SUBJECT: Deferred Maintenance and Capital Outlay Planning
|
|
- Kory Lee
- 5 years ago
- Views:
Transcription
1 Capital Planning, Design and Construction Elvyra F. San Juan 401 Golden Shore, 2 nd Floor Assistant Vice Chancellor Long Beach, CA (562) esanjuan@calstate.edu DATE: March 19, 2015 TO: CSU Presidents April 1, 2015 Deferred Maintenance Lists April 20, 2015 Draft Capital Programs June 15, 2015 Final Capital Programs FROM: Elvyra F. San Juan Assistant Vice Chancellor SUBJECT: Deferred Maintenance and Capital Outlay Planning This memorandum is to request: (1) campus review and correction to the draft Deferred Maintenance Lists compiled for and (2) campus capital outlay project justifications and descriptions for the Capital Outlay Program for through Deferred Maintenance As the Governor s Budget Proposal includes one-time general funds of $25 million for CSU, Facilities Planning staff have contacted campuses to compile the enclosed list to convey the highest priority projects for use of the proposed funds. In addition, a second list of $25 million is being compiled in the event the legislature proposes additional one-time funds to address the CSU deferred maintenance backlog. These two lists are enclosed for your review and edit as needed. Staff used the Critical Infrastructure Assessment developed as part of the Utility Master Plan effort to help create this draft list in consultation with the campus. It is anticipated the final lists (totaling roughly $50 million) will be provided to both the Department of Finance and the legislature in support of the funding needs of the CSU. It is anticipated the support budget should be finalized by July 1, Capital Outlay Program through This call for capital outlay project descriptions and justifications will be used for setting the system priorities for and compiling the Five-Year Capital Improvement Program through This letter incorporates modest changes in the planning process to reflect statutory deadlines and proposed changes to the board s criteria for priority setting. Due to the identification of significant infrastructure deficiencies, we hope to continue an emphasis on the use of our new capital financing authority to address improvements to infrastructure to avoid campuswide or critical building shutdowns and yet provide sufficient flexibility to meet the most critical campus needs in an effective manner. CSU Campuses Bakersfield Channel Islands Chico Dominguez Hills East Bay Fresno Fullerton Humboldt Long Beach Los Angeles Maritime Academy Monterey Bay Northridge Pomona Sacramento San Bernardino San Diego San Francisco San José San Luis Obispo San Marcos Sonoma Stanislaus
2 Presidents March 19, 2015 Page 2 Program funding is dependent upon the Board of Trustees approval to issue long-term debt financing pursuant to the new capital financing authority granted to the CSU and funding in the support budget to pay for the annual debt service. Guidelines Deferred Maintenance/Infrastructure Improvement Program 1) The 2015 Governor s Budget Proposal includes one-time funding of $25 million for deferred maintenance. If approved, these funds could be used to complete phased infrastructure projects begun with the program funding and projects on the critical infrastructure lists provided by the Utility Master Plan reports. Campuses can review and update the Deferred Maintenance lists of projects as provided in Attachments 3 and 4 to confirm and/or correct the campus priority projects. Please also complete the simplified project description (Capital Outlay Budget Change Proposal (COBCP) form 1-4) and construction cost estimate (Capital Outlay Estimate form 2-7) forms to convey the need, scope and budget for all the listed projects. Submit your revised lists and descriptions by April 1, This short turnaround is necessary to keep on track with the budget approval process. 2) For the Systemwide Infrastructure Improvement program, the campus should continue to identify projects to address life-safety, critical utility and building needs, energy and water conservation. Projects that remain unfunded or partially funded from the above noted Deferred Maintenance lists can be used as the basis for the Systemwide Infrastructure Improvement program. Please submit the campus draft Infrastructure Improvement list and project descriptions by April 20, Major Renovations and New Construction 1) The budget estimates will be based on the California Construction Cost Index (CCCI) 6255 and Equipment Price Index (EPI) An updated Capital Outlay Estimate form 2-7 is available on line for the budget year. A cashflow estimate is also requested for bond financing (the form is included in the form 2-7 workbook). 2) Please review the previously submitted ( ) action year COBCP project (the campus highest priority project; typically a major renovation, replacement building or growth project) to verify that it is still the campus highest priority after the projects on the Infrastructure Improvements list. The campus should reconfirm the project description and cost estimate to ensure they are accurately represented. 3) Please review the enrollment and space capacity companion reports to the Five-Year Capital Improvement Program that are key planning tools used for the system:
3 Presidents March 19, 2015 Page 3 Questions a. Summary of Campus Capacity with multi-year enrollment projections at rts/campus_sumcap.shtml b. Laboratory Enrollment FTES versus Laboratory Capacity FTES at abftes.shtml The required Campus Program Submittals, Cost Guide, Categories and Criteria (pending Board of Trustees approval) and Guidelines for Feasibility Study for the program will be available online. Several support documentation forms have been modified to facilitate streamlined budget development. All program submittals should use current CPDC forms. Access all program information via the CPDC page of the Chancellor's Office website: Select Facilities Planning, then either Call Letters or Forms, as needed. For specific program area questions, contact: State funded submissions Larry Piper, Chief of Facilities Planning, Capital Planning, Design and Construction (562) Financial documentation required to support non-state funded submissions Robert Eaton, Assistant Vice Chancellor, Financing and Treasury/Risk Management (562) Please submit all documents to Elvyra F. San Juan, Assistant Vice Chancellor, Capital Planning, Design and Construction. We thank you and your staff for your efforts to prepare the annual capital outlay program. CPDC staff will continue to identify process changes to streamline the program production in light of anticipated funding and possible authority changes. Attachment 1: Schedule of Submissions Attachment 2: Categories and Criteria for through Attachment 3: Deferred Maintenance Governor s Proposal Attachment 4: Deferred Maintenance Additional Need
4 Presidents March 19, 2015 Page 4 Distribution: Vice Presidents, Administration and Finance Vice Presidents, Student Affairs Timothy P. White, Chancellor, The California State University Steve Relyea, Executive Vice Chancellor/Chief Financial Officer, CSU Office of the Chancellor Ryan Storm, Assistant Vice Chancellor for Budget, CSU Office of the Chancellor Karen Yelverton-Zamarripa, Assistant Vice Chancellor, Advocacy and State Relations, CSU Office of the Chancellor Robert Eaton, Assistant Vice Chancellor, Financing and Treasury/Risk Management, CSU Office of the Chancellor Executive Facilities Officers Directors of Facilities Operations Building Coordinators Energy Managers Financing and Treasury Managers CPDC Planners
5 The California State University Attachment 1 Five-Year Capital Improvement Program Page 1 of 1 SCHEDULE OF SUBMISSIONS & CALENDAR OF CAPITAL OUTLAY PROCESS This schedule includes the capital program submittal dates for the action year. January 10, 2015 Governor's Budget proposed for March 24-25, 2015 March - May 2015 Board of Trustees approves Categories & Criteria for capital program. Legislative Committee hearings on the budget. April 1, 2015 Campuses submit the Deferred Maintenance lists for April 20, 2015 April 20, 2015 May 22, 2015 June 15, 2015 August 1, 2015 Summer/Fall 2015 Sept.1, 2015 Sept. 8-9, 2015 Nov. 1, 2015 Nov , 2015 Dec. 1, 2015 Campuses submit the COBCPs for the Draft Capital Outlay Program (COP) and Five-Year Capital Improvement Program (CIP). Campuses also submit related financial plans to Financing and Treasury. Campuses submit master plan map, facility legend and campus history. CPDC submits to Presidents proposed revisions to the Draft COP & CIP. Campuses submit the Final COP and CIP (one paper and one electronic copy). Program should include: Final State and Non-State COBCPs. Final equipment lists. Final Financial Plan for Non-State projects. Approval of Housing Proposal Review Committee (if applicable). Financing and Treasury approves campus final financial plan for projects to be funded by bonds, including auxiliary projects, for the Action Year. Campus site visits by State Agencies. CPDC submits final COBCPs and equipment lists to DOF/JLBC. Board of Trustees approves Draft COP & CIP & Statement of Support. DOF provides preliminary list of approved CSU projects to JLBC. Board of Trustees approves the Final COP & CIP. DOF submits final list of approved projects to CSU. January 10, 2016 Governor's Budget proposal for February 1, 2016 March - May 2016 April 1, 2016 June 2016 DOF provides preliminary list of approved CSU projects to JLBC. Legislative Committee hearings on the budget. DOF submits final list of approved projects to CSU. Campuses complete design architect selections/agreements for projects included in the Budget.
6 Attachment 2 Categories and Criteria to Set Academic Program Priorities General Criteria Priorities will be determined based upon the strategic needs of the system in consideration of existing deficiencies in the type, amount and/or condition of campus space to serve the academic master plan. In particular, priority will be given to projects that address critical seismic and infrastructure deficiencies, including life/fire safety, utilities infrastructure critical to campus-wide operations, capital renewal and minor capital outlay in existing facilities. Projects programmed for modernizing existing facilities or constructing new replacement buildings in response to academic needs or enrollment demand will be considered on a case-by-case basis. Campuses will be encouraged to identify funding sources for projects to receive priority consideration, however such funding will not guarantee a higher prioritization for the project based on the strategic needs of the system. A campus may submit a maximum of one major capital project for the budget year, one project for the planning year, and three projects per planning years , including health and safety projects. Exceptions to these limits will be considered on an individual project basis. Equipment and seismic strengthening projects are excluded from this limit. Seismic strengthening projects will be prioritized according to recommendations from the CSU Seismic Review Board. Approval of multi-phase projects may require the project funding to be allocated over more than one year. Campus requests for preliminary plans, working drawings, and construction (PWC) lump sum funding will be considered on an individual project basis based on the project s complexity, scope, schedule, and the availability of non-appropriated funds to augment the project. Current trustee-approved campus physical master plan enrollment ceilings apply to on-campus seat enrollment only. These numbers are to be used as the basis of comparison for justifying capital projects that address enrollment demand to be accommodated on campus. Enrollment estimates that exceed these figures should be accommodated through distributed learning and other off-campus instructional means.
7 Individual Categories and Criteria I. Existing Facilities/Infrastructure A. Critical Infrastructure Deficiencies CD (Critical Deficiencies) These funds correct structural, health and safety code deficiencies by addressing life safety problems and promoting code compliance in existing facilities. Projects include seismic strengthening, correcting building code deficiencies, failing infrastructure, and addressing regulatory changes which impact campus facilities or equipment. These funds also include the Systemwide Infrastructure Improvement and Minor Capital Outlay programs. B. Modernization/Renovation FIM (Facilities Infrastructure/Modernization) These funds make new and remodeled facilities operable by providing group II equipment (furnishings) and replacing utility services/building systems to improve facilities and the campus infrastructure. These funds also meet campus needs by modernizing existing facilities or constructing new replacement buildings in response to academic and support program needs as well as enrollment demand. II. New Facilities/Infrastructure ECP (Enrollment/Caseload/Population) These funds eliminate instructional and support deficiencies to support campus growth, including new buildings and their group II equipment, additions, land acquisitions, and site development.
8 Deferred Maintenance Governor's Proposal Attachment 3 Campus Campus DM Projects Project Estimate Bakersfield Replace electrical distribution transformers $1,000,000 Channel Islands Electrical and Fire Alarm Upgrade $950,000 Sanitary Sewer Replacement $75,000 ADA Pathway Upgrades $100,000 TOTAL $1,125,000 Chico Generator for fire egress system $1,023,000 TOTAL $1,023,000 Dominquez Hills Gas Line, Sensors and Valves Replacement $550,000 Arc Flash Study $275,000 TOTAL $825,000 East Bay Replace water pressure regulators and boilers $1,408,000 TOTAL $1,408,000 Fresno $0 TOTAL $0 Fullerton Undergrounding of electrical lines $650,000 TOTAL $650,000 Humboldt Fire Alarm Replacement $489,000 Elevator System Replacement $596,000 Building Controls System Replacement $549,000 TOTAL $1,634,000 Long Beach Sewer Line Replacement $1,500,000 TOTAL $1,500,000 Los Angeles Electrical Switchgear at King Hall $650,000 TOTAL $650,000 Maritime Academy Repair natural gas distribution system $370,000 Repair storm drain system, Academy Road $648,000 TOTAL $1,018,000 Monterey Bay 15kv distribution, Main Quad $2,100,000 TOTAL $2,100,000 Northridge Heating Hot Water Line Replacement $1,200,000 TOTAL $1,200,000 Pomona Central Plant Cooling Tower and HHW Line Upgrade $1,500,000 TOTAL $1,500,000 Sacramento MPOE Fire Suppression at AIRC $500,000 Arc Flash Study $200,000 Repair gas lines $650,000 TOTAL $1,350,000 San Bernardino Chiled Water Line Replacement $1,200,000 TOTAL $1,200,000 San Diego 15kv Switch Gear $1,300,000 TOTAL $1,300,000 San Francisco Sewer System Upgrade and Electrical at Tiburon $982,000 Emergency phones $385,000 TOTAL $1,367,000 San Jose Infrastructure Improvements, Phase 1C $1,400,000 TOTAL $1,400,000 San Luis Obispo Fire Alarm Replacement $500,000 Elevator Replacement $500,000 San Marcos $0 TOTAL $0 Sonoma Stevenson and Art Building Roofs $350,000 Upgrade Central Plant Controls $400,000 TOTAL $750,000 Stanislaus Boiler Plant and Corp Yard Roof Replacement $780,000 Chilled Water Expansion Tank Replacement $220,000 Total $25,000,000 All projects include PWC funding. 3/19/2015
9 Deferred Maintenance Additional Needs Attachment 4 Campus Campus Deferred Maintenance Projects Project Estimate Bakersfield Replace electrical distribution transformers $1,200,000 TOTAL $1,200,000 Channel Islands HVAC Replacement $500,000 Sanitary Sewer Replacement $400,000 ADA Upgrades $100,000 Chico Acker/Shurmer Fire Alarm Egress System $1,073,000 TOTAL $1,073,000 Dominquez Hills TBD $780,000 TOTAL $780,000 East Bay Water Pressure Regulators and Boiler Replacement $1,500,000 TOTAL $1,500,000 Fresno TBD $500,000 TOTAL $500,000 Fullerton Physical Services, Phase 1 $1,000,000 Humboldt Replace Natural Research Generator $175,000 Repair Mill Street Sewer and Water System Infrastructure $100,000 Building Controls System $500,000 Fire Alarm System $210,000 TOTAL $985,000 Long Beach TBD $500,000 TOTAL $500,000 Los Angeles Boiler Replacement - Campuswide $658,000 TOTAL $658,000 Maritime Academy Wharf Area Electrical Improvement $1,218,000 TOTAL $1,218,000 Monterey Bay TBD $1,000,000 Northridge HHW Upper Etiwanda and Jacaranda Walk $1,600,000 TOTAL $1,600,000 Pomona Domestic Water Line Replacement $1,000,000 Sacramento Elevator Modernization $1,000,000 San Bernardino Utility Project $1,300,000 TOTAL $1,300,000 San Diego Condensate line, Boiler $1,786,000 TOTAL $1,786,000 San Francisco Portable Generator Quick Connect Switchboards $1,480,000 TOTAL $1,480,000 San Jose Infrastructure IIA $1,620,000 TOTAL $1,620,000 San Luis Obispo Replace Transite Water Lines $600,000 Gas Isolation Valves $190,000 Engineering and Dexter Building Gas Piping Replacement $210,000 San Marcos Elevator Replacement - Craven Hall $800,000 TOTAL $800,000 Sonoma TBD $1,000,000 Stanislaus Drama Air Handler Replacement $1,000,000 Total $25,000,000 All projects include PWC funding. 3/19/2015
The California State University - OFFICE OF THE CHANCELLOR
The California State University - OFFICE OF THE CHANCELLOR MEMORANDUM To: Vice Presidents, Finance I Administration From: Elvyra F. San Ju~ C;-n~or Assistant Vice Capital Planning, Design and Construction
More informationATTACHMENT A /13 Budget Allocations Contingent on the Passage of Proposition 30, Gross Budget Summary Coded Memo B , October 5, 2012
ATTACHMENT A - Budget Allocations Contingent on the Passage of Proposition 30, Gross Budget Summary Coded Memo B 2012-03, October 5, 2012 (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13) (14) (15)
More informationATTACHMENT A /14 Final Budget Allocations, Gross Budget Summary Coded Memo B , July 24, 2013
ATTACHMENT A - Final Budget s, Gross Budget Summary Coded Memo B 2013-02, July 24, 2013 (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13) (14) (15) 2012/13 FIRMS Final Budget Detail Budget Gross
More informationBudgets in the CSU. CSU 101 Budget February 2012 Pismo Beach. Debbie Brothwell Deputy Vice President, Finance CSU East Bay
Budgets in the CSU CSU 101 Budget February 2012 Pismo Beach Debbie Brothwell Deputy Vice President, Finance CSU East Bay Overview How is the CSU Funded? Overview of the CSU Budget Process State of California
More informationTHE CALIFORNIA STATE UNIVERSITY
THE CALIFORNIA STATE UNIVERSITY BAKERSFIELD CHANNEL ISLANDS CHICO DOMINGUEZ HILLS FRESNO FULLERTON HAYWARD HUMBOLDT LONG BEACH LOS ANGELES MARITIME ACADEMY MONTEREY BAY NORTHRIDGE POMONA SACRAMENTO SAN
More informationThe California State University BUSINESS AND FINANCE
I The California State University BUSINESS AND FINANCE 401 Golden Shore, 5th Floor Long Beach, CA 90802-42 10 CSU Legislative Reports Website https://www.calstateedu/legislativereports/ Steve Relyea Executive
More informationFiscal State of the University. Presentation to the Academic Senate
Fiscal State of the University Presentation to the Academic Senate November 21, 2013 Administration and Finance Budget Planning and Administration Agenda FY 2013-14 Budget Update University Strategic Plan
More informationMary Ek, Assistant Vice Chancellor/Controller, Financial Services. 2017/2018 Centrally Paid Costs Direct Costs and Debt Service
Financial Services 401 Golden Shore, 5th Floor Long Beach, CA 90802-4210 www.calstate.edu Mary Ek Assistant Vice Chancellor/Controller 562-951-4540 Coded Memo: FS 2017-02 Date: To: From: Subject: May 30,
More informationBudget Forum February 2, 2018
Budget Forum February 2, 2018 Open Forum on Budget 2/2/18 Goals Have a common understanding of our current budget challenges Appreciate the urgency of addressing our fiscal situation See that we have a
More informationSubject: Audit Report 17-55, Cashiering, California State University, San Bernardino
Larry Mandel Vice Chancellor and Chief Audit Officer Office of Audit and Advisory Services 401 Golden Shore, 4th Floor Long Beach, CA 90802-4210 562-951-4430 562-951-4955 (Fax) lmandel@calstate.edu May
More informationAny observations not included in this report were discussed with your staff at the informal exit conference and may be subject to follow-up.
Larry Mandel Vice Chancellor and Chief Audit Officer Office of Audit and Advisory Services 401 Golden Shore, 4th Floor Long Beach, CA 90802-4210 562-951-4430 562-951-4955 (Fax) lmandel@calstate.edu August
More informationSubject: Audit Report 18-37, Accounts Receivable, San Francisco State University
Larry Mandel Vice Chancellor and Chief Audit Officer Audit and Advisory Services 401 Golden Shore, 4th Floor Long Beach, CA 90802-4210 562-951-4430 562-951-4955 (Fax) lmandel@calstate.edu December 19,
More informationFINANCIAL STATEMENTS
FINANCIAL STATEMENTS June 30, 2015 CSU Chico Chancellor s Office Cal Poly Pomona Sonoma State University CSU Stanislaus Bakersfield Channel Islands Chico Dominguez Hills East Bay Fresno Fullerton Humboldt
More informationUniversity Budget Committee. April 13, 2018
University Budget Committee April 13, 2018 1 Agenda I. Welcome II. Review and Approve Minutes from March 23, 2018 III. IV. UBC Feedback on Academic Senate Resolution on Increasing Faculty Involvement in
More informationCAL STATE UNIVERSITY IN A TIME OF FISCAL CRISIS: A CAUTIONARY TALE OF MANAGERIAL FLEXIBILITY
CAL STATE UNIVERSITY IN A TIME OF FISCAL CRISIS: A CAUTIONARY TALE OF MANAGERIAL FLEXIBILITY CALIFORNIA FACULTY ASSOCIATION FEBRUARY 8, 2011 Governor Brown s proposal for California s 2011-12 budget contains
More informationCalifornia State University. Fullerton. Financial Report Fiscal Year Budget Report Fiscal Year
California State University Fullerton California State University Fullerton Financial Report Fiscal Year 2017-18 Budget Report Fiscal Year 2016-17 Table of Contents I. Foreword II. Fiscal Year Budget 1
More informationAGENDA COMMITTEE ON INSTITUTIONAL ADVANCEMENT
AGENDA COMMITTEE ON INSTITUTIONAL ADVANCEMENT Meeting: 1:00 p.m., Tuesday, January 27, 2009 Glenn S. Dumke Auditorium Consent Item George G. Gowgani, Chair Peter G. Mehas, Vice Chair Carol R. Chandler
More informationCampus Budget Submissions Due: August 19, 2008
System Budget Office 401 Golden Shore, 5 th Floor Long Beach, CA 90802-4210 562-951-4560 Fax 562-951-4971 www.calstate.edu/budget FINAL-Budget Act of 2008 was chaptered on 9/23/08, AB 1781, Chapter 268
More informationThis budget is the first to incorporate our university community s shared goals as expressed in our new strategic plan, Building on Excellence.
Office of the President San Diego State University 5500 Campanile Drive San Diego, CA 92182 8000 Tel: 619 594 5201 Fax: 619 594 8894 September 30, 2014 Members of the university community: San Diego State
More informationWorkers Compensation Program July 1, 2014 July 1, 2015
Workers Compensation Program July 1, 2014 July 1, 2015 Insurers: Policy No.: Covered Name Entity: Covered Member: Coverages: Coverage Limits: Primary - CSURMA CSURMA primary pooled layer coverage Safety
More informationApplication for Audencia Winter Intersession November and December 2014 (field trip and workshop), January 2015 (abroad)
Application for Audencia Winter Intersession November and December 2014 (field trip and workshop), January 2015 (abroad) 1. Name Last Name, First Name Middle Initial 2. Student ID # 3. E-Mail Address (mandatory)
More informationAGENDA COMMITTEE ON FINANCE
AGENDA COMMITTEE ON FINANCE Meeting: 1:00 p.m., Tuesday, September 11, 2018 Glenn S. Dumke Auditorium John Nilon, Chair Peter J. Taylor, Vice Chair Jane W. Carney Douglas Faigin Emily Hinton Jack McGrory
More informationPROGRAMS COMMITTEE MEETING This is an Open Public Meeting
PROGRAMS COMMITTEE MEETING This is an Open Public Meeting In accordance with the requirements of the Bagley-Keene Open Meeting Act, notice of this meeting must be posted in a publicly accessible place,
More informationAdministration and Finance. April 22, 2011
Administration and Finance PRBC Presentation April 22, 2011 Division Mission Partners In Learning Division Mission: The Division of Administration and Finance contributes to the University mission by managing
More informationCAPITAL PLANNING, DESIGN AND CONSTRUCTION SECTION I -CAPITAL OUTLAY AND PUBLIC WORKS CONTRACTS SECTIONS TABLE OF CONTENTS
TABLE OF CONTENTS SECTION PAGE Capital Outlay and Public Works Contracts 9000 1 Capital Outlay 9001 1 Decentralized Capital Outlay Process 9002 2 Public Works Construction Contracts 9003 4 Public Works-Related
More informationCALIFORNIA STATE UNIVERSITY
CALIFORNIA STATE UNIVERSITY DOMINGUEZ HILLS BUDGET PLAN FISCAL YEAR 2010/2011 Prepared by: Budget Planning and Administration Profile of the University California State University Dominguez Hills was founded
More informationCP DC MASTERING THE 2-7. Presented by CPDC Facilities Planning. Systemwide Professional Development
CP DC MASTERING THE 2-7 Presented by CPDC Facilities Planning Produced by Systemwide Professional Development Mastering Facilities Planning Series of six sessions Mastering Feasibility Studies May 17,
More informationFinal Project Proposal 20 -
APPENDIX E: FINAL PROJECT PROPOSAL Final Project Proposal 20 - Community College Construction Act of 1980 Capital Outlay Budget Change Proposal Proposal Name Community College District College or Center
More informationCALIFORNIA STATE UNIVERSITY
CALIFORNIA STATE UNIVERSITY DOMINGUEZ HILLS BUDGET PLAN FISCAL YEAR 2011/2012 Prepared by: Budget Planning and Administration Profile of the University California State University Dominguez Hills was founded
More informationCALIFORNIA STATE UNIVERSITY INSTITUTE. Financial Statements and Supplementary Schedules. June 30, 2011 and 2010
Financial Statements and Supplementary Schedules (With Independent Auditors Report Thereon) Table of Contents Independent Auditors Report 1 Financial Statements: Statements of Net Assets 2 Statements of
More informationCALIFORNIA STATE UNIVERSITY INSTITUTE A Discretely Presented Component Unit of the California State University
Financial Statements and Supplementary Schedules (With Independent Auditors Report Thereon) Table of Contents Independent Auditors Report 1 Financial Statements: Statements of Net Position 3 Statements
More informationTrustees of the California State University. Resolutions
Trustees of the California State University Resolutions November 13-14, 2018 California State University Office of the Chancellor 401 Golden Shore, Long Beach, CA 90802 COMMITTEE ON UNIVERSITY AND FACULTY
More informationPlease indicate your approval of the attached 2017/18 Preliminary Cost Allocation Plan with your signature below.
SJSU SAN JOSE STATE UNIVERSITY April 14, 2017 Finance Office of The Associate Vice President Accounting Services Accounts Payable Budget & Risk Management Bursar's Office Contracts & Purchasing Distribution
More informationCSURMA ATHLETIC INJURY MEDICAL EXPENSE COMMITTEE MEETING AGENDA This is an Open Public Meeting
CSURMA ATHLETIC INJURY MEDICAL EPENSE COMMITTEE MEETING AGENDA This is an Open Public Meeting In accordance with the requirements of the Bagley-Keene Open Meeting Act, notice of this meeting must be posted
More informationCALIFORNIA STATE UNIVERSITY DOMINGUEZ HILLS BUDGET PLAN
CALIFORNIA STATE UNIVERSITY DOMINGUEZ HILLS BUDGET PLAN FISCAL YEAR 2017-2018 Prepared by: Budget Planning and Administration CALIFORNIA STATE UNIVERSITY, DOMINGUEZ HILLS CONTENTS 2017-18 BUDGET PLAN Total
More informationCAPITAL PLANNING, DESIGN AND CONSTRUCTION SECTION IV FISCAL RESOURCES FOR CAMPUS DEVELOPMENT SECTIONS Table of Contents
SECTIONS 9025 9041 Table of Contents SECTION PAGE Fiscal Resources for Campus Development 9025 1 State Capital Outlay Appropriations to CSU 9026 1 Procedures for Securing Funding for Proposed Capital Outlay
More informationCalifornia Community Colleges
California Community Colleges Capital Outlay Planning Background California Community Colleges capital outlay demands far exceed the available state resources to fund them. Currently, there is a backlog
More informationBUDGET PLAN FISCAL YEAR 2008/2009
C A L I F O R N I A S T A T E U N I V E R S I T Y DOMINGUEZ HILLS BUDGET PLAN FISCAL YEAR 2008/2009 Prepared by: Budget Administration & Financial Reporting Profile of the University California State University
More informationCHAPTER 3: PROJECT PRIORITIES AND SELECTION
CHAPTER 3: PROJECT PRIORITIES AND SELECTION 3.1 Overview 3.2 Steps in the Capital Outlay Process 3.3 State Funding Configurations 3.4 Priority Criteria for Capital Outlay 3.5 Types of Projects 3.6 Community
More informationAGENDA COMMITTEE ON FINANCE
AGENDA COMMITTEE ON FINANCE Meeting: 1:00 p.m., Tuesday, January 22, 2019 Glenn S. Dumke Auditorium John Nilon, Chair Peter J. Taylor, Vice Chair Jane W. Carney Douglas Faigin Emily Hinton Jack McGrory
More informationAGENDA COMMITTEE ON FINANCE
AGENDA COMMITTEE ON FINANCE Meeting: 1:30 p.m., Tuesday, September 19, 2017 Glenn S. Dumke Auditorium Peter J. Taylor, Chair John Nilon, Vice Chair Jane W. Carney Adam Day Hugo N. Morales Jorge Reyes Salinas
More informationCSURMA 1A Introduction to CSURMA May 14, 2015
CSURMA 1A Introduction to CSURMA May 14, 2015 Rob Leong rleong@alliant.com 415-403-1441 Mimi Long mlong@alliant.com 415-403-1423 Melissa Diaz mdiaz@alliant.com 415-403-1444 Presentation Outline 1. Overview
More informationAGENDA COMMITTEE ON FINANCE
AGENDA COMMITTEE ON FINANCE Meeting: 2:00 p.m., Tuesday, November 17, 2015 Glenn S. Dumke Auditorium Adam Day, Chair Peter J. Taylor, Vice Chair Silas H. Abrego Kelsey M. Brewer Rebecca D. Eisen Douglas
More informationMEMO TO: Vice Presidents, Deans, Directors, Chairs and Administrative Heads. SUBJECT: Presidential Directive
September 22, 2005 MEMO TO: Vice Presidents, Deans, Directors, Chairs and Administrative Heads Office of the President One Washington Square San José, CA 95192-0002 Voice: 408-924-1177 Fax: 408-924-1199
More informationCHAPTER 15 CAPITAL PROJECTS FUNDING FOR UNIVERSITY FACILITIES
CHAPTER 15 CSU FUND: Operating CSU Funds 441 TF Extended Education Operations 444 TF Extended Education Campus Partners 452 TF Facility Revenue Fund-Health Facilities Fees 472 TF Parking Revenue Fund-Parking
More information226
http://www.csus.edu/aba/facilities/facilities-planning.html 226 Five-Year Capital Improvement Program 2016/17 through 2020/21 227 Five-Year Capital Improvement Program 2016/17 through 2020/21 228 Sacramento
More informationPlanning, Building and Grounds (CPB&G) Board of Trustees. csu ORIENTATION FOR MEMBERS OF THE COMMITTEE ON. The California State University
csu The California State University Board of Trustees Board of Trustees Authority for Construction and Development ORIENTATION FOR MEMBERS OF THE COMMITTEE ON Campus Education Code Section 66606 www.leginfo.ca.gov/.html/edc_table_of_contents.html
More informationLETTER FROM THE EXECUTIVE VICE CHANCELLOR, CHIEF FINANCIAL OFFICER
LETTER FROM THE EXECUTIVE VICE CHANCELLOR, CHIEF FINANCIAL OFFICER The California State University is a remarkable institution that is comprised of 23 campuses offering an outstanding education to 438,157
More informationCHAPTER 15 CAPITAL PROJECTS FUNDING FOR UNIVERSITY FACILITIES
CHAPTER 15 CSU FUND: Operating CSU Funds 441 TF Extended Education Operations 444 TF Extended Education Campus Partners 452 TF Facility Revenue Fund-Health Facilities Fees 472 TF Parking Revenue Fund-Parking
More informationCSU Auxiliary Audit 2012
CSU Auxiliary Audit 2012 AOA Annual Conference January 10, 2012 Office of the University Auditor Mike Caldera Interim Senior Director Caroline Lee Auxiliary Audit Manager AGENDA OUA Department Update/Changes
More informationOPERATING AGREEMENT BETWEEN CALIFORNIA STATE UNIVERSITY AND CALIFORNIA STATE UNIVERSITY FOUNDATION
OPERATING AGREEMENT BETWEEN CALIFORNIA STATE UNIVERSITY AND CALIFORNIA STATE UNIVERSITY FOUNDATION This agreement is made and entered into by and between the Trustees of the California State University
More informationFiscal Year (FY13) Operating Budget and Capital Budget Overview
Approved by President Rush Fiscal Year 2012-2013 (FY13) Operating Budget and Capital Budget Overview Background A university budget represents the complex interchange between revenue streams that support
More informationStreamlined Capital Outlay Projects Funded from. Capital Outlay Bond Funds Legislative Report Legislative Session
Streamlined Capital Outlay Projects Funded from Capital Outlay Bond Funds Legislative Report 2008-09 Legislative Session November 2008 November 2008 UNIVERSITY OF CALIFORNIA Report on Streamlined Capital
More informationBOARD OF TRUSTEES THE CALIFORNIA STATE UNIVERSITY
LOTTERY FUNDS CALIFORNIA STATE UNIVERSITY, EAST BAY Audit Report 14-23 April 22, 2014 Lupe C. Garcia, Chair Steven M. Glazer, Vice Chair Adam Day Rebecca D. Eisen Hugo Morales Members, Committee on Audit
More informationTHE UNIVERSITY OF NORTH CAROLINA AT CHAPEL HILL CAPITAL IMPROVEMENT PROJECT PROCESS
Rev. 08/01/07 THE UNIVERSITY OF NORTH CAROLINA AT CHAPEL HILL CAPITAL IMPROVEMENT PROJECT PROCESS This document describes the project development and approval process for Capital Improvement Projects,
More informationErica Bowers, Ed.D. Chair, Planning, Resource, and Budget Committee (PRBC)
MEMORANDUM Date: May 5, 2016 To: From: Mildred García, Ed.D. University President Erica Bowers, Ed.D. Chair, Planning, Resource, and Budget Committee (PRBC) Subject: PRBC Recommendations for FY 2016-17
More informationSONOMA COUNTY JUNIOR COLLEGE DISTRICT PROPOSITION 39 AND MEASURE A GENERAL OBLIGATION BONDS SANTA ROSA, CALIFORNIA
SONOMA COUNTY JUNIOR COLLEGE DISTRICT PROPOSITION 39 AND MEASURE A GENERAL OBLIGATION BONDS SANTA ROSA, CALIFORNIA YEAR ENDED TABLE OF CONTENTS PAGE Independent Auditors' Report 1 Objectives 2 Scope of
More informationSONOMA COUNTY JUNIOR COLLEGE DISTRICT PROPOSITION 39 AND MEASURE A GENERAL OBLIGATION BONDS SANTA ROSA, CALIFORNIA
SONOMA COUNTY JUNIOR COLLEGE DISTRICT PROPOSITION 39 AND MEASURE A GENERAL OBLIGATION BONDS SANTA ROSA, CALIFORNIA YEAR ENDED TABLE OF CONTENTS PAGE Independent Auditors' Report 1 Objectives 2 Scope of
More informationRyan Storm Interim Assistant Vice Chancellor for Budget CSU Business Conference March 11, 2014
Ryan Storm Interim Assistant Vice Chancellor for Budget CSU Business Conference March 11, 2014 1 Roadmap Current Year Finances Budget Year Finances Multi-Year Trends CSU Support Budget Governor s Budget
More informationTalks on Faculty Contract resume this week
From the California Faculty Association CFA HEADLINES September 17, 2014 Weekly news digest from CFA Talks on faculty contract resume this week Attend your CFA campus chapter Bargaining Update Meeting
More informationTO MEMBERS OF THE COMMITTEE ON GROUNDS AND BUILDINGS: DISCUSSION ITEM
GB3 Office of the President TO MEMBERS OF THE COMMITTEE ON GROUNDS AND BUILDINGS: For Meeting of DISCUSSION ITEM STATUS OF THE PILOT PHASE OF THE DELEGATED PROCESS FOR CAPITAL IMPROVEMENT PROJECTS EXECUTIVE
More informationSTATE FUNDING REQUESTED VS. GOVERNOR S PROPOSAL. Proposed by the Governor
2 STATE FUNDING REQUESTED VS. GOVERNOR S PROPOSAL CSU Request $216.6M Proposed by the Governor $119.5M Funding Gap $97.1M 3 ENROLLMENT PLAN 2013/14 2014/15 2015/16 Base Surplus Total Base Surplus Total
More informationEarthquake Safety and Emergency Response Bond Program. Citizens General Obligation Bond Oversight Committee
Bond Oversight Committee Prepared by Charles Higueras, Program Manager December 31, 2010 TABLE OF CONTENTS Executive Summary... Page 1 Program Summary and Status Auxiliary Water Supply System (AWSS)...
More informationNOW, THEREFORE, the above-referenced entities have reached agreement on the terms and conditions of the model contract, which are contained herein.
Model Agreement Memorandum of Understanding Between The Department of General Services and The University of California and The California State University Revised May 15, 2017 MOU #AB20-2016, Amendment
More informationApril 26, Charlie Faas Vice President of Administration & Finance and CFO. Marna Genes Associate Vice President, Finance
Finance Office of The Associate Vice President Accounting Services Accounts Payable Budget & Financial Management Bursar s Office Contracts & Purchasing Distribution Services Finance Support One Washington
More informationSTATE CAPITAL OUTLAY PLANNING
STATE CAPITAL OUTLAY PLANNING CCC Chancellor s Office Cheryl Larry Lan Yuan San Mateo CCD Jose Nunez Karen Pinkham CCFC 2016 AGENDA Overview Eligibility Priority Review/Approval Effective Practices 1 Key
More informationACTION ITEM APPROVAL OF UNIVERSITY OF CALIFORNIA BUDGET FOR CURRENT OPERATIONS AND AND BUDGETS FOR STATE CAPITAL IMPROVEMENTS
F6 Office of the President TO MEMBERS OF THE COMMITTEE ON FINANCE: For Meeting of ACTION ITEM APPROVAL OF UNIVERSITY OF CALIFORNIA 2014-15 BUDGET FOR CURRENT OPERATIONS AND 2013-14 AND 2014-15 BUDGETS
More informationGoverning Board Bond Update. Measure G Bond Program. for. Solano Community College District
Governing Board Bond Update for Measure G Bond Program prepared by Kitchell for the Solano Community College District Included in Booklet: Board Update Bond Financial Summary Completed Projects Projects
More informationRISK MANAGEMENT AND INSURANCE CALIFORNIA POLYTECHNIC STATE UNIVERSITY, SAN LUIS OBISPO. Report Number February 26, 2004
RISK MANAGEMENT AND INSURANCE CALIFORNIA POLYTECHNIC STATE UNIVERSITY, SAN LUIS OBISPO Report Number 03-33 February 26, 2004 Shailesh J. Mehta, Chair Roberta Achtenberg, Vice Chair Debra S. Farar William
More informationGuidance Memo February 1, Subject: State of California Model Agreement (formerly the AB20 Model Agreement) Background
Guidance Memo 16-01 February 1, 2016 Subject: State of California Model Agreement (formerly the AB20 Model Agreement) Background In January of 2010, Assembly Bill 20 (AB20 2009-2010) became effective and
More informationBoard of Trustees Budget, Finance and Facilities Committee Meeting January 24, 2019
Board of Trustees Budget, Finance and Facilities Committee Meeting January 24, 2019 PRESENTED BY Finance and Administration Florida Agricultural and Mechanical University 1 ACTION ITEM IV: Approval of
More informationCHAIR OF THE BOARD CHAIR OF THE COMMITTEE ON GROUNDS AND BUILDINGS PRESIDENT OF THE UNIVERSITY
UNIVERSITY OF CALIFORNIA BERKELEY DAVIS IRVINE LOS ANGELES MERCED RIVERSIDE SAN DIEGO SAN FRANCISCO SANTA BARBARA SANTA CRUZ OFFICE OF THE PRESIDENT 1111 Franklin Street Oakland, CA 94607-5200 Phone: (510)
More informationCentral Michigan University Capital Budget
Central Michigan University Capital Budget 1999-2000 Table of Contents Central Michigan University Capital Budget Table of Contents I. Narrative A. Overview and Process...1 B. Funding Sources...2 C. Capital
More informationCONSTRUCTION CALIFORNIA STATE UNIVERSITY, DOMINGUEZ HILLS EDUCATIONAL RESOURCE CENTER ADDITION. Audit Report December 16, 2010
CONSTRUCTION CALIFORNIA STATE UNIVERSITY, DOMINGUEZ HILLS EDUCATIONAL RESOURCE CENTER ADDITION Audit Report 10-17 December 16, 2010 Members, Committee on Audit Henry Mendoza, Chair Raymond W. Holdsworth,
More informationCSU Health Insurance Education Project: Project Poll & Analysis
Health Insurance Education Project CSU Health Insurance Education Project: Project Poll & Analysis Walter Zelman Project Director, CSU HIEP Chair, Department of Public Health, CSULA June 12, 2014 Our grant
More informationYou are being provided with the background, explanation, and instructions for the Reciprocal Self-Certification Form (PERS-CASD 801).
California Public Employees Retirement System P.O. Box 942709 Sacramento, CA 94229-2709 888 CalPERS (or 888-225-7377) TTY: (877) 249-7442 Fax: (916) 795-4166 www.calpers.ca.gov Employer Account Management
More informationCHAPTER 4: FIVE-YEAR CONSTRUCTION PLAN
CHAPTER 4: FIVE-YEAR CONSTRUCTION PLAN 4.1 Overview 4.2 Master Plan Summary 4.3 List of Projects in Order of Priority 4.4 Cumulative Capacities and Loads for each Space Type 4.5 The Capacity of Existing
More informationSAN FRANCISCO COMMUNITY COLLEGE DISTRICT
SCHEDULE OF PROCEEDS AND USE OF GENERAL OBLIGATION BONDS (ELECTION OF 2005, SERIES A) WITH INDEPENDENT AUDITOR S REPORT For the period from June 20, 2006 through June 30, 2006 SCHEDULE OF PROCEEDS AND
More informationCARLSBAD UNIFIED SCHOOL DISTRICT $265 MILLION BOND MEASURE July 2018
CARLSBAD UNIFIED SCHOOL DISTRICT $265 MILLION BOND MEASURE July 2018 SDCTA Position: SUPPORT Rationale for Position: The District has provided all requested information and has adopted all SDCTA recommended
More informationCalifornia Public Employees Retirement System 888 CalPERS 888 Employer Account Management Division
Employer Account Management Division Dear Member, You are being provided with the background, explanation, and instructions for the Reciprocal Self-Certification Form (PERS-EAMD 801). Reciprocity among
More informationCALIFORNIA COMMUNITY COLLEGES
CALIFORNIA COMMUNITY COLLEGES 2006-07 FIVE-YEAR CAPITAL OUTLAY PLAN SYSTEM OFFICE FACILITIES PLANNING & UTILIZATION UNIT July 2005 Members of the Board Kay Albiani Elk Grove George T. Caplan Los Angeles
More informationCoaches Handbook. California Faculty Association.
Coaches Handbook California Faculty Association www.calfac.org WELCOME This edition of the CFA Coaches Handbook comes to you through the efforts of your California Faculty Association colleagues. It will
More informationProgram and Project Status Update
Program and Project Status Update Citizens Bond Oversight Committee Meeting October 14, 2014 Robert Ball, Bond Program Manager 1 Capital Improvement Program General Updates Close out of completed projects
More informationCALIFORNIA STATE UNIVERSITY INSTITUTE A Discretely Presented Component Unit of the California State University
Financial Statements and Supplementary Schedules (With Independent Auditors Report Thereon) Table of Contents Independent Auditors Report 1 Management s Discussion and Analysis (Unaudited) 3 Financial
More informationAPPENDIX A FULL TEXT OF BOND MEASURE
APPENDIX A FULL TEXT OF BOND MEASURE INTRODUCTION To repair aging classrooms / leaky roofs / old facilities, and provide a safe, quality learning environment for current and future students, shall Grass
More informationCALIFORNIA COMMUNITY COLLEGES
CALIFORNIA COMMUNITY COLLEGES 2005-06 FIVE-YEAR CAPITAL OUTLAY PLAN SYSTEM OFFICE FACILITIES PLANNING & UTILIZATION UNIT January 2005 Members of the Board Kay Albiani Elk Grove Anthony J. Alvarado Coronado
More informationOverview of Public Schools CIP
Overview of Public Schools CIP The Public Schools Community Investment Plan (CIP) includes school construction, additions and modernizations, as well as other school related projects. For more than a decade
More informationSacramento City College
Sacramento City College Strategic Planning System Title: Plan Type: OPR: Collaborative Group: References: Facility Management Resource Allocation Operations Division Campus Development Committee ADA Transition
More informationUniversity Budget Advisory Committee Composition
University Budget Advisory Composition The University Budget (UBAC) is established by the President to provide input and recommendations to the President regarding the University s General Operating Fund
More informationGov's Planning Estimates Project Title Rank Fund Project Requests for State Funds
This document is made available electronically by the Minnesota Legislative Reference Library as part of an ongoing digital archiving project. http://www.leg.state.mn.us/lrl/lrl.asp State Academies Projects
More informationCONSTRUCTION PROJECTS STATUS REPORT BOARD OF TRUSTEES MEETING - October 31, 2018
Planning Academic & Research Facilities - Homer 300008 $1,850,000 $1,603,349 P UCONN 2000 Bond Funds 03/29/17 2022 Babbidge Library Renovations Northwest Science Quad Infrastucture- 3 300103 $700,000 P
More informationSacramento City College Strategic Planning System
Sacramento City College Strategic Planning System Title: Plan Type: OPR: Collaborative Groups: Resource Management and Capital Outlay Master Plan 2018 Institutional VPA Resource Allocation Groups: Budget
More informationCalifornia Public Employees Retirement System 888 CalPERS 888 Employer Account Management Division
California Public Employees Retirement System P.O. Box 942709 Sacramento, CA 94229-2709 888 CalPERS (or 888-225-7377) TTY: (877) 249-7442 Fax: (916) 795-4166 www.calpers.ca.gov Employer Account Management
More informationAllan Hancock Joint Community College District
One Stop Studen Allan Hancock Joint Community College District One Stop Student Services Public S Public Safety Com Public Safety Complex Childc Childcare Addit Childcare Addition BOND MEASURE I Progress
More informationCALIFORNIA STATE UNIVERSITY, POMONA. Financial Statements. June 30, (With Independent Auditors Report Thereon)
Financial Statements (With Independent Auditors Report Thereon) Table of Contents Page Independent Auditors Report 1 Management s Discussion and Analysis (Unaudited) 3 Financial Statements: Statement of
More informationProposition E: Escondido Union School District $182.1 Million Bond Measure
Proposition E: Escondido Union School District $182.1 Million Bond Measure SDCTA is NEUTRAL on Proposition E. The measure meets most of the key provisions of the SDCTA Bond Support Criteria. The application
More informationMT. SAN ANTONIO COMMUNITY COLLEGE DISTRICT PROPOSITION 39, GENERAL OBLIGATION BONDS (MEASURE R, NOVEMBER 2001) PERFORMANCE AUDIT.
(MEASURE R, NOVEMBER 2001) (MEASURE R, NOVEMBER 2001) CONTENTS Page Independent Auditor s Report... 1 Objectives... 2 Scope of the Audit... 2 Background Information... 3 Procedures Performed... 3 Results
More informationFiscal Year 2014 (FY14) Operating and Capital Budget Overview
Fiscal Year 2014 (FY14) Operating and Capital Budget Overview Approved by President Rush Background The FY14 CSU Channel Islands budget provides an update on budget actions for the next fiscal year and
More informationSan Francisco State University. We Make Great Things Happen
San Francisco State University We Make Great Things Happen Fiscal Year 2015/16 November 2015 University Budget Committee 2 Summary of the Governor s 2015/16 Budget Summary of the Governor s 2015/16 State
More informationFacilities Planning & Construction Report nd Quarter Ending December 31, 2017
Facilities Planning & Construction Report 2017 18 2 nd Quarter Ending December 31, 2017 Overview District SRID Spending (MG100) Summary By College By Site District Measure J Spending (MJ100) Summary By
More information