1 FY2007 Proposed Budget Fiscal 2007 Proposed Budget Briefing Division Planning, Development, Engineering Construction Budget Committee January 26,

2 Division Planning! Development! Engineering! Construction (PDEC) P. Takis Salpeas Deputy General Manager Linda Stfregen Executive Assistant Mary C. Knight Office Administrar Edward L. Thomas AGM Planning & Info Technology Gary Malasky Direcr Property Development And Management George Lea Chief Engineer Facilities Harry E. Lupia Chief Engineer Systems Dan E. Hanlon Chief Engineer Vehicles James R. Haggins Direcr Construction David W. Couch Direcr Infrastructure Renewal Programs Joyce L. Jones Direcr Administration 2

3 FY2007 Proposed Budget MISSION STATEMENT: Utilizing it s high quality experienced, multi-disciplinary planning, real estate, pressional engineering, architecture, construction management, inspection, information technology administration staff, PDEC provides a single point accountability for planning, designing, implementing operational enhancements, system expansion, system access, technology, rolling sck infrastructure renewal projects. In terms WMATA s core mission, PDEC provides on-going engineering leadership for Bus Rail support Operations, integrate WMATA s experiences so that the future projects are implemented better-faster-cheaper in full compliance with Federal, State, Local WMATA regulary oversight code(s) requirements. P D E C PLANNING DEVELOPMENT ENGINEERING CONSTRUCTION 3

4 Division Planning! Development! Engineering! Construction A Valued Asset the Authority The Division Planningh DevelopmenthEngineeringhConstruction (PDEC) is the outgrowth the Authority s Engineering Construction Division which built the 106-mile, 86-station, Metrorail System. The Division reflects a comprehensive organization with decades progressive diverse experience in successfully completing thouss complex public infrastructure projects estimated at more than $25 billion. The Division brings gether 564 staff in a unique synergy talents, expertise experiences deliver annually projects with a minimum owner cost, thus create value for the Authority. Capital funded projects are always dependent on the scope work available funded. For example, should the Dulles project not proceed as planned, there could be an Authority-wide reduction in force 50 FTEs. Goals: Zero-lerance for project schedule delays. On average, at least 75 cents every project dollar should be for direct construction/ installation contracting; 12 cents for consulting services, no more than 13 cents in tal for the owner organization. Individual accountability for senior managers proactively ensure successful project implementation. 4

5 FY 2007 Proposed Budget Division Planning, Development, Engineering & Construction What We Do How We Do It Plan, develop, design construct infrastructure projects for New-Starts modernization, rolling sck (Bus Railcars), technology (hardware stware) Formulate deliver capital-intensive facilities, systems, technology rolling sck projects from Cradle- Grave Manage hundreds competitively procured contracts; annually implement projects ranging from $1M $400M Oversee pressional consulting firms in developing delivering the Authority s transit projects, continued inspections every constructed project vehicle procurement Advise the CEO Board Direcrs on proposed projects, technology improvements, project risk assessments, cost estimates staffing requirements Develop, motivate, menr continuously train staff update technical specifications, designs criteria, code(s) compliance requirements project management methods techniques Goals: Maintain complete open relationships with regulary oversight agencies (e.g. FTA project management oversight) Certify that each project has been completed based on a well formulated quality safety plan fully satisfies the FTA project management principles: (a) time cost increases should be no more than 5%; (b) continuously enhance safety security aspects; (c) provide capacity for increased ridership by 1% each year Maintain an effective communication with the planning, engineering construction staff in all WMATA jurisdictions via bi-monthly quarterly coordination meetings 5

6 FY2007 Proposed Budget Division Planning, Development, Engineering & Construction Summary Operating Expense: $ Millions FY2006 FY2007 Labor $19.2 $19.5 $0.3 Fringes Services Materials Other Total $33.1 $34.4 $ % FY2006 FY2007 Capital Expense $40.8 $42.6 $ % FY2007 FY2006 Budgeted Positions Detail Overall net reduction in positions for the Division based on increases & decreases in projects. No significant changes from FY Major Major Cost Cost Drivers Drivers & Program Program s s Services Services increases increases support: support: Multi-disciplinary Multi-disciplinary engineering engineering support support services services More More joint joint development development projects projects Advancement Advancement Dulles Dulles Metrorail Metrorail Project Project Continuation Continuation Parking Parking Expansion Expansion Program Program 6

7 FY 2007 Proposed Budget Division Planning, Development, Engineering & Construction Department Planning Information Technology plans system expansion, station enhancements, bus system improvements, installs upgrades the Authority s business management systems supports the IT/ROCS infrastructure. Planning Develop station access capacity analysis lay foundation for station area vision plans, improvements joint development Conducts corridor studies for system expansion Advance bus projects in priority bus corridors identified by Metro Matters Bus Program Information Technology Replace major legacy business systems (Information Technology Renewal Program) with modern integrated systems Restructure transition ITSV support new IT systems Ensure IT infrastructure capacity through completion Server Consolidation Project database management Assume operations maintenance responsibility for the new Rail Operating Computer System (ROCS) Promote implementation Public-Private Technology Partnership Measures Benchmarks 100% ITRP remaining modules are implemented Maintain ROCS reliability at 99.9% Assure every project is well planned fully coordinated with the local jurisdictions Represent WMATA in all jurisdictional transportation planning activities Maintain WMATA Intranet reliability at 98% with full cusmer support all WMATA users Ensure Regional CLRP includes WMATA Ten Year Capital Plan Ensure Regional TIP includes WMATA Six Year Capital Improvement Plan Minimize the schedule delays for Development projects 7

8 FY 2007 Proposed Budget Division Planning, Development, Engineering & Construction Office Property Development Management assist with negotiations real estate agreements the management certain leases. Actively support 54 real estate joint development projects Issue Requests for Proposal implement retail concession programs at Metrorail Stations Complete installation ATMs at 35 Metrorail Stations Has generated approximately $150 million in support funding Authority operations Offer Vienna real estate for disposition coordinate other possible dispositions as directed by the Board Direcrs Measures Benchmarks Ensure 100% joint development fees are collected Maintain 100% Authority leases as current 100% coordination all projects both internally with planning, engineering architecture externally with the WMATA jurisdictions Total compliance with the Federal, State, Local WMATA regulary oversight code(s) requirements 8

9 FY 2007 Proposed Budget Division Planning, Development, Engineering & Construction Office Chief Engineer-Facilities provides engineering leadership continued technical support operations ensuring safety, reliability services, best maintenance practices adherence the Authority s Design Criteria Stards prevailing code(s). Provide support for operations, new facilities, maintenance, infrastructure renewal projects in the civil/track structures, architecture, electro-mechanical environmental engineering areas. Provide the Authority s Architect services Support Dulles rail expansion Metro Matters Yards upgrade numerous reimbursable projects Perform reviews updates preventive maintenance procedures for HVAC systems station power systems Provide Authority-wide support on an on-call basis for supported technical issue resolution Ensure environmental code compliance facility waste discharges Implement advanced engineering technology include ground penetrating radar remote moniring critical mechanical systems Maintain asset invenry emergency response maps Measures Benchmarks Provide 24/7 engineering support Operations for both Bus Rail. Utilize state--the-art criteria stards in design engineering support during construction 100% design reviews by pressional engineers architects 9

10 FY 2007 Proposed Budget Division Planning, Development, Engineering & Construction Office Chief Engineer-Systems provides engineering leadership continued technical support operations ensuring safety, reliability services, best maintenance practices adherence the Authority s Design Criteria Stards prevailing code(s). Provide support for operations, new facilities, maintenance, infrastructure renewal projects in the traction power, communication, aumatic train control, computer system engineering areas Support Dulles rail expansion Metro Matters Yards upgrade numerous reimbursable projects Provide Authority-wide support on an on-call basis for supported technical issue resolution Implement advanced engineering technology include moniring the performance traction power aumatic train control systems Maintain asset invenry emergency response maps Measures Benchmarks Provide24/7 engineering support Operations for both Bus Rail. Utilize state--the-art criteria stards in design engineering support during construction 100% design reviews by pressional engineers Maintain computer based diagnostics aumatically detect rapidly correct problems minimize cusmer service interruptions (e.g. track circuit diagnostics) 10

11 FY 2007 Proposed Budget Division Planning, Development, Engineering & Construction Office Chief Engineer-Vehicles provide engineering leadership continued technical support operations ensuring safety, reliability best maintenance practices for railcars buses while providing for project management, inspection acceptance for new rehabilitated buses railcars. Reduce service delays through improved trend analysis for maintenance problems component failures Oversee warranty work by vehicle contracrs Review reliability trends by subsystem develop specific annual remediation work programs. Improve reliability focused maintenance process procedures Support Operations Maintenance Training Support Technical evaluation, stards & configuration development Reliability focused planning improvement programs Engineering documentation management system performance moniring Measures Benchmarks Monir weekly the fleet reliability performance by subsystem report engineering analysis Maintain skillful exploitation state--the-art safety, criteria stards in design testing 100% testing acceptance review by pressional engineers 100% adherence the delivery schedules for both buses railcars Document Lessons Learned by project/contract Provide project management performance tal satisfaction the funding agencies WMATA requirements Report status Vehicle Programs (Bus & Rail) bi-annually Board 11

12 FY 2007 Proposed Budget Division Planning, Development, Engineering & Construction Office Construction responsible for the design, project management testing for a wide range New Starts projects which are part the Authority s System Access Program (SAP) System Expansion Program (SEP) the Metro Matters Yards Program. Complete active projects as planned working closely with the community ensuring all requirements the applicable jurisdiction are met: District Columbia (i.e., New York Avenue, MTPD Police Station) Maryl (i.e., Largo extension, New Carrolln Yard) Virginia (i.e., Dulles, Huntingn Parking Garage) Measures Benchmarks Continue update existing construction ols contracting practices Document Lessons Learned by project/contract Provide project management performance tal satisfaction the funding agencies WMATA requirements Ensure all projects are managed by credentialed engineers construction managers Closeout construction contracts within a year completion 12

13 FY 2007 Proposed Budget Division Planning, Development, Engineering & Construction Infrastructure Renewal Programs responsible for the design, project management, installation testing for bus rail infrastructure renewal projects as well as adjacent construction joint development. Concurrently manage over 60 active projects - critical FY07 projects include Traction Power Upgrade for 8-Car trains bus system integration FY07 projected work in place $130 million Detailed design underway for over 30 Metro Matters rehabilitation contracts Perform field inspections ensure contracr compliance with approved procedures Improve serviceability provide better cusmer access, safety comfort Manage all adjacent construction projects in accordance with WMATA jurisdictional requirements Measures Benchmarks Continue update existing construction ols contracting practices Document Lessons Learned by project/contract Provide project management performance tal satisfaction the funding agencies WMATA requirements Ensure all projects are managed by credentialed engineers construction managers Report status Capital Improvement Plan program Board bi-annually Closeout construction contracts within a year completion 13

14 FY 2007 Proposed Budget Division Planning, Development, Engineering & Construction Office Administration is responsible for administration, coordination reporting for environmental compliance, cost estimating, project controls, quality & safety assurance, staffing, for all projects programs for the Division. Project Controls Manages reports on funding activities by project Prepares monthly Project Controls Reports for each project/program Works closely with the Department Finance assure consistency with CFO directions Coordinates the development the Division s operating Capital annual budgets Compliance Provides the Authority s independent cost estimating for projects/programs contracts Monirs independent project schedules; reviews reports findings Monirs reports on environmental compliance planning requirements Develops project policies procedures assure full compliance with Authority requirements Conducts frequent quality safety audits assure compliance with Authority plans Human Resource Administrative Services Performs overall administrative support including statistical management analyses by fice/project Assists in the recruiting hiring staff for the various fices within PDEC Coordinates inter-division project project placements based on project needs in compliance with Authority s procedures Develops Division Reduction-In-Force Increase-In-Force plans based on affordability analysis Measures Benchmarks 100% FTA project management plan, regulary, safety, quality code(s) compliance for all projects 100% independent cost estimating schedule reviews for all projects 100% compliance with WMATA WDFA human resource policies procedures 14

15 FY 2007 Proposed Budget Division Planning, Development, Engineering & Construction Division Planning! Development! Engineering! Construction (PDEC) Conclusion: PDEC provides efficient successful stewardship public resources strict attention the guiding principles WMATA s strategic vision, including improving service quality capacity accommodate ridership growth, by managing a wide variety projects programs for WMATA its jurisdictions, while ensuring quality, cusmer safety, security. Through detailed short-term longterm planning its integration pressional services, PDEC has established a solid foundation guide its response future needs continues improve its husbing public resources provide projects better, faster, cheaper safer for the Washingn Metropolitan Area public. 15

16 FY2007 Proposed Budget Division Planning, Development, Engineering Construction Appendix Office Budgets for: Planning, Development, Engineering & Construction Deputy GM Planning & Information Technology Assistant GM -Business Planning Project Development -Information Technology Services -Information Technology Renewal Program Property Development Management Chief Engineer Facilities Chief Engineer Systems Chief Engineer Vehicles Office Construction Infrastructure Renewal Program Group Office Administration 16

17 FY2007 Proposed Budget Deputy GM Planning, Development, Engineering Construction Operating Expense: $ Millions Labor $0.5 $0.5 $0.0 Fringes Services Materials Other Total $0.6 $0.6 $ % s s Subsequent Subsequent print print the the Budget Budget Book, Book, one one position position was was moved moved another another fice fice in in the the Division Division Capital Expense $0.1 $0.1 $ % From FY2007 FY2006 Budgeted Positions Detail Subsequent publishing one position moved Chief Engineer-Systems. Current positions st at 5. 17

18 FY2007 Proposed Budget Assistant GM Planning Information Technology Operating Expense: $ Millions Labor $0.4 $0.4 $0.0 Fringes Services Materials Other Total $0.8 $0.8 $ % s s No No significant significant change change Capital Expense $0.2 $0.2 $ % From FY2007 FY2006 Budgeted Positions Detail 18

19 FY2007 Proposed Budget - Business Planning Project Development Office Operating Expense: $ Millions Labor $0.9 $0.9 $0.0 Fringes Services Materials Other Total $1.3 $1.3 $ % s s Removal Removal a a position position out out BPPD BPPD Minimal Minimal increase increase nonpersonnel nonpersonnel expenses expenses Capital Expense $0.7 $0.7 $ % From FY2007 FY2006 Budgeted Positions Detail Movement a position within the Division 19

20 FY2007 Proposed Budget - Information Technology Services Office Operating Expense: $ Millions Labor $7.4 $7.4 $0.0 Fringes Services Materials Other Total $14.5 $14.6 $ % s s No No significant significant changes changes Capital Expense $2.7 $2.7 $ % From FY2007 FY2006 Budgeted Positions Detail Movement positions within the Division 20

21 FY2007 Proposed Budget - Information Technology Renewal Program Operating Expense: $ Millions FY2006 FY2007 Labor $0.0 $0.0 $0.0 Fringes Materials Other Total $0.0 $0.0 $ % s s No No significant significant changes changes FY2006 FY2007 Capital Expense $2.4 $1.5 ($0.9) From FY2007 FY2006 Budgeted Positions Detail 21

22 FY2007 Proposed Budget Office Property Development Management Operating Expense: $ Millions FY2006 FY2007 Labor $1.6 $1.7 $0.1 Fringes Services Materials Other Total $2.3 $2.6 $ % FY2006 FY2007 Capital Expense $0.5 $0.5 $ % From FY2007 FY2006 Budgeted Positions s s Services Services increase increase due due number number new new joint joint development development projects projects in in negotiation negotiation Appraisals Appraisals completed completed in in prior prior years years are are outdated outdated require require current current market market value value analysis analysis Appraisals Appraisals bus bus garages garages increased increased the the requirement requirement for for thus thus the the cost cost Real Real Estate Estate consultants consultants Detail Services increased for real estate consultants. 22

23 FY2007 Proposed Budget - Chief Engineer - Facilities Operating Expense: $ Millions * Labor $2.3 $2.4 $0.1 Fringes Services Materials Other Total $4.5 $4.9 $ % FY2006 FY2007 Capital Expense $3.8 $4.2 $ % From FY2007 FY2006 Budgeted Positions Detail Movement positions other fices within the Division; some postions returned the Division Operations. s s Environmental Environmental compliance compliance Engineering Engineering technical technical services, services, support, support, evaluation evaluation Metrorail Metrorail Metrobus Metrobus operations operations Training Training staff staff development development Technical Technical resources resources equipment equipment maintain maintain current current codes codes stards stards 23

24 FY2007 Proposed Budget Chief Engineer - Systems Operating Expense: $ Millions Labor $1.3 $1.3 $0.0 Fringes Services Materials Other Total $1.7 $1.7 $ % Capital Expense $4.6 $4.9 $ % From FY2007 FY2006 Budgeted Positions Detail Movement positions within the Division. s s FTE s FTE s provide provide engineering engineering technical technical expertise expertise maintain maintain operate operate Metrorail Metrorail Metrobus Metrobus systems systems Provide Provide engineering engineering leadership leadership IRPG IRPG CONS CONS Training Training staff staff development development Technical Technical resources resources equipment equipment maintain maintain current current codes codes stards stards 24

25 FY2007 Proposed Budget Chief Engineer - Vehicles Operating Expense: $ Millions Labor $2.7 $2.8 $0.1 Fringes Services Materials Other Total $4.1 $4.8 $ % Capital Expense $2.7 $3.0 $ % s s Staffing Staffing reassignments reassignments improve improve the the effectiveness effectiveness program program delivery delivery operational operational reliability reliability Additional Additional consultant consultant services services required required for for engineering engineering support support reliability reliability improvements improvements FY2007 FY2006 Budgeted Positions Detail Position change attributed receipt 2 positions from CFO & movement within the Division. Services increased due need for Booz-Allen support. 25

26 FY2007 Proposed Budget Office Construction Operating Expense: $ Millions Labor $0.1 $0.1 $0.0 Fringes Services Materials Other Total $0.1 $0.1 $ % s s Advancement Advancement Dulles Dulles Metro Metro rail rail project project Continuation Continuation Parking Parking Expansion Expansion Program Program Capital Expense $13.4 $14.7 $ % From FY2007 FY2006 Budgeted Positions Detail Movement positions within the Division 26

27 FY2007 Proposed Budget Infrastructure Renewal Programs Group Operating Expense: $ Millions Labor $1.6 $1.6 $0.0 Fringes Services Materials Other Total $2.6 $2.6 $ % Capital Expense $7.3 $7.5 $ % s s Over Over 80% 80% the the cost cost is is labor labor Time Time required required review review coordinate coordinate submittals submittals is is the the main main cost cost Over Over active active projects projects at at any any point point in in year year Budgeted Positions Detail One position transferred Workforce Development Administration one position moved another fice in the Division. There were postion changes subsequent issuance the Budget Book. 27

28 FY2007 Proposed Budget Office Administration Operating Expense: $ Millions Labor $0.4 $0.4 $0.0 Fringes Services Materials Other Total $0.5 $0.5 $ % s s No No significant significant changes changes Capital Expense $2.4 $2.6 $ % From FY2007 FY2006 Budgeted Positions Detail N/A 28

WASHINGTON METROPOLITAN AREA TRANSIT AUTHORITY TRANSPORTATION IMPROVEMENT PROGRAM CAPITAL COSTS (in $1,000)

WASHINGTON METROPOLITAN AREA TRANSIT AUTHORITY TRANSPORTATION IMPROVEMENT PROGRAM CAPITAL COSTS (in $1,000) TIP ID: 5853 Agency ID: Title: Rail Cars - Replacement, Rehabilitation, Expansion, & Enhancements Local 0/0/100 11,629 e 5,380 e 5,600 e 10,980 PRIIA 50/0/50 265,887 e 154,860 e 246,189 e 158,438 e 141,875

More information

FY2018 Third Quarter Financial Update

FY2018 Third Quarter Financial Update Finance and Committee Information Item IV-A May 10, 2018 Third Quarter Financial Update Page 30 of 53 Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information

More information

FY2020 Budget Outlook

FY2020 Budget Outlook Finance and Capital Committee Information Item IV-A October 11, 2018 FY2020 Budget Outlook 35 of 60 Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information MEAD

More information

FY2017 Budget Discussion

FY2017 Budget Discussion Finance & Administration Committee Information Item IV-B November 5, 2015 FY2017 Budget Discussion Page 70 of 116 Washington Metropolitan Area Transit Authority Board Action/Information Summary Action

More information

Getting Metro Back on Track

Getting Metro Back on Track NVTC Presents: Getting Metro Back on Track A discussion with Virginia members of the WMATA Board This forum is sponsored by the Northern Virginia Transportation Commission. It is separate and distinct

More information

FY2017 Year-End Financial Update

FY2017 Year-End Financial Update Finance Committee Information Item III-A September 14, 2017 FY2017 Year-End Financial Update Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information MEAD Number:

More information

CHAPTER 7: Financial Plan

CHAPTER 7: Financial Plan CHAPTER 7: Financial Plan Report Prepared by: Contents 7 FINANCIAL PLAN... 7-1 7.1 Introduction... 7-1 7.2 Assumptions... 7-1 7.2.1 Operating Revenue Assumptions... 7-2 7.2.2 Operating Cost Assumptions...

More information

Report by Finance and Administration Committee (B) Washington Metropolitan Area Transit Authority Board Action/Information Summary

Report by Finance and Administration Committee (B) Washington Metropolitan Area Transit Authority Board Action/Information Summary Report by Finance and Administration Committee (B) 01-28-2016 Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information MEAD Number: 201701 Resolution: Yes No TITLE:

More information

TESTIMONY OF RICHARD SARLES

TESTIMONY OF RICHARD SARLES TESTIMONY OF RICHARD SARLES Before the Council of the District of Columbia Committee on Economic Development on WMATA s FY2015 Budget Wednesday, April 30, 2014 Good Morning, Chairperson Bowser and other

More information

FY2017 Budget Guidance

FY2017 Budget Guidance Finance & Administration Committee Information Item IV-D September 10, 2015 FY2017 Budget Guidance Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information MEAD

More information

Notice of Public Hearing Washington Metropolitan Area Transit Authority

Notice of Public Hearing Washington Metropolitan Area Transit Authority Notice of Public Hearing Washington Metropolitan Area Transit Authority Docket B18-01: Proposed FY2019 Operating Budget and Docket B18-02: Proposed FY2019 Capital Improvement Program and Federal FY2018

More information

FY2011 Budget Forum. District of Columbia. October 19, 2009

FY2011 Budget Forum. District of Columbia. October 19, 2009 FY2011 Budget Forum District of Columbia October 19, 2009 0 Meeting agenda What is Metro and what is the value of Metro service? What are the Fiscal Year 2011 budget challenges? What are the potential

More information

Getting Metro Back on Track

Getting Metro Back on Track NVTC Presents: Getting Metro Back on Track A discussion with Virginia members of the WMATA Board @NovaTransit This forum is sponsored by the Northern Virginia Transportation Commission. Learn more about

More information

Capital & Strategic Planning Committee. Item III - A. January 25, FY2019 Capital Budget Work Session

Capital & Strategic Planning Committee. Item III - A. January 25, FY2019 Capital Budget Work Session Capital & Strategic Planning Committee Item III - A January 25, 2018 FY2019 Capital Budget Work Session Page 4 of 29 Washington Metropolitan Area Transit Authority Board Action/Information Summary Action

More information

Washington Metropolitan Area Transit Authority Metro Budget Overview

Washington Metropolitan Area Transit Authority Metro Budget Overview Washington Metropolitan Area Transit Authority Metro Budget Overview February 2011 Metro 10,877 Employees (10,974 budgeted) 1,491 Buses 588 Escalators and 237 Elevators 106 Miles of Track 92 Traction Power

More information

SUBJECT: APPROVAL OF FISCAL CAPITAL IMPROVEMENT PROGRAM

SUBJECT: APPROVAL OF FISCAL CAPITAL IMPROVEMENT PROGRAM PRESENTED AND ADOPTED: SUBJECT: APPROVAL OF FISCAL 2007 2012 CAPITAL IMPROVEMENT PROGRAM RESOLUTION OF THE BOARD OF DIRECTORS OF THE WASHINGTON METROPOLITAN AREA TRANSPORTATION AUTHORITY WHEREAS, The Board

More information

Finance & Administration Committee Information Item IV-A October 9, 2014 Momentum Update

Finance & Administration Committee Information Item IV-A October 9, 2014 Momentum Update Finance & Administration Committee Information Item IV-A October 9, 2014 Momentum Update Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information MEAD Number:

More information

Keeping Metro Safe, Reliable and Affordable

Keeping Metro Safe, Reliable and Affordable Finance Committee Information Item III-B September 14, 2017 Keeping Metro Safe, Reliable and Affordable Washington Metropolitan Area Transit Authority Keeping Metro Safe, Reliable and Affordable 1 Purpose

More information

Washington Metropolitan Area Transit Authority

Washington Metropolitan Area Transit Authority Washington Metropolitan Area Transit Authority Financial Report issued in Accordance with Government Auditing Standards For the Years Ended June 30, 2016 and 2015 Single Audit Reports issued in Accordance

More information

FY2014 Capital and Operating Budget Discussion

FY2014 Capital and Operating Budget Discussion Finance & Administration Committee Information Item III-B December 6, 2012 FY2014 Capital and Operating Budget Discussion Page 18 of 44 Washington Metropolitan Area Transit Authority Board Action/Information

More information

Arlington County, Virginia

Arlington County, Virginia Arlington County, Virginia METRO METRO 2015 2024 CIP Metro Funding Project Description The Washington Metropolitan Area Transit Authority (WMATA/Metro) is a unique federal-state-local partnership formed

More information

Jul Aug Sept Oct Nov Dec Jan Feb Mar Apr May Jun

Jul Aug Sept Oct Nov Dec Jan Feb Mar Apr May Jun REVENUE AND RIDERSHIP 4th Quarter FY2014 REVENUE (in Millions) $90M $85M $80M $75M $70M $65M $60M $55M $50M 79 77 74 74 72 70 FY2013 Actual FY2014 Budget FY2014 Actual 79 85 78 78 77 67 66 70 59 67 65

More information

Washington Metropolitan Area Transit Authority

Washington Metropolitan Area Transit Authority Washington Metropolitan Area Transit Authority Financial Report For the Fiscal Years Ended June 30, 2017 and 2016 Table of Contents Washington Metropolitan Area Transit Authority Financial Report For the

More information

DULLES CORRIDOR COMMITTEE

DULLES CORRIDOR COMMITTEE M E T R O P O L I T A N W A S H I N G T O N A I R P O R T S A U T H O R I T Y DULLES CORRIDOR COMMITTEE Approval Of Phase 2 Cooperative Agreements With The Airports Authority And The Washington Metropolitan

More information

Potomac Yard Metrorail Station TIIF Allocation

Potomac Yard Metrorail Station TIIF Allocation Planning, Development and Real Estate Committee Board Action Item III-B February 26, 2009 Potomac Yard Metrorail Station TIIF Allocation Washington Metropolitan Area Transit Authority Board Action/Information

More information

FISCAL YEAR 2009 ACTUAL AND MID-YEAR 2010 SPENDING

FISCAL YEAR 2009 ACTUAL AND MID-YEAR 2010 SPENDING FISCAL YEAR 2009 ACTUAL AND MID-YEAR 2010 SPENDING Testimony of John B. Catoe, Jr. General Manager Washington Metropolitan Area Transit Authority Before the Council of the District of Columbia s Committee

More information

FY2018 Second Quarter Financial Update

FY2018 Second Quarter Financial Update Finance and Committee Information Item III-A February 8, 2018 Second Quarter Financial Update 4 of 52 Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information

More information

METRO. Metro Funding. Associated Master Plan: Comprehensive Master Transportation Plan (MTP) for Arlington. Neighborhood(s):

METRO. Metro Funding. Associated Master Plan: Comprehensive Master Transportation Plan (MTP) for Arlington. Neighborhood(s): METRO METRO METRO 2017 2026 CIP Metro Funding Project Description The Washington Metropolitan Area Transit Authority (WMATA/Metro) is a unique federal-state-local partnership formed to provide mass transit

More information

MEMORANDUM. Santa Clara Valley Transportation Authority Board of Directors. Michael T. Burns General Manager. DATE: August 4, 2008

MEMORANDUM. Santa Clara Valley Transportation Authority Board of Directors. Michael T. Burns General Manager. DATE: August 4, 2008 MEMORANDUM TO: FROM: Santa Clara Valley Transportation Authority Board of Directors Michael T. Burns General Manager DATE: August 4, 2008 SUBJECT: BART Operating Subsidy This memorandum summarizes and

More information

FY2013 Preliminary Operating Budget

FY2013 Preliminary Operating Budget Finance & Administration Committee Information Item IV-D December 1, 2011 FY2013 Preliminary Operating Budget Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information

More information

FY06 Operating Budget. FY2006 Proposed Operating Budget. Final Summary for Board Referral

FY06 Operating Budget. FY2006 Proposed Operating Budget. Final Summary for Board Referral FY2006 Proposed Operating Budget Final Summary for Board Referral 1 Operating Statements Subsidy nearly $10M lower than December proposal Dec Base Other Subtot Mar Prop$ Adj Adj Changes Prop$ Revenues

More information

PROPOSED FISCAL YEAR 2011 BUDGET. Testimony of. Richard Sarles, General Manager. Washington Metropolitan Area Transit Authority.

PROPOSED FISCAL YEAR 2011 BUDGET. Testimony of. Richard Sarles, General Manager. Washington Metropolitan Area Transit Authority. PROPOSED FISCAL YEAR 2011 BUDGET Testimony of Richard Sarles, General Manager Washington Metropolitan Area Transit Authority Before the Council of the District of Columbia Committee on Public Works and

More information

Vision The Best Ride in the Nation

Vision The Best Ride in the Nation Washington Metropolitan Area Transit Authority FY 2008 Comprehensive Annual Financial Report Vision The Best Ride in the Nation Mission Provide the nation s best transit service to our customers and improve

More information

TESTIMONY OF RICHARD SARLES. Before the Council of the District of Columbia s Committee on Economic Development. April 22, 2013

TESTIMONY OF RICHARD SARLES. Before the Council of the District of Columbia s Committee on Economic Development. April 22, 2013 TESTIMONY OF RICHARD SARLES Before the Council of the District of Columbia s Committee on Economic Development April 22, 2013 Good Morning, Chairperson Bowser and other members of the Committee on Economic

More information

PUBLIC HEARING ON WASHINGTON METROPOLITAN AREA TRANSIT AUTHORITY FISCAL YEAR 2008 BUDGET

PUBLIC HEARING ON WASHINGTON METROPOLITAN AREA TRANSIT AUTHORITY FISCAL YEAR 2008 BUDGET PUBLIC HEARING ON WASHINGTON METROPOLITAN AREA TRANSIT AUTHORITY FISCAL YEAR 2008 BUDGET Before the Committee on Public Works and the Environment Council of the District of Columbia The Honorable Jim Graham,

More information

REAL ESTATE COMMITTEE APPROVE THE USE OF FAIRFAX COUNTY S TIIF FUNDS FOR THE HUNTINGTON GARAGE

REAL ESTATE COMMITTEE APPROVE THE USE OF FAIRFAX COUNTY S TIIF FUNDS FOR THE HUNTINGTON GARAGE REAL ESTATE COMMITTEE APPROVE THE USE OF FAIRFAX COUNTY S TIIF FUNDS FOR THE HUNTINGTON GARAGE 9 REAL ESTATE COMMITTEE PURPOSE: To Request Real Estate Committee, Budget Committee, and Board Approval to

More information

Providers of Public Transportation Individual Targets

Providers of Public Transportation Individual Targets APPENDIX Providers of Public Transportation Individual Targets The following letters, presentation slides, and other data were provided by the individual reporting entities, and are posted on the MWCOG

More information

Amend FY07 System Access Program for Artwork

Amend FY07 System Access Program for Artwork Item: 10 Amend FY07 System Access Program for Artwork 55 of 75 Board Budget Committee July 6, 2006 EXECUTIVE SUMMARY Budget Committee Meeting July 6, 2006 Request for Board approval to amend the fiscal

More information

Metro s Path Forward. A comprehensive approach toward reform. July 26, 2017

Metro s Path Forward. A comprehensive approach toward reform. July 26, 2017 Metro s Path Forward A comprehensive approach toward reform July 26, 2017 Metro Reform: Executive Summary Metro is not living up to the promise of public transit: to be a safe, affordable and reliable

More information

Amend FY 2006 Infrastructure Renewal Program

Amend FY 2006 Infrastructure Renewal Program Washington Metropolitan Area Transit Authority Amend FY 2006 Infrastructure Renewal Program Budget Committee December 8, 2005 Purpose That the Budget Committee approve and forward to the Board for approval

More information

FY2017 Budget Work Session

FY2017 Budget Work Session Finance & Administration Committee Information Item IV-B January 14, 2016 FY2017 Budget Work Session Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information MEAD

More information

VALLEY METRO RAIL FY18 Budget EXECUTIVE SUMMARY

VALLEY METRO RAIL FY18 Budget EXECUTIVE SUMMARY VALLEY METRO RAIL FY18 Budget EXECUTIVE SUMMARY FY18 ADOPTED ANNUAL OPERATING AND CAPITAL BUDGET Valley Metro Rail, Inc. (VMR) is a public non-profit corporation whose members are the cities of Chandler,

More information

OPERATING BUDGET REPORT

OPERATING BUDGET REPORT OPERATING BUDGET REPORT OPERATING BUDGET ($ in Millions) MTD Nov-FY2012 Nov-FY2013 Actual Actual Budget $ Percent Revenue $ 63.0 $ 65.7 $ 68.3 $ (2.7) -3.9% Expense $ 107.6 $ 124.8 $ 129.8 $ 5.0 3.8% Subsidy

More information

Contents. Appendix. Cost Model Structure. Tables

Contents. Appendix. Cost Model Structure. Tables Alternatives Analysis Alt ti A l i Technical Methodology Report: Operating and Cost Estimating and Results Prepared for: Washington County Regional Railroad Authority on behalf of the Gateway Corridor

More information

Report by Finance and Administration Committee (A) Washington Metropolitan Area Transit Authority Board Action/Information Summary

Report by Finance and Administration Committee (A) Washington Metropolitan Area Transit Authority Board Action/Information Summary Report by Finance and Administration Committee (A) 07-23-2015 Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information MEAD Number: 201642 Resolution: Yes No TITLE:

More information

Washington Metropolitan Area Transportation Authority Board Action/Information Summary. MEAD Number: 99808

Washington Metropolitan Area Transportation Authority Board Action/Information Summary. MEAD Number: 99808 Washington Metropolitan Area Transportation Authority Board Action/Information Summary Action Information MEAD Number: 99808 Resolution: Yes No PURPOSE To obtain Board approval to modify the MetroAccess

More information

BOARD OF SUPERVISORS FINANCE/GOVERNMENT OPERATIONS AND ECONOMIC DEVELOPMENT COMMITTEE INFORMATION ITEM

BOARD OF SUPERVISORS FINANCE/GOVERNMENT OPERATIONS AND ECONOMIC DEVELOPMENT COMMITTEE INFORMATION ITEM Date of Meeting: February 14, 2017 BOARD OF SUPERVISORS FINANCE/GOVERNMENT OPERATIONS AND ECONOMIC DEVELOPMENT COMMITTEE INFORMATION ITEM # 12 SUBJECT: Metrorail Financial Obligations ELECTION DISTRICT:

More information

The 2017 Audit Work Plan provides City Council with an overview of how the resources allocated to the Auditor General s Office will be used in 2017.

The 2017 Audit Work Plan provides City Council with an overview of how the resources allocated to the Auditor General s Office will be used in 2017. AUDITOR GENERAL S REPORT ACTION REQUIRED 2017 Audit Work Plan Date: October 13, 2016 To: From: Wards: Audit Committee Auditor General All Reference Number: SUMMARY The purpose of this report is to provide

More information

FINANCE AND PROCUREMENT

FINANCE AND PROCUREMENT Budget Book Page Number -32 FINANCE AND PROCUREMENT The Department of supports County Departments and Constitutional Officers in the provision of services to the residents and businesses of Loudoun County.

More information

Review of WMATA FY 2006 Operating Budget. Jurisdictional Coordination Committee Thursday, May 12, 2005

Review of WMATA FY 2006 Operating Budget. Jurisdictional Coordination Committee Thursday, May 12, 2005 Review of WMATA FY 2006 Operating Budget Jurisdictional Coordination Committee Thursday, May 12, 2005 2 Executive Summary Goals and Objectives: JCC FY 06 Budget Review Process Goal of JCC Review Process

More information

Board Guidance and Notes to Accompany FY 2018 Adopted Budget

Board Guidance and Notes to Accompany FY 2018 Adopted Budget Board Guidance and Notes to Accompany FY 2018 Adopted Budget 1. Real Estate Tax Rate: The total real estate tax rate increased 1 ½ cents from $0.978 to $0.993 (base rate excluding the sanitary district

More information

BOARD OF DIRECTORS MEETING

BOARD OF DIRECTORS MEETING Revised 12/10/14 See Item No. 11 SOUTHERN CALIFORNIA REGIONAL RAIL AUTHORITY BOARD OF DIRECTORS MEETING FRIDAY, DECEMBER 12, 2014 10:00a.m. LOS ANGELES COUNTY METROPOLITAN TRANSPORTATION AUTHORITY (METRO)

More information

RAC Capital Presentatition May 5, 2010

RAC Capital Presentatition May 5, 2010 RAC Capital Presentation ti May 5, 2010 Flexible Six-Year Agreement Flexible Six-Year Agreement minimum funding commitment to match Federal funds, and to annually assess availability of additional funds

More information

Next Capital Funding Agreement

Next Capital Funding Agreement Finance & Administration Committee Action Item II-A April 22, 2010 Next Capital Funding Agreement The Next Capital Funding Agreement and the 2011-2016 Capital Program Finance and Administration Committee

More information

Operating Budget Report

Operating Budget Report Operating Budget Report Operating Budget ($ in Millions) Operating Expenditures ($ in Millions) MTD May-FY2011 May - FY2012 Variance FY12 Actual Actual Budget $ Percent $140M Revenue $ 68,140 $ 70,480

More information

AUDITOR GENERAL S REPORT ACTION REQUIRED Audit Work Plan SUMMARY RECOMMENDATION. Date: October 10, Audit Committee. To: Auditor General

AUDITOR GENERAL S REPORT ACTION REQUIRED Audit Work Plan SUMMARY RECOMMENDATION. Date: October 10, Audit Committee. To: Auditor General AUDITOR GENERAL S REPORT ACTION REQUIRED 2013 Audit Work Plan Date: October 10, 2012 To: From: Wards: Audit Committee Auditor General All Reference Number: SUMMARY The purpose of this report is to provide

More information

QUALITY MANAGEMENT SYSTEM PLAN (QMSP)

QUALITY MANAGEMENT SYSTEM PLAN (QMSP) QUALITY MANAGEMENT SYSTEM PLAN (QMSP) Washington Metropolitan Area Transit Authority (WMATA) August 2018 Quality Assurance, Internal Compliance & Oversight (QICO) Promoting Transparency, Accountability,

More information

GM/CEO s Proposed FY2020 Budget

GM/CEO s Proposed FY2020 Budget Finance and Capital Committee Information Item IV-A November 1, 2018 GM/CEO s Proposed FY2020 Budget Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information MEAD

More information

Operating Budget Report

Operating Budget Report Operating Budget Report MTD Operating Budget ($ in Millions) Oct-FY2012 Oct-FY2013 Variance FY13 Actual Actual Budget $ Percent $140M Operating Expenditures ($ in Millions) Revenue $ 67 $ 70 $ 79 $ (8)

More information

Proposed Budget Fiscal Year 2010 July 1, 2009 June 30, 2010

Proposed Budget Fiscal Year 2010 July 1, 2009 June 30, 2010 Proposed Budget Fiscal Year 2010 July 1, 2009 June 30, 2010 Presented to the Board of Directors: Finance, Administration, and Oversight Committee January 8, 2009 1 General Manager s Overview And Summary

More information

VALLEY METRO RPTA FY18 Budget EXECUTIVE SUMMARY

VALLEY METRO RPTA FY18 Budget EXECUTIVE SUMMARY VALLEY METRO RPTA FY18 Budget EXECUTIVE SUMMARY FY18 ADOPTED ANNUAL OPERATING AND CAPITAL BUDGET Valley Metro Regional Public Transportation Authority (RPTA) provides public transportation services for

More information

2007 Legislative Program Northern Virginia Transportation Authority Approved: November 10, 2006

2007 Legislative Program Northern Virginia Transportation Authority Approved: November 10, 2006 State Legislative Items: Additional Transportation Funding 2007 Legislative Program Northern Virginia Transportation Authority Approved: November 10, 2006 Position: The Northern Virginia Transportation

More information

This chapter describes the initial financial analysis and planning for the construction and operations of the Locally Preferred Alternative (LPA).

This chapter describes the initial financial analysis and planning for the construction and operations of the Locally Preferred Alternative (LPA). 8 FINANCIAL ANALYSIS This chapter describes the initial financial analysis and planning for the construction and operations of the Locally Preferred Alternative (LPA). The alternative formerly known as

More information

Chairman Skinner and the VRE Operations Board. Authorization to Issue a Request for Proposals for Federal Legislative Services

Chairman Skinner and the VRE Operations Board. Authorization to Issue a Request for Proposals for Federal Legislative Services Agenda Item 8-A Consent Item To: From: Chairman Skinner and the VRE Operations Board Doug Allen Date: February 19, 2016 Re: Authorization to Issue a Request for Proposals for Federal Legislative Services

More information

SUBJECT: Capital Program and 10-Year Capital Forecast

SUBJECT: Capital Program and 10-Year Capital Forecast MEETING DATE: October 23, 2002 SUBJECT: 2003-2007 Capital Program and 10-Year Capital Forecast RECOMMENDATION It is recommended that the Commission: 1. Approve the 2003-2007 Capital Program in the amount

More information

METRO. Monthly Board Report. June 2006

METRO. Monthly Board Report. June 2006 METRO Monthly Board Report Operating Capital Service Performance June 26 7/17/26 June 26 MONTHLY BOARD REPORT INDEX Section A Section B Section C Section D Section E Section F Section G Operating Budget

More information

BOARD OF SUPERVISORS TRANSPORTATION/LAND USE COMMITTEE INFORMATION ITEM. Dulles Corridor Metrorail Phase 2 Update

BOARD OF SUPERVISORS TRANSPORTATION/LAND USE COMMITTEE INFORMATION ITEM. Dulles Corridor Metrorail Phase 2 Update BOARD OF SUPERVISORS TRANSPORTATION/LAND USE COMMITTEE INFORMATION ITEM Date of Meeting: March 11, 2016 # 4 SUBJECT: Dulles Corridor Metrorail Phase 2 Update ELECTION DISTRICT: Countywide STAFF CONTACTS:

More information

EXECUTIVE DIVISION MISSION STATEMENT STRATEGIC PLAN CHANGE INITIATIVES & SCORECARD MEASURES

EXECUTIVE DIVISION MISSION STATEMENT STRATEGIC PLAN CHANGE INITIATIVES & SCORECARD MEASURES EXECUTIVE DIVISION MISSION STATEMENT The Mission of the Executive Division is to plan, execute, and manage the efficient, effective, safe, and courteous delivery of quality public transportation services

More information

Operating Budget Report

Operating Budget Report Operating Report Operating ($ in Millions) Operating Expenditures ($ in Millions) Jun-11 Jun-12 $ Percent Revenue $ 212,640 $ 217,643 $ 214,671 $ 2,973 1% Expense $ 359,102 $ 361,882 $ 366,332 $ 4,450

More information

SERVICE DELIVERY & GOVERNMENTAL TRANSPARENCY Infrastructure & Operational Enhancements

SERVICE DELIVERY & GOVERNMENTAL TRANSPARENCY Infrastructure & Operational Enhancements SERVICE DELIVERY & GOVERNMENTAL TRANSPARENCY Infrastructure & Operational Enhancements To improve service delivery, the Proposed Budget continues a focus on improvements in: Core infrastructure Vital services

More information

METRO. Fiscal Year 2014 Monthly Board Report. May 2014

METRO. Fiscal Year 2014 Monthly Board Report. May 2014 METRO Fiscal Year 2014 Monthly Board Report Revenue Expense Ridership Performance 7/11/2014 Table of Contents Section A Section B Section C Section D Section E Section F Section G Section H Section I Section

More information

Transit Subsidy. Mission Statement. Mandates

Transit Subsidy. Mission Statement. Mandates Mission Statement The Potomac and Rappahannock Transportation Commission (PRTC) is a multi-jurisdictional agency representing Prince William, Stafford, and Spotsylvania Counties and the Cities of Manassas,

More information

8. FINANCIAL ANALYSIS

8. FINANCIAL ANALYSIS 8. FINANCIAL ANALYSIS This chapter presents the financial analysis conducted for the Locally Preferred Alternative (LPA) selected by the Metropolitan Transit Authority of Harris County (METRO) for the.

More information

Approval of FY2013 Budget

Approval of FY2013 Budget Finance & Administration Committee Action Item III-A May 10, 2012 Approval of FY2013 Budget Page 3 of 126 Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information

More information

Metro 2025 Alternative Funding and Financing

Metro 2025 Alternative Funding and Financing Finance & Administration Committee Information Item IV-A June 12, 2014 Metro 2025 Alternative Funding and Financing 37 of 100 Washington Metropolitan Area Transit Authority Board Action/Information Summary

More information

Quarterly Financial Report FY2015 Q3 January March 2015

Quarterly Financial Report FY2015 Q3 January March 2015 Washington Metropolitan Area Transit Authority Fiscal Year 2015 Financials Quarterly Financial Report FY2015 Q3 January March 2015 Page 1 of 54 WASHINGTON METROPOLITAN AREA TRANSIT AUTHORITY QUARTERLY

More information

Program: Facilities and Construction Management. Program Based Budget Page 117

Program: Facilities and Construction Management. Program Based Budget Page 117 Program: Facilities and Construction Management Program Based Budget 2014-2016 Page 117 Program: Facilities and Construction Management Vision: To develop and maintain town buildings that is safe, comfortable

More information

RECOMMENDATION PAPER FOR THE DULLES CORRDOR COMMITTEE

RECOMMENDATION PAPER FOR THE DULLES CORRDOR COMMITTEE Dulles Rail RECOMMENDATION PAPER FOR THE DULLES CORRDOR COMMITTEE RECOMMENDATION TO APPROVE MEMORADUM OF AGREEMENT FOR PHASE 2 OF THE DULLES CORRDOR METRORAIL PROJECT, AND AGREEMENT CONCERNING PROJECT

More information

Safety and Operations Committee. Information Item III-B. January 24, 2019

Safety and Operations Committee. Information Item III-B. January 24, 2019 Safety and Operations Committee Information Item III-B January 24, 2019 Overnight Maintenance Window and Work Hours Page 54 of 75 Washington Metropolitan Area Transit Authority Board Action/Information

More information

MUTUAL HOUSING MANAGEMENT

MUTUAL HOUSING MANAGEMENT J O B D E S C R I P T I O N Job Title: Location: Department: Reports To: FSLA Status: Director of Property Management Sacramento Property Management Chief Executive Officer Exempt (professional) Updated:

More information

Report by Finance and Administration Committee (B) Washington Metropolitan Area Transit Authority Board Action/Information Summary

Report by Finance and Administration Committee (B) Washington Metropolitan Area Transit Authority Board Action/Information Summary Report by Finance and Administration Committee (B) 06-25-2015 Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information MEAD Number: 201605 Resolution: Yes No TITLE:

More information

METRO. Fiscal Year 2013 Monthly Board Report. January 2013

METRO. Fiscal Year 2013 Monthly Board Report. January 2013 METRO Fiscal Year 2013 Monthly Board Report Revenue Expense Ridership Performance 2/14/2013 Table of Contents Section A Section B Section C Section D Section E Section F Section G Section H Section I Section

More information

Real Property Branch Asset Management Name Branch

Real Property Branch Asset Management Name Branch Real Property Branch Asset Management Name Branch Department: Business Transformation Services Executive Director: Stephen Finnamore Department: Deputy City Manager: Branch: Real Property Asset Management

More information

METRO MONTHLY BOARD REPORT

METRO MONTHLY BOARD REPORT METRO Revenue Expenses Service Performance Fiscal Year FY2011 Table of Contents Section A Section B Section C Section D Section E Section F Section G Section H Summary Sales Tax Revenue Fare Revenue Operating

More information

FY 2016 Proposed Budget Work Session

FY 2016 Proposed Budget Work Session Department of Environmental Services FY 2016 Proposed Budget Work Session Tuesday, March 24, 2:30 5:00 Agenda Tuesday, March 24, 2015 2:30 5:00 PM Related FAAC Report: DES Department / Topic Book pgs Web

More information

Operating Budget Report

Operating Budget Report Operating Budget Report MTD Operating Budget ($ in Millions) Sept-FY2012 Sept-FY2013 Variance FY13 Actual Actual Budget $ Percent $140M Operating Expenditures ($ in Millions) Revenue $ 67 $ 68 $ 71 $ (3)

More information

Operating Budget. Second Quarter Financial Report

Operating Budget. Second Quarter Financial Report Second Quarter Financial Report INDEX A. Executive Summary... A-1 B. Revenue and Expense Analysis... B-1 C. Budget Variance Reports... C-1 D. Ridership and Performance Measures... D-1 Board Budget Committee

More information

Total Operating Activities for FY17 are $56.9 million, an increase of $5.1M or 9.8% from FY16.

Total Operating Activities for FY17 are $56.9 million, an increase of $5.1M or 9.8% from FY16. FY17 ADOPTED ANNUAL OPERATING AND CAPITAL BUDGET Valley Metro Rail, Inc. (VMR) is a public non-profit corporation whose members are the cities of Chandler, Glendale, Mesa, Phoenix, and Tempe. VMR plans,

More information

FY2014 Operating Budget Performance Report

FY2014 Operating Budget Performance Report Finance & Administration Committee Information Item IV-C September 11, 2014 FY2014 Operating Budget Performance Report Washington Metropolitan Area Transit Authority Board Action/Information Summary Action

More information

Approval of FY2017 Capital Budget and FY Capital Improvement Program

Approval of FY2017 Capital Budget and FY Capital Improvement Program Finance Committee Action Item III-B April 14, 2016 Approval of FY2017 Capital Budget and FY2017-2022 Capital Improvement Program Page 23 of 68 Washington Metropolitan Area Transit Authority Board Action/Information

More information

Case 1:14-cv RJL Document 98-3 Filed 08/23/16 Page 1 of 15. Exhibit 2

Case 1:14-cv RJL Document 98-3 Filed 08/23/16 Page 1 of 15. Exhibit 2 Case 1:14-cv-01471-RJL Document 98-3 Filed 08/23/16 Page 1 of 15 Exhibit 2 Case 1:14-cv-01471-RJL Document 98-3 Filed 08/23/16 Page 2 of 15 DECLARATION OF CHARLES LATTUCA My name is Charles Lattuca, and

More information

Public Hearing on Peak Fares for Peak Service

Public Hearing on Peak Fares for Peak Service Finance and Capital Committee Action Item II-B September 13, 2018 Public Hearing on Peak Fares for Peak Service Page 287 of 463 Washington Metropolitan Area Transit Authority Board Action/Information Summary

More information

Financial Update for the Period Ended June 2, 2018

Financial Update for the Period Ended June 2, 2018 For Action Financial Update for the Period Ended June 2, 2018 Date: July 10, 2018 To: TTC Board From: Chief Financial Officer Summary The purpose of this report is to provide the Board with the operating

More information

METRO. Fiscal Year Monthly Performance Report. Revenue Expense Ridership Performance. November 2018 (Third Quarter Fiscal Year-to Date)

METRO. Fiscal Year Monthly Performance Report. Revenue Expense Ridership Performance. November 2018 (Third Quarter Fiscal Year-to Date) METRO Fiscal Year 2019 Monthly Performance Report Revenue Expense Ridership Performance (Third Quarter Fiscal Year-to Date) 12/12/2018 Table of Contents Section A Section B Section C Section D Section

More information

Approval of Reimbursable Project for Purchase of Buses for DC Circulator

Approval of Reimbursable Project for Purchase of Buses for DC Circulator Finance & Administration Committee Action Item III-A March 13, 2014 Approval of Reimbursable Project for Purchase of Buses for DC Circulator Page 3 of 14 Washington Metropolitan Area Transit Authority

More information

INTERDEPARTMENTAL SERVICES

INTERDEPARTMENTAL SERVICES INTERDEPARTMENTAL SERVICES Office of the City Engineer... 160 Mail and Printing Services... 163 Property and Facilities Management (PFM)... 164 Information Systems... 169 Interdepartmental Services Non-Departmental...

More information

RTD Board Briefing. Eagle P3 Project Draft RFP. January 6, 2009

RTD Board Briefing. Eagle P3 Project Draft RFP. January 6, 2009 RTD Board Briefing Eagle P3 Project Draft RFP January 6, 2009 Eagle P3 Draft RFP Background Outline of Draft RFP Major Deal Points Payment Structure Page 2 Page 3 Background Eagle P3 Project Eagle P3 Project

More information

Operating Budget. Third Quarter Financial Report (July 2005 March 2006)

Operating Budget. Third Quarter Financial Report (July 2005 March 2006) Third Quarter Financial Report (July 2005 March 2006) INDEX A. Executive Summary...page 2 B. Revenue and Expense Analysis...page 3 C. Budget Variance Reports...page 14 D. Ridership and Performance Measures...page

More information

Transit Subsidy. Mission Statement. Mandates

Transit Subsidy. Mission Statement. Mandates Mission Statement The Potomac and Rappahannock Transportation Commission (PRTC) is a multi-jurisdictional agency representing Prince William, Stafford, and Spotsylvania Counties and the Cities of Manassas,

More information

Quarterly Capital Progress Update

Quarterly Capital Progress Update Finance & Administration Committee Information Item IV-A September 13, 2012 Quarterly Capital Progress Update Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information

More information