Campus Construction Program Report WLAC Monthly Facilities Committee Meeting February 22, 2016

Size: px
Start display at page:

Download "Campus Construction Program Report WLAC Monthly Facilities Committee Meeting February 22, 2016"

Transcription

1 Campus Construction Program Report WLAC Monthly Facilities Committee Meeting February 22, Cost Update 2. Schedule Update 3. PreDesign Update 4. Design Update 5. Contractor Procurement Update February 22, 2016 Facilities Committee Meeting Handout Page 1

2 Cost Update BUNDLE ACTIVE S WLAC - Update for the Facilities Committee Updated 2/16/ Data as of 2/1/2016 November 2015 Baseline Budget revised Current Budget (BUD) Expended Remaining (BUD - Expended) Estimate At Completion (EAC) Variance (BUD - EAC) NOTES 2 Campus Entry Signage $ 706, $ 706, $ 672, $ 33, $ 680, $ 25, Design Bid Build Central Plant Phase 2 $ 1,729, $ 1,729, $ 333, $ 1,396, $ 1,979, $ (250,078.00) 10 Projects * Physical Education & Dance RENOVATION $ 418, $ 418, $ 42, $ 375, $ 418, $ Performing Arts Amphitheater $ 842, $ 842, $ 87, $ 754, $ 897, $ (54,659.40) 13 *** Technology Learning Center 2 $ 26,695, $ 26,101, $ 707, $ 25,394, $ 26,378, $ (277,084.64) 14 Watson Center 2 $ 9,853, $ 9,853, $ 783, $ 9,070, $ 9,831, $ 22, JTrans/Access Imprv Remaining Priority 1 & 2 $ 1,728, $ 1,735, $ 311, $ 1,423, $ 1,735, $ 16 **** Master Planning Environmental Impact Report (Dismantle Sound Walls) $ 2,679, $ 2,679, $ 2,385, $ 293, $ 2,679, $ *Physical Education & Dance NEW $ 340, $ 340, $ 340, $ $ 340, $ 17 Sci/Math Building Renovation for Allied Health $ 62, $ 62, $ 62, $ $ 62, $ 18 Science Center Renovation $ 48, $ 48, $ 48, $ $ 48, $ 19 Demo Temp & Obsolete Facilities Building B1 $ 4, $ 4, $ 4, $ $ 4, $ Deferred 20 Renovation OmniAcoustical Perf Lab $ 38, $ 38, $ 38, $ $ 38, $ 21 Heldman Learning Resource Center Renovation Phase 2 $ 170, $ 170, $ 170, $ $ 170, $ 22 CE RENOVATION (Unfunded) $ 1,430, $ 1,430, $ 1,427, $ 3, $ 1,430, $ 23 DEMOLITION BLDG A9 (Unfunded) $ $ $ $ $ $ 40J Active Projects Above CAMPUS Active Projects Above TOTAL Active Projects: Campus + 40J 40J Completed & Cancelled Projects Total Campus Deferred & Unfunded CAMPUS Completed & Cancelled / Master Planning / Project Support TOTAL Completed / Cancelled / Master Planning / Support / Deferred Total 40J Active Completed & Cancelled Projects $ 17,265, $ 13,352, $ 602, $ 12,749, $ 13,352, $ 0.26 $ 46,350, $ 45,755, $ 5,440, $ 40,314, $ 46,289, $ (533,512.69) $ 63,615, $ 59,107, $ 6,043, $ 53,064, $ 59,641, $ (533,512.43) $ 2,109, $ 2,102, $ 2,061, $ 41, $ 2,102, $ 0.01 $ 2,095, $ 2,095, $ 2,092, $ 3, $ 2,095, $ $ 348,979, $ 348,979, $ 346,549, $ 2,430, $ 348,445, $ 533, $ 353,184, $ 353,177, $ 350,702, $ 2,474, $ 352,644, $ 533, $ 19,374, $ 15,454, $ 2,663, $ 12,791, $ 15,454, $ 0.27 * The PE Dance Renovation will be completed and the New Building deferred therefore the Project is shown in both places. Diebold LLB 4&5 **40JPhysical Security and Hardware West 4,673, Safety & Security Pkg $ 754, $ 21, $ 732, $ 754, $ 0.13 ** The Fire Alarm and Security Upgrade projects are being combined into the 40J Physical Security and 6 Plant Facilities Center (FMO) $ 3,424, $ 3,424, $ 427, $ 2,996, $ 3,424, $ Hardware Project and supplemental funding is going to McCARTHY DB be added from 40J-IT. 7 40J Storm Water Project Phase 2 Pave Lot 7 $ 754, $ 754, $ 21, $ 732, $ 754, $ DB 40J Energy Efficiency Project $ 4,715, $ 4,715, $ 50, $ 4,664, $ 4,715, $ 9 Balfour Beatty 40JTrans/Access Imprv ATALot 2 Bridge B4/5 Elev $ 2,189, $ 2,189, $ 111, $ 2,077, $ 2,189, $ 11 NEW/RENOVATION 40JTrans/Access Imprv Lot 5 Tower & AV Ramp $ 3,204, $ 3,204, $ 84, $ 3,119, $ 3,204, $ *** Technology Learning Center 2 has been reduced by $307, as the anticipated insurance refund will go toward the Sinanian Claim. The negative variance is a pending budget transfer. **** On previous versions of the SEP this project was reported at the financial ID level. On this version we are reporting to the Sub-Project level as directed. Total CAMPUS Active/Completed & Cancelled/Master Plng/Project Support/Deferred TOTAL Active + Completed & Cancelled 40J + CAMPUS $ 397,425, $ 396,830, $ 354,082, $ 42,748, $ 396,830, $ 0.40 $ 416,799, $ 412,285, $ 356,746, $ 55,539, $ 412,285, $ 0.67 February 22, 2016 Facilities Committee Meeting Handout Page 2

3 BUNDLE ACTIVE S First Ad or Release of RFP/RFQ Schedule Update WLAC - Update for the Facilities Committee Updated 2/16/ Data as of 2/1/2016 P6 data date 2/1/2016 Construction Start 2 Campus Entry Signage 1May15 4Aug15 15Sep15 Close Out Substantial Completion F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # Design Bid Build Central Plant Phase 2 14Apr16 3Aug16 7Nov16 A A A A A A B B B 10 Projects Physical Education & Dance RENOVATION 1Feb16 11May16 21Jun16 A A A B B 12 Performing Arts Amphitheater 13Apr16 13Jun16 19Oct16 A A A A B B B B B 4&5 Diebold LLB Safety & Security Pkg 40JPhysical Security and Hardware West 3Mar15 4Apr16 19Sep16 A A B B B B B B 6 Plant Facilities Center (FMO) 1Jun11 22Jun16 1Mar17 A A A A A B B B B B B B B McCARTHY DB 7 40J Storm Water Project Phase 2 Pave Lot 7 3Dec15 4Dec16 2Feb17 A A A A A A A A A A B B 8 DB 40J Energy Efficiency Project 14Mar16 5Oct17 5Sep18 A A A A A A A A A A A A A A A A A A A A B B B B B B B B B B B 9 Balfour Beatty 40JTrans/Access ImprvATALot 2 Bridge B4/5 Elev 22May15 20Apr17 26Sep17 A A A A A A A A A A A A A A A B B B B B 11 NEW/RENOVATION 40JTrans/Access Imprv Lot 5 Tower & AV Ramp 22May15 11Oct17 15Mar18 A A A A A A A A A A A A A A A A A A A A B B B B B 13 Technology Learning Center 2 9Feb15 7Nov17 10Apr19 A A A A A A A A A A A A A A A A A A A A A B B B B B B B B B B B B B B B B B 14 Watson Center 2 9Feb15 15Mar17 17Jan18 A A A A A A A A A A A A A B B B B B B B B B B B Campus Improvments 15 Package 40JTrans/Access Imprv Remaining Priority 1 & 2 9Feb15 1Feb17 8May18 A A A A A A A A A A A A B B B B B B B B B B B B B B B 16 Master Planning Environmental Impact Report (Dismantle Sound Walls) 9Feb15 12Sep18 13Nov18 C C C C C C C C C C C C C C C C C C C C A A A A A A A A A A A B B Preconstruction Construction F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A No. of Projects in Construction Notes: Campus Improvements Lower fire Service Road and 40JTrans/Access ImprvSignage are complete and have been removed from this list. February 22, 2016 Facilities Committee Meeting Handout Page 3

4 Pre-Design Update Storm Water Project Phase 2 Pave Lot 7 The PMO legal department has determined that this can be added to the McCarthy Plant Facilities contract. A proposal is in process. Energy Efficiency Project This project will be procured as a design-build contract. Programming is in process. February 22, 2016 Facilities Committee Meeting Handout Page 4

5 Design Update Plant Facilities Center The Design-Builder has submitted the package to DSA. 40J-Physical Security and Hardware-West Design in process. 100% CDs due 2/26/2016. Technology Learning Center 2 TSK Architects developing the Schematic Design Drawings. Watson Center 2 TSK Architects have completed the Design Development Drawings. Comments provided by Campus. Final DDs due 3/1/2016. February 22, 2016 Facilities Committee Meeting Handout Page 5

6 Design Update West - Trans and Accessibility Improvements - Remaining Priority 1 & 2 Items TSK Architects have completed the Design Development Drawings. User group comments provided. West - Trans and Accessibility Improvements - ATA-Lot 2 Bridge TSK Architects have completed the Schematic Design Drawings. The B4/5 Elevator has been deferred to accommodate the additional DSA requirements. West - Trans and Accessibility Improv.- Lot 5 Elevator & Albert Vera Ramp TSK Architects developing the Schematic Design Drawings. February 22, 2016 Facilities Committee Meeting Handout Page 6

7 Contractor Procurement Update Campus Improvements Package Formerly known as the Lease-Lease- Back package, is being proposed by PMO Legal to be converted into a Design-Build procurement. Review of the Design-Build price proposal is underway. Central Plant Phase 2 All documents have been submitted to the PMO for contractor procurement. Performing Arts Amphitheater (Slope Stabilization) All documents have been submitted to the PMO for contractor procurement. Physical Education & Dance Renovation All documents have been submitted to the PMO for contractor procurement. February 22, 2016 Facilities Committee Meeting Handout Page 7

Los Angeles Community College District PROGRAM MANAGEMENT SERVICES. PMO Annual Update

Los Angeles Community College District PROGRAM MANAGEMENT SERVICES. PMO Annual Update Los Angeles Community College District PROGRAM MANAGEMENT SERVICES PMO Annual Update District Citizens Oversight Committee October 9, 2015 1 One Goal: Strong Program Finish ON TIME ON BUDGET NO LITIGATION

More information

Agenda (Items may be taken out of order) D. Active Construction Project Status Report (for receive and file only)

Agenda (Items may be taken out of order) D. Active Construction Project Status Report (for receive and file only) I. ROLL CALL LOS ANGELES COMMUNITY COLLEGE DISTRICT BOARD OF TRUSTEES FACILITIES MASTER PLANNING & OVERSIGHT COMMITTEE Educational Services Center Board Room 770 Wilshire Boulevard Los Angeles, CA 90017

More information

ORANGE UNIFIED SCHOOL DISTRICT Measure S Bond Program September 2017 Monthly Progress Report

ORANGE UNIFIED SCHOOL DISTRICT Measure S Bond Program September 2017 Monthly Progress Report ORANGE UNIFIED SCHOOL DISTRICT Measure S Bond Program September 2017 Monthly Progress Report PERIOD COVERED: September 1 30, 2017 FISCAL YEAR FY 2017 2018 PROGRESS REPORT NO. PR 03 1718 003 PREPARED BY:

More information

Business & Financial Services December 2017

Business & Financial Services December 2017 Business & Financial Services December 217 Completed Procurement Transactions by Month 2 4 175 15 125 1 75 5 2 1 Business Days to Complete 25 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 217 Procurement

More information

XML Publisher Balance Sheet Vision Operations (USA) Feb-02

XML Publisher Balance Sheet Vision Operations (USA) Feb-02 Page:1 Apr-01 May-01 Jun-01 Jul-01 ASSETS Current Assets Cash and Short Term Investments 15,862,304 51,998,607 9,198,226 Accounts Receivable - Net of Allowance 2,560,786

More information

VALENCIA COLLEGE FINANCIAL SUMMARY FISCAL YEAR As of March 31, 2016

VALENCIA COLLEGE FINANCIAL SUMMARY FISCAL YEAR As of March 31, 2016 VALENCIA COLLEGE FINANCIAL SUMMARY FISCAL YEAR 2015-16 As of March 31, 2016 Budgeted Annual Collected % Collected Revenue Year To Date Of Annual Enrollment Based 94,185,539 94,205,294 100% State Funding

More information

Spheria Australian Smaller Companies Fund

Spheria Australian Smaller Companies Fund 29-Jun-18 $ 2.7686 $ 2.7603 $ 2.7520 28-Jun-18 $ 2.7764 $ 2.7681 $ 2.7598 27-Jun-18 $ 2.7804 $ 2.7721 $ 2.7638 26-Jun-18 $ 2.7857 $ 2.7774 $ 2.7690 25-Jun-18 $ 2.7931 $ 2.7848 $ 2.7764 22-Jun-18 $ 2.7771

More information

Facilities Planning & Construction Report nd Quarter Ending December 31, 2017

Facilities Planning & Construction Report nd Quarter Ending December 31, 2017 Facilities Planning & Construction Report 2017 18 2 nd Quarter Ending December 31, 2017 Overview District SRID Spending (MG100) Summary By College By Site District Measure J Spending (MJ100) Summary By

More information

Grossmont-Cuyamaca Community College District Project Labor Agreement Evaluation Plan

Grossmont-Cuyamaca Community College District Project Labor Agreement Evaluation Plan March 16, 2017 PROCEDURE MANUAL TABLE OF CONTENTS PLA EVALUATION PLAN PROCESS A. OVERVIEW... 2 Projects... 2 Controlling Laws and Regulations... 2 Roles and Responsibilities... 2 B. KEY PERFORMANCE INDICATORS

More information

Big Walnut Local School District

Big Walnut Local School District Big Walnut Local School District Monthly Financial Report for the month ended September 30, 2012 Prepared By: Felicia Drummey Treasurer BIG WALNUT LOCAL SCHOOL DISTRICT SUMMARY OF YEAR-TO-DATE FINANCIAL

More information

Governing Board Bond Update. Measure G Bond Program. for. Solano Community College District

Governing Board Bond Update. Measure G Bond Program. for. Solano Community College District Governing Board Bond Update for Measure G Bond Program prepared by Kitchell for the Solano Community College District Included in Booklet: Board Update Bond Financial Summary Completed Projects Projects

More information

Planning and Construction Department 1130 Fifth Avenue, Chula Vista, CA (619) FAX (619)

Planning and Construction Department 1130 Fifth Avenue, Chula Vista, CA (619) FAX (619) Planning and Construction Department 1130 Fifth Avenue, Chula Vista, CA 91911 (619) 691-5553 FAX (619) 420-0339 Prop O Project Summary page 1 General for CBOC Meeting of January 20, 2016 1 2 date info

More information

WESTWOOD LUTHERAN CHURCH Summary Financial Statement YEAR TO DATE - February 28, Over(Under) Budget WECC Fund Actual Budget

WESTWOOD LUTHERAN CHURCH Summary Financial Statement YEAR TO DATE - February 28, Over(Under) Budget WECC Fund Actual Budget WESTWOOD LUTHERAN CHURCH Summary Financial Statement YEAR TO DATE - February 28, 2018 General Fund Actual A B C D E F WECC Fund Actual Revenue Revenue - Faith Giving 1 $ 213 $ 234 $ (22) - Tuition $ 226

More information

Review of Membership Developments

Review of Membership Developments RIPE Network Coordination Centre Review of Membership Developments 7 October 2009/ GM / Lisbon http://www.ripe.net 1 Applications development RIPE Network Coordination Centre 140 120 100 80 60 2007 2008

More information

Fiscal Year 2018 Project 1 Annual Budget

Fiscal Year 2018 Project 1 Annual Budget Fiscal Year 2018 Project 1 Annual Budget Table of Contents Table Page Summary 3 Summary of Costs Table 1 4 Treasury Related Expenses Table 2 5 Summary of Full Time Equivalent Table 3 6 Positions Cost-to-Cash

More information

University of Colorado Capital Construction Project Status SUMMARY - May 2017 (accounting noted by campus)

University of Colorado Capital Construction Project Status SUMMARY - May 2017 (accounting noted by campus) of Colorado Capital Project Status SUMMARY - May (accounting noted by campus) Legend On-Track Risks Approved - Adjustments Needed Awaiting $ Start-Up Phase In Bidding Phase In Closeout Project Completed

More information

Asset Manager Performance Comparison

Asset Manager Performance Comparison Cape Peninsula University of Technology Retirement Fund August 2017 DISCLAIMER AND WARNINGS: Towers Watson (Pty) Ltd, a Willis Towers Watson company, is an authorised financial services provider. Although

More information

Asset Manager Performance Comparison

Asset Manager Performance Comparison Cape Peninsula University of Technology Retirement Fund September 2017 DISCLAIMER AND WARNINGS: Towers Watson (Pty) Ltd, a Willis Towers Watson company, is an authorised financial services provider. Although

More information

Oceanside Gateway Business Park O. A.

Oceanside Gateway Business Park O. A. Operating Budget-Final Parcel Parcel Address Parcel / Bldg / Unit Sq. Ft. % of project Total Monthly Assessment Total Quarterly Assessment PSF/Mo. 1 Hamann Co 33,100 6.78% $ 1,735 $ 5,205 $ 0.052 2-1 BP

More information

Common stock prices 1. New York Stock Exchange indexes (Dec. 31,1965=50)2. Transportation. Utility 3. Finance

Common stock prices 1. New York Stock Exchange indexes (Dec. 31,1965=50)2. Transportation. Utility 3. Finance Digitized for FRASER http://fraser.stlouisfed.org/ Federal Reserve Bank of St. Louis 000 97 98 99 I90 9 9 9 9 9 9 97 98 99 970 97 97 ""..".'..'.."... 97 97 97 97 977 978 979 980 98 98 98 98 98 98 987 988

More information

HUD NSP-1 Reporting Apr 2010 Grantee Report - New Mexico State Program

HUD NSP-1 Reporting Apr 2010 Grantee Report - New Mexico State Program HUD NSP-1 Reporting Apr 2010 Grantee Report - State Program State Program NSP-1 Grant Amount is $19,600,000 $9,355,381 (47.7%) has been committed $4,010,874 (20.5%) has been expended Grant Number HUD Region

More information

Review of Registered Charites Compliance Rates with Annual Reporting Requirements 2016

Review of Registered Charites Compliance Rates with Annual Reporting Requirements 2016 Review of Registered Charites Compliance Rates with Annual Reporting Requirements 2016 October 2017 The Charities Regulator, in accordance with the provisions of section 14 of the Charities Act 2009, carried

More information

MONTHLY FINANCIAL SUMMARY FISCAL YEAR (SEPTEMBER)

MONTHLY FINANCIAL SUMMARY FISCAL YEAR (SEPTEMBER) MONTHLY FINANCIAL SUMMARY FISCAL YEAR 2017-2018 (SEPTEMBER) Original Budget Revenues Collected YTD % Collected of Annual Enrollment Based $ 109,171,283 $ 45,498,974 41.7% State Funding 85,551,407 21,308,376

More information

Fiscal Year 2010 Columbia Generating Station Annual Operating Budget

Fiscal Year 2010 Columbia Generating Station Annual Operating Budget Fiscal Year 2010 Columbia Generating Station Annual Operating Budget Table of Contents Table Page Summary 3 Key Assumptions/Qualifications 4 Memorandum of Agreement (MOA) Table 1 5 Columbia Station Costs

More information

Invoice Process and Payment Review for BuildLACCD. Briefing No. 3. May 25, 2016

Invoice Process and Payment Review for BuildLACCD. Briefing No. 3. May 25, 2016 Invoice Process and Payment Review for BuildLACCD Briefing No. 3 May 25, 2016 Status Update On February 26, 2016, LACCD s Board and AECOM requested Deloitte to assess the invoice and payment process at

More information

FACILITIES PLAN STATUS REPORT July 21, 2014 SADDLEBACK COLLEGE 1. SCIENCES BUILDING

FACILITIES PLAN STATUS REPORT July 21, 2014 SADDLEBACK COLLEGE 1. SCIENCES BUILDING Page 1 of 11 FACILITIES PLAN STATUS REPORT July 21, 2014 SADDLEBACK COLLEGE 1. SCIENCES BUILDING Project Budget: $52,234,000 $8,308,000 $67,358,000 State Match: $36,564,000 ($36,564,000) - Basic Aid Allocation:

More information

FACILITIES PLAN STATUS REPORT January 22, 2019 CAPITAL IMPROVEMENT PLANNING

FACILITIES PLAN STATUS REPORT January 22, 2019 CAPITAL IMPROVEMENT PLANNING Page 1 of 19 FACILITIES PLAN STATUS REPORT January 22, 2019 CAPITAL IMPROVEMENT PLANNING The decision to design and construct capital improvement projects begins with the Education and Facilities Master

More information

FOR - ARRA Financial and Operational Review Report Investigations

FOR - ARRA Financial and Operational Review Report Investigations Program Description 96-3133 Investigations This appropriation funds studies to determine the need, engineering feasibility, and economic and environmental return to the Nation of potential solutions to

More information

QUESTION 2. QUESTION 3 Which one of the following is most indicative of a flexible short-term financial policy?

QUESTION 2. QUESTION 3 Which one of the following is most indicative of a flexible short-term financial policy? QUESTION 1 Compute the cash cycle based on the following information: Average Collection Period = 47 Accounts Payable Period = 40 Average Age of Inventory = 55 QUESTION 2 Jan 41,700 July 39,182 Feb 18,921

More information

Status of the Unemployment Trust Fund and Related Issues. Commission on Unemployment Compensation. Ellen Marie Hess, Commissioner.

Status of the Unemployment Trust Fund and Related Issues. Commission on Unemployment Compensation. Ellen Marie Hess, Commissioner. Status of the Unemployment Trust Fund and Related Issues Commission on Unemployment Compensation August 8, 2018 Ellen Marie Hess, Commissioner 2 Trust Fund Data Standard Forecast (Millions of Dollars)

More information

Construction Report Update

Construction Report Update NEW TRIER HIGH SCHOOL Construction Report Update September 2016 New Trier Winnetka Campus West Side Addition TABLE OF CONTENTS I. Neighbor Relations II. III. IV. Project Summary Schedule Progress Milestones

More information

THURGOOD MARSHALL MIDDLE SCHOOL LYNN, MA

THURGOOD MARSHALL MIDDLE SCHOOL LYNN, MA THURGOOD MARSHALL MIDDLE SCHOOL LYNN, MA Monthly Project Update Report SEPTEMBER 2012 FS/SD DD CD Bidding Construction Closeout THURGOOD MARSHALL MIDDLE SCHOOL SEPTEMBER 2012 01 TASKS COMPLETED DURING

More information

DETROIT LAKES CITY COUNCIL SPECIAL MEETING AGENDA TUESDAY, June 19, 2018

DETROIT LAKES CITY COUNCIL SPECIAL MEETING AGENDA TUESDAY, June 19, 2018 DETROIT LAKES CITY COUNCIL SPECIAL MEETING AGENDA TUESDAY, June 19, 2018 The items on my desk as of Wednesday, June 13, 2018, to be presented for discussion and action at the Special Meeting of the City

More information

Financial & Business Highlights For the Year Ended June 30, 2017

Financial & Business Highlights For the Year Ended June 30, 2017 Financial & Business Highlights For the Year Ended June, 17 17 16 15 14 13 12 Profit and Loss Account Operating Revenue 858 590 648 415 172 174 Investment gains net 5 162 909 825 322 516 Other 262 146

More information

Community College District. Measure M

Community College District. Measure M Community College District Measure M Monthly Report October 2015 San Bernardino Community College District Program Management Measure M Monthly Report October 2015 1. Valley Campus Project Sheets 2. Crafton

More information

T2/T3 Modernization Program Status Update

T2/T3 Modernization Program Status Update T2/T3 Modernization Program Status Update [ADD IMAGE] Board of Airport Commissioners T2/T3 Modernization Program Status Update Agenda 2017 Program Status Update T2/T3 Modernization Program Status Update

More information

Big Walnut Local School District

Big Walnut Local School District Big Walnut Local School District Monthly Financial Report for the month ended September 30, 2013 Prepared By: Felicia Drummey Treasurer BIG WALNUT LOCAL SCHOOL DISTRICT SUMMARY OF YEAR TO DATE FINANCIAL

More information

($M) ($M) ($M) ($M) ($M) ($M) ($M) ($M) ($M) ($M)

($M) ($M) ($M) ($M) ($M) ($M) ($M) ($M) ($M) ($M) Table 1 Table 1 Projects >$10M Total Project Cost 1 Project Project Final Total In-Service In-Service In-Service 2007 2008 2009 2010 2011 2012 Line Summary Start In-Service Project Cost 2 2010 2011 2012

More information

Bonnie Beard Agriculture Center Dedication November 29, Design & Construction Managed Projects. Monthly Report

Bonnie Beard Agriculture Center Dedication November 29, Design & Construction Managed Projects. Monthly Report Bonnie Beard Agriculture Center Dedication November 29, 2017 Design & Construction Managed Projects Monthly Report November 2017 Design & Construction Managed Projects Table of Contents Page Understanding

More information

TERMS OF REFERENCE FOR THE INVESTMENT COMMITTEE

TERMS OF REFERENCE FOR THE INVESTMENT COMMITTEE I. PURPOSE The purpose of the Investment Committee (the Committee ) is to recommend to the Board the investment policy, including the asset mix policy and the appropriate benchmark for both ICBC and any

More information

General Fund Revenue

General Fund Revenue Millions Percent of Kathy Steinert, Director of Fiscal Services Phone: 541.923.8927 145 SE Salmon Ave Redmond, OR 97756 kathy.steinert@redmond.k12.or.us Date: May 23, 2014 To: Redmond School District Board

More information

The Beverly Middle School Flexible Learning Academy

The Beverly Middle School Flexible Learning Academy Transformative Learning Through Architecture The Beverly Middle School Flexible Learning Academy Flexible Classroom Studios FLEXIBLE ACADEMY Flexible Configurations Flexible Support Exhibits Cross Discipline

More information

11 May Report.xls Office of Budget & Fiscal Planning

11 May Report.xls Office of Budget & Fiscal Planning Education and General Fund Actual Revenues and s by Month MTD YTD Change Revenue Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Per 14 Total over FY06 Enrollment Fees $ 8,211 $ 219 $ 41,952 ($ 818) $

More information

Current Employment Statistics

Current Employment Statistics Current Employment Statistics October 2017 If you have any questions or seek additional information, please contact: Vermont Department of Labor Economic and Labor Market Information Division 802-828-4202

More information

Original Revision Total Project Budget: $14,530,000 $47,700,000 $62,230,000 District Funding Commitment Anticipated State Match: $14,530,000 $N/A

Original Revision Total Project Budget: $14,530,000 $47,700,000 $62,230,000 District Funding Commitment Anticipated State Match: $14,530,000 $N/A Page 1 of 14 FACILITIES PLAN STATUS REPORT April 30, 2018 CAPITAL IMPROVEMENT PLANNING The decision to design and construct capital improvement projects begins with the Education and Facilities Master

More information

Current Employment Statistics

Current Employment Statistics Current Employment Statistics December 2017 If you have any questions or seek additional information, please contact: Vermont Department of Labor Economic and Labor Market Information Division 802-828-4202

More information

Cost Estimation of a Manufacturing Company

Cost Estimation of a Manufacturing Company Cost Estimation of a Manufacturing Company Name: Business: Date: Economics of One Unit: Manufacturing Company (Only complete if you are making a product, such as a bracelet or beauty product) Economics

More information

FOR RELEASE: MONDAY, MARCH 21 AT 4 PM

FOR RELEASE: MONDAY, MARCH 21 AT 4 PM Interviews with 1,012 adult Americans conducted by telephone by Opinion Research Corporation on March 18-20, 2011. The margin of sampling error for results based on the total sample is plus or minus 3

More information

Status: Structural steel installation complete at primary building. Observatory construction underway. Central Plant modifications are complete.

Status: Structural steel installation complete at primary building. Observatory construction underway. Central Plant modifications are complete. Page 1 of 14 FACILITIES PLAN STATUS REPORT August 24, 2015 SADDLEBACK COLLEGE 1. SCIENCES BUILDING Project Budget: $52,234,000 $8,308,000 $67,358,000 State Match: $36,564,000 ($36,564,000) - Basic Aid

More information

LOUISVILLE GAS AND ELECTRIC COMPANY Gas Rates 2018 Monthly Billing Adjustments

LOUISVILLE GAS AND ELECTRIC COMPANY Gas Rates 2018 Monthly Billing Adjustments 2018 Monthly Billing Adjustments GAS LINE TRACKER CHARGES GAS LINE TRACKER CHARGES DSM (2) PER MONTH PER METER PER MONTH PER CCF TAX CUTS AND JOBS ACT $ Per CCF Firm Trans. SURCREDIT ($ per ccf) (3) GAS

More information

Original Revision Total Project Budget: $52,234,000 $ 8,308,000 $67,358,000 District Funding Commitment: $15,670,000 $51,688,000 $67,358,000

Original Revision Total Project Budget: $52,234,000 $ 8,308,000 $67,358,000 District Funding Commitment: $15,670,000 $51,688,000 $67,358,000 Page 1 of 20 FACILITIES PLAN STATUS REPORT June 27, 2016 CAPITAL IMPROVEMENT PLANNING The decision to design and construct capital improvement projects begins with the Education and Facilities Master Planning

More information

PHOENIX ENERGY MARKETING CONSULTANTS INC. HISTORICAL NATURAL GAS & CRUDE OIL PRICES UPDATED TO July, 2018

PHOENIX ENERGY MARKETING CONSULTANTS INC. HISTORICAL NATURAL GAS & CRUDE OIL PRICES UPDATED TO July, 2018 Jan-01 $12.9112 $10.4754 $9.7870 $1.5032 $29.2595 $275.39 $43.78 $159.32 $25.33 Feb-01 $10.4670 $7.8378 $6.9397 $1.5218 $29.6447 $279.78 $44.48 $165.68 $26.34 Mar-01 $7.6303 $7.3271 $5.0903 $1.5585 $27.2714

More information

Factor Leave Accruals. Accruing Vacation and Sick Leave

Factor Leave Accruals. Accruing Vacation and Sick Leave Factor Leave Accruals Accruing Vacation and Sick Leave Factor Leave Accruals As part of the transition of non-exempt employees to biweekly pay, the UC Office of the President also requires standardization

More information

The equity derivatives market: The state of the art

The equity derivatives market: The state of the art The equity derivatives market: The state of the art Susan Thomas susant@igidr.ac.in http://www.igidr.ac.in/~susant August 11, 2001 Turnover Page 1 of 19 Goals Index futures Index options Stock options

More information

Projections/Estimated - Unrestricted Cash / Board Designated Cash & Investments September 2017

Projections/Estimated - Unrestricted Cash / Board Designated Cash & Investments September 2017 Projections/Estimated - Unrestricted Cash / Board Designated Cash & Investments September 2017 25.0 20.0 17.1 16.9 15.0 10.0 11.7 11.0 9.1 10.1 9.7 7.7 7.0 6.8 15.1 14.8 11.5 13.1 13.8 9.9 11.4 12.2 8.4

More information

Status: Structural steel installation underway at primary building. Observatory construction underway.

Status: Structural steel installation underway at primary building. Observatory construction underway. Page 1 of 11 FACILITIES PLAN STATUS REPORT March 30, 2015 SADDLEBACK COLLEGE 1. SCIENCES BUILDING Project Budget: $52,234,000 $8,308,000 $67,358,000 State Match: $36,564,000 ($36,564,000) - Basic Aid Allocation:

More information

UNIVERSITY OF NORTHERN COLORADO: FINANCIAL REPORT 12/31/2010

UNIVERSITY OF NORTHERN COLORADO: FINANCIAL REPORT 12/31/2010 UNIVERSITY OF NORTHERN COLORADO: FINANCIAL REPORT 12/31/2010 OVERVIEW The following is a summary of the financial highlights contained in the second quarter report for fiscal year 2010-11: Cash and Accounts

More information

Executive Summary. July 17, 2015

Executive Summary. July 17, 2015 Executive Summary July 17, 2015 The Revenue Estimating Conference adopted interest rates for use in the state budgeting process. The adopted interest rates take into consideration current benchmark rates

More information

2011 Budget Initial Stakeholder Call

2011 Budget Initial Stakeholder Call 2011 Budget Initial Stakeholder Call Michael Epstein Director of Financial Planning June 23, 2010 Agenda TOPIC PRESENTER Introduction Steve Berberich Budget principles & strategic initiatives Steve Berberich

More information

Financial and Operating Plan Kevyn D. Orr Emergency Manager

Financial and Operating Plan Kevyn D. Orr Emergency Manager Financial and Operating Plan Kevyn D. Orr Emergency Manager June 10, 2013 Detroit spends more than it takes in it is insolvent. It has borrowed hundreds of millions of dollars and has deferred just as

More information

MONTHLY FINANCIAL SUMMARY FISCAL YEAR (MARCH)

MONTHLY FINANCIAL SUMMARY FISCAL YEAR (MARCH) MONTHLY FINANCIAL SUMMARY FISCAL YEAR 20172018 (MARCH) Original Budget Revenues Collected YTD % Collected of Annual Enrollment Based $ 109,171,283 $ 101,304,928 92.8% State Funding 85,551,407 63,950,143

More information

OTHER DEPOSITS FINANCIAL INSTITUTIONS DEPOSIT BARKAT SAVING ACCOUNT

OTHER DEPOSITS FINANCIAL INSTITUTIONS DEPOSIT BARKAT SAVING ACCOUNT WEIGHTAGES JAN FEB MAR APR MAY JUN JUL AUG SEPT OCT NOV DEC ANNOUNCEMENT DATE 19.Dez.14 27.Jän.15 24.Feb.15 26.Mär.15 27.Apr.15 26.Mai.15 25.Jun.15 28.Jul.15 26.Aug.15 23.Sep.15 27.Okt.15 25.Nov.15 MUDARIB

More information

PUBLIC HEALTH & 2016 SAFETY BOND. San Francisco Department of Public Health. Full Health Commission February 21 st, 2017

PUBLIC HEALTH & 2016 SAFETY BOND. San Francisco Department of Public Health. Full Health Commission February 21 st, 2017 PUBLIC HEALTH & 2016 SAFETY BOND San Francisco Department of Public Health Full Health Commission February 21 st, 2017 Topics & Presenters Introduction to Bonds Mark Primeau Quarterly Highlights Terry

More information

Government Bond Market Development in Myanmar

Government Bond Market Development in Myanmar Government Bond Market Development in Myanmar Daw Si Si Pyone Deputy Director General Treasury Department 11-8-2017 Ministry of Planning and Finance 1 Outlines I. Key Milestones in Development of Treasury

More information

Performance Report October 2018

Performance Report October 2018 Structured Investments Indicative Report October 2018 This report illustrates the indicative performance of all Structured Investment Strategies from inception to 31 October 2018 Matured Investment Strategies

More information

2011 Budget vs. Actual Status

2011 Budget vs. Actual Status 2011 Budget vs. Actual Status (unaudited d results) ($ in millions, unless otherwise noted) Draft - For Discussion Purposes Only Cheryl Hussey Controller & Asst. Treasurer Budget & Priorities Working Group

More information

Billing and Collection Agent Report For period ending September 30, To NANC

Billing and Collection Agent Report For period ending September 30, To NANC Billing and Collection Agent Report For period ending September 30, 2010 To NANC October 14, 2010 STATEMENT OF FINANCIAL POSITION September 30, 2010 Assets Cash Balance in bank account $ 2,926,706 Receivable

More information

CPA Australia Plan Your Own Enterprise Competition

CPA Australia Plan Your Own Enterprise Competition Financial Plan Your financial plan should include: 1. A list of Start-Up Costs and how these will be paid for (eg from savings, bank loan or family loan) 2. A Breakeven Analysis, which includes: a list

More information

HIPIOWA - IOWA COMPREHENSIVE HEALTH ASSOCIATION Unaudited Balance Sheet As of July 31

HIPIOWA - IOWA COMPREHENSIVE HEALTH ASSOCIATION Unaudited Balance Sheet As of July 31 Unaudited Balance Sheet As of July 31 Total Enrollment: 407 Assets: Cash $ 9,541,661 $ 1,237,950 Invested Cash 781,689 8,630,624 Premiums Receivable 16,445 299,134 Prepaid 32,930 34,403 Assessments Receivable

More information

THE B E A CH TO WN S O F P ALM B EA CH

THE B E A CH TO WN S O F P ALM B EA CH THE B E A CH TO WN S O F P ALM B EA CH C OU N T Y F LO R I D A August www.luxuryhomemarketing.com PALM BEACH TOWNS SINGLE-FAMILY HOMES LUXURY INVENTORY VS. SALES JULY Sales Luxury Benchmark Price : 7,

More information

Original Revision Total Project Budget: $14,530,000 $47,700,000 $62,230,000 District Funding Commitment Anticipated State Match: $14,530,000 $N/A

Original Revision Total Project Budget: $14,530,000 $47,700,000 $62,230,000 District Funding Commitment Anticipated State Match: $14,530,000 $N/A Page 1 of 15 FACILITIES PLAN STATUS REPORT June 25, 2018 CAPITAL IMPROVEMENT PLANNING The decision to design and construct capital improvement projects begins with the Education and Facilities Master Planning

More information

Beatitudes Campus. Occupancy. Days of Cash on Hand. Occupancy. Operating Ratio. Debt Service Coverage Ratio

Beatitudes Campus. Occupancy. Days of Cash on Hand. Occupancy. Operating Ratio. Debt Service Coverage Ratio 86% 96% 95% 80% 2018 Forecast 86% 95% 80% 2018 YTD 2017 2016 2015 2014 2013 Operating Ratio Operating Ratio (Revenue ) / (Expenses-(Depreciation & Amortization)) (Revenue)/(Expenses-(Depr & Amort)) Debt

More information

HIPIOWA - IOWA COMPREHENSIVE HEALTH ASSOCIATION Unaudited Balance Sheet As of January 31

HIPIOWA - IOWA COMPREHENSIVE HEALTH ASSOCIATION Unaudited Balance Sheet As of January 31 Unaudited Balance Sheet As of January 31 Total Enrollment: 371 Assets: Cash $ 1,408,868 $ 1,375,117 Invested Cash 4,664,286 4,136,167 Premiums Receivable 94,152 91,261 Prepaid 32,270 33,421 Assessments

More information

EARNED VALUE MANAGEMENT. Is it worth the effort?

EARNED VALUE MANAGEMENT. Is it worth the effort? EARNED VALUE MANAGEMENT Is it worth the effort? Session Objectives Examples of earned value in use. Why don t more Project Managers use EMV? Road Map to EVA Maturity? What you need to know? How is our

More information

VALENCIA COLLEGE FINANCIAL SUMMARY FISCAL YEAR As of April 30, 2016

VALENCIA COLLEGE FINANCIAL SUMMARY FISCAL YEAR As of April 30, 2016 VALENCIA COLLEGE FINANCIAL SUMMARY FISCAL YEAR 201516 As of April 30, 2016 Budgeted Annual Collected % Collected Revenue Year To Date Of Annual Enrollment Based 94,185,539 96,696,137 103% State Funding

More information

Status: Structural steel installation complete at primary building. Observatory construction underway. Central Plant modifications are complete.

Status: Structural steel installation complete at primary building. Observatory construction underway. Central Plant modifications are complete. Page 1 of 11 FACILITIES PLAN STATUS REPORT June 22, 2015 SADDLEBACK COLLEGE 1. SCIENCES BUILDING Project Budget: $52,234,000 $8,308,000 $67,358,000 State Match: $36,564,000 ($36,564,000) - Basic Aid Allocation:

More information

Ohlone Community College District

Ohlone Community College District Ohlone Community College District General Obligation Bond Refinancing Overview June 8, 2016 Outstanding General Obligation Bonds Issue Date Issue Amount Description Call Date Maturity Outstanding 6/19/2002

More information

Original Revision Total Project Budget: $14,530,000 $47,700,000 $62,230,000 District Funding Commitment Anticipated State Match: $14,530,000 $N/A

Original Revision Total Project Budget: $14,530,000 $47,700,000 $62,230,000 District Funding Commitment Anticipated State Match: $14,530,000 $N/A Page 1 of 14 FACILITIES PLAN STATUS REPORT May 21, 2018 CAPITAL IMPROVEMENT PLANNING The decision to design and construct capital improvement projects begins with the Education and Facilities Master Planning

More information

FUEL PRICE RISK MANAGEMENT POLICY REPORT "FUEL HEDGE"

FUEL PRICE RISK MANAGEMENT POLICY REPORT FUEL HEDGE FUEL PRICE RISK MANAGEMENT POLICY REPORT "FUEL HEDGE" Sep-18 FUEL PRICE RISK MANAGEMENT POLICY REPORT Sep-18 (Office of Management and Budget 09/30/2018) The Fuel Price Risk Management Policy approved

More information

Title: COST CONTRACT CONTINUOUS MAINTENANCE AND EMERGENT WORK REPORT. Number: DI-FNCL Approval Date:

Title: COST CONTRACT CONTINUOUS MAINTENANCE AND EMERGENT WORK REPORT. Number: DI-FNCL Approval Date: DATA ITEM DESCRIPTION Title: COST CONTRACT CONTINUOUS MAINTENANCE AND EMERGENT WORK REPORT Number: Approval Date: 20091026 AMSC Number: N9105 Limitation: DTIC Applicable: N/A GIDEP Applicable: N/A Office

More information

UNIVERSITY OF NORTHERN COLORADO: FINANCIAL REPORT 09/30/2018

UNIVERSITY OF NORTHERN COLORADO: FINANCIAL REPORT 09/30/2018 UNIVERSITY OF NORTHERN COLORADO: FINANCIAL REPORT 09/30/2018 OVERVIEW Financial highlights of the fiscal year 2018-19 1 st quarter financial report are summarized below: Cash (pages 2-3) The University

More information

1 Long Term Debt $ 9,298,554 $ (250,000) $ 9,048, Preferred Stock 30,450 30, % 5 Common Equity 250, %

1 Long Term Debt $ 9,298,554 $ (250,000) $ 9,048, Preferred Stock 30,450 30, % 5 Common Equity 250, % SUMMARY SCHEDULE ($000'S) Schedule 1 Page 1 of 1 Line Capitalization HISTORICAL YEAR ENDED 12/31/16 Hybrid Percent Equity Adjusted of Total Cost of Cost of Amount Adjustment Amount Capitalization Capital

More information

LRD IWTF Projects Update Inland Waterways Users Board

LRD IWTF Projects Update Inland Waterways Users Board LRD IWTF Projects Update Inland Waterways Users Board MS. JEANINE HOEY, PE, PMP CHIEF, E&C Division Pittsburgh District 13 Dec 2016 The views, opinions and findings contained in this report are those of

More information

Earned Value Management An Overview March 2014

Earned Value Management An Overview March 2014 Earned Value Management An Overview March 2014 SAVE International Cascadia Chapter Introduction What is Earned Value? Why is Earned Value important? What is required? Earned Value Definitions & Process

More information

Distribution Group Study Process. August 26, 2014

Distribution Group Study Process. August 26, 2014 Distribution Group Study Process August 26, 2014 Agenda Overview Applying for DGSP DGSP Interconnection Process Applicability and Utility Contacts Questions 2 Process Overview Open Window Period Evaluation

More information

QUARTERLY REPORT AND CERTIFICATION OF THE COUNTY TREASURER For Quarter Ending June 30, 2009 COMPLIANCE CERTIFICATION

QUARTERLY REPORT AND CERTIFICATION OF THE COUNTY TREASURER For Quarter Ending June 30, 2009 COMPLIANCE CERTIFICATION QUARTERLY REPORT AND CERTIFICATION OF THE COUNTY TREASURER For Quarter Ending June 30, 2009 The Government Code requires the County Treasurer to render a Quarterly Report to the County Administrator, the

More information

STATE CAPITAL OUTLAY PLANNING

STATE CAPITAL OUTLAY PLANNING STATE CAPITAL OUTLAY PLANNING CCC Chancellor s Office Cheryl Larry Lan Yuan San Mateo CCD Jose Nunez Karen Pinkham CCFC 2016 AGENDA Overview Eligibility Priority Review/Approval Effective Practices 1 Key

More information

Fiscal Year 2017 Columbia Generating Station Annual Operating Budget

Fiscal Year 2017 Columbia Generating Station Annual Operating Budget Fiscal Year 2017 Columbia Generating Station Annual Operating Budget Table of Contents Table Page Summary 3 Key Assumptions/Qualifications 4 Memorandum of Agreement (MOA) Table 1 5 Columbia Station Costs

More information

Isle Of Wight half year business confidence report

Isle Of Wight half year business confidence report half year business confidence report half year report contents new company registrations closed companies (dissolved) net company growth uk company share director age director gender naming trends sic

More information

U.S. Natural Gas Storage Charts

U.S. Natural Gas Storage Charts U.S. Natural Gas Storage Charts BMO Capital Markets Commodity Products Group November 26, 214 Total U.S. Natural Gas in Storage 5, Total Stocks This Week 3432 4, 3, 2, 1, Reported On: November 26, 214

More information

SANTA ANA COLLEGE FACILITIES COMMITTEE MEETING MAY 15, 2018

SANTA ANA COLLEGE FACILITIES COMMITTEE MEETING MAY 15, 2018 FACILITIES COMMITTEE MEETING MAY 15, 2018 1 PROJECTS Dunlap Hall Renovation - Completed Central Plant & Infrastructure - Completed Johnson Student Center Johnson Demolition Science Center & Building J

More information

Billing and Collection Agent Report For period ending April 30, To NANC

Billing and Collection Agent Report For period ending April 30, To NANC Billing and Collection Agent Report For period ending April 30, 2011 To NANC May 17, 2011 STATEMENT OF FINANCIAL POSITION April 30, 2011 Assets Cash Balance in bank account $ 1,824,073 Receivable from

More information

Foundations of Investing

Foundations of Investing www.edwardjones.com Member SIPC Foundations of Investing 1 5 HOW CAN I STAY ON TRACK? 4 HOW DO I GET THERE? 1 WHERE AM I TODAY? MY FINANCIAL NEEDS 3 CAN I GET THERE? 2 WHERE WOULD I LIKE TO BE? 2 Develop

More information

From Suspicion to Invaluable Transition of Two Project Managers

From Suspicion to Invaluable Transition of Two Project Managers From Suspicion to Invaluable Transition of Two Project Managers June 2010 Shilpi Kumar & Sunita Raman Agenda Unisys and HOLMES 2 Nature of Projects and Roles Why EVA? How? EVA in Development Projects Transition

More information

Revenue Estimating Conference Tobacco Tax and Surcharge Executive Summary

Revenue Estimating Conference Tobacco Tax and Surcharge Executive Summary Revenue Estimating Conference Tobacco Tax and Surcharge Executive Summary February 12, 2014 The Revenue Estimating Conference reviewed Tobacco Tax and Surcharge revenues on February 12, 2014. The forecasts

More information

Approve Assure Note. Board of Directors Meeting Report 31 July Agenda item 254/13. Title. Sponsoring Director. Authors.

Approve Assure Note. Board of Directors Meeting Report 31 July Agenda item 254/13. Title. Sponsoring Director. Authors. Board of Directors Meeting Report 31 July 213 Agenda item 254/13 Title Quarter One Cost Improvement Programme Update Sponsoring Director Jacqueline Totterdell Chief Executive Authors Purpose Liam Slattery

More information

Board of Directors October 2018 and YTD Financial Report

Board of Directors October 2018 and YTD Financial Report Board of Directors October 2018 and YTD Financial Report Consolidated Financial Results Operating Margin October ($30,262) $129,301 ($159,563) Year-to-date $292,283 $931,358 ($639,076) Excess of Revenue

More information

Development of Economy and Financial Markets of Kazakhstan

Development of Economy and Financial Markets of Kazakhstan Development of Economy and Financial Markets of Kazakhstan National Bank of Kazakhstan Macroeconomic development GDP, real growth, % 116 112 18 14 1 113,5 11,7 216,7223,8226,5 19,8 19,8 19,3 19,619,7 199,

More information

2016 PUBLIC HEALTH & SAFETY BOND Quarterly Update. Full Health Commission October 2, 2018

2016 PUBLIC HEALTH & SAFETY BOND Quarterly Update. Full Health Commission October 2, 2018 2016 PUBLIC HEALTH & SAFETY BOND Quarterly Update Full Health Commission October 2, 2018 Topics & Presenters Bond Overview Mark Primeau Budget/Bond Sales Mark Primeau Accomplishments since September Health

More information

The year to date is less than budget and prior year by 15.4 million and 11.6 million, respectively.

The year to date is less than budget and prior year by 15.4 million and 11.6 million, respectively. To: Chicago Transit Authority Board From: Jeremy Fine, Chief Financial Officer Re: Financial Results for September 2016 Date: November 16, 2016 I. Summary CTA s financial results are $0.3 million unfavorable

More information