Session: WED How to Cost Load a schedule. OR Understanding the SDEF

Size: px
Start display at page:

Download "Session: WED How to Cost Load a schedule. OR Understanding the SDEF"

Transcription

1 Session: WED How to Cost Load a schedule for USACE s QCS/RMS OR Understanding the SDEF

2 (understanding the SDEF) Introduction David Long Sr. Project Controls Specialist With 20+ years of Scheduling and Cost Analysis experience on USACE funded/managed projects. Including Environmental, Bid/Construct, and Design/Build. Cost reimbursable, Time and Material, and Firm Fixed Price Contracts. It is important to understand the USACE intent and usage of a cost loaded schedule and QCS/RMS as part of the Progress Payment process. That is, your cost loaded schedule is your SOV. Therefore, it is understanding the Process and the Standard Data Exchange File (SDEF) that becomes the key to understanding how to Cost Load the Schedule.

3 (understanding the SDEF) Introduction Today s presentation is built around Primavera s P6 Version 6.2 but the principles and techniques are applicable to MS Project and other Scheduling Applications It is also based on Firm Fixed Price Contracts, however, applicable for Cost Reimbursable and T&M contracts.. Based on Actual Cost not Earned Value Firm Fixed Price vs. Cost Reimbursable Affects the source of Actual Cost not the Field used.

4 Relative Standards / Documents

5 ER

6 ER This regulation states the policy on the use of any of the various scheduling management methods. various systems (bar charts, network analysis etc.) as well as administration of contract provisions. This regulation is applicable to all USACE commands. FAR DOD FAR Supplement

7 Primavera P6 SDEF Conversion

8 Primavera P6 SDEF Conversion

9 Unified Facilities Guide Specifications (UFGS) ************************************************************************** USACE / NAVFAC / AFCEC / NASA UFGS (August 2008) Change 1 08/13 Preparing Activity: USACE Superseding UFGS (July 2007) UNIFIED FACILITIES GUIDE SPECIFICATIONS References are in agreement with UMRL dated October 2013 ************************************************************************** SECTION PROJECT SCHEDULE ************************************************************************** NOTE: This guide specification covers the requirements for the preparation and maintenance of the project schedule for construction projects or design build construction projects.

10 Basic Reason for Cost Loading the Schedule USFG Section Paragraph 3.2 BASIS FOR PAYMENT AND COST LOADING To Get Use the schedule as the basis for determining contract earnings during each update period and therefore the amount of each progress payment. That is, the cost loaded schedule is your schedule of value for progress payments. Therefore

11 Cost Loading the Schedule It is reasonable. Acceptable to the Contracting Officer. The activity scope is measurable and represents a deliverable value to the Government. All activities for a specified CLIN sums up to the CLIN value USFG Section Paragraph 3.2 BASIS FOR PAYMENT AND COST LOADING Activity cost loading shall be reasonable, as determined by the Contracting Officer. The aggregate value of all activities coded to a contract CLIN shall equal the value of the CLIN on the Schedule. The schedule is your schedule of value for progress payments.

12 Cost Loading the Schedule The Earnings Report Budgeted Total Cost at the activity level must roll up and equal to the Contract CLINs (SubCLINS) Actual Cost is the actual cost to date for Cost Reimbursement Contract or is equal to the Earned Value for FFP Contracts (SOV Value)

13 Cost Loading the Schedule Only Resource Assignment Budget and Actual Cost are exported to QCS/RMS. That is: User Defined Cost Fields or P6 Expenses are not included in the SDEF Multiple Resource Assignments are allowed, however, it is only the Resource Assignment s total Budget and Actual Cost that are exported to QCS/RMS. Resource units, Activity Earned Value, Activity % Complete are not exported to QCS/RMS. That is: % Complete is calculated in QCS/RMS by dividing the Actual Cost by the Budget, that is, % Spent.

14 Cost Loading the Schedule Role ID SUB/MTL Resource ID $$$$.Fully Burdened Cost Resource Type Nonlabor [NOTE: can use Labor or Material Resource Type] Rate Type Used with Resource or Role Rate Source Rate Source Override (allows for manual entry of Price/Unit) [NOTE: Resource or Role Rate Source can be used] Price/Unit Used if Calculate Cost form Units is Checked Budgeted Cost Budget (Price/Unit * Budget Units) Actual Units Actual Units to date (Entered value unless using Auto Compute ) Actual Cost Actual Cost to date (Entered value unless using Cal cost from units) SDEF PROG Record PROG C AUG SEP12 17SEP12 + 7

15 Cost Loading the Schedule The Earnings Report Review

16 Cost Loading the Schedule

17 Cost Loading the Schedule? SDEF ACTV Record ACTV C1040 Install Storm Water System CVIL DRNG CN W Stabilization Methods

18 Cost Loading the Schedule Direct Cost (Direct Labor include Fringe and Overhead) Any Contingency and prorated General Conditions and PMO Costs G&A and any other indirect costs excluding Bond and Insurance costs Fee / Profit (unless allowed as a separate billing line item typically Cost Re) Cost must be loaded on deliverable activities with measurable scope having value to the Government.

19

20 Cost Loading the Schedule Prep/Submit Concept Design Design Management/Support Staff (GC) Gov't Review Concept Design Prep/Submit 100% Civil Design Design Conf. Concept Design Gov't Review 100% Civil Design Construction Management/Support Staff (GC) Prep/Submit SWS Submittal Design Conf. 100% Design Prep/Submit IFC Civil Design Gov't Review/Acceptance IFC Civil Design Issue IFC Civil Design Civil and SWS Preparatory Remove Fencing Fill/Compact Sinkhole Del. Fencing Materials Install Storm Water System $ 2, $ 0.00 $ 0.00 $ 5, $ 0.00 $ 0.00 $ 0.00 $ 1, $ 0.00 $ 1, $ 0.00 $ 1, $ 0.00 $ $ 6, $ 2, $12,000.00

21 The Process Schedule Review and Reports Network Diagram Earnings Report Activity Report Logic Report Total Float Report Generate the SDEF Load SDEF into QCS [CLINs must balance with RMS] Submit to RMS Draft Prompt Payment and Application for Payment Progress Cost Loaded Schedule Payment Received Internal Approval, Compliance, and Billing Process [Signed Prompt Payment and Pay Application]

22 Understanding SDEF Requirements Cost Loaded That is: Cost to the Government. Activity Coded That is: 10 specifically defined activity codes in ER USFG Section Paragraph Approved Project Schedule Use the approved Project Schedule to measure the progress of the work Make the schedule cost loaded and activity coded. The schedule will provide the basis for all progress payments.

23 Understanding the SDEF Requirements Standard Activity Codes USFG Section Paragraph Standard Activity Coding Dictionary Use the activity coding structure defined in the Standard Data Exchange Format (SDEF) in ER , Appendix A. This exact structure is mandatory, even if some fields are not used. The SDEF format is as follows: Activity Code Field Code Length Description 1 WRKP 3 Workers per Day 2 RESP 4 Responsible Party (e.g. GC, subcontractor, USACE) 3 AREA 4 Area of Work 4 MODF 6 Modification or REA number 5 BIDI 6 Bid Item (CLIN or SubCLIN) 6 PHAS 2 Phase of Work 7 CATW 1 Category of Work 8 FOW1 10 Feature of Work (used up to 10 characters in length) 9 FOW2 10 Feature of Work (used up to 20 characters in length) 10 FOW3 10 Feature of Work (used up to 30 characters in length)

24 Understanding the SDEF Requirements Standard Activity Codes USFG Section Paragraph Standard Activity Coding Dictionary These activity codes were originally defined for P3 which was a flat and finite length register. Therefore, all codes had to be Use the activity coding structure defined in the Standard Data Exchange Format defined (SDEF) in the in ER order , shown Appendix and A. with This code exact length structure as is specified. mandatory, even if some fields are not used. The SDEF format is as follows: Several Tips and Tricks for P6: The order Activity is no Code longer important, in fact you do not even need to define all Fieldof them. Code Length Description 1 The Max WRKP length of 3 the Code Workers ID per is still Dayimportant, except: 2 FOW RESP 1, 2, & 43 needs Responsible to be replaced Party (e.g. with GC, just subcontractor, FOW with a USACE) code value of 3 AREA 4 Area of Work 1 to 20 characters it is not the code value that gets converted to the 4 MODF 6 Modification or REA number SDEF, it will load up to 30 characters of the Code Value Description. 5 BIDI 6 Bid Item (CLIN or SubCLIN) 6 You can PHAS use the Hierarchical 2 Phase Activity of Work Code feature in P6 What gets 7 converted CATW to the 1 SDEF is Category simple of the Work code assigned at whatever level you 8 assign FOW1 it. 10 Feature of Work (used up to 10 characters in length) 9 FOW2 10 Feature of Work (used up to 20 characters in length) 10 FOW3 10 Feature of Work (used up to 30 characters in length)

25 Title Sub-Title

26 Understanding the SDEF Requirements First work day = NTP +1d 7 day no holiday calendar for activities contractually assigned calendar days. Use an appropriate work week calendar for each activity as you plan to work it. Identify Weather Sensitive Installation with a weather day calendar. Plan the work then work the plan. If you do not show non work periods you cannot claim as non work days in a time impact analysis. Calendars USFG Section Paragraph Scheduled Project Completion and Activity Calendars The first scheduled work period shall be the day after NTP is received by the Contractor. Activities may be assigned to a 7 day calendar when the contract assigns calendar day durations for the activity If the Contractor intends to perform physical work less than seven days per week, schedule the associated activities on a calendar with non work periods identified including weekends and holidays. Assign the Category of Work Code [CATW] Weather Sensitive Installation to those activities that are weather sensitive. Original durations must account for anticipated normal adverse weather. The Government will interpret all work periods not identified as non work periods on each calendar as meaning the Contractor intends to perform work during those periods.

27 Understanding the SDEF Requirements The SDEF Records ER Part 2 SDEF SPECIFICATION, Section 6. SDEF Organization: The SDEF shall consist of the following records provided in the exact sequence shown Below: Volume Record Mandatory First Line of File Project Record Mandatory Second Line of File Calendar Record(s) Mandatory One Record Min. (one record for each calendar) Holiday Record(s) Mandatory if Holidays Used (one record for each calendar) Activity Record(s) Mandatory Records (one for every activity) Precedence Record(s) Mandatory for Precedence (one record for each pred.) Unit Cost Record(s) Mandatory for Unit Costs (scheduling application specific) Progress Record(s) Mandatory Records (one for every activity) File End Record Mandatory Last Line of Disk/File SDEF Example

28 Thank you Q & A

29 Record Activity Act Start Act Finish Rem SDEF PROGRSS RECORDS Acty Cost Cost to ID ID Date Date Dur (budget) Date Materials PROG CNTP 4 Jun 12 4 Jun PROG D Jun 12 8 Jun PROG D Jun Jun PROG D Jun Jun PROG D Jun Jul PROG D Jul Jul PROG D Jul Jul PROG D Aug Aug PROG D Aug Aug PROG P Jul Jul PROG P Jul Jul PROG P Jul Aug PROG P Aug Aug PROG C Aug Aug PROG D Aug Aug PROG C Aug Aug PROG C Aug Aug PROG C Aug Aug PROG C Aug Sep Sep PROG C Sep 12 7 Sep Sep Sep PROG C Sep Sep 12 2 Nov 12 2 Nov PROG C Sep 12 5 Oct Sep Oct PROG C Oct 12 8 Oct Oct Oct PROG C Oct Oct Oct 12 1 Nov PROG C Oct Oct 12 2 Nov 12 2 Nov PROG CEND Oct Oct 12 2 Nov 12 2 Nov PROG D Jun Aug PROG C Jul Oct PROG P Aug Aug Stored Early Start Date Early Finish Date Late Start Date Late Finish Date Float Sign Total Float

30 SDEF ACTIVITY RECORDS Record Activity Acty Constraint Cal Hammock ID ID Activity Description Dur Date Type Code Code WRKP RESP AREA MODF BIDI PHAS CATW FOW ACTV CNTP Contract NTP GOVT PMO PM Z Project/Contract ACTV D1000 Prep/Submit Concept Design PRIM DEGN DE E Project/Contract ACTV D1010 Gov't Review Concept Design GOVT DEGN DE G Project/Contract ACTV D1020 Design Conf. Concept Design PRIM DEGN DE H Project/Contract ACTV D1030 Prep/Submit 100% Civil Design PRIM DEGN DE E Project/Contract ACTV D1040 Gov't Review 100% Civil Design GOVT DEGN DE G Project/Contract ACTV D1050 Design Conf. 100% Design PRIM DEGN DE H Project/Contract ACTV D1060 Prep/Submit IFC Civil Design PRIM DEGN DE E Project/Contract ACTV D1070 Gov't Review/Acceptance IFC Ci GOVT DEGN DE G Project/Contract ACTV P1000 Issue Civil/SWS Contract PRIM PROC PR P Storm Water System ACTV P1010 Prep/Submit SWS Submittal ULTY PROC PR P Storm Water System ACTV P1020 Gov't Review SWS Submittals GOVT PROC PR P Storm Water System ACTV P1030 Gov't Accptance SWS Submittals GOVT PROC PR A Storm Water System ACTV C1000 Civil and SWS Preparatory PRIM DRNG CN N Storm Water System ACTV D1080 Issue IFC Civil Design GOVT DEGN DE G Project/Contract ACTV C1010 Remove Fencing PRIM DRNG CN W Removal of Exsiting Structure ACTV C1020 Fill/Compact Sinkhole CVIL DRNG CN W Stabilization Methods ACTV C1030 Site Grading Drainage CVIL DRNG CN W Site Grading ACTV C1040 Install Storm Water System CVIL DRNG CN W Stabilization Methods ACTV C1050 Final Grading/Restore Disturbe CVIL DRNG CN W Plantings (Rack and Seed Grass ACTV C1060 Replace Fencing PRIM DRNG CN N Fencing ACTV C1070 Water/Estabish Grass PRIM DRNG TO N Planting Maintaince ACTV C1080 Airate and Overseed Grass PRIM DRNG TO N Planting Maintaince ACTV C1090 Water/Estabish Grass PRIM DRNG TO N Planting Maintaince ACTV C1100 Winterize Grass PRIM DRNG TO N Planting Maintaince ACTV CEND Contract End GOVT PMO PM Z Project/Contract ACTV D0000 Design Management/Support Staf 50 5 Y 0 PRIM DEGN DE E Project/Contract ACTV C0000 Construction Management/Suppor 4 5 Y 0 PRIM DRNG DE E Project/Contract ACTV P1040 Del. Fencing Customr Materials PRIM PROC PR W Removal of Exsiting Structure

31 myproject SDEF Example VOLM 1 PROJ 01SEP12 mypr My Backyard Project P 04JUN12 03NOV12 CLDR S NYYYYYN Standard 5 Day Workweek w/ Bas CLDR 1 NYYYYYN Standard 5 Day Workweek CLDR 5 NYYYYYN 5 day work week w/holidays CLDR 2 YNNNNNY Weekends/Holidays Only HOLI S 01SEP03 27NOV03 28NOV03 25DEC03 26DEC03 01JAN04 31MAY04 05JUL04 06SEP04 25NOV04 26NOV04 24DEC04 31DEC04 30MAY05 04JUL05 HOLI S 05SEP05 24NOV05 25NOV05 26DEC05 02JAN06 29MAY06 04JUL06 04SEP06 23NOV06 24NOV06 25DEC06 01JAN07 28MAY07 04JUL07 03SEP07 HOLI S 22NOV07 23NOV07 25DEC07 01JAN08 26MAY08 04JUL08 01SEP08 27NOV08 28NOV08 25DEC08 01JAN09 25MAY09 03JUL09 07SEP09 26NOV09 HOLI S 27NOV09 25DEC09 01JAN10 31MAY10 05JUL10 06SEP10 25NOV10 26NOV10 24DEC10 HOLI 5 01SEP03 27NOV03 28NOV03 25DEC03 26DEC03 01JAN04 31MAY04 05JUL04 06SEP04 25NOV04 26NOV04 24DEC04 31DEC04 30MAY05 04JUL05 HOLI 5 05SEP05 24NOV05 25NOV05 26DEC05 02JAN06 29MAY06 04JUL06 04SEP06 23NOV06 24NOV06 25DEC06 01JAN07 28MAY07 04JUL07 03SEP07 HOLI 5 22NOV07 23NOV07 25DEC07 01JAN08 26MAY08 04JUL08 01SEP08 27NOV08 28NOV08 25DEC08 01JAN09 25MAY09 03JUL09 07SEP09 26NOV09 HOLI 5 27NOV09 25DEC09 01JAN10 31MAY10 05JUL10 06SEP10 25NOV10 26NOV10 24DEC10 02JUL12 03SEP12 15OCT12 22NOV12 25DEC12 01JAN13 HOLI 5 18FEB13 27MAY13 04JUL13 ACTV CNTP Contract NTP GOVT PMO PM Z Project/Contract ACTV D1000 Prep/Submit Concept Design PRIM DEGN DE E Project/Contract ACTV D1010 Gov't Review Concept Design GOVT DEGN DE G Project/Contract ACTV D1020 Design Conf. Concept Design PRIM DEGN DE H Project/Contract ACTV D1030 Prep/Submit 100% Civil Design PRIM DEGN DE E Project/Contract ACTV D1040 Gov't Review 100% Civil Design GOVT DEGN DE G Project/Contract ACTV D1050 Design Conf. 100% Design PRIM DEGN DE H Project/Contract ACTV D1060 Prep/Submit IFC Civil Design PRIM DEGN DE E Project/Contract ACTV D1070 Gov't Review/Acceptance IFC Ci GOVT DEGN DE G Project/Contract ACTV P1000 Issue Civil/SWS Contract PRIM PROC PR P Storm Water System ACTV P1010 Prep/Submit SWS Submittal ULTY PROC PR P Storm Water System ACTV P1020 Gov't Review-SWS Submittals GOVT PROC PR P Storm Water System ACTV P1030 Gov't Accptance SWS Submittals GOVT PROC PR A Storm Water System ACTV C1000 Civil and SWS Preparatory PRIM DRNG CN N Storm Water System ACTV D1080 Issue IFC Civil Design GOVT DEGN DE G Project/Contract ACTV C1010 Remove Fencing PRIM DRNG CN W Removal of Exsiting Structure ACTV C1020 Fill/Compact Sinkhole CVIL DRNG CN W Stabilization Methods Page 1

32 myproject SDEF Example ACTV C1030 Site Grading - Drainage CVIL DRNG CN W Site Grading ACTV C1040 Install Storm Water System CVIL DRNG CN W Stabilization Methods ACTV C1050 Final Grading/Restore Disturbe CVIL DRNG CN W Plantings (Rack and Seed Grass ACTV C1060 Replace Fencing PRIM DRNG CN N Fencing ACTV C1070 Water/Estabish Grass PRIM DRNG TO N Planting Maintaince ACTV C1080 Airate and Overseed Grass PRIM DRNG TO N Planting Maintaince ACTV C1090 Water/Estabish Grass PRIM DRNG TO N Planting Maintaince ACTV C1100 Winterize Grass PRIM DRNG TO N Planting Maintaince ACTV CEND Contract End GOVT PMO PM Z Project/Contract ACTV D0000 Design Management/Support Staf 50 5 Y 0 PRIM DEGN DE E Project/Contract ACTV C0000 Construction Management/Suppor 4 5 Y 0 PRIM DRNG DE E Project/Contract ACTV P1040 Del. Fencing Customr Materials PRIM PROC PR W Removal of Exsiting Structure PRED D1000 CNTP C 1 PRED D1010 D1000 C 0 PRED D1020 D1010 C 0 PRED D1040 D1030 C 0 PRED D1050 D1040 C 0 PRED D1030 D1020 C 0 PRED D1060 D1050 C 0 PRED D1070 D1060 C 0 PRED P1000 D1030 S 0 PRED P1020 P1010 C 0 PRED P1030 P1020 C 0 PRED P1020 D1050 S 0 PRED P1030 D1070 S 0 PRED P1010 P1000 C 0 PRED D1080 D1070 C 0 PRED C1000 D1080 C 0 PRED C1000 P1030 C 0 PRED C1010 C1000 C 0 PRED C1020 C1010 C 0 PRED C1030 C1020 C 0 PRED C1040 C1030 S 0 PRED C1050 C1040 C 0 PRED C1050 C1030 C 0 Page 2

33 myproject SDEF Example PRED C1060 C1050 C 0 PRED C1070 C1050 C 0 PRED C1080 C1070 C 0 PRED C1090 C1080 C 0 PRED D0000 D1000 S 0 PRED D1080 D0000 F 0 PRED C1100 C1090 C 0 PRED CEND C1100 C 0 PRED C0000 D1040 S 0 PRED CEND C0000 F 0 PRED P1040 C1010 C 0 PRED C1060 P1040 C 0 UNIT D UNIT D UNIT D UNIT P UNIT D UNIT C UNIT C UNIT C UNIT C UNIT C UNIT C UNIT C UNIT C UNIT C UNIT C UNIT D UNIT P PROG CNTP 04JUN12 04JUN PROG D JUN12 08JUN PROG D JUN12 19JUN PROG D JUN12 20JUN PROG D JUN12 23JUL PROG D JUL12 31JUL PROG D JUL12 31JUL PROG D AUG12 13AUG PROG D AUG12 20AUG PROG P JUL12 25JUL PROG P JUL12 27JUL PROG P JUL12 10AUG PROG P AUG12 17AUG PROG C AUG12 23AUG PROG D AUG12 24AUG PROG C AUG12 23AUG PROG C AUG12 29AUG PROG C AUG12 31AUG PROG C AUG SEP12 17SEP Page 3

34 myproject SDEF Example PROG C SEP12 07SEP12 18SEP12 18SEP PROG C SEP12 10SEP12 02NOV12 02NOV PROG C SEP12 05OCT12 19SEP12 17OCT PROG C OCT12 08OCT12 18OCT12 18OCT PROG C OCT12 23OCT12 19OCT12 01NOV PROG C OCT12 24OCT12 02NOV12 02NOV PROG CEND OCT12 24OCT12 02NOV12 02NOV PROG D JUN12 15AUG PROG C JUL12 18OCT PROG P AUG12 24AUG END Page 4

SECTION PROJECT SCHEDULE 08/08

SECTION PROJECT SCHEDULE 08/08 SECTION 01 32 01.00 10 PROJECT SCHEDULE 08/08 PART 1 GENERAL 1.1 REFERENCES The publications listed below form a part of this specification to the extent referenced. The publications are referred to within

More information

Contents Cloud or On-Premises Content Introduction Data Dictionary... 23

Contents Cloud or On-Premises Content Introduction Data Dictionary... 23 P6 Data Dictionary Version 17 July 2017 Contents Cloud or On-Premises Content... 19 Introduction... 21 Data Dictionary... 23 % Allocation... 23 Access Level... 23 Access Time... 23 Accounting Variance...

More information

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR CRITICAL PATH METHOD NETWORK SCHEDULE

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR CRITICAL PATH METHOD NETWORK SCHEDULE MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR CRITICAL PATH METHOD NETWORK SCHEDULE C&T:JTL 1 of 6 C&T:APPR:JDC:PAL:07-24-02 FHWA:APPR:06-01-11 a. Description. In addition to the progress

More information

VIRGINIA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR SECTION 109 MEASUREMENT AND PAYMENT

VIRGINIA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR SECTION 109 MEASUREMENT AND PAYMENT SECTION 102.01 PREQUALIFICATION OF BIDDERS of the Specifications is amended as follows: The eighth paragraph is replaced by the following: When the Contractor's actual progress is more than 10 percent

More information

PROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA

PROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA This section is used for projects over $1,000,000 use other section if less than $1M SECTION 01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 SCOPE A. Preliminary Contract Schedule, Contract

More information

Cash & Liquidity The chart below highlights CTA s cash position at March 2018 compared to March 2017.

Cash & Liquidity The chart below highlights CTA s cash position at March 2018 compared to March 2017. To: Chicago Transit Authority Board From: Jeremy Fine, Chief Financial Officer Re: Financial Results for March 2018 Date: May 9, 2018 I. Summary CTA s financial results are $0.9 million favorable to budget

More information

Beginning Date: January 2016 End Date: June Managers in Zephyr: Benchmark: Morningstar Short-Term Bond

Beginning Date: January 2016 End Date: June Managers in Zephyr: Benchmark: Morningstar Short-Term Bond Beginning Date: January 2016 End Date: June 2018 Managers in Zephyr: Benchmark: Manager Performance January 2016 - June 2018 (Single Computation) 11200 11000 10800 10600 10400 10200 10000 9800 Dec 2015

More information

Beginning Date: January 2016 End Date: September Managers in Zephyr: Benchmark: Morningstar Short-Term Bond

Beginning Date: January 2016 End Date: September Managers in Zephyr: Benchmark: Morningstar Short-Term Bond Beginning Date: January 2016 End Date: September 2018 Managers in Zephyr: Benchmark: Manager Performance January 2016 - September 2018 (Single Computation) 11400 - Yorktown Funds 11200 11000 10800 10600

More information

Power Accountants Association Annual Meeting Potential Impacts from Oct 2015 Rate Change

Power Accountants Association Annual Meeting Potential Impacts from Oct 2015 Rate Change Power Accountants Association Annual Meeting Potential Impacts from Oct 2015 Rate Change Material Provided by: Chris Mitchell Chris Mitchell Management Consultants (CMMC) mail@chrismitchellmc.com 5/14/2015

More information

XML Publisher Balance Sheet Vision Operations (USA) Feb-02

XML Publisher Balance Sheet Vision Operations (USA) Feb-02 Page:1 Apr-01 May-01 Jun-01 Jul-01 ASSETS Current Assets Cash and Short Term Investments 15,862,304 51,998,607 9,198,226 Accounts Receivable - Net of Allowance 2,560,786

More information

FDD FIRM STORAGE SERVICE NORTHERN NATURAL GAS COMPANY

FDD FIRM STORAGE SERVICE NORTHERN NATURAL GAS COMPANY FDD FIRM STORAGE SERVICE NORTHERN NATURAL GAS COMPANY FIRM STORAGE SERVICE OPTIONS Northern s firm storage service is provided pursuant to the FDD Rate Schedule located in Northern s FERC Gas Tariff. The

More information

AACE International 48th Annual Meeting Washington, DC June 2004 DEVELOPING & MANAGING CONTIGENCY ON THE BASIS OF RISK. Robert Tichacek, P.E.

AACE International 48th Annual Meeting Washington, DC June 2004 DEVELOPING & MANAGING CONTIGENCY ON THE BASIS OF RISK. Robert Tichacek, P.E. AACE International 48th Annual Meeting Washington, DC June 2004 DEVELOPING & MANAGING CONTIGENCY ON THE BASIS OF RISK Robert Tichacek, P.E. Presentation Outline Review of Basic Project Risk Management

More information

VIRGINIA DEPARTMENT OF TRANSPORATION SPECIAL PROVISION FOR CPM PROGRESS SCHEDULE FOR CATEGORY IV PROJECTS

VIRGINIA DEPARTMENT OF TRANSPORATION SPECIAL PROVISION FOR CPM PROGRESS SCHEDULE FOR CATEGORY IV PROJECTS S108D00-0911 VIRGINIA DEPARTMENT OF TRANSPORATION SPECIAL PROVISION FOR CPM PROGRESS SCHEDULE FOR CATEGORY IV PROJECTS March 1, 2011 Section 103.06(e) Progress Schedule of the Specifications is deleted

More information

THURGOOD MARSHALL MIDDLE SCHOOL LYNN, MA

THURGOOD MARSHALL MIDDLE SCHOOL LYNN, MA THURGOOD MARSHALL MIDDLE SCHOOL LYNN, MA Monthly Project Update Report SEPTEMBER 2012 FS/SD DD CD Bidding Construction Closeout THURGOOD MARSHALL MIDDLE SCHOOL SEPTEMBER 2012 01 TASKS COMPLETED DURING

More information

Cash & Liquidity The chart below highlights CTA s cash position at March 2017 compared to March 2016.

Cash & Liquidity The chart below highlights CTA s cash position at March 2017 compared to March 2016. To: Chicago Transit Authority Board From: Jeremy Fine, Chief Financial Officer Re: Financial Results for March 2017 Date: May 10, 2017 I. Summary CTA s financial results are $0.6 million favorable to budget

More information

VIRGINIA DEPARTMENT OF TRANSPORATION SPECIAL PROVISION FOR CPM PROGRESS SCHEDULE FOR CATEGORY III PROJECTS

VIRGINIA DEPARTMENT OF TRANSPORATION SPECIAL PROVISION FOR CPM PROGRESS SCHEDULE FOR CATEGORY III PROJECTS S108C00-0911 VIRGINIA DEPARTMENT OF TRANSPORATION SPECIAL PROVISION FOR CPM PROGRESS SCHEDULE FOR CATEGORY III PROJECTS March 1, 2011 Section 103.06(e) Progress Schedule of the Specifications is deleted

More information

SECTION ARCHITECTURAL AND ENGINEERING CPM SCHEDULES

SECTION ARCHITECTURAL AND ENGINEERING CPM SCHEDULES SECTION 01 32 16.01 ARCHITECTURAL AND ENGINEERING CPM SCHEDULES PART 1- GENERAL 1.1 DESCRIPTION: The Architect/Engineer of Record (A/E) shall develop a Critical Path Method (CPM Schedule) plan and schedule

More information

Big Walnut Local School District

Big Walnut Local School District Big Walnut Local School District Monthly Financial Report for the month ended September 30, 2012 Prepared By: Felicia Drummey Treasurer BIG WALNUT LOCAL SCHOOL DISTRICT SUMMARY OF YEAR-TO-DATE FINANCIAL

More information

REQUEST FOR PROPOSAL

REQUEST FOR PROPOSAL REQUEST FOR PROPOSAL For Construction Manager as Constructor for Tri-North Middle School Response Due: April 2, 2018, 1:00 pm MCCSC Service Building 560 E. Miller Drive Bloomington, IN 47401. REQUEST FOR

More information

SUPPLEMENTAL SPECIFICATION CRITICAL PATH METHOD CONSTRUCTION SCHEDULES

SUPPLEMENTAL SPECIFICATION CRITICAL PATH METHOD CONSTRUCTION SCHEDULES March 1, 2007 SUPPLEMENTAL SPECIFICATION CRITICAL PATH METHOD CONSTRUCTION SCHEDULES General This supplemental specification addresses the Critical Path Method (CPM) construction schedule requirements

More information

(RISK.03) Integrated Cost and Schedule Risk Analysis: A Draft AACE Recommended Practice. Dr. David T. Hulett

(RISK.03) Integrated Cost and Schedule Risk Analysis: A Draft AACE Recommended Practice. Dr. David T. Hulett (RISK.03) Integrated Cost and Schedule Risk Analysis: A Draft AACE Recommended Practice Dr. David T. Hulett Author Biography David T. Hulett, Hulett & Associates, LLC Degree: Ph.D. University: Stanford

More information

Operating Reserves Educational Session Part B

Operating Reserves Educational Session Part B Operating Reserves Educational Session Part B Energy Market Uplift Senior Task Force September 17, 2013 Joseph Bowring Joel Romero Luna Operating Reserves Operating reserves can be grouped into five categories:

More information

Cash & Liquidity The chart below highlights CTA s cash position at July 2016 compared to July 2015.

Cash & Liquidity The chart below highlights CTA s cash position at July 2016 compared to July 2015. To: Chicago Transit Authority Board From: Jeremy Fine, Chief Financial Officer Re: Financial Results for July 2016 Date: September 14, 2016 I. Summary CTA s financial results are $0.4 million favorable

More information

Cash & Liquidity The chart below highlights CTA s cash position at January 2018 compared to January 2017.

Cash & Liquidity The chart below highlights CTA s cash position at January 2018 compared to January 2017. To: Chicago Transit Authority Board From: Jeremy Fine, Chief Financial Officer Re: Financial Results for January 2018 Date: March 14, 2018 I. Summary CTA s financial results are $1.7 million unfavorable

More information

The year to date is less than budget and prior year by 15.4 million and 11.6 million, respectively.

The year to date is less than budget and prior year by 15.4 million and 11.6 million, respectively. To: Chicago Transit Authority Board From: Jeremy Fine, Chief Financial Officer Re: Financial Results for September 2016 Date: November 16, 2016 I. Summary CTA s financial results are $0.3 million unfavorable

More information

Cash & Liquidity The chart below highlights CTA s cash position at June 2018 compared to June 2017.

Cash & Liquidity The chart below highlights CTA s cash position at June 2018 compared to June 2017. To: Chicago Transit Authority Board From: Jeremy Fine, Chief Financial Officer Re: Financial Results for June 2018 Date: August 15, 2018 I. Summary CTA s financial results are unfavorable to budget for

More information

Billing and Collection Agent Report For period ending April 30, To NANC

Billing and Collection Agent Report For period ending April 30, To NANC Billing and Collection Agent Report For period ending April 30, 2011 To NANC May 17, 2011 STATEMENT OF FINANCIAL POSITION April 30, 2011 Assets Cash Balance in bank account $ 1,824,073 Receivable from

More information

Budget Manager Meeting. February 20, 2018

Budget Manager Meeting. February 20, 2018 Budget Manager Meeting February 20, 2018 Meeting Agenda DISCUSSION DRAFT NOT FOR DISTRIBUTION Budget Office Current Year Forecast Process Endowment Payout Control Charts FY19 Target Meetings Delphi Project

More information

Integrated Cost Schedule Risk Analysis Using the Risk Driver Approach

Integrated Cost Schedule Risk Analysis Using the Risk Driver Approach Integrated Cost Schedule Risk Analysis Using the Risk Driver Approach Qatar PMI Meeting February 19, 2014 David T. Hulett, Ph.D. Hulett & Associates, LLC 1 The Traditional 3-point Estimate of Activity

More information

Cash & Liquidity The chart below highlights CTA s cash position at February 2017 compared to February 2016.

Cash & Liquidity The chart below highlights CTA s cash position at February 2017 compared to February 2016. To: Chicago Transit Authority Board From: Jeremy Fine, Chief Financial Officer Re: Financial Results for February 2017 Date: April 5, 2017 I. Summary CTA s financial results are $0.3 million favorable

More information

PRINTED OR COPIED DOUBLE-SIDED ON POSTCONSUMER FIBER CONTENT PAPER (JUL 2013)

PRINTED OR COPIED DOUBLE-SIDED ON POSTCONSUMER FIBER CONTENT PAPER (JUL 2013) NNC14CA39C Clause Number Clause Date Clause Title 1852.216-73 (DEC 1991) ESTIMATED COST AND COST SHARING 1852.232-81 (JUN 1990) CONTRACT FUNDING 1852.211-70 (SEP 2005) PACKAGING, HANDLING, AND TRANSPORTATION

More information

SECTION PROJECT SCHEDULES (SMALL PROJECTS DESIGN/BID/BUILD)

SECTION PROJECT SCHEDULES (SMALL PROJECTS DESIGN/BID/BUILD) SECTION 01 32 16.15 PROJECT SCHEDULES (SMALL PROJECTS DESIGN/BID/BUILD) PART 1- GENERAL 1.1 DESCRIPTION: A. The Contractor shall develop a Critical Path Method (CPM) plan and schedule demonstrating fulfillment

More information

Development of Economy and Financial Markets of Kazakhstan

Development of Economy and Financial Markets of Kazakhstan Development of Economy and Financial Markets of Kazakhstan National Bank of Kazakhstan Macroeconomic development GDP, real growth, % 116 112 18 14 1 113,5 11,7 216,7223,8226,5 19,8 19,8 19,3 19,619,7 199,

More information

Cash & Liquidity The chart below highlights CTA s cash position at December 2017 compared to December 2016.

Cash & Liquidity The chart below highlights CTA s cash position at December 2017 compared to December 2016. To: Chicago Transit Authority Board From: Jeremy Fine, Chief Financial Officer Re: Financial Results for December 2017 Date: February 14, 2018 I. Summary CTA s financial results are $4.7 million favorable

More information

Billing and Collection Agent Report For period ending April 30, To FCC Contract Oversight Sub Committee

Billing and Collection Agent Report For period ending April 30, To FCC Contract Oversight Sub Committee Billing and Collection Agent Report For period ending April 30, 2018 To FCC Contract Oversight Sub Committee May 10, 2018 NANPA FUND STATEMENT OF FINANCIAL POSITION April 30, 2018 Assets Cash in bank $

More information

(17) Delete Section J, Attachment 6: Past Performance Tables

(17) Delete Section J, Attachment 6: Past Performance Tables PAGE 2 of 14 The purpose of this modification is to: (1) Correct the Clinger-Cohen Act citation under Section B.2 AUTHORITY; (2) Clarify the CAF formula and make it optional to include CAF in Loaded Hourly

More information

Cash & Liquidity The chart below highlights CTA s cash position at August 2018 compared to August 2017.

Cash & Liquidity The chart below highlights CTA s cash position at August 2018 compared to August 2017. To: Chicago Transit Authority Board From: Jeremy Fine, Chief Financial Officer Re: Financial Results for August 2018 Date: October 10, 2018 I. Summary CTA s financial results are favorable to budget for

More information

Billing and Collection Agent Report For period ending January 31, To B&C Working Group

Billing and Collection Agent Report For period ending January 31, To B&C Working Group Billing and Collection Agent Report For period ending January 31, 2018 To B&C Working Group February 5, 2018 NANPA FUND STATEMENT OF FINANCIAL POSITION January 31, 2018 Assets Cash in bank $ 4,550,060

More information

U.S. Natural Gas Storage Charts

U.S. Natural Gas Storage Charts U.S. Natural Gas Storage Charts BMO Capital Markets Commodity Products Group November 26, 214 Total U.S. Natural Gas in Storage 5, Total Stocks This Week 3432 4, 3, 2, 1, Reported On: November 26, 214

More information

Cash & Liquidity The chart below highlights CTA s cash position at September 2017 compared to September 2016.

Cash & Liquidity The chart below highlights CTA s cash position at September 2017 compared to September 2016. To: Chicago Transit Authority Board From: Jeremy Fine, Chief Financial Officer Re: Financial Results for September 2017 Date: November 15, 2017 I. Summary CTA s financial results are $7.7 million favorable

More information

Session no. G I WON A CONSTRUCTION CONTRACT, NOW WHAT DO I DO? (Sequel)

Session no. G I WON A CONSTRUCTION CONTRACT, NOW WHAT DO I DO? (Sequel) Session no. G I WON A CONSTRUCTION CONTRACT, NOW WHAT DO I DO? (Sequel) Dennis Chung P. E. Resident Engineer Schofield Barracks Area Office Ph: 655-1508 U.S. Army Corps of Engineers 20 May 2010 US Army

More information

EARNED VALUE AS A RISK ASSESSMENT TOOL

EARNED VALUE AS A RISK ASSESSMENT TOOL EARNED VALUE AS A RISK ASSESSMENT TOOL Introduction Earned Value Definition: Employment of a Single Management Control System Providing Accurate, Consistent, Reliable, and Timely Data That Management at

More information

Integrated Cost Schedule Risk Analysis Using the Risk Driver Approach

Integrated Cost Schedule Risk Analysis Using the Risk Driver Approach Integrated Cost Schedule Risk Analysis Using the Risk Driver Approach David T. Hulett, Ph.D. Hulett & Associates 24rd Annual International IPM Conference Bethesda, Maryland 29 31 October 2012 (C) 2012

More information

2018 Financial Management Classes

2018 Financial Management Classes 2018 Financial Management Classes MONEY MANAGEMENT CLASS/BANKING OPERATONS (1ST & 3RD FRIDAY) INVESTING BASICS (2ND FRIDAY) CREDIT MANAGEMENT BLENDED RETIREMENT SYSTEM/THRIFT SAVINGS PLAN (4TH FRIDAY)

More information

Title: COST CONTRACT CONTINUOUS MAINTENANCE AND EMERGENT WORK REPORT. Number: DI-FNCL Approval Date:

Title: COST CONTRACT CONTINUOUS MAINTENANCE AND EMERGENT WORK REPORT. Number: DI-FNCL Approval Date: DATA ITEM DESCRIPTION Title: COST CONTRACT CONTINUOUS MAINTENANCE AND EMERGENT WORK REPORT Number: Approval Date: 20091026 AMSC Number: N9105 Limitation: DTIC Applicable: N/A GIDEP Applicable: N/A Office

More information

General Fund Revenue

General Fund Revenue Millions Percent of Kathy Steinert, Director of Fiscal Services Phone: 541.923.8927 145 SE Salmon Ave Redmond, OR 97756 kathy.steinert@redmond.k12.or.us Date: May 23, 2014 To: Redmond School District Board

More information

Portfolio Project Performance Reporting. Client Case Study

Portfolio Project Performance Reporting. Client Case Study Portfolio Project Performance Reporting Client Case Study MetaPM 2016 The Challenge MetaPM s client need a mechanism to enable them to balance, reprioritise and provide recommendations (backed up by data)

More information

Business & Financial Services December 2017

Business & Financial Services December 2017 Business & Financial Services December 217 Completed Procurement Transactions by Month 2 4 175 15 125 1 75 5 2 1 Business Days to Complete 25 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 217 Procurement

More information

Looking at a Variety of Municipal Valuation Metrics

Looking at a Variety of Municipal Valuation Metrics Looking at a Variety of Municipal Valuation Metrics Muni vs. Treasuries, Corporates YEAR MUNI - TREASURY RATIO YEAR MUNI - CORPORATE RATIO 200% 80% 175% 150% 75% 70% 65% 125% Average Ratio 0% 75% 50% 60%

More information

Spheria Australian Smaller Companies Fund

Spheria Australian Smaller Companies Fund 29-Jun-18 $ 2.7686 $ 2.7603 $ 2.7520 28-Jun-18 $ 2.7764 $ 2.7681 $ 2.7598 27-Jun-18 $ 2.7804 $ 2.7721 $ 2.7638 26-Jun-18 $ 2.7857 $ 2.7774 $ 2.7690 25-Jun-18 $ 2.7931 $ 2.7848 $ 2.7764 22-Jun-18 $ 2.7771

More information

CONSTRUCTION CLAIMS MANAGEMENT & EOT DELAYS ANALYSIS. Presented by : Hany Ismail, MSc, PMP

CONSTRUCTION CLAIMS MANAGEMENT & EOT DELAYS ANALYSIS. Presented by : Hany Ismail, MSc, PMP CONSTRUCTION CLAIMS MANAGEMENT & EOT DELAYS ANALYSIS Presented by : Hany Ismail, MSc, PMP CONSTRUCTION CLAIMS MANAGEMENT EOT DELAYS ANALYSIS LESSON 7 TIME IMPACT WINDOW DELAY ANALYSIS TECHNIQUE TIME IMPACT

More information

Beginning Date: January 2016 End Date: February Managers in Zephyr: Benchmark: Morningstar Short-Term Bond

Beginning Date: January 2016 End Date: February Managers in Zephyr: Benchmark: Morningstar Short-Term Bond Beginning Date: January 2016 End Date: February 2018 Managers in Zephyr: Benchmark: Manager Performance January 2016 - February 2018 (Single Computation) 11200 11000 10800 10600 10400 10200 10000 9800

More information

Using projections to manage your programs

Using projections to manage your programs Using projections to manage your programs To project total provider reimbursements To do what ifs based on caseloads or other metrics To project amounts of admin & support available for spending Based

More information

Fiscal Year 2010 Columbia Generating Station Annual Operating Budget

Fiscal Year 2010 Columbia Generating Station Annual Operating Budget Fiscal Year 2010 Columbia Generating Station Annual Operating Budget Table of Contents Table Page Summary 3 Key Assumptions/Qualifications 4 Memorandum of Agreement (MOA) Table 1 5 Columbia Station Costs

More information

EARNED VALUE MANAGEMENT. Is it worth the effort?

EARNED VALUE MANAGEMENT. Is it worth the effort? EARNED VALUE MANAGEMENT Is it worth the effort? Session Objectives Examples of earned value in use. Why don t more Project Managers use EMV? Road Map to EVA Maturity? What you need to know? How is our

More information

Managing Multiple Funding Streams

Managing Multiple Funding Streams Managing Multiple Funding Streams CAPLAW 2010 National Training Conference June 17, 2010 4:00 p.m. 5:30 p.m. Savannah, GA Marjorie Lombard Director, Finance Action for Boston Community Development 178

More information

Purpose: The purpose of this modification is to incorporate updates to all Seaport e Contracts.

Purpose: The purpose of this modification is to incorporate updates to all Seaport e Contracts. Page 1 of 11 Modification Details Purpose: The purpose of this modification is to incorporate updates to all Seaport e Contracts. 1. Make the following Changes in Section G: a. ADD HQ G-2-0005 Payment

More information

2 nd Topic X: Budgets

2 nd Topic X: Budgets Date:02/09-12/2015 2 nd Class Objective: Apply the concept to model exponential growth and decay. Apply the concept to visualize and interpret a budget using a pie chart, a bar graph, and a line graph

More information

N G-0001 Clause Number Clause Date Clause Title (OCT 2005) PACKAGING AND MARKING OF REPORTS (NAVAIR) (JUN 1998)

N G-0001 Clause Number Clause Date Clause Title (OCT 2005) PACKAGING AND MARKING OF REPORTS (NAVAIR) (JUN 1998) N00421-14-G-0001 Clause Number Clause Date Clause Title 5252.247-9507 (OCT 2005) PACKAGING AND MARKING OF REPORTS 5252.247-9508 (JUN 1998) PROHIBITED PACKING MATERIALS 5252.247-9509 (JUL 1998) PRESERVATION,

More information

DALLAS COUNTY DISTRICT COURT ADMINISTRATION

DALLAS COUNTY DISTRICT COURT ADMINISTRATION DALLAS COUNTY DISTRICT COURT ADMINISTRATION April 14, 2009 BRIEFING MEMORANDUM TO: FROM: Honorable Commissioners Court Duane Allen Gallup ADR Coordinator SUBJECT: ADR Program & Dispute Mediation Services

More information

Large Commercial Rate Simplification

Large Commercial Rate Simplification Large Commercial Rate Simplification Presented to: Key Account Luncheon Red Lion Hotel Presented by: Mark Haddad Assistant Director/CFO October 19, 2017 Most Important Information First There is no rate

More information

P6 Data Dictionary Release 8.3

P6 Data Dictionary Release 8.3 P6 Data Dictionary Release 8.3 March 2013 Legal Notices Oracle Primavera P6 Data Dictionary Copyright 1999, 2013, Oracle and/or its affiliates. All rights reserved. Oracle and Java are registered trademarks

More information

Quarterly Summary Report

Quarterly Summary Report Quarterly Summary Report Produced by: Edition 11 March 2018 Connect Agent Hosted Dinner Thursday 21st June 18:00-21:30 Rockcliffe Hall, Darlington Join the mia, directors and booking staff from a selection

More information

GCS 224 Surviving DCAA Audits with GCS Premier. Presented by: Nicole Mitchell, Aronson & Company

GCS 224 Surviving DCAA Audits with GCS Premier. Presented by: Nicole Mitchell, Aronson & Company GCS 224 Surviving DCAA Audits with GCS Premier Presented by: Nicole Mitchell, Aronson & Company Agenda Government Contract Audits and the Role of DCAA and DCMA Basic Attributes of a Government Approved

More information

David T. Hulett, Ph.D, Hulett & Associates, LLC # Michael R. Nosbisch, CCC, PSP, Project Time & Cost, Inc. # 28568

David T. Hulett, Ph.D, Hulett & Associates, LLC # Michael R. Nosbisch, CCC, PSP, Project Time & Cost, Inc. # 28568 David T. Hulett, Ph.D, Hulett & Associates, LLC # 27809 Michael R. Nosbisch, CCC, PSP, Project Time & Cost, Inc. # 28568 Integrated Cost-Schedule Risk Analysis 1 February 25, 2012 1 Based on AACE International

More information

Voya Indexed Universal Life-Protector

Voya Indexed Universal Life-Protector calculation examples Values as of 07/28/2018 Voya ed Universal Life-Protector Issued by Security Life of Denver Insurance Company Required training! VFA Registered Representatives must review the Required

More information

(APR 1984) Gratuities (MAY 2014) Covenant Against Contingent Fees (SEP 2006) Restrictions On Subcontractor Sales To The

(APR 1984) Gratuities (MAY 2014) Covenant Against Contingent Fees (SEP 2006) Restrictions On Subcontractor Sales To The N00019-18-C-1007 Clause Number Date Title 52.246-15 (APR 1984) Certificate of Conformance 5252.223-9502 (APR 2009) HAZARDOUS MATERIAL (NAVAIR) 5252.247-9507 (OCT 2005) PACKAGING AND MARKING OF REPORTS

More information

Factor Leave Accruals. Accruing Vacation and Sick Leave

Factor Leave Accruals. Accruing Vacation and Sick Leave Factor Leave Accruals Accruing Vacation and Sick Leave Factor Leave Accruals As part of the transition of non-exempt employees to biweekly pay, the UC Office of the President also requires standardization

More information

Foundations of Investing

Foundations of Investing www.edwardjones.com Member SIPC Foundations of Investing 1 5 HOW CAN I STAY ON TRACK? 4 HOW DO I GET THERE? 1 WHERE AM I TODAY? MY FINANCIAL NEEDS 3 CAN I GET THERE? 2 WHERE WOULD I LIKE TO BE? 2 Develop

More information

Simple Interest. S.Y.Tan. 1.1 Simple Interest

Simple Interest. S.Y.Tan. 1.1 Simple Interest Simple Interest Interest (I) a benefit in the form of a fee that lender received for letting borrower use of his money Origin date (O.D.) the date on which the borrowed money is received by the borrower

More information

Section 6621 of the Internal Revenue Code establishes the interest rates on

Section 6621 of the Internal Revenue Code establishes the interest rates on Part 1 Section 6621.--Determination of Rate of Interest 26 CFR 301.6621-1: Interest rate. Rev. Rul. -32 Section 6621 of the Internal Revenue Code establishes the interest rates on overpayments and underpayments

More information

Distribution Group Study Process. August 26, 2014

Distribution Group Study Process. August 26, 2014 Distribution Group Study Process August 26, 2014 Agenda Overview Applying for DGSP DGSP Interconnection Process Applicability and Utility Contacts Questions 2 Process Overview Open Window Period Evaluation

More information

Billing and Collection Agent Report For period ending January 31, To NANC

Billing and Collection Agent Report For period ending January 31, To NANC Billing and Collection Agent Report For period ending January 31, 2016 To NANC February 4, 2016 NANPA FUND STATEMENT OF FINANCIAL POSITION JANUARY 31, 2016 Assets Cash Balance in bank account $ 3,587,973

More information

Section 6621(c) provides that for purposes of interest payable under 6601 on any large corporate underpayment, the underpayment

Section 6621(c) provides that for purposes of interest payable under 6601 on any large corporate underpayment, the underpayment Section 6621. Determination of Interest Rate 26 CFR 301.6621 1: Interest rate. Interest rates; underpayments and overpayments. The rate of interest determined under section 6621 of the Code for the calendar

More information

DEPARTMENT OF ADMINISTRATIVE SERVICES PURCHASING COUNTY OF MERCED REQUEST FOR PROPOSAL NUMBER 6552 FOR

DEPARTMENT OF ADMINISTRATIVE SERVICES PURCHASING COUNTY OF MERCED REQUEST FOR PROPOSAL NUMBER 6552 FOR Issue Date: February 10, 2011 DEPARTMENT OF ADMINISTRATIVE SERVICES PURCHASING COUNTY OF MERCED REQUEST FOR PROPOSAL NUMBER 6552 FOR Mark A. Cowart Chief Information Officer 2222 M Street Merced, CA 95340

More information

ORANGE UNIFIED SCHOOL DISTRICT Measure S Bond Program September 2017 Monthly Progress Report

ORANGE UNIFIED SCHOOL DISTRICT Measure S Bond Program September 2017 Monthly Progress Report ORANGE UNIFIED SCHOOL DISTRICT Measure S Bond Program September 2017 Monthly Progress Report PERIOD COVERED: September 1 30, 2017 FISCAL YEAR FY 2017 2018 PROGRESS REPORT NO. PR 03 1718 003 PREPARED BY:

More information

SELF-STORAGE FOR SALE

SELF-STORAGE FOR SALE PURCHASE PRICE: $495,000 CAP RATE: 8.68% OCCUPANCY: 86.4% NOI: $42,973 LOT SIZE: 1.462ac (combined) BLDG CLASS: C OVERVIEW Multi-building storage facility in a rapidly growing area. The land offers over

More information

Review of Registered Charites Compliance Rates with Annual Reporting Requirements 2016

Review of Registered Charites Compliance Rates with Annual Reporting Requirements 2016 Review of Registered Charites Compliance Rates with Annual Reporting Requirements 2016 October 2017 The Charities Regulator, in accordance with the provisions of section 14 of the Charities Act 2009, carried

More information

SECTION NETWORK ANALYSIS SCHEDULES (DESIGN-BUILD ONLY)

SECTION NETWORK ANALYSIS SCHEDULES (DESIGN-BUILD ONLY) SECTION 01 32 16.16 NETWORK ANALYSIS SCHEDULES (DESIGN-BUILD ONLY) PART 1- GENERAL 1.1 DESCRIPTION: SPEC WRITER NOTES: 1. Coordinate this Design-Build Specification with FAR 52.232, VAAR 852.236 and Section

More information

Proving and Tracking Damages of your Claim

Proving and Tracking Damages of your Claim Proving and Tracking Damages of your Claim J. Mark Dungan October 6, 2017 1 Schedules: Back to Basics I. CPM Scheduling Basics II. The Baseline Schedule III. The Schedule Update IV. Delay Analysis V. Proving

More information

CONTINUOUS SETTLEMENT AND THE ROLE OF KPEI SECURITIES LENDING Providing Intermediated Financing Methods To Set A New Business Risks

CONTINUOUS SETTLEMENT AND THE ROLE OF KPEI SECURITIES LENDING Providing Intermediated Financing Methods To Set A New Business Risks CONTINUOUS SETTLEMENT AND THE ROLE OF KPEI SECURITIES LENDING Providing Intermediated Financing Methods To Set A New Business Risks By: Hoesen President Director KPEI (Indonesia Central Counter Party)

More information

Review of Membership Developments

Review of Membership Developments RIPE Network Coordination Centre Review of Membership Developments 7 October 2009/ GM / Lisbon http://www.ripe.net 1 Applications development RIPE Network Coordination Centre 140 120 100 80 60 2007 2008

More information

Statement of Revenues, Expenses, and Changes in Net Position (Income Statement) Page 4

Statement of Revenues, Expenses, and Changes in Net Position (Income Statement) Page 4 M E M O R A N D U M EUGENE WATER & ELECTRIC BOARD TO: FROM: DATE: August 26, 2016 SUBJECT: OBJECTIVE: Commissioners Simpson, Helgeson, Manning, Mital and Brown Sue Fahey, CFO; Susan Eicher, Accounting

More information

Infor LN Project User Guide for Project Estimation

Infor LN Project User Guide for Project Estimation Infor LN Project User Guide for Project Estimation Copyright 2015 Infor Important Notices The material contained in this publication (including any supplementary information) constitutes and contains confidential

More information

DOCUMENT SCHEDULING OF WORK PART 1 GENERAL 1.1 RELATED DOCUMENTS AND PROVISIONS

DOCUMENT SCHEDULING OF WORK PART 1 GENERAL 1.1 RELATED DOCUMENTS AND PROVISIONS DOCUMENT 01 32 13 PART 1 GENERAL 1.1 RELATED DOCUMENTS AND PROVISIONS All Contract Documents should be reviewed for applicable provisions related to the provisions in this document, including without limitation:

More information

Fiscal Year 2018 Project 1 Annual Budget

Fiscal Year 2018 Project 1 Annual Budget Fiscal Year 2018 Project 1 Annual Budget Table of Contents Table Page Summary 3 Summary of Costs Table 1 4 Treasury Related Expenses Table 2 5 Summary of Full Time Equivalent Table 3 6 Positions Cost-to-Cash

More information

2009 Reassessment As Impacted by Senate Bill 711

2009 Reassessment As Impacted by Senate Bill 711 Saint Louis County 2009 Reassessment As Impacted by Senate Bill 711 Impacts of SB711 on the 2009 Reassessment Plan The County must notify property owners of changes in the projected tax liability resulting

More information

APPLICABLE COMMERCIAL PROVISIONS WHEN SOLICITATION OR PURCHASE ORDER IS IN SUPPORT OF A GOVERNMENT CONTRACT:

APPLICABLE COMMERCIAL PROVISIONS WHEN SOLICITATION OR PURCHASE ORDER IS IN SUPPORT OF A GOVERNMENT CONTRACT: APPLICABLE COMMERCIAL PROVISIONS WHEN SOLICITATION OR PURCHASE ORDER IS IN SUPPORT OF A GOVERNMENT CONTRACT: General Provisions and Certifications for Government Contracts: The following clauses are applicable

More information

Monthly Trading Report Trading Date: May Monthly Trading Report May 2018

Monthly Trading Report Trading Date: May Monthly Trading Report May 2018 Trading Date: May 8 Monthly Trading Report May 8 Trading Date: May 8 Figure : May 8 (% change over previous month) % Major Market Indicators 9 8 Figure : Summary of Trading Data USEP () Daily Average Daily

More information

GPs for COST REIMBURSABLE SUBCONTRACTS

GPs for COST REIMBURSABLE SUBCONTRACTS GPs for COST REIMBURSABLE SUBCONTRACTS The FAR and DEAR clauses listed in this Exhibit, which are located in Chapters 1 and 9 of CFR Title 48 and available at http://www.gpo.gov/fdsys/ are hereby incorporated

More information

P305 POST IMPLEMENTATION REVIEW

P305 POST IMPLEMENTATION REVIEW Public P35 POST IMPLEMENTATION REVIEW Webinar 16 March 217 Emma Tribe Who we are Presenter Emma Tribe Market Analyst Answering questions Roger Harris David Thomas What I m going to cover Analysis and information

More information

Questions to Consider When You Implement Oracle Assets

Questions to Consider When You Implement Oracle Assets Questions to Consider When You Implement Oracle Assets Cindy Cline Cline Consulting and Training Solutions, LLC During the implementation of Oracle Assets, several issues will arise and numerous decisions

More information

PASSENGER REJECTION REDUCTION INITIATIVE KIRK PEREIRA. 24 th April 2018

PASSENGER REJECTION REDUCTION INITIATIVE KIRK PEREIRA. 24 th April 2018 PASSENGER REJECTION REDUCTION INITIATIVE KIRK PEREIRA 24 th April 2018 WHAT IS THIS PROJECT ABOUT? Well we are not going into that again this year! Nearly everyone in this room knows about the project

More information

Billing and Collection Agent Report For period ending August 31, 2016 To B&C Working Group September 15, 2016

Billing and Collection Agent Report For period ending August 31, 2016 To B&C Working Group September 15, 2016 Billing and Collection Agent Report For period ending August 31, 2016 To B&C Working Group September 15, 2016 Welch LLP - Chartered Professional Accountants 123 Slater Street, 3 rd floor, Ottawa, ON K1P

More information

2017 Fund holidays for Vanguard Investments Series plc

2017 Fund holidays for Vanguard Investments Series plc 2017 Fund holidays for Vanguard Investments Series plc Vanguard Investment Series Plc (Irish-domiciled) *Effective 3 March 2014, Vanguard U.S. Opportunities Fund is closed to all new accounts; existing

More information

Project Risk Analysis. Neil Dunkerley 17 th May 2012

Project Risk Analysis. Neil Dunkerley 17 th May 2012 Project Risk Analysis Neil Dunkerley 17 th May 2012 About EC Harris EC Harris is a leading global Built Asset Consultancy, helping clients make the most from their investment and expenditure in built assets.

More information

Supplemental Terms and Conditions

Supplemental Terms and Conditions FEDERAL ACQUISITION REGULATIONS (FAR), DEPARTMENT OF DEFENCE FAR SUPPLEMENT (DFARS), NATIONAL AERONAUICS and SPACE ADMINISTRATION (NASA) FAR SUPPLEMENT. The following clauses set forth in the FAR and DFARS

More information

HIPIOWA - IOWA COMPREHENSIVE HEALTH ASSOCIATION Unaudited Balance Sheet As of July 31

HIPIOWA - IOWA COMPREHENSIVE HEALTH ASSOCIATION Unaudited Balance Sheet As of July 31 Unaudited Balance Sheet As of July 31 Total Enrollment: 407 Assets: Cash $ 9,541,661 $ 1,237,950 Invested Cash 781,689 8,630,624 Premiums Receivable 16,445 299,134 Prepaid 32,930 34,403 Assessments Receivable

More information

HUD NSP-1 Reporting Apr 2010 Grantee Report - New Mexico State Program

HUD NSP-1 Reporting Apr 2010 Grantee Report - New Mexico State Program HUD NSP-1 Reporting Apr 2010 Grantee Report - State Program State Program NSP-1 Grant Amount is $19,600,000 $9,355,381 (47.7%) has been committed $4,010,874 (20.5%) has been expended Grant Number HUD Region

More information

Historical Pricing PJM COMED, Around the Clock. Cal '15 Cal '16 Cal '17 Cal '18 Cal '19 Cal '20 Cal '21 Cal '22

Historical Pricing PJM COMED, Around the Clock. Cal '15 Cal '16 Cal '17 Cal '18 Cal '19 Cal '20 Cal '21 Cal '22 $50 Historical Pricing PJM COMED, Around the Clock $48 $46 $44 $42 $40 $38 $36 $34 $32 $30 $28 $26 Cal '15 Cal '16 Cal '17 Cal '18 Cal '19 Cal '20 Cal '21 Cal '22 The information presented above was gathered