1 Bonnie Beard Agriculture Center Dedication November 29, 2017 Design & Construction Managed Projects Monthly Report November 2017

2 Design & Construction Managed Projects Table of Contents Page Understanding the Monthly Report 3-6 Executive Summary 7 Program Cost Report by Schedule Phase 8 Program Cost Report by Project 9 PROJECT NAME PROJECT NUMBER PROJECT MANAGER Design Facilities Assessment 2018 DC Kamila Andrzejak 10 Close Out Bonnie Beard Agriculture Center DCXX-XXX Ashley Dixon 11 Dulles ES Classroom Enclosure-Phase II DCXX-XXX James Caylor 12 Report Date: 11/30/2017 Table of Contents

3 Design & Construction Managed Projects Understanding the Monthly Report Schedule Phase Description: Not Started- Design or construction activities have not begun Graphical representation of the total project budgets grouped by Phase Pre-Design- Activities between Board Approval of architectural services (if applicable) and actual design work Design-Programming and design through Construction Documents Bidding and Negotiations- Includes bidding, award and negotiation process with the contractor for construction work Construction-Construction work in progress Close Out Final inspection, submission and acceptance of required documents, and concluding payment Move In- Occupancy is permitted though minor activities or corrections continue - this phase includes project closeout Report Date: 11/30/2017 Understanding the Monthly Report 3

4 Design & Construction Managed Projects Understanding the Monthly Report Graphical representation of the /Costs status for the overall Program Column Headings: - budget funded through this report date -Approved budget adjustments by FBISD Current -Current project budget through the report period -Sum of all contracts, contract change orders, and purchase orders through the report period Additional to Complete-Additional costs anticipated on the project - plus additional commitments to complete Over/Under-Current minus the - it represents savings or overruns in the project Cost to Date-Sum of all contract invoices and general invoices entered through the report period % Expended-Cost to Date divided by Current Report Date: 11/30/2017 Understanding the Monthly Report 4

5 Design & Construction Managed Projects Understanding the Monthly Report Activity Description: Design -Duration from programming through Construction Documents Bidding and Negotiations-Duration of procurement activities through negotiations with the contractor for construction work Construction -Duration for construction Close Out-Duration for move in and closeout Activity Bars: Planned Bar- Baseline schedule for the project. The start and finish dates of the baseline are preset throughout the project and future schedule updates are measured against the baseline. Actual Bar- Actual performance by phase #: Number noted inside each bar indicates number of calendar days Dates: 1 st Column - Activity START date 2 nd Column - Activity END date Report Date: 11/30/2017 Understanding the Monthly Report 5

6 Design & Construction Managed Projects Understanding the Monthly Report Cost Description: Architect & Engineering/Professional Services-A/E Design Fees, A/E Design Reimbursables, Surveying, Geotechnical, Material Testing & Inspection, Commissioning, TAB (Test and Balancing), Consulting Other, Haz-mat Consulting Services Construction-Facility Construction in general and other associated costs such as Allowances and Construction Contingency Furniture, Fixtures & Equipment-Costs for furniture, fixtures and equipment Site Development-Permit & Site Fees related to construction Administrative and Other Project Costs- Construction related costs outside of main Construction Contract with the General Contractor. It includes: Temporary Buildings & Services, Printing/Misc., Bid Advertising, Hazmat/Abatement, etc. Project Contingency- to be used as necessary for unanticipated project costs following approval from FBISD Report Date: 11/30/2017 Understanding the Monthly Report 6

7 Design & Construction Managed Projects Executive Summary Current : $4,354,747 : $4,354,747 Program Status* As of November 30, 2017, the Fort Bend Independent School District Design and Construction Department (FBISD D&C) currently has three capital projects. The active projects current budgets total $4,354,747 with approximately 19% in Design and 81% in Close-Out. The active projects have expended $3,235,499 representing approximately 74% of the current budget. The composition of the portfolio by phase of work is represented in the following table and charts: Phase # Projects Current Design 1 $ 835,298 Close-Out 2 $ 3,519,449 TOTAL 3 $ 4,354,747 Report Date: 11/30/2017 Executive Summary 7

8 Fort Bend Independent School District Design and Construction Department Program Cost Report By Schedule Phase Value of Projects by Phase Current Close Out $3,519,449 Design $835,298 Close Out $3,519,449 Total: $4,354,747 Design $835,298 BUDGET COMMITMENTS A B C=A+B D E F G H=D+E+F+G I=C-H J COST K=J/C Description Current Approved Pending Commitment s Estimate To Complete Commitment s Over/Under Cost To Date % Expende d Design $835,298 $835,298 $835,298 $835,298 0% Close Out $3,519,449 $3,519,449 $3,407,091 $6 $112,353 $3,519,450 $3,235,499 92% Grand Totals: $4,354,747 $4,354,747 $4,242,389 $6 $112,353 $4,354,748 $3,235,499 74% Report Date: 11/30/17 Program Cost Report By Schedule Phase 8

9 Fort Bend Independent School District Design and Construction Department Program Cost Report By Project $25,000,000 $20,000,000 $15,000,000 $10,000,000 $5,000,000 Current Cost To date BUDGET COMMITMENTS COST A B C=A+B D E F G H=D+E+F+G I=C-H J K=J/C Project Name Current Commitment s Approved Pending Commitment s Estimate To Complete Commitment s Over/Under Cost To Date % Expended Bonnie Beard Agriculture Center $3,085,052 $3,085,052 $3,012,185 $26,630 $46,237 $3,085,052 $2,899,350 94% Dulles ES - Classroom Enclosure-Phase II $434,397 $434,397 $394,906 $(26,625) $66,116 $434,397 $336,150 77% Facilities Assessment Bond $835,298 $835,298 $835,298 $835,298 0% Grand Totals: $4,354,747 $4,354,747 $4,242,389 $6 $112,353 $4,354,748 $(0) $3,235, % Report Date: 11/30/2017 Program Cost Report By Project 9

10 FBISD Design and Construction Project Number : DC Project Manager : Kamila Andrzejak Architect/Engineer : PBK Architects, Inc. General Contractor : N/A Project Summary Facilities Assessment Bond SCHEDULE SUMMARY Design - Baseline: 9/18/2017 3/31/ Design - Actual: 9/18/ Bidding & Negotiations - Baseline: Bidding & Negotiations - Actual: Construction - Baseline: Construction - Actual: Move In - Baseline: Move In - Actual: Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 BUDGET COMMITMENTS COST A B C=A+B D E F G H=D+E+F+G I=C-H J K=J/C Description Current Approved Pending Estimate To Complete Over/Under Cost To Date % Expended Construction 0% Furniture, Fixtures & Equipment 0% Site Development 0% Administrative and Other Project Costs 0% Project Contingency 0% Architect & Engineering/ Professional Services $835,298 $835,298 $835,298 $835,298 0% Totals: $835,298 $835,298 $835,298 $835,298 0% SCOPE/COMMENTS PROJECT PHOTO BUDGET/COST STATUS SCOPE: This project includes the deficiency assessment of all 92 FBISD facilities for use in planning the 2018 Bond. The project also includes the development and updates of the Educational Specifications for elementary, middle, and high schools as well as the construction specifications to align with Board of Trustees ' Guiding Principles and stakeholder input. COMMENTS: Consultant has completed the assessment for 31 facilities in the East Zone and has begun the assessments for the West Zone. The Central Zone assessments will be forthcoming. $835K $835K A committee with staff, students, and community representatives met November 30th to further develop and update the elementary, middle, and high school Educational Specifications. A second committee meeting will be held on December 14th. Departmental meetings with the architect and FBISD staff are ongoing. K Current Cost To Date Report Date: 11/30/2017 Facilities Assessment Bond 10

11 FBISD Design and Construction Project Number : DCXX-XXX Project Manager : Ashley Dixon Architect/Engineer : PBK Architects General Contractor : Bass Construction Company, Inc. Project Summary Bonnie Beard Agriculture Center SCHEDULE SUMMARY Design - Baseline: 10/28/2015 2/29/ Design - Actual: 10/28/2015 5/12/ Bidding & Negotiations - Baseline: 3/1/2016 5/31/ Bidding & Negotiations - Actual: 5/13/2016 8/12/ Construction - Baseline: 6/1/2016 1/31/ Construction - Actual: 10/10/2016 9/12/ Close Out - Baseline: 2/1/2017 3/31/ Close Out - Actual: 9/12/ Oct-15 Oct-16 Oct-17 BUDGET COMMITMENTS COST A B C=A+B D E F G H=D+E+F+G I=C-H J K=J/C Description Current Approved Pending Estimate To Complete Over/Under Cost To Date % Expended Architect & Engineering/ Professional Services $134,615 $56,271 $190,886 $190,086 $800 $190,886 $152,253 80% Construction $2,879,052 ($226,192) $2,652,860 $2,623,795 $25,830 $3,235 $2,652,860 $2,548,794 96% Furniture, Fixtures & Equipment $100,000 $100,000 $57,001 $42,999 $100,000 $57,000 57% Site Development $22,018 $119,288 $141,306 $141,303 $3 $141,306 $141, % Administrative and Other Project Costs 0% Project Contingency $49,367 ($49,367) 0% Totals: $3,085,052 $3,085,052 $3,012,185 $26,630 $46,237 $3,085,052 $2,899,350 94% SCOPE/COMMENTS PROJECT PHOTO BUDGET/COST STATUS SCOPE: The scope of work for this project includes a pre-engineered metal building (8,521 square feet) including modular pens for both large and small animals, animal wash-off areas, and restrooms. COMMENTS: This project is in the close-out phase. The center's dedication was held on Wednesday, November 29th. $3,085K $3,039K $2,899K Current Cost To Date Report Date: 11/30/2017 Bonnie Beard Agriculture Center 11

12 FBISD Design and Construction Project Summary Project Number : DCXX-XXX Dulles ES - Classroom Enclosure-Phase II Project Manager : James Caylor Architect/Engineer : Archi Technics/3, Inc. General Contractor : Tandus & Firetron SCHEDULE SUMMARY Design - Baseline: 12/5/2016 1/30/ Design - Actual: 12/5/2016 1/30/2017 Bidding & Negotiations - Baseline: 1/31/2017 2/13/ Bidding & Negotiations - Actual: 1/31/2017 2/13/ Construction - Baseline: 2/13/2017 Construction - Actual: 3/3/2017 8/15/2017 Close Out - Baseline: 8/6/2017 8/10/2017 Close Out - Actual: 173 8/5/2017 8/16/ Dec-16 Feb-17 Apr-17 Jun-17 Aug-17 BUDGET Description Oct-17 COMMITMENTS COST A B C=A+B D E F G H=D+E+F+G I=C-H J K=J/C Current Approved Pending Estimate To Complete Over/Under Cost To Date % Expended $434,397 $434,397 $394,906 $(26,625) $66,116 Furniture, Fixtures & Equipment Site Development Administrative and Other Project Costs Project Contingency $434,397 $434,397 $394,906 $(26,625) Architect & Engineering/ Professional Services Construction Totals: Dec-17 SCOPE/COMMENTS 0% $434,397 $336,150 77% 0% 0% 0% 0% $66,116 $434,397 $336,150 PROJECT PHOTO 77% BUDGET/COST STATUS SCOPE: Phase II of this project includes flooring replacement and an upgrade to the fire suppression system which is scheduled for the Summer of COMMENTS: Close-out documents have been received and are being reviewed by FBISD staff. $434K $368K Current Report Date: 11/30/2017 Dulles ES - Classroom Enclosure-Phase II $336K Cost To Date 12

Monthly Report. April 2017

Monthly Report. April 2017 Monthly Report April 2017 El Paso ISD Bond Program Program Manager: Jacobs Table of Contents Report Date: 04/30/2017 Understanding the Monthly Report... 3 Executive Summary. 7 Program Report by Phase...

More information

Bond Oversight Committee Bond program. January 7, 2016

Bond Oversight Committee Bond program. January 7, 2016 Bond Oversight Committee 2014 Bond program January 7, 2016 Bond Oversight Committee 1 AGENDA Welcome, introductions, reminder of scope/role of BOC Stewart Jacobson, Chair Program Management: Max Cleaver

More information

REQUEST FOR PROPOSAL

REQUEST FOR PROPOSAL REQUEST FOR PROPOSAL For Construction Manager as Constructor for Tri-North Middle School Response Due: April 2, 2018, 1:00 pm MCCSC Service Building 560 E. Miller Drive Bloomington, IN 47401. REQUEST FOR

More information

SmallBizU WORKSHEET 1: REQUIRED START-UP FUNDS. Online elearning Classroom. Item Required Amount ($) Fixed Assets. 1 -Buildings $ 2 -Land $

SmallBizU WORKSHEET 1: REQUIRED START-UP FUNDS. Online elearning Classroom. Item Required Amount ($) Fixed Assets. 1 -Buildings $ 2 -Land $ WORKSHEET 1: REQUIRED START-UP FUNDS Item Required Amount () Fixed Assets 1 -Buildings 2 -Land 3 -Initial Inventory 4 -Equipment 5 -Furniture and Fixtures 6 -Vehicles 7 Total Fixed Assets Working Capital

More information

Review of Registered Charites Compliance Rates with Annual Reporting Requirements 2016

Review of Registered Charites Compliance Rates with Annual Reporting Requirements 2016 Review of Registered Charites Compliance Rates with Annual Reporting Requirements 2016 October 2017 The Charities Regulator, in accordance with the provisions of section 14 of the Charities Act 2009, carried

More information

Sales and Use Tax Collection Report December 2018 Issued January 10, 2019

Sales and Use Tax Collection Report December 2018 Issued January 10, 2019 Financial Services Sales Tax Division 215 N. Mason Street 2 nd Floor PO Box 580Fort Collins, CO 80522-0580 970.221.6780 970.221.6782 - fax fcgov.com Sales and Use Tax Collection Report December 2018 Issued

More information

Common stock prices 1. New York Stock Exchange indexes (Dec. 31,1965=50)2. Transportation. Utility 3. Finance

Common stock prices 1. New York Stock Exchange indexes (Dec. 31,1965=50)2. Transportation. Utility 3. Finance Digitized for FRASER http://fraser.stlouisfed.org/ Federal Reserve Bank of St. Louis 000 97 98 99 I90 9 9 9 9 9 9 97 98 99 970 97 97 ""..".'..'.."... 97 97 97 97 977 978 979 980 98 98 98 98 98 98 987 988

More information

FOR RELEASE: MONDAY, MARCH 21 AT 4 PM

FOR RELEASE: MONDAY, MARCH 21 AT 4 PM Interviews with 1,012 adult Americans conducted by telephone by Opinion Research Corporation on March 18-20, 2011. The margin of sampling error for results based on the total sample is plus or minus 3

More information

REQUEST FOR QUALIFICATIONS CONSTRUCTION MANAGER SERVICES DICKINSON PUBLIC SCHOOL DISTRICT NO. 1 DICKINSON, NORTH DAKOTA

REQUEST FOR QUALIFICATIONS CONSTRUCTION MANAGER SERVICES DICKINSON PUBLIC SCHOOL DISTRICT NO. 1 DICKINSON, NORTH DAKOTA REQUEST FOR QUALIFICATIONS CONSTRUCTION MANAGER SERVICES NEW MIDDLE SCHOOL 212,000 SQUARE FEET DICKINSON PUBLIC SCHOOL DISTRICT NO. 1 DICKINSON, NORTH DAKOTA November 25, 2014 1. INTRODUCTION: Dickinson

More information

Unrestricted Cash / Board Designated Cash & Investments December 2014

Unrestricted Cash / Board Designated Cash & Investments December 2014 Unrestricted Cash / Board Designated Cash & Investments December 2014 25.0 20.0 21.0 20.8 18.9 19.9 15.0 10.0 11.5 12.8 11.6 9.1 10.4 9.8 11.1 10.2 9.8 17.0 16.8 15.4 14.7 14.2 14.1 13.6 13.0 12.0 10.2

More information

Business & Financial Services December 2017

Business & Financial Services December 2017 Business & Financial Services December 217 Completed Procurement Transactions by Month 2 4 175 15 125 1 75 5 2 1 Business Days to Complete 25 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 217 Procurement

More information

UNIVERSITY OF NORTHERN COLORADO: FINANCIAL REPORT 12/31/2010

UNIVERSITY OF NORTHERN COLORADO: FINANCIAL REPORT 12/31/2010 UNIVERSITY OF NORTHERN COLORADO: FINANCIAL REPORT 12/31/2010 OVERVIEW The following is a summary of the financial highlights contained in the second quarter report for fiscal year 2010-11: Cash and Accounts

More information

Planning and Construction Department 1130 Fifth Avenue, Chula Vista, CA (619) FAX (619)

Planning and Construction Department 1130 Fifth Avenue, Chula Vista, CA (619) FAX (619) Planning and Construction Department 1130 Fifth Avenue, Chula Vista, CA 91911 (619) 691-5553 FAX (619) 420-0339 Prop O Project Summary page 1 General for CBOC Meeting of January 20, 2016 1 2 date info

More information

Egg Entrepreneurship Records

Egg Entrepreneurship Records Egg Entrepreneurship Records Name 4-H Program Year PROJECT GOAL Setting goals and then checking progress on the attainment of those goals is an important part of 4-H. Complete the boxes 1-3 at the beginning

More information

THURGOOD MARSHALL MIDDLE SCHOOL LYNN, MA

THURGOOD MARSHALL MIDDLE SCHOOL LYNN, MA THURGOOD MARSHALL MIDDLE SCHOOL LYNN, MA Monthly Project Update Report SEPTEMBER 2012 FS/SD DD CD Bidding Construction Closeout THURGOOD MARSHALL MIDDLE SCHOOL SEPTEMBER 2012 01 TASKS COMPLETED DURING

More information

HUD NSP-1 Reporting Apr 2010 Grantee Report - New Mexico State Program

HUD NSP-1 Reporting Apr 2010 Grantee Report - New Mexico State Program HUD NSP-1 Reporting Apr 2010 Grantee Report - State Program State Program NSP-1 Grant Amount is $19,600,000 $9,355,381 (47.7%) has been committed $4,010,874 (20.5%) has been expended Grant Number HUD Region

More information

Los Angeles Community College District PROGRAM MANAGEMENT SERVICES. PMO Annual Update

Los Angeles Community College District PROGRAM MANAGEMENT SERVICES. PMO Annual Update Los Angeles Community College District PROGRAM MANAGEMENT SERVICES PMO Annual Update District Citizens Oversight Committee October 9, 2015 1 One Goal: Strong Program Finish ON TIME ON BUDGET NO LITIGATION

More information

Key IRS Interest Rates After PPA

Key IRS Interest Rates After PPA Key IRS Rates - After PPA - thru 2011 Page 1 of 10 Key IRS Interest Rates After PPA (updated upon release of figures in IRS Notice usually by the end of the first full business week of the month) Below

More information

DETROIT LAKES CITY COUNCIL SPECIAL MEETING AGENDA TUESDAY, June 19, 2018

DETROIT LAKES CITY COUNCIL SPECIAL MEETING AGENDA TUESDAY, June 19, 2018 DETROIT LAKES CITY COUNCIL SPECIAL MEETING AGENDA TUESDAY, June 19, 2018 The items on my desk as of Wednesday, June 13, 2018, to be presented for discussion and action at the Special Meeting of the City

More information

1.2 The purpose of the Finance Committee is to assist the Board in fulfilling its oversight responsibilities related to:

1.2 The purpose of the Finance Committee is to assist the Board in fulfilling its oversight responsibilities related to: Category: BOARD PROCESS Title: Terms of Reference for the Finance Committee Reference Number: AB-331 Last Approved: February 22, 2018 Last Reviewed: February 22, 2018 1. PURPOSE 1.1 Primary responsibility

More information

XML Publisher Balance Sheet Vision Operations (USA) Feb-02

XML Publisher Balance Sheet Vision Operations (USA) Feb-02 Page:1 Apr-01 May-01 Jun-01 Jul-01 ASSETS Current Assets Cash and Short Term Investments 15,862,304 51,998,607 9,198,226 Accounts Receivable - Net of Allowance 2,560,786

More information

Tooele County. Financial Recovery Plan 3rd Quarter 2014 Update

Tooele County. Financial Recovery Plan 3rd Quarter 2014 Update Tooele County Financial Recovery Plan 3rd Quarter 2014 Update Original Projection 14,000,000 Tooele County Cash 2009-2015 12,000,000 10,000,000 8,000,000 6,000,000 4,000,000 2,000,000 - Ahead of Projection

More information

Financial & Business Highlights For the Year Ended June 30, 2017

Financial & Business Highlights For the Year Ended June 30, 2017 Financial & Business Highlights For the Year Ended June, 17 17 16 15 14 13 12 Profit and Loss Account Operating Revenue 858 590 648 415 172 174 Investment gains net 5 162 909 825 322 516 Other 262 146

More information

Big Walnut Local School District

Big Walnut Local School District Big Walnut Local School District Monthly Financial Report for the month ended September 30, 2012 Prepared By: Felicia Drummey Treasurer BIG WALNUT LOCAL SCHOOL DISTRICT SUMMARY OF YEAR-TO-DATE FINANCIAL

More information

Spheria Australian Smaller Companies Fund

Spheria Australian Smaller Companies Fund 29-Jun-18 $ 2.7686 $ 2.7603 $ 2.7520 28-Jun-18 $ 2.7764 $ 2.7681 $ 2.7598 27-Jun-18 $ 2.7804 $ 2.7721 $ 2.7638 26-Jun-18 $ 2.7857 $ 2.7774 $ 2.7690 25-Jun-18 $ 2.7931 $ 2.7848 $ 2.7764 22-Jun-18 $ 2.7771

More information

Investit Software Inc. INVESTOR PRO CANADA 20 UNIT CONDOMINIUM DEVELOPMENT EXAMPLE

Investit Software Inc.  INVESTOR PRO CANADA 20 UNIT CONDOMINIUM DEVELOPMENT EXAMPLE INVESTOR PRO CANADA 20 UNIT CONDOMINIUM DEVELOPMENT EXAMPLE INTRODUCTION This example uses the Development Condominium template. This practice example consists of two Sections; 1. The input information

More information

THE B E A CH TO WN S O F P ALM B EA CH

THE B E A CH TO WN S O F P ALM B EA CH THE B E A CH TO WN S O F P ALM B EA CH C OU N T Y F LO R I D A August www.luxuryhomemarketing.com PALM BEACH TOWNS SINGLE-FAMILY HOMES LUXURY INVENTORY VS. SALES JULY Sales Luxury Benchmark Price : 7,

More information

ORANGE UNIFIED SCHOOL DISTRICT Measure S Bond Program September 2017 Monthly Progress Report

ORANGE UNIFIED SCHOOL DISTRICT Measure S Bond Program September 2017 Monthly Progress Report ORANGE UNIFIED SCHOOL DISTRICT Measure S Bond Program September 2017 Monthly Progress Report PERIOD COVERED: September 1 30, 2017 FISCAL YEAR FY 2017 2018 PROGRESS REPORT NO. PR 03 1718 003 PREPARED BY:

More information

Unrestricted Cash / Board Designated Cash & Investments December 2015

Unrestricted Cash / Board Designated Cash & Investments December 2015 Unrestricted Cash / Board Designated Cash & Investments December 2015 25.0 21.0 20.0 19.5 18.9 18.1 16.8 16.5 15.9 15.0 10.0 11.0 12.8 9.1 10.4 9.8 11.1 14.7 14.2 14.1 9.9 12.0 8.4 13.0 10.2 11.6 14.9

More information

Grossmont-Cuyamaca Community College District Project Labor Agreement Evaluation Plan

Grossmont-Cuyamaca Community College District Project Labor Agreement Evaluation Plan March 16, 2017 PROCEDURE MANUAL TABLE OF CONTENTS PLA EVALUATION PLAN PROCESS A. OVERVIEW... 2 Projects... 2 Controlling Laws and Regulations... 2 Roles and Responsibilities... 2 B. KEY PERFORMANCE INDICATORS

More information

ICE LIBOR Holiday Calendar 2019

ICE LIBOR Holiday Calendar 2019 ICE LIBOR Holiday Calendar Date Day Holiday GBP CHF JPY 01-Jan- Tuesday New Year's Day O O O O O 21-Jan- Monday Martin Luther King's Birthday () P No O/N P P P 18-Feb- Monday President's Day () P No O/N

More information

Campus Construction Program Report WLAC Monthly Facilities Committee Meeting February 22, 2016

Campus Construction Program Report WLAC Monthly Facilities Committee Meeting February 22, 2016 Campus Construction Program Report WLAC Monthly Facilities Committee Meeting February 22, 2016 1. Cost Update 2. Schedule Update 3. PreDesign Update 4. Design Update 5. Contractor Procurement Update February

More information

TERMS OF REFERENCE FOR THE INVESTMENT COMMITTEE

TERMS OF REFERENCE FOR THE INVESTMENT COMMITTEE I. PURPOSE The purpose of the Investment Committee (the Committee ) is to recommend to the Board the investment policy, including the asset mix policy and the appropriate benchmark for both ICBC and any

More information

Key IRS Interest Rates After PPA

Key IRS Interest Rates After PPA Key IRS Interest After PPA (updated upon release of figures in IRS Notice usually by the end of the first full business week of the month) Below are Tables I, II, and III showing official interest rates

More information

11 May Report.xls Office of Budget & Fiscal Planning

11 May Report.xls Office of Budget & Fiscal Planning Education and General Fund Actual Revenues and s by Month MTD YTD Change Revenue Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Per 14 Total over FY06 Enrollment Fees $ 8,211 $ 219 $ 41,952 ($ 818) $

More information

REGISTER OF IOWA STATE UNIVERSITY CAPITAL IMPROVEMENT BUSINESS TRANSACTIONS

REGISTER OF IOWA STATE UNIVERSITY CAPITAL IMPROVEMENT BUSINESS TRANSACTIONS OCTOBER 18-19, 2017 REGISTER OF IOWA STATE UNIVERSITY CAPITAL IMPROVEMENT BUSINESS TRANSACTIONS Actions Requested: Consider recommending to the Board approval of the: 1. Following actions for the Knoll

More information

Sacramento City College Strategic Planning System

Sacramento City College Strategic Planning System Sacramento City College Strategic Planning System Title: Plan Type: OPR: Collaborative Groups: Resource Management and Capital Outlay Master Plan 2018 Institutional VPA Resource Allocation Groups: Budget

More information

ANNUAL REPORT. In accordance with Government Code Section 66006, the District provides the following information for fiscal year :

ANNUAL REPORT. In accordance with Government Code Section 66006, the District provides the following information for fiscal year : THE COACHELLA VALLEY UNIFIED SCHOOL DISTRICT ANNUAL AND FIVE-YEAR REPORTABLE FEES REPORT FOR FISCAL YEAR 2009-2010, IN COMPLIANCE WITH GOVERNMENT CODE SECTIONS 66006 AND 66001 Government Code Sections

More information

Constructing a Cash Flow Forecast

Constructing a Cash Flow Forecast Constructing a Cash Flow Forecast Method and Worked Example A cash flow forecast shows the estimates of the timing and amounts of cash inflows and outflows over a period of time. The sections of a cash

More information

University of Colorado Capital Construction Project Status SUMMARY - May 2017 (accounting noted by campus)

University of Colorado Capital Construction Project Status SUMMARY - May 2017 (accounting noted by campus) of Colorado Capital Project Status SUMMARY - May (accounting noted by campus) Legend On-Track Risks Approved - Adjustments Needed Awaiting $ Start-Up Phase In Bidding Phase In Closeout Project Completed

More information

Status: Structural steel installation complete at primary building. Observatory construction underway. Central Plant modifications are complete.

Status: Structural steel installation complete at primary building. Observatory construction underway. Central Plant modifications are complete. Page 1 of 14 FACILITIES PLAN STATUS REPORT August 24, 2015 SADDLEBACK COLLEGE 1. SCIENCES BUILDING Project Budget: $52,234,000 $8,308,000 $67,358,000 State Match: $36,564,000 ($36,564,000) - Basic Aid

More information

Cost Estimation of a Manufacturing Company

Cost Estimation of a Manufacturing Company Cost Estimation of a Manufacturing Company Name: Business: Date: Economics of One Unit: Manufacturing Company (Only complete if you are making a product, such as a bracelet or beauty product) Economics

More information

Cash & Liquidity The chart below highlights CTA s cash position at December 2017 compared to December 2016.

Cash & Liquidity The chart below highlights CTA s cash position at December 2017 compared to December 2016. To: Chicago Transit Authority Board From: Jeremy Fine, Chief Financial Officer Re: Financial Results for December 2017 Date: February 14, 2018 I. Summary CTA s financial results are $4.7 million favorable

More information

Development of Economy and Financial Markets of Kazakhstan

Development of Economy and Financial Markets of Kazakhstan Development of Economy and Financial Markets of Kazakhstan National Bank of Kazakhstan Macroeconomic development GDP, real growth, % 116 112 18 14 1 113,5 11,7 216,7223,8226,5 19,8 19,8 19,3 19,619,7 199,

More information

Cash & Liquidity The chart below highlights CTA s cash position at March 2017 compared to March 2016.

Cash & Liquidity The chart below highlights CTA s cash position at March 2017 compared to March 2016. To: Chicago Transit Authority Board From: Jeremy Fine, Chief Financial Officer Re: Financial Results for March 2017 Date: May 10, 2017 I. Summary CTA s financial results are $0.6 million favorable to budget

More information

Cash & Liquidity The chart below highlights CTA s cash position at September 2017 compared to September 2016.

Cash & Liquidity The chart below highlights CTA s cash position at September 2017 compared to September 2016. To: Chicago Transit Authority Board From: Jeremy Fine, Chief Financial Officer Re: Financial Results for September 2017 Date: November 15, 2017 I. Summary CTA s financial results are $7.7 million favorable

More information

City of Justin NOVEMBER

City of Justin NOVEMBER City of Justin MONTHLY FINANCIAL REPORT NOVEMBER - 2018 1 Revenues: Sales tax revenue is up 14.5% from this time prior year and November s sales tax collections increased 2.4% from November 2017. The City

More information

WAKULLA COUNTY, FLORIDA CLERK OF COURT FY 2016 INDIRECT COST RATE PROPOSAL

WAKULLA COUNTY, FLORIDA CLERK OF COURT FY 2016 INDIRECT COST RATE PROPOSAL FY 2016 INDIRECT COST RATE PROPOSAL Based on Actual Costs for the Fiscal Year Ended September 30, 2014 Table of Contents TAB A TAB B TAB C TAB D TAB E TAB F TAB G TAB H TAB I TAB J TAB K TAB L CERTIFICATE

More information

FERC EL Settlement Agreement

FERC EL Settlement Agreement FERC EL05-121-009 Settlement Agreement Ray Fernandez Manager, Market Settlements Development Market Settlements Subcommittee June 14, 2018 Settlement Agreement Details Settlement Agreement Details FERC

More information

VALENCIA COLLEGE FINANCIAL SUMMARY FISCAL YEAR As of March 31, 2016

VALENCIA COLLEGE FINANCIAL SUMMARY FISCAL YEAR As of March 31, 2016 VALENCIA COLLEGE FINANCIAL SUMMARY FISCAL YEAR 2015-16 As of March 31, 2016 Budgeted Annual Collected % Collected Revenue Year To Date Of Annual Enrollment Based 94,185,539 94,205,294 100% State Funding

More information

Quarterly Statistical Digest

Quarterly Statistical Digest Quarterly Statistical Digest August Volume 27, No. 3 The Statistical Digest is a quarterly publication of the Central Bank of The Bahamas, prepared by the Research Department for issue in February, May,

More information

U.S. Natural Gas Storage Charts

U.S. Natural Gas Storage Charts U.S. Natural Gas Storage Charts BMO Capital Markets Commodity Products Group November 26, 214 Total U.S. Natural Gas in Storage 5, Total Stocks This Week 3432 4, 3, 2, 1, Reported On: November 26, 214

More information

Mitchell Electric Charitable Fund PO Box 409 Camilla, GA (229) or FAX:

Mitchell Electric Charitable Fund PO Box 409 Camilla, GA (229) or FAX: Mitchell Electric Charitable Fund PO Box 409 Camilla, GA 31730 (229) 336-5221 or 1-800-479-6034 FAX: 229-336-7088 For Office use only: Agency / Organization Application All attached sheets, including financial

More information

QUESTION 2. QUESTION 3 Which one of the following is most indicative of a flexible short-term financial policy?

QUESTION 2. QUESTION 3 Which one of the following is most indicative of a flexible short-term financial policy? QUESTION 1 Compute the cash cycle based on the following information: Average Collection Period = 47 Accounts Payable Period = 40 Average Age of Inventory = 55 QUESTION 2 Jan 41,700 July 39,182 Feb 18,921

More information

The year to date is less than budget and prior year by 15.4 million and 11.6 million, respectively.

The year to date is less than budget and prior year by 15.4 million and 11.6 million, respectively. To: Chicago Transit Authority Board From: Jeremy Fine, Chief Financial Officer Re: Financial Results for September 2016 Date: November 16, 2016 I. Summary CTA s financial results are $0.3 million unfavorable

More information

School Board of Brevard County, Florida Half-Cent Sales Surtax Round 6 Internal Audit Report Fiscal Year February 21, 2019

School Board of Brevard County, Florida Half-Cent Sales Surtax Round 6 Internal Audit Report Fiscal Year February 21, 2019 School Board of Brevard County, Florida Half-Cent Sales Surtax Round 6 Internal Audit Report Fiscal Year 2018-19 February 21, 2019 TABLE OF CONTENTS Transmittal Letter... 1 Executive Summary... 2 Overview...

More information

Construction Report Update

Construction Report Update NEW TRIER HIGH SCHOOL Construction Report Update September 2016 New Trier Winnetka Campus West Side Addition TABLE OF CONTENTS I. Neighbor Relations II. III. IV. Project Summary Schedule Progress Milestones

More information

Status of the Unemployment Trust Fund and Related Issues. Commission on Unemployment Compensation. Ellen Marie Hess, Commissioner.

Status of the Unemployment Trust Fund and Related Issues. Commission on Unemployment Compensation. Ellen Marie Hess, Commissioner. Status of the Unemployment Trust Fund and Related Issues Commission on Unemployment Compensation August 8, 2018 Ellen Marie Hess, Commissioner 2 Trust Fund Data Standard Forecast (Millions of Dollars)

More information

Original Revision Total Project Budget: $52,234,000 $ 8,308,000 $67,358,000 District Funding Commitment: $15,670,000 $51,688,000 $67,358,000

Original Revision Total Project Budget: $52,234,000 $ 8,308,000 $67,358,000 District Funding Commitment: $15,670,000 $51,688,000 $67,358,000 Page 1 of 20 FACILITIES PLAN STATUS REPORT June 27, 2016 CAPITAL IMPROVEMENT PLANNING The decision to design and construct capital improvement projects begins with the Education and Facilities Master Planning

More information

I. ACTION ITEM PRESENTATION

I. ACTION ITEM PRESENTATION M E M O R A N D U M TO: FROM: Members of the Administration and Finance Committee Robert M. Tata, Chair Larry R. Hill, Vice Chair Carlton F. Bennett (ex-officio) Lisa B. Smith (ex-officio) Yvonne T. Allmond

More information

Ch. 13 Practice Questions Solution

Ch. 13 Practice Questions Solution Buad 121 Ch. 13 Practice Questions Solution Exercise 13-9 (20 minutes) a. Mar. 10 Machinery... 60,000 Cash... 60,000 Purchased machinery for cash. b. Mar. 10 Machinery... Accounts Payable... 60,000 60,000

More information

Cash & Liquidity The chart below highlights CTA s cash position at January 2018 compared to January 2017.

Cash & Liquidity The chart below highlights CTA s cash position at January 2018 compared to January 2017. To: Chicago Transit Authority Board From: Jeremy Fine, Chief Financial Officer Re: Financial Results for January 2018 Date: March 14, 2018 I. Summary CTA s financial results are $1.7 million unfavorable

More information

Cash & Liquidity The chart below highlights CTA s cash position at June 2018 compared to June 2017.

Cash & Liquidity The chart below highlights CTA s cash position at June 2018 compared to June 2017. To: Chicago Transit Authority Board From: Jeremy Fine, Chief Financial Officer Re: Financial Results for June 2018 Date: August 15, 2018 I. Summary CTA s financial results are unfavorable to budget for

More information

Projections/Estimated - Unrestricted Cash / Board Designated Cash & Investments September 2017

Projections/Estimated - Unrestricted Cash / Board Designated Cash & Investments September 2017 Projections/Estimated - Unrestricted Cash / Board Designated Cash & Investments September 2017 25.0 20.0 17.1 16.9 15.0 10.0 11.7 11.0 9.1 10.1 9.7 7.7 7.0 6.8 15.1 14.8 11.5 13.1 13.8 9.9 11.4 12.2 8.4

More information

Use of State and District Construction Funds

Use of State and District Construction Funds 8 Use of State and District Construction Funds Through its long-range planning process, the district has met its facilities needs without issuing significant debt. To improve cost efficiency, however,

More information

EMPLOYER S MUNICIPAL INCOME TAX WITHHOLDING FORMS INSTRUCTIONS FOR FILING FORM LW-1

EMPLOYER S MUNICIPAL INCOME TAX WITHHOLDING FORMS INSTRUCTIONS FOR FILING FORM LW-1 CITY TAX DEPT 50 TOWN SQUARE P.O. BOX 155 LIMA, OHIO 45802 PHONE (419) 221-5245 FAX (419) 998-5527 (MONTHLY OR QUARTERLY STATEMENT) FORM LW-3 (ANNUAL RECONCILIATION) EMPLOYER S MUNICIPAL INCOME TAX WITHHOLDING

More information

Big Walnut Local School District

Big Walnut Local School District Big Walnut Local School District Monthly Financial Report for the month ended September 30, 2013 Prepared By: Felicia Drummey Treasurer BIG WALNUT LOCAL SCHOOL DISTRICT SUMMARY OF YEAR TO DATE FINANCIAL

More information

AB SICAV I. Report of income for UK tax purposes. Dear Investor,

AB SICAV I. Report of income for UK tax purposes. Dear Investor, AB SICAV I Report of income for UK tax purposes Dear Investor, This website comprises a report of income to investors who held investments in AB SICAV I as at 31 May 2017. The classes of shares listed

More information

Status: Structural steel installation complete at primary building. Observatory construction underway. Central Plant modifications are complete.

Status: Structural steel installation complete at primary building. Observatory construction underway. Central Plant modifications are complete. Page 1 of 11 FACILITIES PLAN STATUS REPORT June 22, 2015 SADDLEBACK COLLEGE 1. SCIENCES BUILDING Project Budget: $52,234,000 $8,308,000 $67,358,000 State Match: $36,564,000 ($36,564,000) - Basic Aid Allocation:

More information

DRAFT FOR PUBLIC COMMENT

DRAFT FOR PUBLIC COMMENT CITY OF IMPERIAL SUCCESSOR AGENCY FOR THE FORMER REDEVELOPMENT AGENCY DUE DILIGENCE REVIEW PURSUANT TO AB1484 LOW AND MODERATE INCOME HOUSING FUND TABLE OF CONTENTS INDEPENDENT ACCOUNTANTS REPORT 3 ATTACHMENT

More information

Dulles Corridor Metrorail Project

Dulles Corridor Metrorail Project Dulles Corridor Metrorail Project MONTHLY COST AND SCHEDULE UPDATE FOR PHASES 1 AND 2 AS OF NOVEMBER 30, 2014 JANUARY 2015 0 Phase 1 Cost Summary November Expenditures $ 1.6 Million Total Expenditures

More information

Projections/Estimated - Unrestricted Cash / Board Designated Cash & Investments March 2018

Projections/Estimated - Unrestricted Cash / Board Designated Cash & Investments March 2018 Projections/Estimated - Unrestricted Cash / Board Designated Cash & Investments March 2018 25.0 20.0 19.0 16.9 17.2 15.0 10.0 11.0 10.9 9.1 10.1 9.7 7.7 7.0 6.8 15.1 14.8 14.4 11.5 13.8 9.9 12.1 12.2 8.4

More information

(Internet version) Financial & Statistical Report November 2018

(Internet version) Financial & Statistical Report November 2018 (Internet version) Financial & Statistical Report November 2018 12/17/2018 Statement of Operations For the Period Ended November 30, 2018 (in millions) Current Month Year-to-Date Operating Revenue $ 31.4

More information

Construction of the #7 Line Subway Extension Project New York September 17, 2018

Construction of the #7 Line Subway Extension Project New York September 17, 2018 Construction of the #7 Line Subway Extension Project New York September 17, 2018 Saibal Basuroy, PMP Project Controls Director, Hill International Inc. Disclaimer This presentation is protected by US and

More information

LOAN MARKET DATA AND ANALYTICS BY THOMSON REUTERS LPC

LOAN MARKET DATA AND ANALYTICS BY THOMSON REUTERS LPC LOAN MARKET DATA AND ANALYTICS BY THOMSON REUTERS LPC GLOBAL LOAN MARKET DATA AND ANALYTICS BY THOMSON REUTERS LPC Secondary Market Bid Levels: Europe Slide 2 European CLO New Issue Volume Monthly Slide

More information

BOARD OF TRUSTEES YEARLY CALENDAR

BOARD OF TRUSTEES YEARLY CALENDAR BOARD OF TRUSTEES YEARLY CALENDAR 2017-2018 July Wednesday July 1 July 10 Beginning of Fiscal Year Review handbooks Supt Formative Evaluation Set date for Goal Setting Session Annual adoption - Student

More information

MONTHLY REPORT.PDF

MONTHLY REPORT.PDF 1. 11-21-13 School Building Committee Meeting Minutes Documents: 11-21-13 SBC MINUTES.PDF 2. November 2013 Monthly Report Documents: 11-2013 MONTHLY REPORT.PDF Longmeadow High School Longmeadow, MA Meeting

More information

Board of Directors October 2018 and YTD Financial Report

Board of Directors October 2018 and YTD Financial Report Board of Directors October 2018 and YTD Financial Report Consolidated Financial Results Operating Margin October ($30,262) $129,301 ($159,563) Year-to-date $292,283 $931,358 ($639,076) Excess of Revenue

More information

MEDICAID FEDERAL SHARE OF MATCHING FUNDS

MEDICAID FEDERAL SHARE OF MATCHING FUNDS MEDICAID FEDERAL SHARE OF MATCHING FUNDS revised by EDR based on FFIS Estimated for FFY 2019 August 3, 2017 Effective State Budget Year State adopted February 2017 State State FY real Difference in state

More information

WESTWOOD LUTHERAN CHURCH Summary Financial Statement YEAR TO DATE - February 28, Over(Under) Budget WECC Fund Actual Budget

WESTWOOD LUTHERAN CHURCH Summary Financial Statement YEAR TO DATE - February 28, Over(Under) Budget WECC Fund Actual Budget WESTWOOD LUTHERAN CHURCH Summary Financial Statement YEAR TO DATE - February 28, 2018 General Fund Actual A B C D E F WECC Fund Actual Revenue Revenue - Faith Giving 1 $ 213 $ 234 $ (22) - Tuition $ 226

More information

2016 PUBLIC HEALTH & SAFETY BOND Quarterly Update. Full Health Commission October 2, 2018

2016 PUBLIC HEALTH & SAFETY BOND Quarterly Update. Full Health Commission October 2, 2018 2016 PUBLIC HEALTH & SAFETY BOND Quarterly Update Full Health Commission October 2, 2018 Topics & Presenters Bond Overview Mark Primeau Budget/Bond Sales Mark Primeau Accomplishments since September Health

More information

Planning and Control for the Non-Financial Manager

Planning and Control for the Non-Financial Manager Planning and Control for the NonFinancial Manager By John M. Burson The managing principal of a design firm is often an architect or engineer who is a nonfinancial manager not trained in accounting. This

More information

General Fund Revenue

General Fund Revenue Millions Percent of Kathy Steinert, Director of Fiscal Services Phone: 541.923.8927 145 SE Salmon Ave Redmond, OR 97756 kathy.steinert@redmond.k12.or.us Date: May 23, 2014 To: Redmond School District Board

More information

Friday 23 May 2014 Afternoon

Friday 23 May 2014 Afternoon Friday 23 May 2014 Afternoon GCSE ECONOMICS A592/01 How the Economy Works *1095673855* Candidates answer on the Question Paper. OCR supplied materials: None Other materials required: Calculators may be

More information

(Internet version) Financial & Statistical Report September 2017

(Internet version) Financial & Statistical Report September 2017 (Internet version) Financial & Statistical Report September 2017 10/23/2017 Statement of Operations For the Period Ended September 30, 2017 (in millions) Current Month Year-to-Date Operating Revenue &

More information

(Internet version) Financial & Statistical Report December 2017

(Internet version) Financial & Statistical Report December 2017 (Internet version) Financial & Statistical Report December 2017 01/22/2018 Statement of Operations For the Period Ended December 31, 2017 (in millions) Current Month Year-to-Date Operating Revenue & Patronage

More information

(Internet version) Financial & Statistical Report December 2016

(Internet version) Financial & Statistical Report December 2016 (Internet version) Financial & Statistical Report December 2016 1/23/2017 Statement of Operations For the Period Ended December 31, 2016 (in millions) Current Month Year-to-Date Operating Revenue & Patronage

More information

QUARTERLY FINANCIAL REPORT March 31, 2018

QUARTERLY FINANCIAL REPORT March 31, 2018 California Independent System Operator QUARTERLY FINANCIAL REPORT March 31, 2018 250 Outcropping Way Folsom, CA 95630 (916) 351-4000 CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION QUARTERLY FINANCIAL

More information

Beginning Date: January 2016 End Date: June Managers in Zephyr: Benchmark: Morningstar Short-Term Bond

Beginning Date: January 2016 End Date: June Managers in Zephyr: Benchmark: Morningstar Short-Term Bond Beginning Date: January 2016 End Date: June 2018 Managers in Zephyr: Benchmark: Manager Performance January 2016 - June 2018 (Single Computation) 11200 11000 10800 10600 10400 10200 10000 9800 Dec 2015

More information

FOR RELEASE: WEDNESDAY, NOVEMBER 17 AT 11:30 AM

FOR RELEASE: WEDNESDAY, NOVEMBER 17 AT 11:30 AM Interviews with 1,014 adult Americans conducted by telephone by Opinion Research Corporation on November 11-14, 2010. The margin of sampling error for results based on the total sample is plus or minus

More information

Capital Project Delivery Handbook. Facilities Planning & Construction

Capital Project Delivery Handbook. Facilities Planning & Construction Capital Project Delivery Handbook Facilities Planning & Construction 1 FACILITIES PLANNING & CONSTRUCTION 3/8/09 2 FACILITIES PLANNING & CONSTRUCTION 1. WELCOME TO FACILITIES PLANNING & CONSTRUCTION...

More information

Project Connect. June 22, 2011

Project Connect. June 22, 2011 Project Connect June 22, 2011 Introduction Meeting Minutes Approval Project Status Report IV&V Update By Ernst & Young Other Business Public Comments Review of Actions from Meeting Schedule Next Meeting

More information

CITY OF RICHMOND MONTHLY FINANCE REPORT AS OF APRIL 30, 2017

CITY OF RICHMOND MONTHLY FINANCE REPORT AS OF APRIL 30, 2017 CITY OF RICHMOND MONTHLY FINANCE REPORT AS OF APRIL 30, 2017 CITY OF RICHMOND DEPARTMENT OF FINANCE TABLE OF CONTENTS Letter of Transmittal I General Fund - Budgetary Comparison Schedule - Revenues 1

More information

PRESS RELEASE. Securities issued by Hungarian residents and breakdown by holding sectors. January 2019

PRESS RELEASE. Securities issued by Hungarian residents and breakdown by holding sectors. January 2019 7 March 2019 PRESS RELEASE Securities issued by Hungarian residents and breakdown by holding sectors January 2019 According to securities statistics, the amount outstanding of equity securities and debt

More information

FINANCIAL MANAGEMENT STRATEGY REPORT ON OUTCOMES FOR THE YEAR ENDED MARCH 31, 2016

FINANCIAL MANAGEMENT STRATEGY REPORT ON OUTCOMES FOR THE YEAR ENDED MARCH 31, 2016 FINANCIAL MANAGEMENT STRATEGY REPORT ON OUTCOMES FOR THE YEAR ENDED MARCH 31, 2016 Manitoba Finance General Inquiries: Room 109, Legislative Building Winnipeg, Manitoba R3C 0V8 Phone: 204-945-5343 Fax:

More information

Cash & Liquidity The chart below highlights CTA s cash position at August 2018 compared to August 2017.

Cash & Liquidity The chart below highlights CTA s cash position at August 2018 compared to August 2017. To: Chicago Transit Authority Board From: Jeremy Fine, Chief Financial Officer Re: Financial Results for August 2018 Date: October 10, 2018 I. Summary CTA s financial results are favorable to budget for

More information

QUARTERLY FINANCIAL REPORT June 30, 2017

QUARTERLY FINANCIAL REPORT June 30, 2017 California Independent System Operator QUARTERLY FINANCIAL REPORT June 30, 2017 250 Outcropping Way Folsom, CA 95630 (916) 351-4000 CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION QUARTERLY FINANCIAL

More information

City of Richmond Monthly Financial Report DECEMBER 2018

City of Richmond Monthly Financial Report DECEMBER 2018 City of Richmond Monthly Financial Report DECEMBER 2018 Table of Contents Letter of Transmittal... 3 General Fund Revenues... 5 General Fund Expenditures... 6 General Fund Encumbrance Report... 7 Operating

More information

Welcome Colome Consolidated School Public Meeting. January 17, 2019 January 21, 2019

Welcome Colome Consolidated School Public Meeting. January 17, 2019 January 21, 2019 Welcome School Public Meeting January 17, 2019 January 21, 2019 How Did We Get Here? August 2017 started talking to Architects and Construction Managers We retained an architectural firm to design a Conceptual

More information

Beginning Date: January 2016 End Date: September Managers in Zephyr: Benchmark: Morningstar Short-Term Bond

Beginning Date: January 2016 End Date: September Managers in Zephyr: Benchmark: Morningstar Short-Term Bond Beginning Date: January 2016 End Date: September 2018 Managers in Zephyr: Benchmark: Manager Performance January 2016 - September 2018 (Single Computation) 11400 - Yorktown Funds 11200 11000 10800 10600

More information