1 HINDUSTAN PETROLEUM CORPORATION LIMITED Tender Document for Qualitative Risk Analysis & Disaster Management Plan of Depots/Terminals November 2011

2 Index Sl. No Description Page No A Brief of Locations 5 B Deliverables & Detailed Response Requirements 7 C Scope of Job 12 C1Qualitative Risk Analysis 15 Hazop Study Consequence Analysis Event Tree Analysis Fault Tree Analysis Emergency Preparedness and Disaster 23 C2 Management Plan D Pre Qualification criteria 29 E Guidelines for proposal submission 35 F Vendor Profile and Support Requirements 40 G General Terms and Conditions 43 Attachment I Confidentiality Agreement Attachment II Integrity Pact 58 Attachment III Bank Mandate Attachment IV List of Locations

3 NIT TEXT: This is an e-tender and bids are to be submitted on line only at Response in any other form shall not be accepted. For bidding it is suggested that bidders should not wait for last date / tender due date for their bid preparation as several documents are to be uploaded in the offer and prices are to be entered on screen for all the items. There is a facility to keep the bid ready in the system for final submission. However, bidders are requested to keep sufficient time margin with them for modifications, connectivity issues etc. All the items of the tender are mandatory. Scope of job includes carrying out Qualitative Risk Analysis including Vapor Cloud Explosion scenario and Preparation of Disaster Management Plan across seven geographical zones of HPCL across the country. The job is proposed to be awarded to multiple vendors. Selection of the parties would be done as per the following process. The entire list of locations is made into three groups Group A, Group B & Group C. Accordingly the tender has been divided in 3 Parts HD Part 1, e tender no: 8376 for QRA and DMP for Group A Locations HD Part II, e tender no: 8378 for QRA and DMP for Group B Locations HD Part III, e tender no: 8381 for QRA and DMP for Group C Locations Group A includes all large locations having storage capacity of >30000 KL Group B includes all medium sized locations having storage capacity between KL & KL

4 Group C includes all small locations having storage capacity of <10000 KL Where ever reference is made in the tender about Group A, Group B and Group C, it should be treated as though reference is made to the cluster of locations as mentioned above. Itemized rates for individual group of locations as per the above description shall be quoted by the tenderers. HPCL proposes to finalize the job to multiple vendors. Evaluation would be carried out on the basis of lowest quoted amount for Group A ie e tender 8376, Group B ie e tender 8378 and Group C ie 8381 individually. Following process would be adopted for selection of vendors: Step 1: Price bids of all technically qualified parties for e tender 8376 would be opened in respect of locations under Group A. L1 bidder under this Category would be awarded the job for all locations under Group A. Step 2: Price bids of all technically qualified parties, excepting the L1 bidder for e tender 8378 under Group A, would be opened in respect of locations under Group B. L1 bidder would be awarded the contract under this category. Step 3: Price bids of all technically qualified parties of e tender 8381 would be opened in respect of locations under Group C. L1 bidder under this Category would be awarded the job for all locations under Group C. Order would be finalized on the parties who had quoted the lowest value under the respective e tenders. For details please refer tender document. In case of discrepancy between details given here (NIT text) & tender document, the details / terms of tender document shall prevail. The taxes mentioned in

5 techno-commercial sheet on-line (service tax, works contract tax etc.) will be added to the rates quoted by bidder for arriving at total offer value. Please enter the applicable taxes in % there and zero can be put against non applicable taxes.

6 A.Brief on Locations

7 Brief on Locations 1. HPCL has Depots and Terminals across India where Petroleum Products are received, stored and further distributed to Retail Outlets / Consumers. Huge quantities of Petroleum Products are stored at these installations. 2. Qualitative Risk Analysis (QRA) is required to be carried out for each installation to assess the risk. The QRA will form the basis for designing the facilities and also preparation of Disaster Management Plan (DMP). 3. No two locations are identical with respect to layout, surroundings, products, storage quantities, meteorological data etc. Therefore QRA and DMP will be location specific and no effort shall be made to replicate the QRA & DMP of another location. 4. QRA & DMP shall be prepared conforming to various statutory requirements Factories Act (as amended in 1987). Manufacture, Storage and Import of Hazardous Chemicals Rules, 1989 (amended in 1994) [ MSIHC ] OISD-GDN-168: Emergency Preparedness Plan for Marketing Locations of Oil Industry Any other statutory requirement applicable to the location 5. QRA shall include Vapour Cloud Explosion scenario also. 6. The necessary preventive and protective steps that are required to be taken before, during and after the accident need to be covered in the Disaster Management Plan. 7. Following details shall be covered in the analysis: a) Nature, causes, consequences of hazards b) Hazard analysis. c) Risk Analysis including Vapour Cloud Explosion Scenario c) Key personnel and their duties during an emergency. d) Steps to be taken before, during and after emergency. e) Response Evaluation and updation of the plan.

8 B. Deliverables & Detailed Response Requirements

9 A) Purpose of the Tender: Hindustan Petroleum Corporation Limited proposes to place P.O for carrying out Qualitative Risk Analysis and preparation of Disaster Management Plan for Terminal /Depots across the country. B) Scope of the Job: HPCL has got 95 POL installations. Sizes of the installations are broadly categorized based on the storage capacity as Large, Medium and Small installations and no. of installations in each category are as on date are under: Description No. of Installations Large Installation (>30000 KL) 27 Medium Installation(10000KL KL) 38 Small Installation (<10000 KL) 30 As per the prevailing statutory norms, QRA shall be prepared once in three years for operating locations as well as whenever modifications are proposed to be carried out at existing locations (addition / deletion of facilities). This tender is being floated for placing P.O Detailed scope and guidelines for carrying out QRA and preparation of DMP are covered in the following chapters. C) Deliverables: Deliverables shall include the following: Documents: 1. Brief on the Location and the facilities including capacities 2. HAZOP analysis 3. Consequence Analysis 4. Event Tree Analysis 5. Recommendations on Mitigation measures 6. Disaster Management Plan

10 Presentation to management: a. Location: A detailed presentation shall be made to the location in charge and the officers at the installation on the findings of the QRA study and the DMP. b. Zone: A consolidated presentation shall be made to the respective Zonal Heads of O&D covering the findings of the QRA study and the DMP prepared in respect the locations under their zone. Accordingly, separate presentations have to be made at EZ/NZ/NCZ/NWZ/SZ/SCZ/WZ Payment shall be processed in respect of the individual locations only if the confirmation of the location in charge that the presentation is made to their satisfaction and the documentary proof is attached to the bill. D) Methodology of Payment : Partial payments are allowed. Payments will be effected from Disbursement section, Hindustan Bhavan, HB-4 Party shall submit the bill along with the report and other deliverables as per scope of the tender within 15 days of completion of the job at each location. Bill along with the attachments shall be submitted to DGM-Operations, HB-2. Payments shall be made within 15 days of receipt of certified bills at Disbursement section. Applicable Tax will be deducted at source. No advance payment will be made. The payment shall be tendered to the agency in electronic mode (e-payment) through any of the designated banks. The agency will comply by furnishing full particulars of bank account (mandate) to which the payments will be routed. Owner reserves the right to make payment in alternate mode also. E) Rates: The party has to quote lump sum rates per location. F) Completion Period: Entire job as per scope of this tender shall be completed within a period of SIX MONTHS from the date of releasing P.O/LOI. Detailed Response Requirements Scope, Approach, and Methodology:

11 This section will act as the scope of the work which is to be used as a guideline by the agency during the job execution. This section should include a description of each of the major elements of work being requested, method and approach used to manage the overall project including the details of engagement from beginning to end of the proposed project. All information that you provide will be held in strict confidence. Sample Reports: This includes samples of the reports to be used to provide and summarize information as per the Deliverables mentioned above. Important note: The bidder shall enclose one sample report of the QRA & DMP prepared for any major hazardous installation preferably a Petroleum Installation (Largest installation for the purpose is defined as any installation having storage capacity of more than KL/MT. Quality of the report will form part of the evaluation process for shortlisting of the vendors during technical evaluation. Profile of the Project Team : Please describe the personnel profile of Specialist/ agency Team who will be engaged on full time and part time basis, in the following manner: Name Designation Age Photograph Academic Qualifications Details of working experience prior to the current assignment, if any Affirm that no employees working on this proposed project have ever been convicted of a felony. Company Overview It should include Official registered name, Address, Key contact name, Title, Address, Telephone numbers (Landline and Mobile) and addresses. Detailed and itemized pricing: As per price bid

12 Other Requirements: 1. Quality Assurance Definite Quality Assurance Process to ensure complete achievement of scope has to be brought out and the Agencies are to assist the Organization for smooth implementation of the same. Any part or total process under the project may be audio/video-recorded by HPCL for its uses. 2. Documentation End to end documentation for the entire process should be prepared by the agency and made available to the Corporation. Weekly progress of the process would have to be documented for the review of the concerned HPCL officials. Written feedback is to be obtained and submitted to HPCL. Besides, agency is required to provide the list of documents which will be provided to the executives of the corporation during the entire process. The rights to use and circulate data/documents used and generated during the project will be vested with HPCL. 3. Others Travel, Boarding and Lodging arrangements, arrangement of computers and other logistical support etc. should be arranged by the agency only. All the costs for the same may please be included in the items of price bid.

13 C.Scope of Job

14 Nature, Causes and Consequences of Hazards. A. Nature of Hazards Accidents leading to an emergency in the Petroleum Installation may be due to one or more of the following events: a) Release of flammable liquids or gases resulting in vapour clouds/ fire/ explosion and consequent thermal radiation and smoke. b) Spillages on ground or into water resulting in pollution / contamination of air, water etc. c) Emergency arising from neighborhood. B. Causes Common causes for the above events may be due to any one of the following reasons a) Electrical: Short circuiting due to loose wiring. Use of non-flame proof fittings such as lights, torch, motors, fan, telephone, temporary lighting etc. Static electricity as result of improper bonding / grounding to tanks, conveyor system, tank truck, tank wagon etc. b) Vehicle : Defective spark arrestors. Operation of non-flp electrical switches such as vehicle ignition. Spark from the loose contact on vehicle batteries. Spark from exhaust of railway engine. c) Others Landing of crackers (flying type ) in hazardous areas. Spark from Chiselling / hammering. Lighted agarbatti. Excessive release of vapour beyond safe limit and fire due to outside source of ignition. Lightning Smoking

15 C. Consequences : The consequences of an accident may be confined within the premises or may spill to off-site triggering cascading effects. The occurrence is considered On-site when the accident occurs within and effects are confined to the premises involving only the people working in the unit. The consequences of an accident are fire explosion, deflagration, blast waves, fast spreading flames resulting in direct effects like damage to buildings/property, burns, fatalities. However, an accident in the neighbourhood may sometimes cascade into an on-site emergency. D. Scope for Emergency Planning : The emergency planning needs to focus on following three types of scenarios: i) The emergency occurs within the installation premises and is confinable and controllable with available resources (onsite emergency). ii) The onsite emergency not controllable with available resources and assistance from mutual aid industries are required. iii) The impact of the emergency goes beyond the boundary of installation area and surrounding area / population is likely to get affected. The district administration is alerted for help along with mutual aid partners to effectively respond (offsite emergencies).

16 C1.Qualitative Risk Analysis

17 Risk Assessment A. Hazard Analysis Assessing the hazard potential of an installation is the first step in planning for emergencies. To analyze and to assess the potential hazards and safety of an installation, hazard analysis shall be carried out covering the following areas: a) Identify the products which are Hazardous in nature b) Design deficiencies likely to contribute to Hazard c) Identify the likely failures or errors that could cause abnormalities leading to an accident d) Consequences of a major accident on the workers, people in neighborhood and the environment. e) Mitigation of the consequences of an accident. f) Measures for preventing the accident. The three basic steps of hazard analysis are: a) Hazard Identification b) Vulnerability analysis c) Risk analysis. Hazard Identification: Hazard identification shall include the following a) The types and quantities of hazardous products stored, handled and disposed in the location; b Layout of storage tanks & other facilities. c) Potential hazards associated with the spillage and release. Various components of hazard identification are - a) Chemical Identity & Nature of Hazard - The stored products shall be classified as toxic, flammable or explosive. b) Quantity - The estimation of quantity of each hazardous product at a location should include the maximum quantity likely to be stored on site. Location and Storage Condition: The location, configuration and condition under which the hazard products are stored, handled shall be taken into account while carrying out the risk analysis. The inter-distances play an important role for assessing the

18 consequential risk due to the impact from emergencies arising at other facilities. This aspect shall be considered while recommending the fire protection system for each individual facility. B. Vulnerability Analysis: Vulnerability analysis is the second step of hazard analysis and provides estimation of the zones of influence or vulnerable zones. The process of estimation of zone of influence comprises of the following : a) The maximum single storage of hazardous product should be identified and then probable maximum loss scenario should be determined. b) Considering the probable maximum loss scenario, the vulnerable zone(s) that will be affected by the effect/consequences of the accident should be considered. Depiction of vulnerable zones should be done by drawing the contours of various emergency damage distances for the identified scenarios on the plot plan with the surrounding area maps, to know the extent of emergency effects. In case of Fire, the thermal radiation zones should be shown whereas for explosion, the overpressure zones could be depicted. Hazard or vulnerability mapping will be used both for onsite as well as offsite emergency management. Hazard maps identify and display the location of hazard zones, areas where there are dangers to humans and their property and depict hazard zone geometries. Risk maps can be drawn based on calculation of the conditional probability that a given area will experience a particular hazard or a combination of hazards. To estimate the effects of the accident and draw evacuation plan, following data shall be collected Population statistics- No. of people likely to be affected within the installation as well as in the near vicinity Facilities and the environment encompassed within the vulnerable zone should be identified. C. Risk Analysis: Risk analysis is the third step of hazard analysis process. Risk Analysis provides a relative measure of the likelihood and severity of various possible hazardous events and enables the emergency plan to focus on the greatest potential risk.

19 Risk is defined as: Risk = Consequence x Probability Risk assessment must consider both catastrophic and less severe release. In other words, all scenarios which are likely to lead to emergency situations shall be considered for the purpose of Risk Assessment. Accordingly the recommendations for fire protection design and mitigation methods shall be made for each scenario of risk. The risks associated with failures include catastrophic failures like tank collapse, rupture of vessels etc. as well as the less severe releases like gasket leak/failure, tank filling piping failure, hose rupture etc. After calculating the risk, it must be brought to a level of "Maximum Tolerable Criterion" above which the risk is regarded as intolerable. The risk should also be made "As Low As Reasonable Practicable. Quantitative assessment of risk shall be worked out considered by determining the following factors: probability of occurrence of each event likely to occur consequence of each event Calculate the risk by multiplying the probability of occurrence of each event by the consequences of that event. Probability of occurrence: The events which are likely to produce hazardous situations shall be identified. a) Heat effects. b) Over pressure effects. Types of event normally considered in risk analysis at POL installationsare those that lead to one or more of the following : a) Flammable vapour cloud fire (burning of a flammable gas/air mixture). b) Toxic vapor cloud (toxic gas mixed with air) c) Storage tank on fire d) Pool fire (burning pool of liquid fuel) e) Torch fire (burning of gas or liquid being released under pressure) f) Vapour cloud explosion (rapid combustion of flammable gas outdoors) g) Physical explosion (failure of a pressure vessel due to internal pressure). h) Confined space explosion (rapid combustion of flammable gas in an enclosure). Following are some of the emergencies identified for risk evaluation:

20 Storage tank on fire (to be considered for each tank) Pool fire in tank farm (Combustion of a flammable liquid pool) Flange joint leakage in Pipelines Fire in TT / TW gantry. Hose rupture. Vent fire in lightening Jet fire (combustion of high pressure gas or liquid) Spray fire (combustion of a pressurized liquid release) Flash fire (combustion of a flammable gas where the flame propagates at a speed insufficient to result in damaging overpressures) Explosion (combustion of flammable gas /vapour in which confinement and /or flame velocities sufficient to result in damaging overpressure) Uncontrollable leakage of volatile product, evaporation and vapour cloud explosions and severe multi-tank fires. Besides the above, any other probable risk applicable to the location shall also be identified and shall be considered for Risk Evaluation. Hazardous event probability - Once the hazardous events are identified, the probability of each individual event occurring must be estimated. Such estimate can be based on following: a) historical data based on experience of identical/similar system b) generic failure rate for similar type of equipment. c) fault tree / event tree analysis d) engineering practices. Consequence Analysis - The expected adverse effects that would result if each hazardous event was to occur must be quantified before the risk can be determined. The adverse effects that may be quantified range from merely being exposed to a hazardous condition, to being fatally injured by exposure to the hazardous condition. During consequence analysis, it is necessary to take into account the population density and distribution around the facility. It is also necessary to know the minimum levels of exposure to hazardous conditions that will produce the consequences of the incident (for example, what is the minimum level of thermal radiation that is capable of causing burn injury/fatalities within particular exposure time etc.,) Only then can the consequences be

21 quantified by overlaying the hazard zones of interest on the local population, and counting the number of persons exposed to the hazard. Risk quantification: Once the probability of occurrence and potential consequence of a hazardous event has been quantified, the risk associated with that event can be calculated by multiplying the probability with consequence. Risk Matrix shall be prepared plotting the probability vs consequences of individual risks. Risk reduction measures - Risk calculated as per the above modality shall be compare with the minimum acceptable limit in respect of each facility individually and where ever the risk is assessed to be beyond acceptable limits, risk reduction / mitigation measures shall be recommended. It may be possible to reduce / mitigate the risk by risk reduction factors like: a) modifying the facility to eliminate or reduce the probability of occurrence of hazardous events. b) modifying the facility so that hazardous events are eliminated. c) restricting the consequence of some of the events by improving hazard mitigation systems. d) reducing the exposed population by increasing safe distances by acquiring property around the facility. Important Note: The Risk Reduction Measures shall be recommended for the location based on the Risk Analysis study. The Statutory Regulations stipulate the minimum standards. Location specific recommendations for the risk mitigation shall be submitted along with final report. Quantities of various Fire Fighting equipment required shall be worked out. Positioning of the various Fire fighting equipment shall be plotted on the layout and submitted. Back up data for the quantities of Fire Fighting Equipment shall be included in the report. Hazard Analysis Methods a) Hazard and Operability Study. b) Accident Consequence Analysis. c) Event Tree Analysis. d) Fault Tree Analysis.

22 a. Hazard and Operability Study (HAZOP): The technique plays a vital role in the hazard identification step. A systemic approach shall be adopted for the HAZOP study to identify all possible deviations from normal operation. It shall also establish the likelihood and consequences of events. Deviations that could lead to a hazardous event or operability problem are to be identified. Consequences of possible deviations are assessed and potential means for detection and correction shall be examined. b. Accident Consequences Analysis: The method is used in the analysis of identified hazard. An accident consequences analysis should be carried out to determine the consequences of a potential major accident on the Installation, the workers, the neighbourhood and the environment. It should contain: a) A description of the potential accident ( tank fire, pool fire, rupture of pipeline, tank truck on fire at Tank Truck Loading Gantry, failure of safety valve and fire ). b) An estimation of quantity of hazardous materials released ( flammable and explosive ). c) Where appropriate, a calculation of the dispersion of the material released (gas or evaporating liquid like Naphtha/gasoline). d) An assessment of the harmful effects ( heat radiation blast wave ). The techniques of accident consequence analysis should include physical models for dispersion of pollutants in the atmosphere, propagation of blast waves, thermal radiation etc. depending on type of hazardous substance present in the Installation. The results of the analysis should be used to determine which preventive measures such as fire fighting system, alarm system of pressure release system are required Event Tree Analysis: This is a formalized deductive technique that works forward from specific events or sequences of events that could lead to an accident. It graphically displays events that could result in hazards and can be used

23 to calculate the likelihood of an accident sequences occurring. ETA process shall be adopted for Hazard identification Fault Tree Analysis This is a formalised deductive technique that works backward from an accident defined to identify and graphically display the combination of equipment failures and operational errors that lead up to the accident. This method can be used to estimate the quantitative likelihood of events. FTA process shall be adopted for Consequence analysis.

24 C2. Emergency Preparedness & Disaster Management Plan

25 Emergency Planning and Response Disaster Management Plan (DMP) is a pre-plan to handle any emergency situation. Some of the identified emergencies are: Uncontrollable leakage of Hydro carbons. Lightning Heavy floods Earthquakes/ land slides Sabotage/ terrorist outrage War situation DMP shall be developed with an overall objective reduce the possible consequences of the emergency by: Preventing fatalities and injuries; Minimizing damage to property and environment. Minimizing impact to neighbouring Industries and outside locality. Quick restoration of normal operations. Due to varying risk potentials and also varying hazards at/ around each location Disaster Management Plan' for each location shall be drawn up individually based on the outline given below: (i) Identify Disaster scenario i.e. the situation under which the plan would become operational. Plan shall be drawn for the worst possible scenarios. (ii) Identify resources required from each of the outside agencies. (iii) Establish outside agencies, role of each agency and obtain their commitment for rendering the assistance in crisis situation as per the agreed plan. (iv) Establish organogram for Disaster Management based on available manpower in various groups and identify the leader and alternative leader for each for the groups and the role to be played by each team in various likely crisis situations. (v) Identify Disaster control room / group. (vi) Furnish detailed data and drawings relevant for the crisis management. (vii) Establish channel of communication at the local level to Statutory Authorities and higher authorities within the organisation.

26 Disaster Management shall deal with the following aspects: Command, Control, and emergency communications. Safety of people and other livestock (preventing fatalities and injuries) Protection of company properties and plant (Minimizing damage to buildings, materials, and equipment) Recovery and Restoration of industrial activity (Hastening of the resumption of normal operations) Administration and Logistics supports Dealing with community concerns. Hastening of the resumption of normal operations Contents of an Onsite Emergency Planning. Roles and responsibilities of Company employees as well as contractor workmen shall be identified. Emergency Response Plan (or Disaster Management Plan) to be drawn out in coordination with related outside agencies, such as local administration, Police authorities, Fire Brigade, hospital authorities, home guards, neighbouring industries etc. Brief Description of activities/operations and information on storages with built-in control measures. Operation/handling hazards and the control measures. Other hazards (mechanical, electrical and biological) and control measures with Hazardous Area Classification. Details of the Risk picture(qualitative and/or Quantitative) based on risk analysis i.e. Frequency-wise and Consequence-wise) Location specific Credible Emergency Scenarios identified and its description of consequences including evacuation distances. Scenario-specific emergency actions or responses Evacuation Plan and Assembly Points Emergency Alerting Procedures(1st and 2nd alerts) Roles and Responsibility of Emergency Controllers/Coordinators, Key personnel with their contact details. Emergency Control Room, its Staffing and Facilities Resources availability for Onsite Disaster Details of First-aid and Medical facilities

27 Emergency Alarm and Siren Details Emergency Transport Arrangements Details of other essential facilities MSDS Information Pollution Abatement and Control Measures Information on Waste Disposal Weather Details and Atmospheric Conditions Internal & External Communication facilities and procedures Offsite Emergency Information and resource sharing Mutual-aid Schemes and resources availability Declaration of Onsite Emergency(Responsibility & Procedure) Procedures to inform authorities including Statutory Authority Procedures to provide authoritative and verified information to the news media. Procedures for Treatment of injured, identify the fatalities and to inform and help relatives. Procedures for All Clear proclamation Procedures to assess damages and the Insurance claim. Procedures to ensure safety of the works before personnel re-enter and resume work to maintain business continuity. Procedures to preserve records, equipment etc. and to organize investigation into the cause of the emergency and to suggest preventive measures to stop its recurrence Procedures for periodical rehearsal of the plan. Procedures for Updating the Plan Procedures for dissemination of Emergency information to all interested parties e.g. employees, contractors personnel, visitors etc. Fire Fighting Organisation Plan The Fire Organization Plan shall include the following activities:

28 Display of important telephone numbers viz fire brigade, ambulance, Police etc. Blowing the fire siren. Shutting / cut off the source of hydro carbon any leakage point/ fire. Summoning the fire brigade / police. Fire control, with first aid, fire fighting equipment. Operation of fixed water sprinkler system on storage tanks / TW gantry Starting of fire pump (s) and application of water hose jets/ sprays for containing/ extinguishing fires. Cooling of storage tanks and other equipment / facilities. Closing down all operations in the installation including closure of valves and stopping of pumps. Preventing all sources of ignition in case of hydrocarbon leakage. Evacuation of vehicles. Evacuation and mustering of personnel. Establishing an emergency fire control centre. Traffic control. Stations and duties of all personnel. Policing of affected areas. Any other specialised duties. All clear signal by competent person. Details of following agencies shall be incorporated in the DMP: a. local fire services b. police authorities c. voluntary organisations like ambulance service / Govt. medical service d. Home Guards e. Defence personnel. Communication organogram : Communication organogram shall be drawn up giving flow of communication from the originating location to various local agencies and also to Statutory Authorities and upwards within the organisation to mobilise support and to consider alternatives for maintaining essential supplies. Assembly Points : Pre-designated areas where the personnel like workers, staff, contractor workers etc. not involved in emergency operations (as per Emergency Plan) shall assemble in case of an emergency shall be identified and plotted on the layout. Depending on the location of the emergency, the

29 assembly point can vary. For each potential hazardous zone, a specific assembly point(s) shall be identified. Emergency Control Room & Equipment : Location for setting up of the emergency control room at a safe location shall be identified and marked on the site plan. The control room will be activated in case of an emergency to direct and coordinate the operations to handle the emergency. Facilities required to be provided at the Emergency Control Room shall be identified and listed in the Plan. Mutual aid Program 1. Mutual aid arrangements should be worked out in the Onsite plan to facilitate additional help in the following areas: i) fire fighting ii) rescue operation iii) manpower support iv) medical aid or v) Rescue, fire and life saving equipments etc.

30 D.Bid qualification Criteria

31 Interested parties must fulfil the criteria mentioned below and should attach documentary proof supporting the same: 1. Parties who are affiliates of one another can decide which Affiliate will make a bid. Only one affiliate may submit a bid. Two or more affiliates are not permitted to make separate bids directly or indirectly. If 2 or more affiliates submit a bid, then any one or all of them are liable for disqualification. However upto 3 affiliates may make a joint bid as a consortium, and in which case the conditions applicable to a consortium shall apply to them. Affiliate of a Party shall mean any company or legal entity which: (a) controls either directly or indirectly a Party, or (b) which is controlled directly or indirectly by a Party; or (c) is directly or indirectly controlled by a company, legal entity or partnership which directly or indirectly controls a Party. Control means actual control or ownership of at least a 50% voting or other controlling interest that gives the power to direct, or cause the direction of, the management and material business decisions of the controlled entity. 2. Offers may be submitted by: a) a single person/ entity (called sole bidder); b) a newly formed incorporated joint venture (JV) which has not completed 3 financial years from the date of commencement of business; c) a consortium (including an unincorporated JV) having a maximum of 3 (three) members; d) an Indian arm of a foreign company. 3. Fulfilment of Eligibility criteria and certain additional conditions in respect of each of the above 4 types of bidders is stated below, respectively: a) The sole bidder (including an incorporated JV which has completed 3 financial years after date of commencement of business) shall fulfil each eligibility criteria.

32 b) In case the bidder is a newly formed and incorporated joint venture and which has not completed three financial years from the date of commencement of business, then either the said JV shall fulfil each eligibility criteria or any one constituent member/ promoter of such a JV shall fulfil each eligibility criteria. If the bid is received with the proposal that one constituent member/ promoter fulfils each eligibility criteria, then this member/promoter shall be clearly identified and he/it shall assume all obligations under the contract and provide such comfort letter/guarantees as may be required by HPCL. The guarantees shall cover inter-alia the commitment of the member/ promoter to complete the entire work in all respects and in a timely fashion, being bound by all the obligations under the contract, an undertaking to provide all necessary technical and financial support to the JV to ensure completion of the contract when awarded, an undertaking not to withdraw from the JV till completion of the work, etc. c) In case the bidder(s) is/are a consortium (including an unincorporated JV), then the following conditions shall apply: i) Each member in a consortium may only be a legal entity and not an individual person; ii) The Bid shall specifically identify and describe each member of the consortium; iii) The consortium member descriptions shall indicate what type of legal entity the member is and its jurisdiction of incorporation (or of establishment as a legal entity other than as a corporation) and provide evidence by a copy of the articles of incorporation (or equivalent documents); iv) One participant member of the consortium shall be identified as the Prime member and contracting entity for the consortium; v) This prime member shall be solely responsible for all aspects of the Bid / Proposal including the execution of all tasks and performance of all consortium obligations; vi) The prime member shall fulfil each eligibility criteria;

33 vii) a commitment shall be given from each of the consortium members in the form of a letter signed by a duly authorized officer clearly identifying the role of the member in the Bid and the member s commitment to perform all relevant tasks and obligations in support of the Prime/lead member of the Consortium and a commitment not to withdraw from the consortium; viii) No change shall be permitted in the number, nature or share holding pattern of the Consortium members after prequalification, without the prior written permission of HPCL. ix) No change in project plans, timetables or pricing will be permitted as a consequence of any withdrawal or failure to perform by a consortium member; x) No consortium member shall hold less than 25% stake in a consortium; xi) Entities which are affiliates of one another are allowed to bid either as a sole bidder or as a consortium only; xii) Any person or entity can bid either singly or as a member of only one consortium. d) In case the bidder is an Indian arm (subsidiary, authorized agent, branch office or affiliate) of a foreign bidder, then the foreign bidder shall have to full fill each eligibility criteria. If such foreign company desires that the contract be entered into with the Indian arm, then a proper back to back continuing (parent company) guarantee shall be provided by the foreign company clearly stating that in case of any failure of any supply or performance of the equipment, machinery, material or plant or completion of the work in all respects and as per the warranties/ guarantees that may have been given, then the foreign company shall assume all obligations under the contract. Towards this purpose, it shall provide such comfort letter/guarantees as may be required by Owner. The guarantees shall cover inter alia the commitment of the foreign company to complete the entire work in all respects and in a timely fashion, being bound by all the obligations under the

34 contract, an undertaking to provide all necessary technical and financial support to the Indian arm or to render the same themselves so as to ensure completion of the contract when awarded, an undertaking not to withdraw from the contract till completion of the work, etc. 4. Financial criteria: The agency should have average financial turn over of INR lacs / year during the last three financial years ending 31 st March For the agencies following financial year closing at the end of June or September or December, the last 3 (three) financial years ending with the respective quarter of / will be considered. 5. Technical criteria: The bidder should be engaged in the business of conducting similar studies of QRA and preparation of DMP for a minimum period of 36 completed months during last 7 years ending 31 st October 2011 for a reputed Public Sector / Private Sector Organization. Bidders shall have experience of having successfully carried out and completed similar work as per any of the following: At least one order of value lacs OR At least two orders of value lacs each OR At least three orders of value lacs each Itemized rates for individual group of locations as per the above description shall be quoted by the tenderers. HPCL proposes to finalize the job to multiple vendors. Evaluation would be carried out on the basis of lowest quoted amount for Group A ie e tender 8376, Group B ie e tender 8378 and Group C ie 8381 individually. Following process would be adopted for selection of vendors: Step 1: Price bids of all technically qualified parties for e tender 8376 would be opened in respect of locations under Group A. L1 bidder under this Category would be awarded the job for all locations under Group A.

35 Step 2: Price bids of all technically qualified parties, excepting the L1 bidder for e tender 8378 under Group A, would be opened in respect of locations under Group B. L1 bidder would be awarded the contract under this category. Step 3: Price bids of all technically qualified parties of e tender 8381 would be opened in respect of locations under Group C. L1 bidder under this Category would be awarded the job for all locations under Group C. Order would be finalized on the parties who had quoted the lowest value under the respective e tenders. Pls furnish details of largest 5 work orders executed by the agency in last 7 years: Sr No Description of the job Organization Period Value of the Order (Purchase Order Copies to be attached) The short-listed vendors shall be required to make a detailed presentation of their experience and capability to HPCL at Mumbai at their own cost. The Commercial (priced) bids will be opened only for those agencies who secure more than 65% on overall basis, in the presentations. The presentation should be given by Agency on the following: 1. Capability alignment ( Max. Marks : 15) - Indian Size, Image, Presence with Resource profile - Team to be deployed & its profile 2. Understanding of requirements ( Max. Marks : 15) - Awareness of Business Context - Awareness of contextual issues

36 3. Methodology and Approach ( Max. Marks : 30) - Proposed Methodology - Suitability of the proposed methodology for HPCL - Flexibility of the Methodology 4. Strategy and Detailed plans (Max. Marks : 20) - Detailed strategy for the project - Innovative Approach 5. Expertise/ Experience in the field ( Max. Marks : 20) - Experience in similar work in Oil Terminals - Credentials - Indian Client s feedback The presentations will be reviewed by HPCL s panel and evaluated on the above parameters. During the presentation, the bidders are required to explain the modality they propose to adopt for achieving the following: a. Random generation of inspection schedules. b. Ensuring confidentiality of the schedules and inspection reports. c. Controls proposed to be exercised to ensure that inspectors deliver the job with utmost confidentiality and integrity. d. Procedure of releasing inspection to HPCL thru coordinator within 48 hrs of conducting the inspection. The Bidder fulfilling the criteria mentioned as above may submit the following details. Proof of company registration/ consortium/ JV Documentary proof of above turnover by submitting audited Balance sheet and Profit and Loss statement along with Certificate from Auditor Name, Designation and contact details of key Person(s) in the organization where similar jobs have been undertaken successfully. Performance certificates from minimum 2 (two) reputed clients of having successfully completed training programs similar to the programs proposed by HPCL.

37 6. DISQUALIFICATIONS Without prejudice, a bidder may be disqualified and the offer submitted may be dropped from further consideration for any of the reasons listed below: o Material misrepresentation by such bidder in the EOI or otherwise. o Failure by such bidder to provide the requisite information / documentation required to be provided while submitting the proposal as described in Section 4 & 5 above pertaining to financial and technical eligibility criteria. The companies / entities not satisfying the eligibility and requisite qualification criteria specified in the above sections are not eligible.

38 E. Guidelines for Proposal Submission

39 Overview The request for proposal for carrying out the job of Qualitative Risk Analysis & Preparation of DMP in two bid format Professional (unpriced) and Commercial (priced) is invited by Hindustan Petroleum Corporation Limited, hereinafter referred to as HPCL. The proposal should respond to all sections of this request for Professional (unpriced) and Commercial (priced) bid including agency profile and support requirements. Confidentiality All material and information provided by HPCL should be regarded as confidential information and not to be released to any other parties. This information will be made available to all members of the selection committee to assist in the evaluation process and the HPCL personnel involved. HPCL requires all agencies to adhere to highest standards of ethical behavior. Revision to Bid In the event it becomes necessary to revise any part of Bid document, HPCL reserves the right to issue amendments to the Bid. A written addendum will be provided via /registered/courier mail to all Bidders to whom the original Bid has been sent. Bid: Questions and Answers A. All questions concerning the Professional (unpriced) Bid documents may be brought to the attention of following. Shri. K.Somasekhara Rao Phone No: HPCL will compile all questions and answers, and make every effort to reply through /Telephone on a timely basis. The cut off query time will be 7 days before the due date of submission of bid. HPCL reserves the right to decline answering any or all questions and also reserve the right to share such information to all participating vendors.

40 B. Under no circumstances should the Bidder enter into negotiations concerning this Bid with representatives other than the authorized representative identified above. Failure to comply with the above requirements may result in disqualification of the Bid. Completeness of Bid Prior to the submission of the Bid, the Bidder shall make, and be deemed to have made a careful examination of the Bids. Each Bidder should thoroughly understand the requirements detailed in the document and will be required to comply with all Bid requirements. Submission of Responses has to be done on-line at site Responses in any other form shall not be considered. Detailed response to the methodology that would be adopted to ensure achievement o scope of the study as enumerated in the Section C of this Professional Bid (unpriced) document. Quality assurance process that would be adopted to ensure compliance of accepted methodology and plans Profile of the people to be deployed for the assignment. Any other relevant information, catalogues, brochures. Evaluation Process A. Professional (unpriced) Bid The Professional (unpriced) Bid submitted will be evaluated according to the following procedure:- 1. Professional Bid (Unpriced) submitted by the Bidder will be evaluated by the Corporation to determine if all of the Professional Bid requirements have been met, or if the Bidder has proposed an acceptable alternative. 2. Failure of the Bidder to provide any information required in this Professional Bid (Unpriced) may result in disqualification in the proposal. 3. HPCL will review each proposal and invite the agencies to make individual presentations at scheduled date and time. The presentations will be in Mumbai in a span of 2 or 3 different dates depending on the response to the tender and HPCL s convenience. A notice of 7 days will be given for

41 the agencies with regard to the scheduled date and time. Any requests for change in the scheduled date and time may or may not be considered by HPCL. The presentation should be given by Agency on the following: 1. Capability alignment ( Max. Marks : 15) - Indian Size, Image, Presence with Resource profile - Team to be deployed & its profile 2. Understanding of requirements ( Max. Marks : 15) - Awareness of Business Context - Awareness of contextual issues 3. Methodology and Approach ( Max. Marks : 30) - Proposed Methodology - Suitability of the proposed methodology for HPCL - Flexibility of the Methodology 4. Strategy and Detailed plans (Max. Marks : 20) - Detailed strategy for the project - Innovative Approach 5. Expertise/ Experience in the field ( Max. Marks : 20) - Experience in similar work in Oil Terminals - Credentials - Indian Client s feedback The presentations will be reviewed by HPCL s panel and evaluated on the above parameters. During the presentation, the bidders are required to explain the modality they propose to adopt for achieving the following: e. Random generation of inspection schedules. f. Ensuring confidentiality of the schedules and inspection reports. g. Controls proposed to be exercised to ensure that inspectors deliver the job with utmost confidentiality and integrity. h. Procedure of releasing inspection to HPCL thru coordinator within 48 hrs of conducting the inspection. B. Commercial (priced) Bid:

42 The Commercial (priced) bids will be opened only for those agencies who secure more than 65% on overall basis, in the presentations. Subsequently, HPCL s Purchase Procedure will be followed for finalizing the order, taking into consideration the Priced Bid. Standard Provisions 1. Proposals submitted in response to this invitation will be considered as contractually binding undertakings on the part of the Bidder should the Bidder s proposal be found acceptable to HPCL. 2. All materials received by HPCL as a result of this Bid becomes the property of HPCL and not returnable. HPCL accepts no financial responsibility for any cost incurred by any Bidder in responding to this Bid. Regardless of the Bidder being selected or not, HPCL reserves the right to use any information presented in the Bid to HPCL s benefit. 3. Proposals submitted in response hereto should not be construed as an obligation on the part of HPCL to award the Order for any or all items/services or a combination of services or items. 4. This Bid, including all sections and attachments or terms and conditions may be changed by HPCL either through additions or deletions before actual issuance of Execution Order/Signing of the Agreement/Contract. 5. Order will be placed on lowest bidder in individual zones. Accordingly, the order may be placed either on one party or more than one party. 6. Proposals submitted in response hereto will be considered as firm offers for a period of 120 days from the Bid due date or extended due date. HPCL may decide to place an order for a part/section of the Deliverables. 7. Pre bid meeting Pre bid meeting will be organized on HRS at Gresham House,! "## ##$ %& ' During the pre bid meet salient features of the Tender will be informed and techno commercial clarifications pertaining to the tender will be answered.

(BIDDING DOCUMENT NO HD-10129) (EIL REFERENCE No. S.M/A LZ-MR-4050/1024)

(BIDDING DOCUMENT NO HD-10129) (EIL REFERENCE No. S.M/A LZ-MR-4050/1024) DETAILED NOTICE INVITING TENDER (NIT) UNDER INTERNATIONAL COMPETITIVE BIDDING (ICB) FOR SUPPLY OF VAPOUR RECOVERY SYSTEM (ACTIVATED CARBON ADSORPTION TYPE) FOR MDPL CAPACITY EXPANSION AND PALANPUR-VADODARA

More information

NOTICE INVITING TENDER FOR EXCAVATION AND TRANSPORTATION OF GYPSUM (INDIAN COMPETITIVE BIDDING) HINDUSTAN PETROLEUM CORPORATION LTD.

NOTICE INVITING TENDER FOR EXCAVATION AND TRANSPORTATION OF GYPSUM (INDIAN COMPETITIVE BIDDING) HINDUSTAN PETROLEUM CORPORATION LTD. FOR EXCAVATION AND TRANSPORTATION OF GYPSUM (INDIAN COMPETITIVE BIDDING) HINDUSTAN PETROLEUM CORPORATION LTD. VISAKH REFINERY Tender no.: 17000124-HD-46009 IMPORTANT: Please note that this is an e-public

More information

The bidders, intending to participate shall fulfil the following qualification criteria (Financial & Technical):

The bidders, intending to participate shall fulfil the following qualification criteria (Financial & Technical): () Name of work: High Performance Liquid Chromatograph Bidding Document No: 1.0 HPCL invites sealed bids on unit rate basis for SUPPLY OF HIGH PERFORMANCE LIQUID CHROMATORAPH ALONGWITH SPARES AND CONSUMABLES

More information

Regulation DD-12.0: Risk Assessment Study

Regulation DD-12.0: Risk Assessment Study Regulation DD-12.0: Risk Assessment Study 12.0 Risk Assessment Study 12.1 Guidelines for Conducting Risk Assessment (RA) Study 12.2 Outline for Risk Assessment Study Report 12.3 Specific Fire Protection

More information

PROCEDURE: APPROVAL FOR RISK ASSESSMENT (RA) STUDIES

PROCEDURE: APPROVAL FOR RISK ASSESSMENT (RA) STUDIES 1. PURPOSE: PROCEDURE: APPROVAL FOR RISK ASSESSMENT (RA) STUDIES The development of projects under the jurisdiction of Trakhees-EHS, that possess a significant risk of Environment, Health & Safety and

More information

Industrial Accident Risk Assessment Procedures and Risk Reduction Measures

Industrial Accident Risk Assessment Procedures and Risk Reduction Measures Republic of Latvia Cabinet Regulation No. 131 Adopted 1 March 2016 Industrial Accident Risk Assessment Procedures and Risk Reduction Measures Issued pursuant to Section 11, Paragraph two of the Chemical

More information

Classification Based on Performance Criteria Determined from Risk Assessment Methodology

Classification Based on Performance Criteria Determined from Risk Assessment Methodology OFFSHORE SERVICE SPECIFICATION DNV-OSS-121 Classification Based on Performance Criteria Determined from Risk Assessment Methodology OCTOBER 2008 This document has been amended since the main revision (October

More information

Tender Number :: Title :: HAZOP/DNPL/10/26/26 NIT for HIRING OF SERVICE FROM CONSULTANT FOR CONDUCTING HAZOP AND QRA for DNPL 18/11/2016.

Tender Number :: Title :: HAZOP/DNPL/10/26/26 NIT for HIRING OF SERVICE FROM CONSULTANT FOR CONDUCTING HAZOP AND QRA for DNPL 18/11/2016. Tender Details Tender Number :: Title :: Date:: NIT for HIRING OF SERVICE FROM CONSULTANT FOR CONDUCTING HAZOP for DNPL 18/11/2016 Tender Details >> Due Date of Submission :: Up to 2:00 PM on 27/12/2016

More information

Pre-Earthquake, Emergency and Contingency Planning August 2015

Pre-Earthquake, Emergency and Contingency Planning August 2015 RiskTopics Pre-Earthquake, Emergency and Contingency Planning August 2015 Regions that are regularly exposed to seismic events are well-known, e.g. Japan, New Zealand, Turkey, Western USA, Chile, etc.

More information

EXPRESSION OF INTEREST (EOI) FOR EMPANELMENT OF INSURANCE BROKERS FOR GROUP PERSONAL ACCIDENT & GROUP TERM LIFE INSURANCE POLICIES

EXPRESSION OF INTEREST (EOI) FOR EMPANELMENT OF INSURANCE BROKERS FOR GROUP PERSONAL ACCIDENT & GROUP TERM LIFE INSURANCE POLICIES EXPRESSION OF INTEREST (EOI) FOR EMPANELMENT OF INSURANCE BROKERS FOR GROUP PERSONAL ACCIDENT & GROUP TERM LIFE INSURANCE POLICIES FOR SALARY ACCOUNT HOLDERS OF STATE BANK OF INDIA EOI REFERENCE NO. SBI/PB/G&ITU/2018-19/185

More information

Occupational Health and Safety Act, Major Hazard Installation Regulations

Occupational Health and Safety Act, Major Hazard Installation Regulations Occupational Health and Safety Act, 1993 Major Hazard Installation Regulations The Minister of Labour has, after consultation with the Advisory Council for Occupational Health and Safety, under section

More information

Tata AIG General Insurance Company Limited

Tata AIG General Insurance Company Limited PROPOSAL FORM FOR PUBLIC LIABILITY INSURANCE POLICY (INDUSTRIAL RISK) LIABILITY OF THE COMPANY DOES NOT COMMENCE UNTIL THE PROPOSAL HAS BEEN ACCEPTED AND THE PREMIUM PAID THE TERRITORIAL LIMIT AS APPLICABLE

More information

Insurance of Property & other assets of Reserve Bank of India for the period of July 1, 2018 to June 30, 2019

Insurance of Property & other assets of Reserve Bank of India for the period of July 1, 2018 to June 30, 2019 Insurance of Property & other assets of Reserve Bank of India for the period of July 1, 2018 to June 30, 2019 The Reserve Bank of India intends taking insurance cover of all the Properties & other assets

More information

Contractor Health and Safety Code of Practice. Updated June 4, 2018

Contractor Health and Safety Code of Practice. Updated June 4, 2018 Contractor Health and Safety Code of Practice 2018 Updated June 4, 2018 Updated June 4, 2018 TABLE OF CONTENTS A. DEFINITIONS...3 B. PURPOSE...7 C. STRATEGIC ALIGNMENT...7 D. REGULATORY CONSIDERATIONS...7

More information

Invitation for Pre-Qualification of Bidders for 1X600 MT Mounded Pressurized Storage Vessel at Lucknow LPG Plant.

Invitation for Pre-Qualification of Bidders for 1X600 MT Mounded Pressurized Storage Vessel at Lucknow LPG Plant. Invitation for Pre-Qualification of Bidders for 1X600 MT Mounded Pressurized Storage Vessel at Lucknow LPG Plant. TENDER NO. : E&P:PQR:MSV/12-13/ 01 DATED 13-07-2012 Bharat Petroleum Corporation Ltd.,

More information

Corporate Overseas Travel Insurance for employees of Reserve Bank of India from January 14, 2019 to June 30, 2020

Corporate Overseas Travel Insurance for employees of Reserve Bank of India from January 14, 2019 to June 30, 2020 Corporate Overseas Travel Insurance for employees of Reserve Bank of India from January 14, 2019 to June 30, 2020 The Reserve Bank of India (the Bank) intends taking corporate overseas travel insurance

More information

CONTRACTOR S RESPONSIBILITY FOR PROJECT SAFETY [Major Construction Category]

CONTRACTOR S RESPONSIBILITY FOR PROJECT SAFETY [Major Construction Category] CONTRACTOR S RESPONSIBILITY FOR PROJECT SAFETY [Major Construction Category] RFP Language Contract Language 1. Contractor recognizes the importance of performing the work in a safe and responsible manner

More information

European Railway Agency Recommendation on the 1 st set of Common Safety Methods (ERA-REC SAF)

European Railway Agency Recommendation on the 1 st set of Common Safety Methods (ERA-REC SAF) European Railway Agency Recommendation on the 1 st set of Common Safety Methods (ERA-REC-02-2007-SAF) The Director, Having regard to the Directive 2004/49/EC 1 of the European Parliament, Having regard

More information

MAIN CIVIL WORKS CONTRACT SCHEDULE 10 SAFETY TABLE OF CONTENTS

MAIN CIVIL WORKS CONTRACT SCHEDULE 10 SAFETY TABLE OF CONTENTS MAIN CIVIL WORKS CONTRACT SCHEDULE 10 SAFETY TABLE OF CONTENTS 1 INTERPRETATION... 1 1.1 Definitions... 1 2 GENERAL OCCUPATIONAL HEALTH AND SAFETY REQUIREMENTS... 2 2.1 Safety Areas... 2 2.2 General Duties

More information

Environmental Impairment Liability

Environmental Impairment Liability PROPOSAL FORM Environmental Impairment Liability Fixed Facilities, Pipelines & Storage Tanks & Goods in Transit Pollution Liability (road) Underwritten by The Hollard Insurance Co. Ltd, an authorised Financial

More information

Info Sheet for Contractor Personnel

Info Sheet for Contractor Personnel Page 1 of 6 I. Introduction To assure smooth operations on our premises it is necessary to read the information in this policy prior to accepting the contract. The contractor and its employees are required

More information

NOTICE INVITING TENDER

NOTICE INVITING TENDER Board of School Education Haryana NOTICE INVITING TENDER Sealed tenders are hereby invited from experienced service providers for providing the Signal Silencer / Jammer to block voice/image transmission

More information

CEPA S200 The Risk-based Approach

CEPA S200 The Risk-based Approach CEPA S200 The Risk-based Approach Presented by Ertugrul Alp, Ph.D., P.Eng. February 24, 2004 Toronto, Ontario Incorporated Change Agents in Risk Management, Specialists in Risk Assessment 87 Topham Crescent,

More information

TENDER FOR SUPPLY OF LAPTOPS AT STPI NOIDA MODE OF TENDERING: SEALED TWO-BID SYSTEM 1. DATE & TIME OF PRE-BID MEETING : 12/09/2014 ; 12:30 HRS

TENDER FOR SUPPLY OF LAPTOPS AT STPI NOIDA MODE OF TENDERING: SEALED TWO-BID SYSTEM 1. DATE & TIME OF PRE-BID MEETING : 12/09/2014 ; 12:30 HRS Software Technology Parks of India (Department of Electronics & Information Technology, Ministry of Communications & Information Technology, Govt. of India) Ganga Software Technology Complex, Sector-29,

More information

DESIGN AND CONSTRUCTION STANDARDS GENERAL DESIGN GUIDELINES 2.01

DESIGN AND CONSTRUCTION STANDARDS GENERAL DESIGN GUIDELINES 2.01 2.01 GENERAL This section contains general compliance and safety planning information to be used by design professionals and contractors in the design and construction of University facilities. The criteria

More information

Annex A. ERM Approved Inspection Authority, Certificates of Accreditation

Annex A. ERM Approved Inspection Authority, Certificates of Accreditation Annex A ERM Approved Inspection Authority, Certificates of Accreditation Annex B Major Hazard Installation Legislation Government Gazette REPUBLIC OF SOUTH AFRICA Regulation Gazette No. 7122 Vol. 433

More information

DELHI METRO RAIL CORPORATION LIMITED

DELHI METRO RAIL CORPORATION LIMITED Contract No: CC-89 : Water Supply Arrangements for Underground portion of Line-7 (From Nizamuddin to Bhikaji Kama Palace) DELHI METRO RAIL CORPORATION LIMITED Water Supply Arrangements for Underground

More information

Controlling Risk Ranking Variability Using a Progressive Risk Registry

Controlling Risk Ranking Variability Using a Progressive Risk Registry Controlling Risk Ranking Variability Using a Progressive Risk Registry 32nd Annual National VPPPA Safety & Health Conference/Expo September 1, 2016 Agenda What is a Progressive Risk Registry? How does

More information

Hindustan Shipyard Ltd (A Government of India Undertaking) GANDHIGRAM, VISAKHAPATNAM ( An ISO 9001 Company )

Hindustan Shipyard Ltd (A Government of India Undertaking) GANDHIGRAM, VISAKHAPATNAM ( An ISO 9001 Company ) E-Procurement NOTICE INVITING TENDERS (e-nit) Sealed E-tenders from reputed and experienced firms are invited in two-bid system for Provision of Printing Facility Inside HSL. 1 Tender Number OS/998/Printing/147/2017

More information

Request for Proposal For Consultant for availing the Duty Credit scrip- under Foreign Trade Policy ( )

Request for Proposal For Consultant for availing the Duty Credit scrip- under Foreign Trade Policy ( ) Request for Proposal For Consultant for availing the Duty Credit scrip- under Foreign Trade Policy (2009-14) PREQUALIFICATION CUM TENDER NOTICE FOR CONSULTANT FOR AVAILING DUTY CREDIT SCRIP UNDER FOREIGN

More information

Sub: Request For Proposal (RFP) from Chartered Accountants Firms for providing financial services to IIT Indore

Sub: Request For Proposal (RFP) from Chartered Accountants Firms for providing financial services to IIT Indore To, Sub: Request For Proposal (RFP) from Chartered Accountants Firms for providing financial services to IIT Indore Dear Sir, Indian Institute of Technology Indore invites RFP from the Practicing Chartered

More information

Comparison of Two Industrial Quantitative Risk Analyses Using the OECD Risk Assessment Dictionary/Thesaurus

Comparison of Two Industrial Quantitative Risk Analyses Using the OECD Risk Assessment Dictionary/Thesaurus Comparison of Two Industrial Quantitative Risk Analyses Using the OECD Risk Assessment Dictionary/Thesaurus Dennis C. Hendershot Rohm and Haas Company PO Box 584 Bristol, PA 19007 EMail: nagdh@rohmhaas.com

More information

(e-procurement System)

(e-procurement System) B I D D I N G D O C U M E N T For Procurement of Design, Supply, Installation and commissioning of Transmission Substations and Lines - (AFD) Project (e-procurement System) IPC No: KP1/6A.1/PT/1/18/A69

More information

The Challenge of Risk Control in a Hydrogen based Economy, Part I

The Challenge of Risk Control in a Hydrogen based Economy, Part I The Challenge of Risk Control in a Hydrogen based Economy, Part I Hans J. Pasman Chemical Risk Management What are the risks, how can we determine them, How can we avoid, how to reduce, when can we be

More information

Chennai Metro Rail Limited (A Joint Venture of Govt. of India and Govt. of Tamil Nadu)

Chennai Metro Rail Limited (A Joint Venture of Govt. of India and Govt. of Tamil Nadu) Chennai Metro Rail Limited (A Joint Venture of Govt. of India and Govt. of Tamil Nadu) NIT.No: CMRL/RS/04/2017 Date: 17.07.2017 Sub: Invitation of sealed quotation for Supply, Installation, Testing & Commissioning

More information

Telecommunications Consultants India Ltd. (A Government of India Enterprise) EOI Ref No. TCIL/13/STC/17 18/EoI/ISS February 26, 2018

Telecommunications Consultants India Ltd. (A Government of India Enterprise) EOI Ref No. TCIL/13/STC/17 18/EoI/ISS February 26, 2018 EOI Ref No. TCIL/13/STC/17 18/EoI/ISS February 26, 2018 Expression of Interest (EoI) for selection of Technology Partner for Installation and Commissioning of Security and Surveillance System Telecommunications

More information

NIT for Tender No. GCO 8524 P19

NIT for Tender No. GCO 8524 P19 NIT for Tender No. GCO 8524 P19 Oil India Limited, a Government of India Enterprise intends to hiring of services for upkeepment of coating material store and handling of materials located at PS-4, SEKONI,

More information

Contract/O&M/T-21: Provision of CCTV coverage in technical rooms at Stations, Depots area, train sidings and its integration with existing CCTV system

Contract/O&M/T-21: Provision of CCTV coverage in technical rooms at Stations, Depots area, train sidings and its integration with existing CCTV system NOTICE INVITING TENDER (e-tender) DELHI METRO RAIL CORPORATION LIMITED 1.1.1 NIT No.: DMRC/GM(S&T)/NIT/2015-16/T-21, dated 18.12.2015 Name of Work: Delhi Metro Rail Corporation (DMRC) Ltd. invites Open

More information

PROPERTY RISK ENGINEERING IN THE CHEMICAL SECTOR. August 2016

PROPERTY RISK ENGINEERING IN THE CHEMICAL SECTOR. August 2016 PROPERTY RISK ENGINEERING IN THE CHEMICAL SECTOR August 2016 PROPERTY RISK ENGINEERING IN THE CHEMICAL SECTOR When chemical sector professionals in Europe think of chemical site safety, they normally think

More information

2) Area: square feet (AC & Non-AC) comprising of i. Ground, 1 st to 5 th Floors ii. Lower & Upper Basements iii. Stores Area on 7 th Floor

2) Area: square feet (AC & Non-AC) comprising of i. Ground, 1 st to 5 th Floors ii. Lower & Upper Basements iii. Stores Area on 7 th Floor Annexure II 1) Premises: Engineering Projects (India) Ltd. (A Govt. of India Enterprises) Scope Complex, Core 3 7, institutional area, Lodhi Road, New Delhi 110003 2) Area: 61492 square feet (AC & Non-AC)

More information

Risk Assessments for Fire and Life Safety

Risk Assessments for Fire and Life Safety Risk Assessments for Fire and Life Safety Cameron Bardas, P.Eng. March 12, 2015 FIRE RESCUE E D M O N T O N What is a Risk Assessment? * Tool used for decision making * Systematic, defensible, measures

More information

HIGH RISK CONSTRUCTION WORK

HIGH RISK CONSTRUCTION WORK CONTRACTOR WHS SYSTEM STANDARD HIGH RISK CONSTRUCTION WORK EXTERNAL USE ONLY Principles in the Optus Contractor WHS management process CONTRACTOR MANAGEMENT STAGES PRINCIPLES THIS STANDARD REQUISITION

More information

Hazard Identification, Risk Assessment and Control Procedure

Hazard Identification, Risk Assessment and Control Procedure Hazard Identification, Risk Assessment and Control Procedure 1. Purpose To ensure that there is a formal process for hazard identification, risk assessment and control to effectively manage workplace and

More information

(Last amended 18 December 2017, cf. page 4)

(Last amended 18 December 2017, cf. page 4) REGULATIONS RELATING TO MANAGEMENT AND THE DUTY TO PROVIDE INFORMATION IN THE PETROLEUM ACTIVITIES AND AT CERTAIN ONSHORE FACILITIES (THE MANAGEMENT REGULATIONS) (Last amended 18 December 2017, cf. page

More information

AIA Document A201 TM 1997

AIA Document A201 TM 1997 AIA Document A201 TM 1997 General Conditions of the Contract for Construction for the following PROJECT: (Name and location or address): Project University of Maine at Farmington THE OWNER: (Name and address):

More information

Commercial General Liability Application for Insurance

Commercial General Liability Application for Insurance Commercial General Liability Application for Insurance This proposal for insurance will be the basis of any subsequent insurance policy that we issue to you. It is essential that you answer fully and accurately

More information

ORDINANCE NO N.S.

ORDINANCE NO N.S. ORDINANCE NO. 1-13 N.S. AN ORDINANCE OF THE CITY COUNCIL OF THE CITY OF RICHMOND AMENDING CHAPTER 6.43 OF THE RICHMOND MUNICIPAL CODE RELATING TO INDUSTRIAL SAFETY WHEREAS, on December 18, 2001, the City

More information

GASCADE Gastransport GmbH HSE-GUIDELINE-CONTRACTORS. Version 5 Status: 15th May 2017

GASCADE Gastransport GmbH HSE-GUIDELINE-CONTRACTORS. Version 5 Status: 15th May 2017 GASCADE Gastransport GmbH HSE-GUIDELINE-CONTRACTORS Version 5 Status: 15th May 2017 CONTENT 1. Preamble... 2. Scope... 3. General requirements, access, intoxicants... 4. Responsibility / organisation /

More information

Common Safety Methods CSM

Common Safety Methods CSM Common Safety Methods CSM A common safety method on risk evaluation and assessment Directive 2004/49/EC, Article 6(3)(a) Presented by: matti.katajala@safetyadvisor.fi / www.safetyadvisor.fi Motivation

More information

GAIL (INDIA) LIMITED

GAIL (INDIA) LIMITED GAIL (INDIA) LIMITED GAIL Complex, Vijaipur Distt. Guna, Madhya Pradesh- 473112 EXPRESS OF INTEREST FOR LEASING OF HOT TAPPING MACHINE AND THEIR ACCESSORIES ON LONG TERM BASIS EOI DOCUMENT NO : GAIL/VJPR/PL/EOI/2018-19/01

More information

RISK CONTROL SOLUTIONS

RISK CONTROL SOLUTIONS RISK CONTROL SOLUTIONS A Service of the Michigan Municipal League Liability and Property Pool and the Michigan Municipal League Workers Compensation Fund CONTRACTORS Municipalities often need services

More information

MSEZL/TTP-Membrane Replacement/ INVITATION FOR PROPOSALS

MSEZL/TTP-Membrane Replacement/ INVITATION FOR PROPOSALS INVITATION FOR PROPOSALS a. Mangalore SEZ Limited (MSEZL) is jointly promoted by Oil & Natural Gas Corporation Ltd. (ONGC), Infrastructure Leasing & Financial Services Ltd., Karnataka Industrial Areas

More information

GOVERNMENT OF INDIA MINISTRY OF ENVIRONMENT & FORESTS PARYAVARAN BHAWAN, CGO COMPLEX, LODHI RAOD, NEW DELHI

GOVERNMENT OF INDIA MINISTRY OF ENVIRONMENT & FORESTS PARYAVARAN BHAWAN, CGO COMPLEX, LODHI RAOD, NEW DELHI GOVERNMENT OF INDIA MINISTRY OF ENVIRONMENT & FORESTS PARYAVARAN BHAWAN, CGO COMPLEX, LODHI RAOD, NEW DELHI-110003 EXPRESSION OF INTEREST (EOI) The Ministry of Environment and Forests invites Techno-financial

More information

Request for Proposal Supply & Install Generators at District Health Centers Project

Request for Proposal Supply & Install Generators at District Health Centers Project HSA1011SER04 Cayman Islands Health Services Authority Request for Proposal Supply & Install Generators at District Health Centers Project #HSA1314 SER08 Contents I. Instructions to Proposers... 2 II. Information

More information

BID-DOCUMENT CONSULTANT - GST FOR THE FINANCIAL YEAR TERMS OF REFERENCE

BID-DOCUMENT CONSULTANT - GST FOR THE FINANCIAL YEAR TERMS OF REFERENCE BID-DOCUMENT CONSULTANT - GST FOR THE FINANCIAL YEAR 2019-20 TERMS OF REFERENCE 1. KRIDL is a Government of Karnataka undertaking registered under Company Act 1956/2013 engaged in Civil Constructions entrusted

More information

NOTICE INVITING TENDER (NIT)

NOTICE INVITING TENDER (NIT) 1.1 GENERAL NOTICE INVITING TENDER (NIT) 1.1.1 Name of Work: Delhi Metro Rail Corporation (DMRC) Ltd. invites Open e-tenders on Local Competitive Basis (LCB) from all countries and all areas, who fulfil

More information

CAMBRIDGESHIRE GUIDED BUSWAY OPERATIONS POLICY

CAMBRIDGESHIRE GUIDED BUSWAY OPERATIONS POLICY CAMBRIDGESHIRE GUIDED BUSWAY OPERATIONS POLICY Page 1 of 7 CGB OPERATIONS POLICY Contents: 1. Introduction 2. Contents 3. General Policy 4. Safety Inductions 5. Access 6. Requirements and Restrictions

More information

DELHI METRO WELFARE ORGANISATION CONTRACT NO: DMWO-C1

DELHI METRO WELFARE ORGANISATION CONTRACT NO: DMWO-C1 DELHI METRO WELFARE ORGANISATION Construction of Multi Storeyed flats for housing scheme of DMWO members at Koyal Enclave CONTRACT NO: DMWO-C1 TENDER DOCUMENTS VOLUME 1 NOTICE INVITING TENDER INSTRUCTION

More information

TENDER No: WRO/CON/757/0155

TENDER No: WRO/CON/757/0155 AN ISO 9001 & 14001 COMPANY TENDER DOCUMENT TENDER No: WRO/CON/757/0155 Appointment of Consultant for Providing Comprehensive GRIHA services to achieve GRIHA-4 star rating for Construction of District

More information

GUIDE BUSINESS & INDUSTRY A STEP-BY-STEP APPROACH TO EMERGENCY PLANNING, RESPONSE AND RECOVERY FOR COMPANIES OF ALL SIZES

GUIDE BUSINESS & INDUSTRY A STEP-BY-STEP APPROACH TO EMERGENCY PLANNING, RESPONSE AND RECOVERY FOR COMPANIES OF ALL SIZES GUIDE EMERGENCY MANAGEMENT GUIDE FOR BUSINESS & INDUSTRY A STEP-BY-STEP APPROACH TO EMERGENCY PLANNING, RESPONSE AND RECOVERY FOR COMPANIES OF ALL SIZES Sponsored by a Public-Partnership with the Federal

More information

Establishing an Essential Records List Criteria and Reporting Essential Records to the University s Records Management and Archives Department

Establishing an Essential Records List Criteria and Reporting Essential Records to the University s Records Management and Archives Department Establishing an Essential Records List Criteria and Reporting Essential Records to the University s Records Management and Archives Department December, 2015 ESTABLISHING AN ESSENTIAL RECORDS LIST What

More information

NIT for Tender No. GCO 8770 P19. Oil India Limited, a Government of India Enterprise intends for Hiring the services as stated below.

NIT for Tender No. GCO 8770 P19. Oil India Limited, a Government of India Enterprise intends for Hiring the services as stated below. NIT for Tender No. GCO 8770 P19 Oil India Limited, a Government of India Enterprise intends for Hiring the services as stated below. Tender No GCO 8770 P19 Service Description Services of maintaining OIL'S

More information

STANDARD BIDDING DOCUMENTS UNDER JAPANESE ODA LOANS

STANDARD BIDDING DOCUMENTS UNDER JAPANESE ODA LOANS PLANT STANDARD BIDDING DOCUMENTS UNDER JAPANESE ODA LOANS PROCUREMENT OF PLANT DESIGN, SUPPLY AND INSTALLATION Japan International Cooperation Agency (JICA) February 2013 Version 1.1 i Preface These Standard

More information

NOTICE INVITING TENDER (NIT)

NOTICE INVITING TENDER (NIT) NOTICE INVITING TENDER (NIT) 1.1 GENERAL 1.1.1 Name of Work: Delhi Metro Rail Corporation (DMRC) Ltd. invites open tenders from eligible applicants, who fulfill qualification criteria as stipulated in

More information

CONTRACTOR S RESPONSIBILITY FOR PROJECT SAFETY [Major Construction Category]

CONTRACTOR S RESPONSIBILITY FOR PROJECT SAFETY [Major Construction Category] CONTRACTOR S RESPONSIBILITY FOR PROJECT SAFETY [Major Construction Category] RFP Language Contract Language 1. Contractor recognizes the importance of performing the Work in a safe and responsible manner

More information

M 328 DEPOSITED. October 13, /2017 B.C.REG.

M 328 DEPOSITED. October 13, /2017 B.C.REG. M 328 DEPOSITED October 13, 2017 B.C.REG. 186/2017 September 14, 2017 SPILL CONTINGENCY PLANNING REGULATION PART 1- INTERPRETATION Definitions 2 Specified quantity Contents PART 2 - CONTENTS OF SPILL CONTINGENCY

More information

(Ord. No N.S., I, ; Ord. No N.S., I, )

(Ord. No N.S., I, ; Ord. No N.S., I, ) Chapter 6.43 - INDUSTRIAL SAFETY Sections: 6.43.010 - Summary. This chapter imposes regulations which supplement the requirements of California Health and Safety Code, Article 2 (commencing with Section

More information

Supersedes: 9/01/11 (Rev.5) Preparer: Owner: Approver: Team Member, North America Process Safety Center of Expertise

Supersedes: 9/01/11 (Rev.5) Preparer: Owner: Approver: Team Member, North America Process Safety Center of Expertise Procedure No.: BC032.019 Page: 1 of 12 Preparer: Owner: Approver: Team Member, North America Process Safety Center of Expertise Manager, North America Process Safety Center of Expertise Sr. Vice President,

More information

Phone Office: /89 Maulana Azad Campus, Chelmsford Road New Delhi

Phone Office: /89 Maulana Azad Campus, Chelmsford Road New Delhi DETAILS FOR PUBLISHING BID Bid Ref. No.: MAEF/18-19/ELECTRICITY/01 Name of the Organization: MAULANA AZAD EDUCATION FOUNDATION Type of Organization: Under Aegis of Ministry of Minority Affairs Bid Title:

More information

NOTICE INVITING TENDER FOR AWARD OF CONTRACT FOR PROVIDING SECURITY GUARDS (WITHOUT ARMS)

NOTICE INVITING TENDER FOR AWARD OF CONTRACT FOR PROVIDING SECURITY GUARDS (WITHOUT ARMS) NATIONAL INSTITUTE OF EDUCATIONAL PLANNING AND ADMINISTRATION 17-B, Sri Aurobindo Marg, New Delhi 110016 Tel. 26544800, 26565600 Fax: 26853041, 26865180 Website: www.nuepa.org NOTICE INVITING TENDER FOR

More information

BANK OF BARODA BARODA CORPORATE CENTRE MUMBAI CORRIGENDUM / EXTENSION OF LAST DATE OF SUBMISSION OF TENDER

BANK OF BARODA BARODA CORPORATE CENTRE MUMBAI CORRIGENDUM / EXTENSION OF LAST DATE OF SUBMISSION OF TENDER BANK OF BARODA BARODA CORPORATE CENTRE MUMBAI CORRIGENDUM / EXTENSION OF LAST DATE OF SUBMISSION OF TENDER WITH REFERENCE TO OUR TENDER NOTICE DATED 11.09.2013 FOR ANNUAL MAINTENANCE CONTRACT OF FIRE HYDRANT

More information

BANK OF BARODA BARODA CORPORATE CENTRE MUMBAI

BANK OF BARODA BARODA CORPORATE CENTRE MUMBAI BANK OF BARODA BARODA CORPORATE CENTRE MUMBAI TENDER NOTICE FOR ANNUAL MAINTENANCE CONTRACT OF FIRE HYDRANT/SPRINKLER SYSTEM INSTALLED AT BARODA CORPORATE CENTRE, MUMBAI NAME OF WORK: Bank of Baroda invites

More information

Contract for the storage of motor vehicles and boats between:

Contract for the storage of motor vehicles and boats between: Date of Execution: Contract for the storage of motor vehicles and boats between: Name: Mailing Address: City State, Zip Code: Phone Numbers: Mobile: Home: Work: E-mail Address: Additional authorized person(s)

More information

Page 1 of 55 First Revision No. 13-NFPA 600-2013 [ Global Input ] Change Title of the document from NFPA 600 Standard on Industrial Fire Brigades to NFPA 600 Standard on Facility Fire Brigades Submittal

More information

(Ord ) Chapter RISK MANAGEMENT Background and findings Purpose and goals. Page 1.

(Ord ) Chapter RISK MANAGEMENT Background and findings Purpose and goals. Page 1. Chapter 450-8 - RISK MANAGEMENT Sections: 450-8.002 - Background and findings. The board of supervisors of Contra Costa County finds as follows: (a) Recent incidents in Contra Costa County at industrial

More information

State Bank of India PREMISES & ESTATE DEPT., LOCAL HEAD OFFICE, CHENNAI

State Bank of India PREMISES & ESTATE DEPT., LOCAL HEAD OFFICE, CHENNAI NIT NO : 3 / 2017-18 State Bank of India invites applications for Empanelment of the Fire Auditors for conducting Fire Safety Audit for its branches/office in Tamil Nadu and Pondicherry from the Fire auditors/consulting

More information

APPLICATION OF LOPA AND SIL ASSESSMENT TO A NEW COMAH PLANT

APPLICATION OF LOPA AND SIL ASSESSMENT TO A NEW COMAH PLANT APPLICATION OF LOPA AND ASSESSMENT TO A NEW COMAH PLANT Jerry Mullins Principal Consultant, Abbott Risk Consulting, Manchester, UK High hazard industries such as those regulated by COMAH face a number

More information

1. Risk of regularizing illegal connections

1. Risk of regularizing illegal connections 1. Risk of regularizing illegal connections Background: This is an example of a contract provision for mitigating the risk of converting illegal connections to legal connections in a 300,000 population

More information

AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER PRE-CONSTRUCTION AND CONSTRUCTION SERVICES

AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER PRE-CONSTRUCTION AND CONSTRUCTION SERVICES AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER PRE-CONSTRUCTION AND CONSTRUCTION SERVICES AGREEMENT made by and between, hereinafter called the Owner, and SITESCOMMERCIAL, LLC 185 WIND CHIME COURT, SUITE

More information

BANGALORE INTERNATIONAL AIRPORT LIMITED. Administration Block, Kempegowda International Airport, Devanahalli, Bangalore

BANGALORE INTERNATIONAL AIRPORT LIMITED. Administration Block, Kempegowda International Airport, Devanahalli, Bangalore BANGALORE INTERNATIONAL AIRPORT LIMITED Administration Block, Kempegowda International Airport, Devanahalli, Bangalore 560 300 INVITATION TO EXPRESSION OF INTEREST Invitation to Expression of Interest

More information

PART 6 EVENT TREE ANALYSIS

PART 6 EVENT TREE ANALYSIS PART 6 EVENT TREE ANALYSIS Prof. Arshad Ahmad Email: arshad@utm.my Overview of Event Tree Analysis 2 Event Tree Analysis An event tree is a visual representation of all the events which can occur in a

More information

Contract/O&M/A-51: Comprehensive Annual Maintenance Contract (CAMC) for Automatic Fare Collection (AFC) Servers installed at OCC Shastri park.

Contract/O&M/A-51: Comprehensive Annual Maintenance Contract (CAMC) for Automatic Fare Collection (AFC) Servers installed at OCC Shastri park. NOTICE INVITING SINGLE TENDER (E-Tender) DELHI METRO RAIL CORPORATION LIMITED NIT No.:- NIT/51/GM(S&T)/2016, dated 29.09.2016 (from OEM authorized Vendors) 1.1.1 Name of Work: Delhi Metro Rail Corporation

More information

OKEECHOBEE COUNTY ROAD STRIPING AND MARKING SERVICES

OKEECHOBEE COUNTY ROAD STRIPING AND MARKING SERVICES OKEECHOBEE COUNTY ROAD STRIPING AND MARKING SERVICES RFP 2017-17 Due September 27, 2017 Room 123 304 NW 2 nd Street Okeechobee, FL 34972 1 INSTRUCTIONS TO BIDDERS In order to be considered responsive,

More information

Document Download Start Date & time (e-tender) Lac at Hrs

Document Download Start Date & time (e-tender) Lac at Hrs Tender Reference Broad Head of Material Estimated Value (in Rs.) P-55/2016-17/PC-III 11 KV HT AB Cable 3X120+1X125 sq. mm Document Download Start Date & time (e-tender) 51.04 Lac 23.03.2017 at 14.00 Hrs

More information

Prequalification Questionnaire For Turnkey EPC - Contractor Prequalification Questionnaire

Prequalification Questionnaire For Turnkey EPC - Contractor Prequalification Questionnaire Order number: 1003 Document number: 1003-2013 Revision: 0 Client: Project: Services Under this Document: Ministry of Health Libya Design, Build, and Operate of New 33 Prefabricated Hospitals Sizes (60

More information

AN ISO 9001 & ISO COMPANY TENDER DOCUMENT. NIT No.: NRO/CON/738/667 date : FOR

AN ISO 9001 & ISO COMPANY TENDER DOCUMENT. NIT No.: NRO/CON/738/667 date : FOR AN ISO 9001 & ISO 14001 COMPANY TENDER DOCUMENT NIT No.: NRO/CON/738/667 date : 12.10.2018 FOR Supply, Installation, Testing, Commissioning & Handing- over of Medical equipments (Group-7F) for Government

More information

ALL INDIA INSTITUTE OF SPEECH AND HEARING, Naimisham Campus, Manasagangothri, Mysore Global Tender Document. Purchase of Technical Equipment

ALL INDIA INSTITUTE OF SPEECH AND HEARING, Naimisham Campus, Manasagangothri, Mysore Global Tender Document. Purchase of Technical Equipment ; ALL INDIA INSTITUTE OF SPEECH AND HEARING, Naimisham Campus, Manasagangothri, Mysore 570 006 Global Tender Document Purchase of Technical Equipment INDEX Sl. No. Contents Page No. 1. Global Tender Notification

More information

Town of Manchester, Connecticut General Services Department. Request for Proposals for Fingerprinting Services 17/18-85.

Town of Manchester, Connecticut General Services Department. Request for Proposals for Fingerprinting Services 17/18-85. Town of Manchester, Connecticut General Services Department Request for Proposals for Fingerprinting Services 17/18-85 Proposals Due: May 29, 2018 @ 4:00 P.M. General Services Department 494 Main St. Manchester,

More information

STCI FINANCE LIMITED REQUEST FOR PROPOSAL ENGAGEMENT OF CONSULTANT FOR UNDERTAKING EQUITY VALUATION

STCI FINANCE LIMITED REQUEST FOR PROPOSAL ENGAGEMENT OF CONSULTANT FOR UNDERTAKING EQUITY VALUATION REQUEST FOR PROPOSAL ENGAGEMENT OF CONSULTANT FOR UNDERTAKING EQUITY VALUATION 1. Background STCI Finance Limited ( STCI or the Company ), is a Systemically Important Non-Deposit Taking Non-Banking Financial

More information

OSHA 1926 Subpart A General

OSHA 1926 Subpart A General OSHA 1926 Subpart A General 1926.2 Variances (a) Variances from the standards may be granted (b) To obtain a variance, a specific request must be made to OSHA 1926.3 Inspections Right of Entry (a) Authorized

More information

Work Health and Safety Conditions

Work Health and Safety Conditions Work Health and Safety Conditions Table of Contents PURPOSE AND SCOPE... 1 RESPONSIBILITIES... 1 DEFINITIONS, ABBREVIATIONS AND ACRONYMS... 1 GENERAL WH&S & ELECTRICAL SAFETY REQUIREMENTS... 1 Compliance...

More information

NOTICE INVITING TENDER (e-tender)

NOTICE INVITING TENDER (e-tender) NOTICE INVITING TENDER (e-tender) 1.1.1 Name of Work: Delhi Metro Rail Corporation (DMRC) Ltd. invites Open e-tenders (Single Packet System) from eligible applicants, who fulfil qualification criteria

More information

SBI. PREMISES & ESTATE DEPT., LOCAL HEAD OFFICE, 3 rd FLOOR KOTI, BANK STREET, HYDERABAD

SBI. PREMISES & ESTATE DEPT., LOCAL HEAD OFFICE, 3 rd FLOOR KOTI, BANK STREET, HYDERABAD NIT NO: 33/2017-18 dated 20/03/2018 State Bank of India invites applications for Empanelment of the Fire Auditors for conducting Fire Safety Audit for its branches/office in Telangana Circle from the Fire

More information

DELHI METRO RAIL CORPORATION LIMITED CONTRACT NO: LKCC- 02 (R)

DELHI METRO RAIL CORPORATION LIMITED CONTRACT NO: LKCC- 02 (R) DELHI METRO RAIL CORPORATION LIMITED Construction of balanced cantilever span of approx 255 m (Central Span of 105m and end Spans each of 75 m approx.) at Mawaiya Railway Crossing (as shown on drawings)

More information

Attachment no. 9 to PS-12

Attachment no. 9 to PS-12 Number of pages number 5 1 GENERAL PRINCIPLES OF CONDUCTING AND ORGANIZING WORK ON THE PREMISES OF - KWIDZYN CONTRACTOR IS OBLIGED TO CONFIRM ORDER ACCEPTANCE IN WRITING. Order acceptance means unequivocal

More information

a) Bidding Document No. : A096/T-205/10-11/RKS/19 (Corresponding e-tender no ) b) Bidding Document on : From to

a) Bidding Document No. : A096/T-205/10-11/RKS/19 (Corresponding e-tender no ) b) Bidding Document on : From to GAIL INDIA LTD.. INVITATION FOR BIDS (IFB) FOR CATHODIC PROTECTION SYSTEM WORKS FOR GAIL PETROCHEMICAL COMPLEX-II, PATA (U.P.) (BIDDING DOCUMENT NO. A096/T-205/10-11/RKS/19) (INTERNATIONAL COMPETITIVE

More information

Guidance for Analysis Required by COMAR Hazardous Material Security

Guidance for Analysis Required by COMAR Hazardous Material Security Guidance for Analysis Required by COMAR 26.27.01 Hazardous Material Security 1.0 Prioritization of security threats, vulnerabilities, and consequences 1.1 Exclusions 1.1.1 Facilities in Baltimore City

More information

TENDER NO: BLC/CFS/ISO14001:18001:28000 /13 Dt Tender Document for

TENDER NO: BLC/CFS/ISO14001:18001:28000 /13 Dt Tender Document for BalmerLawrie& Co Ltd. Container Freight Station (Chennai) Tender No.BLC/CFS/ISO 14001:18001:28000/13 BALMERLAWRIE & CO. LTD. CONTAINER FREIGHT STATION [No.32, Sattangadu Village, Manali, Chennai-600068

More information

APPLICATION FOR PRE-QUALIFICATION OF CONTRACTORS/ APPLICATORS FOR TERRACE WATERPROOFING WORKS IN BANK S RESIDENTIAL FLATS AT GHATKOPAR (E), MUMBAI

APPLICATION FOR PRE-QUALIFICATION OF CONTRACTORS/ APPLICATORS FOR TERRACE WATERPROOFING WORKS IN BANK S RESIDENTIAL FLATS AT GHATKOPAR (E), MUMBAI APPLICATION FOR PRE-QUALIFICATION OF CONTRACTORS/ APPLICATORS FOR TERRACE WATERPROOFING WORKS IN BANK S RESIDENTIAL FLATS AT GHATKOPAR (E), MUMBAI Last Date of Submission: 3 rd March 2017 1 NOTICE FOR

More information

TENDER NOTIFICATION NO. GMRC/O&M-1/PH-1/2019

TENDER NOTIFICATION NO. GMRC/O&M-1/PH-1/2019 TENDER NOTIFICATION NO. SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF 12 NOS. OF X-RAY BAGGAGE MACHINE WITH COMPREHENSIVE ANNUAL MAINTAINANCE CONTRAT (CAMC) OF 10 YEARS INCLUDING 2 YEARS OF DEFECT