ACRP Report 139 Overview
|
|
- Brett Berry
- 6 years ago
- Views:
Transcription
1 ACRP Report 139 Overview Optimizing Airport Building Operations and Maintenance Through Retrocommissioning: A Whole-Systems Approach ACI-NA Annual Conference & Exhibition Long Beach, California October 3, 2015 Contact: Abbe Bjorklund, PE, CEM, CPMP Vice President, Sebesta, Inc. abjorklund@sebesta.com
2 Report: Guidebook for Airports Provides Overview of Benefits of Whole Systems Lifecycle Approach to Retrocommissioning Provides Guidance for Planning and Executing Retrocommissioning Process
3 What is Retrocommissioning? A Systematic Process for Optimizing Existing Facilities through Identifying and Correcting Deficiencies Investigate Correct Validate Performance
4 ACRP Report 139 Appendix D Optimization for Airport Facilities Scoping Planning Investigation Implementation Verification
5 Project Scoping START: Identify General Focus Area Assess Feasibility/Limits Finalize Retrocommissioning Scope of Work Potential Considerations: Building Footprint Control System AHU/Pressure Zones Chronic repair issues Area Use Secure Passengers General Public Baggage Handling Potential Considerations: System configuration Number of AHUs Number of VAVs Space uses Building vintage Revise Scope as Necessary to Meet Budget/Time Constraints Request for Proposals and Budgeting Begin Planning Phase Project Scoping Planning Phase Investigation Phase Implementation Phase Verification Phase
6 Planning Phase Kick Off Meeting Facility Preliminary Inspection Project Scoping Document & Design Review Management & Maintenance Staff Interview Document Current Facility Requirements Develop Retrocommissioning Plan Operations Record Review Begin Investigation Phase Project Scoping Planning Phase Investigation Phase Implementation Phase Verification Phase
7 Investigation Phase Site Diagnostic Monitoring Test and Balance Systems Planning Phase Occupant Interviews System Test Procedure and Plan Development Detailed System Investigation & Testing Identify Opportunities To Optimize System Performance Implement minor repairs ( quick fixes ) to realize immediate improvements Systems Condition Assessment Document System Operations & Modifications Final Retrocommissionin g Investigation Report Begin Implementation Phase Project Scoping Planning Phase Investigation Phase Implementation Phase Verification Phase
8 Implementation Phase Commission New Capital Improvements Implement Cost- Effective Capital Improvements Review Capital Improvements Needed to Meet CFRs N o Investigation Phase Develop Implementation Plan Implement No- Cost and Low- Cost Improvements Adjustments sufficient to meet CFRs? Y es Update Training Materials & Conduct Training Develop or Update Systems Manual Implementation Phase Final Report Lessons Learned Meeting Begin Verification Phase Project Scoping Planning Phase Investigation Phase Implementation Phase Verification Phase
9 Verification Phase Verification Update Training Materials & Conduct Training Training Track + Evaluate 12-month Performance Identify and Correct Issues as needed Implementation Phase Verification or Ongoing Cx? Basic Ongoing Performance Evaluation Enhanced Restart Project Scoping Identify Tasks and Frequency for Ongoing Cx Assess Trend Data and Test Results Identify and Correct Issues as Needed Ongoing Commissioning
10 Benefits of Retrocommissioning Immediate Improvements Quick Payback Energy Savings 15% average O&M Team Training
11 Cost of Retrocommissioning Professional Fees: $ $1.20/SF Quick Fix Allowance: $ $0.25/SF Corrective Action Allowance: $ $0.50/SF Monitoring and Verification: $ $0.25/SF/YR
12 Report Resources Retrocommissioning Process Map/Description Sample Retrocommissioning Scopes of Work Sample Reports/Retrocommissioning Plans
13 Spreadsheet Tool Master List of Recommendations Ranking Tool
14 Case Study: Colorado Springs Airport Energy Audit
15 Case Study: MSP Airport Enterprise Energy Management System
16 Case Study: Boston Logan Airport Central Plant Retrocommissioning
17 ACRP Report 139 Overview Questions? Contact: Abbe Bjorklund, PE, CEM, CPMP Vice President, Sebesta, Inc
Third-Year Program Results for a Utility Recommissioning Program
Third-Year Program Results for a Utility Recommissioning Program Ellen Franconi, PhD, Martin Selch, Jim Bradford PhD, PE Nexant, Inc. Bill Gruen Xcel Energy Synopsis Xcel Energy offers the Recommissioning
More informationFY 2018 Energy Management Plan
FY 2018 Energy Management Plan Instructions: The FY 2018 Energy Management Plan is broken up into multiple sections. This plan represents a comprehensive approach to energy reduction each section is completed
More informationPlanning and Investigating Existing Buildings
Planning and Investigating Existing Buildings Robert Austin Associate Vice President Kenny Reed PE, CEM, CxAP Commissioning Services Director AIA Quality Assurance The Building Commissioning Association
More informationPROGRAM DEFINITION DOCUMENTS AN AIRPORT OWNER S PERSPECTIVE Using PDD s at Baltimore/Washington International Thurgood Marshall Airport
Track: PM/CM Workshop: 3 Title: Moderator: Avoid an Identity Crisis! Program Definition from Master Plan to Program Execution Michael D. Floyd Jacobs Date: 7 February 2013 PROGRAM DEFINITION DOCUMENTS
More informationHigh Performance Schools- How do we get there? Build an Energy Team and Utilize Performance Contracting
High Performance Schools- How do we get there? Build an Energy Team and Utilize Performance Contracting How do we go from this to High Performance? Teamwork! 76% of all school district in the US indicated
More informationPRIME NE GLISAN STOREFRONT UNIQUE LOCATION LEASE NORTHEAST. NE PORTLAND 2nd-GENERATION SPACE for lease STOREFRONT OPPORTUNITY HIGH-TRAFFIC LOCATION!
FOR LEASE HIGH-TRAFFIC LOCATION! NE GLISAN ST Near 72nd ave - 14,000 VPD UNIQUE STOREFRONT OPPORTUNITY - in - PRIME NORTHEAST LOCATION --- NE GLISAN ST. --- 2839 SW 2nd Avenue Portland OR, 97201 503.222.1655
More informationLesson 3 Experience Rating
Lesson 3 Experience Rating 1. Objective This lesson explains the purpose and process of experience rating and how it impacts the premium of workers compensation insurance. 2. Introduction to Experience
More informationFY 2019 Energy Management Plan
FY 2019 Energy Management Plan Instructions: The FY 2019 Energy Management Plan is broken up into multiple sections. This plan represents a comprehensive approach to energy reduction please complete each
More informationAir Traffic Organization Policy. Air Traffic Organization Safety Management System
Air Traffic Organization Policy ORDER JO 1000.37 Effective Date: March 19, 2007 SUBJ: Air Traffic Organization Safety Management System The purpose of the Air Traffic Organization (ATO) is to provide a
More informationBuilding Systems and Performance: an Introduction to Building Operator Certification Lesson 19: Energy Audits
Building Systems and Performance: an Introduction to Building Operator Certification Lesson 19: Energy Audits CUNY Institute for Urban Systems Building Performance Lab Introduction to Energy Audits 2 Topic
More informationThe Empire State Building Repositioning an Icon as a Model of Energy Efficient Investment
The Empire State Building Repositioning an Icon as a Model of Energy Efficient Investment Paul Rode, P.E. Johnson Controls Inc. ACEEE National Symposium on Market Transformation April 12 th, 2011 The Empire
More information12 Months Master Pay Scale Salary Table
B-1 Master Pay Scale Salary Table 2017-2018 An employee who does not earn a credited year of service and/or who remains on the same pay step for any other reason (such as being at the maximum pay step)
More informationProcurement, Lease, Maintenance and Use of Motor Vehicles
Procurement, Lease, Maintenance and Use of Motor Vehicles Category: Approval: Responsibility: Date: Operations Vice President, Finance and Administration Vice President, Finance and Administration Date
More informationTransparency In Airport Rates & Charges
Transparency In Airport Rates & Charges ACI-NA Airport Economics and Finance Conference General Session II April 29, 2008 1 Panel Susan Warner-Dooley, Deputy Executive Director, Finance & Admin, Metropolitan
More informationREQUEST FOR PROPOSALS FOR CIVIL ENGINEERING SERVICES
Saddle Creek Community Services District 1000 Saddle Creek Drive - Copperopolis, CA 95228 (209) 785-0100 saddlecreekcsd.org DIRECTORS Larry Hoffman, President Ken Albertson, Vice President Darlene, DeBaldo,
More informationREPORT ON THE COST EFFECTIVENESS AND PROGRESS OF THE SUSTAINABLE BUILDING 2030 STANDARDS
This document is made available electronically by the Minnesota Legislative Reference Library as part of an ongoing digital archiving project. http://www.leg.state.mn.us/lrl/lrl.asp REPORT ON THE COST
More information2016 Statewide Retrocommissioning Policy & Procedures Manual
2016 Statewide Retrocommissioning Policy & Procedures Manual Version 1.0 Effective Date: July 19, 2016 Utility Administrators: Pacific Gas and Electric San Diego Gas & Electric Southern California Edison
More informationRetro-Commissioning Draft Impact Evaluation Plan
Prepared by SBW Consulting, Inc. PWP, Inc. For the California Public Utilities Commission December 19, 2007 TABLE OF CONTENTS EXECUTIVE SUMMARY... 5 1. PROGRAMS EVALUATED... 8 2. EVALUATOR CONTACT INFORMATION...
More information2018 IHCDA Asset Management Trend Analysis
2018 IHCDA Asset Management Trend Analysis OVERVIEW Asset Management Policy was created in 2015 to assess IHCDA s rental housing portfolio Housing portfolio is separated into 2 categories Pre-Stabilization
More informationCHANGE REQUEST for FY BUDGET REQUEST CYCLE
CHANGE REQUEST for FY 2010-11 BUDGET REQUEST CYCLE Department(s): Colorado Department of Human Services & Colorado Department of Health Care Policy and Financing Priority Number: 1 Change Request Title:
More informationBulletin. TO: All Freddie Mac Sellers and Servicers October 17, 2008
Bulletin TO: All Freddie Mac Sellers and Servicers October 17, 2008 SUBJECTS Selling requirements are amended in this Single-Family Seller/Servicer Guide (Guide) Bulletin. This Bulletin provides final
More informationReducing Project Lifecycle Cost with exsilentia
Reducing Project Lifecycle Cost with exsilentia Kate Hildenbrandt Iwan van Beurden exida Sellersville PA, 18960, USA khildenbrandt@exida.com January 2017 1 Abstract The international functional safety
More informationALDOT TRANSIT ASSET MANAGEMENT PLAN
ALDOT TRANSIT ASSET MANAGEMENT PLAN What is Transit Asset Management? Transit Asset Management (TAM) is a business model that uses the condition of assets to guide the optimal prioritization of funding
More informationTEMPORARY SELLING REQUIREMENTS FOR PROPERTIES IMPACTED BY THE CALIFORNIA WILDFIRES
TO: Freddie Mac Sellers December 6, 2018 2018-25 SUBJECT: TEMPORARY SELLING REQUIREMENTS RELATED TO CALIFORNIA WILDFIRES AND UPDATES TO ELIGIBILITY FOR PROPERTIES IMPACTED BY HURRICANE IRMA Freddie Mac
More informationImperial County Transportation Commission & ARC-Imperial Valley. Med-Express Transit Service Report For The Year Ended June 30, 2014
Imperial County Transportation Commission & ARC-Imperial Valley Med-Express Transit Service Report For The Year Ended June 30, 2014 TABLE OF CONTENTS Page INDEPENDENT ACCOUNTANTS' REPORT 3-4 ACCOUNTANTS'
More informationPRELIMINARY BUDGET
PRELIMINARY BUDGET 2017-2018 OPERATIONAL FUNDS JULY 31, 2017 EDUCATIO N FUND OPE RATIONS & MAINTE NANCE FUND TRANSPORTAT I ON FUND Operational Funds Revenue Assumptions Property Tax Same as Pre-Preliminary
More informationINSTITUTIONAL EFFECTIVENESS Procedures Manual. Developed by the Office of Institutional Effectiveness
INSTITUTIONAL EFFECTIVENESS Procedures Manual Developed by the Office of Institutional Effectiveness 2014-2018 INSTITUTIONAL EFFECTIVENESS PROCEDURES MANUAL Purpose < To support a comprehensive institutional
More informationADVIA 360, 560, and 560 AL Hematology Systems: Correlation Results
Sue Mead, ADVIA 360, 560, and 560 AL Hematology s: Correlation Results Unrestricted Siemens Healthcare Diagnostics Inc. 2015 All rights reserved. Answers for life. Table of Contents Page 3-5 Page 6 Page
More informationFOREIGN TRADE ZONES PETROLEUM TECHNICAL INFORMATION FOR PRE-ASSESSMENT SURVEY (TIPS)
FOREIGN TRADE ZONES PETROLEUM TECHNICAL INFORMATION FOR PRE-ASSESSMENT SURVEY (TIPS) TABLE OF CONTENTS PART 1 BACKGROUND... 2 PART 2 PETROLEUM FTZ GUIDANCE... 2 2.1 EXAMPLES OF RED FLAGS...3 2.2 EXAMPLES
More informationEXHIBIT "A" RESPONSIBILITIES AND SERVICES OF PROGRAM MANAGER 1. BASIC SERVICES A-1 2. GENERAL PROGRAM SERVICES A-6
EXHIBIT "A" RESPONSIBILITIES AND SERVICES OF PROGRAM MANAGER 1. BASIC SERVICES A-1 2. GENERAL PROGRAM SERVICES A-6 3. PLANNING AND ADMINISTRATION A-6 OF THE PROJECT 4. PRECONSTRUCTION PHASE A-7 5. PRE-BIDDING
More informationMEMORANDUM OF UNDERSTANDING Standards Based Capital Outlay Project
MEMORANDUM OF UNDERSTANDING 2008-2009 Standards Based Capital Outlay Project PROJECT NUMBER: P08-003 Phase II This Memorandum of Understanding (MOU) is made and entered into by the Public School Facilities
More informationBUILDING PERMIT RESIDENTIAL BASEMENT FINISH
BUILDING PERMIT RESIDENTIAL BASEMENT FINISH DOCUMENTS YOU WILL NEED 1. Building Permit Residential Basement Finish Package 2. Contractors copy of state and business license ADDITIONAL FORMS YOU MAY NEED
More informationEVALUATING PRICING IN DUE DILIGENCE FOR VALUE CREATION IN PRIVATE EQUITY
EVALUATING PRICING IN DUE DILIGENCE FOR VALUE CREATION IN PRIVATE EQUITY By George Bene, Pete Czerepak, Thomas Kohler, John Pineda, Jeff Robinson, Vik Krishnan In today s hypercompetitive deal environment,
More informationIssued: October 3, 2016 Proposals Due: November 28, 2016
REQUEST FOR QUALIFICATIONS PROFESSIONAL SERVICES For Boulder City Municipal Airport Issued: October 3, 2016 Proposals Due: November 28, 2016 Page 1 of 8 I. Introduction Request For Statements of Qualifications
More informationFOREIGN TRADE ZONES (FTZ) MANUFACTURING TECHNICAL INFORMATION FOR PRE-ASSESSMENT SURVEY (TIPS)
FOREIGN TRADE ZONES (FTZ) MANUFACTURING TECHNICAL INFORMATION FOR PRE-ASSESSMENT SURVEY (TIPS) TABLE OF CONTENTS PART 1 BACKGROUND...2 PART 2 MANUFACTURING FTZ GUIDANCE...2 2.2 EXAMPLES OF BEST PRACTICES...4
More informationRisk Management Plan for the <Project Name> Prepared by: Title: Address: Phone: Last revised:
for the Prepared by: Title: Address: Phone: E-mail: Last revised: Document Information Project Name: Prepared By: Title: Reviewed By: Document Version No: Document Version Date: Review Date:
More informationLLC FORMATION MASTER CHECKLIST
LLC FORMATION MASTER CHECKLIST Preliminary Notes 1. The checklist in the table below (the Table ) identifies the 36 principal tax and non-tax legal tasks that should normally be performed for clients who
More informationAVIATION AUTHORITY REGULAR BOARD MEETING. Thursday, July 2, :00 A.M. Boardroom Level 3 at Tampa International Airport AGENDA
AVIATION AUTHORITY REGULAR BOARD MEETING Thursday, 9:00 A.M. Boardroom Level 3 at Tampa International Airport AGENDA Any person who desires to appeal any decisions made at this meeting will need a record
More informationChapter 7 Department of Transportation and Infrastructure. Pre-mixed Asphalt Procurement
Pre-mixed Asphalt Procurement Chapter 7 Department of Transportation and Infrastructure Pre-mixed Asphalt Procurement Contents Why We Chose this Project.. 259 Background...... 260 Objective and Methodology......
More informationDisaster Harvey, Irma and Maria ( HIM ) and California Wildfires Loan Plan Setup Form Please Complete and Return to your Fidelity Client Service Team
Disaster Harvey, Irma and Maria ( HIM ) and California Wildfires Loan Plan Setup Form Please Complete and Return to your Fidelity Client Service Team Plan #: Plan Name: The Disaster Tax Relief and Airport
More informationRequest for Proposal #2036. Orange Coast College Exterior Lighting Energy Efficiency Project Implementation
Request for Proposal #2036 Orange Coast College Exterior Lighting Energy Efficiency Project Implementation I. NOTICE A. Statement of Proposal NOTICE IS HEREBY GIVEN that Coast Community College District
More informationFeasibility Update. RMRA Feasibility Study Steering Committee. Study Work Schedule: Tasks 1 thru May 22, 2009.
Presentation To RMRA Feasibility Study Steering Committee Feasibility Update May 22, 2009 TEMS, Inc. / Quandel Consultants, LLC 0 Study Work Schedule: Tasks 1 thru 4.4.2 1 1 Study Work Schedule: Tasks
More informationNCHRP Consequences of Delayed Maintenance
NCHRP 14-20 Consequences of Delayed Maintenance Recommended Process for Bridges and Pavements prepared for NCHRP prepared by Cambridge Systematics, Inc. with Applied Research Associates, Inc. Spy Pond
More informationPlease Refer to Attached Sample Form
Revised Cal. P.U.C. Sheet No. 41147-E Cancelling Revised Cal. P.U.C. Sheet No. 40751-E U 39 San Francisco, California ELECTRIC SAMPLE FORM NO. 79-978 Sheet 1 Interconnection Agreement for Net Energy Metering
More informationCHAPTER 4 COST RECOVERY AND REGULATORY TREATMENT PREPARED DIRECT TESTIMONY OF REGINALD M. AUSTRIA ON BEHALF OF SOUTHERN CALIFORNIA GAS COMPANY
Application No: A.1-0- Exhibit No.: Witness: R. Austria Application of Southern California Gas Company (U 0 G) for Approval To Extend the Mobilehome Park Utility Upgrade Program. Application 1-0- (Filed
More informationMEMORANDUM TO: FROM: Karen Schaefer, Manager - Budget ( ) SUBJECT: DATE: October 21, Finance and Administration Committee
MEMORANDUM Page 1 of 9 TO: Finance and Administration Committee FROM: Karen Schaefer, Manager - Budget (612-794-9143) SUBJECT: REPORTS Budget Variance Report 3 rd Quarter DATE: October 21, The third quarter
More informationCity of Cedar Rapids Stewardship. Presented By: TrueNorth
City of Cedar Rapids Stewardship Presented By: TrueNorth 2017 Program Highlights Restructured Property Policy for 2017-2018 Raised Flood and Earthquake Limits to $100 Million from $50 million Modified
More informationWhy Choose ESPC? (What s the Difference?)
Session: Project Financing Why Choose ESPC? (What s the Difference?) Kurmit Rockwell DOE Federal Energy Management Program 1 Rhode Island Convention Center Providence, Rhode Island ESPC Basics Financial
More informationMECKLENBURG COUNTY Land Use & Environmental Services Agency Solid Waste
MECKLENBURG COUNTY Land Use & Environmental Services Agency Solid Waste SUBJECT: REQUEST FOR QUALIFICATIONS (RFQ) MECKLENBURG COUNTY SOLID WASTE ENGINEERING SERVICES I. INTRODUCTION This Request for Qualifications
More informationRFP ATTACHMENT 2 For an Energy Service Company for the Energy Performance Contract UT Health Science Center SBC No.
RFP ATTACHMENT 2 For an Energy Service Company for the Energy Performance Contract UT Health Science Center SBC No. 540/013-05-2016 QUALIFICATIONS AND TECHNICAL PROPOSAL SECTION A: MANDATORY REQUIREMENTS
More informationPACE Financing. J. Caleb Bell, Partner Bricker & Eckler LLP
PACE Financing J. Caleb Bell, Partner Bricker & Eckler LLP 614.227.2384 jbell@bricker.com PACE Financing PACE = Property Assessed Clean Energy Ohio s PACE Law Energy SID A special type of financing district
More informationValidating Process Safety Assumptions using Operations Data Taylor W. Schuler & Jim Garrison aesolutions
Validating Process Safety Assumptions using Operations Data Taylor W. Schuler & Jim Garrison aesolutions 250 Commonwealth Drive, Suite 200 Greenville, SC 29615 Taylor s Bio Taylor Schuler has more than
More informationWe appreciate the opportunity to conduct this performance audit and look forward to serving HCPS again in the near future.
September 5, 2018 Mr. Jeff Eakins, Superintendent Hillsborough County Public Schools 901 East Kennedy Boulevard Tampa, Florida 33602 Dear Mr. Eakins: McConnell & Jones LLP (MJ) is pleased to submit our
More informationEast of Merle Hay Road
East of Merle Hay Road Johnston, Iowa 2017 APWA Spring Conference March 2017 Oldest neighborhood in the City Settled in 1846 Narrow rural corridor with aging or non-existent infrastructure Inadequate
More informationSTATE OF COLORADO OFFICE OF THE STATE ARCHITECT STATE BUILDINGS PROGRAM CONTRACTOR'S DESIGN/BID/BUILD (D/B/B) AGREEMENT (STATE FORM SC-6.
CONTRACTOR'S DESIGN/BID/BUILD (D/B/B) AGREEMENT DEPARTMENT ID: CONTRACT ID #: N/A N/A PROJECT #: PROJECT NAME: Rev. 7/2015 SC-6.21 TABLE OF CONTENTS Page RECITALS 1 ARTICLE 1. PERFORMANCE OF THE WORK..
More informationPublic Private Ventures Process Guide
Public Private Ventures Process Guide This guideline is applicable for proposed privatized transactions that utilize private bond proceeds or other private financing to fund a portion or all cost for development
More informationNYISO Capital Budgeting Process. Draft 01/13/03
NYISO Capital Budgeting Process Draft 01/13/03 1 1.0 INTRODUCTION An effective, capital budgeting process is essential to ensure sound capital investment decisions. This report details a recommended approach
More informationCONFERENCE January 11-13, 2012
ACI-NA RISK MANAGEMENT CONFERENCE January 11-13, 2012 Performance Optimization of Insurance Carriers and Third Party Administrators Presented by: Ginga Griffin, CPCU, ALCM ESIS Inc Health Safety & Environmental
More informationHOLLYWOOD BURBANK AIRPORT REPLACEMENT PASSENGER TERMINAL CONCEPT VALIDATION
11-5-18 Commission Mtg. Item No. 8.a. RPT Concept Validation HOLLYWOOD BURBANK AIRPORT REPLACEMENT PASSENGER TERMINAL CONCEPT VALIDATION COPYRIGHT BUROHAPPOLD ENGINEERING. ALL RIGHTS RESERVED HOLLYWOOD
More informationRevenue Plan. August 12, Dennis Davies Deputy Director of Public Works 200 Civic Center Way El Cajon, CA 92020
1925 Palomar Oaks Way, Suite 3 Carlsbad, California 928 tel: 76 438 7755 fax: 76 438 7411 Dennis Davies Deputy Director of Public Works 2 Civic Center Way El Cajon, CA 922 Subject: Six Year Revenue Plan
More informationORGANIZATIONAL BACKGROUND & SCOPE OF ACTIVITIES IDENTIFIED OBJECTIVES AND SCOPE OF SERVICES
CAYMAN AIRWAYS LTD. REQUEST FOR PROPOSALS AIRCRAFT MODEL SAAB 340 B+ OPERATING LEASE Central Tenders Committee Tender CTC/15-16/CAL/004 Saab Acquisition CTC Reference CTC/15-16/CAL/004 Saab Acquisition
More informationLoan Servicing Procedures Guide
Loan Servicing Procedures Guide Multifamily Capital Markets Newmark Knight Frank provides post-closing services to you for your loan. Your entire relationship is overseen by your Portfolio Manager. As
More informationBURBANK-GLENDALE-PASADENA AIRPORT AUTHORITY Schedule of Customer Facility Charge Revenues and Expenditures Year ended June 30, 2016 (With Independent
BURBANK-GLENDALE-PASADENA AIRPORT AUTHORITY Schedule of Customer Facility Charge Revenues and Expenditures Year ended June 30, 2016 (With Independent Auditor s Reports Thereon) This page left blank intentionally
More informationTransportation Asset Management Webinar Series Webinar 28: Financial Plans
Transportation Asset Management Webinar Series Webinar 28: Financial Plans Sponsored by FHWA and AASHTO Webinar 28 October 11, 2017 1 FHWA-AASHTO Asset Management Webinar Series This is the 28 th in a
More informationThe Economics of Fleet
Session #11 The Economics of Fleet - Presented by NAFA Fleet Management Association Katherine Vigneau, CAFM Agenda 11 Essentials of Fleet Management Lifecycle Costs Analysis Exercise 1 Select the Best
More informationPERSONAL AND PROFESSIONAL EXCELLENCE. Critical System ITN 50 TH ANNUAL CONFERENCE MAY 24-27, 2017 ORLANDO, FLORIDA
PERSONAL AND PROFESSIONAL EXCELLENCE 50 TH ANNUAL CONFERENCE MAY 24-27, 2017 ORLANDO, FLORIDA Critical System ITN Presented by: Denise K Schneider, CPPO, C.P.M., CPPB, CM HOW TO GET THE BEST SERVICE PROVIDER
More informationPlease Refer to Attached Sample Form
Revised Cal. P.U.C. Sheet No. 40226-E Cancelling Original Cal. P.U.C. Sheet No. 29493-E U 39 San Francisco, California Electric Sample Form 79-1118 Sheet 1 General Off-Bill and On-Bill Financing Loan Agreement
More informationAudit Report Community Development Fund 113. County of Collier CLERK OF THE CIRCUIT COURT
Collier County Clerk of the Circuit Court Internal Audit Department Audit Report 2003 7 Community Development Fund 113 County of Collier CLERK OF THE CIRCUIT COURT 2 Collier County Clerk of the Circuit
More informationFacilities Planning & Purchasing Health Sciences Building Marguerite Parkway Mission Viejo, CA Attn: David Schiermeyer
Pool REQUEST FOR QUALIFICATIONS (RFQ) FOR COMMISSIONING SERVICES FOR INCLUSION IN A DISTRICT POOL OF COMMISSIONING SERVICE FIRMS FOR A FIVE (5) YEAR PERIOD AND REQUEST FOR PROPOSALS (RFP) FOR COMMISSIONING
More informationProSIS-FSE. SIL Calculator V1.6 User Guide
SIL Calculator V1.6 User Guide Page 1 of 12 ProSIS-FSE SIL Calculator V1.6 User Guide 1 of 12 Table of Contents ProSIS-FSE... 1 SIL Calculator V1.6 User Guide... 1 1 OBJECTIVES... 3 2 REFERENCES... 4 2.1
More informationImperial County Transportation Commission & First Transit, Inc. Imperial Valley Transit Service Report
Imperial County Transportation Commission & First Transit, Inc. Imperial Valley Transit Service Report For the Year Ended June 30, 2015 TABLE OF CONTENTS INDEPENDENT ACCOUNTANTS REPORT 3-4 ACCOUNTANTS
More informationSOUTH DAKOTA DEPARTMENT OF TRANSPORTATION CONSULTANT SERVICES MANUAL
SOUTH DAKOTA DEPARTMENT OF TRANSPORTATION CONSULTANT SERVICES MANUAL 2017 Approved by FHWA on March 1, 2017 THIS PAGE INTENTIONALLY LEFT BLANK INDEX Chapter Section Title PAGE ACRONYMS i DEFINITIONS ii
More informationReport to the Legislative Budget Board and Governor Pursuant to Rider No. 5 to The University of Texas System Administration HB 1, 84th Legislature,
CAPITAL PROJECTS FOR THE UNIVERSITY OF TEXAS SYSTEM ADMINISTRATION December 2016 Prepared by The University of Texas System Office of the Controller Report to the Legislative Budget Board and Governor
More informationThe Quest for Cost-Efficient Local Government in New England: What Role for Regional Consolidation?
The Quest for Cost-Efficient Local Government in New England: What Role for Regional Consolidation? Yolanda K. Kodrzycki presented at New England Fiscal Leaders Meeting February 23, 2013 The views expressed
More informationAPPENDIX J. CIP Renewal and Replacement Process. Revision History
APPENDIX J CIP Renewal and Replacement Process Revision History Revision Date Approval Reason 0 09/30/05 Original 1 05/25/11 2 09/27/12 3 03/26/14 4 11/14/16 E. Yong Updated Clearinghouse process and replaced
More information60.2 Deposit and Apply Receipts
This document is a draft and subject to change Date: 03/14/2019 Revision: DRAFT Table of Contents Table of Contents... 2 Business Process Name... 3 General Information... 3 Dependencies and Constraints...
More informationCommunity Contracting in the Malawi Social Action Fund: Local Stakeholder Perspectives
No. 163 July 2000 Community Contracting in the Malawi Social Action Fund: Local Stakeholder Perspectives The Malawi Social Action Fund (MASAF) is a quick-disbursing facility which routes money directly
More informationDepartment of Defense Explosives Safety Board (DDESB)
Department of Defense Explosives Safety Board (DDESB) Explosives Safety Munitions Risk Management (ESMRM) Technical Paper 23- DoD Explosives Safety And Munitions Risk Management: Acquisition Lifecycle
More informationSUBJECT: SELLING AND SERVICING UPDATES
TO: Freddie Mac Sellers and Servicers February 17, 2015 2015-2 SUBJECT: SELLING AND SERVICING UPDATES This Single-Family Seller/Servicer Guide ( Guide ) Bulletin announces: Selling and Servicing topics
More informationSupersedes: 9/01/11 (Rev.5) Preparer: Owner: Approver: Team Member, North America Process Safety Center of Expertise
Procedure No.: BC032.019 Page: 1 of 12 Preparer: Owner: Approver: Team Member, North America Process Safety Center of Expertise Manager, North America Process Safety Center of Expertise Sr. Vice President,
More informationAn Overview of Life-Cycle Cost Analysis
Maturity and Value of Energy Efficiency PNNL-SA-128396 An Overview of Life-Cycle Cost Analysis Doug Elliott Pacific Northwest National Laboratory August 17, 2017 Tampa Convention Center Tampa, Florida
More informationBuilding Optimization Analysis (BOA) Tool Training
Building Optimization Analysis (BOA) Tool Training Dave Moser, Senior Engineer, PECI Michelle Lichtenfels, Program Manager, PECI September 8 and 13, 2010 Training Objectives Use the BOA Tool to calculate
More informationFerry Terminal in East Java and Bali Islands Urgent Rehabilitation Project
Indonesia Ferry Terminal in East Java and Bali Islands Urgent Rehabilitation Project 1. Project Profile and Japan s ODA Loan (1) Background Report Date: June 2000 Field Survey: May 2000 Indonesia is a
More informationEMPLOYMENT CONSUMER REPORT AUTHORIZATION
EMPLOYMENT CONSUMER REPORT AUTHORIZATION You have advised me that, in the normal course of processing my employment application, you may obtain a consumer report for employment purposes and/or an investigative
More informationUsing Asset Management Planning to Make Roadway Improvements
Using Asset Management Planning to Make Roadway Improvements 1 Presentation Overview Status of Municipal Infrastructure Asset Management 101 15+ Year Pavement Life cycle Data, M,R&R, Prediction Models,
More informationCOUNTY OF ORANGE, CALIFORNIA REQUEST FOR PROPOSALS
COUNTY OF ORANGE, CALIFORNIA REQUEST FOR PROPOSALS UNDERWRITER SERVICES FOR JOHN WAYNE AIRPORT CAPITAL IMPROVEMENT PROGRAM GENERAL AIRPORT REVENUE BONDS AND PFC (PASSENGER FACILITY CHARGE) - BACKED BONDS
More informationEconomic and Technical Evaluations for Engineering and Maintenance Projects. Germany, Munich, relexa hotel München.
Training Course : Economic and Technical Evaluations for Engineering and Maintenance Projects Training Course For One Week In Germany, Munich, relexa hotel München Which Be Held As Under Details : Tel.
More informationSOCALGAS REBUTTAL TESTIMONY OF MARIA MARTINEZ (PIPELINE INTEGRITY FOR TRANSMISSION AND DISTRIBUTION) JUNE 18, 2018
Company: Southern California Gas Company (U904G) Proceeding: 2019 General Rate Case Application: A.17-10-007/-008 (cons.) Exhibit: SCG-214 SOCALGAS REBUTTAL TESTIMONY OF MARIA MARTINEZ (PIPELINE INTEGRITY
More informationForm 996E Tips and Best Practices
Overview Warehouse Lenders provide Sellers with interim financing in exchange for a security interest in, or beneficial ownership of, mortgages that are subsequently offered for sale to Freddie Mac. The
More informationStanford Life Cycle Cost Analysis Guide. Introduction & Methodology Interpreting LCCA Results LCCA Timeline Tool Instructions
Stanford Life Cycle Cost Analysis Guide Introduction & Methodology Interpreting LCCA Results LCCA Timeline Tool Instructions January 2016 Introduction & Methodology Stanford University has an ongoing commitment
More informationFLAIR Financial Reporting Overview
FLAIR Financial Reporting Overview 1 Month-end and Year-end Closing Central and Departmental FLAIR 2 Closing Closing allows for a snapshot of account balances at a point in time which reflects the results
More informationExhibit 300: Non-Information Technology Capital Asset Plan and Business Case Summary Part I: Summary Information and Justification
CAPITAL ASSET PLAN AND BUSINESS CASE Guidance EXHIBIT 300 Exhibit 300: NonInformation Technology Capital Asset Plan and Business Case Summary Part I: Summary Information and Justification Section A: Overview
More informationFINAL DRAFT CONSISTENCY REVIEW AND RECOMMENDATIONS REPORT
CHRIS CHRISTIE Governor KIM GUADAGNO Lt. Governor State of New Jersey Highlands Water Protection and Planning Council 100 North Road (Route 513) Chester, New Jersey 07930-2322 (908) 879-6737 (908) 879-4205
More informationAnalysis of Past NBI Ratings for Predicting Future Bridge System Preservation Needs
Analysis of Past NBI Ratings for Predicting Future Bridge System Preservation Needs Xiaoduan Sun, Ph.D., P.E. Civil Engineering Department University of Louisiana at Lafayette P.O. Box 4229, Lafayette,
More informationPublic Works and Development Services
City of Commerce Capital Improvement Program Prioritization Policy Public Works and Development Services SOP 101 Version No. 1.0 Effective 05/19/15 Purpose The City of Commerce s (City) Capital Improvement
More informationHaving regard to the Treaty establishing the European Atomic Energy Community, and in particular Articles 31 and 32 thereof,
L 219/42 COUNCIL DIRECTIVE 2014/87/EURATOM of 8 July 2014 amending Directive 2009/71/Euratom establishing a Community framework for the nuclear safety of nuclear installations THE COUNCIL OF THE EUROPEAN
More informationREQUEST FOR PROPOSALS For On-Call Construction Inspection Services CITY OF SAN MATEO, CALIFORNIA
REQUEST FOR PROPOSALS For On-Call Construction Inspection Services CITY OF SAN MATEO, CALIFORNIA The City of San Mateo Public Works Department hereby requests proposals from qualified firms to provide
More informationPresentation on. Risk Assessment. ICAI Seminar on Internal Audit
Presentation on Risk Assessment ICAI Seminar on Internal Audit 1 st Feb 2014 Why Risk Based Audit Plan Definition of Internal Audit Internal Auditing is an independent, objective assurance and consulting
More informationNorth Carolina Reinsurance Facility
North Carolina Reinsurance Facility October 26, 2009 CIRCULAR LETTER TO ALL MEMBER COMPANIES Re: Revision of Commercial Automobile Insurance Rates On behalf of all member companies, the North Carolina
More informationInternal Audit Report
Internal Audit Report State Infrastructure Bank TxDOT Internal Audit Division Objective To evaluate the State Infrastructure Bank program to determine if objectives are being met and are in compliance
More information