CONSULTING ENGINEERS ANNUAL REPORT FOR THE SEWER SYSTEM. 369 East Park Drive Harrisburg, PA (717)

Size: px
Start display at page:

Download "CONSULTING ENGINEERS ANNUAL REPORT FOR THE SEWER SYSTEM. 369 East Park Drive Harrisburg, PA (717)"

Transcription

1 369 East Park Drive Harrisburg, PA (717) OCTOBER 2014 CONSULTING ENGINEERS ANNUAL REPORT FOR THE SEWER SYSTEM CAPITAL REGION WATER DAUPHIN COUNTY, PENNSYLVANIA HRG Project No

2 TABLE OF CONTENTS Page INTRODUCTION... 1 REGULATIONS AND COMPLIANCE... 4 MAINTENANCE, REPAIR AND OPERATION... 5 PLANNED CAPITAL IMPROVEMENTS... 6 SYSTEM DEMAND AND CAPACITY ENGINEER ESTIMATED EXPENSES APPENDICES APPENDIX A Sewer System Map APPENDIX B Municipal Wasteload Management Report Calendar Year 2013 APPENDIX C Wholesale Wastewater Rate Study Report APPENDIX D 20 Year Capital Improvements Plan

3 CONSULTING ENGINEERS ANNUAL REPORT October 2014 INTRODUCTION PURPOSE Capital Region Water ( CRW ), formerly known as The Harrisburg Authority ( THA ) owns and operates sewer collection, conveyance and treatment facilities serving the City of Harrisburg and surrounding suburban municipalities. In 2014, the Authority issued a Wastewater System Revenue Note with Manufacturers and Traders Trust Company to provide interim financing for their Advanced Wastewater Treatment Facility Improvements Project. The Note was secured through a Trust Indenture dated March 1, Specific engineering duties as outlined in Section 808 of the Indenture are as follows: It shall be the duty of the Consulting Engineer, in addition to the other duties prescribed elsewhere in this Indenture, to prepare and file with the Authority and with the Trustee on or before 90 days prior to the beginning of each Fiscal Year while this Indenture is in force, a report setting forth the following: (a.) Its advice and recommendations as to the proper maintenance, repair and operation of the System during the next Fiscal Year; (b.) Its advice and recommendations as to the Capital Additions that should be made during the next Fiscal Year, and its estimate of the amounts of money that should be expended for Operating Expenses and its estimate of the amounts of money necessary for such purposes; and (c.) Its finding whether the properties of the System have been maintained in good repair, working order and condition and its estimate of the amount, if any, required to place such properties in such condition and the details of such expenditures and the approximate time required therefor. The contents of this report have been prepared in accordance with the stated Indenture requirements and are intended to provide a consolidated overview of the system and key operational matters. The following pages include a description of the existing sewer system and information relative to ownership, operations, regulations, revenues and expenses. 1

4 SYSTEM DESCRIPTION The wastewater system is comprised of (1) the collection system portion of the sewer system (separate sanitary and storm sewer facilities as well as combined stormwater/sanitary sewer facilities; (2) and conveyance facilities and the Advanced Wastewater Treatment Plant. The conveyance and treatment system provides wastewater conveyance and treatment to City retail customers and suburban wholesale communities. The suburban communities account for approximately 60% of the flow through the conveyance and treatment system and include Susquehanna Township, Lower Paxton Township, Swatara Township, Paxtang Borough, Penbrook Borough, and Steelton Borough, all of which are located in Dauphin County. The conveyance and treatment system includes interceptors, pumping stations, and a wastewater treatment facility, a High Purity Oxygen Activated Sludge plant, which is known as the Advanced Wastewater Treatment Facility ( AWTF ). The conveyance system carries wastewater from the collection system along with wastewater from surrounding communities to the AWTF. In August 2009, DEP approved THA s 537 Plan which called for an upgrade to the AWTF including a combination of innovative technology and nutrient credit trading. The technology involves side-stream treatment with bio-augmentation to overcome space limitations of the AWTF site and cost-effectively achieve the nitrogen and ammonia removal requirements. In order to comply with the Chesapeake Bay Tributary Strategy and meet new National Pollution Discharge Elimination System (NPDES) permit discharge requirements, CRW has secured financing and commenced upgrades to its AWTF in The facility is one of the largest publically owned treatment facilities in the Commonwealth and currently the largest in Pennsylvania within the Chesapeake Bay watershed. The requirements for nitrogen, phosphorus and ammonia removal outlined in their current NPDES permit, which have reduced by half in recent years, have necessitated the current facility upgrade. The current AWTF Improvements Project will employ biological nutrient removal technology to the existing processes of the 37.7 MGD activated sludge plant to cost-effectively achieve the nitrogen and ammonia removal requirements associated with the new NPDES discharge permit. Integration includes the modification and addition of multiple tanks and processes. The sewer system is comprised of approximately 250,800 feet of sanitary sewers, 152,000 feet of stormwater sewers and 457,000 feet of sanitary and stormwater sewers. CRW is in the process of completing a GIS and Asset Management System project to locate and inspect all sanitary, storm and combined sewer features in addition to completing mapping, condition assessment and connectivity analysis. Information will be used to expand CRW s current Capital Improvement Plan through the use of an in depth Asset Management System. Capital Region Water s current system serves approximately 82,470 EDUs located in the City of Harrisburg along with Steelton Borough, Paxtang Borough, Penbrook Borough, Susquehanna Township, Swatara Township and Lower Paxton Township. 2

5 Financial stress facing the City of Harrisburg caused the City and Authority to re-evaluate their ownership, operation and management relationship. The long-term Capital Improvement Plan, included in Appendix D, outlines approximately $117 million of proposed infrastructure improvements over the next twenty (20) years. Borrowings through the capital market were necessary to finance current regulatory driven improvements and additional borrowings are anticipated in future years to finance other necessary improvements. Change in Ownership and Operations: Prior to November 2013, the City of Harrisburg owned the sewer collection system while The Harrisburg Authority owned the conveyance and treatment facilities. These facilities were operated and maintained by the City of Harrisburg through an Agreement of Lease dated September 15, As part of the financial recovery plan of the City, The Office of the Receiver of the City of Harrisburg, THA, and the City administration agreed to terminate the Agreement of Lease and transfer ownership of all sanitary and storm collection systems to The Harrisburg Authority. On November 4, 2013, the agreements pursuant to which the City previously operated the water system and the wastewater system were terminated, and certain operating personnel were transferred and the Authority became exclusively responsible for the water system and wastewater system operations. On December 4, 2013, the remaining collection system assets were fully transferred from the City to the Authority. This change in ownership and operations provides the following: 1. Independent Personnel Authority: The Authority directs and controls its labor force, subject to applicable labor agreements. Certain City employees became direct employees of the Authority. The Authority has established new personnel rules and new benefit plans, including a pension plan, subject to applicable labor agreements. 2. Independent Contracting Authority: The Authority has the ability to contract with outside parties to provide services and support. 3. Operational Control: The Authority controls all operations (including utility operations, billing and collection, customer service, finances, human resources, IT, legal, etc.) related to the sewer utility, either through Authority personnel or contracting with the City or outside parties. 4. Access to Capital Markets: The Authority now has independent control of the resources of the sewer facilities to provide assurances to the bond market that it will make full and timely repayment. The Harrisburg Authority becomes Capital Region Water: In March 2014, as part of this transition and rebranding process, the Harrisburg Authority formally changed its name to Capital Region Water to reflect the Authority s mission of providing potable water services and the management and treatment of wastewater and storm water in the south-central Pennsylvania capital region. 3

6 REGULATIONS AND COMPLIANCE As mentioned in the introduction section of this report, Capital Region Water s staff now directly operate and maintain the Sewer System. Sewer quality is regulated by the Federal Clean Water Act, enforced through laws and regulations administered by the Pennsylvania Department of Environmental Protection (DEP). National Pollution Discharge Elimination System (NPDES) Permit Renewal The AWTF is permitted to discharge to the Susquehanna River under NPDES Permit No. PA issued on January 1, 2010 which expires December 31, An NPDES renewal application was submitted in July of Necessary Improvements to Comply with State and Federal Regulations The conveyance and treatment facilities are regulated by the Clean Water Act enforced by the United States Environmental Protection Agency (USEPA) and the Pennsylvania Department of Environmental Protection (PADEP). The three (3) major regulatory drivers currently faced by CRW relative to the sewer facilities for compliance with the Clean Water Act include the following: 1. NPDES Permit Compliance Ammonia (NH 3 ) Discharge Limit. 2. NPDES Permit Compliance - Chesapeake Bay Tributary Strategy (CBTS) Compliance for total nitrogen (TN) and total phosphorus (TP) cap loadings. 3. CSO Control Policy Compliance Nine Minimum Controls and Long Term Control Plan Updates. Compliance with these regulations is the top priority for the Capital Improvements Plan. Transfer of DEP Permits All sewer system operating permits were previously held by The Harrisburg Authority, therefore, no permit transfers were required in order for The Harrisburg Authority (now Capital Region Water) to terminate the 1976 Agreement of Lease. 4

7 MAINTENANCE, REPAIR AND OPERATION Through the termination of the 1976 Lease Agreement, Capital Region Water Staff are now directly responsible for providing the following services: general supervision and control of operations; employment and supervision of employees; contracting and purchasing of supplies and services; extensions, alterations and improvements to the sewer system; and preparing and filing of reports. In addition to the items listed above, CRW Staff strived to ensure the sewer collection, conveyance and treatment facilities are all properly operational and maintained. The cost to provide routine and preventive maintenance is included in CRW s annual operating budget. Major rehabilitations and replacements are financed by CRW through the use of system reserve funds or future borrowings. 5

8 PLANNED CAPITAL IMPROVEMENTS In April of 2013, HRG prepared a Five Year Capital Improvement Plan (CIP) for Sewer Conveyance and Treatment Facilities. That document serves as the basis for recommended improvements to the system. Updated projects scopes and costs to be implemented in the upcoming fiscal year are outlined below. CRW is in the process of investigating separate sanitary and storm collection facilities, along with combined sewers in order to evaluate the current facilities and prioritize repairs. This work is being completed as part of CRW s Geographic Information and Asset Management System project in addition to Technical Assistance being completed for CRW by the United States Army Corps of Engineers. Capital Improvements Completed in 2014 In March 2014, CRW awarded contracts to three (3) construction contractors (General, Electrical, Mechanical) totaling $36,455, for upgrades to the AWTF relative to the BNR Upgrade Project, referred to as the 2014/2015 AWTF Improvements Project. Total project cost of the BNR Upgrade is approximately $49.2MM. Notice to Proceed was issued in March 2014 and construction is anticipated to be complete in In July 2014, CRW awarded an additional contract totaling $161,000 relative to HVAC Improvements at the AWTF which will be completed in Sanitary/Storm GIS and Asset Management work completed in 2014 included continued survey level data collection of above grade sanitary, storm, and combined sewer features, including manholes, inlets, and outfalls and incorporation of the information into CRW s GIS. Work completed also included NASSCO PACP data collection and assessment by Redzone Robotics of approximately 75,800 feet of CRW s interceptor piping. NASSCO MACP Level 2 data collection and assessment of approximately 200 interceptor manholes is also to occur in The USACE is also completing data collection, assessment, and inventorying of CRW s MS4 facilities. The Authority also continued discussions with EPA and provided focused efforts related to updates and revisions to its Long Term Control Plan along with MS4 Permit compliance. Capital Improvements Planned for 2015 On September 15, 2014 HRG met with CRW Staff to discuss updates to the 2013 Capital Improvement Plan and reprioritize system repairs, upgrades and improvements based upon investigation, condition assessments, regulatory requirements and other related drivers. The meeting resulted in reprioritization of projects and identification of additional improvements to be included in the 2015 Capital Improvement Budget budgeted costs also include investigation and condition assessment of the Authority s sanitary, storm and combined collection facilities in order to identify and prioritize improvements in upcoming years. The updated table outlining 20 Year Planned Capital Improvements for sewer collection, conveyance and treatment facilities is included in Appendix D. Refer to Table 2 on page 14 of this report for a listing of Year 2015 Proposed Capital Improvements and associated estimated costs. Those projects include: 6

9 AWTF - BNR Upgrade Project As previously discussed, in accordance with the Chesapeake Bay Tributary Strategy (CBTS), PADEP issued an NPDES permit to the Authority on December 4, 2009 which set an annual total nitrogen (TN) discharge loading limit for the AWTF of 688,575 pounds per year, roughly one half of the typical nitrogen discharged by the facility in recent years and a total phosphorus (TP) discharge loading limit of 91,810 pounds per year. The NPDES permit also includes a seasonal effluent ammonia limit of 11 mg/l. The requirements of the NPDES permit necessitated a major plant upgrade. As an update to the 2013 Five Year Capital Improvements Plan we offer that design of the AWTF Improvements Project was completed in 2013, the construction contracts totaling $36,455, were awarded in March 2014 and construction will continue into The 2015 Estimated Budget of $27,000,000 identified in Table 2 will cover construction, engineering, administrative and legal fees associated with this project in AWTF - Headworks Screening/ Trucked-in-Waste Receiving Station Study A screening study is necessary in order to evaluate and select the best alternative for providing the necessary screening equipment at the AWTF. Screens are necessary at the AWTF to protect downstream equipment, particularly the grit removal pumps. In addition to providing screening at the AWTF, the existing screening systems at the Front Street and Spring Creek Pump Stations have reached the end of their useful life and are in need of replacement. The Screening Study will evaluate upgrading the existing pump station screening equipment with new course screening equipment, as well as evaluation of alternatives for a new fine screening system and trucked-in-waste screening facility at the AWTF. As an update to the 2013 Five Year Capital Improvements Plan we offer that CRW has entered into a contract with Hazen & Sawyer, P.C. to complete the study for a total not to exceed fee of $46,750. Work on the study will commence in October 2014 and continue into the first quarter of The 2015 Estimated Budget of $16,667 identified in Table 2 will cover the engineering fees associated with this study in AWTF Headworks Screening/Trucked-in-Waste Receiving Station Design Adequate screening at the AWTF is necessary to maximize the efficiency of the existing grit removal system as well as protect downstream components such as pumps, primary clarifier mechanism, etc. from unnecessary wear and failure. Damage to downstream components, as a result of the lack of influent screening, has resulted in an increase in operation and maintenance costs, as well as downtime for process-sensitive treatment systems. The new headworks screening facility would include various components such as a new fine screen and compactor equipment, a new headworks screening building, and ancillary electrical and control work necessary to provide automation and remote monitoring of the screening system. 7

10 Installation of a trucked-in waste receiving station at the AWTF will provide the operations staff with a better means of managing the contract waste hauling system and controlling the discharge of trucked-in-waste to the facility. This facility would provide pre-treatment of the trucked-in-waste prior to discharge to the AWTF for ultimate treatment and disposal. The new trucked-in-waste facility would include various components such as septage receiving equipment and treatment for contract waste haulers, new process piping connections, revision to truck traffic routings and waste discharge locations, and manual and automatic sampling equipment. The annual revenue received from trucked in waste at the AWTF is approximately $600,000. As identified in the 2013 Five Year Capital Improvements Plan the total estimated project cost for the Headworks Screening is $4,100,000 and the total estimated project cost for the Trucked-in- Waste Receiving Station is $2,300,000. It is anticipated that these projects will be designed, bid and constructed as a single project which may also include the Front Street and Spring Creek Pump Station Improvements project described below after completion of the Headworks Screening/ Trucked-in-Waste Receiving Station Study in The 2015 Estimated Budget of $652,000 identified in Table 2 will cover the engineering fees associated with preliminary and final design of the Headworks Screening/Trucked-in-Waste Receiving Station Project in GIS Mapping CRW continues to implement the GIS Mapping and Asset Management System Project for both the water and sewer facilities in accordance with the phasing outlined in the 2013 GIS Data Collection and Implementation Plan. CRW intends to commence with Phases 5 and 7 of the Project in 2014 which will extend into late Phase 5 includes the completion of a detailed subsurface investigation of all sanitary sewer manholes and a rapid assessment of all sanitary sewer mains to identify system connectivity, material, size, and general condition as observed from the manholes. Phase 7 includes the completion of a detailed subsurface investigation of the storm sewer facilities and identification of system connectivity, material, and size, and condition as can be observed from the inlets or manholes. The total estimated cost for this work in 2015 is $1,364,250. Sewer Maintenance & Repair Due to Deferred COH Action -- Equipment Needs Evaluation & Procurement This budgetary item if for the identification and purchase of equipment necessary to effectively operate and maintain the collection and conveyance facilities budgeted amount is $216,817. Capital Investments (Renewal and Replacement) -- Collection System This project relates to the repair and/or replacement of collection system facilities in a critically deteriorated state as identified in the GIS and Asset Management System inspection and condition assessment. The 2015 budgeted amount is $1,111,690. 8

11 Legal, Regulatory, Community Relations This includes work associated with CSO NMCP Implementation, NMCP Notification procedures, MS4 MCM #1 and #2 Plan, Ongoing public Outreach/Involvement/Notification, Legal document preparation related to sewer use/illicit discharge regulations/code, development/construction regulations/codes, agreements/mous with Suburban Municipalities, Consent Decree interaction with Government Agencies, document preparation and the like budgeted amount is $307,214. Flow, Rain and Water Quality Monitoring This project includes the implementation of Characterization Monitoring and supplemental monitoring (as needed), H/H model refinement, model testing/sensitivity, and model calibration. The amount budgeted for this project in 2015 is $1,124,414 Integrated Long Term Control Planning This line item includes various items associated with the Long Term Control Plan including initial system optimization assessment and project definition, high priority capital investments for system optimization, source control demonstration projects, and assessment of financial capabilities for Plan implementation. The amount budgeted for 2015 is $565,791. Misc. AWTF Improvements Projects This budgetary item is for up to $150,000 of high need repairs/replacement/improvements to the AWTF identified during facility operation in Misc. Conveyance Facilities Projects This budgetary item is for up to $150,000 of high need repairs/ replacement / improvements to the conveyance facilities identified during facility operation in AWTF Anaerobic Digester Rehabilitation Due to the importance and age of the equipment, improvements are necessary in order to effectively rehabilitate the existing anaerobic digesters. These improvements generally include roof replacement of the primary digesters and primary digester control building; cleaning and inspection of Primary Digester No. 1 and both secondary digesters; replacement of primary and secondary digester sludge valves and replacement of piping. Additional work may be necessary depending on the condition of the digesters identified during inspection. It should be noted that Primary Digester No. 2 is required to be operational prior to isolating, cleaning, and inspecting Primary Digester No. 1. The total estimated project cost to replace both primary digester roofs as well as the primary digester control house, boiler building and cogeneration building roof is $330,000 and this work will be completed in Piping improvements, secondary digester sludge valve replacement and additional improvements to the digestion facilities will be summarized and quantified after completion of a detailed inspection and cleaning of the digester facilities. 9

12 AWTF Primary Thickener & Gravity Thickener Sludge Pump Replacement After review with CRW Operations Staff, it was identified that the three (3) existing 25 horsepower thickener pumps and the two (2) 25 horsepower primary sludge pumps have outlived their useful life and are in need of replacement. In addition to replacing the pumps, the operations staff has identified a need to replace the existing starters with variable frequency drives in order to provide improved operational control and reduce electrical consumption. This work will be completed in 2015 and the estimated project cost is $215,

13 SYSTEM DEMAND AND CAPACITY System demand and capacity are reported yearly through the annual Municipal Wasteload Management Report, which can be found in Appendix B for calendar year

14 2015 ENGINEER ESTIMATED EXPENSES 2015 Budget Requirements included in Section 808 of the Trust Indenture which secures the Authority s Sewer Revenue Bonds require a sewer system budget to be prepared each year for adoption by the Authority. CRW is currently reviewing this budget, along with operation, maintenance, administrative, debt service, capital improvement, and other Authority operational costs to develop a proposed 2015 Authority budget. Generally, the Authority adopts a finalized budget in November of each year. Listings of engineer estimated Operating Expenses and Capital Improvements for 2015 are included in Table 1 and Table 2 below. The below budgets makes several assumptions relative to the Capital Improvements Plan, Authority operational costs, and other related items. An update of the 20-year anticipated capital improvements can be found in Appendix D. 12

15 Table 1 - Sewer System Comparison of Past and Proposed Operating Budgets Description Actual Actual Projected Budget Estimated OPERATING EXPENSES: PERSONNEL EXPENSES: Salaries and Wages 1,815,212 1,992,744 2,054,473 2,439,596 2,446,100 P/R Taxes 139, , , , ,600 Employee Benefits 536, , , , ,716 Other Subtotal Personnel Expenses 2,492,033 2,753,833 2,876,378 3,350,881 3,389,416 OPERATING AND MAINTENANCE EXPENSES: Equipment Repairs and Maintenance 57,405 96, , , ,000 Vehicle Repairs and Maintenance 47,119 62,750 74, , ,672 Infastructure Repairs and Maintenance 8, , , , ,500 Chemicals, Lab Supplies 365, , , , ,200 Building, Grounds Maintenance 16,000 12,000 12,985 12,000 14,400 Utilities 2,026,053 2,291,400 2,116,100 2,098,400 1,806,000 GIS 15,724 16,876 17,000 71,250 52,800 Lease Expense Insurance 403, , , , ,055 Computer and Softw are 9,584 9, Administrative Expenses 7,309, , ,538 65,600 1,150 Other Operating Expenses 871,616 5,945,290 5,084,310 2,859,250 3,494,165 Street Cleaning ,544, ,496 Community Relations 92,308 Subtotal Operating and Maintenance Expenses 11,130,723 10,429,311 9,425,606 8,960,034 7,872,746 Total Operating Expenses 13,622,756 13,183,144 12,301,984 12,310,915 11,262,162 CAPITAL PROJECTS FUNDED WITH CASH OR NEW DEBT ,933,239 3,073,693 TOTAL O&M and CI EXPENSES 13,622,756 13,183,144 12,301,984 14,244,154 14,335,855 Note: 2013 Actual Expense budget not yet consolidated (City of Harrisburg/THA) by CRW, therefore the projected budged is reflected above. 13

16 Table 2 - Sewer System 2015 Proposed Capital Improvements CAPITAL PROJECTS 2015 Estimated Budget AWTF - BNR Upgrade Project 27,000,000 AWTF - Headworks Screening/Trucked-in-Waste Receiving Station Study 16,667 AWTF - Headworks Screening/Trucked-in-Waste Receiving Station Design 652,000 General - GIS Mapping 1,364,250 Sewer Maintenance & Repair Due to Deferred COH Action Equipment Needs Eval & Procurement 216,817 Capital Investments (R&R) Collection System 1,111,690 Legal, Regulatory, Community Relations 307,214 Flow, Rain and Water Quality Monitoring 1,124,414 Integrated Long Term Control Planning 565,791 Miscellaneous AWTF Projects 150,000 Miscellaneous Conveyance System Projects 150,000 AWTF - Anaerobic Digester Rehabilitation 330,000 AWTF - Primary Thickener & Gravity Thickener Sludge Pump Replacement 215,200 Total Funds Expended for New Projects $ 33,204,043 Less Amount Funded by Ex. Debt Issues 29,130,350 Less Amount Funded by 2014 Nutrient Credit Carry-Over 1,000,000 Capital Funded by Cash or New Borrowing 3,073,693 The Authority is currently evaluating system revenues and developing an appropriate strategy for financing Year 2015 Capital Expenditures through rate revenue, funds on hands or debt financings. Rates Malcolm Pirnie - The Water Division of ARCADIS, completed a Wholesale Wastewater Rate Study Report for the sewer system on January 6, 2014, attached herein as Appendix C. As part of the Authority s current budgeting process, a rate study is being conducted to determine if a revenue increase in 2015 is necessary to meet requirements of the Trust Indenture. Rate increases will likely be necessary over the next few years in order to recover the cost of operations, maintenance, repairs, debt service and capital improvements. We recommend CRW fully implement rates proposed through these studies accordingly. 14

17 APPENDIX A SEWER SYSTEM MAP

18

19 APPENDIX B MUNICIPAL WASTELOAD MANAGEMENT REPORT CALENDAR YEAR 2013

20

21

22

23

24

25

26

27

28

29

30

31

32

33

34

35

36

37

38

39

40

41

42

43

44

45

46

47 APPENDIX C WHOLESALE WASTEWATER RATE STUDY REPORT

48 Imagine the result The Harrisburg Authority Wholesale Wastewater Rate Study Report January 6, 2014

49 Wholesale Wastewater Rate Study Report John Mastracchio, P.E., CFA Associate Vice President Prepared for: The Harrisburg Authority Prepared by: Malcolm Pirnie, Inc. 855 Route 146 Suite 210 Clifton Park New York Tel Fax Our Ref.: Date: January 6, 2014 This document is intended only for the use of the individual or entity for which it was prepared and may contain information that is privileged, confidential and exempt from disclosure under applicable law. Any dissemination, distribution or copying of this document is strictly prohibited.

50 Table of Contents 1. Introduction Rate Study Scope and Objectives Background Inter-Municipal Agreement and Existing Suburban Wholesale Rates 2 2. Sewer Rate Revenue Requirements 5 3. Cost Allocations Cost Categorization Cost Allocation 8 4. Wholesale Rate Calculation 10 Tables Table 1 Summary of Existing FY2013 Wholesale Rates 5 Table 2 Sewer Rate Revenue Requirements 6 Table 3 Summary of FY2014 Cost Categorization Results 8 Table 4 Units of Service (FY2014) 9 Table 5 Units of Service Allocated to Cost Factors 9 Table 6 Unit Cost of Service (FY2014) 10 Table 7 Calculated Wholesale Rates (FY2014) 10 Appendices A Wholesale Rate Calculation Details final - wholesale rate report (1-6-14) i

51 Table of Contents Acronyms and Abbreviations AWTF Advanced Wastewater Treatment Facility CIP Capital Improvement Plan O&M Operations and Maintenance THA FY The Harrisburg Authority Fiscal Year final - wholesale rate report (1-6-14) ii

52 Whosale Wastewater Rate Study Report 1. Introduction 1.1 Rate Study Scope and Objectives This Wholesale Wastewater Rate Study report was prepared for The Harrisburg Authority ( THA ) for the purposes of developing a Wholesale rate for fiscal year ( FY ) THA s fiscal year begins on January 1 of each year. The Wholesale Rate Study and Wholesale rate for FY 2014 was developed by completing the following steps: 1. Determination of THA Sewer Fund Revenue Requirements 2. Allocation of Revenue Requirements to Cost Factors 3. Calculation of Wholesale Rates based on Revenue Requirements, Units of Service, and Inter-Municipal Agreement terms 1.2 Background THA is an operating authority that was formed in 1990 under the Municipal Authorities Act and provides wastewater, water, and solid waste services. THA provides wastewater service to the City of Harrisburg ( City ) and Suburban communities surrounding the City consisting of Penbrook Borough, Paxtang Borough, Swatara Townshop, Lower Paxton Township, Susquehanna Township, and Steelton Borough (the Suburban communities or customers ). THA provides conveyance and treatment services to the Suburban communities in accordance with an inter-municipal agreement, the Second Supplemental Agreement between the City and the Suburban customers dated September 5, 1976 (the Inter-Municipal Agreement ). THA owns and operates an Advanced Wastewater Treatment Facility ( AWTF ) and conveyance system, which it leases to the City. The wastewater and stormwater collection systems within the City limits are currently owned and operated by the City. Under the terms of a transfer agreement between the City and THA, the existing lease and operating agreements between the City and THA are anticipated to be terminated prior to the end of FY 2013, and the ownership and operation of the City s wastewater and stormwater collection systems will be transferred to the THA. 1 The transfer agreement also identifies ongoing services that will be provided by the City to THA, 1 Agreement in Principle between the City of Harrisburg and The Harrisburg Authority, Water, Wastewater, and Stormwater Systems, dated August 14,

53 Whosale Wastewater Rate Study Report including street cleaning and leaf removal, vehicle maintenance and repair, and information technology support. The estimated cost of these services has been included in THA s FY 2014 budget. 1.3 Inter-Municipal Agreement and Existing Suburban Wholesale Rates The Inter-Municipal Agreement contains pricing provisions that specify how the Wholesale rates are established. A summary of the pertinent sections of the Inter- Municipal Agreement is provided below Each Municipality agrees to pay the City for sewage transport, treatment, and disposal services rendered by the City with respect to sewage and wastes emanating from each such Municipality in accordance with Schedule A of the Agreement Each Municipality agrees to pay to the City for each Industrial Establishment, a surcharge for pollutant load for all sewage and waste discharged to the Harrisburg Facilities and emanating from or containing a pollutant load of such strength character as to be classified as high strength by application of generally accepted engineering principles, or provisions of any Grant Agreement, or any state or federal law or regulation, which surcharge shall be determined by the City City agrees to deliver to each Municipality, a statement of any adjustments to the rates and charges for the next calendar year no later than December 1 of any year. The City will cause its Consulting Engineers to prepare and deliver to it no later than October 1 of each year, a report which shall include estimates of Operating Expenses, and other expenditures, costs, revenues, and changes to the rates for the next calendar year Each Municipality covenants to pay all taxes and assessments including income, profits, property, franchise, excise, and/or other taxes levied or assessed by Federal, State or any municipal government against the City upon or by reason of payment or receipt of any sums payable by such Municipality hereunder to the City Each of the Joint Municipalities agrees to pay to the City for sewage transportation, treatment, and disposal, the following separate and 2

54 Whosale Wastewater Rate Study Report distinct charges for customers of any of the Joint Municipalities discharging sewage and wastes to City sewer collection lines referred to in Section 6.01:. A. An amount equal to the amount charged per customer for sewage and wastes discharged through the Harrisburg Conveyance System; and B. An amount equal to the separate amount charged per customer in the City as a sewer maintenance charge (as distinguished from sewer treatment charge) If the City during the term hereof shall incur extra-ordinary costs in repairs to or in replacement of that part of its sewer lines governed by Article VI, to which sewage and wastes are discharged by one or more of the Joint Municipalities, any such Joint Municipality using that part of the sewer lines shall pay to the City such increased annual fees as are adequate to compensate the City for such additional costs If any Joint Municipality during the term hereof shall incur extraordinary costs in repair to or replacements of that part if its sewer collection system used jointly with the City, the City agrees to equitably share in the costs of such extraordinary repairs or replacements or to reduce annual fees paid by such Joint Municipality to the City under this Article VI... Schedule A Rates and Charges for Sewage Services 1. The categories of rates and charges to be paid to the City for sewage transportation, treatment, and disposal services in accordance with Section 5.02 are as follows: (a) Separate rates shall be applied to customers of the City, to customers of the Municipalities discharging wastes through the Harrisburg Conveyance System, and to customers of the Municipalities discharging wastes through the Steelton Conveyance System. (b) For each Residence served by metered water service and for each Non-Residential establishment, a rate per 1,000 gallons of water used shall be charged, subject however to minimum charges. Water used for Non-Residential establishments shall be determined by water meter 3

55 Whosale Wastewater Rate Study Report or by estimates made by the Municipality in accordance with generally accepted engineering standards and practices. (c) For each Residence not served by metered water service, a flat rate shall be charged. 2 The rates and charges described above shall be determined in accordance with the following: (a) Rates apply to all customers of the Municipalities and the City shall be based upon a uniform distribution of the estimated amount to be received allocable to the Operating Expenses of the Harrisburg Facilities, subject to (c). (b) Rates applied to customers in the Municipalities shall equal the rates applied to customers of the City, plus 15 percent of the portion of the City rates that is based on upon the estimated amount to be received allocable to Lease Rental payments and a margin of the same, as required under the Lease, subject to (c). (c) Rates applied to customers of the Municipalities discharging wastes through the Steelton Conveyance System shall be based on the Harrisburg Facilities annual revenue requirements allocated only to the sewage treatment plant. (d) The flat rate for Residences shall be based on the rate for customers with metered water service and an average water usage applicable to Residences in the service area of the Harrisburg Facilities. (e) The minimum rates shall be those minimum rates which are imposed within each of the Municipalities and the City, respectively. The Suburban Wholesale rates that were calculated in FY 2013 are provided in Table 1 for comparison purposes. 4

56 Whosale Wastewater Rate Study Report Table 1 Summary of Existing FY 2013 Wholesale Rates Rate Component City Suburban Steelton O&M Rates Treatment $ $ $ Conveyance Collection Total O&M Rates $ $ $ Lease Rental Rates Treatment $ $ $ Conveyance Collection Total Lease Rental $ $ $ Total $ $ $ Sewer Rate Revenue Requirements THA s sewer rate revenue requirements for a five year period from FY 2014 through FY 2018 ( the forecast period ) were developed based on THA s FY 2014 draft budget dated September 30, 2013, with subsequent modifications provided by THA, and capital improvement plan ( CIP ). Operating expenses for the years subsequent to FY 2014 were estimated by applying cost escalation factors ranging from 2.5 percent and 6.0 percent to individual budget line items, depending upon the type of expense. The rate revenue requirements include operations and maintenance ( O&M ) expenses, existing and projected debt service, pay-as-you-go cash funded capital expenditures, and amounts needed to satisfy a minimum debt service coverage target of 1.20 times, and a working capital target of 90 days. A summary of the rate revenue requirements projected over the forecast period is provided in Table 2. 5

57 Whosale Wastewater Rate Study Report Table 2 Sewer Rate Revenue Requirements Line Fiscal Year Ending December 31 No. Description Operation and Maintenance Expense $ 13,921,196 $ 14,591,271 $ 14,809,071 $ 15,301,347 $ 15,811,116 Capital Expenditures 2 Debt Service 1,709,642 3,009,227 5,881,534 6,411,305 7,123,902 3 Pay-Go Cash Funded Capital 1,933,239 1,877,339 1,526,341 1,579,763 1,653,533 4 Total Capital Expenditures 3,642,881 4,886,566 7,407,875 7,991,068 8,777,436 5 Total O&M and Capital Expenses $ 17,564,077 $ 19,477,838 $ 22,216,945 $ 23,292,415 $ 24,588,552 Less Revenue From Other Sources 6 Miscellaneous Revenue $ (710,000) $ (729,880) $ (750,317) $ (771,326) $ (792,923) 7 Interest Income (14,011) (16,411) (18,375) (18,819) (19,445) 8 Sources & Uses of Funds 228, ,147 54, , ,442 9 Net Rate Revenue Requirements 17,068,938 19,462,693 21,502,703 22,625,340 23,903,626 Rate Revenue Increase From Prior Year 51.0% 14.0% 10.5% 5.2% 5.6% The calculated revenue requirements include both debt service and pay-as-you-go cash funded capital as part of the capital expenses for each year. In prior Wholesale rate calculations, THA included a separate revenue requirement line for meeting a debt service coverage target of 1.1 times, which is in accordance with Schedule A 2(b) of the Inter-Municipal Agreement. THA s financial advisor, Public Resources Advisory Group, has advised THA that it may need to plan to achieve a debt service coverage target of 1.2 times or more in order to be able to execute its capital financing plan. Therefore, the revenue requirements projection shown in Table 2 was established to achieve at least 1.2 times coverage. In FY 2014 and FY 2015, THA plans to fund a sufficient amount of capital projects on a pay-as-you-go basis, which is anticipated to exceed the 1.2 coverage target. In the remaining years of the forecast, the amount of pay-as-you-go cash funding was adjusted from what was contained in THA s capital plan in order to forecast debt service coverage of at least 1.2 times coverage. As a result, a separate revenue requirement line item for debt service coverage was not included in the revenue requirement forecast, as was done in prior Wholesale rate calculations. It is important to note that due to the anticipated transfer agreement between the City and THA, which contains new shared service provisions between the City and THA, there is a greater level of uncertainty regarding the FY 2014 budget than in the past. In addition, the amount and terms of the capital financing anticipated for FY 2014 has not been finalized, and may result in future changes to the FY 2014 budget. However, for the purposes of this study, we have used the current budget information provided by THA to determine the rate revenue requirements as described above. Furthermore, a projection of rate revenue requirements for FY 2015 through FY 2018 is provided for 6

58 Whosale Wastewater Rate Study Report informational purposes only, and the remaining sections of this report focus on the development of the FY 2014 Wholesale wastewater rate calculations. These projected revenue requirements may be subject to change based upon receipt of additional information from THA. To the extent the THA budget or revenue requirement projections change, they may have a material effect on the Wholesale wastewater rates calculated herein. 3. Cost Allocations 3.1 Cost Categorization The rate revenue requirements for FY 2014 were allocated to several different cost factors. These cost factors consist of the following categories: Treatment Related to wastewater treatment, which such costs are shared by all users of the system. Conveyance Related to shared use conveyance facilities, which such costs are shared by all users of the system, except customers whose wastewater flow is conveyed through the Steelton Interceptor. Collection Related to the City s collection system, which such costs are shared only by City customers Other Related to system costs or revenues associated with City-only customers and not shared by other users of the system. In addition, administration costs were first categorized into a separate administration cost category and then subsequently re-allocated to the four categories listed above. The details of the cost allocations and basis for the allocations are provided in Appendix A. A summary of the resulting revenue requirement categorizations for FY 2014 is provided in Table 3, and additional details are provided in Appendix A. O&M revenue requirements are annual O&M costs less miscellaneous revenue offsets. Capital revenue requirements are annual capital costs less miscellaneous revenue offsets. 7

59 Whosale Wastewater Rate Study Report Table 3 Summary of FY 2014 Cost Categorization Results Description Treatment Conveyance Collection Other Total Operating Revenue Requirement $ 7,347,562 $ 2,712,759 $ 2,904,608 $ 232,606 $ 13,197,535 56% 21% 22% 2% Capital Revenue Requirement $ 1,619,168 $ 806,084 $ 1,169,690 $ 47,589 $ 3,642,531 44% 22% 32% 1% Total $ 8,966,730 $ 3,518,843 $ 4,074,298 $ 280,195 $ 16,840,066 53% 21% 24% 2% As described above, the allocation of the capital revenue requirements for FY 2014 includes capital items budgeted in FY 2014 related to GIS mapping and THA s Non Minimum Control Plan and Long-Term Control Plan Update. These items include characterization of wet weather flows in the conveyance system, as well as assessment and planning costs associated with meeting wet weather regulatory requirements. These items were allocated to the cost categories based on current available information and estimates provided by THA. As more characterization and assessment information becomes available in the future, these cost allocations should be re-evaluated. 3.2 Cost Allocation The categorized costs were then allocated to City and Suburban customers based on each customer s estimated proportionate usage of the system. A summary of the units of service associated with City and Suburban customers is summarized in Table 4. 8

60 Whosale Wastewater Rate Study Report Table 4 Units of Service (FY 2014) 1 Non-Metered Non-Metered Metered Total Consumption Consumption Consumption Consumption Customer Class EDU's (1,000 gallons) (1,000 gallons) (1,000 gallons) City of Harrisburg - - 1,473,126 1,473,126 Penbrook Borough 1,332 86,580 10,838 97,418 Paxtang Borough ,550 5,669 49,219 Swatara Township - via Harrisburg , ,829 Swatara Township - via Steelton ,366 70,366 Lower Paxton Township 12, , ,393 1,027,028 Susquehanna Township 10, , , ,316 Steelton Borough ,074 97,074 Total 25,606 1,664,390 2,469,986 4,134,376 1 Based on FY 2012 billing data provided by the City. 2 One EDU w as assumed to equal 65,000 gallons of residential non-metered consumption per year. According to the City, a significant number of City customer water meters were not recording water readings properly in FY 2012 because some of the electric water meters had batteries that were expired. For the purposes of billing, the City used estimated consumption from prior periods to bill these customers. We have incorporated these estimated readings in the units of service shown in Table 4. The unit cost of service was calculated by dividing the categorized costs by the units of service. The units of service were distributed to each cost category as shown in Table 5 based on the system characteristics associated with each customer type. A summary of the unit cost of service is provided in Table 6. Table 5 Units of Service Allocated to Cost Factors Allocation (%) Customer Class Treatment Conveyance Collection Other City of Harrisburg 100% 100% 100% 100% Penbrook Borough 100% 100% 0% 0% Paxtang Borough 100% 100% 0% 0% Swatara Township - via Harrisburg 100% 100% 0% 0% Swatara Township - via Steelton 100% 0% 0% 0% Lower Paxton Township 100% 100% 0% 0% Susquehanna Township 100% 100% 0% 0% Steelton Borough 100% 0% 0% 0% 9

61 Whosale Wastewater Rate Study Report Table 6 Unit Cost of Service (FY 2014) Description Treatment Conveyance Collection Other Units of Service (1,000 gallons) 4,134,376 3,966,936 1,473,126 1,473,126 Operating Revenue Requirement $ 7,347,562 $ 2,712,759 $ 2,904,608 $ 232,606 Capital Revenue Requirement $ 1,619,168 $ 806,084 $ 1,169,690 $ 47,589 Operating Unit Cost ($/1,000 gallons) $1.78 $0.68 $1.97 $0.16 Capital Unit Cost ($/1,000 gallons) $0.39 $0.20 $0.79 $ Wholesale Rate Calculation Wholesale rates were calculated for the Suburban customers for FY 2014 based on the calculated unit cost of service, each Suburban customer s units of service, and the terms of the Agreement. A summary of the calculated Wholesale wastewater rates for FY 2014 is provided in Table 7. Table 7 Calculated Wholesale Rates (FY 2014) Customer Class Description City Suburbs 1 Steelton 2 O&M Rate Treatment $1.78 $1.78 $1.78 Conveyance $0.68 $0.68 $0.00 Collection $1.97 $0.00 $0.00 Other $0.16 $0.00 $0.00 Total O&M Rate ($/1,000 gallons) $4.59 $2.46 $1.78 Capital Charge (Lease Rental Rates) 3 Treatment $0.39 $0.45 $0.45 Conveyance $0.20 $0.23 $0.00 Collection $0.79 $0.00 $0.00 Other $0.03 $0.00 $0.00 Total Capital Charge ($/1,000 gallons) $1.42 $0.68 $0.45 Total Rate ($/1,000 gallons) 4 $6.01 $3.15 $ Penbrook and Paxtang Borough, and Sw atara, Low er Paxton, and Susquehanna Tow nship. 2 Steelton Borough and a portion of Sw atara do not share in the conveyance system costs. 3 Reflects a 15% adjustment to the unit costs per Section 2b of Schedule A of the Agreement. 4 The Wholesale Rate Report prepared in November 2013 calculated a total Suburban rate of $3.00 per 1,000 gallons. This report assumed higher nutrient credit costs, w hich increased the Suburban rates as show n above. For revenue forecasting purposes, a rate of $3.00 per 1,000 gallons w as assumed for Wholesale customers. 10

62 Whosale Wastewater Rate Study Report In preparing the Wholesale rate calculations, we have assumed that the Inter-Municipal Agreement between the City and the Suburban customers, and associated pricing terms, would be transferred to THA. We have also assumed that the lease rental rates shall be replaced by a capital charge, consisting of annual wastewater debt service and pay-as-you-go capital expenditures, since it is anticipated that the lease agreement between the City and THA will be terminated with the transfer agreement that is anticipated to be executed by the end of FY

63 Appendix A Wholesale Rate Calculation Details

64 Table A.1 Operating Expense Allocation The Harrisburg Authority Wholesale Cost Allocation Study FY2014 Alloc Allocation % Allocation $ Line Dept Description Projected Ref Treatment Conveyance Collection Administration Other Treatment Conveyance Collection Administration Other 2010 Sewerage Administration Division Administration - Personnel: Salaries & Wages $ 158, % 17.1% 5.0% 0.0% 0.0% $ 123,699 $ 27,231 $ 7,944 $ - $ Overtime % 17.1% 5.0% 0.0% 0.0% Sick Leave Buy-Back % 17.1% 5.0% 0.0% 0.0% Social Security 12, % 17.1% 5.0% 0.0% 0.0% 9,463 2, Medical % 17.1% 5.0% 0.0% 0.0% Severance Pay % 17.1% 5.0% 0.0% 0.0% Pension 5, % 17.1% 5.0% 0.0% 0.0% 4, Leave Payout 78, % 17.1% 5.0% 0.0% 0.0% 61,189 13,470 3, Unemployment Comp % 17.1% 5.0% 0.0% 0.0% Workers' Comp-Adj % 17.1% 5.0% 0.0% 0.0% Loss Time & Med % 17.1% 5.0% 0.0% 0.0% State Fees & Assess % 17.1% 5.0% 0.0% 0.0% Excess Policy & Bon % 17.1% 5.0% 0.0% 0.0% Administration - Operating: Advertising $ 2, % 0.0% 0.0% 100.0% 0.0% $ - $ - $ - $ 2,000 $ Printing 8, % 0.0% 0.0% 100.0% 0.0% , Telephone 12, % 0.0% 0.0% 100.0% 0.0% , Postage 1, % 0.0% 0.0% 100.0% 0.0% , Legal - 0.0% 0.0% 0.0% 100.0% 0.0% Audit - 0.0% 0.0% 0.0% 100.0% 0.0% Consulting 20, % 30.0% 10.0% 0.0% 0.0% 12,000 6,000 2, Collection (Opt & LI - 0.0% 0.0% 0.0% 100.0% 0.0% Other Professional 90, % 0.0% 0.0% 0.0% 0.0% 90, Stop / Loss Premium - 0.0% 0.0% 0.0% 100.0% 0.0% Automobile Prem - 0.0% 0.0% 0.0% 100.0% 0.0% Auto Deduct - 0.0% 0.0% 0.0% 100.0% 0.0% General Liability - 0.0% 0.0% 0.0% 100.0% 0.0% Boiler - 0.0% 0.0% 0.0% 100.0% 0.0% Property & Crime - 0.0% 0.0% 0.0% 100.0% 0.0% Property Deduct - 0.0% 0.0% 0.0% 100.0% 0.0% Inland Marine - 0.0% 0.0% 0.0% 100.0% 0.0% Flood Prem - 0.0% 0.0% 0.0% 100.0% 0.0% Public Off Prem - 0.0% 0.0% 0.0% 100.0% 0.0% Excess Liability - 0.0% 0.0% 0.0% 100.0% 0.0% Terrorism - 0.0% 0.0% 0.0% 100.0% 0.0% Uniform Rentals 10, % 29.0% 27.7% 0.0% 0.0% 4,322 2,904 2, Service Contracts - 0.0% 0.0% 0.0% 100.0% 0.0% Maint Serv Contract - 0.0% 0.0% 0.0% 100.0% 0.0% Tuition/Training 7, % 0.0% 0.0% 100.0% 0.0% , Admin/Trustee Fee - 0.0% 0.0% 0.0% 100.0% 0.0% Laundry - 0.0% 0.0% 0.0% 100.0% 0.0% Travel - 0.0% 0.0% 0.0% 100.0% 0.0% Conferences 1, % 0.0% 0.0% 100.0% 0.0% , Memberships - 0.0% 0.0% 0.0% 100.0% 0.0% Disaster Recovery - 0.0% 0.0% 0.0% 100.0% 0.0% Misc Contract Srv - 0.0% 0.0% 0.0% 100.0% 0.0% Bank Serv Charges - 0.0% 0.0% 0.0% 100.0% 0.0% Software 71, % 59.2% 31.0% 0.0% 0.0% 6,949 42,212 22, Subscriptions % 0.0% 0.0% 100.0% 0.0% Photography - 0.0% 0.0% 0.0% 100.0% 0.0% Data Processing - 0.0% 0.0% 0.0% 100.0% 0.0% Office 2, % 0.0% 0.0% 100.0% 0.0% , Misc Supplies - 0.0% 0.0% 0.0% 100.0% 0.0%

Capital Region Water. Water and Wastewater Rate Study Report. November 22, Capital Region Water Water and Wastewater Rate Study

Capital Region Water. Water and Wastewater Rate Study Report. November 22, Capital Region Water Water and Wastewater Rate Study Capital Region Water Water and Wastewater Rate Study Report November 22, 2017 Capital Region Water Water and Wastewater Rate Study TABLE OF CONTENTS 1. INTRODUCTION...1 1.1 RATE STUDY SCOPE AND OBJECTIVES...1

More information

Capital Region Water Proposed 2019 Budget and Rates. November 20, 2018

Capital Region Water Proposed 2019 Budget and Rates. November 20, 2018 Capital Region Water Proposed 2019 Budget and Rates November 20, 2018 Road Map Successes to Date and Challenges Ahead Budget and Rate Setting Process Proposed 2019 Budgets and Rates Questions and Comments

More information

2008 Water System Annual Report and 2009 Operating Budget

2008 Water System Annual Report and 2009 Operating Budget DRAFT The Greenville Water Authority Mercer County, Pennsylvania 2008 Water System Annual Report and 2009 Operating Budget February 2009 1. INTRODUCTION 1.1 Introduction... 1.1 1.2 Greenville Water Authority

More information

SAUSALITO-MARIN CITY SANITARY DISTRICT 1 EAST ROAD SAUSALITO, CALIFORNIA Telephone: (415) Fax: (415)

SAUSALITO-MARIN CITY SANITARY DISTRICT 1 EAST ROAD SAUSALITO, CALIFORNIA Telephone: (415) Fax: (415) 1 EAST ROAD SAUSALITO, CALIFORNIA Telephone: (415) 332-0244 Fax: (415) 332-0453 Budget FY 2017/18 Adopted by Board on June 5, 2017 BUDGET EXECUTIVE SUMMARY FISCAL YEAR 2017/18 DISTRICT OVERVIEW The Sausalito-Marin

More information

:;ols. Name of Community Carroll Township Authority Charleroi Authority. Rostraver Authority. Monongahela Authority Belle Vernon Authority

:;ols. Name of Community Carroll Township Authority Charleroi Authority. Rostraver Authority. Monongahela Authority Belle Vernon Authority FUTURE RATE INCREASES The Authority is currently working with its consulting engineering firm Gannett Fleming, Inc. to revise its current rate structure. The new rates are expected to be approved in October

More information

REGULATORY FEE RECOMMENDATION REPORT TO THE ENVIRONMENTAL QUALITY BOARD

REGULATORY FEE RECOMMENDATION REPORT TO THE ENVIRONMENTAL QUALITY BOARD REGULATORY FEE RECOMMENDATION REPORT TO THE ENVIRONMENTAL QUALITY BOARD NPDES Permit and Annual Fees Chapter 92a. National Pollutant Discharge Elimination System Permitting, Monitoring and Compliance BACKGROUND:

More information

Wastewater Utilities. FY Budget Presentation

Wastewater Utilities. FY Budget Presentation Utilities FY 2018-19 Budget Presentation 1 Volume Forecast Wastewater Customers by Class Fiscal Year Residential Commercial Wholesale Total Growth 2013 26,995 1.1% 3,091 0.8% 4 30,090 1.1% 2014 27,548

More information

Derry Township Municipal Authority Wastewater Fund Budget

Derry Township Municipal Authority Wastewater Fund Budget Derry Township Municipal Authority 2019 Wastewater Fund Budget APPROVED DTMA Board Resolution #2018-51 November 19, 2018 TABLE 1 OPERATING FUND Comparative Cash Budget (in thousands) Category / Item 2019

More information

SIGNIFICANT BUDGET CHANGES

SIGNIFICANT BUDGET CHANGES Department of Environmental Services Our Mission: To build and maintain water delivery, sanitary sewer collection, and wastewater treatment systems that provide high-quality water and sewer services and

More information

CITY OF DETROIT, MICHIGAN_Sewage Disposal System Revenue

CITY OF DETROIT, MICHIGAN_Sewage Disposal System Revenue CITY OF DETROIT, MICHIGAN_Sewage Disposal System Revenue MICHIGAN FINANCE AUTHORITY, Local Government Loan Program Revenue Bonds, Series 2014C 1 (Detroit Water and Sewerage Department Sewage Disposal System

More information

Wastewater Rate Study. Villa Park, Illinois

Wastewater Rate Study. Villa Park, Illinois Wastewater Rate Study Villa Park, Illinois June 2013 Executive Summary General The Village of Villa Park s Wastewater Utility is responsible for operation and maintenance of the Village s separate sanitary

More information

2016 WATER SYSTEM ANNUAL REPORT & 2017 OPERATING BUDGET

2016 WATER SYSTEM ANNUAL REPORT & 2017 OPERATING BUDGET THE GREENVILLE WATER AUTHORITY M E RCER COUNTY, PENNS YLV AN I A 2016 WATER SYSTEM ANNUAL REPORT & 2017 OPERATING BUDGET Prepared by: Robert J. Horvat www.entecheng.com Project No.: 4631.01 Dated: Entech

More information

Stormwater Management Fee Policy Options and Recommendations

Stormwater Management Fee Policy Options and Recommendations Green Infrastructure Advisory Committee Report Stormwater Management Fee Policy Options and Recommendations Prepared for City of Lancaster, PA March 17, 2014 1717 Arch Street Suite 4400 Philadelphia, PA

More information

FRANKLIN TOWNSHIP MUNICIPAL SANITARY AUTHORITY SERVICE AGREEMENT

FRANKLIN TOWNSHIP MUNICIPAL SANITARY AUTHORITY SERVICE AGREEMENT FRANKLIN TOWNSHIP MUNICIPAL SANITARY AUTHORITY SERVICE AGREEMENT INDUSTRIAL SEWER USE SERVICE AGREEMENT This Service Agreement, dated as of the day of,, by and between the Franklin Township Municipal Sanitary

More information

Town Hall Meeting Community Utilities of Indiana, Inc. Wednesday, Wednesday 29, :00PM - 8:00PM at Seasons Lakehouse 1048 N.

Town Hall Meeting Community Utilities of Indiana, Inc. Wednesday, Wednesday 29, :00PM - 8:00PM at Seasons Lakehouse 1048 N. Town Hall Meeting Community Utilities of Indiana, Inc. Wednesday, Wednesday 29, 2018 7:00PM - 8:00PM at Seasons Lakehouse 1048 N. Lakeshore Drive, Crown Point, Indiana Community Utilities of Indiana, Inc.

More information

Sewer and Water Permit Check List

Sewer and Water Permit Check List 18 East High Street, Manheim, PA 17545-1506 Phone: 717-665-2737 Fax: 888-602-5300 Web: www.mawsa.org Sewer and Water Permit Check List Sewer Permit Sewer Regulations/Fees Water Permit Water Regulations/Fees

More information

2018 SEWER PERMIT APPLICATION updated 1/4/18

2018 SEWER PERMIT APPLICATION updated 1/4/18 18 East High Street, Manheim, PA 17545-1506 Phone: 717-665-2737 Fax: 888-602-5300 Web: www.mawsa.org 2018 SEWER PERMIT APPLICATION updated 1/4/18 Date: Applicant Name: Property Owner (if different than

More information

Wastewater Utility Enterprise

Wastewater Utility Enterprise Wastewater Utility Enterprise Wastewater Utility Operating Fund Summary Wastewater Utility Revenue (62) Wastewater Utility Collection Systems Operations (62-4510) Wastewater Treatment Operations (62-4515)

More information

STONY BROOK REGIONAL SEWERAGE AUTHORITY

STONY BROOK REGIONAL SEWERAGE AUTHORITY STONY BROOK REGIONAL SEWERAGE AUTHORITY HOPEWELL BOROUGH HOPEWELL TOWNSHIP PENNINGTON BOROUGH PRINCETON SOUTH BRUNSWICK TOWNSHIP WEST WINDSOR TOWNSHIP STONY BROOK REGIONAL SEWERAGE AUTHORITY Financial

More information

SIGNIFICANT BUDGET CHANGES

SIGNIFICANT BUDGET CHANGES Department of Environmental Services Our Mission: To build and maintain water delivery, sanitary sewer collection, and wastewater treatment systems that provide high-quality water and sewer services and

More information

SIGNIFICANT BUDGET CHANGES

SIGNIFICANT BUDGET CHANGES Department of Environmental Services Our Mission: To build and maintain water delivery, sanitary sewer collection, and wastewater treatment systems that provide high-quality water and sewer services and

More information

RE:EX Toronto Water CAPITAL BUDGET NOTES CONTENTS CONTACTS CAPITAL BUDGET AND PLAN OVERVIEW. Overview

RE:EX Toronto Water CAPITAL BUDGET NOTES CONTENTS CONTACTS CAPITAL BUDGET AND PLAN OVERVIEW. Overview RE:EX29.18 CAPITAL BUDGET NOTES CONTENTS Overview 1: Recommended 10-Year Capital Plan 5 2: Issues for Discussion 22 Appendices: 1. 2017 Performance 30 2. Recommended 10-Year Capital Plan Summary 32 Toronto

More information

PETERS TOWNSHIP SANITARY AUTHORITY. Audited Financial Statements and Required Supplementary Information

PETERS TOWNSHIP SANITARY AUTHORITY. Audited Financial Statements and Required Supplementary Information Audited Financial Statements and Required Supplementary Information For The Years Ended TABLE OF CONTENTS PAGE NO.... Independent Auditors Report. i-xiv... Management Discussion and Analysis. 1... Statements

More information

Water Consultancy. Montecito Sanitary District Wastewater Rate Study Report. Montecito Sanitary District

Water Consultancy. Montecito Sanitary District Wastewater Rate Study Report. Montecito Sanitary District 3585 Maple Street, Suite 250 Ventura, CA 93003 805-404-1467 Montecito Sanitary District Wastewater Rate Study Report March 2016 Montecito Sanitary District 1042 Monte Cristo Lane Santa Barbara CA 93108

More information

STORMWATER MANAGEMENT FUND DEPARTMENT OF ENVIRONMENTAL SERVICES

STORMWATER MANAGEMENT FUND DEPARTMENT OF ENVIRONMENTAL SERVICES DEPARTMENT OF ENVIRONMENTAL SERVICES Mission: To implement a comprehensive stormwater management program that balances the following goals: 1) to reduce the potential for stormwater threats to public health,

More information

WATER AND WASTEWATER FUND REVENUES

WATER AND WASTEWATER FUND REVENUES WATER AND WASTEWATER FUND REVENUES Water revenues comprise $12.11 million, or 70.6% of total revenues of the fund, while wastewater (sewer) charges comprise $4.25 million, or 24.7% of total revenues. Water

More information

Cutting Costs through Regional

Cutting Costs through Regional Cutting Costs through Regional Stormwater Management Presented by: Jim Tomaine, P.E. Executive Director, Wyoming Valley Sanitary Authority Adrienne Vicari, P.E. Financial Services Practice Area Leader

More information

Peters Township Sanitary Authority. Summary Report of Tapping Fee Calculation and Connection Charges

Peters Township Sanitary Authority. Summary Report of Tapping Fee Calculation and Connection Charges Peters Township Sanitary Authority Summary Report of Tapping Fee Calculation and Connection Charges June 30, 2008 Update No. 2 August 12, 2008 Summary Report Tapping Fee Calculation and Connection Charges

More information

Fiscal Year Budget Proposal

Fiscal Year Budget Proposal Fiscal Year 20182019 Budget Proposal Board of Directors March 27, 2018 RIVANNA WATER & SEWER AUTHORITY FY 2019 Proposed Budget Table of Contents Budget Highlights Prepared: March 6, 2018 Adopted: Draft

More information

City of Centerville BMP Pages Table of Contents. Minimum Control Measure 1. Public Education and Outreach

City of Centerville BMP Pages Table of Contents. Minimum Control Measure 1. Public Education and Outreach i City of Centerville s Table of Contents Minimum Control Measure 1. Public Education and Outreach Best Management Practice Page 1-1: Outreach Publications...1 1-2: 30-day Public Notice for Annual Storm

More information

DRAFT ORDINANCE NO. 656 ORDINANCE ESTABLISHING USER RATES. Rates Effective May 1, 2019 This Ordinance No. 656 Supersedes Ordinance No.

DRAFT ORDINANCE NO. 656 ORDINANCE ESTABLISHING USER RATES. Rates Effective May 1, 2019 This Ordinance No. 656 Supersedes Ordinance No. DRAFT ORDINANCE NO. 656 ORDINANCE ESTABLISHING USER Rates Effective May 1, 2019 This Ordinance. 656 Supersedes Ordinance. 644 WHEREAS, the Board of Trustees (Board) of the Wheaton Sanitary District (the

More information

Finance Committee Meeting

Finance Committee Meeting Finance Committee Meeting FY19 Strategic Business and Operating Plan and Preliminary Budget Review April 3, 2018 1 Finance Committee Meeting FY19 Strategic Business Operating Plan and Preliminary Budget

More information

Chicopee River CSO Project Springfield Water & Sewer Commission. APWA Congress September 9, CSO Control Plan. CSO Control

Chicopee River CSO Project Springfield Water & Sewer Commission. APWA Congress September 9, CSO Control Plan. CSO Control Chicopee River CSO Project Springfield Water & Sewer Commission APWA Congress September 9, 2007 CSO Control Plan Typical Approach Different Thinking on Controlling Costs Case Example Springfield MA CSO

More information

STEGE SANITARY DISTRICT FINANCIAL PLAN AND RATE REVIEW

STEGE SANITARY DISTRICT FINANCIAL PLAN AND RATE REVIEW STEGE SANITARY DISTRICT FINANCIAL PLAN AND RATE REVIEW June 2014 BARTLE WELLS ASSOCIATES Independent Public Finance Advisors 1889 Alcatraz Avenue Berkeley CA 94703 Tel. 510/653-3399 TABLE OF CONTENTS

More information

Lancaster Area Sewer Authority 130 Centerville Rd Lancaster PA 17603

Lancaster Area Sewer Authority 130 Centerville Rd Lancaster PA 17603 LANCASTER AREA SEWER AUTHORITY 2014 2015 BUDGET REPORT Lancaster Area Sewer Authority 130 Centerville Rd Lancaster PA 17603 Tel. 717-299-4843 Fax 717-299-9658 www.lasa.org Table of Contents Page Section

More information

Finance Committee Meeting

Finance Committee Meeting Finance Committee Meeting FY18 Strategic Business and Operating Plan and Preliminary Budget Review April 04, 2017 1 Finance Committee Meeting FY18 Strategic Business Operating Plan and Preliminary Budget

More information

Finance Committee Meeting

Finance Committee Meeting Finance Committee Meeting FY16 Strategic Business and Operating Plan and Preliminary Budget Review April 8, 2015 Finance Committee Meeting FY16 Strategic Business Operating Plan and Preliminary Budget

More information

WATER, WASTEWATER, STORMWATER, AND MUNICIPAL SOLID WASTE COST OF SERVICE AND RATE DESIGN STUDY

WATER, WASTEWATER, STORMWATER, AND MUNICIPAL SOLID WASTE COST OF SERVICE AND RATE DESIGN STUDY REPORT January 2017 WATER, WASTEWATER, STORMWATER, AND MUNICIPAL SOLID WASTE COST OF SERVICE AND RATE DESIGN STUDY PREPARED BY: ECONOMICS STRATEGY STAKEHOLDERS SUSTAINABILITY www.newgenstrategies.net 3420

More information

City of San Carlos Sewer Financial Plan & Rate Update

City of San Carlos Sewer Financial Plan & Rate Update City of San Carlos Sewer Financial Plan & Rate Update Revised 06/13/16 1889 Alcatraz Avenue Berkeley, CA 94703 Tel: 510 653 3399 www.bartlewells.com June 13, 2016 City of San Carlos Department of Public

More information

WATER POLLUTION CONTROL

WATER POLLUTION CONTROL WATER POLLUTION CONTROL WATER POLLUTION CONTROL NARRATIVE City of Warrensburg Water Pollution Control Division is under the supervision of the Public Works Department. The Administration budget includes

More information

MANHEIM AREA WATER & SEWER AUTHORITY Resolution : Fee Schedule

MANHEIM AREA WATER & SEWER AUTHORITY Resolution : Fee Schedule MANHEIM AREA WATER & SEWER AUTHORITY Resolution 7 2015: Fee Schedule NOW THEREFORE BE IT RESOLVED that the Manheim Area Water & Sewer Authority hereby establish the following fees for services rendered:

More information

LIBERTY UTILITIES (ENTRADA DEL ORO SEWER) CORP.

LIBERTY UTILITIES (ENTRADA DEL ORO SEWER) CORP. DOCKET NO. SW-04316A-16-0078, et al. Sheet No. i 1 TABLE OF CONTENTS Pan One Statement of No. l 1. Rates 11. Taxes and Assessments...Sheet No. 2 111. Additional Charges No. 3. n. Permitted Sheet No. 4

More information

Final Report Water and Sewer Rate Model Town of Denton, MD

Final Report Water and Sewer Rate Model Town of Denton, MD Final Report Water and Sewer Rate Model Town of Denton, MD January 30, 2014 MCET Water and Sewer Rate Model for Denton, MD Page 1 Table of Contents Water and Sewer Rate Model Study Town of Denton, MD January

More information

San Francisco Public Utilities Commission

San Francisco Public Utilities Commission San Francisco Public Utilities Commission Water & Wastewater Rate Study Report March 6, 2009 Prepared by: Table of Contents I. EXECUTIVE SUMMARY...1 A. Pricing Objectives...2 B. Review of Findings Water...2

More information

STORMWATER MANAGEMENT FUND DEPARTMENT OF ENVIRONMENTAL SERVICES

STORMWATER MANAGEMENT FUND DEPARTMENT OF ENVIRONMENTAL SERVICES DEPARTMENT OF ENVIRONMENTAL SERVICES Mission: To implement a comprehensive stormwater management program that balances the following goals: 1) to reduce the potential for stormwater threats to public health,

More information

SUMMERLAND SANITARY DISTRICT

SUMMERLAND SANITARY DISTRICT SUMMERLAND SANITARY DISTRICT Financial Plan and Rate Study December 6, 2017 445 S. Figueroa Street Suite #2270 Los Angeles, CA 90071 Phone 213.262.9300 Fax 213.262.9303 www.raftelis.com December 6, 2017

More information

Rate Schedule. Fiscal Year-2018 (July 1, 2017 June 30, 2018) P.O. Box 5911 Virginia Beach, Virginia

Rate Schedule. Fiscal Year-2018 (July 1, 2017 June 30, 2018) P.O. Box 5911 Virginia Beach, Virginia Rate Schedule Fiscal Year-2018 (July 1, 2017 June 30, 2018) P.O. Box 5911 Virginia Beach, Virginia 23471-0911 757.460.2491 www.hrsd.com HRSD Rate Schedule Fiscal Year-2018 (July 1, 2017 June 30, 2018)

More information

THE MUNICIPAL AUTHORITY OF THE TOWNSHIP OF ROBINSON

THE MUNICIPAL AUTHORITY OF THE TOWNSHIP OF ROBINSON THE MUNICIPAL AUTHORITY OF THE TOWNSHIP OF ROBINSON ALLEGHENY COUNTY, PENNSYLVANIA ANNUAL CONSULTING ENGINEER S REPORT FOR OPERATING YEAR 6-30-14 TO 6-30-15 AND BUDGET FOR FISCAL YEAR ENDING 6-30-16 NIRA

More information

SANITARY SEWER FUND PUBLIC WORKS

SANITARY SEWER FUND PUBLIC WORKS 285 2015 2016 2017 2017 2018 Actual Actual Budget Estimate Budget Beginning Net Position $ 1,556,256 $ 2,133,912 $ 3,537,945 $ 3,537,945 $ 3,333,823 Operating Revenue 5,758,183 6,475,486 6,751,246 6,681,766

More information

2016 Collection Systems Workshop. Asset Management for Small to Midsized Communities

2016 Collection Systems Workshop. Asset Management for Small to Midsized Communities 2016 Collection Systems Workshop FISHBECK, THOMPSON, CARR & HUBER, INC. Asset Management for Small to Midsized Communities Ohio Water Environment Association May 18 2016 An asset management program identifies

More information

Stormwater Utility Agency Overview

Stormwater Utility Agency Overview Stormwater Utility Agency Overview Agency Mission The mission of the Stormwater Utility is to provide stormwater management services to the City of Madison with an equitable rate structure. Agency Overview

More information

Stormwater Utility Agency Overview

Stormwater Utility Agency Overview Agency Overview Agency Mission The mission of the Stormwater Utility is to provide stormwater management services to the City of Madison with an equitable rate structure. Agency Overview The Stormwater

More information

CITY OF ALBANY CITY COUNCIL AGENDA STAFF REPORT

CITY OF ALBANY CITY COUNCIL AGENDA STAFF REPORT CITY OF ALBANY CITY COUNCIL AGENDA STAFF REPORT Agenda date: July 31, 2017 Reviewed by: PC SUBJECT: FROM: Public Hearing on Proposal to increase monthly sewer service charges for purposes of environmental

More information

Rate Schedule. Fiscal Year-2015 (July 1, 2014 June 30, 2015) Amended July 22, 2014 Amended August 26, 2014

Rate Schedule. Fiscal Year-2015 (July 1, 2014 June 30, 2015) Amended July 22, 2014 Amended August 26, 2014 Rate Schedule Fiscal Year-2015 (July 1, 2014 June 30, 2015) Amended July 22, 2014 Amended August 26, 2014 P.O. Box 5911 Virginia Beach, Virginia 23471-0911 757.460.2491 www.hrsd.com HRSD Rate Schedule

More information

CAPITAL IMPROVEMENT PROGRAM CAPITAL IMPROVEMENT PROGRAM FY FY

CAPITAL IMPROVEMENT PROGRAM CAPITAL IMPROVEMENT PROGRAM FY FY CAPITAL IMPROVEMENT PROGRAM CAPITAL IMPROVEMENT PROGRAM FY 2017-2021 FY 2017-2021 Narraganse Bay Commission Vincent J. Mesolella Chairman Raymond J. Marshall, P.E. Execu ve Director Capital Project Summary

More information

DATE: September 12, 2017 REPORT NO. PW Chair and Members Committee of the Whole Operations and Administration

DATE: September 12, 2017 REPORT NO. PW Chair and Members Committee of the Whole Operations and Administration DATE: September 12, 2017 REPORT NO. PW2017-061 TO: FROM: Chair and Members Committee of the Whole Operations and Administration E. (Beth) Goodger, General Manager Public Works Commission 1.0 TYPE OF REPORT

More information

TITLE 18. ENVIRONMENTAL QUALITY CHAPTER 14. DEPARTMENT OF ENVIRONMENTAL QUALITY PERMIT AND COMPLIANCE FEES ARTICLE 1. WATER QUALITY PROTECTION FEES

TITLE 18. ENVIRONMENTAL QUALITY CHAPTER 14. DEPARTMENT OF ENVIRONMENTAL QUALITY PERMIT AND COMPLIANCE FEES ARTICLE 1. WATER QUALITY PROTECTION FEES Section R18-14-101. R18-14-102. Table 1. R18-14-103. R18-14-104. Table 2. Table 3. R18-14-105. R18-14-106. R18-14-107. R18-14-108. Table 4. Table 5. R18-14-109. Table 6. R18-14-110. Table 7. R18-14-111.

More information

TOWN OF DEEP RIVER AND TOWN OF CHESTER INTERMUNICIPAL WASTEWATER TREATMENT AGREEMENT

TOWN OF DEEP RIVER AND TOWN OF CHESTER INTERMUNICIPAL WASTEWATER TREATMENT AGREEMENT TOWN OF DEEP RIVER AND TOWN OF CHESTER INTERMUNICIPAL WASTEWATER TREATMENT AGREEMENT This INTERMUNICIPAL WASTEWATER TREATMENT AGREEMENT ( Agreement ), dated as of August 19, 2005, is made and entered into

More information

COMPREHENSIVE COST OF SERVICE AND RATE DESIGN ANALYSIS

COMPREHENSIVE COST OF SERVICE AND RATE DESIGN ANALYSIS Black & Veatch Holding Company 2011. All rights reserved. COMPREHENSIVE COST OF SERVICE AND RATE DESIGN ANALYSIS San Antonio Water System PREPARED FOR San Antonio Water System 26 MAY 2015 B&V PROJECT NO.

More information

City of Des Moines. Budget Workshop. December 7, 2015

City of Des Moines. Budget Workshop. December 7, 2015 City of Des Moines Budget Workshop December 7, 2015 Today s Agenda SSMID Review Sanitary and Storm Sewer 2 Self-Supported Municipal Improvement Districts 3 Operation and Terms Each SSMID has a separate

More information

STORMWATER MANAGEMENT FUND Department of Environmental Services

STORMWATER MANAGEMENT FUND Department of Environmental Services Department of Environmental Services Mission: To implement a comprehensive stormwater management program that balances the following goals: 1) to reduce the potential for stormwater threats to public health,

More information

CITY OF ALHAMBRA UTILITIES DEPARTMENT SEWER SYSTEM MAINTENANCE PROGRAM (SSMP)

CITY OF ALHAMBRA UTILITIES DEPARTMENT SEWER SYSTEM MAINTENANCE PROGRAM (SSMP) CITY OF ALHAMBRA UTILITIES DEPARTMENT SEWER SYSTEM MAINTENANCE PROGRAM (SSMP) APRIL 2009 Table of Contents INTRODUCTION... 3 SECTION I: GOALS... 3 SECTION II: ORGANIZATION... 4 SECTION III: LEGAL AUTHORITY...

More information

Revenue Plan. August 12, Dennis Davies Deputy Director of Public Works 200 Civic Center Way El Cajon, CA 92020

Revenue Plan. August 12, Dennis Davies Deputy Director of Public Works 200 Civic Center Way El Cajon, CA 92020 1925 Palomar Oaks Way, Suite 3 Carlsbad, California 928 tel: 76 438 7755 fax: 76 438 7411 Dennis Davies Deputy Director of Public Works 2 Civic Center Way El Cajon, CA 922 Subject: Six Year Revenue Plan

More information

DRAFT COMPREHENSIVE COST OF SERVICE AND RATE DESIGN ANALYSIS. San Antonio Water System. San Antonio Water System 21 MAY 2015 PREPARED FOR

DRAFT COMPREHENSIVE COST OF SERVICE AND RATE DESIGN ANALYSIS. San Antonio Water System. San Antonio Water System 21 MAY 2015 PREPARED FOR Black & Veatch Holding Company 2011. All rights reserved. DRAFT COMPREHENSIVE COST OF SERVICE AND RATE DESIGN ANALYSIS San Antonio Water System PREPARED FOR San Antonio Water System 21 MAY 2015 B&V PROJECT

More information

CITY OF ROSEBURG, OREGON TABLE OF CONTENTS ENTERPRISE FUNDS

CITY OF ROSEBURG, OREGON TABLE OF CONTENTS ENTERPRISE FUNDS TABLE OF CONTENTS ENTERPRISE FUNDS Storm Drainage Fund... 121-124 Off Street Parking Fund... 125-126 Airport Fund... 127-131 Water Service Fund... 132-145 STORM DRAINAGE FUND CURRENT OPERATIONS This fund

More information

FTE 1 Table Year (proposed) # Budgeted FTE s

FTE 1 Table Year (proposed) # Budgeted FTE s P1 ENVIRONMENTAL SERVICES DEPARTMENT PROPOSED SERVICE PLAN 2019-2022 1. Mandate: Environmental Services (ENVS) provides leadership in environmental protection and sustainable service for the citizens of

More information

City Council Report 915 I Street, 1 st Floor

City Council Report 915 I Street, 1 st Floor Meeting Date: 6/25/2013 Report Type: Consent Report ID: 2013-00467 22 City Council Report 915 I Street, 1 st Floor www.cityof.org Title: Agreement: Regional County Sanitation District for Wastewater Operations

More information

PETERS TOWNSHIP SANITARY AUTHORITY 2011 BUDGET WORKSHOP. November 30, 2010

PETERS TOWNSHIP SANITARY AUTHORITY 2011 BUDGET WORKSHOP. November 30, 2010 PETERS TOWNSHIP SANITARY AUTHORITY 2011 BUDGET WORKSHOP November 30, 2010 Agenda A. 2010 Budget Performance Summary B. 2011 Budget Request C. 2011 Capital Plan D. Consulting Engineer s Annual Report Preliminary

More information

City of Rohnert Park SEWER FINANCIAL PLAN

City of Rohnert Park SEWER FINANCIAL PLAN City of Rohnert Park SEWER FINANCIAL PLAN AND RATE STUDY February 17, 2011 3053 Freeport Boulevard #158 Sacramento, CA 95818-4346 (916) 444-9622 www.thereedgroup.org TABLE OF CONTENTS I. EXECUTIVE SUMMARY...1

More information

FINANCIAL PLAN WATER AND WASTEWATER LINES OF SERVICE

FINANCIAL PLAN WATER AND WASTEWATER LINES OF SERVICE UCS2018-0223 ATTACHMENT 1 FINANCIAL PLAN 2019-2022 WATER AND WASTEWATER LINES OF SERVICE 2018 MARCH 14 MAKING LIFE BETTER EVERY DAY UCS2018-0223 Financial Plan 2019-2022 - Water and Wastewater Lines of

More information

CHAPTER 11. CAPITAL FACILITIES PLAN ELEMENT

CHAPTER 11. CAPITAL FACILITIES PLAN ELEMENT CHAPTER 11. CAPITAL FACILITIES PLAN ELEMENT 11.1 INTRODUCTION A is one of eight elements required by the Growth Management Act (GMA) to be included in Yakima County s comprehensive plan. The reason for

More information

ADOPTED OPERATING BUDGET & CAPITAL IMPROVEMENTS PLAN ADOPTED ON: OCTOBER 30, 2014

ADOPTED OPERATING BUDGET & CAPITAL IMPROVEMENTS PLAN ADOPTED ON: OCTOBER 30, 2014 ADOPTED 2015 OPERATING BUDGET & CAPITAL IMPROVEMENTS PLAN ADOPTED ON: OCTOBER 30, 2014 GFOA AWARD The Government Finance Officers Association of the United States and Canada (GFOA) presented a Distinguished

More information

Statement of Policy. Milwaukee Metropolitan Sewerage District s Private Property Inflow and Infiltration Reduction Program.

Statement of Policy. Milwaukee Metropolitan Sewerage District s Private Property Inflow and Infiltration Reduction Program. Milwaukee Metropolitan Sewerage District s 2011-2020 Private Property Inflow and Infiltration Reduction Program Introduction Infiltration is the quantity of water entering a sewer system through such sources

More information

New Castle Sanitation Authority

New Castle Sanitation Authority New Castle Sanitation Authority Lawrence County, Pennsylvania Consulting Engineer's Annual Report and Budget for Fiscal Year 2011 October 201 0 Prepared by AECOM Water Consulting Engineer's Annual Report

More information

Lehigh County Authority Capital Plan. Preliminary Plan: Board Presentation August 28, 2017

Lehigh County Authority Capital Plan. Preliminary Plan: Board Presentation August 28, 2017 Lehigh County Authority 2018-2022 Capital Plan Preliminary Plan: Board Presentation August 28, 2017 1 Project Prioritization Categories Project Category Regulatory New Cust CA/OS AM - Low AM - Med AM -

More information

REQUEST FOR PROPOSALS

REQUEST FOR PROPOSALS REQUEST FOR PROPOSALS Water & Sewer Utilities Optimization City of Wichita Public Works & Utilities May 14, 2015 PROJECT DEFINITION The City of Wichita is seeking proposals for assistance with the risk,

More information

VOLUME 2 - RULES AND REGULATIONS. Part B - Schedule of Rates, Fees and Other Charges. Table of Contents. 1. Definitions... 1

VOLUME 2 - RULES AND REGULATIONS. Part B - Schedule of Rates, Fees and Other Charges. Table of Contents. 1. Definitions... 1 VOLUME 2 - RULES AND REGULATIONS Part B - Schedule of Rates, Fees and Other Charges Table of Contents 1. Definitions... 1 1.1 Applicant... 1 1.2 Availability... 1 1.3 Availability Fees... 1 1.4 Availability

More information

TOWN OF ORO VALLEY WATER UTILITY COMMISSION WATER RATES ANALYSIS REPORT OCTOBER 7, 2009

TOWN OF ORO VALLEY WATER UTILITY COMMISSION WATER RATES ANALYSIS REPORT OCTOBER 7, 2009 TOWN OF ORO VALLEY WATER UTILITY COMMISSION WATER RATES ANALYSIS REPORT OCTOBER 7, 2009 EXECUTIVE SUMMARY The functions and duties of the Oro Valley Water Utility Commission include reviewing and developing

More information

City of Fayette Water/Sewer Utility Application PO Box 28, 11 S. Main St., Fayette, Iowa

City of Fayette Water/Sewer Utility Application PO Box 28, 11 S. Main St., Fayette, Iowa City of Fayette Water/Sewer Utility Application PO Box 28, 11 S. Main St., Fayette, Iowa 52142 563-425-4316 info@fayetteiowa.com www.fayetteiowa.com Current Date: Move-In Date: Person responsible for bill

More information

PACP Based Asset Management

PACP Based Asset Management PACP Based Asset Management Objectives of Asset Management Maintain function or level of service as cost effectively as possible Maintain individual components (assets) at lowest life cycle cost possible

More information

Financial Statements. Delaware County Regional Water Quality Control Authority. December 31, 2013 and 2012

Financial Statements. Delaware County Regional Water Quality Control Authority. December 31, 2013 and 2012 Financial Statements Delaware County Regional Water Quality Control Authority December 31, 2013 and 2012 INDEX Title Page No. Independent Auditor s Report 1-3 Management's Discussion and Analysis 4-12

More information

CITY OF MASCOTTE OPERATING BUDGET FISCAL YEAR GENERAL FUND REVENUE & EXPENDITURE SUMMARY BUDGET

CITY OF MASCOTTE OPERATING BUDGET FISCAL YEAR GENERAL FUND REVENUE & EXPENDITURE SUMMARY BUDGET Page 1 of 37 GENERAL FUND REVENUE & EXPENDITURE SUMMARY ACCOUNT TITLE FY2008-2009 REVENUES $ 3,892,462 EXPENDITURES 3,892,462 RESERVES TRANSFERRED IN (OUT) $ - 2008-2009 2009 Fiscal Year budget is balanced,

More information

Water Quality Improvement Act Purpose and Need For Legislation

Water Quality Improvement Act Purpose and Need For Legislation Water Quality Improvement Act Purpose and Need For Legislation Sec. 1 Short Title: Water Quality Improvement Act. Sec. 2. Sewer Overflow Control Grants: The capital costs that cities bear to address combined

More information

New Strategies for Prioritizing Old Projects Using Risk and Triple Bottom Line Criteria Presenter: Celine Hyer, PE ARCADIS/Malcolm Pirnie 5/23/2012

New Strategies for Prioritizing Old Projects Using Risk and Triple Bottom Line Criteria Presenter: Celine Hyer, PE ARCADIS/Malcolm Pirnie 5/23/2012 New Strategies for Prioritizing Old Projects Using Risk and Triple Bottom Line Criteria Presenter: Celine Hyer, PE ARCADIS/Malcolm Pirnie 5/23/2012 Today s Agenda Overview of Toho Water Authority Risk

More information

CITY OF STURGIS INTEGRATING 20 YEARS OF MAINTENANCE HISTORY INTO AN AMP

CITY OF STURGIS INTEGRATING 20 YEARS OF MAINTENANCE HISTORY INTO AN AMP CITY OF STURGIS INTEGRATING 20 YEARS OF MAINTENANCE HISTORY INTO AN AMP ASSET MANAGEMENT FROM PLAN TO PROGRAM - JANUARY 25, 2017 Tom Sikorski WWTP Superintendent Allen Gelderloos, PE AMP Project Manager

More information

NORTH HUNTINGDON TOWNSHIP MUNICIPAL AUTHORITY

NORTH HUNTINGDON TOWNSHIP MUNICIPAL AUTHORITY NORTH HUNTINGDON TOWNSHIP MUNICIPAL AUTHORITY T a p p i n g F e e C a l c u l a t i o n A p r i l 2 0 1 8 5 1 7 3 C A M P B E L L S R U N R O A D P I T T S B U R G H, P A 1 5 2 0 5-9 7 3 3 Table of Contents

More information

PUBLIC SERVICE COMMISSION OF WEST VIRGINIA CHARLESTON

PUBLIC SERVICE COMMISSION OF WEST VIRGINIA CHARLESTON , PUBLIC SERVICE COMMISSION OF WEST VIRGINIA CHARLESTON Entered by the Public Service Commission of West Virginia, in the City of Charleston on the 3'd day ofoctober 2016. CASE NO. 16-1347-S-PC-CN CITY

More information

Funding Methods and Revenue Generating Capacity

Funding Methods and Revenue Generating Capacity TOWNSHIP OF FERGUSON Funding Methods and Revenue Generating Capacity Executive Summary The purpose of this paper is to examine the funding mechanisms available to the Township to support a stormwater management

More information

(per 1,000 gal.) General - American City and County Municipal Cost Index 20-Year Average as of April 2017

(per 1,000 gal.) General - American City and County Municipal Cost Index 20-Year Average as of April 2017 TEST YEAR Beginning Fund Balance $ 2018 2,009,742 Target Debt Service Coverage Target Days Operating Reserve 1.10 90 Schedule 1 CURRENT WATER RATES BUDGET FORECAST INFLATION FACTORS Year 1 Year 2 Year

More information

ALEXANDRIA RENEW ENTERPRISES

ALEXANDRIA RENEW ENTERPRISES ALEXANDRIA RENEW ENTERPRISES ALEXANDRIA RENEW ENTERPRISES FISCAL YEAR 2016 OPERATING & CAPITAL BUDGET -FINAL- October 1, 2015 September 30, 2016 Public Hearing: September 15, 2015 Adopted: September 15,

More information

Town of South Kingstown Public Services Department. Regulations Governing On-Site Wastewater Management

Town of South Kingstown Public Services Department. Regulations Governing On-Site Wastewater Management Town of South Kingstown Public Services Department Regulations Governing On-Site Wastewater Management 1 REGULATIONS GOVERNING THE SOUTH KINGSTOWN ONSTIE WASTEWATER MANAGEMENT DISTRICT October 15, 2001

More information

TOWNSHIP OF WEST LINCOLN

TOWNSHIP OF WEST LINCOLN TOWNSHIP OF WEST LINCOLN April 18, 2016 dfa DFA Infrastructure International Inc. dfa DFA Infrastructure International Inc. 664-B Vine Street St. Catharines Ontario Canada L2M 7L8 Telephone: (905) 938-0965

More information

ITHACA AREA WASTEWATER TREATMENT FACILITY

ITHACA AREA WASTEWATER TREATMENT FACILITY ITHACA AREA WASTEWATER TREATMENT FACILITY TOWN OF ITHACA CITY OF ITHACA TOWN OF DRYDEN, OWNERS 1) Welcome 2) Agenda Review and Approval of Minutes 525 THIRD STREET ITHACA, NEW YORK 14850 (607) 273-8381

More information

DRAFT. Stormwater Management Program Credit Policy and Appeals Process Manual Policies & Procedures LOWER ALLEN TOWNSHIP STORMWATER AUTHORITY

DRAFT. Stormwater Management Program Credit Policy and Appeals Process Manual Policies & Procedures LOWER ALLEN TOWNSHIP STORMWATER AUTHORITY DRAFT Stormwater Management Program Credit Policy and Appeals Process Manual Policies & Procedures LOWER ALLEN TOWNSHIP STORMWATER AUTHORITY JANUARY 2019 Table of Contents Introduction 3 Definitions 3

More information

INTERGOVERNMENTAL STORMWATER COMMITTEE AGREEMENT THIS INTERGOVERNMENTAL STORMWATER COMMITTEE AGREEMENT,

INTERGOVERNMENTAL STORMWATER COMMITTEE AGREEMENT THIS INTERGOVERNMENTAL STORMWATER COMMITTEE AGREEMENT, INTERGOVERNMENTAL STORMWATER COMMITTEE AGREEMENT THIS INTERGOVERNMENTAL STORMWATER COMMITTEE AGREEMENT, ALLEGHENY TOWNSHIP, ANTIS TOWNSHIP, BELLWOOD BOROUGH, BLAIR TOWNSHIP, CITY OF ALTOONA, DUNCANSVILLE

More information

RESOLUTION CONNECTION CHARGES, PLANT INVESTMENT FEES, AND UTILITY RATES FOR WATER AND SEWER SERVICE

RESOLUTION CONNECTION CHARGES, PLANT INVESTMENT FEES, AND UTILITY RATES FOR WATER AND SEWER SERVICE RESOLUTION 30-17 CONNECTION CHARGES, PLANT INVESTMENT FEES, AND UTILITY RATES FOR WATER AND SEWER SERVICE A RESOLUTION establishing and directing the levy, charge and collection of connection charges,

More information

CITY OF REDLANDS WATER AND WASTEWATER RATE STUDY. Prepared by:

CITY OF REDLANDS WATER AND WASTEWATER RATE STUDY. Prepared by: CITY OF REDLANDS WATER AND WASTEWATER RATE STUDY Prepared by: August 30, 2010 201 S. Lake Blvd, Suite 301 Pasadena CA 91101 Phone Fax 626 583 1894 626 583 1411 www.raftelis.com August 30, 2010 Mr. Chris

More information

Financial Statements. Delaware County Regional Water Quality Control Authority. December 31, 2015 and 2014

Financial Statements. Delaware County Regional Water Quality Control Authority. December 31, 2015 and 2014 Financial Statements Delaware County Regional Water Quality Control Authority December 31, 2015 and 2014 INDEX Title Page No. Independent Auditor s Report 1-2 Independent Auditor s Report on Internal Control

More information

STORMWATER MANAGEMENT FUND Department of Environmental Services

STORMWATER MANAGEMENT FUND Department of Environmental Services Department of Environmental Services Mission: To implement a comprehensive stormwater management program that balances the following goals: 1) to reduce the potential for stormwater threats to public health,

More information

Stormwater Management Program

Stormwater Management Program Derry Township Municipal Authority Stormwater Management Program Stormwater Stakeholder Advisory Committee Meeting #3 February 24, 2016 Agenda 1. News & Updates 2. Recap Average/Expanded Level of Service

More information