1 Blackboard Enterprise Learning Management System Project Name: Blackboard Enterprise LMS Sponsor: Darin King Report Type: Execution For Period: April (March 16-April 12) Project Manager: Angela O Leary EXECUTIVE SUMMARY Overall Summary Prior Status Green Current Status Green Green Yellow Red The project is within 20% variance of the currently approved baseline for budget and schedule and is expected to substantially meet all of the business objectives established in the startup report. The project has exceeded 20% variance of the currently approved baseline for budget and/or schedule and is expected to substantially meet all of the business objectives established in the startup report. The project is at risk of termination, or at risk of not substantially meeting the business objectives established in the startup report. Overall, the project status is both green for the schedule and budget this month. Below are the details on the project. SaaS Both MaSU and NDSU have 1930 courses left to migration to SaaS. This work is scheduled to be d at the end of spring term. SIS Integration NDSU needs to test the Grades Integration on STG during the months of April/May. Governance- decision document found HERE No decisions were made this past month. Governance is currently working on a proposal to restructure the Governance committee to transition from a project to an operational committee. Once Governance has approved of the restructure, the Executive Steering Committee will have an opportunity to review the proposal and provide feedback and grant approval. Ally Implementation Campus Kickoff Technical Setup Deployment & Adoption Plan BSC Complete Courses enabled on STG- Courses to enable to PRD- not started Training DSU Complete Courses to enable to PRD- not started Detailed Agenda sent MaSU Complete Courses enabled on STG- NDSCS Complete Courses enabled to STG- UND Complete Courses enabled on STG- WSC Complete Courses enabled on STG- Page 1 of 5 Detailed Agenda sent Remote Session Workshop Planning- In progress Monthly Check-ins 2 Monthly Check-ins - 1 Monthly Check-ins- 1 Completed two sections of Accessibility Instructors and Courses- Completed two sections of Accessibility Instructors and Courses-
2 VCSU Complete Courses enabled on STG- Courses to Enable to PRD- Reports Overview- Reports Setup for campus- Monthly Check-ins- 1 Course Materials: Accessibility Instructors and Course Remote Instructor Training- Reporting There is one remaining report to be worked on: Report Name Status Contextual Grades Need to schedule a meeting with the work group Page 2 of 5
3 COST MANAGEMENT Summary Prior Status Green Current Status Green Green Variance to cost is within 10% Yellow Variance to cost equals or exceeds 10%, but is within 20% Red Variance to cost equals or exceeds 20% Paid invoice for the Ally product revising the baseline budget by an increase of $276, Below budget 2.2% Innovation Fund Use Cost Total Usage $ Innovation Fund Total (Renewed Sept. 18-Sept. 19) $ 50, Balance $ 50, The budget is showing savings due to the following: o Campuses have opted for remote Bb training versus onsite therefore there is no travel cost Budget Type Original Budget Current Revised Baseline 2019 April Actual Cost $1,236,102 $ 276, $1,513, % Cost Variance Over Under Estimate at Completion Blackboard Software Blackboard $497,200 $0 $497,200 Services eplus $503,676 $0 $503, Travel Costs $133,000 $0 $53, Risk $0 $0 Project Budget $2,369, $276, $2,567, % Under $ 2,586, Help Desk (ecolleges 1 st year) Learn Admin Certification for CTS Learn Admin Certification for System Admins $0 $39,500 $39,500 $0 $6,400 $6,400 $0 $17,095 $17,095 B2 Customization $0 $216,000 $216,000 Reporting Dashboard $0 $18,230 $18,230 DDA Training $0 $16,000 $16,000 Reporting Dashboard $0 $233,000 $233,000 Basic LTI modification $3, Custom Ally Reporting $47,000 Baseline Sub-Total $2,369, $3,243, $3,163, Management Reserve $647, $50,775 Total Budget $3,016, $3,293, Page 3 of 5
4 SCHEDULE MANAGEMENT Summary Prior Status Green Current Status Green Green Variance to schedule is within 10% Yellow Variance to schedule equals or exceeds 10%, but is within 20% Red Variance to schedule equals or exceeds 20% High-level milestones are outlined in the chart below. These milestones have been broken down into smaller tasks that are monitored for status tracking purposes by CTS PM. Milestones that are flagged as having Some Issues Delays : System Governance Decisions continue to be flagged for the following reasons: o Topics are time sensitive and continue to require a quick turnaround from the campuses o Encouraging information sharing and improved communication among committee members continues to be a priority Project Start Date Original Baseline End Date Current Revised End Date % Schedule Variance Ahead Behind Estimated Completion Date 10/1/ /30/ /15/ % BEHIND 08/20/2019 Page 4 of 5
5 Summary SCOPE MANAGEMENT This project report will include the high-level change control and milestone acceptance summary. Change Control Log Summary Change # Description Action: Accept/Reject Action Date Milestone Acceptance Log Summary Deliverable Description # Action: Accept/Reject Action Date Summary There are no issues or risks to report this month RISK/ISSUE MANAGEMENT Risk Management Log Summary Risk # Description Action Action Date No Issues or Risks reported this month Issue Management Log Summary Issue # Description Action Action Date Page 5 of 5
Blackboard Enterprise Learning Management System
Blackboard Enterprise Learning Management System Project Name: Blackboard Enterprise LMS Sponsor: Darin King Report Type: Execution For Period: May 2017 Project Manager: Lindsay Olson EXECUTIVE SUMMARY
More informationAdministrative Affairs Council Minutes February 10, :00 p.m. Conference Call
Administrative Affairs Council Minutes February 10, 2009 1:00 p.m. Conference Call Participants Tamara Barber BSC Becky Lang LRSC Steve Bensen MaSU Jonelle Watson MiSU Jim Borkowski MiSU-BC Mike Renk NDSCS
More informationNDUS ACA Eligibility Criteria, Draft 10/28/14
NDUS ACA Eligibility Criteria, Draft 10/28/14 1. Applicable Large Employer a. State of ND has determined that it is an applicable large employer b. Notified by OMB and PERS on 7/2/14 that the State of
More informationCity of Menifee Development Code Update
City of Menifee June 13, 2018 5:00 PM Agenda Purpose of Project Schedule and Milestones Audit Report Summary Annotated Outline Approach City Council/Planning Commission and Public Feedback Next Steps Project
More informationStrategic IT Accountability Board
Strategic IT Accountability Board 4:00-5:00 p.m., November 12, 2015, Stark Library (MAI 400) I. Fiscal Year 2014-2015 Priorities and ITS Capital Budget Update (Brad Englert) II. Fiscal Year 2015-2016 Priorities
More informationInternal Audit Staffing Levels
State Capitol 600 E Boulevard Ave Dept. 215 Bismarck ND 58505-0230 Phone: 701.328.2960 Fax: 701.328.2961 E-mail: ndus.office@ndus.edu Web: ndus.edu TO: FROM: Members, SBHE Budget, Audit, and Finance Committee
More informationNORTH DAKOTA UNIVERSITY SYSTEM FINANCIAL REVIEW Fiscal Year Ending 2010 (with trends since FY 2007) Prepared in March 2011
NORTH DAKOTA UNIVERSITY SYSTEM FINANCIAL REVIEW Fiscal Year Ending 2010 (with trends since FY 2007) Prepared in March 2011 As with any large business organization governed by a board, it is essential that
More informationProject Connect Connect January 11, 2012
Project Connect January 11, 2012 Introduction Meeting Minutes Approval Project Status Report IV&V Update By Ernst & Young Other Business Public Comments Review of Actions from Meeting Scheduling of Next
More informationProject Connect. August 10, 2011
Project Connect August 10, 2011 Introduction Meeting Minutes Approval Project Status Report IV&V Update By Ernst & Young Other Business Public Comments Review of Actions from Meeting Schedule Next Meeting
More informationSt. Johns County School District, Florida
St. Johns County School District, Florida Contract Compliance Review SunGard Public Sector, Inc. Prepared By: Internal Auditors June 25, 2013 TABLE OF CONTENTS SECTION PAGE Transmittal Letter... 1 Executive
More informationProject Connect. July 11, 2012
Project Connect July 11, 2012 Introduction Meeting Minutes Approval Project Status Report IV&V Update by Ernst & Young Other Business Public Comments Review of Actions from Meeting Scheduling of Next Meeting
More informationNorth Dakota University System Campus Solutions Gainful Employment Reporting
Set Up The first step is to do set up at NSLDS and to complete a set up page for each gainful employment program. In order for an institution to be able to report GE information via batch, an online user
More informationAdministrative Affairs Council Meeting Minutes Thursday February 4, :00 p.m. Conference Call
Administrative Affairs Council Meeting Minutes Thursday February 4, 2016 1:00 p.m. Conference Call Attendance: BSC, Tamara Barber, Dave Clark, Mary Eisenbraun DCB, Laura Pfeifer DSU, Scott Hanson, Janet
More informationExecutive Steering Committee Medicaid Eligibility System Project. October 24, 2014
Executive Steering Committee Medicaid Eligibility System Project October 24, 2014 Minutes -2- Federal Partner Update -3- Account Transfers Federally Facilitated Marketplace (FFM) As of October 20, 249,417
More informationVDOT Dashboard 4.0 Projects User Guide DRAFT
VDOT Dashboard 4.0 Projects User Guide DRAFT March 2018 Table of Contents INTRODUCTION... 1 About this Guide...1 Purpose of the Guide... 1 Audience for the Guide... 1 About Dashboard...1 VDOT Dashboard...
More informationPerformance After Funding Breakout Session #4. Thursday, September 20, 2018 Michaela McCain Moderator Outreach Manager Local Assistance Division
Performance After Funding Breakout Session #4 Thursday, September 20, 2018 Michaela McCain Moderator Outreach Manager Local Assistance Division Federal Funds Management Wendy E. Thomas Director of Federal
More informationPerformance After Funding Breakout Session #4. Thursday, September 20, 2018 Michaela McCain Moderator Outreach Manager Local Assistance Division
Performance After Funding Breakout Session #4 Thursday, September 20, 2018 Michaela McCain Moderator Outreach Manager Local Assistance Division Project Dashboard Nicholas J. Roper, P.E. Project Development
More informationProject Connect. September 14, 2011
Project Connect September 14, 2011 Introduction Meeting Minutes Approval Project Status Report IV&V Update By Ernst & Young Other Business Public Comments Review of Actions from Meeting Schedule Next Meeting
More informationProject Connect Executive Steering Committee Update. April 10, 2013
Project Connect Executive Steering Committee Update April 10, 2013 Agenda Introduction Meeting Minutes Approval Project Status Report IV&V Update by Ernst & Young Other Business Public Comments Review
More informationProject Connect. May 9, 2012
Project Connect May 9, 2012 Introduction Meeting Minutes Approval Project Status Report IV&V Update by Ernst & Young Other Business Public Comments Review of Actions from Meeting Scheduling of Next Meeting
More informationQuick Reference Card PPM Pro Project Data Field Dictionary
Actual Completion Date This is the date the project actual completed. When this date is entered the project Status should be moved to Completed. This field is used in the standard Project metric reports.
More informationBudget Manager Meeting. February 20, 2018
Budget Manager Meeting February 20, 2018 Meeting Agenda DISCUSSION DRAFT NOT FOR DISTRIBUTION Budget Office Current Year Forecast Process Endowment Payout Control Charts FY19 Target Meetings Delphi Project
More informationWorkshop II Project Management
Workshop II Project Management UNITAR-HIROSHIMA FELLOWSHIP FOR AFGHANISTAN 2007 Introduction to Project Management 15 17 August 2007, Dehradun, India Presented by: Dr. Jobaid Kabir Fellowshop Program 2007
More informationPMI Long Island Chapter s Tools and Techniques Series PM101
PMI Long Island Chapter s Tools and Techniques Series PM101 Project Metrics & KPIs Agenda Overview Why Metrics and KPIs important Source of Metrics and KPIs Common PM Metrics and KPIs Other PM Metrics
More informationVAT Information System*
116 Compendium of e-governance Initiatives CHAPTER in India 9 VAT Information System* M.M. Shrivastava Commissioner of Commercial Taxes, Govt. of Gujarat Office of Commissioner of Commercial Taxes, Sales
More informationDC Program and Project Managers Meeting #2
+ Trevor Lowing Trevor.Lowing@gmail.com DC Program and Project Managers Meeting #2 Session 1: Planning projects with MS Project Session 2: Workshop: Generating Reports with MS Project and Visual Basic
More informationNORTH DAKOTA UNIVERSITY SYSTEM FINANCIAL REVIEW Fiscal Year Ending 2015 (with trends since FY 2012) Date: March 31, 2016
NORTH DAKOTA UNIVERSITY SYSTEM FINANCIAL REVIEW Fiscal Year Ending 2015 (with trends since FY 2012) Date: March 31, 2016 The central purpose and use of the information in this report is to provide a financial
More informationProject Atlas Update (SAP - FIS/HR/Payroll System)
Project Atlas Update (SAP - FIS/HR/Payroll System) (City Council on December 14, 15 and 16, 1999, adopted this Clause, without amendment.) The Policy and Finance Committee recommends the adoption of the
More informationNorth Dakota University System
North Dakota University System Commitment Accounting Manual PeopleSoft HRMS 9.1 Table of Contents COMMITMENT ACCOUNTING... 4 OVERVIEW... 4 Objectives... 4 UNDERSTANDING COMMITMENT ACCOUNTING... 5 Commitment
More informationWyoCloud Planning & Budgeting Townhall. December 12 th, 2017
WyoCloud Planning & Budgeting Townhall December 12 th, 2017 1 Agenda Why does UW need WyoCloud Planning and Budgeting? What is WyoCloud Planning and Budgeting? WyoCloud Planning and Budgeting User Groups
More informationUNDERSTANDING CAEP FEES & ACCREDITATION COSTS
UNDERSTANDING CAEP FEES & ACCREDITATION COSTS KEISHA WALKER MANAGER OF FINANCE & EVENTS, CAEP Washington, District of Columbia September 2017 Agenda CAEP FEES & ACCREDITATION SITE VISIT COSTS Background
More informationProject Management. Joycelyn M. Ray HCC Insurance Holdings SCCE- Chicago 9/08
Project Management Joycelyn M. Ray HCC Insurance Holdings SCCE- Chicago 9/08 Society of Corporate Compliance and Ethics 6500 Barrie Road, Suite 250, Minneapolis, MN 55435, United States www.corporatecompliance.org
More informationPFM MoneyMobile. Product Overview Guide. August 2013
PFM MoneyMobile Product Overview Guide August 2013 1 Contents MoneyMobile iphone App... 3 New Navigation Menu... 5 Accounts... 6 Transactions... 13 Excluded Transactions... 16 Spending Wheel... 17 Bubble
More informationWRIA 1 Program Coordination
WRIA 1 Program Coordination WRIA 1 Management Team Meeting Date: October 12, 2016 Time: 10:00am-12:00pm Location: Garden Room, Civic Center Annex, 322 N. Commercial, Bellingham, WA 98225 ADMINISTRATIVE
More informationPART-TIME NEW-HIRE FREQUENTLY ASKED QUESTIONS
PART-TIME NEW-HIRE FREQUENTLY ASKED QUESTIONS Initially Setting up your Username and Password...2 Signing in to mycfcc...6 Signing in to Your CFCC Email...7 Signing in to WebAdvisor...8 Locating Your Monthly
More informationProject Connect Executive Steering Committee Update. August 14, 2013
Project Connect Executive Steering Committee Update August 14, 2013 Agenda Introduction Meeting Minutes Approval Project Status Report Other Business Public Comments Review of Actions from Meeting Scheduling
More informationProject Connect. June 22, 2011
Project Connect June 22, 2011 Introduction Meeting Minutes Approval Project Status Report IV&V Update By Ernst & Young Other Business Public Comments Review of Actions from Meeting Schedule Next Meeting
More information2. Achievements / Performance in the period to December 2017
Library Plan Update 2017/18 December 2017 Q3 1. Background At its meeting on 25 March 2017 the Board agreed the 2017/18 Library Plan (BM/17/04). The plan continues to be based upon the six strategic priorities
More informationTown Hall: FY18 Final Budget. Grand Salon Monday, September 25, :00 am
Town Hall: FY18 Final Budget Grand Salon Monday, September 25, 2017 10:00 am Agenda 1. 2017/18 Approved Budget (System-wide and campus-level overview) 2. Strategic Initiatives Steering Committee 3. 2018/19
More informationProfessional & Managerial Staff 3-5 Advisory Committee Meeting Summary April 22, 2014
1) Caucus Time (30 minutes) Professional & Managerial Staff 3-5 Advisory Committee Meeting Summary April 22, 2014 Time for members to discuss scheduled agenda items or other issues. 2) Updates on s from
More informationFinancial Performance Management Training Catalog. Management Planning and Control Vantage Risk and Budgeting
Financial Performance Management Training Catalog Management Planning and Control Vantage Risk and Budgeting January 2019 June 2019 Table of Contents Performance Management Solutions Training from Fiserv...
More informationINSTITUTIONAL EFFECTIVENESS Procedures Manual. Developed by the Office of Institutional Effectiveness
INSTITUTIONAL EFFECTIVENESS Procedures Manual Developed by the Office of Institutional Effectiveness 2014-2018 INSTITUTIONAL EFFECTIVENESS PROCEDURES MANUAL Purpose < To support a comprehensive institutional
More informationWRA/WLA Communications Transition Plan
WRA/WLA Communications Transition Plan SUMMARY OF BRAINSTORMING Getting an inventory of existing WLA Communications was the initial step of the Communications transition process. The group determined the
More informationOregon Department of Justice
Oregon Department of Justice Ellen F. Rosenblum, Attorney General Oregon Department of Justice Division of Child Support Oregon Child Support System Project Presentation to Joint Emergency Board Interim
More informationPhase 1: Water Budget Based Rate Structure Feasibility Analysis
Attachment #1 SCOPE OF WORK NOTE: All references to meeting(s) will mean face-to-face meetings and not conference calls. Phase 1: Water Budget Based Rate Structure Feasibility Analysis Task 1: Kick-off
More informationNorth Dakota University System
North Dakota University System FSA Manual PeopleSoft Version 9.1 DISCLAIMER Written by the North Dakota University System, September, 2006. Updated October 2008; November 2008 Updated to 9.1 June 2011
More informationLoan Pay Guide 1. Log in to Online Banking; the loan pay display is labeled My Loan Payment Guide and appears directly below My Accounts.
Loan Pay Guide 1 Loan Pay is a tool that exists within online banking and allows qualified users to pay a Sun East loan, at no charge, from any checking, savings, or money market account at any financial
More informationILTA Webinar November 2, 2012
ILTA Webinar November 2, 2012 Introduction BudgetManager Randy Steere LLC Randy535@aol.com 617.794.4100 Part II in Series First Part was about creating matter budgets This second session will be about
More informationVDOT S NEW DASHBOARD AND WHAT IT MEANS TO LOCALITIES
VDOT S NEW DASHBOARD AND WHAT IT MEANS TO LOCALITIES Webinar for Localities April 26, 2018 Agenda Topics Why is the Dashboard important? Objective and Expected Outcomes The New Dashboard 4.0 Governing
More informationNORTH DAKOTA UNIVERSITY SYSTEM FINANCIAL REVIEW Fiscal Year Ending 2014 (with trends since FY2011) March 2015
NORTH DAKOTA UNIVERSITY SYSTEM FINANCIAL REVIEW Fiscal Year Ending 2014 (with trends since FY2011) March 2015 The central purpose and use of the information in this report is to provide the board with
More informationIT TRANSFORMATION PROJECT January 2019
1 IT TRANSFORMATION PROJECT January 2019 PROJECT UPDATE The IT Transformation Project keeps moving forward in this new calendar year. The holiday season was filled with progress as more college units,
More informationINDOOR AQUATICS CENTER
INDOOR AQUATICS CENTER FEASIBILITY & ANALYSIS PRESENTATION City of Cambridge, MN Aquatics Task Force ORB Management Corporation November 16, 2015 AGENDA Topics 1. Task Force Purpose 2. Project Parameters
More information1/18/2017. Dear Valued Michelin Direct Retailer,
1/18/2017 Dear Valued Michelin Direct Retailer, As an instrumental asset within the Michelin Retail Network, we truly value your input and recommendations you have provided to us and deemed critical for
More informationProject Connect. November 14, 2012
Project Connect November 14, 2012 Introduction Meeting Minutes Approval Project Status Report IV&V Update by Ernst & Young Other Business Public Comments Review of Actions from Meeting Scheduling of Next
More informationDASHBOARD 4.0. VTCA-VDOT Consultant Forum. Jay Styles, Performance and Strategic Planning Director. October 2018
DASHBOARD 4.0 VTCA-VDOT Consultant Forum Jay Styles, Performance and Strategic Planning Director October 2018 Agenda Topics Why is the Dashboard important? Objective and Expected Outcomes The New Dashboard
More informationWelcome to the. Financial Aid and Scholarships
Welcome to the Financial Aid and Scholarships 2018-2019 Today's Topics: COSTS How much does it cost to attend? RESOURCES Savings Grants & Scholarships Loans NEXT STEPS I will have a balance due what are
More informationManaging Customer Expectations. Dean P. Mallory 23 Oct 2018
Managing Customer Expectations Dean P. Mallory 23 Oct 2018 But we didn t call it Project Management Consolidate mainframe computer operations Ft Bragg, Pope AFB Air Show and Open House Commander s Conference
More informationFrom Suspicion to Invaluable Transition of Two Project Managers
From Suspicion to Invaluable Transition of Two Project Managers June 2010 Shilpi Kumar & Sunita Raman Agenda Unisys and HOLMES 2 Nature of Projects and Roles Why EVA? How? EVA in Development Projects Transition
More informationBanking & Settlement. Cash Sales Non-Sponsored Accounts Receivable Endowments & Spendable Gifts. March 27, 2017
Banking & Settlement Cash Sales Non-Sponsored Accounts Receivable Endowments & Spendable Gifts Workday@Yale March 27, 2017 Agenda Overview Key Changes & Demo Cash Sales Non-Sponsored Accounts Receivables
More informationFY 2020 ANNUAL FUNDING DIRECTIVES
1 FY 2020 ANNUAL FUNDING DIRECTIVES INTRODUCTION All Chartered Student Organizations (CSOs) and committees of the Association proven to be fiscally responsible are eligible to petition the Senate for annual
More informationCost Management Mock Exam. Lab for PMP Exam Prep Course Part 2 #347 Instructor: Neal L. Rowland, PMP
Cost Management Mock Exam Lab for PMP Exam Prep Course Part 2 #347 Instructor: Neal L. Rowland, PMP 10 Practice Questions Move at Your Own Pace Question 1 You are project manager for a $2.3M project that
More informationWork Breakdown Structures (WBS)
Work Breakdown Structures (WBS) 1 WBS Technique originally developed by financial specialists to track spent money on a program or track the anticipated a need to spend money A control mechanism to make
More informationRETURN TO ROME Dr. Kenneth F. Smith, PMP Project Management Fundamentals 1
RETURN TO ROME Project Management Fundamentals 1 Work - Milestones Plan: MS 4 Four Day Rome Project S-Curve Work vs Time Actual vs. Plan MS 3 MS 2 MS 1 = Plan = Actual Cumulative Milestones Completed 0
More informationNorth Dakota University System Campus Solutions Financial Aid Direct Loans Set Up
Contents Resources... 3 U. S. Department of Education... 3 G5... 3 COD/SAIG... 3 HEUG... 3 National Direct Student Loan Coalition... 3 UPK for DL... 3 COPY Feature... 4 Item Type Numbering... 4 Decisions/Other
More informationThe Pension Problem and What the City Is Doing About It
The Pension Problem and What the City Is Doing About It 1 2 Why Are We Here Today? I N F O R M P L A N Q & A Inform all stakeholders of the problem and the process to develop a plan Lay out process to
More informationSection II PROJECT MANAGEMENT METHODOLOGY GUIDELINES
Section II B PROJECT MANAGEMENT METHODOLOGY GUIDELINES Chapter 8 INTRODUCTION TO A METHODOLOGY Vision The vision of the Project Management Center of Excellence (PMCoE) organization is to achieve a world-class
More informationUR Budget. Demo Days Meeting. October 2017
UR Budget Demo Days Meeting October 2017 Chatting for Zoom Participants For those joining the Zoom: 1) Please access the chat feature at the top of your screen 2) Please chat directly with Libby Deibler
More informationLocks and Dams 2-3-4, Monongahela River (Lower Mon) Bottom Line Up Front
Locks and Dams 2-3-4, Monongahela River (Lower Mon) Bottom Line Up Front Current Schedule: On Schedule March 2023 (Early Project Operational, 90% benefits) January 2024 (Early Project Complete) Current
More informationTerms of Reference Consultancy for the Assessment of Green Investment Opportunities in Kenya October 2017
In partnership with Terms of Reference Consultancy for the Assessment of Green Investment Opportunities in Kenya October 2017 1. Background The Kenya Bankers Association (KBA) is the financial sector's
More informationUpdates & Milestones re: Peak Demand Reduction. EEAC Consultants (with PA contributions) (Revised, 3/13/17)
Updates & Milestones re: Peak Demand Reduction EEAC Consultants (with PA contributions) (Revised, 3/13/17) Key Work Streams in 2016-2018 Following the Analytical Framework Cost-Effectiveness Framework
More informationW R I T I N G C E N T E R W E E K L Y A C T I V I T Y O V E R V I E W F A L L S P R I N G
W R I T I N G C E N T E R W E E K L Y A C T I V I T Y O V E R V I E W F A L L 2 0 1 6 - S P R I N G 2 0 1 7 The following report provides a snapshot of the average weekly activities in the Writing Center
More informationTo understand project management, it is important to understand the definition of a project:
Management To understand project management, it is important to understand the definition of a project: A project has two characteristics: 1. s have a beginning and an end. The beginning may be somewhat
More informationSociety of American Archivists Council Conference Call January 17, 2018
Agenda Item V.D. Society of American Archivists Council Conference Call January 17, 2018 November 2017 Year-to-Date Financial Statements FY 2018 (Prepared by Cheryl Stadel-Bevans and Peter Carlson) Overview
More informationUR Budget. Demo Days Meeting. December 2017
UR Budget Demo Days Meeting December 2017 Chatting for Zoom Participants For those joining the Zoom: 1) Please access the chat feature at the top of your screen 2) Please chat directly with Libby Deibler
More informationThe University of Western Ontario Department of Political Science Master of Public Administration, Local Government Program
The University of Western Ontario Department of Political Science Master of Public Administration, Local Government Program Nigel Bellchamber 519-61-1189 E-mail: nbellcha@uwo.ca PA 9912b Financial Management
More informationANNUAL FINANCIAL REPORT. June 30, 2017
ANNUAL FINANCIAL REPORT June 30, 2017 NORTH DAKOTA UNIVERSITY SYSTEM ANNUAL FINANCIAL REPORT Fiscal Year Ended JUNE 30, 2017 Prepared by the North Dakota University System Director of Financial Reporting
More informationAdvanced Credit Control Module Administrators Guide DOCUMENTATION. Phone: Fax:
Advanced Credit Control Module Administrators Guide DOCUMENTATION Phone: 01981 590410 Fax: 01981 590411 E-mail: information@praceng.com CHANGE HISTORY ORIGINAL DOCUMENT AUTHOR: MICHELLE HARRIS DATE: OCT
More informationFinancial Indicators. FY18 Third Quarter Report
Financial Indicators Third Quarter Report Financial Indicators Table of Contents Introduction... 3 Total Cash Statement for Quarter..... 4 BHSU... 5 DSU.. 6 NSU.. 7 SDSMT.. 8 SDSU/AES/Extension.. 9 USD
More informationINTRODUCTION TO FLORIDA S STATEWIDE TRAVEL MANAGEMENT SYSTEM
INTRODUCTION TO FLORIDA S STATEWIDE TRAVEL MANAGEMENT SYSTEM GETTING STARTED System Purpose Why create it? Who does this system serve? Project Organization Project Approach Training Approach Onboarding
More informationPEOPLESOFT APPLICATION ROAD MAP PROJECT THE WAY FORWARD
PEOPLESOFT APPLICATION ROAD MAP PROJECT THE WAY FORWARD Phase 2 The HABIT Program HCM Automation and Business Information Transformation Program October 16, 2014 Agenda Summary of The Program Program Timeline
More informationHSCIC Financial Management and Reporting
HSCIC Financial Management and Reporting Author: Rebecca Giles/Carl Vincent Date 24 th February 2014 1 Copyright 2014, Health and Social Care Information Centre. Contents Contents 2 Introduction 3 Current
More informationFlorida International University EABM Meeting. April 20, 2012
Florida International University EABM Meeting April 20, 2012 Agenda Chart of Account Redesign Project Questions & Answers Chart of Account Redesign Goals To develop a financial structure which will identify,
More informationANNUAL FINANCIAL REPORT. June 30, 2016
ANNUAL FINANCIAL REPORT June 30, 2016 NORTH DAKOTA UNIVERSITY SYSTEM ANNUAL FINANCIAL REPORT Fiscal Year Ended JUNE 30, 2016 Prepared by the North Dakota University System Director of Financial Reporting
More informationCEdMA Market Barometer 12Q2
CEdMA Market Barometer 12Q2 It s like pulling teeth! 86 members were sent the survey 23 completed by August 10, the first deadline 24 completed by August 24, the second deadline 33 completed by August
More informationQuick Start Guide: Set a budget and track a project. ARGUS Developer 7.6. Snapshot Module
Quick Start Guide: Set a budget and track a project ARGUS Developer 7.6 Snapshot Module PURPOSE This brief guide has been designed to show the user how the basic features in Snapshot are used to produce
More informationBIOSURF. (BIOmethane SUstainable and Renewable Fuel) Project Handbook (D1.1) Loriana PAOLUCCI & Stefano PROIETTI (ISIS)
(BIOmethane SUstainable and Renewable Fuel) Project Handbook (D1.1) Authors: Loriana PAOLUCCI & Stefano PROIETTI (ISIS) Version: Final Quality Review: Stefano PROIETTI Date: 28-02-2015 Grant Agreement
More information2020 Capital Budget For Architects & Engineers
2020 Capital Budget For Architects & Engineers What you need to know about the 2020 Capital Budget Process with Minnesota State MINNESOTA STATE May 2018 Greg Ewig, System Director, Capital Development
More informationW R I T I N G C E N T E R W E E K L Y A C T I V I T Y O V E R V I E W F A L L S P R I N G
W R I T I N G C E N T E R W E E K L Y A C T I V I T Y O V E R V I E W F A L L 2 0 1 6 - S P R I N G 2 0 1 7 The following report provides a snapshot of the average weekly activities in the Writing Center
More informationFAQ. Q: Where can I find my account number? A: You can find your account number on a recent paper bill.
FAQ Q: Do I need any special hardware or software to sign up for this E-Bill Express payment service? A: No special hardware or software is required to use this service. You will only need Web access and
More informationINSE 6230 Total Quality Project Management Winter 2018 Quiz I. Max : 70 points. This is a closed book exam. Answer all the questions in the booklet.
. Surname, given names: Student Number: INSE 6230 Total Quality Project Management Winter 2018 Quiz I. Max : 70 points This is a closed book exam. Answer all the questions in the booklet. Ensure that your
More informationFinancial Performance Management Training Catalog. Management Planning and Control Vantage Risk and Budgeting
Financial Performance Management Training Catalog Management Planning and Control Vantage Risk and Budgeting January 2018 June 2018 Table of Contents Performance Management Solutions Training from Fiserv...
More information"Charting the Course... MOC A Microsoft Dynamics AX 2012 Public Sector-Financials Course Summary
Course Summary Description This two-day instructor-led course, Microsoft Dynamics AX 2012 Public Sector-Financials, provides students with the necessary tools and resources to perform advanced tasks using
More informationAudaDashboard Quick Start Guide
AudaDashboard Quick Start Guide G E T T I N G S T A R T E D A N D U N D E R S T A N D I N G M E T R I C S OVERVIEW AudaDashboard is a Repairer / Bodyshop management information tool that provides an at-a
More informationA16 Documenting CECAS PRC 29 Request & Baseline SIF Data Training Script ( ) 1
A16 Documenting CECAS PRC 29 Request & Baseline SIF Data Training Script (04.17.14) 1 Welcome 9:00 9:05 1:00 1:05 Hello and welcome to the Documenting CECAS PRC 29 Request and Baseline SIF Data training
More informationResponding to a Project Call: How To Guide
Responding to a Project Call: How To Guide CALL WORKSHOP September 8, 2016 D M D I I. O R G Projected Timeline for the July 2016 Project Call PHASE 1 PRE-SELECTION EVALUATION & SELECTION CALL NOTICE Jul
More informationWhat s New? Travel Forms and More. July 2016 Julie Hughes, Travel & Complex Payment Supervisor
What s New? Travel Forms and More July 2016 Julie Hughes, Travel & Complex Payment Supervisor Agenda Goals for Travel Changes Travel Advances Exception Basis Maximization of P-card usage Prepayments to
More informationManaged Services Product Terms
1. Our contract with you Managed Services Product Terms 1.1. These Product Terms apply to the services ("Managed Services") provided by the Company ("us", "we" or "our") to the Customer ("you" or "your")
More informationTopic 5 - Organising and Supporting Events. N4/N5 Administration & IT
Topic 5 - Organising and Supporting Events N4/N5 Administration & IT 1 Learning Intentions / Success Criteria Learning Intentions Organising and Supporting Events Success Criteria By end of this topic
More informationEarned Value Project Management. Amber L. Romero, CPM, P.M.P., Policy Analyst Sandia National Laboratories 505/ ;
Dollars $M Earned Value Project Management Amber L. Romero, CPM, P.M.P., Policy Analyst Sandia National Laboratories 505/284-0634; allewis@sandia.gov 95 th ISM Annual International Supply Management Conference,
More informationCost Planning, Control & Optimization
An Intensive 5 Day Training Course Cost Planning, Control & Optimization in a Major Oil & Gas Company 10-14 Nov 2019, Dubai 28-NOV-18 This course is Designed, Developed, and will be Delivered under ISO
More information