Presented herewith is my proposed Capital Improvement Program for fiscal years beginning July 1, 2018 and ending June 30, 2023.

Size: px
Start display at page:

Download "Presented herewith is my proposed Capital Improvement Program for fiscal years beginning July 1, 2018 and ending June 30, 2023."

Transcription

1 WICOMICO COUNTY, MARYLAND OFFICE OF THE COUNTY EXECUTIVE P.O. BOX 870 SALISBURY, MARYLAND FAX: Bob Culver R. Wayne Strausburg County Executive Director of Administration December 5, 2017 The Honorable County Council Wicomico County Maryland Salisbury, Maryland Presented herewith is my proposed Capital Improvement Program for fiscal years beginning July 1, 2018 and ending June 30, The five year Capital Improvement Program is an important tool that assists Wicomico County in its longrange financial and public works plans. Each year, the program is reviewed and priorities are reevaluated. Often new projects that have become matters of higher priority are added. The first year of the program will be considered as the Capital Improvement Budget. It is this portion which receives the closest scrutiny and for which funding decisions are made. The remaining years serve as a guide and an indicator of what future capital requirements are likely to be, their cost and probable sources of funding. That part of the Capital Budget requiring County funds may come from current revenues, prior fund balances, grants and the proceeds from the sale of General Obligation Bonds. In order to receive the maximum favorable interest rate, the County must pledge the County's full faith and credit to servicing the bonded debt, subject to Charter restrictions. A Capital, by its definition in Section 702C of the County Charter, "...shall mean (1) the building or purchase of any physical public betterment or improvement or any preliminary studies and surveys relative thereto; (2) the acquisition of property of a Wicomico County Celebrating 150 Years

2 permanent nature for public use; and (3) the purchase of equipment for any public betterment or improvement when first erected or acquired. The term shall not include any public betterment or improvement, the acquisition of any real property or the purchase of any equipment, if the total cost and expense thereof is to be paid out of the proceeds of the succeeding year's taxes, nor shall the term include the resurfacing of any road". The outstanding principal balance of all indebtedness for Capital Budgets from previous years that were funded through the sale of bonds is referred to as the General Obligation Indebtedness. As of June 30, 2017, this amount totaled $119,746,720. The County s total debt limitation is established by Section 313 of the County Charter. This section limits borrowing for any period in excess of twelve months to an amount in aggregate of no more than 3.2 percent of the County real property assessable base plus 8% of the County personal property assessable base at the time of issuance. As the County's assessable base changes, the County s borrowing capacity also changes within the limits set by law. As of June 30, 2017, the County s borrowing capacity was $219,929,984. Thus, the outstanding debt of $ 119,746,720, subject to debt limitation, represents 54.4% percent of total capacity. General Obligation Public Improvement Bonds are being sold in fiscal year 2018 (December 12, 2017) in the amount of $9,800,000; of that amount, $8,108,000 for School s, $600,000 for Public Safety, $92,000 for GOB Phone System and $1,000,000 for Public Works projects. As a result, the General Obligation indebtedness of Wicomico County on June 30, 2018 will be approximately $118.6 million. Based on the 2018 estimated values of Real Property and Personal Property, this indebtedness would represent 53% of the allowable debt limit. The County has adopted a policy goal that would keep the percentage of debt service payment, (principal and interest (P&I) for governmental activities) to less than 12% of the total general fund estimated new revenue, if possible. The $15.4 million in principal and interest payments required for debt service in fiscal year 2018 is 11.5 percent of the fiscal year 2018 budgeted new revenue. The Capital Improvement Budget recommends a bond sale in the fall of calendar year 2018 (FY19) in the amount of $10,504,500 (new debt, no refunding) and $7,260,291 from General Fund Paygo. Of that Paygo amount, $3,050,000 is for reinvestment into the Salisbury Ocean City Wicomico Airport either for funding or forwardfunding of projects to enhance the Airport s appeal. In 2018, the County will be retiring $10,937,223. Management has made a conscientious effort to only borrow equal or less than the amount of Principal that is being retired within the calendar year. In an effort to make the CIP easier to understand and to also provide more detail, the CIP is being submitted in a new format for the FY19 FY23 planning cycle. The format is broken into two sections. The first section of the CIP summarizes the project costs and funding sources which includes a Summary of Costs and and Lists of the s by their Funding Source. The second half of the CIP has the Requests by Department. This includes a Summary of each Department s s and detailed sheets on each project. If there are dollar values in the fiscal year 2019 column, the project is being recommended for funding in fiscal year If there are amounts shown in the columns for years , the project is being programmed for funding in those years. It is important to remember that once a project is started, the funding shown in the future years will have to be available. If approved and

3

4 CAPITAL IMPROVEMENTS PLAN And 2019 CAPITAL BUDGET Submitted December 5, 2017 Bob Culver County Executive

5 WICOMICO COUNTY, MARYLAND FY2019 FY 2023 CAPITAL IMPROVEMENTS PLAN CONTENTS Summary s Costs and 1 5 Costs and 1 By Funding Source General Fund "Paygo" / Bonds / To Be Determined 2 By Funding Source Enterprise Funds 4 By Funding Source State and Federal Grants / Other 5 Requests by Department General Services Department Summary of Costs and 6 Health Dept Hurdle Basement Floor Improvements 7 Health Dept Fritz Building Roof Replacement/HVAC 8 Nursing Home PTAC Unit Replacement 9 Extension Services Facility Roof Replacement 10 Circuit Court Complex Remodeling and Renovations 11 NCH AC Unit Replacement Controls Upgrade 12 GOB Roof Replacement 13 County Sheriff Department Summary of Costs and 14 Public Safety Building 15 Dept of Corrections Department Summary of Costs and 16 HVAC Controls Upgrade/ Hot H2O Valve Replacement 17 Roof Replacement continued from FY18 18 Inmate Shower Restoration continued from FY18 19 Dept of Public Works Departments 24, 50 and Summary of Costs and 20 Dept of Public Works Department Chesapeake Bay WIP 22 Water & Sewer Master Plan 23 Airport Water Main Extension 24 Dept of Public Works Roads Division Department Anderson Mill Pond Dam Rehabilitation 25 Bear Swamp Bridge Replacement 26 Dry Storage Building 27 Hobbs Road at Beaver Dam Creek 28 Riverside Drive at Hunting Park 29 Westside Collector Phase 3 30 Dept of Public Works Solid Waste Division Department Civic Center Recycling Center Design & Relocation 31 Landfill Scale & Scale House Replacement 32 Landfill Drainage Revision Plan 33 Convenience Center Improvements 34 Landfill Cell 7 Construction 35

6 Board of Education Department Summary of Costs and 36 WCBOE FY 2019 ity List WorWic Community College Department Summary of Costs and 38 New Academic Building Public Library Department Summary of Costs and 40 Renovate Lower Level Bathrooms 41 Renovate Lower Level Meeting Rooms 42 Renovate Lower Level Reflooring 43 Pittsville Branch Library Public Health Department Summary of Costs and 45 Upgrade Back Up / Replace Fiber Backbone Switch 46 Hurdle Building Replace Carpet 47 Fritz Building Replace Tile Floors 48 Hurdle Building Replace Tile 49 Fritz Building Replace Carpet SalisburyOcean CityWicomico Airport Department Summary of Costs and 51 STARS and ADSB Equipment 52 ARFF (Aircraft Rescue and Fire Fighting) Station 53 Taxilane C Apron and Corporate Hangar Ramp 54 Rehab Access Control System 55 Snow Removal Equipment (SRE) Building 56 Drone Facility Design and Site 57 Air Traffic Control Tower Equipment 58 Runway 14/32 Extension 59 Taxiway A Rehabiliation 60 Land Acquisition for Runway 14 Runway Protection Zone (RPZ) 61 Air Carrier Terminal Rehabiliation (30% Design in 2013) 62 Replace Condemned Corporate 3 rows of T Hangars (38,000 sq ft Hangar) 63 FEMA/Cargo Joint Use Distribution Center 64 Taxi F Extension and Apron Recreation, Parks & Tourism Departments 60, 61 and Summary of Costs and Wicomico Youth & Civic Center Department Exterior Metal 67 Elevator / Escalator Replacement 68 Midway HVAC Replacement 69

7 Recreation and Parks Department Cedar Hill Cabins & Bathroom Renovation 70 Pirate's Wharf Master Plan & Development 71 Playground Equipment 72 Tennis and Basketball Court Restoration 73 Harmon Field Fencing 74 AWP Stadium Boiler Replacement 75 AWP Stadium Modernization continued project 76 Roaring Point Park Break Waters 77 Cove Road Beach Access 78 Cedar Hill Harbor Restoration 79

8 SUMMARY WICOMICO COUNTY, MARYLAND FY2019 FY2023 CAPITAL IMPROVEMENTS PLAN CAPITAL PROJECT COSTS Departments FY 2019 FY 2020 FY 2021 FY 2022 FY Year '19 '23 Contingency $ 200,000 $ 200,000 $ 200,000 $ 200,000 $ 200,000 $ 1,000,000 $ 1,000,000 Dept of Corrections $ 841,291 $ 411,667 $ 1,252,958 $ 677,492 $ 1,930,450 Dept of Public Works Engineering $ 4,330,924 $ 200,000 $ 200,000 $ 200,000 $ 200,000 $ 5,130,924 $ 1,142,000 $ 6,272,924 Dept of Public Works Roads Division $ 325,000 $ 950,000 $ 2,250,000 $ 3,525,000 $ 50,000 $ 3,575,000 Dept of Public Works Solid Waste Division $ 650,000 $ 305,000 $ 160,000 $ 5,750,000 $ 50,000 $ 6,915,000 $ 6,915,000 General Services $ 2,015,000 $ 758,100 $ 2,773,100 $ 1,750,000 $ 4,523,100 Public Health $ 41,000 $ 247,000 $ 150,000 $ 150,000 $ 200,000 $ 788,000 $ 788,000 SalisburyOcean CityWicomico Airport $ 8,815,135 $ 52,750,000 $ 7,450,000 $ 69,015,135 $ 984,865 $ 70,000,000 Wicomico County Board of Education $ 17,047,000 $ 2,250,000 $ 19,297,000 $ 2,876,000 $ 22,173,000 Wicomico County Public Library $ 25,000 $ 450,000 $ 400,000 $ 4,000,000 $ 4,875,000 $ 4,875,000 Wicomico County Recreation, Parks & Tourism $ 2,314,000 $ 1,390,000 $ 765,000 $ 235,000 $ 4,704,000 $ 3,790,000 $ 8,494,000 Wicomico County Sheriff $ 5,189,500 $ 5,189,500 $ 10,379,000 $ 725,000 $ 11,104,000 WorWic Community College $ 2,748,670 $ 31,727,345 $ 1,252,260 $ 35,728,275 $ 35,728,275 Capital Costs $ 41,793,850 $ 65,101,267 $ 14,323,670 $ 42,262,345 $ 1,902,260 $ 165,383,392 $ 11,995,357 $ 177,378,749 CAPITAL PROJECT FUNDING SOURCES General Obligation Bond Proceeds (New Money) $ 10,504,500 $ 8,189,500 $ 2,050,000 $ 2,700,000 $ 200,000 $ 23,644,000 $ 6,493,000 $ 30,137,000 General Obligation Bond Proceeds (Old Money) $ 2,250,000 $ 2,250,000 $ 2,250,000 General Fund "PayGo" $ 7,260,291 $ 4,144,767 $ 1,676,500 $ 463,500 $ 400,000 $ 13,945,058 $ 2,730,492 $ 16,675,550 County Enterprise Funds 1,476,284 $ 4,873,500 $ 292,500 $ 5,750,000 $ 50,000 $ 12,442,284 $ 163,716 $ 12,606,000 Education BOE and WorWic State Funding $ 9,682,000 $ 2,061,503 $ 23,795,509 $ 939,195 $ 36,478,207 $ 36,478,207 State Grant $ 5,295,775 $ 4,108,500 $ 371,000 $ 1,621,500 $ 11,396,775 $ 1,946,149 $ 13,342,924 Federal Grant $ 4,275,000 $ 36,585,000 $ 2,385,000 $ 43,245,000 $ 270,000 $ 43,515,000 Other $ 1,050,000 $ 7,200,000 $ 5,000,928 $ 2,319,269 $ 91,540 $ 15,661,737 $ 392,000 $ 16,053,737 To Be Determined $ 486,239 $ 5,612,567 $ 221,525 $ 6,320,331 $ 6,320,331 $ 41,793,850 $ 65,101,267 $ 14,323,670 $ 42,262,345 $ 1,902,260 $ 165,383,392 $ 11,995,357 $ 177,378,749 1

9 General Obligation Bond Proceeds (New Money) General Obligation Bond Proceeds (Old Money) General Fund "PayGo" To Be Determined Department s by Funding Source General Fund "Paygo" / Bonds / To Be Determined Number FY 19 FY 20 FY 21 FY 22 FY 23 General Services Health Dept Hurdle Basement Floor Improvements $ 160,000 $ 210,000 $ 370,000 General Services Health Dept Fritz Building Roof Replacement/HVAC $ 262,600 $ 262,600 General Services Nursing Home PTAC Unit Replacement $ 450,000 $ 450,000 General Services Extension Services Facility Roof Replacement $ 125,000 $ 125,000 General Services Circuit Court Complex Remodeling and Renovations $ 800,000 $ 800,000 General Services NCH AC Unit Replacement Controls Upgrade $ 480,000 $ 480,000 General Services GOB Roof Replacement $ 285,500 $ 285,500 Wicomico County Sheriff Public Safety Building $ 5,189,500 $ 5,189,500 $ 10,379,000 Dept of Corrections HVAC Controls Upgrade/ Hot H2O Valve Replacement $ 163,800 $ 163,800 Dept of Corrections Roof Replacement continued from FY $ 411,666 $ 411,667 $ 823,333 Dept of Corrections Inmate Shower Restoration continued from FY $ 265,825 $ 265,825 Dept of Public Works Engineering Chesapeake Bay WIP $ 200,000 $ 200,000 $ 200,000 $ 200,000 $ 200,000 $ 1,000,000 Dept of Public Works Engineering Water & Sewer Master Plan $ 300,000 $ 300,000 Wicomico County BOE ity #1 Delmar Elementary $ 852,000 $ 852,000 Wicomico County BOE ity #2 Beaver Run Study / Planning $ 2,250,000 $ 2,250,000 $ 4,500,000 Wicomico County BOE ity #3 Glen Avenue $ 331,000 $ 331,000 Wicomico County BOE ity #4 Pinehurst Elementary Roof $ 154,000 $ 154,000 Wicomico County BOE ity #8 Fruitland Primary $ 75,000 $ 75,000 Wicomico County BOE ity #9 Pinehurst Elementary Retrofit $ 1,047,000 $ 1,047,000 Wicomico County BOE ity #10 Mardela HS $ 1,216,000 $ 1,216,000 Wicomico County BOE ity #12 Stadium $ 490,000 $ 490,000 Wicomico County BOE ity #13 Wicomico HS Auditorium $ 500,000 $ 500,000 Wicomico County BOE ity #14 Parkside Auditorium $ 450,000 $ 450,000 WorWic Community College New Academic Building $ 486,239 $ 5,612,567 $ 221,525 $ 6,320,331 Wicomico County Public Library Renovate Lower Level Bathrooms $ 175,000 $ 175,000 Wicomico County Public Library Renovate Lower Level Meeting Rooms $ 25,000 $ 25,000 Wicomico County Public Library Renovate Lower Level Reflooring $ 275,000 $ 275,000 Wicomico County Public Library Pittsville Branch Library $ 400,000 $ 2,500,000 $ 2,900,000 Public Health Upgrade Back Up / Replace Fiber Backbone Switch $ 41,000 $ 41,000 Public Health Hurdle Building Replace Carpet $ 247,000 $ 247,000 Public Health Fritz Building Replace Tile Floors $ 150,000 $ 150,000 Public Health Hurdle Building Replace Tile 150,000 $ 150,000 $ 2 5Year '19 '23

10 Public Health Fritz Building Replace Carpet $ 200,000 $ 200,000 Dept of Public Works Roads Division Anderson Mill Pond Dam Rehabilitation $ 50,000 $ 350,000 $ 400,000 Dept of Public Works Roads Division Bear Swamp Bridge Replacement $ 165,000 $ 165,000 Dept of Public Works Roads Division Dry Storage Building $ 160,000 $ 160,000 Dept of Public Works Roads Division Hobbs Beaver Dam Creek $ 400,000 $ 400,000 Dept of Public Works Roads Division Riverside Hunting Park $ 400,000 $ 400,000 Dept of Public Works Roads Division Westside Collector Phase 3 $ 500,000 $ 1,500,000 $ 2,000,000 SalisburyOcean CityWicomico Airport STARS and ADSB Equipment $ 600,000 $ 600,000 SalisburyOcean CityWicomico Airport ARFF (Aircraft Rescue and Fire Fighting) Station $ 900,000 $ 900,000 SalisburyOcean CityWicomico Airport Taxilane C Apron and Corp Hangar Ramp $ 750,000 $ 750,000 SalisburyOcean CityWicomico Airport Rehab Access Control System $ 500,000 $ 500,000 SalisburyOcean CityWicomico Airport Snow Removal Equipment (SRE) Building $ 50,000 $ 150,000 $ 200,000 SalisburyOcean CityWicomico Airport Drone Facility Design and Site $ 750,000 $ 750,000 Wicomico County Recreation, Parks & Tourism WY&CC Exterior Metal $ 250,000 $ 250,000 Wicomico County Recreation, Parks & Tourism WY&CC Elevator / Escalators $ 450,000 $ 450,000 Wicomico County Recreation, Parks & Tourism WY&CC Midway HVAC Replacement $ 400,000 $ 400,000 Wicomico County Recreation, Parks & Tourism Cedar Hill Cabins & Bathroom Renovation $ 60,000 $ 60,000 Wicomico County Recreation, Parks & Tourism Pirate's Wharf Master Plan & Development $ 100,000 $ 350,000 $ 450,000 Wicomico County Recreation, Parks & Tourism Playground Equipment $ 25,000 $ 11,000 $ 16,500 $ 52,500 Wicomico County Recreation, Parks & Tourism Tennis and Basketball Court Restoration $ 28,000 $ 14,000 $ 10,000 $ 13,500 $ 65,500 Wicomico County Recreation, Parks & Tourism Harmon Field Fencing $ 3,000 $ 3,000 Wicomico County Recreation, Parks & Tourism AWP Boiler Replacement $ 200,000 $ 100,000 $ 100,000 $ 400,000 Contingency Contingency $ 200,000 $ 200,000 $ 200,000 $ 200,000 $ 200,000 $ 1,000,000 $ 20,014,791 $ 12,334,267 $ 4,212,739 $ 8,776,067 $ 821,525 $ 46,159,389 GENERAL FUND / BOND PROJECT FUNDING SOURCES General Obligation Bond Proceeds (New Money) $ 10,504,500 $ 8,189,500 $ 2,050,000 $ 2,700,000 $ 200,000 $ 23,644,000 General Obligation Bond Proceeds (Old Money) $ 2,250,000 $ 2,250,000 General Fund "PayGo" $ 7,260,291 $ 4,144,767 $ 1,676,500 $ 463,500 $ 400,000 $ 13,945,058 To Be Determined $ 486,239 $ 5,612,567 $ 221,525 $ 6,320,331 $ 20,014,791 $ 12,334,267 $ 4,212,739 $ 8,776,067 $ 821,525 $ 46,159,389 3

11 s by Funding Source Enterprise Funds Department Number FY 19 FY 20 FY 21 FY 22 FY 23 5Year '19 '23 SalisburyOcean CityWicomico Airport Air Traffic Control Tower Equipment $ 103,784 $ 103,784 SalisburyOcean CityWicomico Airport Runway 14/32 Extension $ 470,000 $ 3,000,000 $ 3,470,000 SalisburyOcean CityWicomico Airport Taxiway A Rehabiliation $ 2,500 $ 7,500 $ 132,500 $ 142,500 SalisburyOcean CityWicomico Airport Land Acquisition for Runway 14 Runway Protection Zone (RPZ) $ 300,000 $ 300,000 SalisburyOcean CityWicomico Airport Air Carrier Terminal Rehabiliation (30% Design in 2013) $ 1,100,000 $ 1,100,000 SalisburyOcean CityWicomico Airport Taxi F Extension and Apron $ 150,000 $ 150,000 Public Works Solid Waste Division Civic Center Recycling Center Design & Relocation $ 150,000 $ 150,000 Public Works Solid Waste Division Landfill Scale & Scale House Replacement $ 350,000 $ 350,000 Public Works Solid Waste Division Landfill Drainage Revision Plan $ 100,000 $ 250,000 $ 350,000 Public Works Solid Waste Division Landfill Cell 7 Construction $ 100,000 $ 5,700,000 $ 5,800,000 Public Works Solid Waste Division Convenience Center Improvements $ 50,000 $ 55,000 $ 60,000 $ 50,000 $ 50,000 $ 265,000 Wicomico County Recreation, Parks & Tourism WY&CC Exterior Metal $ 250,000 $ 250,000 Wicomico County Recreation, Parks & Tourism Cedar Hill Harbor Restoration $ 11,000 $ 11,000 $ 1,476,284 $ 4,873,500 $ 292,500 $ 5,750,000 $ 50,000 $ 12,442,284 ENTERPRISE FUNDING TOTALS SalisburyOcean CityWicomico Airport $ 576,284 $ 4,557,500 $ 132,500 $ 5,266,284 Public Works Solid Waste Division $ 650,000 $ 305,000 $ 160,000 $ 5,750,000 $ 50,000 $ 6,915,000 Wicomico County Recreation, Parks & Tourism $ 250,000 $ 11,000 $ 261,000 $ 1,476,284 $ 4,873,500 $ 292,500 $ 5,750,000 $ 50,000 $ 12,442,284 4

12 s by Funding Source State and Federal Grants / Other Department Number FY 19 FY 20 FY 21 FY 22 FY 23 5 Year '19 '23 Salisbury Ocean City Wicomico Airport MAA Air Traffic Control Tower Equipment $ 311,351 $ 311,351 Salisbury Ocean City Wicomico Airport FAA Runway 14/32 Extension $ 4,230,000 $ 27,000,000 $ 31,230,000 Salisbury Ocean City Wicomico Airport FAA Snow Removal Equipment (SRE) Building $ 1,350,000 $ 1,350,000 Salisbury Ocean City Wicomico Airport MAA Taxiway A Rehabiliation $ 2,500 $ 7,500 $ 132,500 $ 142,500 Salisbury Ocean City Wicomico Airport FAA Taxiway A Rehabiliation $ 45,000 $ 135,000 $ 2,385,000 $ 2,565,000 Salisbury Ocean City Wicomico Airport MAA Land Acquisition for Runway 14 Runway Protection Zone (RPZ) $ 300,000 $ 300,000 Salisbury Ocean City Wicomico Airport FAA Land Acquisition for Runway 14 Runway Protection Zone (RPZ) $ 5,400,000 $ 5,400,000 Salisbury Ocean City Wicomico Airport Replace Condemed Corporate/3 rows of T Hangars (38,000 sq. ft Hangar) $ 600,000 $ 7,000,000 $ 7,600,000 Salisbury Ocean City Wicomico Airport MAA Air Carrier Terminal Rehabiliation (30% Design in 2013) $ 3,300,000 $ 3,300,000 Salisbury Ocean City Wicomico Airport FEMA/Cargo Joint Use Distribution Center $ 200,000 $ 4,800,000 $ 5,000,000 Salisbury Ocean City Wicomico Airport MAA Taxi F Extension and Apron $ 150,000 $ 150,000 Salisbury Ocean City Wicomico Airport FAA Taxi F Extension and Apron $ 2,700,000 $ 2,700,000 Dept of Public Works Engineering Airport Water Main Extension $ 3,830,924 $ 3,830,924 Wicomico County Public Library Pittsville Branch Library $ 1,500,000 $ 1,500,000 Wicomico County Recreation, Parks & Tourism Cedar Hill Cabins & Bathroom Renovation $ 45,000 $ 45,000 Wicomico County Recreation, Parks & Tourism Pirate's Wharf Master Plan & Development $ 50,000 $ 50,000 Wicomico County Recreation, Parks & Tourism Playground Equipment $ 225,000 $ 99,000 $ 148,500 $ 472,500 Wicomico County Recreation, Parks & Tourism Tennis and Basketball Court Restoration $ 252,000 $ 126,000 $ 90,000 $ 121,500 $ 589,500 Wicomico County Recreation, Parks & Tourism Harmon Field Fencing $ 27,000 $ 27,000 Wicomico County Recreation, Parks & Tourism AWP Stadium Modernization $ 480,000 $ 480,000 Wicomico County Recreation, Parks & Tourism AWP Stadium Modernization $ 100,000 $ 100,000 Wicomico County Recreation, Parks & Tourism Roaring Point Park Break Waters $ 250,000 $ 250,000 Wicomico County Recreation, Parks & Tourism Cove Road Beach Access $ 100,000 $ 100,000 Wicomico County Recreation, Parks & Tourism Cedar Hill Harbor Restoration $ 99,000 $ 99,000 $ 198,000 Wor Wic Community College State Funding New Academic Building $ 2,061,503 $ 23,795,509 $ 939,195 $ 26,796,207 Wor Wic Community College Worcester County New Academic Building $ 200,928 $ 2,319,269 $ 91,540 $ 2,611,737 Wicomico County BOE ity #1 Delmar Elementary $ 7,395,000 $ 7,395,000 Wicomico County BOE ity #3 Glen Avenue $ 1,562,000 $ 1,562,000 Wicomico County BOE ity #4 Pinehurst Elementary Roof $ 725,000 $ 725,000 $ 20,302,775 $ 47,893,500 $ 9,818,431 $ 27,736,278 $ 1,030,735 $ 106,781,719 FEDERAL / STATE / OTHER FUNDING TOTALS Education BOE and Wor Wic State Funding $ 9,682,000 $ $ 2,061,503 $ 23,795,509 $ 939,195 $ 36,478,207 State Grant $ 5,295,775 $ 4,108,500 $ 371,000 $ 1,621,500 $ $ 11,396,775 Federal Grant $ 4,275,000 $ 36,585,000 $ 2,385,000 $ $ $ 43,245,000 Other $ 1,050,000 $ 7,200,000 $ 5,000,928 $ 2,319,269 $ 91,540 $ 15,661,737 $ 20,302,775 $ 47,893,500 $ 9,818,431 $ 27,736,278 $ 1,030,735 $ 106,781,719 5

13 GENERAL SERVICES WICOMICO COUNTY, MARYLAND FY 2019 FY 2023 CAPITAL IMPROVEMENTS PLAN Number 5Year '19 '23 CAPITAL COSTS General Fund / Bond s Health Dept Hurdle Basement Floor Improvements $ 160,000 $ 210,000 $ 370,000 $ 370,000 Health Dept Fritz Building Roof Replacement/HVAC $ 262,600 $ 262,600 $ 262,600 Nursing Home PTAC Unit Replacement $ 450,000 $ 450,000 $ 450,000 Extension Services Facility Roof Replacement $ 125,000 $ 125,000 $ 125,000 Circuit Court Complex Remodeling and Renovation $ 800,000 $ 800,000 1,750,000 $ 2,550,000 NCH AC Unit Replacement Controls Upgrade $ 480,000 $ 480,000 $ 480,000 GOB Roof Replacement $ 285,500 $ 285,500 $ 285,500 General Fund / Bond s $ 2,015,000 $ 758,100 $ 2,773,100 $ 1,750,000 $ 4,523,100 FUNDING SOURCES General Obligation Bond Proceeds (New Money) $ 1,750,000 $ 1,750,000 General Obligation Bond Proceeds (Old Money) General Fund "PayGo" $ 2,015,000 $ 758,100 $ 2,773,100 $ 2,773,100 County Enterprise Fund Board of Education State Grant Federal Grant Other To Be Determined $ 2,015,000 $ 758,100 $ 2,773,100 $ 1,750,000 $ 4,523,100 6

14 Wicomico County Capital Improvements Plan 2019 Department: Department Number: Title: General Services 14 Health Department Hurdle Basement Floor Improvement Number: Description / Status: New project in FY19. The basement level of the Hurdle building rests at elevation +3.5 feet above the mean tidal datum. It is believed certain tidal events are causing water infiltration into the basement level floor system. Ground water levels may also have an influence on this infiltration. A detailed hydraulic analysis would be required to positively identify the actual water source. During previous remedial work, it was determined the primer coating used for the existing concrete slab was a product to be used on new concrete. That product is used in dry applications only. It was not for applications where there is excessive moisture and hydrostatic pressure. The proposed solution will be sequenced in at least 2 steps over FY19 and FY20. The FY19, the first procedure entails removing the existing vinyl tile, gypsum leveling agent and incorrect primer down to the bare slab and retention of a mold remediation specialist to evaluate and correct problematic areas. The installation of another remote sump pump to aid relief of the under slab hydrostatic pressure will be concurrent. Residual water will be removed from the building via an exterior drain. In FY20, a series of applications of an epoxy type product suitable for the repair will occur. That application will be integral with the cemetitious material to further resolve the problem. This repair will allow possible moisture problems in the future to be made at a minimal cost with little disturbance to the overall facility. 5Year '19 '23 Estimated Costs Design, Study, Planning Land Acquisition Construction $ 160,000 $ 210,000 $ 370,000 $ 370,000 Equipment / Furnishings Estimated Costs $ 160,000 $ 210,000 $ 370,000 $ 370,000 General Obligation Bond Proceeds (New Money) General Obligation Bond Proceeds (Old Money) General Fund "PayGo" $ 160,000 $ 210,000 $ 370,000 $ 370,000 County Enterprise Fund Board of Education State Grant Federal Grant Other To Be Determined $ 160,000 $ 210,000 $ 370,000 $ 370,000 7

15 Wicomico County Capital Improvements Plan 2019 Department: Department Number: Title: General Services 14 Health Department Fritz Building Roof Replacement Number: Description / Status: New in FY19, scheduled for FY20. The Fritz building is in need of roof replacement due to age and lack of maintenance. The scope will be to remove all existing roofing materials to the deck. A new TPO 115 Mil Fleece back roofing product with new insulation will be installed. Pitch for correct flow of storm water to new roof leaders will be provided. The AC units will have to be removed and reinstalled to allow for proper flashing of the roofing curbs. Repairs have been performed in October 2017 to stop leaks that have been occurring. These repairs will allow sufficient time to budget and appropriate the funding for the entire project. 5Year '19 '23 Estimated Costs Design, Study, Planning Land Acquisition Construction $ 262,600 $ 262,600 $ 262,600 Equipment / Furnishings Estimated Costs $ 262,600 $ 262,600 $ 262,600 General Obligation Bond Proceeds (New Money) General Obligation Bond Proceeds (Old Money) General Fund "PayGo" $ 262,600 $ 262,600 $ 262,600 County Enterprise Fund Board of Education State Grant Federal Grant Other To Be Determined $ 262,600 $ 262,600 $ 262,600 8

16 Wicomico County Capital Improvements Plan 2019 Department: Department Number: Title: General Services 14 Nursing Home PTAC Unit Replacement Number: Description / Status: New in FY19. Replace (56) existing McQuay PTAC units with new inverter base PTAC units. The current McQuay PTAC units are out of production and inefficient. There are 30 PTAC units requiring hot water supply lines to be modified to accept the new units. Additionally, 30 units require modification of the wall opening to allow proper installation height. 26 units require electrical modifications. There are 8 ton and 10 ton Split Systems that will be replaced as well as a 12 ton MakeUp Air unit. Because the facility is year round, continuous operation, the increase in operating efficiency will have a substantial operating cost savings. The County is able to purchase the PTAC units directly from the distributor resulting in a savings of 25% on unit costs. 5Year '19 '23 Estimated Costs Design, Study, Planning Land Acquisition Construction $ 450,000 $ 450,000 $ 450,000 Equipment / Furnishings Estimated Costs $ 450,000 $ 450,000 $ 450,000 General Obligation Bond Proceeds (New Money) General Obligation Bond Proceeds (Old Money) General Fund "PayGo" $ 450,000 $ 450,000 $ 450,000 County Enterprise Fund Board of Education State Grant Federal Grant Other To Be Determined $ 450,000 $ 450,000 $ 450,000 9

17 Wicomico County Capital Improvements Plan 2019 Department: Department Number: Title: General Services 14 Extension Services Facility Roof Replacement Number: Description / Status: New in FY19. Since FY17 there has been a concerted effort with the University of Maryland to bring the entire building up to currently building code standards. FY FY19, a new standing seam metal truss roof system is recommended. The new roof will be installed above the current flat root system. Removal of the existing rooftop HVAC unit is included in this work. The estimated cost of $125,000 includes new overhanging fascia, soffits, gutters and downspouts. Maintenance costs to the existing roof are estimated to exceed $10,000 annually over the next several years. A standing seam metal roof has a life expectancy of 25 years or longer and will remove the $10,000 per year maintenance amount. In estimate, the metal roof would pay for itself in approximately 11 years. 5Year '19 '23 Estimated Costs Design, Study, Planning Land Acquisition Construction $ 125,000 $ 125,000 $ 125,000 Equipment / Furnishings Estimated Costs $ 125,000 $ 125,000 $ 125,000 General Obligation Bond Proceeds (New Money) General Obligation Bond Proceeds (Old Money) General Fund "PayGo" $ 125,000 $ 125,000 $ 125,000 County Enterprise Fund Board of Education State Grant Federal Grant Other To Be Determined $ 125,000 $ 125,000 $ 125,000 10

18 Wicomico County Capital Improvements Plan 2019 Department: Department Number: Title: General Services 14 Circuit Court Complex Remodeling and Renovations Number: Description / Status: Existing project from FY13, revised in FY19. $200,000 in funding was appropriated in FY14 for the engineering study plus $600,000 for phase one of remodeling and renovation of Circuit Court Building and Old Courthouse. $950,000 was appropriated in FY15. This will be phase two of remodeling and renovation of Circuit Court Building. The FY14 estimate of $850,000 was increased in FY15 by $100,000 to reflect the need to modify the elevator in the new courthouse to enable compliance with State and Federal mandates to maintain separation of malefemale and adultyouth defendants. Remodeling and renovation is required to expand the court facilities to accommodate an additional judge with related staff. The $800,000 in FY19 is necessary to provide remedial HVAC work to the 2nd floor and to address the State mandated PREA regulations, both of which were not part of the original project cost estimations. 5Year '19 '23 Estimated Costs Design, Study, Planning Land Acquisition Construction $ 800,000 $ 800,000 $ 1,750,000 $ 2,550,000 Equipment / Furnishings Estimated Costs $ 800,000 $ 800,000 $ 1,750,000 $ 2,550,000 General Obligation Bond Proceeds (New Money) $ 1,750,000 $ 1,750,000 General Obligation Bond Proceeds (Old Money) General Fund "PayGo" $ 800,000 $ 800,000 $ 800,000 County Enterprise Fund Board of Education State Grant Federal Grant Other To Be Determined $ 800,000 $ 800,000 $ 1,750,000 $ 2,550,000 11

19 Wicomico County Capital Improvements Plan 2019 Department: Department Number: Title: General Services 14 NCH AC Unit Replacement & Controls Upgrade Number: Description / Status: New project in FY19. This project replaces the water source heat pumps in the new courthouse on the 3rd and 4th floors, estimated cost $480,000. The units are currently 20+ years old. They are at or nearing the end of their service life. The units are no longer manufactured. Spares and replacement parts are not available. Installing new units and updating the building automation controls will improve operating efficiency. The result will be a significant reduction in energy costs. The upgraded building automation system will allow programming of the units for occupancy and provide alarm notification on failures. There are a total of 26 units to be replaced along with 2 condenser loop pumps. The loop pumps will have variable frequency drives to increase efficiency. Due to the age of the existing equipment, failure is imminent. 5Year '19 '23 Estimated Costs Design, Study, Planning Land Acquisition Construction $ 480,000 $ 480,000 $ 480,000 Equipment / Furnishings Estimated Costs $ 480,000 $ 480,000 $ 480,000 General Obligation Bond Proceeds (New Money) General Obligation Bond Proceeds (Old Money) General Fund "PayGo" $ 480,000 $ 480,000 $ 480,000 County Enterprise Fund Board of Education State Grant Federal Grant Other To Be Determined $ 480,000 $ 480,000 $ 480,000 12

20 Wicomico County Capital Improvements Plan 2019 Department: Department Number: Title: General Services 14 Government Office Building Roof Replacement Number: Description / Status: New project in FY19, scheduled for FY20. The roof on the Government Office Building (GOB) is at or near the end of its service life. Replacement is required. Several areas have large blisters that have formed. The blisters are potential sources of leaks in the near future. The roof currently has three layers of TPO roofing. The project is to remove all layers of the metal deck. Replacement material will be a 115 Mil fleece backed TPO roof system. Additionally, two 1975 original large exhaust fan units will be replaced. 5Year '19 '23 Estimated Costs Design, Study, Planning Land Acquisition Construction $ 285,500 $ 285,500 $ 285,500 Equipment / Furnishings Estimated Costs $ 285,500 $ 285,500 $ 285,500 General Obligation Bond Proceeds (New Money) General Obligation Bond Proceeds (Old Money) General Fund "PayGo" $ 285,500 $ 285,500 $ 285,500 County Enterprise Fund Board of Education State Grant Federal Grant Other To Be Determined $ 285,500 $ 285,500 $ 285,500 13

21 SHERIFF'S OFFICE WICOMICO COUNTY, MARYLAND FY 2019 FY 2023 CAPITAL IMPROVEMENTS PLAN Number 5Year '19 '23 CAPITAL COSTS General Fund / Bond s Public Safety Building $ 5,189,500 $ 5,189,500 $ 10,379, ,000 $ 11,104,000 General Fund / Bond s $ 5,189,500 $ 5,189,500 $ 10,379,000 $ 725,000 $ 11,104,000 FUNDING SOURCES General Obligation Bond Proceeds (New Money) $ 5,189,500 $ 5,189,500 $ 10,379,000 $ 625,000 $ 11,004,000 General Obligation Bond Proceeds (Old Money) General Fund "PayGo" $ 100,000 $ 100,000 County Enterprise Fund Board of Education State Grant Federal Grant Other To Be Determined $ 5,189,500 $ 5,189,500 $ 10,379,000 $ 725,000 $ 11,104,000 14

22 Wicomico County Capital Improvements Plan 2019 Department: Sheriff's Office Department Number: Title: 17 Public Safety Building Number: Description / Status: Existing project from FY14 CIP. Funds in the amount of $25,000 were appropriated in FY14 for an engineering study. The Sheriff's building has experienced a number of structural and building mechanical issues. Preliminary estimates are being discussed for the cost of replacing the Sheriff's facility. In FY17, the CIP included $100,000 for project study, in FY18 $600,000 for architectural, engineering and land acquisition, $5,189,500 in FY19 and FY20 for construction. This building will also house Emergency Services. 5Year '19 '23 Estimated Costs Design, Study, Planning 25,000 $ 25,000 Land Acquisition Construction $ 5,189,500 $ 5,189,500 $ 10,379, ,000 $ 11,079,000 Equipment / Furnishings Costs $ 5,189,500 $ 5,189,500 $ 10,379,000 $ 725,000 $ 11,104,000 General Obligation Bond Proceeds (New Money) $ 5,189,500 $ 5,189,500 $ 10,379,000 $ 625,000 $ 11,004,000 General Obligation Bond Proceeds (Old Money) $ General Fund "PayGo" $ 100,000 $ 100,000 County Enterprise Fund $ Board of Education $ State Grant $ Federal Grant $ Other $ To Be Determined $ $ 5,189,500 $ 5,189,500 $ 10,379,000 $ 725,000 $ 11,104,000 15

23 DEPARTMENT OF CORRECTIONS WICOMICO COUNTY, MARYLAND FY 2019 FY 2023 CAPITAL IMPROVEMENTS PLAN Number 5Year '19 '23 CAPITAL COSTS General Fund / Bond s HVAC Controls Upgrade/ Hot H2O Valve Replacement $ 163,800 $ 163,800 $ 163,800 Roof Replacement continued from FY $ 411,666 $ 411,667 $ 823, ,667 $ 1,235,000 Inmate Shower Restoration continued from FY $ 265,825 $ 265, ,825 $ 531,650 General Fund / Bond s $ 841,291 $ 411,667 $ 1,252,958 $ 677,492 $ 1,930,450 FUNDING SOURCES General Obligation Bond Proceeds (New Money) General Obligation Bond Proceeds (Old Money) General Fund "PayGo" $ 841,291 $ 411,667 $ 1,252,958 $ 677,492 $ 1,930,450 County Enterprise Fund Board of Education State Grant Federal Grant Other To Be Determined $ 841,291 $ 411,667 $ 1,252,958 $ 677,492 $ 1,930,450 16

24 Wicomico County Capital Improvements Plan 2019 Department: Department Number: Title: Department of Corrections 21 HVAC Controls Upgrade / Hot H20 Valve Replacement Number: To Be Determined Description / Status: New project in FY19. Mechanical controls upgrade to the 1998 wing of the Detention Center and replacement of hot & chilled water valves on the fan coil units (FCU's). There are 57 FCU's on the administration wing requiring replacement. There are 39 FCU's that need building automation controls installed. This will improve building energy efficiency by eliminating valve leakby and allowing scheduled run time of equipment for occupied hours. 5Year '19 '23 Estimated Costs Design, Study, Planning Land Acquisition Construction $ 163,800 $ 163,800 $ 163,800 Equipment / Furnishings Costs $ 163,800 $ 163,800 $ 163,800 General Obligation Bond Proceeds (New Money) General Obligation Bond Proceeds (Old Money) General Fund "PayGo" $ 163,800 $ 163,800 $ 163,800 County Enterprise Fund Board of Education State Grant Federal Grant Other To Be Determined $ 163,800 $ 163,800 $ 163,800 17

25 Wicomico County Capital Improvements Plan 2019 Department: Department Number: Title: Department of Corrections 21 Detention Center Roof Replacement Number: Description / Status: Existing project from FY18 CIP and is on schedule to start in the Spring of 2018.The original roof on the Detention Center was installed in 1986 and the roof on the Administration Building was installed in 1998; both are in need of replacement. There have been repairs and sections replaced on the roof about 59 years after it was installed. There are no clear maintenance records to show what was done exactly and where the locations were. The repairs were believed to have been completed under warranty due to the premature failure from the original installation. Several repairs have been contracted on the Administration Building roof. This roof is in poor shape given its age. There are numerous penetrations due to the Emergency Services equipment installations. Peninsula Roofing assessed the roof in 2014 giving a remaining service life of 5 years. Between 2012 and 2014, over 20 different leak locations on the roof were repaired. Every major rain reveals a new leak. It was recommended to put a thicker roofing membrane down to help give a longer life to the roof and prevent punctures. Research has been done to find the most cost effective and practical approach in type and methods of replacement. There are other options that could be used for the roof replacement and would double or triple the cost of the project and would give no extra life to the roof. 5Year '19 '23 Estimated Costs Design, Study, Planning Land Acquisition Construction $ 411,666 $ 411,667 $ 823, ,667 $ 1,235,000 Equipment / Furnishings Costs $ 411,666 $ 411,667 $ 823,333 $ 411,667 $ 1,235,000 General Obligation Bond Proceeds (New Money) General Obligation Bond Proceeds (Old Money) General Fund "PayGo" $ 411,666 $ 411,667 $ 823,333 $ 411,667 $ 1,235,000 County Enterprise Fund Board of Education State Grant Federal Grant Other To Be Determined $ 411,666 $ 411,667 $ 823,333 $ 411,667 $ 1,235,000 18

26 Wicomico County Capital Improvements Plan 2019 Department: Department Number: Title: Department of Corrections 21 Inmate Shower Restoration Number: Description / Status: Existing project from FY18 CIP and is on schedule to start in the Spring of is to upgrade the 33 inmate showers that are currently 30 years old and are having various types of failures. This is to have a company come in with a HEPA vacuum system to grind the existing tiles down and apply an epoxy coating system on the entire shower area to make it easy to clean, slip resistant and safe for staff and inmates. New shower controls will be installed to monitor the amount of time the showers can be running and not left on for continuous points of time. There is currently an annual waste in excess of over 2 million gallons of water per year that could be saved with this new system. 5Year '19 '23 Estimated Costs Design, Study, Planning Land Acquisition Construction $ 265,825 $ 265, ,825 $ 531,650 Equipment / Furnishings Costs $ 265,825 $ 265,825 $ 265,825 $ 531,650 General Obligation Bond Proceeds (New Money) General Obligation Bond Proceeds (Old Money) General Fund "PayGo" $ 265,825 $ 265,825 $ 265,825 $ 531,650 County Enterprise Fund Board of Education State Grant Federal Grant Other To Be Determined $ 265,825 $ 265,825 $ 265,825 $ 531,650 19

27 DEPARTMENT OF PUBLIC WORKS WICOMICO COUNTY, MARYLAND FY 2019 FY 2023 CAPITAL IMPROVEMENTS PLAN Number 5Year '19 '23 CAPITAL COSTS General Fund / Bond s PW Engineering Chesapeake Bay WIP $ 200,000 $ 200,000 $ 200,000 $ 200,000 $ 200,000 $ 1,000,000 $ 1,000,000 $ 2,000,000 PW Engineering Water & Sewer Master Plan $ 300,000 $ 300,000 $ 300,000 PW Engineering Airport Water Main Extension $ 3,830,924 $ 3,830,924 $ 142,000 $ 3,972,924 Public Works Engineering $ 4,330,924 $ 200,000 $ 200,000 $ 200,000 $ 200,000 $ 5,130,924 $ 1,142,000 $ 6,272,924 PW Roads Anderson Mill Pond Dam Rehabilitation $ 50,000 $ 350,000 $ 400,000 $ 400,000 PW Roads Bear Swamp Bridge Replacement $ 165,000 $ 165,000 $ 50,000 $ 215,000 PW Roads Dry Storage Building $ 160,000 $ 160,000 $ 160,000 PW Roads Hobbs Beaver Dam Creek $ 400,000 $ 400,000 $ 400,000 PW Roads Riverside Hunting Park $ 400,000 $ 400,000 $ 400,000 PW Roads Westside Collector Phase 3 $ 500,000 $ 1,500,000 $ 2,000,000 $ 2,000,000 Public Works Roads $ 325,000 $ 950,000 $ 2,250,000 $ 3,525,000 $ 50,000 $ 3,575,000 General Fund / Bond s $ 4,655,924 $ 1,150,000 $ 2,450,000 $ 200,000 $ 200,000 $ 8,655,924 $ 1,192,000 $ 9,847,924 Enterprise s PW Solid Waste Civic Center Recycling Center Design & Relocation $ 150,000 $ 150,000 $ 150,000 PW Solid Waste Landfill Scale & Scale House Replacement $ 350,000 $ 350,000 $ 350,000 PW Solid Waste Landfill Drainage Revision Plan $ 100,000 $ 250,000 $ 350,000 $ 350,000 PW Solid Waste Convenience Center Improvements $ 50,000 $ 55,000 $ 60,000 $ 50,000 $ 50,000 $ 265,000 $ 265,000 PW Solid Waste Landfill Cell 7 Construction $ 100,000 $ 5,700,000 $ 5,800,000 $ 5,800,000 Enterprise s $ 650,000 $ 305,000 $ 160,000 $ 5,750,000 $ 50,000 $ 6,915,000 $ 6,915,000 Public Works s $ 5,305,924 $ 1,455,000 $ 2,610,000 $ 5,950,000 $ 250,000 $ 15,570,924 $ 1,192,000 $ 16,762,924 20

28 DEPARTMENT OF PUBLIC WORKS WICOMICO COUNTY, MARYLAND FY 2019 FY 2023 CAPITAL IMPROVEMENTS PLAN FUNDING SOURCES 5Year '19 '23 General Obligation Bond Proceeds (New Money) $ 550,000 $ 1,850,000 $ 2,400,000 $ 2,400,000 General Obligation Bond Proceeds (Old Money) General Fund "PayGo" $ 825,000 $ 600,000 $ 600,000 $ 200,000 $ 200,000 $ 2,425,000 $ 1,050,000 $ 3,475,000 County Enterprise Fund $ 650,000 $ 305,000 $ 160,000 $ 5,750,000 $ 50,000 $ 6,915,000 $ 6,915,000 Board of Education State Grant (MDE low interest loan) $ 3,830,924 $ 3,830,924 $ 3,830,924 Federal Grant Other $ 142,000 $ 142,000 To Be Determined $ 5,305,924 $ 1,455,000 $ 2,610,000 $ 5,950,000 $ 250,000 $ 15,570,924 $ 1,192,000 $ 16,762,924 21

29 Wicomico County Capital Improvements Plan 2019 Department: Department Number: Title: Department of Public Works Engineering Division 24 Chesapeake Bay Watershed Implementation Plan (WIP) Number: Description / Status: Continued from FY14. Federal and State mandates require that each county and certain municipalities be responsible for the implementation of the WIP. In order to accomplish this task Wicomico County will need to prepare a watershed planning study for each of its three watersheds: Wicomico River, Nanticoke River and Pocomoke River. County, state and federal funds will be needed for the actual implementation which is estimated to cost $695,000,000 with an average annual cost of $58,000,000 per year (cost per year over 12 years ( )) excluding agricultural properties and the City of Salisbury. 5Year '19 '23 Estimated Costs Design, Study, Planning $ 50,000 $ 50,000 $ 50,000 $ 50,000 $ 50,000 $ 250,000 $ 250,000 $ 500,000 Land Acquisition Construction $ 150,000 $ 150,000 $ 150,000 $ 150,000 $ 150,000 $ 750,000 $ 750,000 $ 1,500,000 Equipment / Furnishings Estimated Costs $ 200,000 $ 200,000 $ 200,000 $ 200,000 $ 200,000 $ 1,000,000 $ 1,000,000 $ 2,000,000 General Obligation Bond Proceeds (New Money) General Obligation Bond Proceeds (Old Money) General Fund "PayGo" $ 200,000 $ 200,000 $ 200,000 $ 200,000 $ 200,000 $ 1,000,000 $ 1,000,000 $ 2,000,000 County Enterprise Fund Board of Education State Grant Federal Grant Other To Be Determined $ 200,000 $ 200,000 $ 200,000 $ 200,000 $ 200,000 $ 1,000,000 $ 1,000,000 $ 2,000,000 22

30 Wicomico County Capital Improvements Plan 2019 Department: Department Number: Title: Department of Public Works Engineering Division 24 Water and Sewer Master Plan Number: Description / Status: New project in FY19. This project funds the development of a Countywide water and sewer master plan. It develops and recommends strategies for the County to address failing residential well and sceptic systems in unincorporated areas of the County outside the reach of a municipal water and sewer system. This plan, through ultimately connecting failing septic systems to municipal sewer, will aide the County in meeting its Watershed Implementation Plan goals. 5Year '19 '23 Estimated Costs Design, Study, Planning $ 300,000 $ 300,000 $ 300,000 Land Acquisition Construction Equipment / Furnishings Estimated Costs $ 300,000 $ 300,000 $ 300,000 General Obligation Bond Proceeds (New Money) General Obligation Bond Proceeds (Old Money) General Fund "PayGo" $ 300,000 $ 300,000 $ 300,000 County Enterprise Fund Board of Education State Grant Federal Grant Other (General Fund, department 24) To Be Determined $ 300,000 $ 300,000 $ 300,000 23

31 Wicomico County Capital Improvements Plan 2019 Department: Department Number: Title: Department of Public Works Engineering Division 24 Airport Water Main Extension Number: Description / Status: Continued from FY18. The project involves bringing water service from the City of Salisbury to the SalisburyOcean CityWicomico Regional Airport. In FY18, the design and easement acquisition commenced. In FY19, a 12" water main will be installed from the existing water tank located at WorWic Community College to the airport facilities. The proposed route runs primarily along Walston Switch Road and Airport Road and will include service lines to existing facilities. The City of Salisbury will operate and maintain the system under an Urban Services Agreement. 5Year '19 '23 Estimated Costs Design, Study, Planning $ 142,000 $ 142,000 Land Acquisition Construction $ 3,830,924 $ 3,830,924 $ 3,830,924 Equipment / Furnishings Estimated Costs $ 3,830,924 $ 3,830,924 $ 142,000 $ 3,972,924 General Obligation Bond Proceeds (New Money) General Obligation Bond Proceeds (Old Money) General Fund "PayGo" County Enterprise Fund Board of Education State Grant (MDE Low Interest Loan) $ 3,830,924 $ 3,830,924 $ 3,830,924 Federal Grant Other $ 142,000 $ 142,000 To Be Determined $ 3,830,924 $ 3,830,924 $ 142,000 $ 3,972,924 24

32 Wicomico County Capital Improvements Plan 2019 Department: Department Number: Title: Department of Public Works Roads Division 50 Anderson Mill Pond Dam Rehabilitation Number: Description / Status: New in FY19. Anderson Mill Pond Dam is a partially private dam in poor condition per MDE. The outfall structure and upstream bank are private, the road (Pemberton Drive) and downstream bank are County owned. MDE has indicated the vegetation on the upstream bank is overgrown and needs to be removed. MDE has also indicated the outfall pipes are undersized. MDE desires the rehabilitation of this dam for safety reasons. The current owner has indicated some interest in giving control of the dam to the County. Public Works is open to this idea as it could prevent another Barren Creek style washout since the outfall structure is privately controlled. The project is dependent on the property owner being willing to donate the upstream land. 5Year '19 '23 Estimated Costs Design, Study, Planning $ 50,000 $ 50,000 $ 50,000 Land Acquisition Construction $ 350,000 $ 350,000 $ 350,000 Equipment / Furnishings Estimated Costs $ 50,000 $ 350,000 $ 400,000 $ 400,000 General Obligation Bond Proceeds (New Money) $ 50,000 $ 350,000 $ 400,000 $ 400,000 General Obligation Bond Proceeds (Old Money) General Fund "PayGo" County Enterprise Fund Board of Education State Grant Federal Grant Other To Be Determined $ 50,000 $ 350,000 $ 400,000 $ 400,000 Operating Budget Implact: 25

33 Wicomico County Capital Improvements Plan 2019 Department: Department Number: Title: Department of Public Works Roads Division 50 Bear Swamp Bridge Replacement Number: Description / Status: Continued from FY18. The Public Works Roads Division proposes to replace the existing Bear Swamp timber bridge with three 48 diameter HDPE culvert pipes. This will eliminate an ongoing maintenance issue associated with the existing bridge which is located on an isolated dirt road and subject to constant vandalism. Replacement of the bridge with pipes will remove the structure from the bridge inventory thereby eliminating inspection requirements and most maintenance. 5Year '19 '23 Estimated Costs Design, Study, Planning $ 50,000 $ 50,000 Land Acquisition Construction $ 165,000 $ 165,000 $ 165,000 Equipment / Furnishings Estimated Costs $ 165,000 $ 165,000 $ 50,000 $ 215,000 General Obligation Bond Proceeds (New Money) General Obligation Bond Proceeds (Old Money) General Fund "PayGo" $ 165,000 $ 165,000 $ 50,000 $ 215,000 County Enterprise Fund Board of Education State Grant Federal Grant Other To Be Determined $ 165,000 $ 165,000 $ 50,000 $ 215,000 26

January 03, The Honorable County Council Wicomico County Maryland Salisbury, Maryland 21803

January 03, The Honorable County Council Wicomico County Maryland Salisbury, Maryland 21803 January 03, 2012 The Honorable County Council Wicomico County Maryland Salisbury, Maryland 21803 I would like to begin by thanking the Council for approving resolution 135-2011 granting an extension of

More information

Carroll County Maryland. Community Investment Plan Request Fiscal Years

Carroll County Maryland. Community Investment Plan Request Fiscal Years Carroll County Maryland Community Investment Plan Request Fiscal Years 2019-2024 PRODUCED BY The Department of Management and Budget Ted Zaleski... Director Deborah Effingham... Chief, Bureau of Budget

More information

OPERATING BUDGET WICOMICO COUNTY, MARYLAND

OPERATING BUDGET WICOMICO COUNTY, MARYLAND OPERATING BUDGET WICOMICO COUNTY, MARYLAND 2018-2019 Adopted Budget (including Executive's Budget Message) June 14, 2018 Determination of Tax Rate and Revenue under Revenue Cap Part 1 - Determination of

More information

OPERATING BUDGET WICOMICO COUNTY, MARYLAND

OPERATING BUDGET WICOMICO COUNTY, MARYLAND OPERATING BUDGET WICOMICO COUNTY, MARYLAND 20152016 Adopted June 2, 2015 FY16 General Fund Revenue by Category 3% 3% 5% 1% 2% 0% 5% 32% 48% Local Property Tax Local Income Tax Local Property Tax (48%)

More information

Property tax revenues are expected to remain strong with a projected FY 08 growth rate of 8.7% mainly due to growth in reassessments.

Property tax revenues are expected to remain strong with a projected FY 08 growth rate of 8.7% mainly due to growth in reassessments. Operating Revenues Property Tax Property tax revenues are expected to remain strong with a projected FY 08 growth rate of 8.7% mainly due to growth in reassessments. Since 2000, the average home sale price

More information

Capital Improvement Program (CIP)

Capital Improvement Program (CIP) (CIP) Citrus County maintains a (CIP) that covers a five-year period and is updated annually in conjunction with the operating budget. The projects included in this program will enable the County to meet

More information

FY 16 - FY 18 Capital Fund Revenues

FY 16 - FY 18 Capital Fund Revenues FY 16 - FY 18 Capital Fund Revenues Fiscal Year $ Change 2016 2017 2018 FY 17 to Revenue Source Budget Budget Budget FY 18 Local Transfer from General Fund $3,136,950 $2,977,556 $6,087,130 $3,109,574 Local

More information

Subject: Capital Reserve Expenditure Guidelines. *incl. former OCHAP/CSHP Peel Access to Housing (PATH)

Subject: Capital Reserve Expenditure Guidelines. *incl. former OCHAP/CSHP Peel Access to Housing (PATH) HIP Housing In Peel Subject: Capital Reserve Expenditure Guidelines Date: August 1, 2012 Applicable To The information contained in this document applies to the following: Municipal & Private Non- Federal

More information

Agenda Item # 5b Page 1 of 43

Agenda Item # 5b Page 1 of 43 Page 1 of 43 Page 2 of 43 Page 3 of 43 Page 4 of 43 Page 5 of 43 Page 6 of 43 Page 7 of 43 Page 8 of 43 Page 9 of 43 Page 10 of 43 Page 11 of 43 Page 12 of 43 Page 13 of 43 Page 14 of 43 Page 15 of 43

More information

CAPITAL IMPROVEMENT PROJECTS CAPITAL PROJECTS FUND FISCAL YEAR 2013/2014 PROJECTS SCHEDULED FOR CONSTRUCTION. Local Option Sales Tax Funds $ 500,000

CAPITAL IMPROVEMENT PROJECTS CAPITAL PROJECTS FUND FISCAL YEAR 2013/2014 PROJECTS SCHEDULED FOR CONSTRUCTION. Local Option Sales Tax Funds $ 500,000 CAPITAL IMPROVEMENT PROJECTS CAPITAL PROJECTS FUND FISCAL YEAR 2013/2014 PROJECTS SCHEDULED FOR CONSTRUCTION On-Going Pavement Management Program: In 2009/2010 the city completed the initial 3-year plan

More information

OPERATING BUDGET WICOMICO COUNTY, MARYLAND Adopted. June 3, 2014

OPERATING BUDGET WICOMICO COUNTY, MARYLAND Adopted. June 3, 2014 OPERATING BUDGET WICOMICO COUNTY, MARYLAND 2014-2015 Adopted June 3, 2014 Estimated Revenue FY2015 Personal Property 6.9% Local Income Tax 30.7% Real Property 41.8% Recordation Tax, 2.1% Other Taxes, 0.7%

More information

COUNTY BUILDINGS & CAPITAL CONSTRUCTION

COUNTY BUILDINGS & CAPITAL CONSTRUCTION EXECUTIVE SUMMARY The Department of General Services (DGS) is responsible for planning and financing construction of new county facilities as well as minor alterations, improvements, and major equipment

More information

Yearly Totals $4,575,931 $29,650,463 $33,918,732 $8,480,000 $49,160,000 $24,630,000 $9,000,000 $145,839,195 $159,415,126. Revised March 26, 2018

Yearly Totals $4,575,931 $29,650,463 $33,918,732 $8,480,000 $49,160,000 $24,630,000 $9,000,000 $145,839,195 $159,415,126. Revised March 26, 2018 BHM Airport Capital Improvement Plan (ACIP) ACIP Annual Expense Summary 5 YEAR ACIP 2019 2023 Prior Year(s) Budgeted Budgeted Budgeted Budgeted Budgeted Estimated Five (5) Year Total Project NPS Priority

More information

2017 Budget & Capital Improvement Plan AUGUST 29, 2017

2017 Budget & Capital Improvement Plan AUGUST 29, 2017 2017 Budget & Capital Improvement Plan AUGUST 29, 2017 FY 2017 Budget Calendar May June July August September October November December Financial Forecast & Public Safety Staffing Priorities, Programs,

More information

STORMWATER MANAGEMENT FUND Department of Environmental Services

STORMWATER MANAGEMENT FUND Department of Environmental Services Department of Environmental Services Mission: To implement a comprehensive stormwater management program that balances the following goals: 1) to reduce the potential for stormwater threats to public health,

More information

City School District of Albany Five Year Facilities Plan 3/14/2019

City School District of Albany Five Year Facilities Plan 3/14/2019 Bold indicates change from 3/7/19 BOE meeting Available Local Share $ 3,300,000 1 SPA Air condition gymnasium $ 267,000 1 $ 41,385 $ 41,385 $ 267,000 2 DCS Air condition gymnasium $ 221,000 1 $ 34,255

More information

Reserve Analysis Report

Reserve Analysis Report Reserve Analysis Report Parkway Towers 1155 Ash St Denver, CO 80220 Level I Study with Site Inspection Fiscal Year End Date: 12/31/2014 8597 Via Mallorca Suite E La Jolla, CA 92037 Phone: 858-764-1895

More information

County of Gloucester Virginia

County of Gloucester Virginia County of Gloucester Virginia Adopted Capital Improvements Plan FY 2014 to FY 2018 Capital Planning The basic function of a Capital Improvement Program is to provide governments with an orderly process

More information

Present: Matthew E. Creamer, Council Administrator; Edgar A. Baker, Jr., County Attorney and Melissa Holland, Recording Secretary.

Present: Matthew E. Creamer, Council Administrator; Edgar A. Baker, Jr., County Attorney and Melissa Holland, Recording Secretary. The Wicomico County Council met in Legislative Session on Tuesday, February 4, 2014 at 6:00 p.m. in Council Chambers, Government Office Building, Salisbury, Maryland. In attendance: Matt Holloway, President;

More information

CAPITAL RESERVE STUDY

CAPITAL RESERVE STUDY CAPITAL RESERVE STUDY FOR THE HIALEAH CONDOMINIUM WILDWOOD CREST, NEW JERSEY Project Number: 12-1066 W:\2012\12-1066\CORR\12-1066v1.doc Date: March 29, 2013 Table of Contents Section Page Executive Summary...

More information

City of Hartford Capital Improvement Program Share Total Project Cost. General Obligation Debt

City of Hartford Capital Improvement Program Share Total Project Cost. General Obligation Debt 2019 Summary of Costs ~ Governmental Funds Law Enforcement Number Priority 2019 Share Total Cost General Obligation Term Borrowings Grants & Aids Trusts & Donations Retained Earnings Police Patrol Vehicle

More information

CITY OF FRUITLAND FISCAL YEAR BUDGET

CITY OF FRUITLAND FISCAL YEAR BUDGET CITY OF FRUITLAND FISCAL YEAR 2018 2019 BUDGET June 12, 2018 CITY OF FRUITLAND, MD UTILITIES DEPARTMENT BUDGET FISCAL YEAR 2019 FISCAL YEAR 2018 FISCAL YEAR 2017 SANITATION WATER SEWER SANITATION WATER

More information

Physical Plant. Five-Year Capital Budget Plan. State College Area School District November Page 1 of 15

Physical Plant. Five-Year Capital Budget Plan. State College Area School District November Page 1 of 15 Physical Plant Five-Year Capital Budget Plan State College Area School District November 2011 Page 1 of 15 Table of Contents Background and 2013 Projects Pages 3-5 Funding Level Pages 6-7 Existing Buildings

More information

DeKalb County School District/Elementary Schools Dunwoody Elementary Final School Assessment Report May 19, 2016

DeKalb County School District/Elementary Schools Dunwoody Elementary Final School Assessment Report May 19, 2016 DeKalb County School District/Elementary Schools Dunwoody Elementary Final School Assessment Report May 19, 2016 PARSONS School Assessment Report Table of Contents School Executive Summary 4 School Condition

More information

MUNICIPAL BONDED INDEBTEDNESS LIMITS AND EXCEPTIONS TO THOSE LIMITS

MUNICIPAL BONDED INDEBTEDNESS LIMITS AND EXCEPTIONS TO THOSE LIMITS kslegres@klrd.ks.gov 68-West Statehouse, 300 SW 10th Ave. Topeka, Kansas 66612-1504 (785) 296-3181 FAX (785) 296-3824 http://www.kslegislature.org/klrd August 31, 2016 MUNICIPAL BONDED INDEBTEDNESS LIMITS

More information

INTRODUCTION. Summary of revenue/expenditures available for new construction and remodeling projects only. CERTIFICATION

INTRODUCTION. Summary of revenue/expenditures available for new construction and remodeling projects only. CERTIFICATION INTRODUCTION The 5-Year District Facilities Work Program is a very important document. The Department of Education, Legislature, Governor's Office, Division of Community Planning (growth management), local

More information

IMPLEMENTATION A. INTRODUCTION C H A P T E R

IMPLEMENTATION A. INTRODUCTION C H A P T E R C H A P T E R 11 IMPLEMENTATION A. INTRODUCTION This chapter addresses implementation of the General Plan. The Plan s seven elements include 206 individual actions. 1 Many are already underway or are on-going.

More information

Prior Years FY 2015 FY 2016 FY 2017 FY 2018 FY 2019 Future

Prior Years FY 2015 FY 2016 FY 2017 FY 2018 FY 2019 Future SUMMARY OF AIRPORT PROJECTS DOLLARS IN THOUSANDS Project Estimates: Years FY 2015 FY 2016 FY 2017 FY 2018 FY 2019 Future Project 5Year CIP Planning 189 874 935 300 600 700 3,598 2,709 Land 1,000 3,200

More information

FY 2016 FY 2020 Capital Improvement Program (CIP) Executive Summary

FY 2016 FY 2020 Capital Improvement Program (CIP) Executive Summary FY 2016 FY 2020 Capital Improvement Program (CIP) Executive Summary The adopted FY 2016 FY 2020 CIP is $205.3 million (including prior year expenditures) and is $2.9 million lower than the previous CIP

More information

One and two family residences... $ Mobile Homes... $73.73 Commercial Building... $ All other miscellaneous applications... $44.

One and two family residences... $ Mobile Homes... $73.73 Commercial Building... $ All other miscellaneous applications... $44. EXHIBIT "A" BUILDING PERMITS, HOUSING CODE AND MOBILE HOME PERMIT FEES Page 1 of 9 I. APPLICATION FEES (Non-refundable) One and two family residences... $147.59 Mobile Homes... $73.73 Commercial Building...

More information

REPLACEMENT RESERVE GUIDE

REPLACEMENT RESERVE GUIDE CANADA MORTGAGE AND HOUSING CORPORATION REPLACEMENT RESERVE GUIDE What is the Replacement Reserve? The replacement reserve is a fund kept by each housing sponsor under the terms of its operating agreement

More information

The Citizen s Report 2009

The Citizen s Report 2009 ERNIE LEE MAGAHA YOUR ESCAMBIA COUNTY CLERK and COMPTROLLER PRESENTS The Citizen s Report 2009 A Summary Report of the COMPREHENSIVE ANNUAL FINANCIAL REPORT Fiscal Year Ended September 30, 2009 Independent

More information

Issued: October 3, 2016 Proposals Due: November 28, 2016

Issued: October 3, 2016 Proposals Due: November 28, 2016 REQUEST FOR QUALIFICATIONS PROFESSIONAL SERVICES For Boulder City Municipal Airport Issued: October 3, 2016 Proposals Due: November 28, 2016 Page 1 of 8 I. Introduction Request For Statements of Qualifications

More information

Overview of Public Schools CIP

Overview of Public Schools CIP Overview of Public Schools CIP The Public Schools Community Investment Plan (CIP) includes school construction, additions and modernizations, as well as other school related projects. For more than a decade

More information

TO MEMBERS OF THE COMMITTEE ON GROUNDS AND BUILDINGS: ACTION ITEM

TO MEMBERS OF THE COMMITTEE ON GROUNDS AND BUILDINGS: ACTION ITEM 104 Office of the President TO MEMBERS OF THE COMMITTEE ON : For Meeting of ACTION ITEM AMENDMENT OF THE BUDGET FOR CAPITAL IMPROVEMENTS AND THE CAPITAL IMPROVEMENT PROGRAM AND APPROVAL OF EXTERNAL FINANCING

More information

POCOMOKE CITY, MARYLAND FINANCIAL STATEMENTS YEAR ENDED JUNE 30, 2015

POCOMOKE CITY, MARYLAND FINANCIAL STATEMENTS YEAR ENDED JUNE 30, 2015 FINANCIAL STATEMENTS YEAR ENDED JUNE 30, 2015 TABLE OF CONTENTS Page INDEPENDENT AUDITORS REPORT 1-2 MANAGEMENT S DISCUSSION AND ANALYSIS 3-10 BASIC FINANCIAL STATEMENTS Government-wide financial statements

More information

Capital Improvement Plan City of Rye, New York

Capital Improvement Plan City of Rye, New York 20182022 Capital Improvement Plan City of Rye, New York Planning and Funding For City Projects For Fiscal Years Ending December 31, 2018 through 2022 September 2017 Capital Improvement Plan 20182022 TABLE

More information

Our Focus: Your Future

Our Focus: Your Future Town of Fort Erie Infrastructure Services Our Focus: Your Future Prepared for Council-in-Committee Report No. IS-53-07 Agenda Date November 19, 2007 File No. 220102 Subject 5 YEAR FACILITY CONDITION STATUS

More information

VILLAGE OF FRANKLIN MASTER FEE SCHEDULE

VILLAGE OF FRANKLIN MASTER FEE SCHEDULE 1 VILLAGE OF FRANKLIN MASTER FEE SCHEDULE BUILDING PERMIT APPLICATION FEE A non-refundable fee shall accompany each permit application. This fee shall be credited to the approved permit fee. CURRENTLY

More information

BUILDING PERMIT FEES

BUILDING PERMIT FEES BUILDING PERMIT FEES 1. Building Permit Fee Based on the Construction Valuation of the project excluding site work. Refer to Fee Charts below. Electrical, Mechanical and Plumbing permits are not included

More information

Pinellas County Capital Improvement Program, FY2011 Through FY2016 INTRODUCTION AND BACKGROUND

Pinellas County Capital Improvement Program, FY2011 Through FY2016 INTRODUCTION AND BACKGROUND Introduction to the Six-Year Capital Improvement Program (CIP) The Pinellas County Capital Improvement Program (CIP) is a comprehensive six-year plan of proposed capital projects, intended to identify

More information

Ronald E. McNair Discovery Learning Academy

Ronald E. McNair Discovery Learning Academy DeKalb County School District/Elementary Schools Ronald E. McNair Discovery Learning Academy Final School Assessment Report May 20, 2016 PARSONS School Assessment Report Table of Contents School Executive

More information

STORMWATER MANAGEMENT FUND Department of Environmental Services

STORMWATER MANAGEMENT FUND Department of Environmental Services Department of Environmental Services Mission: To implement a comprehensive stormwater management program that balances the following goals: 1) to reduce the potential for stormwater threats to public health,

More information

PIERCE COUNTY AIRPORT THUN FIELD rd Avenue Ct. E Puyallup, WA (253)

PIERCE COUNTY AIRPORT THUN FIELD rd Avenue Ct. E Puyallup, WA (253) PIERCE COUNTY AIRPORT THUN FIELD 16915 103 rd Avenue Ct. E Puyallup, WA 98374 (253)798 7800 AIRCRAFT HANGAR / TIE DOWN AGREEMENT TENANT INFORMATION Name: Business Name: Address: City: State: Zip Code:

More information

FY 2017 FY 2021 Capital Improvement Program (CIP) Executive Summary

FY 2017 FY 2021 Capital Improvement Program (CIP) Executive Summary FY 2017 FY 2021 Capital Improvement Program (CIP) Executive Summary The adopted FY 2017 FY 2021 CIP is $235.8 million (including prior year expenditures) and is $28 million higher than the previous CIP

More information

Hyde Park Place Owners' Association, Inc.

Hyde Park Place Owners' Association, Inc. RESERVE STUDY Full Study Hyde Park Place Owners' Association, Inc. Published - February 10, 2016 Browning Reserve Group / Emmett, ID 83617 Office (208) 365-0977 Tony@BrowningRG.com / www.browningrg.com

More information

Georgetown County Capital Improvement Plan Revenue Projections 2018 Update (October 9, 2018)

Georgetown County Capital Improvement Plan Revenue Projections 2018 Update (October 9, 2018) Revenue Projections Revenue Sources Current Funds Available for CIP Projects 2003 Bond Funds (for Facilities) $ - $ - $ - $ - $ - $ - $ - $ - $ 11,206,726 Grants for Campbell Marine Complex - - - - - -

More information

WATER AND WASTEWATER FUND REVENUES

WATER AND WASTEWATER FUND REVENUES WATER AND WASTEWATER FUND REVENUES Water revenues comprise $12.11 million, or 70.6% of total revenues of the fund, while wastewater (sewer) charges comprise $4.25 million, or 24.7% of total revenues. Water

More information

APPENDIX A FULL TEXT OF BOND MEASURE

APPENDIX A FULL TEXT OF BOND MEASURE APPENDIX A FULL TEXT OF BOND MEASURE INTRODUCTION To repair aging classrooms / leaky roofs / old facilities, and provide a safe, quality learning environment for current and future students, shall Grass

More information

CAPITAL IMPROVEMENT PROGRAM

CAPITAL IMPROVEMENT PROGRAM CAPITAL IMPROVEMENT PROGRAM CAPITAL IMPROVEMENT PLAN This section of the Pinellas County Annual Operating and Capital Budget document contains information on the Capital Improvement Program (CIP). The

More information

Update With Site Visit

Update With Site Visit Update With Site Visit Le Chateau Bellevue, WA 10/28/2011 Report #1002 Phone: 253-241-8151 Fax: 360-872-8073 E-mail: jeremy@reservesolutions.net www.reservesolutions.net Le Chateau Client Info: REPORT

More information

CAPITAL IMPROVEMENT PLAN

CAPITAL IMPROVEMENT PLAN CAPITAL IMPROVEMENT PLAN This section of the Pinellas County Annual Operating and Capital Budget document contains information on the Capital Improvement Program (CIP). The CIP is a comprehensive ten-year

More information

Overview of Public Schools CIP

Overview of Public Schools CIP Overview of Public Schools CIP The Board of Education CIP includes public school construction, addition and modernization projects as well as other school related projects. The primary sources of funding

More information

Local Option Sales Tax Report Card Your Penny At Work. District 4

Local Option Sales Tax Report Card Your Penny At Work. District 4 Local Option Sales Tax Report Card Your Penny At Work District 4 Local Option Sales Tax 2007-2017 Report Card Your Penny At Work Transportation $153,816,450 Public Facilities $50,384,889 Natural Resources/

More information

Cover section: Buildings

Cover section: Buildings Buildings easy Index 1. Definitions that apply to your building section 2 2. Conditions for cover 2 3. What we cover 2 4. Main cover 3 5. Additional benefits 3 6. Optional benefits 5 7. Specific exclusions

More information

Brookwood Homeowners Association, Inc.

Brookwood Homeowners Association, Inc. RESERVE STUDY Full Study Brookwood Homeowners Association, Inc. Published - February 05, 2013 Browning Reserve Group / Emmett, ID 83617 Office (208) 365-0977 Tony@BrowningRG.com / www.browningrg.com Browning

More information

APPROVED CAPITAL BUDGET

APPROVED CAPITAL BUDGET 2011-2013 APPROVED CAPITAL BUDGET Administration Administration Capital Revenues Operating (86,400) (86,400) (86,410) (259,210) Reserves (513,317) (145,000) (50,000) (708,317) Provincial Transfers (1,114,373)

More information

Robert Shaw Theme Elementary

Robert Shaw Theme Elementary DeKalb County School District/Elementary Schools Robert Shaw Theme Elementary Final School Assessment Report May 20, 2016 PARSONS School Assessment Report Table of Contents School Executive Summary 4 School

More information

THE CLARIDGE OF POMPANO CONDOMINIUM, INC. ARCHITECTURAL REVIEW COMMITTEE REQUEST FOR MODIFICATION PART A - COMPLETED BY OWNER

THE CLARIDGE OF POMPANO CONDOMINIUM, INC. ARCHITECTURAL REVIEW COMMITTEE REQUEST FOR MODIFICATION PART A - COMPLETED BY OWNER THE CLARIDGE OF POMPANO CONDOMINIUM, INC. ARCHITECTURAL REVIEW COMMITTEE REQUEST FOR MODIFICATION PART A - COMPLETED BY OWNER I, of UNIT # request approval by the Architectural Review Committee for the

More information

City of Denton Debt Summary Report Fiscal Year Ending September 30, 2017

City of Denton Debt Summary Report Fiscal Year Ending September 30, 2017 Debt Summary Report Contact: City of Denton Finance Department Attn: Antonio Puente, Jr. Director of Finance 215 E. McKinney St. Denton, Texas 76201 Email: Antonio.Puente@cityofdenton.com Phone: 940-349-8566

More information

Social Housing Administration Directive No

Social Housing Administration Directive No Regional Municipality of Halton Social Housing Administration Directive No. 06-05 Date: August 30, 06 To: Federally-Funded Social Housing Providers subject to Operating Agreements under Section 95 of the

More information

M-NCPPC, Montgomery Department of Parks Proposed FY13-18 Capital Improvements Program List of Project Description Forms (PDFs)

M-NCPPC, Montgomery Department of Parks Proposed FY13-18 Capital Improvements Program List of Project Description Forms (PDFs) M-NCPPC, Montgomery Department of Parks Proposed FY13-18 Capital Improvements Program List of Project Description Forms (PDFs) Bold = Projects with County Executive's Recommended Change PDF # PDF Title

More information

Pleasantdale Elementary

Pleasantdale Elementary DeKalb County School District/Elementary Schools Pleasantdale Elementary Final School Assessment Report May 20, 2016 PARSONS School Assessment Report Table of Contents School Executive Summary 5 School

More information

to year to. reflect the County. Funds in Strategic

to year to. reflect the County. Funds in Strategic Five-Year Capital Improvement Plan Introduction The proposed five-year Capital Improvement Plann (CIP) forr FY 2012-13 throughh FY 2016-17 is the County s compilation of a long-term list of significant

More information

CAPITAL IMPROVEMENT PLAN

CAPITAL IMPROVEMENT PLAN CAPITAL IMPROVEMENT PLAN This section of the Pinellas County Annual Operating and Capital Budget document contains information on the Capital Improvement Program (CIP). The CIP is a comprehensive ten-year

More information

CAPITAL IMPROVEMENTS ELEMENT

CAPITAL IMPROVEMENTS ELEMENT [COMPREHENSIVE PLAN] 2025 INTRODUCTION EXHIBIT F CAPITAL IMPROVEMENTS ELEMENT A primary purpose of the Capital Improvements Element (CIE) is to assess and demonstrate the financial feasibility of the Clay

More information

Board of County Commissioners. Workshop/Meeting Tuesday, April 8, :00 A.M. School Board Administrative Complex

Board of County Commissioners. Workshop/Meeting Tuesday, April 8, :00 A.M. School Board Administrative Complex Board of County Commissioners Workshop/Meeting Tuesday, April 8, 2014 9:00 A.M. School Board Administrative Complex Workshop Goals and Objectives 1) To Provide Both a Long and Short Term Overview of Major

More information

CAPITAL FUNDS 2015 Budget

CAPITAL FUNDS 2015 Budget CAPITAL FUNDS This section provides comparisons of revenues and expenditures/appropriations for all capital funds for 2014 2016, the 2017 budget, and the 2018 2022 plan. Historical fund balances and the

More information

Marion County Marion Public County Works Public Building Works Inspection Division

Marion County Marion Public County Works Public Building Works Inspection Division FEE SCHEDULE The final determination of valuation, occupancy, and/or construction type under any of the provisions of this order shall be made by the Building Official. A. Structural Permits: The valuation

More information

THE FLOOD HAZARD AREA Valda Opara New Jersey Department of Environmental Protection June 8, 2012

THE FLOOD HAZARD AREA Valda Opara New Jersey Department of Environmental Protection June 8, 2012 THE FLOOD HAZARD AREA Valda Opara New Jersey Department of Environmental Protection June 8, 2012 Individual Permits Building Requirements 0% Net-fill Standards JET SKIING DURING A FLOOD ESCAPING THE FLOOD

More information

City of Des Moines. Citizen Engagement Capital Improvement Program. November 29, 2016

City of Des Moines. Citizen Engagement Capital Improvement Program. November 29, 2016 City of Des Moines Citizen Engagement Capital Improvement Program November 29, 2016 Goals of Citizen Engagement Goal Focus on service levels Department definitions of adequate service and opportunities

More information

Purpose of LOST SALES AND USE TAXATION. Local Option Sales Tax (LOST) Taxation 101 Larry Hanson City Manager City of Valdosta June 26, /16/2017

Purpose of LOST SALES AND USE TAXATION. Local Option Sales Tax (LOST) Taxation 101 Larry Hanson City Manager City of Valdosta June 26, /16/2017 SALES AND USE TAXATION Taxation 101 Larry Hanson City Manager City of Valdosta June 26, 2017 Local Option Sales Tax (LOST) Purpose of LOST To assist in funding governmental services authorized by the Constitution

More information

CITY OF FORT PIERCE BUILDING DEPARTMENT

CITY OF FORT PIERCE BUILDING DEPARTMENT CITY OF FORT PIERCE BUILDING DEPARTMENT APPLICATION FOR DETERMINATION OF SUBSTANTIAL IMPROVEMENT This is a request for determination by the City s Floodplain Administrator as to whether or not the project

More information

CITY OF JENKS COMMERCIAL BUILDING PERMIT P.O. Box N. Elm Jenks, OK 74037(918)

CITY OF JENKS COMMERCIAL BUILDING PERMIT P.O. Box N. Elm Jenks, OK 74037(918) CITY OF JENKS COMMERCIAL BUILDING PERMIT P.O. Box 2007 211 N. Elm Jenks, OK 74037(918) 299-5883 CERTIFICATE OF OCCUPANCY: DATE RECEIVED: BUILDING ADDRESS: LOT: BLOCK: ADDITION: SECTION: TOWNSHIP: RANGE:

More information

SPECIAL COUNCIL MEETING MARCH 6, Capital Improvements

SPECIAL COUNCIL MEETING MARCH 6, Capital Improvements SPECIAL COUNCIL MEETING MARCH 6, 2012 Capital Improvements 1 CAPITAL PROJECTS Review Requests from the Departments for FY 2012-13 Capital Improvements and Machinery & Equipment Discussion and Recommendations

More information

CAPITAL IMPROVEMENT PLAN

CAPITAL IMPROVEMENT PLAN CAPITAL IMPROVEMENT PLAN This section of the Pinellas County Annual Operating and Capital Budget document contains information on the Capital Improvement Program (CIP). The CIP is a comprehensive ten-year

More information

Ballot Measures-T Section

Ballot Measures-T Section T, Westminster School District Classroom Improvement Measure To upgrade aging schools and improve the quality of education with funding that cannot be taken by the State; provide heating, ventilation and

More information

Overview of Public Schools CIP

Overview of Public Schools CIP Overview of Public Schools CIP The Public Schools Community Investment Plan (CIP) includes school construction, such as additions and modernizations, as well as other school-related projects. School construction

More information

STORMWATER MANAGEMENT FUND Department of Environmental Services

STORMWATER MANAGEMENT FUND Department of Environmental Services Department of Environmental Services Mission: To implement a comprehensive stormwater management program that balances the following goals: 1) to reduce the potential for stormwater threats to public health,

More information

CAPITAL PROJECTS FUNDS

CAPITAL PROJECTS FUNDS CAPITAL PROJECTS FUNDS Capital projects funds are used to account for and report financial resources that are restricted, committed, or assigned to expenditure for capital outlays, including the acquisition

More information

CAPITAL RESERVE STUDY. Meadow Wood Commons. City, State

CAPITAL RESERVE STUDY. Meadow Wood Commons. City, State CAPITAL RESERVE STUDY FOR THE Meadow Wood Commons City, State Management Company: Any Management Company Contact Name: Mr. Bob Smith Date: July 28, 2014 Table of Contents Section Name Section # Executive

More information

Description of Fund Types and Funds

Description of Fund Types and Funds Financial activities for local government fall into three broad categories, governmental, proprietary, and fiduciary fund categories. Governmental funds are used to account for activities primarily supported

More information

Combining & Individual Fund Statements & Schedules

Combining & Individual Fund Statements & Schedules Combining & Individual Fund Statements & Schedules Provides detailed statements for the nonmajor Special Revenue and Capital Projects Funds and the Agency Fiduciary Funds, budget to actual schedules for

More information

FEE SCHEDULES. Class "B" Fermented Malt $ per year

FEE SCHEDULES. Class B Fermented Malt $ per year FEE SCHEDULES Exhibit A LIQUOR LICENSE Class "A" Fermented Malt $ 100.00 per year Class "B" Fermented Malt $ 100.00 per year Picnic $ 10.00 per day Wholesalers Fermented Malt Beverage $ 25.00 per year

More information

CHAPTER 11. CAPITAL FACILITIES PLAN ELEMENT

CHAPTER 11. CAPITAL FACILITIES PLAN ELEMENT CHAPTER 11. CAPITAL FACILITIES PLAN ELEMENT 11.1 INTRODUCTION A is one of eight elements required by the Growth Management Act (GMA) to be included in Yakima County s comprehensive plan. The reason for

More information

SECTION 6: CAPITAL IMPROVEMENT DETAIL

SECTION 6: CAPITAL IMPROVEMENT DETAIL SECTION 6: CAPITAL IMPROVEMENT DETAIL Summary... 1 General Government... 2 Public Safety... 6 Public Works... 12 Recreation and Leisure... 18 Education... 24 SUMMARY TOTALS CAPITAL IMPROVEMENT PLAN AND

More information

City of Chicago, Illinois Chicago O Hare International Airport

City of Chicago, Illinois Chicago O Hare International Airport City of Chicago, Illinois Chicago O Hare International Airport Basic Financial Statements for the Years Ended December 31, 2005 and 2004, Required Supplementary Information, Additional Information, Statistical

More information

PDFs follow in order listed above.

PDFs follow in order listed above. M-NCPPC, Montgomery Department of Parks Proposed FY13-18 Capital Improvements Program List of Project Description Forms (PDFs) PDF # PDF Title PDF # PDF Title Acquisition 767828 Acquisition: Local Parks

More information

Resurrection Lutheran Church. Replacement Reserve Report FY November 2018

Resurrection Lutheran Church. Replacement Reserve Report FY November 2018 Resurrection Lutheran Church Replacement Reserve Report FY 2019 November 2018 Replacement Reserve Study and Report was prepared, under contract, by MillerDodson a Capital Reserve Consultant, in Annapolis,

More information

Dillingham - Dillingham Library and Museum Building Roof Repairs

Dillingham - Dillingham Library and Museum Building Roof Repairs Total Project Snapshot Report 2012 Legislature TPS Report 56142v2 Agency: Commerce, Community and Economic Development Grants to Municipalities (AS 37.05.315) Grant Recipient: Dillingham Project Title:

More information

Spartanburg County South Carolina. Recommended Capital Improvement Plan

Spartanburg County South Carolina. Recommended Capital Improvement Plan Spartanburg County South Carolina Recommended Capital Improvement Plan Fiscal Year July 1, 2017 through June 30, 2022 Includes FY 2017/18 Capital Year Budget Jeffrey A. Horton Chairman Michael Brown Council

More information

CR# Issued Date: June 14, 2016 Waterville, OH

CR# Issued Date: June 14, 2016 Waterville, OH SECTION 00 65 36 - WARRANTY FORMS PART 1 - GENERAL 1.1 SUMMARY A. Section includes: 1. The following warranty forms: a. Building Warranty b. Kroger Asphalt Paving Warranty c. Kroger Roof System Limited

More information

Use of State and District Construction Funds

Use of State and District Construction Funds 8 Use of State and District Construction Funds Through its long-range planning process, the district has met its facilities needs without issuing significant debt. To improve cost efficiency, however,

More information

STORMWATER MANAGEMENT FUND DEPARTMENT OF ENVIRONMENTAL SERVICES

STORMWATER MANAGEMENT FUND DEPARTMENT OF ENVIRONMENTAL SERVICES DEPARTMENT OF ENVIRONMENTAL SERVICES Mission: To implement a comprehensive stormwater management program that balances the following goals: 1) to reduce the potential for stormwater threats to public health,

More information

Estimating capital requirements, budgeting priority projects and developing revenue sources for proposed improvements.

Estimating capital requirements, budgeting priority projects and developing revenue sources for proposed improvements. Capital Improvements A Capital Improvement Program is a schedule of public improvements to be constructed with resources available to finance the projected expenditures. Capital Improvements are expenditures

More information

Highlights from the Proposed Budget Fiscal Year

Highlights from the Proposed Budget Fiscal Year Highlights from the Proposed Budget Fiscal Year 2018-2019 City of Plant City Florida Budget Highlights KEY BUDGET HIGHLIGHTS: This budget is a responsible, proactive spending plan that will benefit Plant

More information

INTRODUCTION. Summary of revenue/expenditures available for new construction and remodeling projects only. CERTIFICATION

INTRODUCTION. Summary of revenue/expenditures available for new construction and remodeling projects only. CERTIFICATION INTRODUCTION The 5-Year District Facilities Work Program is a very important document. The Department of Education, Legislature, Governor's Office, Division of Community Planning (growth management), local

More information

CITY OF ROSEBURG, OREGON TABLE OF CONTENTS ENTERPRISE FUNDS

CITY OF ROSEBURG, OREGON TABLE OF CONTENTS ENTERPRISE FUNDS TABLE OF CONTENTS ENTERPRISE FUNDS Storm Drainage Fund... 121-124 Off Street Parking Fund... 125-126 Airport Fund... 127-131 Water Service Fund... 132-145 STORM DRAINAGE FUND CURRENT OPERATIONS This fund

More information

Section III.C. Capital Investments Plan

Section III.C. Capital Investments Plan Section III.C. Capital Investments Plan Section III.C. Capital Investments Plan 61 The capital facilities of local governments are essential to meeting the service needs of the community in an efficient

More information

CITY OF SACRAMENTO CALIFORNIA. April 27, 2012

CITY OF SACRAMENTO CALIFORNIA. April 27, 2012 OFFICE OF THE CITY MANAGER CALIFORNIA April 27, 2012 CITY HALL 5 th FLOOR 915 I STREET SACRAMENTO, CA 95814-2684 PH 916-808-5704 FAX 916-808-7618 Honorable Mayor and City Council Sacramento, California

More information