The Cost of Poor Reliability for Future Particle Accelerator Driven Systems in the UK Energy Market
|
|
- Arthur Houston
- 5 years ago
- Views:
Transcription
1 The Cost of Poor Reliability for Future Particle Accelerator Driven Systems in the UK Energy Market Steven J Steer, William J Nuttall, Geoff T Parks & Leonardo V N Gonçalves
2 Accelerator Driven Nuclear Power A design Concept Feasibility Study UK Engineering and Physical Sciences Research Council (EPSRC) funded project Investigating the potential of accelerator assisted nuclear reactor designs both as radioactive waste transmuters and as commercial power generators The study is dedicated to examining the entire picture: Can the engineering challenges faced by accelerators be overcome? Is there a market for the technology and can an economically viable design be realised. Quantifying the economics of reliability Reliability is a critical issue regarding using accelerators in the energy market As a part of the feasibility study, the value lost due to poor reliability has been predicted
3 Uranium Supply Nuclear Fuel (OECD NEA & IAEA report Uranium 2007: Resources, Production and Demand) At 2006 rates of consumption, Identified Resources are sufficient for about 100 years Five options for increasing the available energy I. Increase spent fuel reprocessing II. Switch to fusion III. Extract uranium from seawater IV. Fast fission (increased fuel burn efficiency) V. Replace uranium with thorium Accelerator Drive Subcritical Reactor (ADSR) This design concept addresses: thorium and fuel efficiency and (optional) fuel recycling
4 Accelerator Driven Subcritical Reactors Without the accelerator the nuclear core cannot sustain fission Accelerator system provides an additional kick to perpetuate fission Switching off the accelerator system shuts down the reactor this adds a safety failsafe Unplanned accelerator outages ( beam trips ) therefore also cause reactor shutdowns The implications of trips Potentially damage the core Cost of fulfilling sales contracts The economic cost of beam trips has been predicted for ADSRs of any chosen reliability
5 System Buy Price (2006 /MWh) Real Market Conditions UK market Using 2006 historical data Selling 600MWe to market Expected sales position Large capital costs, therefore: base load electricity Price takes at the long-term Market Index Price (MIP) During (instantaneous) unplanned shutdown: Pay the Nat. Grid the System Buy Price (SBP) for honouring contracts* Arrange short-term contracts at MIP to avoid paying the SBP 600 *The model modifies the historical SBP by + 100/MWh to simulate the impact of the failure on the grid assumption under review Data for the 2006 SBP in 30 minute periods minute period of 2006
6 Example: Cost of a Single 24 hour trip Select a random 24 hour (48 periods) from 2006 Generate success rate of arranging short-term contracts Repeat for 10,000 iterations Example of 3 iterations of the simulation 1 period = 30 minutes
7 Frequency Example: Cost of a Single 24 hour trip (cont.d) 10,000 iterations of the cost of a 24 hour shutdown. 16% Red: Loss Made Blue: Opportunity Cost 12% 8% 4% Mean Opportunity Cost: 1.37 million Standard Deviation: 0.31 million 0% Cost (2006 )
8 Cost of failures 30 minutes 24 hours in duration Opportunity Cost Repeat the process for all periods up to a maximum failure duration of 48 periods (24 hours) 0 30 minute period Plotted are the mean and standard deviation cost of failure for failure durations up to 48 periods
9 Cost (2006 Million) Trip Frequency Trip Frequency data of Existing Accelerators Observed Relative frequency of trips of different durations 2/3 power law Relationship: Frequency vs. durations greater than or equal to time t 50% uniform volatility about the mean (J. Galambos et al.) 1000,0 100,0 Trip frequency relative to a single 48 unit in duration failure 10, ,0 0, Duration of Failure (30 minute periods) Cost of failure per 48 unit in duration failure Failure duration in 30 minute periods
10 An ADSR of the user s specifications It is not certain what accelerator system reliability and load factor will be achieved An accelerator system like that required by an ADSR has never been built Research facilities are the closest existing match their research interests and (publically funded) budgets change priorities The model has been constructed so that the user can identify the cost of failure of their ADSR An ADSR with a lifetime of 40 years This is the standard life expectancy of a nuclear power station (Calculations have been repeated for a 60 year lifetime) A nominal failure rate is scaled to the user s rate The nominal rate is chosen to be 1% of the ADSR s life (For computational ease 0.77% has been used thus far, the presented numbers are for this 0.77% rate...this is going to be corrected when the analysis is completed)
11 Accounting for Inflation and Discounted Cash Flow Frequency Annually inflate electricity prices and discounted cash flow rate This requires that the cost of failure per year is identified Using the nominal shutdown rate, generate the trips experienced in a year Generate the cost of failure of each trip Repeat for 10,000 iterations 8% 6% 4% Cost of failure per year (prior to accounting for inflation and DCF) 2% 0% Cost per year for (2006 )
12 Opportunity Cost (2006 Millions) The Nominal Lifetime Cost of Failure % 6% 8% 10% 12% 14% Discounted Cash Flow Inflation rate 0.0% 1.5% 3.0% 4.5% 6.0% Nominal Lifetime Cost of Failure for a range of inflation and DCF rates Scaling from the nominal to the actual failure rate 1) Choose an inflation and DCF rate, then determine the corresponding nominal cost of failure 2) Choose a load factor and reliability coefficient and scale:
13 Opportunity Cost (2006 Millions) The Expected Cost of Failure of a Contemporary Accelerator System Existing Accelerator systems realise a Load Factor of 65% and a Reliability coefficient of 90% % 6% 8% 10% 12% 14% Discounted Cash Flow 0.0% 1.5% 3.0% 4.5% 6.0% For an Inflation rate of 3% and a (nominal) DCF rate of 10%: The lifetime cost of failure is: 600 million (PV 2006 )
14 PDS-XADS Research & Development Efforts Preliminary Design Studies experimental Accelerator Driven System Can be considered the best case engineering will achieve It expects 5 trips per year Assuming each trip is 24 hours in duration... Inflation: 3%, DCF rate: 10%: The lifetime Cost of Failure will be = 100 million CORDIS Contract Number: FIKW-CT Engineering Expenditure that takes existing technology to the best case technology should not exceed 500 million (Inflation 3%; DCF 10%; PV 2006 )
15 Overview A fleet of ADSRs will all benefit from the research Building multiple ADSRs will significantly increase the budget for improving the design Summary A monte carlo technique has been applied to asses the value of reliability engineering of ADSRs in the nuclear power industry The model identifies the cost of failure using data from existing systems and markets It defines quantitative goals for the budget engineers need to work within in order to maximise the value of future technology The model has been designed to be flexible, making it applicable to any chosen specifications (i.e. Load factor, reliability, inflation rate, DCF rate)
Guide. Commission Recommendation
Guide to the Commission Recommendation on the management of financial resources for the decommissioning of nuclear installations, spent fuel and radioactive waste (2006/851/Euratom) 1 2 Objective of the
More informationA European Industrial Initiative for Sustainable Fission (SET Plan),
The Sustainable Nuclear Energy Technology Platform (SNE-TP) building the European Research Area in nuclear fission A European Industrial Initiative for Sustainable Fission (SET Plan), Prepared by SNE-TP
More informationDOES LOST TIME COST YOU MONEY AND CREATE HIGH RISK?
DOES LOST TIME COST YOU MONEY AND CREATE HIGH RISK? Dr. István Fekete Corvinus University of Budapest H-1093 Budapest Fővám tér 8. Tel: +3630-456-3424 e-mail: istvan.fekete@uni-corvinus.hu Keywords: risk
More informationCOUNCIL OF THE EUROPEAN UNION. Brussels, 7 August 2002 (OR. en) 11382/02 Interinstitutional File: 2001/0125 (CNS) LIMITE RECH 136 ATO 103
COUNCIL OF THE EUROPEAN UNION Brussels, 7 August 2002 (OR. en) 11382/02 Interinstitutional File: 2001/0125 (CNS) LIMITE RECH 136 ATO 103 LEGISLATIVE ACTS AND OTHER INSTRUMENTS Subject : Council Decision
More informationSeminar on neutron research centre in the Øresund region (European Spallation Source) 29 November ESS, P&T and EU
Seminar on neutron research centre in the Øresund region (European Spallation Source) 29 November 2002 ESS, P&T and EU What is the impact of ESS and P&T on EU s energy policy? On EU-financed research?
More informationUse of the Risk Driver Method in Monte Carlo Simulation of a Project Schedule
Use of the Risk Driver Method in Monte Carlo Simulation of a Project Schedule Presented to the 2013 ICEAA Professional Development & Training Workshop June 18-21, 2013 David T. Hulett, Ph.D. Hulett & Associates,
More informationINTERNATIONAL CO-OPERATION IN RADIOACTIVE WASTE MANAGEMENT: ISSUES ARISING IN NUCLEAR LIABILITY JAKUB HANDRLICA *
INTERNATIONAL CO-OPERATION IN RADIOACTIVE WASTE MANAGEMENT: ISSUES ARISING IN NUCLEAR LIABILITY JAKUB HANDRLICA * Abstract International cooperation on the back end of the fuel cycle has potential to mobilize
More informationProbabilistic Safety Analysis (PSA): Applications. Guideline for Swiss Nuclear Installations ENSI-A06
Guideline for Swiss Nuclear Installations ENSI-A06 Edition November 2015 Edition November 2015 Guideline for Swiss Nuclear Installations ENSI-A06/e Contents Guideline for Swiss Nuclear Installations
More informationCNSC Cost Recovery Program
CNSC Cost Recovery Program Canadian Nuclear Safety Commission Cost Recovery Program Published by the Canadian Nuclear Safety Commission Également publié en français sous le titre de Programme de recouvrement
More informationCost Risk Assessment Building Success and Avoiding Surprises Ken L. Smith, PE, CVS
Cost Risk Assessment Building Success and Avoiding Surprises Ken L. Smith, PE, CVS 360-570-4415 2015 HDR, Inc., all rights reserved. Addressing Cost and Schedule Concerns Usual Questions Analysis Needs
More informationToolbox 7: Economic Feasibility Assessment Methods
Toolbox 7: Economic Feasibility Assessment Methods Dr. John C. Wright MIT - PSFC 05 OCT 2010 Introduction We have a working definition of sustainability We need a consistent way to calculate energy costs
More informationSNN Investors Teleconference. POWERed by people. Financial results for the period of three months ended 31 st March Q
SNN Investors Teleconference POWERed by people Financial results for the period of three months ended 31 st March 2017 -Q1 2017- Bucharest: May 12 th, 2017 Q1 2017 financial result highlights RON '000
More informationIntegrating Contract Risk with Schedule and Cost Estimates
Integrating Contract Risk with Schedule and Cost Estimates Breakout Session # B01 Donald E. Shannon, Owner, The Contract Coach December 14, 2015 2:15pm 3:30pm 1 1 The Importance of Estimates Estimates
More informationPHASE I.A. STOCHASTIC STUDY TESTIMONY OF DR. SHUCHENG LIU ON BEHALF OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION
Rulemaking No.: 13-12-010 Exhibit No.: Witness: Dr. Shucheng Liu Order Instituting Rulemaking to Integrate and Refine Procurement Policies and Consider Long-Term Procurement Plans. Rulemaking 13-12-010
More informationEuratom Fission Energy Research
Euratom Fission Energy Research Towards Horizon 2020 Roger GARBIL Acting Head of Unit DG Research and Innovation Euratom Fission European Commission Roger.Garbil@ec.europa.eu Nuclear data week, ANDES and
More informationMONITORING & REVIEW of IMPLEMENTATION PROGRESS. Definition and Quantification of the KPIs for the SET-Plan EIIs
1 MONITORING & REVIEW of IMPLEMENTATION PROGRESS Definition and Quantification of the KPIs for the SET-Plan EIIs Monitoring & Review - A reminder - SG Meeting _240511 2 2 Council Conclusions (12 (12 March
More informationANNEXES. to the. Proposal for a COUNCIL REGULATION
EUROPEAN COMMISSION Brussels, 7.6.2018 COM(2018) 437 final ANNEXES 1 to 2 ANNEXES to the Proposal for a COUNCIL REGULATION establishing the Research and Training Programme of the European Atomic Energy
More informationNIC Global Summit Outlook on Decommissioning Market
NIC Global Summit Outlook on Decommissioning Market January 12, 2016 Edward M. Davis Edavis@pegasusgroup.us State of Play - Nuclear Energy Worldwide At the end of 2015, world s 382 GW, 441 reactors, of
More informationUse of the Graded Approach in Regulation
Use of the Graded Approach in Regulation M. de Vos, New Major Facilities Licensing Division Directorate of Regulatory Improvement and Major Projects Management SMR Licensing Session Nuclear Institute Event:
More informationSIMULATION CHAPTER 15. Basic Concepts
CHAPTER 15 SIMULATION Basic Concepts Monte Carlo Simulation The Monte Carlo method employs random numbers and is used to solve problems that depend upon probability, where physical experimentation is impracticable
More informationOfficial Journal of the European Union. (Acts whose publication is not obligatory) COMMISSION
L 2/36 II (Acts whose publication is not obligatory) COMMISSION COMMISSION RECOMMDATION of 18 December 2003 on standardised information on radioactive airborne and liquid discharges into the environment
More informationCost Risk Assessments Planning for Project or Program Uncertainty with Confidence Brian Bombardier, PE
Cost Risk Assessments Planning for Project or Program Uncertainty with Confidence Brian Bombardier, PE 602-778-7324 brian.bombardier@hdrinc.com 2015 HDR, Inc., all rights reserved. Addressing Cost and
More informationRisk Video #1. Video 1 Recap
Risk Video #1 Video 1 Recap 1 Risk Video #2 Video 2 Recap 2 Risk Video #3 Risk Risk Management Process Uncertain or chance events that planning can not overcome or control. Risk Management A proactive
More informationChapter VI of the EURATOM Treaty
Chapter VI of the EURATOM Treaty Supply of Fuels and the Euratom Supply Agency Jussi Vihanta ESA, Head of Sector 30 April 2014 1 Summary 1 Mission of ESA - supply of fuels 2 Tools given to ESA to implement
More informationStatement on behalf of the Euratom Community
Statement on behalf of the Euratom Community Mr Massimo Garribba, Director, Directorate-General for Energy, European Commission 58 th General Conference of the IAEA Vienna, 22-26 September 2014 Mr President,
More informationOfficial Journal of the European Union L 330/31 COMMISSION
28.11.2006 Official Journal of the European Union L 330/31 COMMISSION COMMISSION RECOMMDATION of 24 October 2006 on the management of financial resources for the decommissioning of nuclear installations,
More informationOptimal Search for Parameters in Monte Carlo Simulation for Derivative Pricing
Optimal Search for Parameters in Monte Carlo Simulation for Derivative Pricing Prof. Chuan-Ju Wang Department of Computer Science University of Taipei Joint work with Prof. Ming-Yang Kao March 28, 2014
More informationVolatility estimation in Real Options with application to the oil and gas industry i
Volatility estimation in Real Options with application to the oil and gas industry i by Jenifer Piesse and Alexander Van de Putte Estimating volatility for use in financial options is a pretty straight
More informationNuclear Energy Agency. Costs of Decommissioning Nuclear Power Plants
Nuclear Energy Agency Costs of Decommissioning Nuclear Power Plants International Conference on Financing of Decommissioning Stockholm, Sweden 20-21 September 2016 Geoffrey Rothwell, PhD, Principal Economist
More informationLong term Plutonium management: Pre-consultation discussion paper covering decision methodology and timetable for decision making
Long term Plutonium management: Pre-consultation discussion paper covering decision methodology and timetable for decision making October 2009 URN 09D/735 CONTENTS Section 1: Introduction Section 2: Background
More informationSSC - Appendix A35. South Staffordshire Water PR19. Monte Carlo modelling of ODI RoRE. Issue 3 Final 29/08/18. South Staffordshire Water
Document Ti tle SSC - Appendix A35 South Staffordshire Water PR19 Monte Carlo modelling of ODI RoRE Issue 3 Final 29/08/18 South Staffordshire Water South Staffordshire Water PR19 Project No: B2342800
More informationAssessment in the Area of Economics. Pablo Florido MANAGING DIRECTOR FLORESTAN TECHNOLOGY ARGENTINA
Workshop on IAEA Tools for Nuclear Energy System Assessment (NESA) for Long Term Planning and Development (Technical Cooperation Project INT/4/142) July 20-23 23 2009, Vienna, Austria Assessment in the
More informationHaving regard to the Treaty establishing the European Atomic Energy Community, and in particular Articles 31 and 32 thereof,
L 219/42 COUNCIL DIRECTIVE 2014/87/EURATOM of 8 July 2014 amending Directive 2009/71/Euratom establishing a Community framework for the nuclear safety of nuclear installations THE COUNCIL OF THE EUROPEAN
More informationIntegrated Cost Schedule Risk Analysis Using the Risk Driver Approach
Integrated Cost Schedule Risk Analysis Using the Risk Driver Approach Qatar PMI Meeting February 19, 2014 David T. Hulett, Ph.D. Hulett & Associates, LLC 1 The Traditional 3-point Estimate of Activity
More informationStochastic Loss of Load Study for the 2011 Integrated Resource Plan
November 18, 2010 Stochastic Loss of Load Study for the 2011 Integrated Resource Plan INTRODUCTION PacifiCorp evaluates the desired level of capacity planning reserves for each integrated resource plan.
More informationPresented to: Eastern Idaho Chapter Project Management Institute. Presented by: Carl Lovell, PMP Contract and Technical Integration.
Project Risk Management Tutorial Presented to: Eastern Idaho Chapter Project Management Institute Presented by: Carl Lovell, PMP Contract and Technical Integration March 2009 Project Risk Definition An
More informationCouncil of the European Union Brussels, 31 March 2017 (OR. en) Mr Jeppe TRANHOLM-MIKKELSEN, Secretary-General of the Council of the European Union
Council of the European Union Brussels, 31 March 2017 (OR. en) Interinstitutional File: 2017/0036 (NLE) 7892/17 RECH 100 ATO 12 PROPOSAL From: date of receipt: 23 February 2017 To: No. Cion doc.: Secretary-General
More informationExcavation and haulage of rocks
Use of Value at Risk to assess economic risk of open pit slope designs by Frank J Lai, SAusIMM; Associate Professor William E Bamford, MAusIMM; Dr Samuel T S Yuen; Dr Tao Li, MAusIMM Introduction Excavation
More informationUncertainty in Economic Analysis
Risk and Uncertainty Uncertainty in Economic Analysis CE 215 28, Richard J. Nielsen We ve already mentioned that interest rates reflect the risk involved in an investment. Risk and uncertainty can affect
More informationexecutive summary ExEcuTivE SuMMAry
executive summary 1 British Energy was privatised in 1996. In 2002, the price of electricity fell and on 5 September 2002, the Company applied to the Department of Trade and Industry (the Department) for
More informationF19: Introduction to Monte Carlo simulations. Ebrahim Shayesteh
F19: Introduction to Monte Carlo simulations Ebrahim Shayesteh Introduction and repetition Agenda Monte Carlo methods: Background, Introduction, Motivation Example 1: Buffon s needle Simple Sampling Example
More informationCoping with Sequence Risk: How Variable Withdrawal and Annuitization Improve Retirement Outcomes
Coping with Sequence Risk: How Variable Withdrawal and Annuitization Improve Retirement Outcomes September 25, 2017 by Joe Tomlinson Both the level and the sequence of investment returns will have a big
More informationPickering Whole-Site Risk
Pickering Whole-Site Risk Jack Vecchiarelli Manager, Pickering Relicensing Update to Commission Members December 14, 2017 CMD 17-M64.1 Outline Background Whole-site risk considerations Use of Probabilistic
More information(RISK.03) Integrated Cost and Schedule Risk Analysis: A Draft AACE Recommended Practice. Dr. David T. Hulett
(RISK.03) Integrated Cost and Schedule Risk Analysis: A Draft AACE Recommended Practice Dr. David T. Hulett Author Biography David T. Hulett, Hulett & Associates, LLC Degree: Ph.D. University: Stanford
More informationParameter Sensitivities for Radionuclide Concentration Prediction in PRAME
Environment Report RL 07/05 Parameter Sensitivities for Radionuclide Concentration Prediction in PRAME The Centre for Environment, Fisheries and Aquaculture Science Lowestoft Laboratory Pakefield Road
More informationSpecified Generator Guidance
1. Introduction Specified Generator Guidance This guidance explains how to comply with the Specified Generator Regulations(here required by Schedule 25 B of Statutory Instrument 2018 No. 110 made 29 January
More informationChapter-8 Risk Management
Chapter-8 Risk Management 8.1 Concept of Risk Management Risk management is a proactive process that focuses on identifying risk events and developing strategies to respond and control risks. It is not
More informationEfficient Nested Simulation for CTE of Variable Annuities
Ou (Jessica) Dang jessica.dang@uwaterloo.ca Dept. Statistics and Actuarial Science University of Waterloo Efficient Nested Simulation for CTE of Variable Annuities Joint work with Dr. Mingbin (Ben) Feng
More informationMFE8812 Bond Portfolio Management
MFE8812 Bond Portfolio Management William C. H. Leon Nanyang Business School January 16, 2018 1 / 63 William C. H. Leon MFE8812 Bond Portfolio Management 1 Overview Value of Cash Flows Value of a Bond
More informationMining. LCC methodology application for equipment replacement strategy definition. Mineração. Abstract. 1. Introduction. 2. Material and method
http://dx.doi.org/10.1590/0370-44672018720141 Eduardo Cruvinel Kayashima 1,2 https://orcid.org/0000-0002-6377-5079 Ubirajara Marques Junior 1,3 https://orcid.org/0000-0002-5302-9451 1 CSN Mineração - Maintenance
More informationNUCLEAR NEW BUILD: INSIGHTS INTO FINANCING AND PROJECT MANAGEMENT. Dr. Jan Horst Keppler, Senior Economic Advisor NEA Nuclear Development Division
NUCLEAR NEW BUILD: INSIGHTS INTO FINANCING AND PROJECT MANAGEMENT Dr. Jan Horst Keppler, Senior Economic Advisor NEA Nuclear Development Division Context Results are based on study of the OECD Nuclear
More informationREFURBISHMENT AND NEW GENERATION NUCLEAR
Filed: 00--0 EB-00-00 Exhibit D Tab Page of 0 0 0 REFURBISHMENT AND NEW GENERATION NUCLEAR.0 PURPOSE The purpose of this evidence is to present an overview description of the nuclear plant refurbishment
More informationCOMPARISON OF NUCLEAR OUTAGE OM&A
Filed: 0-0- Page of 0 0 0 COMPARISON OF NUCLEAR OUTAGE OM&A.0 PURPOSE This evidence presents period-over-period comparisons of outage OM&A by station for 0-0 in support of the approval of OPG s forecast
More informationReal Options: Creating and Capturing the Option Value in Regulated Assets
STRATEGIC CONSULTING Energy Real Options: Creating and Capturing the Option Value in Regulated Assets White Paper The fundamental insight is recognizing that faced with uncertainty, flexibility has value.
More informationSIMULATION OF ELECTRICITY MARKETS
SIMULATION OF ELECTRICITY MARKETS MONTE CARLO METHODS Lectures 15-18 in EG2050 System Planning Mikael Amelin 1 COURSE OBJECTIVES To pass the course, the students should show that they are able to - apply
More informationNIPPON EXPORT AND INVESTMENT INSURANCE GUIDELINES FOR INFORMATION DISCLOSURE CONSIDERATIONS FOR NUCLEAR SECTOR PROJECTS IN TRADE INSURANCE
NIPPON EXPORT AND INVESTMENT INSURANCE GUIDELINES FOR INFORMATION DISCLOSURE CONSIDERATIONS FOR NUCLEAR SECTOR PROJECTS IN TRADE INSURANCE December, 2017 NIPPON EXPORT AND INVESTMENT INSURANCE (NEXI) GUIDELINES
More informationCollective Defined Contribution Plan Contest Model Overview
Collective Defined Contribution Plan Contest Model Overview This crowd-sourced contest seeks an answer to the question, What is the optimal investment strategy and risk-sharing policy that provides long-term
More informationCOUNCIL OF THE EUROPEAN UNION. Brussels, 4 June /14 Interinstitutional File: 2013/0340 (NLE) ATO 45
COUNCIL OF THE EUROPEAN UNION Brussels, 4 June 2014 10410/14 Interinstitutional File: 2013/0340 (NLE) ATO 45 NOTE from: General Secretariat of the Council to: Delegations No. Cion prop.: 15030/13 ATO 119
More informationGEEREF IMPACT METHODOLOGY
S I T I, U G A N D A ( F RO N T I E R ) GEEREF IMPACT METHODOLOGY L a s t u p d a t e : M a y 2 0 1 5 Frontier Investment Management INTRODUCTION The GEEREF team focuses on backing emerging investment
More informationd) Find the standard deviation of the random variable X.
Q 1: The number of students using Math lab per day is found in the distribution below. x 6 8 10 12 14 P(x) 0.15 0.3 0.35 0.1 0.1 a) Find the mean for this probability distribution. b) Find the variance
More informationNEWLANCER. The NEWLANCER project: towards a better integration of NMS potential in the SNETP Strategic Research Agenda
The NEWLANCER project: towards a better integration of NMS potential in the SNETP Strategic Research Agenda Daniela Diaconu On behalf of NEWLANCER Consortium 12/7/2011 SNETP General Assembly, Warsaw November
More informationConvention on Nuclear Safety 7 th Review Meeting 2017
Convention on Nuclear Safety 7 th Review Meeting 2017 International Atomic Energy Agency IAEA, Vienna Country Review Report for Luxembourg Drafted by Country Group 6 Republic of Korea, United Kingdom,
More informationProviding the competitiveness of nuclear energy in the implementation of. PRORYV project
1 98 Providing the competitiveness of nuclear energy in the implementation of PRORYV project D. Tolstoukhov 1 1 ITCP «PRORYV», Moscow, Russian Federation E-mail contact: tda@proryv2020.ru Abstract. In
More informationReport. by the Comptroller and Auditor General. Department for Business, Energy & Industrial Strategy. Hinkley Point C
Report by the Comptroller and Auditor General Department for Business, Energy & Industrial Strategy Hinkley Point C HC 40 SESSION 2017-18 23 JUNE 2017 4 Key facts Hinkley Point C Key facts 18bn estimated
More informationAACE International 48th Annual Meeting Washington, DC June 2004 DEVELOPING & MANAGING CONTIGENCY ON THE BASIS OF RISK. Robert Tichacek, P.E.
AACE International 48th Annual Meeting Washington, DC June 2004 DEVELOPING & MANAGING CONTIGENCY ON THE BASIS OF RISK Robert Tichacek, P.E. Presentation Outline Review of Basic Project Risk Management
More informationFundamentals of Project Risk Management
Fundamentals of Project Risk Management Introduction Change is a reality of projects and their environment. Uncertainty and Risk are two elements of the changing environment and due to their impact on
More informationQuantitative Retention Management for Life Insurers
Quantitative Retention Management for Life Insurers Kai Kaufhold, Ad Res Advanced Reinsurance Services GmbH 2016 SOA Life & Annuity Symposium, Nashville, TN May 16, 2016 Introducing the speaker Kai Kaufhold,
More informationIntegrated Cost-Schedule Risk Analysis Improves Cost Contingency Calculation ICEAA 2017 Workshop Portland OR June 6 9, 2017
Integrated Cost-Schedule Risk Analysis Improves Cost Contingency Calculation ICEAA 2017 Workshop Portland OR June 6 9, 2017 David T. Hulett, Ph.D., FAACE Hulett & Associates, LLC David.hulett@projectrisk
More informationMeasurement of contingent liabilities
Session 4 : Improving comparability and predictability through measurement Measurement of contingent liabilities Lerzan ÜLGENTÜRK lerzan.ulgenturk@hazine.gov.tr Turkish Treasury Pretoria, SA, December
More informationQuantitative Risk Analysis with Microsoft Project
Copyright Notice: Materials published by ProjectDecisions.org may not be published elsewhere without prior written consent of ProjectDecisions.org. Requests for permission to reproduce published materials
More informationClimate Action Reserve Forest Project Protocol Proposed Guidelines for Aggregation
Climate Action Reserve Forest Project Protocol Proposed Guidelines for Aggregation Table of Contents Introduction... 2 Proposed Aggregation Guidelines... 3 Eligible Project Types... 3 Number of Landowners...
More informationThe European Waste Directive: Gunnar Buckau, JRC-ITU
The European Waste Directive: Structure, Content and Implementation Guidance Operational Issues in Radioactive Waste Management and Nuclear Decommissioning Summer School September 2014, ISPRA The European
More informationESTIMATING ECONOMIC BENEFITS OF ALLOWING A FLEXIBLE WINDOW FOR MARYLAND PURCHASES OF SPONGE CRABS
ESTIMATING ECONOMIC BENEFITS OF ALLOWING A FLEXIBLE WINDOW FOR MARYLAND PURCHASES OF SPONGE CRABS Douglas Lipton Department of Agricultural & Resource Economics & Maryland Sea Grant Extension Program University
More informationEntergy s Spent Fuel Storage. What is the Litigation All About? How to Store Pilgrim s Spent Nuclear Fuel?
Entergy s Spent Fuel Storage What is the Litigation All About? Jim Lampert How to Store Pilgrim s Spent Nuclear Fuel? There are now 3300 spent fuel assemblies in the spent fuel pool every assembly Pilgrim
More informationPreprint: Will be published in Perm Winter School Financial Econometrics and Empirical Market Microstructure, Springer
STRESS-TESTING MODEL FOR CORPORATE BORROWER PORTFOLIOS. Preprint: Will be published in Perm Winter School Financial Econometrics and Empirical Market Microstructure, Springer Seleznev Vladimir Denis Surzhko,
More informationPOWERed by people. Investors Meeting 9M 2016 financial results Bucharest November 9, 2016
POWERed by people Investors Meeting 9M 2016 financial results Bucharest November 9, 2016 Nuclearelectrica - overview Company structure NUCLEARELECTRICA Executive Office Bucharest Cernavoda NPP Units 1&2
More informationHANDLING UNCERTAIN INFORMATION IN WHOLE LIFE COSTING - A COMPARATIVE STUDY
HANDLING UNCERTAIN INFORMATION IN WHOLE LIFE COSTING - A COMPARATIVE STUDY Mohammed Kishk, Assem Al-Hajj and Robert Pollock Scott Sutherland School, The Robert Gordon University, Aberdeen AB10 7QB, UK.
More informationELIA LFC Block Operational Agreement
ELIA LFC Block Operational Agreement Revision History V0.1 10.07.2018 ELIA s proposal for public consultation Disclaimer This document, provided by ELIA, is the draft for stakeholder consultation of the
More informationMeasuring and managing market risk June 2003
Page 1 of 8 Measuring and managing market risk June 2003 Investment management is largely concerned with risk management. In the management of the Petroleum Fund, considerable emphasis is therefore placed
More informationNuclear fuel supply in the Euratom Treaty: the role of the Euratom Supply Agency
Nuclear fuel supply in the Euratom Treaty: the role of the Euratom Supply Agency Dr Stamatios TSALAS ESA Director General Florence, June 2012 1 Summary 1 Mission of ESA 2 Tools given to ESA to implement
More informationSteering RWE through a challenging environment
Steering RWE through a challenging environment UniCredit German Investment Conference September 22, 2010 Dr. Bernhard Günther Chief Financial Officer, RWE Supply & Trading GmbH Dr. Stephan Lowis Vice President,
More informationNuclear Safeguards in the European Community - A Regional Approach
Nuclear Safeguards in the European Community - A Regional Approach by H.W. Schleicher INTRODUCTION Article III of the Non-Proliteration Treaty requires the application of IAEA safeguards to all non-nuclear
More informationReasoning with Uncertainty
Reasoning with Uncertainty Markov Decision Models Manfred Huber 2015 1 Markov Decision Process Models Markov models represent the behavior of a random process, including its internal state and the externally
More informationThe impact of different financing structures on investor risk. Marco Cometto OECD/NEA, Nuclear Development Division
The impact of different financing structures on investor risk Marco Cometto OECD/NEA, Nuclear Development Division General background Objectives More realistic model of the choices of a private investor,
More informationQuantitative Trading System For The E-mini S&P
AURORA PRO Aurora Pro Automated Trading System Aurora Pro v1.11 For TradeStation 9.1 August 2015 Quantitative Trading System For The E-mini S&P By Capital Evolution LLC Aurora Pro is a quantitative trading
More informationReview of Benchmark Infrastructure Costings. Presenter: Viraj Abeykoon
Review of Benchmark Infrastructure Costings Presenter: Viraj Abeykoon 24 July 2018 Disclaimer This presentation contains certain statements and projections provided by or on behalf of Cardno Limited with
More informationModelling the Sharpe ratio for investment strategies
Modelling the Sharpe ratio for investment strategies Group 6 Sako Arts 0776148 Rik Coenders 0777004 Stefan Luijten 0783116 Ivo van Heck 0775551 Rik Hagelaars 0789883 Stephan van Driel 0858182 Ellen Cardinaels
More informationTITLE IV NUCLEAR MATTERS Subtitle A Price-Anderson Act Amendments
REDLINE OF CHAIRMAN S MARK 0 SEC. 0. SHORT TITLE. TITLE IV NUCLEAR MATTERS Subtitle A Price-Anderson Act Amendments This subtitle may be cited as the Price-Anderson Amendments Act of 00. SEC. 0. EXTENSION
More informationLEAVING THE EU THE EURATOM TREATY PART 2: A FRAMEWORK FOR THE FUTURE
LEAVING THE EU THE EURATOM TREATY PART 2: A FRAMEWORK FOR THE FUTURE The nuclear industry is facing huge uncertainties, as the UK leaves the Euratom Treaty at the same time as the European Union. No amendment
More informationDecision Support Models 2012/2013
Risk Analysis Decision Support Models 2012/2013 Bibliography: Goodwin, P. and Wright, G. (2003) Decision Analysis for Management Judgment, John Wiley and Sons (chapter 7) Clemen, R.T. and Reilly, T. (2003).
More informationProbabilistic Benefit Cost Ratio A Case Study
Australasian Transport Research Forum 2015 Proceedings 30 September - 2 October 2015, Sydney, Australia Publication website: http://www.atrf.info/papers/index.aspx Probabilistic Benefit Cost Ratio A Case
More informationLET S GET REAL! Managing Strategic Investment in an Uncertain World: A Real Options Approach by Roger A. Morin, PhD
LET S GET REAL! Managing Strategic Investment in an Uncertain World: A Real Options Approach by Roger A. Morin, PhD Robinson Economic Forecasting Conference J. Mack Robinson College of Business, Georgia
More informationSPO PLANNING ANALYSIS 2015 ENO IRP. Updates for the Final IRP SEPTEMBER 18, 2015
SPO PLANNING ANALYSIS 2015 ENO IRP Updates for the Final IRP SEPTEMBER 18, 2015 INTRODUCTION OBJECTIVES The following topics will be discussed: Effects of Union Reallocation on ENO Supply Plan Supply Role
More informationMohammed Rafiuddin CEO and General Manager, BIOSI Biohazards Solutions Innovators
Mohammed Rafiuddin CEO and General Manager, BIOSI Biohazards Solutions Innovators Profile of Mohammed Rafiuddin Mohammed is an active member of AACE International since 2006 with 30 years of experience
More informationEuratom FP7 ( /13) in Geological Disposal. DG RTD (Research and Innovation) Unit K4 Nuclear Fission Christophe Davies
Euratom FP7 (2007-2011/13) in Geological Disposal DG RTD (Research and Innovation) Unit K4 Nuclear Fission Christophe Davies OVERVIEW 1. European Union Directive on Radioactive Waste 2. Projects funded
More informationYOU TO KNOW NEED INDUSTRY AVERAGES
INDUSTRY AVERAGES YOU NEED TO KNOW A list of the 12 industry averages that have the BIGGEST impact on the success and growth of mental health practices. YOU CAN T CONTROL WHAT YOU CAN T MEASURE Your bottom
More informationPresented by Kristina Narvaez President & CEO ERM Strategies, LLC
Presented by Kristina Narvaez President & CEO ERM Strategies, LLC www.erm-strategies.com Regulations to Support Value Creation Sarbanes Oxley 2002 NYSE 2004 SEC 33-9089 Dodd Frank Section 165 Part C S
More informationRenewable Energy Guidance
NewClimate Institute, Verra Renewable Energy Guidance Guidance for assessing the greenhouse gas impacts of renewable energy policies May 2018 How to describe the policy or action being assessed 5. DESCRIBING
More informationEuropean Joint Programme in Radioactive Waste Management
Euratom Treaty, 1957 European Joint Programme in Radioactive Waste Management JOPRAD programme document workshop, London, 04 April 2017 DG Research and Innovation Unit G4 Fission Energy Christophe Davies
More informationEuratom research and training programme under Horizon-2020
European Nuclear Young Generation Forum 2015 (dedicated to Nuclear and Environment / http://enygf2015.org/) Cité des Sciences et de l Industrie, Paris, La Villette / 22-26 June 2015 organised by the European
More information