1 San Francisco Public Utilities Commission Water & Wastewater Rate Study Report March 6, 2009 Prepared by:

2 Table of Contents I. EXECUTIVE SUMMARY...1 A. Pricing Objectives...2 B. Review of Findings Water...2 Water System...2 Capital Financing Plan Summary...3 Review of Water Revenue Requirements...3 Reserve Funds...5 Current Water Rate Structure...5 Cost of Service - Water...6 Rate Design - Water...7 C. Recommendations and Proposed Changes - Water...7 User Classifications...7 Proposed Water Rate Structure...7 Customer Impacts - Water...9 D. Review of Findings Wastewater...11 Wastewater System...11 Wastewater Capital Financing Plan Summary...11 Review of Wastewater Revenue Requirements...12 Reserve Funds...14 Current Wastewater Rate Structure...14 Cost of Service - Wastewater...15 E. Recommendations and Proposed Changes Wastewater...15 User Classifications...15 Proposed Wastewater Rate Structure...15 Customer Impacts...18 Comparison with Other Utilities...20 Raftelis Financial Consultants, Inc. i

3 II. INTRODUCTION...23 A. Current Environment...23 B. Study and Pricing Objectives...24 C. Scope of the Study...25 III. WATER SYSTEM AND CURRENT WATER RATE STRUCTURE...27 A. Water System...27 B. Existing Rate Structure...27 C. Growth...30 D. Usage Characteristics...30 IV. WATER REVENUE REQUIREMENTS...32 A. Annual Operating Revenues Under Existing Rates...32 B. Operating and Capital Expenses...33 D. Proposed Revenue Adjustments...37 E. Debt Coverage...40 F. Reserve Fund...41 V. PROPOSED WATER RATES AND CUSTOMER IMPACTS...46 A. Overview of Rate Setting...46 B. Cost of Service Analysis...46 C. Unit Costs of Service...50 D. Proposed Water Rate Structure and Rates...56 E. Customer Impacts...62 F. Comparisons with Other Local Utilities...64 VI. WASTEWATER SYSTEM AND CURRENT RATE STRUCTURE...67 A. Wastewater System...67 B. Current Rate Structure...67 C. Growth...70 Raftelis Financial Consultants, Inc. ii

4 D. Wastewater Customer Accounts...70 E. Wastewater Discharge Characteristics...70 VII. WASTEWATER REVENUE REQUIREMENTS...72 A. Revenues Under Existing Retail Rates...72 B. Operating and Capital Expenses...73 B. Wastewater Capital Financing Plan...74 C. Proposed Revenue Adjustments...76 D. Debt Coverage...79 C. Reserve Funds...80 VIII. PROPOSED WASTEWATER RATES AND CUSTOMER IMPACTS...82 A. Overview of Rate Setting...82 B. Cost of Service Analysis...82 C. Unit Cost of Service...83 D. Proposed Wastewater Rate Structure and Rates...86 E. Customer Impacts...90 F. Comparisons with Other Local Utilities...97 Raftelis Financial Consultants, Inc. iii

5 PAGE INTENTIONALLY LEFT BLANK

6 I. EXECUTIVE SUMMARY In July 2008, the San Francisco Public Utilities Commission ( SFPUC ) engaged Raftelis Financial Consultants, Inc. ( RFC ) to provide utility rate consulting services and complete a water and wastewater rate study ( Study ). The objectives of the Study was to evaluate the financial impacts of the SFPUC s ten-year financial plan from fiscal year ( FY ) 2009 through FY 2018 and provide water and wastewater rate structure and revenue adjustment recommendations for the next five years. To address these objectives, RFC developed separate ten-year water and wastewater rate and financial planning models (referred to collectively as Models or separately as Water Model and Wastewater Model ) to serve as planning tools in evaluating alternative rate structures and providing more detailed forecasts to assist in updating rates in future years. The Study recommendations and resulting rate structures need to be in compliance with the City of San Francisco ( City ) Charter based on the following objectives: Provide sufficient revenues for the operations, maintenance, and repair of the enterprise consistent with good utility practice; Provide sufficient revenues to improve or maintain financial condition and bond ratings at or above levels equivalent to highly rated utilities of each enterprise; Meet requirements and covenants under all bond indentures; Rates based on cost of service; Investigate and develop capacity fees for new development; Investigate and develop rate-based conservation incentives; and Investigate and develop affordability programs for low-income customers. This executive summary ( ES ) documents the results of the Study and identifies the recommended changes to cost allocations and rate structures that are more appropriate in addressing the SFPUC s utility pricing objectives in FY 2010 and beyond. This ES discusses the SFPUC s rate pricing objectives, the findings of our analysis of the water and wastewater systems, and the cost of service and rate recommendations for water and wastewater enterprises. All years referenced in this ES and water and wastewater rate report ( Report ) should be assumed to be fiscal years, unless stated otherwise. The conceptual design memorandum and the results of our benchmarking survey are included as appendices to this report, while our recommendations related to the water and wastewater capacity fees, miscellaneous fees, and stormwater issues evaluated as part of this Study are documented in separate reports. Raftelis Financial Consultants, Inc. 1

7 A. Pricing Objectives The Study began with a kick-off meeting and a conceptual design workshop to assist RFC in understanding and prioritizing the SFPUC s rate pricing objectives. Following the August 2008 kick-off meeting, RFC developed a list of utility pricing objectives based on initial discussions with the SFPUC management team and our preliminary understanding of the important issues facing the SFPUC. As part of this process, these pricing objectives were confirmed with the SFPUC management team and serve as the basis for evaluating the rate structure alternatives recommended in the report. As part of the conceptual design workshop, RFC analyzed the existing water and wastewater rate structures, performed a water usage analysis, and examined alternative rate structures to ensure proposed rates would be consistent with the SFPUC pricing objectives and financial planning goals. This conceptual design process resulted in the identification of rate structures, and/or modifications to existing rates, suitable for further evaluation. B. Review of Findings Water This section of the ES provides a brief description of the water system, a review of the revenue requirements, the capital financing plan, an analysis of cost of service, the current rate structure, the design of water rates, and customer impacts for two alternative water rate structures. Water System The SFPUC currently provides water to retail customers in the City and County of San Francisco ( retail area ) and 28 wholesale ( regional ) water customers in Santa Clara, Alameda, and San Mateo counties. The population of the retail area is estimated to be about 825,000 with approximately 173,000 water accounts that includes customers located both inside and outside the City s corporate boundaries. Water sales to retail customers currently represent about 31% of the total water sales and approximately 44% of the total water revenue. The SFPUC water system extends from Hetch Hetchy Valley in Yosemite National Park to the Bay Area. The transmission system operates primarily through gravity lines and traverses three major fault lines. SFPUC is currently in the process of implementing a $4.4 billion Water System Improvement Program ( WSIP ) to improve system reliability and enhance quality of the water it delivers to its customers. 1 WSIP includes seismic improvements to reservoirs as well as 1 Although the total estimated cost of the WSIP is approximately $4.4 billion (including financing costs), the SFPUC already began and/or secured financing for certain project components of the WSIP. As a result, the total costs funded during the ten-year financial planning period for this Study are approximately $3.9 billion. Raftelis Financial Consultants, Inc. 2

8 pipeline replacement, and new facilities. The primary mechanism to fund WSIP will be debt, and the financial impacts from implementation of the WSIP will be significant. Capital Financing Plan Summary WSIP includes regional capital projects that address capital needs that benefit wholesale and retail customers and local capital projects that solely benefit retail customers. In addition to WSIP, the Water ten-year capital plan evaluated as part of this Study also includes smaller renewal and replacement ( R&R ) projects. The WSIP projects, totaling approximately $3.3 billion, will be funded through the issuance of long term debt. R&R projects, totaling approximately $398 million, will be funded through current revenues. Figure ES-1 displays all capital spending. FIGURE ES-1 WATER CAPITAL SPENDING Millions $900 $800 WSIP R&R $700 $600 $500 $400 $300 $200 $100 $ Based on the WSIP spending plan, the SFPUC anticipates issuing $3.9 billion of Water Revenue Bonds. In additional to the $3.3 billion for project funding, the bonds will include funding for issuance costs, funding reserves, and capitalized interest. The SFPUC plans to fund the $398 million of R&R projects using annual rate revenues during the ten-year financial planning period. As Figure ES-1 demonstrates, the majority of the water capital spending is required for the WSIP from FY 2009 through FY The annual R&R project spending is less substantial and more consistent annually as these expenditures remain within a range of approximately $40 to $70 million during the forecast period. Review of Water Revenue Requirements Figure ES-2 shows the water system s estimated total revenue requirements of approximately $279 million in FY 2010, which consist of operating & maintenance ( O&M ) expenses, debt Raftelis Financial Consultants, Inc. 3

9 service, and revenue funded capital. Water revenue requirements will escalate considerably after FY 2010 primarily due to the additional debt service on bonds used to fund the WSIP. For example, total debt service increase from approximately $70 million in FY 2010 to approximately $321 million in FY Millions $700 $600 $500 $400 $300 $200 $100 $- $(100) FIGURE ES-2 WATER REVENUE REQUIREMENTS O&M Debt Service Net Revenues Revenue Under Proposed Rates Capital Outlay Revenue Funded Capital Revenue Under Existing Rates The water system s principal source of operating revenue is from rates and charges on water sales to both retail and wholesale customers. Revenues from retail customers under the existing rates are expected to increase from $122.4 million in FY 2009 to $127.3 million by FY The wholesale customer revenues are expected to increase from $126.5 million in FY 2009 to $342.3 million by FY 2018, assuming wholesale rate adjustments based on the terms of existing contract. As the red line in Figure ES-2 demonstrates, anticipated revenues to be generated through the existing rates will not sufficient to recover the annual revenue requirements, fund operating reserves, and debt service coverage requirements during the ten-year financial planning period. To address this shortfall, revenue adjustments will be needed. The green line reflects the revenue stream under RFC s proposed rate adjustments, which results in sufficient revenues to meet both operating and capital funding needs. Both the red and green lines include wholesale revenue forecasts under the existing contract. With approximately $3.9 billion in new bonds issued to fund WSIP, additional revenues must increase significantly to meet bond covenant requirements (i.e. net revenues plus operating reserves must be at least 1.25 times annual debt service). Meeting this coverage test is crucial as Raftelis Financial Consultants, Inc. 4

10 a failure to maintain indenture requirements would result in a default of the bond covenant. Should the SFPUC fail to remedy a default, the bondholders could demand full payment of all outstanding bonds. To sustain operations, adequately fund reserves, and continue to meet bond indenture requirements over the planning period, RFC forecasts in Table ES-1 the following annual retail rate adjustments over the next five years. TABLE ES-1 WATER REVENUE ADJUSTMENTS (FY 2010 THROUGH FY 2014) FY % FY % FY % FY % FY % Following FY 2014, we forecast annual revenue adjustments of 3% for the remainder of the forecast period. Given the inelastic nature of the SFPUC usage, these annual retail revenue adjustments do not consider nor assume any reductions in water demands due to price elasticity. A discussion of proposed rates in Section V provides more information on the potential effects of price elasticity. Reserve Funds The Water Enterprise s unappropriated fund balance functions as an operating reserve. This reserve is used for working capital requirements to meet the ongoing expenses of the water system operations. In addition, the SFPUC bond indentures allow these funds to be counted toward calculating the debt service coverage. Generally, practice in the utility business is to target a balance of 10 to 40% of annual O&M expenses. The SFPUC s current goal is approximately 25% of annual O&M expenses. Because water consumption does not vary much during the year and revenue is stable, we feel that 25% of annual O&M is a reasonable target for the operating reserve. As part of this Study, RFC conducted a benchmark survey of eleven water and/or wastewater utilities in large cities throughout the country and the majority of the respondents identified operating reserve policies that were below the SFPUC s current 25% of annual O&M expenses. However, many of these utilities also indicated having other types of reserves that provide additional levels of unappropriated cash balances. The result of the survey is presented in Table ES-8. Current Water Rate Structure The SFPUC s existing rate structure consists of two parts: a variable portion and a fixed monthly/bi-monthly charge. For single-family residential ( SFR ) customers, the variable Raftelis Financial Consultants, Inc. 5

11 portion is comprised of a two-tier, inclining block rate structure. Both multi-family residential ( MFR ) and non-residential customers pay uniform commodity rates specific to their customer class. The fixed monthly/bi-monthly charges are applicable to all customer classes and vary by meter size. 2 Private fire protection service rates are also assessed according to meter size. Customers located outside of the retail area have the same rate structures as the retail customers, but are charged a 25% outside-city differential. Affordability is important, especially in the current economic climate. By EPA guidelines, bills less than 2% of median housing income are deemed affordable. The median monthly household income in the City is $5,459 (annual income of $65,519) as of An average water bill of $21.21 at existing rates represents less than 1% (0.39%) of monthly median household income. Despite recent rate increases, the monthly water bill for the typical SFR customer with consumption of 6.5 hundred cubic feet ( Ccf ) within the City of San Francisco compares reasonably with similar communities, as shown at the end of this ES in Figure ES-5. The findings of RFC s review of the City s existing water rate structure were mostly favorable. The existing fixed charges appear to be largely consistent with meter capacity ratios, cost of service principles, and accepted industry practices. The commodity charges are also largely consistent with cost of service principles but can be improved to comply more with the City Charter objective to provide rate-based conservation incentives. Cost of Service - Water The cost of service ( COS ) to be recovered from retail users through rates is estimated at approximately $141 million in FY 2010 and increases to $236 million by FY The COS allocations conducted for this study are based on the Base-Extra Capacity method endorsed by the American Water Works Association ( AWWA ). Under the Base-Extra Capacity method, revenue requirements are allocated to the different user classes proportionately to their use of the water system. Allocations are based on average day ( Base ) usage, maximum day peak ( Max Day ) usage, maximum hour peak ( Max Hour ) usage, meters and services, and billing and collection. 2 The non-residential customer class comprises various customer classifications including commercial, industrial, docks & ships, builders & contractors, municipal, non-paying, agriculture, and airport. 3 Raftelis Financial Consultants, Inc. 6

12 Rate Design - Water The rate alternatives presented as part of this Study incorporate AWWA recommended methodologies adapted to meet the SFPUC s specific characteristics and provides for a system of user charges that will enhance the proportionate recovery of costs from the various user classes. C. Recommendations and Proposed Changes - Water RFC s recommendations were designed to address the SFPUC s pricing objectives and enhance equity in the recovery of costs of the water utility to the benefit of the SFPUC s customers. These changes include adjustments to monthly service charges, an updated cost of service for all commodity rates, and modifications to the SFR rate structure. User Classifications At this time, we recommend retaining the existing customer classes. However, we have adjusted the class peaking factors provided by the SFPUC. These factors will help provide a more equitable distribution of costs among SFR, MFR, and non-residential classes. Proposed Water Rate Structure The following discussion outlines proposed alternatives to address rate findings described in the previous section. RFC recommends retaining a tiered SFR commodity rate structure with the two alternatives to consider, including 1) implementing an additional third tier; or 2) retaining the current two tiered structure. The additional tier under the first alternative will provide an additional incentive for water conservation, while enhancing customer equity by improving the cost justification for the tiered rates through the Base-Extra Capacity cost allocations. Under the three tier structure, the first block usage cut-off will remain at 3 Ccf (approximately 2,200 gallons) per month, which is roughly one half of the 6.5 Ccf (approximately 4,900 gallons) per month average usage for the SFR customer class. The second block usage cut-off will be set at a monthly usage of 10 Ccf (approximately 7,500 gallons). The first and second tier cutoffs encompass 84% of the consumption and 88% of the customer bills. The proposed rates are shown in Table ES-2. Should the SFPUC decide the recommended three tier rate structure for SFR customers is not appropriately aligned with community values, and opt to continue with the two tiered structure, the SFPUC should implement cost of service based two tiered commodity rates. Under the revised two-tiered rate structure, the block cutoff would Raftelis Financial Consultants, Inc. 7

13 remain at 3 units and the tier one and tier two rates would be $2.45 and $3.94, respectively. Under both options the other customer classifications will retain uniform commodity rates that reflect their peaking characteristics. The cost of providing private fire protection was also updated as part of our analysis. The existing private rates were set many years ago and have not been updated since The rates were updated to be more consistent with the COS principles outlined in the AWWA M-1 manual chapter on Rates for Fire Protection Services. Table ES-2 reflects the SFPUC s existing rates and recommended changes for FY Rates for outside-city customers will include a 25% premium. Rate adjustments for the forecast period beyond FY 2010 will be across-the-board increases. TABLE ES-2 EXISTING AND PROPOSED WATER RATES Fixed Monthly Charge Potable Fire Service Existing Proposed Existing Proposed Meter Size FY 09 FY10 FY 09 FY10 5/8" $ 4.70 $ /4" $ 5.70 $ 6.60 N/A 1" $ 7.60 $ 8.40 $ 9.30 $ /2" $ $ $ $ " $ $ $ $ " $ $ $ $ " $ $ $ $ " $ $ $ $ " $ $ $ $ " $ $ $ $ " $ $ $ $ " $ $ N/A Commodity Rates Customer Existing Proposed Class Block FY 09 Block FY10 CPRS (Single Family) 0-3 $ $ $ $ $ 4.82 CPRM (Multi Family) $ $ 3.32 CPCM (Commercial) $ $ 3.45 CPIN (Industrial) $ $ 3.45 CPDS (Docks & Ships) $ $ 3.45 CPBC (Builders & Contractors) $ $ 3.45 CPMU (Municipal) $ $ 3.45 AG/AP $ $ 3.45 Raftelis Financial Consultants, Inc. 8

14 Customer Impacts - Water COS principles serve as the basis of the rate calculations throughout the process. Because the SFPUC is facing multiple years of rate increases, the impact on various customers was considered during the entire rate design process. Raftelis Financial Consultants, Inc. 9

15 Single-family Residential All SFR customers will experience bill increases in FY 2010 as a result of increases to both the fixed service charge and the commodity rates. Table ES-3 summarizes impacts for various SFR customers in FY TABLE ES-3 BI-MONTHLY BILL IMPACTS FOR SFR 5/8 METERS FY 2010 Alternative 1 Alternative 2 Total Bill Change Change Usage Existing Proposed % $ Proposed % $ 6 $ $ % $ 3.02 $ % $ $ $ % $ 4.68 $ % $ $ $ % $ 6.34 $ % $ $ $ % $ 8.00 $ % $ $ $ % $ 8.83 $ % $ $ $ % $ $ % $ $ $ % $ $ % $ $ $ % $ $ % $ $ $ % $ $ % $ CCF is the average bi-monthly usage Multi-Family Residential All MFR customers will also be impacted as a result of increases to both the fixed charge and the commodity charge. Table ES-4 presents FY 2010 impacts to certain MFR customers; the impacts are the same under both alternatives. TABLE ES-4 BILL IMPACTS FOR MULTI-FAMILY 5/8 METERS FY 2010 Non-Residential/Commercial Total Bill Change Usage Existing Proposed % $ 2 $ $ % $ $ $ % $ $ $ % $ $ $ % $ $ $ % $ $ $ % $ $ $ % $ $ $ % $ $ $ % $ 8.30 Most non-residential customers will be impacted by increases to both the fixed charge and the commodity rate. Table ES-5 displays impacts to the certain non-residential customers in FY 2010; the impacts are the same under both alternatives. Raftelis Financial Consultants, Inc. 10

16 TABLE ES-5 BILL IMPACTS FOR COMMERCIAL 5/8 METERS FY 2010 Total Bill Change Usage Existing Proposed % $ 6 $ $ % $ $ $ % $ $ $ % $ $ $ % $ $ $ % $ $ $ % $ $ $ % $ $ $ % $ D. Review of Findings Wastewater This section of the ES provides a brief description of the wastewater system, a review of the revenue requirements, the capital financing plan, an analysis of COS, the design of wastewater rates, and customer impacts. Wastewater System The wastewater system serves the City and County of San Francisco and adjacent areas. The system provides service to approximately 173,000 accounts, the vast majority of which are residential. The wastewater system is a combined sewer and stormwater system which is divided into zones. The wastewater system consists of two wastewater treatment plants, a wet weather facility, and 898 miles of wastewater lines. To meet regulatory requirements, large transportation sewers maintain underground storage structures to limit the number and volume of combined sewer overflows. The SFPUC is addressing neighborhood flooding and odor issues through a five-year interim capital improvement program ( CIP ) and has a long-term vision and strategy for the management of the SFPUC s wastewater and stormwater infrastructure as part of a long-term master plan. Wastewater Capital Financing Plan Summary Similar to the water enterprise, the wastewater system has a significant amount of capital projects planned. The wastewater CIP is segregated into three categories of projects: 1) wastewater master plan projects totaling $3.4 billion that will be funded primarily through new debt issues; 2) R&R projects totaling $230 million that will be funded through annual rate revenues; and 3) the five-year interim CIP projects, totaling $215 million. The CIP includes projects to address odor control, sewer collection system replacements, and treatment facilities and pump stations upgrades. Figure ES-3 reflects the total capital expenditures during the forecast period. Raftelis Financial Consultants, Inc. 11

17 FIGURE ES-3 WASTERWATER CAPITAL SPENDING Millions $800 $700 $600 $500 $400 $300 $200 $100 $ Master Plan R&R 5 year CIP As Figure ES-3 demonstrates, the majority of the wastewater capital spending relates to master plan projects that are anticipated to occur from FY 2014 through FY 2018, with the peak year of $642 million in capital expenditures occurring in FY Review of Wastewater Revenue Requirements Estimates show the wastewater system s total revenue requirements is approximately $216 million in FY 2010, which consist of O&M expenses, debt service and annual revenue funded capital. Annual revenue requirements escalate thereafter due to anticipated inflation in O&M expenses and on-going R&R spending. The majority of the annual increases result from new debt service associated with anticipated bonds required to fund the wastewater master plan projects. For example, total debt service requirements increase from approximately $67 million in FY 2009 to approximately $179 million in FY Figure ES-4 represents the projected revenue requirements over the ten-year forecast period. Raftelis Financial Consultants, Inc. 12

18 Millions $450 $400 $350 $300 $250 $200 $150 $100 $50 $0 -$50 FIGURE ES-4 WASTEWATER REVENUE REQUIREMENTS O&M Debt Service Capital Outlay Revenue Funded Capital Transfer to Capital Fund Net Revenues Revenue Under Existing Rates Revenue Under Proposed Rates The wastewater system s principal source of operating revenue is from user charges to both retail customers and three special districts served under separate Joint Powers Agreements. The retail customer revenues under the current rates are expected to increase from $206.0 million in FY 2009 to $215.5 million by FY 2018 while the revenues received from special districts are shown to remain at $6.0 million throughout the ten-year forecast period. As a result, the total user charge revenues under the current rates are expected to increase from $212.0 million in FY 2009 to $ million by FY As the red line in Figure ES-4 demonstrates, anticipated revenues to be generated through the existing rates are not sufficient to recover the annual revenue requirements including funding operating reserve and meet debt service requirements during the ten-year financial planning period. To address this shortfall, revenue adjustments will be needed. The green line reflects the revenue stream under the proposed annual adjustments, which results in sufficient revenues to meet both operating and capital funding needs. With approximately $3.8 billion in new bonds issued over the forecast period to fund the significant capital plan, additional revenues needed to meet debt coverage requirements will be needed.. Specifically, in order to meet revenue requirements we forecast revenue adjustments for the next five years as presented in Table ES-7. Raftelis Financial Consultants, Inc. 13

19 TABLE ES-7 WASTEWATER REVENUE ADJUSTMENTS (FY 2010 THROUGH FY 2014) FY % FY % FY % FY % FY % Subsequent to FY 2014, additional wastewater revenue adjustments will range from 5 to 9%. Reserve Funds Similar to the Water Enterprise, the Wastewater Enterprise s unappropriated fund balance functions as an operating reserve. This reserve is used for working capital requirements to meet the ongoing expenses of the wastewater system operations. In addition, the SFPUC bond indentures allow these funds to be counted toward calculating the debt service coverage. Generally, practice in the utility business is to target a balance of 10 to 40% of annual O&M expenses. The SFPUC s current goal is approximately 25% of annual O&M expenses. Because wastewater billings do not vary much during the year and revenue is stable, we feel that 25% of annual O&M is a reasonable target for the operating reserve. Again, the majority of the respondents in our benchmark group of large utilities identified operating reserve policies that were at or below the SFPUC s current 25% of annual O&M expenses. Table ES-8 identifies the eleven respondents and summarizes the various types of reserves the respondents indicated utilizing as either policy or practice. TABLE ES-8 OPERATING RESERVE BENCHMARKING Benchmark Utility Operating Stabilization Capital Debt Other Replace Assistance San Antonio Water System X X Phoenix Water Services Department X X Seattle Public Utilities X X Portland Water Bureau X X X San Diego Water Department X X X X San Diego Metropolitan Wastewater X X X X Los Angeles LADWP X X Los Angeles (LABS) X Denver Water X Sacramento (SCRSD) X X X XX XX XX New York City X X Note: More than one x indicates more than one fund in that category Current Wastewater Rate Structure Residential wastewater customers (Schedule A), consisting of single-family and multi-family, and are charged a three-tiered rate structure. The rate for the first three units of wastewater flow is $3.42, followed by a rate of $8.55 for the next two discharge units, and $9.77 for any Raftelis Financial Consultants, Inc. 14

20 additional discharge units. 4 No additional charges are assessed to these residential customers for wastewater strength, as these costs are recovered through the flow rates based on domestic strength levels. Non-residential customers (Schedule B) pay a uniform rate of $ per unit, which is based on 90% of metered water usage. Unlike residential customers, non-residential customers are charged separatel wastewater strength charges. For chemical oxygen demand ( COD ) the strength charge is $0.216 per ( lb ), while the strength charges for suspended solids ( SS ) and grease and oil ( G/O ) are $ and $ per lb, respectively. Again, with a median monthly household income in the City of $5,650, an average $40.06 wastewater bill represents less than 1% (0.7%) of monthly median household income. According to EPA guidelines, bills of less than 2% of median housing income are deemed affordable. Despite recent rate increases, the monthly wastewater bills for the typical SFR customer with consumption of 6.5 hundred cubic feet ( Ccf ) within the City of San Francisco compares reasonably with similar communities, as shown at the end of this ES in Figure ES-5. Cost of Service - Wastewater The COS to be recovered from retail users through rates is estimated at approximately $221.5 million in FY 2010 and increases to $288 million by FY E. Recommendations and Proposed Changes Wastewater Based on our understanding of the SFPUC s wastewater financial and pricing objectives, RFC developed rate structure modifications designed to enhance the equitable recovery of wastewater costs from various SFPUC wastewater customers based on COS principles and accepted industry practices. User Classifications At this time, we recommend retaining the existing customer classes. This includes residential (single-family and multi-family) wastewater customers and non-residential customers. Proposed Wastewater Rate Structure To reflect full COS, we recommend recovering the appropriate amount of capital costs assigned to each customer class through the rates assessed to those customers. In the case of the 4 A discharge unit represents 100 cubic feet of metered water usage multiplied by the SFR return factor of 90% and MFR return factor of 95%. Raftelis Financial Consultants, Inc. 15

21 residential customer class, this can be accomplished by moving toward a uniform rate structure that incorporates all capital costs allocated to the class. This rate structure is outlined in the first of three rate structure alternatives (designated as A-1, A-2 and A-3) presented in this section. Ideally rates should be set in accordance with A-1. However, because of the significant impacts on residential customers, A-2 and A-3 are provided as additional alternatives that phase in the recommended rate structure. A-1 implements the uniform residential rate immediately and moves to the cost of service based rate structure in the first year. The existing rate structure and proposed rates for the five-year forecast period are shown in the following table. After the test year, FY 2010, the rates are increased across the board by the annual revenue adjustment. Table ES-9 outlines the existing and proposed A-1 rates. TABLE ES-9 EXISTING AND PROPOSED WASTEWATER RATES ALTERNATIVE 1 Existing Residential Discharge ($/CCF) $ Discharge ($/CCF) $ Discharge ($/CCF) $ 9.77 Non-Residential Discharge ($/CCF) $ COD ($/lb) $ SS ($/lb) $ G/O ($/lb) $ Proposed - Alternative Residential Discharge ($/CCF) $ $ $ $ $ Non-Residential Discharge ($/CCF) $ $ $ $ $ COD ($/lb) $ $ $ $ $ SS ($/lb) $ $ $ $ $ G/O ($/lb) $ $ $ $ $ A-2 and A-3 ultimately end up at the same place as A-1 the rates in FY 2014 are identical in each alternative. Table ES-10 outlines the existing and A-2 rates. This approach implements a uniform rate for residential customers right away, but it phases in the full cost of service rate over the five year period. Raftelis Financial Consultants, Inc. 16

22 TABLE ES-10 EXISTING AND PROPOSED WASTEWATER RATES ALTERNATIVE 2 Existing Residential Discharge ($/CCF) $ Discharge ($/CCF) $ Discharge ($/CCF) $ 9.77 Non-Residential Discharge ($/CCF) $ COD ($/lb) $ SS ($/lb) $ G/O ($/lb) $ Proposed - Alternative Residential Discharge ($/CCF) $ $ $ $ $ Non-Residential Discharge ($/CCF) $ $ $ $ $ COD ($/lb) $ $ $ $ $ SS ($/lb) $ $ $ $ $ G/O ($/lb) $ $ $ $ $ A-3, outlined in Table ES-11 on the following page, retains the current three tier rate structure and phases it out over several years, as shown below. This option would have more gradual impacts on customers. Raftelis Financial Consultants, Inc. 17

23 TABLE ES-11 EXISTING AND PROPOSED WASTEWATER RATES ALTERNATIVE 3 Existing Residential Discharge ($/CCF) $ Discharge ($/CCF) $ Discharge ($/CCF) $ 9.77 Non-Residential Discharge ($/CCF) $ COD ($/lb) $ SS ($/lb) $ G/O ($/lb) $ Proposed - Alternative Residential 0-3 Discharge ($/CCF) $ $ $ $ $ Discharge ($/CCF) $ $ $ $ $ Discharge ($/CCF) $ $ $ $ $ Non-Residential Discharge ($/CCF) $ $ $ $ $ COD ($/lb) $ $ $ $ $ SS ($/lb) $ $ $ $ $ G/O ($/lb) $ $ $ $ $ Customer Impacts The tables in this section will cover bill impacts under the three wastewater rate structure alternatives. Because the proposed rate structure includes a re-allocation of costs between customer classes in addition to the revenue adjustments, the initial impacts for residential customers are more than the overall annual revenue adjustment required in the forecast period. However, this initial impact is necessary to correct to current cost recovery issues associated with the first tier residential rate and to move toward a uniform rate over five years. Table ES-12 presents impacts for residential customers in FY 2010 under A-1. All residential bill impacts will be calculated on a bi-monthly basis. Bill impacts for non-residential customers under A-1 are shown in Table ES-13. Since rate adjustments thereafter are applied across the board, the bill impacts will be equal to the overall annual revenue adjustment. Raftelis Financial Consultants, Inc. 18

24 TABLE ES-12 BILL IMPACTS FOR RESIDENTIAL WASTEWATER CUSTOMERS ALTERNATIVE 1 - FY 2010 Change Discharge Existing Proposed % $ 3 $ $ % $ $ $ % $ $ $ % $ $ $ % $ $ $ % $ $ $ % $ $ $ % $ $ $ % $ $ $ % $ CCF is the average MFR bi-monthly discharge 12 CCF is the average SFR bi-monthly dishcarge TABLE ES-13 BILL IMPACTS FOR NON-RESIDENTIAL WASTEWATER CUSTOMERS ALTERNATIVE 1 - FY 2010 Change Discharge Existing Proposed % $ 10 $ $ % -$ $ $ % -$ $ $ % -$ $ $ % -$ $ $ % -$ $ $ % -$ $ $ % -$ $ $ % -$ $ $ % -$ $ $ % -$ Table ES-14 and ES-15 outlines the bill impacts for residential customers in FY 2010 under A2 and A-3, respectively. Non-residential bills are unchanged until FY Bill impacts for the full five year period can be found in the main section of this report. Raftelis Financial Consultants, Inc. 19

25 TABLE ES-14 BILL IMPACTS FOR RESIDENTIAL WASTEWATER CUSTOMERS ALTERNATIVE 2 - FY 2010 Change Discharge Existing Proposed % $ 3 $ $ % $ $ $ % $ $ $ % $ $ $ % $ $ $ % $ $ $ % $ $ $ % $ (0.49) 16 $ $ % $ (6.70) 18 $ $ % $ (12.91) 12 CCF is the average SFR bi-monthly dishcarge 10 CCF is the average MFR bi-monthly discharge TABLE ES-15 BILL IMPACTS FOR RESIDENTIAL WASTEWATER CUSTOMERS ALTERNATIVE 3 - FY 2010 Change Discharge Existing Proposed % $ 3 $ $ % $ $ $ % $ $ $ % $ $ $ % $ $ $ % $ $ $ % $ $ $ % $ $ $ % $ $ $ % $ CCF is the average SFR bi-monthly dishcarge 10 CCF is the average MFR bi-monthly discharge Comparison with Other Utilities An important aspect of evaluating the impacts of the recommended rate alternatives and anticipated rate adjustments is a comparison with other large utilities and utilities serving local communities. To develop this comparison, RFC gathered current utility rate schedules from the large utilities participating in our benchmark survey and from utilities serving other local communities. Since the 6.5 Ccf average monthly water use per SFR account in the SFPUC retail Raftelis Financial Consultants, Inc. 20

26 service area is less than half the national average, RFC calculated the monthly bills for each utility according to the monthly average single-family water use in each local area. 5 The chart in Figure ES-5 presents the average monthly residential utility bill for each of the benchmark utilities in comparison with the average SFR monthly utility bills for SFPUC customers under the existing rates and under alternative 1 (A-1) for both water and wastewater. Alternative 1 (water and wastewater) was selected for this comparison since this alternative results in the greatest combined impact for all the water and wastewater alternatives. (Since some utilities recover wet weather flows through separate stormwater charges, the average stormwater bills for those utilities are also included in the average monthly residential wastewater bills.) FIGURE ES-5 COMPARISON OF MONTHLY BILL WITH BENCHMARCK UTILITIES 6 Residential Combined Monthly Bill (Average Local Use) Water Sewer Stormwater $120 $110 $100 $100 $112 $90 $80 $70 $60 $50 $40 $36 $39 $44 $48 $50 $51 $55 $58 $58 $62 $63 $65 $72 $74 $75 $75 $82 $85 $30 $20 $10 $- San Antonio Santa Clara Hayward Houston Fremont (USD) San Jose Dallas *Phoenix Las Vegas Combined Average San Francisco Existing *Oakland (EBMUD) *Sacramento Seattle San Francisco A-1 (W&S) Walnut Creek (CCCSD) Palo Alto *Portland *San Diego *Los Angeles 5 According to the AWWA statistics, average daily household water use is 350 gallons per day (10,500 gallons and 13.4 Ccf per month). 6 Although the SFPUC bills the majority of its retail residential customers on a bi-monthly basis, it publishes, compares, and assesses its rate structure based on a monthly usage levels. Raftelis Financial Consultants, Inc. 21

27 The SFR bill under the existing SFPUC water rates is below the average water bill for the benchmark group. Furthermore, the SFR water bill under each water option or alternative (A-1 and A-2) is also below the average water bill for the benchmark group. On the other hand, the SFR wastewater bill under the existing SFPUC wastewater rates, as well as the SFR wastewater bills for each wastewater option or alternative (A-1, A-2, & A-3), is above the average wastewater bill for the benchmark group. When combined, the water and wastewater SFR bills under the existing SFPUC rates and the combined water and wastewater bills for water and wastewater alternatives 1 are above the combined average utility bill for the benchmark group. Raftelis Financial Consultants, Inc. 22

28 II. INTRODUCTION In July 2008, The San Francisco Public Utilities Commission ( SFPUC ) engaged Raftelis Financial Consultants, Inc. ( RFC ) to provide utility consulting services with the purpose of developing equitable rate structures for water and wastewater services to recover costs of providing service to customer groups based on usage characteristics while addressing community values. The ( Study ) required recommendations related to cost justified customer class rate differentials, lifeline rates, conservation rates, public and private fire protection charges, and an evaluation of the recovery of costs for stormwater runoff. The Study included the following major deliverables: review of the existing water and wastewater system rate structure and underlying cost allocations; recommend changes to the rate structures as well as revenue adjustments for the next five years; develop a ten-year financial plan from fiscal year ( FY ) 2009 through FY 2018; determine capacity charge recommendations; and evaluate the feasibility of separate wet weather charges. The rates for water and wastewater were developed in separate financial planning and rate models ( Models ) that have been used to evaluate alternative rate structures and provide more detailed forecasts to assist in financial planning and updating rates in future years. Although our wastewater rate recommendations are designed to recover both dry and wet weather flows, we have included an evaluation of the operating and capital costs required to collect and treat stormwater runoff. Additionally, we have provided an evaluation of potential incentives to encourage Low Impact Development ( LID ) and our capacity charge recommendations in separately submitted reports. A. Current Environment The SFPUC currently provides water for a population of over 2.4 million people which includes both retail customers and wholesale customers. Retail water service to customers located in the City of San Francisco ( City ), the Town of Sunol in Alameda County, San Francisco International Airport, the San Francisco jail in San Bruno, and other customers immediately adjacent to major transmission. The majority of retail customers are provided service thorough the local water system. The SFPUC currently provides wholesale water services to 28 suburban wholesale customers in San Mateo, Santa Clara, and Alameda counties. The SFPUC water system extends from Hetch Hetchy Valley in Yosemite National Park to the Bay Area. The majority of water supplied, approximately 85%, originates from the Upper Tuolumne River watershed. The remainder comes from reservoirs in the Alameda and Peninsula watersheds. Water from the Alameda and Peninsula watersheds is treated at two SFPUC owned water treatment plants. Approximately two thirds of potable water produced is used by wholesale customers and the remaining third used by the retail customers. To enhance its ability to provide reliable, cost-effective, high-quality water in an environmentally responsible manner, in 2002 the Raftelis Financial Consultants, Inc. 23

29 SFPUC began a multi-year Water System Improvement Program ( WSIP ) that is currently estimated to total $4.4 billion. The SFPUC provides wastewater service to the City and County of San Francisco as well as parts of the surrounding areas. These surrounding areas include San Mateo County through Joint Power Agreements with the North San Mateo County Sanitary District No. 3, the Bayshore Sanitary District, and the City of Brisbane. The wastewater system has a collection and transport capacity of approximately million gallons per day ( MGD ) and a wastewater treatment design hydraulic capacity providing primary treatment of 415 MGD. The wastewater system is a combined sewer and stormwater system which is divided into three zones. The SFPUC owns two treatment plants and one wet weather plant to treat all wastewater. The Southeast Water Pollution Control Plant treats wastewater discharges from the eastern portion of the City, while the Oceanside Water Pollution Control Plant treats wastewater discharges from western portion of the City. The SFPUC also operates the North Point Wet Weather Facility during wet weather events and maintains underground storage structures to limit the number and volume of combined sewer overflows in order to meet regulatory requirements. All costs associated with dry and wet weather flows are currently recovered through the SFPUC s wastewater rate structure. B. Study and Pricing Objectives The Study began with a kick-off meeting and a conceptual design workshop to assist RFC in understanding and prioritizing the SFPUC s rate pricing objectives. Following the August 2008 kick-off meeting, RFC developed a list of utility pricing objectives based on our discussions with the SFPUC management team and our preliminary understanding of the important issues facing the SFPUC. As part of this process and the conceptual design workshop, RFC analyzed the existing SFPUC water and wastewater rate structures, performed a water usage analysis, and examined alternative rate structures to ensure proposed rates are consistent with SFPUC pricing objectives and financial planning goals. The goal of the workshop was to gain a preliminary understanding of the important issues facing the SFPUC and discuss how any potential future rate structures would address those issues. Based on our discussions with the SFPUC management team and our understanding of the important issues facing the SFPUC, RFC developed, and the SFPUC management team confirmed, the following list of utility pricing objectives: Customer Equity: Rates should be designed such that the costs recovered from each customer class are directly related to the way in which class demand characteristics and usage patterns cause the utility to incur costs and no customer class should subsidize or be subsidized by another customer class. Raftelis Financial Consultants, Inc. 24

30 Revenue Sufficiency: Rates should generate revenues sufficient to meet revenue requirements despite fluctuations in demand. Conservation / Demand Management: Rates should promote the optimal use of available water resources while reducing peak demand levels and the average consumption per customer. Ease of Implementation: Rates should be easily implemented using existing staff and the existing billing and collection infrastructure with only minor modifications. Defensibility and Reasonableness: Rates should be designed according to standard industry practice and in accordance with applicable law to avoid disputes. Easy to Understand: Rates should be readily understandable by customers. Affordability for Economically Disadvantaged Customers: Rates should be designed with mechanisms in place that allow for economically disadvantaged customers to continue receiving water service. Public Acceptance / Communication: The rate and charge structures should address internal and external stakeholder concerns and be compatible with the SFPUC administrative system. In addition, the rate and charge structure should allow for the continuation of existing management and system reports. C. Scope of the Study The scope of this Study focuses on the development of cost-based water and wastewater user rates for the retail customers through a comprehensive cost of service ( COS ) and rate design study process. Figure 2-1 provides a graphical representation of the various steps involved in the comprehensive COS and rate design process. The steps involved are: Financial Vision: Prioritize pricing objectives and develop suitable alternative rate structures for further evaluation. Financial Planning: Revenue requirements are projected for FY 2009 through FY Financial planning involves estimation of annual operating & maintenance ( O&M ) and capital expenditures, reserve targets, and operating and capital revenue sources, and the determination of required annual user revenues from rates and charges. Cost of Service Analysis: Cost of service analysis involves identifying and apportioning annual revenue requirements to the different user classes proportionate to their demand on the water and wastewater systems. Raftelis Financial Consultants, Inc. 25

31 Rate Design: Rate design involves developing fixed and variable schedules of rates for different user classes to proportionately recover the costs attributable to them. The SFPUC pricing objectives, identified above, are considered at this stage. FIGURE 2-1 COST OF SERVICE/RATE DESIGN PROCESS Raftelis Financial Consultants, Inc. 26

COMPREHENSIVE COST OF SERVICE AND RATE DESIGN ANALYSIS

COMPREHENSIVE COST OF SERVICE AND RATE DESIGN ANALYSIS Black & Veatch Holding Company 2011. All rights reserved. COMPREHENSIVE COST OF SERVICE AND RATE DESIGN ANALYSIS San Antonio Water System PREPARED FOR San Antonio Water System 26 MAY 2015 B&V PROJECT NO.

More information

La Cañada Irrigation District

La Cañada Irrigation District La Cañada Irrigation District Water Rate Study Report - 2009 March, 2009 201 S. Lake Blvd, Suite 803 Pasadena CA 91101 Phone Fax 626 583 1894 626 583 1411 www.raftelis.com March 30, 2009 Mr. Douglas M.

More information

DRAFT COMPREHENSIVE COST OF SERVICE AND RATE DESIGN ANALYSIS. San Antonio Water System. San Antonio Water System 21 MAY 2015 PREPARED FOR

DRAFT COMPREHENSIVE COST OF SERVICE AND RATE DESIGN ANALYSIS. San Antonio Water System. San Antonio Water System 21 MAY 2015 PREPARED FOR Black & Veatch Holding Company 2011. All rights reserved. DRAFT COMPREHENSIVE COST OF SERVICE AND RATE DESIGN ANALYSIS San Antonio Water System PREPARED FOR San Antonio Water System 21 MAY 2015 B&V PROJECT

More information

The City of Sierra Madre

The City of Sierra Madre The City of Sierra Madre Comprehensive Water and Wastewater Cost of Service Study Report / December 24, 2018 24640 Jefferson Avenue Suite 207 Murrieta, CA 92562 Phone 951.698.0145 www.raftelis.com December

More information

1. Accept staff report on the updated study of cost of service to provide potable water to San Jose Municipal Water System (SJMWS) customers; and

1. Accept staff report on the updated study of cost of service to provide potable water to San Jose Municipal Water System (SJMWS) customers; and CITY OF Cr SAN IPSE CAPITAL OF SILICON VALLEY TO: HONORABLE MAYOR AND CITY COUNCIL SUBJECT: MUNICIPAL WATER SYSTEM COST OF SERVICE STUDY COUNCIL AGENDA: 05/09/17 ITEM: 7.2 Memorandum FROM: Kerrie Romanow

More information

Santa Clarita Water Division

Santa Clarita Water Division Santa Clarita Water Division Retail Water Rate Cost of Service Study Report September 2017 445 S Figueroa St Suite 2270 Los Angeles, CA 90039 Phone 213.262.9300 www.raftelis.com September 11, 2017 Mr.

More information

YORK COUNTY, SOUTH CAROLINA

YORK COUNTY, SOUTH CAROLINA YORK COUNTY, SOUTH CAROLINA Water and Sewer Financial Planning and Rate Study Report October 25, 2017 1031 S. Caldwell Street Suite 100 Charlotte, NC 28203 Phone 704.373.1199 Fax 704.373.1113 www.raftelis.com

More information

Long-Term Financial Stability Workshop 6 Capstone Board of Directors January 13, 2015 Overview Introduction Review of key workshop topics Policy considerations and the upcoming budget 1 Introduction 2

More information

Temescal Valley Water District

Temescal Valley Water District Temescal Valley Water District Comprehensive Water, Recycled Water, and Wastewater Cost of Service Study Draft Report / December 7, 2016 24640 Jefferson Avenue Suite 207 Murrieta, CA 92562 Phone 951.698.0145

More information

REQUEST FOR PROPOSALS

REQUEST FOR PROPOSALS REQUEST FOR PROPOSALS REQUEST FOR PROPOSALS FOR WATER RATES AND FINANCIAL MODEL STUDY Date of Issue: January 13, 2014 Due Date: January 31, 2014 The City requests that firms interested in responding to

More information

WATER AND WASTEWATER RATE STUDY

WATER AND WASTEWATER RATE STUDY WATER AND WASTEWATER RATE STUDY Draft July 3, 2013 Prepared by: Page 1 Page 2 201 S. Lake Avenue Suite 301 Pasadena, CA 91101 Phone 626. 583. 1894 Fax 626. 583. 1411 www.raftelis.com July 1, 2013 Mr. Don

More information

SAN FRANCISCO WATER ENTERPRISE AND HETCH HETCHY WATER AND POWER. Statement of Changes in the Balancing Account. June 30, 2009

SAN FRANCISCO WATER ENTERPRISE AND HETCH HETCHY WATER AND POWER. Statement of Changes in the Balancing Account. June 30, 2009 Statement of Changes in the Balancing Account (With Independent Auditors Report Thereon) kpmg Independent Auditors Report The City and County of San Francisco and the Suburban Purchasers: KPMG LLP has

More information

Capital Region Water. Water and Wastewater Rate Study Report. November 22, Capital Region Water Water and Wastewater Rate Study

Capital Region Water. Water and Wastewater Rate Study Report. November 22, Capital Region Water Water and Wastewater Rate Study Capital Region Water Water and Wastewater Rate Study Report November 22, 2017 Capital Region Water Water and Wastewater Rate Study TABLE OF CONTENTS 1. INTRODUCTION...1 1.1 RATE STUDY SCOPE AND OBJECTIVES...1

More information

From: Lex Warmath and Elaine Conti, Raftelis Financial Consultants, Inc.

From: Lex Warmath and Elaine Conti, Raftelis Financial Consultants, Inc. 227 West Trade Street Phone 704 373 1199 www.raftelis.com Suite 1400 Fax 704 373 1113 Charlotte, NC 28202 Date: June 21, 2016 To: Mr. Bob Walker, Executive Director From: Lex Warmath and Elaine Conti,

More information

SAN ANTONIO WATER SYSTEM (SAWS) RATE ADVISORY COMMITTEE: MEETING 3

SAN ANTONIO WATER SYSTEM (SAWS) RATE ADVISORY COMMITTEE: MEETING 3 01 April, 2014 SAN ANTONIO WATER SYSTEM (SAWS) RATE ADVISORY COMMITTEE: MEETING 3 Bill Zieburtz Richard Campbell Robert Chambers RATE SETTING PROCESS STUDY APPROACH RATE SETTING OBJECTIVES FINANCIAL PLAN

More information

CITY OF REDLANDS WATER AND WASTEWATER RATE STUDY. Prepared by:

CITY OF REDLANDS WATER AND WASTEWATER RATE STUDY. Prepared by: CITY OF REDLANDS WATER AND WASTEWATER RATE STUDY Prepared by: August 30, 2010 201 S. Lake Blvd, Suite 301 Pasadena CA 91101 Phone Fax 626 583 1894 626 583 1411 www.raftelis.com August 30, 2010 Mr. Chris

More information

Water and Sewer Utility Rate Studies

Water and Sewer Utility Rate Studies Final Report Water and Sewer Utility Rate Studies July 2012 Prepared by: HDR Engineering, Inc. July 27, 2012 Mr. Mark Brannigan Director of Utilities 591 Martin Street Lakeport, CA 95453 Subject: Comprehensive

More information

Water & Sewer Rate Study. Water & Sewer Cost of Service Rate Study. City of Norco, CA. Draft Report for

Water & Sewer Rate Study. Water & Sewer Cost of Service Rate Study. City of Norco, CA. Draft Report for Water & Sewer Cost of Service Rate Study for City of Norco, CA October 11, 2016 Table of Contents October 11, 2016 Chad Blais Director of Public Works City of Norco 2870 Clark Avenue Norco, CA 92860 Re:

More information

Final Report COMPREHENSIVE WATER AND WASTEWATER COST OF SERVICE AND RATE STUDY

Final Report COMPREHENSIVE WATER AND WASTEWATER COST OF SERVICE AND RATE STUDY Final Report COMPREHENSIVE WATER AND WASTEWATER COST OF SERVICE AND RATE STUDY Phase 2 Cost of Service and Rate Design BLACK & VEATCH PROJECT NO. 192366 Black & Veatch Holding Company 2017. All rights

More information

Long-Term Financial Stability Workshop #4. Capital Investment & Financing. Board of Directors September 23, 2014

Long-Term Financial Stability Workshop #4. Capital Investment & Financing. Board of Directors September 23, 2014 Long-Term Financial Stability Workshop #4 Capital Investment & Financing Board of Directors September 23, 2014 Agenda Introduction Capital Investment & Financing Seismic Surcharge 2 Workshop Topics Workshop

More information

FORT COLLINS- LOVELAND WATER DISTRICT

FORT COLLINS- LOVELAND WATER DISTRICT FORT COLLINS- LOVELAND WATER DISTRICT Water Financial Planning and Rate Study Report March 16, 2018 District of Thousand Oaks Water and Wastewater Financial Plan Study Report March 16, 2018 Board of Directors

More information

WATER AND SEWER RATE STUDY

WATER AND SEWER RATE STUDY FINAL WATER AND SEWER RATE STUDY B&V PROJECT NO. 179322.0100 PREPARED FOR City of Lynwood, CA JANUARY 11, 2017 Black & Veatch Holding Company 2011. All rights reserved. City of Lynwood, CA WATER AND SEWER

More information

SAUSALITO-MARIN CITY SANITARY DISTRICT 1 EAST ROAD SAUSALITO, CALIFORNIA Telephone: (415) Fax: (415)

SAUSALITO-MARIN CITY SANITARY DISTRICT 1 EAST ROAD SAUSALITO, CALIFORNIA Telephone: (415) Fax: (415) 1 EAST ROAD SAUSALITO, CALIFORNIA Telephone: (415) 332-0244 Fax: (415) 332-0453 Budget FY 2017/18 Adopted by Board on June 5, 2017 BUDGET EXECUTIVE SUMMARY FISCAL YEAR 2017/18 DISTRICT OVERVIEW The Sausalito-Marin

More information

YORBA LINDA WATER DISTRICT

YORBA LINDA WATER DISTRICT YORBA LINDA WATER DISTRICT 2015 Water and Sewer Rate Study Report FINAL August 25, 2015 City of Thousand Oaks Water and Wastewater Financial Plan Study Report 445 S. Figueroa Street Suite #227 Los Angeles,

More information

MARINA COAST WATER DISTRICT FINANCIAL PLAN AND RATE AND FEE STUDY FINAL REPORT. September 2013

MARINA COAST WATER DISTRICT FINANCIAL PLAN AND RATE AND FEE STUDY FINAL REPORT. September 2013 MARINA COAST WATER DISTRICT FINANCIAL PLAN AND RATE AND FEE STUDY FINAL REPORT September 2013 10540 TALBERT AVENUE, SUITE 200 EAST FOUNTAIN VALLEY, CALIFORNIA 92708 P. 714.593.5100 F. 714.593.5101 MARINA

More information

Rainbow Municipal Water District

Rainbow Municipal Water District Rainbow Municipal Water District Potable Water Cost of Service Study November 10, 2015 201 S Lake Ave. Suite 301 Pasadena CA 91101 Phone 626.583.1894 Fax 626.583.1411 www.raftelis.com November 10, 2015

More information

CITY OF CALISTOGA WATER RATE STUDY FINAL REPORT

CITY OF CALISTOGA WATER RATE STUDY FINAL REPORT CITY OF CALISTOGA WATER RATE STUDY FINAL REPORT February 2, 218 This page was intentionally left blank. City of Calistoga Water Rate Study Report Page 2 February 2, 218 Dylan Feik City Manager City of

More information

SAN FRANCISCO WATER ENTERPRISE AND HETCH HETCHY WATER AND POWER. Statement of Changes in the Balancing Account. June 30, 2014

SAN FRANCISCO WATER ENTERPRISE AND HETCH HETCHY WATER AND POWER. Statement of Changes in the Balancing Account. June 30, 2014 Statement of Changes in the Balancing Account June 30, 2014 (With Independent Auditors Report Thereon) KPMG LLP Suite 1400 55 Second Street San Francisco, CA 94105 Independent Auditors Report The City

More information

Study Workshops are designed to be both educational and to seek broad direction from the Board

Study Workshops are designed to be both educational and to seek broad direction from the Board Study Workshops are designed to be both educational and to seek broad direction from the Board Workshop #1 Financial Forecast & Cost of Service Water, recycled water, & sewer services Revenue requirement

More information

SAN FRANCISCO WATER ENTERPRISE AND HETCH HETCHY WATER AND POWER. Statement of Changes in the Balancing Account. June 30, 2015

SAN FRANCISCO WATER ENTERPRISE AND HETCH HETCHY WATER AND POWER. Statement of Changes in the Balancing Account. June 30, 2015 Statement of Changes in the Balancing Account June 30, 2015 (With Independent Auditors Report Thereon) KPMG LLP Suite 1400 55 Second Street San Francisco, CA 94105 Independent Auditors Report The City

More information

Final COST OF SERVICE STUDY SEPTEMBER City of San Clemente

Final COST OF SERVICE STUDY SEPTEMBER City of San Clemente Final COST OF SERVICE STUDY SEPTEMBER 2017 City of San Clemente Contents CONTENTS Executive Summary... 1 Study Goals and Drivers... 1 Water Rate Analysis & Adoption... 2 Recycled Water Rate Analysis &

More information

WATER AND SEWER UTILITIES RATE STUDY

WATER AND SEWER UTILITIES RATE STUDY WATER AND SEWER UTILITIES RATE STUDY RATE DESIGN WORKSHOP WITHCITYCOUNCIL / UTILITIES COMMISSION March 6, 2014 Agenda Overview of Rate Study Process Water / Sewer Developer Impact Fees Sewer Rates Water

More information

City of San Carlos Sewer Financial Plan & Rate Update

City of San Carlos Sewer Financial Plan & Rate Update City of San Carlos Sewer Financial Plan & Rate Update Revised 06/13/16 1889 Alcatraz Avenue Berkeley, CA 94703 Tel: 510 653 3399 www.bartlewells.com June 13, 2016 City of San Carlos Department of Public

More information

MONROE CITY COUNCIL. Agenda Bill No

MONROE CITY COUNCIL. Agenda Bill No MONROE CITY COUNCIL Agenda Bill No. 15-145 TITLE: Discussion: Utility Rates (Postponed from August 18, 2015) 1 DATE: DEPT: CONTACT: PRESENTER: ITEM: 08/18/2015 Public Works Brad Feilberg Brad Feilberg

More information

Alameda County Water District. Financial Workshop Proposed Rates & Charges

Alameda County Water District. Financial Workshop Proposed Rates & Charges Alameda County Water District Financial Workshop Proposed Rates & Charges Month, October Day, Year 25, 2018 Presentation Overview Review Financial Workshops Timeline Proposed Development Charges Financial

More information

WATER UTILITY FINANCIAL PLAN AND RATE STUDY CITY OF WHITEFISH, MT MARCH 2016

WATER UTILITY FINANCIAL PLAN AND RATE STUDY CITY OF WHITEFISH, MT MARCH 2016 WATER UTILITY FINANCIAL PLAN AND RATE STUDY CITY OF WHITEFISH, MT MARCH 2016 The Financial Link Executive Summary - Water In May 2015, the City of Whitefish (City) retained AE2S to complete a Water and

More information

LONG BEACH WATER DEPARTMENT COST OF SERVICE AND RATE STUDY

LONG BEACH WATER DEPARTMENT COST OF SERVICE AND RATE STUDY LONG BEACH WATER DEPARTMENT COST OF SERVICE AND RATE STUDY Final Report / February 1, 2017 445 S. Figueroa Street Suite 2270 Los Angeles, CA 90071 Phone Fax 213. 262. 9300 213. 262. 9303 www.raftelis.com

More information

City and County of San Francisco

City and County of San Francisco City and County of San Francisco Office of the Controller City Services Auditor SAN FRANCISCO PUBLIC UTILITIES COMMISSION: The Department Appropriately Categorized Program Management Costs, but Should

More information

City and Borough of Juneau, AK WATER UTILITY AND WASTEWATER UTILITY RATE STUDY

City and Borough of Juneau, AK WATER UTILITY AND WASTEWATER UTILITY RATE STUDY City and Borough of Juneau, AK WATER UTILITY AND WASTEWATER UTILITY RATE STUDY Summary of Findings October 2003 Financial Consulting Solutions Group, Inc. 8201 -- 164th Ave. NE, Suite 300, Redmond, WA

More information

WATER VALIDATION, COST OF SERVICE & RATE DESIGN ANALYSIS WASTEWATER VALIDATION & RATE ANALYSIS MISCELLANEOUS FEES & OVERHEAD RATE ANALYSIS

WATER VALIDATION, COST OF SERVICE & RATE DESIGN ANALYSIS WASTEWATER VALIDATION & RATE ANALYSIS MISCELLANEOUS FEES & OVERHEAD RATE ANALYSIS WATER VALIDATION, COST OF SERVICE & RATE DESIGN ANALYSIS WASTEWATER VALIDATION & RATE ANALYSIS MISCELLANEOUS FEES & OVERHEAD RATE ANALYSIS B&V PROJECT NO. 179801.0100 PREPARED FOR Vallecitos Water District,

More information

Goleta Water District

Goleta Water District 201 S Lake Ave. Suite 301 Pasadena CA 91101 Phone 626 583 1894 www.raftelis.com Water Rates and Cost of Service Study Final Report / June 11, 2015 Water Cost of Service & Rate Study Report 2015 201 S Lake

More information

TOWN OF ORO VALLEY WATER UTILITY COMMISSION WATER RATES ANALYSIS REPORT OCTOBER 7, 2009

TOWN OF ORO VALLEY WATER UTILITY COMMISSION WATER RATES ANALYSIS REPORT OCTOBER 7, 2009 TOWN OF ORO VALLEY WATER UTILITY COMMISSION WATER RATES ANALYSIS REPORT OCTOBER 7, 2009 EXECUTIVE SUMMARY The functions and duties of the Oro Valley Water Utility Commission include reviewing and developing

More information

City of Ann Arbor, MI Water and Sewer Cost of Service Study Final Draft Report

City of Ann Arbor, MI Water and Sewer Cost of Service Study Final Draft Report City of Ann Arbor, MI Water and Sewer Cost of Service Study Final Draft Report June 15, 2018 June 15, 2018 Ms. Lynne Chaimowitz Budget and Finance Supervisor City of Ann Arbor 301 E. Huron Street Ann Arbor,

More information

City of Newport News Virginia. Waterworks Ratings Presentation. April 27, 2017

City of Newport News Virginia. Waterworks Ratings Presentation. April 27, 2017 City of Newport News Virginia Waterworks Ratings Presentation April 27, 2017 I. Overview Newport News Waterworks Mission Statement: To provide high quality drinking water and support public health, safety,

More information

CITY OF THOUSAND OAKS

CITY OF THOUSAND OAKS CITY OF THOUSAND OAKS 2018 Wastewater Financial Plan Update Final Report / June 23, 2017 445 S. Figueroa Street Suite #2270 Los Angeles, CA 90071 Phone 213.262.9300 Fax 213.262.9303 www.raftelis.com June

More information

Squaw Valley PSD. Water & Sewer Rate and Connection Fee Study. Presented by: Shawn Koorn Associate Vice President HDR Engineering, Inc.

Squaw Valley PSD. Water & Sewer Rate and Connection Fee Study. Presented by: Shawn Koorn Associate Vice President HDR Engineering, Inc. Squaw Valley PSD Water & Sewer Rate and Connection Fee Study February 15, 2017 Presented by: Shawn Koorn Associate Vice President HDR Engineering, Inc. Purpose of the District s Study Provide sufficient

More information

DISTRICT OF COLUMBIA WATER AND SEWER AUTHORITY

DISTRICT OF COLUMBIA WATER AND SEWER AUTHORITY DC Retail Water and Sewer Rates Committee - 1. Call to Order - Alan Roth, Chairman DISTRICT OF COLUMBIA WATER AND SEWER AUTHORITY Board of Directors DC Retail Water and Sewer Rates Committee Tuesday November

More information

Revenue Plan. August 12, Dennis Davies Deputy Director of Public Works 200 Civic Center Way El Cajon, CA 92020

Revenue Plan. August 12, Dennis Davies Deputy Director of Public Works 200 Civic Center Way El Cajon, CA 92020 1925 Palomar Oaks Way, Suite 3 Carlsbad, California 928 tel: 76 438 7755 fax: 76 438 7411 Dennis Davies Deputy Director of Public Works 2 Civic Center Way El Cajon, CA 922 Subject: Six Year Revenue Plan

More information

Wastewater Rate Study. Villa Park, Illinois

Wastewater Rate Study. Villa Park, Illinois Wastewater Rate Study Villa Park, Illinois June 2013 Executive Summary General The Village of Villa Park s Wastewater Utility is responsible for operation and maintenance of the Village s separate sanitary

More information

Alameda County Water District Community Meetings Proposed 2019 Rates & Charges

Alameda County Water District Community Meetings Proposed 2019 Rates & Charges Alameda County Water District Community Meetings Proposed 2019 Rates & Charges Los Cerritos Community Center, January Month, 30, 2019 Day, Year Presentation Overview ACWD Rate Setting Process Why are Water

More information

BODEGA BAY PUBLIC UTILITY DISTRICT Water and Wastewater Rate Study

BODEGA BAY PUBLIC UTILITY DISTRICT Water and Wastewater Rate Study BODEGA BAY PUBLIC UTILITY DISTRICT Water and Wastewater Rate Study FINAL REPORT March 22, 2018 BARTLE WELLS ASSOCIATES Independent Public Finance Advisors 1889 Alcatraz Avenue Berkeley, CA 94703-2714 Tel.

More information

WATER SUPPLY AGREEMENT THE CITY AND COUNTY OF SAN FRANCISCO WHOLESALE CUSTOMERS ALAMEDA COUNTY, SAN MATEO COUNTY AND SANTA CLARA COUNTY. between.

WATER SUPPLY AGREEMENT THE CITY AND COUNTY OF SAN FRANCISCO WHOLESALE CUSTOMERS ALAMEDA COUNTY, SAN MATEO COUNTY AND SANTA CLARA COUNTY. between. WATER SUPPLY AGREEMENT between THE CITY AND COUNTY OF SAN FRANCISCO and WHOLESALE CUSTOMERS in ALAMEDA COUNTY, SAN MATEO COUNTY AND SANTA CLARA COUNTY JULY 2009 1840795.8 TABLE OF CONTENTS Page Introduction...

More information

Town of Hillsborough. City Council Public Hearing. Water Rate Cost-of-Service Study. February 13, 2017

Town of Hillsborough. City Council Public Hearing. Water Rate Cost-of-Service Study. February 13, 2017 City Council Public Hearing February 13, 2017 Public Hearing on Proposed Water Rates PRESENTED BY Kelly J. Salt Partner 2016 Best Best & Krieger LLP Article X, section 2 (1928) The general welfare requires

More information

WASTEWATER FINANCIAL PLAN STUDY REPORT

WASTEWATER FINANCIAL PLAN STUDY REPORT WASTEWATER FINANCIAL PLAN STUDY REPORT FINAL October 7, 2013 Prepared by: Page 1 201 S. Lake Avenue Suite 301 Pasadena, CA 91101 Phone 626.583. 1894 Fax 626.583. 1411 www.raftelis.com October 7, 2013 Mr.

More information

Sanitation Rate Study Final Report

Sanitation Rate Study Final Report Sanitation Rate Study Final Report City of Simi Valley April 24, 2015 Prepared by: Page 1 201 S. Lake Avenue Suite 301 Pasadena, CA 91101 Phone 626.583.1894 Fax 626.583.1411 www.raftelis.com April 24,

More information

SUMMERLAND SANITARY DISTRICT

SUMMERLAND SANITARY DISTRICT SUMMERLAND SANITARY DISTRICT Financial Plan and Rate Study December 6, 2017 445 S. Figueroa Street Suite #2270 Los Angeles, CA 90071 Phone 213.262.9300 Fax 213.262.9303 www.raftelis.com December 6, 2017

More information

July 1, Tier Percent of Allocation Cost per ccf $0.91 $1.27 $2.86 $4.80 $ % % % % 201+%

July 1, Tier Percent of Allocation Cost per ccf $0.91 $1.27 $2.86 $4.80 $ % % % % 201+% 1 CHART EXAMPLES OF WATER RATES AND CHARGES OF MWD MEMBER AGENCIES AND THEIR SUBAGENCIES MWD Member Agencies shown: MWDOC, SDCWA, Calleguas, Las Virgenes, West Basin, LADWP, Eastern and Foothill Member

More information

City Services Appendix

City Services Appendix Technical vices 1.0 Introduction... 1 1.1 The Capital Facilities Plan... 1 1.2 Utilities Plan... 2 1.3 Key Principles Guiding Bremerton s Capital Investments... 3 1.4 Capital Facilities and Utilities Addressed

More information

April 6, Katherine Godbey Director of Finance, Coachella Valley Water District Hovley Lane East Palm Desert, CA 92260

April 6, Katherine Godbey Director of Finance, Coachella Valley Water District Hovley Lane East Palm Desert, CA 92260 April 6, 2016 Katherine Godbey Director of Finance, Coachella Valley Water District 75515 Hovley Lane East Palm Desert, CA 92260 Dear Ms. Godbey: Hawksley Consulting (a subsidiary of MWH Global) is pleased

More information

CITY OF WATERLOO Water & Sanitary Sewer Rate Design Study Final Report & Financial Plan No

CITY OF WATERLOO Water & Sanitary Sewer Rate Design Study Final Report & Financial Plan No CITY OF WATERLOO Water & Sanitary Sewer Rate Design Study Final Report & Financial Plan No. 112301 April 1st 2016 DFA Infrastructure International Inc. dfa DFA Infrastructure International Inc. 33 Raymond

More information

CITY OF TACOMA. Wastewater, Surface Water, and Solid Waste Cost of Service Rate Study December 31, 2016

CITY OF TACOMA. Wastewater, Surface Water, and Solid Waste Cost of Service Rate Study December 31, 2016 CITY OF TACOMA Wastewater, Surface Water, and Solid Waste Cost of Service Rate Study December 31, 2016 TABLE OF CONTENTS SECTION ES EXECUTIVE SUMMARY... 1 Background... 1 Objectives... 1 Rate Development

More information

Sewer Rate Study CRESCENT CITY CALIFORNIA

Sewer Rate Study CRESCENT CITY CALIFORNIA CRESCENT CITY CALIFORNIA Sewer Rate Study 27368 Via Industria, Suite 110, Temecula, California 925904856 T 951.587.3500 800.755.6864 F 888.326.6864 www.willdan.com Mr. Eugene Palazzo City Manager City

More information

UNION SANITARY DISTRICT

UNION SANITARY DISTRICT UNION SANITARY DISTRICT WASTEWATER RATE AND COST OF SERVICE STUDY December 8, 2015 HF&H Consultants, LLC This page intentionally left blank UNION SANITARY DISTRICT 5072 Benson Road Union City, CA 94587

More information

City and County of San Francisco Public Utilities Commission

City and County of San Francisco Public Utilities Commission sf p u c Water Wastewater Power City and County of San Francisco Public Utilities Commission The San Francisco Public Utilities Commission An Enterprise Department of the City and County of San Francisco,

More information

Comprehensive Water Rate Study

Comprehensive Water Rate Study Final Report Dublin San Ramon Services District Comprehensive Water Rate Study January 213 Prepared by: HDR Engineering, Inc. January 1, 213 Ms. Lori Rose Financial Services Manager Dublin San Ramon Services

More information

SAN FRANCISCO WASTEWATER ENTERPRISE. Financial Statements. June 30, 2009 and (With Independent Auditors Report Thereon)

SAN FRANCISCO WASTEWATER ENTERPRISE. Financial Statements. June 30, 2009 and (With Independent Auditors Report Thereon) Financial Statements (With Independent Auditors Report Thereon) Table of Contents Independent Auditors Report 1 Management s Discussion and Analysis 3 Financial Statements: Statements of Net Assets 14

More information

Water Consultancy. Montecito Sanitary District Wastewater Rate Study Report. Montecito Sanitary District

Water Consultancy. Montecito Sanitary District Wastewater Rate Study Report. Montecito Sanitary District 3585 Maple Street, Suite 250 Ventura, CA 93003 805-404-1467 Montecito Sanitary District Wastewater Rate Study Report March 2016 Montecito Sanitary District 1042 Monte Cristo Lane Santa Barbara CA 93108

More information

WATER, WASTEWATER, STORMWATER, AND MUNICIPAL SOLID WASTE COST OF SERVICE AND RATE DESIGN STUDY

WATER, WASTEWATER, STORMWATER, AND MUNICIPAL SOLID WASTE COST OF SERVICE AND RATE DESIGN STUDY REPORT January 2017 WATER, WASTEWATER, STORMWATER, AND MUNICIPAL SOLID WASTE COST OF SERVICE AND RATE DESIGN STUDY PREPARED BY: ECONOMICS STRATEGY STAKEHOLDERS SUSTAINABILITY www.newgenstrategies.net 3420

More information

SAN FRANCISCO WATER ENTERPRISE AND HETCH HETCHY WATER AND POWER ENTERPRISE. Statement of Changes in the Balancing Account.

SAN FRANCISCO WATER ENTERPRISE AND HETCH HETCHY WATER AND POWER ENTERPRISE. Statement of Changes in the Balancing Account. Statement of Changes in the Balancing Account (With Independent Auditors Report Thereon) kpmg Independent Auditors Report The City and County of San Francisco and the Suburban Purchasers: KPMG LLP has

More information

2016 Water and Recycled Water Rate Study WEBINAR WITH DISTRICT STAFF JUNE 29, 2016

2016 Water and Recycled Water Rate Study WEBINAR WITH DISTRICT STAFF JUNE 29, 2016 2016 Water and Recycled Water Rate Study WEBINAR WITH DISTRICT STAFF JUNE 29, 2016 Agenda Financial Policy & Financial Plan Capacity Fees Preliminary Results Tier Definitions Next Steps 2016 Water & RW

More information

NALDRAFT SEPTEMBER2015 WASTEWATE

NALDRAFT SEPTEMBER2015 WASTEWATE FI NALDRAFT SEPTEMBER2015 Cos tof S e r v i c e s S T UDY WATE R WASTEWATE R RE CY CL E DWATE R ST ORMWATE R E NVI RONME NT ALRE SOURCE S CITY OF OXNARD PUBLIC WORKS INTEGRATED MASTER PLAN COST OF SERVICE

More information

FY 2019 Approved Budget Approved by the Board of Directors on March 1, 2018

FY 2019 Approved Budget Approved by the Board of Directors on March 1, 2018 FY 2019 Approved Budget Approved by the Board of Directors on March 1, 2018 DISTRICT OF COLUMBIA WATER AND SEWER AUTHORITY Enhanced Clarification Facility Lucy Tunnel Boring Machine First Street Tunnel

More information

Distinguished Budget Presentation Award

Distinguished Budget Presentation Award GOVERNMENT FINANCE OFFICERS ASSOCIATION Distinguished Budget Presentation Award PRESENTED TO San Francisco Public Utilities Commission California For the Biennium Beginning July 1,2012 President Executive

More information

SANTA FE IRRIGATION DISTRICT

SANTA FE IRRIGATION DISTRICT SANTA FE IRRIGATION DISTRICT Water Rate Study FINAL Report/March 2016 445 S Figueroa Street Suite 2270 Los Angeles, CA 90071 Phone 213 262 9300 Fax 213 262 9303 www.raftelis.com March 21, 2016 Ms. Jeanne

More information

City of La Palma Agenda Item No. 5

City of La Palma Agenda Item No. 5 City of La Palma Agenda Item No. 5 MEETING DATE: January 19, 2016 TO: FROM: SUBMITTED BY: CITY COUNCIL CITY MANAGER Mike Belknap, Community Services Director AGENDA TITLE: Adopt a Resolution Approving

More information

FINANCIAL PLAN WATER AND WASTEWATER LINES OF SERVICE

FINANCIAL PLAN WATER AND WASTEWATER LINES OF SERVICE UCS2018-0223 ATTACHMENT 1 FINANCIAL PLAN 2019-2022 WATER AND WASTEWATER LINES OF SERVICE 2018 MARCH 14 MAKING LIFE BETTER EVERY DAY UCS2018-0223 Financial Plan 2019-2022 - Water and Wastewater Lines of

More information

Finance Committee Meeting

Finance Committee Meeting Finance Committee Meeting FY16 Strategic Business and Operating Plan and Preliminary Budget Review April 8, 2015 Finance Committee Meeting FY16 Strategic Business Operating Plan and Preliminary Budget

More information

Managing Financial Risk and Declining Demand. Presentation Outline

Managing Financial Risk and Declining Demand. Presentation Outline Managing Financial Risk and Declining Demand Washington Association of Sewer & Water Districts Spring Conference April 13, 2012 John Ghilarducci Presentation Outline 1. Why Consumption is Declining Potential

More information

CITY OF ALBANY CITY COUNCIL AGENDA STAFF REPORT

CITY OF ALBANY CITY COUNCIL AGENDA STAFF REPORT CITY OF ALBANY CITY COUNCIL AGENDA STAFF REPORT Agenda date: July 31, 2017 Reviewed by: PC SUBJECT: FROM: Public Hearing on Proposal to increase monthly sewer service charges for purposes of environmental

More information

TAUSSIG DEVELOPMENT IMPACT FEE JUSTIFICATION STUDY CITY OF ESCALON. Public Finance Public Private Partnerships Urban Economics Clean Energy Bonds

TAUSSIG DEVELOPMENT IMPACT FEE JUSTIFICATION STUDY CITY OF ESCALON. Public Finance Public Private Partnerships Urban Economics Clean Energy Bonds DAVID TAUSSIG & ASSOCIATES, INC. DEVELOPMENT IMPACT FEE JUSTIFICATION STUDY CITY OF ESCALON B. C. SEPTEMBER 12, 2016 Public Finance Public Private Partnerships Urban Economics Clean Energy Bonds Prepared

More information

TOWN OF HILLSBOROUGH. Water Rate Cost-of-Service Study

TOWN OF HILLSBOROUGH. Water Rate Cost-of-Service Study TOWN OF HILLSBOROUGH December 12, 2016 TOWN OF HILLSBOROUGH 1600 Floribunda Avenue Hillsborough, CA 94010 WATER RATE COST-OF-SERVICE STUDY December 12, 2016 HF&H CONSULTANTS, LLC 201 North Civic Drive,

More information

City of Rohnert Park SEWER FINANCIAL PLAN

City of Rohnert Park SEWER FINANCIAL PLAN City of Rohnert Park SEWER FINANCIAL PLAN AND RATE STUDY February 17, 2011 3053 Freeport Boulevard #158 Sacramento, CA 95818-4346 (916) 444-9622 www.thereedgroup.org TABLE OF CONTENTS I. EXECUTIVE SUMMARY...1

More information

San Francisco Public Utilites Commission. Retail Electric Rate Study

San Francisco Public Utilites Commission. Retail Electric Rate Study San Francisco Public Utilites Commission Retail Electric Rate Study December 30, 2010 TABLE OF CONTENTS EXECUTIVE SUMMARY... 2 OVERVIEW OF UTILITY RATE SETTING PRINCIPLES... 4 DEVELOPMENT OF THE REVENUE

More information

March 25, To the Honorable, the City Council: RECOMMENDATIONS

March 25, To the Honorable, the City Council: RECOMMENDATIONS To the Honorable, the City Council: March 25, 2019 RECOMMENDATIONS The City administration and City Council continue to recognize the importance of minimizing increases in water and sewer rates. I recommend

More information

Water Rate Study Final Report

Water Rate Study Final Report Phelan Pinon Hills Community Services District March 6, 2013 Water Rate Study Final Report Corporate Office: Anaheim, California Temecula Office: 27368 Via Industria, Suite 110 Temecula, California 92590

More information

Rate Comparison & Benchmarking Analysis

Rate Comparison & Benchmarking Analysis + Rate Comparison & Benchmarking Analysis Final Report September 2016 Firm Headquarters Redmond Town Center 7525 166 th Ave. NE Suite D-215 Redmond, WA 98052 T: (425) 867-1802 F: (425) 867-1937 www.fcsgroup.com

More information

ES.1 Findings and Recommendations... ES Overview Current Rates Rate Making Objectives

ES.1 Findings and Recommendations... ES Overview Current Rates Rate Making Objectives Table of Contents Executive Summary ES.1 Findings and Recommendations... ES-1 Chapter 1. Introduction 1.1 Overview... 1-1 1.2 Current Rates... 1-1 1.3 Rate Making Objectives... 1-1 Chapter 2. Revenue Requirement

More information

Table 2-2 Projected Water Production and Costs

Table 2-2 Projected Water Production and Costs Table 2-2 Projected Water Production and Costs Recorded Estimated Budget Forecast Description FY 2007-08 FY 2008-09 FY 2009-10 FY 2010-11 FY 2011-12 FY 2012-13 FY 2013-14 Well Production (OCWD, A-F, a)

More information

CITY OF ALHAMBRA UTILITIES DEPARTMENT SEWER SYSTEM MAINTENANCE PROGRAM (SSMP)

CITY OF ALHAMBRA UTILITIES DEPARTMENT SEWER SYSTEM MAINTENANCE PROGRAM (SSMP) CITY OF ALHAMBRA UTILITIES DEPARTMENT SEWER SYSTEM MAINTENANCE PROGRAM (SSMP) APRIL 2009 Table of Contents INTRODUCTION... 3 SECTION I: GOALS... 3 SECTION II: ORGANIZATION... 4 SECTION III: LEGAL AUTHORITY...

More information

Table of Contents. Page Witness Background and Experience General Matters Major Wastewater Rate Changes Wastewater Revenue...

Table of Contents. Page Witness Background and Experience General Matters Major Wastewater Rate Changes Wastewater Revenue... MSD Exhibit No. MSD H 0 Rate Change Proceeding WILLIAM STANNARD Direct Testimony Metropolitan St. Louis Sewer District February, 0 Table of Contents Page Witness Background and Experience... General Matters...

More information

The series 2008 Water & Sewer Revenue Bonds Feasibility Report recommended the City perform and implement a rate study for the following reasons:

The series 2008 Water & Sewer Revenue Bonds Feasibility Report recommended the City perform and implement a rate study for the following reasons: Additional Background Information Water and Wastewater The City of Fort Lauderdale supplies water and sewer services on a regional basis to over 250,000 residents of central Broward County. The areas serviced

More information

DENVER SOUTHEAST SUBURBAN WATER AND SANITATION DISTRICT MANAGEMENT S DISCUSSION AND ANALYSIS

DENVER SOUTHEAST SUBURBAN WATER AND SANITATION DISTRICT MANAGEMENT S DISCUSSION AND ANALYSIS The management of Denver Southeast Suburban Water and Sanitation District (the District) offers the readers of the District s financial statements this narrative overview and analysis of the financial

More information

Public Hearing FY15 Proposed Non-Prop 218 Rates, Charges & Regulations. June 10, 2014

Public Hearing FY15 Proposed Non-Prop 218 Rates, Charges & Regulations. June 10, 2014 Public Hearing FY15 Proposed Non-Prop 218 Rates, Charges & Regulations June 10, 2014 Key Dates FY15 Adopted Prop 218 Rates, Fees June 11, 2013 & Charges FY15 GM Report on Recommended May 13, 2014 Non-Prop

More information

WATER USER RATES & FEE STUDY

WATER USER RATES & FEE STUDY WATER USER RATES & FEE STUDY FINAL REPORT February 2016 BARTLE WELLS ASSOCIATES Independent Public Finance Consultants 1889 Alcatraz Avenue Berkeley, California 94703 www.bartlewells.com Tel: 510/653-3399

More information

City of Arroyo Grande Department of Public Works REQUEST FOR PROPOSAL WATER AND WASTEWATER RATE STUDY UPDATE

City of Arroyo Grande Department of Public Works REQUEST FOR PROPOSAL WATER AND WASTEWATER RATE STUDY UPDATE I. INTRODUCTION City of Arroyo Grande Department of Public Works REQUEST FOR PROPOSAL WATER AND WASTEWATER RATE STUDY UPDATE The City of Arroyo Grande, California (the City ) was incorporated as a general

More information

Water Rate Study FINAL January 31, 2018

Water Rate Study FINAL January 31, 2018 Water Rate Study FINAL January 31, 2018 1889 Alcatraz Avenue Berkeley, CA 94703 Tel: 510 653 3399 www.bartlewells.com January 31, 2018 Joshua Basin Water District P.O. Box 675 / 61750 Chollita Road Joshua

More information

Long-Term Financial Stability Workshop FY17 Board of Directors December 13, 2016 Workshop Agenda Review of Long-Term Financial Stability Goals Review of Financial Planning O&M, Capital and Debt Service

More information

Cost Accounting for Rate & Fee Setting: Calculating Defensible Rates and Charges

Cost Accounting for Rate & Fee Setting: Calculating Defensible Rates and Charges Cost Accounting for Rate & Fee Setting: Calculating Defensible Rates and Charges UNC School of Government EFC 2017 Water & Wastewater Finance Workshop February 28 March 1, 2017 The William & Ida Friday

More information

REQUEST FOR PROPOSALS

REQUEST FOR PROPOSALS REQUEST FOR PROPOSALS Water & Sewer Utilities Optimization City of Wichita Public Works & Utilities May 14, 2015 PROJECT DEFINITION The City of Wichita is seeking proposals for assistance with the risk,

More information

8. Current Residential Water Bills

8. Current Residential Water Bills 8. Current Residential Water Bills BAWSCA Figure 8A: Single Family Water Bills Based on Average Monthly Use Using Rates in Effect for FY 2017-18 Brisbane/GVMID Daly City Westborough WD Hayward San Bruno

More information