Indirect cost associated with project increases linearly with project duration. A typical line for indirect cost is shown in figure above.
|
|
- Ginger Melton
- 5 years ago
- Views:
Transcription
1 CPM Model The PERT model was developed for project characterized by uncertainty and the CPM model was developed for projects which are relatively risk-free. While both the approached begin with the development of the network and a focus on the critical path. The PERT approach is probabilistic and the CPM approach is deterministic. This does not howver mean that in the CPM analysis we work with single time estimates. In fact the principle focus of CPM analysis in on variations in activity times as a result of changes in resources assignment. These variations are planned and related to resource assignments and are not caused by random factor beyond the control of management as in case of PERT analysis. The main thrust of CPM analysis is on time-cost relationships and it seeks to determine the project schedule which minimize total cost. Assumption: The usual assumption of CPM model are: i. The cost associated with project can be divided into two components: direct cost and indirect cost. Direct costs are incurred on direct material and direct labour. Indirect cost consist of overhead items like indirect supplies, rent, insurance, managerial services etc. ii. Activities of the project can be expedited by crashing which involves employing more resources iii. Crashing reduces time but enhances direct costs because of factors like overtime payments, extra payments, and wastages. The relationship between time and direct activity cost can be reasonably approximated by a downward slopping straight line. A typical cost-time line is shown below: iv. Indirect cost associated with project increases linearly with project duration. A typical line for indirect cost is shown in figure above. Procedure: Given above assumption, CPM analysis seeks to examine the consequences of crashing on total cost (direct cost plus indirect cost). Since the behavior of indirect project cost is well defined, the bulk of CPM analysis is concerned with the relationship between the total direct cost and project duration. The procedure used in this respect is generally as follows:
2 i. Obtain the critical path in the network. Determine the project duration and direct cost. ii. Examine the cost-time slope of activities on the critical path obtained and crash the activity which has the least slope. iii. Construct the new critical path after crashing as per step-2. Determine the project duration and cost. iv. Repeat step-2 and step-3 till activities on the critical path (which may change every time) are crashed. Example Figure below shows the activity duration, direct activity cost of a project. The indirect cost is Rs 2000 per week Time in weeks Cost Cost to Expedite per week Activity Normal Crash Normal Rs. Crash Rs. Rs , Project network with normal duration is shown below: Figure CPM-1
3 The critical path in the all-normal network is ( ). The project duration is 30 weeks and the total direct cost is Rs. 45,200/- Examining the time-cost slope of activities on the critical path we find that the activity(2-4) has the lowest slope; in other words, the cost to expedite per week is the lowest for activity (2-4). Hence activity (2-4) is crashed. The proper network after such a crashing is shown below: Figure CPM-2 In this figure the critical path is ( ), with a length of 29 weeks, and the total direct cost is Rs. 46,700. Looking at the time-cost slope of the activities on the new critical path ( ). We find that the activity (5-6) has the lowest slope. Hence the activity is crashed. The project network after such a crashing is shown below where critical path is ( ) with a length of 27 weeks and the total direct cost is Rs
4 Figure CPM-3 Comparing the cost-time slope of the non-crashed activities on the new critical path ( ), we find that the activity which costs the least to crash is (1-2). Hence this is crashed. The project network after such a crash is shown below where the new critical path is ( ) with a length of 24 weeks and total direct cost of Rs /- Figure CPM-4 Looking at the time-cost slope of the non-crashed activities on the new critical path ( ), we find that the activity (6-7) has the lowest slope. Hence it is crashed. The project network after such a crash is shown below having two new critical path ( ) and ( ), both with a length of 21 weeks, and total direct cost of Rs /-
5 Figure CPM-5 Considering the time-cost of non-crashed activities on crtical path ( ) and ( ), we find that activity (3-5) which is common to both the critical paths is the least costly to crash. Hence, it is crashed. The new network is shown below having the new critical path ( ) with duration of 20 weeks and total direct cost is Rs Figure CPM-6 Looking at the new critical path ( ) we find that the only non-crashed activity is (4-6). Crashing this gives us the project network shown below having the critical path ( ) with duration of 19.5weeks and total cost Rs /- - Figure CPM-7
6 Since all the activities on the critical path ( ) are crashed, there is no possibility of further time reduction. Hence let us now look at the time-cost relationship from all above figures and as shown below: Figure Activity crashed Project duration in weeks Total Direct cost Total Indirect cost Total Cost CPM-1 None CPM-2 (2-4) CPM-3 (2-4) and (5-6) CPM-4 (1-2), (2-4) and (5-6) CPM-5 (1-2), (2-4), (5-6) and (6-7) CPM-6 (1-2), (2-4), (3-5), (5-6) and (6-7) CPM-7 (1-2), (2-4), (3-5) (5-6) and (6-7) Figure CPM-8 If the objective is to minimize the total cost of the project, the pattern of crashing suggested by CPM-6 is optimul. If the objective is to minimize the project durationthen the pattern of crashing suggested by fig CPM-7 is optimal. In real life situation, however, both the factors may be important. In addition, factors like strain on resources and degree of manageability are also important. The final decision would involve a careful weighing and balancing of these diverse factors, some quantitative, some qualitative. In any case, information along the lines provided in figure CPM-8 provides useful input for decision making.
INTRODUCTION PROJECT MANAGEMENT
CHAPTER 7. 1 RESOURCE INTRODUCTION ALLOCATION TO PROJECT MANAGEMENT Prepared by: Dr. Maria Elisa Linda T. Cruz Prepared by: Dr. Maria Elisa Linda T. Cruz 1 Chapter 7. Resource Allocation 7.1 Critical Path
More informationProject Time-Cost Trade-Off
Project Time-Cost Trade-Off 7.1 Introduction In the previous chapters, duration of activities discussed as either fixed or random numbers with known characteristics. However, activity durations can often
More informationSCHEDULE CREATION AND ANALYSIS. 1 Powered by POeT Solvers Limited
SCHEDULE CREATION AND ANALYSIS 1 www.pmtutor.org Powered by POeT Solvers Limited While building the project schedule, we need to consider all risk factors, assumptions and constraints imposed on the project
More informationOptimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur. Lecture - 18 PERT
Optimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur Lecture - 18 PERT (Refer Slide Time: 00:56) In the last class we completed the C P M critical path analysis
More informationReducing Project Duration
CHAPTER NINE Reducing Project Duration McGraw-Hill/Irwin Copyright 2011 by The McGraw-Hill Companies, Inc. All rights reserved. Rationale for Reducing Project Duration Time Is Money: Cost-Time Tradeoffs
More informationProject Planning. Jesper Larsen. Department of Management Engineering Technical University of Denmark
Project Planning jesla@man.dtu.dk Department of Management Engineering Technical University of Denmark 1 Project Management Project Management is a set of techniques that helps management manage large-scale
More informationA convenient analytical and visual technique of PERT and CPM prove extremely valuable in assisting the managers in managing the projects.
Introduction Any project involves planning, scheduling and controlling a number of interrelated activities with use of limited resources, namely, men, machines, materials, money and time. The projects
More informationAllocate and Level Project Resources
Allocate and Level Project Resources Resource Allocation: Defined Resource Allocation is the scheduling of activities and the resources required by those activities while taking into consideration both
More informationTime and Cost Optimization Techniques in Construction Project Management
Time and Cost Optimization Techniques in Construction Project Management Mr.Bhushan V 1. Tatar and Prof.Rahul S.Patil 2 1. INTRODUCTION In the field of Construction the term project refers as a temporary
More informationProject Planning. Identifying the Work to Be Done. Gantt Chart. A Gantt Chart. Given: Activity Sequencing Network Diagrams
Project Planning Identifying the Work to Be Done Activity Sequencing Network Diagrams Given: Statement of work written description of goals work & time frame of project Work Breakdown Structure Be able
More informationCHAPTER 6 CRASHING STOCHASTIC PERT NETWORKS WITH RESOURCE CONSTRAINED PROJECT SCHEDULING PROBLEM
CHAPTER 6 CRASHING STOCHASTIC PERT NETWORKS WITH RESOURCE CONSTRAINED PROJECT SCHEDULING PROBLEM 6.1 Introduction Project Management is the process of planning, controlling and monitoring the activities
More informationBudgeting planning. Breakers, Inc. is preparing budgets for the quarter ending June 30. Budgeted sales for the next five months are:
Budgeting planning We use budgets as a target that we hope or expect to achieve. These are financial and non-financial in nature, but typically offer some quantitative measure We will begin by talking
More informationINTERNATIONAL BURCH UNIVERSITY
INTERNATIONAL BURCH UNIVERSITY FACULTY OF ECONOMICS MANAGEMENT AND INFORMATION TECHNOLOGIES IMPLEMENTATION OF CRITICAL PATH METHOD AND PROJECT EVALUATION AND REVIEW TECHNIQUE Graduate Project by Selma
More informationAppendix A Decision Support Analysis
Field Manual 100-11 Appendix A Decision Support Analysis Section I: Introduction structure development, and facilities. Modern quantitative methods can greatly facilitate this Complex decisions associated
More informationProject Management. Chapter 2. Copyright 2013 Pearson Education, Inc. publishing as Prentice Hall
Project Management Chapter 2 02-0 1 What is a Project? Project An interrelated set of activities with a definite starting and ending point, which results in a unique outcome for a specific allocation of
More informationUNIT-II Project Organization and Scheduling Project Element
UNIT-II Project Organization and Scheduling Project Element Five Key Elements are Unique. Projects are unique, one-of-a-kind, never been done before. Start and Stop Date. Projects must have a definite
More informationProject Risk Management
Project Risk Management Introduction Unit 1 Unit 2 Unit 3 PMP Exam Preparation Project Integration Management Project Scope Management Project Time Management Unit 4 Unit 5 Unit 6 Unit 7 Project Cost Management
More informationProject Management. A Practitioner s Guide. Steven M. Bragg
Project Management A Practitioner s Guide Steven M. Bragg Chapter 1 Overview of Project Management... 1 Learning Objectives... 1 Introduction... 1 Project Management Activities... 1 The Need for Project
More informationTo acquaint yourself with the practical applications of simulation methods.
Unit 5 SIMULATION THEORY Lesson 40 Learning objectives: To acquaint yourself with the practical applications of simulation methods. Hello students, Now when you are aware of the methods of simulation and
More information1 of 14 4/27/2009 7:45 AM
1 of 14 4/27/2009 7:45 AM Chapter 7 - Network Models in Project Management INTRODUCTION Most realistic projects that organizations like Microsoft, General Motors, or the U.S. Defense Department undertake
More information8.6 FORMULATION OF PROJECT REPORT. 160 // Management and Entrepreneurship
160 // Management and Entrepreneurship (9) Raw material: List of raw material required by quality and quantity, sources of procurement, cost of raw material, tie-up arrangements, if any for procurement
More informationProject Theft Management,
Project Theft Management, by applying best practises of Project Risk Management Philip Rosslee, BEng. PrEng. MBA PMP PMO Projects South Africa PMO Projects Group www.pmo-projects.co.za philip.rosslee@pmo-projects.com
More informationProject Management. Project Mangement. ( Notes ) For Private Circulation Only. Prof. : A.A. Attarwala.
Project Mangement ( Notes ) For Private Circulation Only. Prof. : A.A. Attarwala. Page 1 of 380 26/4/2008 Syllabus 1. Total Project Management Concept, relationship with other function and other organizations,
More informationPhD PROPOSAL WRITING GUIDE
Code PO.3.2.0 ENG Adoption date 12/09/2016 Revision date - Pages 12 PhD PROPOSAL Content: 1. General notes 2. Parts of PhD Proposal 3. Other instructions 4. Example 5. Publications Requirements Prepared
More informationA UNIT BASED CRASHING PERT NETWORK FOR OPTIMIZATION OF SOFTWARE PROJECT COST PRITI SINGH, FLORENTIN SMARANDACHE, DIPTI CHAUHAN, AMIT BHAGHEL
A UNIT BASED CRASHING PERT NETWORK FOR OPTIMIZATION OF SOFTWARE PROJECT COST PRITI SINGH, FLORENTIN SMARANDACHE, DIPTI CHAUHAN, AMIT BHAGHEL Abstract: Crashing is a process of expediting project schedule
More informationProgramme Evaluation and Review Technique
15 Programme Evaluation and Review Technique LEARNING OBJECTIVES : After studying this chapter, you will be able to : l l l l l l l l l Explain generic term network analysis and such related terms as Critical
More informationISSN: [Mali* et al., 6(3): March, 2017] Impact Factor: 4.116
IJESRT INTERNATIONAL JOURNAL OF ENGINEERING SCIENCES & RESEARCH TECHNOLOGY TIME AND COST OPTIMIZATION BY MSP SOFTWARE Mali P. A*, Lokhande A.Y, Kadam S.K, Shirole S.B, More P.N, Velhal A.J * Department
More informationThe objectives of the producer
The objectives of the producer Laurent Simula October 19, 2017 Dr Laurent Simula (Institute) The objectives of the producer October 19, 2017 1 / 47 1 MINIMIZING COSTS Long-Run Cost Minimization Graphical
More informationDISCLAIMER. The Institute of Chartered Accountants of India
DISCLAIMER The Suggested Answers hosted in the website do not constitute the basis for evaluation of the students answers in the examination. The answers are prepared by the Faculty of the Board of Studies
More informationA New Mathematical Model for Time Cost Trade-off. Problem with Budget Limitation Based on. Time Value of Money
Applied Mathematical Sciences, Vol. 4, 2010, no. 63, 3107-3119 A New Mathematical Model for Time Cost Trade-off Problem with Budget Limitation Based on Time Value of Money H. Nikoomaram Dept. of management,
More informationPAPER 5 : COST MANAGEMENT Answer all questions.
Question 1 (a) (b) PAPER 5 : COST MANAGEMENT Answer all questions. A company uses absorption costing system based on standard costs. The total variable manufacturfing cost is Rs. 6 per unit. The standard
More informationProject Management Chapter 13
Lecture 12 Project Management Chapter 13 Introduction n Managing large-scale, complicated projects effectively is a difficult problem and the stakes are high. n The first step in planning and scheduling
More informationRandom Variables and Probability Distributions
Chapter 3 Random Variables and Probability Distributions Chapter Three Random Variables and Probability Distributions 3. Introduction An event is defined as the possible outcome of an experiment. In engineering
More informationDISCLAIMER. The Institute of Chartered Accountants of India
DISCLAIMER The Suggested Answers hosted in the website do not constitute the basis for evaluation of the students answers in the examination. The answers are prepared by the Faculty of the Board of Studies
More informationInternational Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ
International Project Management prof.dr MILOŠ D. MILOVANČEVIĆ Project time management Project cost management Time in project management process Time is a valuable resource. It is also the scarcest. Time
More informationUNIT 8 CONTROLLING Meaning & Definition Controlling means ensuring that activities in an organisation are performed as per the plans. Controlling also ensures that an organisation s resources are being
More informationProgram Evaluation and Review Technique (PERT) in Construction Risk Analysis Mei Liu
Applied Mechanics and Materials Online: 2013-08-08 ISSN: 1662-7482, Vols. 357-360, pp 2334-2337 doi:10.4028/www.scientific.net/amm.357-360.2334 2013 Trans Tech Publications, Switzerland Program Evaluation
More informationReal-World Project Management. Chapter 15
Real-World Project Chapter 15 Characteristics of Project Unique one-time focus Difficulties arise from originality Subject to uncertainties Unexplained or unplanned events often arise, affecting resources,
More informationCOMPARATIVE STUDY OF TIME-COST OPTIMIZATION
International Journal of Civil Engineering and Technology (IJCIET) Volume 8, Issue 4, April 2017, pp. 659 663, Article ID: IJCIET_08_04_076 Available online at http://www.iaeme.com/ijciet/issues.asp?jtype=ijciet&vtype=8&itype=4
More informationu w 1.5 < 0 These two results imply that the utility function is concave.
A person with initial wealth of Rs.1000 has a 20% possibility of getting in a mischance. On the off chance that he gets in a mishap, he will lose Rs.800, abandoning him with Rs.200; on the off chance that
More informationTextbook: pp Chapter 11: Project Management
1 Textbook: pp. 405-444 Chapter 11: Project Management 2 Learning Objectives After completing this chapter, students will be able to: Understand how to plan, monitor, and control projects with the use
More informationEXERCISE Draw the network diagram. a. Activity Name A B C D E F G H
XRIS. What do you mean by network analysis? xplain with counter examples.. What are the basic differences between PM and PRT analysis of project work?. State the rule of constructing the network diagram..
More informationSUGGESTED SOLUTION FINAL MAY 2014 EXAM
SUGGESTED SOLUTION FINAL MAY 2014 EXAM ADVANCED MANAGEMENT ACCOUNTING Prelims (Test Code - F N J 3 0 5) (Date : 08 April, 2014) Head Office :Shraddha, 3 rd Floor, Near Chinai College, Andheri (E), Mumbai
More informationChapter 9: Reducing Project Duration 4KF3
Lecture Notes Options for Accelerating Project Completion Unconstrained Resources o Adding resources o Outsourcing o Overtime o Core project team o Do it twice Constrained Resources o Fast-tracking o Critical-chain
More informationDecision Support Tool for Project Time-Cost Trade-off
Decision Support Tool for Project Time-Cost Trade-off Fikri Dweiri Industrial Engineering and Engineering Management Department University of Sharjah Sharjah, UAE, 27272 fdweiri@sharjah.ac.ae Abstract
More informationCHAPTER 5 STOCHASTIC SCHEDULING
CHPTER STOCHSTIC SCHEDULING In some situations, estimating activity duration becomes a difficult task due to ambiguity inherited in and the risks associated with some work. In such cases, the duration
More informationCOST MANAGEMENT IN CONSTRUCTION PROJECTS WITH THE APPROACH OF COST-TIME BALANCING
ISSN: 0976-3104 Lou et al. ARTICLE OPEN ACCESS COST MANAGEMENT IN CONSTRUCTION PROJECTS WITH THE APPROACH OF COST-TIME BALANCING Ashkan Khoda Bandeh Lou *, Alireza Parvishi, Ebrahim Javidi Faculty Of Engineering,
More informationNPV Method. Payback Period
1. Why the payback method is often considered inferior to discounted cash flow in capital investment appraisal? A. It does not take account of the time value of money B. It does not calculate how long
More informationCISC 322 Software Architecture
CISC 22 Software Architecture Project Scheduling (PERT/CPM) Ahmed E. Hassan (Edited For Course Presentation, 206) Project A project is a temporary endeavour undertaken to create a "unique" product or service
More informationProject Management Techniques (PMT)
Project Management Techniques (PMT) Critical Path Method (CPM) and Project Evaluation and Review Technique (PERT) are 2 main basic techniques used in project management. Example: Construction of a house.
More informationLogistics. Lecture notes. Maria Grazia Scutellà. Dipartimento di Informatica Università di Pisa. September 2015
Logistics Lecture notes Maria Grazia Scutellà Dipartimento di Informatica Università di Pisa September 2015 These notes are related to the course of Logistics held by the author at the University of Pisa.
More informationIntroduction. Introduction. Six Steps of PERT/CPM. Six Steps of PERT/CPM LEARNING OBJECTIVES
Valua%on and pricing (November 5, 2013) LEARNING OBJECTIVES Lecture 12 Project Management Olivier J. de Jong, LL.M., MM., MBA, CFD, CFFA, AA www.olivierdejong.com 1. Understand how to plan, monitor, and
More informationMonitoring and Controlling RCC Work in Delayed Construction Projects
Monitoring and Controlling RCC Work in Delayed Construction s Nimesh Gujarati, Dr. B S Balapgol Post Graduate Student (Construction and Management), DYPCOE, Akurdi, Pune-44, Maharashtra, India Principal,
More information06IP/IM74 OPERATIONS RESEARCH
06IP/IM74 OPERATIONS RESEARCH UNIT - 6: PROJECT MANAGEMENT USING NETWORK ANALYSIS (By Dr.G.N.MOHAN BABU, Prof & HOD (I&P Engg), MCE, Hassan 573 021) LEARNING OBJECTIVES OF THE MODULE: By the end of this
More informationDetermining the Failure Level for Risk Analysis in an e-commerce Interaction
Determining the Failure Level for Risk Analysis in an e-commerce Interaction Omar Hussain, Elizabeth Chang, Farookh Hussain, and Tharam S. Dillon Digital Ecosystems and Business Intelligence Institute,
More informationPoor Man s Approach to Monte Carlo
Poor Man s Approach to Monte Carlo Based on the PMI PMBOK Guide Fourth Edition 20 IPDI has been reviewed and approved as a provider of project management training by the Project Management Institute (PMI).
More information6/7/2018. Overview PERT / CPM PERT/CPM. Project Scheduling PERT/CPM PERT/CPM
/7/018 PERT / CPM BSAD 0 Dave Novak Summer 018 Overview Introduce PERT/CPM Discuss what a critical path is Discuss critical path algorithm Example Source: Anderson et al., 01 Quantitative Methods for Business
More informationSubject O Basic of Operation Research (D-01) Date O 20/04/2011 Time O 11.00 to 02.00 Q.1 Define Operation Research and state its relation with decision making. (14) What are the opportunities and short
More informationTopic 3: An introduction to cost terms and concepts
Topic 3: An introduction to cost terms and concepts Ana Mª Arias Alvarez University of Oviedo Department of Accounting amarias@uniovi.es School of Business Administration Course: Financial Statement Analysis
More informationExcavation and haulage of rocks
Use of Value at Risk to assess economic risk of open pit slope designs by Frank J Lai, SAusIMM; Associate Professor William E Bamford, MAusIMM; Dr Samuel T S Yuen; Dr Tao Li, MAusIMM Introduction Excavation
More informationECONOMICS. Time Allowed: 3 hours Maximum Marks: 100
Sample Paper (CBSE) Series ECO/SP/1B Code No. SP/1-B ECONOMICS Time Allowed: 3 hours Maximum Marks: 100 General Instructions: (i) All Questions in both the sections are compulsory. However there is internal
More informationInternational Finance. Estimation Error. Campbell R. Harvey Duke University, NBER and Investment Strategy Advisor, Man Group, plc.
International Finance Estimation Error Campbell R. Harvey Duke University, NBER and Investment Strategy Advisor, Man Group, plc February 17, 2017 Motivation The Markowitz Mean Variance Efficiency is the
More informationChapter 4 Topics. Behavior of the representative consumer Behavior of the representative firm Pearson Education, Inc.
Chapter 4 Topics Behavior of the representative consumer Behavior of the representative firm 1-1 Representative Consumer Consumer s preferences over consumption and leisure as represented by indifference
More information13304 Strategic Management Accounting CA Professional (Strategic Level I) Examination December 2013
SUGGESTED SOLUTIONS 13304 Strategic Management Accounting CA Professional (Strategic Level I) Examination December 2013 THE INSTITUTE OF CHARTERED ACCOUNTANTS OF SRI LANKA All Rights Reserved Answer No.
More informationPROJECT MANAGEMENT: PERT AMAT 167
PROJECT MANAGEMENT: PERT AMAT 167 PROBABILISTIC TIME ESTIMATES We need three time estimates for each activity: Optimistic time (t o ): length of time required under optimum conditions; Most likely time
More information(RISK.03) Integrated Cost and Schedule Risk Analysis: A Draft AACE Recommended Practice. Dr. David T. Hulett
(RISK.03) Integrated Cost and Schedule Risk Analysis: A Draft AACE Recommended Practice Dr. David T. Hulett Author Biography David T. Hulett, Hulett & Associates, LLC Degree: Ph.D. University: Stanford
More informationThe New Normative Macroeconomics
The New Normative Macroeconomics This lecture examines the costs and trade-offs of output and inflation in the short run. Five General Principles of Macro Policy Analysis A. When making decisions, people
More informationPerformance risk evaluation of long term infrastructure projects (PPP-BOT projects) using probabilistic methods
EPPM, Singapore, 20-21 Sep 2011 Performance risk evaluation of long term infrastructure projects (PPP-BOT projects) using probabilistic Meghdad Attarzadeh 1 and David K H Chua 2 Abstract Estimation and
More informationPROJECT COST MANAGEMENT
PROJECT COST MANAGEMENT For the PMP Exam using PMBOK Guide 5 th Edition PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. 1 Contacts Name: Khaled El-Nakib, PMP, PMI-RMP
More informationTransactions Demand for Money
Transactions Demand for Money Money is the medium of exchange, and people hold money to make purchases. Economists speak of the transactions demand for money, as people demand money to make transactions.
More informationINSTITUTE OF MANAGEMENT, NIRMA UNIVERSITY MBA (FT)- I (Batch ) : Term III (End Term Exam)
INSTITUTE OF MANAGEMENT, NIRMA UNIVERSITY MBA (FT)- I (Batch 2015-2017) : Term III (End Term Exam) Course : Managerial Economics Maximum Marks: 100 Date: 06-08-2015 Duration: 1 Hour Close Book Exam Instructions:
More informationfeature Elements of a Typical Laboratory Budget
feature Elements of a Typical Laboratory Budget Donna H. MacMillan, BS, MT(ASCP), MBA Division of Laboratory Medicine, Massachusetts General Hospital, Boston, MA DOI: 10.1309/99F7NNJ09M3TGQHW An organization's
More informationFinancial Management Bachelors of Business (Specialized in Finance) Tutorial Questions Chapter 1: Introduction to Cost Accounting
Financial Management Bachelors of Business (Specialized in Finance) Tutorial Questions Chapter 1: Introduction to Cost Accounting 1 Practice Questions Question 1 Cost Accounting System is neither unnecessary
More informationPaper 8- Cost Accounting
Paper 8- Cost Accounting Dos, The Institute of Cost Accountants of India (Statutory Body under an Act of Parliament) Page 1 Paper 8- Cost Accounting Full Marks : 100 Time allowed: 3 hours Section A Question
More informationALL IN ONE MGT 402 MIDTERM PAPERS MORE THAN ( 10 )
ALL IN ONE MGT 402 MIDTERM PAPERS MORE THAN ( 10 ) MIDTERM EXAMINATION MGT402- Cost & Management Accounting Question No: 1 ( Marks: 1 ) - Please choose one D Corporation uses process costing to calculate
More informationFree of Cost ISBN : Appendix. CMA (CWA) Inter Gr. II (Solution upto Dec & Questions of June 2013 included)
Free of Cost ISBN : 978-93-5034-631-0 Appendix CMA (CWA) Inter Gr. II (Solution upto Dec. 2012 & Questions of June 2013 included) Paper - 8 : Cost and Management Accounting Chapter - 3 : Labour Accounting
More informationFINALTERM EXAMINATION Spring 2010 MGT402- Cost & Management Accounting (Session - 4) Solved by Mehreen Humayun vuzs Team.
FINALTERM EXAMINATION Spring 2010 MGT402- Cost & Management Accounting (Session - 4) Solved by Mehreen Humayun vuzs Team Time: 90 min Marks: 69 Question No: 1 ( Marks: 1 ) - Please choose one Cost of finished
More informationVALLIAMMAI ENGINEERING COLLEGE
VALLIAMMAI ENGINEERING COLLEGE SRM Nagar, Kattankulathur 603 203 DEPARTMENT OF CIVIL ENGINEERING QUESTION BANK VI SEMESTER CE6005 CONSTRUCTION PLANNING AND SCHEDULING Regulation 2013 Academic Year 2017
More information56:171 Operations Research Midterm Exam Solutions October 22, 1993
56:171 O.R. Midterm Exam Solutions page 1 56:171 Operations Research Midterm Exam Solutions October 22, 1993 (A.) /: Indicate by "+" ="true" or "o" ="false" : 1. A "dummy" activity in CPM has duration
More informationPROJECT MANAGEMENT CPM & PERT TECHNIQUES
PROJECT MANAGEMENT CPM & PERT TECHNIQUES FLOW OF PRESENTATION INTRODUCTION NETWORK PLANNING ESTIMATING TIME CPM PERT Project Management Project A project is an interrelated set of activities that has a
More information{List Sales (1 Trade Discount) Total Cost} (1 Tax Rate) = 0.06K
FINAL CA MAY 2018 ADVANCED MANAGEMENT ACCOUNTING Test Code F84 Branch: Date : 04.03.2018 (50 Marks) Note: All questions are compulsory. Question 1(4 Marks) (c) Selling Price to Yield 20% Return on Investment
More informationSOLUTIONS TO ASSIGNMENT PROBLEMS. Problem No. 1. Total Amount (Rs.)
6. OVERHEADS - 1 Primary Distribution of s: Item SOLUTIONS TO ASSIGNMENT PROBLEMS Total Amount (Rs.) Problem No. 1 Production Departments Service Departments X (Rs.) Y (Rs.) Z (Rs.) A (Rs.) B (Rs.) Indirect
More informationCHAPTER 5. Project Scheduling Models
CHAPTER 5 Project Scheduling Models 1 5.1 Introduction A project is a collection of tasks that must be completed in minimum time or at minimal cost. Objectives of Project Scheduling Completing the project
More informationAn Application of Mathematical Model to Time-cost Trade off Problem (Case Study)
Australian Journal of Basic and Applied Sciences, 5(7): 208-214, 2011 ISSN 1991-8178 An Application of Mathematical Model to Time-cost Trade off Problem (ase Study) 1 Amin Zeinalzadeh 1 Tabriz Branch,
More informationAfter complete studying this chapter, You should be able to
Chapter 10 Project Management Ch10: What Is Project Management? After complete studying this chapter, You should be able to Define key terms like Project, Project Management, Discuss the main characteristics
More informationThe Production Process and Costs. By Asst. Prof. Kessara Thanyalakpark, Ph.D.
The Production Process and Costs By Asst. Prof. Kessara Thanyalakpark, Ph.D. 1 Production Analysis Production Function Q = F(K,L) The maximum amount of output that can be produced with K units of capital
More informationA Linear Programming Approach for Optimum Project Scheduling Taking Into Account Overhead Expenses and Tardiness Penalty Function
A Linear Programming Approach for Optimum Project Scheduling Taking Into Account Overhead Expenses and Tardiness Penalty Function Mohammed Woyeso Geda, Industrial Engineering Department Ethiopian Institute
More informationAssignment Questions for M.Com. Part I (Sem. I) Oct./Nov. 2016
Assignment Questions for M.Com. Part I (Sem. I) Oct./Nov. 2016 Instructions for Assignment Submission Please note following instructions for submission of Assignments: 1. These assignments should be submitted
More informationBPC6C Cost and Management Accounting. Unit : I to V
BPC6C Cost and Management Accounting Unit : I to V UNIT -1 FUNDAMENTALS OF COST ACCOUNTING Nature and scope of Cost Accounting, Distinction between cost and financial accounting, Cost sheet, tenders Characteristics
More informationFull Monte. Looking at your project through rose-colored glasses? Let s get real.
Realistic plans for project success. Looking at your project through rose-colored glasses? Let s get real. Full Monte Cost and schedule risk analysis add-in for Microsoft Project that graphically displays
More informationProject Planning. Planning is an important step in project execution. Planning means:
Project Planning Planning is an important step in project execution. Planning means: Thinking through future project actions Seeking and mentally inspecting the long path from the start to the finish Achieving
More informationUNIT 11: STANDARD COSTING
UNIT 11: STANDARD COSTING Introduction One of the prime functions of management accounting is to facilitate managerial control and the important aspect of managerial control is cost control. The efficiency
More informationLINES AND SLOPES. Required concepts for the courses : Micro economic analysis, Managerial economy.
LINES AND SLOPES Summary 1. Elements of a line equation... 1 2. How to obtain a straight line equation... 2 3. Microeconomic applications... 3 3.1. Demand curve... 3 3.2. Elasticity problems... 7 4. Exercises...
More informationCONTRACTOR S CASH FLOW RISK QUANTIFICATION IN ROAD INFRASTRUCTURE PROJECT PORTFOLIO
Bulletin of the Transilvania University of Braşov Vol. 1 (59) Special Issue No. 1-217 Series I: Engineering Sciences CONTRACTOR S CASH FLOW RISK QUANTIFICATION IN ROAD INFRASTRUCTURE PROJECT PORTFOLIO
More informationCA Final Gr. II Paper - 5 (Solution of November ) Paper - 5 : Advance Management Accounting
Solved Scanner Appendix CA Final Gr. II Paper - 5 (Solution of November - 2015) Paper - 5 : Advance Management Accounting Chapter - 1 : Developments in the Business Environment 2015 - Nov [1] {C} (b) Costs
More informationMGT402 Short Notes Lecture 23 to 45 By
MGT402 Short Notes Lecture 23 to 45 By http://vustudents.ning.com Lec # 23 PROCESS COSTING SYSTEM (Opening balance of work in process) Two methods of cost allocation (1) The weighted average (or averaging)
More informationMINIMIZE TIME AND COST FOR SUCCESSFUL COMPLETION OF A LARGE SCALE PROJECT APPLYING PROJECT CRASHING METHOD
International Journal of Advanced Research and Review www.ijarr.in MINIMIZE TIME AND COST FOR SUCCESSFUL COMPLETION OF A LARGE SCALE PROJECT APPLYING PROJECT CRASHING METHOD Shifat Ahmed Lecturer, Southeast
More informationCrashing the Schedule An Algorithmic Approach with Caveats and Comments
ing the Schedule An Algorithmic Approach with Caveats and Comments Gilbert C. Brunnhoeffer, III PhD, P.E. and B. Gokhan Celik PhD LEED AP Roger Williams University Bristol, Rhode Island and Providence
More informationCost Reduction: Planning & Control. Impacting the Bottom Line
Cost Reduction: Planning & Control Break Even Point & Decision Tree Analysis (l.u. 4/2/11) Impacting the Bottom Line Calls for an understanding of: Variation Waste & Value Investments (time, capital, resources,
More informationInternational Journal of Advanced Engineering and Management Research Vol. 2 Issue 4, ISSN:
International Journal of Advanced Engineering and Management Research Vol. 2 Issue 4, 2017 http://ijaemr.com/ ISSN: 2456-3676 CPM AND PERT COMPARISON ANALYSIS IN PROJECT PLANNING ABSTRACT Talatu Muhammad
More information