1 CUNY Capital Budget University Faculty Senate and Community College Caucus April 19, 2013 Office of Facilities Planning, Construction & Management Vice Chancellor Iris Weinshall

2 Capital Budget Bond Funds New Buildings Building Renovations Equipment Purchases Large IT projects with Long Term Benefits Grants Federal/State/City/Private

3 Budget Funders Governor State Division of Budget (DOB) Legislature Mayor Office of Management and Budget (OMB) City Council Borough Presidents

4 Projects with City Council funding York College SIM Lab

5 Projects with City Council funding LaGuardia CC Center 3 Building Facade

6 Capital Budget Process Five-Year Plan/Request Six-month process Colleges and FPCM staff participate CUNY Board approves in November

7 Current Capital Program Program focuses on Completing funding for partially funded projects Critical Maintenance funding Expanding science facilities Providing for growth and programmatic changes

8 Types of Projects Partially-Funded Projects

9 Types of Projects Critical Maintenance

10 Types of Projects Expanding Science Facilities

11 Types of Projects Programmatic Expansion

12 State Budget Request FY Year Request total $6.4 billion $5.1 Billion $650 million $650 Million Senior Colleges - State Community Colleges - State Community Colleges - City

13 State FY Budget Results Funding appropriated $8 M critical maintenance at Community Colleges $55 M challenge grant for CUNY 2020 Initiative $37 M administrative costs for capital program $3.1 billion existing funding (re-appropriations) $20.4 M Superstorm Sandy recovery funds

14 State funding over $3 billion in last six years FY 08/09 FY 09/10 FY 10/11 FY 11/12 FY 12/13 FY13/14 $1.8 B (start of five-year plan) $284 million $319 million $315 million $311 million $63 million

15 CUNY capital program spending Last five years capital spending State and City combined ($ millions) FY FY FY FY FY TOTAL $429 $666 $697 $483 $421 $2,696

16 Recently completed new facilities CUNY Law New Facility

17 Recently completed new facilities BMCC Fiterman Hall

18 Recently completed new facilities Bronx CC North Hall & Library

19 Recently completed new facilities Lehman New Science Facility

20 Available Funds Senior

21 Quick primer on State funds Appropriations are allocated to CUNY Available until expended Re-appropriated each year CUNY is allowed to spend to a cash ceiling Less cash is allocated than appropriations Critical Maintenance

22 Available State Re-appropriations State $3.1 billion is available Seniors $2.7 billion Over 300 projects underway Senior and Community College State cash spending cap for FY almost $500 million

23 Re-appropriations Seniors Examples of existing major Senior College Commitments - Programmatic ASRC & CCNY Science Buildings Baruch 17 Lexington Avenue Brooklyn Performing Arts Center Central Office Data Center Integration CUNY FIRST Hunter Weill Cornell NYC College of Technology Academic Bldg. I Hunter Science/Health Professions Bldg. Medgar Evers Library Expansion Total $419 M $ 33 M $ 70 M $ 25 M $ 32 M $ 65 M $235 M $ 54 M $ 22 M $955 M

24 Major projects starting construction NYCC Tech Academic Building I Baruch Field Bldg at 17 Lex

25 Seniors - major projects in design Brooklyn - Roosevelt Hall

26 Seniors - major projects in design York - Academic Village

27 Seniors - major projects in design CSI - Computational Ctr.

28 Seniors - major projects in design Hunter - Science & Health Professions Bldg

29 Seniors - major projects in design Queens Fitzgerald Gym Ren0vation

30 Seniors Re-appropriations Existing major critical maintenance projects Lehman Utility Upgrades CCNY Marshak Building HVAC Upgrades Queens NSB Building HVAC Upgrades Brooklyn Ingersoll Hall Renovations Medgar Evers Carroll St. Building Upgrades NYCCT Namm Hall Elevator and Bathroom Hunter College HVAC Upgrades $ 33 M $ 22 M $ 28 M $ 36 M $ 25 M $ 15 M $ 23 M CSI Campus Wide Underground Utilities $ 6.5 M Total $ M

31 Available Funds Community Colleges

32 Community College funding process 50/50 matching requirement State has committed to matching city critical maintenance $71 million agreement with City Council/OMB provides some additional critical maintenance lump sum funding

33 Re-appropriations Community Colleges No substantive change due to State Budget City allocations drive funding CUNY received $25 million a year local elected officials and OMB State normally matches Community Colleges have accumulated over $260 million in last five years

34 Available State Re-appropriations State $3.1 billion is available Community Colleges approximately $800 million (matched) Over 300 projects underway State cash spending cap for FY almost $500 million

35 Re-appropriations Examples of existing major Community College commitments LaGuardia Center 3 Façade Bronx Utility Upgrades Kingsborough Central Plant Queensborough Electrical Upgrade BMCC Bathroom ADA Upgrades BMCC Student Commons Expansion Various College fire alarm upgrades Various College roof repairs Various College façade repairs Total $100 M $50 M $19 M $35 M $ 7 M $11 M $10 M $20 M $15 M $256 M

36 Questions?

Amount Requested. Project Name

Amount Requested. Project Name The City University of New York FY 2008-09 Capital Results State Five-Year Capital Plan FY 2008-09 to FY 2012-13 SENIOR COLLEGES Requested 2008-09 Enacted CUNY-Wide Seniors C.A.: Health & Safety $ 165,769

More information

THE CITY UNIVERSITY OF NEW YORK. Basic Financial Statements, Management s Discussion and Analysis, and Supplementary Schedules.

THE CITY UNIVERSITY OF NEW YORK. Basic Financial Statements, Management s Discussion and Analysis, and Supplementary Schedules. Basic Financial Statements, Management s Discussion and Analysis, and Supplementary Schedules (With Independent Auditors Report Thereon) Table of Contents Independent Auditors Report 1 Management s Discussion

More information

THE CITY UNIVERSITY OF NEW YORK. Basic Financial Statements and Management s Discussion and Analysis. June 30, 2013

THE CITY UNIVERSITY OF NEW YORK. Basic Financial Statements and Management s Discussion and Analysis. June 30, 2013 Basic Financial Statements and Management s Discussion and Analysis (With Independent Auditors Report Thereon) Table of Contents Independent Auditors Report 1 Management s Discussion and Analysis (Unaudited)

More information

NEW YORK STATE ASSEMBLY PROPOSALS FOR EXECUTIVE BUDGET RESUBMISSION

NEW YORK STATE ASSEMBLY PROPOSALS FOR EXECUTIVE BUDGET RESUBMISSION CONCURRENT RESOLUTION in response to the 2008-2009 Executive Budget submission (Assembly Bill Nos. A. 9800-B, A. 9801-A, A. 9803-B, A. 9804-B, A. 9805-B, A. 9806-B, A. 9807-B, A. 9808-B, A. 9809-B, and

More information

THE CITY UNIVERSITY OF NEW YORK. Basic Financial Statements, Management s Discussion and Analysis, and Supplementary Schedules.

THE CITY UNIVERSITY OF NEW YORK. Basic Financial Statements, Management s Discussion and Analysis, and Supplementary Schedules. Basic Financial Statements, Management s Discussion and Analysis, and Supplementary Schedules (With Independent Auditors Report Thereon) Table of Contents Independent Auditors Report 1 Management s Discussion

More information

Supplemental Financial Statements Schedules (Un-audited)

Supplemental Financial Statements Schedules (Un-audited) RESEARCH FOUNDATION of The CITY UNIVERSITY OF NEW YORK Supplemental Financial Statements Schedules (Un-audited) Prepared For the Board of Directors For Fiscal Year Ending June 30, 2011 with comparison

More information

THE CITY UNIVERSITY OF NEW YORK. Basic Financial Statements and Management s Discussion and Analysis. June 30, 2014

THE CITY UNIVERSITY OF NEW YORK. Basic Financial Statements and Management s Discussion and Analysis. June 30, 2014 Basic Financial Statements and Management s Discussion and Analysis (With Independent Auditors Report Thereon) Table of Contents Independent Auditors Report 1 Management s Discussion and Analysis (Unaudited)

More information

Hostos Community College Budget Process

Hostos Community College Budget Process Hostos Community College Budget Process Note: The following is largely excerpted from the 2017 MSCHE Periodic Review Report The Budget Components and Financial Planning Process The primary source of annual

More information

RESOLUTION OF THE CITY UNIVERSITY CONSTRUCTION FUND APPROVING THE ANNUAL REPORT ON PROCUREMENT CONTRACTS AND THE GUIDELINES FOR PROCUREMENT CONTRACTS

RESOLUTION OF THE CITY UNIVERSITY CONSTRUCTION FUND APPROVING THE ANNUAL REPORT ON PROCUREMENT CONTRACTS AND THE GUIDELINES FOR PROCUREMENT CONTRACTS Item 3 Resolution No 2270 June 27, 2018 RESOLUTION OF THE CITY UNIVERSITY CONSTRUCTION FUND APPROVING THE ANNUAL REPORT ON PROCUREMENT CONTRACTS AND THE GUIDELINES FOR PROCUREMENT CONTRACTS RESOLVED: That

More information

2018 Educational and Facilities Master Plan (EFMP) and Proposed Bond Projects. June 27, 2018 // Board of Trustees Meeting

2018 Educational and Facilities Master Plan (EFMP) and Proposed Bond Projects. June 27, 2018 // Board of Trustees Meeting 2018 Educational and Facilities Master Plan (EFMP) and Proposed Bond Projects June 27, 2018 // Board of Trustees Meeting Proposed Bond Projects Overall Phasing Phase 1A Phase 1B Phase 2 Phase 3 Phase TBD

More information

Operating & Capital Budget Plan May 2017

Operating & Capital Budget Plan May 2017 2017-2018 Operating & Capital Budget Plan May 2017 Operating and Capital Budget Plan FY 2018 Operating Budget - Highlights Table 1: Composite Operating Budget 4 Table 2: Composite Operating Budget - by

More information

Capital Maintenance. 2. Deferred Maintenance, May 18, 2009 <http://en.wikipedia.org/wiki/deferred_maintenance>

Capital Maintenance. 2. Deferred Maintenance, May 18, 2009 <http://en.wikipedia.org/wiki/deferred_maintenance> Capital Maintenance Capital Maintenance Capital maintenance has previously been known as deferred maintenance, the act of postponing maintenance in order to save money or avoid costs. 2 At NYU, the term

More information

Capital Projects Completed since 1988

Capital Projects Completed since 1988 Projects Completed since 1988 Project Cost FY1988 ICCB Building Illinois Repair & Renovation - Replace Carpet in Classroom Buildings, Library and Lobby of Admin $ 51,901.00 $ 51,901.00 $ 51,901.00 FY1990

More information

Facilities Planning & Construction Report nd Quarter Ending December 31, 2017

Facilities Planning & Construction Report nd Quarter Ending December 31, 2017 Facilities Planning & Construction Report 2017 18 2 nd Quarter Ending December 31, 2017 Overview District SRID Spending (MG100) Summary By College By Site District Measure J Spending (MJ100) Summary By

More information

Presentation to the UH Faculty Senate. University of Houston FY 2016 Budget For current information see

Presentation to the UH Faculty Senate. University of Houston FY 2016 Budget For current information see Presentation to the UH Faculty Senate University of Houston FY 2016 Budget For current information see http://www.uh.edu/af/budget/index.htm 1 Contents Background and Process Slides 3-12 Budget Topic:

More information

TEXAS TECH UNIVERSITY HEALTH SCIENCES CENTER OPERATING BUDGET FISCAL YEAR 2018

TEXAS TECH UNIVERSITY HEALTH SCIENCES CENTER OPERATING BUDGET FISCAL YEAR 2018 TEXAS TECH UNIVERSITY HEALTH SCIENCES CENTER 7335191 OPERATING BUDGET FISCAL YEAR 2018 Fiscal Year 2018 Operating Budget Summary TABLE OF CONTENTS Fiscal Year 2018 Operating Budget - Source of Funds (Graph)......................

More information

PROPOSITION FARMINGTON SCHOOLS. April 8, 2014 Bond Issue

PROPOSITION FARMINGTON SCHOOLS. April 8, 2014 Bond Issue PROPOSITION FARMINGTON SCHOOLS April 8, 2014 Bond Issue PROPOSITION FARMINGTON SCHOOLS - BOND LANGUAGE Shall the Board of Education of the Farmington R-7 School District of St. Francois County, Missouri,

More information

Governing Board Bond Update. Measure G Bond Program. for. Solano Community College District

Governing Board Bond Update. Measure G Bond Program. for. Solano Community College District Governing Board Bond Update for Measure G Bond Program prepared by Kitchell for the Solano Community College District Included in Booklet: Board Update Bond Financial Summary Completed Projects Projects

More information

TEXAS TECH UNIVERSITY HEALTH SCIENCES CENTER

TEXAS TECH UNIVERSITY HEALTH SCIENCES CENTER TEXAS TECH UNIVERSITY HEALTH SCIENCES CENTER FY2015 16973569 7335191 3000000 3525000 1500000 2000000 OPERATING BUDGET FISCAL YEAR 2017 Fiscal Year 2017 Operating Budget Summary TABLE OF CONTENTS Fiscal

More information

Attachment FC 16 SBCC 11/17/2017. STATE BOARD OF COMMUNITY COLLEGES Construction and Property November 17, 2017

Attachment FC 16 SBCC 11/17/2017. STATE BOARD OF COMMUNITY COLLEGES Construction and Property November 17, 2017 A. Approval - New (Non-State and Other State Funds) Name (Other State) (Other State) Non-State Funds/ Undetermined 1 N/A B. Approval - Amended (Non-State and Other State Funds) 1 Coastal Carolina Main

More information

Board Agenda Item G.1. Board Agenda Item G.2.

Board Agenda Item G.1. Board Agenda Item G.2. AGENDA FACILITIES PLANNING COMMITTEE BOARD OF SUPERVISORS FOR THE UNIVERSITY OF LOUISIANA SYSTEM *10:35 a.m., Thursday, August 23, 2018** Room 100, Louisiana Purchase Room Claiborne Conference Center 1201

More information

DESERT COMMUNITY COLLEGE DISTRICT PROPOSITION 39, GENERAL OBLIGATION BONDS (MEASURE B, MARCH 2004) PERFORMANCE AUDIT JUNE 30, 2008

DESERT COMMUNITY COLLEGE DISTRICT PROPOSITION 39, GENERAL OBLIGATION BONDS (MEASURE B, MARCH 2004) PERFORMANCE AUDIT JUNE 30, 2008 (MEASURE B, MARCH 2004) (MEASURE B, MARCH 2004) TABLE OF CONTENTS Page Independent Auditors Report 1 Objectives... 2 Scope of the Audit. 2 Background Information 2-3 Procedures Performed... 3-4 Results

More information

THE FLORIDA INTERNATIONAL UNIVERSITY BOARD OF TRUSTEES December 5, 2018

THE FLORIDA INTERNATIONAL UNIVERSITY BOARD OF TRUSTEES December 5, 2018 Consent Agenda FF2 THE FLORIDA INTERNATIONAL UNIVERSITY BOARD OF TRUSTEES December 5, 2018 Subject: Approval of Carryforward Funds Proposed Board Action: Approve the Florida International University (FIU)

More information

A N N U A L R E P O R T DORMITORY AUTHORITY S T A T E O F N E W Y O R K

A N N U A L R E P O R T DORMITORY AUTHORITY S T A T E O F N E W Y O R K DASNY Annual Report 2017 A N N U A L R E P O R T 2 0 1 7 DORMITORY AUTHORITY S T A T E O F N E W Y O R K 4 16 28 36 40 Innovative Communities 4 Educated Communities 16 Healthy Communities 28 Resilient

More information

University of Houston System

University of Houston System UNIVERSITY of HOUSTON SYSTEM University of Houston System FY2014 Annual Budget August 14, 2013 1 UNIVERSITY of HOUSTON SYSTEM FY2013 Current year Total Budget $ Millions Operating Budget $ 1,247.5 Capital

More information

TEXAS TECH UNIVERSITY HEALTH SCIENCES CENTER OPERATING BUDGET FISCAL YEAR 2019

TEXAS TECH UNIVERSITY HEALTH SCIENCES CENTER OPERATING BUDGET FISCAL YEAR 2019 TEXAS TECH UNIVERSITY HEALTH SCIENCES CENTER 7335191 OPERATING BUDGET FISCAL YEAR 2019 Fiscal Year 2019 Operating Budget Summary TABLE OF CONTENTS Fiscal Year 2019 Operating Budget - Source of Funds (Graph)......................

More information

Thompson Rivers University

Thompson Rivers University Thompson Rivers University Operating Budget 2010 2011 Senate Presentation April 2010 Budget Committee of Senate BCOS Regular monthly meetings Regular capital construction updates Presentations from Faculty

More information

The Ohio State University Board of Trustees. October 28, 2009

The Ohio State University Board of Trustees. October 28, 2009 The Ohio State University Board of Trustees TOPIC: October 28, 2009 CONTEXT: Capital Recommendations At the September 17 th Fiscal Affairs Committee meeting, the University Administration promised to come

More information

EAST TENNESSEE STATE UNIVERSITY BOARD OF TRUSTEES FINANCE AND ADMINISTRATION COMMITTEE MARCH 2018 SPECIAL CALLED MEETING AGENDA

EAST TENNESSEE STATE UNIVERSITY BOARD OF TRUSTEES FINANCE AND ADMINISTRATION COMMITTEE MARCH 2018 SPECIAL CALLED MEETING AGENDA EAST TENNESSEE STATE UNIVERSITY BOARD OF TRUSTEES FINANCE AND ADMINISTRATION COMMITTEE MARCH 2018 SPECIAL CALLED MEETING 3:00-4:00pm EDT Thursday March 29, 2018 President s Conference Room Burgin Dossett

More information

TEXAS TECH UNIVERSITY HEALTH SCIENCES CENTER. Fiscal Year 2004 Operating Budget Summary

TEXAS TECH UNIVERSITY HEALTH SCIENCES CENTER. Fiscal Year 2004 Operating Budget Summary Fiscal Year 2004 Operating Budget Summary TABLE OF CONTENTS Educational and General Funds Budget Summary................................ 1 Higher Education Assistance Funds Allocation...................................

More information

FY 2016 BUDGET RUTGERS NEWARK

FY 2016 BUDGET RUTGERS NEWARK RUTGERS SCHOOLS Office of Budget and Resource Studies January 29, 2016 Office of Budget and Resource Studies 33 Knightsbridge Road Piscataway, NJ 08854 budget.rutgers.edu p. 848-932-7472 f. 732-445-3579

More information

CONSTRUCTION PROJECTS STATUS REPORT BOARD OF TRUSTEES MEETING - August 2, 2017

CONSTRUCTION PROJECTS STATUS REPORT BOARD OF TRUSTEES MEETING - August 2, 2017 Planning Academic & Research Facilities - Homer 300008 $1,850,000 $128 P UCONN 2000 Bond Funds 03/29/17 2020 Babbidge Library Renovations Main Campus Parking Replacements 300023 $500,000 $0 P 06/28/17

More information

Department Chair Online Resource Center Facility Maintenance or Facility Improvement? Taking a Responsible Approach

Department Chair Online Resource Center Facility Maintenance or Facility Improvement? Taking a Responsible Approach Department Chair Online Resource Center Facility Maintenance or Facility Improvement? Taking a Responsible Approach Richard Bettega, associate vice president for facilities, Lewis and Clark College. Facility

More information

ADVANCING CAPITAL OUTLAY

ADVANCING CAPITAL OUTLAY ADVANCING CAPITAL OUTLAY Robert R. Broyden Assistant Vice President for Capital Assets and Financial Management 1 Major Topics Today: 1) Commitment to long-range planning processes 2) Update on 2012 General

More information

Summary of Capital Budget Request Tennessee Board of Regents. of the. September 21, 2017

Summary of Capital Budget Request Tennessee Board of Regents. of the. September 21, 2017 Summary of Capital Budget Request 2018-2019 of the Tennessee Board of Regents September 21, 2017 1 This is the Summary of the Capital Budget Request for Fiscal Year 2018-2019 for the Finance and Business

More information

Chabot College Project List Biology Building Phase 1 $0 $0 $0 Measure B $0 $0 $0 Measure A 2016 $0 $0 $0

Chabot College Project List Biology Building Phase 1 $0 $0 $0 Measure B $0 $0 $0 Measure A 2016 $0 $0 $0 Chabot College Project List 552330 Biology Building Phase 1 $0 $0 $0 Measure A 2016 $0 $0 $0 562100 Library & Learning Conncetions Building Replacement 100 $57,875,000 $0 $0 Measure A 2016 $57,875,000

More information

Budget Flint Campus

Budget Flint Campus 2016-2017 Budget Flint Campus This page left blank intentionally. Table of Contents The University of Michigan - Flint Section One - Summary of Budgeted Revenues and Expenditures Schedule A: Summary by

More information

CONSTRUCTION PROJECTS STATUS REPORT BOARD OF TRUSTEES MEETING - September 27, 2017

CONSTRUCTION PROJECTS STATUS REPORT BOARD OF TRUSTEES MEETING - September 27, 2017 Planning Budget Phase Academic & Research Facilities - Homer 300008 $1,850,000 $391 P UCONN 2000 Bond Funds 03/29/17 2020 Babbidge Library Renovations Main Campus Parking Replacements 300023 $500,000 $32,640

More information

PROPOSED BUDGET San Jacinto Community College District Budget Hearing August 4, 2014

PROPOSED BUDGET San Jacinto Community College District Budget Hearing August 4, 2014 PROPOSED BUDGET 2014-2015 San Jacinto Community College District Budget Hearing August 4, 2014 1 Highlights of the Proposed 2014 2015 Budget State Revenue Major Revenue Assumptions No change in rate FY15,

More information

FY 2018 Stockton University Operational & Capital Report as of May 31, 2018

FY 2018 Stockton University Operational & Capital Report as of May 31, 2018 FY 2018 Stockton University Operational & Capital Report Table of Contents Page Operational Budgets 1-2 Internal Capital Projects Summary 3 Internal Capital Projects 4-5 Other Capital Projects 6 State

More information

Fiscal Year (FY13) Operating Budget and Capital Budget Overview

Fiscal Year (FY13) Operating Budget and Capital Budget Overview Approved by President Rush Fiscal Year 2012-2013 (FY13) Operating Budget and Capital Budget Overview Background A university budget represents the complex interchange between revenue streams that support

More information

9 th Annual Budget Forum April 2014

9 th Annual Budget Forum April 2014 9 th Annual Budget Forum April 2014 Presenters: Helen Benjamin Chancellor Gene Huff Executive Vice Chancellor Jonah Nicholas Associate Vice Chancellor GOALS Information Arzu Smith Director of District

More information

Division of Finance and Administration Financial Update. Karol Kain Gray Vice Chancellor for Finance and Administration September 25, 2013

Division of Finance and Administration Financial Update. Karol Kain Gray Vice Chancellor for Finance and Administration September 25, 2013 Division of Finance and Administration Financial Update September 25, 2013 CAFR AWARD o The UNC Finance Division earned the University s 18 th consecutive Certificate of Achievement for Excellence in Financial

More information

HOCKING COLLEGE Fee Pledge Request - $22,000,000 April, I. Project Overview

HOCKING COLLEGE Fee Pledge Request - $22,000,000 April, I. Project Overview I. Project Overview Hocking College is seeking approval to issue fixed rate general receipts bonds under the State s Credit Enhancement Program for two-year institutions for the following purposes: Purchase

More information

CENTRAL STATE UNIVERSITY Wilberforce, Ohio. FINANCIAL STATEMENTS June 30, 2017 and 2016

CENTRAL STATE UNIVERSITY Wilberforce, Ohio. FINANCIAL STATEMENTS June 30, 2017 and 2016 Wilberforce, Ohio FINANCIAL STATEMENTS Wilberforce, Ohio FINANCIAL STATEMENTS CONTENTS INDEPENDENT AUDITOR S REPORT... 1 MANAGEMENT S DISCUSSION AND ANALYSIS (UNAUDITED)... 3 FINANCIAL STATEMENTS STATEMENTS

More information

Capital Projects Ordinances (CPO)

Capital Projects Ordinances (CPO) Capital Projects Ordinances (CPO) This section accounts for financial resources to be used for the acquisition or construction of major capital facilities. Listed below are brief descriptions for active

More information

2017/18 Annual Budget Report. Charlie Faas VP Administration & Finance/CFO

2017/18 Annual Budget Report. Charlie Faas VP Administration & Finance/CFO 2017/18 Annual Budget Report Charlie Faas VP Administration & Finance/CFO Fiscal Year Budget Overview Increase in tuition and General Fund appropriation Tuition rate increase ($270, 4.9% increase) +240

More information

SONOMA COUNTY JUNIOR COLLEGE DISTRICT PROPOSITION 39 AND MEASURE A GENERAL OBLIGATION BONDS SANTA ROSA, CALIFORNIA

SONOMA COUNTY JUNIOR COLLEGE DISTRICT PROPOSITION 39 AND MEASURE A GENERAL OBLIGATION BONDS SANTA ROSA, CALIFORNIA SONOMA COUNTY JUNIOR COLLEGE DISTRICT PROPOSITION 39 AND MEASURE A GENERAL OBLIGATION BONDS SANTA ROSA, CALIFORNIA YEAR ENDED TABLE OF CONTENTS PAGE Independent Auditors' Report 1 Objectives 2 Scope of

More information

1. Program & Planning Adjustments: 2. Cash flow: 3. Indenture Amendments:

1. Program & Planning Adjustments: 2. Cash flow: 3. Indenture Amendments: The key elements underlying the revisions to the phasing outline are detailed below. These changes are driven by academic priorities, economic realities and the importance of spending bond proceeds in

More information

SONOMA COUNTY JUNIOR COLLEGE DISTRICT PROPOSITION 39 AND MEASURE A GENERAL OBLIGATION BONDS SANTA ROSA, CALIFORNIA

SONOMA COUNTY JUNIOR COLLEGE DISTRICT PROPOSITION 39 AND MEASURE A GENERAL OBLIGATION BONDS SANTA ROSA, CALIFORNIA SONOMA COUNTY JUNIOR COLLEGE DISTRICT PROPOSITION 39 AND MEASURE A GENERAL OBLIGATION BONDS SANTA ROSA, CALIFORNIA YEAR ENDED TABLE OF CONTENTS PAGE Independent Auditors' Report 1 Objectives 2 Scope of

More information

ROCHESTER COMMUNITY AND TECHNICAL COLLEGE

ROCHESTER COMMUNITY AND TECHNICAL COLLEGE ROCHESTER COMMUNITY AND TECHNICAL COLLEGE A MEMBER OF THE MINNESOTA STATE COLLEGES AND UNIVERSITIES SYSTEM ANNUAL FINANCIAL REPORT FOR THE YEARS ENDED JUNE 30, 2013 and 2012 Prepared by: Rochester Community

More information

New Jersey Institute of Technology

New Jersey Institute of Technology New Jersey Institute of Technology FY18 Budget Status Report and FY19 Budget Development Status Presented to the Joint Session of the Strategic Planning Steering Committee and Committee on Academic Strategic

More information

University of Virginia Status Report on the Plan to Address Deferred Maintenance

University of Virginia Status Report on the Plan to Address Deferred Maintenance Executive Summary University of Virginia Status Report on the Plan to Address Deferred Maintenance The University of Virginia s facilities portfolio includes 540 buildings and related infrastructure, encompassing

More information

FLORIDA BOARD OF GOVERNORS NOTICE OF PROPOSED AMENDED REGULATION. REGULATION NUMBER AND TITLE: Regulation State University Operating Budgets

FLORIDA BOARD OF GOVERNORS NOTICE OF PROPOSED AMENDED REGULATION. REGULATION NUMBER AND TITLE: Regulation State University Operating Budgets FLORIDA BOARD OF GOVERNORS NOTICE OF PROPOSED AMENDED REGULATION DATE: June 27, 2016 REGULATION NUMBER AND TITLE: Regulation 9.007 State University Operating Budgets SUMMARY: This regulation is being amended

More information

Connecticut State University System (The System Office, Central Connecticut State University, Eastern Connecticut State University, Southern

Connecticut State University System (The System Office, Central Connecticut State University, Eastern Connecticut State University, Southern Connecticut State University System (The System Office, Central Connecticut State University, Eastern Connecticut State University, Southern Connecticut State University, Western Connecticut State University,

More information

MEASURE I CITIZENS' OVERSIGHT COMMITTEE MEETING AUGUST 5, 2014 QUARTERLY FINANCIAL REPORT

MEASURE I CITIZENS' OVERSIGHT COMMITTEE MEETING AUGUST 5, 2014 QUARTERLY FINANCIAL REPORT MEASURE I CITIZENS' OVERSIGHT COMMITTEE MEETING AUGUST 5, 214 QUARTERLY FINANCIAL REPORT Bond Income and Expenditure Summary Income Statement Projects List Project Expenditure Summary Cash Flow Report

More information

Frequently asked questions on the Ridgewood Public School Budget. 2. Why does the Board approve a preliminary budget?

Frequently asked questions on the Ridgewood Public School Budget. 2. Why does the Board approve a preliminary budget? Over the last few weeks the Board of Education has received a number of questions regarding the proposed 2018-19 budget. We hope that the Frequently Asked Questions and our Answers below will help to shed

More information

FISCAL 2018 BUDGET UPDATE

FISCAL 2018 BUDGET UPDATE FISCAL 2018 BUDGET UPDATE BASED ON APPROVED BUDGET INSTITUTE BUDGET PLANNING AND ADMINISTRATION JULY 1, 2017 Outline 1. Capital Budget funding sources & current projects 2. Fiscal 2018 Operating Budget

More information

Funding for Maintenance and Repair at UMKC. Faculty Senate November 4, 2014

Funding for Maintenance and Repair at UMKC. Faculty Senate November 4, 2014 Funding for Maintenance and Repair at UMKC Faculty Senate November 4, 2014 Changing the Conversation Space Understand how age profile drives capital and operational demands Capital Multiyear plans that

More information

FY2019 MEIF / Auxiliary Services / E&G Budget Discussion

FY2019 MEIF / Auxiliary Services / E&G Budget Discussion 1 of 20 FY2019 MEIF / Auxiliary Services / E&G Budget Discussion Kody Varahramyan Vice President for Research and Dean of the Graduate School Susan J. Hunter President Claire Strickland Chief Business

More information

ANALYSIS TABLES

ANALYSIS TABLES QUILLEN COLLEGE of MEDICINE ANALYSIS TABLES 208-209 THE STATE UNIVERSITY AND COMMUNITY COLLEGE SYSTEM OF TENNESSEE JULY PROPOSED BUDGET 208-9 BUDGET ANALYSIS FORMS 2 Contra Revenue Accounts for Bad Debt

More information

Stockton University FY 2019 Operational and Capital Report as of January 31, 2019

Stockton University FY 2019 Operational and Capital Report as of January 31, 2019 Stockton University FY 2019 Operational and Capital Report Stockton University FY 2019 Operational and Capital Report Table of Contents Page Operational Budget Summary: University, Auxiliaries, and Agency

More information

Colorado State University System Financial Statements and Independent Auditor s Reports Financial Audit Years Ended June 30, 2016 and 2015 Compliance

Colorado State University System Financial Statements and Independent Auditor s Reports Financial Audit Years Ended June 30, 2016 and 2015 Compliance Colorado State University System Financial Statements and Independent Auditor s Reports Financial Audit Compliance Audit Year Ended June 30, 2016 THIS PAGE LEFT BLANK INTENTIONALLY Table of Contents...

More information

Making the Case for Funding Deferred Maintenance Before it s Too Late

Making the Case for Funding Deferred Maintenance Before it s Too Late Making the Case for Funding Deferred Maintenance Before it s Too Late Jim Kadamus Vice President Sightlines Cuba Plain Assistant Vice President for Budget Planning and Development University of Missouri

More information

Working with Overhead Rates and Fringe Benefits

Working with Overhead Rates and Fringe Benefits Working with Overhead Rates and Fringe Benefits Ken Miller, Assistant Vice President for Finance & University Controller Dave McGarry, Associate Controller, Financial Reporting & Cost Accounting Sharon

More information

BUDGET AND FINANCE COMMITTEE. March 19, Minutes

BUDGET AND FINANCE COMMITTEE. March 19, Minutes BOARD OF GOVERNORS BUDGET AND FINANCE COMMITTEE March 19, 2003 Minutes The meeting was called to order at 1:05 p.m. by Governor Driker in the Alumni Lounge. Secretary Miller called the roll. A quorum was

More information

CONSTRUCTION PROJECTS STATUS REPORT BOARD OF TRUSTEES MEETING - April 26, 2017

CONSTRUCTION PROJECTS STATUS REPORT BOARD OF TRUSTEES MEETING - April 26, 2017 Project Name by Construction Project # Planning Academic & Research Facilities - Homer 300008 $1,850,000 $0 P UCONN 2000 Bond Funds 03/29/17 2020 Babbidge Library Renovations Stamford Campus Improvements/Housing

More information

University of Colorado Denver

University of Colorado Denver University of Colorado Denver Fiscal Policy Title: Source: Prepared by: Approved by: Budgeting Budget Office Budget Office Associate Vice Chancellor for Budget and Operations Effective Date: July 1, 2010

More information

GUIDELINES FOR MANAGING FUND DEPOSITS

GUIDELINES FOR MANAGING FUND DEPOSITS GUIDELINES FOR MANAGING FUND DEPOSITS AND DISBURSEMENTS Policy Id: Bus.029 - Guidelines for Managing Fund Deposits and Disbursements Contact: Executive Director of Finance and Business Services (212) 237-8516

More information

City University of New York Bronx Community College. College-wide P&B Meeting September 20, 2017

City University of New York Bronx Community College. College-wide P&B Meeting September 20, 2017 City University of New York Bronx Community College College-wide P&B Meeting September 20, 2017 FY 2018 Tax Levy Budget Review Funding Allocation Summary Resources and Expenditures Operating Expenditures

More information

Priority #1 Request for Construction FY Priority #2 Anticipated Request for Planning FY 2019

Priority #1 Request for Construction FY Priority #2 Anticipated Request for Planning FY 2019 V. IMPLEMENTATION PLAN a) Prioritize major capital projects requested from the State, including a brief project description and estimated cost, in the format provided. (Adjust previously developed or prior

More information

Tuition Increase Recommendation FY June 18, 2009 June Regular Board Meeting

Tuition Increase Recommendation FY June 18, 2009 June Regular Board Meeting With the assumption that the Mississippi State Legislature will adopt a budget by June 30, 2009 for FY 2010, approval is requested budgets (including Ayers) and Auxiliary Fund budgets. For all other general

More information

SUBJECT: Deferred Maintenance and Capital Outlay Planning

SUBJECT: Deferred Maintenance and Capital Outlay Planning Capital Planning, Design and Construction Elvyra F. San Juan 401 Golden Shore, 2 nd Floor Assistant Vice Chancellor Long Beach, CA 90802-4210 www.calstate.edu (562) 951-4090 esanjuan@calstate.edu DATE:

More information

Bond Amount: $18,470,000. Proposed I&S Tax Rate Increase: $.3180

Bond Amount: $18,470,000. Proposed I&S Tax Rate Increase: $.3180 Bond Amount: $18,470,000 Proposed I&S Tax Rate : $.3180 How was the EBISD 2017 Bond developed? The bond package was developed from K-12 academic needs identified by our fifty-member community facilities

More information

Redwoods Community College District Eureka, California SCHEDULE OF PROCEEDS AND USE OF GENERAL OBLIGATION BONDS INDEPENDENT AUDITORS REPORTS

Redwoods Community College District Eureka, California SCHEDULE OF PROCEEDS AND USE OF GENERAL OBLIGATION BONDS INDEPENDENT AUDITORS REPORTS Eureka, California SCHEDULE OF PROCEEDS AND USE OF GENERAL OBLIGATION BONDS INDEPENDENT AUDITORS REPORTS June 30, 2016 General Obligation Bonds TABLE OF CONTENTS June 30, 2016 Page Number Independent Auditors

More information

CONSTRUCTION PROJECTS STATUS REPORT BOARD OF TRUSTEES MEETING - June 28, 2017

CONSTRUCTION PROJECTS STATUS REPORT BOARD OF TRUSTEES MEETING - June 28, 2017 Planning Budget Phase Academic & Research Facilities - Homer 300008 $1,850,000 $0 P UCONN 2000 Bond Funds 03/29/17 2020 Babbidge Library Renovations Main Campus Parking Replacements 300023 $500,000 $0

More information

Erica Bowers, Ed.D. Chair, Planning, Resource, and Budget Committee (PRBC)

Erica Bowers, Ed.D. Chair, Planning, Resource, and Budget Committee (PRBC) MEMORANDUM Date: May 5, 2016 To: From: Mildred García, Ed.D. University President Erica Bowers, Ed.D. Chair, Planning, Resource, and Budget Committee (PRBC) Subject: PRBC Recommendations for FY 2016-17

More information

Capital Improvements Program FY CIP Projects by Component

Capital Improvements Program FY CIP Projects by Component CIP Projects by Component HEF Lamar Institute of Technology Student Service Learning Center 2020 $42,778,500 $0 $12,778,500 $0 $30,000,000 $0 $0 Carry Over Amended Lamar State College-Orange Academic Building

More information

DATE: May 31, 2017 Data Code: PROJECT: Alamo Colleges Program Management. SUBJECT: Reaffirmation Information: Construction Report

DATE: May 31, 2017 Data Code: PROJECT: Alamo Colleges Program Management. SUBJECT: Reaffirmation Information: Construction Report DATE: May 31, 2017 Data Code: 1.02 TO: John W. Strybos, PE FROM: K. LeBlanc, PE, CFM, LEED GA PROJECT NO.: 170-11026-000 Routing V. Buzzelli R. Reyes J. Grom PROJECT: Alamo Colleges Program Management

More information

Streamlined Capital Outlay Projects Funded from. Capital Outlay Bond Funds Legislative Report Legislative Session

Streamlined Capital Outlay Projects Funded from. Capital Outlay Bond Funds Legislative Report Legislative Session Streamlined Capital Outlay Projects Funded from Capital Outlay Bond Funds Legislative Report 2008-09 Legislative Session November 2008 November 2008 UNIVERSITY OF CALIFORNIA Report on Streamlined Capital

More information

Chancellor s Message - Achievements

Chancellor s Message - Achievements Chancellor s Message - Achievements We have achieved significant educational and operational advances. To name a few: $41 million in savings from operations through the elimination of redundancies and

More information

UNIVERSITY OF NORTHERN COLORADO: FINANCIAL REPORT 03/31/2011

UNIVERSITY OF NORTHERN COLORADO: FINANCIAL REPORT 03/31/2011 UNIVERSITY OF NORTHERN COLORADO: FINANCIAL REPORT 03/31/2011 OVERVIEW Financial highlights of the 3 rd quarter financial report for fiscal year 2011-12 are summarized below: Cash The University s cash

More information

Department Report. Cultural Affairs Commission June 15, Cliff Gillespie, Business Operations Manager Office of Cultural Affairs City of Dallas

Department Report. Cultural Affairs Commission June 15, Cliff Gillespie, Business Operations Manager Office of Cultural Affairs City of Dallas Department Report Cultural Affairs Commission June 15, 2017 Cliff Gillespie, Business Operations Manager Office of Cultural Affairs City of Dallas Agenda FY 2017-18 Budget Update 2017 Bond Program Moody

More information

BUDGET AND FINANCE COMMITTEE. October 1, Minutes

BUDGET AND FINANCE COMMITTEE. October 1, Minutes BOARD OF GOVERNORS BUDGET AND FINANCE COMMITTEE October 1, 2003 Minutes The meeting was called to order at 11:00 a.m. by Governor Driker in the Alumni Lounge, Alumni House. Secretary Miller called the

More information

$4,701,440 $2,727,355 $2,596,419 $447,703 $11,216,598 $21,689,515

$4,701,440 $2,727,355 $2,596,419 $447,703 $11,216,598 $21,689,515 INTRODUCTION The 5-Year District Facilities Work Program is a very important document. The Department of Education, Legislature, Governor's Office, Division of Community Planning (growth management), local

More information

CONSTRUCTION PROJECTS STATUS REPORT BOARD OF TRUSTEES MEETING December 12, 2012

CONSTRUCTION PROJECTS STATUS REPORT BOARD OF TRUSTEES MEETING December 12, 2012 Project Name by Phase Project # Current BOT Approved Budget Encumbrances (As of 11/28/12) Budget Phase Budgeted Funding Source(s) (s) Planning Budget Phase Ecology and Evolutionary Biology (EEB) 201583

More information

Progress Update Identified Needs & Capital Plan

Progress Update Identified Needs & Capital Plan Progress Update Identified Needs & Capital Plan May 29, 2012 Buena Park School District Facilities Assessment & Implementation Plan 0 Facilities Planning, Public Finance, Program Administration Summary

More information

ANNUAL FINANCIAL REPORT

ANNUAL FINANCIAL REPORT ANNUAL FINANCIAL REPORT FOR THE YEARS ENDED JUNE 30, 2014 and 2013 A MEMBER OF THE MINNESOTA STATE COLLEGES AND UNIVERSITIES SYSTEM ST. CLOUD STATE UNIVERSITY A MEMBER OF THE MINNESOTA STATE COLLEGES

More information

University of Cincinnati. Office of Management and Budget Circular A-133 Reports for the Year Ended June 30, 2009

University of Cincinnati. Office of Management and Budget Circular A-133 Reports for the Year Ended June 30, 2009 University of Cincinnati Office of Management and Budget Circular A-133 Reports for the Year Ended June 30, 2009 BOARD OF TRUSTEES Trustee Term Expires Jeffrey L. Wyler 2010 H. C. Buck Niehoff Chairperson

More information

Capital Outlay. Approved Capital Outlay Amendments ( biennium)

Capital Outlay. Approved Capital Outlay Amendments ( biennium) Capital Outlay The approved capital outlay amendments include three types of actions with a combined impact of $451.6 million on the general funds available for appropriation to assist with balancing of

More information

Informational Session for Fiscal Year Budget

Informational Session for Fiscal Year Budget Informational Session for Fiscal Year 2016-2017 Budget PRESENTED BY Angela M. Poole, CPA Acting Vice President for Finance and Administration Florida Agricultural and Mechanical University Budget and Finance

More information

AGENDA UNIVERSITY OF SOUTHERN INDIANA BOARD OF TRUSTEES. January 12, 2017

AGENDA UNIVERSITY OF SOUTHERN INDIANA BOARD OF TRUSTEES. January 12, 2017 Agenda Page 1 AGENDA UNIVERSITY OF SOUTHERN INDIANA BOARD OF TRUSTEES January 12, 2017 SECTION I GENERAL AND ACADEMIC MATTERS A. APPROVAL OF MINUTES OF NOVEMBER 3, 2016, MEETING B. ESTABLISHMENT OF NEXT

More information

GENERAL ASSEMBLY OF NORTH CAROLINA Session 2017 Legislative Fiscal Note

GENERAL ASSEMBLY OF NORTH CAROLINA Session 2017 Legislative Fiscal Note GENERAL ASSEMBLY OF NORTH CAROLINA Session 2017 Legislative Fiscal Note BILL NUMBER: House Bill 620 (First Edition) SHORT TITLE: UNC Capital Projects. SPONSOR(S): Representatives Brawley, Saine, Szoka,

More information

REDWOODS COMMUNITY COLLEGE DISTRICT

REDWOODS COMMUNITY COLLEGE DISTRICT REDWOODS COMMUNITY COLLEGE DISTRICT Eureka, California SCHEDULE OF PROCEEDS AND USE OF GENERAL OBLIGATION BONDS (ELECTION OF 2004, SERIES 2005 AND 2007) WITH INDEPENDENT AUDITORS REPORT TABLE OF CONTENTS

More information

FY 2017 Stockton University Expenditure Report as of May 31, 2017

FY 2017 Stockton University Expenditure Report as of May 31, 2017 FY 2017 Stockton University Expenditure Report Table of Contents Page Operational Budgets 1-2 Internal Capital Projects Summary 3 FY17 Internal Capital Projects 4 State Bond/Grants 5 STOCKTON UNIVERSITY

More information

YOSEMITE COMMUNITY COLLEGE DISTRICT. MEASURE E GENERAL OBLIGATION BONDS PERFORMANCE AUDIT June 30, 2016

YOSEMITE COMMUNITY COLLEGE DISTRICT. MEASURE E GENERAL OBLIGATION BONDS PERFORMANCE AUDIT June 30, 2016 PERFORMANCE AUDIT June 30, 2016 Modesto, California PERFORMANCE AUDIT June 30, 2016 CONTENTS INDEPENDENT AUDITOR S REPORT... 1 BACKGROUND: LEGISLATIVE HISTORY... 2... 2 PERFORMANCE AUDIT: OBJECTIVES...

More information

FY2018 Internal Bank Update Office of Financial Services. Jake Wozniak, Interim Treasurer Finance Committee August 30, 2018

FY2018 Internal Bank Update Office of Financial Services. Jake Wozniak, Interim Treasurer Finance Committee August 30, 2018 FY2018 Internal Bank Update Office of Financial Services Jake Wozniak, Interim Treasurer Finance Committee August 30, 2018 Internal Bank Overview Internal Bank Function Overview: The Office of Financial

More information

Town Hall Meetings. Budget Update and Planning. May 6, 2009

Town Hall Meetings. Budget Update and Planning. May 6, 2009 Town Hall Meetings Budget Update and Planning May 6, 2009 Agenda FY 09 Status Budget Development Events FY 10-13 Strategy FY 10-13 Projection Reports by Area Academic Affairs Student Life & Development

More information

FINANCIAL STATE OF THE COLLEGE

FINANCIAL STATE OF THE COLLEGE FINANCIAL STATE OF THE COLLEGE Presented by: Horace Chase Vice President for Financial & Administrative Affairs February 12, 2015 AGENDA Current Financial Position Allocation of Funds Renewal & Replacement

More information

University of Virginia Status Report on the Plan to Address Deferred Maintenance

University of Virginia Status Report on the Plan to Address Deferred Maintenance Executive Summary University of Virginia Status Report on the Plan to Address Deferred Maintenance The University of Virginia s facilities portfolio includes 552 buildings and related infrastructure, encompassing

More information