1 NC DOT s Planning & Mitigation Program with focus on Orange County By: Bruce O. Ellis, CLM, PWS Mitigation Implementation Unit Head Project Development and Environmental Analysis Branch
2 Agenda I. TIP Overview II. NEPA/Mitigation Process III. Division VII IV. Q&A
3 Overview of the Transportation Improvement Program
4 ORGANIZATION - NCDOT Board of Transportation Governor Secretary Deputy Secretary for Transportation & Environment Deputy Secretary Transportation Chief Financial Officer Deputy Secretary Administration Deputy Secretary Personnel Commissioner DMV
5 ORGANIZATION - NC Divisions
6 Project Development Systems Plan Needs List TIP List/ Feasibility Study TIP Funding Planning/ Environmental Studies Design Plans Right-of-way Acquisitions Construction Maintenance and Operation
7 Long-Range Planning Determining the Need Program Development Funding the Projects Project Planning Minimizing the Impacts Project Design Design & ROW Construction & Maintenance Building & Maintaining the Road
8 Metropolitan Transportation Planning Process Major Elements Public Involvement Planning Factors Financial Plan Air Quality Conformity Transportation Plan Transportation Improvement Program Major Investment Studies Management System Inputs
9 Long-Range Planning Determining the Need Program Development Funding the Projects Project Planning Minimizing the Impacts Project Design Design & ROW Construction & Maintenance Building & Maintaining the Road
10 What is the TIP? Schedule and Funding of Transportation Projects Statewide Seven-Year Program, financially constrained Objectives Provides public information Facilitates public involvement Advances transportation projects in an organized way Provides responsive transportation systems Multi-modal Does not include maintenance projects
11 How is the TIP Developed? Two year process Increase Public Participation Odd Years Hold public meetings to request input (fall/winter) Develop draft TIP Program (spring/summer) Release Draft TIP (September)
12 How is the TIP Developed? Even Years Hold public meetings to review draft TIP (fall/winter) Review public comments (winter/spring) BOT Approval of TIP (June)
13 Who Decides What Projects Go into the TIP? The Public Staff, MPO and Board of Transportation review Board of Transportation approval
14 How are priorities made for approved projects? DOT/MPO Discussion Financially Constrained Consider Local/Intrastate Demand Funding/Authorization Constraints
15 CONCEPTUAL OVERVIEW MPO PUBLIC LOCAL GOVERNMENT CIVIC GROUPS LEGISLATURE MPO/PUBLIC REVIEW RECEIVE REQUESTS BOARD OF TRANSPORTATION REVIEW DRAFT STIP SPECIAL INTEREST GROUPS LEGISLATIVE LEGISLATIVE REVIEW REVIEW ADOPT STIP
16 Long-Range Planning Determining the Need Program Development Funding the Projects Project Planning Minimizing the Impacts Project Design Design & ROW Construction & Maintenance Building & Maintaining the Road
17 Overview of the NEPA/Mitigation Process
18 NEPA Process 1. Establish Purpose and Need 2. Agreement on detailed alternatives 3. Selection of a preferred alternative 4. Mitigation of the alternative 5. Permit and mitigate the project
19 01 Merger Revised Project Development Flow Process Statewide Planning P&N ALTS C. Public LEDPA Hearing CIW DEIS 4A M in. D. Public Hearing FEIS ROD Project Development and Environmental Analysis PDEA-Mitigation Roadway Hydraulics Right-of-Way Scoping Meeting Env. Req. Functional Design 404/Stream Verification Preliminary Design Tech Reports M C P 1 M C P 2 Submit Permit Application Surveys M C P 3 M C P 4 MIN R/W Plan/ Preparation Final Plans Hydro. Des. Complete 4B M in. Build Site Submit Permit MOD Receive Permit Permit Drawings Complete & 4C Min. R/W Plans Complete R/W Acquistion Months
20 ORGANIZATION - NC Divisions
21 Division 7 Initiatives
22 Division Projects Proposed - 7 years Bridge Replacement 76 - Roadway, Intersection Improvements, etc.
23 Orange County 19 Projects Proposed - 7 years_ 10 - Bridge Replacement 9 - Roadway, Intersection Improvements, etc.
24
25
26
27
28
29
Project Development Process
Brought to you by: Project Development Process 89 th Annual Purdue Road School March 25, 2003 David Holtz INDOT Program Development (317) 232-7588 dholtz@indot.state.in.us Chris Baynes INDOT Project Management
More informationPrioritization and Programming Process. NCDOT Division of Planning and Programming November 16, 2016
Prioritization and Programming Process NCDOT Division of Planning and Programming November 16, 2016 Today s Roadmap 1. Planning and Programming Division Overview 2. Strategic Investments (STI) Law 3. Prioritization
More informationMassDOT Highway ACEC State Markets Conference April 5, Jonathan Gulliver, Highway Administrator John J. Bechard, P.E., Deputy Chief Engineer
MassDOT Highway ACEC State Markets Conference April 5, 2018 Jonathan Gulliver, Highway Administrator John J. Bechard, P.E., Deputy Chief Engineer About MassDOT Highway 9,561 Lane Miles of Interstate, Numbered
More informationMetropolitan Planning Organizations in North Carolina. Chris Lukasina NCAMPO
Metropolitan Planning Organizations in North Carolina Chris Lukasina NCAMPO February 1, 2016 Items to Discuss What is an MPO/RPO? Why were they established? How are they structured? What areas do they
More informationTransportation Trust Fund Overview
Transportation Trust Fund Overview Created pursuant to New Jersey Transportation Trust Fund Authority Act of 1984 Established to finance the cost of planning, acquisition, engineering, construction, reconstruction,
More informationCRTPO Project Selection Direct Attributable & Bonus Allocation Funds
CRTPO Project Selection Direct Attributable & Bonus Allocation Funds January 21, 2015 Strategic Transportation Investments is State Driven STI process drives NC s TIP Data element tempered by local preference
More informationTexas Department of Transportation Corpus Christi District
Texas Department of Transportation Corpus Christi District U.S. 181 Harbor Bridge Project Environmental Documentation and Schematic Development Citizens Advisory Committee Meeting January 11, 2012 Welcome
More informationPennsylvania Department of Transportation s Statewide Procedures for STIP and TIP Revisions
MEMORANDUM OF UNDERSTANDING Pennsylvania Department of Transportation s Statewide Procedures for 2017-2020 STIP and TIP Revisions Purpose This Memorandum of Understanding (MOU) establishes a set of procedures
More informationIn addition to embarking on a new dialogue on Ohio s transportation priorities,
Strategic Initiatives for 2008-2009 ODOT Action to Answer the Challenges of Today In addition to embarking on a new dialogue on Ohio s transportation priorities, the Strategic Initiatives set forth by
More informationNCDOT. Local Programs Management Office. Locally Administered Projects OVERVIEW
NCDOT Local Programs Management Office Locally Administered Projects OVERVIEW Local Programs Management Office ------------------------------------------------------------------------------------------------------------------------
More informationAppendix J: MTP Checklist. Introduction
J MTP Checklist Appendix J: MTP Checklist Introduction The 2016 Regional Transportation Plan (RTP) Guidelines includes a checklist that the Metropolitan Planning Organization is required to complete upon
More informationChapter 6. Transportation Planning and Programming. Chapter 6
Chapter 6 Planning and ming Chapter 6 73 Chapter 6 Planning and ming VTA prepares a variety of transportation planning and programming documents that impact Santa Clara County s future mobility. Planning
More informationGovernor Harry W. Nice Memorial Bridge Improvement Project. Charles County Commissioners Presentation September 1, 2009
Governor Harry W. Nice Memorial Bridge Improvement Project Charles County Commissioners Presentation September 1, 2009 Purpose of Presentation Provide a project update since the last Charles County Commissioners
More informationI-64 Capacity Improvements Segment III Initial Financial Plan
I-64 Capacity Improvements Segment III Initial Financial Plan State Project # 0064-965-229/0064-099-229 P101, R201, C501, B638, B639, B640, B641, B642, B643, D609, D610, D611 Federal # NHPP-064-3(498)/
More information2017 UNIFIED TRANSPORTATION PROGRAM AND HB 20 IMPLEMENTATION
2017 UNIFIED TRANSPORTATION PROGRAM AND HB 20 IMPLEMENTATION TEMPO Meeting July 21, 2016 Current Initiatives On-going efforts to address performance-based planning and programming processes as required
More informationAct 89 of January 2014
Act 89 of 2013 January 2014 Act 89 Basics Passed by the Legislature November 21, 2013 Signed by Governor into law November 25, 2013 Increase funding for transportation by $2.3 Billion annually Address
More information2017 UNIFIED TRANSPORTATION PROGRAM AND HB 20 IMPLEMENTATION
2017 UNIFIED TRANSPORTATION PROGRAM AND HB 20 IMPLEMENTATION HGAC Transportation Policy Council Meeting Current Initiatives On-going efforts to address performance-based planning and programming processes
More informationNASHVILLE AREA MPO TRANSPORTATION IMPROVEMENT PROGRAM FY
NASHVILLE AREA MPO TRANSPORTATION IMPROVEMENT PROGRAM FY 2008-2011 Amendment Conformity Report for August 20, 2008 Amendments (Amendment # 2008-028 thru 2008-030) On August 20, 2008 the Executive Board
More informationMEMORANDUM OF UNDERSTANDING Lehigh Valley Transportation Study's Procedures for TIP M odifications
MEMORANDUM OF UNDERSTANDING Lehigh Valley Transportation Study's Procedures for 2017-2020 TIP M odifications Purpose This Memorandum of Understanding (MOU) establishes a set of procedures to be used by
More informationDeveloping a Transportation Asset Management Plan
Developing a Transportation Asset Management Plan A Workshop for the NCDOT July 2, 2015 Conducted By: Katie Zimmerman, P.E., Applied Pavement Technology, Inc. (APTech) And Lacy Love, Volkert, Inc. Workshop
More informationTRANSPORTATION IMPROVEMENT PROGRAM MODIFICATION POLICY Policies and Procedures to Streamline Project Delivery
The Transportation Improvement Program (TIP) is a staged, multi-year program of projects approved for funding with federal, State, and local funds within the Dallas-Fort Worth area. A new TIP is approved
More informationTEXAS DEPARTMENT OF TRANSPORTATION
TEXAS DEPARTMENT OF TRANSPORTATION FY 2013-2016 2016 STIP STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM HOUSTON DISTRICT AUGUST 2014 Quarterly Revision HIGHWAY August 2014 . HOUSTON-GALVESTON AREA COUNCIL
More informationNC Turnpike Authority Presentation to the Joint Legislative Transportation Oversight Committee. David Joyner November 4, 2011
NC Turnpike Authority Presentation to the Joint Legislative Transportation Oversight Committee David Joyner November 4, 2011 Agenda NC Turnpike Authority Tolling Process Projects Toll Operations National
More informationJACKSONVILLE URBAN AREA METROPOLITAN PLANNING ORGANIZATION UNIFIED PLANNING WORK PROGRAM AMENDMENT 1 FISCAL YEAR 2018 TABLE OF CONTENTS
JACKSONVILLE URBAN AREA METROPOLITAN PLANNING ORGANIZATION UNIFIED PLANNING WORK PROGRAM AMENDMENT 1 FISCAL YEAR 2018 TABLE OF CONTENTS Introduction 1 Five Year Planning Calendar 3 Budget Summary 4 Unified
More informationMetroplan White Paper
Background White Paper 30 Crossing Plan and TIP Amendments The 30 Crossing Project is a major design-build-finance reconstruction and expansion project on I-40 from the US 67/167 interchange to the north
More informationRegional Transportation Plan Checklist (Revised February 2010)
Regional Transportation Plan Checklist (Revised February 2010) (To be completed electronically in Microsoft Word format by the MPO/RTPA and submitted along with the draft RTP to Caltrans) Name of MPO/RTPA:
More informationReport on NCDOT Cash Balances
Report on NCDOT Cash Balances Evan Rodewald, Chief Financial Officer, NCDOT November 8, 2018 Overview of Report on NCDOT Cash Balances NCDOT Funding History of Cash Model Current Trends in Cash Balances
More informationRegional Transportation Plan 2040
South Jersey Transportation Planning Organization Regional Transportation Plan 2040 Technical Appendix #6: Financial Plan SJTPO July 2012 Version: July 16, 2012 The FHWA and FTA developed and issued the
More informationMEMORANDUM OF UNDERSTANDING PROCEDURES FOR STIP AND TIP MODIFICATIONS
MEMORANDUM OF UNDERSTANDING PROCEDURES FOR 2015-2018 STIP AND TIP MODIFICATIONS Lackawanna-Luzerne Transportation Study Metropolitan Planning Organization PURPOSE This Memorandum of Understanding (MOU)
More informationTribal Transportation Program Workshop. Transportation Planning
Tribal Transportation Program Workshop Transportation Planning Outline Planning LRTP TIP Why Plan? Provide direction To arrive at informed and thoughtful decisions. To have a product that is Efficient,
More informationACTION ELEMENT CONCLUSIONS
ACTION ELEMENT CONCLUSIONS The Action Element identifies all transportation projects within the horizon of the RTP/SCS and are financially constrained. This Action Element implements the Policy Element
More informationTwin Cities Area Transportation Study (TwinCATS) Adopted:
Introduction Twin Cities Area Transportation Study (TwinCATS) Transportation Improvement Program Administrative Modification & Amendment Policy Adopted: This document provides guidance that defines the
More informationMEMORANDUM. Requested Action Provide comments and questions to staff regarding the proposed TIP projects funding scenario.
MEMORANDUM To: MPO Technical and Citizens Advisory Committees From: Joshua Desmond, AICP BMCMPO Director Date: March 15, 2017 Re: FY 20182021 TIP s Proposal The MPO is developing the s 2018 through 2021
More informationHB2 and HB1887 Update
HB2 and HB1887 Update Nick Donohue Deputy Secretary of Transportation April 20, 2015 HB2 Legislation Requires Commonwealth Transportation Board to adopt statewide prioritization process to evaluate projects
More informationN A D O N A D O R E S E A R C H F O U N D AT I O N R P O A M E R I C A
2009 NATIONAL SCAN: RURAL TRANSPORTATION PLANNING ORGANIZATIONS 2009 National Scan Results: Rural Transportation Planning Organizations Since the passage of ISTEA, an increasing number of states have turned
More informationSOUTH CENTRAL PLANNING AND DEVELOPMENT COMMISSION. Scope of Services. Terrebonne Parish
SOUTH CENTRAL PLANNING AND DEVELOPMENT COMMISSION Scope of Services Terrebonne Parish Houma-Thibodaux Metropolitan Planning Organization Project Description This project will review the feasibility of
More informationBINGHAMTON METROPOLITAN TRANSPORTATION STUDY CERTIFICATION NARRATIVE FY 2016
BINGHAMTON METROPOLITAN TRANSPORTATION STUDY CERTIFICATION NARRATIVE FY 2016 The Binghamton Metropolitan Transportation Study Policy Committee is designated by the Governor of New York as the Metropolitan
More informationProject Delivery Manual Overview Introduction 2007
Project Delivery Manual Overview Introduction 2007 Project Delivery Manual Introduction Where do projects come from? How do they get in the Highway Program? Once they are in the Program, what do we do
More informationTransportation Planning in the Denver Region
The Prospectus Transportation Planning in the Denver Region Draft Version August 2016 Approved December 2004 Revised November 2006 Revised August 2007 Revised March 2009 Revised September 2011 Revised
More informationStandard Policy No: (P) Effective: 4/17/1015 rev. 2/21/2018 Responsible Division: Finance STATE INFRASTRUCTURE BANK (SIB) LOANS AND BONDS
Approved: Jerry Wray Director Standard Policy No: 18-012(P) Effective: 4/17/1015 rev. 2/21/2018 Responsible Division: Finance BACKGROUND: STATE INFRASTRUCTURE BANK (SIB) LOANS AND BONDS SIB LOANS In 1995
More information2045 Long Range Transportation
The Jackson Area Comprehensive Transportation Study 2045 Long Range Transportation June 2018 Jackson Area Comprehensive Transportation Study 2045 Long Range Transportation Plan Jackson County, Michigan
More informationHouse Bill 20 Implementation. House Select Committee on Transportation Planning Tuesday, August 30, 2016, 1:00 P.M. Capitol Extension E2.
House Bill 20 Implementation Tuesday,, 1:00 P.M. Capitol Extension E2.020 INTRODUCTION In response to House Bill 20 (HB 20), 84 th Legislature, Regular Session, 2015, and as part of the implementation
More informationRPO Technical Advisory Committee May 24th, :30 Pisgah Room (Medium) Conference Room Land of Sky Regional Council
RPO Technical Advisory Committee May 24th, 2017 2:30 Pisgah Room (Medium) Conference Room Land of Sky Regional Council 1. WELCOME AND HOUSEKEEPING A. Welcome and Introductions Brownie Newman B. Ethics
More informationDURHAM-ORANGE LIGHT RAIL TRANSIT PROJECT FINANCIAL RISKS AND MITIGATION STRATEGIES APRIL 2017
DURHAM-ORANGE LIGHT RAIL TRANSIT PROJECT FINANCIAL RISKS AND MITIGATION STRATEGIES APRIL 2017 There are several financial risks to the 2017 County Transit Plans (Plans) that could arise at different times
More informationP r i o r i t i z a t i o n S u b c o m m i t t e e M e e t i n g A g e n d a
P r i o r i t i z a t i o n S u b c o m m i t t e e M e e t i n g A g e n d a February 6, 2018 9:00 A.M. Agenda 1. WELCOME AND HOUSEKEEPING (5 min) A. Welcome and Introductions, Approval of Agenda Josh
More informationBudget Initial Public Forum FY Town of Chapel Hill 405 Martin Luther King Jr. Blvd.
Budget Initial Public Forum FY2018 19 Agenda Forum Topics Budget Process Budget Status Purpose of the Public Forum Forum Topics Budget Process Budget Status present background information on budget topics
More informationMankato/North Mankato Area Planning Organization (MAPO) 2018 & (2019 Draft) Work Program & Budget
Mankato/North Mankato Area Planning Organization (MAPO) 2018 & (2019 Draft) Work Program & Budget Technical Advisory Committee: August 17, 2017 Policy Board: September 7, 2017 Mankato/North Mankato Area
More informationThis item is under the Consent Agenda for approval; see Item #14-O. Mr. Dwight Farmer, Executive Director, will brief the HRTPO Board on this item.
ITEM #9: MEMORANDUM OF AGREEMENT: VDOT AND HRTPO At its May Retreat, the HRTPO Board was briefed on the ongoing coordination between the Commonwealth and HRTPO on the revenue collection, distribution process,
More informationSection 7. Financial Constraints
Section 7 Financial Constraints Under federal law, Skagit 2040 must make reasonable financing assumptions, accounting for existing or new revenue sources which can be reasonably expected to be available
More informationJoint Appropriations Subcommittee on Transportation
Joint Appropriations Subcommittee on Transportation Funding Overview February 21, 2013 H. Tasaico, PE 1 NCDOT Funding Overview - Agenda State Transportation Comparative Data Transportation Funding Sources
More informationProgramed Totals $39,761 $35,676 $75,437 $73,111 $2,326 $0 $17,109 $17,109 $17,109 $0 $0 $14,580 $14,580 $14,580 $0
WCOG Managed WHATCOM COUNCIL OF GOVERNMENTS 2014 Transportation Improvement Program Amendment #1 (1401) MPO Financial Feasibility Summary Anticipated Federal Funding* & Programmed Expenditures (in Thousands)
More informationLOCAL MAJOR BRIDGE PROGRAM
LOCAL MAJOR BRIDGE PROGRAM The Local Major Bridge Program provides federal funds to counties and municipal corporations for bridge replacement or bridge major rehabilitation projects. A Local Major Bridge
More informationCity of Grand Forks Staff Report
City of Grand Forks Staff Report Committee of the Whole November 28, 2016 City Council December 5, 2016 Agenda Item: Federal Transportation Funding Request Urban Roads Program Submitted by: Engineering
More informationSTATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM TIP FY 2006-2008 METROPOLITAN PLANNING ORGANIZATIONS - FY 2006 FEDERAL STATE LOCAL OTHER PART TOTAL FUNDING ESTIMATED COST BROWNSVILLE HARLINGEN-SAN BENITO
More information339 New Leicester Highway, Suite 140 Asheville. NC
WELCOME AND HOUSEKEEPING Chairman O Conner opened the meeting and introductions followed. CONSENT AGENDA Chairman O Conner requested approval for the Consent Agenda consisting of the May 2018 TCC minutes;
More informationTECHNICAL PLANNING COMMITTEE AGENDA 3/18/2015; ITEM II.B. Amendment Number Four to the FY Transportation Improvement Program
TECHNICAL PLANNING COMMITTEE AGENDA 3/18/2015; ITEM II.B. Amendment Number Four to the FY 2015-2018 Transportation Improvement Program AGENDA DESCRIPTION: Ozarks Transportation Organization (Springfield,
More informationNorth Carolina Department of Transportation Wetland and Stream Mitigation
North Carolina Department of Transportation Wetland and Stream Mitigation Why does NCDOT need mitigation? NCDOT Mission Statement Connecting people and places safely and efficiently, with accountability
More informationBRISTOL TENNESSEE / VIRGINIA URBAN AREA METROPOLITAN PLANNING ORGANIZATION
BRISTOL TENNESSEE / VIRGINIA URBAN AREA METROPOLITAN PLANNING ORGANIZATION Amendment # 2 FY 2017-2020 Transportation Improvement Program Amendment Summary: The Transportation Improvement Program (TIP)
More informationSOUTHERN BELTWAY US-22 TO I-79 PROJECT 2013 FINANCIAL PLAN. Pennsylvania Turnpike Commission Allegheny and Washington Counties, Pennsylvania
SOUTHERN BELTWAY US-22 TO I-79 PROJECT 2013 FINANCIAL PLAN Pennsylvania Turnpike Commission Allegheny and Washington Counties, Pennsylvania January 2013 Table of Contents... 1 Introduction... 2 Project
More information85 th Legislature: Impact on Funding and UTP
85 th Legislature: Impact on Funding and UTP Brian Ragland, Chief Financial Officer Peter Smith, Director, Transportation Planning and Programming Division TxDOT Budget FY -2019 Use of Funds 2 Proposition
More informationMEMORANDUM OF UNDERSTANDING Pennsylvania Department of Transportation s Statewide Procedures for STIP and TIP Modifications
MEMORANDUM OF UNDERSTANDING Pennsylvania Department of Transportation s Statewide Procedures for 2015-2018 STIP and TIP Modifications Purpose This Memorandum of Understanding (MOU) establishes a set of
More informationLehigh Valley Transportation Study s Procedures for Transportation Improvement Program Revisions
Purpose MEMORANDUM OF UNDERSTANDING Lehigh Valley Transportation Study s Procedures for 2019-2022 Transportation Improvement Program Revisions This Memorandum of Understanding (MOU) between the Pennsylvania
More informationFY STIP. Amarillo District May Quarterly Revisions STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM HIGHWAY
FY 2011-2014 STIP STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM HIGHWAY Amarillo District May Quarterly Revisions May 2011 MINUTES AMARILLO METROPOLITAN PLANNING ORGANIZATION POLICY COMMITTEE MEETING The
More informationCapital Improvements
Capital Improvements CAPITAL IMPROVEMENT ELEMENT GOAL 7-1: PROVIDE & MAINTAIN PUBLIC FACILITIES AND SERVICES Provide and maintain public facilities and services which protect and promote the public health,
More informationFY STIP. Houston District. November Quarterly Revisions TRANSIT STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM
FY 2011-2014 STIP STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM TRANSIT Houston District November Quarterly Revisions November 2011 HOUSTON-GALVESTON AREA COUNCIL PO Box 22777 3555 Timmons Ln. Houston,
More informationTransportation Funding in the Charlotte Region
Transportation Funding in the Charlotte Region Andy Grzymski, Charlotte DOT August 21, 2007 Charlotte Region HOV/HOT/ Managed Lanes Study Workshop Background The Charlotte Region One of the South s s
More informationOverview of Final Circular B Title VI Requirements and Guidelines for Recipients. February 2013
Overview of Final Circular 4702.1B Title VI Requirements and Guidelines for Recipients February 2013 Title VI Prohibits discrimination on the basis of race, color, or national origin in Federally funded
More information2017 Educational Series FUNDING
2017 Educational Series FUNDING TXDOT FUNDING INTRODUCTION Transportation projects take many years to develop and construct. In addition to the design, engineering, public involvement, right-of-way acquisition,
More informationFEDERAL FISCAL YEAR TRANSPORTATION IMPROVEMENT PROGRAM
FEDERAL FISCAL YEAR 2019-2022 TRANSPORTATION IMPROVEMENT PROGRAM A regional program of surface transportation improvement projects to enhance the movement of goods and people along the greater Des Moines
More informationAmendments and Administrative Actions Guidelines
NORTHEASTERN PENNSYLVANIA METROPOLITAN PLANNING ORGANIZATION (NEPA MPO) 2017-2020 TRANSPORTATION IMPROVEMENT PROGRAM (TIP) AMENDMENTS AND ADMINISTRATIVE ACTIONS GUIDELINES AND PROCEDURES MEMORANDUM OF
More informationTransportation Improvement Program
Transportation Improvement Program Transportation Conformity Check List The Transportation Improvement Program (TIP) and all amendments must include a conformity report. The conformity report must address
More informationCAPITAL BUDGET AND MULTI-YEAR CAPITAL PLAN SECTION 1 INTRODUCTION INTRODUCTION. Purpose of the Capital Improvement Plan
INTRODUCTION Purpose of the Capital Improvement Plan The Multi-Year Capital Plan (the Capital Improvement Plan or CIP) is an official statement of public policy regarding long-range physical development
More informationChapter VIII Financial Plan
Chapter VIII Financial Plan 2017-2020 Transportation Improvement Program ccording to the Metropolitan Planning regulations reaffirmed under the Fixing merica s Surface Transportation (FST) ct (23 CFR Part
More informationTransportation Infrastructure Finance and Innovation Act (TIFIA) Program Overview
Transportation Infrastructure Finance and Innovation Act (TIFIA) Program Overview (general summary and overview only for full details, see 23 United States Code Section 601) TIFIA IS A CREDIT PROGRAM (not
More information125 EAST 11 TH STREET AUSTIN, TEXAS 78701-2483 (512) 463-8588 WWW.TXDOT.GOV Mrs. Barbara C. Maley, AICP Env/Tranp Plan Coord & Air Quality Specialist Barbara.Maley@dot.gov December 27, 2016 Transmitted
More informationFEDERAL FISCAL YEARS TRANSPORTATION IMPROVEMENT PROGRAM. REVISION #12 Amendment 6/3/16 DRAFT. July 2016
FEDERAL FISCAL YEARS 215-218 TRANSPORTATION IMPROVEMENT PROGRAM REVISION #12 Amendment July 216 Oahu Metropolitan Planning Organization 77 Richards Street, Suite 2 Honolulu, Hawaii 96813-4623 (88) 587-215
More informationTRANSPORTATION IMPROVEMENT PROGRAM REVISION 19 F E D E R A L F I S C A L Y E A R S Expedited Administrative Modifications
TRANSPORTATION IMPROVEMENT PROGRAM F E D E R A L F I S C A L Y E A R S 2 0 1 5 2 0 1 8 REVISION 19 Expedited Administrative Modifications TRANSPORTATION IMPROVEMENT PROGRAM FEDERAL FISCAL YEARS 2015-2018
More informationGLOSSARY. At-Grade Crossing: Intersection of two roadways or a highway and a railroad at the same grade.
Glossary GLOSSARY Advanced Construction (AC): Authorization of Advanced Construction (AC) is a procedure that allows the State to designate a project as eligible for future federal funds while proceeding
More information2017 UNIFIED TRANSPORTATION PROGRAM AND HB 20 IMPLEMENTATION
2017 UNIFIED TRANSPORTATION PROGRAM AND HB 20 IMPLEMENTATION Texas Transportation Commission Workshop 06/29/16 Commission Workshop Outline Introduction of performance-based planning and programming processes.
More informationTechnical Appendix. FDOT 2040 Revenue Forecast
Technical Appendix FDOT 040 Revenue Forecast This page was left blank intentionally. APPENDIX FOR THE METROPOLITAN LONG RANGE PLAN 040 Forecast of State and Federal Revenues for Statewide and Metropolitan
More informationDraft. List of Tables. Table of Contents
Table of Contents Executive Summary... 2 1 The Public Participation Plan... 3 2 Planning Process and Need for Public Involvement..3 3 Regulations and Requirements... 4 4 RTC Committees... 6... 7 5 MPO
More informationAPPENDIX FOR THE METROPOLITAN LONG RANGE TRANSPORTATION PLAN Forecast of State and Federal Revenues for Statewide and Metropolitan Plans
APPENDIX FOR THE METROPOLITAN LONG RANGE TRANSPORTATION PLAN 2035 Forecast of State and Federal Revenues for Statewide and Metropolitan Plans Overview This appendix documents the current Florida Department
More informationTEXAS TRANSPORTATION FUNDING, INCLUDING TEXAS CLEAR LANES AND CONGESTION RELIEF UPDATE
TEXAS TRANSPORTATION FUNDING, INCLUDING TEXAS CLEAR LANES AND CONGESTION RELIEF UPDATE Presentation for Texas Transportation Commission March 28, 2018 Purposes of the Workshop The Texas Transportation
More informationAppendix E: Revenues and Cost Estimates
Appendix E: Revenues and Cost Estimates Photo Source: Mission Media Regional Financial Plan 2020-2040 Each metropolitan transportation plan must include a financial plan. In this financial plan, the region
More informationDecember 27, Mr. Patrick McKenna, Director Missouri Department of Transportation P.O. Box 270 Jefferson City, Missouri 65102
U.S. Department of Transportation Mr. Patrick McKenna, Director Missouri Department of Transportation P.O. Box 270 Jefferson City, Missouri 65102 Federal Transit Administration Federal Highway Administration
More informationApplication to fund Executive level position for the Altamont Regional Rail Working Group
SUBJECT: FROM: Application to fund Executive level position for the Altamont Regional Rail Working Group Michael Tree, Executive Director DATE: August 1, 2016 Action Requested The staff recommendation
More informationChapter 6: Financial Resources
Chapter 6: Financial Resources Introduction This chapter presents the project cost estimates, revenue assumptions and projected revenues for the Lake~Sumter MPO. The analysis reflects a multi-modal transportation
More informationTransportation Primer
Transportation Primer Joint Appropriations Committee on Transportation February 11, 2015 Amna Cameron Fiscal Research Division Agenda Background Transportation Revenues Items for Consideration Transportation
More information1. identifies the required capacity of capital improvements to serve existing and future development based on level-of-service (LOS) standards;
DIVISION 4.200 CAPITAL IMPROVEMENTS ELEMENT SECTION 4.201 INTRODUCTION The purpose of the Capital Improvements Element (CIE) is to tie the capital improvement needs identified in the other elements to
More informationCC: Ms. Rhiannon Chambers, State Program Development Office, TDOT Mr. Nate Brugler, Local Programs Development Office, TDOT Ms. Meghan Wilson, Local
CC: Ms. Rhiannon Chambers, State Program Development Office, TDOT Mr. Nate Brugler, Local Programs Development Office, TDOT Ms. Meghan Wilson, Local Programs Development Office, TDOT Ms. Whitney Britt,
More informationThe DRAFT Bus and Rail Investment Plan in Orange County
The DRAFT Bus and Rail Investment Plan in Orange County 5/31/2012 The Bus and Rail Investment Plan in Orange County I. INTRODUCTION 3 II. TRANSIT STEPS LEADING UP TO THIS PLAN 4 III. PLAN ELEMENTS 5 A.
More informationFEDERAL FISCAL YEAR TRANSPORTATION IMPROVEMENT PROGRAM
FEDERAL FISCAL YEAR 2016 2019 TRANSPORTATION IMPROVEMENT PROGRAM A regional program of surface transportation improvement projects to enhance the movement of goods and people along the greater Des Moines
More informationNCDOT Funding Overview
NCDOT Funding Overview Joint Appropriations Subcommittee on Transportation Mark L. Foster, CFO H. Tasaico February 16, 2011 Transportation Outlook NCDOT Funding Sources Transportation Funding Equity Cash
More informationSKATS FY 2018-FY 2023
SKATS FY 2018-FY 2023 Metropolitan Transportation Improvement Program and Air Quality Conformity Determination PUBLIC REVIEW Salem-Keizer Area Transportation Study Cover Photos Top left: 45th Avenue NE
More informationDurham Chapel-Hill Carrboro Metropolitan Planning Organization
Durham Chapel-Hill Carrboro Metropolitan Planning Organization FY2019 Unified Planning Work Program Approved 2.14.18 Hillsborough Durham Carrboro Chapel Hill RTP Table of Contents Page Adopting Resolution
More informationStrategic Prioritization Office of Transportation Local Input Point Assignment Methodology
Introduction Strategic Prioritization Office of Transportation Local Input Point Assignment Methodology The Down East Rural Planning Organization (DERPO), covering Carteret, Craven, Jones, Onslow and Pamlico
More informationPreliminary Findings and Recommendations
Review of the Comprehensive Agreement between the North Carolina Department of Transportation and I-77 Mobility Partners LLC Preliminary Findings and Recommendations July 2017 Overview NCDOT has initiated
More informationPENNSYLVANIA S 2017 TRANSPORTATION PROGRAM FINANCIAL GUIDANCE
November 20, 2015 Revised December 18, 2015 to reflect FAST Act PENNSYLVANIA S 2017 TRANSPORTATION PROGRAM FINANCIAL GUIDANCE This is a collaborative product jointly developed by the Pennsylvania Planning
More informationINVESTMENT STRATEGIES
3 INVESTMENT STRATEGIES 70 INVESTMENT STRATEGIES 71 A key role of Mobilizing Tomorrow is to outline a strategy for how the region will invest in transportation infrastructure over the next 35 years. This
More informationTerre Haute Seelyville West Terre Haute Vigo County. Brazil Harmony Knightsville Clay County
TRANSPORTATION IMPROVEMENT PROGRAM Terre Haute Seelyville West Terre Haute Vigo County Brazil Harmony Knightsville Clay County SFY 2018 2021 Metropolitan Planning Organization West Central Indiana Economic
More information