April 24, Subject: Amendments to the FY Transportation Improvement Program

Size: px
Start display at page:

Download "April 24, Subject: Amendments to the FY Transportation Improvement Program"

Transcription

1 CAMPO Capital Area Metropolitan Planning Organization April 24, 2006 Mr. Robert Daigh District Engineer Texas Department of Transportation - Austin District PO Drawer Austin, TX Subject: Amendments to the FY Transportation Improvement Program Dear Mr. Daigh, On April 10, 2006 the CAMPO Board approved the requested amendments (see attached list of amendments and financial plan) to the FY Transportation Improvement Program. We asked that the State Transportation Improvement Program be updated with the approved amendments. Please call me at or Michael Dutton at if you have any questions. Sincerely, Michael R. Aulick Executive Director Cc: Ed Collins, TxDOT - Austin District 505 Barton Springs Road Suite 700 Austin Texas P.O. Box 1088 Austin Texas (voice) (fax) campo@campotexas.org

2 Amendment Description CAMPO FY TIP - Amendments by Board on April 10, 2006 Program Name Sponsor Name Project Name Project Limits Work Description Bicycle and Facilities 1 Added - New Public Transit Capital Area Rural Transportation System 2 Added - New Public Transit Capital Area Rural Transportation System 3 Added - New Public Transit City of Round Rock Bus Purchase Transportation Service Purchase Streetscape Improvement Project CAMPO Planning Area CAMPO Planning Area Round Rock's Intermodal Transit and Parking Facility 3 Type-3 accessible alt-fuel buses Bicycle and facilities are considered in all CARTS programs Purchase of Transportation Service Instalation of sidewalks, curbs and gutters, and landscaping Bicycle and facilities are considered in all CARTS programs Implements CAMPO public transportation policy PT-5. Create viable connections between public transportation and other transportation modes, such as walking, bicycling and driving Non Federal Non Federal Non Federal Federal Project Non Federal Federal Total Project Total Federal Total Project Total Federal Total Project Total Total Total Total Total Total Total $ 47,869 $ 191,476 $ 239,345 $ 48,130 $ 192,518 $ 240,648 $ 48,000 $ 192,000 $ 240,000 $ 143,999 $ 575,994 $ 719,993 $ 6,000 $ 24,000 $ 30,000 $ 8,000 $ 32,000 $ 40,000 $ 7,000 $ 28,000 $ 35,000 $ 21,000 $ 84,000 $ 105,000 $ - $ - $ - $ 1,400,000 $ - $ 1,400,000 $ - $ - $ - $ 1,400,000 $ - $ 1,400,000 4 Added - New Roadway City of Austin Cesar Chavez Street Two Way Conversion San Antonio Street to Brazos Street Convert a five block section to two-way traffic, add turn bays, traffic signals, wide sidewalks and landscaping Wide sidewalks $ - $ - $ - $ 3,000,000 $ 1,920,000 $ 4,920,000 $ - $ - $ - $ 3,000,000 $ 1,920,000 $ 4,920,000 5 Added - New Roadway City of Austin East 7th Street Corridor Improvements Project IH 35 to Shady Lane Upgrade pedestian and streetlighting along the corridor, landscaping, installation of pavers in intersection and center turn lane, improve transit staops, consolidation of driveways, instalation of a gateway at the Pleasant Valley intersection, and the in See Work Description $ 4,300,000 $ 2,820,000 $ 7,120,000 $ - $ - $ - $ - $ - $ - $ 4,300,000 $ 2,820,000 $ 7,120,000 6 Added - New Roadway TxDOT FM 1431 East of US 183 Reconstruct existing roadway to 6-lane to 183A divided roadway 7 Added - Previously Bicycle City of Austin Barton Springs Robert E Lee Install 5' Wide Shoulder, Complete Road Bicycle Rd to Existing Gap, Access to Zilker Park Lanes Rollingwood Dr (075 Mi) 8 Added - Previously 9 Added - Previously Bicycle Bicycle City of Austin Jollyville Road / Loop 360 Bicycle / Crossing City of Austin Jollyville Road Sidewalk Jollyville Rd to Arboretum Blvd Floral Park to Braker Lane Improved Bike/Ped Crossing At Loop 360, 10' Wide Path Connecting Bike Route to Two Malls, Dell (053 Mi) Complete Gaps In Sidewalk On West Side; Access to Transit Stops, Churches, Employment, Retail, Single, & Multi - Family Residential (053 Mi) Includes bicycle and pedestrian accomodations $ 3,000,000 $ 1,000,000 $ 4,000,000 $ - $ - $ - $ - $ - $ - $ 3,000,000 $ 1,000,000 $ 4,000,000 See Work Description $ 184,576 $ 738,304 $ 922,880 $ - $ - $ - $ - $ - $ - $ 184,576 $ 738,304 $ 922,880 See Work Description $ 164,938 $ 659,750 $ 824,688 $ - $ - $ - $ - $ - $ - $ 164,938 $ 659,750 $ 824,688 See Work Description $ 104,392 $ 417,568 $ 521,960 $ - $ - $ - $ - $ - $ - $ 104,392 $ 417,568 $ 521, Added - Previously 11 Added - Previously 12 Added - Previously 13 Added - Previously 14 Added - Previously 15 Added - Previously Bicycle Bicycle Bicycle Bicycle Bicycle Bicycle City of Austin City of Austin City of Cedar Park City of Cedar Park City of Leander City of Leander Martin Luther Perez St to King Jr Mi E of Boulevard / FM Tannehill Lane 969 North Acres Park Bike Trail In Austin Park Plaza Dr. terminus to Furness Dr. Design And Construct Sidewalk On Northside Bicycle Trail: 1) Project dev., engrg, surveying, inspection, & materials testing; and 2) constr. Park Street At US 183 (N) Construct left turn lane on east and westbound side of Park Street US 183 (W) Revitalization Project ( Accessibility) Bagdad Road (S) (Sidewalk) CR 272/Crystal Falls Parkway Cypress Creek Rd (S) to FM 1431 (N) Crystal Falls Pkwy to Leander Hs US 183 (N) to Parmer Lane Provide Continuous Access Through Primary Commercial Areas and to Govt offices, Complete Gaps On Both Sides US183 (1.5 Mi) Design & Install 6' Wide Sidewalk On Both Sides, Complete Gap to High School (09 Mi) Intersection and Signal Improvements and Rail Crossing Upgrade Projects See Work Description $ 143,129 $ 572,517 $ 715,646 $ - $ - $ - $ - $ - $ - $ 143,129 $ 572,517 $ 715,646 See Work Description $ 68,178 $ 272,712 $ 340,890 $ - $ - $ - $ - $ - $ - $ 68,178 $ 272,712 $ 340,890 Park Street to be included in the cities bike route system; Project part of US 183(W) Revitalization Project $ 63,260 $ 253,040 $ 316,300 $ - $ - $ - $ - $ - $ - $ 63,260 $ 253,040 $ 316,300 See Work Description $ 119,735 $ 478,939 $ 598,674 $ - $ - $ - $ - $ - $ - $ 119,735 $ 478,939 $ 598,674 See Work Description $ 84,340 $ 337,360 $ 421,700 $ - $ - $ - $ - $ - $ - $ 84,340 $ 337,360 $ 421,700 TBD by the City of Leander $ 532,000 $ 2,128,000 $ 2,660,000 $ - $ - $ - $ - $ - $ - $ 532,000 $ 2,128,000 $ 2,660,000 Page 1 of 2

3 Amendment Description 16 Added - Previously 17 Added - Previously 18 Added - Previously 19 Added - Previously 20 Added - Previously 21 Added - Previously 22 Added - Previously 23 Added - Previously 24 Added - Previously 25 Added - Previously 26 Added - Previously 27 Added - Previously CAMPO FY TIP - Amendments by Board on April 10, Program Name Sponsor Name Project Name Project Limits Work Description Bicycle and Facilities Non Federal Non Federal Non Federal Federal Project Non Federal Federal Total Project Total Federal Total Project Total Total Total Total Total Total Total Federal Total Project Total Bicycle City of Manor Carrie Manor Rd See Work Description $ 20,620 $ 82,480 $ 103,100 $ - $ - $ - $ - $ - $ - $ 20,620 $ 82,480 $ 103,100 Sidewalk Project Bicycle Bicycle Bicycle CAMPO Programs CAMPO Programs CAMPO Programs City of Rollingwood City of San Marcos City of San Marcos CAMPO CAMPO CAMPO Bike/Ped Safety Project And Park Trail System North LBJ Drive Intersection Improvements Sessom Drive Intersection Improvements Demographics Data Collection Modeling Network and Traffic Serial Zone Refinement Transportation Modeler Burnet Rd to east end of Carrie Manor Rd Various locations Sessom Drive to Holland Street Loop 82 to Commanche Street CAMPO Planning Area CAMPO Planning Area CAMPO Planning Area Enhancements City of Austin Austin Austin Crosstown Bike Crosstown Bike Trail Trail Enhancements City of Austin Shoal Creek Trail; Enhancements City of Austin Walnut Creek Trail Enhancements City of Hutto Cottonwood Trail, Phase 2 In N Central Austin along Shoal Creek - Shoal Creek Trail Northern Walnut Creek in Austin Cottonwood Trail, Ph2 in City of Hutto Enhancements City of Taylor Taylor Old Town Taylor Old Town Design & Install Sidewalk, Complete Gaps to Elementary and Middle Schools, Park, and Downtown Area Provide Bike Lane Striping and Construct Walking Trail Intersection, Signal, and Bicycle Improvements Intersection, Signal, and Bicycle Improvements Manage the update of the population and employment estimates for the next model update in the five county area using the state (Texas State Data Center and Texas Workforce Commission) and local (building permits updated by cities and counties) data source Adjust the modeling network in the five county area to better represent the ground configuration using Global Positioning System (GPS) technology centerline network files Work with TxDOT on the next model calibration and develop in-house model run capabilities for performing routine analyses of traffic impacts due to minor network changes. Construct Bike Trail Enhancement- Urban Trail System Construct Trail Construct Trail Const Streetscape Project See Work Description $ 25,109 $ 100,435 $ 125,544 $ - $ - $ - $ - $ - $ - $ 25,109 $ 100,435 $ 125,544 See Work Description $ 550,000 $ 2,200,000 $ 2,750,000 $ - $ - $ - $ - $ - $ - $ 550,000 $ 2,200,000 $ 2,750,000 See Work Description $ 426,250 $ 1,705,000 $ 2,131,250 $ - $ - $ - $ - $ - $ - $ 426,250 $ 1,705,000 $ 2,131,250 Not Applicable (Program) $ 10,000 $ 40,000 $ 50,000 $ - $ - $ - $ - $ - $ - $ 10,000 $ 40,000 $ 50,000 Not Applicable (Program) $ 16,000 $ 64,000 $ 80,000 $ - $ - $ - $ - $ - $ - $ 16,000 $ 64,000 $ 80,000 Not Applicable (Staff) $ 4,000 $ 16,000 $ 20,000 $ - $ - $ - $ - $ - $ - $ 4,000 $ 16,000 $ 20,000 Bike and pedestrians accommodated in project Bike and pedestrians accommodated in project Bike and pedestrians accommodated in project Bike and pedestrians accommodated in project s accommodated on sidewalks $ 393,316 $ 1,573,265 $ 1,966,581 $ - $ - $ - $ - $ - $ - $ 393,316 $ 1,573,265 $ 1,966,581 $ 101,028 $ 404,112 $ 505,140 $ - $ - $ - $ - $ - $ - $ 101,028 $ 404,112 $ 505,140 $ 651,557 $ 2,606,230 $ 3,257,787 $ - $ - $ - $ - $ - $ - $ 651,557 $ 2,606,230 $ 3,257,787 $ 138,096 $ 552,382 $ 690,478 $ - $ - $ - $ - $ - $ - $ 138,096 $ 552,382 $ 690,478 $ 281,176 $ 1,124,702 $ 1,405,878 $ - $ - $ - $ - $ - $ - $ 281,176 $ 1,124,702 $ 1,405, Added - Previously Enhancements Williamson County Cross County Heritage Trail Cross County Heritage Trail Construct Walking/Bike Scenic Trail Bike and pedestrians accommodated in project $ 186,973 $ 747,892 $ 934,865 $ - $ - $ - $ - $ - $ - $ 186,973 $ 747,892 $ 934, Added - Previously Roadway City of Pflugerville Pfluger Lane / Greenlawn Blvd Pflugerville Loop to Railroad Ave Construct 4 - Lane Divided Roadway Sidewalk On One Side and Hike / Bike Trail On The Other $ 1,907,000 $ 7,628,000 $ 9,535,000 $ - $ - $ - $ - $ - $ - $ 1,907,000 $ 7,628,000 $ 9,535,000 Totals $ 13,529,541 $ 28,738,165 $ 42,267,706 $ 4,456,130 $ 2,144,518 $ 6,600,648 $ 55,000 $ 220,000 $ 275,000 $ 18,040,671 $ 31,102,683 $ 49,143,354 Page 2 of 2

4 The CAMPO FY TIP Financial Summary 4/24/2006 Funding Source Category of Work Total Apportioned Programmed Apportioned Programmed Apportioned Programmed Apportioned Programmed Federal - FHWA 1- Preventative Maintenance and Rehabilitation $ - $ 6,047,200 $ - $ 600,000 $ - $ - $ - $ 6,647, Metropolitan Area Corridor Projects $ - $ - $ - $ - $ - $ - $ - $ Urban Area Corridor Projects $ - $ - $ - $ - $ - $ - $ - $ Statewide Connectivity Projects $ - $ - $ - $77,695,200 $ - $25,830,000 $ - $103,525, Congestion Mitigation and Air Quality $ - $ - $ - $ - $ - $ - $ - $ Consolidated Structure Rehabilitation $ - $ - $ - $ - $ - $ - $ - $ STP Metropolitan Mobility $12,776,000 $38,235,754 $23,120,000 $ 470,000 $15,124,000 $ 920,000 $51,020,000 $ 39,625, Safety $ - $ - $ - $ - $ - $ - $ - $ Enhancement $ - $ 7,008,583 $ - $ - $ - $ - $ - $ 7,008, Miscellaneous $ - $ 1,000,000 $ - $ - $ - $ - $ - $ 1,000, District Discretionary $ - $ 1,404,576 $ - $16,120,320 $ - $ - $ - $ 17,524, Strategic Priority (Federal Funds) $ - $ - $ - $ 4,320,000 $ - $ - $ - $ 4,320,000 Total $12,776,000 $53,696,113 $23,120,000 $99,205,520 $15,124,000 $26,750,000 $51,020,000 $179,651,633 State Federal Highway Funds $ - $ - $ - $ - $ - $ - $ - $ Strategic Priority (100% State) $ - $ - $ - $ - $ - $ - $ - $ - State Highway Funds $ - $ - $ - $ - $ - $ - $ - $ - Locally Funded Projects City $ - $30,101,644 $ - $ 6,320,000 $ - $ - $ - $ 36,421,644 County $ - $ - $ - $ - $ - $ - $ - $ - Other $ - $ - $ - $ - $ - $ - $ - $ - Federal - FTA 5307 $ - $66,689,000 $ - $20,975,000 $ - $37,260,000 $ - $124,924, $ - $23,370,000 $ - $25,000,000 $ - $15,000,000 $ - $ 63,370, $ - $ 443,476 $ - $ 224,518 $ - $ 220,000 $ - $ 887, $ - $ 3,197,106 $ - $ - $ - $ - $ - $ 3,197,106 Totals - Transit $ - $93,699,582 $ - $46,199,518 $ - $52,480,000 $ - $192,379,101

5 FY 2006 TRANSIT PROJECT LISTING CAMPO TRANSPORTATION IMPROVEMENT PROGRAM, MAY 2006 STIP AMENDMENT General Project Information Funding Information TxDOT District 14 Fiscal Year: FY 2006 Project Sponsor: Capital Area Rural Transportation System Federal Funding 5310 MPO Project N/A Federal Share: 24,000 Project Contract State - TxDOT: Project Phase: Local Share: 6,000 Brief Project Purchase of Transportation Services Total Cost of 30,000 General Project Information Funding Information TxDOT District 14 Fiscal Year: FY 2006 Project Sponsor: Capital Area Rural Transportation System Federal Funding 5310 MPO Project N/A Federal Share: 191,476 Project Contract State - TxDOT: Project Phase: Local Share: 47,869 Brief Project Purchase 3 Type-3 accessible alt-fuel buses Total Cost of 239,345 FY 2007 TRANSIT PROJECT LISTING CAMPO TRANSPORTATION IMPROVEMENT PROGRAM, MAY 2006 STIP AMENDMENT General Project Information Funding Information TxDOT District 14 Fiscal Year: FY 2007 Project Sponsor: Capital Area Rural Transportation System Federal Funding 5310 MPO Project N/A Federal Share: 32,000 Project Contract State - TxDOT: Project Phase: Local Share: 8,000 Brief Project Purchase of Transportation Services Total Cost of 40,000 General Project Information Funding Information TxDOT District 14 Fiscal Year: FY 2007 Project Sponsor: Capital Area Rural Transportation System Federal Funding 5311 MPO Project N/A Federal Share: 192,518 Project Contract State - TxDOT: Project Phase: Local Share: 48,130 Brief Project Purchase 3 Type-3 accessible alt-fuel buses Total Cost of 240,648 FY 2008 TRANSIT PROJECT LISTING CAMPO TRANSPORTATION IMPROVEMENT PROGRAM, MAY 2006 STIP AMENDMENT General Project Information Funding Information TxDOT District 14 Fiscal Year: FY 2008 Project Sponsor: Capital Area Rural Transportation System Federal Funding 5310 MPO Project N/A Federal Share: 28,000 Project Contract State - TxDOT: Project Phase: Local Share: 7,000 Brief Project Purchase of Transportation Services Total Cost of 35,000 General Project Information Funding Information TxDOT District 14 Fiscal Year: FY 2008 Project Sponsor: Capital Area Rural Transportation System Federal Funding 5311 MPO Project N/A Federal Share: 192,000 Project Contract State - TxDOT: Project Phase: Local Share: 48,000 Brief Project Purchase 3 Type-3 accessible alt-fuel buses Total Cost of 240,000

6 FY 2007 TRANSIT PROJECT LISTING - REGIONALLY SIGNIFICANT, LOCALLY FUNDED General Project Information Funding Information TxDOT District 14 Fiscal Year: 2007 Project Sponsor: City of Round Rock Federal Funding Category: Potential Section 5307 or Section 5309 funding MPO Project N/A Federal Share: Project Contract State - TxDOT: Project Phase: Local Share: 1,400,000 Brief Project Description: CAMPO TRANSPORTATION IMPROVEMENT PROGRAM, MAY 2006 STIP AMENDMENT Installation of sidewalks, curbs and gutters, Total Cost of and landscaping Project: 1,400,000

7 STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM METROPOLITAN PLANNING ORGANIZATIONS - FY 2006 FEDERAL STATE LOCAL PART TOTAL FUNDING ESTIMATED COST $ 28,522,689 $ 9,175,672 $ 37,698,361 $ 41,998, TOTAL $ 28,522,689 $ 9,175,672 $ 37,698,361 $ 41,998,361

8 STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM METROPOLITAN PLANNING ORGANIZATIONS - FY 2007 FEDERAL STATE LOCAL PART TOTAL FUNDING ESTIMATED COST $ 1,920,000 $ 3,000,000 $ 4,920,000 $ 4,920, TOTAL $ 1,920,000 $ 3,000,000 $ 4,920,000 $ 4,920,000

9 STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM METROPOLITAN PLANNING ORGANIZATIONS - FY 2008 FEDERAL STATE LOCAL PART TOTAL FUNDING ESTIMATED COST 2008 TOTAL MPO TOTAL $ 30,442,689 $ 9,175,672 $ 3,000,000 $ 42,618,361 $ 46,918,361

10 STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM TXDOT DISTRICTS - FY 2006 FEDERAL STATE LOCAL PART TOTAL FUNDING ESTIMATED COST 2006 TOTAL

11 STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM TXDOT DISTRICTS - FY 2007 FEDERAL STATE LOCAL PART TOTAL FUNDING ESTIMATED COST $ 1,842,764 $ 157,500 $ 342,566 $ 2,342,830 $ 2,412, TOTAL $ 1,842,764 $ 157,500 $ 342,566 $ 2,342,830 $ 2,412,830

12 STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM TXDOT DISTRICTS - FY 2008 FEDERAL STATE LOCAL PART TOTAL FUNDING ESTIMATED COST 2008 TOTAL DISTRICT TOTAL $ 1,842,764 $ 157,500 $ 342,566 $ 2,342,830 $ 2,412,830 STATE TOTAL $ 32,285,453 $ 9,333,172 $ 3,342,566 $ 44,961,191 $ 49,331,191

13 MONDAY, MAY 01, :27:36 AM STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM METROPOLITAN PLANNING ORGANIZATION FY 2006 PAGE: 7 OF MPO PROJECT NUM: 07/2006 COMPLETE GAPS IN SIDEWALK JOLLYVILLE RD SIDEWALK- FR FLORAL P BRAKER LANE $ 417,568 $ 104,392 $ 521,960 $ 521,960 HAYS AT SESSOM DR IN SAN MARCOS CS MPO PROJECT NUM: INTERSECTION, SIGNAL, & BICYCLE PEDESTRIAN IMPROVEMENTS $ 1,705,000 $ 426,250 $ 2,131,250 $ 2,131,250 HAYS AT N LBJ DR. IN SAN MARCOS CS MPO PROJECT NUM: INTERSECTION, SIGNAL AND BICYCLE PEDESTRIAN IMPROVEMENTS $ 2,200,000 $ 550,000 $ 2,750,000 $ 2,750,000 DEMOGRAPHICS DATA COLLECTION AT RIOUS LOCS IN MPO MPO PROJECT NUM: C,E FOR 5 CNTY AREA USING TX ST DATA CNTR & TWC, AND LOCAL DATA SOURCE. $ 40,000 $ 10,000 $ 50,000 $ 50,000 MODELING NETWORK & TRAF SER ZN REF AT RIOUS LOCS IN MPO MPO PROJECT NUM: C,E BETTER REPRESENT THE GROUND CONFIG USING GPS CENTERLINE NETWORK FILES $ 64,000 $ 16,000 $ 80,000 $ 80,000 TRANSPORTATION MODELER AT R LOCS IN MPO MPO PROJECT NUM: C,E INHOUSE MODEL RUN CAPABILITIES FOR PERFORMING ROUTINE ANALYS IS OF TRAFFIC IMPACTS DUE TO MINOR NETWORK CHANGES $ 16,000 $ 4,000 $ 20,000 $ 20,000 NORTH ACRES BIKE TRAIL- FROM FURNES PARK PLAZA MPO PROJECT NUM: CONST BIKE TRAIL ALONG WALNUT CREEK $ 272,712 $ 68,178 $ 340,890 $ 340,890 C = CONSTRUCTION, E = ENGINEERING, R = ROW, T = TRANSFER

14 MONDAY, MAY 01, :27:36 AM STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM METROPOLITAN PLANNING ORGANIZATION FY 2006 PAGE: 8 OF MPO PROJECT NUM: CONSTRUCT BIKE TRAIL CROSSTOWN BIKE TRAIL. $ 1,573,265 $ 393,316 $ 1,966,581 $ 1,966,581 ROLLINGWOOD ON RIOUS STREETS IN ROLLINGWOOD MPO PROJECT NUM: ADD BIKE LN STRIPING & CONSTRUCT WALKING TRAIL $ 100,435 $ 25,109 $ 125,544 $ 125,544 BARTON SPRINGS RD BIKE LNS FR ROBER LEE RD TO ROLLINGWOOD DR MPO PROJECT NUM: INSTALL 5' SHOULDER JOLLYVILLE RD/LP 360 BIKE/PED CROSS FR JOLLYVILLE RD TO ARBORETUM BLVD MPO PROJECT NUM: IMPROVE BIKE/PED CROSSING MANOR SIDEWALK IMPROVEMENT PROGRM F HWY 20 BRIDGE TO EAST END WHEELER MPO PROJECT NUM: DESIGN AND CONSTRUCT SIDEWALK $ 738,304 $ 184,576 $ 922,880 $ 922,880 $ 659,750 $ 164,938 $ 824,688 $ 824,688 $ 82,480 $ 20,620 $ 103,100 $ 103, MPO PROJECT NUM: CONSTRUCT TRAIL NORTHERN WALNUT CREEK TRAIL. $ 2,606,230 $ 651,557 $ 3,257,787 $ 3,257,787 IH 35 CS US MPO PROJECT NUM: EAST 7TH ST CORRIDOR IMPROVEMENTS $ 2,820,000 $ 2,820,000 $ 7,120, MPO PROJECT NUM: ENHANCEMENT- URBAN TRAIL SYSTEM IN N CENTRAL ALONG SHOAL CREEK- SHOAL CREEK TRAIL $ 404,112 $ 101,028 $ 505,140 $ 505,140 C = CONSTRUCTION, E = ENGINEERING, R = ROW, T = TRANSFER

15 MONDAY, MAY 01, :27:36 AM STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM METROPOLITAN PLANNING ORGANIZATION FY 2006 PAGE: 9 OF 16 CR MPO PROJECT NUM: CONST 4-LN DIVIDED ROADWAY GREENLAWN BLVD RAILROAD AVE $ 7,628,000 $ 1,907,000 $ 9,535,000 $ 9,535,000 FM MPO PROJECT NUM: CONSTRUCT SIDEWALKS PEREZ ST US 183 $ 572,517 $ 143,129 $ 715,646 $ 715,646 WILLIAMSON MPO PROJECT NUM: CONSTRUCT SIDEWALK BAGDAD RD SIDEWALK FR CRYSTAL FALLS LEANDER HS $ 337,360 $ 84,340 $ 421,700 $ 421,700 WILLIAMSON MPO PROJECT NUM: CONSTRUCT PEDESTRIAN ACCESS US 183 REVITAL PRJ-PED ACCESS FR CYPRESS CRK RD S TO FM 1431 N $ 478,939 $ 119,735 $ 598,674 $ 598,674 WILLIAMSON MPO PROJECT NUM: CONST LTL ON EB/WB SIDE OF PARK ST CEDAR PARK ON PARK ST AT US 183 N. $ 253,040 $ 63,260 $ 316,300 $ 316,300 WILLIAMSON ON CRYSTAL FALLS PKWY (CR 272) FROM CR US 183 TO PARMER LANE MPO PROJECT NUM: INTERSECTION,SIGNAL IMPRVMTS, & RR CROSSING UPGRADE PROJECTS $ 2,128,000 $ 532,000 $ 2,660,000 $ 2,660,000 WILLIAMSON MPO PROJECT NUM: CONST STREETSCAPE PROJECT TAYLOR OLD TOWN. $ 1,124,702 $ 281,176 $ 1,405,878 $ 1,405,878 WILLIAMSON MPO PROJECT NUM: CONST WALKING/BIKE SCENIC TRAIL CROSS COUNTY HERITAGE TRAIL. $ 747,892 $ 186,973 $ 934,865 $ 934,865 C = CONSTRUCTION, E = ENGINEERING, R = ROW, T = TRANSFER

16 MONDAY, MAY 01, :27:36 AM STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM METROPOLITAN PLANNING ORGANIZATION FY 2006 PAGE: 10 OF 16 WILLIAMSON MPO PROJECT NUM: CONSTRUCT TRAIL COTTONWOOD TRAIL, PHASE 2 IN CITY OF HUTTO $ 552,382 $ 138,096 $ 690,478 $ 690,478 WILLIAMSON RM MPO PROJECT NUM: RECONSTRUCT TO 6-LN DIV RDWY US 183 US 183-A $ 1,000,000 $ 3,000,000 $ 4,000,000 $ 4,000,000 METROPOLITAN PLANNING ORGANIZATION FY 2006 TOTAL: $ 28,522,689 $ 9,175,672 $ 37,698,361 $ 41,998,361 C = CONSTRUCTION, E = ENGINEERING, R = ROW, T = TRANSFER

17 MONDAY, MAY 01, :27:36 AM STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM METROPOLITAN PLANNING ORGANIZATION FY 2007 PAGE: 11 OF 16 UPG CESAR CHAVEZ ST CS FROM SAN ANTONIO ST TO BRAZOS ST MPO PROJECT NUM: 08/2007 DESIGN & CONSTRUCT TO CONVERT 2-WAY RD W/LANDSCAPE AND PED IMPROVEMENTS $ 1,920,000 $ 3,000,000 $ 4,920,000 $ 4,920,000 METROPOLITAN PLANNING ORGANIZATION FY 2007 TOTAL: $ 1,920,000 $ 3,000,000 $ 4,920,000 $ 4,920,000 C = CONSTRUCTION, E = ENGINEERING, R = ROW, T = TRANSFER

18 MONDAY, MAY 01, :27:36 AM STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM METROPOLITAN PLANNING ORGANIZATION PAGE: 12 OF 16 METROPOLITAN PLANNING ORGANIZATION TOTAL: $ 1,920,000 $ 3,000,000 $ 4,920,000 $ 4,920,000 C = CONSTRUCTION, E = ENGINEERING, R = ROW, T = TRANSFER

19 MONDAY, MAY 01, :27:36 AM STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM PAGE: 13 OF 16 STATE METROPOLITAN PLANNING ORGANIZATION TOTAL: $ 1,920,000 $ 3,000,000 $ 4,920,000 $ 4,920,000 C = CONSTRUCTION, E = ENGINEERING, R = ROW, T = TRANSFER

20 MONDAY, MAY 01, :27:36 AM STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM TXDOT DISTRICT FY 2007 PAGE: 14 OF 16 BLANCO MPO PROJECT NUM: 09/2006 CONSTRUCT TRAILS CITY OF JOHNSON CONSTRUCTION PEDESTRIAN TRAILS $ 472,500 $ 157,500 $ 630,000 $ 700,000 CALDWELL LOCKHART AT HISTORIC JAIL IN CITY OF LOCKHAR MPO PROJECT NUM: 09/2006 RESTORATION OF HISTORIC CALDWELL COUNTY JAIL OF 1909 $ 55,160 $ 13,790 $ 68,950 $ 68,950 CALDWELL LOCKHART SPRINGS WALKWAY MPO PROJECT NUM: 09/2006 CONSTRUCT PEDESTRIAN/BICYCLE TRAIL $ 1,315,104 $ 328,776 $ 1,643,880 $ 1,643,880 TXDOT DISTRICT FY 2007 TOTAL: $ 1,842,764 $ 157,500 $ 342,566 $ 2,342,830 $ 2,412,830 C = CONSTRUCTION, E = ENGINEERING, R = ROW, T = TRANSFER

21 MONDAY, MAY 01, :27:36 AM STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM TXDOT DISTRICT PAGE: 15 OF 16 TXDOT DISTRICT TOTAL: $ 1,842,764 $ 157,500 $ 342,566 $ 2,342,830 $ 2,412,830 C = CONSTRUCTION, E = ENGINEERING, R = ROW, T = TRANSFER

22 MONDAY, MAY 01, :27:36 AM STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM PAGE: 16 OF 16 STATE TXDOT DISTRICT TOTAL: STATE TOTAL: $ 1,842,764 $ 157,500 $ 342,566 $ 2,342,830 $ 2,412,830 $ 32,285,453 $ 9,333,172 $ 3,342,566 $ 44,961,191 $ 49,331,191

How to Read the Project Modification Listings - Roadway Section

How to Read the Project Modification Listings - Roadway Section How to Read the Project Modification Listings - Roadway Section Sa m pl e The project listing includes all projects for which Regional Transportation Council action will be requested during this Transportation

More information

TEXAS DEPARTMENT OF TRANSPORTATION

TEXAS DEPARTMENT OF TRANSPORTATION TEXAS DEPARTMENT OF TRANSPORTATION FY 2013-2016 2016 STIP STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM HOUSTON DISTRICT AUGUST 2014 Quarterly Revision HIGHWAY August 2014 . HOUSTON-GALVESTON AREA COUNCIL

More information

FY STIP. Houston District. November Quarterly Revisions TRANSIT STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM

FY STIP. Houston District. November Quarterly Revisions TRANSIT STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM FY 2011-2014 STIP STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM TRANSIT Houston District November Quarterly Revisions November 2011 HOUSTON-GALVESTON AREA COUNCIL PO Box 22777 3555 Timmons Ln. Houston,

More information

STAUNTON-AUGUSTA-WAYNESBORO METROPOLITAN PLANNING ORGANIZATION

STAUNTON-AUGUSTA-WAYNESBORO METROPOLITAN PLANNING ORGANIZATION STAUNTON-AUGUSTA-WAYNESBORO METROPOLITAN PLANNING ORGANIZATION City of Staunton County of Augusta City of Waynesboro 112 MTANLY PLE STAUNTON, VIRGINIA 24401 PHONE (540) 885-5174 FAX (540) 885-2687 July

More information

FY February Quarterly Revision. Houston DISTRICT

FY February Quarterly Revision. Houston DISTRICT FY 2013-2016 STIP STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM February Quarterly Revision Houston DISTRICT TRANSIT February 2013 HOUSTON-GALVESTON AREA COUNCIL PO Box 22777 3555 Timmons Ln. Houston,

More information

FY February Quarterly Revision. Bryan DISTRICT

FY February Quarterly Revision. Bryan DISTRICT FY 20132016 STIP STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM February Quarterly Revision Bryan DISTRICT TRANSIT Administrative Amendment February 2013 BCSMPO, Final FY 20132016 TIP, FY 2013 2016 Transportation

More information

How to Read the Project Modification Listings Roadway Section

How to Read the Project Modification Listings Roadway Section How to Read the Project Modification Listings Roadway Section The project listing includes all projects for which Regional Transportation Council action will be requested during this Transportation Improvement

More information

STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM TIP FY 2006-2008 METROPOLITAN PLANNING ORGANIZATIONS - FY 2006 FEDERAL STATE LOCAL OTHER PART TOTAL FUNDING ESTIMATED COST BROWNSVILLE HARLINGEN-SAN BENITO

More information

DRAFT UTP November Update - Funding Adjustments Summary EXHIBIT A REVISION DATE 11/7/14. (Amounts in millions) Sum $0

DRAFT UTP November Update - Funding Adjustments Summary EXHIBIT A REVISION DATE 11/7/14. (Amounts in millions) Sum $0 UTP November Update - Funding Adjustments Summary (Amounts in millions) District/Division//TMA Fiscal Year Adjusted Amount Post Public Meeting Adjustments Austin 3 SH 130 Concession FY $6,500,000 3 SH

More information

Chapter 6: Financial Resources

Chapter 6: Financial Resources Chapter 6: Financial Resources Introduction This chapter presents the project cost estimates, revenue assumptions and projected revenues for the Lake~Sumter MPO. The analysis reflects a multi-modal transportation

More information

NASHVILLE AREA MPO TRANSPORTATION IMPROVEMENT PROGRAM FY

NASHVILLE AREA MPO TRANSPORTATION IMPROVEMENT PROGRAM FY NASHVILLE AREA MPO TRANSPORTATION IMPROVEMENT PROGRAM FY 2008-2011 Amendment Conformity Report for August 20, 2008 Amendments (Amendment # 2008-028 thru 2008-030) On August 20, 2008 the Executive Board

More information

Transportation Improvement Program

Transportation Improvement Program Transportation Improvement Program Transportation Conformity Check List The Transportation Improvement Program (TIP) and all amendments must include a conformity report. The conformity report must address

More information

BEXAR COUNTY MPO CATEGORY 7 RECAP FY 2013

BEXAR COUNTY MPO CATEGORY 7 RECAP FY 2013 BEXAR COUNTY MPO CATEGORY 7 RECAP FY 2013 Total Uncommitted Funds FY 2013 A + B = C C + D = E E - F = G A B C D E F G Balance Carryover from FY 12 FY (includes all adjustments) Total Available Total Obligations

More information

TEXAS DEPARTMENT OF TRANSPORTATION BRYAN DISTRICT T I P

TEXAS DEPARTMENT OF TRANSPORTATION BRYAN DISTRICT T I P TEXAS DEPARTMENT OF TRANSPORTATION S T A T E W I D E T R A N S P O R T A T I O N I M P R O V E M E N T P R O G R A M S T I P 2 015201 8 BRYAN DISTRICT 2 0 1 5 2 0 1 8 T I P H I G H W AY I n i t i a l 2015

More information

Chapter 5: Cost and Revenues Assumptions

Chapter 5: Cost and Revenues Assumptions Chapter 5: Cost and Revenues Assumptions Chapter 5: Cost and Revenues Assumptions INTRODUCTION This chapter documents the assumptions that were used to develop unit costs and revenue estimates for the

More information

Transportation Improvement Program Page 39

Transportation Improvement Program Page 39 Fiscal Year CSJ Project # Facility From To 1 - Preventive Maintenance 2019 2022 Transportation Improvement Program Page 39 2U - Urban Mobility 3LC - Local Contribution 4 - Congestion, Connectivity, Corridor

More information

FY TRANSPORTATION IMPROVEMENT PROGRAM

FY TRANSPORTATION IMPROVEMENT PROGRAM FY 2019 2022 TRANSPORTATION IMPROVEMENT PROGRAM Approved for Public Review and Comment: April 16, 2018 Approved by the Policy Board: May 21, 2018 Table of Contents Permian Basin MPO Membership and Structure...

More information

Chapter 4: Plan Implementation

Chapter 4: Plan Implementation This chapter discusses the financial and regulatory needs associated with the implementation of this Transportation System Plan. Projected Funding for Transportation Improvements Projecting the revenue

More information

TEXAS TRANSPORTATION COMMISSION

TEXAS TRANSPORTATION COMMISSION TEXAS TRANSPORTATION COMMISSION VARIOUS Counties MINUTE ORDER Page 1 of 2 DALLAS & FORT WORTH Districts Transportation Code, 228.012 requires the Texas Department of Transportation (department) to create

More information

How to Read the Project Modification Listings Roadway Section

How to Read the Project Modification Listings Roadway Section How to Read the Project Modification Listings Roadway Section The project listing includes all projects for which Regional Transportation Council action will be requested during this Transportation Improvement

More information

TEXAS TRANSPORTATION COMMISSION

TEXAS TRANSPORTATION COMMISSION TEXAS TRANSPORTATION COMMISSION VARIOUS Counties MINUTE ORDER Page 1 of 2 DALLAS & FORT WORTH Districts Transportation Code, 228.012 requires the Texas Department of Transportation (department) to create

More information

Appendix D Total Project Cost and Year of Expenditure Breakdown

Appendix D Total Project Cost and Year of Expenditure Breakdown Total Project Cost and Year of Expenditure Breakdown p. D -1 Total Project Cost and Year of Expenditure Breakdown Financial Constraint Methodology using Total Project Cost and Year of Expenditure Dollars

More information

OHIO MPO AND LARGE CITY CAPITAL PROGRAM SFY 2015 SUMMARY

OHIO MPO AND LARGE CITY CAPITAL PROGRAM SFY 2015 SUMMARY OHIO MPO AND LARGE CITY CAPITAL PROGRAM SFY 2015 SUMMARY TABLE OF CONTENTS MPO AND LARGE CITY PROGRAM OVERVIEW.. 3 MPO AND LARGE CITY SFY 2015 STP BUDGET SUMMARY......... 4 MPO AND LARGE CITY SFY 2015

More information

TEXAS TRANSPORTATION COMMISSION

TEXAS TRANSPORTATION COMMISSION TEXAS TRANSPORTATION COMMISSION VARIOUS Counties MINUTE ORDER Page 1 of 2 DALLAS & FORT WORTH Districts Transportation Code, 228.012 requires the Texas Department of Transportation (department) to create

More information

INVESTING STRATEGICALLY

INVESTING STRATEGICALLY 11 INVESTING STRATEGICALLY Federal transportation legislation (Fixing America s Surface Transportation Act FAST Act) requires that the 2040 RTP be based on a financial plan that demonstrates how the program

More information

JACKSON METROPOLITAN PLANNING ORGANIZATION (MPO) TRANSPORTATION IMPROVEMENT PROGRAM (TIP)

JACKSON METROPOLITAN PLANNING ORGANIZATION (MPO) TRANSPORTATION IMPROVEMENT PROGRAM (TIP) HINDS Project: 480001 Responsible Agency: CITY OF CLINTON Total Project Cost: $6,068,000 Route: PINEHAVEN/NORTHSIDE DR Fund Source: EARMARK Project Length: 1.25 Pinehaven Dr from Northside Dr to 400' N

More information

LAKE~SUMTER MPO - COST FEASIBLE PROJECTS

LAKE~SUMTER MPO - COST FEASIBLE PROJECTS - COST FEASIBLE PROJECTS TABLE 1 - STATE PROJECTS (STRATEGIC INTERMODAL SYSTEM / FLORIDA'S TURNPIKE / CENTRAL FLORIDA EXPRESSWAY AUTHORITY) Facility From To Project Current Year Cost Estimates M-SIS M-SIS

More information

EXHIBIT A DONATIONS Cullen Blvd, An Individual Series of Forefunders Partners, LLC. Houston District

EXHIBIT A DONATIONS Cullen Blvd, An Individual Series of Forefunders Partners, LLC. Houston District EXHIBIT A DONATIONS NO. DONOR D/D/O COUNTY DESCRIPTION 1 9607 Cullen Blvd, An Individual Series of Forefunders Partners, LLC 2 Apache Corporation Houston District Harris The donor is donating the design

More information

Our Mission: To provide critical transportation infrastructure to enhance the community s long-term economic and environmental sustainability.

Our Mission: To provide critical transportation infrastructure to enhance the community s long-term economic and environmental sustainability. Department of Environmental Services Our Mission: To provide critical transportation infrastructure to enhance the community s long-term economic and environmental sustainability. Transportation Capital

More information

Transportation Improvement Program

Transportation Improvement Program Transportation Improvement Program Transportation Conformity Check List The Transportation Improvement Program (TIP) and all amendments must include a conformity report. The conformity report must address

More information

AGENDA Technical Advisory Committee Meeting

AGENDA Technical Advisory Committee Meeting AGENDA Technical Advisory Committee Meeting MEETING OF TYLER AREA METROPOLITAN PLANNING ORGANIZATION Thursday, March 7, 2013 2:30 p.m. Tyler Development Center, Large Conference Room, 423 W. Ferguson Street,

More information

TEXAS CLEAR LANES AND CONGESTION RELIEF TASK FORCE COMMITTEE ACTIVITY

TEXAS CLEAR LANES AND CONGESTION RELIEF TASK FORCE COMMITTEE ACTIVITY TEXAS CLEAR LANES AND CONGESTION RELIEF TASK FORCE COMMITTEE ACTIVITY Texas Transportation Commission September 26, 2018 Governor s Charge for Congestion Relief Initiative The State of Texas is spurring

More information

125 EAST 11 TH STREET AUSTIN, TEXAS 78701-2483 (512) 463-8588 WWW.TXDOT.GOV Mrs. Barbara C. Maley, AICP Env/Tranp Plan Coord & Air Quality Specialist Barbara.Maley@dot.gov December 27, 2016 Transmitted

More information

FY Transportation Improvement Program (TIP)

FY Transportation Improvement Program (TIP) Corvallis Area Metropolitan Planning Organization (CAMPO) FY2018-2021 Transportation Improvement Program (TIP) Approved by the Corvallis Area Metropolitan Planning Organization Policy Board May 17, 2017

More information

WICHITA FALLS DISTRICT

WICHITA FALLS DISTRICT TEXAS DEPARTMENT OF TRANSPORTATION S T A T E W I D E T R A N S P O R T A T I O N I M P R O V E M E N T P R O G R A M S T I P 2 015-201 8 WICHITA FALLS DISTRICT 2 0 1 5-2 0 1 8 T I P T R A N S I T I n i

More information

Route Route Z Intersection Realignment

Route Route Z Intersection Realignment Route N @ Route Z Intersection Realignment Sponsor County Highway Project No. RB18-000016 Project Type Traffic Flow TOTAL FUNDING Total County Sponsor Federal $3,310,000 $1,776,000 $0 $1,534,000 Project

More information

ALL Counties. ALL Districts

ALL Counties. ALL Districts TEXAS TRANSPORTATION COMMISSION ALL Counties rhnute ORDER Page of ALL Districts The Texas Transportation Commission (commission) finds it necessary to propose amendments to. and., relating to Transportation

More information

FY TRANSPORTATION IMPROVEMENT PROGRAM

FY TRANSPORTATION IMPROVEMENT PROGRAM FY 2017 2020 TRANSPORTATION IMPROVEMENT PROGRAM Approved for Public Review and Comment: April 18, 2016 Table of Contents Permian Basin MPO Membership and Structure... 3 Mission Statement... 3 Vision Statement...

More information

FY STIP. Paris District STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM. October Out-of-Cycle Revisions HIGHWAY

FY STIP. Paris District STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM. October Out-of-Cycle Revisions HIGHWAY FY 2011-2014 STIP STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM HIGHWAY Paris District October Out-of-Cycle Revisions October 2011 FY 2012 PAGE: 1 OF 4 1 - PARIS FANNIN 0045-20-017 US 82 LIMITS FROM GRAYSON

More information

UNIFIED TRANSPORTATION PROGRAM

UNIFIED TRANSPORTATION PROGRAM 2002 UNIFIED TRANSPORTATION PROGRAM Blank Page SUMMARY OF CATEGORIES CATEGORIES NUMBER, NAME AND YEAR ESTABLISHED PROGRAMMING AUTHORITY FUNDING BANK BALANCE (Yes/) RESPONSIBLE ENTITY RANKING INDEX OR ALLOCATION

More information

GLOSSARY. At-Grade Crossing: Intersection of two roadways or a highway and a railroad at the same grade.

GLOSSARY. At-Grade Crossing: Intersection of two roadways or a highway and a railroad at the same grade. Glossary GLOSSARY Advanced Construction (AC): Authorization of Advanced Construction (AC) is a procedure that allows the State to designate a project as eligible for future federal funds while proceeding

More information

Michigan City Urbanized Area & Non-Urban LaPorte County Changes

Michigan City Urbanized Area & Non-Urban LaPorte County Changes 2016-2019 Transportation Improvement Program for Lake, Porter, and Counties, Indiana Amendment #8 December 2015 Michigan City Urbanized Area & Non-Urban Changes 1297092 Supplemental Local Bridge Inspections

More information

125 EAST 11TH STREET, AUSTIN, TEXAS TxDOT DISCLAIMER

125 EAST 11TH STREET, AUSTIN, TEXAS TxDOT DISCLAIMER 125 EAST 11TH STREET, AUSTIN, TEXAS 78701-2483 512.463.8588 WWW.TXDOT.GOV TxDOT DISCLAIMER The Texas Department of Transportation ( TxDOT ) engaged Stantec Consulting Services Inc., ( Stantec ) the Traffic

More information

WASATCH FRONT REGIONAL TRANSPORTATION PLAN FINANCIAL PLAN. Technical Report 47 May 2007 DAVIS MORGAN SALT LAKE TOOELE WEBER

WASATCH FRONT REGIONAL TRANSPORTATION PLAN FINANCIAL PLAN. Technical Report 47 May 2007 DAVIS MORGAN SALT LAKE TOOELE WEBER WASATCH FRONT REGIONAL TRANSPORTATION PLAN 2007-2030 FINANCIAL PLAN Technical Report 47 May 2007 DAVIS MORGAN SALT LAKE TOOELE WEBER 2030 RTP Financial Plan WASATCH FRONT REGIONAL TRANSPORTATION PLAN

More information

RIDOA STATEWIDE PLANNING PROGRAM Transportation Planning

RIDOA STATEWIDE PLANNING PROGRAM Transportation Planning RIDOA STATEWIDE PLANNING PROGRAM Transportation Planning Land & Water Conservation Summit March 10, 2012 Statewide Planning Framework Department of Administration Statewide Planning Program State Planning

More information

TEXAS TRANSPORTATION FUNDING, INCLUDING TEXAS CLEAR LANES AND CONGESTION RELIEF UPDATE

TEXAS TRANSPORTATION FUNDING, INCLUDING TEXAS CLEAR LANES AND CONGESTION RELIEF UPDATE TEXAS TRANSPORTATION FUNDING, INCLUDING TEXAS CLEAR LANES AND CONGESTION RELIEF UPDATE Presentation for Texas Transportation Commission March 28, 2018 Purposes of the Workshop The Texas Transportation

More information

Statewide Transportation Improvement Program November 2017 Quarterly Revision - Highway

Statewide Transportation Improvement Program November 2017 Quarterly Revision - Highway 2017-2020 Statewide Transportation Improvement Program November 2017 Quarterly Revision - Highway 2017-2020 Statewide Transportation Improvement Program TxDOT Corpus Christi District Highway Projects TUESDAY,

More information

FY S T I P. Amarillo District STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM. July Out-of-Cycle Revisions

FY S T I P. Amarillo District STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM. July Out-of-Cycle Revisions FY 2011-2014 S T I P STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM H IGHWAY Amarillo District July Out-of-Cycle Revisions July 2012 Amarillo MPO June 7, 2012 2011-14 Transportation Improvement Program July

More information

Transportation Funding

Transportation Funding Transportation Funding TABLE OF CONTENTS Introduction... 3 Background... 3 Current Transportation Funding... 4 Funding Sources... 4 Expenditures... 5 Case Studies... 6 Washington, D.C... 6 Chicago... 8

More information

Index of Projects CS 602/CS 650/GRANGE ROAD FROM SR 21 TO E OF SR 25 Z001 GDOT

Index of Projects CS 602/CS 650/GRANGE ROAD FROM SR 21 TO E OF SR 25 Z001 GDOT 0002923 Index of Projects PI # DESCRIPTION FUNDING SR 25 CONN/BAY STREET FROM I-516 TO THE BAY STREET VIADUCT CURRENT SPONSOR FY CST PAGE Z001, Z230 Chatham County 2016 3 0007885 CS 602/CS 650/GRANGE ROAD

More information

ABILENE MPO TRANSPORTATION POLICY BOARD MEETING

ABILENE MPO TRANSPORTATION POLICY BOARD MEETING ABILENE MPO TRANSPORTATION POLICY BOARD MEETING Tuesday, October 16, 2018 at 1:30 pm City Council Chambers Abilene City Hall 555 Walnut Street, Abilene, Texas 1. Call to Order. Public comment may be taken

More information

BRISTOL TENNESSEE / VIRGINIA URBAN AREA METROPOLITAN PLANNING ORGANIZATION

BRISTOL TENNESSEE / VIRGINIA URBAN AREA METROPOLITAN PLANNING ORGANIZATION BRISTOL TENNESSEE / VIRGINIA URBAN AREA METROPOLITAN PLANNING ORGANIZATION Amendment # 2 FY 2017-2020 Transportation Improvement Program Amendment Summary: The Transportation Improvement Program (TIP)

More information

2017 UNIFIED TRANSPORTATION PROGRAM AND HB 20 IMPLEMENTATION

2017 UNIFIED TRANSPORTATION PROGRAM AND HB 20 IMPLEMENTATION 2017 UNIFIED TRANSPORTATION PROGRAM AND HB 20 IMPLEMENTATION HGAC Transportation Policy Council Meeting Current Initiatives On-going efforts to address performance-based planning and programming processes

More information

TENTATIVE FIVE YEAR WORK PROGRAM FISCAL YEARS

TENTATIVE FIVE YEAR WORK PROGRAM FISCAL YEARS TENTATIVE FIVE YEAR WORK PROGRAM FISCAL YEARS 2019-2023 MANATEE COUNTY FLORIDA DEPARTMENT OF TRANSPORTATION - DISTRICT ONE MISSION STATEMENT The Department will provide a safe, interconnected statewide

More information

DRAFT C APITAL I MPROVEMENT P LAN C ITY OF G EORGETOWN, TEXAS S TREETS/ DRAINAGE/AIRPORT F ISCAL Y EAR 201 6

DRAFT C APITAL I MPROVEMENT P LAN C ITY OF G EORGETOWN, TEXAS S TREETS/ DRAINAGE/AIRPORT F ISCAL Y EAR 201 6 C ITY OF G EORGETOWN, TEXAS C APITAL I MPROVEMENT P LAN S TREETS/ DRAINAGE/AIRPORT F ISCAL Y EAR 201 6 Georgetown Transportation Advisory Board April 10, 2015 Table of Contents Introduction... 1 Transportation

More information

BHJTS TRANSPORTATION IMPROVEMENT PROGRAM FEDERAL, STATE & LOCAL PROJECTS 2016 THROUGH 2019 FOUR-YEAR SHORT RANGE PROGRAM

BHJTS TRANSPORTATION IMPROVEMENT PROGRAM FEDERAL, STATE & LOCAL PROJECTS 2016 THROUGH 2019 FOUR-YEAR SHORT RANGE PROGRAM TOTAL PROJECT ESTIMATE ($) STATE ALLOCATION CODE (SAC) FUND TYPE ENCUMBERED FROM BEFORE FY 2011 PE/RW PRIOR TO FY 2016 LOCAL MATCH LOCAL LABOR STATE LABOR FED LABOR & TSKF LINE ITEM # ST. LINE ITEM

More information

Development of the Cost Feasible Plan

Development of the Cost Feasible Plan March 15, 2012 TPO Board and Advisory Committee Meetings Development of the Cost Feasible Plan Transportation Outlook 2035 LRTP Update Atkins Development of the Cost Feasible Plan P a g e 1 Development

More information

Joplin Area Transportation Study Organization

Joplin Area Transportation Study Organization Joplin Area Transportation Study Organization 2018-2021 Transportation Improvement Program 602 SOUTH MAIN STREET JOPLIN, MISSOURI 64801 (417) 624-0820 CONTENTS INTRODUCTION... 3 AVIATION... 9 HIGHWAY...

More information

Columbia Area Metropolitan Planning Organization

Columbia Area Metropolitan Planning Organization Columbia Area Metropolitan Planning Organization FY 2009 Annual Listing of Obligated Projects October 1, 2008 September 30, 2009 Approved by the CMCOG Board June 24, 2010 The preparation of this report

More information

FY Transportation Improvement Program (TIP)

FY Transportation Improvement Program (TIP) Corvallis Area Metropolitan Planning Organization (CAMPO) FY2015-2018 Transportation Improvement Program (TIP) Approved by the Corvallis Area Metropolitan Planning Organization Policy Board July 27, 2016

More information

Appendix. G RTP Revenue Assumptions REGIONAL TRANSPORTATION PLAN/SUSTAINABLE COMMUNITIES STRATEGY

Appendix. G RTP Revenue Assumptions REGIONAL TRANSPORTATION PLAN/SUSTAINABLE COMMUNITIES STRATEGY Appendix G RTP Revenue Assumptions REGIONAL TRANSPORTATION PLAN/SUSTAINABLE COMMUNITIES STRATEGY Exhibit G-1 2014 RTP REVENUE FORECAST ASSUMPTIONS LOCAL REVENUES Measure K Sales Tax Renewal Program: Description:

More information

10-Year Capital Highway Investment Plan DRAFT

10-Year Capital Highway Investment Plan DRAFT This document is made available electronically by the Minnesota Legislative Reference Library as part of an ongoing digital archiving project. http://www.leg.state.mn.us/lrl/lrl.asp 10-Year Capital Highway

More information

2. fl Concord REPORT TO MAYOR AND COUNCIL/AGENCY BOARD

2. fl Concord REPORT TO MAYOR AND COUNCIL/AGENCY BOARD AGENDA ITEM NO. 2. fl Concord REPORT TO MAYOR AND COUNCIL/AGENCY BOARD TO THE HONORABLE MAYOR AND COUNCIL: DATE: June 22, 2009 Subiect: ADOPTING RESOLUTION NO. 09-53, APPROVING THE CITY'S REVISED PROPOSITION

More information

BROWNSVILLE METROPOLITAN PLANNING ORGANIZATION F.Y F.Y METROPOLITAN TRANSPORTATION IMPROVEMENT PROGRAM (TIP)

BROWNSVILLE METROPOLITAN PLANNING ORGANIZATION F.Y F.Y METROPOLITAN TRANSPORTATION IMPROVEMENT PROGRAM (TIP) BROWNSVILLE METROPOLITAN PLANNING ORGANIZATION F.Y. 2017-F.Y. 2020 METROPOLITAN TRANSPORTATION IMPROVEMENT PROGRAM (TIP) By: Brownsville MPO Staff City Plaza 1034 E. Levee St., 2 nd floor Brownsville,

More information

OHIO MPO & LARGE CITY CAPITAL PROGRAM SFY 2017 SUMMARY

OHIO MPO & LARGE CITY CAPITAL PROGRAM SFY 2017 SUMMARY OHIO MPO & LARGE CITY CAPITAL PROGRAM SFY 2017 SUMMARY Revised 9/19/2017 TABLE OF CONTENTS MPO AND LARGE CITY PROGRAM OVERVIEW... 3 MPO AND LARGE CITY SFY 2017 STBG BUDGET SUMMARY... 4 MPO AND LARGE CITY

More information

Updated TIP Project Pages as of March 22, 2018

Updated TIP Project Pages as of March 22, 2018 Updated TIP Project Pages as of March 22, 2018 Index of Projects PI # DESCRIPTION FUNDING SPONSOR FY CST PAGE 0012757 I-16 FROM I-95 TO I-516 Z001 GDOT 2018-2021 3 0012758 I-16 @ I-95 INTERCHANGE RECONSTRUCTION

More information

Financial Capacity Analysis

Financial Capacity Analysis FINANCIAL CAPACITY ANALYSIS Introduction Federal transportation planning rules require that metropolitan area transportation plans include a financial capacity analysis to demonstrate that the plan is

More information

FY STIP. Lufkin District. February 2012 Quarterly Revisions HIGHWAY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM

FY STIP. Lufkin District. February 2012 Quarterly Revisions HIGHWAY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM FY 2011-2014 STIP STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM HIGHWAY Lufkin District February 2012 Quarterly Revisions February 2012 FRIDAY, JANUARY 06, 2012 9:37:23 AM STATEWIDE TRANSPORTATION IMPROVEMENT

More information

NASHVILLE AREA MPO. ADJUSTMENT to The Fiscal Years Transportation Improvement Program. Adjustment Number: TIP Number:

NASHVILLE AREA MPO. ADJUSTMENT to The Fiscal Years Transportation Improvement Program. Adjustment Number: TIP Number: NASHVILLE AREA MPO ADJUSTMENT to The Fiscal Years 20082011 Transportation Improvement Program Adjustment Number: 2009019 TIP Number: 200852034 FROM: TIP# 200852034 Jurisdiction: Hendersonville Project:

More information

Capital Improvement Projects

Capital Improvement Projects Capital Improvement Projects This section highlights the Capital Improvement Program (CIP) projects proposed for FY 2017-2018. Capital projects are designed to enhance the City s infrastructure, extend

More information

This page intentionally left blank

This page intentionally left blank 197 This page intentionally left blank 198 Capital Improvement Program PROCEDURE Each year the Capital Improvement Program (CIP) is prepared from project requests submitted by the various departments.

More information

TECHNICAL ADVISORY COMMITTEE MEETING Monday, May 21, 2018 University Park, Suite N. IH 35, Austin, Texas :00 p.m.

TECHNICAL ADVISORY COMMITTEE MEETING Monday, May 21, 2018 University Park, Suite N. IH 35, Austin, Texas :00 p.m. TECHNICAL ADVISORY COMMITTEE MEETING Monday, May 21, 2018 University Park, Suite 300 3300 N. IH 35, Austin, Texas 78705 2:00 p.m. AGENDA ACTION: 1. Certification of Quorum Quorum requirement is 13 members......chair

More information

Transportation Committee

Transportation Committee Business Item No. 2013-341 Consent Transportation Committee Meeting date: December 9, 2013 For the Metropolitan Council meeting of January 15, 2014 Subject: 2014-2017 TIP Amendment for North Urban Regional

More information

2017 UNIFIED TRANSPORTATION PROGRAM AND HB 20 IMPLEMENTATION

2017 UNIFIED TRANSPORTATION PROGRAM AND HB 20 IMPLEMENTATION 2017 UNIFIED TRANSPORTATION PROGRAM AND HB 20 IMPLEMENTATION TEMPO Meeting July 21, 2016 Current Initiatives On-going efforts to address performance-based planning and programming processes as required

More information

HOUSTON-GALVESTON AREA COUNCIL PO Box Timmons Ln. Houston, Texas /

HOUSTON-GALVESTON AREA COUNCIL PO Box Timmons Ln. Houston, Texas / HOUSTON-GALVESTON AREA COUNCIL PO Box 22777 3555 Timmons Ln. Houston, Texas 77227-2777 713/627-3200 Mr. Delvin Dennis, P.E. Houston District Engineer Texas Department of Transportation P.O. Box 1386 Houston,

More information

Funding Update. House Transportation Subcommittee on Long-Term Infrastructure Planning September 10, 2015, 9:00 A.M. Capitol Extension E2.

Funding Update. House Transportation Subcommittee on Long-Term Infrastructure Planning September 10, 2015, 9:00 A.M. Capitol Extension E2. Funding Update House Transportation Subcommittee on Long-Term Infrastructure Planning September 10, 2015, 9:00 A.M. Capitol Extension E2.012 Transportation Funding Sources for the FY 2016-2017 Biennium

More information

FY2018 Approved Capital Budget and Program Table of Contents

FY2018 Approved Capital Budget and Program Table of Contents FY2018 Approved Capital Budget and Program Table of Contents CAPITAL BUDGET OVERVIEW Affordability... 1 Capital Highlights and Significant Capital Projects... 4 Financial Summaries... 6 Explanation of

More information

Transportation Planning FAQ s

Transportation Planning FAQ s Transportation Planning FAQ s 1. What is the Master Thoroughfare Plan (MTP)? The Master Thoroughfare Plan defines the network of existing and future roads deemed appropriate to accommodate the various

More information

APPENDIX I REVENUE PROJECTION AND ASSUMPTIONS

APPENDIX I REVENUE PROJECTION AND ASSUMPTIONS APPENDIX I REVENUE PROJECTION AND ASSUMPTIONS The 2018 StanCOG Regional Transportation Plan/Sustainable Communities Strategy (RTP/SCS) financial forecasts provide revenue projections for StanCOG member

More information

Removed Projects TR th Way SE (Snake Hill) Improvements o Will be completed in TR th Ave SE Gap Project

Removed Projects TR th Way SE (Snake Hill) Improvements o Will be completed in TR th Ave SE Gap Project Agenda Bill City Council Regular Meeting June 19, 2018 SUBJECT: 2019-2024 Six-Year Transportation Improvement Plan (TIP) DATE SUBMITTED: June 12, 2018 DEPARTMENT: Public Works NEEDED FROM COUNCIL: Action

More information

City of Laredo Capital Improvement Program (CIP) INTRODUCTION

City of Laredo Capital Improvement Program (CIP) INTRODUCTION City of Laredo Capital Improvement Program (CIP) INTRODUCTION The Capital Improvements Program (CIP) The following is a summary of the Capital Improvements Project (CIP) Program for fiscal years 2003-2007,

More information

Approved by the Roanoke Valley-Alleghany Regional Commission April 25, 2013

Approved by the Roanoke Valley-Alleghany Regional Commission April 25, 2013 FY 2014 Rural Transportation Planning Assistance Program SCOPE OF WORK For the Roanoke Valley-Alleghany Regional Commission (July 1, 2013 June 30, 2014) Approved by the Roanoke Valley-Alleghany Regional

More information

TESTIMONY. The Texas Transportation Challenge. Testimony Before the Study Commission on Transportation Financing

TESTIMONY. The Texas Transportation Challenge. Testimony Before the Study Commission on Transportation Financing TESTIMONY The Texas Transportation Challenge Testimony Before the Study Commission on Transportation Financing Ric Williamson Chairman Texas Transportation Commission April 19, 2006 Texas Department of

More information

QUALITY TRANSPORTATION SUMMARY

QUALITY TRANSPORTATION SUMMARY QUALITY TRANSPORTATION SUMMARY Quality Transportation Overview... 126 Department of Transportation... 127 Traffic Field Operations... 129 Winston-Salem Transit Authority... 131 Quality Transportation Non-Departmental...

More information

Existing Conditions/Studies

Existing Conditions/Studies CAMPO Plan and Model Pesentation Presentation June 17, 2008 CAMPO 2035 Plan Timeline September 2008 Network/Modal Environmental Demographic Fiscal/Policy Needs Analysis Existing Conditions/Studies Vision/

More information

City of St. Petersburg, FL 2015 thru 2019 Capital Improvement Plan - Project Descriptions by Fund Bicycle/Pedestrian Safety Grants CIP Fund (3004)

City of St. Petersburg, FL 2015 thru 2019 Capital Improvement Plan - Project Descriptions by Fund Bicycle/Pedestrian Safety Grants CIP Fund (3004) City of St. Petersburg FY15 Adopted Fiscal Plan Fiscal Year 2015 R-1 CIP Other Funds City of St. Petersburg, FL 2015 thru 2019 Capital Improvement Plan - Project Descriptions by Fund Bicycle/Pedestrian

More information

DRAFT. Summary of Projects List UNOFFICIAL. UNOFFICIAL Project Name Project No. Const. Yr Total UNOFFICIAL.

DRAFT. Summary of Projects List UNOFFICIAL. UNOFFICIAL Project Name Project No. Const. Yr Total UNOFFICIAL. Summary of Projects List Osage Nation Project Name Project No. Const. Yr 2019 2020 2021 2022 2023 Total Wildland Fire Management Building 2018 $0 $50,000 $0 $0 $0 $50,000 Dog Thresher Creek BR176 2018

More information

Okaloosa-Walton 2035 Long Range Transportation Plan Amendment

Okaloosa-Walton 2035 Long Range Transportation Plan Amendment Okaloosa-Walton 2035 Long Range Transportation Plan Amendment Adopted August 22, 2013 This report was financed in part by the U.S. Department of Transportation, Federal Highway Administration, the Florida

More information

Region 5 Upcoming Projects for Summer/Fall 2018

Region 5 Upcoming Projects for Summer/Fall 2018 Region 5 Upcoming Projects for Summer/Fall 2018 The budget amount provided does not reflect the construction costs for projects. The amounts may include ROW, engineering, design, and utility costs. The

More information

4.A.14-2

4.A.14-2 4.A.14-1 4.A.14-2 Administration and Projects Committee STAFF REPORT Meeting Date: June 2, 2016 Subject Summary of Issues FY 2016-17 Proposed Budget for the Contra Costa Transportation Authority and Congestion

More information

Annual Listing of Obligated Projects Federal Fiscal Year 2013

Annual Listing of Obligated Projects Federal Fiscal Year 2013 Annual Listing of Obligated Projects Federal Fiscal Year 2013 Nashua Regional Planning Commission 9 Executive Park Drive Suite 201 Merrimack, NH 03054 (603) 424-2240 www.nashuarpc.org A N N U A L L I S

More information

Approved STIP Formal Amendments for the Period of 11/01/2018-3/15/2019

Approved STIP Formal Amendments for the Period of 11/01/2018-3/15/2019 3116-151 Hwy 169 from Taconite to Pengilly, Safety Improvements 5409-32 Concrete resurface, raise grade at levee's, install lighting, improve drainage and pedestrian accessibility on Hwy 75 in Halstad

More information

MEMORANDUM. Requested Action Provide comments and questions to staff regarding the proposed TIP projects funding scenario.

MEMORANDUM. Requested Action Provide comments and questions to staff regarding the proposed TIP projects funding scenario. MEMORANDUM To: MPO Technical and Citizens Advisory Committees From: Joshua Desmond, AICP BMCMPO Director Date: March 15, 2017 Re: FY 20182021 TIP s Proposal The MPO is developing the s 2018 through 2021

More information

Technical Report No. 4. Revenue and Costs

Technical Report No. 4. Revenue and Costs Technical Report No. 4 Revenue and Costs Technical Report No. 4 REVENUE AND COSTS PASCO COUNTY METROPOLITAN PLANNING ORGANIZATION 8731 Citizens Drive New Port Richey, FL 34654 Ph (727) 847-8140, fax (727)

More information

City of Des Moines. Citizen Engagement Capital Improvement Program. November 29, 2016

City of Des Moines. Citizen Engagement Capital Improvement Program. November 29, 2016 City of Des Moines Citizen Engagement Capital Improvement Program November 29, 2016 Goals of Citizen Engagement Goal Focus on service levels Department definitions of adequate service and opportunities

More information

Amarillo Metropolitan Transportation Plan October 18, 2007 Revision Use Of Year-Of-Expenditure Cost Estimates

Amarillo Metropolitan Transportation Plan October 18, 2007 Revision Use Of Year-Of-Expenditure Cost Estimates 2005-30 Amarillo Metropolitan Transportation Plan October 18, 2007 Revision Use Of Year-Of-Expenditure Cost Estimates The Federal Transportation bill, the Safe Accountable, Flexible, Efficient Transportation

More information

Capital Improvements Program. City Council October 14, 2014

Capital Improvements Program. City Council October 14, 2014 Capital Improvements Program City Council October 14, 2014 Neighborhood Attendees ~15 (Paul Kaspar) Presentation Today CIP Advantages/Process Approved CIP Program (FY14 - FY18 CIP) Financial Forecast Projects

More information

Oakland Park Transportation Improvement Program (TIP) Projects. Mobility. Oakland Park Blvd. Total Funding Amounts ($):

Oakland Park Transportation Improvement Program (TIP) Projects. Mobility. Oakland Park Blvd. Total Funding Amounts ($): Oakland Park 2016-2020 Transportation Improvement Program (TIP) Projects 4358081 4346971 4359251 4360971 4366851 4331651 4368751 4316721 4316721 4260161 4387321 Legend Projects Interstates Roadway Mobility

More information

MEASURE B AND MEASURE BB Annual Program Compliance Report Reporting Fiscal Year AGENCY CONTACT INFORMATION

MEASURE B AND MEASURE BB Annual Program Compliance Report Reporting Fiscal Year AGENCY CONTACT INFORMATION MEASURE B AND MEASURE BB Annual Program Compliance Report Reporting Fiscal Year 20172018 AGENCY CONTACT INFORMATION Agency Name: City of Fremont Date: 12/21/2018 Primary Point of Contact Name: Tish Saini

More information

TENTATIVE FIVE YEAR WORK PROGRAM FISCAL YEARS

TENTATIVE FIVE YEAR WORK PROGRAM FISCAL YEARS TENTATIVE FIVE YEAR WORK PROGRAM FISCAL YEARS 2019-2023 CHARLOTTE COUNTY FLORIDA DEPARTMENT OF TRANSPORTATION - DISTRICT ONE MISSION STATEMENT The Department will provide a safe, interconnected statewide

More information