CONSTRUCTION CLAIMS MANAGEMENT & EOT DELAYS ANALYSIS. Presented by : Hany Ismail, MSc, PMP
|
|
- Darrell Hoover
- 6 years ago
- Views:
Transcription
1 CONSTRUCTION CLAIMS MANAGEMENT & EOT DELAYS ANALYSIS Presented by : Hany Ismail, MSc, PMP
2 CONSTRUCTION CLAIMS MANAGEMENT EOT DELAYS ANALYSIS LESSON 7 TIME IMPACT WINDOW DELAY ANALYSIS TECHNIQUE TIME IMPACT WINDOW ANALYSIS
3 Agenda Introduction. Why is TIA preferred technique? Analysis Technique Analysis Technique Steps Smart s Time Periods
4 Introduction Time Impact Analysis Technique is Actual Based Approach Which depends on the actual consequence and dates happened in the site during the execution not only the planning schedule. TIA is widely recognized by the construction industry as the most accepted method to quantify schedule delay. In this method the analyst develops and adds a model of the change to an approved schedule to quantify the delay to project completion
5 TIA is preferred delay analysis technique TIA is preferred delay analysis technique for the following reasons it allows assessment of the actual state of progress at the time the delay event occurred. the responsibility for delay prior to the impact of the delaying event is not material to the calculation of the effect of the delaying event itself. It determines whether the delay event impacted the critical path. The exact impact of the delay event can be calculated.
6 Analysis Technique analysis is a time impact technique which focus on the impact of delays in specific periods of time, identifying gains or losses ( delays and recovery ) to the actual critical and sub-critical paths as they occur with each period of time. The project life cycle is divided into a series of consecutive time s.
7 Analysis Technique Cont For Each window - Each window is analyzed to identify the activities that were impacted, delay or recovery and the results are investigated to identify the events that caused the deviation in progress. - Analysis steps
8 Technique Analysis Steps Step 1 : Incorporate delay events that have been occurred in the period Step 2 : Establish the impact on time for Completion.
9 Technique Analysis Steps Step 3 : Update the impacted programme with progress with in the window period. Construction Claims Management & EOT Delay Analysis Step 4 : Establish the impact on the Time for Completion. D1 : Impact delay period due to Employer Delay Events D2 : Impact delay period due to Contactor Delays from the update.
10 CONSTRUCTION CLAIMS MANAGEMENT EOT DELAYS ANALYSIS CASE STUDY BANK XYZ PROJECT
11 Technique Case study General Information Project Planned Start Date : 12,March,2012. Project Planned Finish Date : 22,April,. Available Updates Programme : 4 Programme
12 Technique Case study- 0 Start (1) Finish (2) Duration (3) = 2-1 Prog. Source Programme Project Finish date Contractor Delay Employer Total Entitlemen t P0 Appr. Baseline A.01 22,April, W0 31 P1 P0+Delay Events 13,May, P2 P1+Progress update on DD 14,May, Total Entitlement
13 Technique Case study- 1 Start (1) Finish (2) Duration (3) = 2-1 Prog. Source Programme Project Finish date Contractor Delay Employer Total Entitlemen t P3 Approved P2 14,May, W1 264 P4 P3+Delay Events 25,May, P5 P4+Progress update on DD 3,Jun, Total Entitlement
14 Technique Case study- 2 Start (1) Finish (2) Duration (3) = 2-1 Prog. Source Programme Project Finish date Contractor Delay Employer Total Entitlemen t P6 Approved P5 3,Jun, W2 264 P7 P6+Delay Events 9,July, P8 P7+Progress update on DD 21,July, Total Entitlement
15 Technique Case study- 3 Start (1) Finish (2) Duration (3) = 2-1 Prog. Source Programme Project Finish date Contractor Delay Employer Total Entitlemen t P9 Approved P8 21,July, W3 79 P10 P9+Delay Events 15,Aug, P11 P10+Progres s update on DD 15,Sep., Total Entitlement
16 Technique Case study- Summary Start Finish window Duration 0 10-Mar Apr window 1 11-Apr Dec Jan-13 1-Feb Feb Apr Programme P0 P1 Programme Approved BaseLine P0+Delay Events Project Finish Date Contractor Delay Delay Employer Delay 22-Apr May Total Entitlement P2 P1+Progress update on DD 14-May P3 Approved P2 14-May-13 P4 P3+Delay Events 25-May P5 P4+Progress update on DD 3-Jun P6 Approved P5 3-Jun-13 P7 P6+Delay Events 9-Jul P8 P7+Progress update on DD 21-Jul P9 Approved P8 21-Jul-13 P10 P9+Delay Events 15-Aug P11 P10+Progress update on DD Total Entitlement 15-Sep
17 Technique Case study- Conclusion According to the previous analysis the contractor entitled for (93) Calendar day as Excusable Delays Total Entitlement 146 Calendar Day Excusable 93 Day Non-Excusable 53 Day Compensable Non- Compensable
18 Thank You We hope you enjoy our lecture today Hope to receive your feedback and recommendations Contact Info Mobile : /PlanningEngineerDotNet /groups/
Spheria Australian Smaller Companies Fund
29-Jun-18 $ 2.7686 $ 2.7603 $ 2.7520 28-Jun-18 $ 2.7764 $ 2.7681 $ 2.7598 27-Jun-18 $ 2.7804 $ 2.7721 $ 2.7638 26-Jun-18 $ 2.7857 $ 2.7774 $ 2.7690 25-Jun-18 $ 2.7931 $ 2.7848 $ 2.7764 22-Jun-18 $ 2.7771
More informationXML Publisher Balance Sheet Vision Operations (USA) Feb-02
Page:1 Apr-01 May-01 Jun-01 Jul-01 ASSETS Current Assets Cash and Short Term Investments 15,862,304 51,998,607 9,198,226 Accounts Receivable - Net of Allowance 2,560,786
More informationProving and Tracking Damages of your Claim
Proving and Tracking Damages of your Claim Jeffrey E. Fuchs, PE, CPA 1 1. Compensability 2. Excusability of a Delay 3. How is Compensable Delay Priced? 4. Costs and Rates 5. What Should a Schedule Expert
More informationFactor Leave Accruals. Accruing Vacation and Sick Leave
Factor Leave Accruals Accruing Vacation and Sick Leave Factor Leave Accruals As part of the transition of non-exempt employees to biweekly pay, the UC Office of the President also requires standardization
More informationReview of Registered Charites Compliance Rates with Annual Reporting Requirements 2016
Review of Registered Charites Compliance Rates with Annual Reporting Requirements 2016 October 2017 The Charities Regulator, in accordance with the provisions of section 14 of the Charities Act 2009, carried
More informationAnalyze the Market for a Seasonal Bias. It is recommended never to buck the seasonal nature of a market. What is a Seasonal Trend?
The seasonal trend in a market is our way of taking the fundamental price action of a market...and then chart it year-by-year. Analyze the Market for a Seasonal Bias STEP 5 Using Track n Trade Pro charting
More informationExecutive Summary. July 17, 2015
Executive Summary July 17, 2015 The Revenue Estimating Conference adopted interest rates for use in the state budgeting process. The adopted interest rates take into consideration current benchmark rates
More informationFinancial & Business Highlights For the Year Ended June 30, 2017
Financial & Business Highlights For the Year Ended June, 17 17 16 15 14 13 12 Profit and Loss Account Operating Revenue 858 590 648 415 172 174 Investment gains net 5 162 909 825 322 516 Other 262 146
More informationBig Walnut Local School District
Big Walnut Local School District Monthly Financial Report for the month ended September 30, 2013 Prepared By: Felicia Drummey Treasurer BIG WALNUT LOCAL SCHOOL DISTRICT SUMMARY OF YEAR TO DATE FINANCIAL
More informationProving and Tracking Damages of your Claim
Proving and Tracking Damages of your Claim J. Mark Dungan October 6, 2017 1 Schedules: Back to Basics I. CPM Scheduling Basics II. The Baseline Schedule III. The Schedule Update IV. Delay Analysis V. Proving
More informationWESTWOOD LUTHERAN CHURCH Summary Financial Statement YEAR TO DATE - February 28, Over(Under) Budget WECC Fund Actual Budget
WESTWOOD LUTHERAN CHURCH Summary Financial Statement YEAR TO DATE - February 28, 2018 General Fund Actual A B C D E F WECC Fund Actual Revenue Revenue - Faith Giving 1 $ 213 $ 234 $ (22) - Tuition $ 226
More informationTERMS OF REFERENCE FOR THE INVESTMENT COMMITTEE
I. PURPOSE The purpose of the Investment Committee (the Committee ) is to recommend to the Board the investment policy, including the asset mix policy and the appropriate benchmark for both ICBC and any
More informationIsle Of Wight half year business confidence report
half year business confidence report half year report contents new company registrations closed companies (dissolved) net company growth uk company share director age director gender naming trends sic
More informationContract Certainty Subscription Market Progress Update for FSA
Programme Office Contract Certainty Subscription Market Progress Update for FSA 19th September 2006 Dane Douetil, Chair Market Reform Group The Market is making progress in line with expectations 100%
More informationUse of the Risk Driver Method in Monte Carlo Simulation of a Project Schedule
Use of the Risk Driver Method in Monte Carlo Simulation of a Project Schedule Presented to the 2013 ICEAA Professional Development & Training Workshop June 18-21, 2013 David T. Hulett, Ph.D. Hulett & Associates,
More informationCost Estimation of a Manufacturing Company
Cost Estimation of a Manufacturing Company Name: Business: Date: Economics of One Unit: Manufacturing Company (Only complete if you are making a product, such as a bracelet or beauty product) Economics
More information1.2 The purpose of the Finance Committee is to assist the Board in fulfilling its oversight responsibilities related to:
Category: BOARD PROCESS Title: Terms of Reference for the Finance Committee Reference Number: AB-331 Last Approved: February 22, 2018 Last Reviewed: February 22, 2018 1. PURPOSE 1.1 Primary responsibility
More informationConstruction of the #7 Line Subway Extension Project New York September 17, 2018
Construction of the #7 Line Subway Extension Project New York September 17, 2018 Saibal Basuroy, PMP Project Controls Director, Hill International Inc. Disclaimer This presentation is protected by US and
More informationPHOENIX ENERGY MARKETING CONSULTANTS INC. HISTORICAL NATURAL GAS & CRUDE OIL PRICES UPDATED TO July, 2018
Jan-01 $12.9112 $10.4754 $9.7870 $1.5032 $29.2595 $275.39 $43.78 $159.32 $25.33 Feb-01 $10.4670 $7.8378 $6.9397 $1.5218 $29.6447 $279.78 $44.48 $165.68 $26.34 Mar-01 $7.6303 $7.3271 $5.0903 $1.5585 $27.2714
More informationDBS Asia Treasures Membership
DBS Asia Treasures Membership Frequently Asked Questions 1. How do I join as a DBS Asia Treasures member? The DBS Asia Treasures membership is by invitation only. The membership may be extended to clients
More informationOTHER DEPOSITS FINANCIAL INSTITUTIONS DEPOSIT BARKAT SAVING ACCOUNT
WEIGHTAGES JAN FEB MAR APR MAY JUN JUL AUG SEPT OCT NOV DEC ANNOUNCEMENT DATE 19.Dez.14 27.Jän.15 24.Feb.15 26.Mär.15 27.Apr.15 26.Mai.15 25.Jun.15 28.Jul.15 26.Aug.15 23.Sep.15 27.Okt.15 25.Nov.15 MUDARIB
More informationHUD NSP-1 Reporting Apr 2010 Grantee Report - New Mexico State Program
HUD NSP-1 Reporting Apr 2010 Grantee Report - State Program State Program NSP-1 Grant Amount is $19,600,000 $9,355,381 (47.7%) has been committed $4,010,874 (20.5%) has been expended Grant Number HUD Region
More informationEARNED VALUE MANAGEMENT. Is it worth the effort?
EARNED VALUE MANAGEMENT Is it worth the effort? Session Objectives Examples of earned value in use. Why don t more Project Managers use EMV? Road Map to EVA Maturity? What you need to know? How is our
More informationPerformance Report October 2018
Structured Investments Indicative Report October 2018 This report illustrates the indicative performance of all Structured Investment Strategies from inception to 31 October 2018 Matured Investment Strategies
More informationLOAN MARKET DATA AND ANALYTICS BY THOMSON REUTERS LPC
LOAN MARKET DATA AND ANALYTICS BY THOMSON REUTERS LPC GLOBAL LOAN MARKET DATA AND ANALYTICS BY THOMSON REUTERS LPC Secondary Market Bid Levels: Europe Slide 2 European CLO New Issue Volume Monthly Slide
More informationHIPIOWA - IOWA COMPREHENSIVE HEALTH ASSOCIATION Unaudited Balance Sheet As of July 31
Unaudited Balance Sheet As of July 31 Total Enrollment: 407 Assets: Cash $ 9,541,661 $ 1,237,950 Invested Cash 781,689 8,630,624 Premiums Receivable 16,445 299,134 Prepaid 32,930 34,403 Assessments Receivable
More informationHIPIOWA - IOWA COMPREHENSIVE HEALTH ASSOCIATION Unaudited Balance Sheet As of January 31
Unaudited Balance Sheet As of January 31 Total Enrollment: 371 Assets: Cash $ 1,408,868 $ 1,375,117 Invested Cash 4,664,286 4,136,167 Premiums Receivable 94,152 91,261 Prepaid 32,270 33,421 Assessments
More informationApprove Assure Note. Board of Directors Meeting Report 31 July Agenda item 254/13. Title. Sponsoring Director. Authors.
Board of Directors Meeting Report 31 July 213 Agenda item 254/13 Title Quarter One Cost Improvement Programme Update Sponsoring Director Jacqueline Totterdell Chief Executive Authors Purpose Liam Slattery
More informationACCT-112 Final Exam Practice Solutions
ACCT-112 Final Exam Practice Solutions Question 1 Jan 1 Cash 200,000 H. Happee, Capital 200,000 Jan 2 Prepaid Insurance 10,000 Cash 10,000 Jan 15 Equipment 15,000 Cash 5,000 Notes Payable 10,000 Jan 30
More informationBeginning Date: January 2016 End Date: June Managers in Zephyr: Benchmark: Morningstar Short-Term Bond
Beginning Date: January 2016 End Date: June 2018 Managers in Zephyr: Benchmark: Manager Performance January 2016 - June 2018 (Single Computation) 11200 11000 10800 10600 10400 10200 10000 9800 Dec 2015
More informationSmallBizU WORKSHEET 1: REQUIRED START-UP FUNDS. Online elearning Classroom. Item Required Amount ($) Fixed Assets. 1 -Buildings $ 2 -Land $
WORKSHEET 1: REQUIRED START-UP FUNDS Item Required Amount () Fixed Assets 1 -Buildings 2 -Land 3 -Initial Inventory 4 -Equipment 5 -Furniture and Fixtures 6 -Vehicles 7 Total Fixed Assets Working Capital
More informationBusiness & Financial Services December 2017
Business & Financial Services December 217 Completed Procurement Transactions by Month 2 4 175 15 125 1 75 5 2 1 Business Days to Complete 25 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 217 Procurement
More informationBeginning Date: January 2016 End Date: September Managers in Zephyr: Benchmark: Morningstar Short-Term Bond
Beginning Date: January 2016 End Date: September 2018 Managers in Zephyr: Benchmark: Manager Performance January 2016 - September 2018 (Single Computation) 11400 - Yorktown Funds 11200 11000 10800 10600
More informationEARNED VALUE AS A RISK ASSESSMENT TOOL
EARNED VALUE AS A RISK ASSESSMENT TOOL Introduction Earned Value Definition: Employment of a Single Management Control System Providing Accurate, Consistent, Reliable, and Timely Data That Management at
More informationBig Walnut Local School District
Big Walnut Local School District Monthly Financial Report for the month ended September 30, 2012 Prepared By: Felicia Drummey Treasurer BIG WALNUT LOCAL SCHOOL DISTRICT SUMMARY OF YEAR-TO-DATE FINANCIAL
More informationSCHEDULE 10 INDEX FACTOR
SCHEDULE 10 INDEX FACTOR SCHEDULE 10 INDEX FACTOR 1. GENERAL 1.1 Capitalized Terms Capitalized terms used in this Schedule have the definitions as set out in the Agreement to Design, Build, Finance and
More informationJanuary 2019 Data Release
Mar-11 Apr-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Jul-13
More informationAdvanced Budgeting Workshop. Contents are subject to change. For the latest updates visit
Advanced Budgeting Workshop Page 1 of 8 Why Attend 'Advanced Budgeting Workshop' is the second level course in budgeting after Meirc's 'Effective Budgeting and Cost ' course. It goes beyond the theory
More informationOctober 2018 Data Release
Mar-11 Apr-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Jul-13
More informationDown, Set, Hut! Quarterbacking your LDI Program. Martin Jaugietis, CFA Managing Director, LDI Solutions, Russell Investments
Down, Set, Hut! Quarterbacking your LDI Program Martin Jaugietis, CFA Managing Director, LDI Solutions, Russell Investments Funded Ratios (%) The end zone is getting closer funding levels have improved
More informationFrom Suspicion to Invaluable Transition of Two Project Managers
From Suspicion to Invaluable Transition of Two Project Managers June 2010 Shilpi Kumar & Sunita Raman Agenda Unisys and HOLMES 2 Nature of Projects and Roles Why EVA? How? EVA in Development Projects Transition
More informationStatus of the Unemployment Trust Fund and Related Issues. Commission on Unemployment Compensation. Ellen Marie Hess, Commissioner.
Status of the Unemployment Trust Fund and Related Issues Commission on Unemployment Compensation August 8, 2018 Ellen Marie Hess, Commissioner 2 Trust Fund Data Standard Forecast (Millions of Dollars)
More informationDistribution Group Study Process. August 26, 2014
Distribution Group Study Process August 26, 2014 Agenda Overview Applying for DGSP DGSP Interconnection Process Applicability and Utility Contacts Questions 2 Process Overview Open Window Period Evaluation
More informationDevelopment of Economy and Financial Markets of Kazakhstan
Development of Economy and Financial Markets of Kazakhstan National Bank of Kazakhstan Macroeconomic development GDP, real growth, % 116 112 18 14 1 113,5 11,7 216,7223,8226,5 19,8 19,8 19,3 19,619,7 199,
More informationConsumer confidence and economic climate indicators continue to increase
%/3mma Business and Consumer Surveys July 2017 28 July 2017 Consumer confidence and economic climate indicators continue to increase The Consumer confidence indicator increased in July, resuming the positive
More informationSCHEDULE 10 INDEX FACTOR
DRAFT SCHEDULE 10 INDEX FACTOR SCHEDULE 10 INDEX FACTOR 1. GENERAL 1.1 Capitalized Terms Capitalized terms used in this Schedule have the definitions as set out in the Agreement to Design, Build, Finance
More informationA Case for Project Revenue Management. Peter Varani PMP
A Case for Project Revenue Management Peter Varani PMP A Case for Project Revenue Management PMBOK GUIDE (4 th edition) Cost 845 Revenue 3 Unisys Annual Report (2008) Cost 174 Revenue 152 2 Balanced Approach
More informationAlgo Trading System RTM
Year Return 2016 15,17% 2015 29,57% 2014 18,57% 2013 15,64% 2012 13,97% 2011 55,41% 2010 50,98% 2009 48,29% Algo Trading System RTM 89000 79000 69000 59000 49000 39000 29000 19000 9000 2-Jan-09 2-Jan-10
More informationPRESS RELEASE. Securities issued by Hungarian residents and breakdown by holding sectors. January 2019
7 March 2019 PRESS RELEASE Securities issued by Hungarian residents and breakdown by holding sectors January 2019 According to securities statistics, the amount outstanding of equity securities and debt
More informationDivision of Bond Finance Interest Rate Calculations. Revenue Estimating Conference Interest Rates Used for Appropriations, including PECO Bond Rates
Division of Bond Finance Interest Rate Calculations Revenue Estimating Conference Interest Rates Used for Appropriations, including PECO Bond Rates November 16, 2018 Division of Bond Finance Calculation
More informationUsing projections to manage your programs
Using projections to manage your programs To project total provider reimbursements To do what ifs based on caseloads or other metrics To project amounts of admin & support available for spending Based
More informationConsumer confidence and economic climate indicators increase
%/3mma Business and Consumer Surveys March 2017 March, 30 th 2017 Consumer confidence and economic climate indicators increase The Consumer confidence indicator increased between September and March, resuming
More informationSection 12L of the Income Tax Act (1962) on the allowance For Energy Efficiency Savings
Section 12L of the Income Tax Act (1962) on the allowance For Energy Efficiency Savings Eskom and Capital City Business Chamber, Energy Efficiency Conference and Exhibition: Reducing operating costs by
More informationEMPLOYER S MUNICIPAL INCOME TAX WITHHOLDING FORMS INSTRUCTIONS FOR FILING FORM LW-1
CITY TAX DEPT 50 TOWN SQUARE P.O. BOX 155 LIMA, OHIO 45802 PHONE (419) 221-5245 FAX (419) 998-5527 (MONTHLY OR QUARTERLY STATEMENT) FORM LW-3 (ANNUAL RECONCILIATION) EMPLOYER S MUNICIPAL INCOME TAX WITHHOLDING
More informationProject NEON Interim Finance Committee Rudy Malfabon Director
Project NEON Interim Finance Committee Rudy Malfabon Director October 22, 2014 1 Project Benefits Safety & Congestion 1,000 crashes per year! Connectivity /Mobility for City Redevelopment Efforts Congestion:
More informationSimple Interest. S.Y.Tan. 1.1 Simple Interest
Simple Interest Interest (I) a benefit in the form of a fee that lender received for letting borrower use of his money Origin date (O.D.) the date on which the borrowed money is received by the borrower
More informationKey IRS Interest Rates After PPA
Key IRS Rates - After PPA - thru 2011 Page 1 of 10 Key IRS Interest Rates After PPA (updated upon release of figures in IRS Notice usually by the end of the first full business week of the month) Below
More information2018 Financial Management Classes
2018 Financial Management Classes MONEY MANAGEMENT CLASS/BANKING OPERATONS (1ST & 3RD FRIDAY) INVESTING BASICS (2ND FRIDAY) CREDIT MANAGEMENT BLENDED RETIREMENT SYSTEM/THRIFT SAVINGS PLAN (4TH FRIDAY)
More informationEarnings Results. Second Quarter 2015
Earnings Results Second Quarter 2015 Forward Looking Statements This presentation contains, or may be deemed to contain, forward-looking statements. By their nature, forward-looking statements involve
More informationEffective Budgeting and Cost Control. Contents are subject to change. For the latest updates visit
Effective Budgeting and Cost Page 1 of 9 Why Attend ning and budgeting are must-have skills for all professionals regardless of their function or managerial level. This course covers the concept of budgeting
More informationSTRUCTURED INVESTMENT PERFORMANCE UPDATE 3 Years Bonus Enhanced Structured Equity Linked Investment Series 1
STRUCTURED INVESTMENT PERFORMANCE UPDATE 3 Years Bonus Enhanced Structured Equity Linked Investment Series 1 Report as at: 30Jun16 The product is closed for subscription. This is an interim update and
More informationDepartment of Public Welfare (DPW)
Department of Public Welfare (DPW) Office of Income Maintenance Electronic Benefits Transfer Card Risk Management Report Out-of-State Residency Review FISCAL YEAR 2014-2015 September 2014 (June, July and
More informationConstructing a Cash Flow Forecast
Constructing a Cash Flow Forecast Method and Worked Example A cash flow forecast shows the estimates of the timing and amounts of cash inflows and outflows over a period of time. The sections of a cash
More informationDividend Report. December 2018
Warning: Aberdeen Global has the discretion to determine the and rate of dividend to be distributed. The dividends are not guaranteed and may be investment income, gains or at the discretion of the Board
More informationQUESTION 2. QUESTION 3 Which one of the following is most indicative of a flexible short-term financial policy?
QUESTION 1 Compute the cash cycle based on the following information: Average Collection Period = 47 Accounts Payable Period = 40 Average Age of Inventory = 55 QUESTION 2 Jan 41,700 July 39,182 Feb 18,921
More informationEmployers Compliance with the Health Insurance Act ANNUAL REPORT. Bermuda. Health Council
Employers Compliance with the Health Insurance Act 1970 2016 ANNUAL REPORT Bermuda ea Health Council Employers Compliance with the Health Insurance Act 1970 2016 Annual Report Contact us: If you would
More informationSolution to Problem 31 Adjusting entries. Solution to Problem 32 Closing entries.
Solution to Problem 31 Adjusting entries. 1. Utilities expense 27,000 Accounts payable 27,000 2. Rent revenue 4,000 Unearned revenue 4,000 3. Supplies 2,000 Supplies expense 2,000 4. Interest receivable
More informationSection 6621 of the Internal Revenue Code establishes the interest rates on
Part 1 Section 6621.--Determination of Rate of Interest 26 CFR 301.6621-1: Interest rate. Rev. Rul. -32 Section 6621 of the Internal Revenue Code establishes the interest rates on overpayments and underpayments
More informationPRESS RELEASE. Securities issued by Hungarian residents and breakdown by holding sectors. October 2018
PRESS RELEASE 10 December 2018 Securities issued by Hungarian residents and breakdown by holding sectors October 2018 According to securities statistics, the amount outstanding of equity securities and
More informationTrade Finance, Letters of Credit and Bank Guarantees
Trade Finance, Letters of Credit and Bank Guarantees Page 1 of 10 Why Attend Securing company s assets while transacting with local and international customers is critical for the success and sustainability
More informationLOUISVILLE GAS AND ELECTRIC COMPANY Gas Rates 2018 Monthly Billing Adjustments
2018 Monthly Billing Adjustments GAS LINE TRACKER CHARGES GAS LINE TRACKER CHARGES DSM (2) PER MONTH PER METER PER MONTH PER CCF TAX CUTS AND JOBS ACT $ Per CCF Firm Trans. SURCREDIT ($ per ccf) (3) GAS
More informationCertificate in Advanced Budgeting and Forecasting
Certificate in Advanced Budgeting and Forecasting Page 1 of 9 Why Attend This course is the second level course in budgeting after Meirc's 'Effective Budgeting and Cost ' course. It goes beyond the theory
More informationAsset Manager Performance Comparison
Cape Peninsula University of Technology Retirement Fund August 2017 DISCLAIMER AND WARNINGS: Towers Watson (Pty) Ltd, a Willis Towers Watson company, is an authorised financial services provider. Although
More informationFiscal Year 2018 Project 1 Annual Budget
Fiscal Year 2018 Project 1 Annual Budget Table of Contents Table Page Summary 3 Summary of Costs Table 1 4 Treasury Related Expenses Table 2 5 Summary of Full Time Equivalent Table 3 6 Positions Cost-to-Cash
More informationCorporate Accounting: Earnings and Distribution
Chapter 20 Corporate Accounting: Earnings and Distribution Net income of a corporation and corporate income taxes Cash dividends Stock dividends Stock splits Appropriations of retained earnings Retained
More informationCash & Liquidity The chart below highlights CTA s cash position at December 2017 compared to December 2016.
To: Chicago Transit Authority Board From: Jeremy Fine, Chief Financial Officer Re: Financial Results for December 2017 Date: February 14, 2018 I. Summary CTA s financial results are $4.7 million favorable
More informationExam 1 Problem Solving Questions Review
Exam 1 Problem Solving Questions Review SECTION 1 The following data were obtained from a recent quarterly report for Dell Computer (in millions): Net revenue $8,028 Cost of revenue $6,580 Inventories:
More informationCash & Liquidity The chart below highlights CTA s cash position at March 2017 compared to March 2016.
To: Chicago Transit Authority Board From: Jeremy Fine, Chief Financial Officer Re: Financial Results for March 2017 Date: May 10, 2017 I. Summary CTA s financial results are $0.6 million favorable to budget
More informationOpinions on technical and scientific matters concerning mutual recognition: working procedure for the Biocidal Products Committee (BPC)
1 (5) Opinions on technical and scientific matters concerning mutual recognition: working procedure for the Biocidal Products Committee (BPC) The purpose of this document is to establish principles to
More informationCommon stock prices 1. New York Stock Exchange indexes (Dec. 31,1965=50)2. Transportation. Utility 3. Finance
Digitized for FRASER http://fraser.stlouisfed.org/ Federal Reserve Bank of St. Louis 000 97 98 99 I90 9 9 9 9 9 9 97 98 99 970 97 97 ""..".'..'.."... 97 97 97 97 977 978 979 980 98 98 98 98 98 98 987 988
More informationAsset Manager Performance Comparison
Cape Peninsula University of Technology Retirement Fund September 2017 DISCLAIMER AND WARNINGS: Towers Watson (Pty) Ltd, a Willis Towers Watson company, is an authorised financial services provider. Although
More informationNonfarm Payroll Employment
PRESIDENT'S REPORT TO THE BOARD OF DIRECTORS, FEDERAL RESERVE BANK OF BOSTON Current Economic Developments - June 10, 2004 Data released since your last Directors' meeting show the economy continues to
More informationFERC EL Settlement Agreement
FERC EL05-121-009 Settlement Agreement Ray Fernandez Manager, Market Settlements Development Market Settlements Subcommittee June 14, 2018 Settlement Agreement Details Settlement Agreement Details FERC
More informationSection 6621(c) provides that for purposes of interest payable under 6601 on any large corporate underpayment, the underpayment
Section 6621. Determination of Interest Rate 26 CFR 301.6621 1: Interest rate. Interest rates; underpayments and overpayments. The rate of interest determined under section 6621 of the Code for the calendar
More informationSCHEDULE 10 INDEX FACTOR
SCHEDULE 10 INDEX FACTOR 1. GENERAL 1.1 Capitalized Terms Capitalized terms used in this Schedule have the definitions as set out in the Agreement to Design, Build, Finance and Maintain Nine New Schools
More informationCash & Liquidity The chart below highlights CTA s cash position at September 2017 compared to September 2016.
To: Chicago Transit Authority Board From: Jeremy Fine, Chief Financial Officer Re: Financial Results for September 2017 Date: November 15, 2017 I. Summary CTA s financial results are $7.7 million favorable
More informationPASSENGER REJECTION REDUCTION INITIATIVE KIRK PEREIRA. 24 th April 2018
PASSENGER REJECTION REDUCTION INITIATIVE KIRK PEREIRA 24 th April 2018 WHAT IS THIS PROJECT ABOUT? Well we are not going into that again this year! Nearly everyone in this room knows about the project
More informationWhen Dashboards are Stupid Presented by John Alber and Chris Emerson #ORG4
When Dashboards are Stupid Presented by John Alber and Chris Emerson #ORG4 Jan-11 Feb-11 Mar-11 Apr-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12
More informationTaxation in Denmark. Tax for foreigners
Taxation in Denmark Tax for foreigners Programme Public spending Top 3 Tax liability Calendar E-tax Final tax Leaving Denmark Further information Contact information Questions Full or limited tax liability
More informationThe First Steps in Implementing a Simplified Earned Value Management System
2007 Joint ISPA/SCEA National Conference & Workshop June 12-15, 2007 The First Steps in Implementing a Simplified Earned Value Management System Dorothy Tiffany, CPA, PMP NASA/GSFC EVM System Interface
More informationPRESS RELEASE. Securities issued by Hungarian residents and breakdown by holding sectors. October 2017
11 December 2017 PRESS RELEASE Securities issued by Hungarian residents and breakdown by holding sectors October 2017 According to securities statistics, the amount outstanding of equity securities and
More informationEMPLOYER S MUNICIPAL INCOME TAX WITHHOLDING FORMS
CITY TAX DEPT 50 TOWN SQUARE P.O. BOX 155 LIMA, OHIO 45802 PHONE (419) 221-5245 FAX (419) 998-5527 FORM LW-1 (MONTHLY OR QUARTERLY STATEMENT) FORM LW-3 (ANNUAL RECONCILIATION) EMPLOYER S MUNICIPAL INCOME
More informationTHE B E A CH TO WN S O F P ALM B EA CH
THE B E A CH TO WN S O F P ALM B EA CH C OU N T Y F LO R I D A August www.luxuryhomemarketing.com PALM BEACH TOWNS SINGLE-FAMILY HOMES LUXURY INVENTORY VS. SALES JULY Sales Luxury Benchmark Price : 7,
More informationCertificate in Advanced Budgeting and Forecasting
Certificate in Advanced Budgeting and Forecasting Page 1 of 12 Why Attend This course is the second level course in budgeting after Meirc's 'Effective Budgeting and Cost Control' course. It goes beyond
More informationApril 2018 Data Release
April 2018 Data Release The Home Purchase Sentiment Index (HPSI) is a composite index designed to track consumers housing-related attitudes, intentions, and perceptions, using six questions from the National
More informationBANK OF GUYANA. BANKING SYSTEM STATISTICAL ABSTRACT Website:
BANK OF GUYANA BANKING SYSTEM STATISTICAL ABSTRACT Website: www.bankofguyana.org.gy RESEARCH DEPARTMENT November 2010 STATISTICAL ABSTRACT TABLES CONTENTS 1. MONETARY AUTHORITY 1.1 Bank of Guyana: Assets
More informationEarned Value Management An Overview March 2014
Earned Value Management An Overview March 2014 SAVE International Cascadia Chapter Introduction What is Earned Value? Why is Earned Value important? What is required? Earned Value Definitions & Process
More informationOrder Making Fiscal Year 2018 Annual Adjustments to Transaction Fee Rates
This document is scheduled to be published in the Federal Register on 04/20/2018 and available online at https://federalregister.gov/d/2018-08339, and on FDsys.gov 8011-01p SECURITIES AND EXCHANGE COMMISSION
More information1 Long Term Debt $ 9,298,554 $ (250,000) $ 9,048, Preferred Stock 30,450 30, % 5 Common Equity 250, %
SUMMARY SCHEDULE ($000'S) Schedule 1 Page 1 of 1 Line Capitalization HISTORICAL YEAR ENDED 12/31/16 Hybrid Percent Equity Adjusted of Total Cost of Cost of Amount Adjustment Amount Capitalization Capital
More informationSOUTHERN AFRICA GROWTH INCENTIVE PROGRAMME (GIP)
SOUTHERN AFRICA GROWTH INCENTIVE PROGRAMME (GIP) PERFORMANCE YEAR (PY) 20/ The presentation contains IP protected works; it is intended for ABOs use only; the content of the presentation should not be
More information