUELPH DEVELOPMENT CHARGE BACKGROUND STUDY Consolidated Report Includes: Development Charge Background Study, Dated: November 1, 2013 Addendum No.1 To City of Guelph Development Charge Background
More informationStrategic Growth in the Rangeview Area Structure Plan
2018 March 22 Page 1 of 8 EXECUTIVE SUMMARY Administration has received and reviewed an Outline Plan/Land Use (OP/LU) application within the Rangeview Area Structure Plan (ASP). The developer of these
More informationFinal Report. Town of New Tecumseth Growth Management Study. Prepared by The Jones Consulting Group Ltd. C. N. Watson and Associates Ltd.
Final Report Town of New Tecumseth Growth Management Study Prepared by The Jones Consulting Group Ltd. C. N. Watson and Associates Ltd. March 13, 2002 CONTENTS Page EXECUTIVE SUMMARY (i) 1. INTRODUCTION
More informationCITY OF STRATFORD OFFICIAL PLAN REVIEW BACKGROUND REPORT DEMOGRAPHIC AND ECONOMIC PROFILE AND POPULATION AND HOUSING GROWTH FORECAST NOVEMBER 21, 2012
CITY OF STRATFORD OFFICIAL PLAN REVIEW BACKGROUND REPORT DEMOGRAPHIC AND ECONOMIC PROFILE AND POPULATION AND HOUSING GROWTH FORECAST NOVEMBER 21, 2012 IN ASSOCIATION WITH: CONTENTS Page 1. INTRODUCTION
More information2014 Development Charges
DEVELOPMENT FINANCE 2014 Development Charges Background Study Amended June 2014 City of London 2014 Development Charges Background Study TABLE OF CONTENTS CHAPTER 1 - EXECUTIVE SUMMARY... 1 CHAPTER 2
More informationHonorable Mayor and Members of the City Council. Elizabeth Corpuz, Director of Planning and Building Services Jason P. Clarke, Senior Planner
Page 1 of 16 14-L TO: ATTENTION: FROM: SUBJECT: Honorable Mayor and Members of the City Council Jeffrey L. Stewart, City Manager Elizabeth Corpuz, Director of Planning and Building Services Jason P. Clarke,
More informationADMINISTRATIVE REPORT
ADMINISTRATIVE REPORT TO: FROM: Planning & Development Committee B. Newell, Chief Administrative Officer DATE: January 17, 2019 RE: Fourth Quarter, 2018 Activity Report Development Services Department
More informationDRAFT. Stormwater Management Program Credit Policy and Appeals Process Manual Policies & Procedures LOWER ALLEN TOWNSHIP STORMWATER AUTHORITY
DRAFT Stormwater Management Program Credit Policy and Appeals Process Manual Policies & Procedures LOWER ALLEN TOWNSHIP STORMWATER AUTHORITY JANUARY 2019 Table of Contents Introduction 3 Definitions 3
More informationIntroduced by the Council President at the request of the Joint. Planning Committee & substituted by the Land Use and Zoning Committee:
Substituted //0 Introduced by the Council President at the request of the Joint Planning Committee & substituted by the Land Use and Zoning Committee: ORDINANCE 0--E AN ORDINANCE AMENDING CHAPTER, ORDINANCE
More information2019 HUMBOLDT COUNTY REGIONAL HOUSING NEEDS ASSESSMENT PLAN
2019 HUMBOLDT COUNTY REGIONAL HOUSING NEEDS ASSESSMENT PLAN 2018 2027 Sixth Housing Element Cycle Adopted March 21, 2019 HUMBOLDT COUNTY ASSOCIATION OF GOVERNMENTS Regional Transportation Planning Agency
More informationMUNICIPALITY OF ARRAN-ELDERSLIE CHESLEY DRINKING WATER SYSTEM FINANCIAL PLAN
MUNICIPALITY OF ARRAN-ELDERSLIE CHESLEY DRINKING WATER SYSTEM FINANCIAL PLAN 15-013 GSS Engineering Consultants Ltd. Unit 104D 1010 9 th Avenue West Owen Sound ON N4K 5R7 519.372.4828 TABLE OF CONTENTS
More informationTITLE 18. ENVIRONMENTAL QUALITY CHAPTER 14. DEPARTMENT OF ENVIRONMENTAL QUALITY PERMIT AND COMPLIANCE FEES ARTICLE 1. WATER QUALITY PROTECTION FEES
Section R18-14-101. R18-14-102. Table 1. R18-14-103. R18-14-104. Table 2. Table 3. R18-14-105. R18-14-106. R18-14-107. R18-14-108. Table 4. Table 5. R18-14-109. Table 6. R18-14-110. Table 7. R18-14-111.
More informationG 1-1. Parkland Dedication By law Review Proposed By law Amendments. Council Meeting May 22, Committee of Council Meeting December 2012
G 1-1 Parkland Dedication By law Review Proposed By law Amendments Council Meeting May 22, 2013 Parkland Dedication By law 1. Background 2. Committee of Council Meeting December 2012 3. Development Industry
More informationFiscal Analysis November 14, Fiscal Analysis Fiscal Conditions Project Background
3.11 Fiscal Analysis Fiscal Analysis 3.11.1 Fiscal Conditions 3.11.1.1 Project Background The proposed action is a 149 unit residential development, including a private road and appurtenances, on a 29.3
More informationNORTH HUNTINGDON TOWNSHIP MUNICIPAL AUTHORITY
NORTH HUNTINGDON TOWNSHIP MUNICIPAL AUTHORITY T a p p i n g F e e C a l c u l a t i o n A p r i l 2 0 1 8 5 1 7 3 C A M P B E L L S R U N R O A D P I T T S B U R G H, P A 1 5 2 0 5-9 7 3 3 Table of Contents
More informationApr. 21, 2009 Ontario Municipal Board Commission des affaires municipales de l Ontario
ISSUE DATE: Apr. 21, 2009 Ontario Municipal Board Commission des affaires municipales de l Ontario IN THE MATTER OF subsection 53(19) of the Planning Act, R.S.O. 1990, c. P.13, as amended Appellant: Applicant:
More informationSection 94A Developer Contribution Plans Land within the Menai Centre May 2008
s 4-20 Eton Street, SUTHERLAND NSW 2232 Tel 02 9710 0800 Fax 02 9710 0265 Email ssc@ssc.nsw.gov.au www.sutherland.nsw.gov.au Table of Contents PART A Levy Summary 3 PART B Expected Development and Demand
More informationSchedule of Fees & Escrow Charges
PLANNING COMMISSION FEES (effective 6/8/10) Site Plan Review Filing Fees... $ 400.00 a) $1,000 (less than 50 acres, 150 units or 200,000 bldg sq ft) Site Plan Review for Attached or Multi-Family Housing
More information8 th Concession Road Sanitary Sewer Outlet
Oldcastle Hamlet Sanitary Sewer Servicing 8 th Concession Road Sanitary Sewer Outlet Cost Recovery By-Law Presentation Outline Background Project Cost Recovery Method Terminology North Talbot Road Sanitary
More informationUnderstanding Housing Development Costs: Components and Examples of Affordable Housing Development
Understanding Housing Development : Components and Examples of Affordable Housing Development A presentation by RI Housing Erin Reedy, Director of Development Four Main Components Determine a Developer
More informationSTAFF REPORT SAUSALITO CITY COUNCIL
STAFF REPORT SAUSALITO CITY COUNCIL AGENDA TITLE: Public hearing on proposed sanitary sewer fee effective fiscal year 2014-15 RECOMMENDED ACTIONS: (1) Open Public Hearing and receive public comment and
More information2018 Development Charges Background Study. Report For Public Consultation. HEMSON C o n s u l t i n g L t d.
2018 Development Charges Background Study Report For Public Consultation C o n s u l t i n g L t d. January 9, 2018 Table of Contents Executive Summary... 1 I Purpose of 2018 Development Charges Background
More informationSolid Waste Management Services Capital Budget Analyst Notes. City Budget 2013
City Budget 2013 Solid Waste Management Services Capital Budget Analyst Notes The City of Toronto's budget is presented by program and service, in Analyst Note format. The City's Capital Budget funds major
More informationGENERAL ADMINISTRATION AND CORPORATE SERVICES (Administration/Corporate/Finance Departments)
This document is provided as a comparison document for reference only. The years noted are based on the assumption that changes were considered for most or all sections of a respective bylaw, although
More informationReport to Committee of the Whole
Report to Committee of the Whole To: Mayor Linton and Members of Council Prepared By: Dan Wilson, Managing Director of Corporate Services / Treasurer Report: COR2018-10 Date: 19 Mar 2018 RE: Asset Management
More informationREGIONAL EVALUATION FRAMEWORK 1.0 INTRODUCTION 2.0 PURPOSE 3.0 DEFINITIONS. Edmonton Metropolitan Region Planning Toolkit
Edmonton Metropolitan Region Planning Toolkit Re-imagine. Plan. Build. Edmonton Metropolitan Region Growth Plan 1.0 INTRODUCTION On October 26, 2017, the Government of Alberta approved the Edmonton Metropolitan
More informationCITY OF MODESTO COMMUNITY FACILITIES DISTRICT NO (HETCH HETCHY) CFD REPORT
CITY OF MODESTO COMMUNITY FACILITIES DISTRICT NO. 2005-1 (HETCH HETCHY) CFD REPORT September 23, 2005 Goodwin Consulting Group, Inc. 555 University Avenue, Suite 280 Sacramento, California 95825 Phone
More informationDevelopment Contributions Plan
Development Contributions Plan Canterbury Town Centre & Riverfront Precinct * Adopted by Council: 11 August 2011 Effective from: 1 September 2011 Jim Montague GENERAL MANAGER City Planning Division Canterbury
More informationMunicipal Levies- A Developers Perspective
Municipal Levies- A Developers Perspective Background Shelter is a basic necessity Serviced land is essential to shelter Cost of lot paid by homebuyer Increased costs =decreased affordability 2 Levy Definition
More informationDevelopment Services Department Building Branch
Development Services Department Building Branch Public Meeting - December 5, 2012 Proposed 2013 Building Permit Fees Purpose On March 14, 2012, Town Council provided the following direction to staff: That
More informationCAPITAL IMPROVEMENTS ELEMENT:
CAPITAL IMPROVEMENTS ELEMENT: Goals, Objectives and Policies Goal 1. The provision of needed public facilities in a timely manner, which protects investments in existing facilities, maximizes the use of
More information4.12 POPULATION, HOUSING, AND EMPLOYMENT
SCOPE AND METHODOLOGY 4.12 POPULATION, HOUSING, AND EMPLOYMENT This section discusses the effects the proposed project may potentially have on local and regional population, housing, and employment. The
More information2007 Property Assessment and Tax Analysis of 2006 Data. Prepared for Real Property Association of Canada. November 23, 2007
2007 Property Assessment and Tax Analysis of 2006 Data Prepared for Real Property Association of Canada November 23, 2007 Prepared by: ALTUS DERBYSHIRE A division of Altus Group Limited 191 The West Mall,
More informationCounty-wide Planning Policies
Kittitas County County-wide Planning Policies Last amended on April 16, 2013 Ordinance No. 2013-005 KITTITAS COUNTY - COUNTY-WIDE PLANNING POLICIES PREAMBLE TO THE COUNTY-WIDE PLANNING POLICIES These Planning
More informationReport to: General Committee Meeting Date: December 5, 2017
Report to: General Committee Meeting Date: December 5, 2017 SUBJECT: 2017 Development s Background Study PREPARED BY: Kevin Ross, Manager, Development Finance Ext. 2126 RECOMMENDATION: 1) THAT the report
More informationEdward R. Sajecki Commissioner of Planning and Building
Corporate Report Clerk s Files Originator s Files CD.03.MIS DATE: TO: FROM: SUBJECT: Chair and Members of Planning and Development Committee Meeting Date: January 12, 2009 Edward R. Sajecki Commissioner
More informationEurobodalla Local Infrastructure Contributions Plan Prepared by. newplan. Urban Planning Solutions
Eurobodalla Local Infrastructure Contributions Plan 2012 Prepared by newplan Urban Planning Solutions Contents Page Number 1. Introduction 1 1.1 Overview of this Plan 1 2. Administration and operation
More informationDEVELOPMENT CHARGES BACKGROUND STUDY
DEVELOPMENT CHARGES BACKGROUND STUDY Revised City of Mississauga C o n s u l t i n g L t d. September 2009 TABLE OF CONTENTS EXECUTIVE SUMMARY... 1 I INTRODUCTION... 10 II METHODOLOGY IS BASED ON A CITY-WIDE
More informationPLANNING AND DEVELOPMENT 2016 TOWN OF MILTON APPROVED BUDGET
PLANNING AND DEVELOPMENT 10 TOWN OF MILTON APPROVED BUDGET Overview Barb Koopmans Director of Planning and Development 55.67 FTEs Capital Operating 2.1% 6.7% $918,557 $7,285,086 Administration Policy
More informationLoudoun 2040 Fiscal Impact Analysis Report Loudoun County, Virginia
Loudoun 2040 Fiscal Impact Analysis Report Loudoun County, Virginia Submitted to: Loudoun County, Virginia July 6, 2018 4701 Sangamore Road Suite S240 Bethesda, Maryland 20816 800.424.4318 www.tischlerbise.com
More informationStrategic Flood Risk Assessment
Strategic Flood Risk Assessment Draft Claremorris Local Area Plan 2012 2018 Prepared by Forward Planning Section Mayo County Council 1 Table of Contents Section 1: Overview of the Guidelines... 4 1.1 Introduction...
More informationCITY OF WATERLOO Water & Sanitary Sewer Rate Design Study Final Report & Financial Plan No
CITY OF WATERLOO Water & Sanitary Sewer Rate Design Study Final Report & Financial Plan No. 112301 April 1st 2016 DFA Infrastructure International Inc. dfa DFA Infrastructure International Inc. 33 Raymond
More informationCORPORATION OF THE TOWNSHIP OF ADELAIDE METCALFE. Financial Statements. December 31, 2015
CORPORATION OF THE TOWNSHIP OF ADELAIDE METCALFE Financial Statements December 31, 2015 Financial Statements Table of Contents PAGE Independent Auditors' Report 1 Statement of Financial Position 2 Statement
More informationCORPORATION OF THE TOWNSHIP OF ADELAIDE METCALFE. Financial Statements. December 31, 2016
CORPORATION OF THE TOWNSHIP OF ADELAIDE METCALFE Financial Statements December 31, 2016 Financial Statements Table of Contents PAGE Independent Auditors' Report 1 Statement of Financial Position 2 Statement
More informationNith Peninsula, Brant County Fiscal Impact Study
Fiscal Impact Study October 25, 2017 Fiscal Impact Study Prepared for: Losani Homes Prepared by: 33 Yonge Street Toronto Ontario M5E 1G4 Phone: (416) 641 9500 Fax: (416) 641 9501 economics@altusgroup.com
More informationImplementing a Vacant Home Tax in Toronto
EX26.4 REPORT FOR ACTION Implementing a Vacant Home Tax in Toronto Date: June 5, 2017 To: Executive Committee From: Deputy City Manager & Chief Financial Officer Wards: All SUMMARY City Council at its
More informationRECOMMENDATION REPORT DESIGN REVIEW FOR GROUND RELATED RESIDENTIAL DEVELOPMENT
Date: 16 July 2008 File: P44 Subject: RECOMMENDATION REPORT DESIGN REVIEW FOR GROUND RELATED RESIDENTIAL DEVELOPMENT Contact: Alex Taranu, Manager, Urban Design OVERVIEW: The purpose of this Report is
More informationCity Policy & Procedure
City Policy & Procedure Subject: PUBLIC-PRIVATE PARTNERSHIP (P3) POLICY Policy Number: #1011 Effective: September 3rd, 2014 Purpose: The City of Brandon Public-Private Partnership (P3) Policy intends to
More informationActing General Manager of Planning and Development Services
ADMINISTRATIVE REPORT Report Date: July 11, 2016 Contact: Randy Pecarski Contact No.: 604.873.7810 RTS No.: 11534 VanRIMS No.: 08-2000-20 Meeting Date: July 26, 2016 TO: FROM: SUBJECT: Vancouver City Council
More information