CUNY Capital Budget. University Faculty Senate and Community College Caucus. Vice Chancellor Iris Weinshall
|
|
- Rodney Barrett
- 6 years ago
- Views:
Transcription
1 CUNY Capital Budget University Faculty Senate and Community College Caucus April 19, 2013 Office of Facilities Planning, Construction & Management Vice Chancellor Iris Weinshall
2 Capital Budget Bond Funds New Buildings Building Renovations Equipment Purchases Large IT projects with Long Term Benefits Grants Federal/State/City/Private
3 Budget Funders Governor State Division of Budget (DOB) Legislature Mayor Office of Management and Budget (OMB) City Council Borough Presidents
4 Projects with City Council funding York College SIM Lab
5 Projects with City Council funding LaGuardia CC Center 3 Building Facade
6 Capital Budget Process Five-Year Plan/Request Six-month process Colleges and FPCM staff participate CUNY Board approves in November
7 Current Capital Program Program focuses on Completing funding for partially funded projects Critical Maintenance funding Expanding science facilities Providing for growth and programmatic changes
8 Types of Projects Partially-Funded Projects
9 Types of Projects Critical Maintenance
10 Types of Projects Expanding Science Facilities
11 Types of Projects Programmatic Expansion
12 State Budget Request FY Year Request total $6.4 billion $5.1 Billion $650 million $650 Million Senior Colleges - State Community Colleges - State Community Colleges - City
13 State FY Budget Results Funding appropriated $8 M critical maintenance at Community Colleges $55 M challenge grant for CUNY 2020 Initiative $37 M administrative costs for capital program $3.1 billion existing funding (re-appropriations) $20.4 M Superstorm Sandy recovery funds
14 State funding over $3 billion in last six years FY 08/09 FY 09/10 FY 10/11 FY 11/12 FY 12/13 FY13/14 $1.8 B (start of five-year plan) $284 million $319 million $315 million $311 million $63 million
15 CUNY capital program spending Last five years capital spending State and City combined ($ millions) FY FY FY FY FY TOTAL $429 $666 $697 $483 $421 $2,696
16 Recently completed new facilities CUNY Law New Facility
17 Recently completed new facilities BMCC Fiterman Hall
18 Recently completed new facilities Bronx CC North Hall & Library
19 Recently completed new facilities Lehman New Science Facility
20 Available Funds Senior
21 Quick primer on State funds Appropriations are allocated to CUNY Available until expended Re-appropriated each year CUNY is allowed to spend to a cash ceiling Less cash is allocated than appropriations Critical Maintenance
22 Available State Re-appropriations State $3.1 billion is available Seniors $2.7 billion Over 300 projects underway Senior and Community College State cash spending cap for FY almost $500 million
23 Re-appropriations Seniors Examples of existing major Senior College Commitments - Programmatic ASRC & CCNY Science Buildings Baruch 17 Lexington Avenue Brooklyn Performing Arts Center Central Office Data Center Integration CUNY FIRST Hunter Weill Cornell NYC College of Technology Academic Bldg. I Hunter Science/Health Professions Bldg. Medgar Evers Library Expansion Total $419 M $ 33 M $ 70 M $ 25 M $ 32 M $ 65 M $235 M $ 54 M $ 22 M $955 M
24 Major projects starting construction NYCC Tech Academic Building I Baruch Field Bldg at 17 Lex
25 Seniors - major projects in design Brooklyn - Roosevelt Hall
26 Seniors - major projects in design York - Academic Village
27 Seniors - major projects in design CSI - Computational Ctr.
28 Seniors - major projects in design Hunter - Science & Health Professions Bldg
29 Seniors - major projects in design Queens Fitzgerald Gym Ren0vation
30 Seniors Re-appropriations Existing major critical maintenance projects Lehman Utility Upgrades CCNY Marshak Building HVAC Upgrades Queens NSB Building HVAC Upgrades Brooklyn Ingersoll Hall Renovations Medgar Evers Carroll St. Building Upgrades NYCCT Namm Hall Elevator and Bathroom Hunter College HVAC Upgrades $ 33 M $ 22 M $ 28 M $ 36 M $ 25 M $ 15 M $ 23 M CSI Campus Wide Underground Utilities $ 6.5 M Total $ M
31 Available Funds Community Colleges
32 Community College funding process 50/50 matching requirement State has committed to matching city critical maintenance $71 million agreement with City Council/OMB provides some additional critical maintenance lump sum funding
33 Re-appropriations Community Colleges No substantive change due to State Budget City allocations drive funding CUNY received $25 million a year local elected officials and OMB State normally matches Community Colleges have accumulated over $260 million in last five years
34 Available State Re-appropriations State $3.1 billion is available Community Colleges approximately $800 million (matched) Over 300 projects underway State cash spending cap for FY almost $500 million
35 Re-appropriations Examples of existing major Community College commitments LaGuardia Center 3 Façade Bronx Utility Upgrades Kingsborough Central Plant Queensborough Electrical Upgrade BMCC Bathroom ADA Upgrades BMCC Student Commons Expansion Various College fire alarm upgrades Various College roof repairs Various College façade repairs Total $100 M $50 M $19 M $35 M $ 7 M $11 M $10 M $20 M $15 M $256 M
36 Questions?
Amount Requested. Project Name
The City University of New York FY 2008-09 Capital Results State Five-Year Capital Plan FY 2008-09 to FY 2012-13 SENIOR COLLEGES Requested 2008-09 Enacted CUNY-Wide Seniors C.A.: Health & Safety $ 165,769
More informationTHE CITY UNIVERSITY OF NEW YORK. Basic Financial Statements, Management s Discussion and Analysis, and Supplementary Schedules.
Basic Financial Statements, Management s Discussion and Analysis, and Supplementary Schedules (With Independent Auditors Report Thereon) Table of Contents Independent Auditors Report 1 Management s Discussion
More informationTHE CITY UNIVERSITY OF NEW YORK. Basic Financial Statements and Management s Discussion and Analysis. June 30, 2013
Basic Financial Statements and Management s Discussion and Analysis (With Independent Auditors Report Thereon) Table of Contents Independent Auditors Report 1 Management s Discussion and Analysis (Unaudited)
More informationNEW YORK STATE ASSEMBLY PROPOSALS FOR EXECUTIVE BUDGET RESUBMISSION
CONCURRENT RESOLUTION in response to the 2008-2009 Executive Budget submission (Assembly Bill Nos. A. 9800-B, A. 9801-A, A. 9803-B, A. 9804-B, A. 9805-B, A. 9806-B, A. 9807-B, A. 9808-B, A. 9809-B, and
More informationTHE CITY UNIVERSITY OF NEW YORK. Basic Financial Statements, Management s Discussion and Analysis, and Supplementary Schedules.
Basic Financial Statements, Management s Discussion and Analysis, and Supplementary Schedules (With Independent Auditors Report Thereon) Table of Contents Independent Auditors Report 1 Management s Discussion
More informationSupplemental Financial Statements Schedules (Un-audited)
RESEARCH FOUNDATION of The CITY UNIVERSITY OF NEW YORK Supplemental Financial Statements Schedules (Un-audited) Prepared For the Board of Directors For Fiscal Year Ending June 30, 2011 with comparison
More informationTHE CITY UNIVERSITY OF NEW YORK. Basic Financial Statements and Management s Discussion and Analysis. June 30, 2014
Basic Financial Statements and Management s Discussion and Analysis (With Independent Auditors Report Thereon) Table of Contents Independent Auditors Report 1 Management s Discussion and Analysis (Unaudited)
More informationHostos Community College Budget Process
Hostos Community College Budget Process Note: The following is largely excerpted from the 2017 MSCHE Periodic Review Report The Budget Components and Financial Planning Process The primary source of annual
More informationRESOLUTION OF THE CITY UNIVERSITY CONSTRUCTION FUND APPROVING THE ANNUAL REPORT ON PROCUREMENT CONTRACTS AND THE GUIDELINES FOR PROCUREMENT CONTRACTS
Item 3 Resolution No 2270 June 27, 2018 RESOLUTION OF THE CITY UNIVERSITY CONSTRUCTION FUND APPROVING THE ANNUAL REPORT ON PROCUREMENT CONTRACTS AND THE GUIDELINES FOR PROCUREMENT CONTRACTS RESOLVED: That
More information2018 Educational and Facilities Master Plan (EFMP) and Proposed Bond Projects. June 27, 2018 // Board of Trustees Meeting
2018 Educational and Facilities Master Plan (EFMP) and Proposed Bond Projects June 27, 2018 // Board of Trustees Meeting Proposed Bond Projects Overall Phasing Phase 1A Phase 1B Phase 2 Phase 3 Phase TBD
More informationOperating & Capital Budget Plan May 2017
2017-2018 Operating & Capital Budget Plan May 2017 Operating and Capital Budget Plan FY 2018 Operating Budget - Highlights Table 1: Composite Operating Budget 4 Table 2: Composite Operating Budget - by
More informationCapital Maintenance. 2. Deferred Maintenance, May 18, 2009 <http://en.wikipedia.org/wiki/deferred_maintenance>
Capital Maintenance Capital Maintenance Capital maintenance has previously been known as deferred maintenance, the act of postponing maintenance in order to save money or avoid costs. 2 At NYU, the term
More informationCapital Projects Completed since 1988
Projects Completed since 1988 Project Cost FY1988 ICCB Building Illinois Repair & Renovation - Replace Carpet in Classroom Buildings, Library and Lobby of Admin $ 51,901.00 $ 51,901.00 $ 51,901.00 FY1990
More informationFacilities Planning & Construction Report nd Quarter Ending December 31, 2017
Facilities Planning & Construction Report 2017 18 2 nd Quarter Ending December 31, 2017 Overview District SRID Spending (MG100) Summary By College By Site District Measure J Spending (MJ100) Summary By
More informationPresentation to the UH Faculty Senate. University of Houston FY 2016 Budget For current information see
Presentation to the UH Faculty Senate University of Houston FY 2016 Budget For current information see http://www.uh.edu/af/budget/index.htm 1 Contents Background and Process Slides 3-12 Budget Topic:
More informationTEXAS TECH UNIVERSITY HEALTH SCIENCES CENTER OPERATING BUDGET FISCAL YEAR 2018
TEXAS TECH UNIVERSITY HEALTH SCIENCES CENTER 7335191 OPERATING BUDGET FISCAL YEAR 2018 Fiscal Year 2018 Operating Budget Summary TABLE OF CONTENTS Fiscal Year 2018 Operating Budget - Source of Funds (Graph)......................
More informationPROPOSITION FARMINGTON SCHOOLS. April 8, 2014 Bond Issue
PROPOSITION FARMINGTON SCHOOLS April 8, 2014 Bond Issue PROPOSITION FARMINGTON SCHOOLS - BOND LANGUAGE Shall the Board of Education of the Farmington R-7 School District of St. Francois County, Missouri,
More informationGoverning Board Bond Update. Measure G Bond Program. for. Solano Community College District
Governing Board Bond Update for Measure G Bond Program prepared by Kitchell for the Solano Community College District Included in Booklet: Board Update Bond Financial Summary Completed Projects Projects
More informationTEXAS TECH UNIVERSITY HEALTH SCIENCES CENTER
TEXAS TECH UNIVERSITY HEALTH SCIENCES CENTER FY2015 16973569 7335191 3000000 3525000 1500000 2000000 OPERATING BUDGET FISCAL YEAR 2017 Fiscal Year 2017 Operating Budget Summary TABLE OF CONTENTS Fiscal
More informationAttachment FC 16 SBCC 11/17/2017. STATE BOARD OF COMMUNITY COLLEGES Construction and Property November 17, 2017
A. Approval - New (Non-State and Other State Funds) Name (Other State) (Other State) Non-State Funds/ Undetermined 1 N/A B. Approval - Amended (Non-State and Other State Funds) 1 Coastal Carolina Main
More informationBoard Agenda Item G.1. Board Agenda Item G.2.
AGENDA FACILITIES PLANNING COMMITTEE BOARD OF SUPERVISORS FOR THE UNIVERSITY OF LOUISIANA SYSTEM *10:35 a.m., Thursday, August 23, 2018** Room 100, Louisiana Purchase Room Claiborne Conference Center 1201
More informationDESERT COMMUNITY COLLEGE DISTRICT PROPOSITION 39, GENERAL OBLIGATION BONDS (MEASURE B, MARCH 2004) PERFORMANCE AUDIT JUNE 30, 2008
(MEASURE B, MARCH 2004) (MEASURE B, MARCH 2004) TABLE OF CONTENTS Page Independent Auditors Report 1 Objectives... 2 Scope of the Audit. 2 Background Information 2-3 Procedures Performed... 3-4 Results
More informationTHE FLORIDA INTERNATIONAL UNIVERSITY BOARD OF TRUSTEES December 5, 2018
Consent Agenda FF2 THE FLORIDA INTERNATIONAL UNIVERSITY BOARD OF TRUSTEES December 5, 2018 Subject: Approval of Carryforward Funds Proposed Board Action: Approve the Florida International University (FIU)
More informationA N N U A L R E P O R T DORMITORY AUTHORITY S T A T E O F N E W Y O R K
DASNY Annual Report 2017 A N N U A L R E P O R T 2 0 1 7 DORMITORY AUTHORITY S T A T E O F N E W Y O R K 4 16 28 36 40 Innovative Communities 4 Educated Communities 16 Healthy Communities 28 Resilient
More informationUniversity of Houston System
UNIVERSITY of HOUSTON SYSTEM University of Houston System FY2014 Annual Budget August 14, 2013 1 UNIVERSITY of HOUSTON SYSTEM FY2013 Current year Total Budget $ Millions Operating Budget $ 1,247.5 Capital
More informationTEXAS TECH UNIVERSITY HEALTH SCIENCES CENTER OPERATING BUDGET FISCAL YEAR 2019
TEXAS TECH UNIVERSITY HEALTH SCIENCES CENTER 7335191 OPERATING BUDGET FISCAL YEAR 2019 Fiscal Year 2019 Operating Budget Summary TABLE OF CONTENTS Fiscal Year 2019 Operating Budget - Source of Funds (Graph)......................
More informationThompson Rivers University
Thompson Rivers University Operating Budget 2010 2011 Senate Presentation April 2010 Budget Committee of Senate BCOS Regular monthly meetings Regular capital construction updates Presentations from Faculty
More informationThe Ohio State University Board of Trustees. October 28, 2009
The Ohio State University Board of Trustees TOPIC: October 28, 2009 CONTEXT: Capital Recommendations At the September 17 th Fiscal Affairs Committee meeting, the University Administration promised to come
More informationEAST TENNESSEE STATE UNIVERSITY BOARD OF TRUSTEES FINANCE AND ADMINISTRATION COMMITTEE MARCH 2018 SPECIAL CALLED MEETING AGENDA
EAST TENNESSEE STATE UNIVERSITY BOARD OF TRUSTEES FINANCE AND ADMINISTRATION COMMITTEE MARCH 2018 SPECIAL CALLED MEETING 3:00-4:00pm EDT Thursday March 29, 2018 President s Conference Room Burgin Dossett
More informationTEXAS TECH UNIVERSITY HEALTH SCIENCES CENTER. Fiscal Year 2004 Operating Budget Summary
Fiscal Year 2004 Operating Budget Summary TABLE OF CONTENTS Educational and General Funds Budget Summary................................ 1 Higher Education Assistance Funds Allocation...................................
More informationFY 2016 BUDGET RUTGERS NEWARK
RUTGERS SCHOOLS Office of Budget and Resource Studies January 29, 2016 Office of Budget and Resource Studies 33 Knightsbridge Road Piscataway, NJ 08854 budget.rutgers.edu p. 848-932-7472 f. 732-445-3579
More informationCONSTRUCTION PROJECTS STATUS REPORT BOARD OF TRUSTEES MEETING - August 2, 2017
Planning Academic & Research Facilities - Homer 300008 $1,850,000 $128 P UCONN 2000 Bond Funds 03/29/17 2020 Babbidge Library Renovations Main Campus Parking Replacements 300023 $500,000 $0 P 06/28/17
More informationDepartment Chair Online Resource Center Facility Maintenance or Facility Improvement? Taking a Responsible Approach
Department Chair Online Resource Center Facility Maintenance or Facility Improvement? Taking a Responsible Approach Richard Bettega, associate vice president for facilities, Lewis and Clark College. Facility
More informationADVANCING CAPITAL OUTLAY
ADVANCING CAPITAL OUTLAY Robert R. Broyden Assistant Vice President for Capital Assets and Financial Management 1 Major Topics Today: 1) Commitment to long-range planning processes 2) Update on 2012 General
More informationSummary of Capital Budget Request Tennessee Board of Regents. of the. September 21, 2017
Summary of Capital Budget Request 2018-2019 of the Tennessee Board of Regents September 21, 2017 1 This is the Summary of the Capital Budget Request for Fiscal Year 2018-2019 for the Finance and Business
More informationChabot College Project List Biology Building Phase 1 $0 $0 $0 Measure B $0 $0 $0 Measure A 2016 $0 $0 $0
Chabot College Project List 552330 Biology Building Phase 1 $0 $0 $0 Measure A 2016 $0 $0 $0 562100 Library & Learning Conncetions Building Replacement 100 $57,875,000 $0 $0 Measure A 2016 $57,875,000
More informationBudget Flint Campus
2016-2017 Budget Flint Campus This page left blank intentionally. Table of Contents The University of Michigan - Flint Section One - Summary of Budgeted Revenues and Expenditures Schedule A: Summary by
More informationCONSTRUCTION PROJECTS STATUS REPORT BOARD OF TRUSTEES MEETING - September 27, 2017
Planning Budget Phase Academic & Research Facilities - Homer 300008 $1,850,000 $391 P UCONN 2000 Bond Funds 03/29/17 2020 Babbidge Library Renovations Main Campus Parking Replacements 300023 $500,000 $32,640
More informationPROPOSED BUDGET San Jacinto Community College District Budget Hearing August 4, 2014
PROPOSED BUDGET 2014-2015 San Jacinto Community College District Budget Hearing August 4, 2014 1 Highlights of the Proposed 2014 2015 Budget State Revenue Major Revenue Assumptions No change in rate FY15,
More informationFY 2018 Stockton University Operational & Capital Report as of May 31, 2018
FY 2018 Stockton University Operational & Capital Report Table of Contents Page Operational Budgets 1-2 Internal Capital Projects Summary 3 Internal Capital Projects 4-5 Other Capital Projects 6 State
More informationFiscal Year (FY13) Operating Budget and Capital Budget Overview
Approved by President Rush Fiscal Year 2012-2013 (FY13) Operating Budget and Capital Budget Overview Background A university budget represents the complex interchange between revenue streams that support
More information9 th Annual Budget Forum April 2014
9 th Annual Budget Forum April 2014 Presenters: Helen Benjamin Chancellor Gene Huff Executive Vice Chancellor Jonah Nicholas Associate Vice Chancellor GOALS Information Arzu Smith Director of District
More informationDivision of Finance and Administration Financial Update. Karol Kain Gray Vice Chancellor for Finance and Administration September 25, 2013
Division of Finance and Administration Financial Update September 25, 2013 CAFR AWARD o The UNC Finance Division earned the University s 18 th consecutive Certificate of Achievement for Excellence in Financial
More informationHOCKING COLLEGE Fee Pledge Request - $22,000,000 April, I. Project Overview
I. Project Overview Hocking College is seeking approval to issue fixed rate general receipts bonds under the State s Credit Enhancement Program for two-year institutions for the following purposes: Purchase
More informationCENTRAL STATE UNIVERSITY Wilberforce, Ohio. FINANCIAL STATEMENTS June 30, 2017 and 2016
Wilberforce, Ohio FINANCIAL STATEMENTS Wilberforce, Ohio FINANCIAL STATEMENTS CONTENTS INDEPENDENT AUDITOR S REPORT... 1 MANAGEMENT S DISCUSSION AND ANALYSIS (UNAUDITED)... 3 FINANCIAL STATEMENTS STATEMENTS
More informationCapital Projects Ordinances (CPO)
Capital Projects Ordinances (CPO) This section accounts for financial resources to be used for the acquisition or construction of major capital facilities. Listed below are brief descriptions for active
More information2017/18 Annual Budget Report. Charlie Faas VP Administration & Finance/CFO
2017/18 Annual Budget Report Charlie Faas VP Administration & Finance/CFO Fiscal Year Budget Overview Increase in tuition and General Fund appropriation Tuition rate increase ($270, 4.9% increase) +240
More informationSONOMA COUNTY JUNIOR COLLEGE DISTRICT PROPOSITION 39 AND MEASURE A GENERAL OBLIGATION BONDS SANTA ROSA, CALIFORNIA
SONOMA COUNTY JUNIOR COLLEGE DISTRICT PROPOSITION 39 AND MEASURE A GENERAL OBLIGATION BONDS SANTA ROSA, CALIFORNIA YEAR ENDED TABLE OF CONTENTS PAGE Independent Auditors' Report 1 Objectives 2 Scope of
More information1. Program & Planning Adjustments: 2. Cash flow: 3. Indenture Amendments:
The key elements underlying the revisions to the phasing outline are detailed below. These changes are driven by academic priorities, economic realities and the importance of spending bond proceeds in
More informationSONOMA COUNTY JUNIOR COLLEGE DISTRICT PROPOSITION 39 AND MEASURE A GENERAL OBLIGATION BONDS SANTA ROSA, CALIFORNIA
SONOMA COUNTY JUNIOR COLLEGE DISTRICT PROPOSITION 39 AND MEASURE A GENERAL OBLIGATION BONDS SANTA ROSA, CALIFORNIA YEAR ENDED TABLE OF CONTENTS PAGE Independent Auditors' Report 1 Objectives 2 Scope of
More informationROCHESTER COMMUNITY AND TECHNICAL COLLEGE
ROCHESTER COMMUNITY AND TECHNICAL COLLEGE A MEMBER OF THE MINNESOTA STATE COLLEGES AND UNIVERSITIES SYSTEM ANNUAL FINANCIAL REPORT FOR THE YEARS ENDED JUNE 30, 2013 and 2012 Prepared by: Rochester Community
More informationNew Jersey Institute of Technology
New Jersey Institute of Technology FY18 Budget Status Report and FY19 Budget Development Status Presented to the Joint Session of the Strategic Planning Steering Committee and Committee on Academic Strategic
More informationUniversity of Virginia Status Report on the Plan to Address Deferred Maintenance
Executive Summary University of Virginia Status Report on the Plan to Address Deferred Maintenance The University of Virginia s facilities portfolio includes 540 buildings and related infrastructure, encompassing
More informationFLORIDA BOARD OF GOVERNORS NOTICE OF PROPOSED AMENDED REGULATION. REGULATION NUMBER AND TITLE: Regulation State University Operating Budgets
FLORIDA BOARD OF GOVERNORS NOTICE OF PROPOSED AMENDED REGULATION DATE: June 27, 2016 REGULATION NUMBER AND TITLE: Regulation 9.007 State University Operating Budgets SUMMARY: This regulation is being amended
More informationConnecticut State University System (The System Office, Central Connecticut State University, Eastern Connecticut State University, Southern
Connecticut State University System (The System Office, Central Connecticut State University, Eastern Connecticut State University, Southern Connecticut State University, Western Connecticut State University,
More informationMEASURE I CITIZENS' OVERSIGHT COMMITTEE MEETING AUGUST 5, 2014 QUARTERLY FINANCIAL REPORT
MEASURE I CITIZENS' OVERSIGHT COMMITTEE MEETING AUGUST 5, 214 QUARTERLY FINANCIAL REPORT Bond Income and Expenditure Summary Income Statement Projects List Project Expenditure Summary Cash Flow Report
More informationFrequently asked questions on the Ridgewood Public School Budget. 2. Why does the Board approve a preliminary budget?
Over the last few weeks the Board of Education has received a number of questions regarding the proposed 2018-19 budget. We hope that the Frequently Asked Questions and our Answers below will help to shed
More informationFISCAL 2018 BUDGET UPDATE
FISCAL 2018 BUDGET UPDATE BASED ON APPROVED BUDGET INSTITUTE BUDGET PLANNING AND ADMINISTRATION JULY 1, 2017 Outline 1. Capital Budget funding sources & current projects 2. Fiscal 2018 Operating Budget
More informationFunding for Maintenance and Repair at UMKC. Faculty Senate November 4, 2014
Funding for Maintenance and Repair at UMKC Faculty Senate November 4, 2014 Changing the Conversation Space Understand how age profile drives capital and operational demands Capital Multiyear plans that
More informationFY2019 MEIF / Auxiliary Services / E&G Budget Discussion
1 of 20 FY2019 MEIF / Auxiliary Services / E&G Budget Discussion Kody Varahramyan Vice President for Research and Dean of the Graduate School Susan J. Hunter President Claire Strickland Chief Business
More informationANALYSIS TABLES
QUILLEN COLLEGE of MEDICINE ANALYSIS TABLES 208-209 THE STATE UNIVERSITY AND COMMUNITY COLLEGE SYSTEM OF TENNESSEE JULY PROPOSED BUDGET 208-9 BUDGET ANALYSIS FORMS 2 Contra Revenue Accounts for Bad Debt
More informationStockton University FY 2019 Operational and Capital Report as of January 31, 2019
Stockton University FY 2019 Operational and Capital Report Stockton University FY 2019 Operational and Capital Report Table of Contents Page Operational Budget Summary: University, Auxiliaries, and Agency
More informationColorado State University System Financial Statements and Independent Auditor s Reports Financial Audit Years Ended June 30, 2016 and 2015 Compliance
Colorado State University System Financial Statements and Independent Auditor s Reports Financial Audit Compliance Audit Year Ended June 30, 2016 THIS PAGE LEFT BLANK INTENTIONALLY Table of Contents...
More informationMaking the Case for Funding Deferred Maintenance Before it s Too Late
Making the Case for Funding Deferred Maintenance Before it s Too Late Jim Kadamus Vice President Sightlines Cuba Plain Assistant Vice President for Budget Planning and Development University of Missouri
More informationWorking with Overhead Rates and Fringe Benefits
Working with Overhead Rates and Fringe Benefits Ken Miller, Assistant Vice President for Finance & University Controller Dave McGarry, Associate Controller, Financial Reporting & Cost Accounting Sharon
More informationBUDGET AND FINANCE COMMITTEE. March 19, Minutes
BOARD OF GOVERNORS BUDGET AND FINANCE COMMITTEE March 19, 2003 Minutes The meeting was called to order at 1:05 p.m. by Governor Driker in the Alumni Lounge. Secretary Miller called the roll. A quorum was
More informationCONSTRUCTION PROJECTS STATUS REPORT BOARD OF TRUSTEES MEETING - April 26, 2017
Project Name by Construction Project # Planning Academic & Research Facilities - Homer 300008 $1,850,000 $0 P UCONN 2000 Bond Funds 03/29/17 2020 Babbidge Library Renovations Stamford Campus Improvements/Housing
More informationUniversity of Colorado Denver
University of Colorado Denver Fiscal Policy Title: Source: Prepared by: Approved by: Budgeting Budget Office Budget Office Associate Vice Chancellor for Budget and Operations Effective Date: July 1, 2010
More informationGUIDELINES FOR MANAGING FUND DEPOSITS
GUIDELINES FOR MANAGING FUND DEPOSITS AND DISBURSEMENTS Policy Id: Bus.029 - Guidelines for Managing Fund Deposits and Disbursements Contact: Executive Director of Finance and Business Services (212) 237-8516
More informationCity University of New York Bronx Community College. College-wide P&B Meeting September 20, 2017
City University of New York Bronx Community College College-wide P&B Meeting September 20, 2017 FY 2018 Tax Levy Budget Review Funding Allocation Summary Resources and Expenditures Operating Expenditures
More informationPriority #1 Request for Construction FY Priority #2 Anticipated Request for Planning FY 2019
V. IMPLEMENTATION PLAN a) Prioritize major capital projects requested from the State, including a brief project description and estimated cost, in the format provided. (Adjust previously developed or prior
More informationTuition Increase Recommendation FY June 18, 2009 June Regular Board Meeting
With the assumption that the Mississippi State Legislature will adopt a budget by June 30, 2009 for FY 2010, approval is requested budgets (including Ayers) and Auxiliary Fund budgets. For all other general
More informationSUBJECT: Deferred Maintenance and Capital Outlay Planning
Capital Planning, Design and Construction Elvyra F. San Juan 401 Golden Shore, 2 nd Floor Assistant Vice Chancellor Long Beach, CA 90802-4210 www.calstate.edu (562) 951-4090 esanjuan@calstate.edu DATE:
More informationBond Amount: $18,470,000. Proposed I&S Tax Rate Increase: $.3180
Bond Amount: $18,470,000 Proposed I&S Tax Rate : $.3180 How was the EBISD 2017 Bond developed? The bond package was developed from K-12 academic needs identified by our fifty-member community facilities
More informationRedwoods Community College District Eureka, California SCHEDULE OF PROCEEDS AND USE OF GENERAL OBLIGATION BONDS INDEPENDENT AUDITORS REPORTS
Eureka, California SCHEDULE OF PROCEEDS AND USE OF GENERAL OBLIGATION BONDS INDEPENDENT AUDITORS REPORTS June 30, 2016 General Obligation Bonds TABLE OF CONTENTS June 30, 2016 Page Number Independent Auditors
More informationCONSTRUCTION PROJECTS STATUS REPORT BOARD OF TRUSTEES MEETING - June 28, 2017
Planning Budget Phase Academic & Research Facilities - Homer 300008 $1,850,000 $0 P UCONN 2000 Bond Funds 03/29/17 2020 Babbidge Library Renovations Main Campus Parking Replacements 300023 $500,000 $0
More informationErica Bowers, Ed.D. Chair, Planning, Resource, and Budget Committee (PRBC)
MEMORANDUM Date: May 5, 2016 To: From: Mildred García, Ed.D. University President Erica Bowers, Ed.D. Chair, Planning, Resource, and Budget Committee (PRBC) Subject: PRBC Recommendations for FY 2016-17
More informationCapital Improvements Program FY CIP Projects by Component
CIP Projects by Component HEF Lamar Institute of Technology Student Service Learning Center 2020 $42,778,500 $0 $12,778,500 $0 $30,000,000 $0 $0 Carry Over Amended Lamar State College-Orange Academic Building
More informationDATE: May 31, 2017 Data Code: PROJECT: Alamo Colleges Program Management. SUBJECT: Reaffirmation Information: Construction Report
DATE: May 31, 2017 Data Code: 1.02 TO: John W. Strybos, PE FROM: K. LeBlanc, PE, CFM, LEED GA PROJECT NO.: 170-11026-000 Routing V. Buzzelli R. Reyes J. Grom PROJECT: Alamo Colleges Program Management
More informationStreamlined Capital Outlay Projects Funded from. Capital Outlay Bond Funds Legislative Report Legislative Session
Streamlined Capital Outlay Projects Funded from Capital Outlay Bond Funds Legislative Report 2008-09 Legislative Session November 2008 November 2008 UNIVERSITY OF CALIFORNIA Report on Streamlined Capital
More informationChancellor s Message - Achievements
Chancellor s Message - Achievements We have achieved significant educational and operational advances. To name a few: $41 million in savings from operations through the elimination of redundancies and
More informationUNIVERSITY OF NORTHERN COLORADO: FINANCIAL REPORT 03/31/2011
UNIVERSITY OF NORTHERN COLORADO: FINANCIAL REPORT 03/31/2011 OVERVIEW Financial highlights of the 3 rd quarter financial report for fiscal year 2011-12 are summarized below: Cash The University s cash
More informationDepartment Report. Cultural Affairs Commission June 15, Cliff Gillespie, Business Operations Manager Office of Cultural Affairs City of Dallas
Department Report Cultural Affairs Commission June 15, 2017 Cliff Gillespie, Business Operations Manager Office of Cultural Affairs City of Dallas Agenda FY 2017-18 Budget Update 2017 Bond Program Moody
More informationBUDGET AND FINANCE COMMITTEE. October 1, Minutes
BOARD OF GOVERNORS BUDGET AND FINANCE COMMITTEE October 1, 2003 Minutes The meeting was called to order at 11:00 a.m. by Governor Driker in the Alumni Lounge, Alumni House. Secretary Miller called the
More information$4,701,440 $2,727,355 $2,596,419 $447,703 $11,216,598 $21,689,515
INTRODUCTION The 5-Year District Facilities Work Program is a very important document. The Department of Education, Legislature, Governor's Office, Division of Community Planning (growth management), local
More informationCONSTRUCTION PROJECTS STATUS REPORT BOARD OF TRUSTEES MEETING December 12, 2012
Project Name by Phase Project # Current BOT Approved Budget Encumbrances (As of 11/28/12) Budget Phase Budgeted Funding Source(s) (s) Planning Budget Phase Ecology and Evolutionary Biology (EEB) 201583
More informationProgress Update Identified Needs & Capital Plan
Progress Update Identified Needs & Capital Plan May 29, 2012 Buena Park School District Facilities Assessment & Implementation Plan 0 Facilities Planning, Public Finance, Program Administration Summary
More informationANNUAL FINANCIAL REPORT
ANNUAL FINANCIAL REPORT FOR THE YEARS ENDED JUNE 30, 2014 and 2013 A MEMBER OF THE MINNESOTA STATE COLLEGES AND UNIVERSITIES SYSTEM ST. CLOUD STATE UNIVERSITY A MEMBER OF THE MINNESOTA STATE COLLEGES
More informationUniversity of Cincinnati. Office of Management and Budget Circular A-133 Reports for the Year Ended June 30, 2009
University of Cincinnati Office of Management and Budget Circular A-133 Reports for the Year Ended June 30, 2009 BOARD OF TRUSTEES Trustee Term Expires Jeffrey L. Wyler 2010 H. C. Buck Niehoff Chairperson
More informationCapital Outlay. Approved Capital Outlay Amendments ( biennium)
Capital Outlay The approved capital outlay amendments include three types of actions with a combined impact of $451.6 million on the general funds available for appropriation to assist with balancing of
More informationInformational Session for Fiscal Year Budget
Informational Session for Fiscal Year 2016-2017 Budget PRESENTED BY Angela M. Poole, CPA Acting Vice President for Finance and Administration Florida Agricultural and Mechanical University Budget and Finance
More informationAGENDA UNIVERSITY OF SOUTHERN INDIANA BOARD OF TRUSTEES. January 12, 2017
Agenda Page 1 AGENDA UNIVERSITY OF SOUTHERN INDIANA BOARD OF TRUSTEES January 12, 2017 SECTION I GENERAL AND ACADEMIC MATTERS A. APPROVAL OF MINUTES OF NOVEMBER 3, 2016, MEETING B. ESTABLISHMENT OF NEXT
More informationGENERAL ASSEMBLY OF NORTH CAROLINA Session 2017 Legislative Fiscal Note
GENERAL ASSEMBLY OF NORTH CAROLINA Session 2017 Legislative Fiscal Note BILL NUMBER: House Bill 620 (First Edition) SHORT TITLE: UNC Capital Projects. SPONSOR(S): Representatives Brawley, Saine, Szoka,
More informationREDWOODS COMMUNITY COLLEGE DISTRICT
REDWOODS COMMUNITY COLLEGE DISTRICT Eureka, California SCHEDULE OF PROCEEDS AND USE OF GENERAL OBLIGATION BONDS (ELECTION OF 2004, SERIES 2005 AND 2007) WITH INDEPENDENT AUDITORS REPORT TABLE OF CONTENTS
More informationFY 2017 Stockton University Expenditure Report as of May 31, 2017
FY 2017 Stockton University Expenditure Report Table of Contents Page Operational Budgets 1-2 Internal Capital Projects Summary 3 FY17 Internal Capital Projects 4 State Bond/Grants 5 STOCKTON UNIVERSITY
More informationYOSEMITE COMMUNITY COLLEGE DISTRICT. MEASURE E GENERAL OBLIGATION BONDS PERFORMANCE AUDIT June 30, 2016
PERFORMANCE AUDIT June 30, 2016 Modesto, California PERFORMANCE AUDIT June 30, 2016 CONTENTS INDEPENDENT AUDITOR S REPORT... 1 BACKGROUND: LEGISLATIVE HISTORY... 2... 2 PERFORMANCE AUDIT: OBJECTIVES...
More informationFY2018 Internal Bank Update Office of Financial Services. Jake Wozniak, Interim Treasurer Finance Committee August 30, 2018
FY2018 Internal Bank Update Office of Financial Services Jake Wozniak, Interim Treasurer Finance Committee August 30, 2018 Internal Bank Overview Internal Bank Function Overview: The Office of Financial
More informationTown Hall Meetings. Budget Update and Planning. May 6, 2009
Town Hall Meetings Budget Update and Planning May 6, 2009 Agenda FY 09 Status Budget Development Events FY 10-13 Strategy FY 10-13 Projection Reports by Area Academic Affairs Student Life & Development
More informationFINANCIAL STATE OF THE COLLEGE
FINANCIAL STATE OF THE COLLEGE Presented by: Horace Chase Vice President for Financial & Administrative Affairs February 12, 2015 AGENDA Current Financial Position Allocation of Funds Renewal & Replacement
More informationUniversity of Virginia Status Report on the Plan to Address Deferred Maintenance
Executive Summary University of Virginia Status Report on the Plan to Address Deferred Maintenance The University of Virginia s facilities portfolio includes 552 buildings and related infrastructure, encompassing
More information