Project Performance Status Report

Size: px
Start display at page:

Download "Project Performance Status Report"

Transcription

1 Bahrain Polytechnic Project Performance Status Report Mechanical Project 6 (project management) Husain Alfarhan /Yahya Saif /Raed Algharaifi /Ali Yusuf /Sayed Mujtaba

2 Table of Contents Abstract... Error! Bookmark not defined. No table of figures entries found.... Error! Bookmark not defined. Document Propose... 2 Project Status Summary... 3 Current Status of Scope... Error! Bookmark not defined. a) Work Completed... Error! Bookmark not defined. b) Work in progress:... Error! Bookmark not defined. c) Work not started... Error! Bookmark not defined. Current status of Milestones:... 0 Current Status of Open Issues... 1 Current Status of Open Risks... 2 Current Status of Change Requests... 3 a. Change Request Log... 3 Table of Tables Table 1: completed scope, schedule, and cost for the entire project... 3 Table 1: completed scope, schedule, and cost for the until the end of semester Table 2, Current status of Milestones... 0 Table 3, Current status of Open Issues... 1 Table 4, Current status of Open Risks... 2 Table 5, Change Request Log... 3 Table 6, progress, planed cost and actual spent... 6 Table 7, PV, EV, AC & BAC... 7 Table 8, Project performance... 7 Page 1 of 13

3 Document Propose The aim of the report is to analyze the performance of the project to see how it is progressing in term of scope, schedule, and cost relative to the plan. This report covers the period starting from (Sunday) and it (Tuesday). This project performance report will highlight the current status of the scope including the accomplishments that were achieved so far, the work that is in progress and the work that is not started yet. It will also highlight the issues that are currently occurring and will suggest mitigation action that could eliminate and reduce their impacts. Furthermore it will predict the possible future risks and will state how they can be avoided. It will also contain a list of changes that need to be done to the project and will show a flow chart for the change in request plan. Page 2 of 13

4 Project Status Summary: Table 1: completed scope, schedule, and cost for the entire project Scope Schedule Cost 48.73% % 54.66% Table 2: completed scope, schedule, and cost for the until the end of semester 2 Scope Schedule Cost 73.1% % % Table 3: variance between the desired and actual completed scope, schedule, and cost for the until the end of semester 2 Scope Schedule Cost 26.9 % % ( BD) 4.37% (71.6 BD) We have completed 33.33% of the scope in semester 1 and have completed 15.40% in semester 2. Therefore the total completed scope is 48.73% while we were supposed to complete 66.67% of the scope until the end of semester 2. This means our progress in scope until this moment is 73.1% of the planned scope for semester 2 and therefore the variance is equal to 26.9%. We have completed 42.85% of the entire project at this stage while we were supposed to complete 66.67% of the entire project. This means we are progressing at 64.28% which means we are behind the schedule by 35.72% (variance cost 2440* = BD)) We have spent 54.66% of the entire project budget (1640 BD out of 3000); since we should spend BD at this stage. This means we are getting BD worth of performance for every 1 BD spent (we used % of the budget specified for semester 1 and 2) which means the variance is equal to 4.37 % (variance cost 1640* = 71.6 BD) Page 3 of 13

5 Current Status of Scope a) Work Completed Components type Deliverable Job required Baseline Period (Days) Actual Period (Days) Chassis Chassis frame D A M Sleeves Front suspension Bushings (type: double wishbone) Wishbones D A M Bolts Bearings Rear suspension Ball joints (type: MacPherson) Coil over spring D A S Interior Drives and passengers seats M 6 6 * Note: D: design. A: analysis. M: manufacturing. S: selecting

6 b) Work in progress: Components type Deliverable Job required Baseline Period (Days) Thermoset Feed pump Cooling system Tubes Cooling fan Radiator Safety relive valve D A S 108 External Steering system D A S 108 components Connections Breaking system Master cylinder Brake pads Brake discs DAS 108 Epicyclic gear box for the automatic transmission system. DAS 108 Exhaust system D A S 108 * Note: D: designing. A: analyzing. M: manufacturing. S: selecting c) Work not started Deliverable Baseline Period (Days) Designing and analyzing a deferential 20 Designing and analyzing rotating shaft that will transmit the power from the engine to the deferential. 29 Selecting suitable wheels size that will provide maximum possible performance. 8 Assembling components of the car together. 6 Testing the car to see if it meets the PDS. 7 Page 1 of 13

7 Current status of Milestones: Table 4, Current status of Milestones Milestone Baseline SD Baseline ED Actual SD Actual ED Status M1 Chassis 16/02/ /06/ /02/ /06/2014 C M2 Front suspension 16/02/ /06/ /02/ /06/2014 C M3 Rear suspension: Bolts, ball joints, coil-over, spring, bearings 16/02/ /06/ /02/ /06/2014 C M4 Simple seats 09/04/ /04/ /04/ /04/2014 C M5 Cooling system 14/09/ /12/ /09/ IP M6 Steering system 14/09/ /12/ /09/ IP M7 Breaking system 14/09/ /12/ /09/ IP M8 Epicyclic gear box 14/09/ /12/ /09/ IP M9 Exhaust system 14/09/ /12/ /09/ IP M10 Deferential 10/02/ /03/ NS M11 Rotating shaft 15/04/ /05/ NS M12 Wheels size 14/05/ /05/ NS M13 Assembling car components 22/05/ /05/ NS M14 Car testing 27/05/ /06/ NS

8 Current Status of Open Issues Table 5, Current status of Open Issues No. Description Root Cause Impact Contingency Plan Lack of experts assistance and Get experts assistance. therefore students took more time to Delay in the plan. solve the problems. I1 I2 Lack of time Damaging the accessories. Lack of resources in the library which caused the students to spend long time researching in the internet. The insufficient training that was given to the students resulted in manufacturing many parts out of tolerance and therefore they were remanufactured which resulted in time loss. Insufficient training period. Bad quality of accessories. I3 Lack of Space Small Workshop. I4 I5 Lack of welding machines. Bad welding There are only two welding machines, and one of them is not working properly. Insufficient training. One of welding machines is not working properly. The welding material is thinner than the required for welding mild steel. More cost spent due to the remanufacturing. Pressure on the students which affected their performance which correspondingly reduced the quality of the car. More money spent on purchasing new accessories. Injuries have occurred because there are many students working with hazardous equipment in a small place. Being behind the schedule. Stress concentration. Heat effected zone which makes the material weaker. Provide username and passwords to students to scientific research databases (such as science-direct, springer, and Elsevier) and EBook library. Increase the practical training period. Extend the project period or work overtime. Increase the number of students per team. Less preferred solution: decrease the scope of the project. Extend the training period. Purchase high quality accessories Putting rules and guidelines. Work on UOB labs. Fixing the defective welding machine. Rent welding machine. Increase the practice period. Fixing the defective welding machine. Purchase the exact welding material, and make sure that is fitted correctly. Page 1 of 13

9 Current Status of Open Risks: Table 6, Current status of Open Risks No. Description Root Cause R1 R2 Chassis might be taken by other students. Running out of time for manufacturing. There are no rules or regulations about the ownership of the project in the university. The specified time for the manufacturing is insufficient. Too big scope targets. Priority (H,M,L) Probabilit y (%) Impact (H,M,) H 10 % H H 90 % H R3 Bad welding Lack of practice. M 70 % M R4 R5 R6 The budget might be reduced to 1000 BHD Injuries Damaging the chassis during the relocation process Bahrain polytechnic management has many projects to do during 2014 and Working in a small workshop in a short period with high pressure. Using dangerous machines and tools. Workers relocate the workshop machines, tools, tables several times each course. M 40 % M H 80 % H L 40 % L Contingency Plan Writing an official letter to Keallen and John asking them to keep the chassis. Increase manufacturing period. Decrease the scope. Increase the number of students per team. Increase the practice period. Choose the best students in welding to do the welding. Negotiate with the management through explaining the importance, aims of the project, and strive to maintain their support. Prepare plan B through finding alternative suppliers. Increase manufacturing period. Working in UOB labs. Applying safety procedures. At least three students must have a valid first-aid license. Wearing personal protective equipment including overall, safety shoes, safety glasses and gloves. Putting rules and regulations (including a rule that states that the chassis should always be covered and rules governing the relocating process). Page 2 of 13

10 Current Status of Change Requests A. Change Request Log: Table 7, Change Request Log Change Request Number CR1 CR2 CR3 CR4 CR5 Change Request Short Description Request Date Current Status Do changes to the chassis design: because it was discovered that the stresses in practical are higher than what was calculated in theory, therefore new triangulations members will be added to the chassis frame, and also it will transformed from two drivers into one driver. Extend the project period to have more time for manufacturing: because the lack of time, it is required to have two more working weeks at least. Change the rear suspension from McPherson to a solid axial: as the solid axial suspension is less complex and requires less time it is recommended to be used to overcome the lack of time issue. Increase the budget in order to purchase high quality accessories: the accessories were getting damaged easily due to their cheap quality, therefore accessories with better quality is required. Change the used material in manufacturing the suspension from mild steel 1020 to mild steel 1018: because in the analysis stages we realized that the stresses are high in the suspensions, therefore stronger material is required. 08/04/ /05/2014 In Review by Change Control Board. Approved and Being Added to the Project Plan. 20/04/2014 Rejected by the CCB. 01/06/2014 Rejected by the CCB. 08/04/2014 Rejected by the CCB. Page 3 of 13

11 B. Integrated Change Control Process (5) The change request process was followed in the project was as illustrated in the flow chart below: Figure 1: Change request process flow chart 1. Change management process 2. Identify the need for a change by, Stakeholder, Customer, and Project Manager. 3. Change is to be logged by the Project Manager in the change request register. 4. Change request to be submitted by the Project Manager to Change Control Board CCB. 5. CCB meets Change control meeting to evaluate change and decides. 6. Project Manager informs the team by the changes, updates plans and baselines, Implement change if Change Control Board CCB approves the change. Page 4 of 13

12 Moreover, the CCB uses a certain methodology to make their decision, which is shown in the flow chart below: Figure 2: decision methodology flow chart Page 5 of 13

13 Key Performance Indicators (KPI's): NO Components Progress Planed cost Actual spent 1 Chassis 100% 150 BD 190 BD Front suspension, Rear suspension, Bolts, ball joints, coil-over, spring, bearings 100% 635 BD 580 BD 5 Simple seats 100% 35 BD 35 BD Total 100% 820 BD 805 BD NO Components Progress Planed cost Actual spent 1 Cooling system 66 % 180 BD 100 BD 2 Steering system 33 % 80 BD 30 BD 3 Braking system 33% 440 BD 80 BD 4 Epicyclic gear box 66 % 800 BD 575 BD 5 Exhaust system 33 % 120 BD 50 BD Total 46.2 % 1620 BD 835 BD NO Components Progress Planed cost Actual spent 1 Deferential 0% 100 BD 0 BD 2 Engine + Rotating shaft 0% 200 BD 0 BD 3 Wheels 0% BD 4 Assembling car components 0% 40 BD 0 BD 5 Testing the car 0% 10 BD 0 BD Total 0% 560 BD 0 BD Table 8, progress, planed cost and actual spent Semester 1 Semester 2 Semester 3 Activity N.O Plan Actual Progress Plan Actual Progress Plan Actual Progress A1 820 BD 805 BD 100 % A BD 835 BD 46.2% A3 560 BD 0 BD 0% Page 6 of 13

14 PV = 2440 BD EV (820 1) + ( ) + (560 0) = AC = 1640 BD BAC 3000 BD Table 9, PV, EV, AC & BAC Control Value Interpretation SV (schedule variance) EV- PV = = BD Behind schedule SPI (schedule performance indicator) EV/PV = /2440 = We are progressing at 64.28% of the pace we are expected to. CV (cost variance) EV-AC = = CPI (cost performance variance) EV/AC = /1640 = We are spending more than planned by BD BD saving. (Losing) We are getting BD worth of performance for every 1 BD spent. Bad EAC (estimate at completion) BAC/CPI = 3000/ = BD New budget which is higher than original. ETC (estimate to complete) EAC AC = = We will expect to spend this amount to complete project VAC (variance at completion) BAC-EAC = = We are expecting to lose BD at the end of this project. A. Schedule: The project is behind Schedule. Schedule Variance (SV): BD. Schedule Performance Index (SPI): % B. Cost: The project is over Budget. Cost Variance (CV): BD. Cost Performance Index (CPI): Table 10, Project performance Page 7 of 13

CS 413 Software Project Management LECTURE 9 COST MANAGEMENT FOR SOFTWARE PROJECT III

CS 413 Software Project Management LECTURE 9 COST MANAGEMENT FOR SOFTWARE PROJECT III LECTURE 9 COST MANAGEMENT FOR SOFTWARE PROJECT III Earned Value Management Earned value management (EVM) is a way of measuring your performance (and the performance of your project team) at any given date

More information

Cumulative trends Problems and issues since last report

Cumulative trends Problems and issues since last report Project Progress Report Format Progress since last report Current status of project 1. Schedule 2. Cost 3. Scope Cumulative trends Problems and issues since last report 1. Actions and resolution of earlier

More information

4/14/2017. Unit 7 Slide Lectures of 19/20/21 April 2017 PROJECT PROGRESS AND PROJECT PERFORMANCE ASSESSMENT (CH. 13)

4/14/2017. Unit 7 Slide Lectures of 19/20/21 April 2017 PROJECT PROGRESS AND PROJECT PERFORMANCE ASSESSMENT (CH. 13) PROJECT AND COMMUNICATION MANAGEMENT Academic Year 2016/2017 PROJECT PROGRESS AND PROJECT PERFORMANCE ASSESSMENT (CH. 13) Unit 7 Slide 7.2.1 Lectures of 19/20/21 April 2017 Structure of a Project Monitoring

More information

INSE 6230 Total Quality Project Management

INSE 6230 Total Quality Project Management Lecture 5 Project Cost Management Project cost management introduction Estimating costs Budget Earned Value Management (EVM) EVM projections 2 IT projects have a poor track record for meeting budget goals

More information

Project Management -- Monitoring the progress

Project Management -- Monitoring the progress Project Management -- Monitoring the progress Dr. Tai-Yue Wang Department of Industrial and Information Management National Cheng Kung University Tainan, TAIWAN, ROC 1 Where We Are Now 2 Structure of a

More information

NEW HORIZONS ONLINE LIVE. Project Management Professional (PMP ) PMBOK Guide 6th Edition DAY 4

NEW HORIZONS ONLINE LIVE. Project Management Professional (PMP ) PMBOK Guide 6th Edition DAY 4 NEW HORIZONS ONLINE LIVE Project Management Professional (PMP ) PMBOK Guide 6th Edition DAY 4 2 3 4 5 6 Other PMP Topics Cost Ranges Rough Order of Magnitude (ROM) (often done in the initiating process

More information

CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon

CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon Abstract- Project Cost Management includes the processes involved in planning, estimating, budgeting,

More information

9/24/2010. Information System Structure (cont d) Information System Structure. Progress since last report Current status of project.

9/24/2010. Information System Structure (cont d) Information System Structure. Progress since last report Current status of project. Project Management Progress and Performance Measurement and Evaluation Haeryip Sihombing 12 Universiti Teknikal Malaysia Melaka (UTeM) BMFP 4542 McGraw-Hill/Irwin 13 2 Project Monitoring System for Control

More information

THE PMP EXAM PREP COURSE

THE PMP EXAM PREP COURSE THE PMP EXAM PREP COURSE Session 3 PMI, PMP and PMBOK are registered marks of the Project Management Institute, Inc. www.falcontraining.co.nz Agenda 9:00 10:15 10:15 10:30 10:30 12:00 12:00 12:45 12:45

More information

PMP Exam Prep Coaching Program

PMP Exam Prep Coaching Program PMP Exam Prep Coaching Program Project Part 1 Presented by Vinai Prakash, PMP 1 Project Plan Estimate s Determine Budget 2 Vinai Prakash, PMCHAMP.COM 1 Process of monitoring the status of the project to

More information

PROJECT COST MANAGEMENT

PROJECT COST MANAGEMENT PROJECT COST MANAGEMENT For the PMP Exam using PMBOK Guide 5 th Edition PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. 1 Contacts Name: Khaled El-Nakib, PMP, PMI-RMP

More information

PMP. Preparation Training. Cost Management. Your key in Successful Project Management. Cost Management Processes. Chapter 7 6/7/2005

PMP. Preparation Training. Cost Management. Your key in Successful Project Management. Cost Management Processes. Chapter 7 6/7/2005 PMP Preparation Training Your key in Successful Project Management Akram Al-Najjar, PMP Cost Management Processes Chapter 7 Cost Management Slide 2 1 AGENDA What is Cost Management? Cost Management Processes

More information

Application of Earned Value Management (EVM) for Effective Project Control

Application of Earned Value Management (EVM) for Effective Project Control Application of Earned Value Management (EVM) for Effective Project Control Course No: B02-012 Credit: 2 PDH Boris Shvartsberg, Ph.D., P.E., P.M.P. Continuing Education and Development, Inc. 9 Greyridge

More information

Carlos Consulting Group

Carlos Consulting Group Carlos Consulting Group Earned Value Management Building A Playhouse Financial analysis that goes one step beyond Budget versus Actual Presented by Tom Carlos, PMP June 20, 2007 Carlos Consulting Group

More information

Lesson 7 The Project Budget

Lesson 7 The Project Budget MBA, Msc, Bsc, PMP, CSM, PMI-ACP Indike Manthilake MBA, Msc, Bsc, CSM, PMI-ACP indikem@unitedmotors.lk.com Lesson 7 The Project Budget Agenda Estimate Costs and income Creating a Preliminary Budget Budget

More information

Earned Value Management - EVM

Earned Value Management - EVM Earned Value Management (EVM) technique used to track the Progress and Status of a Project & Forecast the likely future performance of the Project. Earned Value Management (EVM) technique integrates the

More information

PMP Exam Preparation Course. Madras Management Training W.L.L All Rights Reserved

PMP Exam Preparation Course. Madras Management Training W.L.L All Rights Reserved Project Cost Management 1 Project Cost Management Processes 1. Estimate Costs 2. Determine Budget 3. Control Costs In some projects, especially with smaller scope, cost estimation and cost budgeting are

More information

Pass PMP in 21 Days - ITTO Toolbox PROCESS MAP

Pass PMP in 21 Days - ITTO Toolbox PROCESS MAP PROCESS MAP 1 IntEgratIon Pass PMP in 21 Days - ITTO Toolbox InItIatIng PlannIng ExEcutIng MonItorIng & controlling closing Develop Project Charter Develop Project Management Plan Direct & Manage Project

More information

MMZG 523 PROJECT MANAGEMENT

MMZG 523 PROJECT MANAGEMENT MMZG 523 PROJECT MANAGEMENT BITS Pilani Pilani Campus ARUN MAITY BITS Pilani Pilani Campus PROGRESS & PERFORMANCE MANAGEMENT AND EVALUATION CHAPTER NO 13 TEXTBOOK T1 Need Control holds people accountable

More information

Formulas to Know for EXAM

Formulas to Know for EXAM Formulas to Know for EXAM Activity & Project Duration Formulas In order to calculate Estimated Activity Duration (EAD) of an activity, Optimistic (O), Most Likely (M) and Pessimistic (P) estimates for

More information

Performance measurement

Performance measurement MGT/437 Project Management Session #4 Managing Projects to Achieve Optimal Results University of Phoenix, San José Learning Center 07/06/2004 Brian Smithson 07/06/2004 MGT/437 #4 -- Brian Smithson 1 Agenda

More information

Project Monitoring and Control Project Closure. Week 8

Project Monitoring and Control Project Closure. Week 8 Project Monitoring and Control Project Closure Week 8 Last Week MS Project Tutorial Assignment Guidelines This Week Project Monitoring and Control What is Monitoring and Control Reporting Milestone Monitoring

More information

Thomas Carlos Consulting. Simple Earned Value Management

Thomas Carlos Consulting. Simple Earned Value Management Thomas Carlos Consulting Simple Earned Value Management Financial analysis that goes one step beyond Budget versus Actual Presented by Tom Carlos, PMP September 11, 2008 Thomas Carlos Consulting, Roseville,

More information

Earned Value Project Management. Amber L. Romero, CPM, P.M.P., Policy Analyst Sandia National Laboratories 505/ ;

Earned Value Project Management. Amber L. Romero, CPM, P.M.P., Policy Analyst Sandia National Laboratories 505/ ; Dollars $M Earned Value Project Management Amber L. Romero, CPM, P.M.P., Policy Analyst Sandia National Laboratories 505/284-0634; allewis@sandia.gov 95 th ISM Annual International Supply Management Conference,

More information

PROJECT MANAGEMENT BODY OF KNOWLEDGE

PROJECT MANAGEMENT BODY OF KNOWLEDGE A Guide to the PROJECT MANAGEMENT BODY OF KNOWLEDGE (PMBOK GUIDE ) Sixth edition Chapter 7 Project Cost Management PMBOK is a registered mark of the Project Management Institute, Inc Slide # 1 3FOLD Education

More information

[Project Name] Monthly Performance Report for mmm/yyyy. [Sub-Project, phase, etc.] [Company] [Company Address] Marc Arnecke, PMP

[Project Name] Monthly Performance Report for mmm/yyyy. [Sub-Project, phase, etc.] [Company] [Company Address] Marc Arnecke, PMP This template is downloaded from project-management.magt.biz [Company] [Company Address] Tel: Fax: [Company Phone] [Company Fax] [Company E-mail] May 19, 2015 [Ref. number] Marc Arnecke, PMP [Sub-Project,

More information

Earned Value Management Guide

Earned Value Management Guide 1 Earned Value Management Guide Earned Value Management (EVM) is a project management technique that objectively tracks physical accomplishment of work. More elaborately: EVM is used to track the progress

More information

GPE engineering project management. Project Management in an Engineering Context

GPE engineering project management. Project Management in an Engineering Context GPE engineering project management Project Management in an Engineering Context Earned Value Management System Is a system to MANAGE --- and help resolve control problems in running projects difficulties

More information

Application of Earned Value Analysis in Analysing Project Performance

Application of Earned Value Analysis in Analysing Project Performance Application of Earned Value Analysis in Analysing Project Performance Shyama Salikuma P.G Student (Structural Engg & CM) Dept. of Civil Engg, IIET Nellikuzhy, Kothamangalam Ms. Minu Anna Johny Assistant

More information

SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2016

SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2016 All Rights Reserved No. of Pages - 10 No of Questions - 06 SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2016 MGT 30725 Project

More information

IP-CIS : CIS Project Management

IP-CIS : CIS Project Management Meltem Özturan www.mis.boun.edu.tr/ozturan/mis301 1 Project Management Tools and Techniques (PMTT) Feasibility Analysis Organizational Breakdown Structure Work Breakdown Structure Scheduling Earned Value

More information

Project Management. Mark McKinnon Project Manager

Project Management. Mark McKinnon Project Manager Project Management Mark McKinnon Project Manager Outline General management Staffing Risk management and contingency Earned value and performance metrics Descope options Management: Cost & Scope Control

More information

Department of Industrial Engineering

Department of Industrial Engineering Department of Industrial Engineering Engineering Project Management Presented By Dr. Abed Schokry Chapter 15: Cost Control Learning Outcomes After completing this chapter students should be able to: Define

More information

Earned Value Management. Danielle Kellogg. Hodges University

Earned Value Management. Danielle Kellogg. Hodges University Earned Value Management 1 EARNED VALUE MANAGEMENT Earned Value Management Danielle Kellogg Hodges University Earned Value Management 2 Abstract Earned Value Management has been used with enterprise-level

More information

Earned Value Formulae

Earned Value Formulae Earned Value Formulae This White Paper focuses on the basic values and formulae used in Earned Value calculations. Additional EV resources are available from https://mosaicprojects.com.au/pmki-sch.php

More information

INTRODUCING PROJECT COST MANAGEMENT EXERCISES & QUIZ. Introducing Project Cost Management Exercises & Quiz

INTRODUCING PROJECT COST MANAGEMENT EXERCISES & QUIZ. Introducing Project Cost Management Exercises & Quiz INTRODUCING PROJECT COST MANAGEMENT EXERCISES & QUIZ Introducing Project Cost Management Exercises & Quiz EXERCIS 1: Describe what activities are involved in resource planning EXERCIS 2: Answer the questions

More information

EVMi 101: EARNED VALUE MANAGEMENT FUNDAMENTALS

EVMi 101: EARNED VALUE MANAGEMENT FUNDAMENTALS EVMI - BUILDING & EDUCATING PROJECT STAFF MEMBERS WHO EXECUTE AND DELIVER PROJECTS & PROGRAMS SUCCESSFULLY ACROSS ALL INDUSTRIES EVMi 101: EARNED VALUE MANAGEMENT FUNDAMENTALS COURSE HIGHLIGHTS EVMI 101:

More information

Understanding the Differences. Accounting Practice for Measuring. Supertech Project Management

Understanding the Differences. Accounting Practice for Measuring. Supertech Project Management Understanding the Differences Between Earned Value and Accounting Practice for Measuring and Reporting Performance YOUR PRESENTER Roland Horat Managing Director Global Business, Substituting for James

More information

James A. Wrisley, President 9070 Lakes Blvd. West Palm Beach FL (561)

James A. Wrisley, President 9070 Lakes Blvd. West Palm Beach FL (561) Earned Value Management Results in Early Visibility and Management Opportunities March 21, 2007 James A. Wrisley, President 9070 Lakes Blvd. West Palm Beach FL 33412 (561) 694-1646 E-mail: wrisley@pmassoc.com

More information

Three Numbers to Measure Project Performance

Three Numbers to Measure Project Performance Dr. Thomas Liedtke Alcatel D 70435 Stuttgart (Germany) Peter Paetzold Alcatel D 70435 Stuttgart (Germany) e_mail: TLiedtke@alcatel.de phone: +49 711 821 40346 fax.: +49 711 821 42230 e_mail: Peter.Paetzold@alcatel.de

More information

Predicting Project Completion Date Using Earned Value Management

Predicting Project Completion Date Using Earned Value Management Predicting Project Completion Date Using Earned Value Management A New Tradition in EVM Analysis! AACE International 2009 Spring Symposium February 28 Long Beach, CA Ray W. Stratton, PMP, EVP 714-318-2231

More information

Jefferson Science Associates, LLC. 900 Glossary. Project Control System Manual Revision 7

Jefferson Science Associates, LLC. 900 Glossary. Project Control System Manual Revision 7 Jefferson Science Associates, LLC 900 Glossary Project Control System Manual Revision 7 900 Glossary Actual Cost of Work Performed (ACWP) The direct costs incurred in accomplishing the project work activities,

More information

europe GENEVA 2009 Haute école de gestion de Genève Geneva School of Business Administration EVA Europe 2009 was jointly organised by Gold Sponsors

europe GENEVA 2009 Haute école de gestion de Genève Geneva School of Business Administration EVA Europe 2009 was jointly organised by Gold Sponsors eva europe GENEVA 2009 2009, CERN, HEG, Authors - This material is provided courtesy of EVA Europe 2009, the European organisation for nuclear research(cern), the Geneva School of Business administration

More information

ANALYZE THIS! EARNED VALUE MANAGEMENT CONCEPTS AND ADVANCED FORECASTING?

ANALYZE THIS! EARNED VALUE MANAGEMENT CONCEPTS AND ADVANCED FORECASTING? ANALYZE THIS! EARNED VALUE MANAGEMENT CONCEPTS AND ADVANCED FORECASTING? KANSAS CITY CHAPTER PMI PROFESSIONAL DEVELOPMENT DAYS SEPTEMBER 2012 Glenn Meyer (c) Glenn Meyer, except as noted. 10 Sep 2012 1

More information

Introduction to Project Management. Modeling after NYS ITS

Introduction to Project Management. Modeling after NYS ITS Introduction to Project Management Modeling after NYS ITS What is Project Management? Project management is the application of knowledge, skills, tools and techniques to project activities to meet project

More information

Project Performance Evaluation By Earned Value Method

Project Performance Evaluation By Earned Value Method Project Performance Evaluation By Earned Value Method Antony Prasanth M A #, K Thirumalai Raja * # Department of Civil Engineering, EBETi Kangayam, Thirupur Dist, Thamilnadu, Anna University Chennai *

More information

Analysis of Estimate at Completion of a Project's duration to improve Earned Value Management System 1 N.Vignesh

Analysis of Estimate at Completion of a Project's duration to improve Earned Value Management System 1 N.Vignesh Analysis of Estimate at Completion of a Project's duration to improve Earned Value Management System 1 N.Vignesh 2 S.Sowmya 1. Research Associate, Indian Institute of Management Ahmedabad, 2. SDE, ACS

More information

Professional Development Seminar Series

Professional Development Seminar Series Professional Development Seminar Series Feb, 2019 2019. All rights reserved. online@3foldtraining.com. www.pmexamstudy.com. www.3foldtraining.com. PMP Exam Review Agenda Introduction to Definition Context

More information

Formula SAE Cost Report. Dalhousie University Formula SAE Michigan 2012 Car # 47

Formula SAE Cost Report. Dalhousie University Formula SAE Michigan 2012 Car # 47 Formula SAE Report Dalhousie University Formula SAE Michigan 2012 Car # 47 Summary Dalhousie University Car # 47 Area Totals: Brake System Engine & Drivetrain Frame & Body Electrical Miscellaneous, Fit

More information

Lecture 3: Project Management, Part 2: Verification and Validation, Project Tracking, and Post Performance Analysis

Lecture 3: Project Management, Part 2: Verification and Validation, Project Tracking, and Post Performance Analysis Lecture 3: Project Management, Part 2: Verification and Validation, Project Tracking, and Post Performance Analysis Prof. Shervin Shirmohammadi SITE, University of Ottawa Prof. Shervin Shirmohammadi ELG

More information

Lecture 3: Project Management, Part 2: Verification and Validation, Project Tracking, and Post Performance Analysis

Lecture 3: Project Management, Part 2: Verification and Validation, Project Tracking, and Post Performance Analysis Lecture 3: Project Management, Part 2: Verification and Validation, Project Tracking, and Post Performance Analysis Prof. Shervin Shirmohammadi SITE, University of Ottawa Prof. Shervin Shirmohammadi ELG

More information

PROJECT BY PROJECT MANAGEMENT T OOLS

PROJECT BY PROJECT MANAGEMENT T OOLS Earned Schedule Tejas Sura Joint M.D., Conart Engineers Limited V.P.-President President PMI Mumbai Chapter We are here to know HOW TO GUIDE OUR PROJECT BY PROJECT MANAGEMENT TOOLS Project Monitoring Monitoring

More information

THE VALUE OF EARNED VALUE MANAGEMENT

THE VALUE OF EARNED VALUE MANAGEMENT THE VALUE OF EARNED VALUE MANAGEMENT PMI Pittsburgh Chapter Meeting February 8, 2001 Marilyn McCauley McManagement Group 703-455-0602 703-455-0598 (f) McMgtGrp@aol.com AGENDA Twelve Reasons Why Programs

More information

The Four Pillars of project management

The Four Pillars of project management The Four Pillars of project management Background This article is intended to give a round up of key practical project management practices to the novice as well as to the experienced. About 90% of this

More information

CARE FOR YOUR VEHICLE

CARE FOR YOUR VEHICLE FINANCIAL SERVICES CARE FOR YOUR VEHICLE MAKING VEHICLE CARE POSSIBLE CARING FOR YOUR VEHICLE Hyundai cares about your vehicle as much as you do. We want to make sure that every moment you spend in your

More information

Dealer Warranty Plan Standard Cover

Dealer Warranty Plan Standard Cover Dealer Warranty Plan Standard Cover Choose from 3, 6, 12 or 24 Month Warranties Cover Vehicles up to 15 years & 150,000 Miles (at start of cover) Claims Limit up to Purchase Price of Vehicle Version WA-SD070618

More information

Boise State University. Request for Quote RFQ CF passenger 4x4 Utility Vehicle

Boise State University. Request for Quote RFQ CF passenger 4x4 Utility Vehicle Boise State University Request for Quote RFQ CF17-084 2-passenger 4x4 Utility Vehicle Schedule of Events RFQ issue date Feb. 23, 2017 RFQ closing date Mar. 03, 2017 5:00 PM Product 1 each Kubota RTV-X900

More information

CPM (College of Performance Management) Meetings have focused on this topic in the last year

CPM (College of Performance Management) Meetings have focused on this topic in the last year June 13, 2016 1 PMI - (PMI-ACP Exam tests using EVM with Agile) PMI: EVM should be used on all projects, in all industries, no matter how simple or complex Federal Government is asking for the two approaches

More information

What is Earned Value Analysis?

What is Earned Value Analysis? What is Earned Value Analysis? 1 Earned Value Performance Measurement Time now Budget Cost Actual Good News or Bad? Time 2 Starting point Recording Progress The Plan is in place and work has started, so

More information

Project Control. Ongoing effort to keep your project on track Prerequisite to good control is a good plan Four primary activities:

Project Control. Ongoing effort to keep your project on track Prerequisite to good control is a good plan Four primary activities: Project Control 1 Project Control Ongoing effort to keep your project on track Prerequisite to good control is a good plan Four primary activities: 1. Planning performance Software Development Plan, schedule,

More information

Earned Value Management An Overview March 2014

Earned Value Management An Overview March 2014 Earned Value Management An Overview March 2014 SAVE International Cascadia Chapter Introduction What is Earned Value? Why is Earned Value important? What is required? Earned Value Definitions & Process

More information

A Case for Project Revenue Management. Peter Varani PMP

A Case for Project Revenue Management. Peter Varani PMP A Case for Project Revenue Management Peter Varani PMP A Case for Project Revenue Management PMBOK GUIDE (4 th edition) Cost 845 Revenue 3 Unisys Annual Report (2008) Cost 174 Revenue 152 2 Balanced Approach

More information

Earned Value Management

Earned Value Management Earned Value Management Reading the Roadmap to Project Success (or, Are We There Yet?) Steve Margolis, PMP, CISSP smargolis@us.ibm.com September 5, 2018 Overview EVM Background EVM Basics and Standards

More information

SECTION 7 WARRANTY REQUIREMENTS

SECTION 7 WARRANTY REQUIREMENTS SECTION 7 WARRANTY REQUIREMENTS Initial Issue SECTION 7: WARRANTY REQUIREMENTS... 1 WR 1. Warranty Provisions... 1 WR 1.1 Basic Provisions... 1 WR 1.1.1 Warranty Requirements...1 WR 1.1.1.1 Contractor

More information

Project health monitoring by Earned Value Analysis

Project health monitoring by Earned Value Analysis 13th International Software Testing Conference (STC 2013) December 0-06, 2013 in Bangalore, India. Project health monitoring by Earned Value Analysis Gangadhar. B. Kallur Honeywell Technology Solutions,

More information

DEFENSE ACQUISITION UNIVERSITY EMPLOYEE SELF-ASSESSMENT. Outcomes and Enablers

DEFENSE ACQUISITION UNIVERSITY EMPLOYEE SELF-ASSESSMENT. Outcomes and Enablers 1 Recognize key concepts about Earned Value as an integrated program management tool that integrates cost, schedule, and technical performance Recognize that Earned Value is a management tool that program

More information

Planning, Scheduling and Tracking Of Ongoing Bridge Construction Project Using Primavera Software and EVM Technique

Planning, Scheduling and Tracking Of Ongoing Bridge Construction Project Using Primavera Software and EVM Technique Planning, Scheduling and Tracking Of Ongoing Bridge Construction Project Using Primavera Software and EVM Technique Suvarna P 1 Research Scholar, School of Civil Engineering, REVA University, Bengaluru,

More information

Vendor: PMI. Exam Code: CA Exam Name: Certified Associate in Project Management. Version: Demo

Vendor: PMI. Exam Code: CA Exam Name: Certified Associate in Project Management. Version: Demo Vendor: PMI Exam Code: CA0-001 Exam Name: Certified Associate in Project Management Version: Demo QUESTION: 1 On what is project baseline development established? A. Approved product requirements B. Estimated

More information

Running head: VALUE ANALYSIS REPORTING 1

Running head: VALUE ANALYSIS REPORTING 1 Running head: VALUE ANALYSIS REPORTING 1 Value Analysis Reporting Benjamin Srock Embry-Riddle Aeronautical University Worldwide Campus Effective Communication for Managing Projects PMGT-502 Ki-Young Jeong,

More information

Presenting Earned Value

Presenting Earned Value Successfully Presenting Earned Value Your guide to Earned Value Management What is Earned Value Management? Earned Value Management (EVM) is a project management system which combines schedule performance

More information

Administration. Course Aim. Introductions

Administration. Course Aim. Introductions Practical Application of Earned Value Performance Measurement presented by Paul E Harris of Eastwood Harris Pty Ltd Copyright Copyright 2010 by Eastwood Harris Pty Ltd. No part of this publication may

More information

Optimization on Earned Value Method Combined with Critical Path

Optimization on Earned Value Method Combined with Critical Path Optimization on Earned Value Method Combined with Critical Path Qi-bin Zheng and Xing Bi Abstract When calculating the schedule performance using the traditional earned value method, the earned value in

More information

Pre-Owned Mechanical Breakdown Warranty

Pre-Owned Mechanical Breakdown Warranty Pre-Owned Mechanical Breakdown Warranty Terms & Conditions always there always a pleasure Pre-Owned Mechanical Breakdown Warranty This product provides you with a mechanical and/or electrical breakdown

More information

Financial Management & Accounting in Construction (CUE304) FINANCIAL MANAGEMENT. Dr. Ahmed Elyamany

Financial Management & Accounting in Construction (CUE304) FINANCIAL MANAGEMENT. Dr. Ahmed Elyamany 1 Financial Management & Accounting in Construction (CUE304) FINANCIAL MANAGEMENT Dr. Ahmed Elyamany 2 Course Content Project financial management: Cash flow prediction, Cash flow analysis, Cost of finance

More information

EVM WITHOUT QUALITY IS UNSUITABLE FOR SOFTWARE PROJECT & PROGRAM MANAGEMENT

EVM WITHOUT QUALITY IS UNSUITABLE FOR SOFTWARE PROJECT & PROGRAM MANAGEMENT EVM WITHOUT QUALITY IS UNSUITABLE FOR SOFTWARE PROJECT & PROGRAM MANAGEMENT Ms. Vanshika T 1, Dr. Poonam Sinha 2, Ms. Rachna Kulhare 3 1Department of I T, UIT, BU Bhopal 2 Professor, Department of Electronics,

More information

Monitoring System For Project Cost Control In Construction Industry

Monitoring System For Project Cost Control In Construction Industry Monitoring System For Project Cost Control In Construction Industry Pramod M *, K. Phaniraj **, V. Srinivasan *** * Post graduate student: Construction Engineering and Management, Manipal Institute of

More information

***EMERGENCY ROADSIDE ASSISTANCE Call toll-free ***

***EMERGENCY ROADSIDE ASSISTANCE Call toll-free *** EXTENDED SERVICE CONTRACT ALPHA WARRANTY SERVICES, INC 12256 South 900 East #403A Draper, Utah 84020 Phone 800-662-5519 Fax 801-571-8964 ***EMERGENCY ROADSIDE ASSISTANCE Call toll-free 1-800-451-0459***

More information

Project Management: Cost

Project Management: Cost Project Management: Cost Cost Management the processes required to ensure that a project is completed within the approved budget Estimating cost of resources Forecasting: quantity when they are required

More information

Caring for your Vehicle

Caring for your Vehicle Renault CARE Caring for your Vehicle Renault cares about your vehicle - just as much as you do. We want to make sure that every time you drive your Renault, you look forward to the next time. This booklet

More information

Leading F&I Provider Committed to Delivering Quality Products and Services

Leading F&I Provider Committed to Delivering Quality Products and Services Guaranteed Asset Protection (GAP) Waiver Leading F&I Provider Committed to Delivering Quality Products and Services COMPREHENSIVE SUITE OF PRODUCTS that meets your customers needs Vehicle Service Contracts

More information

pm4dev, 2015 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS

pm4dev, 2015 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS pm4dev, 2015 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage development

More information

Project KPIs and Dashboards Research and Implementation in MS Project

Project KPIs and Dashboards Research and Implementation in MS Project University of Piraeus Department of Industrial Management and Technology Postgraduate Program in Project Management and Product Development Project KPIs and Dashboards Research and Implementation in MS

More information

Detailed Project Scheduling and Cost Management

Detailed Project Scheduling and Cost Management Detailed Project Scheduling and Cost Management A Case Study on Dhaaruni Commercial Complex Bengaluru Lathan B.S 1, Dr.Srinath Shetty.K 2 1 P.G Student, 2 Professor & Head Civil Engineering NMAM Institute

More information

Mounting possibilities 300 plus

Mounting possibilities 300 plus 300 plus Mounting possibilities 300 plus 345 plus 360 plus 375 plus 390 plus 8100, 8200, 8300, 8400, 8500 8100, 8200, 8300, 8400, 8500 8300, 8400, 8500 8400, 8500 8600, 8700, 8800 8600, 8700, 8800 8600,

More information

Cost Management Mock Exam. Lab for PMP Exam Prep Course Part 2 #347 Instructor: Neal L. Rowland, PMP

Cost Management Mock Exam. Lab for PMP Exam Prep Course Part 2 #347 Instructor: Neal L. Rowland, PMP Cost Management Mock Exam Lab for PMP Exam Prep Course Part 2 #347 Instructor: Neal L. Rowland, PMP 10 Practice Questions Move at Your Own Pace Question 1 You are project manager for a $2.3M project that

More information

Chapter 11 Project Execution and Control

Chapter 11 Project Execution and Control Chapter 11 Project Execution and Control Project Management for Business, Engineering, and Technology Prepared by John Nicholas, Ph.D. Loyola University Chicago Phase C: Project Execution Most projects

More information

PMP Exam Preparation Workshop Chapter 7 Project Cost Management

PMP Exam Preparation Workshop Chapter 7 Project Cost Management PMP Exam Preparation Workshop Chapter 7 Project Cost Management 1 Learning Objectives By the end of this session, you should understand: Importance of cost management for the success of a project Cost

More information

Earned Value Management Handbook. arne. alu

Earned Value Management Handbook. arne. alu Earned Value Management Handbook arne alu March 2013 Table of contents Contents 1 Introduction 7 2 Overview 8 3 Definition 39 4 Planning 57 5 Data collection 77 6 Analysis, review and action 80 7 Change

More information

Insurer Directed Poor Quality Unsafe Repair Subaru Impreza

Insurer Directed Poor Quality Unsafe Repair Subaru Impreza Insurer Directed Poor Quality Unsafe Repair 2007 Subaru Impreza The vehicle in this presentation was directed by The Insurance Company to one of their DRP shops. The vehicle had only 329 miles on the odometer

More information

QUALITY CONTROL PROCESS

QUALITY CONTROL PROCESS 1.0 SCOPE The Enterprise Project Management Office (EPMO) established overarching Quality Policy, Quality Objectives in the 0100-0100-005-QMS EPMO QUALITY MANUAL. This procedure defines specific EPMO Information

More information

Project Controls Expo 16 th Nov 2016

Project Controls Expo 16 th Nov 2016 Project Controls Expo 16 th Nov 2016 Emirates Stadium, London Introduction to Planning, Scheduling and Earned Value followed by Case Study on Data Analytics on improved Schedule Data Quality Tushar Tohan

More information

The Value of EVM. Earned Value Management

The Value of EVM. Earned Value Management The Value of EVM Earned Value Management Good decisions are based on knowledge and not on numbers. - Plato What is EVM? A project management technique for measuring project performance and progress, in

More information

TRACKING AND MANAGEMENT OF CONSTRUCTION PROJECTS USING PRIMAVERA

TRACKING AND MANAGEMENT OF CONSTRUCTION PROJECTS USING PRIMAVERA TRACKING AND MANAGEMENT OF CONSTRUCTION PROJECTS USING PRIMAVERA Suchithra L 1, Anne Ligoria S 2 1PG Student, Department of Civil Engineering, Jerusalem College of Engineering, Tamil Nadu, India 2Professor

More information

Earned Value Management System. a system to

Earned Value Management System. a system to Earned Value Management System a system to MANAGE - - - and help resolve control problems in running projects difficul7es to have an overall visibility of risks; a lack of understanding of all the interdependencies

More information

EVMS Fundamentals v.7.0. (Part 2 of 2) Slides and Notes

EVMS Fundamentals v.7.0. (Part 2 of 2) Slides and Notes EVMS Fundamentals v.7.0 (Part 2 of 2) Slides and Notes Course Outline Incorporating Actual Costs 07A. Types of Actual Cost 07B. Direct and Indirect Costs 07C. Applying Indirect Costs Earned Value Basics

More information

Pinnacle PINNACLE PROTECTION PLAN

Pinnacle PINNACLE PROTECTION PLAN Administered by: MPP CO., INC. PINNACLE PROTECTION PLAN In Florida, Administered by: OLD UNITED CASUALTY CO. (Florida License # 03041) P.O. Box 634 P.O. Box 795 Shawnee Mission, Kansas 66201 Shawnee Mission,

More information

Study on Construction Project Cost Control Based on Lean Construction Thought Anning Liu, Xingzhen Ren, Yihao Xu, Xuefeng Chen

Study on Construction Project Cost Control Based on Lean Construction Thought Anning Liu, Xingzhen Ren, Yihao Xu, Xuefeng Chen 2nd International Conference on Education, Management and Information Technology (ICEMIT 2015) Study on Construction Project Cost Control Based on ean Construction Thought Anning iu, Xingzhen Ren, Yihao

More information

EARNED VALUE FEASIBILITY ANALYSIS FOR SOUTH GUJARAT REGION TO ENHANCE PROJECT PERFORMANCE

EARNED VALUE FEASIBILITY ANALYSIS FOR SOUTH GUJARAT REGION TO ENHANCE PROJECT PERFORMANCE EARNED VALUE FEASIBILITY ANALYSIS FOR SOUTH GUJARAT REGION TO ENHANCE PROJECT PERFORMANCE Mr. Divyesh Joshi 1, Mr. Vyom B. Pathak 2, Ms. Neetu B. Yadav 3 M.E. Student, Civil Eng. Dept., SNPIT &RC, Umrakh

More information

PMI - Dallas Chapter. Sample Questions. March 22, 2002

PMI - Dallas Chapter. Sample Questions. March 22, 2002 PMI - Dallas Chapter PMP Exam Sample Questions March 22, 2002 Disclaimer: These questions are intended for study purposes only. Success on these questions is not necessarily predictive of success on the

More information

CAPM Exam Prep.

CAPM Exam Prep. CAPM Exam Prep (What it really takes to prepare and pass) An ebook by Project Road Training, LLC www.project-road.com Bill Baxter Version 6-1 Project Road Training, LLC has been reviewed and approved as

More information