Akbar Jazayeri Vice President, Regulatory Operations Southern California Edison Company P O Box 800 Rosemead, CA 91770
|
|
- Esther Carson
- 5 years ago
- Views:
Transcription
1 STATE OF CALIFORNIA PUBLIC UTILITIES COMMISSION SAN FRANCISCO, CA Edmund G. Brown Jr. Governor February 1, 2012 Advice Letter 2677-E Akbar Jazayeri Vice President, Regulatory Operations Southern California Edison Company P O Box 800 Rosemead, CA Subject: Modification to SCE Company s Preliminary Statement, Part U, California Solar Initiative Program Balancing Account Dear Mr. Jazayeri: Advice Letter 2677-E is effective December 20, Sincerely, Edward F. Randolph, Director Energy Division
2 Akbar Jazayeri Vice President of Regulatory Operations December 20, 2011 ADVICE 2677-E (U 338-E) PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION SUBJECT: Modification to Southern California Edison Company s Preliminary Statement, Part U, California Solar Initiative Program Balancing Account Southern Califonia Edison Company (SCE) hereby submits for filing the following modification to its Preliminary Statement, Part U, California Solar Initiative Program Balancing Account (CSIPBA), listed on Attachment A and attached hereto. PURPOSE The purpose of this advice letter is to modify SCE s Preliminary Statement, Part U, CSIPBA, pursuant to Ordering Paragraph (OP) 2 of the California Public Utilities Commission s (Commission s) Decision (D.) , which modified the California Solar Initiative (CSI) revenue requirement. BACKGROUND On September 22, 2011, Senate Bill (SB) 585 was approved by the Governor and declared to take effect immediately as an urgency statute to address a CSI budget shortfall, which resulted from higher than anticipated performance-based incentive (PBI) payments to systems that qualified for PBI. SB 585 increased the limit on the total cost of CSI Program by $200 million, required the use of accumulated interest from customer collections prior to collecting additional funds from customers, and set the discount rate used for PBI payments at 4 percent. In implementing SB 585, the Commission issued D , Decision Modifying California Solar Initiative Budget, Revenue Requirement and Performance Based Incentives as Adopted in Decision (D.) , D and D The Commission modified the revenue requirement for each utility in light of the $200 million budget increase allowed by SB 585 based on current budget shortfalls and funding needs in each utility service territory. P.O. Box Walnut Grove Ave. Rosemead, California (626) Fax (626)
3 ADVICE 2677-E (U 338-E) December 20, 2011 PROPOSED TARIFF CHANGES In compliance with OP 2 of D , SCE modifies its Preliminary Statement Part U, CSIPBA, as follows: Year Amount* Transfer from SGPICMA on 12/31/2006 $104.6 million 2007 $147.0 million 2008 $147.0 million 2009 $ 0.0 million 2010 $110.0 million 2011 $110.0 million 2012 $110.0 million 2013 $ 74.0 million 2014 $ 74.0 million 2015 $ 82.0 million 2016 $ 81.1 million Interest/Forfeited Funds $ 17.9 million TOTAL $1,057.6 million SCE notes that the Energy Division, pursuant to OP 5 of D , is to monitor interest and forfeited funds in the CSIPBA and may annually propose changes to the CSI revenue requirement for Commission s consideration. TIER DESIGNATION Pursuant to General Order (GO) 96-B, Energy Industry Rule 5.1, this advice letter is submitted with a Tier 1 designation. EFFECTIVE DATE This advice filing will become effective on December 20, 2011, the same date as filed. NOTICE Anyone wishing to protest this advice filing may do so by letter via U.S. Mail, facsimile, or electronically, any of which must be received no later than 20 days after the date of this advice filing. Protests should be mailed to: CPUC, Energy Division Attention: Tariff Unit 505 Van Ness Avenue San Francisco, California jnj@cpuc.ca.gov and mas@cpuc.ca.gov Copies should also be mailed to the attention of the Director, Energy Division, Room 4004 (same address above).
4 ADVICE 2677-E (U 338-E) December 20, 2011 In addition, protests and all other correspondence regarding this advice letter should also be sent by letter and transmitted via facsimile or electronically to the attention of: Akbar Jazayeri Vice President of Regulatory Operations Southern California Edison Company 2244 Walnut Grove Avenue Rosemead, California Facsimile: (626) AdviceTariffManager@sce.com Leslie E. Starck Senior Vice President c/o Karyn Gansecki Southern California Edison Company 601 Van Ness Avenue, Suite 2030 San Francisco, California Facsimile: (415) Karyn.Gansecki@sce.com There are no restrictions on who may file a protest, but the protest shall set forth specifically the grounds upon which it is based and shall be submitted expeditiously. In accordance with Section 4 of GO 96-B, SCE is serving copies of this advice filing to the interested parties shown on the attached GO 96-B and R service lists. Address change requests to the GO 96-B service list should be directed by electronic mail to AdviceTariffManager@sce.com or at (626) For changes to all other service lists, please contact the Commission s Process Office at (415) or by electronic mail at Process_Office@cpuc.ca.gov. Further, in accordance with Public Utilities Code Section 491, notice to the public is hereby given by filing and keeping the advice filing at SCE s corporate headquarters. To view other SCE advice letters filed with the Commission, log on to SCE s web site at For questions, please contact Jill Holmes at (626) or by electronic mail at Jill.Holmes@sce.com. Southern California Edison Company AJ:jh:sq Enclosures Akbar Jazayeri
5 CALIFORNIA PUBLIC UTILITIES COMMISSION ADVICE LETTER FILING SUMMARY ENERGY UTILITY MUST BE COMPLETED BY UTILITY (Attach additional pages as needed) Company name/cpuc Utility No.: Southern California Edison Company (U 338-E) Utility type: Contact Person: James Yee ELC GAS Phone #: (626) PLC HEAT WATER Disposition Notice to: EXPLANATION OF UTILITY TYPE ELC = Electric GAS = Gas PLC = Pipeline HEAT = Heat WATER = Water (Date Filed/ Received Stamp by CPUC) Advice Letter (AL) #: 2677-E Tier Designation: 1 Subject of AL: Modification to Southern California Edison Company s Preliminary Statement, Part U, California Solar Initiative Program Balancing Account Keywords (choose from CPUC listing): Compliance, Balancing Account AL filing type: Monthly Quarterly Annual One-Time Other If AL filed in compliance with a Commission order, indicate relevant Decision/Resolution #: D Does AL replace a withdrawn or rejected AL? If so, identify the prior AL: Summarize differences between the AL and the prior withdrawn or rejected AL 1 : Confidential treatment requested? Yes No If yes, specification of confidential information: Confidential information will be made available to appropriate parties who execute a nondisclosure agreement. Name and contact information to request nondisclosure agreement/access to confidential information: Resolution Required? Yes No Requested effective date: 12/20/11 No. of tariff sheets: -5- Estimated system annual revenue effect: (%): Estimated system average rate effect (%): When rates are affected by AL, include attachment in AL showing average rate effects on customer classes (residential, small commercial, large C/I, agricultural, lighting). Tariff schedules affected: Service affected and changes proposed 1 : Pending advice letters that revise the same tariff sheets: Preliminary Statement Part U and Table of Contents None 1 Discuss in AL if more space is needed.
6 Protests and all other correspondence regarding this AL are due no later than 20 days after the date of this filing, unless otherwise authorized by the Commission, and shall be sent to: CPUC, Energy Division Attention: Tariff Unit 505 Van Ness Ave., San Francisco, CA and Akbar Jazayeri Vice President of Regulatory Operations Southern California Edison Company 2244 Walnut Grove Avenue Rosemead, California Facsimile: (626) Leslie E. Starck Senior Vice President c/o Karyn Gansecki Southern California Edison Company 601 Van Ness Avenue, Suite 2030 San Francisco, California Facsimile: (415)
7 Public Utilities Commission 2677-E Attachment A Cal. P.U.C. Sheet No. Title of Sheet Cancelling Cal. P.U.C. Sheet No. Revised E Preliminary Statement Part U Revised E Revised E Preliminary Statement Part U Revised E Revised E Preliminary Statement Part U Revised E Revised E Table of Contents Revised E Revised E Table of Contents Revised E 1
8 Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No E PRELIMINARY STATEMENT Sheet 1 U. California Solar Initiative Program Balancing Account (CSIPBA) 1. The purpose of the CSIPBA is to track the recorded incremental California Solar Initiative (CSI) program costs and authorized distribution revenue requirement recorded in the Base Revenue Requirement Balancing Account (BRRBA) associated with the CSI program authorized in Decision (D.) , D , D , D , D and D The CSIPBA will separately track in the Performance Based Incentives (PBI) sub-account the forecast PBI payment amounts for all completed solar projects receiving PBI to ensure fund security for the duration of the PBI contract incentive periods. Definitions a. Authorized Annual Funding Levels for CSI Program per D : Year Transfer from SGPICMA on 12/31/2006 Amount* $ million 2007 $ million 2008 $ million 2009 $ 0.0 million 2010 $ million 2011 $ million 2012 $ million 2013 $ 74.0 million 2014 $ 74.0 million 2015 $ 82.0 million 2016 $ 81.1 million Interest/Forfeited Funds $ 17.9 million Total $1,057.6 million *In accordance with Conclusion of Law 8 of D , in cases where funding is or would be exhausted before the end of the funding cycle and following consultation with the Commission and the California Energy Commission (CEC) staffs, the Administrative Law Judge (ALJ) assigned to Rulemaking (R) or its successor proceeding, in consultation with the Assigned Commissioner, may increase the current period s funding by up to 15% of the budget allocated to the subsequent funding period by directing the utilities to use the subsequent period s allocated funds. In accordance with Ordering Paragraph 5 of D , the Energy Division shall monitor interest and forfeited funds in the CSIPBA and may propose changes to the CSI authorized revenues on an annual basis for Commission consideration. (I) (I) (N) (N) (N) (N) (To be inserted by utility) Issued by (To be inserted by Cal. PUC) Advice 2677-E Akbar Jazayeri Date Filed Dec 20, 2011 Decision Vice President Effective Dec 20, H22 Resolution
9 Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No E PRELIMINARY STATEMENT Sheet 2 U. California Solar Initiative Program Balancing Account (CSIPBA) 2. Definitions b. PBI Program In accordance with the rules established by the Commission for the CSI Program, SCE will pay (PBI) to 1) qualifying solar energy systems equal to or greater than 100 kilowatts in size, 2) any size system that elects to receive a CSI incentive through the PBI mechanism, and 3) any size system using building integrated technology. PBI payments will be made monthly based on recorded kilowatt hours (kwh) of solar power produced over a five-year period. PBI payments will be prorated for systems that exceed 1 megawatt (MW) in size by prorating the output of the system based on the ratio of 1 MW to the size of the facility. As an alternative, and if possible, the customer may, at its election and cost, separately meter a 1 MW element of a larger solar energy system. The PBI incentive rate is confirmed when a solar energy system project receives a confirmed reservation, and will remain constant for the five-year term. The PBI rate may vary by utility service area, depending upon the pace of solar demand in each utility s service territory. Please refer to SCE s website ( to determine the currently effective incentive rate. 3. Effective Date The Effective Date of the CSIPBA is January 1, Interest Rate The Interest Rate shall be the most recent annual interest rate on Commercial Paper (prime, three months), published in the Federal Reserve Statistical Release, H.15. Should publication of the interest rate on Commercial Paper (prime, three months) be discontinued, interest shall accrue at the rate of the most recent annual interest rate on Commercial Paper that most closely approximates the rate that was discontinued, and which is published in the Federal Reserve Statistical Release H.15, or its successor publication. (To be inserted by utility) Issued by (To be inserted by Cal. PUC) Advice 2677-E Akbar Jazayeri Date Filed Dec 20, 2011 Decision Vice President Effective Dec 20, C16 Resolution
10 Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No E PRELIMINARY STATEMENT Sheet 3 U. California Solar Initiative Program Balancing Account (CSIPBA) 5. Operation of the CSIPBA Monthly entries to the CSIPBA shall be determined as follows: a. A credit entry to record 1/12 th of the CSI Program Authorized Annual Funding Level as defined in Section 2.a. above. b. A debit entry to transfer forecast five-year expected PBI payment amounts for all completed PBI contracted solar projects from the CSIP Authorized Annual Funding Level to the PBI sub-account. c. A debit entry to reflect the actual incremental program costs associated with the CSI Program excluding the actual PBI payment amounts associated with the CSI Program; In addition, an initial, one-time transfer of the recorded December 31, 2006 balance in the Solar Self-Generation Incentive Component Subaccount of the SGPIC Memorandum Account, if any, shall be made to the CSIPBA. Monthly entries to the PBI sub-account shall be determined as follows: a. A credit transferred from the CSIPBA Authorized Annual Funding Level to reserve expected PBI payment amounts for all completed PBI contracted solar projects. b. A debit entry to reflect the actual PBI payment amounts associated with the CSI Program. Any under-collection or over-collection recorded in a month may be carried over from month-to month over the duration of the CSI Program. Interest Expense shall be calculated annually by applying the Interest Rate to the average balance of the beginning-of-year and the end-of-year balances in the CSIPBA inclusive of the PBI sub-account. Since the CSIPBA is a one-way balancing account, Interest Expense shall only be calculated when the average balance in the CSIPBA is a negative (under-expended) amount. 6. Disposition of the CSIPBA Balances The Company may request disposition of over-collected balances recorded in the CSIPBA in an April Energy Resource Recovery Account (ERRA) Application, or any other proceeding authorized by the Commission. (To be inserted by utility) Issued by (To be inserted by Cal. PUC) Advice 2677-E Akbar Jazayeri Date Filed Dec 20, 2011 Decision Vice President Effective Dec 20, H21 Resolution
11 Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No E TABLE OF CONTENTS Sheet 1 Cal. P.U.C. Sheet No. TITLE PAGE E TABLE OF CONTENTS - RATE SCHEDULES E E TABLE OF CONTENTS - LIST OF CONTRACTS AND DEVIATIONS E TABLE OF CONTENTS - RULES E TABLE OF CONTENTS - INDEX OF COMMUNITIES, MAPS, BOUNDARY DESCRIPTIONS E TABLE OF CONTENTS - SAMPLE FORMS E E PRELIMINARY STATEMENT: A. Territory Served E B. Description of Service E C. Procedure to Obtain Service E D. Establishment of Credit and Deposits E E. General E F. Symbols E G. Gross Revenue Sharing Mechanism E E H. Baseline Service E I. Advanced Metering Infrastructure Balancing Account E J. Palo Verde Balancing Account E K. Nuclear Decommissioning Adjustment Mechanism E L. Purchase Agreement Administrative Costs Balancing Account E M. Income Tax Component of Contributions E N. Memorandum Accounts E E E E E E E O. California Alternate Rates for Energy (CARE) Adjustment Clause E E P. Optional Pricing Adjustment Clause (OPAC) E (To be inserted by utility) Issued by (To be inserted by Cal. PUC) Advice 2677-E Akbar Jazayeri Date Filed Dec 20, 2011 Decision Vice President Effective Dec 20, H7 Resolution
12 Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No E TABLE OF CONTENTS Sheet 2 PRELIMINARY STATEMENT: Cal. P.U.C. Sheet No. Q. Demand Side Management Adjustment Clause E E R. NOT IN USE E S. Procurement Energy Efficiency Balancing Account E T. Electric and Magnetic Fields Measurement Program E U. California Solar Initiative Program Balancing Account E V. Hazardous Substance Cleanup Cost Recovery Mechanism E E W. Departing Load and Customer Generation Departing Load Cost Responsibility E E X. Research, Development and Demonstration Adjustment Clause E Y. Demand Response Program Balancing Account E E Z. Songs 2&3 Steam Generator Replacement Balancing Account E E AA. California Alternate Rates for Energy (CARE) Balancing Account E BB. PBR Distribution Revenue Requirement Adjustment Factor E CC. PBR Distribution Performance Mechanism E E E DD. Cost Of Capital Trigger Mechanism E EE. Electric Deferred Refund Account E FF. Public Purpose Programs Adjustment Mechanism E E GG. Energy Efficiency Program Adjustment Mechanism E HH. Low Income Energy Efficiency Program Adjustment Mechanism E II. Bond Charge Balancing Account E JJ. Direct Access Cost Responsibility Surcharge Tracking Account E KK. NOT IN USE...-E LL. Reliability Investment Incentive Mechanism E MM. Community Choice Aggregation Balancing Account E NN. Mohave Balancing Account E OO. Pension Costs Balancing Account E PP. Post Employment Benefits Other Than Pensions Costs Balancing Account E QQ. Edison SmartConnect Balancing Account E (To be inserted by utility) Issued by (To be inserted by Cal. PUC) Advice 2677-E Akbar Jazayeri Date Filed Dec 20, 2011 Decision Vice President Effective Dec 20, H7 Resolution
Advice Letters 3072-E and 3072-E-A
STATE OF CALIFORNIA PUBLIC UTILITIES COMMISSION SAN FRANCISCO, CA 94102-3298 Edmund G. Brown Jr., Governor August 19, 2014 Advice Letters 3072-E and 3072-E-A Megan Scott-Kakures Vice President, Regulatory
More informationAkbar Jazayeri Vice President, Regulatory Operations Southern California Edison Company P O Box 800 Rosemead, CA 91770
STATE OF CALIFORNIA PUBLIC UTILITIES COMMISSION SAN FRANCISCO, CA 94102-3298 Edmund G. Brown Jr. Governor March 5, 2012 Advice Letter 2692-E Akbar Jazayeri Vice President, Regulatory Operations P O Box
More informationSUBJECT: Establishment of the Distribution Resources Plan Demonstration Balancing Account (DRPDBA) Pursuant to Decision
STATE OF CALIFORNIA Edmund G. Brown Jr., Governor PUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3298 June 2, 2017 Advice Letter 3579-E Russell G. Worden Director, State Regulatory
More informationDecember 14, Modifications to Regulatory Mechanisms Established in Accordance with Decision and Decision
Akbar Jazayeri Director of Revenue and Tariffs December 14, 2005 ADVICE 1940-E (U 338-E) PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION SUBJECT: Modifications to Regulatory Mechanisms
More informationSUBJECT: Establishment of the Avoided Cost Calculator Memorandum Account in Compliance with Decision
STATE OF CALIFORNIA Edmund G. Brown Jr., Governor PUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3298 June 13, 2017 Advice Letter 3566-E Russell G. Worden Director, State Regulatory
More informationJanuary 31, 2006 ADVICE 1960-E (U 338-E) PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION
Akbar Jazayeri Director of Revenue and Tariffs January 31, 2006 ADVICE 1960-E (U 338-E) PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION SUBJECT: Statewide Pricing Pilot Advanced
More informationSeptember 22, Advice Letter 3033-E
STATE OF CALIFORNIA PUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3298 Edmund G. Brown Jr., Governor September 22, 2014 Advice Letter 3033-E Megan Scott-Kakures Vice President,
More informationSUBJECT: Establishment of Demand Response Load Shift Working Group Memorandum Account in Compliance with Decision
STATE OF CALIFORNIA Edmund G. Brown Jr., Governor PUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3298 February 23, 2018 Advice Letter 3729-E Russell G. Worden Director, State Regulatory
More informationMarch 17, 2008 Advice Letter 2211-E
STATE OF CALIFORNIA ARNOLD SCHWARZENEGGER, Governor PUBLIC UTILITIES COMMISSION SAN FRANCISCO, CA 94102-3298 March 17, 2008 Advice Letter 2211-E Akbar Jazayeri Vice President, Regulatory Operations Southern
More informationDecember 11, 2006 PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION
Akbar Jazayeri Vice President, Revenue and Tariffs December 11, 2006 ADVICE 2072-E (U 338-E) PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION SUBJECT: Revision to the Base Revenue
More informationSUBJECT: Modification of the Distribution Resources Plan Memorandum Account Pursuant to Decision
STATE OF CALIFORNIA Edmund G. Brown Jr., Governor PUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3298 April 13, 2018 Advice Letter 3764-E Russell G. Worden Director, State Regulatory
More informationNovember 14, 2005 ADVICE 1929-E (U 338-E) PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION
Akbar Jazayeri Director of Revenue and Tariffs November 14, 2005 ADVICE 1929-E (U 338-E) PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION SUBJECT: Disconnection Notice, Past Due Utility
More informationAkbar Jazayeri Vice President, Regulatory Operations Southern California Edison Company P O Box 800 Rosemead, CA 91770
STATE OF CALIFORNIA ARNOLD SCHWARZENEGGER, Governor PUBLIC UTILITIES COMMISSION SAN FRANCISCO, CA 94102-3298 December 27, 2010 Advice Letter 2427-E Akbar Jazayeri Vice President, Regulatory Operations
More informationSUBJECT: Establishment of the Aliso Canyon Energy Savings Assistance Program Memorandum Account in Response to the Aliso Canyon Emergency
STATE OF CALIFORNIA Edmund G. Brown Jr., Governor PUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3298 June 20, 2016 Advice Letter: 3413-E Russell G. Worden Managing Director, State
More informationJanuary 26, Advice Letter 3721-E
STATE OF CALIFORNIA Edmund G. Brown Jr., Governor PUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3298 January 26, 2018 Advice Letter 3721-E Russell G. Worden Director, State Regulatory
More informationApril 8, 2005 PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION. Revision to the Energy Resource Recovery Account
Akbar Jazayeri Director of Revenue and Tariffs April 8, 2005 ADVICE 1884-E (U 338-E) PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION SUBJECT: Revision to the Energy Resource Recovery
More informationOctober 26, 2017 Advice Letter 3665-E
STATE OF CALIFORNIA PUBLIC UTILITIES COMMISSION SAN FRANCISCO, CA 94102-3298 Edmund G. Brown Jr., Governor October 26, 2017 Advice Letter 3665-E Russell G. Worden Director, Regulatory Operations Southern
More informationJanuary 31, 2003 PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION
Akbar Jazayeri Director of Revenue and Tariffs January 31, 2003 ADVICE 1682-E (U 338-E) PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION SUBJECT: Year 2003 Refund Plan For December
More informationSUBJECT: Establishment of the Transportation Electrification Portfolio Balancing Account Pursuant to D
STATE OF CALIFORNIA Edmund G. Brown Jr., Governor PUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3298 February 26, 2018 Advice Letter 3734-E Russell G. Worden Director, State Regulatory
More informationMay 17, 2002 PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION
Akbar Jazayeri Director of Revenue and Tariffs May 17, 2002 ADVICE 1622-E (U 338-E) PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION SUBJECT: Implementation of the Capital Additions
More informationJune 11, 2018 Advice Letter 3803-E. SUBJECT: Qualified Nuclear Trust Investment Management Agreement with NISA Investment Advisors, LLC
STATE OF CALIFORNIA Edmund G. Brown Jr., Governor PUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3298 June 11, 2018 Advice Letter 3803-E Russell G. Worden Director, State Regulatory
More informationMarch 15, Advice Letter 3543-E
STATE OF CALIFORNIA Edmund G. Brown Jr., Governor PUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3298 March 15, 2017 Advice Letter 3543-E Director, State Regulatory Operations
More informationMay 25, Revisions to Southern California Edison s Critical Peak Pricing Programs for Large Customers with Demands Above 200 kw
Akbar Jazayeri Director of Revenue and Tariffs May 25, 2005 ADVICE 1895-E (U 338-E) PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION SUBJECT: Revisions to Southern California Edison
More informationMarch 1, 2013 Advice Letter 2841-E
STATE OF CALIFORNIA PUBLIC UTILITIES COMMISSION SAN FRANCISCO, CA 94102-3298 Edmund G. Brown Jr. Governor March 1, 2013 Advice Letter 2841-E Akbar Jazayeri Vice President, Regulatory Operations Southern
More informationJune 10, 2005 PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION
Akbar Jazayeri Director of Revenue and Tariffs June 10, 2005 ADVICE 1896-E (U 338-E) PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION SUBJECT: Establishment of Application for California
More informationSeptember 5, 2006 PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION
Akbar Jazayeri Vice President, Revenue and Tariffs September 5, 2006 ADVICE 2039-E (U 338-E) PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION SUBJECT: Request for an Amendment to
More informationSUBJECT: SCEs Request for Cancellation of Plug Load and Appliances (PLA) Subprogram - Appliance Recycling Program (ARP)
STATE OF CALIFORNIA Edmund G. Brown Jr., Governor PUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3298 March 8, 2016 Advice Letter 3365-E Russell G. Worden Director, State Regulatory
More informationSUBJECT: Request for an Amendment to SCE's Bundled Procurement Plan Appendix D.
STATE OF CALIFORNIA Edmund G. Brown Jr., Governor PUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3298 November 14, 2017 Advice Letter 3673-E Russell G. Worden Director, State Regulatory
More informationFebruary 19, Revisions to SCE s 2008 Santa Catalina Island Water Revenue Requirement
Akbar Jazayeri Vice President of Regulatory Operations February 19, 2008 ADVICE 62-W (U 338-W) PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA WATER DIVISION SUBJECT: Revisions to SCE s 2008 Santa
More informationApril 29, Southern California Edison Company 2244 Walnut Grove Avenue Rosemead, CA Dear Ms. Megan Scott-Kakures,
STATE OF CALIFORNIA PUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3298 EDMUND G. BROWN JR., Governor April 29, 2014 Southern California Edison Company 2244 Walnut Grove Avenue
More informationADVICE LETTER (AL) SUSPENSION NOTICE ENERGY DIVISION
ADVICE LETTER (AL) SUSPENSION NOTICE ENERGY DIVISION Utility Name: Southern California Edison Utility Number/Type: U 338-E AL Number(s):3620-E/3620-E-A/3620-E-B Date AL(s) Filed: 6/16/17, 7/28/17, 9/11/17
More informationFebruary 4, 2003 PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION
Akbar Jazayeri Director of Revenue and Tariffs February 4, 2003 ADVICE 1683-E (U 338-E) PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION SUBJECT: Tariff Revisions Necessary to Implement
More informationJanuary 29, 2018 Advice Letter 5133-G
STATE OF CALIFORNIA Edmund G. Brown Jr., Governor PUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3298 January 29, 2018 Advice Letter 5133-G Ronald van der Leeden Director, Regulatory
More informationFeburary 28, 2006 PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION
Akbar Jazayeri Director of Revenue and Tariffs Feburary 28, 2006 ADVICE 1972-E PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION SUBJECT: Employee Safety and Distribution Reliability
More informationRussell G. Worden Director, Regulatory Operations Southern California Edison Company 8631 Rush Street Rosemead, CA 91770
;STATE OF CALIFORNIA PUBLIC UTILITIES COMMISSION SAN FRANCISCO, CA 94102-3298 Edmund G. Brown Jr., Governor November 13, 2015 Advice Letter 3219-E and 3219-E-A Russell G. Worden Director, Regulatory Operations
More informationADVICE LETTER (AL) SUSPENSION NOTICE ENERGY DIVISION
ADVICE LETTER (AL) SUSPENSION NOTICE ENERGY DIVISION Utility Name: SCE Utility Number/Type: U338-E Advice Letter Number(s) 3214-E Date AL(s) Filed) 5/1/15 Utility Contact Person: Darrah Morgan Utility
More informationSeptember 25, 2002 PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION
Akbar Jazayeri Director of Revenue and Tariffs September 25, 2002 ADVICE 1652-E (U 338-E) PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION SUBJECT: Establishment of CARE Ratemaking
More informationApril 4, 2014 Advice Letter 4616-G
STATE OF CALIFORNIA PUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3298 Edmund G. Brown Jr., Governor April 4, 2014 Advice Letter 4616-G Rasha Prince, Director Regulatory Affairs
More informationADVICE LETTER (AL) SUSPENSION NOTICE ENERGY DIVISION
ADVICE LETTER (AL) SUSPENSION NOTICE ENERGY DIVISION Utility Name: Southern California Edison Utility No./Type: U 338-E Advice Letter No.: 3743-E Date Utility Notified: March 9, 2018 via: email [X] E-Mailto:
More informationMarch 13, Advice Letter 218-G/3730-E
STATE OF CALIFORNIA Edmund G. Brown Jr., Governor PUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3298 March 13, 2018 Advice Letter 218-G/3730-E Russell G. Worden Director, State
More informationJuly 9, Advice Letters: 3050-E
STATE OF CALIFORNIA Edmund G. Brown Jr., Governor PUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3298 July 9, 2014 Advice Letters: 3050-E Megan Scott-Kakures Vice President, Regulatory
More informationSubject: Core Pricing Flexibility and Noncore Competitive Load Growth Opportunities Programs
Ronald van der Leeden Director Regulatory Affairs 555 W. Fifth Street, GT14D6 Los Angeles, CA 90013-1011 Tel: 213.244.2009 Fax: 213.244.4957 RvanderLeeden@semprautilities April 29, 2016 Advice No. 4961
More informationJune 8, 2001 PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION. Restatement of the Transition Cost Balancing Account
Akbar Jazayeri Director of Revenue and Tariffs June 8, 2001 ADVICE 1535-E-A (U 338-E) PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION SUBJECT: Restatement of the Transition Cost
More informationJuly 17, 2013 Advice Letter 4504
STATE OF CALIFORNIA Edmund G. Brown Jr., Governor PUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3298 July 17, 2013 Advice Letter 4504 Rasha Prince, Director Regulatory Affairs
More informationDecember 11, 2003 PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION
Akbar Jazayeri Director of Revenue and Tariffs December 11, 2003 ADVICE 1717-E-A (U 338-E) PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION SUBJECT: Tariff Modifications Associated
More informationEnclosed are copies of the following revised tariff sheets for the utility s files:
STATE OF CALIFORNIA PUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3298 EDMUND G. BROWN JR., Governor May 11, 2018 Gary A. Stern, Ph.D. Managing Director, State Regulatory Operations
More informationNovember 16, Advice Letter 5178-A
STATE OF CALIFORNIA PUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3298 November 16, 2017 Ronald van der Leeden Director, Regulatory Affairs Southern California Gas 555 W. Fifth
More informationDecember 5, Advice No (U 904 G) Public Utilities Commission of the State of California
Ronald van der Leeden Director Regulatory Affairs 555 W. Fifth Street, GT14D6 Los Angeles, CA 90013-1011 Tel: 213.244.2009 Fax: 213.244.4957 RvanderLeeden@semprautilities.com December 5, 2017 Advice No.
More informationDecember 14, 2016 Advice Letter 5053
lstate OF CALIFORNIA PUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3298 Edmund G. Brown Jr., Governor December 14, 2016 Advice Letter 5053 Ronald van der Leeden Director, Regulatory
More informationFebruary 26, 2018 Advice Letter 3926-G/5214-E
STATE OF CALIFORNIA PUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3298 EDMUND G. BROWN JR., Governor February 26, 2018 Advice Letter 3926-G/5214-E Erik Jacobson Director, Regulatory
More informationSeptember 22, Establishment of Southern California Edison Company s Credit/Debit Card Bill Payment Option
Akbar Jazayeri Vice President of Regulatory Operations September 22, 2008 ADVICE 67-W (U 338-W) PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA WATER DIVISION SUBJECT: Establishment of Southern
More informationSeptember 16, 2015 Advice Letter 4845
STATE OF CALIFORNIA PUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3298 Edmund G. Brown Jr., Governor September 16, 2015 Advice Letter 4845 Ronald van der Leeden Director, Regulatory
More informationMarch 7, 2018 Advice Letter 5234-G. SUBJECT: Modification of the New Environmental Regulation Balancing Account (NERBA).
STATE OF CALIFORNIA Edmund G. Brown Jr., Governor PUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3298 March 7, 2018 Advice Letter 5234-G Ray B. Ortiz Southern California Gas Company
More informationApril 3, Megan Scott-Kakures Vice President, Regulatory Operations Southern California Edison Company 8631 Rush Street Rosemead, CA 91770
STATE OF CALIFORNIA PUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3298 EDMUND G. BROWN JR., Governor April 3, 2015 Megan Scott-Kakures Vice President, Regulatory Operations Southern
More informationDecember 23, 1998 PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION
Donald A. Fellows, Jr. Manager of Revenue and Tariffs December 23, 1998 ADVICE 1359-E (U 338-E) PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION SUBJECT: Revisions to Preliminary
More informationJune 5, Advice No (U 904 G) Public Utilities Commission of the State of California. Subject: Schedule No. G-CPS May 2018 Cash-Out Rates
Ronald van der Leeden Director Regulatory Affairs 555 W. Fifth Street, GT14D6 Los Angeles, CA 90013-1011 Tel: 213.244.2009 Fax: 213.244.4957 RvanderLeeden@semprautilities.com June 5, 2018 Advice No. 5305
More informationJanuary 12, 2017 Advice Letter 5070
lstate OF CALIFORNIA PUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3298 Edmund G. Brown Jr., Governor January 12, 2017 Advice Letter 5070 Ronald van der Leeden Director, Regulatory
More informationJuly 1, 2015 Advice Letter: 4814-G. Advice Letter 4814-G is effective as of June 29, 2015 with corresponding Tariffs effective as of July 1, 2015.
STATE OF CALIFORNIA EDMUND G. BROWN JR., Governor PUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3298 July 1, 2015 Advice Letter: 4814-G Southern California Gas Company Attention:
More informationSouthern California Edison IEC (Corp ID 6096) Status of Advice Letter 128 As of January 21, Disposition: Effective Date: Accepted
STATE OF CALIFORNIA EDMUND G. BROWN JR., Governor PUBLIC UTILITIES COMMISSION 505 Van Ness Avenue San Francisco CA 94102-3298 Southern California Edison IEC (Corp ID 6096) Status of Advice Letter 128 As
More informationrequest for approval of Telecommunication leases between SCEC and MCImetro access transmission services LLC pursuant to GO 173 Accepted
STATE OF CALIFORNIA EDMUND G. BROWN JR., Governor PUBLIC UTILITIES COMMISSION 505 Van Ness Avenue San Francisco CA 94102-3298 Southern California Edison IEC (Corp ID 6096) Status of Advice Letter 130 As
More informationADVICE LETTER SUMMARY ENERGY UTILITY
ADVICE LETTER SUMMARY ENERGY UTILITY MUST BE COMPLETED BY UTILITY (Attach additional pages as needed) Company name/cpuc Utility No.: Liberty Utilities (CalPeco Electric) LLC (U-933-E) Utility type: Contact
More informationAkbar Jazayeri Vice President, Regulatory Operations Southern California Edison Company P O Box 800 Rosemead, CA 91770
STATE OF CALIFORNIA PUBLIC UTILITIES COMMISSION SAN FRANCISCO, CA 94102-3298 Edmund G. Brown Jr. Governor May 31, 2011 Advice Letter 2550-E Akbar Jazayeri Vice President, Regulatory Operations Southern
More informationAugust 15, 2017 Advice Letter 5167-G
STATE OF CALIFORNIA Edmund G. Brown Jr., Governor PUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3298 August 15, 2017 Advice Letter 5167-G Ronald van der Leeden Director, Regulatory
More informationSUBJECT: System-wide Curtailment Effective February 20, 2018 through March 6, 2018.
STATE OF CALIFORNIA Edmund G. Brown Jr., Governor PUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3298 June 15, 2018 Advice Letter 5267-G Ronald van der Leeden Director, Regulatory
More informationFebruary 1, 2018 Advice Letter 5233-G. SUBJECT: Revision of Gas Preliminary Statements to Implement New Accounting Guidance Principles
STATE OF CALIFORIA Edmund G. Brown Jr., Governor PUBLIC UTILITIES COMMISSIO 505 VA ESS AVEUE SA FRACISCO, CA 94102-3298 February 1, 2018 Advice Letter 5233-G Ronald van der Leeden Director, Regulatory
More informationCALIFORNIA PUBLIC UTILITIES COMMISSION
CALIFORNIA PUBLIC UTILITIES COMMISSION ADVICE LETTER FILING SUMMARY ENERGY UTILITY MUST BE COMPLETED BY UTILITY (Attach additional pages as needed) Company name/cpuc Utility No.: California Pacific Electric
More informationApril 11, 2001 PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION
Donald A. Fellows, Jr. Manager of Revenue and Tariffs April 11, 2001 ADVICE 1532-E (U 338-E) PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION SUBJECT: Revenue Requirement for SCE
More informationNovember 20, Advice Letter: 3014-E
STATE OF CALIFORNIA Edmund G. Brown Jr., Governor PUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3298 November 20, 2014 Advice Letter: 3014-E Megan Scott-Kakures Vice President,
More informationSUBJECT: Deviation to SCE's Added Facilities Agreement - Applicant Financed (Form ) for Fort Irwin
STATE OF CALIFORNIA Edmund G. Brown Jr., Governor PUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3298 October 9, 2014 Advice Letter 3100-E Megan Scott-Kakures Vice President, Regulatory
More informationNovember 22, 2002 PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION. Implementation of the Energy Resource Recovery Account
Akbar Jazayeri Director of Revenue and Tariffs November 22, 2002 ADVICE 1665-E (U 338-E) PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION SUBJECT: Implementation of the Energy Resource
More informationJanuary 22, Establishment of Smart Energy Program and Modification of Summer Discount Plan in Compliance with Decision
Russell G. Worden Managing Director, State Regulatory Operations January 22, 2018 ADVICE 3731-E (U 338-E) PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION SUBJECT: Establishment of
More informationCALIFORNIA PUBLIC UTILITIES COMMISSION
CALIFORNIA PUBLIC UTILITIES COMMISSION ADVICE LETTER FILING SUMMARY ENERGY UTILITY MUST BE COMPLETED BY UTILITY (Attach additional pages as needed) Company name/cpuc Utility No. California Pacific Electric
More informationApril 11, 2001 PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION
Donald A. Fellows, Jr. Manager of Revenue and Tariffs April 11, 2001 ADVICE 1534-E (U 338-E) PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION SUBJECT: Establishment of Four New Balancing
More informationCALIFORNIA PUBLIC UTILITIES COMMISSION
CALIFORNIA PUBLIC UTILITIES COMMISSION ADVICE LETTER FILING SUMMARY ENERGY UTILITY MUST BE COMPLETED BY LSE (Attach additional pages as needed) Company name/cpuc Utility No. Liberty Utilities (CalPeco
More informationADVICE LETTER (AL) SUSPENSION NOTICE ENERGY DIVISION
ADVICE LETTER (AL) SUSPENSION NOTICE ENERGY DIVISION Utility Name: SCE Utility Number/Type: U 338-E Advice Letter Number(s): 3660-E Date AL(s) Filed: September 25, 2017 Utility Contact Person: Darrah Morgan
More informationJune 30, 2015 ADVICE 3241-E (U 338-E) PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION
Russell G. Worden Managing Director, State Regulatory Operations June 30, 2015 ADVICE 3241-E (U 338-E) PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION SUBJECT: Establishment of New
More informationAkbar Jazayeri Vice President, Regulatory Operations Southern California Edison Company P O Box 800 Rosemead, CA 91770
STATE OF CALIFORNIA PUBLIC UTILITIES COMMISSION SAN FRANCISCO, CA 94102-3298 Edmund G. Brown Jr. Governor June 5, 2012 Advice Letter 2684-E Akbar Jazayeri Vice President, Regulatory Operations Southern
More informationJuly 19, 2002 PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION
Director of Revenue and Tariffs July 19, 2002 (U 338-E) PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION SUBJECT: Implementation of Affiliate Transaction Rules With Respect to a New
More informationJuly 31, 2001 PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION
Akbar Jazayeri Director of Revenue and Tariffs July 31, 2001 ADVICE 1567-E (U 338-E) PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION SUBJECT: Addition of the Gibson Environmental,
More informationNovember 14, 2014 Advice Letters: 4582-G 4582-G-A. SUBJECT: Establishment of Rule No. 43, OBR Tariff in Compliance with D.
STATE OF CALIFORNIA Edmund G. Brown Jr., Governor PUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3298 November 14, 2014 Advice Letters: 4582-G 4582-G-A Rasha Prince, Director Regulatory
More informationMay 16, Newly Designed Bill Format and Establishment of an Optional Simplified Bill Format
Akbar Jazayeri Vice President, Revenue and Tariffs May 16, 2007 ADVICE 139-G (U 338-E) PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION SUBJECT: Newly Designed Bill Format and Establishment
More informationJuly 7, 2015 Advice Letters: 4668-G & 4718-G. SUBJECT: Request for Approval of Interruptible Transportation Capacity Contracts with Affiliates
STATE OF CALIFORNIA EDMUND G. BROWN JR., Governor PUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3298 July 7, 2015 Advice Letters: 4668-G & 4718-G Southern California Gas Company
More informationAkbar Jazayeri Vice President, Regulatory Operations Southern California Edison Company P O Box 800 Rosemead, CA 91770
STATE OF CALIFORNIA PUBLIC UTILITIES COMMISSION SAN FRANCISCO, CA 94102-3298 Edmund G. Brown Jr. Governor July 9, 2012 Advice Letter 2696-E Akbar Jazayeri Vice President, Regulatory Operations Southern
More informationApril 20, 2001 PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION
Donald A. Fellows, Jr. Manager of Revenue and Tariffs April 20, 2001 ADVICE 1534-E-A (U 338-E) PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION SUBJECT: Establishment of Four New
More informationSouthern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.
Southern California Edison Revised Cal. PUC Sheet No. 49319-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 46179-E PRELIMINARY STATEMENT Sheet 1 1. Purpose The purpose of the Public
More informationPublic Utilities Commission of the State of California. Subject: Capital Audit Consultant Cost Memorandum Account (CACCMA)
January 30, 2001 ADVICE 2291-G/2077-E (Pacific Gas and Electric Company ID U 39 M) Public Utilities Commission of the State of California Subject: Capital Audit Consultant Cost Memorandum Account (CACCMA)
More informationMay 30, Advice Letter 3444-E
STATE OF CALIFORNIA Edmund G. Brown Jr., Governor PUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3298 May 30, 2017 Advice Letter 3444-E Russell G. Worden Director, State Regulatory
More informationSouthern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.
Southern California Edison Revised Cal. PUC Sheet No. 62547-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 57088-E APPLICABILITY Schedule CCA-INFO Sheet 1 Applicable to Community
More informationOctober 5, 2017 Advice Letter 3488-E
STATE OF CALIFORNIA PUBLIC UTILITIES COMMISSION SAN FRANCISCO, CA 94102-3298 REVISED Edmund G. Brown Jr., Governor October 5, 2017 Advice Letter 3488-E Russell G. Worden Director, Regulatory Operations
More informationOctober 30, Advice 2839-E-A (Pacific Gas and Electric Company U 39 E) Public Utilities Commission of the State of California
Brian K. Cherry Vice President Regulatory Relations 77 Beale Street, Room 1087 San Francisco, CA 94105 Mailing Address Mail Code B10C Pacific Gas and Electric Company P.O. Box 770000 San Francisco, CA
More informationMarch 30, 2000 ADVICE 2225-G/1983-E. Public Utilities Commission of the State of California
ADVICE 2225-G/1983-E Public Utilities Commission of the State of California Pacific Gas and Electric Company (PG&E) hereby submits for filing revisions to its gas and electric tariff sheets. The affected
More informationJuly 20, 2018 Advice Letter 3681-E/3681-E-A
STATE OF CALIFORNIA Edmund G. Brown Jr., Governor PUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3298 July 20, 2018 Advice Letter 3681-E/3681-E-A Russell G. Worden Director, State
More informationAdvice 2746-E December 9, 2005 TABLE I. Input Values For Revised FTA Charges
Advice 2746-E - 2 - December 9, 2005 TABLE I Input Values For Revised FTA Charges Residential Customers Eligible Small Commercial Customers Monthly MWh sales: December 2005 2,788,777 757,582 January 2006
More informationSubject: PG&E s Authorization for Financial Hedging Memorandum Account
September 15, 2003 Advice 2482-G/2420-E (Pacific Gas and Electric Company ID U 39 M) Subject: PG&E s Authorization for Financial Hedging Memorandum Account Pacific Gas and Electric Company (PG&E) hereby
More informationDecember 3, 2009 Advice Letter 2369-E
STATE OF CALIFORNIA ARNOLD SCHWARZENEGGER, Governor PUBLIC UTILITIES COMMISSION SAN FRANCISCO, CA 94102-3298 December 3, 2009 Advice Letter 2369-E Akbar Jazayeri Vice President, Regulatory Operations Southern
More informationAkbar Jazayeri Vice President, Regulatory Operations Southern California Edison Company P O Box 800 Rosemead, CA 91770
STATE OF CALIFORNIA ARNOLD SCHWARZENEGGER, Governor PUBLIC UTILITIES COMMISSION SAN FRANCISCO, CA 94102-3298 April 21, 2010 Advice Letter 160-G/2401-E Akbar Jazayeri Vice President, Regulatory Operations
More informationAugust 11, Supplemental Filing to Advice 3088-E, Establishment of the Mobilehome Park Conversion Program in Compliance with Decision
Megan Scott-Kakures Vice President, Regulatory Operations August 11, 2014 ADVICE 3088-E-A (U 338-E) PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION SUBJECT: Supplemental Filing to
More informationCALIFORNIA PUBLIC UTILITIES COMMISSION
CALIFORNIA PUBLIC UTILITIES COMMISSION ADVICE LETTER FILING SUMMARY ENERGY UTILITY MUST BE COMPLETED BY LSE (Attach additional pages as needed) Company name/cpuc Utility No. Liberty Utilities (CalPeco
More informationSouthern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.
Southern California Edison Revised Cal. PUC Sheet No. 56089-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 56203-E PRELIMINARY STATEMENT Sheet 2 N. MEMORANDUM ACCOUNTS 2. Definitions.
More informationAkbar Jazayeri Vice President, Regulatory Operations Southern California Edison Company P O Box 800 Rosemead, CA 91770
STATE OF CALIFORNIA PUBLIC UTILITIES COMMISSION SAN FRANCISCO, CA 94102-3298 Edmund G. Brown Jr. Governor February 1, 2012 Advice Letter 2675-E Akbar Jazayeri Vice President, Regulatory Operations Southern
More information