1 B O A R D S T A T U S R E P O R T DECEMBER 18, 2018 I. BIDS A. Invitation for Bids. Benson Avenue Stormwater Improvement Project. Bids Opening December 19, 2018 II. PURCHASING A. BLUE CROSS & BLUE SHIELD OF GA, INC. $26, Change order request approved to increase purchase order by $26, for the Authority s employees health care program for a 12-month period from January 1, 2018 to December 31, 2018 for a new purchase order total $1,498, The increase is due to the number of employees who have signed up for our insurance compared to last year. B. EAST ELECTRICAL CONTRACTORS, INC. $28, Purchase order issued to East Electrical Contractors, Inc. in the amount of $28, for emergency valve pit electrical repairs performed at the Sweetwater Creek Sidestream Plant. III. CONTRACTED PROJECT CONSTRUCTION Page 1 of 11 A. 36-Inch Pipeline Construction Approved Purchase Order (Excluding C.O.) $50, Adjusted Purchase Order (including C.O.) $50, Balance Remaining on Adjusted Contract Price $50, No projects at this time. B. 30-Inch Pipeline Construction Approved Purchase Order (Excluding C.O.) $50, Adjusted Purchase Order (including C.O.) $50,000.00
2 Balance Remaining on Adjusted Contract Price $50, No projects at this time. C. 20-Inch & 24-Inch Pipeline Construction Approved Purchase Order (Excluding C.O.) $50, Adjusted Purchase Order (including C.O.) $50, Balance Remaining on Adjusted Contract Price $50, No projects at this time. D. 16-Inch Pipeline Construction Approved Purchase Order (Excluding C.O.) $222, Adjusted Purchase Order (including C.O.) $222, Balance Remaining on Adjusted Contract Price $222, Thornton Road Water Line Extension Estimated Project Cost $172, Amount Paid to Date $ 11, Estimated Cost to Complete Project $161, % Paid of Estimated Cost to Date 6% % Overall Project Completed 10% This project includes extending approximately 2,700 linear feet of 16 water main down Thornton Road from Factory Shoals Road. Construction of the project is under way, and the project should be completed by March 31, E. 12-Inch Pipeline Construction Page 2 of 11
3 Approved Purchase Order (Excluding C.O.) $35, Adjusted Purchase Order (including C.O.) $35, Balance Remaining on Adjusted Contract Price $35, No projects at this time. F. 8-Inch Pipeline Construction (2016 Annual Contract) Contractor: RDJE, Inc. 679 Hwy. 29 South Newnan, GA Approved Purchase Order (Excluding C.O.) $160, Change Orders (C.O.) $ 75, Adjusted Purchase Order (including C.O.) $236, Approved Payments on Contract to Date $236, Balance Remaining on Adjusted Contract Price $ 0.00 Hwy. 78 at Mann Road Water Line Relocation Project Estimated Project Cost $208, Amount Paid to Date $208, Estimated Cost to Complete Project $ 0.00 % Paid of Estimated Cost to Date 100% % Overall Project Completed 100% WSA s planned water line relocation work on this project is complete. GDOT s contractor is continuing work on the intersection improvement project, which may necessitate additional unexpected work on WSA s part. G. 8-Inch Pipeline Construction Approved Purchase Order (Excluding C.O.) $1,232, Adjusted Purchase Order (including C.O.) $1,232, Balance Remaining on Adjusted Contract Price $1,232, Chestnut Log Phase II Water Line Replacement Project Estimated Project Cost $875, Amount Paid to Dated $ 35, Estimated Cost to Complete Project $840, Page 3 of 11
4 Page 4 of 11 % Paid of Estimated Cost to Date 4% % Overall Project Completed 4% This project includes installation of approximately 8,900 LF of 8-inch ductile iron pipe for the replacement of 6-inch and 2- inch waterlines. WSA has requested the contractor to delay this project until completion of the Thornton Road water line extension. Rolling Hills Phase 1 Water Line Replacement Project Estimated Project Cost $735, Amount Paid to Date $319, Estimated Cost to Complete Project $416, % Paid of Estimated Cost to Complete Project 43% % Overall Project Completed 100% This project is complete H. 2-Inch Pipeline Construction Contractor: RDJE, Inc. 679 Hwy. 29 South Newnan, GA Approved Purchase Order (Excluding C.O.) $111, Change Order (C.O.) $ 0.00 Adjusted Purchase Order (including C.O.) $111, Balance Remaining on Adjusted Contract Price $111, Hwy. 92 Phase 4 Water Line Relocation Project Estimated Project Cost $ 76, Amount Paid to Date $ 0.00 Estimated Cost to Complete Project $ 76, % Paid of Estimated Cost to Date 0% % Overall Project Completed 0% GDOT s contractor is working on grading. WSA is coordinating with GDOT and their contractor regarding the start time of the water line relocation. I. AMR/AMI System Project Contractor: Itron, Inc N. Molter Road Liberty Lake, WA Approved Contract Price (Excluding C.O.) $6,348, Change Orders (C.O.) $ 920,574.08
5 Page 5 of 11 Adjusted Contract Price (including C.O.) $7,296, Approved Payments on Contract to Date $6,205, Balance Remaining on Adjusted Contract Price $1,090, % Paid on Contract to date 85% % Overall project completed 93% The read rate is 82.83% this month, which is up from 82.63% last month. Itron anticipates that our read rate should be 84% once the project is completed. This is 2% greater than their contractual obligation. Meter and endpoint installation crews have installed 33,889 meters and endpoints as of December 5, 2018, The crews began installation of the customer s side turn on/off valve on March 27, 2012 and have installed 30,780 valves to date. J. Bear Creek Water Treatment Plant and Dog River Intake 2 Painting Contractor: Llamas Coatings, Inc River View RD. S.E. Lawrenceville, GA Approved Contract Price (Excluding C.O.) $ 69, Change Orders (C.O.) $ 20, Adjusted Contract Price (including C.O.) $ 89, Approved Payments on Contract to Date $ 89, Balance Remaining on Adjusted Contract Price $ 0.00 % Paid on Contract to date 100% % Overall project completed 100% This project is complete K. South Sweetwater Road Stormwater Improvement Project Contractor: Site Engineering, Inc Best Friend Road Atlanta, GA Approved Contract Price (Excluding C.O.) $439, Adjusted Contract Price (including C.O.) $439, Approved Payments on Contract to Date $387, Balance Remaining on Adjusted Contract Price $ 51, % Paid on Contract to date 88% % Overall project completed 100% This project is complete. L. Chapel Hill Farms Drive Stormwater Improvement Project Contractor: The Corbett Group LLC 6535 Bankhead Highway Douglasville, GA 30134
6 Page 6 of 11 Approved Purchase Order (Excluding C.O.) $398, Adjusted Purchase Order (including C.O.) $398, Approved Payments on Contract to Date $370, Balance Remaining on Adjusted Contract Price $ 27, % Paid on Contract to date 93% % Overall project completed 100% This project is complete M. Sewer System Master Plan Contractor: Barge Design Solution, Inc The Corners Parkway, Suite 450 Peachtree Corners, GA Approved Contract Price (Excluding C.O.) $493, Change Orders (C.O.) $ 19, Adjusted Contract Price (including C.O.) $513, Approved Payments on Contract to Date $172, Balance Remaining on Adjusted Contract Price $340, % Paid on Contract to date 34% % Overall Project Completed 40% This project includes the preparation of a sewer system master plan, which will evaluate WSA s sewer system for existing and future capacity, develop a hydraulic model of the system, and make recommendations for improvements to the system. This project is expected to be complete by September 30, N. Northside Wastewater Treatment Plant Paving Project Contractor: Magnum Paving, LLC Carrollton Villa Rica Highway, Suite 209 Villa Rica, GA Approved Purchase Order (Excluding C.O.) $ 98, Change Orders (C.O.) $ 18, Adjusted Purchase Order (including C.O.) $116, Balance Remaining on Adjusted Contract Price $116, % Paid on Contract to date 0% % Overall project completed 25% This project includes repaving of asphalt driveway and parking surfaces at the Northside WWTP. The Project is underway and is expected to be complete by December 31, A change order has been executed to add a Permaflex asphalt layer to prolong the life of the replacement asphalt.
7 Page 7 of 11 O. South Central Wastewater Treatment Plant Equalization Tank Refinishing Project Contractor: Llamas Coatings, Inc River View RD. S.E. Atlanta, GA Approved Purchase Order (Excluding C.O.) $142, Adjusted Purchase Order (including C.O.) $142, Balance Remaining on Adjusted Contract Price $142, % Paid on Contract to date 0% % Overall project completed 0% This project includes removal of existing surface coating, subsequent concrete refinishing and application of cementitious concrete coating of the equalization tank at the South Central Wastewater Treatment Plant. Work is anticipated to begin this month and be complete by February 28, P. Andy Mountain Tank Rehabilitation Project Contractor: Utility Service Co. Inc 535 Courtney Hodges Blvd Perry, GA Approved Contract Price (Excluding C.O.) $246, Adjusted Contract Price (including C.O.) $246, Balance Remaining on Adjusted Contract Price $246, % Paid on Contract to date 0% % Overall project completed 15% This project includes reconditioning the 2,000,000-gallon water tank, including sandblasting the interior surface, pressurewashing the exterior surface, re-coating all surfaces, and making miscellaneous repairs. The project is expected to be complete by March 1, Q. Nations Drive Stormwater Improvement Project Contractor: CMES, Inc McDonough Dr. NW Norcross, GA Approved Contract Price (Excluding C.O.) $258, Adjusted Contract Price (including C.O.) $258,361.00
8 Balance Remaining on Adjusted Contract Price $258, % Paid on Contract to date 0% % Overall project completed 5% This project includes replacement of 30-inch and 36-inch corrugated metal pipes at the intersection of Nations Drive and Redwood Drive with 42-inch and 48-inch reinforced concrete pipe. This project is under construction and expected to be complete by February 4, R Sewer Manhole Rehabilitation Project Contractor: RDJE, Inc. 679 Hwy. 29 South Newnan, GA Approved Contract Price (Excluding C.O.) $ 80, Adjusted Contract Price (including C.O.) $ 80, Balance Remaining on Adjusted Contract Price $ 80, % Paid on Contract to date 0% % Overall project completed 0% This project includes the repair of 24 manholes in several locations by relining the interior surfaces with corrosion resistant materials. Notice to proceed was issued effective December 3, This project is scheduled to be completed by February 1, IV. DIVISIONAL STATUS REPORTS A. Water Operations 1. One of the Water Operations Division s Fiscal Year 2019 goals is to maintain direct water treatment costs below $1.05 per 1,000 gallons. For Fiscal Year 2019 (through October 2018), direct cost was $0.94 per 1,000 gallons. 2. From November 12, 2018 to December 9, 2018, the Bear Creek Water Treatment Plant operated at 49% of its capacity. B. Wastewater Operations 1. One of the Wastewater Operations Division s Fiscal Year 2019 goals is to maintain the average direct wastewater treatment costs below $1.80 per 1,000 gallons. For Fiscal Year 2019 (through October 2018), the average direct costs were $1.61 per 1,000 gallons. Page 8 of 11
9 C. Maintenance 1. During the period of November 11, 2018 to December 10, 2018, the Maintenance group completed 386 service orders (goal is 600). There are currently 542 open service orders in the work order system (goal is under 550) assigned to Maintenance. 2. The sewer crews responded to eight sewer back-ups. Four were on the customer s side and four on WSA s side. One reported damage at 3817 Paul Street where the main backed up due to rock and debris in the main. All repairs have been made. 3. The Leak Detection Crew surveyed 68,732 feet (monthly goal is 88,000 feet) of water line on Kings Highway, Stewart Mill Road, Yeager Road, and North Quail Drive. One main leak, two fire hydrant leaks, and five water service line leaks were found with an estimated water loss of 23,040 gallons per day. All repairs have been made. This crew has been assisting the I&I crew due to short staffing. 4. The I&I Crew inspected and mapped 172 manholes, smoke tested 20,621 feet and surveyed 12,162 feet of line using the SLRAT assessment tool in the Sweetwater Basin. This crew has been assisting the leak detection crew due to short staffing. Nine new easement encroachments were documented this month. To date, 682 encroachments have been identified and 418 have been closed out. 5. The TV Crew televised 4,298 feet of sanitary sewer in the Sweetwater Basin and surveyed 31,303 feet of line with the SLRAT at assessment tool. 6. The Vac Truck assigned to lift stations was used to pressure wash and vacuum 36 lift stations (goal is 30). 7. The Vac Truck crew assigned to sanitary sewer mains was used to clean 5,209 feet of sewer lines in the Sweetwater Basin. This crew assisted in cleaning Rebel Trails Wastewater Treatment Plant aeration basin and in completing a main repair on Strickland Street. 8. Right-of-way crews cleared 12,300 feet of right-of-way in the Sweetwater Basin. Driveways were repaired at the lift stations at Tributary, Leisure Acres, and Ashley Falls. The fence perimeter was cleared at Sweetwater Creek Wastewater Treatment Plant and a sewer main creek crossing sag was repaired in Stone Creek subdivision. This sag was the cause of the previously reported sewer spill on October 3, The Manhole Repair Crew rehabbed 14 manholes in the Sweetwater basin. This crew also assisted the ARV Crew due to short staffing. Page 9 of 11
10 Page 10 of The Air Release Valve (ARV) crew inspected 30 ARV s, replaced seven ARV s and cleaned five. Four buried ARV S were located and on odor control unit was serviced. 11. Due to manning shortages in the water department, the Valve and Hydrant Crew has been assisting with leak repairs. D. Construction 1. All construction crews are continuing to install new meters for the AMR/AMI project. E. Stormwater 1. A new Municipal Separate Storm Sewer System (MS4) permit was issued by the Georgia Environmental Protection Division (EPD) on December 6, This permit supersedes the previous MS4 permit and Stormwater Management Plan (SWMP) under which WSA has been operating. WSA submitted a Notice of Intent to obtain a coverage under the permit on October 25, Per MS4 permit requirements, WSA submitted a new SWMP to EPD on June 4, 2018 and is awaiting comments or approval from EPD. 2. WSA submitted grant applications to GEMA on October 28, 2016 on eight residential structures to determine if they qualify for grant funding. For properties that qualify, WSA will offer to purchase the properties based on their tax assessed values. If the property owners elect to sell, WSA will purchase the properties and demolish the structures to permanently remove them from the floodplain. GEMA completed evaluation of the application, determined they are complete, and forwarded them to FEMA for final approval. GEMA has indicated FEMA anticipates awarding the grant October 2018, but WSA has not yet received award from FEMA. F. General Services 1. Authority employees raised $2, for the 2018 Jeans-4-a-Cause charity, West Georgia Elves. 2. The Authority s Human Resources department was awarded the Medium Agency Achievement Award for Outstanding Contribution in the Field of Human Resource Management by the Georgia Local Government Personnel Association. G. Public Relations 1. On November 28 th, a special needs class from Douglas County School toured the Bear Creek Water Treatment Plant. 2. On December 5 th, WSA hosted a group of teachers and counselors from the CTAE (Career, Technical, and Agricultural Education) Advisory Committee.
11 The group learned about the variety of career opportunities in the industry as well as different partnership ideas to get students interested in working in water. 3. WSA employees Robert Keehn, Chip Butts, and Lyndsey Sargent served as judges for the regional DECA (Distributed Education Clubs of America) competition held at the Douglasville conference center on December 11 th. H. Finance 1. Copies of the Authority s recently completed fiscal year-end June 30, 2018 Comprehensive Annual Financial Report (CAFR) have been sent to Sun Trust Bank and to the Standard and Poor s (S&P) rating agency. 2. Financial information for the year ended June 30, 2018 has been filed with Georgia Department of Community Affairs (DCA) and the authority registration for calendar year 2019 has been completed with DCA as required for every authority by Georgia State law. I. Dog River 1. The Recreational Complex closed to the public at the close of business on Saturday, November 17 th. Season pass holders will still be able to access the Complex during normal business hours. The Complex will reopen to the public on March 1 st, Page 11 of 11
B O A R D S T A T U S R E P O R T MAY 23, Bid Opening May 24, B. Invitation for Bids. Dawn Avenue Stormwater Improvement Project
B O A R D S T A T U S R E P O R T MAY 23, 2017 I. BIDS A. Invitation for Bids. Bear Creek Water Treatment Plant Laboratory Upgrades Bid Opening May 24, 2017 B. Invitation for Bids. Dawn Avenue Stormwater
More informationB O A R D S T A T U S R E P O R T. August 22, 2017 A. ALLAN VIGIL FORD LINCOLN, INC $22, B. ALLAN VIGIL FORD LINCOLN, INC $24,465.
B O A R D S T A T U S R E P O R T August 22, 2017 I. BIDS Nothing to Report II. PURCHASING A. ALLAN VIGIL FORD LINCOLN, INC $22,339.00 Purchase order issued to Allan Vigil Ford Lincoln, Inc. in the amount
More informationStephanie Smith, Project EngineerW
MEMORANDUM v TO: Paul Oehme, Director of Public Works/ City Engineer o FROM: Stephanie Smith, Project EngineerW 7700 Market Boulevard PO Box 147 Chanhassen, MN 55317 Administration Phone: 9522271100 Fax
More informationSTORMWATER MANAGEMENT FUND Department of Environmental Services
Department of Environmental Services Mission: To implement a comprehensive stormwater management program that balances the following goals: 1) to reduce the potential for stormwater threats to public health,
More informationCarroll County Maryland. Community Investment Plan Request Fiscal Years
Carroll County Maryland Community Investment Plan Request Fiscal Years 2019-2024 PRODUCED BY The Department of Management and Budget Ted Zaleski... Director Deborah Effingham... Chief, Bureau of Budget
More informationSTORMWATER MANAGEMENT FUND DEPARTMENT OF ENVIRONMENTAL SERVICES
DEPARTMENT OF ENVIRONMENTAL SERVICES Mission: To implement a comprehensive stormwater management program that balances the following goals: 1) to reduce the potential for stormwater threats to public health,
More informationSTORMWATER MANAGEMENT FUND Department of Environmental Services
Department of Environmental Services Mission: To implement a comprehensive stormwater management program that balances the following goals: 1) to reduce the potential for stormwater threats to public health,
More informationSTORMWATER MANAGEMENT FUND Department of Environmental Services
Department of Environmental Services Mission: To implement a comprehensive stormwater management program that balances the following goals: 1) to reduce the potential for stormwater threats to public health,
More informationMOUNTAIN HOUSE COMMUNITY SERVICES DISTRICT Providing Quality Services to the Community STAFF REPORT
MOUNTAIN HOUSE COMMUNITY SERVICES DISTRICT Providing Quality Services to the Community STAFF REPORT AGENDA TITLE: Approval of Amendments to Severn Trent Contract Extension MEETING DATE: September 9, 2015
More informationCITY OF RIVIERA BEACH, FLORIDA UTILITY SPECIAL DISTRICT S SYSTEMS AND OPERATIONS FOR FISCAL YEAR ENDING SEPTEMBER 30, 2010.
UTILITY SPECIAL DISTRICT S SYSTEMS AND OPERATIONS FOR FISCAL YEAR ENDING SEPTEMBER 30, 2010 Overview The service area of the Utility District s Water System includes the entire City of Riviera Beach (approximately
More informationDOUGLASVILLE-DOUGLAS COUNTY WATER AND SEWER AUTHORITY DOUGLAS COUNTY, GEORGIA
DOUGLASVILLE-DOUGLAS COUNTY WATER AND SEWER AUTHORITY DOUGLAS COUNTY, GEORGIA COMPREHENSIVE ANNUAL FINANCIAL REPORT FOR FISCAL YEARS ENDED JUNE 30, 2016 and 2015 DOUGLASVILLE-DOUGLAS COUNTY WATER AND
More informationpresents: PLANNING FOR THE FUTURE INFORMATIONAL OVERVIEW DETAILS PROVIDED BY:
presents: PLANNING FOR THE FUTURE INFORMATIONAL OVERVIEW www.springcreekud.org DETAILS PROVIDED BY: SPRING CREEK UTILITY DISTRICT Development & Infrastructure About Spring Creek Utility District Spring
More informationINDEX TO 2010 Resolutions
INDEX TO 2010 Resolutions Date Number Description Location / Notes 1/11/2010 18907 1/11/2010 18908 1/11/2010 18909 2/8/2010 18910 Approving expenditures related to 2010 Annual Water Rehab Projects prior
More informationRock Chalk Park - Infrastructure Report. July 2013
Rock Chalk Park Infrastructure Report July 2013 The following report is the first monthly report for the construction of infrastructure at Rock Chalk Park. The format follows the sections outlined in the
More informationINFRASTRUCTURE MANAGEMENT SERVICES. Making communities, associations and special districts stronger.
INFRASTRUCTURE MANAGEMENT SERVICES Making communities, associations and special districts stronger. A LEADER IN MANAGEMENT SERVICES Inframark Infrastructure Management Services is a team of proven professionals
More informationCITY OF TULSA WASTEWATER UNSEWERED AREAS & 5-YEAR CIP
CITY OF TULSA WASTEWATER UNSEWERED AREAS & 5-YEAR CIP TULSA CITY COUNCIL CAPITAL IMPROVEMENT PROGRAM TASK FORCE February 14, 2013 Definitions UNSEWERED AREA DEFINITIONS Unserved area Undeveloped area without
More informationLEBANON UTILITIES 2017 BUDGET - FINAL TABLE OF CONTENTS
LEBANON UTILITIES 2017 BUDGET - FINAL TABLE OF CONTENTS ELECTRIC: Cover Sheet Revenues Revenues/Expenses Revenues/Expenses - Notes Proposed Capital Additions - 2017 Proposed Capital Additions - 2017 through
More informationDoña Ana Mutual Domestic Water Consumers Association INFRASTRUCTURE CAPITAL IMPROVEMENT PLAN FY
Doña Ana Mutual Domestic Water Consumers Association INFRASTRUCTURE CAPITAL IMPROVEMENT PLAN FY 2020-2024 Infrastructure Capital Improvement Plan FY 2020-2024 ICIP for Dona Ana MDWCA Contact: Jennifer
More informationWastewater Rate Study. Villa Park, Illinois
Wastewater Rate Study Villa Park, Illinois June 2013 Executive Summary General The Village of Villa Park s Wastewater Utility is responsible for operation and maintenance of the Village s separate sanitary
More informationYear 2014 Engineer s Report regarding the Status of ownership, Working order and Condition of the Public Infrastructure.
Year 2014 Engineer s Report regarding the Status of ownership, Working order and Condition of the Public Infrastructure. Project: MEADOW PINES (AKA COBBLESTONE) PEMBROKE PINES, FL Prepared for: MEADOW
More informationPUBLIC WORKS DEPARTMENT
Departmental Summary FUND/ACTIVITY ACTUAL ADOPTED AMENDED RECOMM. General Fund: Revenue Administration 494,646 501,667 501,035 508,551 Municipal Trash Collection 101,185 60,358 60,358 60,962 Total Revenues
More informationCITY OF ROSEBURG, OREGON TABLE OF CONTENTS ENTERPRISE FUNDS
TABLE OF CONTENTS ENTERPRISE FUNDS Storm Drainage Fund... 121-124 Off Street Parking Fund... 125-126 Airport Fund... 127-131 Water Service Fund... 132-145 STORM DRAINAGE FUND CURRENT OPERATIONS This fund
More information2015 Financial Assurance 8/6/2015 Estimate Form (with pre-plat construction)
2015 Financial Assurance 8/6/2015 Estimate Form (with pre-plat construction) Project Information The Glen at Widefield Filing No. 9 PDD File: SF-185 9/25/2018 Project Name Section 1 - Grading and Erosion
More informationThis page intentionally left blank
197 This page intentionally left blank 198 Capital Improvement Program PROCEDURE Each year the Capital Improvement Program (CIP) is prepared from project requests submitted by the various departments.
More informationDerry Township Municipal Authority Wastewater Fund Budget
Derry Township Municipal Authority 2019 Wastewater Fund Budget APPROVED DTMA Board Resolution #2018-51 November 19, 2018 TABLE 1 OPERATING FUND Comparative Cash Budget (in thousands) Category / Item 2019
More informationAnnual Services Construction Contract (ASCC) #15 Project Number: PUCN
Annual Services Construction Contract (ASCC) #15 Project Number: PUCN-16-0023 Engineer's Estimate Inlet Construction, Inc. Peters & White Construction Inc. Worley Turf & Irrigation Inc. East West Construction
More informationCITY OF JOPLIN FY 2018 PROPOSED BUDGET
CITY OF JOPLIN FY 2018 PROPOSED BUDGET CITY OF JOPLIN ESTIMATE OF NEEDS PROJECTED FUND BALANCES FOR FISCAL YEAR 2017-2018 Audited Projected Projected Fund Projected 2016-2017 Activity Fund Projected 2017-2018
More informationPUBLIC WORKS DEPARTMENT Departmental Summary FUND/ACTIVITY ACTUAL ADOPTED AMENDED ADOPTED General Fund: Revenue Administration
Departmental Summary FUND/ACTIVITY ACTUAL ADOPTED AMENDED ADOPTED General Fund: Revenue Administration 494,751 453,181 494,253 501,667 Municipal Trash Collection 59,158 59,760 59,760 60,358 Total Revenues
More informationCapital Improvements Program FY FY2020
FY2016 - FY2020 CITY OF MANVEL, TEXAS April 25, 2016 prepared for: City of Manvel Mayor and Council 20025 Morris Avenue Manvel, Texas 77578 prepared by: 19701 Morris Avenue, Manvel, Texas 77578 TBPE F-9827
More informationCRESTVIEW WATER AND SANITATION DISTRICT FINANCIAL STATEMENTS DECEMBER 31, 2014
CRESTVIEW WATER AND SANITATION DISTRICT FINANCIAL STATEMENTS DECEMBER 31, 2014 CONTENTS Independent Auditors Report 2-3 Management s Discussion and Analysis 4-7 BASIC FINANCIAL STATEMENTS Statements of
More informationSTORMWATER ADVISORY GROUP August 26, 2009 Clarkston School District Admin Office 1294 Chestnut Street, Clarkston 5:30-7:30 p.m.
County of Asotin Regional Stormwater Program P.O. Box 160 135 2 nd Street Asotin, WA 99402 509-243-2071 Fax 509-243-2003 STORMWATER ADVISORY GROUP August 26, 2009 Clarkston School District Admin Office
More informationVILLAGE OF LIBERTYVILLE SPECIAL MEETING. Tuesday, March 6, 2018 Village Hall 118 W. Cook Avenue Libertyville, IL :00 p.m.
VILLAGE OF LIBERTYVILLE SPECIAL MEETING Tuesday, March 6, 2018 Village Hall 118 W. Cook Avenue Libertyville, IL 60048 6:00 p.m. 1) Roll Call 2) Continued Discussion of Draft 2018/2019 Budget 3) Executive
More informationWATER, WASTEWATER, STORMWATER, AND MUNICIPAL SOLID WASTE COST OF SERVICE AND RATE DESIGN STUDY
REPORT January 2017 WATER, WASTEWATER, STORMWATER, AND MUNICIPAL SOLID WASTE COST OF SERVICE AND RATE DESIGN STUDY PREPARED BY: ECONOMICS STRATEGY STAKEHOLDERS SUSTAINABILITY www.newgenstrategies.net 3420
More informationORANGE WATER AND SEWER AUTHORITY SCHEDULE OF RATES, FEES, AND CHARGES APPLICABLE TO ALL BILLINGS AND SERVICES ON AND AFTER OCTOBER 1, 2017
APPLICABLE TO ALL BILLINGS AND SERVICES ON AND AFTER OCTOBER 1, 2017 Page SECTION I: SCHEDULE OF WATER RATES AND FEES... 2 SECTION II: SCHEDULE OF SEWER RATES AND FEES... 8 SECTION III: SCHEDULE OF RECLAIMED
More informationCave Creek and Desert Hills Master Plan. Master Plan Cost Estimate. Cave Creek and Desert Hills, AZ BASIS OF ESTIMATE
Cave Creek and Desert Hills Water Company Master Plan Cost Estimate Cave Creek and Desert Hills, AZ Estimate ID: 2008.0041 Project Name: Cave Creek and Desert Hills Master Plan Class Estimate: Class 4
More informationSIGNIFICANT BUDGET CHANGES
Department of Environmental Services Our Mission: To build and maintain water delivery, sanitary sewer collection, and wastewater treatment systems that provide high-quality water and sewer services and
More informationCapital Improvement Plan
Fiscal Year 2016-17 through Fiscal Year 2021-22 Adopted: Overview City of Jonesville 2016-17 through 2021-22 The (CIP) is a six year schedule of all proposed major capital improvement projects including
More informationBOARD OF DIRECTORS METROPOLITAN DOMESTIC WATER IMPROVEMENT DISTRICT PIMA COUNTY, ARIZONA MONDAY, NOVEMBER 13, 2017
BOARD OF DIRECTORS METROPOLITAN DOMESTIC WATER IMPROVEMENT DISTRICT PIMA COUNTY, ARIZONA MONDAY, NOVEMBER 13, 2017 **BOARD CONFERENCE ROOM** METROPOLITAN DOMESTIC WATER IMPROVEMENT DISTRICT 6265 N. LA
More informationWATER AND WASTEWATER FUND REVENUES
WATER AND WASTEWATER FUND REVENUES Water revenues comprise $12.11 million, or 70.6% of total revenues of the fund, while wastewater (sewer) charges comprise $4.25 million, or 24.7% of total revenues. Water
More information2018 Five Year Financial Plan
2018 Five Year Financial Plan Five Year Financial Plan City of Pittsburg, Kansas May 19, 2018 Introduction: It is the role of the City Commission and the City s management staff to find ways to not just
More informationCapital Improvement Plan. Fiscal Year through Fiscal Year
Fiscal Year 2015-16 through Fiscal Year 2020-21 Adopted: May 20, 2015 Overview City of Jonesville 2015-16 through 2020-21 The (CIP) is a six year schedule of all proposed major capital improvement projects
More informationDENVER SOUTHEAST SUBURBAN WATER AND SANITATION DISTRICT MANAGEMENT S DISCUSSION AND ANALYSIS
The management of Denver Southeast Suburban Water and Sanitation District (the District) offers the readers of the District s financial statements this narrative overview and analysis of the financial
More informationLookout Mountain Water District: Genesis and Evolution
Lookout Mountain Water District: Presented by: Genesis and Evolution John Roscoe, President of the Board and Panel: Board of Directors and Contractors September 30, 2010 1 Introduction Purpose: Update
More informationCity of Vacaville FY 2017/2018 CIP Budget, General Plan Consistency and CEQA Review Parks and Recreation
Parks and Recreation Park & Recreation Housing 14160 Grant Total Fund Balance $3,916,598 $3,916,598 Prior Budget Commitments ($2,770,788) ($2,770,788) Other Budget Commitments ($126,482) ($126,482) Other
More informationUnion County, NC Water and Sewer System Development Fee Study
333333333 Union County, NC Water and Sewer System Development Fee Study April 9, 2018 April 9, 2018 Mr. Edward Goscicki Executive Director 500 N. Main Street, Monroe, NC 28112 Re: Water and Sewer System
More informationUtility Board. Agenda topics. For Meeting of June 12, :00 PM to 9:00 PM City Council Chambers, City Hall
Utility Board For Meeting of June 12, 2012 7:00 PM to 9:00 PM City Council Chambers, City Hall Board Members: Council Liaison: Staff: David Laub, Chairman, Benjamin Levie, Vice Chairman, Suresh Malhotra,
More informationSolid Waste & Recycling
Solid Waste & Recycling The Solid Waste & Recycling Fund accounts for the activities of Chatham County's waste management, including the collection sites, hauling, and disposal costs. The Solid Waste &
More informationMAINTENANCE DEPARTMENT
MAINTENANCE DEPARTMENT E-78 City of Mercer Island 2007-2008 Budget Department: Maintenance The Maintenance Department consists of the following functions: 1) administration, 2) capital projects engineering,
More informationEAST NILES COMMUNITY SERVICES DISTRICT
EAST NILES COMMUNITY SERVICES DISTRICT FISCAL YEAR EDISON- ASSESSMENT DISTRICT A/D # 3 KERRNITA PARK-ASSESSMENT DISTRICT A/D # 7 WEEDPATCH HWY WATER SYSTEM-ASSESSMENT DISTRICT A/D# 8 BOARD OF DIRECTORS
More informationBID PROPOSAL. PROPOSAL OF, a corporation, a partnership consisting of. an individual doing business as
Description 103 REMOVE, STORE AND REINSTALL EXISTING RETAINING WALL 107.1 EMBANKMENT (FINAL)(DENS CONT)(TY B) 203.1 TACK COAT BID PROPOSAL PROPOSAL OF, a corporation, a partnership consisting of an individual
More information2012 WATER & SEWER ALLEY CONSTRUCTION CONTRACT, PACKAGE I SAWS WATER JOB. NO /SAWS SEWER JOB NO SOLICITATION #B DD
BID PROPOSAL PROPOSAL OF, a Corporation organized and existing under the laws of the State of, a Partnership consisting of, an Individual doing business as. Enclosed with this bid are (1) Bid Bond, and
More informationUtility Committee Meeting AGENDA. October 3, 2017
Utility Committee Meeting AGENDA October 3, 2017 I. CALL TO ORDER II. MATTERS BEFORE COMMITTEE 1. Purchase - Gas Materials for Estates at Dean Hill Farms 2. Approval - 2016 CDBG Grant Construction Bid
More informationLakewood Ranch CDD 6
Funding Reserve Analysis for Lakewood Ranch CDD 6 May 30, 2017 Florida Reserve Study and Appraisal, Inc. 12407 N. Florida Avenue Tampa, FL 33612 Phone: 813.932.1588 Fax: 813.388.4189 www.reservestudyfl.com
More informationCIP. February,
2018-2022 CIP February, 21 2017 Agenda Biennial Budget 2018/2019 Budget Calendar 2018-2022 CIP Process Prioritized List of Projects Biennial Budgeting Strategic Culture in Olathe Strategic Culture in Olathe
More informationOperating Budget and Capital Improvement Program for Fiscal Year 2018
12770 Second Street, Yucaipa, California 92399 Operating Budget and Capital Improvement Program for Fiscal Year July 1, to June 30, Adopted June 20, Fiscal Year Table of Contents CHAPTER ONE Table of Contents...
More informationENGINEERING AND OPERATIONS COMMITTEE. November 27, :30 PM Greenspot Road, Highland CA AGENDA
ENGINEERING AND OPERATIONS COMMITTEE November 27, 2017-2:30 PM 31111 Greenspot Road, Highland CA 92346 CALL TO ORDER PLEDGE OF ALLEGIANCE PUBLIC COMMENTS NEW BUSINESS AGENDA 1. Approve the September 25,
More informationSUBDIVISION IMPROVEMENTS AGREEMENT
SUBDIVISION IMPROVEMENTS AGREEMENT THIS AGREEMENT, made between GLEN DEVELOPMENT COMPANY, hereinafter called the "Subdivider," and El Paso County by and through the Board of County Commissioners of El
More informationCHAPTER 11. CAPITAL FACILITIES PLAN ELEMENT
CHAPTER 11. CAPITAL FACILITIES PLAN ELEMENT 11.1 INTRODUCTION A is one of eight elements required by the Growth Management Act (GMA) to be included in Yakima County s comprehensive plan. The reason for
More informationCity of Arroyo Grande Department of Public Works REQUEST FOR PROPOSAL WATER AND WASTEWATER RATE STUDY UPDATE
I. INTRODUCTION City of Arroyo Grande Department of Public Works REQUEST FOR PROPOSAL WATER AND WASTEWATER RATE STUDY UPDATE The City of Arroyo Grande, California (the City ) was incorporated as a general
More informationLETTER OF INTENT FOR: HERITAGE HILLS COMMUNITY
LETTER OF INTENT FOR: HERITAGE HILLS COMMUNITY January 5, 205 2 Partially Completed Single Family Lots (65' x 5' typical) 46 Completed Townhome Pads (22' x 50' typical) Sale. This letter of intent outlines
More informationCity of Centerville BMP Pages Table of Contents. Minimum Control Measure 1. Public Education and Outreach
i City of Centerville s Table of Contents Minimum Control Measure 1. Public Education and Outreach Best Management Practice Page 1-1: Outreach Publications...1 1-2: 30-day Public Notice for Annual Storm
More informationVillage of Innisfree Viability Plan June 2018
Village of Innisfree Viability Plan June 2018 A report concerning the viability of the Village of Innisfree Drafted by the Innisfree Viability Review Team Village of Innisfree Viability Review Team Village
More informationAGENDA ASTORIA CITY COUNCIL
AGENDA ASTORIA CITY COUNCIL October 5, 2015 7:00 p.m. 2 nd Floor Council Chambers 1095 Duane Street Astoria OR 97103 1. CALL TO ORDER 2. ROLL CALL 3. REPORTS OF COUNCILORS 4. PROCLAMATIONS (a) Fire Prevention
More informationDRAFT C APITAL I MPROVEMENT P LAN C ITY OF G EORGETOWN, TEXAS S TREETS/ DRAINAGE/AIRPORT F ISCAL Y EAR 201 6
C ITY OF G EORGETOWN, TEXAS C APITAL I MPROVEMENT P LAN S TREETS/ DRAINAGE/AIRPORT F ISCAL Y EAR 201 6 Georgetown Transportation Advisory Board April 10, 2015 Table of Contents Introduction... 1 Transportation
More informationJuly 25, Members of City Council City of League City, Texas
Mark Rohr City Manager 300 W Walker League City, TX 77573 Main: 281.554.1000 Direct: 281.554.1005 www.leaguecity.com July 25, 2016 Members of City Council City of League City, Texas Transmitted herewith
More informationActual Cost Actual Cost HST
s & Charges Department Water % Est # Units 2013 Actual Water Main Taps 20mm to 50mm 58 $ 369.87 $ 375.42 Exempt 1.5% Inflation 100mm & larger 57 $ 689.77 $ 700.12 Exempt 1.5% Inflation Standby time for
More informationUTILITY FUNDS SUMMARY
UTILITY FUNDS SUMMARY On the following pages is important information about the utilities as a whole. This section identifies the emerging issues for each of the utilities, followed by a brief discussion
More informationKentucky Infrastructure Authority Projects for November 2017 Capital Projects Meeting
Kentucky Infrastructure Authority Projects for November 2017 Capital Projects Meeting Fund A Loan Loan # Borrower Loan Amount County A15-002 Regional Water Resource Agency (Increase) $ 8,007,500 Daviess
More informationFINAL 2018 RATE SUPPORTED OPERATING BUDGET TABLE OF CONTENTS
FINAL RATE SUPPORTED OPERATING BUDGET TABLE OF CONTENTS Section 1 Final Rate Supported Operating Budget Water & Wastewater Summary PSAB Format...1 Water & Wastewater Summary...2 Water & Wastewater Administration...3
More informationReserve Study Project No Prepared for Nelson Farm Homeowner Association 1771 Norwood Lane Fort Collins, Colorado
Reserve Study Project No. 09069 Prepared for 1771 Norwood Lane Fort Collins, Colorado Prepared by Bornengineering 1130 West 124 th Avenue, Suite 100 Westminster, Colorado 80234 January 28, 2010 1130 WEST
More information2012 Strategic Business Initiatives Cooperative Extension Service Environmental and Heritage Center Health and Human Services Parks and Recreation
2013 Business Plan 2012 Strategic Business Initiatives Cooperative Extension Service Environmental and Heritage Center Health and Human Services Parks and Recreation Operations Parks and Recreation Project
More informationSTORMWATER MANAGEMENT FUND DEPARTMENT OF ENVIRONMENTAL SERVICES
DEPARTMENT OF ENVIRONMENTAL SERVICES Mission: To implement a comprehensive stormwater management program that balances the following goals: 1) to reduce the potential for stormwater threats to public health,
More informationWater Resources Engineering Division Public Works City of Colorado Springs
Water Resources Engineering Division Public Works City of Colorado Springs Richard Mulledy, P.E. Division Manager City of Colorado Springs/Pueblo County IGA City of Colorado Springs/Pueblo County IGA $460
More informationProgressive Planning for Financially Robust Water Systems
Canadian Water Network: Blue Cities 2017 Progressive Planning for Financially Robust Water Systems May 17, 2017 CITY OF ATLANTA Kasim Reed, Mayor Kishia L. Powell, Commissioner 5/25/2017 1 Discussion I.
More informationElectric Service Information Sheet Georgia Power Company
Electric Service Information Sheet Georgia Power Company Project: Location: Developer: (Name of S/D or Customer) (Street Address or road Name) (Developer s Name) Georgia Power Company (the Company) will
More informationDistrict of Clearwater Utility Rate Review
District of Clearwater 2018 Utility Rate Review Janice Aver May 2018 Table of Contents BACKGROUND... 1 FULL COST OF SERVICE... 2 OPERATIONS... 3 CAPITAL... 5 RESERVES... 10 RATES... 12 RECOMMENDATIONS...
More informationCITY OF WEYBURN GENERAL OPERATING FUND/ UTILITY FUND 2017 BUDGET
/ UTILITY FUND BUDGET BUDGET Operating Fund Revenues Administration/Finance 15,192,307 15,300,577 15,355,313 54,736 0.4% Police Services 628,449 598,860 727,400 128,540 21.5% Fire Services 93,682 134,726
More informationCapital Projects CAPITAL PROJECTS CAPITAL PROJECTS
Capital Projects CAPITAL PROJECTS CAPITAL PROJECTS 121 REVENUE FUNDS REVENUE FUND REFERENCE NUMBERS AND DESCRIPTIONS: 01 - General Fund This fund is the primary fund for the City. In addition to Capital
More informationSALT LAKE CITY COUNCIL STAFF REPORT BUDGET AMENDMENT ANALYSIS FISCAL YEAR
SALT LAKE CITY COUNCIL STAFF REPORT BUDGET AMENDMENT ANALYSIS FISCAL YEAR 2002-03 DATE: May 7, 2002 BUDGET FOR: STAFF REPORT BY: cc: DEPARTMENT OF AIRPORTS Gary Mumford Rocky Fluhart, David Nimkin, Tim
More informationGeneral Manager s Recommended Budget for Fiscal Years 2018 & Maureen A. Stapleton, General Manager
General Manager s Recommended Budget for Fiscal Years 2018 & 2019 Maureen A. Stapleton, General Manager Fiscal Years 2018 & 2019 Recommended Budget Overview Themes Security Cyber & Facilities State & Federal
More informationCOUNTY ADMINISTRATOR PUBLIC WORKS
COUNTY ADMINISTRATOR PUBLIC WORKS Public Works is comprised of several Departments/Divisions that develop, improve, and maintain the County s basic infrastructure needs related to transportation, storm
More informationPublic Works Department
Departmental Summary FUND/ACTIVITY ACTUAL ADOPTED AMENDED ADOPTED General Fund: Revenue Administration 246,334 316,548 245,742 245,742 Municipal Trash Collection 57,049 57,000 58,169 58,169 Total Revenues
More informationRATE INFORMATION. A. The rates adopted by the Authority will be in accordance with of the Code of Virginia, as amended.
Page 1 of 8 Section 1. PURPOSE The purpose of this policy to explain how the Bedford Regional Water Authority ( Authority ) implements the adopted Rates policy and to provide explanation for each of the
More informationCity of Jacksonville Beach Minutes of City Council FY Budget Workshop Tuesday, August 2, :00 PM
City of Jacksonville Beach Minutes of City Council FY 2012 - Budget Workshop Tuesday, August 2, 2011 4:00 PM Mayor Sharp called the Budget Workshop to order at 4:00pm. City Council members in attendance:
More informationStormwater Utility Fund Delivery of Services
Stormwater Utility Fund Delivery of Services Presented by Douglas Wiersig, P.E. Director & Greg Simmons, P.E. Assistant Director Transportation and Public Works Department November 12, 2012 1 Purpose History
More information2017 Budget & Capital Improvement Plan AUGUST 29, 2017
2017 Budget & Capital Improvement Plan AUGUST 29, 2017 FY 2017 Budget Calendar May June July August September October November December Financial Forecast & Public Safety Staffing Priorities, Programs,
More information2012 WATER & SEWER CONSTRUCTION CONTRACT, PACKAGE IV SAWS WATER JOB. NO /SAWS SEWER JOB NO SOLICITATION #B DD BID PROPOSAL
BID PROPOSAL PROPOSAL OF, a Corporation organized and existing under the laws of the State of, a Partnership consisting of, an Individual doing business as. Enclosed with this bid are (1) Bid Bond, and
More informationFY 16 - FY 18 Capital Fund Revenues
FY 16 - FY 18 Capital Fund Revenues Fiscal Year $ Change 2016 2017 2018 FY 17 to Revenue Source Budget Budget Budget FY 18 Local Transfer from General Fund $3,136,950 $2,977,556 $6,087,130 $3,109,574 Local
More informationWetzel County Floodplain Ordinance
Wetzel County Floodplain Ordinance AUTHORITY AND PURPOSE: THE PROVISIONS OF THIS ORDINANCE HAVE BEEN PREPARED WITH THE INTENTION OF MEETING THE REQUIREMENTS OF SECTION 60.3 (D) OF THE NATIONAL FLOOD INSURANCE
More informationSECTION G. RATES AND SERVICE FEES
SECTION G. RATES AND SERVICE FEES UNLESS SPECIFICALLY DEFINED IN THIS SERVICE POLICY, ALL FEES, RATES, AND CHARGES AS STATED HEREIN SHALL BE NON-REFUNDABLE. 1. Classes of Users -- All users of the District
More informationJEFFERSON WATER & SEWER DISTRICT BOARD MEETING MINUTES OCTOBER 5, 2017
JEFFERSON WATER & SEWER DISTRICT BOARD MEETING MINUTES OCTOBER 5, 2017 A regular meeting of the Jefferson Water and Sewer District Board of Trustees was held pursuant to call on October 5, 2017 at 6:30
More informationJANUARY 18, Reference Specifications, Attachment to Form 96 (BID FORM), Bid Proposal: Respectfully submitted,
ADDENDUM NO. 3 TO THE PLANS AND SPECIFICATIONS for STREET AND STORM SEWER IMPROVEMENTS ON HANCOCK AND WASHINGTON STREETS for the FRENCH LICK REDEVELOPMENT COMMISSION ORANGE COUNTY, INDIANA MEI PROJECT
More informationBID TABULATION REPORT ABRAM STREET (SH CITY LIMITS) PROJECT No. PWST09016 BID OPENED : April 22, 2014 at 1:30 p.m.
PAVING IMPROVEMENTS 101 Mobilization and Bonds, LS 1 $ 225,000.00 $ 225,000.00 $ 225,000.00 $ 225,000.00 $ 225,000.00 $ 225,000.00 $ 225,000.00 $ 225,000.00 102 Right-of-way Preparation LS 1 $ 365,500.00
More informationLOUISVILLE WATER COMPANY 2018 TARIFF, RATE SCHEDULE, AND CUSTOMER FEES AND CHARGES
LOUISVILLE WATER COMPANY 2018 TARIFF, RATE SCHEDULE, AND CUSTOMER FEES AND CHARGES Presented to: Louisville Water Company Board of Water Works December 18, 2017 WATER RATES LOUISVILLE WATER COMPANY LOUISVILLE,
More informationCITY OF FLORENCE, SC Monthly Financial Report August 2010
CITY OF FLORENCE, SC Monthly Financial Report City of Florence Finance Department City of Florence, SC Monthly Financial Report Table of Contents For the Month Ended August 31, 21 General Fund 2 General
More informationCITY OF FLORENCE, SC Monthly Financial Report July 2010
CITY OF FLORENCE, SC Monthly Financial Report City of Florence Finance Department City of Florence, SC Monthly Financial Report Table of Contents For the Month Ended July 31, 21 General Fund 2 General
More informationBond and Interest Fund
Bond and Interest Fund J-1 Fund 301 - BOND AND INTEREST Budget Resources by Classification: Total $10,305,374 Fund Bal. Fwd., 44.28% Ad Valorem Taxes, 43.30% Spec. Assessment 5.92% Misc., 0.05% Other Taxes,
More informationAcquisition of Wachs Valve and Hydrant Services LLC
Acquisition of Wachs Valve and Hydrant Services LLC Supplemental Information February 17, 2015 www.puretechltd.com Pure Announces Acquisition of Wachs Water Over 85 Contracts Across North America Strong
More informationCharges. Retail. Charge (water) & Builder. Account Activation Fee. Meter Size. Meter Fee. Water Sewer. Total $7.485 $4.99 $9.98 $9.
Residential Accounts Rates & Fees Calendar Year Meter Size ¾ 1 1 ½ Initial Charges (Single-Family Residential Accounts) Account Activation Fee Total 3 Base Charge New Construction or Irrigation (water)
More informationCity of Ocoee Quarterly Report First Quarter Fiscal Year
City of Ocoee Quarterly Report First Quarter Fiscal Year 2008-2009 Prepared by the Finance Department February 2009 TABLE OF CONTENTS Quarterly Overview...i-iii General Fund... 1 Revenue Comparison Graph...
More information