Measure M and 5-Year Street Paving Plan
|
|
- Job Day
- 6 years ago
- Views:
Transcription
1 Public Works Department and Public Works Commission Measure M and 5-Year Street Paving Plan City Council Worksession October 1, 2013
2 Measure M: $30 Million Accelerate 5-Year Street Paving Plan Incorporate Green Infrastructure
3 BACKGROUND Council Worksession November 15, 2011 Berkeley Streets: A Pavement Management Program Audit Report: Failing Streets: Time to Change Direction Measure M Ballot Measure November 2012 Berkeley Voters Approve $30 million Bond by 73% Council Report March 19, 2013 Measure M Expenditure Plan: Development and Implementation Measure M and 5-Year Street Paving Plan 3
4 PROGRAM DEVELOPMENT Collaborative Community Engagement Process Develop 5-Year Street Plan Plan Realign Project Delivery System Measure M and 5-Year Street Paving Plan 4
5 PUBLIC PARTICIPATION PROCESS Collaborative effort led by Public Works Commission Primary Outcome is the Scorecard Evaluation Criteria Measure M and 5-Year Street Paving Plan 5
6 PROGRAM IMPLEMENTATION Prioritize Projects and Incorporate Scorecard Criteria Begin Construction and Incorporate Green Infrastructure (Spring 2014) Evaluate the Street Improvements (Summer 2014) Update 5-Year Street Paving Plan (Fall 2014) Measure M and 5-Year Street Paving Plan 6
7 PROCESS TO PRIORITIZE PROJECTS Tools for Prioritization Pavement Management System Street Repair Policy Scorecard Evaluation Criteria Measure M and 5-Year Street Paving Plan 7
8 FINALIZE 5-YEAR STREET PAVING PLAN Years 1 + 2: FY 2014 FY 2015 List of Specific Streets Years : FY Projected Funding Levels by Project Category: 1. Overlay and surface treatments 2. Reconstructions 3. Green Infrastructure Measure M and 5-Year Street Paving Plan 8
9 FINALIZE 5-YEAR STREET PAVING PLAN Oct 1 Council Worksession on Progress and Process Oct 3 PW Commission Reviews 5-Year Street Paving Plan Nov 19 Council Consideration of 5-Year Street Paving Plan and Bond Sale Approval Measure M and 5-Year Street Paving Plan 9
10 PROJECT SCHEDULE Spring 2014 Construction Contract: Street Improvements Summer 2014 Construction Contract: Street Improvements and Green Infrastructure Fall 2014 Return to Council with Annual Report and Updated 5-Year Street Paving Plan Measure M and 5-Year Street Paving Plan 10
11 PUBLIC PARTICIPATION PROCESS Measure M and 5-Year Street Paving Plan 11
12 THE ORGANIZING TEAM Berkeley Commissions Public Works lead Community Environmental Advisory Transportation Parks & Waterfront League of Women Voters Berkeley Albany Emeryville Public Works Staff Technical support provided by Skeo Solutions Measure M and 5-Year Street Paving Plan 12
13 MEETING SCHEDULE Measure M and 5-Year Street Paving Plan 13
14 COMMUNITY MEETINGS PW staff and PWC collaborated on a public process to solicit input and advise Council on Measure M policy, including 3 well-attended community meetings: May 2 Provided background information June 8 Reviewed evaluation criteria July 18 Reviewed recommendations Measure M and 5-Year Street Paving Plan 14
15 PUBLIC PARTICIPATION PROCESS Community Meetings Collaborative Effort Public Input Comments recorded and ed back to attendees Breakout group discussions at meetings Outcome of the Public Process Identified goals and target outcomes Developed Scorecard evaluation criteria Outlined an updated planning process Identified performance metrics and oversight monitoring Measure M and 5-Year Street Paving Plan 15
16 PUBLIC PARTICIPATION PROCESS Additional Public Input Over 50 comments to: Extensive comments to Council members Breakout group discussions at meetings Revised recommendations at July 18 meeting Information on CoB website for Measure M: Go to top link Measure M: The Public Works Commission and the Public Process Measure M and 5-Year Street Paving Plan 16
17 SCORECARD CRITERIA BASED ON Criteria and Ranking from Community Meetings Public Works Staff Input Working Team Input Measure M and 5-Year Street Paving Plan 17
18 SCORECARD CRITERIA Project Rating No. Resource Allocation and Durability Evaluation Criteria RAD 1 Rates high on Street Saver output for complete reconstruction 10 RAD 2 Leverages funds 10 RAD 3 Candidate for durable or permeable paving -- long lasting 10 RAD 4 Ready to implement 10 Overall Community Improvement Max. Points Subtotal 40 OCI 1 Enhances public health and safety 10 OCI 2 Advances Berkeley Complete Streets Policy 5 OCI 3 Integrates with City Plans 10 OCI4 Integrates with other City Plan 5 Environment and Climate Subtotal 30 EC 1 Consistent with Watershed Management Plan 15 EC 2 Includes Green Infrastructure 10 EC 3 Consistent with Climate Action Plan Goals 5 Subtotal 30 TOTAL 100 Rating Measure M and 5-Year Street Paving Plan 18
19 ANNUAL PRIORITIZATION PROCESS Current Process: Run StreetSaver Coord. with City programs Coord. with utilities Comply with City policies Prepare prelim 5-yr paving plan Reconstruct Maint. Use Scorecard: Rate each street Summarize street priorities Recommend streets for reconstruction PW Dept. recommends 5-yr paving plan: Consider discretionary needs Reviewed by PW Commission Approval by Council Planning Phase Activities Measure M added steps Measure M and 5-Year Street Paving Plan 19
20 ANNUAL PRIORITIZATION PROCESS Prepare reconstruction designs: Field verify street priorities Incorporate green infrastructure Select durable pavement types Check for grant funding Prepare designs & bid documents Prepare maintenance bid documents: Field verify street priorities Incorporate green infrastructure Select slurry seal or overlay Check for grant funding Prepare bid documents Monitor performance: Track miles of street improvements Track street Pavement Condition Index Track green infrastructure installations Track life cycle cost effectiveness of Measure M investments Design and Monitoring Phase Activities Measure M added steps Measure M and 5-Year Street Paving Plan 20
21 USE OF MEASURE M FUNDS Annual City Funding Allocation (FY 2014 $3.4 M) Slurry seal and overlay treatment Accelerate PCI improvements Measure M Funds (FY 2014 $2.5 M) Use for street reconstructions Incorporate green infrastructure Measure M and 5-Year Street Paving Plan 21
22 PERFORMANCE AND REPORTING Performance Metrics Miles of street improvements PCI Green infrastructure and flood mitigation Life cycle cost Annual Reporting to PWC and City Council Measure M and 5-Year Street Paving Plan 22
23 NEXT STEPS Oct 3 PW Commission Reviews 5-Year Plan Nov 19 Council Consideration of 5-Year Street Paving Plan and Bond Sale Approval Measure M and 5-Year Street Paving Plan 23
24 Measure M and 5-Year Street Paving Plan Questions?
Honorable Mayor and Members of the City Council. Subject: Update of the 5-Year Street Paving Plan FY 2013 FY 2017
Public Works Commission CONSENT CALENDAR November 27, 2012 To: From: Honorable Mayor and Members of the City Council Public Works Commission Submitted by: Keith Alward, Chair, Public Works Commission Subject:
More informationAGENDA ITEM CITY COUNCIL MEETING DATE OCTOBER 18, 2016 BUSINESS ITEMS
AGENDA ITEM CITY COUNCIL MEETING DATE OCTOBER 18, 2016 BUSINESS ITEMS DATE : October 7, 2016 TO : City Manager FROM : Public Works Director SUBJECT : CITYWIDE STREET RESURFACING PROGRAM AND REQUEST FOR
More informationCITY OF ORINDA. Road and Drainage Repairs Plan. (As Updated in 2016) March 15, 2016
CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2016) March 15, 2016 (ORIGINALLY ADOPTED BY THE CITY COUNCIL JULY 17, 2012 AND UPDATED APRIL 22, 2014) CITY OF ORINDA 22 Orinda Way Orinda,
More informationCITY OF ORINDA. Road and Drainage Repairs Plan. (As Updated in 2016) March 15, 2016
CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2016) March 15, 2016 (ORIGINALLY ADOPTED BY THE CITY COUNCIL JULY 17, 2012 AND UPDATED APRIL 22, 2014) CITY OF ORINDA 22 Orinda Way Orinda,
More informationSubmitted by: Jeffrey Egeberg, Secretary, Public Works Commission. Street Repair Policy Update and Permeable Paver Trial Project
Public Works Commission ACTION CALENDAR July 14, 2009 To: From: Honorable Mayor and Members of the City Council Public Works Commission Submitted by: Jeffrey Egeberg, Secretary, Public Works Commission
More informationEffective Use of Pavement Management Programs. Roger E. Smith, P.E., Ph.D. Zachry Department of Civil Engineering Texas A&M University
Effective Use of Pavement Management Programs Roger E. Smith, P.E., Ph.D. Zachry Department of Civil Engineering Texas A&M University 1 Pavement Management Is A Decision Making Process Effective Pavement
More informationCity of Piedmont COUNCIL AGENDA REPORT
City of Piedmont COUNCIL AGENDA REPORT DATE: April 20, 2015 TO: FROM: Mayor and Council Paul Benoit, City Administrator SUBJECT: Street Selection Criteria and Discussion of Budget for the Proposed 2015
More informationInvestment Handout. Complete All 94 Miles of Roads As Proposed In The 15 Year Plan. (The Engineered Solution)
Town Road Improvement Investment Handout DRAFT ONLY 08_08_17 SCENARIO 1 Complete All 94 Miles of Roads As Proposed In The 15 Year Plan. (The Engineered Solution) $9.5 Million Bond $629,180 Value $130 The
More informationCounty Administrator s Office Department of Transportation & Public Works
County Administrator s Office Department of Transportation & Public Works Long-Term Road Ad Hoc Committee Update Current Roads Funding 2014 Proposed Pavement Preservation Program Pavement Management Program
More informationREVISED ENGINEER'S REPORT ASSESSMENT DISTRICT NO OF THE CITY OF SAN JACINTO
REVISED ENGINEER'S REPORT ASSESSMENT DISTRICT NO. 2003-1 OF THE CITY OF SAN JACINTO December 11, 2003 REVISED ENGINEER'S REPORT ASSESSMENT DISTRICT NO. 2003-1 CITY OF SAN JACINTO Prepared for CITY OF SAN
More informationDepartment of Public Works
Department of Public Works Bureau of Street Services Pothole Politics: The Road To Pavement Preservation Rev. Oct. 2008 William A. Robertson Director Potholes Are Like Diamonds They re Forever! HOW BIG
More informationReport to the City Council
The City of San Diego Report to the City Council DATE ISSUED: June 7, 2017 REPORT NO: ATTENTION: Honorable Members of the City Council SUBJECT: Consideration of a Proposed Ballot Measure to Authorize an
More informationLONG RANGE ROAD MAINTENANCE AND RECONSTRUCTION BUDGET FORECASTING St Croix County Unit of the WI Towns Association
LONG RANGE ROAD MAINTENANCE AND RECONSTRUCTION BUDGET FORECASTING St Croix County Unit of the WI Towns Association Scott Counter Chair, St Croix County Unit of the WI Towns Association The following Long
More informationMemorandum. CITY OF DALLAS (Report No. A15-008) June 19, 2015
Memorandum CITY OF DALLAS (Report No. A15-008) DATE: June 19, 2015 TO: SUBJECT: Honorable Mayor and Members of the City Council Audit of the Paving and Maintenance Program / Capital Program 1 The Department
More informationCity of Glendale, Arizona Pavement Management Program
City of Glendale, Arizona Pavement Management Program Current Year Plan (FY 2014) and Five-Year Plan (FY 2015-2019) EXECUTIVE SUMMARY REPORT December 2013 TABLE OF CONTENTS TABLE OF CONTENTS I BACKGROUND
More informationPARKS, RECREATION AND WATERFRONT DEPARTMENT FACILITIES ASSESSMENT AND FUNDING OPTIONS
PARKS, RECREATION AND WATERFRONT DEPARTMENT FACILITIES ASSESSMENT AND FUNDING OPTIONS Worksession February 11, 2014 1 INTRODUCTION/ OVERVIEW Parks Tax Structural Deficit Capital Improvement Program Projected
More informationNCDOT Legislative Report on Outsourcing Pavement Preservation. December 1, 2016
NCDOT Legislative Report on Outsourcing Pavement Preservation December 1, 2016 This report is presented to the Joint Legislative Transportation Oversight Committee (JLTOC) and Fiscal Research Division
More informationTown of Chino Valley Roads Maintenance Program Property Tax Rate Study 2018
Roads Maintenance Program Property Tax Rate Study 2018 This report is prepared to meet the requirements of ARS 9-499.15 October 24, 2018 Page 1 Table of Contents Introduction...3 HURF Fund Cash Flow Projections...3
More informationANNUAL REPORT. Fiscal Year
ANNUAL REPORT Fiscal Year 2014-2015 Morva Drive/Morva Court County Service Area Daniel Woldesenbet, Ph.D., P.E., Director of Public Works Alameda County Public Works Agency 951 Turner Court, Hayward, CA
More informationCity of La Habra Heights. Benefit Assessment Districts. June 6, Presented by Pablo Perez, Director
City of La Habra Heights Benefit Assessment Districts June 6, 2016 Presented by Pablo Perez, Director 1 BENEFIT ASSESSMENT DISTRICTS Proposition 218 Defines Special Benefit as Particular and distinct benefit
More informationMONTE SERENO BETTER STREETS COMMISSION AGENDA 7:00 P.M. Thursday March 8, 2018 Regular Meeting
MONTE SERENO BETTER STREETS COMMISSION AGENDA 7:00 P.M. Thursday March 8, 2018 Regular Meeting Monte Sereno City Council Chambers 18041 Saratoga-Los Gatos Road, Monte Sereno, CA 95030 MEETING CALLED TO
More informationHazim M Abdulwahid, MSC, MBA Hazim Consulting
Road Map for Establishing Pavement Maintenance Management System on the Strategic Level 13 th International O&M Conference in the Arab Countries,17-19 Nov 2015 Hazim M Abdulwahid, MSC, MBA Hazim Consulting
More informationHow To Score, Rank & Prioritize. Improving Regional Water Quality Utah Cultural Celebration Center November 21, 2014
How To Score, Rank & Prioritize Improving Regional Water Quality Utah Cultural Celebration Center November 21, 2014 Why score & prioritize? You can t implement ALL your ideas! (at least not all at once)
More informationFrequently Asked Questions County Road Maintenance Sales Tax Proposition 403: Your Roads. Your Decision.
Frequently Asked Questions County Road Maintenance Sales Tax Proposition 403: Your Roads. Your Decision. For more detailed information, please go to www.coconino.az.gov/countyroads 1. Why is the County
More informationA Stochastic Approach for Pavement Condition Projections and Budget Needs for the MTC Pavement Management System
A Stochastic Approach for Pavement Condition Projections and Budget Needs for the MTC Pavement Management System Rafael Arturo Ramirez-Flores Ph. D. Candidate Carlos Chang-Albitres Ph.D., P.E. April 16,
More informationFinancial Plan Water and Wastewater Lines of Service
2018 March 14 Page 1 of 7 EXECUTIVE SUMMARY The financial plan for The City of Calgary s (The City s) Water Treatment and Supply (Water) and Wastewater Collection and Treatment (Wastewater) lines of service
More informationA Little Less Conversation a Little More ACTION! Louie Greenwell, GISP, CFM T&M Associates Carey Johnson KY Division of Water
A Little Less Conversation a Little More ACTION! Louie Greenwell, GISP, CFM T&M Associates Carey Johnson KY Division of Water Topics Covered It s all about ACTION! Kentucky s plan for delivering actions
More informationChair and Members Engineering and Public Works Committee. Sharon Donald Director of Budgets and Financial Planning. DATE: June 18, 2014
TO: FROM: Chair and Members Engineering and Public Works Committee Sharon Donald Director of s and Financial Planning DATE: June 18, SUBJECT: of Tax Supported Capital March 31, REPORT NO: PW-7--1 RECOMMENDATION
More informationPUBLIC WORKS CIP SUPPORT
PUBLIC WORKS Public Works is comprised of several Departments/Divisions that develop, improve, and maintain the County s basic infrastructure needs related to transportation, storm water management, and
More informationANNUAL REPORT. Fiscal Year
ANNUAL REPORT Fiscal Year 2008-2009 Morva Drive/Morva Court County Service Area Daniel Woldesenbet, Ph.D., P.E., Director of Public Works Alameda County Public Works Agency 951 Turner Court, Hayward, CA
More informationCity of Grand Forks Staff Report
City of Grand Forks Staff Report Committee of the Whole November 28, 2016 City Council December 5, 2016 Agenda Item: Federal Transportation Funding Request Urban Roads Program Submitted by: Engineering
More informationPavement Preservation
Road Foreman Meeting West Windsor, Vermont March 24, 2015 Dan Patenaude, P.E. Hometown: Chester, VT Pavement Preservation Your Key to Pavement Management Success Since 1957 Corporate Headquarters Braintree,
More informationMarin County Flood Control and Water Conservation District FLOOD CONTROL ZONE 5 ADVISORY BOARD MAY 15, 2014 STAFF REPORT
FLOOD CONTROL ZONE 5 ADVISORY BOARD MAY 15, 2014 STAFF REPORT Item 1. Approval of Meeting Minutes for February 10, 2014 Recommended Action: Approve minutes. Item 2. Open Time for Items not on the Agenda
More informationMemorandum CITY OF DALLAS
Memorandum DATE December 21, 2018 CITY OF DALLAS TO Honorable Mayor and Members of the City Council SUBJECT Infrastructure Management Program On Wednesday, January 2, 2019, Robert Perez, Interim Director
More informationCity of Santa Barbara
Attachment #2 City of Comparative Indicators Report Fiscal Year 2012 Budgets November 2011 Page 1 of 5 Attachment #2 The Comparative Indicators report is a snapshot of information in six key areas. The
More informationSB 83 Additional Vehicle Registration Fee Expenditure Plan (July 15, 2010)
1. INTRODUCTION A. SUMMARY In late October, the Governor signed into law SB 83 (Hancock), which authorizes congestion management agencies (CMAs) to impose an annual vehicle registration fee increase of
More informationExhibit Tribal Transportation Improvement Plan-Approved by Board Resolution 15-XXX
See the bottom for totals and percentage of maintenance by year. FY2015 FY2016 FY2017 FY2018 Allocation $900,000 $875,000 $850,000 $825,000 2% Planning Incl. above $0 $0 $0 $0 Total $900,000 $875,000 $850,000
More informationExamples of Decision Support Using Pavement Management Data
Examples of Decision Support Using Pavement Management Data John Coplantz, PE Pavement Management Engineer Oregon Department of Transportation October 27, 2016 Strategic Network (Tactical) Project (Operational)
More informationDeveloping Optimized Maintenance Work Programs for an Urban Roadway Network using Pavement Management System
Developing Optimized Maintenance Work Programs for an Urban Roadway Network using Pavement Management System M. Arif Beg, PhD Principal Consultant, AgileAssets Inc. Ambarish Banerjee, PhD Consultant, AgileAssets
More informationExecutive Summary Interim Capital Improvement Program Overview
Executive Summary Interim Capital Improvement Program Overview Purpose The El Dorado County Community Development Agency (CDA) engages in a number of activities to assess and plan for the short and long
More informationRIDOA STATEWIDE PLANNING PROGRAM Transportation Planning
RIDOA STATEWIDE PLANNING PROGRAM Transportation Planning Land & Water Conservation Summit March 10, 2012 Statewide Planning Framework Department of Administration Statewide Planning Program State Planning
More informationENGINEER S REPORT PROPOSED ASSESSMENT FOR CSA-41 AREA ROAD MAINTENANCE AND CAPITAL IMPROVEMENTS
ENGINEER S REPORT PROPOSED 2018-19 ASSESSMENT FOR CSA-41 AREA ROAD MAINTENANCE AND CAPITAL IMPROVEMENTS PREPARED FOR: CSA-41 ROAD COMMITTEE PREPARED BY: COUNTY OF SANTA BARBARA DEPARTMENT OF PUBLIC WORKS
More informationAGENDA REPORT SUMMARY. Construction Contract Award: 2017 City-wide Street Pavement Maintenance Projects, TS-01001, TS and TS-01004
CONSENT CALENDAR Agenda Item # 5 Meeting Date: July 11, 2017 AGENDA REPORT SUMMARY Subject: Prepared by: Reviewed by: Approved by: Kathy Small, Assistant Civil Engineer Susanna Chan, Public Works Director
More informationBERKELEY UNIFIED SCHOOL DISTRICT Berkeley, California. MEASURE I GENERAL OBLIGATION BONDS PERFORMANCE AUDIT June 30, 2013
PERFORMANCE AUDIT June 30, 2013 PERFORMANCE AUDIT June 30, 2013 CONTENTS INDEPENDENT AUDITOR S REPORT... 1 BACKGROUND: LEGISLATIVE HISTORY... 2... 2 PERFORMANCE AUDIT: OBJECTIVES... 3 SCOPE... 3 METHODOLOGY...
More information1.0 CITY OF HOLLYWOOD, FL
1.0 CITY OF HOLLYWOOD, FL PAVEMENT MANAGEMENT SYSTEM REPORT 1.1 PROJECT INTRODUCTION The nation's highways represent an investment of billions of dollars by local, state and federal governments. For the
More informationMPO Staff Report Technical Advisory Committee: April 8, 2015 MPO Executive Board: April 15, 2015
MPO Staff Report Technical Advisory Committee: April 8, 2015 MPO Executive Board: April 15, 2015 RECOMMENDED ACTION: Approve the Final. RECOMMENDED ACTION from TAC: Accept the Final and include the NDDOT
More informationDRAFT. Prioritizing the Implementation of Harris County Flood Control District 2018 Bond Projects
DRAFT Prioritizing the Implementation of Harris County Flood Control District 2018 Bond Projects February 27, 2019 Purpose This document provides the draft documentation for the Harris County Flood Control
More informationTOWN OF LOS ALTOS HILLS June 21, 2018 Staff Report to the City Council
TOWN OF LOS ALTOS HILLS June 21, 2018 Staff Report to the City Council SUBJECT: APPROVE RESOLUTIONS ADOPTING THE FISCAL YEAR 2018-19 BUDGET AND GANN APPROPRIATIONS LIMIT. FROM: Carl Cahill, City Manager
More informationCity of Dallas Infrastructure Management Plan
City of Dallas Infrastructure Management Plan S.A.M.E Infrastructure Forum February 2, 2018 Rick Galceran, P.E. Director Public Works Dept. Infrastructure Management Plan City of Dallas transportation
More informationHonorable Mayor and City Council Members. Warren Hutmacher, City Manager. Date: May 18, 2016
MANAGEMENT REPORT (BI -MONTHLY) To: From: Honorable Mayor and City Council Members Warren Hutmacher, City Manager Date: May 18, 2016 Subject: Bi-monthly City Manager Report to Elected Officials May 2016
More informationLeveraging Infrastructure Management Systems. Andrea Becker, MASc, P.Eng. Doug Manarin, P.Eng. Engineering 1 Services
Leveraging Infrastructure Management Systems Andrea Becker, MASc, P.Eng. Doug Manarin, P.Eng. Engineering 1 Services PRESENTATION AGENDA Engineering s Asset Management Strategy and Framework Integrated
More informationMnDOT Highway Construction Outlook
MnDOT Highway Construction Outlook Mark Gieseke MnDOT Office of Capital Programs & Performance Measures Minnesota Transportation Alliance November 1, 2012 MnDOT Highway Construction Outlook Forecast Accuracy
More informationFiscal Responsibility to Further Invest in the Future. Executive Committee Department of Finance May 4, 2017
Fiscal Responsibility to Further Invest in the Future Executive Committee Department of Finance May 4, 2017 1 Asset Inventory Denver s Assets Parks and Recreation $1.8B Transportation $4.7B Buildings $1.9B
More informationTown Road Improvement Project Plan
Opening Comments The information to be presented is based upon the Town Road Redevelopment workbook that was created in 2015 and posted on the town website Dec 3, 2015. The approach to be discussed is
More informationCity of Clovis Date completed or revised: September 26, 2014
Date completed or revised: September 26, 2014 Completed by: (print) Renee Mathis The anticipated Fiscal Year 2014-15 revenue allocation for Street Maintenance sub-program: $912,013 X Street Maintenance
More informationGLWA: Working In Collaboration. Sue McCormick, CEO
GLWA: Working In Collaboration MWEA Collections Seminar October 2, 216 Sue McCormick, CEO One Water 2 Who is GLWA? VISION: We are the Service Provider of Choice in Southeast Michigan Sue McCormick, CEO
More informationINITIAL FISCAL IMPACT STATEMENT
Colorado Legislative Council Staff Initiative # 153 INITIAL FISCAL IMPACT STATEMENT Date: Fiscal Analyst: Larson Silbaugh (303-866-4720) LCS TITLE: TRANSPORTATION FUNDING Fiscal Impact Summary FY 2018-19
More informationCOUNTY OF SONOMA AGENDA ITEM SUMMARY REPORT
COUNTY OF SONOMA AGENDA ITEM SUMMARY REPORT Clerk of the Board Use Only Meeting Date Held Until / / / / Agenda Item No: Agenda Item No: Department: Permit and Resource Management Department/Transportation
More informationHouse Bill 20 Implementation. House Select Committee on Transportation Planning Tuesday, August 30, 2016, 1:00 P.M. Capitol Extension E2.
House Bill 20 Implementation Tuesday,, 1:00 P.M. Capitol Extension E2.020 INTRODUCTION In response to House Bill 20 (HB 20), 84 th Legislature, Regular Session, 2015, and as part of the implementation
More informationDepartment of Land Use and Transportation. Road Maintenance Funding Options June 18, 2013
Department of Land Use and Transportation Road Maintenance Funding Options June 18, 2013 Transportation Funding Strategy Three Legged Stool County Transportation System Facts Washington County maintains:
More informationSAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY
THIS PRINT COVERS CALENDAR ITEM NO. : 12 SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY DIVISION: Finance and Information Technology BRIEF DESCRIPTION: Adopting the SFMTA s Fiscal Year (FY) 2019 2023 Capital
More informationA4. Budget WBG LAC A4-1
A4. Budget Attachment 4 identifies and discusses the overall Proposal budget as well as the individual budgets for each of the seven projects proposed for implementation in the Santa Barbara County Region
More informationImproving Management Presentations
Southeastern States Equipment Managers Conference EMTSP Improving Management Presentations 2016 National Conference June 29, 2016 John F. White, PE 803 737 6675 Challenge You have a story to tell. The
More informationExecutive Summary Capital Improvement Program Overview
Executive Summary Capital Improvement Program Overview Purpose The El Dorado County Community Development Agency (CDA) engages in a number of activities to assess and plan for the short- and long term
More informationInternal Audit Vice Presidency (IADVP) FY13 Fourth Quarter Activity Report
Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Internal Audit Vice Presidency (IADVP) FY13 Fourth Quarter Activity Report August 14,
More informationCity of Lawrence Page 1 Strategic Plan Performance Measures
City of Lawrence Page 1 Strategic Plan s Strategic Plan s Performance measures are specific metrics for each aspect of performance to be monitored. In March 2017, the City of Lawrence s Critical Success
More informationDRAFT for Typesetter Legal Text of Local Ballot Measures for November 6, 2018, Consolidated General Election
Proposition A Ordinance calling and providing for a special election to be held in the City and County of San Francisco on Tuesday, November 6, 2018, for the purpose of submitting to San Francisco voters
More informationTable of Contents. Study Overview. Corridor Needs Analysis. Financial Strategies. Legislative Review
Table of Contents Study Overview Corridor Needs Analysis Climbing Lanes Additional Lane I-25/I-80 Cost Estimate ITS Truck Parking Financial Strategies Legislative Review 02 Study Overview The overall goal
More informationInstructions for Completing the Annual Road and Street Finance Report
Instructions for Completing the Annual Road and Street Finance Report Additional information you wish to submit may be attached to the report on 8.5" by 11" paper. Please round all amounts up or down to
More informationUS Army Corps of Engineers South Pacific Division. CMANC Eureka, CA October 2008
US Army Corps of Engineers South Pacific Division CMANC Eureka, CA 13-15 October 2008 Most Important to the Corps is to continue our positive relationship with CMANC Current Initiatives with CMANC Regional
More information2018 Annual Report. Highway Department Accomplishments
2018 Annual Report Highway Department The vision of the Eau Claire County Highway Department is to provide services to the taxpayer that, to the best of our ability, provides safe and efficient travel
More informationMultisector Asset Management Case Studies CHAPTER 5 THE PORTLAND, OREGON, EXPERIENCE
56 Multisector Asset Management Case Studies CHAPTER 5 THE PORTLAND, OREGON, EXPERIENCE The City of Portland (City) with a population of 568,000 comprises an area of approximately 145 square miles in north-western
More informationCapital Investment Program (CIP) About CIP
Capital Investment Program (CIP) About CIP The Capital Investment Program (CIP) is a multi-year program aimed at upgrading and expanding City facilities, buildings, grounds, streets, parks and roads. The
More informationREQUEST FOR PROPOSALS FOR CIVIL ENGINEERING SERVICES
Saddle Creek Community Services District 1000 Saddle Creek Drive - Copperopolis, CA 95228 (209) 785-0100 saddlecreekcsd.org DIRECTORS Larry Hoffman, President Ken Albertson, Vice President Darlene, DeBaldo,
More informationIntegrating Environmental, Social, and Governance Risks into Enterprise Risk Management. 7 May 2018
Integrating Environmental, Social, and Governance Risks into Enterprise Risk Management 7 May 2018 World Business Council for Sustainability Development MISSION: To accelerate the transition to a sustainable
More informationCalPERS Update and Path Forward
CalPERS Update and Path Forward Kelly Fox, Chief, Stakeholder Relations December 13, 2017 League of California Cities Fire Chiefs Facts & Figures 2 CalPERS Retirement Benefits 3 3,000+ employers 4 Financial
More informationStrategic Asset Management Policy
Strategic Asset Management Policy Submission Date: 2018-04-24 Approved by: Council Approval Date: 2018-04-24 Effective Date: 2018-04-24 Resolution Number: Enter policy number. Next Revision Due: Enter
More informationCity of Berkeley Fiscal years 2018 & 2019 ADOPTED CAPITAL IMPROVEMENT PROGRAM
City of Berkeley Fiscal years 2018 & 2019 ADOPTED CAPITAL IMPROVEMENT PROGRAM FY 2018 & 2019 ADOPTED BIENNIAL BUDGET CAPITAL IMPROVEMENT PROGRAM ELECTED OFFICIALS Mayor Jesse Arreguin Councilmembers Linda
More informationStanislaus County Department of Public Works
Roads and Bridges Condition and Funding Review Matt Machado, PE, LS Stanislaus County Department of Public Works June 14, 2016 Stanislaus County More than 1,500 miles of roads More than 230 bridges County
More informationBusiness Plan. BC Oil and Gas Research and Innovation Society. April 1, 2017 to March 31, 2020 Version Harbour Road Victoria, BC V9A 0B7
Business Plan April 1, 2017 to March 31, 2020 Version 1 300-398 Harbour Road Victoria, BC V9A 0B7 Tel: 220-1418 info@bcogris.ca BC OGRIS Business Plan (2017/20) Table of Contents Executive Summary...
More informationSECTION Watershed Informed Approach to FY 2016 Budget Development
SECTION 2 This section provides information and guidance regarding three new initiatives by the Civil Works Integration within USACE to make the budget formulation more streamlined, our investments more
More informationCity of Sonoma 2015 Pavement Management Program Update (P-TAP 16) Final Report February 25, 2016 TABLE OF CONTENTS
City of Sonoma I. Introduction TABLE OF CONTENTS II. Methodology III. Pavement Condition Index (PCI) / Remaining Service Life (RSL) Report IV. Budget Analysis Reports A. Budget Needs Report Five Year B.
More informationAppendix T. Financial Policies
Appendix T Financial Policies The Municipality of Anchorage has established financial policies to achieve and maintain a positive long term financial condition. These policies provide guidelines for current
More informationNew Jersey Institute of Technology
New Jersey Institute of Technology University Senate Committee on Finances November 1, 2017 FY2018 Approved Operating Budget Executive Summary The approved FY2018 Operating Budget: Totals $518.8M, a 6.8%
More informationPublic-Private Partnerships in Maryland. Canada-US Forum on Public-Private Partnerships October 3, 2013
Public-Private Partnerships in Maryland Canada-US Forum on Public-Private Partnerships October 3, 2013 Towards a More Comprehensive P3 Approach 2010 P3 Law (Chapters 640 and 641 of 2010) Joint Legislative
More informationYour Finance Department (FY 2015 Proposed Budget pages 73-81)
Your Finance Department (FY 2015 Proposed Budget pages 73-81) 1 Your Finance Department The Department has the same proportion of budget allocation as staffing (4%) 2 FY 2015 Addition: Risk Analyst for
More informationCity of San Juan Capistrano Agenda Report. Honorable Mayor and Members of the City Council
10/3/2017 E12 City of San Juan Capistrano Agenda Report TO: FROM: Honorable Mayor and Members of the City Council ~jamin Siegel, City Manager SUBMITTED BY: Ste~e May, Public Works and Utilities Director
More information2017 UNIFIED TRANSPORTATION PROGRAM AND HB 20 IMPLEMENTATION
2017 UNIFIED TRANSPORTATION PROGRAM AND HB 20 IMPLEMENTATION TEMPO Meeting July 21, 2016 Current Initiatives On-going efforts to address performance-based planning and programming processes as required
More informationFiscal Year Proposed Budget
Mayor Antonio R. Villaraigosa Fiscal Year 2011-12 Proposed Budget Budget and Financial Policy Team WHAT HAVE WE ALREADY IMPLEMENTED? Workforce Reductions ERIP (2,400), Layoffs (473) and Transfers (618)
More informationCapital Improvements Plan and Budget. April 10, 2012
Capital Improvements Plan and Budget April 10, 2012 1 Sets project priorities for at least a five year period Current CIP shows projects out ten years Serves as a planning tool for capital improvement
More informationHonorable Mayor and Members of the City Council. Failing Streets: Time to Change Direction to Achieve Sustainability
Office of the City Auditor Ann Marie Hogan, City Auditor CONSENT CALENDAR November 15, 2011 To: From: Subject: Honorable Mayor and Members of the City Council Ann-Marie Hogan, City Auditor RECOMMENDATION
More informationMEASURE B AND MEASURE BB Annual Program Compliance Report Reporting Fiscal Year AGENCY CONTACT INFORMATION
MEASURE B AND MEASURE BB Annual Program Compliance Report Reporting Fiscal Year 20172018 AGENCY CONTACT INFORMATION Agency Name: City of Fremont Date: 12/21/2018 Primary Point of Contact Name: Tish Saini
More informationACTION CALENDAR February 13, 2018 (Continued from January 30, 2018) Members of the City Council. Mayor Jesse Arreguin. Subject:
Page 1 of 6 33 Office of the Mayor ACTION CALENDAR February 13, 2018 (Continued from January 30, 2018) To: From: Subject: Members of the City Council Mayor Jesse Arreguin Amending BMC Chapter 9.04: Tax
More informationFOLSOM CORDOVA UNIFIED SCHOOL DISTRICT Rancho Cordova, California
Rancho Cordova, California MEASURE M GENERAL OBLIGATION BONDS PERFORMANCE AUDIT June 30, 2014 MEASURE M GENERAL OBLIGATION BONDS PERFORMANCE AUDIT June 30, 2014 CONTENTS INDEPENDENT AUDITOR S REPORT...
More informationFort Collins Strategic Planning & Budget Process
1 Fort Collins Strategic Planning & Budget Process Macro Planning Process 2013 2014 2015 2016 Elections On Board Planning Activity Strategic Plan 5 Yr View BFO 2015/2016 Execution Activity 2013 Budget
More informationGov's Planning Estimates Project Title Rank Fund Project Requests for State Funds
This document is made available electronically by the Minnesota Legislative Reference Library as part of an ongoing digital archiving project. http://www.leg.state.mn.us/lrl/lrl.asp Water and Soil Resources
More informationCapital Overview. Capital projects also include purchase of infrastructure, plant, and equipment that meet the following thresholds:
Capital Overview The capital budget consists of capital projects, which are a set of activities that maintain or improve a city asset, often referred to as infrastructure-from buildings, to park trails,
More informationFROM: CITY MANAGER DEPARTMENT: PUBLIC WORKS DATE: SEPTEMBER 19, 2001 CMR:354:01
TO: HONORABLE CITY COUNCIL FROM: CITY MANAGER DEPARTMENT: PUBLIC WORKS DATE: SEPTEMBER 19, 2001 CMR:354:01 SUBJECT: REQUEST APPROVAL OF A BUDGET AMENDMENT ORDINANCE FOR FISCAL YEAR 2001-02 IN THE AMOUNT
More informationSTREET FUNDING BEND CITY COUNCIL APRIL 5, 2017 CITY OF BEND
STREET FUNDING BEND CITY COUNCIL APRIL 5, 2017 AGENDA FOR TODAY Objective: Improve condition of Streets for 2017-2019 biennium, per Council Goals 1. Background on Street Funding and related goals and decisions
More informationEXCELLENCE INNOVATION SERVICE VALUE
Incorporation of Geotechnical Elements as an Asset Class within Transportation Asset Management and Development of Risk Based and Life Cycle Cost Performance Strategies by Mark Vessely, P.E. Shannon &
More information